mpar symposium / implementation strategy mpar risk-reduction implementation strategy...
TRANSCRIPT
MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy
08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year
RDT&ENSSL, MIT/LL, others
NWRT
Demo 1Wx
Demo 2Wx/Acft
Algorithm Dev Algorithm & Software Dev
Tradeoff Analyses
Testing
Upgrade to Active Sub-array
Scan Strategies
FAA IOC for Wx &
ASR
RFI
Concept Def3 Contractors, FP
Solicit
Industry Day
AwardRFP
2 Contractors, CPFF
Fly-Off Full
RFP Dev
Solicit
RFP
RFP Dev
Award
Cost-Benefit Study
Pre-Prod Model
RFP Dev
Dev
Limited Prod1 Contractor, CPFF
Solicit
Award
OT&EDT&E
Concept Definition /
System Development
Analysis of Alternatives
Siting/SpectrumSite Surveys
Site Acq & Prep
Spectrum Approvals
Spectrum & Siting Requirements Analysis
Management Approach
Agency InternalTest & Eval Org
Ops Support Org
Program Council Oversight
Joint System Program Office
Ops Concept Development
Reqts Analysis
Reqts Def Definition & Refinement
Employment ConceptRefinement
P3I DevTradeoffs – Design to Budget
Refinement
DOD CPDDOD CDDDOD ICD
DOD FSA DOD POM Bld
DOD DP
DOD DPDOD DP
KDP1 (Def need, priority, and $)
KDP2 (Select design & move to demo/test)
KDP3 (Full Scale Dev)
KDP4(Full Prod)
DOD DP
DOD DP
Mission & Service Needs Analysis andRequirements BASC
Study
Svc Analysis
FAA DPFAA DP
FAA DP
Init Acq Review Wx & Air
Replace ASR-8/9?
Replace 88D?
Ops Concept Development
Reqts Analysis
Reqts Def Definition & Refinement
Employment ConceptRefinement
P3I DevTradeoffs – Design to Budget
Refinement
DOD CPDDOD CDDDOD ICD
DOD FSA DOD POM Bld
DOD DP
DOD DPDOD DP
KDP1 (Def need, priority, and $)
KDP2 (Select design & move to demo/test)
KDP3 (Full Scale Dev)
KDP4(Full Prod)
DOD DP
DOD DP
Mission & Service Needs Analysis andRequirements BASC
Study
Svc Analysis
MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy
08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year
RDT&ENSSL, MIT/LL, others
NWRT
Demo 1Wx
Demo 2Wx/Acft
Algorithm Dev Algorithm & Software Dev
Tradeoff Analyses
Testing
Upgrade to Active Sub-array
Scan Strategies
FAA IOC for Wx &
ASR
FAA DPFAA DP
FAA DP
Init Acq Review Wx & Air
Replace ASR-8/9?
Replace 88D?
MPAR Symposium / Implementation StrategyMPAR Risk-Reduction Implementation Strategy
08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year
RDT&ENSSL, MIT/LL, others
NWRT
Demo 1Wx
Demo 2Wx/Acft
Algorithm Dev Algorithm & Software Dev
Tradeoff Analyses
Testing
Upgrade to Active Sub-array
Scan Strategies
RFI
Concept Def3 Contractors, FP
Solicit
Industry Day
AwardRFP
2 Contractors, CPFF
Fly-Off Full
RFP Dev
Solicit
RFP
RFP Dev
Award
Cost-Benefit Study
Pre-Prod Model
RFP Dev
Dev
Limited Prod1 Contractor, CPFF
Solicit
Award
OT&EDT&E
Concept Definition /
System Development
Analysis of Alternatives
Siting/SpectrumSite Surveys
Site Acq & Prep
Spectrum Approvals
Spectrum & Siting Requirements Analysis
Management Approach
Agency InternalTest & Eval Org
Ops Support Org
Program Council Oversight
Joint System Program Office
FAA DPFAA DP
FAA DP
Init Acq Review Wx & Air
Replace ASR-8/9?
Replace 88D?FAA IOC for Wx &
ASR
Ops Concept Development
Reqts Analysis
Reqts Def Definition & Refinement
Employment ConceptRefinement
P3I DevTradeoffs – Design to Budget
Refinement
DOD CPDDOD CDDDOD ICD
DOD FSA DOD POM Bld
DOD DP
DOD DPDOD DP
KDP1 (Def need, priority, and $)
KDP2 (Select design & move to demo/test)
KDP3 (Full Scale Dev)
KDP4(Full Prod)
DOD DP
DOD DP
Mission & Service Needs Analysis andRequirements BASC
Study
Svc Analysis
As of 29 Jan 08
4
MPAR Symposium / Implementation Strategy
• FAA is committed to R&D funds to assess MPAR as a:
– Cost-effective backup to next-generation cooperative surveillance system
– Possible replacement for legacy weather radars
• NOAA has been funding the National Weather Radar Testbed at annual baseline rate
– NOAA in final stages of identifying additional funding beginning in FY10 for MPAR risk-reduction program
• From Under Secretary mtg on North American Air Defense
– DoD and DHS must take active role in assessing emerging approaches to improving the Nation’s surveillance capabilities, including MPAR
MPAR Program Status
5
Summary
• MPAR planning process has included federal agencies, academia, military laboratories, and radar industry
• Initial analysis indicates MPAR is technically feasible to meet multiple user needs
• Affordability issue can only be addressed through a managed risk-reduction R&D program
• Large cost of R&D effort for MPAR beyond scope of any one agency
– Requires interagency cooperation to succeed
• Now is the time to begin evaluation of MPAR