Monthly Status Report #07 December 2019
jpost
Image
jpost
Text Box
Projects: Southwest Licking Local Schools Site Improvements Package New 4-5 Elementary School New High School
Page 2: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

1 | P a g e

Progress Report No. 07

For the Period Ending December 19th, 2019

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Kandee Engle Southwest Licking Local Schools

Debra Moore Southwest Licking Local Schools

Catherine Spindler Southwest Licking Local Schools

John Vincent Southwest Licking Local Schools

Roger Zeune Southwest Licking Local Schools

Robert Jennell Southwest Licking Local Schools

Richard Jones Southwest Licking Local Schools

Nathan Jones Ohio Facilities Construction Commission

Eric Baltzell Garmann-Miller Architects Engineers

Curt South Garmann-Miller Architects Engineers

Brian Wolf Garmann-Miller Architects Engineers

Julie Taggart Hill International

Michael Maxwell Hill International

Construction Manager:

Robertson Construction Services, Inc.

1801 Thornwood Drive

Heath, Ohio 43056

Architects:

Garmann-Miller Architects Engineers

38 South Lincoln Drive

P.O. Box 71

Minster, Ohio 45865

Owner’s Agent:

Hill International, Inc.

2 Easton Oval #110

Columbus, Ohio 43219

Page 3: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

2 | P a g e

Table of Contents

PROJECT CONTACTS .............................................................................................................. 3

PROJECT FLOOR PLANS ........................................................................................................ 4

New 4-5 Elementary School ................................................................................................... 4

New 9-12 High School ............................................................................................................ 5

EXECUTIVE SUMMARY ........................................................................................................... 6

PROJECT BUDGETS ................................................................................................................ 7

Owner Contingency ................................................................................................................ 7

CMR Contingency .................................................................................................................. 8

PROJECT SCHEDULE .............................................................................................................. 9

Site Improvements Package ................................................................................................... 9

New 4-5 Elementary School ..................................................................................................10

New High School ...................................................................................................................11

PROJECT DOCUMENTATION .................................................................................................12

Site Improvements Package ..................................................................................................12

New 4-5 Elementary School ..................................................................................................13

New High School ...................................................................................................................14

QUALITY CONTROL ................................................................................................................15

New 4-5 Elementary School, Site Improvements Package, and New High School ................15

SAFETY ....................................................................................................................................18

New 4-5 Elementary School ..................................................................................................18

Site Improvements and New High School ................................................................................19

PROGRESS PHOTOS ..............................................................................................................20

New 4-5 Elementary School ..................................................................................................20

New 9-12 High School ...........................................................................................................21

Drone Footage ......................................................................................................................22

Page 4: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

3 | P a g e

PROJECT CONTACTS

All Projects

Eric Baltzell, Garmann-Miller (419) 628-4240

Tom Dutton, Garmann-Miller (419) 628-4240

Clay Keith, Robertson (614) 374-4857

Jessica Post, Robertson (740) 814-6742

Site Improvements Package

Shira Elder, Garmann-Miller (419) 628-4240

Mark Keith, Robertson (740) 404-1805

Kevin Mohler, Robertson (740) 503-7218

New 4-5 Elementary School

Curt South, Garmann-Miller (419) 628-4240

Clyde McIntire, Robertson (740) 404-0111

AJ Saunders, Robertson (740) 348-6932

New High School

Brian Wolf, Garmann-Miller (419) 628-4240

Mark Keith, Robertson (740) 404-1805

Kevin Mohler, Robertson (740) 503-7218

Etna Elementary Renovation

Curt South, Garmann-Miller (419) 628-4240

Clyde McIntire, Robertson (740) 404-0111

AJ Saunders, Robertson (740) 348-6932

September 15, 2019 Drone Photo

May 11,2019 Drone Photo

Page 5: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

4 | P a g e

PROJECT FLOOR PLANS

New 4-5 Elementary School

Page 6: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

5 | P a g e

PROJECT FLOOR PLANS

New 9-12 High School

Page 7: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

6 | P a g e

EXECUTIVE SUMMARY

This report has been prepared to provide a project update for the Southwest Licking New 4-5 Elementary

School and New High School. It is intended to provide a summary review of the status of the project

through December 19th, 2019.

UPCOMING MEETINGS:

January 8th at 10:00 am – Core Team Meeting (Every Two Weeks)

January 7th at 2:00 pm - New 4-5 Elementary School Progress Meeting (Every Tuesday)

January 7th at 12:30 pm - New High School Progress Meeting (Every Tuesday)

New 4-5 Elementary School

CALENDAR DAYS TO COMPLETE

Substantial Completion (Nov 10, 2020) 327

SCHEDULE & WORK COMPLETED

Previous Month:

• Temporary Electric Service Active

• First Floor Masonry at Areas C – 100%

• Masonry at Student Dining – 75%

• First Floor Masonry at Area A – 50%

• AHUs set in Areas C, B, and A

This Month:

• Second Floor Masonry at Area C – 40%

• Temporary Dry-In Area C – 30%

• First Floor Wall Framing Area C – 90%

• Steel Erection & Decking at Area C – 95%

• HVAC, Electrical, and Plumbing Rough-In at

Area C1 – 20%

• Steel Erection & Decking at Area A – 30%

CURRENT ISSUES

• Masonry Winter Protection

• Masonry Veneer Quality Control

• Stair Design Coordination Area A

New High School

CALENDAR DAYS TO COMPLETE

Substantial Completion (Apr 29, 2021) 498

Topsoil, Reseed, Asphalt (May 28, 2021) 527

SCHEDULE & WORK COMPLETED

Previous Month:

• Shop Drawing & Submittal Review

• Auditorium Double Fire Walls Complete

• Concrete Slab Areas E and F Complete

• Structural Steel Deliveries Received for Areas E,

B, and C

• Concrete Footings Complete

This Month:

• Coordination Drawings – 2nd Floor Continue

• Concrete Slab Area G Complete

• Areas H-J, Area B Kitchen, and Area C

Underground Plumbing and Electrical

• Continue Masonry in Academic Wings

• Set Roof Steel and Decking at Gym and

Auditorium

CURRENT ISSUES

• Baseline Schedule Completion – Issued to

subcontractors on 12/12/19

• Excess Site Soil

• Masonry Winter Protection

• Failed Auditorium Masonry Wall

• Acid Waste Piping Fusion - Weather

Page 8: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

7 | P a g e

New 4-5 Elementary School

Owner Contingency Usage

Approved Change Orders Pending Change Orders

Remaining Contingency Site Work Approved Change Orders

Site Work Pending Change Orders

New High School

Owner Contingency Usage

Approved Change Orders Pending Change Orders

Remaining Contingency Site Work Approved Change Orders

Site Work Pending Change Orders

PROJECT BUDGETS

Owner Contingency

Owner Contingency

Elementary School

Original Amount $484,786.40

Approved Change Orders $14,163.61

Pending Change Orders $48,886.61

Remaining Contingency $421,736.18

Site Work Approved Change Orders $(31,529.54)

Site Work Pending Change Orders $46,489.85

Owner Contingency

High School

Original Amount $1,304,165.46

Approved Change Orders $4,704.50

Pending Change Orders $36,594.20

Remaining Contingency $1,262,866.76

Site Work Approved Change Orders $(77,193.02)

Site Work Pending Change Orders $126,644.76

Page 9: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

8 | P a g e

Site Improvements Package

CMR Contingency Usage

Approved Change Orders Pending Change Orders

Remaining Contingency

New 4-5 Elementary School

CMR Contingency Usage

Approved Change Orders Pending Change Orders

Remaining Contingency

New High School

CMR Contingency Usage

Approved Change Orders Pending Change Orders

Remaining Contingency

CMR Contingency

CMR Contingency

Site Work

Original Amount $84,760.00

Approved Change Orders $12,980.56

Pending Change Orders $22,323.80

Remaining Contingency $49,455.64

CMR Contingency

Original Amount $343,225.00

Approved Change Orders $-

Pending Change Orders $107,249.41

Remaining Contingency $235,975.59

CMR Contingency

High School

Original Amount $665,549.00

Approved Change Orders

Pending Change Orders $28,982.00

Remaining Contingency $636,567.00

Page 10: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

9 | P a g e

PROJECT SCHEDULE

Site Improvements Package

RCS Internal Verification Dates

SCHEDULE FROM BID SCHEDULED STATUS

Notice to Proceed February 28, 2019 Complete

Build Building Pad – Elementary School June 10, 2019 Complete

Build Building Pad – High School June 26, 2019 Complete

Substantial Completion of Elementary School November 10, 2020

Substantial Completion of All Work (less Items Below) April 29, 2021

Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021

Schedule Two Week Look Ahead

• Substantial Completion – No longer on the critical path. Miscellaneous work will be

preformed as weather permits and reconvene in the spring.

• Work is suspended through the Winter and will resume in the Spring.

• All Critical Path work is complete.

Page 11: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

10 | P a g e

PROJECT SCHEDULE

New 4-5 Elementary School

RCS Internal Verification Dates

SCHEDULE FROM BASELINE SCHEDULE SCHEDULED STATUS

Notice to Proceed February 28, 2019 Complete

Temporary Dry-In March 5, 2020

Permanent Dry-In May 21, 2020

Final HVAC Start-Up May 12, 2020

Substantial Completion November 10, 2020

Schedule Two Week Look Ahead

Site Work

• Main Electrical Bank Install

Area B

• Stage Roof and Student Dining Bearing

Walls

• Stage Concrete Slab

• Student Dining Concrete Slab

• Set Roof Steel at Student Dining

• Install Roof Blocking at Student Dining

Area C – 1st Floor

• Install Wood Roof Blocking at Area C

Mechanical Tower

• In-Wall HVAC, Electrical, and Plumbing

Rough-Ins

• Install Masonry Veneer above Flat Roof

• Install Membrane Roofing at Flat Roof

Area

Area C – 2nd Floor

• CMU Roof Bearing

Area A – 1st Floor

• Area A Masonry Bearing Walls

• Set Floor Steel at 2nd Floor and

Mechanical Room

• Set Roof Steel at 1-Story Area

• Area A Mechanical Tower Roof Dry-In

Area A – 2nd Floor

• Concrete Slab on Deck Pour

Page 12: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

11 Page

PROJECT SCHEDULE

New High School

RCS Internal Verification Dates

MILESTONE SCHEDULE FROM BID SCHEDULED STATUS

Notice to Proceed May 24, 2019 Complete

Substantial Completion of All Work (less items below) April 29, 2021

Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021

Schedule Two Week Look Ahead

All Building

• Finalize MEPT 3-D Above Ceiling

Coordination 2nd Floor

• Finalize Schedule

Area D

• Foundation Block

Area E

• Setting Gym Roof Steel and Decking

Area B

• Clean-up and evaluation of Area

Area F – 1st Floor

• Masonry Bearing Walls

Area G – 1st Floor

• Exterior Masonry Bearing

Area H – 1st Floor

• Underground Plumbing (60% Complete)

• Start Exterior Masonry Bearing

Area J – 1st Floor

• Pour Concrete Slab

• Exterior Masonry Bearing Start

Page 13: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

12 Page

Site Improvements Package

Request for Information

Open RFIs Closed RFIs

15Total RFIs:

Open RFIs: 1

PROJECT DOCUMENTATION

Site Improvements Package

The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)

and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information

does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and

is intended to highlight critical items to all parties.

The following items may present potential concerns to the project schedule:

Submittal/RFI Responsibility Schedule Concern

Site Improvements Package

Submittals

Approved Submittals Pending Submittals

Closeout Submittals Outstanding Submittals

Total Submittals:

Approved:

Pending:

Outstanding:

Closeout:

82

58

0

0

23

Page 14: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

13 Page

New 4-5 Elementary School

Request for Information

Open RFIs Closed RFIs

Total RFIs:

Open RFIs:

82

0

PROJECT DOCUMENTATION

New 4-5 Elementary School

The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)

and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information

does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and

is intended to highlight critical items to all parties.

The following items may present potential concerns to the project schedule:

Submittal/RFI Responsibility Schedule Concern

New 4-5 Elementary School

Submittals

Approved Submittals Pending Submittals

Closeout Submittals Outstanding Submittals

Total Submittals:

Approved:

Pending:

Outstanding:

Closeout:

1000

497

5

237

261

Page 15: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

14 Page

New High School

Request for Information

Open RFIs Closed RFIs

Total RFIs:

Open RFIs:

79

3

PROJECT DOCUMENTATION

New High School

The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)

and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information

does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and

is intended to highlight critical items to all parties.

The following items may present potential concerns to the project schedule:

Submittal/RFI Responsibility Schedule Concern

New High School

Submittals

Approved Submittals Pending Submittals

Closeout Submittals Outstanding Submittals

Total Submittals:

Approved:

Pending:

Outstanding:

Closeout:

1216

362

50

439

365

Page 16: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

15 Page

QUALITY CONTROL

New 4-5 Elementary School, Site Improvements Package, and New High School

The monitoring of safety and quality of work is an important issue, which Robertson Construction Services and the

Subcontractors take very seriously. Robertson continually monitors the Subcontractor’s safety practices and quality

of work via on-site inspections.

Quality Control

We are reviewing all of the “work in place” to verify it was installed as designed. Any discrepancies from the

Contract Documents are listed in field reports and distributed to the proper Subcontractor for corrections. We also

discuss the items in our weekly subcontractor meetings to ensure each concern has proper closure. The entire

Design Team has taken a thorough and proactive approach to items. Robertson continues to monitor the reports from

Geotechnical Consultants Inc. Corrections are being made in response to these reports.

Additionally, pre-installation meetings are being scheduled with the Architect and appropriate subcontractors to

ensure the work is consistent with the contract specifications and on par with quality standards.

Thus far we have held the following pre-installation meetings:

• Elementary Cast-In-Place Concrete (Footings) – July 23rd at 3:00 pm

• High School Cast-In-Place Concrete (Footings) – August 8th, 2019

• Elementary & High School Unit Masonry – July 30th at 3:00 pm

• Elementary & High School Cast-In-Place Concrete (Slab on Grade) – August 27th at 1:00 pm

• Elementary & High School Membrane and Sheet Metal Roofing – October 8th at 3:00 pm

• Elementary & High School Mechanical Materials/Methods – November 5th at 10:00 am

• Elementary & High School Fire Protection Materials/Methods – November 19th at 10:00 am

• Elementary & High School Plumbing Materials/Methods – November 19th at 9:00 am

• Site Work Clearing and Grubbing – March 7th, 2019

The following Pre-Installation Meetings are to be scheduled:

• Communication Metal Support

• Foamed-In-Place Insulation

The Following Pre-Installation Meetings are to be held per the Specifications:

• Polished Concrete Floor System

• Stone Masonry Veneer

• Storefronts, Curtain Walls, and Glazing

• Door Hardware – Pre-Installation

• Wood Flooring

• Resilient Flooring and Tiling

• Sound, Video, & Communication Systems

• High School Theater & Stage Equipment

• Technology Kick-Off Meeting

• Resinous Matrix Terrazzo and Quartz

Flooring

• Window Shades

• Educational and Library Casework

• Telescoping Bleachers

• Hydraulic Elevators

• Grading

Page 17: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

18 Page

SAFETY

New 4-5 Elementary School

June 2019 – There have been no safety issues this month.

July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019

with no safety violations observed.

August 2019 – There have been no safety issues this month.

September 2019 – There have been no safety issues this month.

October 2019 – A safety audit was held by Robertson on September 19th, 2019. Five (5) safety violations were noted

on the audit, all violations were abated that day.

November 2019 – A third-party inspection was conducted by Ogle on October 23rd, 2019. There were eight (8)

violation that were noted and abated immediately. Subcontractors instituted scaffolding tag-out and tag-

in procedures on site.

December 2019 – A safety audit was held by Robertson on December 5th, 2019. Five (5) safety violations were

noted on the audit, all violations were abated that day.

RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted

during the walkthrough.

Page 18: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

19 Page

SAFETY

Site Improvements and New High School

June 2019 – There have been no safety issues this month.

July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019

with no safety violations observed.

August 2019 – There have been no safety issues this month.

September 2019 – There have been no safety issues this month.

October 2019 – A safety audit was held by Robertson on September 19th, 2019. Two (2) safety violations were noted

on the audit, all violations were abated that day.

November 2019 – A third-party inspection was conducted by Ogle on October 23rd, 2019. There were two (2)

violation that were noted and abated immediately.

December 2019 – A safety audit was held by Robertson on December 5th, 2019. One (1) safety violation was noted

on the audit and it was immediately abated.

December 6th, 2019 – Masonry wall at Auditorium fell. No serious injuries. Insurance carriers and engineers are

reviewing conditions.

RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted

during the walkthrough.

Page 19: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

20 Page

PROGRESS PHOTOS

New 4-5 Elementary School

Stage Steel and Backfill

December 17, 2019

South Side View of Building

December 10, 2019

Area C West Classrooms

Metal Stud Framing

December 17, 2019

Area A Floor Steel

December 17, 2019

HVAC

System

Rough-Ins at

Area C

December 17,

2019

Page 20: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

21 Page

PROGRESS PHOTOS

New 9-12 High School

Area D Foundations

December 10, 2019

Area B Exterior Walls

December 3, 2019

Area G Concrete Slab Pour

December 3, 2019

Main Gymnasium

December 10, 2019

Page 21: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

22 Page

PROGRESS PHOTOS

Drone Footage

East View of Elementary School

November 29, 2019

East View of Campus

November 29, 2019

North East View of High School

November 29, 2019

Page 22: Monthly Status Report #07 December 2019Projects: Southwest ... Report 06 (19-DEC).pdf · 9/15/2019  · Nathan Jones Ohio Facilities Construction Commission ... Clay Keith, Robertson

Southwest Licking Local Schools

New High School and New 4-5 Elementary

Progress Report No. 07, December 19th, 2019

23 Page

Overhead View of Elementary School

November 29, 2019

View of Entire Campus with Connector Road

November 29, 2019

View of Auditorium from the North

November 29, 2019