MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08 09 10 11 12 13 14 15 16 17 18 19 20 Fiscal Year RDT&E NSSL, MIT/LL, others NWRT Demo 1 Wx Demo 2 Wx/Acft Algorithm Dev Algorithm & Software Dev Tradeoff Analyses Testi ng Upgrade to Active Sub- array Scan Strategies FAA IOC for Wx & ASR RFI Concept Def 3 Contractors, FP Soli cit Industry Day Award RFP 2 Contractors, CPFF Fly-Off Ful l RFP Dev Solic it RFP RFP Dev Award Cost- Benefit Study Pre-Prod Model RFP Dev Dev Limited Prod 1 Contractor, CPFF Soli cit Award OT&E DT&E Concept Definition / System Developmen t Analysis of Alternative s Siting/ Spectrum Site Surveys Site Acq & Prep Spectrum Approvals Spectrum & Siting Requirements Analysis Management Approach Agency Internal Test & Eval Org Ops Support Org Program Council Oversight Joint System Program Office Ops Concept Developmen t Reqts Analysis Reqts Def Definition & Refinement Employment Concept Refinemen t P3I Dev Tradeoffs – Design to Budget Refineme nt DOD CPD DOD CDD DOD ICD DOD FSA DOD POM Bld DOD DP DOD DP DOD DP KDP1 (Def need, priority, and $) KDP2 (Select design & move to demo/test) KDP3 (Full Scale Dev) KDP4 (Full Prod) DOD DP DOD DP Mission & Service Needs Analysis and Requirement s BASC Study Svc Analys is FAA DP FAA DP FAA DP Init Acq Review Wx & Air Replace ASR-8/9? Replace 88D?

Upload: joseph-golden

Post on 21-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08091011121314151617181920 Fiscal Year RDT&E NSSL, MIT/LL, others

MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

FAA IOC for Wx &

ASR

RFI

Concept Def3 Contractors, FP

Solicit

Industry Day

AwardRFP

2 Contractors, CPFF

Fly-Off Full

RFP Dev

Solicit

RFP

RFP Dev

Award

Cost-Benefit Study

Pre-Prod Model

RFP Dev

Dev

Limited Prod1 Contractor, CPFF

Solicit

Award

OT&EDT&E

Concept Definition /

System Development

Analysis of Alternatives

Siting/SpectrumSite Surveys

Site Acq & Prep

Spectrum Approvals

Spectrum & Siting Requirements Analysis

Management Approach

Agency InternalTest & Eval Org

Ops Support Org

Program Council Oversight

Joint System Program Office

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements BASC

Study

Svc Analysis

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?

Page 2: MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08091011121314151617181920 Fiscal Year RDT&E NSSL, MIT/LL, others

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements BASC

Study

Svc Analysis

MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

FAA IOC for Wx &

ASR

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?

Page 3: MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08091011121314151617181920 Fiscal Year RDT&E NSSL, MIT/LL, others

MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

RFI

Concept Def3 Contractors, FP

Solicit

Industry Day

AwardRFP

2 Contractors, CPFF

Fly-Off Full

RFP Dev

Solicit

RFP

RFP Dev

Award

Cost-Benefit Study

Pre-Prod Model

RFP Dev

Dev

Limited Prod1 Contractor, CPFF

Solicit

Award

OT&EDT&E

Concept Definition /

System Development

Analysis of Alternatives

Siting/SpectrumSite Surveys

Site Acq & Prep

Spectrum Approvals

Spectrum & Siting Requirements Analysis

Management Approach

Agency InternalTest & Eval Org

Ops Support Org

Program Council Oversight

Joint System Program Office

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?FAA IOC for Wx &

ASR

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements BASC

Study

Svc Analysis

As of 29 Jan 08

Page 4: MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08091011121314151617181920 Fiscal Year RDT&E NSSL, MIT/LL, others

4

MPAR Symposium / Implementation Strategy

• FAA is committed to R&D funds to assess MPAR as a:

– Cost-effective backup to next-generation cooperative surveillance system

– Possible replacement for legacy weather radars

• NOAA has been funding the National Weather Radar Testbed at annual baseline rate

– NOAA in final stages of identifying additional funding beginning in FY10 for MPAR risk-reduction program

• From Under Secretary mtg on North American Air Defense

– DoD and DHS must take active role in assessing emerging approaches to improving the Nation’s surveillance capabilities, including MPAR

MPAR Program Status

Page 5: MPAR Symposium / Implementation Strategy MPAR Risk-Reduction Implementation Strategy 08091011121314151617181920 Fiscal Year RDT&E NSSL, MIT/LL, others

5

Summary

• MPAR planning process has included federal agencies, academia, military laboratories, and radar industry

• Initial analysis indicates MPAR is technically feasible to meet multiple user needs

• Affordability issue can only be addressed through a managed risk-reduction R&D program

• Large cost of R&D effort for MPAR beyond scope of any one agency

– Requires interagency cooperation to succeed

• Now is the time to begin evaluation of MPAR