mp economizer tube replacement of hrsg

32
MHSE MP ECONOMIZER TUBES REPLACEMENT HRSG A/B MUHAMMAD REHAN KHAN MAINTENANCE ENGINEER

Upload: rehan-khan

Post on 17-Dec-2014

210 views

Category:

Engineering


8 download

DESCRIPTION

This presentation is the maintenance plan for the tube replacement of an economizer section of HRSG

TRANSCRIPT

Page 1: Mp economizer tube replacement of hrsg

MHSEMP ECONOMIZER

TUBES REPLACEMENT

HRSG A/B

MUHAMMAD REHAN KHANMAINTENANCE ENGINEER

Page 2: Mp economizer tube replacement of hrsg

EXECUTIVE SUMMARY

• EQUIPMENT OVERVIEW

• REASON FOR TUBE REPLACEMENT

• TUBE REPLACEMENT SCOPE

• TUBE REPLACEMENT STRATEGY

• PRESSURE TESTING STRATEGY

• TIMELINE

Page 3: Mp economizer tube replacement of hrsg

3

FGC

GT/ HRSG

STG

IA/ PA

DEMIN II DEMIN I/ WWTU I

RW

CT II

Page 4: Mp economizer tube replacement of hrsg

NORTH

SIDE

SOUTH

SIDE

LP EVAPORATOR

MP ECONOMIZER

MP SUPER HEATER

MP EVAPORATOR

WEST SIDE VIEW

Page 5: Mp economizer tube replacement of hrsg

BFW INLET

Page 6: Mp economizer tube replacement of hrsg
Page 7: Mp economizer tube replacement of hrsg
Page 8: Mp economizer tube replacement of hrsg

TUBES REPLACEMENT SCOPE

Page 9: Mp economizer tube replacement of hrsg

NORTH

SIDE

SOUTH

SIDE

LP EVAPORATOR

MP ECONOMIZER

MP SUPER HEATER

MP EVAPORATOR

WEST SIDE VIEW

Page 10: Mp economizer tube replacement of hrsg
Page 11: Mp economizer tube replacement of hrsg

TUBES REPLACEMENT STRATEGY

Page 12: Mp economizer tube replacement of hrsg
Page 13: Mp economizer tube replacement of hrsg

SEPARATOR PLATES

INSULATION

Page 14: Mp economizer tube replacement of hrsg

SEPARATOR PLATES

INSULATION

Page 15: Mp economizer tube replacement of hrsg
Page 16: Mp economizer tube replacement of hrsg
Page 17: Mp economizer tube replacement of hrsg
Page 18: Mp economizer tube replacement of hrsg
Page 19: Mp economizer tube replacement of hrsg
Page 20: Mp economizer tube replacement of hrsg

SOUTH SIDE

METHODOLOGY

Page 21: Mp economizer tube replacement of hrsg

SOUTH SIDE

METHODOLOGY

CUT 13 TUBES

Page 22: Mp economizer tube replacement of hrsg

SOUTH SIDE

PERFORM HYDRO TEST OF THE HEADER

RE-WELD 04 TUBES & PLUG 09 TUBES

METHODOLOGY

PLUG

Page 23: Mp economizer tube replacement of hrsg

SOUTH SIDE

PERFORM HYDRO TEST OF THE HEADER

RE-WELD 05 MIDDLE TUBES

PLUG

METHODOLOGY

Page 24: Mp economizer tube replacement of hrsg

SOUTH SIDE

PERFORM HYDRO TEST OF THE HEADER

RE-WELD LAST 04 TUBES

METHODOLOGY

Page 25: Mp economizer tube replacement of hrsg

PRESSURE TESTING ARRANGEMENT OF HEADER

Page 26: Mp economizer tube replacement of hrsg

PRESSURE TESTING STRATEGY

• Current Strategy: Circulation Test of Medium Pressure Side through BFW

Pump

• Problem: Testing time is highPressure holding not possible

• Proposed Strategy:Separate Hydro Testing of the Header

Page 27: Mp economizer tube replacement of hrsg

• Only Outlet connections to be cut

• Flange and Nozzle to be welded

• Filling and Pressurization to be done from the bottom nozzle

• Venting to be done from top

• Pressurization will be done through a pneumatic pump

• Pipe will be welded back

Flanges are already installed outside the

equipment

Page 28: Mp economizer tube replacement of hrsg

TUBE PLUGGING STRATEGY

Page 29: Mp economizer tube replacement of hrsg

NEW TUBE INSERTION STRATEGY

Page 30: Mp economizer tube replacement of hrsg

SOUTH SIDE

NORTHSIDE

EAST SIDE VIEW (BFW PUMP SIDE)

Tube will be lifted horizontally with the help of crane

Page 31: Mp economizer tube replacement of hrsg
Page 32: Mp economizer tube replacement of hrsg

THANK YOU