MONTHLY STATUS REPORT – June 2011LOS ALAMITOS UNIFIED SCHOOL DISTRICTLOS ALAMITOS UNIFIED SCHOOL DISTRICT
McAuliffe Middle School Modernization Projectj
June 28, 2011,Los Alamitos, California
PHASE 4- ACTIVITY SUMMARYPHASE 4- ACTIVITY SUMMARYFinish work ongoing throughout Classroom Building ‘J’ and for Rooms 60, and 61 at Multi-Use Building ‘E’
PHASE 5- ACTIVITY SUMMARYComplete move into storage complete for Multi-Purpose Building F, Media Center Building ‘H’ and for After School programs in Portable Classrooms.Abatement of Building ‘F’ Multi-Purpose.Kitchen portion of Building ‘F’ concrete floor completeKitchen portion of Building ‘F’ concrete floor complete.Rough framing, mechanical, plumbing and electrical installation in the Kitchen portion of Building ‘F’
�ON TIME AND ON BUDGET
ongoing.Building ‘F’ new Kitchen grease interceptor complete.Building ‘H’ Media Center demolition complete�ON TIME AND ON BUDGETBuilding H Media Center demolition complete.
SUMMARY OF PROGRESS
Exterior – SiteCrane Lift – Crane Removal of HVAC Units for Demolition and Installation of New Units.
SUMMARY OF PROGRESS
Interior – Building ‘F’ KitchengDry Storage Area Prepped for New Concrete. Main Kitchen Concrete Complete.
SCHEDULEPhase 4 – Classroom Building ‘J’ and Multi-UsePhase 4 – Classroom Building J and Multi-Use Building ‘E’• Complete Architectural Finishes.• Complete Telecommunications Installation• Complete Demolition and Begin New Work for
Classroom 62 (Formerly Temporary Kitchen)Classroom 62 (Formerly Temporary Kitchen)Phase 5 – Building ‘F’ Kitchen, Multi-Purpose, Classrooms• Complete Demolition (Multi-Purpose and
Classrooms)• Continue Rough Mechanical Electrical andContinue Rough Mechanical, Electrical and
Plumbing• Begin Architectural Finishes.• Continue with Kitchen Equipment Fabrication.
Phase 5 – Building ‘H’ Media Center• Complete Demolition and Abatement