monthly progress report till end 30-04-2019 … · approved 939.329 500.000 200.000 400.000 140.000...

23
Rs. in Million 1 2 3 4 5 7 8 11 15 18 19 20 21 24 ON-GOING SCHEMES LDA 1 5505 Conservation of Energy through Solar Power LED Street Lights in Lahore Approved 60.000 35.689 8.104 8.104 6.078 0.000 0% 35.689 59% Funds Released by FD on 06-08-18 &10- 01-19 2 5506 Establishment of Sports Complex at Rakh Shahdra Lahore (LDP) Approved 605.766 299.990 50.000 50.000 37.500 25.000 67% 324.990 54% Funds Released by FD on 06-08-18 & 20.11.2018 & 10-01-19. Pending liabilities to be cleared. 3 5507 Establishment of Sports Complex in Sabzazar, Lahore (LDP). Approved 574.766 374.999 50.000 50.000 37.500 25.000 67% 399.999 70% Funds Released by FD on 06-08-18 & 20.11.2018 & 10-01-19. 4 5508 Establishment of Sports Complex Singh Pura, Lahore (LDP). Approved 781.766 405.150 50.000 50.000 37.500 10.000 27% 415.150 53% Funds Released by FD on 06-08-18 & 20.11.2018 &10-01-19. 5 5509 Establishment of Sports Complex Model Bazar China Scheme, Lahore (LDP). Approved 490.127 369.957 50.000 50.000 37.500 25.000 67% 394.957 81% Funds Released by FD on 06-08-18 & 20.11.2018 &10-01-19. 6 5510 Establishment of Sports Complex in Tajpura,Lahore(LDP). Approved 543.358 174.974 50.000 50.000 37.500 15.000 40% 189.974 35% Funds Released by FD on 06-08-18 & 20.11.2018 &10-01-19. 7 5511 Establishment of Sports Complex Town Ship, Lahore (LDP). Approved 713.758 235.000 115.000 115.000 86.250 25.300 29% 260.300 36% Funds Released by FD on 06-08-18 & 20.11.2018 &10-01-19. 8 5512 Establishment of Sports Complex Canal Bank near EME Society,Lahore(LDP). Approved 781.358 224.948 100.000 100.000 75.000 3.070 4% 228.018 29% Funds Released by FD on 06-08-18 & 10- 01-19. 9 5513 Establishment of Sports Complex Shalamar Lahore (LDP). Approved 688.766 274.936 50.000 50.000 37.500 0.000 0% 274.936 40% Funds Released by FD on 06-08-18 & 10- 01-19. 10 5514 Widening of Aik Moria Pull,Lahore. Approved 700.647 230.000 200.000 200.000 125.000 28.000 22% 258.000 37% Funds Released by FD on 06-08-18 & 10- 01-19. 11 5515 Construction of Flyover at Shoukat Khanum Chowk along Khayaban-e-Jinnah,Lahore Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10- 01-19.Rs. 200.000 million allocated by P&DD as a Supplementary Grant dated 08- 03-19. 12 5516 Construction of Kasur Sports Complex, Khem Karan Road, Kasur Approved 542.118 464.685 77.433 77.433 58.075 38.717 67% 503.402 93% Funds Released by FD on 06-08-18 & 10- 01-19. MONTHLY PROGRESS REPORT TILL END 30-04-2019 (DEVELOPMENT PROGRAMME 2018-19) Remarks Provision for 2018-19 Revised Allocation during 2018-19 Funds Released by F.D Funds utilized Upto 30-04-2019 %Utilization on Releases Total Cummulative Expenditure Financial Progress till the current Month (%) ADP No Scheme Name Approved Cost Exp. Upto June 18 Sr. No Approval Status

Upload: others

Post on 19-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

Rs. in Million

1 2 3 4 5 7 8 11 15 18 19 20 21 24

ON-GOING SCHEMES

LDA

1 5505 Conservation of Energy through

Solar Power LED Street Lights in

Lahore

Approved 60.000 35.689 8.104 8.104 6.078 0.000 0% 35.689 59% Funds Released by FD on 06-08-18 &10-

01-19

2 5506 Establishment of Sports

Complex at Rakh Shahdra

Lahore (LDP)

Approved 605.766 299.990 50.000 50.000 37.500 25.000 67% 324.990 54% Funds Released by FD on 06-08-18 &

20.11.2018 & 10-01-19.

Pending liabilities to be cleared.

3 5507 Establishment of Sports

Complex in Sabzazar, Lahore

(LDP).

Approved 574.766 374.999 50.000 50.000 37.500 25.000 67% 399.999 70% Funds Released by FD on 06-08-18 &

20.11.2018 & 10-01-19.

4 5508 Establishment of Sports

Complex Singh Pura, Lahore

(LDP).

Approved 781.766 405.150 50.000 50.000 37.500 10.000 27% 415.150 53% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

5 5509 Establishment of Sports

Complex Model Bazar China

Scheme, Lahore (LDP).

Approved 490.127 369.957 50.000 50.000 37.500 25.000 67% 394.957 81% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

6 5510 Establishment of Sports

Complex in

Tajpura,Lahore(LDP).

Approved 543.358 174.974 50.000 50.000 37.500 15.000 40% 189.974 35% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

7 5511 Establishment of Sports

Complex Town Ship, Lahore

(LDP).

Approved 713.758 235.000 115.000 115.000 86.250 25.300 29% 260.300 36% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

8 5512 Establishment of Sports

Complex Canal Bank near EME

Society,Lahore(LDP).

Approved 781.358 224.948 100.000 100.000 75.000 3.070 4% 228.018 29% Funds Released by FD on 06-08-18 & 10-

01-19.

9 5513 Establishment of Sports

Complex Shalamar Lahore

(LDP).

Approved 688.766 274.936 50.000 50.000 37.500 0.000 0% 274.936 40% Funds Released by FD on 06-08-18 & 10-

01-19.

10 5514 Widening of Aik Moria

Pull,Lahore.

Approved 700.647 230.000 200.000 200.000 125.000 28.000 22% 258.000 37% Funds Released by FD on 06-08-18 & 10-

01-19.

11 5515 Construction of Flyover at

Shoukat Khanum Chowk along

Khayaban-e-Jinnah,Lahore

Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-

01-19.Rs. 200.000 million allocated by

P&DD as a Supplementary Grant dated 08-

03-19.12 5516 Construction of Kasur Sports

Complex, Khem Karan Road,

Kasur

Approved 542.118 464.685 77.433 77.433 58.075 38.717 67% 503.402 93% Funds Released by FD on 06-08-18 & 10-

01-19.

MONTHLY PROGRESS REPORT TILL END 30-04-2019

(DEVELOPMENT PROGRAMME 2018-19)

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

Page 2: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

13 5517 Consultancy Services for

Preparation of Master Plan for

Water Supply, Sewerage,

Drainage and Ground Water

Management System for

Sheikhupura, Kasur & Nankana

Sahib Districts.

Approved 159.272 26.160 21.630 21.630 16.223 10.815 67% 36.975 23% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

Total: LDA 7,581.031 3,616.488 1,022.167 1,222.167 731.626 305.902 42% 3,922.390

WASA LDA

14 5518 Improvement of Water Supply

System in MA Johar Town &

Tajpura Zones of Lahore through

Zoning / Isolation, Installation of

Filtration Plants and 100%

Metering (Bulk, Distribution and

Consumer Levels), Lahore.

Approved 1,668.662 434.420 50.000 50.000 37.500 25.000 67% 459.420 28% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A.: 21.11.2014

Filtration plant:

T.S.: 08.05.2015 (FP)

Start of work:: 10.08.2015 Filtration

Plants (FP)

Start of Work: Aug-2015

Completion Date: 05.02.2016 (FP)

OHRs = 19-No.

Consumer Meters = 47,704

BFM = 80-No.

Arsenic Filtration Plant 94,

Bottling Plant

Status:

100% FP installed.

Remaining part:Revised PC-I cost Rs

1965.95 is sent to P&DD by HUD on

27/11/2018 .15 5519 Establishment of SCADA

System at Tubewells, Disposal &

Lift Stations for WASA Lahore.

Approved 697.200 15.703 8.334 8.334 8.334 4.056 49% 19.759 3% Funds Released by FD on 06-08-18.

A.A.: 02.01.2015

Revised PC-I cost Rs 897M is submitted

to Dep Sec(UD) on 25.10.18.

16 5520 Sewerage System from Larechs

Colony to Gulshan-e-Ravi,

Lahore.

Approved 6,928.113 265.446 5.000 5.000 3.750 0.000 0% 265.446 4% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A.: 13.04.2015

96" i/d Sewer = 16,180 m

60" i/d Sewer = 16,920 m

D/S = 350 Cfs.

Status:

PC-I will be submitted to Dy Sec HUD by

consultants after corrections by next

week.Reappropriation of Funds under

process.

17 5521 Changa Pani Programme

(Phase II) / Community

Participation Programme

Approved 329.240 309.240 20.000 20.000 15.000 10.000 67% 319.240 97% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A.: 19.01.16

T.S.: 21.01.16

Start of work:: 05.05.16

Completion date: 05.05.18

Work at site is

completed.Reappropriation of Funds

under process.

Page 3: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

18 5522 Installation of Filtration Plants on

105 No. Tubewells.

Approved 354.981 213.592 50.000 50.000 37.500 24.626 66% 238.218 67% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A.:21.07.16

T.S. :16-1-17

Start of work:16.6.17

F.P at 105 tubewells

Status: 105 Filtration plants are

operational. O&M in progress. 19 5523 Storm Water Drainage System

from Haji Camp to River Ravi via

Laxmi Chowk, McLeod Road,

Nabha Road, Chauburji and

Sham Nagar, Lahore.

Approved 2,400.000 975.000 200.000 200.000 130.000 100.000 77% 1,075.000 45% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A: 15.07.2016

TS: NA

Start of work::15-05-17

Precast Conduit 7(3.20 x 3.20 m) : 5,070

meters.

Lateral Drains (0.90 x 0.75 m)= 2,460 m

Status: PDWP meeting held on 12-02-19.

Revison of project was approved at the

cost of Rs. 3108.412. Land acquisition in

process. Rs 450 M is required for land

acquisition.20 5524 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Ravi

Road, Islampura and Adjoining

Abadies, Lahore.

Approved 494.326 344.326 30.000 30.000 22.500 15.000 67% 359.326 73% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A:15.07.16

TS: 22-11-16

Tender opening: 6.12.16

Start of work::26.12.16

Water Supply Lines:84,800Rft

Sewer:75,300Rft

Status: Work at site is in progress.

.Release of Funds is awaited21 5525 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Sheran

Wala Gate, Fazal Park and

Adjoining Abadies, Lahore.

Approved 501.080 208.192 30.000 30.000 22.500 12.955 58% 221.147 44% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A:15.07.16

TS:23-11-16

Tender opening:07.12.16

Re-tendering:17.12.16

Re-tendering :16-1-17

Start of work:14.2.17

Water Supply Lines:247,000Rft

Sewer:79,960Rft

Status: Work at site is in progress.

.Release of Funds is awaited22 5526 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Allama

Iqbal Town, Canal Park and

Adjoining Abadies, Lahore.

Approved 490.253 287.096 30.000 30.000 22.500 15.000 67% 302.096 62% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A: 15.07.16

TS: 14-11-16

Tender opening:07.12.16

Re-tendering:17.12.16

Re-tendering :16-1-17

Start of work:: 03.02.2017

Water Supply Lines:132,550Rft

Sewer:85,650Rft

Status: Work at site is in progress.

.Release of Funds is awaited

Page 4: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

23 5527 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Shimla

Pahari and Adjoining Abadies

,Lahore.

Approved 507.166 310.000 30.000 30.000 22.500 15.000 67% 325.000 64% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A:15.07.16

TS:09.11.16

Tender opening :27-12-16

Start of work::6.02.2017

Water Supply Lines:138,268Rft

Sewer:104,753ft

TW: 1No. 2 cfs capacity

Filtration Plants:2

Sewage Pump: 25 cfs (one No.)

Status: Work at site is in progress.

.Release of Funds is awaited24 5528 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Chohan

Colony, Singh Pura and

Adjoining Abadies, Lahore.

Approved 499.331 400.358 30.000 30.000 22.500 11.666 52% 412.024 83% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A: 15.08.16

TS:09.11.16

Tender opening: 24.11.16

Water Supply Lines:128,710Rft

Sewer:77,250ft

TW: 3No. 2 cfs capacity

Status:Work at site is in

progress..Release of Funds is awaited25 5529 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Sabzazar

and Adjoining Abadies Lahore.

Approved 493.273 400.100 30.000 30.000 22.500 12.375 55% 412.475 84% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A:27.10.16

TS: 14.11.16

Tender opening:03.12.16

start of work:24.12.16

Water Supply Lines:123,370Rft

Sewer:96,062ft

Sewage Pump 1-No. 6-Cfs Capacity

Status:Work at site is in

progress..Release of Funds is awaited26 5530 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Shahdara

and Adjoining Abadies, Lahore.

Approved 618.782 320.782 30.000 30.000 22.500 15.000 67% 335.782 54% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A:26.10.16

TS:11.11.16

Tender opening:07.12.16

Re-tendering:17.12.16

Water Supply Lines:131,390Rft

Sewer:177,500ft

Disposal Station 1-No. 12-Cfs Capacity

Filtration Plant 12-No.

Status: Work at site is in progress.

.Release of Funds is awaited27 5531 Provision of Clean Drinking

Water, Sewerage System, PCC

and Allied Facilities in Ganj

Bazar, Gulistan Colony and

Adjoining Abadies, Lahore.

Approved 792.704 610.704 30.000 30.000 22.500 15.000 67% 625.704 79% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A: 06.10.16

T.S: 09.11.16

Tender opening:24.11.16

Water Supply Lines:233,300Rft

Sewer:115,800ft

TWs 2-No. (2-Cfs each)

D/S 1-No. (12-Cfs)

Status: Work at site is in progress.

.Release of Funds is awaited

Page 5: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

28 5532 Provision of Arrangements of

Sewerage for Aashiana Housing

Scheme, Lahore (LDP).

Approved 377.902 0.000 5.000 5.000 5.000 5.000 100% 5.000 1% Funds Released by FD on 06-08-18.

AA : 19-07-17.

48” dia from Aashiana-e-Iqbal to Barki

road 7000-Rft, Laying of forcemain

800mm o/d 8000-Rft & construction of

disposal station

Status: Scheme is caped. Reappropriation

of funds under process.29 5533 Improvement of Sewerage

System in Abadies Adjacent to

Saggian Road Shahdara, Lahore

(LDP).

Approved 299.990 0.000 40.000 40.000 30.000 19.310 64% 19.310 6% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

AA : 14-09-17

TS: 07.10.17

Start of work:: 20.2.18.

Sewer: 3.5 km, D/S 60 cfs

Status:Pipes stacked at site. Land

acquisition for disposal station in process.

Release of funds awaited.

30 5534 Development of schemes in

Nishtar town,Lahore

Approved 509.070 255.004 30.000 30.000 22.500 15.000 67% 270.004 53% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

AA: 23.02.17

TS: 27.02.17

Tender opening:06.4.17

Start of work:02.05.17

W/S: 111143 Rft

S/S: 99340 Rft

T/W: 9 No

F/P: 12 No

D/B: 02 No

Status: Status: Work at site is in progress.

Release of Funds is awaited.31 5535 Provision of Water Supply in

Shadipura, Qalandar Pura,

Tanveera Abad, etc. areas.

Approved 198.500 15.000 30.000 30.000 22.500 16.667 74% 31.667 16% Funds Released by FD on 06-08-18 & 10-

01-19.

AA 27.7.17.

TS: 11.09.17

TW:

Start of work:17.11.2017.

W/S

Start of work::04.07.2018

water supply pipe lines 315mm=7000-Rft,

250mm=8000-Rft, 200mm=13000-Rft,

160mm=22000-Rft 110mm=35000-Rft &

4-No. Tubwells 2-cfs capacity each

Status:

TW: 4 No completed.

WS: Work awarded and funds are

insufficient.

32 5536 Provision of Sewerage System

for sanda

kalan,Shaheenabad,Akbar town

& adjoining abadies

Islampura,Lahore (Phase-I)

Approved 200.000 30.000 30.000 30.000 22.500 15.000 67% 45.000 23% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

AA: 31.07.17.

TS: 18.10.17

Start of work:: 19.2.18.

Sewer : 9" i/d to 30" i/d = 26439 Rft

Forcemain = 651 Rft

Const of 2 No D/ S 20-Cfs each

Status: Work at site in progress. Land

acquisition process in progress

Page 6: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

33 5537 Providing / Fixing of

Hypochlorinators on 200 TWs of

WASA Lahore

Approved 20.000 0.000 20.000 20.000 15.000 9.958 66% 9.958 50% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

A.A: 26.09.2017

Hypochlorinators on 200 TWs

Staus : Work completed .Release of

Funds is awaited34 5538 Preparation of Feasibility Study

and Detailed Engineering

Design Regarding Sewerage &

Drainage System for Abadies

Located along Charrar Drain,

Lahore.

Approved 29.000 15.000 14.000 14.000 10.500 7.000 67% 22.000 76% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

AA :28-07-17.

Start of work:16.01.18

Feasibility study

Status

second revision of deliverables have been

submitted by consultant in the light of

comments by WASA. 35 5539 Rehabilitation / Improvement

and Construction of Drains in

Different Areas of Bhummay

Jugian Village in Drainage Sub-

Division North-II WASA LDA,

Lahore.

Approved 35.470 17.735 17.735 17.735 13.301 8.868 67% 26.603 75% Funds Released by FD on 06-08-18 &

20.11.2018 &10-01-19.

AA: 07.08.17

TS:09.08.17

Start of work:30.10.17

Rehab of drain: 3700 Rft

Const of drain: 2600 Rft

Status

Work at site is in progress. .Release of

Funds is awaitedTotal: WASA LDA 18,445.043 5,427.698 760.069 760.069 553.385 372.481 67% 5,800.179

PHA-Lahore #VALUE!

36 5540 Development of Green Corridor /

Recreational Area along Railway

Track from Shahdra to Raiwind,

Lahore.

Approved 721.859 0.000 17.000 17.000 16.667 16.667 100% 16.667 2% Funds Released by FD on 06-08-18.

Funds are not sufficient to offer tenders,

therefore, additional funds are required to

call the tenders.

37 5541 Establishment of New Park at

Sahlimar Town, Lahore (SDGs).

Approved 5.000 4.461 0.539 0.539 0.404 0.000 0% 4.461 89% Funds Released by FD on 20-11-18 & 10-

01-19.

38 5542 Establishment of New Park at

Akhter Estate Near Attari

Saroba, Lahore (SDGs).

Approved 5.000 4.431 0.569 0.569 0.427 0.000 0% 4.431 89% Funds Released by FD on 20-11-18 & 10-

01-19.

Work Stopped due to Stay Order.

39 5543 Establishment of New Park at

Mota Singh Bhara, Lahore

(SDGs)

Approved 7.000 5.773 1.227 1.227 0.920 0.000 0% 5.773 82% Funds Released by FD on 20-11-18 & 10-

01-19.

Stay order.

40 5544 Establishment of New Park at

Dev Kalan Khurd, Lahore

(SDGs).

Approved 7.000 5.673 1.327 1.327 0.995 0.396 40% 6.069 87% Funds Released by FD on 20-11-18 & 10-

01-19.

41 5545 Establishment of New Park at

Village Rorra Bogan Lahore

(SDGs)

Approved 7.000 5.860 1.140 1.140 0.855 0.298 35% 6.158 88% Funds Released by FD on 20-11-18 & 10-

01-19.

42 5546 Establishment of Park Village

Jandiala Lahore (SDGs)

Approved 7.000 5.940 1.060 1.060 0.795 0.435 55% 6.375 91% Funds Released by FD on 20-11-18 & 10-

01-19. Public Interference.

Stay order.

Page 7: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

43 5547 Establishment of Women &

Children Park Including Jogging

Track at D & E Blocks, Architect

Colony, Khayaban e Jinnah,

Lahore

Approved 15.000 7.500 7.500 7.500 5.625 0.000 0% 7.500 50% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

44 5548 Construction of Bab-e-Pakistan

Project

Approved 4,045.269 30.624 8.334 8.334 8.334 8.334 100% 38.958 1% Funds Released by FD on 06-08-18.

Funds are not sufficient to offer tenders,

therefore, additional funds are required to

call the tenders.45 5549 Installation of Fancy lights at

Multiple location in

Lahore(Egerton Road,Davis

Road,Empress Road,Ferozpur

Road,Khayaban-e-Jinnah Road

& Raiwind Road,Lahore

Approved 45.905 18.466 27.439 27.439 20.579 0.000 0% 18.466 40% Funds Released by FD on 20-11-18 & 10-

01-19.

46 5550 Development of Bird Aviary at

Bagh-e-Jinnah,Lahore

Approved 19.547 8.368 9.132 9.132 6.849 3.196 47% 11.564 59% Funds Released by FD on 20-11-18 & 10-

01-19.

Total: PHA-Lahore 4,885.580 97.096 75.267 75.267 62.450 29.326 47% 126.422

FDA

47 5551 Faisalabad Link Roads

Development Programme Links

No. 1,5,6,7,13,14,15 (10% Cost

Sharing by CDGF).

Approved 695.500 495.500 30.000 30.000 22.500 22.500 100% 518.000 74% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

48 5552 Construction of Service Road

from Abdullah Pur to Gatwala

along RB Canal, Faisalabad.

Approved 346.910 241.305 30.000 30.000 22.500 22.500 100% 263.805 76% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

49 5553 Construction of Under Passes At

Kashmir Bridge Along Canal

Faisalabad.

Approved 1,280.209 100.000 230.000 230.000 145.000 145.000 100% 245.000 19% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

50 5554 Establishment of Sports

Complex at Faisalabad City

(LDP)

Approved 487.500 50.000 50.000 50.000 37.500 37.619 100% 87.619 18% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

51 5555 Construction of PCC different

streets in Muhammad

abad,Haseeb Shaheed

colony,Chamanzar

colony,Satellite

colony,Himatpura, District

Faisalabad

Approved 15.000 7.500 7.500 7.500 5.625 4.055 72% 11.555 77% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

52 5556 Construction of PCC/Road and

boundary wall in Peoples Colony

No.2.

Approved 15.000 8.000 7.000 7.000 5.250 3.181 61% 11.181 75% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

53 5557 Construction of PCC/Road in

along Slach Kereyer

Approved 15.000 7.000 8.000 8.000 6.000 5.273 88% 12.273 82% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.54 5558 Construction of PCC/Road in

Bilal Nagar/ Ghusia Park/Ghous

Nagar

Approved 15.000 7.000 8.000 8.000 6.000 1.765 29% 8.765 58% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

Page 8: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

55 5559 Construction of PCC/Road and

boundary wall in Umar Black/Al-

Masoom Town

Approved 15.000 7.000 8.000 8.000 6.000 1.899 32% 8.899 59% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

56 5560 Rehabilitation/Improvement of

Road from around the Khatoon-e-

Janaat Hospital to Younis Town

& Ali Housing Satiana Road with

cross, Faisalabad in District

Faisalabad.

Approved 17.800 8.500 9.300 9.300 6.975 6.560 94% 15.060 85% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

57 5561 Rehabilitation/Improvement of

Road from Naazir Colony Main

Road to Ibn-e-Marrium Colony

with cross and Road from Boota

Chowk to Awais Nagar with

cross Faisalabad in District

Faisalabad.

Approved 17.400 8.000 9.400 9.400 7.050 2.130 30% 10.130 58% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.Work in progress.

58 5562 Rehabilitation/Improvement of

Road from Baghdadi Chowk to

Elahiabad with cross,

Faisalabad in District

Faisalabad.

Approved 16.950 8.000 8.950 8.950 6.713 6.713 100% 14.713 87% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

59 5563 Rehabilitation/Improvement of

Main Road from Ghoas Nagar to

Appalaabad with cross and

Road from Ahmed Nagar to

Malkhanwala Road with cross

Faisalabad in District

Faisalabad.

Approved 14.800 7.000 7.800 7.800 5.850 1.234 21% 8.234 56% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

60 5564 Rehabilitation/Improvement of

different Roads in Kartarywala,

Farooqabad, Abadi Tufail Bhatti

wali Faisalabad in District

Faisalabad.

Approved 21.000 8.000 13.000 13.000 9.750 4.698 48% 12.698 60% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

61 5565 Construction of

PCC/Improvement of

Roads/Streets in

Shamsabad,Amin park,Amin

town,Madina town,Saeed colony

etc,District Faisalabad

Approved 120.000 5.000 8.334 8.334 8.334 8.334 100% 13.334 11% Funds Released by FD on 06-08-18.

Work in progress.

Total: FDA 3,093.069 967.805 435.284 435.284 301.047 273.461 91% 1,241.266

WASA FDA

62 5566 Construction of Disposal Station

at Dawood Chowk.

Approved 80.000 46.485 33.515 33.515 25.136 0.000 0% 46.485 58% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Funds Rs. 23.515 million surrendered due

to some hindrance at site.

Possession of site has been regained on

11/04/2019 with the help of District

administration and work is in progress.

Rs. 8.379 million which is yet not

released, are being surrendered for its

utilization during next financial year 2019-

20.

Page 9: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

63 5567 Extension of Water Supply

Distribution Network to Unserved

Areas.

Approved 548.500 408.515 50.000 50.000 37.500 37.500 100% 446.015 81% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

64 5568 Extension of Water Resource

Faisalabad for City Phase II

(French Funded).

Approved 14,636.928 0.000 50.000 50.000 37.500 0.000 0% 0.000 0% Private land acquisition is in process.

Funds Released by FD on 06-08-18.&

65 5569 Augmentation of Water

Treatment Plant at Millat Town,

Faisalabad.

Approved 99.940 0.000 50.000 50.000 37.500 37.463 100% 37.463 37% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

66 5570 Laying of Sewerage Line Dia

9,12,15 in Usman Town, Usman

Park, Dar-ul-Ihsan Town,

Hussainabad, Rehman Colony,

Chirag Town, Babar Colony,

Tariq Colony, Jaggo Town,

Aagha Town, Sajad Town,

Bilawal Town, Khalid Colony etc.

(Laying of Sewer Line 9”,12”,15”

in Babar Colony, Amir Colony,

Sher Singh Wala, Rafiq Colony,

Bilawal Town, New Garden

Town, Ali Garden, Ansari

Colony, Chiragh Town, Sajjad

Town, Muneeb Town, Babar

Colony No. 2, Wali Pura, Khalid

Colony)

Approved 49.988 20.000 29.988 29.988 22.491 22.432 100% 42.432 85% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Mostly sewer lines laid in this scheme has

been made functional.

67 5571 Provision of New Sewerage

Network for Sewer Deficient

Areas/Replacement of Existing

Sewer Lines and Provision of

Water Supply Lines, District

Faisalabad.

Approved 99.800 30.000 25.000 25.000 18.750 18.718 100% 48.718 49% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Mostly sewer lines laid in this scheme has

been made functional.

68 5572 Provision/ Construction of Water

Supply Lines in District

Faisalabad

Approved 24.988 10.000 14.988 14.988 11.241 7.718 69% 17.718 71% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Funds required to complete the balance

work.69 5573 Provision of Funds for Sewerage

and Water Supply Scheme Un-

served Areas,Ghulam

Muhammad abad etc,

Faisalabad.

Approved 59.990 25.000 34.990 34.990 26.243 26.240 100% 51.240 85% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Mostly sewer lines laid in this scheme has

been made functional.

70 5574 Laying of Water Supply lines in

Different Area in Raza

abad,Gulberg etc,Faisalabad

Approved 19.970 7.500 12.470 12.470 9.353 7.220 77% 14.720 74% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Funds required to complete balance work.

71 5575 Construction of providing and

laying sewer line in Khalida

abad,D type colony

etc,Faisalabad

Approved 49.935 15.000 34.935 34.935 26.201 24.098 92% 39.098 78% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Mostly sewer lines laid in this scheme has

been made functional.

Page 10: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

72 5576 Construction / Replacement of

sewerage lines in District,

Faisalabad.

Approved 74.998 30.000 20.000 20.000 15.000 14.785 99% 44.785 60% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Mostly sewer lines laid in this scheme has

been made functional.Total: WASA FDA 15,745.037 592.500 355.886 355.886 266.915 196.174 73% 788.674

PHA-Faisalabad

73 5577 Improvement/Development of

Canal Park,Faisalabad

Approved 50.000 0.000 3.000 3.000 2.250 2.250 100% 2.250 5% Funds Released by FD on 20-11-18 & 10-

01-19.

PC-1 Submitted on = 03-02-2018

DDC Meeting Held on = 07-02-2018

A.A Issued on = 07-02-18

Tender Opened on = 08-05-2018

Total: PHA-Faisalabad 50.000 0.000 3.000 3.000 2.250 2.250 100% 2.250

GDA

74 5578 Construction of Road along Qila

Mian Singh Minor from Alam

Chowk to Gondlanwala Road to

Samanabad Chungi, District

Gujranwala.

Approved 398.511 292.100 50.000 50.000 37.500 25.731 69% 317.831 80% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

75 5579 Construction of Road along Both

Sides of Upper Chenab Canal

from G. T. Road Bridge (Haji

Murad Trust Eye Hospital) to

Byepass Near WAPDA Town,

Gujranwala.

Approved 263.941 99.950 50.000 50.000 37.500 34.154 91% 134.104 51% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

76 5580 Rehabilitation / Const. of Road

along Noorpur Distributry from

G. T. Road to Medical College

Gondlanwala Road, Gujranwala.

Approved 337.519 73.742 50.000 50.000 37.500 23.996 64% 97.738 29% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

77 5581 Rehabilitation / Const: of Katcha

Khiali Road from Karwan Chowk

to Sheikhupura Road and Zanib

Hospital Road from Sheikhupura

Road to Jinnah Road Including

Allied Branches, Gujranwala.

Approved 283.464 48.682 50.000 50.000 37.500 0.000 0% 48.682 17% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is held up due to court case.

Total: GDA 1,283.435 514.474 200.000 200.000 150.000 83.881 56% 598.355

WASA GDA

78 5582 Sewerage/Drainage at Jinnah

Road Raja Colony, Gulzar

Colony, Khokhaki,Satellite

Town, Pasrur Road, Model

Town, Islamabad,Kotli Rustam,

Hafizabad Road, Garjakh and

Allied Areas, Gujranwala.

Approved 376.300 65.000 55.000 55.000 41.250 41.250 100% 106.250 28% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

79 5583 Sewerage/Drainage System at

G.T Road, Green Town,

Kangniwala,Rana Colony

Asghar Colony, Peoples Colony

and allied areas, Gujranwala

Approved 386.500 99.999 98.000 98.000 73.500 51.766 70% 151.765 39% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Page 11: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

80 5584 Sewerage / Drainage and water

supply at Rakh Kikran Wali

Union Council No. 70, External

Khiali Shahpur Union Council

No. 71 , Kohlu Wala Union

Council No. 72 Gujranwala.

Approved 389.500 191.500 120.000 120.000 90.000 59.035 66% 250.535 64% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

81 5585 Sewerage/Drainage at

Eminabad Gharbi Union Council

No. 73, Gujranwala.

Approved 291.298 94.999 80.000 80.000 60.000 23.392 39% 118.391 41% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

82 5586 Sewerage/ Drainage Scheme

from Sialkot Bypass for

Aroop,Lohianwala & Mandiala

Warraich, Gujranwala.

Approved 396.200 114.999 78.000 78.000 58.500 58.500 100% 173.499 44% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

83 5587 Sewerage/Drainage at

Bhecopura, Madina Colony,

Jagna,Kacha Fatomand Road

and Allied Areas, Gujranwala.

Approved 192.200 89.999 36.111 36.111 27.083 27.083 100% 117.082 61% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in Progress.

Total: WASA GDA 2,031.998 656.496 467.111 467.111 350.333 261.026 75% 917.522

RDA

84 5588 Dualization of Link Road from

Tipu Road to Airport Road,

Rawalpindi.

Approved 323.312 230.124 35.000 52.500 43.750 26.250 60% 256.374 79% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.Rs. 17.50 million

Reappropriated(+) by DG RDA on 10-04-

19

Contractor: M/S M. Arif Construction.

Consultant: -

Work, Structure work & Road Furniture

completed. Tenders for S/I of street lights

is bieng advertized85 5589 Dualization of Qadeer Khan

Road from Islamabad Highway

(Missing Chowk) to Falcon

Complex, Rawalpindi (LDP).

Approved 197.494 0.000 35.000 35.000 26.250 21.718 83% 21.718 11% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

The scheme has been approved on

01.02.2018. Approval of Technical

Sanction is in process.

Page 12: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

86 5590 Construction / Widening &

Improvement of Dry Port Road

from Rahimabad Flyover at

Airport Road to Welfare

Complex via Chaklala Railway

Station & Shell Depot,

Rawalpindi.

Approved 300.000 50.000 50.000 50.000 37.500 10.950 29% 60.950 20% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work awarded on 24.11.2017 after

fulfilling all codal formalities. Revised PC-I

amounting to Rs. 474.822 Million is in

P&D for approval.

Work in Progress.

87 5591 Rehabilitaion of Airport Road

from Ammar Chowk to Karal

Chowk, Rawalpindi

Approved 502.010 414.510 30.000 12.500 5.000 4.901 98% 419.411 84% Original A.A = 27.02.2015

T.S = 09.03.2015

Contractor: M/S NLC.

Consultant: M/S New Vision.

Revised PC-I amounting to Rs. 485.707

million laying with P&DD for approval.

Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.Rs. 17.50 million

Reappropriated(-) by DG RDA on 10-04-

19

Total: RDA 1,322.816 694.634 150.000 150.000 112.500 63.819 57% 758.453

WASA RDA

88 5592 Replacement of Outlived Rusty

& Leaking Pipelines and

Extension of Distribution System

(New) in Leftover Area with

Allied Works in WASA's

Jurisdiction, Rawalpindi. (Gastro

Project Phase-II)

Approved 500.000 246.708 20.000 36.165 31.165 8.993 29% 255.701 51% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.Rs. 16.165

Reappropriated(+) by DG RDA on 19-03-

19.Bills of Rs.50.00 million is pending for

pre-audit due to non availability of dy.

Director Local Fund Audit.

89 5593 Comprehensive Sewerage

System in UC 74,75,76 & 77

(Phase-II)

Approved 348.630 134.998 20.000 40.000 35.000 11.835 34% 146.833 42% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.Rs. 20.000

Reappropriated(+) by DG RDA on 19-03-

19.Bills of Rs.8.00 million is pending for

pre-audit due to non availability of dy.

Director Local Fund Audit. Rs.12.00

million bill is under process with the

consultant90 5594 Augmantation of Girja Scheme

Based on Tubewells UC 91,

Rawalpindi.

Approved 60.000 29.998 30.002 30.002 22.502 1.330 6% 31.328 52% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

One tube well installed further source is

yet not available.91 5595 Comprehensive Water Supply

Scheme for Kakashan Colony,

Janjua Town, Sanjole Estate,

Mohammadi Colony, Khayaban-

e-Jinnah, Bank Colony and

Adjoining Areas.

Approved 357.850 0.000 35.000 26.250 17.500 0.000 0% 0.000 0% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.Rs. 8.750

Reappropriated(-) by DG RDA on 19-03-

19.Prequalification of firms recently

finalized

Page 13: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

92 5596 Water Supply & Sewerage Work

in Satellite Town,Muslim

town,Sadiqabad,Doke Kala

Khan,Doke

Kashmireyan,Khuram

Colony,Pandore & adjoining

areas , District Rawalpindi

Approved 199.196 30.000 60.000 60.000 60.000 28.416 47% 58.416 29% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19 & 25-04-19.

Bills of Rs.16.00 million is pending for pre-

audit due to non availability of dy. Director

Local Fund Audit.

93 5597 Installation of tube wells for

Mazharabad, Palm City Umar

Colony and Rehablitation of

Water supply Scheme of Yousaf

Colony, District Rawalpindi

Approved 19.810 0.971 18.839 4.710 0.000 0.000 #DIV/0! 0.971 5% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.Rs. 14.129

Reappropriated(-) by DG RDA on 19-03-

19.Trail bore failed. Tube well source yet

not available.

Capped and funds has been re-

appropriated to fast moving scheme.

94 5598 Installation of tubewells for clean

drinking water in

Chaklala,Chakra,Doke Munshi &

adjoining areas, District

Rawalpindi

Approved 29.884 9.989 19.895 19.895 14.921 9.165 61% 19.154 64% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress

95 5599 Providing / laying of sewer line in

Gharibabad, UC-79,

Rehmatabad, District Rawalpindi

Approved 22.000 9.982 12.018 3.004 0.000 0.000 #DIV/0! 9.982 45% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.Rs. 9.014

Reappropriated(-) by DG RDA on 19-03-

19.Scheme transferred through LDP. No

further sewer line is required as no proper

disposal available

Capped and funds has been re-

appropriated to fast moving scheme.

96 5600 Construction of Sewerage water

Treatment Plant at Race Course

Park,Rawalpindi

Approved 35.633 0.000 5.000 0.728 0.000 0.000 #DIV/0! 0.000 0% Funds Released by FD on 06-08-18.

Work is in progress.Rs. 4.272

Reappropriated(-) by DG RDA on 19-03-

19.Less funding and no through forward

for next year.

Capped and funds has been re-

appropriated to fast moving scheme.Total: WASA RDA 1,573.003 462.646 220.754 220.754 181.088 59.739 33% 522.385

MDA

97 5601 Widening and improvement of

road from MDA Chowk to Dera

Adda Chowk Multan (Dual

Carriageway).

Approved 574.719 498.523 30.000 30.000 22.500 22.500 100% 521.023 91% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

i) sub base and base course, A.B.C Side

drain completed on available site.

ii) Acquisition issue

iii) Funds required for completion.

The Scheme is expected to be completed

during next financial year due to non

allocation of total balance funds required

for completion in current financial year

Page 14: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

98 5602 Widening and Improvement of

Shamsabad & Eid Ghah Chowk

along with Construction of

Central Median from

Rashidabad Chowk to Jinnah

Chowk, Multan.

Approved 145.084 60.000 30.000 50.000 42.500 27.007 64% 87.007 60% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.Rs. 20.00

Reappropriated(+) by DG MDA on 26-03-

19

(i) sub base and base course, A.W.C

Gully grating completed on available site

(ii) Acquisition issues

(iii) Funds required for completion

(iv) Work not taken in hand due to funds

paucity.

The Scheme is expected to be completed

during next financial year due to non

allocation of total balance funds required

for completion in current financial year

99 5603 Widening and Improvement of

Lodhran Road from Sunar Mill to

BCG Chowk Multan

Approved 293.692 30.000 100.000 80.000 55.000 50.000 91% 80.000 27% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Acquisition and clearance of ROW

pending due to in sufficient funds..Rs.

20.00 Reappropriated(-) by DG MDA on

26-03-19100 5604 Construction of Northern Bypass

from LMQ Road to Bosan Road

(Dual Carriage Way) with

Service Road (Road Length 9.00

KM) (Phase-I).

Approved 761.369 703.220 58.149 58.149 43.612 0.000 0% 703.220 92% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

(i) Dual Carriageway, Minor Bridge &

Culverts etc completed

ii)Pending liabilities to be cleared after

issuence of Revised A.A from ECNIC

101 5605 Construction of Multan Southern

Bypass (Dual Carriageway)

along with Service Road from

LMQ Road to Bahawalpur

Chowk including Railway Over

Head Bridge Multan

Approved 1,787.051 1652.550 134.501 134.501 100.876 5.801 6% 1,658.351 93% Funds Released by FD on 06-08-18. & 20-

11-18 & 10-01-19.

i) Dual Carriageway, Railway Bridge &

Canal Bridge etc completed

(ii)Pending liabilities to be cleared after

issuence of Revised A.A from ECNIC

Total: MDA 3,561.915 2,944.293 352.650 352.650 264.488 105.308 40% 3,049.601

WASA MDA

102 5606 Augmentation /Improvement of

Disposal Station Multan Phase-II

Approved 591.000 265.990 35.000 35.000 26.250 26.250 100% 292.240 49% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress.

Addl: funds Rs.61.806 million is proposed

te be provided through intrasectoral

reappropriation.

Page 15: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

103 5607 Rehabilitation / Improvement of

Water Supply & Sewerage

System in UC 20, Multan.

Approved 61.510 17.125 44.385 44.385 33.289 15.500 47% 32.625 53% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.

Approved on 21.8.2017.

Rs.16.221 M surrenderd & proposed to

be intrasectoral reappropriation

104 5608 10 sewerage schemes by WASA

(Southern Punjab).

Approved 2,817.208 2561.858 40.000 40.000 30.000 30.000 100% 2,591.858 92% Funds Released by FD on 06-08-18 & 10-

01-19.

Work in progress.

Addl: funds Rs.215 million are needed i/c

Balance release of funds. Work in

progress.

105 5609 Replacement & laying of sewer

lines in UC 64 Piranghaib Multan

Approved 62.492 29.342 33.150 33.150 24.863 0.000 0% 29.342 47% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Upward revision discouraged. Rs.24.863

M proposed to be intrasectoral

reappropriation106 5610 Water Supply & Sewerage

Scheme Qasim Bela UC No 127

Multan

Approved 130.196 25.000 40.000 40.000 30.000 30.000 100% 55.000 42% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress

Approved on 21.8.2017.

Work stop by the order of High Court.

107 5611 Water Supply Scheme &

Sewerage Scheme Alamdi Sura

UC 53, Multan.

Approved 165.926 40.000 45.000 45.000 33.750 33.750 100% 73.750 44% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

work in progress

Approved on 21.8.2017.

Addl: funds Rs.30 million is proposed te

be provided through intrasectoral

reappropriation.108 5612 Sewerage Scheme UC 54

Multan

Approved 196.584 50.000 50.000 50.000 37.500 1.925 5% 51.925 26% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work in progress

Approved on 21.8.2017.

Work stop due to statusquo order by the

High Court. Rs. 35.575 M is surenderd &

proposed to be reappropriated 109 5613 Water Supply UC 52 Multan Approved 85.000 42.500 42.500 42.500 31.875 12.728 40% 55.228 65% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Work is in progress.

Approved on 21.8.2017.

Work in progress. Rs.15.147 M

surrenderd & proposed to be intrasectoral

reappropriationTotal: WASA MDA 4,109.916 3,031.815 330.035 330.035 247.527 150.153 61% 3,181.968

BDA

Page 16: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

110 5614 Construction of Shopping Plaza

and BDA Complex at

Bahawalpur City

Approved 300.000 0.000 33.333 33.333 25.000 0.000 0% 0.000 0% Funds Released by FD on 06-08-18 & 10-

01-19.

Amended Pc-1 has been submitted to DG

BDA for signature and will be forwarded

to competent fourm for approval .

111 5615 Construction of Road from One

Unit Chowk to Kanju Chowk

Bahawalpur City (L 1.6 Km)

Approved 127.311 17.000 40.000 40.000 30.000 29.948 100% 46.948 37% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Contractor payment are pending due to no

available of funds.112 5616 Construction of Waiting Shed at

Bahawalpur City

Approved 24.836 12.000 12.836 12.836 9.627 6.317 66% 18.317 74% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Scheme is physically competed

,contractor liablilty yet to be clear IPC

under process.Total: BDA 452.147 29.000 86.169 86.169 64.627 36.265 56% 65.265

FMDA

113 5617 Construction of metalled road

from ring road to Khar Fort

Munro road (By pass)

Approved 43.629 39.660 3.969 3.969 2.977 0.000 0% 39.660 91% Funds Released by FD on 20-11-18 & 10-

01-19.

Contractor has Resumed the Work and

scheme will be completed by 30th June

2018.

4th Qtr funds i.e. Rs. 0.992 not required.

Contractor has resumed the work and the

scheme will be completed on time.114 5618 Establishment of FMDA

Complex

Approved 75.403 11.688 5.000 5.000 5.000 0.345 7% 12.033 16% Funds Released by FD on 06-08-18.

Revise AA is under process

115 5619 Management of Solid Waste at

Fort Munro

Approved 71.620 10.646 5.000 5.000 5.000 0.367 7% 11.013 15% Funds Released by FD on 06-08-18.

Work in progress.

Revised AA is under process.

Rs. 4.633 M Funds surrendered for 2018-

19.116 5620 Extension of Mosque at Fort

Munro.

Approved 3.960 2.841 1.119 1.119 0.839 0.000 0% 2.841 72% Funds Released by FD on 20-11-18 & 10-

01-19.

Scheme Completed, Liability is yet to be

cleared.

4th Qtr funds i.e. Rs. 0.19 required.

117 5621 Development of Master Plan of

Fort Munro District D.G.Khan

Approved 31.020 19.056 11.964 11.964 8.973 0.000 0% 19.056 61% Funds Released by FD on 20-11-18 & 10-

01-19.

Rs. 8.973 M proposed for Surrendered.

4th Qtr funds i.e. Rs. 2.991 M not

required.

118 5622 Construction of Metalled Road

Adjacent Abadi Link Roads 20

KM with Drains

Approved 438.607 173.733 20.000 20.000 16.667 1.352 8% 175.085 40% Funds Released by FD on 06-08-18.

Contractor has Resumed the Work.

Rs. 8.5 M Proposed for Surrender.

4th Qtr Funds i.e. Rs. 3.333 M not

required.

Page 17: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

119 5623 Development of Parks,

Horticulture and Installation of

Solar Light Network at Fort

Munro.

Approved 99.000 72.544 10.000 10.000 7.500 0.000 0% 72.544 73% Funds Released by FD on 20-11-18 & 10-

01-19.

Contractor has Resumed the Work.

Rs. 4 M Proposed for Surrender.

4th Qtr Funds i.e. Rs. 2.5 M not required.

120 5624 Construction of Metalled Road

from N 70 KM No.74 to Fort

Munro via Langar Khandarsir

Length 5 Km

Approved 288.651 112.577 30.000 30.000 22.500 1.453 6% 114.030 40% Funds Released by FD on 06-08-18 & 20-

11-18 & 10-01-19.

Contractor has Resumed the Work.

Rs. 15 M Proposed for Surrender.

4th Qtr Funds i.e. Rs. 7.5 M not required.

121 5625 Rehabilitation of ring road Fort

Munro

Approved 33.500 26.124 7.376 7.376 5.532 0.000 0% 26.124 78% Funds Released by FD on 20-11-18 & 10-

01-19.

Contractor has Resumed the Work and

scheme will be completed by 30th June

2019.

4th Qtr Funds i.e. Rs. 1.844 M not

required.122 5626 Construction of Metaled Road

from Ring Road Tennis Hall to

Triman Lake Road

Approved 109.800 93.507 16.293 16.293 12.220 0.000 0% 93.507 85% Funds Released by FD on 20-11-18 & 10-

01-19.

Contractor has Resumed the Work and

scheme will be completed by 30th June

2019.

4th Qtr Funds i.e. Rs. 4.073 M required.Total: FMDA 1,195.190 562.376 110.721 110.721 87.208 3.517 4% 565.893

PHA Bahawalpur

123 5627 Construction of Park at Jail

Road (Mango Orchard)

Bahawalpur

Approved 63.407 23.520 39.887 39.887 29.915 10.704 36% 34.224 54% Date of T.S : 22-01-2018

Date of Tender : 12-02-18 electrical

Works, 22-3-2018 Horiclture Works, Civil

Work 16-4-2018

Date of start of Project : 12-2-2018

Date of Completion of Project: 30-6-2019

Financial progress. 27-11-18

Major components of Project: Brick Work,

Turbine,Walkways,Razor Wire,Playing

Units,Plantation

Physical Progress:

(i) Completed Part of Project: 80% Land

Requisistion, 70% Elecrical Work ,100%

Wapda Connection,20% walkways

(ii) Remaining parts of project: Brick

Work,Walkways,Razor Wire,Playing

Units,Plantation

Any other issue / bottleneck:

Total: PHA Bahawalpur 63.407 23.520 39.887 39.887 29.915 10.704 36% 34.224

Total: ON-GOING SCHEMES 65,393.587 19,620.841 4,609.000 4,809.000 3,405.359 1,954.006 57% 21,574.847

NEW SCHEMES

Regular

1 5628 Completion of schemes /

clearance of liabilities of un-

funded schemes for UD

Un-

Approved

10.000 0.000 10.000 3.489 0.000 0.000 0% 0.000 0% Rs. 6.511 million allocated by P&DD as a

Supplementary Grant dated 08-03-19.

Total: Regular 10.000 0.000 10.000 3.489 0.000 0.000 0% 0.000 0%

LDA

Page 18: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

2 5629 Construction of Structural Plan

Road from EXPO Center to

Bahria Town / Ring Road

(Parallel to Canal Bank Road),

Lahore

Approved 4,825.350 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

3 5630 Construction of Structural Plan

Road from EXPO Center to

Khayaban e Jinnah, Lahore.

Approved 2,982.996 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

4 5631 Improvement of Parking

Arrangements at Lahore Zoo,

Shahrah-e-Quaid-e-Azam,

Lahore.

Approved 63.946 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% P&D has been requested to allocate 100%

funds keeping in view the sensitivity of the

area.

Total: LDA 7,872.292 0.000 3.000 3.000 0.000 0.000 0% 0.000 0%

WASA LDA

5 5632 Lahore Water and Waste Water

Management Project -

Construction of Surface Water

Treatment Plant at BRBD canal

near ravi syphon.

Un-

Approved

23,131.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :

Surface water treatment plant of 100

cusec

Status: Scheme approved in PDWP

meeting held on 01-03-2019

6 5633 Lahore Water and Waste Water

Management Project -

Construction of Waste Water

Treatment Plant for Mehmood

Booti, Shahdara and Shadbagh

Area.

Un-

Approved

44,102.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :

211 MGD(390 cusec) waste water

treatment plants

Status: A new PC-II cost Rs 170 M is

approved in PDWP meeting. Consultants

hired, LOI issued on 26.04.2019.

7 5634 Feasibility, Detailed Engineering

Design,Preparation of PC-I for

wastewater treatment plants at

Mohlanwal and Ferozpur road

near Hudiara Drain, Lahore

Un-

Approved

100.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :

Feasibility study with necessary

deliverables

Status: Revised PC-II is sent to HUD on

21-01-19

8 5635 Laying of Conduit Sewer along

Alama Iqbal Drain Lahore.

Un-

Approved

2,074.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scope :

Sewer size: 12 to 72” (523,99 Rft)

Conduit size : (12,600 ft) Status: Pre-

PDWP meeting held on 19-03-19.

Corrected PC-I (Cost Rs 2682.503)

uploaded on SMDP. PDWP awaited9 5636 Construction of drain form Ring

Road to Shalimar escape

Channle Amjad Wali Ghaati

Lahore

Un-

Approved

80.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scheme approved in DDC meeting held

on 11.04.2019. A.A awaited.

10 5637 Provision of Clean Drinking

Water in 20 Pilot Areas of

Lahore.

Un-

Approved

3,800.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :

20 No, OHRs

HDPE pipes 75 mm to 300 mm

Control valves. Status: PC-I

(cost Rs 4454M) submitted to

HUD&PHED after corrections in light of

observations raised by design cell of HUD.

Page 19: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

11 5638 Improvement / Replacement of

Water Supply & Sewerage

System at Yasrab Colony,

Reheem Park and its Adjoining

Streets in Dohlanwal Sub-

Division, Lahore.

Un-

Approved

39.810 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% status: Scheme has been

approved.Tender opening on 24.04.2019

Total: WASA LDA 73,326.810 0.000 45.000 45.000 0.000 0.000 0% 0.000 0%

PHA-Lahore

12 5639 Improvement / Upgradation of

Irrigation System through

Sprinkler Sytem and Canal

Water at Different Parks of

Lahore.

Un-

Approved

930.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% PC-I is signed by Secretary, HUD&PHED.

Requested DG, PHA, Lahore to submit 10

copies on 02.01.2019.

Total: PHA-Lahore 930.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0%

WASA FDA

13 5640 Construction of Arterial Main,

Secondary and Distribution

Network in the Areas in the

Eastern Part of City.

Un-

Approved

4,993.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Final report of Master Plan received in this

week. PC-I has to be prepared in the light

of Master Plan and will be submitted

within week.

14 5641 Establishment of Project

Management Unit (PMU) for

Extension of Water Resources

for Faisalabad City Phase-II

Un-

Approved

89.180 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-I sent to HUD & PHE Department

Govt. of the Punjab, Lahore for

consideration and approval from DDSC.

Total: WASA FDA 5,082.180 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%

GDA

15 5642 Master Planning of Traffic

Management in Urban Area of

Gujranwala.

Un-

Approved

25.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II submitted & is in process.

Total: GDA 25.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0%

WASA GDA

16 5643 Updation of Feasibility study ,

detailed Engineering design and

preparation of PC-I for Waste

Water Treatment Plants in

Gujranwala

Un-

Approved

40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II returned by P&D to explore in PPP

Mode.

Total: WASA GDA 40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0%

PHA Gujranwala

17 5644 Establishment of Green belts

(Plantation) from Chanda Qila to

Alam Chowk western side by

pass, both sides Gujranwala.

Un-

Approved

30.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% DG.PHA Gujranwala has shown his

inability to execute the project. May be

dropped

Total: PHA Gujranwala 30.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%

RDA #VALUE!

18 5645 Land Acquisition for

Construction of Rawalpindi Ring

Road.

Un-

Approved

6,000.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I for land acqusition will be prepared

after Feasibility & Detalied Design by the

Consultants

Page 20: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

19 5646 Feasibility Study and Detailed

Design for Construction of

Rawalpindi Ring Road PC-II

(Revised).

Approved 90.975 0.000 10.000 10.000 5.000 0.000 0% 0.000 0% Revised PC-II amounting to

Rs. 90.975 cleared by PDWP in its

meeting held on 16.11.2018.A.A has been

issued on 12.12.2018. Funds amounting

to Rs. 5.00 Million has been released on

10.01.2019. EOIs from consultants is re-

advertised on 09.04.2019. Recived EOIs

will be open by CSC in its meeting held on

04.05.2019

20 5647 Dualization of Taxila to HMC

Farooqia Road (L=10.80),

Rawalpindi.

Un-

Approved

1,103.819 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for

approval, however the scheme is being

transfered to C&W Department vide letter

No.1(17)RO(ADP)P&D/2018 dated

31.12.2018.21 5648 Rehabilitation/Improvement of

Road from Chak Jalal Din to

Girja Road upto Akbar Chowk

(L=4 km), Rawalpindi.

Un-

Approved

119.934 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for

approval, however the scheme is being

transfered to C&W Department vide letter

No.1(17)RO(ADP)P&D/2018 dated

31.12.2018.22 5649 Widening/Improvement of Road

from HMC to Khanpur Road

alongwith Canal (L=6 km),

Rawalpindi.

Un-

Approved

222.765 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for

approval, however the scheme is being

transfered to C&W Department vide letter

No.1(17)RO(ADP)P&D/2018 dated

31.12.2018.23 5650 Rehabilitation/Improvement of

Road from Sangijani to Thata

Khalil (L=11.50), Rawalpindi.

Un-

Approved

223.207 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for

approval, however the scheme is being

transfered to C&W Department vide letter

No.1(17)RO(ADP)P&D/2018 dated

31.12.2018.24 5651 Rehabilitation/Improvement of

Road from Taxila to Thata Khalil

(L=10 km), Rawalpindi.

Un-

Approved

200.751 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for

approval, however the scheme is being

transfered to C&W Department vide letter

No.1(17)RO(ADP)P&D/2018 dated

31.12.2018.

Total: RDA 7,961.451 0.000 70.000 70.000 5.000 0.000 0% 0.000

WASA RDA

25 5652 Augmentation of Water Supply

of Rawalpindi based Chahan

Dam Source Particularly New

Areas Added in WASA's

Jurisdiction, Rawalpindi.

Approved 5,399.556 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Scheme Principally approved on 15

August 2018. AA issued on 27 December

2018 at a cost of Rs.5399.556 million. A

request has been sent to HUD & PHED

for release of Rs.50.00 million. Notification

of PMU has been issued

Page 21: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

26 5653 Feasibility Detailed design of

Sewage treatment plant Outfall

Sewer and Sewerage System of

Rawalpindi City

Un-

Approved

40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II of feasibility study on PPP mode

discussed in Pre-PDWP meeting held on

23 January 2019 and deferred due to

critical linkage with lai Nullah Expressway

Project . Feasibility study of lai nullah

expressway project yet not finalized by

RDA.

27 5654 Construction of Four (04)

Sewage Treatment Plants and

required Sewerage lines under

Phase-I (Rawal Lake and its

surroundings including the

Catchment Area, 36% GoPb

Share).

Un-

Approved

972.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% PC-I cleared from PDWP on 16.1.2019

and and also from CDWP. Municipal

Corporation, Islamabad is the executing

agency of this scheme.

Total: WASA RDA 6,411.556 0.000 105.000 105.000 0.000 0.000 0% 0.000

MDA

28 5655 Improvement of Southern Bye-

Pass Multan

Un-

Approved

300.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scheme is under approval in HUD&PHE

Total: MDA 300.000 0.000 10.000 10.000 0.000 0.000 0% 0.000

WASA MDA

29 5656 Replacement of Outlived Sewer

in Multan Phase II

Approved 2,129.370 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Technical & Financial proposals are

invited from the shortlisted consultants.

30 5657 Upgradation and Enviornmental

Improvement of Chungi No. 09

Dispsal Station Multan.

Approved 2,433.490 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Technical & Financial proposals are

invited from the shortlisted consultants.

Total: WASA MDA 4,562.860 0.000 15.000 15.000 0.000 0.000 0% 0.000

BDA #VALUE!

31 5658 Construction of Road from Civil

Hospital to Dera Bakha

Bahawalpur (11Km) Phase I

Approved 770.440 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Ammended Pc-1 submitted to DG BDA for

singature.

32 5659 Widening and Improvement of

Road from Kanju Chowk to Civil

Hospital Bahawalpur (L= 2.5

Km).

Un-

Approved

120.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Pc-1 submitted for Admin Approval to

Director Development office.

Total: BDA 890.440 0.000 15.000 15.000 0.000 0.000 0% 0.000

PHA D.G. Khan

33 5660 Development of Khosa Park and

Hussain Park in D.G. Khan City.

Approved 10.000 0.000 5.000 5.000 5.000 0.000 0% 0.000 0% Funds Released by P&DD on 20-02-19.

Tender process completed but work order

not issued due tofunds have not been

issued yet by the Finance Department and

are awaited for further proceeding.

34 5661 Beautification of DG Khan and

Taunsa City.

Approved 100.000 0.000 10.000 10.000 10.000 0.000 0% 0.000 0% Funds Released by P&DD on 20-02-19

Tender process completed but work order

not issued due tofunds have not been

issued yet by the Finance Department and

are awaited for further proceeding.

Total: PHA D.G. Khan 110.000 0.000 15.000 15.000 15.000 0.000 0% 0.000

Page 22: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

HUD & PHED

35 5662 Procurement of Machinery and

Equipment for newly Established

PHAs.

Un-

Approved

100.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%

Total: HUD & PHED 100.000 0.000 10.000 10.000 0.000 0.000 0% 0.000

PPP #VALUE!

36 5663 Construction of Outfall Sewer

and Sewage Treatment Plant

Rawalpindi.

Un-

Approved

20,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

37 5664 Providing and Installation of

Consumer Water Meters,

Rawalpindi.

Un-

Approved

1,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

38 5665 Providing and Installation of

Consumer Water Meters,

Multan.

Un-

Approved

600.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Concept brief prepared & sent to the PPP

Cell LHR

39 5666 Construction of Waste Water

Treatment Plant in Faisalabad

Un-

Approved

14,500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% PC-I submitted online as well as Hard

copies. Scheme was reflected in PPP

Mode. DANIDA Business Finance agreed

to funding Rs. 130.00 million Euro. NOC

was obtained from PPP Cell on 07-01-

2019 and PC-I submitted for approval.

40 5667 Extension & Rehabilitation of

Waste Water Treatment Plant

Chokera, Faisalabad.

Un-

Approved

25,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Un-Approved.

Concept Clearance Proposal is submitted

to HUD&PHED.

41 5668 Construction of Eastern

Wastewater Treatment Plant,

Faisalabad (Phase-II).

Un-

Approved

15,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Un-Approved.

Concept Clearance Proposal is submitted

to HUD&PHED.

42 5669 Providing and Installation of

Consumer Water Meters,

Faisalabad.

Un-

Approved

1,500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Concept Clearance Paper has been sent

to HUD & PHE Departament for approval.

43 5670 Construction of Waste Water

Treatment Plant near Main Drain

Gujranwala.

Un-

Approved

15,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

44 5671 Providing and Installation of

Consumer Water Meters,

Gujranwala.

Un-

Approved

500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

45 5672 Construction of New Link

Connecting Lahore Multan

Motorway with Multan Road

Lahore

Un-

Approved

8,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

46 5673 Construction of Waste Water

Treatment Plant at Babu Sabu

Lahore

Un-

Approved

52,527.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Chairman, P&D has desired that all

Projects of WASAs will be analyzed by the

PPP Cell of P&D and after issuance of

NOC by PPP Cell, the Project shall be

considered on other modes of exeuction.

Page 23: MONTHLY PROGRESS REPORT TILL END 30-04-2019 … · Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-01-19.Rs. 200.000

1 2 3 4 5 7 8 11 15 18 19 20 21 24

RemarksProvision

for 2018-19

Revised

Allocation

during

2018-19

Funds

Released

by F.D

Funds

utilized Upto

30-04-2019

%Utilization

on Releases

Total

Cummulative

Expenditure

Financial

Progress till

the current

Month (%)

ADP No Scheme Name Approved

Cost

Exp. Upto

June 18

Sr. No Approval

Status

47 5674 Construction of Waste Water

Treatment Plant including Waste

Water Channel at Multan.

Un-

Approved

33,752.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% PC-I prepared & resubmitted to the Govt.

for approval.

48 5675 Development of the New

Economic City (NEC).

Un-

Approved

10,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%

Total: PPP 197,379.000 0.000 13.000 13.000 0.000 0.000 0% 0.000

Total: NEW SCHEMES 305,031.589 0.000 391.000 384.489 20.000 0.000 0% 0.000

Grand Total(On-Going+New) 370,425.176 19,620.841 5,000.000 5,193.489 3,425.359 1,954.006 57% 21,574.847

Supplementary

WASA LDA

1 8827 Replacement of Tubewells (45

Nos.) WASA Lahore

Approved PDWP 2016/07/15

Lahore

Approved 586.522 545.820 0.000 6.511 0.000 0.000 0% 545.820 Rs. 6.511 million allocated by P&DD as a

Supplementary Grant dated 13-03-19.

Total: WASA LDA 586.522 545.820 0.000 6.511 0.000 0.000 #DIV/0! 545.820

WASA MDA

1 3544 Sewerage Scheme at UC 54, 55

& 56, District Multan

50.000 0.000 20.000 Funds Rs.20 million are needed . Tender

in process.

Total: WASA MDA 50.000 0.000 0.000 20.000 0.000 0.000 #DIV/0! 0.000

PHA D.G. Khan

1 3547 Establishment of Public Park at

Taunsa,district D.G.Khan

Approved 100.000 0.000 0.000 20.000 20.000 0.000 0% 0.000 Scheme Transferred from LG&CD on 25-

01-19.Funds Released by P&DD on 15-02-

19.Funds Released by FD on 25-04-19.

Tender process completed but work order

not issued due tofunds have not been

issued yet by the Finance Department and

are awaited for further proceeding.

2 3548 Renovation of Kamal Park and

City Park Taunsa

Approved 40.000 0.000 0.000 10.000 10.000 0.000 0% 0.000 Scheme Transferred from LG&CD on 25-

01-19.Funds Released by P&DD on 15-02-

19.Funds Released by FD on 25-04-19.

Tender process completed but work order

not issued due tofunds have not been

issued yet by the Finance Department and

are awaited for further proceeding.

Total: PHA D.G. Khan 140.000 0.000 0.000 30.000 30.000 0.000 0% 0.000

Total: Supplementary 776.522 545.820 0.000 56.511 30.000 0.000 0% 545.820

Grand Total(ADP+Suppl) 371,201.698 20,166.661 5,000.000 5,250.000 3,455.359 1,954.006 57% 22,120.667