mps

14
Master Production Schedule States requirements for individual end items and options by date and quantity Constrained by and supports the production plan “Disaggregates” the production plan

Upload: sufian-hasan

Post on 26-Sep-2015

224 views

Category:

Documents


0 download

DESCRIPTION

Master production schedule slide

TRANSCRIPT

  • Master Production ScheduleStates requirements for individual end items and options by date and quantityConstrained by and supports the production planDisaggregates the production plan

  • Relationship to the Production Plan

  • Objectives of Master SchedulingMaintain desired level of customer serviceMake best use of resourcesKeep inventories at desired level

  • Inputs to Master Scheduling ProcessProduction planForecastOrders from customersAdditional independent demandInventory levelsCapacity constraints

  • Steps in Making an MPSMake a preliminary MPSPerform rough-cut capacity planningResolve differences

  • Lot size = 50 unitsPreliminary MPSPeriod123456Forecast303030303030Projected available300 balance4010204010Master production schedule505050

  • Rough-Cut Capacity PlanningRough-cut capacity planning checks whether critical resources are available to support the preliminary master scheduleA resource bill shows the time required for individual items on a critical resource

  • Resolving DifferencesIf required capacity exceeds available capacityCapacity must be increased, orPlan must be altered

  • The MPSThe MPS is notA sales forecastA wish listA final assembly schedule

    The MPS should beThe anticipated build scheduleRealistic and achievable

  • MPS and Delivery PromisesAs orders are received, they consume available production and/or inventoryAny part of the MPS level not consumed is available-to-promiseMPS Level

  • On hand = 200 unitsAvailable-to-Promise (ATP)Period123456Customer orders160202060MPS scheduled receipts200200200Available-to- promise40160140200

  • Planning HorizonThe planning horizon is the amount of time the master schedule extends into the future

    This is normally set to cover a minimum of cumulative lead time plus time for lot sizing low-level components and for capacity changes of primary work centersAPICS Dictionary

  • Planning Horizon

  • Time Fences and Zones

    **************