monthly progress report till end 30-04-2019 … · approved 939.329 500.000 200.000 400.000 140.000...
TRANSCRIPT
Rs. in Million
1 2 3 4 5 7 8 11 15 18 19 20 21 24
ON-GOING SCHEMES
LDA
1 5505 Conservation of Energy through
Solar Power LED Street Lights in
Lahore
Approved 60.000 35.689 8.104 8.104 6.078 0.000 0% 35.689 59% Funds Released by FD on 06-08-18 &10-
01-19
2 5506 Establishment of Sports
Complex at Rakh Shahdra
Lahore (LDP)
Approved 605.766 299.990 50.000 50.000 37.500 25.000 67% 324.990 54% Funds Released by FD on 06-08-18 &
20.11.2018 & 10-01-19.
Pending liabilities to be cleared.
3 5507 Establishment of Sports
Complex in Sabzazar, Lahore
(LDP).
Approved 574.766 374.999 50.000 50.000 37.500 25.000 67% 399.999 70% Funds Released by FD on 06-08-18 &
20.11.2018 & 10-01-19.
4 5508 Establishment of Sports
Complex Singh Pura, Lahore
(LDP).
Approved 781.766 405.150 50.000 50.000 37.500 10.000 27% 415.150 53% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
5 5509 Establishment of Sports
Complex Model Bazar China
Scheme, Lahore (LDP).
Approved 490.127 369.957 50.000 50.000 37.500 25.000 67% 394.957 81% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
6 5510 Establishment of Sports
Complex in
Tajpura,Lahore(LDP).
Approved 543.358 174.974 50.000 50.000 37.500 15.000 40% 189.974 35% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
7 5511 Establishment of Sports
Complex Town Ship, Lahore
(LDP).
Approved 713.758 235.000 115.000 115.000 86.250 25.300 29% 260.300 36% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
8 5512 Establishment of Sports
Complex Canal Bank near EME
Society,Lahore(LDP).
Approved 781.358 224.948 100.000 100.000 75.000 3.070 4% 228.018 29% Funds Released by FD on 06-08-18 & 10-
01-19.
9 5513 Establishment of Sports
Complex Shalamar Lahore
(LDP).
Approved 688.766 274.936 50.000 50.000 37.500 0.000 0% 274.936 40% Funds Released by FD on 06-08-18 & 10-
01-19.
10 5514 Widening of Aik Moria
Pull,Lahore.
Approved 700.647 230.000 200.000 200.000 125.000 28.000 22% 258.000 37% Funds Released by FD on 06-08-18 & 10-
01-19.
11 5515 Construction of Flyover at
Shoukat Khanum Chowk along
Khayaban-e-Jinnah,Lahore
Approved 939.329 500.000 200.000 400.000 140.000 100.000 71% 600.000 64% Funds Released by FD on 06-08-18 & 10-
01-19.Rs. 200.000 million allocated by
P&DD as a Supplementary Grant dated 08-
03-19.12 5516 Construction of Kasur Sports
Complex, Khem Karan Road,
Kasur
Approved 542.118 464.685 77.433 77.433 58.075 38.717 67% 503.402 93% Funds Released by FD on 06-08-18 & 10-
01-19.
MONTHLY PROGRESS REPORT TILL END 30-04-2019
(DEVELOPMENT PROGRAMME 2018-19)
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
13 5517 Consultancy Services for
Preparation of Master Plan for
Water Supply, Sewerage,
Drainage and Ground Water
Management System for
Sheikhupura, Kasur & Nankana
Sahib Districts.
Approved 159.272 26.160 21.630 21.630 16.223 10.815 67% 36.975 23% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
Total: LDA 7,581.031 3,616.488 1,022.167 1,222.167 731.626 305.902 42% 3,922.390
WASA LDA
14 5518 Improvement of Water Supply
System in MA Johar Town &
Tajpura Zones of Lahore through
Zoning / Isolation, Installation of
Filtration Plants and 100%
Metering (Bulk, Distribution and
Consumer Levels), Lahore.
Approved 1,668.662 434.420 50.000 50.000 37.500 25.000 67% 459.420 28% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A.: 21.11.2014
Filtration plant:
T.S.: 08.05.2015 (FP)
Start of work:: 10.08.2015 Filtration
Plants (FP)
Start of Work: Aug-2015
Completion Date: 05.02.2016 (FP)
OHRs = 19-No.
Consumer Meters = 47,704
BFM = 80-No.
Arsenic Filtration Plant 94,
Bottling Plant
Status:
100% FP installed.
Remaining part:Revised PC-I cost Rs
1965.95 is sent to P&DD by HUD on
27/11/2018 .15 5519 Establishment of SCADA
System at Tubewells, Disposal &
Lift Stations for WASA Lahore.
Approved 697.200 15.703 8.334 8.334 8.334 4.056 49% 19.759 3% Funds Released by FD on 06-08-18.
A.A.: 02.01.2015
Revised PC-I cost Rs 897M is submitted
to Dep Sec(UD) on 25.10.18.
16 5520 Sewerage System from Larechs
Colony to Gulshan-e-Ravi,
Lahore.
Approved 6,928.113 265.446 5.000 5.000 3.750 0.000 0% 265.446 4% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A.: 13.04.2015
96" i/d Sewer = 16,180 m
60" i/d Sewer = 16,920 m
D/S = 350 Cfs.
Status:
PC-I will be submitted to Dy Sec HUD by
consultants after corrections by next
week.Reappropriation of Funds under
process.
17 5521 Changa Pani Programme
(Phase II) / Community
Participation Programme
Approved 329.240 309.240 20.000 20.000 15.000 10.000 67% 319.240 97% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A.: 19.01.16
T.S.: 21.01.16
Start of work:: 05.05.16
Completion date: 05.05.18
Work at site is
completed.Reappropriation of Funds
under process.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
18 5522 Installation of Filtration Plants on
105 No. Tubewells.
Approved 354.981 213.592 50.000 50.000 37.500 24.626 66% 238.218 67% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A.:21.07.16
T.S. :16-1-17
Start of work:16.6.17
F.P at 105 tubewells
Status: 105 Filtration plants are
operational. O&M in progress. 19 5523 Storm Water Drainage System
from Haji Camp to River Ravi via
Laxmi Chowk, McLeod Road,
Nabha Road, Chauburji and
Sham Nagar, Lahore.
Approved 2,400.000 975.000 200.000 200.000 130.000 100.000 77% 1,075.000 45% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A: 15.07.2016
TS: NA
Start of work::15-05-17
Precast Conduit 7(3.20 x 3.20 m) : 5,070
meters.
Lateral Drains (0.90 x 0.75 m)= 2,460 m
Status: PDWP meeting held on 12-02-19.
Revison of project was approved at the
cost of Rs. 3108.412. Land acquisition in
process. Rs 450 M is required for land
acquisition.20 5524 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Ravi
Road, Islampura and Adjoining
Abadies, Lahore.
Approved 494.326 344.326 30.000 30.000 22.500 15.000 67% 359.326 73% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A:15.07.16
TS: 22-11-16
Tender opening: 6.12.16
Start of work::26.12.16
Water Supply Lines:84,800Rft
Sewer:75,300Rft
Status: Work at site is in progress.
.Release of Funds is awaited21 5525 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Sheran
Wala Gate, Fazal Park and
Adjoining Abadies, Lahore.
Approved 501.080 208.192 30.000 30.000 22.500 12.955 58% 221.147 44% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A:15.07.16
TS:23-11-16
Tender opening:07.12.16
Re-tendering:17.12.16
Re-tendering :16-1-17
Start of work:14.2.17
Water Supply Lines:247,000Rft
Sewer:79,960Rft
Status: Work at site is in progress.
.Release of Funds is awaited22 5526 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Allama
Iqbal Town, Canal Park and
Adjoining Abadies, Lahore.
Approved 490.253 287.096 30.000 30.000 22.500 15.000 67% 302.096 62% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A: 15.07.16
TS: 14-11-16
Tender opening:07.12.16
Re-tendering:17.12.16
Re-tendering :16-1-17
Start of work:: 03.02.2017
Water Supply Lines:132,550Rft
Sewer:85,650Rft
Status: Work at site is in progress.
.Release of Funds is awaited
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
23 5527 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Shimla
Pahari and Adjoining Abadies
,Lahore.
Approved 507.166 310.000 30.000 30.000 22.500 15.000 67% 325.000 64% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A:15.07.16
TS:09.11.16
Tender opening :27-12-16
Start of work::6.02.2017
Water Supply Lines:138,268Rft
Sewer:104,753ft
TW: 1No. 2 cfs capacity
Filtration Plants:2
Sewage Pump: 25 cfs (one No.)
Status: Work at site is in progress.
.Release of Funds is awaited24 5528 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Chohan
Colony, Singh Pura and
Adjoining Abadies, Lahore.
Approved 499.331 400.358 30.000 30.000 22.500 11.666 52% 412.024 83% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A: 15.08.16
TS:09.11.16
Tender opening: 24.11.16
Water Supply Lines:128,710Rft
Sewer:77,250ft
TW: 3No. 2 cfs capacity
Status:Work at site is in
progress..Release of Funds is awaited25 5529 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Sabzazar
and Adjoining Abadies Lahore.
Approved 493.273 400.100 30.000 30.000 22.500 12.375 55% 412.475 84% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A:27.10.16
TS: 14.11.16
Tender opening:03.12.16
start of work:24.12.16
Water Supply Lines:123,370Rft
Sewer:96,062ft
Sewage Pump 1-No. 6-Cfs Capacity
Status:Work at site is in
progress..Release of Funds is awaited26 5530 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Shahdara
and Adjoining Abadies, Lahore.
Approved 618.782 320.782 30.000 30.000 22.500 15.000 67% 335.782 54% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A:26.10.16
TS:11.11.16
Tender opening:07.12.16
Re-tendering:17.12.16
Water Supply Lines:131,390Rft
Sewer:177,500ft
Disposal Station 1-No. 12-Cfs Capacity
Filtration Plant 12-No.
Status: Work at site is in progress.
.Release of Funds is awaited27 5531 Provision of Clean Drinking
Water, Sewerage System, PCC
and Allied Facilities in Ganj
Bazar, Gulistan Colony and
Adjoining Abadies, Lahore.
Approved 792.704 610.704 30.000 30.000 22.500 15.000 67% 625.704 79% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A: 06.10.16
T.S: 09.11.16
Tender opening:24.11.16
Water Supply Lines:233,300Rft
Sewer:115,800ft
TWs 2-No. (2-Cfs each)
D/S 1-No. (12-Cfs)
Status: Work at site is in progress.
.Release of Funds is awaited
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
28 5532 Provision of Arrangements of
Sewerage for Aashiana Housing
Scheme, Lahore (LDP).
Approved 377.902 0.000 5.000 5.000 5.000 5.000 100% 5.000 1% Funds Released by FD on 06-08-18.
AA : 19-07-17.
48” dia from Aashiana-e-Iqbal to Barki
road 7000-Rft, Laying of forcemain
800mm o/d 8000-Rft & construction of
disposal station
Status: Scheme is caped. Reappropriation
of funds under process.29 5533 Improvement of Sewerage
System in Abadies Adjacent to
Saggian Road Shahdara, Lahore
(LDP).
Approved 299.990 0.000 40.000 40.000 30.000 19.310 64% 19.310 6% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
AA : 14-09-17
TS: 07.10.17
Start of work:: 20.2.18.
Sewer: 3.5 km, D/S 60 cfs
Status:Pipes stacked at site. Land
acquisition for disposal station in process.
Release of funds awaited.
30 5534 Development of schemes in
Nishtar town,Lahore
Approved 509.070 255.004 30.000 30.000 22.500 15.000 67% 270.004 53% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
AA: 23.02.17
TS: 27.02.17
Tender opening:06.4.17
Start of work:02.05.17
W/S: 111143 Rft
S/S: 99340 Rft
T/W: 9 No
F/P: 12 No
D/B: 02 No
Status: Status: Work at site is in progress.
Release of Funds is awaited.31 5535 Provision of Water Supply in
Shadipura, Qalandar Pura,
Tanveera Abad, etc. areas.
Approved 198.500 15.000 30.000 30.000 22.500 16.667 74% 31.667 16% Funds Released by FD on 06-08-18 & 10-
01-19.
AA 27.7.17.
TS: 11.09.17
TW:
Start of work:17.11.2017.
W/S
Start of work::04.07.2018
water supply pipe lines 315mm=7000-Rft,
250mm=8000-Rft, 200mm=13000-Rft,
160mm=22000-Rft 110mm=35000-Rft &
4-No. Tubwells 2-cfs capacity each
Status:
TW: 4 No completed.
WS: Work awarded and funds are
insufficient.
32 5536 Provision of Sewerage System
for sanda
kalan,Shaheenabad,Akbar town
& adjoining abadies
Islampura,Lahore (Phase-I)
Approved 200.000 30.000 30.000 30.000 22.500 15.000 67% 45.000 23% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
AA: 31.07.17.
TS: 18.10.17
Start of work:: 19.2.18.
Sewer : 9" i/d to 30" i/d = 26439 Rft
Forcemain = 651 Rft
Const of 2 No D/ S 20-Cfs each
Status: Work at site in progress. Land
acquisition process in progress
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
33 5537 Providing / Fixing of
Hypochlorinators on 200 TWs of
WASA Lahore
Approved 20.000 0.000 20.000 20.000 15.000 9.958 66% 9.958 50% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
A.A: 26.09.2017
Hypochlorinators on 200 TWs
Staus : Work completed .Release of
Funds is awaited34 5538 Preparation of Feasibility Study
and Detailed Engineering
Design Regarding Sewerage &
Drainage System for Abadies
Located along Charrar Drain,
Lahore.
Approved 29.000 15.000 14.000 14.000 10.500 7.000 67% 22.000 76% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
AA :28-07-17.
Start of work:16.01.18
Feasibility study
Status
second revision of deliverables have been
submitted by consultant in the light of
comments by WASA. 35 5539 Rehabilitation / Improvement
and Construction of Drains in
Different Areas of Bhummay
Jugian Village in Drainage Sub-
Division North-II WASA LDA,
Lahore.
Approved 35.470 17.735 17.735 17.735 13.301 8.868 67% 26.603 75% Funds Released by FD on 06-08-18 &
20.11.2018 &10-01-19.
AA: 07.08.17
TS:09.08.17
Start of work:30.10.17
Rehab of drain: 3700 Rft
Const of drain: 2600 Rft
Status
Work at site is in progress. .Release of
Funds is awaitedTotal: WASA LDA 18,445.043 5,427.698 760.069 760.069 553.385 372.481 67% 5,800.179
PHA-Lahore #VALUE!
36 5540 Development of Green Corridor /
Recreational Area along Railway
Track from Shahdra to Raiwind,
Lahore.
Approved 721.859 0.000 17.000 17.000 16.667 16.667 100% 16.667 2% Funds Released by FD on 06-08-18.
Funds are not sufficient to offer tenders,
therefore, additional funds are required to
call the tenders.
37 5541 Establishment of New Park at
Sahlimar Town, Lahore (SDGs).
Approved 5.000 4.461 0.539 0.539 0.404 0.000 0% 4.461 89% Funds Released by FD on 20-11-18 & 10-
01-19.
38 5542 Establishment of New Park at
Akhter Estate Near Attari
Saroba, Lahore (SDGs).
Approved 5.000 4.431 0.569 0.569 0.427 0.000 0% 4.431 89% Funds Released by FD on 20-11-18 & 10-
01-19.
Work Stopped due to Stay Order.
39 5543 Establishment of New Park at
Mota Singh Bhara, Lahore
(SDGs)
Approved 7.000 5.773 1.227 1.227 0.920 0.000 0% 5.773 82% Funds Released by FD on 20-11-18 & 10-
01-19.
Stay order.
40 5544 Establishment of New Park at
Dev Kalan Khurd, Lahore
(SDGs).
Approved 7.000 5.673 1.327 1.327 0.995 0.396 40% 6.069 87% Funds Released by FD on 20-11-18 & 10-
01-19.
41 5545 Establishment of New Park at
Village Rorra Bogan Lahore
(SDGs)
Approved 7.000 5.860 1.140 1.140 0.855 0.298 35% 6.158 88% Funds Released by FD on 20-11-18 & 10-
01-19.
42 5546 Establishment of Park Village
Jandiala Lahore (SDGs)
Approved 7.000 5.940 1.060 1.060 0.795 0.435 55% 6.375 91% Funds Released by FD on 20-11-18 & 10-
01-19. Public Interference.
Stay order.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
43 5547 Establishment of Women &
Children Park Including Jogging
Track at D & E Blocks, Architect
Colony, Khayaban e Jinnah,
Lahore
Approved 15.000 7.500 7.500 7.500 5.625 0.000 0% 7.500 50% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
44 5548 Construction of Bab-e-Pakistan
Project
Approved 4,045.269 30.624 8.334 8.334 8.334 8.334 100% 38.958 1% Funds Released by FD on 06-08-18.
Funds are not sufficient to offer tenders,
therefore, additional funds are required to
call the tenders.45 5549 Installation of Fancy lights at
Multiple location in
Lahore(Egerton Road,Davis
Road,Empress Road,Ferozpur
Road,Khayaban-e-Jinnah Road
& Raiwind Road,Lahore
Approved 45.905 18.466 27.439 27.439 20.579 0.000 0% 18.466 40% Funds Released by FD on 20-11-18 & 10-
01-19.
46 5550 Development of Bird Aviary at
Bagh-e-Jinnah,Lahore
Approved 19.547 8.368 9.132 9.132 6.849 3.196 47% 11.564 59% Funds Released by FD on 20-11-18 & 10-
01-19.
Total: PHA-Lahore 4,885.580 97.096 75.267 75.267 62.450 29.326 47% 126.422
FDA
47 5551 Faisalabad Link Roads
Development Programme Links
No. 1,5,6,7,13,14,15 (10% Cost
Sharing by CDGF).
Approved 695.500 495.500 30.000 30.000 22.500 22.500 100% 518.000 74% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
48 5552 Construction of Service Road
from Abdullah Pur to Gatwala
along RB Canal, Faisalabad.
Approved 346.910 241.305 30.000 30.000 22.500 22.500 100% 263.805 76% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
49 5553 Construction of Under Passes At
Kashmir Bridge Along Canal
Faisalabad.
Approved 1,280.209 100.000 230.000 230.000 145.000 145.000 100% 245.000 19% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
50 5554 Establishment of Sports
Complex at Faisalabad City
(LDP)
Approved 487.500 50.000 50.000 50.000 37.500 37.619 100% 87.619 18% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
51 5555 Construction of PCC different
streets in Muhammad
abad,Haseeb Shaheed
colony,Chamanzar
colony,Satellite
colony,Himatpura, District
Faisalabad
Approved 15.000 7.500 7.500 7.500 5.625 4.055 72% 11.555 77% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
52 5556 Construction of PCC/Road and
boundary wall in Peoples Colony
No.2.
Approved 15.000 8.000 7.000 7.000 5.250 3.181 61% 11.181 75% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
53 5557 Construction of PCC/Road in
along Slach Kereyer
Approved 15.000 7.000 8.000 8.000 6.000 5.273 88% 12.273 82% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.54 5558 Construction of PCC/Road in
Bilal Nagar/ Ghusia Park/Ghous
Nagar
Approved 15.000 7.000 8.000 8.000 6.000 1.765 29% 8.765 58% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
55 5559 Construction of PCC/Road and
boundary wall in Umar Black/Al-
Masoom Town
Approved 15.000 7.000 8.000 8.000 6.000 1.899 32% 8.899 59% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
56 5560 Rehabilitation/Improvement of
Road from around the Khatoon-e-
Janaat Hospital to Younis Town
& Ali Housing Satiana Road with
cross, Faisalabad in District
Faisalabad.
Approved 17.800 8.500 9.300 9.300 6.975 6.560 94% 15.060 85% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
57 5561 Rehabilitation/Improvement of
Road from Naazir Colony Main
Road to Ibn-e-Marrium Colony
with cross and Road from Boota
Chowk to Awais Nagar with
cross Faisalabad in District
Faisalabad.
Approved 17.400 8.000 9.400 9.400 7.050 2.130 30% 10.130 58% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.Work in progress.
58 5562 Rehabilitation/Improvement of
Road from Baghdadi Chowk to
Elahiabad with cross,
Faisalabad in District
Faisalabad.
Approved 16.950 8.000 8.950 8.950 6.713 6.713 100% 14.713 87% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
59 5563 Rehabilitation/Improvement of
Main Road from Ghoas Nagar to
Appalaabad with cross and
Road from Ahmed Nagar to
Malkhanwala Road with cross
Faisalabad in District
Faisalabad.
Approved 14.800 7.000 7.800 7.800 5.850 1.234 21% 8.234 56% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
60 5564 Rehabilitation/Improvement of
different Roads in Kartarywala,
Farooqabad, Abadi Tufail Bhatti
wali Faisalabad in District
Faisalabad.
Approved 21.000 8.000 13.000 13.000 9.750 4.698 48% 12.698 60% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
61 5565 Construction of
PCC/Improvement of
Roads/Streets in
Shamsabad,Amin park,Amin
town,Madina town,Saeed colony
etc,District Faisalabad
Approved 120.000 5.000 8.334 8.334 8.334 8.334 100% 13.334 11% Funds Released by FD on 06-08-18.
Work in progress.
Total: FDA 3,093.069 967.805 435.284 435.284 301.047 273.461 91% 1,241.266
WASA FDA
62 5566 Construction of Disposal Station
at Dawood Chowk.
Approved 80.000 46.485 33.515 33.515 25.136 0.000 0% 46.485 58% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Funds Rs. 23.515 million surrendered due
to some hindrance at site.
Possession of site has been regained on
11/04/2019 with the help of District
administration and work is in progress.
Rs. 8.379 million which is yet not
released, are being surrendered for its
utilization during next financial year 2019-
20.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
63 5567 Extension of Water Supply
Distribution Network to Unserved
Areas.
Approved 548.500 408.515 50.000 50.000 37.500 37.500 100% 446.015 81% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
64 5568 Extension of Water Resource
Faisalabad for City Phase II
(French Funded).
Approved 14,636.928 0.000 50.000 50.000 37.500 0.000 0% 0.000 0% Private land acquisition is in process.
Funds Released by FD on 06-08-18.&
65 5569 Augmentation of Water
Treatment Plant at Millat Town,
Faisalabad.
Approved 99.940 0.000 50.000 50.000 37.500 37.463 100% 37.463 37% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
66 5570 Laying of Sewerage Line Dia
9,12,15 in Usman Town, Usman
Park, Dar-ul-Ihsan Town,
Hussainabad, Rehman Colony,
Chirag Town, Babar Colony,
Tariq Colony, Jaggo Town,
Aagha Town, Sajad Town,
Bilawal Town, Khalid Colony etc.
(Laying of Sewer Line 9”,12”,15”
in Babar Colony, Amir Colony,
Sher Singh Wala, Rafiq Colony,
Bilawal Town, New Garden
Town, Ali Garden, Ansari
Colony, Chiragh Town, Sajjad
Town, Muneeb Town, Babar
Colony No. 2, Wali Pura, Khalid
Colony)
Approved 49.988 20.000 29.988 29.988 22.491 22.432 100% 42.432 85% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Mostly sewer lines laid in this scheme has
been made functional.
67 5571 Provision of New Sewerage
Network for Sewer Deficient
Areas/Replacement of Existing
Sewer Lines and Provision of
Water Supply Lines, District
Faisalabad.
Approved 99.800 30.000 25.000 25.000 18.750 18.718 100% 48.718 49% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Mostly sewer lines laid in this scheme has
been made functional.
68 5572 Provision/ Construction of Water
Supply Lines in District
Faisalabad
Approved 24.988 10.000 14.988 14.988 11.241 7.718 69% 17.718 71% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Funds required to complete the balance
work.69 5573 Provision of Funds for Sewerage
and Water Supply Scheme Un-
served Areas,Ghulam
Muhammad abad etc,
Faisalabad.
Approved 59.990 25.000 34.990 34.990 26.243 26.240 100% 51.240 85% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Mostly sewer lines laid in this scheme has
been made functional.
70 5574 Laying of Water Supply lines in
Different Area in Raza
abad,Gulberg etc,Faisalabad
Approved 19.970 7.500 12.470 12.470 9.353 7.220 77% 14.720 74% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Funds required to complete balance work.
71 5575 Construction of providing and
laying sewer line in Khalida
abad,D type colony
etc,Faisalabad
Approved 49.935 15.000 34.935 34.935 26.201 24.098 92% 39.098 78% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Mostly sewer lines laid in this scheme has
been made functional.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
72 5576 Construction / Replacement of
sewerage lines in District,
Faisalabad.
Approved 74.998 30.000 20.000 20.000 15.000 14.785 99% 44.785 60% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Mostly sewer lines laid in this scheme has
been made functional.Total: WASA FDA 15,745.037 592.500 355.886 355.886 266.915 196.174 73% 788.674
PHA-Faisalabad
73 5577 Improvement/Development of
Canal Park,Faisalabad
Approved 50.000 0.000 3.000 3.000 2.250 2.250 100% 2.250 5% Funds Released by FD on 20-11-18 & 10-
01-19.
PC-1 Submitted on = 03-02-2018
DDC Meeting Held on = 07-02-2018
A.A Issued on = 07-02-18
Tender Opened on = 08-05-2018
Total: PHA-Faisalabad 50.000 0.000 3.000 3.000 2.250 2.250 100% 2.250
GDA
74 5578 Construction of Road along Qila
Mian Singh Minor from Alam
Chowk to Gondlanwala Road to
Samanabad Chungi, District
Gujranwala.
Approved 398.511 292.100 50.000 50.000 37.500 25.731 69% 317.831 80% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
75 5579 Construction of Road along Both
Sides of Upper Chenab Canal
from G. T. Road Bridge (Haji
Murad Trust Eye Hospital) to
Byepass Near WAPDA Town,
Gujranwala.
Approved 263.941 99.950 50.000 50.000 37.500 34.154 91% 134.104 51% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
76 5580 Rehabilitation / Const. of Road
along Noorpur Distributry from
G. T. Road to Medical College
Gondlanwala Road, Gujranwala.
Approved 337.519 73.742 50.000 50.000 37.500 23.996 64% 97.738 29% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
77 5581 Rehabilitation / Const: of Katcha
Khiali Road from Karwan Chowk
to Sheikhupura Road and Zanib
Hospital Road from Sheikhupura
Road to Jinnah Road Including
Allied Branches, Gujranwala.
Approved 283.464 48.682 50.000 50.000 37.500 0.000 0% 48.682 17% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is held up due to court case.
Total: GDA 1,283.435 514.474 200.000 200.000 150.000 83.881 56% 598.355
WASA GDA
78 5582 Sewerage/Drainage at Jinnah
Road Raja Colony, Gulzar
Colony, Khokhaki,Satellite
Town, Pasrur Road, Model
Town, Islamabad,Kotli Rustam,
Hafizabad Road, Garjakh and
Allied Areas, Gujranwala.
Approved 376.300 65.000 55.000 55.000 41.250 41.250 100% 106.250 28% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
79 5583 Sewerage/Drainage System at
G.T Road, Green Town,
Kangniwala,Rana Colony
Asghar Colony, Peoples Colony
and allied areas, Gujranwala
Approved 386.500 99.999 98.000 98.000 73.500 51.766 70% 151.765 39% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
80 5584 Sewerage / Drainage and water
supply at Rakh Kikran Wali
Union Council No. 70, External
Khiali Shahpur Union Council
No. 71 , Kohlu Wala Union
Council No. 72 Gujranwala.
Approved 389.500 191.500 120.000 120.000 90.000 59.035 66% 250.535 64% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
81 5585 Sewerage/Drainage at
Eminabad Gharbi Union Council
No. 73, Gujranwala.
Approved 291.298 94.999 80.000 80.000 60.000 23.392 39% 118.391 41% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
82 5586 Sewerage/ Drainage Scheme
from Sialkot Bypass for
Aroop,Lohianwala & Mandiala
Warraich, Gujranwala.
Approved 396.200 114.999 78.000 78.000 58.500 58.500 100% 173.499 44% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
83 5587 Sewerage/Drainage at
Bhecopura, Madina Colony,
Jagna,Kacha Fatomand Road
and Allied Areas, Gujranwala.
Approved 192.200 89.999 36.111 36.111 27.083 27.083 100% 117.082 61% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in Progress.
Total: WASA GDA 2,031.998 656.496 467.111 467.111 350.333 261.026 75% 917.522
RDA
84 5588 Dualization of Link Road from
Tipu Road to Airport Road,
Rawalpindi.
Approved 323.312 230.124 35.000 52.500 43.750 26.250 60% 256.374 79% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.Rs. 17.50 million
Reappropriated(+) by DG RDA on 10-04-
19
Contractor: M/S M. Arif Construction.
Consultant: -
Work, Structure work & Road Furniture
completed. Tenders for S/I of street lights
is bieng advertized85 5589 Dualization of Qadeer Khan
Road from Islamabad Highway
(Missing Chowk) to Falcon
Complex, Rawalpindi (LDP).
Approved 197.494 0.000 35.000 35.000 26.250 21.718 83% 21.718 11% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
The scheme has been approved on
01.02.2018. Approval of Technical
Sanction is in process.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
86 5590 Construction / Widening &
Improvement of Dry Port Road
from Rahimabad Flyover at
Airport Road to Welfare
Complex via Chaklala Railway
Station & Shell Depot,
Rawalpindi.
Approved 300.000 50.000 50.000 50.000 37.500 10.950 29% 60.950 20% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work awarded on 24.11.2017 after
fulfilling all codal formalities. Revised PC-I
amounting to Rs. 474.822 Million is in
P&D for approval.
Work in Progress.
87 5591 Rehabilitaion of Airport Road
from Ammar Chowk to Karal
Chowk, Rawalpindi
Approved 502.010 414.510 30.000 12.500 5.000 4.901 98% 419.411 84% Original A.A = 27.02.2015
T.S = 09.03.2015
Contractor: M/S NLC.
Consultant: M/S New Vision.
Revised PC-I amounting to Rs. 485.707
million laying with P&DD for approval.
Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.Rs. 17.50 million
Reappropriated(-) by DG RDA on 10-04-
19
Total: RDA 1,322.816 694.634 150.000 150.000 112.500 63.819 57% 758.453
WASA RDA
88 5592 Replacement of Outlived Rusty
& Leaking Pipelines and
Extension of Distribution System
(New) in Leftover Area with
Allied Works in WASA's
Jurisdiction, Rawalpindi. (Gastro
Project Phase-II)
Approved 500.000 246.708 20.000 36.165 31.165 8.993 29% 255.701 51% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.Rs. 16.165
Reappropriated(+) by DG RDA on 19-03-
19.Bills of Rs.50.00 million is pending for
pre-audit due to non availability of dy.
Director Local Fund Audit.
89 5593 Comprehensive Sewerage
System in UC 74,75,76 & 77
(Phase-II)
Approved 348.630 134.998 20.000 40.000 35.000 11.835 34% 146.833 42% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.Rs. 20.000
Reappropriated(+) by DG RDA on 19-03-
19.Bills of Rs.8.00 million is pending for
pre-audit due to non availability of dy.
Director Local Fund Audit. Rs.12.00
million bill is under process with the
consultant90 5594 Augmantation of Girja Scheme
Based on Tubewells UC 91,
Rawalpindi.
Approved 60.000 29.998 30.002 30.002 22.502 1.330 6% 31.328 52% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
One tube well installed further source is
yet not available.91 5595 Comprehensive Water Supply
Scheme for Kakashan Colony,
Janjua Town, Sanjole Estate,
Mohammadi Colony, Khayaban-
e-Jinnah, Bank Colony and
Adjoining Areas.
Approved 357.850 0.000 35.000 26.250 17.500 0.000 0% 0.000 0% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.Rs. 8.750
Reappropriated(-) by DG RDA on 19-03-
19.Prequalification of firms recently
finalized
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
92 5596 Water Supply & Sewerage Work
in Satellite Town,Muslim
town,Sadiqabad,Doke Kala
Khan,Doke
Kashmireyan,Khuram
Colony,Pandore & adjoining
areas , District Rawalpindi
Approved 199.196 30.000 60.000 60.000 60.000 28.416 47% 58.416 29% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19 & 25-04-19.
Bills of Rs.16.00 million is pending for pre-
audit due to non availability of dy. Director
Local Fund Audit.
93 5597 Installation of tube wells for
Mazharabad, Palm City Umar
Colony and Rehablitation of
Water supply Scheme of Yousaf
Colony, District Rawalpindi
Approved 19.810 0.971 18.839 4.710 0.000 0.000 #DIV/0! 0.971 5% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.Rs. 14.129
Reappropriated(-) by DG RDA on 19-03-
19.Trail bore failed. Tube well source yet
not available.
Capped and funds has been re-
appropriated to fast moving scheme.
94 5598 Installation of tubewells for clean
drinking water in
Chaklala,Chakra,Doke Munshi &
adjoining areas, District
Rawalpindi
Approved 29.884 9.989 19.895 19.895 14.921 9.165 61% 19.154 64% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress
95 5599 Providing / laying of sewer line in
Gharibabad, UC-79,
Rehmatabad, District Rawalpindi
Approved 22.000 9.982 12.018 3.004 0.000 0.000 #DIV/0! 9.982 45% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.Rs. 9.014
Reappropriated(-) by DG RDA on 19-03-
19.Scheme transferred through LDP. No
further sewer line is required as no proper
disposal available
Capped and funds has been re-
appropriated to fast moving scheme.
96 5600 Construction of Sewerage water
Treatment Plant at Race Course
Park,Rawalpindi
Approved 35.633 0.000 5.000 0.728 0.000 0.000 #DIV/0! 0.000 0% Funds Released by FD on 06-08-18.
Work is in progress.Rs. 4.272
Reappropriated(-) by DG RDA on 19-03-
19.Less funding and no through forward
for next year.
Capped and funds has been re-
appropriated to fast moving scheme.Total: WASA RDA 1,573.003 462.646 220.754 220.754 181.088 59.739 33% 522.385
MDA
97 5601 Widening and improvement of
road from MDA Chowk to Dera
Adda Chowk Multan (Dual
Carriageway).
Approved 574.719 498.523 30.000 30.000 22.500 22.500 100% 521.023 91% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
i) sub base and base course, A.B.C Side
drain completed on available site.
ii) Acquisition issue
iii) Funds required for completion.
The Scheme is expected to be completed
during next financial year due to non
allocation of total balance funds required
for completion in current financial year
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
98 5602 Widening and Improvement of
Shamsabad & Eid Ghah Chowk
along with Construction of
Central Median from
Rashidabad Chowk to Jinnah
Chowk, Multan.
Approved 145.084 60.000 30.000 50.000 42.500 27.007 64% 87.007 60% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.Rs. 20.00
Reappropriated(+) by DG MDA on 26-03-
19
(i) sub base and base course, A.W.C
Gully grating completed on available site
(ii) Acquisition issues
(iii) Funds required for completion
(iv) Work not taken in hand due to funds
paucity.
The Scheme is expected to be completed
during next financial year due to non
allocation of total balance funds required
for completion in current financial year
99 5603 Widening and Improvement of
Lodhran Road from Sunar Mill to
BCG Chowk Multan
Approved 293.692 30.000 100.000 80.000 55.000 50.000 91% 80.000 27% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Acquisition and clearance of ROW
pending due to in sufficient funds..Rs.
20.00 Reappropriated(-) by DG MDA on
26-03-19100 5604 Construction of Northern Bypass
from LMQ Road to Bosan Road
(Dual Carriage Way) with
Service Road (Road Length 9.00
KM) (Phase-I).
Approved 761.369 703.220 58.149 58.149 43.612 0.000 0% 703.220 92% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
(i) Dual Carriageway, Minor Bridge &
Culverts etc completed
ii)Pending liabilities to be cleared after
issuence of Revised A.A from ECNIC
101 5605 Construction of Multan Southern
Bypass (Dual Carriageway)
along with Service Road from
LMQ Road to Bahawalpur
Chowk including Railway Over
Head Bridge Multan
Approved 1,787.051 1652.550 134.501 134.501 100.876 5.801 6% 1,658.351 93% Funds Released by FD on 06-08-18. & 20-
11-18 & 10-01-19.
i) Dual Carriageway, Railway Bridge &
Canal Bridge etc completed
(ii)Pending liabilities to be cleared after
issuence of Revised A.A from ECNIC
Total: MDA 3,561.915 2,944.293 352.650 352.650 264.488 105.308 40% 3,049.601
WASA MDA
102 5606 Augmentation /Improvement of
Disposal Station Multan Phase-II
Approved 591.000 265.990 35.000 35.000 26.250 26.250 100% 292.240 49% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress.
Addl: funds Rs.61.806 million is proposed
te be provided through intrasectoral
reappropriation.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
103 5607 Rehabilitation / Improvement of
Water Supply & Sewerage
System in UC 20, Multan.
Approved 61.510 17.125 44.385 44.385 33.289 15.500 47% 32.625 53% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.
Approved on 21.8.2017.
Rs.16.221 M surrenderd & proposed to
be intrasectoral reappropriation
104 5608 10 sewerage schemes by WASA
(Southern Punjab).
Approved 2,817.208 2561.858 40.000 40.000 30.000 30.000 100% 2,591.858 92% Funds Released by FD on 06-08-18 & 10-
01-19.
Work in progress.
Addl: funds Rs.215 million are needed i/c
Balance release of funds. Work in
progress.
105 5609 Replacement & laying of sewer
lines in UC 64 Piranghaib Multan
Approved 62.492 29.342 33.150 33.150 24.863 0.000 0% 29.342 47% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Upward revision discouraged. Rs.24.863
M proposed to be intrasectoral
reappropriation106 5610 Water Supply & Sewerage
Scheme Qasim Bela UC No 127
Multan
Approved 130.196 25.000 40.000 40.000 30.000 30.000 100% 55.000 42% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress
Approved on 21.8.2017.
Work stop by the order of High Court.
107 5611 Water Supply Scheme &
Sewerage Scheme Alamdi Sura
UC 53, Multan.
Approved 165.926 40.000 45.000 45.000 33.750 33.750 100% 73.750 44% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
work in progress
Approved on 21.8.2017.
Addl: funds Rs.30 million is proposed te
be provided through intrasectoral
reappropriation.108 5612 Sewerage Scheme UC 54
Multan
Approved 196.584 50.000 50.000 50.000 37.500 1.925 5% 51.925 26% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work in progress
Approved on 21.8.2017.
Work stop due to statusquo order by the
High Court. Rs. 35.575 M is surenderd &
proposed to be reappropriated 109 5613 Water Supply UC 52 Multan Approved 85.000 42.500 42.500 42.500 31.875 12.728 40% 55.228 65% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Work is in progress.
Approved on 21.8.2017.
Work in progress. Rs.15.147 M
surrenderd & proposed to be intrasectoral
reappropriationTotal: WASA MDA 4,109.916 3,031.815 330.035 330.035 247.527 150.153 61% 3,181.968
BDA
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
110 5614 Construction of Shopping Plaza
and BDA Complex at
Bahawalpur City
Approved 300.000 0.000 33.333 33.333 25.000 0.000 0% 0.000 0% Funds Released by FD on 06-08-18 & 10-
01-19.
Amended Pc-1 has been submitted to DG
BDA for signature and will be forwarded
to competent fourm for approval .
111 5615 Construction of Road from One
Unit Chowk to Kanju Chowk
Bahawalpur City (L 1.6 Km)
Approved 127.311 17.000 40.000 40.000 30.000 29.948 100% 46.948 37% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Contractor payment are pending due to no
available of funds.112 5616 Construction of Waiting Shed at
Bahawalpur City
Approved 24.836 12.000 12.836 12.836 9.627 6.317 66% 18.317 74% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Scheme is physically competed
,contractor liablilty yet to be clear IPC
under process.Total: BDA 452.147 29.000 86.169 86.169 64.627 36.265 56% 65.265
FMDA
113 5617 Construction of metalled road
from ring road to Khar Fort
Munro road (By pass)
Approved 43.629 39.660 3.969 3.969 2.977 0.000 0% 39.660 91% Funds Released by FD on 20-11-18 & 10-
01-19.
Contractor has Resumed the Work and
scheme will be completed by 30th June
2018.
4th Qtr funds i.e. Rs. 0.992 not required.
Contractor has resumed the work and the
scheme will be completed on time.114 5618 Establishment of FMDA
Complex
Approved 75.403 11.688 5.000 5.000 5.000 0.345 7% 12.033 16% Funds Released by FD on 06-08-18.
Revise AA is under process
115 5619 Management of Solid Waste at
Fort Munro
Approved 71.620 10.646 5.000 5.000 5.000 0.367 7% 11.013 15% Funds Released by FD on 06-08-18.
Work in progress.
Revised AA is under process.
Rs. 4.633 M Funds surrendered for 2018-
19.116 5620 Extension of Mosque at Fort
Munro.
Approved 3.960 2.841 1.119 1.119 0.839 0.000 0% 2.841 72% Funds Released by FD on 20-11-18 & 10-
01-19.
Scheme Completed, Liability is yet to be
cleared.
4th Qtr funds i.e. Rs. 0.19 required.
117 5621 Development of Master Plan of
Fort Munro District D.G.Khan
Approved 31.020 19.056 11.964 11.964 8.973 0.000 0% 19.056 61% Funds Released by FD on 20-11-18 & 10-
01-19.
Rs. 8.973 M proposed for Surrendered.
4th Qtr funds i.e. Rs. 2.991 M not
required.
118 5622 Construction of Metalled Road
Adjacent Abadi Link Roads 20
KM with Drains
Approved 438.607 173.733 20.000 20.000 16.667 1.352 8% 175.085 40% Funds Released by FD on 06-08-18.
Contractor has Resumed the Work.
Rs. 8.5 M Proposed for Surrender.
4th Qtr Funds i.e. Rs. 3.333 M not
required.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
119 5623 Development of Parks,
Horticulture and Installation of
Solar Light Network at Fort
Munro.
Approved 99.000 72.544 10.000 10.000 7.500 0.000 0% 72.544 73% Funds Released by FD on 20-11-18 & 10-
01-19.
Contractor has Resumed the Work.
Rs. 4 M Proposed for Surrender.
4th Qtr Funds i.e. Rs. 2.5 M not required.
120 5624 Construction of Metalled Road
from N 70 KM No.74 to Fort
Munro via Langar Khandarsir
Length 5 Km
Approved 288.651 112.577 30.000 30.000 22.500 1.453 6% 114.030 40% Funds Released by FD on 06-08-18 & 20-
11-18 & 10-01-19.
Contractor has Resumed the Work.
Rs. 15 M Proposed for Surrender.
4th Qtr Funds i.e. Rs. 7.5 M not required.
121 5625 Rehabilitation of ring road Fort
Munro
Approved 33.500 26.124 7.376 7.376 5.532 0.000 0% 26.124 78% Funds Released by FD on 20-11-18 & 10-
01-19.
Contractor has Resumed the Work and
scheme will be completed by 30th June
2019.
4th Qtr Funds i.e. Rs. 1.844 M not
required.122 5626 Construction of Metaled Road
from Ring Road Tennis Hall to
Triman Lake Road
Approved 109.800 93.507 16.293 16.293 12.220 0.000 0% 93.507 85% Funds Released by FD on 20-11-18 & 10-
01-19.
Contractor has Resumed the Work and
scheme will be completed by 30th June
2019.
4th Qtr Funds i.e. Rs. 4.073 M required.Total: FMDA 1,195.190 562.376 110.721 110.721 87.208 3.517 4% 565.893
PHA Bahawalpur
123 5627 Construction of Park at Jail
Road (Mango Orchard)
Bahawalpur
Approved 63.407 23.520 39.887 39.887 29.915 10.704 36% 34.224 54% Date of T.S : 22-01-2018
Date of Tender : 12-02-18 electrical
Works, 22-3-2018 Horiclture Works, Civil
Work 16-4-2018
Date of start of Project : 12-2-2018
Date of Completion of Project: 30-6-2019
Financial progress. 27-11-18
Major components of Project: Brick Work,
Turbine,Walkways,Razor Wire,Playing
Units,Plantation
Physical Progress:
(i) Completed Part of Project: 80% Land
Requisistion, 70% Elecrical Work ,100%
Wapda Connection,20% walkways
(ii) Remaining parts of project: Brick
Work,Walkways,Razor Wire,Playing
Units,Plantation
Any other issue / bottleneck:
Total: PHA Bahawalpur 63.407 23.520 39.887 39.887 29.915 10.704 36% 34.224
Total: ON-GOING SCHEMES 65,393.587 19,620.841 4,609.000 4,809.000 3,405.359 1,954.006 57% 21,574.847
NEW SCHEMES
Regular
1 5628 Completion of schemes /
clearance of liabilities of un-
funded schemes for UD
Un-
Approved
10.000 0.000 10.000 3.489 0.000 0.000 0% 0.000 0% Rs. 6.511 million allocated by P&DD as a
Supplementary Grant dated 08-03-19.
Total: Regular 10.000 0.000 10.000 3.489 0.000 0.000 0% 0.000 0%
LDA
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
2 5629 Construction of Structural Plan
Road from EXPO Center to
Bahria Town / Ring Road
(Parallel to Canal Bank Road),
Lahore
Approved 4,825.350 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
3 5630 Construction of Structural Plan
Road from EXPO Center to
Khayaban e Jinnah, Lahore.
Approved 2,982.996 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
4 5631 Improvement of Parking
Arrangements at Lahore Zoo,
Shahrah-e-Quaid-e-Azam,
Lahore.
Approved 63.946 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% P&D has been requested to allocate 100%
funds keeping in view the sensitivity of the
area.
Total: LDA 7,872.292 0.000 3.000 3.000 0.000 0.000 0% 0.000 0%
WASA LDA
5 5632 Lahore Water and Waste Water
Management Project -
Construction of Surface Water
Treatment Plant at BRBD canal
near ravi syphon.
Un-
Approved
23,131.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :
Surface water treatment plant of 100
cusec
Status: Scheme approved in PDWP
meeting held on 01-03-2019
6 5633 Lahore Water and Waste Water
Management Project -
Construction of Waste Water
Treatment Plant for Mehmood
Booti, Shahdara and Shadbagh
Area.
Un-
Approved
44,102.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :
211 MGD(390 cusec) waste water
treatment plants
Status: A new PC-II cost Rs 170 M is
approved in PDWP meeting. Consultants
hired, LOI issued on 26.04.2019.
7 5634 Feasibility, Detailed Engineering
Design,Preparation of PC-I for
wastewater treatment plants at
Mohlanwal and Ferozpur road
near Hudiara Drain, Lahore
Un-
Approved
100.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :
Feasibility study with necessary
deliverables
Status: Revised PC-II is sent to HUD on
21-01-19
8 5635 Laying of Conduit Sewer along
Alama Iqbal Drain Lahore.
Un-
Approved
2,074.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scope :
Sewer size: 12 to 72” (523,99 Rft)
Conduit size : (12,600 ft) Status: Pre-
PDWP meeting held on 19-03-19.
Corrected PC-I (Cost Rs 2682.503)
uploaded on SMDP. PDWP awaited9 5636 Construction of drain form Ring
Road to Shalimar escape
Channle Amjad Wali Ghaati
Lahore
Un-
Approved
80.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scheme approved in DDC meeting held
on 11.04.2019. A.A awaited.
10 5637 Provision of Clean Drinking
Water in 20 Pilot Areas of
Lahore.
Un-
Approved
3,800.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Scope :
20 No, OHRs
HDPE pipes 75 mm to 300 mm
Control valves. Status: PC-I
(cost Rs 4454M) submitted to
HUD&PHED after corrections in light of
observations raised by design cell of HUD.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
11 5638 Improvement / Replacement of
Water Supply & Sewerage
System at Yasrab Colony,
Reheem Park and its Adjoining
Streets in Dohlanwal Sub-
Division, Lahore.
Un-
Approved
39.810 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% status: Scheme has been
approved.Tender opening on 24.04.2019
Total: WASA LDA 73,326.810 0.000 45.000 45.000 0.000 0.000 0% 0.000 0%
PHA-Lahore
12 5639 Improvement / Upgradation of
Irrigation System through
Sprinkler Sytem and Canal
Water at Different Parks of
Lahore.
Un-
Approved
930.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% PC-I is signed by Secretary, HUD&PHED.
Requested DG, PHA, Lahore to submit 10
copies on 02.01.2019.
Total: PHA-Lahore 930.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0%
WASA FDA
13 5640 Construction of Arterial Main,
Secondary and Distribution
Network in the Areas in the
Eastern Part of City.
Un-
Approved
4,993.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Final report of Master Plan received in this
week. PC-I has to be prepared in the light
of Master Plan and will be submitted
within week.
14 5641 Establishment of Project
Management Unit (PMU) for
Extension of Water Resources
for Faisalabad City Phase-II
Un-
Approved
89.180 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-I sent to HUD & PHE Department
Govt. of the Punjab, Lahore for
consideration and approval from DDSC.
Total: WASA FDA 5,082.180 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%
GDA
15 5642 Master Planning of Traffic
Management in Urban Area of
Gujranwala.
Un-
Approved
25.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II submitted & is in process.
Total: GDA 25.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0%
WASA GDA
16 5643 Updation of Feasibility study ,
detailed Engineering design and
preparation of PC-I for Waste
Water Treatment Plants in
Gujranwala
Un-
Approved
40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II returned by P&D to explore in PPP
Mode.
Total: WASA GDA 40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0%
PHA Gujranwala
17 5644 Establishment of Green belts
(Plantation) from Chanda Qila to
Alam Chowk western side by
pass, both sides Gujranwala.
Un-
Approved
30.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% DG.PHA Gujranwala has shown his
inability to execute the project. May be
dropped
Total: PHA Gujranwala 30.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%
RDA #VALUE!
18 5645 Land Acquisition for
Construction of Rawalpindi Ring
Road.
Un-
Approved
6,000.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I for land acqusition will be prepared
after Feasibility & Detalied Design by the
Consultants
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
19 5646 Feasibility Study and Detailed
Design for Construction of
Rawalpindi Ring Road PC-II
(Revised).
Approved 90.975 0.000 10.000 10.000 5.000 0.000 0% 0.000 0% Revised PC-II amounting to
Rs. 90.975 cleared by PDWP in its
meeting held on 16.11.2018.A.A has been
issued on 12.12.2018. Funds amounting
to Rs. 5.00 Million has been released on
10.01.2019. EOIs from consultants is re-
advertised on 09.04.2019. Recived EOIs
will be open by CSC in its meeting held on
04.05.2019
20 5647 Dualization of Taxila to HMC
Farooqia Road (L=10.80),
Rawalpindi.
Un-
Approved
1,103.819 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for
approval, however the scheme is being
transfered to C&W Department vide letter
No.1(17)RO(ADP)P&D/2018 dated
31.12.2018.21 5648 Rehabilitation/Improvement of
Road from Chak Jalal Din to
Girja Road upto Akbar Chowk
(L=4 km), Rawalpindi.
Un-
Approved
119.934 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for
approval, however the scheme is being
transfered to C&W Department vide letter
No.1(17)RO(ADP)P&D/2018 dated
31.12.2018.22 5649 Widening/Improvement of Road
from HMC to Khanpur Road
alongwith Canal (L=6 km),
Rawalpindi.
Un-
Approved
222.765 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for
approval, however the scheme is being
transfered to C&W Department vide letter
No.1(17)RO(ADP)P&D/2018 dated
31.12.2018.23 5650 Rehabilitation/Improvement of
Road from Sangijani to Thata
Khalil (L=11.50), Rawalpindi.
Un-
Approved
223.207 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for
approval, however the scheme is being
transfered to C&W Department vide letter
No.1(17)RO(ADP)P&D/2018 dated
31.12.2018.24 5651 Rehabilitation/Improvement of
Road from Taxila to Thata Khalil
(L=10 km), Rawalpindi.
Un-
Approved
200.751 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% PC-I is prepared and bieng submitted for
approval, however the scheme is being
transfered to C&W Department vide letter
No.1(17)RO(ADP)P&D/2018 dated
31.12.2018.
Total: RDA 7,961.451 0.000 70.000 70.000 5.000 0.000 0% 0.000
WASA RDA
25 5652 Augmentation of Water Supply
of Rawalpindi based Chahan
Dam Source Particularly New
Areas Added in WASA's
Jurisdiction, Rawalpindi.
Approved 5,399.556 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Scheme Principally approved on 15
August 2018. AA issued on 27 December
2018 at a cost of Rs.5399.556 million. A
request has been sent to HUD & PHED
for release of Rs.50.00 million. Notification
of PMU has been issued
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
26 5653 Feasibility Detailed design of
Sewage treatment plant Outfall
Sewer and Sewerage System of
Rawalpindi City
Un-
Approved
40.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% PC-II of feasibility study on PPP mode
discussed in Pre-PDWP meeting held on
23 January 2019 and deferred due to
critical linkage with lai Nullah Expressway
Project . Feasibility study of lai nullah
expressway project yet not finalized by
RDA.
27 5654 Construction of Four (04)
Sewage Treatment Plants and
required Sewerage lines under
Phase-I (Rawal Lake and its
surroundings including the
Catchment Area, 36% GoPb
Share).
Un-
Approved
972.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% PC-I cleared from PDWP on 16.1.2019
and and also from CDWP. Municipal
Corporation, Islamabad is the executing
agency of this scheme.
Total: WASA RDA 6,411.556 0.000 105.000 105.000 0.000 0.000 0% 0.000
MDA
28 5655 Improvement of Southern Bye-
Pass Multan
Un-
Approved
300.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Scheme is under approval in HUD&PHE
Total: MDA 300.000 0.000 10.000 10.000 0.000 0.000 0% 0.000
WASA MDA
29 5656 Replacement of Outlived Sewer
in Multan Phase II
Approved 2,129.370 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Technical & Financial proposals are
invited from the shortlisted consultants.
30 5657 Upgradation and Enviornmental
Improvement of Chungi No. 09
Dispsal Station Multan.
Approved 2,433.490 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Technical & Financial proposals are
invited from the shortlisted consultants.
Total: WASA MDA 4,562.860 0.000 15.000 15.000 0.000 0.000 0% 0.000
BDA #VALUE!
31 5658 Construction of Road from Civil
Hospital to Dera Bakha
Bahawalpur (11Km) Phase I
Approved 770.440 0.000 10.000 10.000 0.000 0.000 0% 0.000 0% Ammended Pc-1 submitted to DG BDA for
singature.
32 5659 Widening and Improvement of
Road from Kanju Chowk to Civil
Hospital Bahawalpur (L= 2.5
Km).
Un-
Approved
120.000 0.000 5.000 5.000 0.000 0.000 0% 0.000 0% Pc-1 submitted for Admin Approval to
Director Development office.
Total: BDA 890.440 0.000 15.000 15.000 0.000 0.000 0% 0.000
PHA D.G. Khan
33 5660 Development of Khosa Park and
Hussain Park in D.G. Khan City.
Approved 10.000 0.000 5.000 5.000 5.000 0.000 0% 0.000 0% Funds Released by P&DD on 20-02-19.
Tender process completed but work order
not issued due tofunds have not been
issued yet by the Finance Department and
are awaited for further proceeding.
34 5661 Beautification of DG Khan and
Taunsa City.
Approved 100.000 0.000 10.000 10.000 10.000 0.000 0% 0.000 0% Funds Released by P&DD on 20-02-19
Tender process completed but work order
not issued due tofunds have not been
issued yet by the Finance Department and
are awaited for further proceeding.
Total: PHA D.G. Khan 110.000 0.000 15.000 15.000 15.000 0.000 0% 0.000
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
HUD & PHED
35 5662 Procurement of Machinery and
Equipment for newly Established
PHAs.
Un-
Approved
100.000 0.000 10.000 10.000 0.000 0.000 0% 0.000 0%
Total: HUD & PHED 100.000 0.000 10.000 10.000 0.000 0.000 0% 0.000
PPP #VALUE!
36 5663 Construction of Outfall Sewer
and Sewage Treatment Plant
Rawalpindi.
Un-
Approved
20,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
37 5664 Providing and Installation of
Consumer Water Meters,
Rawalpindi.
Un-
Approved
1,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
38 5665 Providing and Installation of
Consumer Water Meters,
Multan.
Un-
Approved
600.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Concept brief prepared & sent to the PPP
Cell LHR
39 5666 Construction of Waste Water
Treatment Plant in Faisalabad
Un-
Approved
14,500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% PC-I submitted online as well as Hard
copies. Scheme was reflected in PPP
Mode. DANIDA Business Finance agreed
to funding Rs. 130.00 million Euro. NOC
was obtained from PPP Cell on 07-01-
2019 and PC-I submitted for approval.
40 5667 Extension & Rehabilitation of
Waste Water Treatment Plant
Chokera, Faisalabad.
Un-
Approved
25,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Un-Approved.
Concept Clearance Proposal is submitted
to HUD&PHED.
41 5668 Construction of Eastern
Wastewater Treatment Plant,
Faisalabad (Phase-II).
Un-
Approved
15,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Un-Approved.
Concept Clearance Proposal is submitted
to HUD&PHED.
42 5669 Providing and Installation of
Consumer Water Meters,
Faisalabad.
Un-
Approved
1,500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Concept Clearance Paper has been sent
to HUD & PHE Departament for approval.
43 5670 Construction of Waste Water
Treatment Plant near Main Drain
Gujranwala.
Un-
Approved
15,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
44 5671 Providing and Installation of
Consumer Water Meters,
Gujranwala.
Un-
Approved
500.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
45 5672 Construction of New Link
Connecting Lahore Multan
Motorway with Multan Road
Lahore
Un-
Approved
8,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
46 5673 Construction of Waste Water
Treatment Plant at Babu Sabu
Lahore
Un-
Approved
52,527.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% Chairman, P&D has desired that all
Projects of WASAs will be analyzed by the
PPP Cell of P&D and after issuance of
NOC by PPP Cell, the Project shall be
considered on other modes of exeuction.
1 2 3 4 5 7 8 11 15 18 19 20 21 24
RemarksProvision
for 2018-19
Revised
Allocation
during
2018-19
Funds
Released
by F.D
Funds
utilized Upto
30-04-2019
%Utilization
on Releases
Total
Cummulative
Expenditure
Financial
Progress till
the current
Month (%)
ADP No Scheme Name Approved
Cost
Exp. Upto
June 18
Sr. No Approval
Status
47 5674 Construction of Waste Water
Treatment Plant including Waste
Water Channel at Multan.
Un-
Approved
33,752.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0% PC-I prepared & resubmitted to the Govt.
for approval.
48 5675 Development of the New
Economic City (NEC).
Un-
Approved
10,000.000 0.000 1.000 1.000 0.000 0.000 0% 0.000 0%
Total: PPP 197,379.000 0.000 13.000 13.000 0.000 0.000 0% 0.000
Total: NEW SCHEMES 305,031.589 0.000 391.000 384.489 20.000 0.000 0% 0.000
Grand Total(On-Going+New) 370,425.176 19,620.841 5,000.000 5,193.489 3,425.359 1,954.006 57% 21,574.847
Supplementary
WASA LDA
1 8827 Replacement of Tubewells (45
Nos.) WASA Lahore
Approved PDWP 2016/07/15
Lahore
Approved 586.522 545.820 0.000 6.511 0.000 0.000 0% 545.820 Rs. 6.511 million allocated by P&DD as a
Supplementary Grant dated 13-03-19.
Total: WASA LDA 586.522 545.820 0.000 6.511 0.000 0.000 #DIV/0! 545.820
WASA MDA
1 3544 Sewerage Scheme at UC 54, 55
& 56, District Multan
50.000 0.000 20.000 Funds Rs.20 million are needed . Tender
in process.
Total: WASA MDA 50.000 0.000 0.000 20.000 0.000 0.000 #DIV/0! 0.000
PHA D.G. Khan
1 3547 Establishment of Public Park at
Taunsa,district D.G.Khan
Approved 100.000 0.000 0.000 20.000 20.000 0.000 0% 0.000 Scheme Transferred from LG&CD on 25-
01-19.Funds Released by P&DD on 15-02-
19.Funds Released by FD on 25-04-19.
Tender process completed but work order
not issued due tofunds have not been
issued yet by the Finance Department and
are awaited for further proceeding.
2 3548 Renovation of Kamal Park and
City Park Taunsa
Approved 40.000 0.000 0.000 10.000 10.000 0.000 0% 0.000 Scheme Transferred from LG&CD on 25-
01-19.Funds Released by P&DD on 15-02-
19.Funds Released by FD on 25-04-19.
Tender process completed but work order
not issued due tofunds have not been
issued yet by the Finance Department and
are awaited for further proceeding.
Total: PHA D.G. Khan 140.000 0.000 0.000 30.000 30.000 0.000 0% 0.000
Total: Supplementary 776.522 545.820 0.000 56.511 30.000 0.000 0% 545.820
Grand Total(ADP+Suppl) 371,201.698 20,166.661 5,000.000 5,250.000 3,455.359 1,954.006 57% 22,120.667