Report No. 26
September 2019
City of Lubbock - Citizens Tower
Owner
City of Lubbock
Architect
Perkins + Will
Page 1
Consultants
Civil
Hugo Reed & Associates
Structural
Henderson Rogers
MEP
Schmidt & Stacy
Landscape
Prairie Workshop LLC
IT/AV/Acoustics
DataCom Design Group
General Contractor / Construction Manager at Risk
Lee Lewis Construction, Inc.
Project Scope:
The City of Lubbock purchased the former Citizens Bank building located at the intersection of 14th Street and Avenue K in downtown
Lubbock, Texas. It is a concrete structure with 11 stories above grade, a basement, an adjacent 2 level annex, a 5 level concrete
parking garage, a second basement below the parking lot southeast across the intersection and two connecting tunnels. The project
scope consists of demolition of the parking garage and provide new parking; renovation of the Citizens Bank building into the City of
Lubbock’s new Citizens Tower; and renovation/construction of a single story above the second basement. The tower and annex will
house the majority of City Hall’s departments and functions. The new single story and basement will house the Utility Customer Ser-
vices Center.
This project marks the start of a revitalizing effort targeting future downtown re-development.
The renderings below show the proposed design for the project.
View from 13th Street & Avenue K View from 14th St. & Ave. K Utility Customer Services Center
Monthly Report
Metal fascia panel installation in progress - Utility Customer Services Center
September Project Focus Safety / Building Envelope / Framing & Drywall
Citizens Tower / Annex /
Utility Customer Services Center Page 2
September Summary
Project Costs
Property Acquisition Funds $1,262,500
Initial Funds $63,000,000
PEG Funds $960,000
Total $65,222,500
Acquisitions & Soft Costs $9,409,324
Pre-Construction $2,771,854
Construction GMP $46,665,132
Post-Construction $722,148
FF&E / Move-In $4,111,242
Total Committed Expenditures $63,679,700
Contractor is continuing all major construction ac-
tivities including; mechanical / electrical / plumbing
rough-in, fire suppression system, interior metal
framing & drywall, exterior building envelope and
interior finishes.
Roofing – Tower (Area A) Roof complete and
HVAC framing ready for HVAC equipment. NOTE:
Crane arrived on site for lift and set.
Aluminum Composite Metal panel column covers
80% complete at North façade.
Exterior elevator removed and south wall glass +
terra cotta installs at southeast corner now under-
way.
Exterior screen supports at East stair complete,
touch-up of intumescent coating in progress.
Project Milestones
Property Purchase complete: 11/11/2014
Concept (Programming) complete: 12/07/2015
Schematic Design complete: 04/25/2016
Design Development complete: 05/16/2016
Contract Documents complete: 05/12/2017
Procurement (GMP) complete: 07/13/2017
Construction Notice to Proceed: 08/01/2017
Construction Substantial Completion 22 months Original Target Date 06/01/2019
Time Extension Requests 159 Days
Revised Target Date 11/08/2019
Commissioning / FF&E / Technology 3 Months
Phased Move-In Start Date 12/08/2019
Full Occupancy Target Date 02/08/2020
Crane arriving to job site to lift mechanical equipment to roof
Restroom plumbing fixtures installed on several floors
Citizens Tower / Annex /
Utility Customer Services Center Page 3
Construction Activities
Construction continues at upper floors for safety
guardrails, handrails and barricades around all
areas of demolition & construction activities. All
openings are fall protected with barricades and
designated as 100% tie-off areas. Construction
site traffic control barricades checked daily.
Reception areas and workroom millwork installs
taking place on floors 3 through 6.
Restroom plumbing fixtures being installed on
lower and middle floors.
Terra Cotta installation continues on the south-
west corner following removal of the exterior con-
struction elevator.
HVAC equipment lifted to roof and placed on pre-
set structure.
Revolving doors set at lobby entries.
Lobby area terrazzo floors being ground and Main
Street terrazzo floor preparation, ready for materi-
al placement.
Mail room wall-opening completed and ready for
box units install.
Waterproofing UCSC parking lot slab in progress.
Pressurization fans being lifted to roof
Meeting & Information Activities
Owner, Architect, Contractor (OAC) RFI/Submittal
Log review held September 4 & 18, 2019 via con-
ference call.
Owner, Architect, Contractor (OAC) progress
meetings held September 11 & 25, 2019 on site.
RFP for Move/Relocation services proposals
closed/due August 6, 2019.
3rd Move coordination meeting held September
16, 2019.
Owner, Architect, Contractor (OAC) RFI/Submittal
Log reviews scheduled October 2, 16 & 30, 2019.
Owner, Architect, Contractor (OAC) progress
meetings scheduled October 9 & 23, 2019.
4th Move coordination meeting scheduled Octo-
ber 14, 2019.
Facilities Committee meetings held September 23
& 30, 2019
Facilities Committee meetings scheduled October
14 & 21, 2019.
Lifting chillers to roof
Citizens Tower / Annex /
Utility Customer Services Center Page 4
Progress — Tower Area A
Chillers being lifted to roof
Millwork install level 7
Grinding terrazzo floors
Chillers being lifted to roof
Installing remaining curtain wall Metal panels being installed east side
Terrazzo ready for grinding
LED lighting installed several floors
Chiller installed on roof
Millwork install progressing floor 3 Fur downs being sheet rocked floor 11 HVAC components staged for install at level 11
Citizens Tower / Annex /
Utility Customer Services Center Page 5
Progress — Annex Area B
Temporary fire riser connection Preparing for metal panel fascia & soffit
Doors installed
Fiber line pulled into building Grinding terrazzo annex Offices sheet rocked
Restroom plumbed ready for fixtures
Main street terrazzo
Roof drains
Elevator No. 5 Control Closet LED lighting annex basement
Print room opening for mail slots/boxes
Citizens Tower / Annex /
Utility Customer Services Center Page 6
Progress — UCSC Area C & Miscellaneous
Floors prepped for terrazzo Restrooms being tiled Metal panel install continues
Working on new utility lines
Generator yard progress Removing pole in UCSC parking lot
Glass doors staged & ready for installation
Elevator pit Old deteriorated sidewalks removed at UCSC parking lot
Clearing lot for parking
Waterproofing plies being installed Parking lot slab being sealed