moving from bus rapid transit to integrated public transport
TRANSCRIPT
Moving from Bus Rapid Transit
to Integrated Public Transport
LISA SEFTEL, CITY OF JOHANNESBURGSATC CONFERENCE JULY 2016
Agenda
Introduction and background What did we learn from our planning process Introducing our Integrated Public Transport
Network plan Implementing the plan Concluding remarks
Introduction and Background
ADD PICTURE
Brief overview: City of Johannesburg
Population: 4.4 million Population growth rate: 3.4% Land mass: 1 645 km 2 Population density: 2695/km2 Household number: 1 434 856 Household size: 3 persons per household
Growth rate: 3.3% in 2011 Unemployment: 23% of economically active
people in 2010 but if those who have stopped looking for work are included, the number grows to >30%
67.4% of households live on less than R3200 per month with a large percentage of poor household’s income going towards transport
Gini co-efficient: 0.63,- highest in world
Carbon emissions: 56% is contribution of Joburg to national carbon emissions, 13% highest carbon emitting City in the world and Transport has the highest demand for energy (67%)
Background: Public Transport Chronology
Year What2003 First five year ITP done. Identified need for a Strategic Public Transport Network
2006 Mayoral Committee agrees to implement BRT in Joburg, study tours, engagement with operators start
2007 Infrastructure roll out starts, MOU with operators signed
2009 Phase 1A BRT starts with 40 buses and interim company.
Feb 2011 Phase 1A BRT handover to taxi industry shareholders
First half 2013
Mayoral Committee agrees to restructure Metrobus on similar lines to BRT contracts – agrees turn around business plan
Oct 2013 Phase 1B starts with an interim company. Full roll out by May 2014
June 2014 Phase 1C business plan approved yet with need to do further work on integration and new areas to North
August 2015
Phase 1B handover to taxi industry, 50% board independent and independent management teams
2015 Establishment of engagement and negotiations for third phase – now integrated
Background: Transport Planning chronology
Year What2003 First five year ITP done. Identified need for a Strategic
Public Transport Network and identified routes for all modes. Most not implemented due to policy switch to BRT
2008/9 Started to plan and find funding for next CITP2012 Transport Register done2013 Household survey done2013 Strategic Integrated Transport Plan Framework (see next
slide) approved by Mayoral Committee2016 Integrated Transport Network done with a focus on public
transport (Strategic Integrated Public Transport Network plan) but also approach to freight and NMT network.
How we have planned to do CITP and what have we done
Done
Not doneStrugglin
g to define
how best to do
Mostly done – need to
get input from
PRASA and Gautrain
Ongoing
What did we learn from the planning process?
Household Travel Survey
What did we do In February 2013
we surveyed 6300 households across the City
We asked them about their transport movements and levels of satisfaction
Key conclusions Private: Public split: 57:
43 Further modal split (all
trips)
Satisfaction with public transport from Household Travel Survey
Transport need assessment
What did we do Workshops were held in the seven
regions asking stakeholders including councillors, operators, residents associations and commuter groups to determine the transport challenges they had and their views on our proposed plans
We also engaged with internal and external government partners through the Joburg Intermodal Planning Committee
Key conclusions Key themes were:
Reliable, more frequent and punctual public transport services
Improved customer care Affordability Last mile accessibility
including sidewalks and safety
Stated Preference Survey
What did we do We interviewed 1208
persons representative of low, high and middle income groups
We investigated ‘mode captivity’ and ‘mode choice sensitivity’
Key conclusions Mode captivity:
50% of road users unwilling to switch to public transport, even with significant improvements
Other 50% will move if it is attractive enough (safety, accessibility, frequency and reliability)
Mode choice sensitivity Most sensitive to waiting time, followed by
walking time People more sensitive to price changes vs
speed changes Gautrain was more attractive than other
modes. BRT was considered similar to Metrorail
Transport Model
What did we do Upgraded the 2003 EMME/2 transport
demand model for horizon years 2014 (base year ), 2015 and 2037 (forecasting)
The following information was updated: Road network capacity (JRA
Pavement Management System) Road network utilization (JRA, NRA
Traffic counts) Public transport infrastructure and
services (TIR 2013) O-D matrices (Joburg HTS 2014) Population (Census 2011) Dwellings (Joburg CIP 2014) Worker and floor area (GITMP25)
The model was used to forecast future scenarios and to test alternative network proposals
Key conclusions Concentrated origins and dispersed
destinations Passenger demand volumes in the long
term do not exceed 10000 passengers in the peak hour on road based assignments
With the exception of Modderfontein, no major road network expansions will be required to develop the ITN. Westlake link from Soweto can create opportunities for us
NMT demand within (10km) does not warrant a city wide network however should be built from precinct levels
Impact of BRT on TOD not yet evident
Developing an Integrated Transport Network
What is the purpose of the ITN?
To set out a long term network for public transport, NMT and freight
To be able to guide infrastructural investment decisions, operational planning, transformation initiatives and budget required in the short, medium and long term.
Components of the Integrated Transport NetworkIntegrated Public Transport Network PlanNon-Motorised Transport Planning FrameworkFreight network plan and freight management plan
This presentation will focus on the public transport component
What guided us: Current environment
Significant fiscal constraints impacting on: Reduced PTIS grant and less certainty High exchange rate makes buses and ITS equipment more expensive
Post Eco-Mobility Festival and current road works makes public transport more desirable for all income groups
Climate change (post CoP) to switch to green transport Learnt many operational and sustainability lessons from Phase 1A and 1B Transformation complexities and ongoing taxi industry instability COF emerging theme: Need to reduce spatial inequality (Corridors of
Freedom) and ‘service delivery inequality (disproportionate investment in different modes)
Approach to IPTN IPTN to
Cater for a wide range of demand realities; Be flexible over time: as demand change and/or more
resources become be available Still ensure rapid transit over long distances to address the
apartheid legacy of long travel times and restructure the City along transport corridors
This means gong forward we are focusing not only on BRT but also on: Additional ways of creating public transport priority for all
modes of public transport Shorter term measures to making existing public transport
more attractive and accessible Integration with other modes and NMT Incorporation of new and shared forms of demand responsive
mobility Proposed changes are aligned to:
NDOT and NT policy directives Changes in fiscal conditions Lessons learnt from Phase 1A, 1B and Metrobus
Components of IPTN • Proposed
network hierarchy
• Proposed passenger access (stops, stations, interchanges) typologies
• Design parameters
• Tools of integration
• Proposed city wide Strategic Integrated Public Transport Network
How did we determine the IPTN?
We looked at: Trip generation at the base year
(2014) and on the basis of projected land use, population and employment growth, developed estimated figures for 2025 and 2037 (using same figures as used to develop SDF)
We made certain assumptions about public transport size, frequencies and other service standards (see further slides)
Surrounding land use and future intention (Corridors of Freedom, possibility of mixed use along corridor, Consolidated Infrastructure Programme model)
Public Transport Trip Generation (City wide)
Public Transport Peak Hour Person Trips
Base (2014) 2025 2037
0-500 500-1,000 1,000-2,000 2,000-3,000 3,000-4,000 4,000-5,000 5,000-7,500 7,500-10,000
10,000-15,000
15,000-20,000
20,000-25,000
25,000-30,000
The service will operate for 18 hours (04:00-22:00)
Typology B/C will have a minimum headway of ≥1 min for the peak and ≤15min)Typology D/E the minimum headway will be ≤10min and during the off peak≤30minThe design is at a load factor of 1 for seated passengers and 0.85 for standing passengers.
85% resident within 1km
45kph Rail36kph BRT27kph Bus Routes25kph Feeder
IPTN design parameters: 1
The average travel speeds of route types
Year 1:50%Year 2:50%Year 3:75%Year 4:≥100%
Single-articulated bus : 110 - 118Rigid Bus: 55 -70 (45 - 55 seats)Minibus-taxi: 15 seats (no standees)Double decker bus: 90 - 110
IPTN design parameters: 2
The capacity (vehicles) to be provided relative to the demand
Maximum standing time is planned for 20min
MBT’s per bay/hour = 12Rigid buses per bay/hour = 6-8The number of vehicles per hour
each bay can accommodate
Number of seats per vehicle
Proposed integrated public transport network (IPTN) hierarchy
We are proposing a public transport network hierarchy differentiated in terms of: Demand Right of way (and thus
speed) Frequency of stops
(depends on demand and surrounding land use)
Modes (some only one mode e.g. rail, low density areas can have more than one mode on the network
Degree of investment (for rapid bus, higher investment)
MODE CATEGORIES
TYPOLOGY DEMAND MODE FUNCTION AND FEATURES
Rail Public Transport Network
SIPTN- Type A 9000-15000 Gautrain,
Metro Railo To move people quickly from area of high residential to areas
of employment/income opportunitieso Limited stops. (closed stations)
Rapid Road Public
Transport Network (High
Capacity)
SIPTN-Type B 6000-9000
Bus Rapid Transport, Light
Rail
o Corridors of Freedom, mixed use development , three story residential
o To move people quickly from area of high residential to areas of employment/income opportunities
o Limited intersections and right turns so buses can be relatively speedy
o Limited mostly closed high or low floor stationsRoad Public Transport Network (Medium Capacity)
SIPTN-Type C 3000-6000 Bus Rapid
Transport
o Corridors of Freedom and areas where the City want s o densify along the corridor
o Mixed use development, Three story residential, social housing along corridor.
o Fairly frequent closed and opens low floor stations and some stops
Road Mixed Traffic Public
Transport Network
(Medium to Low Capacity)
IPTN-Type D 1000-3000 Bus (Double
Decker, Standard)
o Frequent stops with shelterso Some public transport priority (e.g. queue jumping)o On street stopping by public transport vehicles o Low to medium density
Road Mixed Traffic Public
Transport Network (Low
Capacity)
IPTN-Type E 500-1500 Bus ( Standard,
Mini bus)o Frequent stops with lay bye es and shelterso Low to medium density
Road Mixed Traffic Public
Network (Demand Driven)
IPTN-Type F <500
Bus, Taxi, Demand
responsive (e.g. ehailing)
o Low to medium densityo Mostly stops or e-hailing
Proposed IPTN Hierarchy: 1
New public transport priority measures for Type C
Proposed passenger access typologies
We have identified different ways in which passengers can access the public transport system as follows: Stops, Shelters, Open Stations Closed Stations Interchanges terminals,
taxi ranks.
The key drivers in reviewing and proposing passenger access typologies are: Differentiated demand Costs and sustainability Accessibility Integration
For example: It does not make financial and
operational sense to erect and run large fully fledged stations for low numbers of passengers in suburban areas.
On the other hand, in areas like Thokoza Park, a station is no longer big enough to accommodate the numbers and an interchange maybe more suitable.
Proposed Passenger Access Typologies: 1Passenger
access Typology
Network Typology Mode
Indicative
DemandTypical features
Stop Type E Double decker , rigid and mini bus
0 to 225(PAX Facility utilization/hour)
• Stop Pole• On board fare collection• Limited static passenger information• Universally accessible
Shelter Type E Double decker , rigid and mini bus
225 to 450
• Standardised bus shelter with Stop Pole• On board fare collection• Static passenger information• Universally accessible
Open Station (Single Module) 18m Shelter only
Type B to D
Articulated , and rigid bus
450 to 1000
• Standardised open Station • Shelter over only 18m long boarding area
(balance of footprint – no shelter)• Simple Totem Pole• On board fare collection• Possible toilet facility,• Possible TVM, • Static passenger information,• Universally accessible• Secured• CCTV and Wi-Fi• Possible bike storage
Proposed Passenger Access Typologies:2Passenger
access Typology
Network Typolog
yMode Indicative
Demand Typical features
Open stations (Single Module only)Full Shelter
Type B to D
Articulated and rigid bus
1000 to 2500 (PAX Facility utilization/hour)
• Standardised open Station with Simple Totem Pole
• On board fare collection• Full shelter, • Possible TVM• Static passenger information,• Possible Toilet facility, Universally accessible• Secured, CCTV and Wi-Fi
Closed station Single ModuleDouble Module
Type B to D
Articulated and rigid bus 2500 to
50005000 to 10000
• Standardised fully closed Station with Totem Pole
• Off board fare collection• TVM• Static and electronic passenger information,
Ticketing/Staff facilities• Toilet facility,• Universally accessible • Fully secured, CCTV and Wi-Fi• Possible adjacent park and ride site & bike
storageInterchange , Terminal and taxi Rank
Type A to E
Articulated and rigid bus, mini bus taxis
> 10000 • Multiple platform semi closed/ open facility with Totem Pole
• Off board fare collection,• TVM• Static and electronic passenger information• Staff facilities,• Toilet facility, • Universally accessible, • Fully secured, CCTV and Wi-Fi• Adjacent park and ride site if possible & bike
storage
Strategic IPTN On the basis of the above, the next slide sets out the proposed Strategic IPTN
until 2025 It is called the “Strategic” IPTN because it focus on high level road and rail
network. The following slide shows the network coverage that is achieved. In respect of Type A (rail based network) we have depicted the routes that
are currently operational – awaiting outcome of Gautrain expansion study In respect of Type B, C and D we have identified 19 road based routes and we
extend the Rea Vaya naming methodology for proposed future phases as follows: Phase 1 (A,B,C) are existing phases Phase 2 (A,B,C) are second phases in same areas as first phases (e.g. 2A
is also in Soweto) Phase 3 are new phases covering new origins and destinations with 2025
horizon Phase 4, 5 are currently operated by Metrobus (Type C/D ) but could
move to B/C in the long term In line with the branding strategy, all these routes will when transformed be
called Rea Vaya
2025 Network Assignment
This is the anticipated
demand for public transport in 2025
(morning peak hour )
2025 is the proposed year for the IPTN (10 year
plan)
SITPN Type A Routes
SITPN Type A+B Routes
SITPNType A+B+C Routes
SITPNType A+B+C+DRoutes
Routes will stay same, alignments may change after detailed feasibility
Phase From SIPTN Routes Destination TypeGautrain Hatfield Sandton Park Station AGautrain OR Tambo Marlboro Sandton A
Metro Rail
Naledi Park Station Germiston AStretford (Orange Farm)
Orlando Park Station A
Princess (Westgate) Florida Park Station A Naledi Crown City George Goch Station A West Rand Orlando Park Station A
1A Thokoza Park Soccer City CBD Ellis Park B1B Thokoza Park UJ, Wits, Parktown CBD B1C CBD Louis Botha, Alexandra Sandton B1A
Extension
Ellis Park Albertina Sisulu East Gate B
2A Thokoza Park Beyers Naude, Randburg Sandton C3 Thokoza Park Roodepoort (3A),Four Ways (3B)
SunninghillMidrand (3C) C
2B Zandspruit Beyers Naude CBD C4 /MB (tbc)
Cosmo City Malibongwe, Barry Hertzog CBD C
2C Diepsloot William Nicol Sandton B&C2C Diepsloot Randburg CBD B&C1C Tembisa/Ivory Park Sunning Hill Sandton C1C Tembisa/Ivory Park 1C CBD C1C Midrand 1C CBD C1C Tembisa/Ivory Park Kaalfontein Midrand B2A Thokoza Park Chris Hani, South Gate Mall of the South D
5 /MB3 South Crest Rifle Range, Klip River Road CBD C5/MB1 Mall of the South True North Rd, Klip River DR, Road CBD D
2A Eldorado Park Nasrec RD, 1B CDB D1B
extension
Wilro Park Ontdekkers Rd, Main Rd CBD C
Tools for integration and sustainability
TOOLS Fare harmonisation Ability to use a single ticket on
different modes Unified passenger information and
marketing platform PUTCO, Metrobus and Rea Vaya
services under single operational ‘command’
Easy and speedy transfers Improved pedestrian network to
PT nodes Reviewed and possible methods of
contracting (fee per km, passenger incentive, who takes the risks and the fares)
CONSIDERATIONS In the business planning
and financial modelling of the operational plans, the costs and benefits of the different tools are being addressed
Tools may need to be sequenced to ensure financial sustainability.
Branding StrategyMayoral Committee has approved the extension of the Rea Vaya brand to quality public transport, walking and cycling
Integrated Quality Transport SystemProof Points: Convenient. Reliable. Affordable. Safe. (Ecofriendly)
BRT Busses
MotorisedTransport (MT)
Non MotorisedTransport (NMT)
MTInfrastructure
Bicycles
NMT Infrastructure
Bus Stations Cycleways Walkways
XXXXBus & Taxi Rank
XXXXStation
Interchanges
XXXXCycleway
XXXXWalkwayBikeshare
XXXXPark & Ride
XXXXBus Stop
XXXXCycle Storage
Rea Vaya brand positioning
Inte
grat
ed
Qua
lity
Tra
nspo
rt S
yste
m Rea Vaya. Metrobus
Rea Vaya. Orlando Stadium Station
Rea Vaya. Alice Lane Cycleway
Rea Vaya. West Street Walkway
Rea Vaya. Bikeshare
Rea Vaya. Westgate Bus & Taxi Rank
Rea Vaya. BRT
Convenient. Reliable. Affordable
Convenient. Safe
Convenient. Ecofriendly
Convenient. Ecofriendly
Convenient. Ecofriendly
Convenient. Safe
Convenient. Fast. Reliable. Safe. Affordable
Street furniture and signage
Non-motorised transport network planning
NMT networkOur aim with the ITN network was to consider a city wide NMT network but the data did not point to the need or viability of such. However Gauteng Province are working on a NMT Master Plan where they proposed a priority list of interventions and then priority areas.
Priority list of interventions: Improve the first and last mile
for existing public transport users
Improve the walking environment for primary walk trips
Encourage a shift from long walk trips to utility cycling
Address the safety of existing utility cycling routes (with proven demand)
Promote a shift from private car to public transport
Promote a shift from private car to utility cycling
Promote a shift from public transport to utility cycling
Promote recreational cycling
Priority areas were identified using following:• IDPs, SDFs, ITPs and NMT Plans• Analysis of Gauteng Household Survey
Data (population, income, mode split, cycling potential)
• Topography –is the area flat enough to cycle?
• Pedestrian activity density (public transport facilities, schools, business nodes etc..)
• Community needs – Quality of Life Survey (GCRO)
• Areas with high number of pedestrian fatalities
• Existing NMT projects proposed by Municipalities
Rationale for project prioritisation
Proposed priority areas for NMT
Implementing our Integrated Public Transport Network
Introduction
On the basis of the ITN and SIPTN (and NMT framework) we are now working on and can align our plans for: PRASA and Gautrain Detailed operational plans for key
quadrants of the City Metrobus
We are also “codifing” our planning and implementation process in a
Transport Governance Framework
Rail
PRASA PRASA recapitalisation will start
with Naledi, Park, Germiston, Tembisa, Tshwane line
Have included an mode shift to rail in SITPN but conservative due to uncertainty
PRASA should be major mode from South with mini bus taxis as feeders to rail
Gautrain City model does not show strong case
for Gautrain. Still to engage with Gautrain on proposed expansion
Gautrain business case built on switch from private car users and thus does not take up any existing public transport demand.
City plans to incorporate Gautrain bus routes in SIPTN so there is a single bus network
Gautrain working on bank based card to ensure integration of ticket medium
Integrated operational planning
We have divided the City into ‘transport catchment areas’ and for each catchment area are developing and then implementing: Detailed Public Transport Operational Plan setting out the
routes, modes, scheduled and unscheduled services, number of vehicles per mode, etc..
Infrastructure plan including number of open, closed stations, interchange, ITS, etc..
Operating Licensing Strategy to include how “seats are allocated” where new buses replace old buses/taxis and how OLS will be allocated to existing/new services
Business plans (fundable, bankable, etc.) for implementation
Also vehicle procurement strategy
across catchment
areas
Progress on operational planning
Focus at the moment is on: North East Quadrant (CBD,
Sandton, Modderfontein, Ivory Park, Midrand)
Greater Soweto (Soweto, CBD, Braamfisherville, South)
“Central areas” (Metrobus traditional areas but will change over time and Metrobus to focus on West (to Roodepoort) and South (Turffontein)
Need to start on “Deep South” with PRASA
Restructuring of Metrobus
What City will do Indicate to Metrobus what routes to
operate, with what frequencies Set and collect fares through an
integrated system Monitor bus through bus
management system Pay Metrobus per km travelled less
penalties Provide holding areas for Metrobus Marketing and communication of
services
What Metrobus will do Ensure buses function on
the routes and to the kms prescribed by the City
Employ, train and manage drivers
Maintain buses Procure new buses
according to a recapitalisation plan
Alignment between Metrobus routes and ITN
With the development of the Integrated Transport Network, we have now:• Aligned the Metrobus routes
to the ITN• Concentrated Metrobus on
C/D network types• Developed a sequenced
implementation plan linked to other operational plan roll outs
• Looked at areas of integration with Rea Vaya and mini bus taxis.
Concluding remarks
Concluding remarks or questions
Retrofitting is inevitable but complex and fraught Planning retrofitting: political imperatives, decisions
made on incomplete information Infrastructure retrofitting: across spheres of
government and within the City, changing demand patterns and horizon years, planned budget vs detailed design budget etc.
Taking out the “R” and introducing “incrementalism” may be more manageable but can it still meet our transformational objectives?