Progress Report No. 05
For the Period Ending October 17th, 2019
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Kandee Engle Southwest Licking Local Schools
Debra Moore Southwest Licking Local Schools
Catherine Spindler Southwest Licking Local Schools
John Vincent Southwest Licking Local Schools
Roger Zeune Southwest Licking Local Schools
Robert Jennell Southwest Licking Local Schools
Richard Jones Southwest Licking Local Schools
Nathan Jones Ohio Facilities Construction Commission
Eric Baltzell Garmann-Miller Architects Engineers
Curt South Garmann-Miller Architects Engineers
Brian Wolf Garmann-Miller Architects Engineers
Julie Taggart Hill International
Michael Maxwell Hill International
Construction Manager:
Robertson Construction Services, Inc.
1801 Thornwood Drive
Heath, Ohio 43056
Architects:
Garmann-Miller Architects Engineers
38 South Lincoln Drive
P.O. Box 71
Minster, Ohio 45865
Owner’s Agent:
Hill International, Inc.
2 Easton Oval #110
Columbus, Ohio 43219
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
2 Page
Table of Contents
PROJECT CONTACTS .............................................................................................................. 3
PROJECT FLOOR PLANS ........................................................................................................ 4
New 4-5 Elementary School ................................................................................................... 4
New 9-12 High School ............................................................................................................ 5
EXECUTIVE SUMMARY ........................................................................................................... 6
PROJECT BUDGETS ................................................................................................................ 7
Owner Contingency ................................................................................................................ 7
CMR Contingency .................................................................................................................. 8
PROJECT SCHEDULE .............................................................................................................. 9
Site Improvements Package ................................................................................................... 9
New 4-5 Elementary School ..................................................................................................10
New High School ...................................................................................................................11
PROJECT DOCUMENTATION .................................................................................................12
Site Improvements Package ..................................................................................................12
New 4-5 Elementary School ..................................................................................................13
New High School ...................................................................................................................14
QUALITY CONTROL & SAFETY ..............................................................................................15
New 4-5 Elementary School ..................................................................................................15
Site Improvements Package and New High School ...............................................................17
PROGRESS PHOTOS ..............................................................................................................19
Site Improvements Package ..................................................................................................19
New 4-5 Elementary School ..................................................................................................20
New 9-12 High School ...........................................................................................................21
Drone Footage ......................................................................................................................22
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
3 Page
PROJECT CONTACTS
All Projects
Eric Baltzell, Garmann-Miller (419) 628-4240
Tom Dutton, Garmann-Miller (419) 628-4240
Clay Keith, Robertson (614) 374-4857
Jessica Post, Robertson (740) 814-6742
Site Improvements Package
Shira Elder, Garmann-Miller (419) 628-4240
Mark Keith, Robertson (740) 404-1805
Kevin Mohler, Robertson (740) 503-7218
New 4-5 Elementary School
Curt South, Garmann-Miller (419) 628-4240
Clyde McIntire, Robertson (740) 404-0111
AJ Saunders, Robertson (740) 348-6932
New High School
Brian Wolf, Garmann-Miller (419) 628-4240
Mark Keith, Robertson (740) 404-1805
Kevin Mohler, Robertson (740) 503-7218
Etna Elementary Renovation
Curt South, Garmann-Miller (419) 628-4240
Clyde McIntire, Robertson (740) 404-0111
AJ Saunders, Robertson (740) 348-6932
September 15, 2019 Drone Photo
May 11,2019 Drone Photo
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
4 Page
PROJECT FLOOR PLANS
New 4-5 Elementary School
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
5 Page
PROJECT FLOOR PLANS
New 9-12 High School
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
6 Page
EXECUTIVE SUMMARY
This report has been prepared to provide a project update for the Southwest Licking New 4-5
Elementary School and New High School. It is intended to provide a summary review of the
status of the project through October 17th, 2019.
UPCOMING MEETINGS:
October 23rd at 10:00 am – Core Team Meeting (Every Two Weeks)
November 13th at 1:00 pm - Site Improvements Package Progress Meeting (Every Second Wednesday)
October 22nd at 2:00 pm - New 4-5 Elementary School Progress Meeting (Every Tuesday)
October 29th at 12:30 pm - New High School Progress Meeting (Every Other Tuesday)
New 4-5 Elementary School
CALENDAR DAYS TO COMPLETE
Substantial Completion (Nov 10, 2020) 390
SCHEDULE & WORK COMPLETED
Previous Month:
• Underground plumbing in Area A – 60%
• Masonry walls in Area A Tower, Area B at Stage, and Gym – 80%
• Pour Elevator Pit
• Slab on Grade Concrete Pour Area C
This Month:
• Underground Electric and Plumbing All – COMPLETE
• Concrete Slab on Grade Pour in Areas C, A, and Gym – COMPLETE
• Masonry Bearing Walls at Gym & Area A-2 Story to Floor Bearing-COMPLETE
• Masonry Bearing Walls Area C-1 Story – 30%
• Bar Joist & Decking at Gym – 95%
• Temporary Electric Service Active CURRENT ISSUES
• Award of RCS Self-Perform Packages for
General Trades, Concrete, and Misc. Metals.
There has been a total amount $300,000 of RCS
self-perform work that cannot be billed for.
• Team review and response time frames
New High School
CALENDAR DAYS TO COMPLETE
Substantial Completion (Apr 29, 2021) 560 Topsoil, Reseed, Asphalt (May 28, 2021) 589
SCHEDULE & WORK COMPLETED
Previous Month:
• Continue with Shop Drawing and Submittal Review
• CMU up to 100’ (Finish Floor) in Areas E, C, and B
• Footings in Areas E (Main Gym), C, and B - COMPLETE
• Gymnasium CMU Walls – COMPLETE
• Orchestra Pit Floors and Walls-COMPLETE
• MEP Underground Coordination in conjunction
with footing pours
• Coordination Drawing Continue
This Month:
• Underground in Areas F1, G1, H1, and J1
• Stage Concrete Slab and cantilever
• Auditorium Double Fire Wall
• Footings in Areas F1, G1, H1, and J1
CURRENT ISSUES
• Baseline Schedule sign-off from contractors
• Excess Site Soil
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
7 Page
New 4-5 Elementary School
Owner Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency Site Work Approved Change Orders
Site Work Pending Change Orders
New High School
Owner Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency Site Work Approved Change Orders
Site Work Pending Change Orders
PROJECT BUDGETS
Owner Contingency
Owner Contingency
Elementary School
Original Amount $ 484,786.40
Approved Change Orders $ 747.74
Pending Change Orders $ 48,547.17
Remaining Contingency $ 435,491.49
Site Work Approved Change Orders $ 18,832.95
Site Work Pending Change Orders $ (30,085.07)
Owner Contingency
High School
Original Amount $ 1,304,165.46
Approved Change Orders $ -
Pending Change Orders $ 46,575.87
Remaining Contingency $ 1,257,589.59
Site Work Approved Change Orders $ 46,108.26
Site Work Pending Change Orders $ (81,955.88)
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
8 Page
New 4-5 Elementary School
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
New High School
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
Site Improvements Package
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
CMR Contingency
CMR Contingency
Site Work
Original Amount $ 84,760.00
Approved Change Orders $ 11,022.27
Pending Change Orders $ 22,997.73
Remaining Contingency $ 50,740.00
CMR Contingency
Original Amount $ 343,225.00
Approved Change Orders $ -
Pending Change Orders $ 10,465.00
Remaining Contingency $ 332,760.00
CMR Contingency
High School
Original Amount $ 665,549.00
Approved Change Orders
Pending Change Orders $ 10,282.00
Remaining Contingency $ 655,267.00
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
9 Page
PROJECT SCHEDULE
Site Improvements Package
RCS Internal Verification Dates
SCHEDULE FROM BID SCHEDULED STATUS
Notice to Proceed February 28, 2019 Complete
Build Building Pad – Elementary School June 10, 2019 Complete
Build Building Pad – High School June 26, 2019 Complete
Substantial Completion of Elementary School November 10, 2020
Substantial Completion of All Work (less Items Below) April 29, 2021
Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021
Schedule Two Week Look Ahead
• Access Road Grading per excess soils
• Stone Box culvert
• Flush hydrants and 4,000 lf of water line
• Punch-out sanitary structures
• Code inspection with SWL and Fire
Department
• Backflow Test to be scheduled
• Survey for asphalt
• Mandrel test is 30 days out
• Relocate excess spoils as directed
• Underground utilities complete
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
10 Page
PROJECT SCHEDULE
New 4-5 Elementary School
RCS Internal Verification Dates
SCHEDULE FROM BASELINE SCHEDULE SCHEDULED STATUS
Notice to Proceed February 28, 2019 Complete
Temporary Dry-In March 5, 2020
Permanent Dry-In May 21, 2020
Final HVAC Start-Up May 12, 2020
Substantial Completion November 10, 2020
Schedule Two Week Look Ahead
All Building
• Continue with MEPT 3-D Above Ceiling
Coordination
Site Work
• Main Electrical Bank Install
• Main Technology Bank Install
Area B
• Set Roof Steel at Gym
• Student Dining & Stage Roof Bearing
Walls
• Install Roof Blocking at Gym
• Install Insulation and Ice & Water Shield
on Gym
• Set AHUs
• Student Dining Concrete Slab
• Set Bar Joist and Roof Deck at Student
Dining
Area C – 1st Floor
• Area C Roof Bearing walls (Mechanical
Room)
• Area C Bearing Walls at 1-Story Area
• Set Bar Joist and Floor Deck at the 2nd
Floor and the Mechanical Room
• Set AHU
• Set Bar Joist and Roof Deck at 1-Story
Area
• Install Roof Blocking at 1-Story Area
Area A – 1st Floor
• Area A Bearing Walls
• Set Bar Joist and Floor Deck at 2nd Floor
and the Mechanical Room
Area A – 1st Floor
• Concrete Slab on Deck Pour
• Masonry Roof Bearing
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
11 Page
PROJECT SCHEDULE
New High School
RCS Internal Verification Dates
MILESTONE SCHEDULE FROM BID SCHEDULED STATUS
Notice to Proceed May 24, 2019 Complete
Substantial Completion of All Work (less items below) April 29, 2021
Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021
Schedule Two Week Look Ahead
All Building
• Continue with MEPT 3-D Above Ceiling
Coordination (on going)
Area E
• Complete Gym Walls
Area B
• Stake Concrete Slab on Grade
• Masonry Walls at Auditorium
• Proscenium Masonry
Area F – 1st Floor
• Footings
• Underground plumbing and electrical
Area G – 1st Floor
• Footings
• Underground plumbing and electrical
Area H – 1st Floor
• Footings
• Underground plumbing and electrical
Area J – 1st Floor
• Footings
• Underground plumbing and electrical
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
12 Page
Site Improvements Package
Request for Information
Open RFIs Closed RFIs
14Total RFIs:
Open RFIs: 0
PROJECT DOCUMENTATION
Site Improvements Package
The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)
and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information
does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and
is intended to highlight critical items to all parties.
The following items may present potential concerns to the project schedule:
Submittal/RFI Responsibility Schedule Concern
CD-001 PR-003: Excess Topsoil Garmann-Miller
ASI-003: New MS Ballfield Garmann-Miller
Site Improvements Package
Submittals
Approved Submittals Pending Submittals
Closeout Submittals Outstanding Submittals
Total Submittals:
Submitted:
Pending:
Outstanding:
82
58
1
8
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
13 Page
New 4-5 Elementary School
Request for Information
Open RFIs Closed RFIs
Total RFIs:
Open RFIs:
68
4
PROJECT DOCUMENTATION
New 4-5 Elementary School
The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)
and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information
does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and
is intended to highlight critical items to all parties.
The following items may present potential concerns to the project schedule:
Submittal/RFI Responsibility Schedule Concern
Team #0001: 030510 Concrete Moisture Vapor Reduction Admixture – Product Data
Garmann-Miller Overdue Submittal
Team #0002: 030510 Concrete Moisture Vapor Reduction Admixture – Product Test Reports
Garmann-Miller Overdue Submittal
Team #0003: 030510 Concrete Moisture Vapor Reduction Admixture – Manufacturer’s Certificate
Garmann-Miller Overdue Submittal
Team #0006: 030510 Concrete Moisture Vapor Reduction Admixture – Warranty Garmann-Miller Overdue Submittal
Team #0520: 142422 Hydraulic Elevator Garmann-Miller Overdue Submittal
Team #1010: 233100 – HVAC Ducts & Casings – Fabric Duct Sample Garmann-Miller Overdue Submittal
Team #1019: 033000 – Cast-In-Place Concrete – Mix Design Garmann-Miller Overdue Submittal
Team #1020: 033000 – Cast-In-Place Concrete – LEED Garmann-Miller Overdue Submittal
Team #1021: 033000 – Cast-In-Place Concrete – Mix Design & LEED Garmann-Miller Overdue Submittal
RFI-064: Edge of Roof Wood Blocking Support at Gym Garmann-Miller Overdue RFI
New 4-5 Elementary School
Submittals
Approved Submittals Pending Submittals
Closeout Submittals Outstanding Submittals
Total Submittals:
Submitted:
Pending:
Outstanding:
985
326
24
367
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
14 Page
New High School
Request for Information
Open RFIs Closed RFIs
Total RFIs:
Open RFIs:
61
4
PROJECT DOCUMENTATION
New High School
The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)
and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information
does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and
is intended to highlight critical items to all parties.
The following items may present potential concerns to the project schedule:
Submittal/RFI Responsibility Schedule Concern
PR-002: Hardware Clarification Garmann-Miller Overdue Submittal
Stage Rigging Submittal Garmann-Miller Coordination
RFI-058: Joist & Deck Shop Drawing Questions Garmann-Miller Overdue RFI
New High School
Submittals
Approved Submittals Pending Submittals
Closeout Submittals Outstanding Submittals
Total Submittals:
Submitted:
Pending:
Outstanding:
1176
241
16
551
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
15 Page
QUALITY CONTROL & SAFETY
New 4-5 Elementary School
The monitoring of safety and quality of work is an important issue, which Robertson Construction Services and the
Subcontractors take very seriously. Robertson continually monitors the Subcontractor’s safety practices and quality
of work via on-site inspections.
Quality Control
We are reviewing all of the “work in place” to verify it was installed as designed. Any discrepancies from the
Contract Documents are listed in field reports and distributed to the proper Subcontractor for corrections. We also
discuss the items in our weekly subcontractor meetings to ensure each concern has proper closure. The entire
Design Team has taken a thorough and proactive approach to items. Robertson continues to monitor the reports from
Geotechnical Consultants Inc. Corrections are being made in response to these reports.
Additionally, pre-installation meetings are being scheduled with the Architect and appropriate subcontractors to
ensure the work is consistent with the contract specifications and on par with quality standards.
Thus far we have held the following pre-installation meetings:
• Cast-In-Place Concrete (Footings) – July 23rd at 3:00 pm
• Unit Masonry – July 30th at 3:00 pm
• Cast-In-Place Concrete (Slab on Grade) – August 27th at 1:00 pm
• Membrane and Sheet Metal Roofing – October 8th at 3:00 pm
The following Pre-Installation Meetings are to be scheduled:
• Communication Metal Support
• Foamed-In-Place Insulation
• Electrical Service Entrance
The Following Pre-Installation Meetings are to be held per the Specifications:
• Polished Concrete Floor System
• Stone Masonry Veneer
• Aluminum-Framed Storefronts
• Glazed Aluminum Curtain Walls
• Door Hardware – Keying Conference
• Door Hardware – Pre-Installation
• Door Hardware – Coordination Conference
• Glazing
• Tiling
• Wood Flooring
• Theater & Stage Equipment
• Resilient Flooring
• Grading
• Technology Kick-Off Meeting
• Resinous Matrix Terrazzo Flooring
• Quartz Flooring
• Window Shades
• Educational Casework
• Library Casework
• Telescoping Bleachers
• Hydraulic Elevators
• Fire Protection Materials/Methods
• Plumbing Materials/Methods
• Mechanical Materials/Methods
• Instruments and Control Elements
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
16 Page
Safety
June 2019 – There have been no safety issues this month.
July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019
with no safety violations observed.
August 2019 – There have been no safety issues this month.
September 2019 – There have been no safety issues this month.
October 2019 – A safety audit was held by Robertson on September 19th, 2019. Five (5) safety violations were noted
on the audit, all violations were abated that day.
RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted
during the walkthrough.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
17 Page
QUALITY CONTROL & SAFETY
Site Improvements Package and New High School
The monitoring of safety and quality of work is an important issue, which Robertson Construction Services and the
Subcontractors take very seriously. Robertson continually monitors the Subcontractor’s safety practices and quality
of work via on-site inspections.
Quality Control
We are reviewing all of the “work in place” to verify it was installed as designed. Any discrepancies from the
Contract Documents are listed in field reports and distributed to the proper Subcontractor for corrections. We also
discuss the items in our weekly subcontractor meetings to ensure each concern has proper closure. The entire
Design Team has taken a thorough and proactive approach to items. Robertson continues to monitor the reports from
Geotechnical Consultants Inc. Corrections are being made in response to these reports.
Additionally, pre-installation meetings are being scheduled with the Architect and appropriate subcontractors to
ensure the work is consistent with the contract specifications and on par with quality standards.
Thus far we have held the following pre-installation meetings:
• Clearing and Grubbing – March 7th, 2019
• Cast-In-Place Concrete (Footings) – August 8th,
2019
• Membrane and Sheet Metal Roofing – October
8th at 3:00 pm
• Cast-In-Place Concrete (SOD/SOG) – August
27th, 2019
• Unit Masonry
The following Pre-Installation Meetings are to be scheduled:
• Communication Metal Support
• Foamed-In-Place Insulation
• Fire Protection Materials/Methods
• Plumbing Materials/Methods
• Mechanical Materials/Methods
• Cable Trays for Electrical Systems
• Electrical Service Entrance
The Following Pre-Installation Meetings are to be held per the Specifications:
• Polished Concrete Floor System • Resinous Matrix Terrazzo Flooring
• Stone Masonry Veneer
• Foamed-In-Place Insulation
• Membrane Roofing
• Sheet Metal Roofing
• Applied Fireproofing
• Aluminum-Framed Storefronts
• Glazed Aluminum Curtain Walls
• Door Hardware – Keying Conference
• Door Hardware – Pre-Installation
• Door Hardware – Coordination Conference
• Glazing
• Tiling
• Wood Flooring
• Resilient Flooring
• Quartz Flooring
• Window Shades
• Educational Casework
• Library Casework
• Telescoping Bleachers
• Hydraulic Elevators
• Fire Protection Materials/Methods
• Plumbing Materials/Methods
• Mechanical Materials/Methods
• Cable Trays for Electrical Systems
• Electrical Service Entrance
• Technology Kick-Off Meeting
• Sound, Video, & Communication Systems
• Site Sanitary Sewerage Gravity Piping
• Stormwater Gravity Piping
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
18 Page
Safety – Site Improvements Package and New High School
June 2019 – There have been no safety issues this month.
July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019
with no safety violations observed.
August 2019 – There have been no safety issues this month.
September 2019 – There have been no safety issues this month.
October 2019 – A safety audit was held by Robertson on September 19th, 2019. Two (2) safety violations were noted
on the audit, all violations were abated that day.
RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted
during the walkthrough.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
19 Page
PROGRESS PHOTOS
Site Improvements Package
High School Parking Lot Stone Base
October 8, 2019
Exterior of Box Culvert at Connector Road
October 5, 2019
High School Parking Lot Stone Base
October 8, 2019
Interior of Box Culvert at Connector Road
October 5, 2019
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
20 Page
PROGRESS PHOTOS
New 4-5 Elementary School
Area C Exterior Walls
October 15, 2019
Gym View from the Courtyard
October 15, 2019
Gym Bar Joist, Steel Decking, and Slab on
Grade Pour
October 15, 2019
Structural Steel being Placed at Gym
October 4, 2019
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
21 Page
PROGRESS PHOTOS
New 9-12 High School
Area F1 Footings and Footer Block
October 15, 2019
Main Gym CMU Walls
October 15, 2019
Area B Viewing Area E
October 15, 2019
Area B Exterior Wall
October 15, 2019
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
22 Page
PROGRESS PHOTOS
Drone Footage
Elementary School – Area C
October 13, 2019
Front View of Elementary and High School
October 13, 2019
Full View of Elementary and High School Site
October 13, 2019
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 05, October 17th, 2019
23 Page
View of Elementary School from Smoke Rd
October 13, 2019
New High School Auditorium
October 13, 2019
New High School
October 13, 2019