mount stromlo campus building m908 hazardous materials …roads and bike trails only robson...

119
Mount Stromlo Campus Building M908 Hazardous Materials Report This document is uncontrolled once printed. You must consult the individual Building Register prior to work commencing.

Upload: others

Post on 04-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Mount Stromlo Campus

Building M908

Hazardous Materials Report

This document is uncontrolled once printed.

You must consult the individual Building

Register prior to work commencing.

Page 2: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Contents Page 1. Revision Table

2. ANU Hazardous Materials Register

3. ANU Hazardous Materials Maintenance Log

4. Robson Environmental Report Dated January 2019

5. Future Inspection Reports and Certificates

Page 3: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

1. Revision Table – Building M908

Rev.

Nature of changes

Approval

Date

1 Asbestos Management Plan Report Generated

M908 Mount Stromlo General Site - Common Areas,

Roads and Bike Trails Only

Robson Environmental

04/04/2019

2 Lead Paint Management Plan Report Generated M908 Mount Stromlo General Site

Robson Environmental

09/05/2019

3 Lead Paint Management Plan Report Generated M908 Mount Stromlo General Site - Oddie Telescope

Robson Environmental

20/05/2019

4

5

6

7

Page 4: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

2. ANU Hazardous Materials Register

Page 5: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Site Location: Building M908 - General SiteAssessor: Jordan Curbishley - Robson Environmental

B1478 AMO CRO CHRY

Refer to Robson Report

Moulded Sheet Exterior island opposite tennis courts adjacent main road - In ground services pit (T18) 1 3 3 2 3 54 H 1 no. Remove

Refer to B1478 AMO CRO CHRY

Refer to Robson Report

Moulded Sheet Exterior island opposite tennis courts adjacent main road - In ground services pit (T17) 1 3 3 2 3 54 H 1 no. Remove

Refer to B1478 AMO CRO CHRY

Refer to Robson Report

Moulded Sheet Exterior adjacent main road - In ground services pit (T15) 1 3 3 2 3 54 H 1 no. Remove

Refer to B1478 AMO CRO CHRY

Refer to Robson Report

Moulded Sheet Exterior adjacent main road - In ground services pit (T16) 1 3 3 2 3 54 H 1 no. Remove

C1475 AMO CHRYRefer to Robson Report

Sheet Debris Exterior adjacent west boundary fence to lower houses - sheet 1 3 3 2 3 54 H Unknown Remove

C1476 AMO CHRYRefer to Robson Report

Sheet Debris Exterior builders waste dump - north corner of lower houses - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1478 AMO CHRYRefer to Robson Report

Sheet Debris Exterior builders waste adjacent abandoned driveway off main road - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1479 CHRYRefer to Robson Report

Sheet Debris Exterior south of work depot - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1480 CHRYRefer to Robson Report

Sheet Debris Exterior adjacent track on the north side of work depot - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1481 CHRYRefer to Robson Report

Sheet Debris Exterior south side of main road - compressed sheet 1 3 3 2 3 54 H Unknown Remove

C1482 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior west side of house near bushland - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1483 AMO CHRYRefer to Robson Report

Sheet Debris Exterior west end of Stromlo Observatory complex - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1484 AMO CHRYRefer to Robson Report

Sheet Debris Exterior below gully at the west end of the Stromlo Observatory complex - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1485 AMO CHRYRefer to Robson Report

Sheet Debris Exterior south west of main Stromlo complex - sheet fragments 1 3 3 2 3 54 H Unknown Remove

Res

ults

Phot

o ID

Description Location

Reinspection Date: January 2024Inspection Date: January 2019

Ris

k Sc

ore

Act

ion

Prio

rity

Qua

ntity

(m, m

2, m

3)

Actions/Comments

Asbestos Containing Materials

Asb

esto

s Ty

pe

Con

ditio

n

Acc

essi

bilit

y

Airb

orne

Pot

entia

l

Expo

sure

Pot

entia

l

Sample No.

Page 6: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

C1486 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior adjacent main road - sheet fragments 1 3 3 2 3 54 H Unknown Remove

Refer to C1486 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior south of C1486 in house footprint - sheet fragments 1 3 3 2 3 54 H Unknown Remove

Refer to C1486 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior south west corner of house - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1487 AMO CHRYRefer to Robson Report

Sheet Debris Exterior west of student accommodation - sheet fragments 1 3 3 2 3 54 H Unknown Remove

Refer to C1487 AMO CHRYRefer to Robson Report

Sheet Debris Exterior adjacent soil dump - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1488 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior north of the green work shed - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1489 AMO CHRYRefer to Robson Report

Sheet Debris Exterior east of telescope dome - sheet fragments 1 3 3 2 3 54 H Unknown Remove

RA C1489 AMO CHRYRefer to Robson Report

Sheet Debris Exterior east of telescope dome - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1490 AMO CHRYRefer to Robson Report

Sheet Debris Exterior down slope of telescope - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1491 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior west bank north end - sheet fragments 1 3 3 2 3 54 H Unknown Remove

Refer to C1491 AMO CRO CHRY

Refer to Robson Report

Sheet Debris Exterior west bank north end - sheet fragments 1 3 3 2 3 54 H Unknown Remove

C1493 CHRYRefer to Robson Report

Sheet Debris Exterior north of top telescopes - sheet fragments 1 3 3 2 3 54 H Unknown Remove

B1455 NADRefer to Robson Report

Moulded Sheet Exterior T7 adjacent main road - In ground services pit - - - - - - N 1 no. No further action required

B1472 NADRefer to Robson Report

Moulded Sheet Exterior T13 east of new student accommodation block - In ground services pit - - - - - - N 1 no. No further action required

C1474 NADRefer to Robson Report

Moulded Sheet Exterior T1 east side of main road opposite houses - In ground services pit - - - - - - N 1 no. No further action required

C1477 NADRefer to Robson Report

Cement Sheet Exterior builders waste dump - north corner of lower houses - jointing material to pipe - - - - - - N - No further action required

C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – Paint sample from FHB01Road adjacent Oddie Telescope - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB02Road adjacent Visitors Centre - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB03Road between Visitors Centre and Directors Residence - - - - - - M - Encapsulate with paint

Maintain in a good condition

Lead Paint Systems (Sampled materials found to be above the threshold criteria of 0.1% by w/w)

No Asbestos Detected

Page 7: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB04Road adjacent Melbourne 50" Telescope - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB05Road adjacent Commonwealth Solar Observatory Building - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB06 (x2)Burnt out house near Faulkner Court - - - - - - M - Remove

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB07Road adjacent houses - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB08Road adjacent shipping containers - - - - - - M - Encapsulate with paint

Maintain in a good condition

Refer to C1494 4.20%Refer to Robson Report

Red Paint Mount Stromlo Observatory – FHB09Road adjacent House 8 - - - - - - M - Encapsulate with paint

Maintain in a good condition

Pb01 >0.06%Refer to Robson Report

Orange Paint Mount Stromlo Observatory – paint to fire hydrantsThroughout site - - - - - - L - Maintain in a good condition

Pb02 >0.06%Refer to Robson Report

Orange Paint Mount Stromlo Observatory – paint to fire extinguisher boxRoad adjacent Melbourne 50" Telescope - - - - - - M - Encapsulate with paint

Maintain in a good condition

Pb03 >0.06%Refer to Robson Report

Red/White Paint Mount Stromlo Observatory – paint to No Smoking signRoad adjacent Melbourne 50" Telescope - - - - - - M - Encapsulate with paint

Maintain in a good condition

Pb04 >0.06%Refer to Robson Report

White Paint Mount Stromlo Observatory – paint to Bowser PumpRoad adjacent Melbourne 50" Telescope - - - - - - M - Encapsulate with paint

Maintain in a good condition

C1523 9.20%Refer to Robson Report

White Paint Mount Stromlo Observatory – paint sample from Oddie Telescope - - - - - - H -Remediate the paint to the telescope

Remediate the soil adjacent the telescope Maintain in a good condition

Pb05 <0.06%Refer to Robson Report

White Paint Mount Stromlo Observatory – paint to concrete blocksOld Seismic Station - - - - - - N - No further action required

Above-ground and Underground Storage TanksNo Above Or Underground Storage Tanks Identified.

No PCB Containing Materials Identified.

Lead Soils (Sampled materials found to be above the ASC NEPM (2013) HIL A site assessment criteria of 300 mg/kg)

Lead Free Soils (Sampled materials found to be below the ASC NEPM (2013) HIL A site assessment criteria of 300 mg/kg)No Lead Soil Samples Taken.

No Lead Free Soil Samples Taken.

No SMF Containing Materials Identified.SMF Containing Materials

PCB Containing Materials

ODS Containing MaterialsNo ODS Contatin Materials Identified.

Lead Free Paint Systems (Sampled materials found to be below the threshold criteria of 0.1% by w/w)

Lead Dust

Lead Free DustNo Lead Dust Samples Taken.

No Lead Free Dust Samples Taken.

Page 8: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

3. ANU Hazardous Materials Maintenance Log

Page 9: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Hazardous Materials Maintenance Log

Site: Building M908 – General Site

ANU Hazardous Materials Maintenance Log The following log should be maintained by the responsible person. It should contain information relating to the on-going maintenance or control measures associated with ACM including removal, remedial works, repairs, inspection, monitoring and clearance details etc.

Site: Building M908 Date Scope/Location Carried out by Result/Comments Entered by 31/01/2019

– 02/02/2019

Original Asbestos Survey Jordan Curbishley & Ben Kendon – Robson Environmental

Undertake a survey of the common areas, roads and bike trails to identify and assess asbestos materials.

Jordan Curbishley – Robson Environmental

25/03/2019 Asbestos Management Plan Report completed

Jordan Curbishley – Robson Environmental

New Asbestos Management Plan Report & Register produced and delivered.

Jordan Curbishley – Robson Environmental

15/04/2019 Original Lead Paint Survey Jordan Curbishley – Robson Environmental

Undertake a survey of the general site to identify and assess lead paint systems

Jordan Curbishley – Robson Environmental

09/05/2019 Lead Paint Management Plan Report completed

Jordan Curbishley – Robson Environmental

New Lead Paint Management Plan Report produced and delivered Updated existing Register to include lead paint systems

Jordan Curbishley – Robson Environmental

20/05/2019 Oddie Telescope Lead Paint Management Plan Report completed

Jordan Curbishley – Robson Environmental

New Oddie Telescope Lead Paint Management Plan Report produced and delivered Updated existing Register to include lead paint systems

Jordan Curbishley – Robson Environmental

Page 10: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

4. Robson Environmental Report

Page 11: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

This report MUST NOT be used as a removal specification

Client: ANU The Australian National University, Canberra, ACT, 2601

No. 3181 Accredited for compliance with

ISO/IEC 17020 Robson Environmental Pty Ltd ~ ABN: 55 008 660 900 ~ www.robsonenviro.com.au

p: 02 6239 5656 ~ f: 02 6239 5669 ~ [email protected] PO Box 112 Fyshwick ACT 2609 ~ 140 Gladstone Street Fyshwick ACT 2609

H2410_T-07266_Mount Stromlo Observatory-20190131

Asbestos Survey & Management Plan

Mount Stromlo Observatory – Common Areas, Roads and Bike Trails Only

Cotter Road

Block 38

Weston Creek ACT 2611

January 2019

Page 12: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 2 of 61

CERTIFICATE OF APPROVAL FOR ISSUE OF DOCUMENTS Document No: H2410 Revision Status: 1 Title: Asbestos Survey & Management Plan Date of Issue: 25/03/2019 Mount Stromlo Observatory - Common Areas, Roads and Bike Trails Only Cotter Road Block 38 Weston Creek ACT 2611

Client: ANU Copy No: One

Assessor Position Signature

Surveyed by:

Ben Kendon - Licensed Asbestos Assessor #LAA001094

Jordan Curbishley – Licensed Asbestos Assessor #AA00039

Manager Environmental Assessment & Remediation

Hazardous Materials

Consultant

Approved by: Anne Robson - Licensed Asbestos Assessor #AA00022 Director

Released by: Anne Robson - Licensed Asbestos Assessor #AA00022 Director

RELEASE STATUS:

Confidential

© Copyright Robson Environmental Pty Ltd

All intellectual property and copyright reserved.

This report remains the property of Robson Environmental Pty Ltd (“Robson”). The person commissioning the report (“the client”) is entitled to retain possession of it upon payment of Robson’s fees or upon arrangements as to payment satisfactory to Robson has been made.

Apart from any fair dealing for the purpose of private study, research, criticism or review, as permitted under the Copyright Act, 1968 the client may not photocopy or otherwise reproduce, transmit, store in a retrieval system or adapt in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) all or any part of this report without the prior written consent of Robson.

In the event that the client photocopies or otherwise reproduces all or any part of this report without the prior written consent of Robson then the client:

a) must immediately upon demand of Robson return to Robson the original (or, if more than one , all originals) and all photocopies or other reproductions of the report;

b) agrees to pay Robson any loss or damage suffered as a result of the breach by the client of this provision; and c) agrees to indemnify Robson against any liability arising from the breach by the client of this provision.

Enquiries should be addressed to Robson Environmental Pty. Ltd.

DISTRIBUTION

Organisation Attention Copy No. Actioned

ANU Brett Morrison 1 25/03/2019

Robson Environmental Pty Ltd John Robson 2 25/03/2019

Page 13: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 3 of 61

Table of Contents

1 EXECUTIVE SUMMARY ......................................................................................................................... 5

1.1 Purpose .................................................................................................................................................................5

1.2 Scope ....................................................................................................................................................................5

1.3 Method ...................................................................................................................................................................5

1.4 Asbestos Key Findings ..........................................................................................................................................6

2 INTRODUCTION ................................................................................................................................... 11

2.1 Requirements for the Asbestos Survey & Management Plan .............................................................................. 11

2.2 Exclusions ........................................................................................................................................................... 12

2.3 Limitations ........................................................................................................................................................... 12

3 ASBESTOS SURVEY ........................................................................................................................... 13

3.1 Survey Details...................................................................................................................................................... 13

3.2 Survey Methodology ............................................................................................................................................ 13

3.3 Sample Analysis .................................................................................................................................................. 13

4 ASBESTOS RISK ASSESSMENT ........................................................................................................ 16

4.1 Introduction .......................................................................................................................................................... 16

4.2 Asbestos Register ................................................................................................................................................ 18

4.3 Risk Assessment ......................................................................................................................................... 24

5 ASBESTOS MANAGEMENT ................................................................................................................ 25

5.1 Control Measures ........................................................................................................................................ 25

5.2 Asbestos Emergency Procedures ............................................................................................................... 26

5.3 Management of ACM ................................................................................................................................... 27

5.4 PMCW Decision Record .............................................................................................................................. 29

5.5 Timetable for Action ..................................................................................................................................... 31

6. RESPONSIBILITIES .............................................................................................................................. 33

6.1 PMCW Responsibilities ............................................................................................................................... 33

6.2 Updating the Risk Assessment .................................................................................................................... 34

6.3 Key Personnel ............................................................................................................................................. 35

7 ASBESTOS REMOVAL WORKS .......................................................................................................... 36

7.1 PMCW Responsibilities ............................................................................................................................... 36

7.2 Removalist Responsibilities ......................................................................................................................... 36

Page 14: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 4 of 61

7.3 Approval to Begin Asbestos Removal Works .............................................................................................. 36

7.4 Work in Areas Containing Asbestos – Trades Personnel ............................................................................ 36

7.5 Emergency Work in Areas Containing Asbestos ......................................................................................... 36

7.6 Monitoring Arrangements ............................................................................................................................ 37

7.7 Clearance Inspections Prior To Re-Occupation .......................................................................................... 37

7.8 ACM removal/maintenance record .............................................................................................................. 37

8 UPDATING THE ASMP ......................................................................................................................... 40

9 APPENDICES........................................................................................................................................ 41

9.1 APPENDIX A – Laboratory Results ..................................................................................................................... 41

9.2 APPENDIX B – Plans .......................................................................................................................................... 45

9.3 APPENDIX C – ACM Item Locations & Representative Photographs ................................................................. 50

9.4 APPENDIX D – Glossary ............................................................................................................................. 60

Page 15: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 5 of 61

1 Executive Summary

1.1 Purpose

This Asbestos Survey & Management Plan (ASMP) for Mount Stromlo Observatory, Cotter Road, Block 38, Weston Creek ACT was commissioned by ANU in order to ensure the occupants receive the highest standards of occupational health and safety in relation to asbestos. The implementation of this Management Plan will assist the client in protecting the occupational health and safety of the occupants and address the regulatory requirements of a person with Management or Control of the Workplace (PMCW) in relation to asbestos in the premises.

1.2 Scope

Hazardous materials assessed included ACM, SMF, PCBs, lead containing paint, ODS and A/UST. The survey commenced on 31 January 2019 to 12 March 2019.

The aim of the survey was to assess the extent, location and condition of Asbestos Containing Material (ACM) on the Mount Stromlo Observatory common areas, roads and bike trails only Materials in similar locations which were visually consistent with those which have been identified as being an ACM are to be considered as being identical.

1.3 Method

The survey involved a visual inspection and subsequent sampling and analysis of collected samples by Robson’s National Association of Testing Authorities (NATA) accredited laboratory using polarised light microscopy. Samples were a representative selection of materials suspected of containing asbestos. Materials were not sampled from all areas due to the uniformity of the materials used.

All site surveying, sampling, laboratory analysis and reporting is in accordance with Robson Environmental’s NATA, ISO9001, AS4801 and ISO14001 accreditations.

The information contained in this document will assist the PMCW to fulfil their obligations under the latest editions of the following codes, regulations/Acts:

How to Manage and Control Asbestos in the Workplace Code of Practice

How to Safely Remove Asbestos Code of Practice

Dangerous Substances (General) Regulation 2004

ACT Dangerous Substances Act 2004

Work Health and Safety Act 2011

Work Health and Safety Regulations 2011

Page 16: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 6 of 61

1.4 Asbestos Key Findings

Table 1A: ACM locations and required actions

Mount Stromlo Observatory ACM Location Action to be Taken

Sheet debris (Non-Friable)

Exterior adjacent main road - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior adjacent soil dump - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior adjacent track on the north side of work depot - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior adjacent west boundary fence to lower houses - sheet Remove

Sheet debris (Non-Friable)

Exterior below gully at the west end of the Stromlo Observatory complex - sheet

fragments Remove

Sheet debris (Non-Friable)

Exterior builders waste adjacent abandoned driveway off main road - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior builders waste dump - north corner of lower houses - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior down slope of telescope - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior east of telescope dome - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior east of telescope dome - sheet fragments Remove

Moulded Sheet (Non-Friable)

Exterior island opposite tennis courts adjacent main road - In ground services pit Remove

Sheet debris (Non-Friable)

Exterior north of the green work shed - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior north of top telescopes - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior south of C1486 in house footprint - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior south of work depot - sheet fragments Remove

Pipe (Non-Friable)

Exterior south side of main road - compressed sheet Remove

Sheet debris (Non-Friable)

Exterior south west corner of house - sheet fragments Remove

Page 17: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 7 of 61

Mount Stromlo Observatory ACM Location Action to be Taken

Sheet debris (Non-Friable)

Exterior south west of main Stromlo complex - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior west bank north end - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior west bank north end - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior west end of Stromlo Observatory complex - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior west of student accommodation - sheet fragments Remove

Sheet debris (Non-Friable)

Exterior west side of house near bushland - sheet fragments Remove

Refer to Section 1.4 - Table 1B for presumed ACMs and Section 2.2 for exclusions

Page 18: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 8 of 61

Table 1B: Presumed ACM, concealed locations and required actions

Type ACM Locations Action to be taken

The materials listed below while not identified on site, should be presumed to be present until a destructive survey confirms otherwise

Presumed ACM

Asbestos cement sheet formwork and electrical cable duct / water pipe debris

Subterranean areas

Any excavation works in the areas or

adjacent areas where ACM has been

identified should be undertaken by

qualified Asbestos personnel under the

supervision of an Asbestos Assessor.

Prior to any planned demolition, refurbishment or maintenance, its effect upon any in situ asbestos must be established by reference to this document including amendments.

Page 19: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 9 of 61

Recommendations

The GPS coordinates for all ACM finds were recorded. Please refer to Appendix B – Plans.

The majority of the observed ACM was located within the footprints of the building sites which had burned down in previous bush fires. The ACM consisted of small fragments which appear to be predominately on the soil surface and are likely to be remnant waste from previously demolished / degraded infrastructure or illegal dumping on site.

ACM was observed to the areas outside these footprints but at a reduced frequency. A significant dump (C1490) was discovered down slope and west of the visitor’s car park adjacent one of the dirt access tracks. Buried asbestos debris may be present beyond the perimeter of the above specified areas. Care must be taken when excavation works are carried out in the contaminated and adjacent areas because asbestos debris may be uncovered at depth.

In ground service pits identified as T15 – T18 in the plans were identified as containing asbestos. These pits are in poor condition and should be removed by a licensed asbestos removalist.

All other in ground service pits identified as T1-T14 in the plans were identified as containing non-asbestos cement sheet.

All ACM finds on site are categorized as non-friable ACM in poor condition.

The presence of the asbestos poses a low risk to site occupants (including the general public). However the areas of impact should either be cordoned off and appropriately sign posted to prevent access to unauthorized personnel or the asbestos removed by hand (‘chicken picked’) by an ACT licensed asbestos removalist.

Due to the extent of the sporadic finds across the site it has also been assessed that it is unlikely that all the ACM will be able to be removed successfully from the site. Therefore Robson recommends an asbestos management plan (AMP) with an unexpected finds protocol (UFP) be developed for the site to manage all ACM finds into the future.

ACM must not be drilled, cut, sanded, damaged or abraded and a good paint finish maintained. Asbestos work on non friable ACM may be undertaken by a licensed Class A or B Asbestos Removalist. Any works on, or in the vicinity of friable ACM must only be undertaken by a licensed Class A Asbestos Removalist.

The Asbestos Register including any risk assessments should be reviewed within the time period recommended by the Asbestos Assessor in 4.2 Asbestos Register Table 3A or earlier where:

- A risk assessment indicates the need for reassessment or - Any ACM has been disturbed or moved

ACM should be labelled with approved asbestos warning labels or signs. Due to the stigma associated with asbestos and to avoid malicious damage to ACM, labelling can be kept to discrete areas. Where labelling cannot be undertaken, the PMCW must adopt strict administrative controls to ensure ACM is not subject to accidental damage.

Page 20: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 10 of 61

Asbestos Removal

Removal of ACM must be undertaken by a licensed Asbestos Removalist in accordance with current legislation. The removal/remediation of friable ACM must be undertaken by a licensed Class A Asbestos Removalist. Removal or remediation of non friable asbestos may be undertaken by either an A or B Class Asbestos Removalist.

Prior to the commencement of any removal or remediation works associated with any amount of friable or non friable asbestos a building certifier must be engaged and building approval granted. An application must be submitted to WorkSafe ACT and ComCare (where applicable) at least 5 days prior to removal works commencing. An asbestos removal contractor must supply an Asbestos Removal Control Plan (ARCP) and a Safe Work Method Statement (SWMS). An independent licensed Asbestos Assessor should be engaged to ensure that the ARCP addresses all safety issues relating to the planned asbestos works.

Air monitoring is mandatory during the removal or remediation of friable asbestos and should be considered during the removal or remediation of non friable asbestos. Air sampling is to be undertaken in accordance with the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres, 2nd Edition and test certificates should be NATA endorsed.

An independent Asbestos Assessor must also be employed to undertake a Clearance Inspection of either friable and non friable asbestos removal or remediation works. A satisfactory clearance certificate for the remediated areas must ensure that no visible asbestos or presumed asbestos remains. Additionally no asbestos fibres should be detected by laboratory analysis if any validation samples are taken. All surfaces within the remediated area must be free of general dust and debris.

Page 21: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 11 of 61

2 INTRODUCTION

This ASMP is designed to address the safe control of ACM identified by Robson Environmental Pty Ltd in the premises. It is also designed to address any future asbestos findings.

This ASMP contains sections covering the identification, evaluation and control of asbestos hazards which were identified during the survey.

2.1 Requirements for the Asbestos Survey & Management Plan

The PMCW must retain a copy of this ASMP and it must be distributed to tenants. Prior to any repair, maintenance or building works to the premises, all stakeholders must be provided with a copy of this ASMP.

Maintenance, trades and other personnel must be instructed not to remove or damage identified or suspected ACM. If ACM is identified in the area where work is to be undertaken the ACM must be removed prior to the work commencing.

Removal of ACM must be undertaken by an ACT licensed Asbestos Removalist in accordance with current legislation.

This ASMP includes the following:

A register of all known ACM Extent, form, condition and risks associated with the ACM Labelling requirements for ACM Safe work methods, removal methods and training requirements Responsibilities of all persons involved in ACM management Procedures to address incidents or spillage involving ACM A timetable for managing risks, including priorities for removal or control of ACM

according to risk and timetable for reviewing risk assessments A procedure for reviewing and updating the ASMP and register of ACM, including a

timetable

This ASMP addresses the current requirements for asbestos management and therefore must be updated as required to reflect legislative changes. The asbestos register and associated risk assessment within this ASMP is designed to be reviewed by a licensed Asbestos Assessor at the intervals shown in 4.2 Asbestos Register Table 3A.

Where ACM has been disturbed, removed, enclosed, encapsulated, sealed or its condition has deteriorated, the existing asbestos risk assessment will no longer be valid and the ASMP will need to be reviewed by the licensed Asbestos Assessor to reflect these changes. Each review should critically assess all the asbestos management procedures and their effectiveness in:

Preventing exposure to asbestos Controlling access to asbestos Highlighting the need for action to maintain or remove ACM Maintaining the accuracy of the ASMP

Details of any mitigating factors must be recorded in the Asbestos Register (refer 4.2 Table 3A).

Page 22: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 12 of 61

2.2 Exclusions

The HMSMP commissioned by the client was to be non-destructive and non-intrusive in nature. This type of commission limits or restricts access to the building structure, some surfaces and materials. No determination can be made regarding the possibility of concealed or inaccessible ACM without gaining access to areas that are not readily accessible to allow for inspections.

Unless specifically noted, the survey did not cover exterior ground surfaces, sub-surfaces (e.g. infill/soil) or items such as materials in laboratories or special purpose facilities.

When any building works are undertaken, care should be taken to determine the existence or otherwise of ACM. As a precaution, all materials that may, or are likely to contain asbestos should be assumed to contain asbestos and be treated appropriately until laboratory analysis confirms otherwise. If, during building works, ACM is located, those works should cease in the areas of concern and a licensed Asbestos Removalist contacted immediately to remove the material. A licensed Asbestos Assessor must issue a clearance certificate before works may recommence in the affected area.

Robson Environmental Pty Ltd recommends that prior to any works, our office be contacted. Our Asbestos Assessors can attend the site to observe the works process, advise as necessary, and in the event of asbestos being located, assist with assessing the extent of ACM. Further, Robson Environmental Pty Ltd provides all occupational hygiene services in relation to asbestos removal.

2.3 Limitations

Although all reasonable care and attention is taken in compiling this report, no guarantee as to its accuracy or completeness can be given. This may be a result of:

normal construction practices of 'building in' some ACM (i.e. during previous renovations or additions)

the random application of asbestos materials other physical or applied constraints on our investigation

Our report is limited by the physical constraints of the structure under investigation. Prior to any refurbishment or hazardous material removal projects, the contractor(s) carrying out the work must fully acquaint themselves with the extent of the hazardous materials, particularly in those areas which may require full or partial demolition, in order to determine the exact extent and location of these materials.

Although extensive, this ASMP must not be used as a specification or method statement for any future asbestos removal project. In these circumstances, detailed plans and quantities would be required.

Page 23: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 13 of 61

3 ASBESTOS SURVEY

3.1 Survey Details

The survey of the site included all accessible areas of the building(s) except where stated otherwise. For further asbestos management information, refer to Appendix D.

3.2 Survey Methodology

The survey involved a visual inspection and subsequent sampling and analysis of materials in Robson Environmental's NATA accredited laboratory using polarised light microscopy. Samples were a representative selection of materials suspected of containing asbestos. Materials were not sampled from all areas due to the uniformity of the materials used.

3.3 Sample Analysis

Table 2: Mineralogical analysis of samples for asbestos using polarising light microscopy

Mount Stromlo Observatory Sample

Reference Sample Location Sample Type Composition

B1455 Exterior adjacent main road - In ground services pit Moulded Sheet No Asbestos

Detected

B1472 Exterior east of new student

accommodation block - In ground services pit

Moulded Sheet No Asbestos Detected

B1478 Exterior island opposite tennis courts adjacent main road - In

ground services pit Moulded Sheet

Amosite, Chrysotile, Crocidolite Asbestos

Detected

C1474 Exterior T1 east side of main road

opposite houses - In ground services pit

Moulded Sheet No Asbestos Detected

C1475 Exterior adjacent west boundary fence to lower houses - sheet Sheet debris Amosite, Chrysotile

Asbestos Detected

C1476 Exterior builders waste dump - north corner of lower houses -

sheet fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1477 Exterior builders waste dump - north corner of lower houses -

jointing material to pipe Cement sheet No Asbestos

Detected

C1478 Exterior builders waste adjacent

abandoned driveway off main road - sheet fragments

Sheet debris Amosite, Chrysotile Asbestos Detected

C1479 Exterior south of work depot - sheet fragments Sheet debris Chrysotile Asbestos

Detected

Page 24: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 14 of 61

Mount Stromlo Observatory Sample

Reference Sample Location Sample Type Composition

C1480 Exterior adjacent track on the north

side of work depot - sheet fragments

Sheet debris Chrysotile Asbestos Detected

C1481 Exterior south side of main road - compressed sheet Pipe Chrysotile Asbestos

Detected

C1482 Exterior west side of house near bushland - sheet fragments Sheet debris

Amosite, Chrysotile, Crocidolite Asbestos

Detected

C1483 Exterior west end of Stromlo Observatory complex - sheet

fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1484 Exterior below gully at the west end

of the Stromlo Observatory complex - sheet fragments

Sheet debris Amosite, Chrysotile Asbestos Detected

C1485 Exterior south west of main Stromlo complex - sheet fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1486 Exterior adjacent main road - sheet fragments Sheet debris

Amosite, Chrysotile, Crocidolite Asbestos

Detected

C1487 Exterior west of student accommodation - sheet fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1488 Exterior north of the green work shed - sheet fragments Sheet debris

Amosite, Chrysotile, Crocidolite Asbestos

Detected

C1489 Exterior east of telescope dome - sheet fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1490 Exterior down slope of telescope - sheet fragments Sheet debris Amosite, Chrysotile

Asbestos Detected

C1491 Exterior west bank north end - sheet fragments Sheet debris

Amosite, Chrysotile, Crocidolite Asbestos

Detected

C1493 Exterior north of top telescopes - sheet fragments Sheet debris Chrysotile Asbestos

Detected

NATA accredited laboratory:

Robson Environmental Pty Ltd Accreditation number: 3181

Page 25: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 15 of 61

Legend

Chrysotile = white asbestos Amosite = grey or brown asbestos

Crocidolite = blue asbestos

It should be noted that the above samples were a representative selection of materials suspected of containing asbestos.

Samples may not have been taken from all areas due to the uniformity of the materials used throughout the premises.

On-site inspections and an examination of the asbestos register and accompanying plans within this report should be undertaken prior to the commencement of any asbestos removal programme.

Robson Environmental Pty Ltd has taken all care to ensure that this report includes the most accurate information available. Where it uses test results prepared by third parties, it relies on the accuracy of the test results in preparing this report. In providing this report, Robson Environmental Pty Ltd does not warrant the accuracy of such third party analytical results.

Page 26: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 16 of 61

4 ASBESTOS RISK ASSESSMENT

4.1 Introduction

The purpose of the risk assessment is to enable informed decisions to be made concerning the control of ACM. The risk assessment should take into account the information in the Asbestos Register including:

the type of ACM (friable or non friable) the condition and location of ACM whether the ACM is likely to be disturbed due to its condition and location the likelihood of exposure

Types of ACM

Non friable ACM

Non friable asbestos (previously known as bonded asbestos) is any material that contains asbestos firmly bound into a matrix. It may consist of cement or various resins/binders and cannot be reduced to a dust by hand pressure. As such it does not present an exposure hazard unless cut, abraded, sanded or otherwise disturbed. Therefore, the exposure risk from non friable ACM is negligible during normal building occupation.

Note: if non friable ACM is damaged or otherwise deteriorated, the risk assessment must be reviewed to reflect a higher potential for exposure to asbestos fibres. Severely damaged, non friable ACM may be assessed as being friable. A licensed Asbestos Assessor must perform the risk assessment.

Friable ACM

Friable asbestos material can be crumbled or reduced to a dust by hand pressure when dry. It can represent a significant exposure hazard as a consequence of minor disturbance. Examples of friable asbestos are hot water pipe lagging, severely damaged asbestos cement sheet, limpet spray to structural beams and electrical duct heater millboard.

Page 27: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 17 of 61

ACM CONDITION RATING

1 Severe Friable: Readily accessible, deteriorated surface in extremely poor condition

2 Poor Friable: Unstable material that is relatively accessible Non friable: Readily accessible, deteriorated surface

3 Normal Friable: Stable asbestos that is relatively inaccessible Non friable: Accessible surfaces in fair condition

4 Good Non friable: Well sealed stable surfaces in accessible locations

ACM RISK RATING

A Very High Friable: Exposure to airborne asbestos as a consequence of extremely minor disturbance

B High

Friable: Exposure to airborne asbestos occurs as a consequence of minor disturbance Non friable: Exposure to airborne asbestos likely as a consequence of significant disturbance

C Medium

Friable: Exposure to airborne asbestos unlikely during normal building use Non friable: Exposure to airborne asbestos highly unlikely during normal building use

D Low Non friable: No exposure to airborne asbestos during normal building use

Page 28: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 18 of 61

4.2 Asbestos Register

The Asbestos Register details the type, location, risk rating and action required for all identified ACM. The register should be accessed to inform all decisions made concerning the control of ACM. Action taken to control ACM must be recorded in this register in order to comply with current legislation.

Table 3A: Asbestos Register (to be updated as required)

Mount Stromlo Observatory

Sample No. ACM Type Locations Condition

Rating Risk

Rating Approx

Quantity Recommended

Management Action Action

Undertaken Assessor/

Date assessed

B1478 Moulded Sheet

Exterior island opposite tennis courts adjacent main road - In ground services pit

(T18)

2 B Unknown Remove

RA B1478 Moulded Sheet

Exterior island opposite tennis courts adjacent main road - In ground services pit

(T17)

2 B Unknown Remove

RA B1478 Moulded Sheet

Exterior adjacent main road - In ground services pit (T15) 2 B Unknown Remove

RA B1478 Moulded Sheet

Exterior adjacent main road - In ground services pit (T16) 2 B Unknown Remove

Page 29: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 19 of 61

Mount Stromlo Observatory

Sample No. ACM Type Locations Condition

Rating Risk

Rating Approx

Quantity Recommended

Management Action Action

Undertaken Assessor/

Date assessed

C1475 Sheet debris (Non-Friable)

Exterior adjacent west boundary fence to lower

houses - sheet 2 B Unknown Remove

C1476 Sheet debris (Non-Friable)

Exterior builders waste dump - north corner of lower

houses - sheet fragments 2 B Unknown Remove

C1478 Sheet debris (Non-Friable)

Exterior builders waste adjacent abandoned

driveway off main road - sheet fragments

2 B Unknown Remove

C1479 Sheet debris (Non-Friable)

Exterior south of work depot - sheet fragments 2 B Unknown Remove

C1480 Sheet debris (Non-Friable)

Exterior adjacent track on the north side of work depot -

sheet fragments 2 B Unknown Remove

C1481 Pipe

(Non-Friable) Exterior south side of main road - compressed sheet 3 C Unknown Remove

C1482 Sheet debris (Non-Friable)

Exterior west side of house near bushland - sheet

fragments 2 B Unknown Remove

Page 30: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 20 of 61

Mount Stromlo Observatory

Sample No. ACM Type Locations Condition

Rating Risk

Rating Approx

Quantity Recommended

Management Action Action

Undertaken Assessor/

Date assessed

C1483 Sheet debris (Non-Friable)

Exterior west end of Stromlo Observatory complex - sheet

fragments 2 B Unknown Remove

C1484 Sheet debris (Non-Friable)

Exterior below gully at the west end of the Stromlo

Observatory complex - sheet fragments

2 B Unknown Remove

C1485 Sheet debris (Non-Friable)

Exterior south west of main Stromlo complex - sheet

fragments 2 B Unknown Remove

C1486 Sheet debris (Non-Friable)

Exterior adjacent main road - sheet fragments 2 B Unknown Remove

RA C1486 Sheet debris (Non-Friable)

Exterior south of C1486 in house footprint - sheet

fragments 2 B Unknown Remove

RA C1486 Sheet debris (Non-Friable)

Exterior south west corner of house - sheet fragments 2 B Unknown Remove

C1487 Sheet debris (Non-Friable)

Exterior west of student accommodation - sheet

fragments 2 B Unknown Remove

Page 31: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 21 of 61

Mount Stromlo Observatory

Sample No. ACM Type Locations Condition

Rating Risk

Rating Approx

Quantity Recommended

Management Action Action

Undertaken Assessor/

Date assessed

RA C1487 Sheet debris (Non-Friable)

Exterior adjacent soil dump - sheet fragments 2 B Unknown Remove

C1488 Sheet debris (Non-Friable)

Exterior north of the green work shed - sheet fragments 2 B Unknown Remove

C1489 Sheet debris (Non-Friable)

Exterior east of telescope dome - sheet fragments 2 B Unknown Remove

RA C1489 Sheet debris (Non-Friable)

Exterior east of telescope dome - sheet fragments 2 B Unknown Remove

C1490 Sheet debris (Non-Friable)

Exterior down slope of telescope - sheet fragments 2 B Unknown Remove

C1491 Sheet debris (Non-Friable)

Exterior west bank north end - sheet fragments 2 B Unknown Remove

RA C1491 Sheet debris (Non-Friable)

Exterior west bank north end - sheet fragments 2 B Unknown Remove

C1493 Sheet debris (Non-Friable)

Exterior north of top telescopes - sheet fragments 2 B Unknown Remove

RA = Referred to another sample as being the same material VA = Material visually assessed as being consistent with ACM

Page 32: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 22 of 61

Note: All asbestos items have been marked up on the plans – Refer to Appendix B Refer to Section 1.4 - Table 1B for presumed ACM and Section 2.2 for exclusions

Page 33: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 23 of 61

Table 3B: Register of sampled non-asbestos materials

Mount Stromlo Observatory

Sample number Type Locations

B1455 Moulded Sheet Exterior T7 adjacent main road - In ground services pit

B1472 Moulded Sheet Exterior T13 east of new student accommodation block - In ground services pit

C1474 Moulded Sheet Exterior T1 east side of main road opposite houses - In ground services pit

C1477 Cement sheet Exterior builders waste dump - north corner of lower houses - jointing material to pipe

Refer to Section 1.4 - Table 1B for presumed ACMs and Section 2.2 for exclusions

Page 34: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 24 of 61

4.3 Risk Assessment

Control Measures General Requirements

Any ACM which is not scheduled for immediate removal should be fenced off to prevent disturbance and appropriate signage displayed..

The details of any deterioration or removal must be entered into the ACM register. All site personnel must be made aware of the location of ACM. The Asbestos Register must be distributed to all stakeholders. Unless holding a valid Asbestos Removal Licence, maintenance all site personnel shall not

remove or knowingly damage identified, presumed or suspected ACM. Prior to any earth works which are likely to disturb the contaminated or adjacent areas its

effect upon any in situ asbestos must be established by reference to this document, including amendments.

Recommended Control Measures for the Premises

Identified, presumed or suspected ACM should be fenced off and approved asbestos warning labels or signs displayed. Where labelling is not practicable, strict administrative controls must be in place to ensure ACM is not subject to accidental damage or misuse.

Prior to any planned demolition, refurbishment or maintenance, its effect upon any in situ asbestos must be established by reference to this document, including amendments.

The asbestos register and associated risk assessments within the ASMP are designed to be reviewed by a licensed Asbestos Assessor at intervals stated in 4.2 Asbestos Register Table 3A.

Where an ACM has been disturbed, removed, enclosed, encapsulated, sealed or its condition has deteriorated, the existing asbestos risk assessment will no longer be valid and the ASMP will need to be revised by a licensed Asbestos Assessor to reflect these changes. – refer section 2.1.

Demolition or any other works within areas where asbestos is located is not to take place until the asbestos removal works have been completed and a Clearance Certificate issued by a licensed Asbestos Assessor.

Note: Buried asbestos debris may be present beyond the perimeter of the above specified areas. Care must be taken when excavation works are carried out in the contaminated and adjacent areas because asbestos debris may be uncovered at depth.

Page 35: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 25 of 61

5 ASBESTOS MANAGEMENT

5.1 Control Measures

General requirements

ACM identified as representing an exposure risk (see Table 3A) should be removed or otherwise controlled.

Any ACM that is not scheduled for immediate removal should be labelled with appropriate warnings and maintained in good condition.

The location of ACM must be entered into the Asbestos Register.

Maintenance and other personnel must be made aware of the location of ACM.

The Asbestos Register must be freely available.

Unless holding a valid Asbestos Removal Licence, maintenance workers, trades or occupants shall not remove or knowingly damage identified ACM.

Before any planned demolition, refurbishment or maintenance, its effect upon any in situ asbestos must be established by reference to this document, including amendments.

Page 36: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 26 of 61

5.2 Asbestos Emergency Procedures

The following course of action should be taken immediately if asbestos containing material (ACM) or suspected ACM is disturbed, or is accidentally damaged.

Evacuate all personnel from the immediate area and if present shut down the air-conditioning system

Restrict access to the area by locking or cordoning off the area until a full assessment has been completed

Report the incident to the PMCW and supply the exact location & short brief of what has occurred

PMCW immediately inform stakeholders of the incident

PMCW to engage a Licensed Asbestos Assessor to conduct a site assessment, take samples, conduct air monitoring (if required) and provide written report containing a risk

assessment

PMCW receives advice from Licensed Asbestos Assessor on outcome of site assessment

No asbestos present Asbestos present

Advise all stakeholders of the outcome Make safe using recommendations of the Licensed Asbestos Assessor

Resume normal operations Management Action & Remediation Plan and Asbestos Register updated

Page 37: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 27 of 61

5.3 Management of ACM

The options for short to medium-term management of ACM are outlined below.

1. Defer action

Appropriate when

Not appropriate when Advantages Disadvantages

Negligible risk of exposure and

Asbestos inaccessible and fully contained

or

Asbestos stable and not liable to damage

Possibility of deterioration or damage

Airborne dust exceeds recommended exposure standard

No initial cost

Cost of removal deferred

Hazard remains

Need for continuing assessment

Asbestos management program required

2. Encapsulate or seal1

Appropriate when

Not appropriate when Advantages Disadvantages

Removal difficult or not feasible Firm bond to substrate Damage unlikely Short life of structure

Asbestos deteriorating Application of sealant may cause damage to material Water damage likely Large areas of damaged asbestos

Quick and economical for repairs to damaged areas May be an adequate technique to control release of asbestos dust

Hazard remains Cost for large areas may be near removal cost Asbestos management system required Eventual removal may be more difficult and costly

1 Seal through application of paint, lacquer or PVA spray

Page 38: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 28 of 61

3. Removal

Appropriate when

Not appropriate when Advantages Disadvantages

Surface friable or asbestos poorly bonded to substrate Asbestos is severely water-damaged or liable to further damage or deterioration Located in air conditioning duct Airborne asbestos exceeds recommended exposure standard Other control techniques inappropriate

Located on complex and inaccessible surfaces Removal extremely difficult and other techniques offer satisfactory alternative

Hazard removed No further action required

Increases immediate risk of exposure especially to removal workers Creates major disturbance in building Often highest cost, most complex and time-consuming method Removal may increase fire risk in building; substitute required Possible contamination of whole building if removal is done poorly

Page 39: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 29 of 61

5.4 PMCW Decision Record

Option 1: Defer action

Item no. ACM and Location Reason Authorisation Date

Page 40: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 30 of 61

Option 2: Encapsulate or seal

Item no. ACM and Location Reason Authorisation Date

Option 3: Removal

Item no. ACM and Location Reason Authorisation Date

Page 41: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 31 of 61

5.5 Timetable for Action

The timetable for action should be administered to ensure the PMCW has a clear plan for all works which may affect ACM in the workplace. This includes maintenance work, scheduled removal work and risk assessment reviews that may impact ACM.

Table 4: Timetable for action

ACM removal/ work

Date of scheduled

works Details Authorisation Date

Page 42: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 32 of 61

ACM removal/ work

Date of scheduled

works Details Authorisation Date

Page 43: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 33 of 61

6. RESPONSIBILITIES

6.1 PMCW Responsibilities

The PMCW must:

ensure the ACM register and all relevant information pertaining to asbestos in the workplace is freely available upon request

provide occupants with up-to-date information relating to the condition and relative risk of ACM in the workplace

provide information on the control measures in place to contain ACM-related risk

provide information to staff and contractors on measures to be taken to ensure there is no exposure to asbestos in the workplace, either through accident or negligence

PMCW Action Record

Record all communication activities undertaken to inform staff/occupants of ACM in the workplace.

Action Authorisation Date

Page 44: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 34 of 61

6.2 Updating the Risk Assessment

The register of ACM, including any risk assessments, should be reviewed at the intervals stated in 4.2 Asbestos Register Table 3A or earlier where:

a risk assessment indicates the need for reassessment any ACM has been disturbed or moved

A visual inspection of identified ACM should be undertaken as part of any review.

Current legislation requires that an Asbestos Management Plan and Risk Assessments are required in addition to an Asbestos Register and Survey. Licensed Asbestos Assessors at Robson Environmental Pty Ltd are able to produce these documents to comply with your obligations.

Each review should critically assess all asbestos management procedures and their effectiveness in:

preventing exposure to asbestos fibres

controlling access to asbestos

highlighting the need for action to maintain or remove ACM

maintaining the accuracy of the ASMP

Details of any mitigating actions must be recorded in the 2.4 Asbestos Register Table 3A.

Page 45: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 35 of 61

6.3 Key Personnel

This section outlines the responsibilities of all persons involved in the safe management of ACM.

1. PMCW

Name:

Contact details:

Responsibilities: e.g. provision of information

2. Occupational Health and Safety Representative

Name:

Contact details:

Responsibilities: e.g. keeping occupants informed of any changes to the status of ACM in the workplace

3. Facilities Management (if applicable)

Name:

Contact details:

Responsibilities: e.g. arrange removal and repair works as required; maintaining the ASMP

4. Other Name:

Contact details:

Responsibilities:

Page 46: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 36 of 61

7 ASBESTOS REMOVAL WORKS

7.1 PMCW Responsibilities

Where it has been determined that ACM is to be removed, the PMCW must ensure that a risk assessment is performed prior to the removal works, and that the removalist takes this risk assessment into account. This risk assessment must include the possibility of uncovering previously concealed ACM and ensuring concealed ACM is identified by a licensed Asbestos Assessor. The PMCW should provide a detailed scope of works for the Asbestos Removalist, including potential hazards, details about areas which may contain asbestos and arrangements for clearance inspections and air monitoring.

7.2 Removalist Responsibilities

Prior to the commencement of removal works, the licensed asbestos removal contractor must:

provide a site-specific Asbestos Removal Control Plan (ARCP) ensure the removal is adequately supervised and carried out in a safe manner ensure all persons carrying out the removal are competent and trained for the type of work

being carried out demonstrate that they have a health surveillance program in accordance with current

legislation.

7.3 Approval to Begin Asbestos Removal Works

All removal methods and procedures are required to be undertaken in accordance with current legislation. The PMCW in conjunction with an Asbestos Assessor will inform the Asbestos Removalist of the Scope of Work. The Asbestos Assessor will be required to provide a clearance certificate on satisfactory completion of the works.

7.4 Work in Areas Containing Asbestos – Trades Personnel

Prior to commencement of works the following undertakings, procedures and awareness must be observed: Work must not proceed under any circumstance without first contacting the PMCW. Refer to this ASMP (including amendments) to determine if ACM are likely to be encountered in the general work area. If no ACM is located in the area of intended work, the area may be entered by all relevant personnel on an unrestricted basis. Work in areas where ACM will, or is likely to be disturbed will only be given to ACT licensed Asbestos Removalists and all access and works will be in accordance with current legislation.

7.5 Emergency Work in Areas Containing Asbestos

If emergency work is required, contact the PMCW. If the PMCW determines that asbestos is likely to be encountered a licensed Asbestos Removalists must undertake any asbestos removal or remediation works.

Page 47: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 37 of 61

Telephone WorkSafe ACT for emergency approval of asbestos work. Advise WorkSafe ACT in writing within 24 hours.

A licensed Asbestos Assessor will be required to provide a clearance certificate on satisfactory completion of the works.

7.6 Monitoring Arrangements

To ensure control measures are effective, air monitoring should be performed whenever friable ACM is being removed from buildings. A Risk Assessment may also require that air monitoring is undertaken during or at the completion of the removal of non friable ACM.

All air monitoring must be performed by a competent person accredited to perform air sampling for asbestos. Sampling should be performed in accordance with the ‘Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres [NOHSC: 3003 (2005)].

It is the Asbestos Removalist’s responsibility to ensure that the maximum fibre levels throughout asbestos removal and associated works do not equal or exceed the minimum practical detection limit of 0.01 fibres per millilitre of air (f/mL). The consequences of airborne fibre levels observed at or exceeding those specified below will result in the Asbestos Assessor instructing the contractor to take the appropriate ‘Control /Action’ as listed below.

Control Level

(airborne asbestos fibres/mL) Control / Action

< 0.01 Continue with control measures

0.01 Review control measures

0.02 Stop removal work and find the cause

7.7 Clearance Inspections Prior To Re-Occupation

Following removal work, a clearance inspection must be undertaken prior to re-occupation of an asbestos work area. This shall be conducted by a licensed Asbestos Assessor.

All barriers and warning signs should remain in place until the area has been cleared.

7.8 ACM removal/maintenance record

The Asbestos Register, Section 4.2, Table 3A, is to be completed by the PMCW after receiving appropriate clearance certification from a licensed Asbestos Assessor.

The ‘Work Performed’ and ‘Asbestos Control Measure’ Tables on the following page are required to be completed by the PMCW.

Page 48: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 38 of 61

1. Work Performed

Company name Contact details Date of work + job no. Scope of work

2. Asbestos Control Measures

Work performed Air monitoring/ decontamination

Clearance certificate issued Other

Page 49: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 39 of 61

3 Additional Information

Page 50: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 40 of 61

8 UPDATING THE ASMP Where an ACM has been disturbed, removed, enclosed, encapsulated, sealed or its condition has deteriorated, the existing asbestos risk assessment will no longer be valid and the ASMP will need to be revised by a licensed Asbestos Assessor to reflect these changes.

The reviews should critically assess all asbestos management procedures and their effectiveness in:

preventing exposure to asbestos fibres controlling access to asbestos highlighting the need for action to maintain or remove ACM maintaining the accuracy of the ASMP details of any mitigating factors must be recorded in 2.4 Asbestos Register – Table 3A

Page 51: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 41 of 61

9 APPENDICES

9.1 APPENDIX A – Laboratory Results

Page 52: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 42 of 61

Page 53: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 43 of 61

Page 54: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 44 of 61

Page 55: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 45 of 61

9.2 APPENDIX B – Plans

Page 56: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 46 of 61

Page 57: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 47 of 61

Page 58: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 48 of 61

Page 59: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 49 of 61

RE = Referred to another sample as being the same material T = Telecommunication/ In ground services pit

Page 60: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 50 of 61

9.3 APPENDIX C – ACM Item Locations & Representative Photographs

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

B1478

Exterior island opposite tennis courts adjacent main road - In

ground services pit (T18)

Moulded Sheet

RA B1478

Exterior island opposite tennis courts adjacent main road - In

ground services pit (T17)

Moulded Sheet

Page 61: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 51 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

RA B1478

Exterior adjacent main road - In

ground services pit (T15)

Moulded Sheet

RA B1478

Exterior adjacent main road - In

ground services pit (T16)

Moulded Sheet

C1475

Exterior adjacent west boundary fence to lower houses - sheet

Sheet debris (Non-Friable)

Page 62: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 52 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1476

Exterior builders waste dump - north corner of lower houses -

sheet fragments

Sheet debris (Non-Friable)

C1478

Exterior builders waste adjacent

abandoned driveway off main

road - sheet fragments

Sheet debris (Non-Friable)

C1479 Exterior south of

work depot - sheet fragments

Sheet debris (Non-Friable)

Page 63: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 53 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1480

Exterior adjacent track on the north

side of work depot - sheet

fragments

Sheet debris (Non-Friable)

C1481

Exterior south side of main road

- compressed sheet

Pipe (Non-Friable)

C1482

Exterior west side of house near

bushland - sheet fragments

Sheet debris (Non-Friable)

Page 64: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 54 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1483

Exterior west end of Stromlo

Observatory complex - sheet

fragments

Sheet debris (Non-Friable)

C1484

Exterior below gully at the west

end of the Stromlo

Observatory complex - sheet

fragments

Sheet debris (Non-Friable)

C1485

Exterior south west of main

Stromlo complex - sheet fragments

Sheet debris (Non-Friable)

Page 65: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 55 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1486 Exterior adjacent main road - sheet

fragments

Sheet debris (Non-Friable)

RA C1486

Exterior south of C1486 in house footprint - sheet

fragments

Sheet debris (Non-Friable)

RA C1486

Exterior south west corner of house - sheet

fragments

Sheet debris (Non-Friable)

Page 66: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 56 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1487

Exterior west of student

accommodation - sheet fragments

Sheet debris (Non-Friable)

RA C1487 Exterior adjacent soil dump - sheet

fragments

Sheet debris (Non-Friable)

C1488

Exterior north of the green work

shed - sheet fragments

Sheet debris (Non-Friable)

Page 67: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 57 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1489 Exterior east of

telescope dome - sheet fragments

Sheet debris (Non-Friable)

RA C1489 Exterior east of

telescope dome - sheet fragments

Sheet debris (Non-Friable)

C1490

Exterior down slope of

telescope - sheet fragments

Sheet debris (Non-Friable)

Page 68: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 58 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1491 Exterior west

bank north end - sheet fragments

Sheet debris (Non-Friable)

RA C1491 Exterior west

bank north end - sheet fragments

Sheet debris (Non-Friable)

Page 69: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 59 of 61

Mount Stromlo Observatory

SAMPLE NO LOCATIONS ACM TYPE PHOTOGRAPH

C1493 Exterior north of top telescopes - sheet fragments

Sheet debris (Non-Friable)

RA = Referred to another sample as being the same material

Page 70: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 60 of 61

9.4 APPENDIX D – Glossary

Air monitoring1 Air Monitoring means airborne asbestos fibre sampling to assist in assessing

exposures and the effectiveness of control measures. Air monitoring includes exposure monitoring, control monitoring and clearance monitoring. Note: Air monitoring should be undertaken in accordance with the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres [NOHSC: 2003 (2005)]

Airborne asbestos fibres2 Any fibres of asbestos small enough to be made airborne. For the purposes of

monitoring airborne asbestos fibres, only respirable asbestos fibres (those less than 3µm wide, more than 5µm long and with a length to width ratio of more than 3 to 1) are counted.

Amosite Grey or brown asbestos

AMP Asbestos Survey and Management Plan

AR Asbestos Register

Asbestos Containing Material (ACM)

Any material, object, product or debris that contains asbestos.

Asbestos Register Inventory of ACM by type, form, location, risk and required action.

Asbestos Removalist2 A licensed person who performs asbestos removal work. Note: licensing

requirements vary from state to state/territory. Asbestos Survey and Management Plan (ASMP)

Document covering the identification, risk assessment, control and management of identified asbestos hazards, developed in accordance with current legislation.

Asbestos2 The fibrous form of mineral silicates belonging to the serpentine and amphibole

groups of rock-forming minerals, including actinolite, amosite, anthophyllite, chrysotile, crocidolite, tremolite or any mixture containing one or more of the mineral silicates belonging to the serpentine and amphibole groups.

Asbestos–cement (AC)2 Products consisting of sand aggregate and cement reinforced with asbestos

fibres (e.g. asbestos cement pipes and flat or corrugated asbestos cement sheets).

Chrysotile White asbestos

Page 71: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_T-07266_Mount Stromlo Observatory-20190131 Page 61 of 61

Clearance inspection2 An inspection carried out by a licensed Asbestos Assessor to verify that an asbestos work area is safe to be returned to normal use after work involving the disturbance of ACM has taken place. A clearance inspection must include a visual inspection, and may also include clearance monitoring and/or settled dust sampling.

Clearance monitoring2 Air monitoring using static or positional sampling to measure the level of

airborne asbestos fibres in an area following work on ACM. An area is ‘cleared’ when the level of airborne asbestos fibres is measured as being below 0.01 fibres/mL.

Control monitoring2 Air monitoring, using static or positional sampling to measure the level of

airborne asbestos fibres in an area during work on ACM. Control monitoring is designed to assist in assessing the effectiveness of control measures. Its results are not representative of actual occupational exposures, and should not be used for that purpose.

Crocidolite Blue asbestos

Exposure monitoring Air monitoring in the breathing zone to determine a person’s likely exposure to

a hazardous substance. Exposure monitoring is designed to reliably estimate the person’s exposure, so that it may be compared with the National Exposure Standard.

Friable asbestos2 Asbestos containing material which when dry is or may become crumbled,

pulverised or reduced to powder by hand pressure. In situ2 Fixed or installed in its original position, not having been removed.

Inaccessible areas Areas which are difficult to access without causing damage to the premises,

such as wall cavities and the interiors of plant and equipment, or areas which cannot be safely accessed.

Licensed Asbestos Assessor Person who is licensed to undertake the sampling and risk assessment of

asbestos and provide recommendations on its safe management.

Membrane A flexible or semi-flexible material, which functions as the waterproofing

component in a roofing or waterproofing assembly. NATA National Association of Testing Authorities

Non friable asbestos ACM that is bound into a stable matrix and cannot be reduced to a dust by

hand pressure. Previously known as Bonded asbestos

PMCW Person with control or management of a workplace

SWMS Safe Work Method Statement

Page 72: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

5. Future Inspection Reports and Certificates

Page 73: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Robson Environmental Pty Ltd ~ ABN: 55 008 660 900 ~ www.robsonenviro.com.au p: 02 6239 5656 ~ f: 02 6239 5669 ~ e: [email protected] PO Box 112 Fyshwick ACT 2609 ~ 140 Gladstone Street Fyshwick ACT 2609

H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509

Lead Paint Assessment

Client: Australian National University

Job Number: H2410

Survey Date: 15/04/2019

Certificate of Approval for Issue of Documents

Document Name HMR319 – Lead Paint Assessment – Swab and Laboratory Analysis

Report Issue Date 09/05/2019 Job Number H2410

Client Australian National University

Client Representative Brett Morrison

Sample Testing and Report Preparation

Reviewed Approved

Jordan Curbishley Hazardous Materials Consultant Robson Environmental Pty. Ltd.

Jordan Curbishley Hazardous Materials Consultant Robson Environmental Pty. Ltd.

Anne Robson Director Robson Environmental Pty Ltd

Copyright & Intellectual Property Statement

1. Robson owns (and will continue to own) all Intellectual Property Rights (including copyright) in this Report. 2. The person commissioning this Report (the Client) is entitled to retain possession of the Report upon payment of all sums owing to

Robson in full or upon Robson agreeing to release the Report (in their absolute discretion and upon terms they think fit). 3. The Client must only use the Report for the purpose for which it was commissioned. 4. The Client may photocopy or reproduce all or any part of the Report provided that reproduction is to fulfil the purpose for which

the Report was commissioned. 5. The Client must not otherwise publish the Report (or any advice given by Robson) to the public or any third parties without

Robson’s prior written consent. Robson will not unreasonably withhold consent but may take into account the reasons for which the Report (or advice) was commissioned and the consequences of the disclosure or potential reliance that will be placed on the Report by third parties.

6. The Client agrees that no party (other than the Client) can rely upon the Report or any advice given by Robson. 7. The Client indemnifies Robson against any costs, losses or damage suffered or incurred (including legal costs on a solicitor and own

client basis) arising out of or as a consequence of the Client’s breach of these provisions. 8. This report is solely for the use of the client and may not contain sufficient information for purposes of other parties, or for other

uses. Any reliance on this report by third parties shall be at such party’s own risk. 9. This report shall only be presented in full and may not be used to support any other objective than those set out in the report,

except where written approval with comments are provided by Robson Environmental Pty Ltd.

Page 74: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 2 of 31

1 Introduction

Lead (Pb) paint is defined by the Australian Standard AS 4361.2 – 2017 (Guide to hazardous paint management Part 2: Lead paint in residential, public and commercial buildings) as a paint or component coat of a paint system containing lead or lead compounds, in which the lead content (calculated as lead metal) is in excess of 0.1% by weight of the dry film as determined by laboratory testing.

Analytical values of ≤ 0.1% Pb allow the sample to be categorised as being lead free paint.

It should be noted that this Standard relates only to the removal of lead paint. In the ACT and NSW, building waste which is painted with lead paint may be disposed of as general demolition waste regardless of the quantity or percentage of lead paint.

Lead in paint (as lead carbonate) is found extensively in homes and commercial and industrial buildings built pre-1970. Although Australian industry has generally phased out lead in paint, levels of below 1 percent are still permitted and industrial application of high-lead paint to residential/commercial dwellings may still continue (Standards Australia, 2017).

Lead-based paint may be a health issue if it becomes mobile in the environment or if ingested. For this reason, sealing or safe removal of paint is strongly recommended, particularly where it is flaking or exposed to the elements.

2 Survey Methodology

Robson Environmental Pty Ltd conducted an assessment for lead-based paint for the Australian National University at Mount Stromlo Observatory on 15/04/2019. The assessment was targeted to the General Site and included information from a previous site visit on 07/02/2019.

The paint samples were qualitatively tested using 3M™ LeadCheck™ Swabs. These are USA EPA-recognised for the determination of lead-based paint with a 600ppm lower detection limit. This is equivalent to 0.06% and is therefore appropriate for the categorisation of tested surfaces as being lead free paint.

If the 3M™ LeadCheck™ Swabs detected the presence of lead, the paint sample was categorically deemed to be lead paint regardless of the number of lead and/or non-lead paint layers present within the sample tested. At the client’s request, additional samples of the paints tested with the 3M™ LeadCheck™ Swabs were not sent for further laboratory analysis to determine the exact percentage of lead present in the paint for all but one of the paint systems.

One sample was sent for quantitative analysis for lead concentration following the method stated in Appendix A of AS/NZS 4361.2. The sample was individually sealed and double bagged, and couriered under Chain of Custody (COC) documentation to Envirolab in Sydney NSW.

Page 75: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 3 of 31

During the lead paint survey, the following criteria were considered by a Licensed Asbestos Assessor

(or competent person) when assessing the risk associated with lead paint systems. This qualitative

assessment determines the Risk Rating. These are shown in Table 1.

Location of the lead paint system

Surface area of the lead paint system

Condition of the lead paint system

Accessibility of the lead paint system

Likelihood of ingesting and/or inhaling lead paint particles

Table 1: Risk Rating Levels and Action Plan

Risk Rating Level Action Plan

High

(H)

Lead is present in paint that is in very poor condition (i.e. bad cracking, flaking, chalking and peeling observed). It covers a large surface area and/or is on a surface that is easily accessible to children.

It may present a health hazard with minor disturbance.

Action should be taken immediately to reduce exposure risk.

Medium

(M)

Lead is present in paint that is in average condition (i.e. some cracking, flaking, chalking and peeling observed). It covers a small surface area and/or is on a surface that is not easily accessible to children.

It may present a health hazard with moderate disturbance.

Action should be taken as soon as practicable to reduce exposure risk.

Low

(L)

Lead is present in paint that is still in good condition (i.e. no cracking, flaking, chalking or peeling observed) and is not a friction or impact surface.

It is not likely to present a health hazard unless significantly disturbed.

Ongoing actions to maintain the lead paint system in good condition and to check it periodically to ensure a low exposure risk.

Nil

(N)

Lead was not detected in paint system being assessed.

No action required.

Page 76: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 4 of 31

3 Results and Recommendations

The quantitative laboratory results analysed from the sample collected on 07 February 2019 show that one lead paint system contained lead concentrations in excess of the 0.1% by weight threshold. These paints are required to be managed as lead paint so risk can be minimised. Please note that AS/NZS 4361.2 states that if ‘one or more tests from a building or portion of a building indicate that lead is present, the paint should be treated as lead paint’.

The qualitative swab results collected on 15 March 2019 show that four lead paint systems contain lead concentrations in excess of the 0.1% by weight threshold. These paints are required to be managed as lead paint so risk can be minimised. Please note that AS/NZS 4361.2 states that if ‘one or more tests from a building or portion of a building indicate that lead is present, the paint should be treated as lead paint’.

The results also show that one lead paint system may be considered lead-free because no lead was detected in the paint samples as tested with the 3M™ LeadCheck™ Swabs. This shows that the concentration is below the definition for lead paint and the paint system poses no risk.

Table 1 presents lead composition in paints, with results shown as a ‘yes’ or ‘no’ for the presence of lead within the paint samples tested as well as the exact percentage of lead determined through laboratory analysis. Recommendations suitable for the relevant lead paint system risk rating are also explained here. Photographs of samples are included in Appendix 1, the full laboratory report is in Appendix 2 and the plans are in Appendix 3.

Page 77: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 5 of 31

Table 1: Lead Composition in Paint by Qualitative and Quantitative Testing

Sample ID Sample Location Paint

Colour

Classified

as Lead

Paint?

Percentage

of Lead

(%w/w)

Risk

Rating Recommendations

C1494

Mount Stromlo Observatory – Paint sample

from FHB01

Road adjacent Oddie Telescope

Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Refer to

C1494

Mount Stromlo Observatory – FHB02

Road adjacent Visitors Centre Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Page 78: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 6 of 31

Refer to

C1494

Mount Stromlo Observatory –FHB03

Road between Visitors Centre and Directors

Residence

Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Refer to

C1494

Mount Stromlo Observatory –FHB04

Road adjacent Melbourne 50” Telescope Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Page 79: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 7 of 31

Refer to

C1494

Mount Stromlo Observatory –FHB05

Road adjacent Commonwealth Solar

Observatory Building

Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Refer to

C1494

Mount Stromlo Observatory – FHB06 (x2)

Burnt out house near Faulkner Court Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

As the two fire hydrant boxes are

redundant it is recommended that they

be removed.

Page 80: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 8 of 31

Refer to

C1494

Mount Stromlo Observatory – FHB07

Road adjacent houses Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Refer to

C1494

Mount Stromlo Observatory – FHB08

Road adjacent shipping containers Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Page 81: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 9 of 31

Refer to

C1494

Mount Stromlo Observatory – FHB09

Road adjacent House 8 Red Yes 4.2% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the fire hydrant box during

the inspection. It is recommended that

the paint system be encapsulated with

paint and maintained in good condition.

Pb01

Mount Stromlo Observatory – paint to fire

hydrants

Throughout site

Orange Yes >0.06% L

Ongoing preventative action should be planned.

This includes:

Maintain the lead paint system in good

condition.

Check it periodically to ensure a low

exposure risk (i.e. no cracking, flaking,

chalking or peeling observed and that it

is not a friction or impact surface).

Review and update the risk rating

appropriately.

Page 82: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 10 of 31

Pb02

Mount Stromlo Observatory – paint to fire

extinguisher box

Road adjacent Melbourne 50” Telescope

Orange Yes >0.06% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the extinguisher during the

inspection. It is recommended that the

paint system be encapsulated with paint

and maintained in good condition.

Pb03

Mount Stromlo Observatory – paint to No

Smoking sign

Road adjacent Melbourne 50” Telescope

Red/White Yes >0.06% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the sign during the

inspection. It is recommended that the

paint system be encapsulated with paint

and maintained in good condition.

Page 83: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 11 of 31

Pb04

Mount Stromlo Observatory – paint to

Bowser Pump

Road adjacent Melbourne 50” Telescope

White Yes >0.06% M

Action should be taken as soon as practicable to

reduce exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking condition were

observed to the Bowser Pump during the

inspection. It is recommended that the

paint system be encapsulated with paint

and maintained in good condition.

Pb05

Mount Stromlo Observatory – paint to

concrete blocks

Old Seismic Station

White No <0.06% N No action required.

Page 84: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 12 of 31

4 Remediating Surfaces Containing Lead Paint

The main exposure risk associated with lead paint is when it becomes an airborne dust or fume.

When paint deteriorates through chipping, cracking, bubbling and flaking, it is not becoming an

airborne dust and cannot be easily inhaled.

The key to safely remediating surfaces containing lead paint is to prevent the generation of dust and

fume. As a result, sanding, buffing, grinding, burning and wet/dry abrasive blasting is not

appropriate. Abrasive blasting is defined as propelling a stream of abrasive material at high speed

against a surface using compressed air, liquid, steam, centrifugal wheels or paddles to clean, abrade,

etch or otherwise change the original appearance or condition of the surface.

In fact, Safe Work Australia prohibits abrasive blasting of lead materials and lead paint systems above a concentration of 0.1% by weight. Refer to https://www.safeworkaustralia.gov.au/chemicals.

To safely remediate surfaces containing lead paint, the following method is acceptable:

1. If indoors, shut all windows and doors to enclose the work area and place heavy duty plastic

sheets on the floor to ease clean up.

2. If outdoors, plan your work for a day that is not windy and when rain is not predicted. Cover

the ground below the painted surface with heavy duty plastic sheeting. For example, strips

that are two metres wide would be suitable for the external wall of a house.

3. Workers are to:

a. Be clean shaven.

b. Wear appropriate respiratory protection. A minimum of P1 is essential but P2

respirators (i.e. disposable masks) are preferred.

c. Wear gloves.

d. Wear a hat to prevent lead paint chips from getting stuck in hair and being

accidentally removed from the area.

e. Wear disposable coveralls to prevent lead paint chips from getting into pockets,

stuck to sweaty skin or getting inside work shirts, etc. and being accidentally

removed from the area. Note: Workers need to be aware of and prevent heat-

related illness, maintain good hydration, take rest breaks in the shade, have cool

drinking water available and avoid working during the hottest parts of the day if

wearing disposable coveralls.

f. Wash hands and face before eating, drinking and smoking to prevent hand-to-month

cross contamination.

4. Manually scrape all loose paint off the surface so the flakes fall on the plastic sheets. Note:

no grinding, buffing, sanding, abrasive blasting, burning, etc.

5. When complete, fold up the plastic sheets to collect all the paint scrapings and dispose of

them appropriately.

6. The surface can be repainted to bind the remaining lead paint to the structure. Several coats

may be required to adhere all old paint to the structure again.

7. Next, the paint flakes that are already on the ground can be addressed:

a. Regarding sealed surfaces, such as concrete, bitumen, timber or tiles:

i. Paint chips can be vacuumed up.

Page 85: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 13 of 31

ii. The vacuum bag contents should then be carefully transferred to a heavy

duty plastic bag to prevent dust from being released. Note: do not overfill

the bags as they will become a manual handling risk and could tear open

under the weight.

iii. Dispose of the waste appropriately.

b. Regarding unsealed surfaces, such as dirt, rocks or grass:

i. Wet the ground around the surface with a fine mist (not a heavy spray) or a

diluted PVA glue solution to prevent dust from being generated in the next

steps.

ii. Use a shovel to manually scrape approximately 10mm to 15mm of loose dirt

and rocks from the top surface of the ground and collect it in heavy duty

plastic bags. Note: do not overfill the bags as they will become a manual

handling risk and could tear open under the weight.

iii. Dispose of the waste appropriately.

8. Continue to inspect the condition of the paint every 5 years to assess whether further

deterioration has occurred.

9. Repeat this process whenever the paint system deteriorates to a point where remediation is

required.

10. In the event that a structure containing a lead paint system is nominated for demolition:

a. Refer to the additional recommendations shown in the next section of this report.

b. Plastic sheets are unnecessary as they will get easily ripped up and damaged.

c. Workers need to be clean shaven and wear respiratory protection, gloves and

exercise proper personal hygiene during the period they are handling lead painted

materials.

d. Personal Protective Equipment (PPE) requirements can be reassessed once all the

components containing a lead paint system are gone and only non-lead paint

systems remain.

e. After the entire structure is gone, the ground will need to be scraped back to collect

all residual paint flakes as described above.

Page 86: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 14 of 31

5 Additional Recommendations for the Demolition and Disposal of

Building Waste Containing Lead Paint

In the ACT & NSW, building waste painted with lead paint is classified as general building waste and may be disposed of without removing the lead paint. As a result, it is recommended that all materials that tested positive for the presence of lead paint be disposed of as general building waste.

The mechanical demolition of structures and objects painted with lead paint do not fall under the category of a ‘lead process’ as defined by the ACT Work Health and Safety Regulations 2011 (Section 392) so the requirements of Part 7.2 in the Regulations do not apply. Refer to https://www.legislation.act.gov.au/View/sl/2011-36/current/PDF/2011-36.PDF.

Only if you are intending to remove the paint from the structures/objects so they may be reused, recycled or refurbished, should the lead paint be removed in strict accordance with the methods specified in AS/NZS 4361.1 and AS/NZS 4361.2.

Due to similarities between environmental cleaning methods for lead paint and asbestos containing materials, it is recommended that a Class B licensed Asbestos Removalists be used to remove lead paint from materials being reused, recycled or refurbished.

Please note that it is not recommended to weld, cut or clean lead painted metal structures/objects using flame (i.e. electric arc, oxy gas, oxyacetylene, plasma arc, etc.) or abrasive cutting equipment that creates heat from friction (i.e. grinders, etc.) because it will burn the paint and generate fume containing lead. This falls under the definition of a ‘lead process’ as defined by the ACT Work Health and Safety Regulations 2011 (Section 392(i)) and the requirements of Part 7.2 of the Regulations apply.

It is recommended that only mechanical cutting methods that do not burn the paint be used (i.e. demolition shears) to avoid the requirements of Section 7.2 of the Regulations. Manually unbolting the pieces can also be done but this would be fairly time-consuming and heat should not be applied to stuck nuts/bolts as it will burn the lead paint.

Page 87: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 15 of 31

6 Limitations

While Robson Environmental has taken all care to ensure that this report includes the most accurate

information available, the report and any risk assessment presented is based on the information

obtained by Robson Environmental at the time of sampling. Any variation in environment, activities,

methods, practices, products, or equipment used may change exposures to hazards, invalidating the

presented risk assessment. Robson recommends that risks be re-assessed prior to making any

changes to the aforementioned factors.

The findings contained within this report are developed from the interpretation of the results of

specific sampling methods used in accordance with generally accepted practices and standards,

based on the current state of knowledge. To the best of Robson Environmental’s knowledge, our

assessment of the data represents a reasonable interpretation of the general conditions, and

subsequent risk at the time of sampling. Should you have any questions or require further

information please contact Robson Environmental.

7 References

Buehler, S & Rhoda, D 2012, ‘3M™ LeadCheck™ Swabs qualitative spot test kit for lead in

paint’, Battelle.

https://www.epa.gov/sites/production/files/documents/3M-leadcheck-report.pdf

Standards Australia, 2017, AS/NZS4361.1-2017: Guide to hazardous paint management, Part

1: Lead and other hazardous metallic pigments in industrial applications, Standards Australia,

Australia.

Standards Australia, 2017, AS/NZS4361.2-2017: Guide to hazardous paint management, Part

2: Lead paint in residential, public and commercial buildings, Standards Australia, Australia.

Page 88: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 16 of 31

Appendix 1 – Photographs of Lead and Lead-Free Paint Systems

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

C1494

Mount Stromlo

Observatory – Paint

sample from FHB01

Road adjacent

Oddie Telescope

Red Yes

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB02

Road adjacent

Visitors Centre

Red Yes

Page 89: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 17 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB03

Road between

Visitors Centre and

Directors Residence

Red Yes

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB04

Road adjacent

Melbourne 50”

Telescope

Red Yes

Page 90: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 18 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB05

Road adjacent

Commonwealth

Solar Observatory

Building

Red Yes

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB06

(x2)

Burnt out house

near Faulkner

Court

Red Yes

Page 91: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 19 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB07

Road adjacent

houses

Red Yes

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB08

Road adjacent

shipping containers

Red Yes

Page 92: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 20 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Refer to

C1494

Mount Stromlo

Observatory – Paint

sample from FHB09

Road adjacent

House 8

Red Yes

Pb01

Mount Stromlo

Observatory – paint

to fire hydrants

Throughout site

Orange Yes

Page 93: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 21 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Pb02

Mount Stromlo

Observatory – paint

to fire extinguisher

box

Road adjacent

Melbourne 50”

Telescope

Orange Yes

Pb03

Mount Stromlo

Observatory – paint

to No Smoking sign

Road adjacent

Melbourne 50”

Telescope

Red/

White Yes

Page 94: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 22 of 31

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

Pb04

Mount Stromlo

Observatory – paint

to Bowser Pump

Road adjacent

Melbourne 50”

Telescope

White Yes

Pb05

Mount Stromlo

Observatory – paint

to concrete blocks

Old Seismic Station

White No

Page 95: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 23 of 31

Appendix 2 - Laboratory Results

Page 96: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 24 of 31

Page 97: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 25 of 31

Page 98: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 26 of 31

Page 99: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 27 of 31

Page 100: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 28 of 31

Page 101: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 29 of 31

Appendix 3 - Plans

Page 102: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 30 of 31

Page 103: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410_Mount Stromlo Observatory_General Site_Lead Paint Assessment_20190509 Page 31 of 31

Page 104: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Robson Environmental Pty Ltd ~ ABN: 55 008 660 900 ~ www.robsonenviro.com.au p: 02 6239 5656 ~ f: 02 6239 5669 ~ e: [email protected] PO Box 112 Fyshwick ACT 2609 ~ 140 Gladstone Street Fyshwick ACT 2609

H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520

Lead Paint Assessment

Client: Australian National University

Job Number: H2410

Survey Date: 15/04/2019

Certificate of Approval for Issue of Documents

Document Name HMR320 – Lead Paint Assessment –Laboratory Analysis Only

Report Issue Date 16/05/2019 Job Number H2410

Client Australian National University

Client Representative Brett Morrison

Sample Testing and Report Preparation

Reviewed Approved

Jordan Curbishley Hazardous Materials Consultant Robson Environmental Pty. Ltd.

Jordan Curbishley Hazardous Materials Consultant Robson Environmental Pty. Ltd.

Anne Robson Director Robson Environmental Pty Ltd

Copyright & Intellectual Property Statement

1. Robson owns (and will continue to own) all Intellectual Property Rights (including copyright) in this Report. 2. The person commissioning this Report (the Client) is entitled to retain possession of the Report upon payment of all sums owing to

Robson in full or upon Robson agreeing to release the Report (in their absolute discretion and upon terms they think fit). 3. The Client must only use the Report for the purpose for which it was commissioned. 4. The Client may photocopy or reproduce all or any part of the Report provided that reproduction is to fulfil the purpose for which

the Report was commissioned. 5. The Client must not otherwise publish the Report (or any advice given by Robson) to the public or any third parties without

Robson’s prior written consent. Robson will not unreasonably withhold consent but may take into account the reasons for which the Report (or advice) was commissioned and the consequences of the disclosure or potential reliance that will be placed on the Report by third parties.

6. The Client agrees that no party (other than the Client) can rely upon the Report or any advice given by Robson. 7. The Client indemnifies Robson against any costs, losses or damage suffered or incurred (including legal costs on a solicitor and own

client basis) arising out of or as a consequence of the Client’s breach of these provisions. 8. This report is solely for the use of the client and may not contain sufficient information for purposes of other parties, or for other

uses. Any reliance on this report by third parties shall be at such party’s own risk. 9. This report shall only be presented in full and may not be used to support any other objective than those set out in the report,

except where written approval with comments are provided by Robson Environmental Pty Ltd.

Page 105: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 2 of 16

1 Introduction

Lead (Pb) paint is defined by the Australian Standard AS 4361.2 – 2017 (Guide to hazardous paint management Part 2: Lead paint in residential, public and commercial buildings) as a paint or component coat of a paint system containing lead or lead compounds, in which the lead content (calculated as lead metal) is in excess of 0.1% by weight of the dry film as determined by laboratory testing.

Analytical values of ≤ 0.1% Pb allow the sample to be categorised as being lead free paint.

It should be noted that this Standard relates only to the removal of lead paint. In the ACT and NSW, building waste which is painted with lead paint may be disposed of as general demolition waste regardless of the quantity or percentage of lead paint.

Lead in paint (as lead carbonate) is found extensively in homes and commercial and industrial buildings built pre-1970. Although Australian industry has generally phased out lead in paint, levels of below 1 percent are still permitted and industrial application of high-lead paint to residential/commercial dwellings may still continue (Standards Australia, 2017).

Lead-based paint may be a health issue if it becomes mobile in the environment or if ingested. For this reason, sealing or safe removal of paint is strongly recommended, particularly where it is flaking or exposed to the elements.

2 Survey Methodology

Robson Environmental Pty Ltd conducted an assessment for lead-based paint for the Australian National University at the Mount Stromlo Observatory Oddie Telescope on 15/04/2019.

At the client’s request, paint samples were not qualitatively tested using 3M™ LeadCheck™ Swabs because identifying the exact percentage of lead present in the paint was requested. Qualitative testing can only give a ‘yes’ or ‘no’ for the presence of lead.

A paint sample of the relevant paint system was collected. The sample was sent for quantitative

analysis for lead concentration following the method stated in Appendix A of AS/NZS 4361.2.

All samples were individually sealed and double bagged, and couriered under Chain of Custody (COC) documentation to Envirolab in Sydney NSW.

Page 106: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 3 of 16

During the lead paint survey, the following criteria were considered by a Licensed Asbestos Assessor (or competent person) when assessing the risk associated with lead paint systems. This qualitative assessment determines the Risk Rating. These are shown in Table 1.

Location of the lead paint system

Surface area of the lead paint system

Condition of the lead paint system

Accessibility of the lead paint system

Likelihood of ingesting and/or inhaling lead paint particles

Table 1: Risk Rating Levels and Action Plan

Risk Rating Level Action Plan

High

(H)

Lead is present in paint that is in very poor condition (i.e. bad cracking, flaking, chalking and peeling observed). It covers a large surface area and/or is on a surface that is easily accessible to children.

It may present a health hazard with minor disturbance.

Action should be taken immediately to reduce exposure risk.

Medium

(M)

Lead is present in paint that is in average condition (i.e. some cracking, flaking, chalking and peeling observed). It covers a small surface area and/or is on a surface that is not easily accessible to children.

It may present a health hazard with moderate disturbance.

Action should be taken as soon as practicable to reduce exposure risk.

Low

(L)

Lead is present in paint that is still in good condition (i.e. no cracking, flaking, chalking or peeling observed) and is not a friction or impact surface.

It is not likely to present a health hazard unless significantly disturbed.

Ongoing actions to maintain the lead paint system in good condition and to check it periodically to ensure a low exposure risk.

Nil

(N)

Lead was not detected in paint system being assessed.

No action required.

Page 107: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 4 of 16

3 Results and Recommendations

The quantitative laboratory results analysed from the sample collected on 15 April 2019 show that one lead paint system contains lead concentrations in excess of the 0.1% by weight threshold. This paint is required to be managed as lead paint so risk can be minimised. Please note that AS/NZS 4361.2 states that if ‘one or more tests from a building or portion of a building indicate that lead is present, the paint should be treated as lead paint’.

Table 1 presents lead composition in paints, with results shown as the exact percentage of lead determined through laboratory analysis. Recommendations suitable for the relevant lead paint system risk rating are also explained here. Photographs of samples are included in Appendix 1 and the full laboratory report is in Appendix 2.

Page 108: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 5 of 16

Table 1: Lead Composition in Paint by Quantitative Testing

Sample ID Sample Location Paint

Colour

Classified

as Lead

Paint?

Percentage

of Lead

(%w/w)

Risk

Rating Recommendations

C1523 Mount Stromlo Observatory – paint sample

from Oddie Telescope White Yes 9.2% H

Action should be taken immediately to reduce

exposure risk. This includes:

Remediate using method detailed in this

report.

Areas of poor and flaking paint were

observed to the exterior of the Oddie

Telescope during the site inspection.

Paint chips were also observed to the

ground surrounding the telescope.

The paint to the exterior of the telescope

needs to be remediated.

The soil adjacent the telescope needs to

be remediated as part of remediation

works to the telescope.

Page 109: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 6 of 16

4 Remediating Surfaces Containing Lead Paint

The main exposure risk associated with lead paint is when it becomes an airborne dust or fume.

When paint deteriorates through chipping, cracking, bubbling and flaking, it is not becoming an

airborne dust and cannot be easily inhaled.

The key to safely remediating surfaces containing lead paint is to prevent the generation of dust and

fume. As a result, sanding, buffing, grinding, burning and wet/dry abrasive blasting is not

appropriate. Abrasive blasting is defined as propelling a stream of abrasive material at high speed

against a surface using compressed air, liquid, steam, centrifugal wheels or paddles to clean, abrade,

etch or otherwise change the original appearance or condition of the surface.

In fact, Safe Work Australia prohibits abrasive blasting of lead materials and lead paint systems above a concentration of 0.1% by weight. Refer to https://www.safeworkaustralia.gov.au/chemicals.

To safely remediate surfaces containing lead paint, the following method is acceptable:

1. If indoors, shut all windows and doors to enclose the work area and place heavy duty plastic

sheets on the floor to ease clean up.

2. If outdoors, plan your work for a day that is not windy and when rain is not predicted. Cover

the ground below the painted surface with heavy duty plastic sheeting. For example, strips

that are two metres wide would be suitable for the external wall of a house.

3. Workers are to:

a. Be clean shaven.

b. Wear appropriate respiratory protection. A minimum of P1 is essential but P2

respirators (i.e. disposable masks) are preferred.

c. Wear gloves.

d. Wear a hat to prevent lead paint chips from getting stuck in hair and being

accidentally removed from the area.

e. Wear disposable coveralls to prevent lead paint chips from getting into pockets,

stuck to sweaty skin or getting inside work shirts, etc. and being accidentally

removed from the area. Note: Workers need to be aware of and prevent heat-

related illness, maintain good hydration, take rest breaks in the shade, have cool

drinking water available and avoid working during the hottest parts of the day if

wearing disposable coveralls.

f. Wash hands and face before eating, drinking and smoking to prevent hand-to-month

cross contamination.

4. Manually scrape all loose paint off the surface so the flakes fall on the plastic sheets. Note:

no grinding, buffing, sanding, abrasive blasting, burning, etc.

5. When complete, fold up the plastic sheets to collect all the paint scrapings and dispose of

them appropriately.

6. The surface can be repainted to bind the remaining lead paint to the structure. Several coats

may be required to adhere all old paint to the structure again.

7. Next, the paint flakes that are already on the ground can be addressed:

a. Regarding sealed surfaces, such as concrete, bitumen, timber or tiles:

i. Paint chips can be vacuumed up.

Page 110: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 7 of 16

ii. The vacuum bag contents should then be carefully transferred to a heavy

duty plastic bag to prevent dust from being released. Note: do not overfill

the bags as they will become a manual handling risk and could tear open

under the weight.

iii. Dispose of the waste appropriately.

b. Regarding unsealed surfaces, such as dirt, rocks or grass:

i. Wet the ground around the surface with a fine mist (not a heavy spray) or a

diluted PVA glue solution to prevent dust from being generated in the next

steps.

ii. Use a shovel to manually scrape approximately 10mm to 15mm of loose dirt

and rocks from the top surface of the ground and collect it in heavy duty

plastic bags. Note: do not overfill the bags as they will become a manual

handling risk and could tear open under the weight.

iii. Dispose of the waste appropriately.

8. Continue to inspect the condition of the paint every 5 years to assess whether further

deterioration has occurred.

9. Repeat this process whenever the paint system deteriorates to a point where remediation is

required.

10. In the event that a structure containing a lead paint system is nominated for demolition:

a. Refer to the additional recommendations shown in the next section of this report.

b. Plastic sheets are unnecessary as they will get easily ripped up and damaged.

c. Workers need to be clean shaven and wear respiratory protection, gloves and

exercise proper personal hygiene during the period they are handling lead painted

materials.

d. Personal Protective Equipment (PPE) requirements can be reassessed once all the

components containing a lead paint system are gone and only non-lead paint

systems remain.

e. After the entire structure is gone, the ground will need to be scraped back to collect

all residual paint flakes as described above.

Page 111: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 8 of 16

5 Additional Recommendations for the Demolition and Disposal of

Building Waste Containing Lead Paint

In the ACT & NSW, building waste painted with lead paint is classified as general building waste and may be disposed of without removing the lead paint. As a result, it is recommended that all materials that tested positive for the presence of lead paint be disposed of as general building waste.

The mechanical demolition of structures and objects painted with lead paint do not fall under the category of a ‘lead process’ as defined by the ACT Work Health and Safety Regulations 2011 (Section 392) so the requirements of Part 7.2 in the Regulations do not apply. Refer to https://www.legislation.act.gov.au/View/sl/2011-36/current/PDF/2011-36.PDF.

Only if you are intending to remove the paint from the structures/objects so they may be reused, recycled or refurbished, should the lead paint be removed in strict accordance with the methods specified in AS/NZS 4361.1 and AS/NZS 4361.2.

Due to similarities between environmental cleaning methods for lead paint and asbestos containing materials, it is recommended that a Class B licensed Asbestos Removalists be used to remove lead paint from materials being reused, recycled or refurbished.

Please note that it is not recommended to weld, cut or clean lead painted metal structures/objects using flame (i.e. electric arc, oxy gas, oxyacetylene, plasma arc, etc.) or abrasive cutting equipment that creates heat from friction (i.e. grinders, etc.) because it will burn the paint and generate fume containing lead. This falls under the definition of a ‘lead process’ as defined by the ACT Work Health and Safety Regulations 2011 (Section 392(i)) and the requirements of Part 7.2 of the Regulations apply.

It is recommended that only mechanical cutting methods that do not burn the paint be used (i.e. demolition shears) to avoid the requirements of Section 7.2 of the Regulations. Manually unbolting the pieces can also be done but this would be fairly time-consuming and heat should not be applied to stuck nuts/bolts as it will burn the lead paint.

Page 112: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 9 of 16

6 Limitations

While Robson Environmental has taken all care to ensure that this report includes the most accurate

information available, the report and any risk assessment presented is based on the information

obtained by Robson Environmental at the time of sampling. Any variation in environment, activities,

methods, practices, products, or equipment used may change exposures to hazards, invalidating the

presented risk assessment. Robson recommends that risks be re-assessed prior to making any

changes to the aforementioned factors.

The findings contained within this report are developed from the interpretation of the results of

specific sampling methods used in accordance with generally accepted practices and standards,

based on the current state of knowledge. To the best of Robson Environmental’s knowledge, our

assessment of the data represents a reasonable interpretation of the general conditions, and

subsequent risk at the time of sampling. Should you have any questions or require further

information please contact Robson Environmental.

7 References

Buehler, S & Rhoda, D 2012, ‘3M™ LeadCheck™ Swabs qualitative spot test kit for lead in

paint’, Battelle.

https://www.epa.gov/sites/production/files/documents/3M-leadcheck-report.pdf

Standards Australia, 2017, AS/NZS4361.1-2017: Guide to hazardous paint management, Part

1: Lead and other hazardous metallic pigments in industrial applications, Standards Australia,

Australia.

Standards Australia, 2017, AS/NZS4361.2-2017: Guide to hazardous paint management, Part

2: Lead paint in residential, public and commercial buildings, Standards Australia, Australia.

Page 113: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 10 of 16

Appendix 1 – Photographs of Lead and Lead-Free Paint Systems

Sample ID

Sample Location Paint

Colour

Classified

as Lead

Paint?

Photograph(s)

C1523

Mount Stromlo

Observatory – paint

sample from Oddie

Telescope

White Yes

C1523

Mount Stromlo

Observatory – paint

sample from Oddie

Telescope

White Yes

Page 114: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 11 of 16

Appendix 2 - Laboratory Results

Page 115: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 12 of 16

Page 116: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 13 of 16

Page 117: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 14 of 16

Page 118: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 15 of 16

Page 119: Mount Stromlo Campus Building M908 Hazardous Materials …Roads and Bike Trails Only Robson Environmental 04/04/2019 ... Exterior north of the green work shed - sheet fragments. 1

Client: ANU H2410 ANU Mt Stromlo Oddie Telescope Lead Paint Assessment 20190520 Page 16 of 16