  • Prepared by: The Morganti Group, Inc.

    September, 2017

    Contract No.: AID-294-I-00-12-00002

    Task Order No.: AID-294-TO-15-00008

    Gaza-Construction of Reservoirs and Pumping Facilities Package I

    MONTHLY PROGRESS REPORT

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Construction Monthly Progress Report

    Reporting Period: September 1, 2017 September 30, 2017

    Contractor: The Morganti Group, Inc.

    DISCLAIMER "This report is made possible by the support of the American People through the United States Agency for International Development (USAID.) The contents of this report are the sole responsibility of The Morganti Group, Inc. and do not necessarily reflect the views of USAID or the United States Government."

    Contract No.: AID-294-I-00-12-00002

    Task Order No.: AID-294-TO-15-00008

    Gaza - Construction of Reservoirs and Pumping Facilities Package I

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Table of Contents

    ABBREVIATION ................................................................................................................................................... 1

    1. TASK ORDER OVERVIEW ........................................................................................................................... 2

    2. SCOPE OF WORK: ......................................................................................................................................... 3

    3. SAFETY .......................................................................................................................................................... 9

    4. ENVIRONMENTAL COMPLIANCE .......................................................................................................... 9

    5. TRAFFIC CONTROL MEASURES ............................................................................................................ 10

    6. RISK MANAGEMENT & MITIGATION MEASURES ............................................................................. 10

    7. COMMUNITY OUTREACH ....................................................................................................................... 10

    8. GENDER ACTION PLAN .......................................................................................................................... 10

    9. COORDINATION AND MEETINGS . ....................................................................................................... 11

    10. SITE VISITORS ............................................................................................................................................ 11

    11. PROGRESS AND SCHEDULING .............................................................................................................. 11

    12. INDICATORS............................................................................................................................................... 15

    13. WORKING / NON WORKING DAYS .................................................................................................... 15

    14. MATERIAL & EQUIPMENT DELIVERED TO SITE ............................................................................. 16

    15. SITE MEMOS ............................................................................................................................................... 16

    16. INSPECTION REQUESTS ......................................................................................................................... 17

    17. QUALITY CONTROL ................................................................................................................................. 18

    18. TESTS RESULTS: ........................................................................................................................................ 18

    19. SUBMITTALS . ............................................................................................................................................. 19

    20. REQUEST FOR INFORMATION . ............................................................................................................ 19

    21. TRANSMITTALS ........................................................................................................................................ 19

    22. TASK ORDER GENERAL STATISTICS . .................................................................................................. 31

    23. PAYMENTS . ............................................................................................................................................... 31

    24. VARIATION ORDERS ............................................................................................................................... 33

    25. VARIATION ORDER REQUESTS . ........................................................................................................... 33

    26. OBSTACLES AND CHALLENGES . .......................................................................................................... 38

    27. PROGRESS PHOTOS . ................................................................................................................................ 39

  • TO-15-00008 Construction Monthly Progress Report September 2017

    ANNEXES ............................................................................................................................................................ 59

    ANNEX A - MATERIALS- EQUIPMENT RECEIVING LOG . .................................................................................... 60 ANNEX B UPDATED SCHEDULE ...................................................................................................................... 63 ANNEX C - PROGRESS S - CURVE . ..................................................................................................................... 103 ANNEX D - ONE MONTH LOOK AHEAD . .......................................................................................................... 105 ANNEX E - INSPECTION REQUEST LOG ............................................................................................................ 112 ANNEX F - SUBMITTAL LOG ............................................................................................................................. 278 ANNEX G REQUEST FOR INFORMATION LOG . ............................................................................................... 337 ANNEX H - GEO-MIS DATA . ............................................................................................................................ 349 ANNEX I - RISK REGISTER LOG . ....................................................................................................................... 354 ANNEX J SITE MEMOS LOG (ENGINEER TO CONTRACTOR) .......................................................................... 357 ANNEX K SITE MEMOS LOG (CONTRACTOR TO ENGINEER) ......................................................................... 366 ANNEX L QC SUBMITTALS LOG...................................................................................................................... 371 ANNEX M ACCIDENT INVESTIGATION REPORT LOG . .................................................................................... 427 ANNEX N NONE COMPLIANCE REPORT LOG ...................................................................................... 429

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Abbreviation

    ACOTR Alternate Contracting Officer Technical Representative CD Calendar Day

    CE Chief Engineer

    CEng Contracts Engineer

    CMC Construction Management Contractor

    CMWU SAK SAK

    Coastal Municipalities Water Utility Saqqa and Khoudary General Contracting Co. Ltd.CO Contracting Officer

    COB Close of Business

    COP Chief of Party

    COR Contracting Officer Representative

    CQC Contractor Quality Control

    CQCP Contractor Quality Control Program

    CRMP Construction Risk Management Plan

    CV Curriculum Vita

    DCL District Civil Liaison

    FO Field Order

    HR High Risk

    HSE Health & Safety Engineer

    IQC Indefinite Quantities Contract

    LR Low Risk

    M Moderate Risk

    MH Medium-High Risk

    ML Medium-Low Risk

    MRR Material Receiving Report

    NCN Non Compliance Notice

    NUC Notice of Unsafe Conditions

    O&M Operation and Maintenance

    OSHA Occupational Safety and Health Act (both Federal and State)

    PA Palestinian Authority

    PCO Project Control Officer

    PIO Public Information Officer

    PM Project Manager

    PSU Program Support Unit

    PWA Palestinian Water Authority

    QA Quality Assurance

    QC Quality Control RE Resident Engineers

    RFI Request for Information

    RFTOP Request for Task Order Proposal

    SAK Saqqa and Khoudary

    SC Sup-Contractor

    SOP Standard Operating Procedure

    TMGI The Morganti group Inc.

    TO Task Order TOL Task Order Leader

    TOM Task Order Manager

    USAID United States Agency for International Development

    VO Variation Order

    VOR Variation Order Request

    WBG West Bank Gaza

    WBWD West Bank Water Department

    Page 1 of 430

    https://www.facebook.com/SAKCONTRACTING/?fref=nf

  • TO-15-00008 Construction Monthly Progress Report September 2017

    1. Task Order Overview 1.1. Description of the Task Order:

    Infrastructure in Gaza suffers from years of neglect and lack of investment. The USAID Mission

    Infrastructure Needs Program II (INP II) focuses on the rehabilitation and construction of roads,

    schools, and water & wastewater projects. The USAID objective is to help the Palestinian economy

    by improving Palestinians access to basic infrastructure and services.

    The objective of this Task Order is to construct two new water reservoirs, two new booster pump

    stations, and their associated supply and distribution pipelines, in order to improve distribution and

    increase access to clean drinking water to the population of Gaza, the first is Al Atatrah area located

    north of the Gaza Strip, the project at Al Atatrah area includes the construction of a 3800m3 ground

    reservoir that will be constructed in place of Al Atatrah abandoned elevated water tank deteriorated

    to be demolished, and also includes the supply and installation of a Skid Mounted Booster Pump

    Station and the supply and installation of a new Booster Pump Station connected to a new UPVC

    distribution network with an approximate total length of 6.3 KLM varying in diameter. The second

    area is Nuseirat, located in the heart of the Gaza Strip, the Nuseirat project includes the construction

    of a 3800m3 ground reservoir and a new Booster Pump Station connected to a new UPVC distribution

    network with an approximate total length of 5.2 KLM varying in diameter.

    1.2. Task Order Information

    Project Name: Gaza - Construction of Reservoirs and Pumping Facilities Package I

    Indefinite Quantity Contract No. AID-294-I-00-12-00002

    Task Order No. AID-294-TO-15-00008

    Award Date September 21, 2015

    NTP Date October 26, 2015

    Contract Value USD 10,275,276.16

    Modified Contact Value USD 10,425,276.16

    BOQ Line Item Amount USD 9,527,437.56

    Modified BOQ Line Item Amount USD 10,274,916.32

    Day Work Amount USD 747,838.60

    Modified Day Work Amount USD 150,359.84

    Start Date of Construction Activity January 21, 2016

    Contractual Period of Performance: 610 Calendar Days

    Modified Contractual Period of Per-formance:

    748 Calendar Days

    Contractual End Date: June 26, 2017

    Modified Contractual End Date: November 11, 2017

    Project Location (Area and governorate)

    The project is located in Gaza Strip (Al Atatrah & Nuseirat).

    1.3. Task Order Key Personnel: No. Name Position

    1 Samir Arafat Task Order Manager

    2 Swilam Mosalem Quality Control Manager

    3 Salim Abu Rafea' Safety and Environmental Compliance Officer

    4 Mohye Naeim Project Control Engineer

    5 Osama Abo Moussa Surveyor

    Page 2 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2. Scope of Work: 2.1. Project 1: Construction of Al Atatrah Reservoir and Pumping Facilities

    2.1.1. Project General Information Project Name: Al Atatrah Reservoir and Pumping Facilities

    Indefinite Quantity Contract No AID-294-I-00-12-00002

    Task Order No AID-294-TO-15-00008

    Award Date September 21, 2015

    NTP Date October 26, 2015

    Contract Value USD 4,698,583.73

    Modified Contract Value USD 5,009,628.38

    Start Date of Construction Activity January 21, 2016

    Contractual Period of Performance: 610 Calendar Days

    Modified Period of Performance 748 Calendar Days

    Contractual End Date: June 26, 2017

    Modified Contractual End Date: November 11, 2017

    Project Location (Area and governorate)

    Bait Lahia - North Governorate.

    2.1.2. Vantage photo:

    Page 3 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2.1.3. Project Key Map

    2.1.4. Project Description This project includes constructing a new water reservoir and booster pump station along with supply and distribution piping. Project elements consist of the following: 2.1.5. Statement of Work (SOW) The project consists of the following constructions

    A. Construction of Facilities 1. Al Atatrah Reservoir Construct new 3,800 m3 2. Al Atatrah Booster Pump Station Construct new. 3. Al Atatrah Skid Mounted Booster Pump Station Furnish & Install new. B. Construction of New Supply & Distribution Pipelines 1. Supply Line TS1 (280 mm x 0.386 km, 225 mm x 0.355 km and 160 mm x 1 km) 2. Supply Line TS2 (225 mm x 0.536 km) 3. Supply Line TS3 & TS2a (280 mm x 1.23 km and 225 mm x 0.747 km) 4. Distribution Line TD1 (355 mm x 0.156 km and 225 mm x 0.762 km) 5. Distribution Line TD2 (315 mm x 1.020 km)

    Al Atatrah Reservoir and Pumping Facilities

    Page 4 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2.1.6. Project Dashboard Status Contract Elapsed Time as of September 30, 2017 [%] 94.39 % *

    Planned Percentage of Completion through September 30, 2017 [%] 100 % **

    Actual Percentage of Completion through September 30, 2017 [%] 91.97 % **

    Float (Days) -140 ***

    * According to the approved Extension of Time variation order ** Actual and Planned percentages of work progress based on approved revised CPM schedule Novem-

    ber 30, 2016. *** The indicated total float is based on the updated approved CPM schedule November 30, 2016, this update reflects the actual project status up to September 30, 2017. The revised CPM schedule will be prepared and submitted for approval to reflect revised completion date " November 11, 2017" per contract modification No. 3.

    2.1.6.1. Progress Chart (September -2017)

    2.1.6.2. Time Elapsed (September - 2017)

    Remainig Construction Period

    5.61%

    Contract Elapsed Time

    94.39%

    Time Elapsed Up to September 30, 2017

    Remaining Construction Period Contract Elapsed Time

    Planned % of Completion Actual % of Completion

    100.00%

    91.97%

    Project 1 ATA Progress Status %

    Page 5 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2.2. Project 2: Construction of Nuseirat Reservoir and Pumping Facilities 2.2.1. Project 2 General Information

    Project Name: Nuseirat Reservoir and Pumping Facilities

    Indefinite Quantity Contract No AID-294-I-00-12-00002

    Task Order No AID-294-TO-15-00008

    Award Date September 21, 2015

    NTP Date October 26, 2015

    Contract Value USD 4,828,853.83

    Modified Contract Value USD 5,265,287.94

    Start Date of Construction Activity January 21, 2016

    Contractual Period of Performance: 610 Calendar Days

    Modified Period of Performance 748 Calendar Days

    Contractual End Date: June 26, 2017

    Modified Contractual End Date: November 11, 2017

    Project Location (Area and governorate) Nuseirat - Middle Governorate.

    2.2.2. Vantage photo:

    Page 6 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2.2.3. Project 2 Key Map

    2.2.4. Project Description This project includes constructing a new water reservoir and booster pump station along with supply and distribution piping. Project elements consist of the following:

    2.2.5. Statement of Work (SOW)

    A. Construction of Facilities 1. Nuseirat Reservoir Construct new 3,800 m3 2. Nuseirat Booster Pump Station Construct new.

    B. Construction of New Supply & Distribution Pipelines 1. Supply Line NS1 (315 mm x 1.872 km) 2. Supply Line NS2 (280 mm x 0.272 km) 3. Supply Line NS3 (110 mm x 0.133 km) 4. Distribution Line ND1 (500 mm x 0.207 km and 280 mm x 0.244 km ) 5. Distribution Line ND2 (500 mm x 0.227 km) 6. Distribution Line ND3 (355 mm x 0.551 km and 280 mm x 0.275 km) 7. Distribution Line ND4 (400 mm x 0.668 km and 315 mm x 0.659 km)

    Nuseirat Reservoir and Pumping Facilities

    Page 7 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    2.2.6. Project Dashboard Status Contract Elapsed Time as of September 30, 2017 [%] 94.38 % *

    Planned Percentage of Completion through September 30, 2017 [%] 100 % **

    Actual Percentage of Completion through September 30, 2017 [%] 90.25 % **

    Float (Days) -154 ***

    * The Extension of Time variation order is under process ** Actual and Planned percentages of work progress based on approved revised CPM schedule November

    30, 2016. *** The indicated total float is based on the updated approved CPM schedule November 30, 2016, this update reflects the actual project status up to September 30, 2017.

    The revised CPM schedule will be prepared and submitted for approval to reflect revised completion date " November 11, 2017" per contract modification No. 3.

    2.2.6.1. Progress Chart (September - 2017)

    2.2.6.2. Time Elapsed (September - 2017)

    Planned % of Completion Actual % of Completion

    100.00%

    90.25%

    Project 2 NUS Progress Status %

    5.61%Remaining Construction

    PeriodContract Elapsed

    Time 94.39%

    Time Elapsed Up to September 30, 2017

    Remaining Construction Period Contract Elapsed Time

    Page 8 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    3. Safety TMGI has submitted the updated safety Plan for the month of July, 2017 to the CMC on

    September 13, 2017 for review and approval and returned back with action A on September 17,

    2017. TMGI has submitted the updated safety Plan for the month of August, 2017 to the CMC

    on September 14, 2017 for review and approval and returned back with action A on September

    17, 2017.Safety plan for month of September 2017 will be submitted during the next month report

    period.

    Moreover, safety plan will be updated on monthly basis.

    3.1. Safety Toolbox Meetings 3.1.1. Project 1 (ATA)

    Three safety toolboxes talk with subcontractor staff and labors were conducted as shown in

    the below table:

    Date of Meeting

    Tool Box No. Location Description

    September 7, 2017 STBM-15-00008-ATA-046 ATA Reservoir yard Electrical Works (Connections between VFD & MCC & PLC)

    September 10, 2017 STBM-15-00008-ATA-047 ATA Reservoir yard Working Inside Reservoir (Installation Works for Launder)

    September 17, 2017 STBM-15-00008-ATA-048 ATA Reservoir yard Confined space (working inside reservoir) internal painting works

    3.1.2. Project 2 (NUS) No toolbox meeting was conducted during this reporting period.

    3.2. Accident Status 3.2.1. Project 1 (ATA)

    No accidents were reported during this reporting period.

    3.2.2. Project 2 (NUS) No accidents were reported during this reporting period.

    3.3. Notice of Unsafe Condition 3.3.1. Project 1 (ATA)

    Zero notice was issued during this reporting period.

    3.3.2. Project 2 (NUS) Zero notice was issued during this reporting period.

    4. Environmental Compliance TMGI has submitted the updated Environmental Monitoring & Mitigation Plan (EMMP) for the

    months of June and July, 2017 to CMC on September 16, 2017 for review and approval and

    returned back with action A on September 17, 2017.

    Environmental Mitigation Plan (EMMP) update for month of August was not submitted, update

    will be submitted during the next month report period.

    TMGI will update the Environmental Monitoring and Mitigation Plan on monthly basis.

    Page 9 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    4.1.1. Project 1 (ATA) Environmental compliance checklist for the month of July 2017 was received on August 16,

    2017, TMGI work on closing it, and it will be submitted during the next reporting period.

    Environmental compliance checklist for the month of August 2017 was received on Septem-

    ber 26, 2017, TMGI work on closing it, and it will be submitted during the next reporting

    period.

    4.1.2. Project 2 (NUS) Environmental compliance checklist for the month of July 2017 was received on August 16,

    2017, TMGI work on closing it, and it will be submitted during the next reporting period.

    Environmental compliance checklist for the month of August 2017 was received on Septem-

    ber 26, 2017, TMGI work on closing it, and it will be submitted during the next reporting

    period.

    5. Traffic Control Measures TMGI implemented the approved traffic plan on reservoir site according to the approved sub-

    mittals and shall be updated upon condition changes.

    5.1.1. Project 1 (ATA) No update on Al Atatrah pipeline traffic plan during this reporting period.

    Traffic signs and barriers are installed onsite according to approved TCP.

    5.1.2. Project 2 (NUS) No update on Nuseirat pipeline traffic plan during this reporting period.

    Traffic signs and barriers are installed onsite according to approved TCP.

    6. Risk Management & Mitigation Measures TMGI has submitted the updated Construction Risk Management Program (CRMP) for the

    months of June and July to CMC on September 13, 2017 for review and approval and

    returned back with action A on September 14, 2017.

    Construction Risk Management Program (CRMP) update for the month of August was not

    submitted, update will be submitted during the next month report period.

    TMGI will update the Risk Management Program on monthly basis.

    Tough restrictions on travel permits between Gaza and West Bank and borders closure are project

    risks concerns (Closure and GRAMM system impede delivery of project materials).

    For more information, please refer to Annex I.

    7. Community Outreach 7.1.1. Project 1 (ATA)

    None issued during this reporting period.

    7.1.2. Project 2 (NUS) None issued during this reporting period.

    8. Gender Action Plan Morganti employed one female Office manager. The Subcontractor SAK also hired a female office

    engineer. Morganti provided sanitary facilities and facilitated the sites for females.

    * No new employments during this reporting period.

    Page 10 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    9. Coordination and Meetings

    Two meetings were held during the month of September as below:

    Coordination Meeting

    Date Attendees Subject Description Location

    September 5, 2017

    BV, TMGI & SAK

    Coordination Meeting No. 097

    To Discuss required of startup

    GAZII AL-Berkah office

    September 19, 2017

    USAID, BV & TMGI

    Coordination Meeting No. 98

    To Disscus Pending Issue BV Main Office, Ramallah

    Several internal meetings were held by Morganti in the main office for safety orientation and forthe progress of construction and preparation works.

    10. Site Visitors

    The following table shows the site visitors during this reporting period:

    Date Time Representative Representing Remarks

    Project 1 (ATA)

    September 20, 2017 04:30 PM Mr. Ghassan Alami TMGI Reservoir Yard

    September 24, 2017 11:50 AM Mr. Peter Lister Black & Veatch Reservoir Yard

    Project 2 (NUS)

    September 6, 2017 11:00 AM Eng. Amran El-Kharouby USAID Reservoir Yard

    September 20, 2017 03:50 PM Mr. Ghassan Alami TMGI Reservoir Yard

    September 24, 2017 03:00 PM Mr. Peter Lister Black & Veatch Reservoir Yard

    September 24, 2017 03:00 PM Mr. Ghassan Alami TMGI Reservoir Yard

    11. Progress and Scheduling

    The Construction phase started on January 21, 2016, preconstruction submittals were closed. Fur-thermore, Materials and Shop drawings submittals are ongoing. TMGI has submitted the Updated CPM Construction Schedule August 31, 2017 Rev. A on Sep-tember 13, 2017 and returned back with action B on September 20, 2017. Furthermore, Materials, Shop drawings and as built drawing submittals are ongoing. TMGI will update the CPM Schedule on monthly basis For more details, please refer to Annex B

    11.1. Activities During This Reporting Period 11.1.1. Project 1 (ATA)

    11.1.1.1. Reservoir Yard 11.1.1.1.1. Continue preparation and submit the construction submittals. 11.1.1.1.2. Continue backfilling works around the facilities buildings for leveling the

    site. 11.1.1.1.3. Applying the external paint coat for the reservoir walls. 11.1.1.1.4. Preparing, welding and installing the stainless-steel launder for the reser-

    voir

    11.1.1.1.5. Installing the float switch and intrusion switch. 11.1.1.1.6. Installing the fire alarm system at the facilities buildings. 11.1.1.1.7. Installing connections between the VFD, PLC & MCC.

    Page 11 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    11.1.1.1.8. Continue conducting training courses 11.1.1.1.9. Installing electrical and mechanical works at the pump station and the

    diesel generator

    11.1.1.1.10. Preparing, welding, connecting and installing the skid mounted pump. 11.1.1.1.11. Installing the instrument devices at the booster station and the reservoir. 11.1.1.1.12. Installing the stainless-steel ladders inside the reservoir 11.1.1.1.13. Applying the internal coating at the reservoir by using the cementitious

    material Nito Cote CM210

    11.1.1.1.14. Continue painting works for all exposed steel pipes at booster station and the reservoir.

    11.1.1.1.15. Casting concrete for base mounted elbow support. 11.1.1.1.16. Fixing/installing mechanicals works for the skid mounted pump 11.1.1.1.17. Conducting a walkthrough for road works outside the reservoir yard in

    the presence of the CMWU

    11.1.1.1.18. Insulation work for reservoir foundation 11.1.1.1.19. Installing the external ladder of the reservoir 11.1.1.1.20. Continue leveling & compaction of the concrete sidewalk around the

    booster pump station, facilities building and reservoir.

    11.1.1.1.21. Continue formwork, steel reinforcement and concrete casting for side-walk around the booster pump station, facilities building and reservoir

    11.1.1.1.22. Complete installing of the booster station shed. 11.1.1.1.23. Filling the construction joint for reservoir floor by using Thioflex 600

    GG

    11.1.1.1.24. Continue electrical work for RIO panel at the disinfection building (ca-bles connection)

    11.1.1.1.25. Coordination with the CMWU & PWA. 11.1.1.1.26. Continue procurement orders for construction requirements and ABC

    material.

    11.1.1.2. New construction of supply & distribution Pipelines

    11.1.1.2.1. Cleaning and flushing works for the following pipelines. TS1, TS2, TS2a, TS3, TD1 & TD2

    11.1.1.2.2. Performing the disinfection process for the following pipeline TS1, TS2, TS2a, TS3, TD1 & TD2

    11.1.1.2.3. Performing the neutralization and cleaning after disinfection process for the following pipelines:

    TS1, TS2, TS2a, TS3, TD1 & TD2

    11.1.1.2.4. Performing the bacteriological tests for the following pipelines: TS1, TS2, TS2a, TS3, TD1 & TD2

    11.1.1.2.5. Continue finishing works inside chambers

    11.1.2. Project 2 (NUS) 11.1.2.1. Reservoir Yard

    11.1.2.1.1. Continue preparation and submit the construction submittals.

    Page 12 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    11.1.2.1.2. Continue installing the chlorination system at disinfection building 11.1.2.1.3. Installing, welding for all steel pipes at the booster station and the reser-

    voir.

    11.1.2.1.4. Pulling wires and installing the fire system at the facilities building 11.1.2.1.5. Pulling wires for instruments from VFD panel to the pump station 11.1.2.1.6. Casting concrete for the pipe support pad 11.1.2.1.7. Continue conducting training courses 11.1.2.1.8. Surface preparation for the reservoir walls and foundation from outside 11.1.2.1.9. Pulling wires and control cables at the reservoir yard. 11.1.2.1.10. Pulling the control cables and preparing connection between the discon-

    nect switch and pump motors

    11.1.2.1.11. Lubricating works for gate valves at the sustaining line, discharge pipe & flow meter pipe

    11.1.2.1.12. Isolation works for the reservoir foundation and the buried part of the reservoir wall

    11.1.2.1.13. Installing the flow meter at supply pipes. 11.1.2.1.14. Applying the external painting works at the reservoir. 11.1.2.1.15. Installing the chlorination system at the disinfection building. 11.1.2.1.16. Performing the function test for cables insulation at the pump station,

    diesel generator and the facilities buildings

    11.1.2.1.17. Installing connections between the VFD, PLC & MCC. 11.1.2.1.18. Continue painting works for all exposed steel pipes at booster station and

    the reservoir.

    11.1.2.1.19. Installing electrical and mechanical works at the pump station and the diesel generator

    11.1.2.1.20. Continue leveling & compaction of the concrete sidewalk around the booster pump station, facilities building and reservoir.

    11.1.2.1.21. Continue formwork, steel reinforcement and concrete casting for side-walk around the booster pump station, facilities building and reservoir

    11.1.2.1.22. Continue electrical work for RIO panel at the disinfection building (ca-bles connection)

    11.1.2.1.23. Installing the instrument devices at the booster station and the reservoir. 11.1.2.1.24. Coordination with the CMWU & PWA. 11.1.2.1.25. Continue procurement orders for construction requirements and ABC

    material.

    11.1.2.2. New construction of supply & distribution Pipelines

    11.1.2.2.1. Cleaning and flushing works for the following pipelines. NS1, NS2, NS3, NS4, ND1, ND2, ND3 & ND4

    11.1.2.2.2. Performing the disinfection process for the following pipeline NS1, NS2, NS3, NS4

    11.1.2.2.3. Performing the neutralization and cleaning after disinfection process for the following pipelines NS1, NS2, NS3, NS4

    11.1.2.2.4. Performing the bacteriological tests for the following pipelines

    Page 13 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    NS1, NS2, NS3, NS4 11.1.2.2.5. Continue finishing works inside chambers

    11.2. Planned Activities for Next Month 11.2.1. Project 1 (ATA)

    The following are the main activities planned for next reporting period:

    11.2.1.1. Reservoir Yard: 11.2.1.1.1. Continue preparation and submit the construction submittals. 11.2.1.1.2. Continue furnish and Installation of grounding system for the reservoir. 11.2.1.1.3. Start installation and fixation of the reservoir air vents and level indicator. 11.2.1.1.4. Checkered plate installation for electrical and control building and for

    booster pump station

    11.2.1.1.5. Start performing the string test and functional tests (start-up process) 11.2.1.1.6. Applying final painting coats for all buildings 11.2.1.1.7. Continue casting concrete for the remaining sidewalk 11.2.1.1.8. Laying the asphalt layer for the road inside the reservoir yard. 11.2.1.1.9. Performing the disinfection process inside the reservoir. 11.2.1.1.10. Coordination with the CMWU & PWA. 11.2.1.1.11. Continue procurement orders for construction requirements and ABC

    material.

    11.2.1.2. New construction of supply & distribution Pipelines: 11.2.1.2.1. Continue laying asphalt layer including 200mm base course layer for the

    road front the reservoir and inside the reservoir yard.

    11.2.2. Project 2 (NUS) 11.2.2.1. Reservoir Yard:

    11.2.2.1.1. Continue preparation and submit the construction submittals. 11.2.2.1.2. Start installation and fixation of the external ladders for the reservoir 11.2.2.1.3. Start installation and fixation of the internal ladders for the reservoir. 11.2.2.1.4. Start installation and fixation of the reservoir air vents and level indicator

    and SS launder. 11.2.2.1.5. Start applying the cementitious coating inside reservoir 11.2.2.1.6. Checkered plate installation for electrical and control building and for

    booster pump station 11.2.2.1.7. Start installation of the booster shed 11.2.2.1.8. Continue casting concrete for the remaining sidewalk 11.2.2.1.9. Conducting the functional tests (start-up process) 11.2.2.1.10. Performing the disinfection process inside the reservoir. 11.2.2.1.11. Applying final painting coats for all buildings. 11.2.2.1.12. Coordination with the CMWU & PWA. 11.2.2.1.13. Continue procurement orders for construction requirements and ABC

    material.

    11.2.2.2. New construction of supply & distribution Pipelines 11.2.2.2.1. Continue the disinfection for the entire pipelines and connections for the

    distribution pipeline. For more details, refer to Annex D.

    Page 14 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    12. Indicators

    12.1. Project 1 (ATA)

    12.1.1. Indicator 1: Quantity of drinking water available as a result of USG Assistance Project 1: Al Atatrah

    Total number of Beneficiaries

    Male Female

    No. % No. % Target 59,444 30,316 51% 29,128 49%

    Actual 0 0 0% 0 0%

    12.1.2. Indicator 2: Person Days of employment generated for this reporting period Project 1: Al Atatrah

    Total number (Person Days)

    Male Female

    No. No.

    Target 18,350 16,384 1,966

    Actual Previously 19532.22 18961.44 570.78

    Actual during this reporting period 833 805.50 27.50

    Total actual 20365.22 19766.94 598.28

    12.2. Project 2 (NUS) 12.2.1. Indicator 1: Quantity of drinking water available as a result of USG Assistance

    Project 2: Nuseirat

    Total number of Beneficiaries

    Male Female

    No. % No. %

    Target 104,622 53,357 51% 51,265 49%

    Actual 0 0 0% 0 0%

    12.2.2. Indicator 2: Person Days of employment generated for this reporting period Project 2: Nuseirat

    Total number (Person Days)

    Male Female

    No. No.

    Target 18,350 16,384 1,966

    Actual Previously 19425.57 18856.82 568.75

    Actual during this reporting period 750.38 722.88 27.50

    Total actual 20175.95 19579.70 596.25

    13. Working / Non Working Days13.1. Project 1 (ATA)1 Total Period of Performance (Original) 610

    2 Total Excusable delays/approved extensions 138

    3 Modified Period of Performance 748

    4 Modified Completion Date November 11,

    2017

    5 No. of Working Days during this reporting Period 22

    6 Accumulated Working Days 578.155

    7 Total No. of non-working days (Holidays and weekends) during this reporting Period

    8

    8 Accumulated non-working days (Holidays and weekends) 107.5

    9 No. of non-working days (Due to Weather) during this month 0

    10 Accumulated non-working days (Due to Weather) 14.875

    Page 15 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    11 No. of non-working days (Due to Objections) during this month 0

    12 Accumulated non-working days (Due to Objections) 5

    13 No. of non-working days (Due to unstable security situation in Gaza) during this month

    0

    14 Accumulated non-working days (Due to unstable security situation in Gaza)

    0.47

    13.2. Project 2 (NUS) 1 Total Period of Performance (Original) 610

    2 Total Excusable delays/approved extensions 138

    3 Modified Period of Performance 748

    4 Modified Completion Date November 11,

    2017

    5 No. of Working Days during this reporting Period 24

    6 Accumulated Working Days 579.905

    7 No. of non-working days (Holidays and weekends) during this month 6

    8 Accumulated non-working days (Holidays and weekends) 101

    9 No. of non-working days (Due to Weather) during this month 0

    10 Accumulated non-working days (Due to Weather) 17.375

    11 No. of non-working days (Due to Objections) during this month 0

    12 Accumulated non-working days (Due to Objections) 7.5

    13 No. of non-working days (Due to unstable security situation in Gaza) during this month

    0

    14 Accumulated non-working days (Due to unstable security situation in Gaza)

    0.22

    14. Material & equipment delivered to site

    14.1 Project 1 (ATA) * Please refer to Annex A Material and Equipment delivered to the site.

    14.2 Project 2 (NUS)* Please refer to Annex A Material and Equipment delivered to the site.

    15. Site Memos

    15.1. TMGI received three site memos from CMC/B&V, for GAZI project About:

    Response for SM-15-00008-GAZI-C-E-032: Response for Site Memo no. SM-15-00008-GAZI-E-C-095 (Welding Works for Reservoir and Pump Station Steel Pipes without Con-tractor's CWI Presence/Inspection.)

    Revised Site Layouts for the Reservoirs Sites Stainless Steel Pipe for Level Float Indicator

    15.1.1. Project 1 (ATA) TMGI received one site memo from CMC/B&V for Al Atatrah project about:

    Pump Station Shed at Al Atatrah Project.15.1.2. Project 2 (NUS)

    TMGI received five site memos from CMC/B&V for Nuseirat project about:

    Third-Party Test Reports for Nuseirat Project-Satisfactory Test Results Third-Party Test Reports for Nuseirat Project-Unsatisfactory Test Results

    Page 16 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    15.2. No site memo was issued to CMC/B&V for GAZI project during this reporting period

    15.2.1. Project 1 (ATA) TMGI issued three site memos to CMC/B&V for Al Atatrah project about:

    Response for Site Memo no. SM-15-00008-ATA-E-C-094 Response for Site Memo no. SM-15-00008-ATA-E-C-036 Al Atatrah asphalt works

    15.2.2. Project 2 (NUS) No site memo was issued to CMC/B&V for Nuseirat project during this reporting period.

    16. Inspection Requests

    During this reporting period, 13 inspection requests for both projects under GAZI task order

    were issued:

    No. IR Number REV. Description Inspection

    Date Actual

    Return Date 1st

    Inspection

    1 IR-15-00008-GAZI-130-A B Inspection request of the materials in the at-

    tached MRR (VFD Panel). September 6, 2017 September 7, 2017 A

    2 IR-15-00008-GAZI-131-A B Inspection request of the materials in the at-

    tached MRR (Skid Mounted Booster Pump).

    At SAK ware house.

    September 6, 2017 September 6, 2017 C

    3 IR-15-00008-GAZI-131-B A Inspection request of the materials in the at-

    tached MRR (Skid Mounted Booster Pump).

    At SAK ware house.

    September 14, 2017 September 14, 2017 A

    4 IR-15-00008-GAZI-132-A A

    Inspection request of the materials in the fol-

    lowing attached MRR:

    CONTROL CABLE 5X2.5 (TELDOR)

    CONTROL CABLE 12X2.5 (TELDOR)

    FIRE CABLE 2 PAIR (TELDOR)

    FIRE CABLE 4 PAIR (TELDOR)

    At SAK ware house.

    September 6, 2017 September 6, 2017 A

    5 IR-15-00008-GAZI-133-A B Inspection request for the external ladder for

    reservoir before painting. September 6, 2017 September 9, 2017 C

    6 IR-15-00008-GAZI-133-B A Inspection request for the external ladder for

    reservoir before painting. September 12, 2017 September 13, 2017 A

    7 IR-15-00008-GAZI-134-A A Inspection request of the materials in the at-

    tached MRR (PLC Panel). September 7, 2017 September 10, 2017 A

    8 IR-15-00008-GAZI-135-A A

    Inspection request of the materials in the fol-

    lowing attached MRR:

    Pipe Stainless Steel 75mm

    Pipe Stainless Steel 50mm

    Pipe Stainless Steel 32mm

    Cable Stainless Steel 8mm

    At SAK ware house.

    September 11, 2017 September 12, 2017 C

    9 IR-15-00008-GAZI-136-A A Inspection request of the materials in the at-

    tached MRR (THIOFLEX600 GG).

    At SAK ware house.

    September 14, 2017 September 14, 2017 A

    10 IR-15-00008-GAZI-137-A A Inspection request of the materials in the at-

    tached MRR (Copper Tube).At Al Atatrah

    Storage Yard.

    September 19, 2017 September 20, 2017 C

    Page 17 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    11 IR-15-00008-GAZI-137-B A Inspection request of the materials in the at-

    tached MRR (Copper Tube).

    At Al Atatrah Storage Yard.

    September 24, 2017 September 27, 2017 C

    12 IR-15-00008-GAZI-138-A A

    Inspection request of the materials in the fol-

    lowing attached MRR:

    Electrical Enclosure Tekpan Type

    (60x40x20) cm for flow meter

    Electrical Enclosure Tekpan Type

    (40x30x15) cm for Booster control valve

    At SAK ware house.

    September 20, 2017 September 21, 2017 A

    13 IR-15-00008-GAZI-139-A A

    Inspection request of the materials in the fol-

    lowing attached MRR:

    Soap Holder

    Liquid Soap Bottle 500 ML

    Towel bar

    Towel ring

    Mirror

    At Al Atatrah Storage Yard.

    September 20, 2017 September 21, 2017 A

    16.1. Project 1 (ATA) During this reporting period, 63 inspection requests were issued.

    16.2. Project 2 (NUS) During this reporting period, 67 inspection requests were issued.

    For more details, please refer to Annex E.

    17. Quality Control

    Updated Quality Control Plan for months of April, May, June, July, August & September will be

    submitted in the next reporting period.

    Quality Control Plan shall be updated on monthly basis.

    17.1. NONE COMPLIANCE REPORT Zero notice was issued during this reporting period

    17.1.1. Project 1 (ATA) Zero notice was issued during this reporting period

    17.1.2. Project 2 (NUS) Zero notice was issued during this reporting period

    For more information, please refer to Annex N.

    18. Tests Results:

    1 test result was issued for GAZI during this reporting period.

    18.1. Project 1 (ATA) During this reporting period, 8 tests were issued.

    18.2. Project 2 (NUS) During this reporting period, 14 tests were issued.

    For more details, please refer to Annex K.

    Page 18 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    19. Submittals

    During this reporting period, 95 submittals for GAZI were issued.

    19.1. Project 1 (ATA) During this reporting period, 14 submittals for Al Atatrah project were issued.

    19.2. Project 2 (NUS) During this reporting period, 13 submittals for Nuseirat project were issued.

    * TMGI Continue on submitting construction submittals.

    For more details, please refer to Annex F.

    20. Request for Information

    During this reporting period, two RFIs for GAZI were issued about:

    Drainage Piping for Air Release valves Level indicator 75mm SS pipe

    20.1. Project 1 (ATA)None issued during this reporting period for Al Atatrah project.

    20.2. Project 2 (NUS) None issued during this reporting period for Nuseirat project.

    For more details, please refer to Annex G.

    21. Transmittals

    21.1. Outgoing / Incoming USAID Transmittals (TMGI/ USAID)

    Date Contractor Trans. No.

    Sender / Recipient

    Subject

    September 5, 2017 By Email TMGI/USAID

    USAID COR APPROVAL - TO-15-00008-GAZI Con-struction Monthly Progress Report No.22 August , 2017

    September 18, 2017 By Email USAID/TMGI

    September 19, 2017 By Email TMGI/USAID

    September 27, 2017 By Email USAID/TMGI

    September 11, 2017 By Email TMGI/USAID Project 1295 -GRAMMS update of the pending items

    stage 15, stage 17 and Cohen office September 11, 2017

    September 15, 2017 By Email USAID/TMGI Re: TO 15-0008/9 GAZA I&II: Project 1295 -GRAMMS update - Critical September 16, 2017 By Email TMGI/USAID

    September 17, 2017 By Email TMGI/USAID GAZI- Vetting Request- Renewal

    Page 19 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    21.2. Transmittals from Contractor to Engineers Contractors to

    Engineer Description Issued Date Response Date

    TRS. 00008.C-E-622

    TEST - Factory test results for Al Atatrah VFD September 5,

    2017 September 6,

    2017

    TEST - Factory test results for Nuseirat VFD September 5,

    2017 September 6,

    2017

    Manufacturers Field Services Representative for Gate Valve- Option II

    September 5, 2017

    Retracted

    TRS. 00008.C-E-623 RFI - Drainage Piping for Air Release valves September 6,

    2017 September 26,

    2017

    TRS. 00008.C-E-624

    TEST - 7 Days Results for 21 MPa-Cylinder for encasement of the building next to asphalt road outside the reservoir yard.

    September 6, 2017

    September 12, 2017

    TEST - 7 Days Results for 21 MPa-Cylinder for encasement around 6 sleeves PVC pipes for external electrical (MV) Network.

    September 6, 2017

    September 12, 2017

    TEST - Test Results for the asphalt layer (7.0cm) for road outside & inside the reservoir yard.

    September 6, 2017

    September 12, 2017

    TEST - Factory test results for Al Atatrah Skid Mounted Booster Pump

    September 6, 2017

    September 13, 2017

    TRS. 00008.C-E-625

    TEST - 28 Days Results for 30 MPa-Cylinder for electrical pull manhole for the external electrical cable.

    September 7, 2017

    September 25, 2017

    AS BUILT DRAWINGS: Nuseirat Architectural and Struc-tural Retaining & Boundary Walls

    September 7, 2017

    September 20, 2017

    Electrical AS BUILT DRAWINGS: Metering Panel -AL-Ata-trah

    September 7, 2017

    September 12, 2017

    Electrical AS BUILT DRAWINGS: Metering Panel -Nusei-rat

    September 7, 2017

    September 12, 2017

    Electrical AS BUILT DRAWINGS: Guard House -Al Ata-trah

    September 7, 2017

    September 19, 2017

    Electrical AS BUILT DRAWINGS: Guard House -Nuseirat September 7,

    2017 September 19,

    2017

    Mechanical AS BUILT DRAWINGS: Pump Station Al Atatrah

    September 7, 2017

    September 20, 2017

    TRS. 00008.C-E-626

    Section 4H: Lightning and Earthing System Final Operation & Maintenance Manual

    September 10, 2017

    September 13, 2017

    Section 4D: Lighting Fixture Final Operation & Maintenance Manual.

    September 10, 2017

    September 13, 2017

    Section 4L: Photovoltaic system Final Operation & Mainte-nance Manual

    September 10, 2017

    September 13, 2017

    Section 4E: 400V Distribution Boards Final Operation & Maintenance Manual

    September 10, 2017

    September 19, 2017

    Section 1A: Vertical Booster Pumps and 400V Electric Mo-tors Final Operation & Maintenance Manual

    September 10, 2017

    September 27, 2017

    Section 4F: 600V Motor Control Center Final Operation & Maintenance Manual

    September 10, 2017

    September 20, 2017

    Section 7D: Flow Switches [Pump Station] Final Operation & Maintenance Manual

    September 10, 2017

    September 12, 2017

    Page 20 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Section 4G: Fire Alarm System Final Operation & Mainte-nance Manual

    September 10, 2017

    September 12, 2017

    TRS. 00008.C-E-627

    Training for VFD Operator September 10,

    2017 Retracted

    Training for VFD Programmer September 10,

    2017 Retracted

    Training for HMI Programmer September 10,

    2017 Retracted

    Training for HMI Operator September 10,

    2017 Retracted

    Training for PLC Operator September 10,

    2017 Retracted

    Training for PLC Programmer September 10,

    2017 Retracted

    Section 7H: Ultrasonic Level Transmitter Final Operation & Maintenance Manual

    September 10, 2017

    September 13, 2017

    String Test Method Statement for Vertical Pumps September 10,

    2017 September 13,

    2017

    Nuseirat Site Layout Revised Shop Drawing September 10,

    2017 Retracted

    Section 4A: Engine Generators Final Operation & Mainte-nance Manual

    September 10, 2017

    September 12, 2017

    TRS. 00008.C-E-628

    Section 8C: Eyewash & Emergency Shower with Remote Tank Final Operation & Maintenance Manual

    September 11, 2017

    September 13, 2017

    Section 4K: Disconnect Switch Final Operation & Mainte-nance Manual

    September 11, 2017

    September 12, 2017

    Section 7G: Proximity Switch Final Operation & Mainte-nance Manual

    September 11, 2017

    September 20, 2017

    Section 10B: Steel Mesh fences and Gate Final Operation & Maintenance Manual

    September 11, 2017

    September 12, 2017

    Section 7B: Level Pressure Transmitters Final Operation & Maintenance Manual

    September 11, 2017

    September 12, 2017

    TEST - 28 Days Results for 21 MPa-Cylinder for encasement of discharge header.

    September 11, 2017

    September 12, 2017

    TRS. 00008.C-E-629 Al Atatrah Site Layout Revised Shop Drawing September 11,

    2017 Retracted

    TRS. 00008.C-E-630 VOR - Changes to Task Orders' Permanent Signs September 12,

    2017 Retracted

    TRS. 00008.C-E-631

    AS BUILT DRAWINGS: Disinfection Building (Architec-tural & Structural)-Nuseirat

    September 12, 2017

    September 21, 2017

    Galvanized Steel Clamp- With Sample September 12,

    2017 September 13,

    2017

    Section 4C: LV Cable Final Operation & Maintenance Man-ual

    September 12, 2017

    September 13, 2017

    Section 7F: Premium Accuracy Pressure Transmitters Final Operation & Maintenance Manual

    September 12, 2017

    September 13, 2017

    Section 4B: Transformer Final Operation & Maintenance Manual

    September 12, 2017

    September 19, 2017

    Page 21 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    TRS. 00008.C-E-632 Updated CPM Construction Schedule August 31, 2017 September 13,

    2017 September 20,

    2017

    TRS. 00008.C-E-633

    AS BUILT DRAWINGS: Disinfection Building (Architec-tural & Structural)-Al Atatrah

    September 13, 2017

    September 25, 2017

    Section 6K: Strainers Final Operation & Maintenance Manual September 13,

    2017 September 19,

    2017

    Section 4I: Communication and control cable Final Opera-tion & Maintenance Manual

    September 13, 2017

    September 19, 2017

    Section 7C: Float Type Level Switches Final Operation & Maintenance Manual

    September 13, 2017

    September 19, 2017

    Enclosure for Flow meter September 13,

    2017 September 17,

    2017

    Updated Construction Risk Management Program (CRMP) June 2017

    September 13, 2017

    September 14, 2017

    Updated Construction Risk Management Program (CRMP) July 2017

    September 13, 2017

    September 14, 2017

    Updated Construction Risk Management Program (CRMP) August 2017

    September 13, 2017

    September 25, 2017

    Update Safety Plan July 2017 September 13,

    2017 September 17,

    2017

    TRS. 00008.C-E-634

    Training for Control Valves September 14,

    2017 September 17,

    2017

    Nuseirat Site Layout Revised Shop Drawing September 14,

    2017 Under Review

    Al Atatrah Site Layout Revised Shop Drawing September 14,

    2017 Under Review

    Update Safety Plan August 2017 September 14,

    2017 September 17,

    2017

    Section 1B Variable Frequency Drive Final Operation & Maintenance Manual

    September 14, 2017

    September 19, 2017

    Section 6L: Backflow Preventer Valve Final Operation & Maintenance Manual

    September 14, 2017

    September 19, 2017

    Section 14A & 15A: Short circuit & coordination and study protective device studies Final Operation & Maintenance Manual

    September 14, 2017

    September 19, 2017

    Start Up and Function Test Schedule September 14,

    2017 September 19,

    2017

    TRS. 00008.C-E-635

    Electrical AS BUILT DRAWINGS: Main Distribution Board (MCC) for Nuseirat Reservoir

    September 16, 2017

    September 27, 2017

    Electrical AS BUILT DRAWINGS: Sub Distribution Board September 16,

    2017 Under Review

    AS BUILT DRAWINGS: Nuseirat Pipe Line Shop Drawing September 16,

    2017 September 28,

    2017

    Electrical AS BUILT DRAWINGS: Main Distribution Board (MCC) Al Atatrah

    September 16, 2017

    September 27, 2017

    Booster Pump Station Shed Revised Column Location Shop Drawings - Al Atatrah

    September 16, 2017

    September 27, 2017

    Updated Environmental Monitoring & Mitigation Plan (June 2017)

    September 16, 2017

    September 17, 2017

    Updated Environmental Monitoring & Mitigation Plan (July 2017)

    September 16, 2017

    September 17, 2017

    Material and Method Statement for Repair the irregular con-crete surface

    September 16, 2017

    Under Review

    Page 22 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Material and Method Statement for Placing New SS Anchor Bolts

    September 16, 2017

    September 27, 2017

    TRS. 00008.C-E-636

    Section 10C: Manholes and Manholes Covers Final Opera-tion & Maintenance Manual

    September 17, 2017

    September 17, 2017

    Section 5: PLC and Control Systems Final Operation & Maintenance Manual

    September 17, 2017

    September 19, 2017

    Section 7A: Electromagnetic Flow Meter Final Operation & Maintenance Manual

    September 17, 2017

    September 19, 2017

    Section 11-A: Water heating System Final Operation & Maintenance Manual

    September 17, 2017

    September 27, 2017

    Section 7E: Pressure Switch Final Operation & Maintenance Manual

    September 17, 2017

    September 19, 2017

    Section 7L: Pressure Gauges Final Operation & Maintenance Manual

    September 17, 2017

    September 19, 2017

    TRS. 00008.C-E-637

    Section 4M: Reservoir LCP Level Panel Final Operation & Maintenance Manual

    September 18, 2017

    September 20, 2017

    Section 11-E: Wall Mounted Exhaust Fans Final Operation & Maintenance Manual

    September 18, 2017

    September 21, 2017

    Mechanical AS BUILT DRAWINGS: Disinfection Building September 18,

    2017 September 27,

    2017

    Section 3: Grinder Pump Package Lift Station Final Opera-tion & Maintenance Manual

    September 18, 2017

    September 20, 2017

    Section 7J: Electrode/Conductance Relay Level Switches Fi-nal Operation & Maintenance Manual

    September 18, 2017

    September 20, 2017

    TEST - Core Test Results for the asphalt layer for road out-side & inside the reservoir yard.

    September 18, 2017

    Under Review

    TEST - 7 Days Results for 35 MPa-Cylinder for pipe support pad - foundation.

    September 18, 2017

    September 25, 2017

    TRS. 00008.C-E-638

    Instrumentation and control system (PLC and Automation) Trainers

    September 19, 2017

    September 27, 2017

    Variable Frequency Drive (VFD)Trainers September 19,

    2017 September 27,

    2017

    Mechanical AS BUILT DRAWINGS: Electrical & Control Building

    September 19, 2017

    September 27, 2017

    Page 23 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Training for Control Valves September 19,

    2017 September 21,

    2017

    Mechanical AS BUILT DRAWINGS: Pump Station Nusei-rat

    September 19, 2017

    September 25, 2017

    Training for HMI Operator September 19,

    2017 September 20,

    2017

    Section III: Plant Description and general layout Final Oper-ation & Maintenance Manual

    September 19, 2017

    September 20, 2017

    Section 8D: Chemical Storage Tank Final Operation & Maintenance Manual

    September 19, 2017

    September 21, 2017

    Training for HMI Programmer September 19,

    2017 September 20,

    2017

    Training for PLC Operator September 19,

    2017 September 20,

    2017

    AS BUILT DRAWINGS: Nuseirat 3800M3 Reservoir Struc-tural & Architectural Drawing's

    September 19, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for TS2a pipeline at Al Atatrah project

    September 19, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for TS3 pipeline at Al Atatrah project

    September 19, 2017

    Under Review

    TEST - 28 Days Results for 21 MPa-Cylinder for encasement of the building next to asphalt road outside the reservoir yard.

    September 19, 2017

    September 25, 2017

    TRS. 00008.C-E-639

    Nuseirat Electrical & Control Building Checkered Plate Shop Drawings

    September 20, 2017

    September 27, 2017

    AL - Atatrah Electrical & Control Building Checkered Plate Shop Drawings

    September 20, 2017

    September 27, 2017

    AS BUILT DRAWINGS: Al Atatrah 3800M3 Reservoir Structural & Architectural Drawing's

    September 20, 2017

    Under Review

    Mechanical AS BUILT DRAWINGS: Pump Station Al Atatrah

    September 20, 2017

    September 21, 2017

    Electrical AS BUILT DRAWINGS: Disinfection Building September 20,

    2017 Under Review

    Galvanized PVC coated flexible - Option II September 20,

    2017 September 27,

    2017

    TRS. 00008.C-E-640

    TEST - Fire and control cables - Test certificate September 21,

    2017 September 25,

    2017

    TEST - Flushing, disinfection & bacteriological test result for TS2 pipeline at Al Atatrah project

    September 21, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for supply pipeline TS1 from St. 1+000 to St. 1+630 at Al Ata-trah project

    September 21, 2017

    Under Review

    Page 24 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    TEST - Flushing, disinfection & bacteriological test result for supply pipeline TS1 from St. 1+630 to St. 2+960 at Al Ata-trah project

    September 21, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for distribution pipelines TD1 & TD2 at Al Atatrah project

    September 21, 2017

    Under Review

    Training for VFD Operator September 21,

    2017 September 21,

    2017

    Guard House Furniture September 21,

    2017 Under Review

    TRS. 00008.C-E-641 VOR - Electrical Installation deficiencies at Al Atatrah and Nuseirat Projects-Item No.04-Rio Panel

    September 21, 2017

    September 21, 2017

    TRS. 00008.C-E-642

    Training for VFD Operator September 24,

    2017 September 25,

    2017

    Training for VFD Programmer September 24,

    2017 September 25,

    2017

    Section 11H: Portable Fire Extinguishers Final Operation & Maintenance Manual

    September 24, 2017

    September 25, 2017

    Section 8B: Free Chlorine Analyzer Final Operation & Maintenance Manual

    September 24, 2017

    September 27, 2017

    Section 8A: Dosing Pump Final Operation & Maintenance Manual

    September 24, 2017

    September 27, 2017

    TRS. 00008.C-E-643

    Training for PLC Programmer September 24,

    2017 September 25,

    2017

    Electrical AS BUILT DRAWINGS: Electrical & Control Building - Al Atatrah

    September 24, 2017

    Under Review

    TRS. 00008.C-E-644 VOR - Storage Costs of Dual Use Materials that Arrived to Gaza up to July 11, 2017

    September 25, 2017

    Under Review

    TRS. 00008.C-E-645 RFI - Level indicator 75mm SS pipe September 25,

    2017 Under Review

    TRS. 00008.C-E-646

    Toilet Accessories With Sample September 25,

    2017 September 27,

    2017

    Reservoir External Ladder Shop Drawings September 25,

    2017 September 27,

    2017

    Steel Pipes Painting Prepare Method Statement September 25,

    2017 September 27,

    2017

    Local Representative for Vertical Turbines Pumps September 25,

    2017 September 27,

    2017

    Local Representative for Engine Generator September 25,

    2017 September 27,

    2017

    Local Representative for Variable Frequency Drive (VFD) September 25,

    2017 September 27,

    2017

    Local Representative for Control Valves September 25,

    2017 September 27,

    2017

    Local Representative for Motor Control Center (MCC) September 25,

    2017 September 27,

    2017

    Local Representative for Chlorine System September 25,

    2017 September 27,

    2017

    Local Representative for Photo-Voltaic System September 25,

    2017 September 27,

    2017

    Local Representative for PLC September 25,

    2017 September 27,

    2017

    Page 25 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Local Representative for Skid Mounted Booster Pump September 25,

    2017 September 27,

    2017

    AS BUILT DRAWINGS: Guard House (Architectural & Structural)-Nuseirat

    September 25, 2017

    Under Review

    AS BUILT DRAWINGS: Guard House (Architectural & Structural)-Al Atatrah

    September 25, 2017

    Under Review

    TRS. 00008.C-E-647 VOR - Changes to Task Orders' Permanent Signs September 26,

    2017 September 26,

    2017

    TRS. 00008.C-E-648

    RFI - Replace manual pressure gauge calibrator by PVC pres-sure pipes

    September 26, 2017

    Retracted

    Mechanical AS BUILT DRAWINGS: Skid Mounted Booster Pump Al Atatrah

    September 26, 2017

    September 28, 2017

    AS BUILT DRAWINGS: Nuseirat Chambers September 26,

    2017 Under Review

    TRS. 00008.C-E-649

    Mechanical AS BUILT DRAWINGS: Pump Station Nusei-rat

    September 27, 2017

    Under Review

    Section 6I: Dismantling Joint Final Operation & Maintenance Manual

    September 27, 2017

    Under Review

    Section 12D: PP-R Pipe for Disinfection Building Final Op-eration & Maintenance Manual

    September 27, 2017

    Under Review

    Section 11-J: Expansion Joint Final Operation & Mainte-nance Manual

    September 27, 2017

    Under Review

    TEST - Soil field density for leveling & compaction under side walk area around the facilities buildings.

    September 27, 2017

    Under Review

    TEST - 28 Days Results for 21 MPa-Cylinder for encasement around 6 sleeves PVC pipes for external electrical (MV) Network.

    September 27, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for Supply pipeline NS1 at Nuseirat project

    September 27, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for Supply pipeline NS2 at Nuseirat project

    September 27, 2017

    Under Review

    TEST - Flushing, disinfection & bacteriological test result for Supply pipeline NS3 at Nuseirat project

    September 27, 2017

    Under Review

    TRS. 00008.C-E-650

    Training for VFD Programmer September 28,

    2017 Under Review

    Training for PLC Programmer September 28,

    2017 Under Review

    Training for HMI Operator September 28,

    2017 Under Review

    Training for HMI Programmer September 28,

    2017 Under Review

    Training for PLC Operator September 28,

    2017 Under Review

    Section 6E: Gate Valve Final Operation & Maintenance Manual

    September 28, 2017

    Under Review

    Section 9B: Steel Pipe & Fitting Final Operation & Mainte-nance Manual

    September 28, 2017

    Under Review

    Section 11-I: Ultraviolet (UV) Water Purifier Final Operation & Maintenance Manual

    September 28, 2017

    Under Review

    Section 12C: PVC and HDPE Pipes Final Operation & Maintenance Manual

    September 28, 2017

    Under Review

    Mechanical AS BUILT DRAWINGS: Guard House September 28,

    2017 Under Review

    Page 26 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    TRS. 00008.C-E-651 Painted G.S corrugated sheet 0.6mm - With Sample September 30,

    2017 Under Review

    21.3. Transmittals from Engineers to Contractor Engineers to Contractor

    Description Received Date

    TRS-15-00008-E-C-525

    TEST - Certified Factory Pump Performance Test Result Al Atatrah. September 5, 2017

    TEST - Certified Factory Pump Performance Test Result Nuseirat September 5, 2017

    TEST - 28 Days Results for 35 MPa-Cylinder for flow meter - (booster pump station) and external ladder pad at the guard house.

    September 5, 2017

    TRS-15-00008-E-C-526

    Manufacturers Field Services Representative for Air Release Valve September 6, 2017

    PVC Support for disinfection wet panel September 6, 2017

    Certificate of Test for Grounding system September 6, 2017

    Factory test results for Al Atatrah VFD September 6, 2017

    Factory test results for Nuseirat VFD September 6, 2017

    TRS-15-00008-E-C-527 Section 12C: PVC and HDPE Pipes Preliminary Operation & Maintenance Manual

    September 10, 2017

    TRS-15-00008-E-C-528 TEST - Certificate of Test for Grounding system September 11, 2017

    TRS-15-00008-E-C-529

    TEST - 7 Days Results for 21 MPa-Cylinder for encasement of the building next to asphalt road outside the reservoir yard.

    September 12, 2017

    TEST - 7 Days Results for 21 MPa-Cylinder for encasement around 6 sleeves PVC pipes for external electrical (MV) Network.

    September 12, 2017

    TEST - Test Results for the asphalt layer (7.0cm) for road outside & inside the reservoir yard.

    September 12, 2017

    TEST - 28 Days Results for 21 MPa-Cylinder for encasement of discharge header.

    September 12, 2017

    Electrical AS BUILT DRAWINGS: Metering Panel -AL-Atatrah September 12, 2017

    Electrical AS BUILT DRAWINGS: Metering Panel -Nuseirat September 12, 2017

    Section 7D: Flow Switches [Pump Station] Final Operation & Maintenance Manual

    September 12, 2017

    Section 4G: Fire Alarm System Final Operation & Maintenance Manual September 12, 2017

    Section 4A: Engine Generators Final Operation & Maintenance Manual September 12, 2017

    Section 4K: Disconnect Switch Final Operation & Maintenance Manual September 12, 2017

    Section 10B: Steel Mesh fences and Gate Final Operation & Maintenance Manual

    September 12, 2017

    Section 7B: Level Pressure Transmitters Final Operation & Maintenance Manual

    September 12, 2017

    TRS-15-00008-E-C-530

    Section 4H: Lightning and Earthing System Final Operation & Mainte-nance Manual

    September 13, 2017

    Section 4D: Lighting Fixture Final Operation & Maintenance Manual. September 13, 2017

    Section 4L: Photovoltaic system Final Operation & Maintenance Manual September 13, 2017

    Section 7H: Ultrasonic Level Transmitter Final Operation & Maintenance Manual

    September 13, 2017

    String Test Method Statement for Vertical Pumps September 13, 2017

    Section 8C: Eyewash & Emergency Shower with Remote Tank Final Oper-ation & Maintenance Manual

    September 13, 2017

    Galvanized Steel Clamp- With Sample September 13, 2017

    Page 27 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Section 4C: LV Cable Final Operation & Maintenance Manual September 13, 2017

    Section 7F: Premium Accuracy Pressure Transmitters Final Operation & Maintenance Manual

    September 13, 2017

    TEST - Factory test results for Al Atatrah Skid Mounted Booster Pump September 13, 2017

    VOR - Storage Costs of Dual Use Materials that Arrived to Gaza up to July 11, 2017

    September 13, 2017

    TRS-15-00008-E-C-531

    AS BUILT DRAWINGS: Guard House (Architectural & Structural)-Nuseirat

    September 14, 2017

    AS BUILT DRAWINGS: Al Atatrah Pipe Line Shop Drawing September 14, 2017

    Updated Construction Risk Management Program (CRMP) June 2017 September 14, 2017

    Updated Construction Risk Management Program (CRMP) July 2017 September 14, 2017

    TRS-15-00008-E-C-532

    AS BUILT DRAWINGS: Guard House (Architectural & Structural)-Al Atatrah

    September 17, 2017

    Training for Control Valves September 17, 2017

    Al Atatrah Asphalt works Shop Drawing September 17, 2017

    Enclosure for Flow meter September 17, 2017

    Update Safety Plan July 2017 September 17, 2017

    Update Safety Plan August 2017 September 17, 2017

    Updated Environmental Monitoring & Mitigation Plan (June 2017) September 17, 2017

    Updated Environmental Monitoring & Mitigation Plan (July 2017) September 17, 2017

    Section 10C: Manholes and Manholes Covers Final Operation & Mainte-nance Manual

    September 17, 2017

    TRS-15-00008-E-C-533

    TEST - 7 Days Results for 30 MPa-Cylinder for electrical pull manhole for the external electrical cable.

    September 18, 2017

    Nuseirat Pump Station Checkered Plate Shop Drawings September 18, 2017

    TRS-15-00008-E-C-534

    Electrical AS BUILT DRAWINGS: Guard House -Al Atatrah September 19, 2017

    Electrical AS BUILT DRAWINGS: Guard House -Nuseirat September 19, 2017

    Section 4E: 400V Distribution Boards Final Operation & Maintenance Manual

    September 19, 2017

    Section 4B: Transformer Final Operation & Maintenance Manual September 19, 2017

    Section 6K: Strainers Final Operation & Maintenance Manual September 19, 2017

    Section 4I: Communication and control cable Final Operation & Mainte-nance Manual

    September 19, 2017

    Section 7C: Float Type Level Switches Final Operation & Maintenance Manual

    September 19, 2017

    Section 1B Variable Frequency Drive Final Operation & Maintenance Man-ual

    September 19, 2017

    Section 6L: Backflow Preventer Valve Final Operation & Maintenance Manual

    September 19, 2017

    Section 14A & 15A: Short circuit & coordination and study protective de-vice studies Final Operation & Maintenance Manual

    September 19, 2017

    Start Up and Function Test Schedule September 19, 2017

    Section 5: PLC and Control Systems Final Operation & Maintenance Man-ual

    September 19, 2017

    Section 7A: Electromagnetic Flow Meter Final Operation & Maintenance Manual

    September 19, 2017

    Section 7E: Pressure Switch Final Operation & Maintenance Manual September 19, 2017

    Page 28 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Section 7L: Pressure Gauges Final Operation & Maintenance Manual September 19, 2017

    TRS-15-00008-E-C-535

    AS BUILT DRAWINGS: Nuseirat Architectural and Structural Retaining & Boundary Walls

    September 20, 2017

    Mechanical AS BUILT DRAWINGS: Pump Station Al Atatrah September 20, 2017

    Section 4F: 600V Motor Control Center Final Operation & Maintenance Manual

    September 20, 2017

    Updated CPM Construction Schedule August 31, 2017 September 20, 2017

    Section 4M: Reservoir LCP Level Panel Final Operation & Maintenance Manual

    September 20, 2017

    Section 3: Grinder Pump Package Lift Station Final Operation & Mainte-nance Manual

    September 20, 2017

    Section 7J: Electrode/Conductance Relay Level Switches Final Operation & Maintenance Manual

    September 20, 2017

    TRS-15-00008-E-C-536

    Section 7G: Proximity Switch Final Operation & Maintenance Manual September 20, 2017

    Training for HMI Operator September 20, 2017

    Section III: Plant Description and general layout Final Operation & Maintenance Manual

    September 20, 2017

    Training for HMI Programmer September 20, 2017

    Training for PLC Operator September 20, 2017

    TRS-15-00008-E-C-537

    AS BUILT DRAWINGS: Disinfection Building (Architectural & Struc-tural)-Nuseirat

    September 21, 2017

    Training for Control Valves September 21, 2017

    Mechanical AS BUILT DRAWINGS: Pump Station Al Atatrah September 21, 2017

    Training for VFD Operator September 21, 2017

    Section 11-E: Wall Mounted Exhaust Fans Final Operation & Maintenance Manual

    September 21, 2017

    Section 8D: Chemical Storage Tank Final Operation & Maintenance Man-ual

    September 21, 2017

    TRS-15-00008-E-C-538 VOR - Electrical Installation deficiencies at Al Atatrah and Nuseirat Pro-jects-Item No.04-Rio Panel

    September 21, 2017

    TRS-15-00008-E-C-539

    TEST - Fire and control cables - Test certificate September 25, 2017

    TEST - 28 Days Results for 30 MPa-Cylinder for electrical pull manhole for the external electrical cable.

    September 25, 2017

    TEST - 7 Days Results for 35 MPa-Cylinder for pipe support pad - founda-tion.

    September 25, 2017

    TEST - 28 Days Results for 21 MPa-Cylinder for encasement of the build-ing next to asphalt road outside the reservoir yard.

    September 25, 2017

    TEST - AS BUILT DRAWINGS: Disinfection Building (Architectural & Structural)-Al Atatrah

    September 25, 2017

    Training for VFD Operator September 25, 2017

    Training for VFD Programmer September 25, 2017

    Training for PLC Programmer September 25, 2017

    Updated Construction Risk Management Program (CRMP) August 2017 September 25, 2017

    Mechanical AS BUILT DRAWINGS: Pump Station Nuseirat September 25, 2017

    Section 11H: Portable Fire Extinguishers Final Operation & Maintenance Manual

    September 25, 2017

    TRS-15-00008-E-C-540 RFI - Drainage Piping for Air Release valves September 26, 2017

    Page 29 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    Changes to Task Orders' Permanent Signs September 26, 2017

    TRS-15-00008-E-C-541

    Toilet Accessories With Sample September 27, 2017

    Reservoir External Ladder Shop Drawings September 27, 2017

    Nuseirat Electrical & Control Building Checkered Plate Shop Drawings September 27, 2017

    AL - Atatrah Electrical & Control Building Checkered Plate Shop Drawings September 27, 2017

    Steel Pipes Painting Prepare Method Statement September 27, 2017

    Instrumentation and control system (PLC and Automation) Trainers

    September 27, 2017

    Variable Frequency Drive (VFD)Trainers September 27, 2017

    Local Representative for Vertical Turbines Pumps September 27, 2017

    Local Representative for Engine Generator September 27, 2017

    Local Representative for Variable Frequency Drive (VFD) September 27, 2017

    Local Representative for Control Valves September 27, 2017

    Local Representative for Motor Control Center (MCC) September 27, 2017

    Local Representative for Chlorine System September 27, 2017

    Local Representative for Photo-Voltaic System September 27, 2017

    Local Representative for PLC September 27, 2017

    Local Representative for Skid Mounted Booster Pump September 27, 2017

    Electrical AS BUILT DRAWINGS: Main Distribution Board (MCC) for Nuseirat Reservoir

    September 27, 2017

    Electrical AS BUILT DRAWINGS: Main Distribution Board (MCC) Al Atatrah

    September 27, 2017

    Mechanical AS BUILT DRAWINGS: Electrical & Control Building September 27, 2017

    Section 1A: Vertical Booster Pumps and 400V Electric Motors Final Oper-ation & Maintenance Manual

    September 27, 2017

    Booster Pump Station Shed Revised Column Location Shop Drawings - Al Atatrah

    September 27, 2017

    Material and Method Statement for Placing New SS Anchor Bolts September 27, 2017

    Section 11-A: Water heating System Final Operation & Maintenance Man-ual

    September 27, 2017

    Mechanical AS BUILT DRAWINGS: Disinfection Building September 27, 2017

    Galvanized PVC coated flexible - Option II September 27, 2017

    Section 8B: Free Chlorine Analyzer Final Operation & Maintenance Man-ual

    September 27, 2017

    Section 8A: Dosing Pump Final Operation & Maintenance Manual September 27, 2017

    TRS-15-00008-E-C-542

    AS BUILT DRAWINGS: Nuseirat Pipe Line Shop Drawing September 28, 2017

    Mechanical AS BUILT DRAWINGS: Skid Mounted Booster Pump Al Atatrah

    September 28, 2017

    Page 30 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    22. Task Order General Statistics

    NO. Description This Month Cumulative

    1 Preconstruction Submittals 0 93

    2 Material Submittals 6 606

    3 Shop drawings Submittals

    3.1 Mutual for ATA & NUS (GAZI) 1 123

    3.2 Project 1 ATA 3 112

    3.3 Project 2 NUS 2 92

    4 Preliminary Operation & Maintenance Manual 1 87

    5 Inspection Request (IR)

    5.1 Mutual for ATA & NUS (GAZI) 13 149 5.2 Project 1 ATA 63 1087

    5.3 Project 2 NUS 67 883

    6 Request for Information (RFI)

    6.1 Mutual for ATA & NUS (GAZI) 2 50

    6.2 Project 1 ATA 0 4

    6.3 Project 2 NUS 0 6

    23. Payments

    Invoice No. Project Submitted

    date Received by

    BV on Amount $

    Retention Amount

    Amount Received

    Received Date

    PAY-15-00008-GAZI-

    001

    ATA January 18,

    2016 January 21,

    2016 263,471.99 - 263,471.99

    February 09, 2016

    NUS January 18,

    2016 January 21,

    2016 270,776.85 - 270,776.85

    February 09, 2016

    GAZI (Total)

    January 18, 2016

    January 21, 2016

    534,248.84 - 534,248.84 February 09,

    2016

    PAY-15-00008-GAZI-

    002

    ATA May 29, 2016 May 31, 2016 288,625.54 - 288,625.54 June 16, 2016

    NUS May 29, 2016 May 31, 2016 54,907.57 - 54,907.57 June 16, 2016

    GAZI (Total)

    May 29, 2016 May 31, 2016 343,533.11 - 343,533.11 June 16, 2016

    PAY-15-00008-GAZI-

    003

    ATA June 19, 2016 June 21, 2016 61,941.06 - 61,941.06 June 30, 2016

    NUS June 19, 2016 June 21, 2016 24,329.93 - 24,329.93 June 30, 2016

    GAZI (Total)

    June 19, 2016 June 21, 2016 86,270.99 - 86,270.99 June 30, 2016

    Page 31 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    PAY-15-00008-GAZI-

    004

    ATA September 5,

    2016 September 5,

    2016 96,420.36 - 96,420.36

    September 14, 2016

    NUS September 5,

    2016 September 5,

    2016 207,048.76 - 207,048.76

    September 14, 2016

    GAZI (Total)

    October 5, 2016

    September 5, 2016

    303,469.12 - 303,469.12 September 14, 2016

    PAY-15-00008-GAZI-

    005

    ATA October 24,

    2016 October 24,

    2016 515,498.53 - 515,498.53

    November 09, 2016

    NUS October 24,

    2016 October 24,

    2016 438,828.04 - 438,828.04

    November 09, 2016

    GAZI (Total)

    October 24, 2016

    October 24, 2016

    954,326.57 - 954,326.57 November 09, 2016

    PAY-15-00008-GAZI-

    006

    ATA December 6,

    2016 December 6,

    2016 226,915.42 - 226,915.42

    December 14, 2016

    NUS December 6,

    2016 December 6,

    2016 479,259.76 - 479,259.76

    December 14, 2016

    GAZI (Total)

    December 6, 2016

    December 6, 2016

    706,175.18 - 706,175.18 December 14, 2016

    PAY-15-00008-GAZI-

    007

    ATA February 09,

    2017 February 09,

    2017 449,104.50 - 449,104.50

    March 03, 2017

    NUS February 09,

    2017 February 09,

    2017 539,372.37 - 539,372.37

    March 03, 2017

    GAZI (Total)

    February 09, 2017

    February 09, 2017

    988,476.87 - 988,476.87 March 03,

    2017

    PAY-15-00008-GAZI-

    008

    ATA May 09, 2017 May 15, 2017 546,561.61 - 546,561.61 June 05, 2017

    NUS May 09, 2017 May 15, 2017 584,968.77 - 584,968.77 June 05, 2017

    GAZI (Total)

    May 09, 2017 May 15, 2017 1,131,530.38 - 1,131,530.38 June 05, 2017

    PAY-15-00008-GAZI-

    009

    ATA August 09,

    2017 August 09,

    2017 779,134.97 - 779,134.97

    August 24, 2017

    NUS August 09,

    2017 August 09,

    2017 811,327.30 - 811,327.30

    August 24, 2017

    GAZI (Total)

    August 09, 2017

    August 09, 2017

    1,590,462.27 - 1,590,462.27 August 24,

    2017

    Page 32 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    24. Variation Orders

    Two variation order was approved during this reporting period.

    VO. No. Description VO

    Status USAID

    Approval date

    Variation Order

    Amount

    Time Extension

    Days

    VO-15-00008-

    GAZI-01

    Changes in Requirements, New Items, New Definitive Quantities, Correction of Typo, Sequential and Arithmetic Errors and Time Extension

    Approved August 3, 2016 176,084.76 $ 21

    VO-15-00008-

    GAZI-02

    The Use of Steel Pipes In lieu of Ductile Iron Pipes for Reservoir's Yard Piping

    Approved August 25, 2016 Zero Zero

    VO-15-00008-

    GAZI-03

    Changes in Requirements, New Definitive Quantities.

    Approved January 20, 2016 54,944.11 $ Zero

    VO-15-00008-

    GAZI-04

    Changes in Requirements, New Definitive Quantities.

    Approved May 24, 2016 (89,824.41) $ Zero

    VO-15-00008-

    GAZI-05

    Changes in Requirements, New Definitive Quantities.

    Approved August 3, 2017 14,352.44 $ Zero

    VO-15-00008-

    GAZI-06

    Extension of Time (Modification No. AID-294-TO-15-00008-02)

    Approved July 17, 2017 Zero 31

    VO-15-00008-

    GAZI-07

    Cost Time Extension and New Defini-tive Quantities

    Approved September 29,

    2017 591,921.86 $ 86

    VO-15-00008-

    GAZI-08

    Contract modification (Modification No. AID-294-TO-15-00008-03)

    Approved September 28,

    2017 591,921.86 $ 86

    25. Variation Order Requests

    VOR No. Description VO. No. Variation

    Order Amount

    Time Extension

    Days

    VOR-15-00008-GAZI-001-A Purchase and delivered the additional quantities of UPVC pipes fittings, restrained joints and FA

    001-A 41,133.00 $ Zero time Extension

    VOR-15-00008-GAZI-001-B Purchase and delivered the additional quantities of UPVC pipes fittings, restrained joints and FA

    001-B 40,533.00 $ Zero time Extension

    VOR-15-00008-GAZI-001-C Purchase and delivered the additional quantities of UPVC pipes fittings, restrained joints and FA

    001-C 35,993.00 $ Zero time Extension

    VOR-15-00008-GAZI-002-A Use of Steel Mini Guard In lieu of Concrete New Jersey Barriers

    002-A Zero Cost Zero time Extension

    VOR-15-00008-GAZI-002-B Use of Steel Mini Guard In lieu of Concrete New Jersey Barriers

    002-B Zero Cost Zero time Extension

    VOR-15-00008-GAZI-002-C Use of Steel Mini Guard In lieu of Concrete New Jersey Barriers

    002-C Zero Cost Zero time Extension

    Page 33 of 430

  • TO-15-00008 Construction Monthly Progress Report September 2017

    VOR-15-00008-GAZI-003-A Use of coloured PVC conduits for embedded installations instead of rigid schedule 40 PVC conduits

    003-A Zero Cost Zero time Extension

    VOR-15-00008-GAZI-003-B Use of coloured PVC conduits for embedded installations instead of rigid schedule 40 PVC conduits

    003-B Zero Cost Zero time Extension

    VOR-15-00008-GAZI-003-C Use of coloured PVC conduits for embedded installations instead of rigid schedule 40 PVC conduits

    003-C Saving

    (1,380.00) $ Zero time Extension

    VOR-15-00008-GAZI-004-A GFCI (Ground Fault Circuit Interrupter) Receptacles

    004-A Zero Cost Zero time Extension

    VOR-15-00008-GAZI-005-A The use of PE pipe PN12.5 instead of PVC-U pipe PN16 for Reservoir Drain Pipe

    005-A Zero Cost Zero time Extension

    VOR-15-00008-GAZI-005-B The use of HDPE pipe PN12.5 instead of PVC-U pipe PN16 for Reservoir Drain Pipe

    005-B Zero Cost Zero time Extension

    VOR-15-00008-GAZI-005-C The use of HDPE pipe PN12.5 instead of PVC-U pipe PN16 for Reservoir Drain Pipe

    005-C Zero Cost Zero time Extension

    VOR-15-00008-GAZI-006-A Impact of Walkthrough for Al Atatrah Supply and Distribution Pipelines

    006-A 32,587.5 $ Zero time Extension

    VOR-15-00008-GAZI-006-B Impact of Walkthrough for Al Atatrah Supply and Distribution Pipelines

    006-B 31337.5 $ Zero time Extension

    VOR-15-00008-GAZI-007-A Impact of Walkthrough for Nuseirat Supply and Distribution Pipelines

    007-A 127,175.00 $ Zero time Extension

    VOR-15-00008-GAZI-007-B Impact of Walkthrough for Nuseirat Supply and Distribution Pipelines

    007-B 105,300.00 $ Zero time Extension

    VOR-15-00008-GAZI-008-A Request of Time Extension to Compensate Excusable Delays

    008-A 11382.93 $ 13 Days

    VOR-15-00008-GAZI-008-B Request of Time Extension to Compensate Excusable Delays

    008-A 66300.00 $ 13 Days

    VOR-15-00008-GAZI-009-A The use of Gaza available sand materials and the calcareous sand material as fill-ing material (Kurkar) under structures.

    009-A Zero Cost Zero time Extension

    VOR-15-00008-GAZI-010-A Replace Pad-Mount Transformer by Pole Mount Transformer for Al Atatrah Project

    010-A 94,784.00 $ 21 Days

    VOR-15-00008-GAZI-010-B Replace Pad-Mount Transformer by Pole Mount Transformer for Al Atatrah Project

    010-B 89,810.00 $ 21 Days

    VOR-15-00008-GAZI-010-C Replace Pad-Mount Transformer by Pole Mount Transformer for Al Atatrah Project

    010-C 84,310.00 $ 21 Days

    VOR-15-00008-GAZI-010-D Replace Pad-Mount Transformer by Pole Mount Transformer for Al Atatrah Project

    010-C 79,170.00 $ 21 Days

    VOR-15-00008-GAZI-011-A Replace Pa