monthly progress report no.05 - june-2012
TRANSCRIPT
Asset Man
Asset Management Group (Wasl)
File: CoverCreated: 07-Apr-12Printed on 05/07/2012 at 08:05
June-2012
Al Muraqqabat Mixed Use Development
Monthly Progress Report
003 07-May-12
004 07-Jun-12
005 07-Jul-12
Monthly Project Progress Sameh Kandil
Monthly Project Progress
Monthly Project Progress
REV. DATE
Printed names here confirm that the document has been signed off approved, the original held by Document Control
Regards,
Raouf Ezzat
REASON FOR ISSUE PREPARED CHECKED APPROVED
Raouf EzzatProject Manager
File: CoverCreated: 07-Apr-12Printed on 05/07/2012 at 08:05
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
1.0 Table of Contents
2.0 PROJECT STATUS SUMMARY ....................................................................................................... 2
3.0 PROJECT DASH BOARD ................................................................................................................. 3
4.0 PROJECT S-CURVE ......................................................................................................................... 4
5.0 CONCRETE HISTOGRAM ................................................................................................................ 5
6.0 PROJECT PROGRAM UPDATE ..................................................................................................... 6
6.1 COMPLETED & IN PROGRESS ACTIVITIES ............................................................................................ 6 6.2 PACKGE PLANNED VS ACTUAL PERCENTAGES .................................................................................... 6 6.3 TWO MONTHS LOOKAHEAD PROGRAM ................................................................................................ 6
7.0 PROCUREMENT LOG ...................................................................................................................... 7
7.1 CIVIL AND ARCHITECTURAL LOG .......................................................................................................... 7 7.2 MEP AND SPECIALITY WORKS LOG .................................................................................................... 7
8.0 ENGINEERING LOG ......................................................................................................................... 8
8.1 CIVIL-ARCHITECTURAL-SPECIALITY-PS LOG ...................................................................................... 8 8.2 MEP LOG ......................................................................................................................................... 8
9.0 SAFETY REPORT ............................................................................................................................. 9
9.1 HSE PROGRESS STATUS .................................................................................................................. 9 9.2 MANHOURS AND FIRST AID HISTOGRAM.............................................................................................. 9
10.0 QUALITY REPORT ......................................................................................................................... 10
10.1 COMPRESSSIVE STRENGTH RESULT FOR CONCERTE ......................................................................... 10 10.2 NCR & SITE INSTRUCTIONS LOG ..................................................................................................... 10
11.0 FINANCIAL REPORT ...................................................................................................................... 11
11.1 SCHUDLE OF PAYMENT .................................................................................................................... 11 11.2 SUMMARY OF VO’S ........................................................................................................................... 11 11.3 SUMMARY OF CLAIMS ....................................................................................................................... 11 11.4 SUMMARY OF PROVISIONAL SUM ....................................................................................................... 11 11.5 FORECASTING OF MONTHLY INVOICES (BASELINE) ............................................................................. 11
12.0 PROGRESS PHOTOS ..................................................................................................................... 12
Any comments, questions, or concerns regarding this Status Report or the project in general should be directed to (Raouf Ezzat / Sameh Kandil, [email protected] / Sameh. [email protected])
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
2.0 PROJECT STATUS SUMMARY
Project Title : Al Muraqqabat Mixed Use Development Project No. : 269Location : Report No : 5Client : Asset Management Group (WASL) Period Ending : 30-Jun-12
1.0- Safety This Period Previous To DateN/A N/A N/A
151,580 479,090 630,670 / / /
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Monthly Report No.05 - June-2012
Dubai
N MiMonthly Report No - 05 (Up to 30-June-11)Lost Time Injury (LTI)
N/A N/A N/A
2.0-Quality NCR Status Issued by Client Internal Audits OperationalIssued by Suppliers
Issued by Subcontractor
Issued 8 - - - -Closed 7 - - - -Open 1 - - - -
* Safety figures are for Workers and Staff Manpower.
3.0- Executive Summary
Contract TypeContract Duration
Near Misses
Contract Value (AED)
Details
285,000,000 Lump Sum640 Days
This Period To Date4 0- Progress
Commencement Date as per Contract
1729310Activities Remaining to Start
% Time Elapsed
Completion date as per Contract
Activities in Progress
15-Feb-1215-Nov-13
10355873
Calendar Days ElapsedCalendar Days Remaining
13750321%
Activities Completed
Revise Completion date as per Approved EOTExpected Completion DateTotal Calendar Days (Contractual Duration)
Nil01-Feb-14
640
% Time RemainingTotal Number of Activities
79%
Planned Actual Planned Actual3.77% 2.88% 12.78% 13.54%
Staff Workers (Direct)Planned Actual Planned Actual
ASGC (Up to 30-June-12) 24 25 311 414
Total 25 414Change in Period
44 108
4.0- Progress
5.0- Manpower
Calculated Percentage
* The Planned Progress Percentage has been developed based on the Approved Program Rev.01 assigning a weight to each activity in the schedule.
AWI 205 Att. 1 Rev. 6 24 Oct. 2010 Page 1 of 2
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Monthly Report No.05 - June-2012
6.0- Significant Events 6.01-This Period:
Block A
1. Third floor slab works was casted on 18-June-2012.2. Works for fourth floor slab was started on 24-June-2012.3. Block works were started in B2,B1,Ground and first floor.4 Plaster works were started in B2
Construction
Block B
Block C
C1
C2
4. Plaster works were started in B2.
1. Columns from basement 1 to ground floor was completed.2. 1st floor slab was casted on 13-June-2012.3. Columns works,from ground to 1st floor, were started on 24-June-2012.4. Block works were started in B2.
1. 1st floor slab was casted on 30-June-2012.2. Curing work is in progress.
1. 1st floor Slab was casted on 25-June-2012.2. Columns and core walls works from ground to 1st floor were started on 28-June-2012.3. Block works were started in B2.
6.02- Areas of Concern - Late of issuing the ID drawings (IFC) and the conflict between Arch,MEP and ID
drawings.Furthermore a revised electrical load schedule was issued in June-2012.All of these delays and conflict will dramatically affect :-1- Submission the light and power drawings which are related to the approvals process to obtain the Wild Air.2- Procurement of electrical long lead items
AWI 205 Att. 1 Rev. 6 24 Oct. 2010 Page 2 of 2
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
3.0 PROJECT DASH BOARD
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATION
June
30 2012
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
File Name :-Progress Dashboard Page 1 of 5 Printed On :- 05/07/2012 at 09:30
Company Contact Baseline Completion DateForecast Completion Date Last Month
Mohammed Viquarrddin/Ali Al Khateeb Forecast Date at Current MonthVariance Days (Calendar Days)
Progress by Discipline%Pld %Act %Pld %Act
1.00 100.00% 3.77% 2.88% 12.78% 13.54% 0.8%1.10 General 2% 3.02% 2.37% 31.32% 21.51% ‐9.8%1.20 Engineering 4% 11.58% 12.49% 53.22% 37.70% ‐15.5%1.30 Procurement 6% 11.31% 3.03% 29.69% 10.28% ‐19.4%1.40 Construction 80% 3.20% 2.68% 10.27% 13.69% 3.4%1 50 H di O 8% 0 00% 0 00% 0 00% 0 00% 0 0%
15‐Nov‐13
d ‐ Progress of W
ork
Client WASL Abdullah Zarooni 30‐Dec‐13
Weight %This Period Cumulative
Lead Consultant Bel Yoahah 01‐Feb‐14Main Contractor ASGC Raouf Ezzat ‐78
Variance
Overall Progress
21.51%
37.70%
10.28%
13.69%
0 00%
General
Engineering
Procurement
Construction
Handing Over
Actual %
1.50 Handing Over 8% 0.00% 0.00% 0.00% 0.00% 0.0%
Weekly Project Dashb
oar
velopm
en
0.00%
56.68%
67.88%
77.84%
85.89%
89.99%
92.50%94.43%
96.54% 97.39% 98.61% 99.66%100.00%
61.43%
75.60%
85.36%90.85%
93.31%96.27% 97.19% 98.14% 99.32%
100.00%
60.00%
70.00%
80.00%
90.00%
100.00%
s % Early Monthly
Figure.1 ‐ Overall Project Progress
Al M
uraq
qaba
t Mixed
Use Dev
C
12.78%
17.07%20.93%
25.69%
33.73%
45.25%
9.33%12.41%
14.82%18.11%
22.86%
28.94%
38.11%
50.00%
13.54%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
Feb 12 Mar 12 Apr 12 May 12 Jun 12 Jul 12 Aug 12 Sep 12 Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13 Nov 13
% P
rogr
ess % Early Monthly
% Late Monthly
% Actual Monthly
% Accu. Early Monthly
% Accu. Late Monthly
% Accu. Actual
ASG
CFeb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13Months
File Name :-Progress Dashboard Page 1 of 5 Printed On :- 05/07/2012 at 09:30
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATIONCompany Contact Baseline Completion Date
June
30 2012
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
15‐Nov‐13
File Name :-Progress Dashboard Page 2 of 5 Printed On :- 05/07/2012 at 09:30
p y pForecast Completion Last Month
Mohammed Viquarrddin/Ali Al Khateeb Actual/ForecastDateVariance Days (Calendar Days)
Progress by Building Wise%Pld %Act %Pld %Act
1.00 Building ‐ A 21.73% 2.31% 2.89% 11.47% 14.29% 2.8%1.10 Civil Work 4.67% 10.36% 12.35% 52.98% 65.39% 12.4%1.20 Architectural 6.06% 0% 0.0% 0.0%1.30 MEP (Incl. LPG) 10.38% 0% 0.0% 0.0%1.40 Elevators 0.21% 0% 0.0% 0.0%1.50 External Facade 0.26% 0% 0.0% 0.0%1 60 Façade Lighting 0 11% 0% 0 0% 0 0% D
ashb
oard ‐ Progress of W
ork
Client WASL Abdullah Zarooni 30‐Dec‐13Lead Consultant Bel Yoahah 01‐Feb‐14Main Contractor ASGC Raouf Ezzat ‐78
Weight %This Period Cumulative
Variance
65.39%
Civil Work
Architectural
MEP (Incl. LPG)
Elevators
External Facade
Façade Lighting
Façade Cleaning
Actual Overall Progress %
1.60 Façade Lighting 0.11% 0% 0.0% 0.0%1.70 Façade Cleaning 0.01% 0% 0.0% 0.0%1.80 Garbage & Linen Chute 0.04% 0% 0.0% 0.0%
Weekly Project D
se Develop
men
t
52.98%
65.39%
%Pld %Act
Building ‐ A
Façade Cleaning
Garbage & Linen Chute
Figure.1 ‐ Planned Vs. Actual Progress for Block A
Al M
uraq
qaba
t Mixed
Us
ASG
C
Civil Work Architectural MEP (Incl. LPG) Elevators External Facade Façade Lighting Façade Cleaning Garbage & Linen Chute
0% 0% 0% 0% 0% 0% 0%
File Name :-Progress Dashboard Page 2 of 5 Printed On :- 05/07/2012 at 09:30
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATIONCompany Contact Baseline Completion Date
Forecast Completion Last MonthM h d Vi ddi /Ali Al Kh b A l/F D
Client WASL Abdullah Zarooni 15‐Nov‐13L d C lt t
June
30 2012
B l Y h h 01 F b 14
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
15‐Nov‐13
File Name :-Progress Dashboard Page 3 of 5 Printed On :- 05/07/2012 at 09:30
Mohammed Viquarrddin/Ali Al Khateeb Actual/ForecastDateVariance Days (Calendar Days)
Progress by Building Wise%Pld %Act %Pld %Act
2.00 Building ‐ B 28.29% 3.23% 2.92% 10.33% 14.35% 4.0%2.10 Civil Work 7.34% 12.47% 11.14% 39.83% 55.20% 15.4%2.20 Architectural 8.16% 0% 0.0% 0.0%2.30 MEP (Incl. LPG) 12.27% 0% 0.0% 0.0%2.40 Elevators 0.15% 0% 0.0% 0.0%2.50 External Facade 0.24% 0% 0.0% 0.0%2.60 Façade Lighting 0.08% 0% 0.0% 0.0%2.70 Façade Cleaning 0.01% 0% 0.0% 0.0%
Variance
Lead Consultant
Weight %This Period Cumulative
Bel Yoahah 01‐Feb‐14Main Contractor ASGC Raouf Ezzat ‐78
ct Dashb
oard ‐ Progress of W
ork
Actual Overall Progress %
55.20%
Civil Work
Architectural
MEP (Incl. LPG)
Elevators
External Facade
Façade Lighting
Façade Cleaning
Garbage & Linen Chute
Actual Overall Progress %
2.70 Façade Cleaning 0.01% 0% 0.0% 0.0%2.80 Garbage & Linen Chute 0.04% 0% 0.0% 0.0%
Use Develop
men
tWeekly Projec
g
3%
55.20%
%Pld %Act
Building ‐ B
Figure.2 ‐ Planned Vs. Actual Progress for Block B
ASG
CAl M
uraq
qaba
t Mixed
Civil Work Architectural MEP (Incl. LPG) Elevators External Facade Façade Lighting Façade Cleaning Garbage & Linen Chute
39.8
0% 0% 0% 0% 0% 0% 0%
A
File Name :-Progress Dashboard Page 3 of 5 Printed On :- 05/07/2012 at 09:30
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATIONCompany Contact Baseline Completion Date
Forecast Completion Last MonthM h d Vi ddi /Ali Al Kh b A l/F D
June
30 2012
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
15‐Nov‐13Client WASL Abdullah Zarooni 15‐Nov‐13L d C lt t B l Y h h 01 F b 14
File Name :-Progress Dashboard Page 4 of 5 Printed On :- 05/07/2012 at 09:30
Mohammed Viquarrddin/Ali Al Khateeb Actual/ForecastDateVariance Days (Calendar Days)
Progress by Building Wise%Pld %Act %Pld %Act
3.00 Building ‐ C 30.15% 3.80% 2.31% 9.34% 12.64% 3.3%3.10 Civil Work 8.19% 13.99% 8.43% 34.37% 46.45% 12.1%3.20 Architectural 10.57% 0% 0.0% 0.0%3.30 MEP (Incl. LPG) 10.58% 0% 0.0% 0.0%3.40 Elevators 0.39% 0% 0.0% 0.0%3.50 External Facade 0.26% 0% 0.0% 0.0%3.60 Façade Lighting 0.11% 0% 0.0% 0.0%3.70 Façade Cleaning 0.01% 0% 0.0% 0.0%
ASGC Raouf Ezzat ‐78
ject Dashb
oard ‐ Progress of W
orkLead Consultant Bel Yoahah 01‐Feb‐14
Main Contractor
Weight %This Period Cumulative
Variance Actual Overall Progress %
46.45%
Civil Work
Architectural
MEP (Incl. LPG)
Elevators
External Facade
Façade Lighting
Façade Cleaning
Garbage & Linen Chute
Actual Overall Progress %
3.70 Façade Cleaning 0.01% 0% 0.0% 0.0%3.80 Garbage & Linen Chute 0.04% 0% 0.0% 0.0%
Use Develop
men
tWeekly Proj
g
4.37%
46.45%
%Pld %Act
Building ‐ C
Figure.3 ‐ Planned Vs. Actual Progress for Block C
Al M
uraq
qaba
t Mixed
ASG
C
Civil Work Architectural MEP (Incl. LPG) Elevators External Facade Façade Lighting Façade Cleaning Garbage & Linen Chute
34
0% 0% 0% 0% 0% 0% 0%
A
File Name :-Progress Dashboard Page 4 of 5 Printed On :- 05/07/2012 at 09:30
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATIONCompany Contact Baseline Completion Date
June
30 2012
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
15‐Nov‐13
File Name :-Progress Dashboard Page 5 of 5 Printed On :- 05/07/2012 at 09:30
Forecast Completion Last MonthRaouf Ezzat Actual/ForecastDate
Variance Days (Calendar Days)
oard ‐ Progress of W
ork
Client WASL Abdullah Zarooni 15‐Nov‐13Lead Consultant Bel Yoahah 01‐Feb‐14Main Contractor ASGC Raouf Ezzat ‐78
pmen
tWeekly Project Dashb
oAl M
uraq
qaba
t Mixed
Use Develop
File Name :-Progress Dashboard Page 5 of 5 Printed On :- 05/07/2012 at 09:30
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
4.0 PROJECT S-CURVE
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Overall Progress S-Curve
85 89%
89.99%
92.50%94.43%
96.54% 97.39% 98.61% 99.66%100.00%
90.85%93.31%
96.27% 97.19% 98.14%99.32%
100.00%
90.00%
100.00%
File Name : Progress S-Curve Page 1 of 1 Printed On : 05/07/2012 at 09:05
45.25%
56.68%
67.88%
77.84%
85.89%
50.00%
61.43%
75.60%
85.36%
40.00%
50.00%
60.00%
70.00%
80.00%
% P
rogr
ess
% Early Monthly
% Late Monthly
% Actual Monthly
% Accu. Early Monthly
% Accu. Late Monthly
12.78%
17.07%
20.93%
25.69%
33.73%
9.33%
12.41%14.82%
18.11%
22.86%
28.94%
38.11%
13.54%
0.00%
10.00%
20.00%
30.00%
0 00%
Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13
Months
% Accu. Actual
Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13
% Early Monthly 0.79% 2.36% 2.78% 3.08% 3.77% 4.29% 3.86% 4.76% 8.04% 11.52% 11.43% 11.20% 9.96% 8.05% 4.10% 2.51% 1.93% 2.12% 0.85% 1.22% 1.05% 0.34%
% Accu. Early Monthly 0.79% 3.15% 5.93% 9.01% 12.78% 17.07% 20.93% 25.69% 33.73% 45.25% 56.68% 67.88% 77.84% 85.89% 89.99% 92.50% 94.43% 96.54% 97.39% 98.61% 99.66% 100.00%
% Late Monthly 0.32% 1.85% 1.88% 2.33% 2.95% 3.08% 2.41% 3.29% 4.75% 6.09% 9.17% 11.88% 11.44% 14.17% 9.76% 5.49% 2.46% 2.96% 0.92% 0.95% 1.18% 0.68%
% Accu. Late Monthly 0.32% 2.17% 4.05% 6.38% 9.33% 12.41% 14.82% 18.11% 22.86% 28.94% 38.11% 50.00% 61.43% 75.60% 85.36% 90.85% 93.31% 96.27% 97.19% 98.14% 99.32% 100.00%
Early Planned
Late Planned
Months
% Actual Monthly 0.80% 3.15% 3.64% 3.07% 2.88%
% Accu. Actual 0.80% 3.95% 7.59% 10.66% 13.54%Actual
File Name : Progress S-Curve Page 1 of 1 Printed On : 05/07/2012 at 09:05
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
5.0 CONCRETE HISTOGRAM
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Concrete Histogram
34,939.00
38,114.00
39,570.00 39,999.00 40,053.00
34,307.00
37,662.00
39,098.00 39,257.00 39,449.00 39,607.00 39,612.00 39,612.00 39,612.00 40,052.00
35,000
40,000
File Name : Commodoties Progress Page 1 of 1 Printed On : 05/07/2012 at 08:22
12 267 00
15,018.00
18,673.00
23,505.00
27,197.00
30,969.00
14,763.00
18,490.00
23,021.00
26,329.00
30,200.00
17,300.50
21,832.00
26,038.00
15,000
20,000
25,000
30,000
Qua
ntity
(m3)
Early Monthly
Late Monthly
Actual Monthly
Accu. Early Monthly
Accu. Late Monthly
Accu. Actual
F b 12 M 12 A 12 M 12 J 12 J l 12 A 12 S 12 O 12 N 12 D 12 J 13 F b 13 M 13 A 13 M 13 J 13 J l 13
12,267.00 11,872.00
3,129.50
10,904.00
0
5,000
10,000
Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13
Months
Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13
Early Monthly 1,167 4,894 6,206 2,751 3,655 4,832 3,692 3,772 3,970 3,175 1,456 429 54 - - - - -
Accu. Early Monthly 1,167.00 6,061.00 12,267.00 15,018.00 18,673.00 23,505.00 27,197.00 30,969.00 34,939.00 38,114.00 39,570.00 39,999.00 40,053.00
Late Monthly 557 4,350 6,965 2,891 3,727 4,531 3,308 3,871 4,107 3,355 1,436 159 192 158 5 - - 440
Accu. Late Monthly 557.00 4,907.00 11,872.00 14,763.00 18,490.00 23,021.00 26,329.00 30,200.00 34,307.00 37,662.00 39,098.00 39,257.00 39,449.00 39,607.00 39,612.00 39,612.00 39,612.00 40,052.00
Actual Monthly 3,129.50 7,774.50 6,396.50 4,531.50 4,206.0
Accu. Actual 3,129.50 10,904.00 17,300.50 21,832.00 26,038.00
Early Planned
Late Planned
Actual
File Name : Commodoties Progress Page 1 of 1 Printed On : 05/07/2012 at 08:22
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.1 COMPLETED & IN PROGRESS ACTIRIVITES
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Al MuraqqAl Muraqqabat Mixed Use Development 597 06-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 75.14% 93.12%
GeneralGeneral 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 100% 81.35%
Contractual Contractual Milestones 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 0% 0%
A1000 Project Commencement Date 0 15-Feb-12 A 15-Feb-12 15-Feb-12 0 100% 100%
A1050 Overall Duration of Phase 1 550 15-Feb-12 A 17-Aug-13 0 15-Feb-12 17-Aug-13 15-Feb-12 17-Aug-13 0 24.91% 24.91%
A1030 Completion Date of Phase 1 0 03-Nov-13* -64 17-Aug-13 17-Aug-13 0 0% 0%
A1020 Overall Duration of Phase 2 411 15-Feb-12 A 15-Nov-13 0 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 0 33.33% 0%
A1010 Completion Date of Phase 2 0 01-Feb-14* -78 15-Nov-13 15-Nov-13 0 0% 0%
Authorities AAuthorities Approvals 78 15-Feb-12 A 30-Jul-12 -63 15-Feb-12 16-May-12 15-Feb-12 16-May-12 100% 56%
Temporary PTemporary Power Connection 78 15-Feb-12 A 30-Jul-12 -63 15-Feb-12 16-May-12 15-Feb-12 16-May-12 100% 56%
MEP DrawingMEP Drawings & Fees 78 15-Feb-12 A 30-Jul-12 -63 15-Feb-12 16-May-12 15-Feb-12 16-May-12 100% 56%
A1348 Receipt of Design NOC for Electrical Drawings 0 15-Feb-12 A 15-Feb-12 15-Feb-12 0 100% 100%
A1358 Confirmation of RMU & Transformers Rooms Layout 0 15-Feb-12 A 15-Feb-12 15-Feb-12 0 100% 100%
A1516 Submission & Approval of MEP Shop Drawings 78 16-Feb-12 A 30-Jul-12 -63 16-Feb-12 16-May-12 16-Feb-12 16-May-12 0 100% 56%
Client SubmClient Submissions 0 10-Jun-12 A 10-Jun-12 A 28-May-12 28-May-12 28-May-12 28-May-12 0% 0%
Awarding ofAwarding of Provisional Sum Packages 0 10-Jun-12 A 10-Jun-12 A 28-May-12 28-May-12 28-May-12 28-May-12 0% 0%
A1456 Awarding of Kitchen Equipments Package to ASGC 0 10-Jun-12 A 28-May-12 28-May-12 0 100% 100%
A1466 Awarding of Laundry Equipments Package to ASGC 0 10-Jun-12 A 28-May-12 28-May-12 0 100% 100%
MobilizationMobilization 64 15-Feb-12 A 07-Jun-12 A 15-Feb-12 14-May-12 10-Mar-12 19-Jun-12 100% 100%
Project SiteProject Site 15 15-Feb-12 A 07-Jun-12 A 15-Feb-12 03-Mar-12 10-Mar-12 07-Apr-12 100% 100%
A5410 Installation of Fence 8 15-Feb-12 A 23-Feb-12 A 15-Feb-12 23-Feb-12 12-Mar-12 20-Mar-12 22 100% 100%
A5450 Installation of Site Offices 15 15-Feb-12 A 03-Mar-12 A 15-Feb-12 03-Mar-12 21-Mar-12 07-Apr-12 30 100% 100%
A5460 Installation of Generator 7 15-Feb-12 A 01-Mar-12 A 15-Feb-12 22-Feb-12 13-Mar-12 20-Mar-12 23 100% 100%
A5470 Installation of Septic Tank & Water Tank 7 23-Feb-12 A 01-Mar-12 A 23-Feb-12 01-Mar-12 21-Mar-12 28-Mar-12 23 100% 100%
A5480 Installation of Store Yard 10 15-Feb-12 A 26-Feb-12 A 15-Feb-12 26-Feb-12 21-Mar-12 01-Apr-12 30 100% 100%
A5490 Installation of Project Signboard 6 15-Feb-12 A 07-Jun-12 A 15-Feb-12 21-Feb-12 14-Mar-12 20-Mar-12 24 100% 100%
A8920 Installation of Workshop 10 15-Feb-12 A 26-Feb-12 A 15-Feb-12 26-Feb-12 10-Mar-12 20-Mar-12 20 100% 100%
A8950 Installation of Site Gate 5 15-Feb-12 A 26-Feb-12 A 15-Feb-12 20-Feb-12 15-Mar-12 20-Mar-12 25 100% 100%
Tower CraneTower Cranes 61 19-Feb-12 A 17-Apr-12 A 15-Mar-12 14-May-12 03-Apr-12 19-Jun-12 100% 100%
A5430 Installation of Tower Crane 2 12 16-Apr-12 A 17-Apr-12 A 09-Apr-12 22-Apr-12 05-Jun-12 19-Jun-12 49 100% 100%
A5440 Installation of Tower Crane 3 12 19-Feb-12 A 23-Feb-12 A 01-May-12 14-May-12 05-Jun-12 19-Jun-12 30 100% 100%
A5467 Installation of Tower Crane 4 12 22-Feb-12 A 25-Feb-12 A 15-Mar-12 28-Mar-12 30-May-12 12-Jun-12 65 100% 100%
A5420 Installation of Tower Crane 1 12 25-Feb-12 A 28-Feb-12 A 15-Mar-12 28-Mar-12 03-Apr-12 16-Apr-12 16 100% 100%
PreliminariesPreliminaries 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0% 0%
Monthly PreMonthly Preliminaries 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0% 0%
A1766 Preliminaries for Month of Feb-2012 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0 21.76% 21.76%
EngineerinEngineering 132 06-Feb-12 A 01-Oct-12 102 15-Feb-12 15-Jan-13 15-Feb-12 25-Mar-13 81.61% 91.08%
Shop DrawinShop Drawings 132 06-Feb-12 A 01-Oct-12 102 15-Feb-12 15-Jan-13 15-Feb-12 25-Mar-13 81.39% 90.78%
CivilCivil 129 06-Feb-12 A 01-Oct-12 102 15-Feb-12 15-Jan-13 15-Feb-12 25-Mar-13 51.91% 89.83%
GeneralGeneral 25 15-Feb-12 A 22-Mar-12 A 15-Feb-12 14-Mar-12 15-Feb-12 02-Apr-12 100% 100%
SubmissionSubmission 9 15-Feb-12 A 25-Feb-12 A 15-Feb-12 25-Feb-12 15-Feb-12 13-Mar-12 100% 100%A46740 Submission of Excavation Level 1 15-Feb-12 A 16-Feb-12 A 15-Feb-12 15-Feb-12 15-Feb-12 15-Feb-12 0 100% 100%
A46750 Submission of Water Proofing Details 2 15-Feb-12 A 20-Feb-12 A 15-Feb-12 16-Feb-12 19-Feb-12 20-Feb-12 3 100% 100%
A46760 Submission of Tower Crane Layout 7 18-Feb-12 A 25-Feb-12 A 18-Feb-12 25-Feb-12 06-Mar-12 13-Mar-12 15 100% 100%
A46770 Submission of Raft Construction Joint Layout 2 15-Feb-12 A 16-Feb-12 A 15-Feb-12 16-Feb-12 20-Feb-12 21-Feb-12 4 100% 100%
A46780 Submission of Retaining Wall Joint Layout 4 15-Feb-12 A 19-Feb-12 A 15-Feb-12 19-Feb-12 22-Feb-12 26-Feb-12 6 100% 100%ApprovalApproval 20 16-Feb-12 A 22-Mar-12 A 16-Feb-12 14-Mar-12 16-Feb-12 02-Apr-12 100% 100%A117180 Approval of Excavation Level 1 16-Feb-12 A 22-Feb-12 A 16-Feb-12 16-Feb-12 16-Feb-12 16-Feb-12 0 100% 100%
A117190 Approval of Water Proofing Details 2 19-Feb-12 A 22-Mar-12 A 19-Feb-12 20-Feb-12 21-Feb-12 22-Feb-12 2 100% 100%
A117200 Approval of Tower Crane Layout 14 26-Feb-12 A 14-Mar-12 A 26-Feb-12 14-Mar-12 14-Mar-12 02-Apr-12 13 100% 100%
A117210 Approval of Raft Construction Joint Layout 2 19-Feb-12 A 10-Mar-12 A 19-Feb-12 20-Feb-12 22-Feb-12 23-Feb-12 3 100% 100%
A117220 Approval of Retaining Wall Joint Layout 12 20-Feb-12 A 18-Mar-12 A 20-Feb-12 06-Mar-12 27-Feb-12 13-Mar-12 5 100% 100%
Hotel ApartemHotel Apartements (Block A) 129 15-Feb-12 A 30-Aug-12 153 15-Feb-12 21-Oct-12 16-Feb-12 21-Mar-13 61.51% 92.52%
Deep FoundDeep Foundation 7 15-Feb-12 A 22-Feb-12 A 15-Feb-12 23-Feb-12 16-Feb-12 23-Feb-12 100% 100%SubmissionSubmission 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 100% 100%A46720 Submission of Structural Dwgs. for Raft 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 1 100% 100%
ApprovalApproval 5 16-Feb-12 A 22-Feb-12 A 19-Feb-12 23-Feb-12 19-Feb-12 23-Feb-12 100% 100%A46730 Approval of Structural Dwgs. for Raft 5 16-Feb-12 A 22-Feb-12 A 19-Feb-12 23-Feb-12 19-Feb-12 23-Feb-12 0 100% 100%
1st Baseme1st Basement Floor Slab 37 15-Feb-12 A 18-Mar-12 A 19-Feb-12 25-Apr-12 20-Feb-12 14-Oct-12 100% 100%SubmissionSubmission 34 15-Feb-12 A 20-Feb-12 A 19-Feb-12 05-Apr-12 20-Feb-12 24-Sep-12 100% 100%A101060 Submission of Structural Dwgs. for Slab 3 15-Feb-12 A 20-Feb-12 A 23-Feb-12 26-Feb-12 23-Feb-12 26-Feb-12 0 100% 100%
A101070 Submission of Structural Dwgs. for Ret. Walls -Columns 3 15-Feb-12 A 15-Feb-12 A 19-Feb-12 21-Feb-12 20-Feb-12 22-Feb-12 1 100% 100%
A101080 Submission of Structural Dwgs. for Core Walls 2 15-Feb-12 A 15-Feb-12 A 23-Feb-12 25-Feb-12 27-Feb-12 28-Feb-12 3 100% 100%
A101090 Submission of Structural Dwgs. for Ramp 3 15-Feb-12 A 15-Feb-12 A 19-Feb-12 21-Feb-12 11-Mar-12 13-Mar-12 18 100% 100%
A101140 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 29-Mar-12 05-Apr-12 17-Sep-12 24-Sep-12 144 100% 100%ApprovalApproval 22 16-Feb-12 A 18-Mar-12 A 22-Feb-12 25-Apr-12 27-Feb-12 14-Oct-12 100% 100%A101100 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 18-Mar-12 A 27-Feb-12 15-Mar-12 27-Feb-12 15-Mar-12 0 100% 100%
A101110 Approval of Structural Dwgs. for Ret. Walls -Columns 10 16-Feb-12 A 16-Feb-12 A 22-Feb-12 06-Mar-12 29-Feb-12 13-Mar-12 5 100% 100%
A101120 Approval of Structural Dwgs. for Core Walls 10 16-Feb-12 A 29-Feb-12 A 26-Feb-12 08-Mar-12 29-Feb-12 13-Mar-12 3 100% 100%
A101130 Approval of Structural Dwgs. for Ramp 14 16-Feb-12 A 08-Mar-12 A 22-Feb-12 12-Mar-12 14-Mar-12 02-Apr-12 15 100% 100%
A101150 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 08-Mar-12 A 08-Apr-12 25-Apr-12 25-Sep-12 14-Oct-12 119 100% 100%Ground FloGround Floor Slab 38 15-Feb-12 A 27-Mar-12 A 17-Mar-12 27-May-12 17-Mar-12 17-Oct-12 100% 100%SubmissionSubmission 34 15-Feb-12 A 10-Mar-12 A 17-Mar-12 07-May-12 17-Mar-12 29-Sep-12 100% 100%A101160 Submission of Structural Dwgs. for Slab 4 15-Feb-12 A 15-Feb-12 A 26-Mar-12 29-Mar-12 27-Mar-12 31-Mar-12 1 100% 100%
A101170 Submission of Structural Dwgs. for Ret. Walls -Columns 7 21-Feb-12 A 10-Mar-12 A 17-Mar-12 24-Mar-12 17-Mar-12 24-Mar-12 0 100% 100%
A101180 Submission of Structural Dwgs. for Core Walls 7 21-Feb-12 A 10-Mar-12 A 17-Mar-12 24-Mar-12 18-Mar-12 25-Mar-12 1 100% 100%
A101240 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 30-Apr-12 07-May-12 22-Sep-12 29-Sep-12 121 100% 100%
A102200 Submission of Structural Dwgs. for Ramp 7 15-Feb-12 A 15-Feb-12 A 22-Mar-12 29-Mar-12 01-Apr-12 08-Apr-12 8 100% 100%ApprovalApproval 26 16-Feb-12 A 27-Mar-12 A 25-Mar-12 27-May-12 26-Mar-12 17-Oct-12 100% 100%A101200 Approval of Structural Dwgs. for Slab 12 16-Feb-12 A 27-Mar-12 A 01-Apr-12 16-Apr-12 01-Apr-12 16-Apr-12 0 100% 100%
A101210 Approval of Structural Dwgs. for Ret. Walls -Columns 14 13-Mar-12 A 22-Mar-12 A 25-Mar-12 11-Apr-12 26-Mar-12 12-Apr-12 1 100% 100%
A101220 Approval of Structural Dwgs. for Core Walls 14 11-Mar-12 A 19-Mar-12 A 25-Mar-12 11-Apr-12 26-Mar-12 12-Apr-12 1 100% 100%
A101250 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 08-Mar-12 A 08-May-12 27-May-12 30-Sep-12 17-Oct-12 100 100% 100%
A102210 Approval of Structural Dwgs. for Ramp 13 16-Feb-12 A 19-Mar-12 A 01-Apr-12 17-Apr-12 09-Apr-12 25-Apr-12 6 100% 100%1st Floor Sl1st Floor Slab 57 15-Feb-12 A 02-May-12 A 31-Mar-12 10-Jun-12 31-Mar-12 21-Oct-12 100% 100%SubmissionSubmission 33 15-Feb-12 A 08-Apr-12 A 31-Mar-12 21-May-12 31-Mar-12 01-Oct-12 100% 100%A101260 Submission of Structural Dwgs. for Slab 12 26-Mar-12 A 08-Apr-12 A 09-Apr-12 22-Apr-12 09-Apr-12 22-Apr-12 0 100% 100%
A101270 Submission of Structural Dwgs. for Columns 8 15-Feb-12 A 25-Feb-12 A 31-Mar-12 08-Apr-12 31-Mar-12 08-Apr-12 0 100% 100%
A101280 Submission of Structural Dwgs. for Core Walls 8 07-Mar-12 A 14-Mar-12 A 31-Mar-12 08-Apr-12 31-Mar-12 08-Apr-12 0 100% 100%
A101340 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 14-May-12 21-May-12 24-Sep-12 01-Oct-12 111 100% 100%ApprovalApproval 40 16-Feb-12 A 02-May-12 A 09-Apr-12 10-Jun-12 18-Apr-12 21-Oct-12 100% 100%A101300 Approval of Structural Dwgs. for Slab 14 09-Apr-12 A 02-May-12 A 23-Apr-12 10-May-12 23-Apr-12 10-May-12 0 100% 100%
A101310 Approval of Structural Dwgs. for Columns 14 26-Feb-12 A 05-Apr-12 A 09-Apr-12 26-Apr-12 18-Apr-12 07-May-12 7 100% 100%
A101320 Approval of Structural Dwgs. for Core Walls 14 15-Mar-12 A 27-Mar-12 A 09-Apr-12 26-Apr-12 18-Apr-12 07-May-12 7 100% 100%
A101350 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 22-May-12 10-Jun-12 02-Oct-12 21-Oct-12 92 100% 100%2nd Floor S2nd Floor Slab 73 15-Feb-12 A 22-May-12 A 21-Apr-12 05-Jul-12 21-Apr-12 01-Nov-12 94.05% 100%SubmissionSubmission 66 15-Feb-12 A 21-Apr-12 A 21-Apr-12 16-Jun-12 21-Apr-12 13-Oct-12 100% 100%A102220 Submission of Structural Dwgs. for Slab 14 03-Apr-12 A 21-Apr-12 A 05-May-12 20-May-12 05-May-12 20-May-12 0 100% 100%
A102230 Submission of Structural Dwgs. for Columns 5 06-Mar-12 A 14-Mar-12 A 21-Apr-12 25-Apr-12 21-Apr-12 25-Apr-12 0 100% 100%
A102240 Submission of Structural Dwgs. for Core Walls 7 01-Mar-12 A 10-Mar-12 A 26-Apr-12 03-May-12 26-Apr-12 03-May-12 0 100% 100%
A102280 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 09-Jun-12 16-Jun-12 06-Oct-12 13-Oct-12 99 100% 100%ApprovalApproval 60 16-Feb-12 A 22-May-12 A 26-Apr-12 05-Jul-12 03-May-12 01-Nov-12 91.07% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Overall Duration
Over
Submission & Approval of MEP Shop Drawings
Preli
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 1 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A102250 Approval of Structural Dwgs. for Slab 14 22-Apr-12 A 22-May-12 A 21-May-12 07-Jun-12 21-May-12 07-Jun-12 0 100% 100%
A102260 Approval of Structural Dwgs. for Columns 14 15-Mar-12 A 19-Apr-12 A 26-Apr-12 15-May-12 03-May-12 22-May-12 5 100% 100%
A102270 Approval of Structural Dwgs. for Core Walls 14 11-Mar-12 A 19-Mar-12 A 07-May-12 24-May-12 15-May-12 03-Jun-12 6 100% 100%
A102290 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 18-Jun-12 05-Jul-12 14-Oct-12 01-Nov-12 82 64.29% 100%3rd & 4th Fl3rd & 4th Floor Slab 74 15-Feb-12 A 13-Jun-12 A 14-May-12 01-Aug-12 14-May-12 08-Nov-12 69.05% 100%SubmissionSubmission 73 15-Feb-12 A 07-Jun-12 A 14-May-12 12-Jul-12 14-May-12 20-Oct-12 75% 100%A101360 Submission of Structural Dwgs. for Slab 14 26-Apr-12 A 07-Jun-12 A 30-May-12 14-Jun-12 31-May-12 16-Jun-12 1 100% 100%
A101370 Submission of Structural Dwgs. for Columns 9 27-Mar-12 A 01-Apr-12 A 14-May-12 23-May-12 14-May-12 23-May-12 0 100% 100%
A101380 Submission of Structural Dwgs. for Core Walls 9 18-Apr-12 A 22-Apr-12 A 14-May-12 23-May-12 15-May-12 24-May-12 1 100% 100%
A101440 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 05-Jul-12 12-Jul-12 13-Oct-12 20-Oct-12 83 0% 100%ApprovalApproval 61 16-Feb-12 A 13-Jun-12 A 24-May-12 01-Aug-12 03-Jun-12 08-Nov-12 66.07% 100%A101400 Approval of Structural Dwgs. for Slab 14 28-Apr-12 A 13-Jun-12 A 18-Jun-12 05-Jul-12 18-Jun-12 05-Jul-12 0 64.29% 100%
A101410 Approval of Structural Dwgs. for Columns 14 02-Apr-12 A 22-May-12 A 24-May-12 12-Jun-12 03-Jun-12 21-Jun-12 6 100% 100%
A101420 Approval of Structural Dwgs. for Core Walls 14 23-Apr-12 A 02-May-12 A 24-May-12 12-Jun-12 03-Jun-12 21-Jun-12 6 100% 100%
A101450 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 15-Jul-12 01-Aug-12 21-Oct-12 08-Nov-12 68 0% 100%5th & 6th Fl5th & 6th Floor Slab 120 15-Feb-12 A 15-Jul-12 109 30-Jun-12 12-Sep-12 30-Jun-12 25-Nov-12 2.38% 89.17%SubmissionSubmission 112 15-Feb-12 A 02-Jul-12 118 30-Jun-12 23-Aug-12 30-Jun-12 04-Nov-12 7.14% 97.5%A102390 Submission of Structural Dwgs. for Columns 7 19-Apr-12 A 18-Jun-12 A 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 0 14.29% 100%
A102400 Submission of Structural Dwgs. for Core Walls 7 29-Apr-12 A 02-Jul-12 24 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 0 14.29% 90%
A102380 Submission of Structural Dwgs. for Slab 12 11-Jun-12 A 13-Jun-12 A 10-Jul-12 23-Jul-12 10-Jul-12 23-Jul-12 0 0% 100%
A102440 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 14-Aug-12 23-Aug-12 28-Oct-12 04-Nov-12 60 0% 100%ApprovalApproval 99 16-Feb-12 A 15-Jul-12 91 08-Jul-12 12-Sep-12 17-Jul-12 25-Nov-12 0% 85%A102420 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 26-Jun-12 A 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 0% 100%
A102430 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 04-Jul-12 23 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 0% 90%
A102450 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 26-Aug-12 12-Sep-12 05-Nov-12 25-Nov-12 50 0% 100%
A102410 Approval of Structural Dwgs. for Slab 14 14-Jun-12 A 15-Jul-12 20 24-Jul-12 12-Aug-12 24-Jul-12 12-Aug-12 0 0% 50%7th Floor Sl7th Floor Slab 129 15-Feb-12 A 02-Aug-12 108 25-Jul-12 03-Oct-12 25-Jul-12 12-Dec-12 0% 70.83%SubmissionSubmission 112 15-Feb-12 A 07-Jul-12 124 25-Jul-12 15-Sep-12 25-Jul-12 21-Nov-12 0% 87.5%A102470 Submission of Structural Dwgs. for Columns 9 11-Jun-12 A 18-Jun-12 A 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0 0% 100%
A102480 Submission of Structural Dwgs. for Core Walls 9 11-Jun-12 A 07-Jul-12 37 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0 0% 50%
A102460 Submission of Structural Dwgs. for Slab 12 11-Jun-12 A 25-Jun-12 A 13-Aug-12 28-Aug-12 13-Aug-12 28-Aug-12 0 0% 100%
A102520 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 08-Sep-12 15-Sep-12 13-Nov-12 21-Nov-12 55 0% 100%ApprovalApproval 106 16-Feb-12 A 02-Aug-12 90 05-Aug-12 03-Oct-12 28-Aug-12 12-Dec-12 0% 62.5%A102500 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 28-Jun-12 A 05-Aug-12 26-Aug-12 28-Aug-12 16-Sep-12 15 0% 100%
A102530 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 16-Sep-12 03-Oct-12 22-Nov-12 12-Dec-12 47 0% 100%
A102510 Approval of Structural Dwgs. for Core Walls 14 13-Jun-12 A 16-Jul-12 42 05-Aug-12 26-Aug-12 28-Aug-12 16-Sep-12 15 0% 50%
A102490 Approval of Structural Dwgs. for Slab 14 26-Jun-12 A 02-Aug-12 31 29-Aug-12 17-Sep-12 29-Aug-12 17-Sep-12 0 0% 0%Roof Floor Roof Floor Slab 123 15-Feb-12 A 30-Aug-12 114 14-Aug-12 02-Oct-12 14-Aug-12 15-Jan-13 0% 66.67%SubmissionSubmission 114 15-Feb-12 A 21-Aug-12 76 14-Aug-12 12-Sep-12 14-Aug-12 27-Nov-12 0% 66.67%A101470 Submission of Structural Dwgs. for Columns 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%
A101480 Submission of Structural Dwgs. for Core Walls 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%
A101540 Submission of Structural Dwgs. for Staircase 9 15-Feb-12 A 15-Feb-12 A 03-Sep-12 12-Sep-12 18-Nov-12 27-Nov-12 62 0% 100%ApprovalApproval 101 16-Feb-12 A 30-Aug-12 95 27-Aug-12 02-Oct-12 13-Sep-12 15-Jan-13 0% 66.67%A101550 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 13-Sep-12 02-Oct-12 26-Dec-12 15-Jan-13 71 0% 100%
A101510 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%
A101520 Approval of Structural Dwgs. for Core Walls 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%Upper RoofUpper Roof Floor Slab 18 15-Feb-12 A 19-Apr-12 A 24-Sep-12 21-Oct-12 24-Feb-13 21-Mar-13 0% 100%SubmissionSubmission 7 15-Feb-12 A 15-Feb-12 A 24-Sep-12 01-Oct-12 24-Feb-13 03-Mar-13 0% 100%A101640 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 24-Sep-12 01-Oct-12 24-Feb-13 03-Mar-13 125 0% 100%
ApprovalApproval 14 16-Feb-12 A 19-Apr-12 A 02-Oct-12 21-Oct-12 04-Mar-13 21-Mar-13 0% 100%A101650 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 02-Oct-12 21-Oct-12 04-Mar-13 21-Mar-13 104 0% 100%
Hotel (Block Hotel (Block B) 124 06-Feb-12 A 01-Oct-12 81 15-Feb-12 15-Jan-13 23-Feb-12 28-Feb-13 41.89% 88.92%
Deep FoundDeep Foundation 19 15-Feb-12 A 22-Feb-12 A 15-Feb-12 07-Mar-12 23-Feb-12 20-Mar-12 100% 100%SubmissionSubmission 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 23-Feb-12 26-Feb-12 100% 100%A102540 Submission of Structural Dwgs. for Raft 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 23-Feb-12 26-Feb-12 7 100% 100%
ApprovalApproval 14 18-Feb-12 A 22-Feb-12 A 19-Feb-12 07-Mar-12 01-Mar-12 20-Mar-12 100% 100%A102550 Approval of Structural Dwgs. for Raft 14 18-Feb-12 A 22-Feb-12 A 19-Feb-12 07-Mar-12 01-Mar-12 20-Mar-12 9 100% 100%
1st Baseme1st Basement Floor Slab 56 15-Feb-12 A 31-Mar-12 A 10-Mar-12 18-Jun-12 10-Mar-12 13-Nov-12 100% 100%SubmissionSubmission 40 15-Feb-12 A 20-Feb-12 A 10-Mar-12 28-May-12 10-Mar-12 23-Oct-12 100% 100%A104100 Submission of Structural Dwgs. for Water Tank 3 15-Feb-12 A 20-Feb-12 A 10-Mar-12 12-Mar-12 18-Apr-12 21-Apr-12 34 100% 100%
A102560 Submission of Structural Dwgs. for Slab 13 15-Feb-12 A 20-Feb-12 A 10-Apr-12 24-Apr-12 10-Apr-12 24-Apr-12 0 100% 100%
A102570 Submission of Structural Dwgs. for Ret. Walls -Columns 3 15-Feb-12 A 15-Feb-12 A 10-Mar-12 12-Mar-12 10-Mar-12 12-Mar-12 0 100% 100%
A102580 Submission of Structural Dwgs. for Core Walls 4 15-Feb-12 A 15-Feb-12 A 04-Apr-12 08-Apr-12 04-Apr-12 08-Apr-12 0 100% 100%
A102590 Submission of Structural Dwgs. for Ramp 12 15-Feb-12 A 16-Feb-12 A 10-Mar-12 22-Mar-12 29-Mar-12 11-Apr-12 17 100% 100%
A102640 Submission of Structural Dwgs. for Staircase 12 15-Feb-12 A 20-Feb-12 A 15-May-12 28-May-12 10-Oct-12 23-Oct-12 124 100% 100%ApprovalApproval 37 16-Feb-12 A 31-Mar-12 A 13-Mar-12 18-Jun-12 12-Apr-12 13-Nov-12 100% 100%A104110 Approval of Structural Dwgs. for Water Tank 14 21-Feb-12 A 10-Mar-12 A 13-Mar-12 01-Apr-12 22-Apr-12 09-May-12 28 100% 100%
A102600 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 31-Mar-12 A 25-Apr-12 14-May-12 25-Apr-12 14-May-12 0 100% 100%
A102610 Approval of Structural Dwgs. for Ret. Walls -Columns 13 16-Feb-12 A 16-Feb-12 A 13-Mar-12 29-Mar-12 15-Apr-12 01-May-12 23 100% 100%
A102620 Approval of Structural Dwgs. for Core Walls 14 16-Feb-12 A 29-Feb-12 A 09-Apr-12 26-Apr-12 23-Apr-12 10-May-12 10 100% 100%
A102630 Approval of Structural Dwgs. for Ramp 14 18-Feb-12 A 28-Mar-12 A 25-Mar-12 11-Apr-12 12-Apr-12 01-May-12 14 100% 100%
A102650 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 29-May-12 18-Jun-12 24-Oct-12 13-Nov-12 103 100% 100%Ground FloGround Floor Slab 51 14-Feb-12 A 01-May-12 A 29-Apr-12 25-Jul-12 29-Apr-12 19-Nov-12 80.95% 100%SubmissionSubmission 41 14-Feb-12 A 07-Apr-12 A 29-Apr-12 07-Jul-12 29-Apr-12 29-Oct-12 82.86% 100%A102720 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 30-Jun-12 07-Jul-12 20-Oct-12 29-Oct-12 94 14.29% 100%
A102680 Submission of Structural Dwgs. for Core Walls 7 07-Mar-12 A 01-Apr-12 A 14-May-12 21-May-12 14-May-12 21-May-12 0 100% 100%
A103060 Submission of Structural Dwgs. for Ramp 7 01-Apr-12 A 07-Apr-12 A 29-Apr-12 06-May-12 28-May-12 04-Jun-12 25 100% 100%
A102660 Submission of Structural Dwgs. for Slab 10 15-Mar-12 A 26-Mar-12 A 19-May-12 29-May-12 19-May-12 29-May-12 0 100% 100%
A102670 Submission of Structural Dwgs. for Ret. Walls -Columns 7 07-Mar-12 A 18-Mar-12 A 29-Apr-12 06-May-12 29-Apr-12 06-May-12 0 100% 100%ApprovalApproval 37 21-Feb-12 A 01-May-12 A 07-May-12 25-Jul-12 24-May-12 19-Nov-12 80% 100%A102690 Approval of Structural Dwgs. for Slab 14 27-Mar-12 A 26-Apr-12 A 30-May-12 19-Jun-12 30-May-12 19-Jun-12 0 100% 100%
A102700 Approval of Structural Dwgs. for Ret. Walls -Columns 14 19-Mar-12 A 01-May-12 A 07-May-12 24-May-12 24-May-12 12-Jun-12 13 100% 100%
A102710 Approval of Structural Dwgs. for Core Walls 14 01-Apr-12 A 01-May-12 A 22-May-12 10-Jun-12 27-May-12 13-Jun-12 3 100% 100%
A102730 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 08-Jul-12 25-Jul-12 30-Oct-12 19-Nov-12 79 0% 100%
A103070 Approval of Structural Dwgs. for Ramp 14 08-Apr-12 A 21-Apr-12 A 07-May-12 24-May-12 05-Jun-12 25-Jun-12 21 100% 100%1st Floor Sl1st Floor Slab 70 06-Feb-12 A 16-Jun-12 A 24-May-12 02-Sep-12 24-May-12 02-Jan-13 52.88% 100%SubmissionSubmission 52 06-Feb-12 A 03-Jun-12 A 24-May-12 11-Aug-12 24-May-12 12-Dec-12 72.92% 100%A102740 Submission of Structural Dwgs. for Slab 12 25-Apr-12 A 05-May-12 A 18-Jun-12 01-Jul-12 18-Jun-12 01-Jul-12 0 91.67% 100%
A102750 Submission of Structural Dwgs. for Columns 7 06-Feb-12 A 25-Feb-12 A 24-May-12 31-May-12 24-May-12 31-May-12 0 100% 100%
A102760 Submission of Structural Dwgs. for Core Walls 7 24-Apr-12 A 02-May-12 A 06-Jun-12 13-Jun-12 06-Jun-12 13-Jun-12 0 100% 100%
A102800 Submission of Structural Dwgs. for Staircase 7 20-Feb-12 A 03-Jun-12 A 04-Aug-12 11-Aug-12 05-Dec-12 12-Dec-12 100 0% 100%ApprovalApproval 53 21-Feb-12 A 16-Jun-12 A 03-Jun-12 02-Sep-12 21-Jun-12 02-Jan-13 42.86% 100%A102770 Approval of Structural Dwgs. for Slab 14 06-May-12 A 16-Jun-12 A 02-Jul-12 19-Jul-12 02-Jul-12 19-Jul-12 0 0% 100%
A102780 Approval of Structural Dwgs. for Columns 14 26-Feb-12 A 24-May-12 A 03-Jun-12 21-Jun-12 21-Jun-12 10-Jul-12 13 100% 100%
A102790 Approval of Structural Dwgs. for Core Walls 14 03-May-12 A 14-May-12 A 14-Jun-12 04-Jul-12 25-Jun-12 12-Jul-12 6 71.43% 100%
A102810 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 16-Jun-12 A 12-Aug-12 02-Sep-12 13-Dec-12 02-Jan-13 84 0% 100%2nd Floor S2nd Floor Slab 71 13-Feb-12 A 21-Jun-12 A 20-Jun-12 04-Oct-12 20-Jun-12 28-Feb-13 9.52% 100%SubmissionSubmission 55 13-Feb-12 A 07-Jun-12 A 20-Jun-12 16-Sep-12 20-Jun-12 10-Feb-13 25% 100%A103080 Submission of Structural Dwgs. for Slab 12 23-May-12 A 07-Jun-12 A 10-Jul-12 23-Jul-12 10-Jul-12 23-Jul-12 0 0% 100%
A103090 Submission of Structural Dwgs. for Columns 7 06-Mar-12 A 14-Mar-12 A 20-Jun-12 27-Jun-12 20-Jun-12 27-Jun-12 0 100% 100%
A103100 Submission of Structural Dwgs. for Core Walls 7 25-Apr-12 A 24-May-12 A 01-Jul-12 08-Jul-12 01-Jul-12 08-Jul-12 0 0% 100%
A103140 Submission of Structural Dwgs. for Staircase 7 13-Feb-12 A 20-Feb-12 A 09-Sep-12 16-Sep-12 03-Feb-13 10-Feb-13 120 0% 100%ApprovalApproval 54 21-Feb-12 A 21-Jun-12 A 28-Jun-12 04-Oct-12 17-Jul-12 28-Feb-13 1.79% 100%A103110 Approval of Structural Dwgs. for Slab 14 24-May-12 A 21-Jun-12 A 24-Jul-12 12-Aug-12 24-Jul-12 12-Aug-12 0 0% 100%
A103120 Approval of Structural Dwgs. for Columns 14 15-Mar-12 A 04-Jun-12 A 28-Jun-12 17-Jul-12 17-Jul-12 05-Aug-12 13 7.14% 100%
A103130 Approval of Structural Dwgs. for Core Walls 14 26-May-12 A 04-Jun-12 A 09-Jul-12 26-Jul-12 17-Jul-12 05-Aug-12 6 0% 100%
A103150 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 17-Sep-12 04-Oct-12 11-Feb-13 28-Feb-13 100 0% 100%3rd & 4th Fl3rd & 4th Floor Slab 107 14-Feb-12 A 14-Aug-12 162 16-Jul-12 29-Oct-12 16-Jul-12 28-Feb-13 0% 79.17%SubmissionSubmission 100 14-Feb-12 A 05-Aug-12 170 16-Jul-12 08-Oct-12 16-Jul-12 10-Feb-13 0% 87.5%A102830 Submission of Structural Dwgs. for Columns 7 08-Apr-12 A 07-Jun-12 A 16-Jul-12 23-Jul-12 16-Jul-12 23-Jul-12 0 0% 100%
A102820 Submission of Structural Dwgs. for Slab 11 14-Jun-12 A 20-Jun-12 A 01-Aug-12 13-Aug-12 01-Aug-12 13-Aug-12 0 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Submission of Structural Dwgs. for Core Walls
b
Approval of Structural Dwgs. for Core Walls
b Approval of Structural Dwgs. for Slab
s
s Submission of Structural Dwgs. for Core Walls
b
s
s Approval of Structural Dwgs. for Core Walls
ab Approval of Structural Dwgs. for Slab
ns Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
b
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 2 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A102840 Submission of Structural Dwgs. for Core Walls 8 11-Jun-12 A 05-Aug-12 12 23-Jul-12 31-Jul-12 23-Jul-12 31-Jul-12 0 0% 50%
A102880 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 01-Oct-12 08-Oct-12 03-Feb-13 10-Feb-13 101 0% 100%ApprovalApproval 84 21-Feb-12 A 14-Aug-12 135 26-Jul-12 29-Oct-12 09-Aug-12 28-Feb-13 0% 75%A102860 Approval of Structural Dwgs. for Columns 14 09-Apr-12 A 16-Jun-12 A 26-Jul-12 14-Aug-12 09-Aug-12 30-Aug-12 10 0% 100%
A102890 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 09-Oct-12 29-Oct-12 11-Feb-13 28-Feb-13 84 0% 100%
A102850 Approval of Structural Dwgs. for Slab 14 16-Jun-12 A 14-Aug-12 13 14-Aug-12 04-Sep-12 14-Aug-12 04-Sep-12 0 0% 50%
A102870 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 14-Aug-12 10 01-Aug-12 22-Aug-12 09-Aug-12 30-Aug-12 6 0% 50%5th & 6th Fl5th & 6th Floor Slab 110 14-Feb-12 A 28-Aug-12 152 09-Aug-12 05-Dec-12 09-Aug-12 27-Feb-13 0% 62.5%SubmissionSubmission 110 14-Feb-12 A 07-Aug-12 162 09-Aug-12 13-Nov-12 09-Aug-12 09-Feb-13 0% 68.75%A103180 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 05-Aug-12 30 18-Aug-12 28-Aug-12 18-Aug-12 28-Aug-12 0 0% 50%
A103170 Submission of Structural Dwgs. for Columns 8 19-Apr-12 A 07-Aug-12 16 09-Aug-12 18-Aug-12 09-Aug-12 18-Aug-12 0 0% 25%
A103160 Submission of Structural Dwgs. for Slab 12 26-Jun-12 A 30-Jun-12 A 06-Sep-12 19-Sep-12 06-Sep-12 19-Sep-12 0 0% 100%
A103220 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 06-Nov-12 13-Nov-12 02-Feb-13 09-Feb-13 71 0% 100%ApprovalApproval 49 21-Feb-12 A 28-Aug-12 127 23-Aug-12 05-Dec-12 17-Sep-12 27-Feb-13 0% 58.33%A103230 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 14-Nov-12 05-Dec-12 10-Feb-13 27-Feb-13 58 0% 100%
A103210 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 15-Aug-12 34 30-Aug-12 18-Sep-12 17-Sep-12 04-Oct-12 12 0% 50%
A103200 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 28-Aug-12 28 23-Aug-12 11-Sep-12 17-Sep-12 04-Oct-12 17 0% 25%7th Floor Sl7th Floor Slab 104 14-Feb-12 A 17-Sep-12 80 13-Sep-12 15-Jan-13 13-Sep-12 27-Feb-13 0% 66.67%SubmissionSubmission 93 14-Feb-12 A 06-Sep-12 80 13-Sep-12 25-Dec-12 13-Sep-12 09-Feb-13 0% 66.67%A103250 Submission of Structural Dwgs. for Columns 7 11-Jun-12 A 06-Sep-12 16 13-Sep-12 20-Sep-12 13-Sep-12 20-Sep-12 0 0% 50%
A103260 Submission of Structural Dwgs. for Core Walls 7 11-Jun-12 A 06-Sep-12 20 22-Sep-12 29-Sep-12 22-Sep-12 29-Sep-12 0 0% 50%
A103300 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 18-Dec-12 25-Dec-12 02-Feb-13 09-Feb-13 37 0% 100%ApprovalApproval 81 21-Feb-12 A 17-Sep-12 66 23-Sep-12 15-Jan-13 18-Oct-12 27-Feb-13 0% 66.67%A103280 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 17-Sep-12 38 23-Sep-12 10-Oct-12 21-Oct-12 08-Nov-12 20 0% 50%
A103290 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 17-Sep-12 37 30-Sep-12 17-Oct-12 18-Oct-12 07-Nov-12 14 0% 50%
A103310 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 26-Dec-12 15-Jan-13 10-Feb-13 27-Feb-13 30 0% 100%Roof Floor Roof Floor Slab 110 14-Feb-12 A 01-Oct-12 118 03-Oct-12 25-Nov-12 03-Oct-12 27-Feb-13 0% 75%SubmissionSubmission 99 14-Feb-12 A 22-Sep-12 118 03-Oct-12 04-Nov-12 03-Oct-12 09-Feb-13 0% 75%A102910 Submission of Structural Dwgs. for Columns 7 18-Jun-12 A 22-Sep-12 16 03-Oct-12 10-Oct-12 03-Oct-12 10-Oct-12 0 0% 50%
A102960 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 28-Oct-12 04-Nov-12 02-Feb-13 09-Feb-13 79 0% 100%ApprovalApproval 86 21-Feb-12 A 01-Oct-12 99 11-Oct-12 25-Nov-12 30-Oct-12 27-Feb-13 0% 75%A102940 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 01-Oct-12 33 11-Oct-12 31-Oct-12 30-Oct-12 19-Nov-12 12 0% 50%
A102970 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 05-Nov-12 25-Nov-12 10-Feb-13 27-Feb-13 65 0% 100%
Residentail (BResidentail (Block C) 125 15-Feb-12 A 03-Sep-12 126 15-Feb-12 24-Dec-12 26-Feb-12 25-Mar-13 46.32% 86.72%
Deep FoundDeep Foundation 8 15-Feb-12 A 29-Feb-12 A 15-Feb-12 23-Feb-12 26-Feb-12 20-Mar-12 100% 100%SubmissionSubmission 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 26-Feb-12 28-Feb-12 100% 100%A103320 Submission of Structural Dwgs. for Raft 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 26-Feb-12 28-Feb-12 9 100% 100%
ApprovalApproval 5 17-Feb-12 A 29-Feb-12 A 19-Feb-12 23-Feb-12 14-Mar-12 20-Mar-12 100% 100%A103330 Approval of Structural Dwgs. for Raft 5 17-Feb-12 A 29-Feb-12 A 19-Feb-12 23-Feb-12 14-Mar-12 20-Mar-12 18 100% 100%
1st Baseme1st Basement Floor Slab 38 15-Feb-12 A 31-Mar-12 A 08-Mar-12 05-Jun-12 08-Mar-12 08-Nov-12 100% 100%SubmissionSubmission 37 15-Feb-12 A 20-Feb-12 A 08-Mar-12 16-May-12 08-Mar-12 20-Oct-12 100% 100%A103340 Submission of Structural Dwgs. for Slab 12 15-Feb-12 A 20-Feb-12 A 04-Apr-12 17-Apr-12 04-Apr-12 17-Apr-12 0 100% 100%
A103350 Submission of Structural Dwgs. for Ret. Walls -Columns 7 15-Feb-12 A 16-Feb-12 A 08-Mar-12 15-Mar-12 08-Mar-12 15-Mar-12 0 100% 100%
A103360 Submission of Structural Dwgs. for Core Walls 7 15-Feb-12 A 16-Feb-12 A 03-Apr-12 10-Apr-12 03-Apr-12 10-Apr-12 0 100% 100%
A103370 Submission of Structural Dwgs. for Water Tank 7 15-Feb-12 A 15-Feb-12 A 08-Mar-12 15-Mar-12 27-Mar-12 03-Apr-12 16 100% 100%
A103420 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 09-May-12 16-May-12 13-Oct-12 20-Oct-12 131 100% 100%ApprovalApproval 26 16-Feb-12 A 31-Mar-12 A 18-Mar-12 05-Jun-12 08-Apr-12 08-Nov-12 100% 100%A103380 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 22-Mar-12 A 18-Apr-12 07-May-12 18-Apr-12 07-May-12 0 100% 100%
A103390 Approval of Structural Dwgs. for Ret. Walls -Columns 14 18-Feb-12 A 19-Feb-12 A 18-Mar-12 04-Apr-12 11-Apr-12 30-Apr-12 18 100% 100%
A103400 Approval of Structural Dwgs. for Core Walls 14 18-Feb-12 A 21-Feb-12 A 11-Apr-12 30-Apr-12 12-Apr-12 01-May-12 1 100% 100%
A103410 Approval of Structural Dwgs. for Water Tank 14 16-Feb-12 A 10-Mar-12 A 18-Mar-12 04-Apr-12 08-Apr-12 25-Apr-12 15 100% 100%
A103430 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 17-May-12 05-Jun-12 21-Oct-12 08-Nov-12 108 100% 100%Ground FloGround Floor Slab 48 15-Feb-12 A 11-Apr-12 A 15-Apr-12 01-Jul-12 15-Apr-12 21-Feb-13 98.81% 100%SubmissionSubmission 37 15-Feb-12 A 18-Mar-12 A 15-Apr-12 10-Jun-12 15-Apr-12 03-Feb-13 100% 100%A103440 Submission of Structural Dwgs. for Slab 12 01-Mar-12 A 18-Mar-12 A 10-May-12 23-May-12 10-May-12 23-May-12 0 100% 100%
A103450 Submission of Structural Dwgs. for Ret. Walls -Columns 7 06-Mar-12 A 12-Mar-12 A 15-Apr-12 22-Apr-12 15-Apr-12 22-Apr-12 0 100% 100%
A103460 Submission of Structural Dwgs. for Core Walls 7 06-Mar-12 A 14-Mar-12 A 29-Apr-12 06-May-12 10-May-12 17-May-12 10 100% 100%
A103500 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 03-Jun-12 10-Jun-12 27-Jan-13 03-Feb-13 195 100% 100%ApprovalApproval 35 19-Feb-12 A 11-Apr-12 A 23-Apr-12 01-Jul-12 21-May-12 21-Feb-13 98.21% 100%A103470 Approval of Structural Dwgs. for Slab 14 19-Mar-12 A 11-Apr-12 A 24-May-12 12-Jun-12 24-May-12 12-Jun-12 0 100% 100%
A103480 Approval of Structural Dwgs. for Ret. Walls -Columns 14 13-Mar-12 A 29-Mar-12 A 23-Apr-12 10-May-12 21-May-12 07-Jun-12 20 100% 100%
A103490 Approval of Structural Dwgs. for Core Walls 14 15-Mar-12 A 27-Mar-12 A 07-May-12 24-May-12 21-May-12 07-Jun-12 10 100% 100%
A103510 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 11-Jun-12 01-Jul-12 04-Feb-13 21-Feb-13 162 92.86% 100%1st Floor Sl1st Floor Slab 52 15-Feb-12 A 26-May-12 A 16-May-12 02-Aug-12 16-May-12 12-Dec-12 69.05% 100%SubmissionSubmission 44 15-Feb-12 A 18-Apr-12 A 16-May-12 15-Jul-12 16-May-12 21-Nov-12 75% 100%A103520 Submission of Structural Dwgs. for Slab 12 02-Apr-12 A 18-Apr-12 A 02-Jun-12 14-Jun-12 03-Jun-12 16-Jun-12 1 100% 100%
A103530 Submission of Structural Dwgs. for Columns 7 13-Mar-12 A 25-Mar-12 A 16-May-12 23-May-12 16-May-12 23-May-12 0 100% 100%
A103540 Submission of Structural Dwgs. for Core Walls 7 14-Mar-12 A 28-Mar-12 A 26-May-12 02-Jun-12 27-May-12 03-Jun-12 1 100% 100%
A103580 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 08-Jul-12 15-Jul-12 13-Nov-12 21-Nov-12 106 0% 100%ApprovalApproval 38 19-Feb-12 A 26-May-12 A 24-May-12 02-Aug-12 12-Jun-12 12-Dec-12 66.07% 100%A103550 Approval of Structural Dwgs. for Slab 14 19-Apr-12 A 26-May-12 A 18-Jun-12 05-Jul-12 18-Jun-12 05-Jul-12 0 64.29% 100%
A103560 Approval of Structural Dwgs. for Columns 14 26-Mar-12 A 07-Apr-12 A 24-May-12 12-Jun-12 12-Jun-12 02-Jul-12 13 100% 100%
A103570 Approval of Structural Dwgs. for Core Walls 14 29-Mar-12 A 08-Apr-12 A 03-Jun-12 21-Jun-12 12-Jun-12 02-Jul-12 7 100% 100%
A103590 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 11-Apr-12 A 16-Jul-12 02-Aug-12 22-Nov-12 12-Dec-12 89 0% 100%2nd Floor S2nd Floor Slab 77 15-Feb-12 A 19-Jun-12 A 09-Jun-12 29-Aug-12 09-Jun-12 14-Mar-13 44.35% 100%SubmissionSubmission 52 15-Feb-12 A 11-Jun-12 A 09-Jun-12 07-Aug-12 09-Jun-12 24-Feb-13 68.75% 100%A103860 Submission of Structural Dwgs. for Slab 12 23-Apr-12 A 11-Jun-12 A 20-Jun-12 03-Jul-12 20-Jun-12 03-Jul-12 0 75% 100%
A103870 Submission of Structural Dwgs. for Columns 7 12-Apr-12 A 17-Apr-12 A 09-Jun-12 16-Jun-12 09-Jun-12 16-Jun-12 0 100% 100%
A103880 Submission of Structural Dwgs. for Core Walls 7 12-Apr-12 A 17-Apr-12 A 09-Jun-12 16-Jun-12 20-Jun-12 27-Jun-12 9 100% 100%
A103920 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 31-Jul-12 07-Aug-12 17-Feb-13 24-Feb-13 164 0% 100%ApprovalApproval 59 19-Feb-12 A 19-Jun-12 A 18-Jun-12 29-Aug-12 01-Jul-12 14-Mar-13 32.14% 100%A103890 Approval of Structural Dwgs. for Slab 14 24-Apr-12 A 19-Jun-12 A 04-Jul-12 23-Jul-12 04-Jul-12 23-Jul-12 0 0% 100%
A103900 Approval of Structural Dwgs. for Columns 14 18-Apr-12 A 01-May-12 A 18-Jun-12 05-Jul-12 01-Jul-12 18-Jul-12 9 64.29% 100%
A103910 Approval of Structural Dwgs. for Core Walls 14 18-Apr-12 A 01-May-12 A 18-Jun-12 05-Jul-12 02-Jul-12 19-Jul-12 10 64.29% 100%
A103930 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 08-Aug-12 29-Aug-12 25-Feb-13 14-Mar-13 136 0% 100%3rd & 4th Fl3rd & 4th Floor Slab 111 15-Feb-12 A 24-Jul-12 188 26-Jun-12 26-Sep-12 26-Jun-12 10-Mar-13 8.33% 75%SubmissionSubmission 101 15-Feb-12 A 04-Jul-12 205 26-Jun-12 08-Sep-12 26-Jun-12 18-Feb-13 25% 87.5%A103610 Submission of Structural Dwgs. for Columns 8 08-Apr-12 A 20-Jun-12 A 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 50% 100%
A103600 Submission of Structural Dwgs. for Slab 13 26-Apr-12 A 11-Jun-12 A 08-Jul-12 22-Jul-12 08-Jul-12 22-Jul-12 0 0% 100%
A103660 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 01-Sep-12 08-Sep-12 11-Feb-13 18-Feb-13 134 0% 100%
A103620 Submission of Structural Dwgs. for Core Walls 8 20-Jun-12 A 04-Jul-12 9 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 50% 50%ApprovalApproval 87 19-Feb-12 A 24-Jul-12 156 05-Jul-12 26-Sep-12 16-Jul-12 10-Mar-13 0% 68.75%A103630 Approval of Structural Dwgs. for Slab 14 28-Apr-12 A 25-Jun-12 A 23-Jul-12 09-Aug-12 23-Jul-12 09-Aug-12 0 0% 100%
A103670 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 09-Sep-12 26-Sep-12 19-Feb-13 10-Mar-13 112 0% 100%
A103640 Approval of Structural Dwgs. for Columns 14 09-Apr-12 A 04-Jul-12 24 05-Jul-12 24-Jul-12 18-Jul-12 06-Aug-12 9 0% 75%
A103650 Approval of Structural Dwgs. for Core Walls 14 21-Jun-12 A 24-Jul-12 7 05-Jul-12 24-Jul-12 16-Jul-12 02-Aug-12 7 0% 0%5th & 6th Fl5th & 6th Floor Slab 109 16-Feb-12 A 29-Jul-12 182 23-Jul-12 24-Oct-12 23-Jul-12 06-Mar-13 0% 56.25%SubmissionSubmission 101 16-Feb-12 A 14-Jul-12 194 23-Jul-12 06-Oct-12 23-Jul-12 16-Feb-13 0% 68.75%A103940 Submission of Structural Dwgs. for Slab 10 18-Jun-12 A 30-Jun-12 A 16-Aug-12 02-Sep-12 16-Aug-12 02-Sep-12 0 0% 100%
A103950 Submission of Structural Dwgs. for Columns 7 19-Apr-12 A 11-Jul-12 27 23-Jul-12 30-Jul-12 23-Jul-12 30-Jul-12 0 0% 50%
A104000 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 29-Sep-12 06-Oct-12 09-Feb-13 16-Feb-13 108 0% 100%
A103960 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 14-Jul-12 39 06-Aug-12 14-Aug-12 06-Aug-12 14-Aug-12 0 0% 25%ApprovalApproval 85 19-Feb-12 A 29-Jul-12 152 31-Jul-12 24-Oct-12 22-Aug-12 06-Mar-13 0% 50%A104010 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 07-Oct-12 24-Oct-12 17-Feb-13 06-Mar-13 90 0% 100%
A103980 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 22-Jul-12 35 31-Jul-12 21-Aug-12 22-Aug-12 10-Sep-12 14 0% 50%
A103970 Approval of Structural Dwgs. for Slab 14 19-Jun-12 A 25-Jul-12 39 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0 0% 25%
A103990 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 29-Jul-12 33 15-Aug-12 05-Sep-12 27-Aug-12 13-Sep-12 6 0% 25%7th Floor Sl7th Floor Slab 104 16-Feb-12 A 16-Aug-12 135 26-Aug-12 25-Nov-12 26-Aug-12 06-Mar-13 0% 66.67%SubmissionSubmission 94 16-Feb-12 A 07-Aug-12 135 26-Aug-12 04-Nov-12 26-Aug-12 16-Feb-13 0% 66.67%A104030 Submission of Structural Dwgs. for Columns 7 11-Jun-12 A 07-Aug-12 27 26-Aug-12 02-Sep-12 26-Aug-12 02-Sep-12 0 0% 50%
A104040 Submission of Structural Dwgs. for Core Walls 7 11-Jun-12 A 07-Aug-12 27 03-Sep-12 10-Sep-12 03-Sep-12 10-Sep-12 0 0% 50%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s Submission of Structural Dwgs. for Core Walls
b Approval of Structural Dwgs. for Slab
s Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Columns
ab
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
ns Submission of Structural Dwgs. for Columns
ns Approval of Structural Dwgs. for Columns
ls Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
ls Approval of Structural Dwgs. for Core Walls
ab
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
ab Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Core Walls
s Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 3 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A104080 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 28-Oct-12 04-Nov-12 09-Feb-13 16-Feb-13 85 0% 100%ApprovalApproval 81 19-Feb-12 A 16-Aug-12 113 03-Sep-12 25-Nov-12 30-Sep-12 06-Mar-13 0% 66.67%A104060 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 16-Aug-12 42 03-Sep-12 20-Sep-12 30-Sep-12 17-Oct-12 19 0% 50%
A104070 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 16-Aug-12 42 11-Sep-12 30-Sep-12 30-Sep-12 17-Oct-12 13 0% 50%
A104090 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 05-Nov-12 25-Nov-12 17-Feb-13 06-Mar-13 70 0% 100%Roof Floor Roof Floor Slab 109 16-Feb-12 A 03-Sep-12 119 13-Sep-12 24-Dec-12 13-Sep-12 12-Mar-13 0% 75%SubmissionSubmission 98 16-Feb-12 A 25-Aug-12 119 13-Sep-12 04-Dec-12 13-Sep-12 20-Feb-13 0% 75%A103690 Submission of Structural Dwgs. for Columns 7 18-Jun-12 A 25-Aug-12 30 13-Sep-12 20-Sep-12 13-Sep-12 20-Sep-12 0 0% 50%
A103740 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 26-Nov-12 04-Dec-12 13-Feb-13 20-Feb-13 65 0% 100%ApprovalApproval 85 19-Feb-12 A 03-Sep-12 99 23-Sep-12 24-Dec-12 17-Oct-12 12-Mar-13 0% 75%A103720 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 03-Sep-12 45 23-Sep-12 10-Oct-12 17-Oct-12 06-Nov-12 18 0% 50%
A103750 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 05-Dec-12 24-Dec-12 21-Feb-13 12-Mar-13 54 0% 100%Upper RoofUpper Roof Floor Slab 23 03-Mar-12 A 25-Mar-12 A 24-Nov-12 20-Dec-12 26-Feb-13 25-Mar-13 0% 100%SubmissionSubmission 7 03-Mar-12 A 10-Mar-12 A 24-Nov-12 01-Dec-12 26-Feb-13 05-Mar-13 0% 100%A103820 Submission of Structural Dwgs. for Staircase 7 03-Mar-12 A 10-Mar-12 A 24-Nov-12 01-Dec-12 26-Feb-13 05-Mar-13 78 0% 100%
ApprovalApproval 14 11-Mar-12 A 25-Mar-12 A 03-Dec-12 20-Dec-12 06-Mar-13 25-Mar-13 0% 100%A103830 Approval of Structural Dwgs. for Staircase 14 11-Mar-12 A 25-Mar-12 A 03-Dec-12 20-Dec-12 06-Mar-13 25-Mar-13 65 0% 100%
ArchitecturalArchitectural 95 29-Mar-12 A 29-Jul-12 160 07-May-12 03-Oct-12 07-May-12 10-Feb-13 38.8% 88.8%
Hotel ApartemHotel Apartements (Block A) 88 29-Mar-12 A 25-Jun-12 A 07-May-12 26-Aug-12 07-May-12 05-Nov-12 48.18% 100%
2nd Baseme2nd Basement Floor 25 29-Mar-12 A 23-Apr-12 A 07-May-12 05-Jun-12 07-May-12 21-Oct-12 100% 100%SubmissionSubmission 9 29-Mar-12 A 08-Apr-12 A 07-May-12 16-May-12 07-May-12 16-May-12 100% 100%A119010 Submission of Block Work Setting Out Plan for 2nd Basement 9 29-Mar-12 A 08-Apr-12 A 07-May-12 16-May-12 07-May-12 16-May-12 0 100% 100%
ApprovalApproval 14 09-Apr-12 A 23-Apr-12 A 17-May-12 05-Jun-12 02-Oct-12 21-Oct-12 100% 100%A119290 Approval of Block Work Setting Out Plan for 2nd Basement 14 09-Apr-12 A 23-Apr-12 A 17-May-12 05-Jun-12 02-Oct-12 21-Oct-12 95 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 17-May-12 13-Jun-12 17-May-12 13-Aug-12 100% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 17-May-12 26-May-12 17-May-12 26-May-12 100% 100%A119410 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 17-May-12 26-May-12 17-May-12 26-May-12 0 100% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 27-May-12 13-Jun-12 25-Jul-12 13-Aug-12 100% 100%A119550 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 27-May-12 13-Jun-12 25-Jul-12 13-Aug-12 42 100% 100%
Ground FloGround Floor 25 11-Jun-12 A 24-Jun-12 A 20-Jun-12 18-Jul-12 20-Jun-12 05-Nov-12 36.36% 100%SubmissionSubmission 8 11-Jun-12 A 19-Jun-12 A 20-Jun-12 28-Jun-12 20-Jun-12 28-Jun-12 100% 100%A118450 Submission of Block Work Setting Out Plan for Ground 8 11-Jun-12 A 19-Jun-12 A 20-Jun-12 28-Jun-12 20-Jun-12 28-Jun-12 0 100% 100%
ApprovalApproval 14 21-Jun-12 A 24-Jun-12 A 01-Jul-12 18-Jul-12 16-Oct-12 05-Nov-12 0% 100%A118480 Approval of Block Work Setting Out Plan for Ground 14 21-Jun-12 A 24-Jun-12 A 01-Jul-12 18-Jul-12 16-Oct-12 05-Nov-12 75 0% 100%
Typical FlooTypical Floors 26 29-May-12 A 25-Jun-12 A 30-Jun-12 26-Aug-12 30-Jun-12 09-Sep-12 2.27% 100%GeneralGeneral 26 29-May-12 A 25-Jun-12 A 30-Jun-12 26-Aug-12 30-Jun-12 09-Sep-12 2.27% 100%SubmissiSubmission 8 29-May-12 A 07-Jun-12 A 30-Jun-12 04-Aug-12 30-Jun-12 04-Aug-12 6.25% 100%A117470 Submission of Block Work Setting Out Plan for 1st Floor 8 29-May-12 A 07-Jun-12 A 30-Jun-12 08-Jul-12 30-Jun-12 08-Jul-12 0 12.5% 100%
A117230 Submission of Block Work Setting Out Plan for 2nd Floor 8 29-May-12 A 07-Jun-12 A 26-Jul-12 04-Aug-12 26-Jul-12 04-Aug-12 0 0% 100%ApprovalApproval 14 09-Jun-12 A 25-Jun-12 A 09-Jul-12 26-Aug-12 05-Aug-12 09-Sep-12 0% 100%A117490 Approval of Block Work Setting Out Plan for 2nd Floor 14 09-Jun-12 A 25-Jun-12 A 05-Aug-12 26-Aug-12 05-Aug-12 26-Aug-12 0 0% 100%
A117480 Approval of Block Work Setting Out Plan for 1st Floor 14 09-Jun-12 A 25-Jun-12 A 09-Jul-12 26-Jul-12 21-Aug-12 09-Sep-12 29 0% 100%
Hotel (Block Hotel (Block B) 83 12-Apr-12 A 29-Jul-12 160 19-May-12 03-Oct-12 28-May-12 10-Feb-13 25% 68.18%
2nd Baseme2nd Basement Floor 68 12-Apr-12 A 02-May-12 A 19-May-12 14-Jun-12 28-May-12 08-Jan-13 100% 100%SubmissionSubmission 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 28-May-12 05-Jun-12 100% 100%A123210 Submission of Block Work Setting Out Plan for 2nd Basement 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 28-May-12 05-Jun-12 8 100% 100%
ApprovalApproval 14 22-Apr-12 A 02-May-12 A 28-May-12 14-Jun-12 19-Dec-12 08-Jan-13 100% 100%A123490 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Apr-12 A 02-May-12 A 28-May-12 14-Jun-12 19-Dec-12 08-Jan-13 141 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 03-Jul-12 31-Jul-12 12-Jul-12 10-Oct-12 0% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 12-Jul-12 21-Jul-12 0% 100%A123610 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 12-Jul-12 21-Jul-12 8 0% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 23-Sep-12 10-Oct-12 0% 100%A123770 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 23-Sep-12 10-Oct-12 49 0% 100%
Typical FlooTypical Floors 32 11-Jun-12 A 29-Jul-12 160 28-Aug-12 03-Oct-12 06-Sep-12 10-Feb-13 0% 36.36%GeneralGeneral 32 11-Jun-12 A 29-Jul-12 160 28-Aug-12 03-Oct-12 06-Sep-12 10-Feb-13 0% 36.36%SubmissiSubmission 15 11-Jun-12 A 28-Jun-12 A 28-Aug-12 15-Sep-12 06-Sep-12 16-Dec-12 0% 100%A121790 Submission of Block Work Setting Out Plan for 2nd Floor 8 20-Jun-12 A 28-Jun-12 A 06-Sep-12 15-Sep-12 08-Dec-12 16-Dec-12 75 0% 100%
A122030 Submission of Block Work Setting Out Plan for 1st Floor 8 11-Jun-12 A 20-Jun-12 A 28-Aug-12 05-Sep-12 06-Sep-12 15-Sep-12 8 0% 100%ApprovalApproval 20 21-Jun-12 A 29-Jul-12 133 06-Sep-12 03-Oct-12 22-Oct-12 10-Feb-13 0% 0%A122040 Approval of Block Work Setting Out Plan for 2nd Floor 14 30-Jun-12 A 29-Jul-12 133 16-Sep-12 03-Oct-12 21-Jan-13 10-Feb-13 87 0% 0%
A122070 Approval of Block Work Setting Out Plan for 1st Floor 14 21-Jun-12 A 29-Jul-12 72 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32 0% 0%
Residential AResidential Apartments (Block C) 68 12-Apr-12 A 30-Jun-12 A 19-May-12 13-Aug-12 19-May-12 13-Nov-12 42.31% 100%
2nd Baseme2nd Basement Floor 68 12-Apr-12 A 11-Jun-12 A 19-May-12 14-Jun-12 19-May-12 13-Nov-12 100% 100%SubmissionSubmission 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 19-May-12 27-May-12 100% 100%A121110 Submission of Block Work Setting Out Plan for 2nd Basement 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 19-May-12 27-May-12 0 100% 100%
ApprovalApproval 14 22-Apr-12 A 11-Jun-12 A 28-May-12 14-Jun-12 24-Oct-12 13-Nov-12 100% 100%A121390 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Apr-12 A 11-Jun-12 A 28-May-12 14-Jun-12 24-Oct-12 13-Nov-12 104 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 03-Jul-12 31-Jul-12 03-Jul-12 01-Nov-12 0% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 03-Jul-12 11-Jul-12 0% 100%A121510 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 03-Jul-12 11-Jul-12 0 0% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 14-Oct-12 01-Nov-12 0% 100%A121670 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 14-Oct-12 01-Nov-12 64 0% 100%
Ground FloGround Floor 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0% 100%SubmissionSubmission 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0% 100%A120780 Submission of Block Work Setting Out Plan for Ground 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0 0% 100%
MEPMEP 129 08-Feb-12 A 18-Jul-12 205 15-Feb-12 07-Aug-12 15-Feb-12 24-Mar-13 94.96% 91.1%
Hotel ApartemHotel Apartements (Block A) 121 11-Feb-12 A 18-Jul-12 204 15-Feb-12 07-Aug-12 16-Feb-12 21-Mar-13 96.17% 95.75%
2nd Baseme2nd Basement Floor 31 11-Feb-12 A 18-Jul-12 194 15-Feb-12 22-Mar-12 16-Feb-12 11-Mar-13 100% 92.95%SubmissionSubmission 14 11-Feb-12 A 23-Apr-12 A 15-Feb-12 04-Mar-12 16-Feb-12 17-Feb-13 100% 100%A1245 Submission of Drainage Layout & Details 4 10-Mar-12 A 14-Mar-12 A 15-Feb-12 19-Feb-12 16-Feb-12 20-Feb-12 1 100% 100%
A1255 Submission of Water Supply Layout & Details 10 23-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 30-Jan-13 10-Feb-13 289 100% 100%
A1265 Submission of Fire Fighting Layout & Details 10 24-Mar-12 A 03-Apr-12 A 18-Feb-12 28-Feb-12 05-Jan-13 15-Jan-13 268 100% 100%
A1275 Submission of HVAC Layout & Details 10 08-Mar-12 A 18-Mar-12 A 18-Feb-12 28-Feb-12 17-Oct-12 30-Oct-12 205 100% 100%
A1285 Submission of MEP Cordination Layout 10 13-Feb-12 A 23-Apr-12 A 22-Feb-12 04-Mar-12 17-Oct-12 30-Oct-12 201 100% 100%
A1295 Submission of MEP Builder Work Layout 2 15-Feb-12 A 16-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 1 100% 100%
A1305 Submission of Lighting Layout & Details 10 11-Feb-12 A 20-Feb-12 A 18-Feb-12 28-Feb-12 21-Oct-12 03-Nov-12 208 100% 100%
A1315 Submission of Power Layout & Details 10 31-Mar-12 A 09-Apr-12 A 18-Feb-12 28-Feb-12 21-Oct-12 03-Nov-12 208 100% 100%
A1325 Submission of Fire Alarm Layout & Details 10 26-Feb-12 A 07-Mar-12 A 18-Feb-12 28-Feb-12 06-Feb-13 17-Feb-13 295 100% 100%
A1335 Submission of CBS Layout & Details 10 22-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 06-Feb-13 17-Feb-13 295 100% 100%
A1345 Submission of CCTV,Access Control,Intercom Layout & Details 10 15-Feb-12 A 25-Feb-12 A 18-Feb-12 28-Feb-12 28-Nov-12 10-Dec-12 238 100% 100%
A1365 Submission of BMS Layout & Details 10 01-Apr-12 A 12-Apr-12 A 18-Feb-12 28-Feb-12 01-Dec-12 12-Dec-12 240 100% 100%
A1375 Submission of Data & Telephone Layout & Details 10 04-Mar-12 A 14-Mar-12 A 18-Feb-12 28-Feb-12 15-Jan-13 27-Jan-13 277 100% 100%ApprovalApproval 24 17-Feb-12 A 18-Jul-12 161 19-Feb-12 22-Mar-12 19-Feb-12 11-Mar-13 100% 88.46%A124720 Approval of Drainage Layout & Details 14 15-Mar-12 A 17-Mar-12 A 20-Feb-12 08-Mar-12 20-Feb-13 11-Mar-13 254 100% 100%
A124730 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 29-Feb-12 19-Mar-12 11-Feb-13 28-Feb-13 240 100% 100%
A124740 Approval of Fire Fighting Layout & Details 14 04-Apr-12 A 08-Apr-12 A 29-Feb-12 19-Mar-12 16-Jan-13 05-Feb-13 223 100% 100%
A124760 Approval of MEP Cordination Layout 14 04-Mar-12 A 03-May-12 A 05-Mar-12 22-Mar-12 31-Oct-12 20-Nov-12 168 100% 100%
A124770 Approval of MEP Builder Work Layout 4 17-Feb-12 A 05-Mar-12 A 19-Feb-12 22-Feb-12 19-Feb-12 22-Feb-12 0 100% 100%
A124780 Approval of Lighting Layout & Details 14 21-Feb-12 A 29-Feb-12 A 29-Feb-12 19-Mar-12 04-Nov-12 22-Nov-12 173 100% 100%
A124790 Approval of Power Layout & Details 14 10-Apr-12 A 24-Apr-12 A 29-Feb-12 19-Mar-12 04-Nov-12 22-Nov-12 173 100% 100%
A124810 Approval of CBS Layout & Details 14 04-Mar-12 A 20-Mar-12 A 29-Feb-12 19-Mar-12 18-Feb-13 07-Mar-13 245 100% 100%
A124820 Approval of CCTV,Access Control,Intercom Layout & Details 14 26-Feb-12 A 05-Mar-12 A 29-Feb-12 19-Mar-12 11-Dec-12 30-Dec-12 198 100% 100%
A124840 Approval of BMS Layout & Details 14 29-Feb-12 A 19-Mar-12 A 29-Feb-12 19-Mar-12 13-Dec-12 02-Jan-13 200 100% 100%
A124850 Approval of Data & Telephone Layout & Details 14 29-Feb-12 A 19-Mar-12 A 29-Feb-12 19-Mar-12 28-Jan-13 14-Feb-13 230 100% 100%
A124750 Approval of HVAC Layout & Details 14 19-Mar-12 A 09-Jul-12 92 29-Feb-12 19-Mar-12 31-Oct-12 20-Nov-12 171 100% 50%
A124800 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 159 29-Feb-12 19-Mar-12 18-Feb-13 07-Mar-13 245 100% 0%1st Baseme1st Basement Floor 39 23-Feb-12 A 18-Jul-12 191 18-Feb-12 05-Apr-12 18-Feb-12 07-Mar-13 100% 95.51%SubmissionSubmission 22 23-Feb-12 A 21-Apr-12 A 18-Feb-12 18-Mar-12 18-Feb-12 17-Feb-13 100% 100%A124870 Submission of Drainage Layout & Details 10 08-Mar-12 A 18-Mar-12 A 18-Feb-12 28-Feb-12 18-Feb-12 28-Feb-12 0 100% 100%
A124890 Submission of Water Supply Layout & Details 10 23-Feb-12 A 03-Mar-12 A 03-Mar-12 13-Mar-12 22-Jan-13 03-Feb-13 271 100% 100%
A124900 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 03-Mar-12 13-Mar-12 09-Dec-12 19-Dec-12 234 100% 100%
A124910 Submission of HVAC Layout & Details 10 08-Mar-12 A 18-Mar-12 A 03-Mar-12 13-Mar-12 07-Nov-12 19-Nov-12 209 100% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
ns Submission of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Columns
d
nd
or
r
oor Approval of Block Work Setting Out Plan for 2nd Floor
or Approval of Block Work Setting Out Plan for 1st Floor
nd
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 4 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A125000 Submission of MEP Cordination Layout 10 02-Apr-12 A 12-Apr-12 A 07-Mar-12 18-Mar-12 22-Jul-12 01-Aug-12 116 100% 100%
A124880 Submission of MEP Builder Work Layout 8 10-Mar-12 A 18-Mar-12 A 18-Feb-12 26-Feb-12 18-Feb-12 26-Feb-12 0 100% 100%
A124920 Submission of Lighting Layout & Details 10 11-Mar-12 A 22-Mar-12 A 03-Mar-12 13-Mar-12 22-Jul-12 01-Aug-12 120 100% 100%
A124930 Submission of Power Layout & Details 10 18-Mar-12 A 28-Mar-12 A 03-Mar-12 13-Mar-12 22-Jul-12 01-Aug-12 120 100% 100%
A124940 Submission of Fire Alarm Layout & Details 10 04-Mar-12 A 14-Mar-12 A 03-Mar-12 13-Mar-12 05-Jan-13 15-Jan-13 256 100% 100%
A124950 Submission of CBS Layout & Details 10 04-Mar-12 A 14-Mar-12 A 03-Mar-12 13-Mar-12 06-Feb-13 17-Feb-13 283 100% 100%
A124960 Submission of CCTV,Access Control,Intercom Layout & Details 10 10-Apr-12 A 21-Apr-12 A 03-Mar-12 13-Mar-12 28-Nov-12 10-Dec-12 226 100% 100%
A124980 Submission of BMS Layout & Details 10 02-Apr-12 A 12-Apr-12 A 03-Mar-12 13-Mar-12 01-Dec-12 12-Dec-12 228 100% 100%
A124990 Submission of Data & Telephone Layout & Details 10 08-Apr-12 A 18-Apr-12 A 03-Mar-12 13-Mar-12 15-Jan-13 27-Jan-13 265 100% 100%ApprovalApproval 31 04-Mar-12 A 18-Jul-12 159 27-Feb-12 05-Apr-12 27-Feb-12 07-Mar-13 100% 92.31%A125020 Approval of Drainage Layout & Details 14 19-Mar-12 A 27-Mar-12 A 29-Feb-12 19-Mar-12 20-Jan-13 07-Feb-13 225 100% 100%
A125040 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 14-Mar-12 02-Apr-12 04-Feb-13 21-Feb-13 225 100% 100%
A125050 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 17-Mar-12 A 14-Mar-12 02-Apr-12 20-Dec-12 09-Jan-13 195 100% 100%
A125060 Approval of HVAC Layout & Details 14 19-Mar-12 A 29-Mar-12 A 14-Mar-12 02-Apr-12 20-Nov-12 10-Dec-12 174 100% 100%
A125150 Approval of MEP Cordination Layout 14 14-Apr-12 A 24-Apr-12 A 19-Mar-12 05-Apr-12 02-Aug-12 23-Aug-12 97 100% 100%
A125030 Approval of MEP Builder Work Layout 14 19-Mar-12 A 21-Mar-12 A 27-Feb-12 15-Mar-12 27-Feb-12 15-Mar-12 0 100% 100%
A125070 Approval of Lighting Layout & Details 14 23-Mar-12 A 31-Mar-12 A 14-Mar-12 02-Apr-12 02-Aug-12 23-Aug-12 100 100% 100%
A125080 Approval of Power Layout & Details 14 29-Mar-12 A 05-Apr-12 A 14-Mar-12 02-Apr-12 02-Aug-12 23-Aug-12 100 100% 100%
A125100 Approval of CBS Layout & Details 14 15-Mar-12 A 21-Mar-12 A 14-Mar-12 02-Apr-12 18-Feb-13 07-Mar-13 235 100% 100%
A125110 Approval of CCTV,Access Control,Intercom Layout & Details 14 22-Apr-12 A 03-May-12 A 14-Mar-12 02-Apr-12 11-Dec-12 30-Dec-12 188 100% 100%
A125130 Approval of BMS Layout & Details 14 14-Apr-12 A 03-May-12 A 14-Mar-12 02-Apr-12 13-Dec-12 02-Jan-13 190 100% 100%
A125140 Approval of Data & Telephone Layout & Details 14 19-Apr-12 A 17-May-12 A 14-Mar-12 02-Apr-12 28-Jan-13 14-Feb-13 220 100% 100%
A125090 Approval of Fire Alarm Layout & Details 14 15-Mar-12 A 18-Jul-12 137 14-Mar-12 02-Apr-12 16-Jan-13 05-Feb-13 213 100% 0%Ground FloGround Floor 87 01-Mar-12 A 09-Jul-12 212 27-Feb-12 16-Apr-12 27-Feb-12 21-Mar-13 100% 97.27%SubmissionSubmission 71 01-Mar-12 A 10-May-12 A 27-Feb-12 27-Mar-12 27-Feb-12 03-Mar-13 100% 100%A125210 Submission of HVAC Layout & Details 10 20-Mar-12 A 01-Apr-12 A 17-Mar-12 27-Mar-12 18-Oct-12 31-Oct-12 182 100% 100%
A125300 Submission of MEP Cordination Layout 12 17-Apr-12 A 29-Apr-12 A 08-Mar-12 21-Mar-12 28-Oct-12 10-Nov-12 195 100% 100%
A125180 Submission of MEP Builder Work Layout 3 21-Mar-12 A 24-Mar-12 A 08-Mar-12 11-Mar-12 08-Mar-12 11-Mar-12 0 100% 100%
A125220 Submission of Lighting Layout & Details 10 13-Mar-12 A 24-Mar-12 A 17-Mar-12 27-Mar-12 12-Nov-12 24-Nov-12 201 100% 100%
A125230 Submission of Power Layout & Details 10 15-Mar-12 A 29-Mar-12 A 17-Mar-12 27-Mar-12 12-Nov-12 24-Nov-12 201 100% 100%
A125290 Submission of Data & Telephone Layout & Details 10 25-Mar-12 A 04-Apr-12 A 17-Mar-12 27-Mar-12 20-Feb-13 03-Mar-13 283 100% 100%
A125470 Submission of Drainage Layout & Details (High Level) 16 10-Apr-12 A 29-Apr-12 A 10-Mar-12 27-Mar-12 11-Oct-12 31-Oct-12 182 100% 100%
A125170 Submission of Drainage Layout & Details (Low Level) 5 05-May-12 A 10-May-12 A 27-Feb-12 03-Mar-12 27-Feb-12 03-Mar-12 0 100% 100%
A125190 Submission of Water Supply Layout & Details 16 01-Apr-12 A 17-Apr-12 A 10-Mar-12 27-Mar-12 11-Oct-12 31-Oct-12 182 100% 100%
A125200 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 17-Mar-12 27-Mar-12 03-Nov-12 13-Nov-12 193 100% 100%ApprovalApproval 69 11-Mar-12 A 09-Jul-12 176 04-Mar-12 16-Apr-12 12-Mar-12 21-Mar-13 100% 95%A125320 Approval of Drainage Layout & Details (Low Level) 14 12-May-12 A 21-May-12 A 04-Mar-12 21-Mar-12 03-Dec-12 20-Dec-12 190 100% 100%
A125340 Approval of Water Supply Layout & Details 14 18-Apr-12 A 29-Apr-12 A 28-Mar-12 16-Apr-12 25-Nov-12 13-Dec-12 167 100% 100%
A125350 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 26-May-12 A 28-Mar-12 16-Apr-12 14-Nov-12 05-Dec-12 161 100% 100%
A125450 Approval of MEP Cordination Layout 14 30-Apr-12 A 24-Jun-12 A 22-Mar-12 10-Apr-12 11-Nov-12 29-Nov-12 162 100% 100%
A125330 Approval of MEP Builder Work Layout 14 25-Mar-12 A 02-Apr-12 A 12-Mar-12 29-Mar-12 12-Mar-12 29-Mar-12 0 100% 100%
A125370 Approval of Lighting Layout & Details 14 25-Mar-12 A 02-Apr-12 A 28-Mar-12 16-Apr-12 25-Nov-12 13-Dec-12 167 100% 100%
A125380 Approval of Power Layout & Details 14 30-Mar-12 A 27-May-12 A 28-Mar-12 16-Apr-12 25-Nov-12 13-Dec-12 167 100% 100%
A125440 Approval of Data & Telephone Layout & Details 3 01-May-12 A 03-May-12 A 28-Mar-12 16-Apr-12 04-Mar-13 21-Mar-13 235 100% 100%
A125480 Approval of Drainage Layout & Details (High Level) 14 30-Apr-12 A 03-Jun-12 A 28-Mar-12 16-Apr-12 03-Dec-12 20-Dec-12 172 100% 100%
A125360 Approval of HVAC Layout & Details 14 02-Apr-12 A 09-Jul-12 93 28-Mar-12 16-Apr-12 01-Nov-12 21-Nov-12 152 100% 50%1st Floor1st Floor 67 01-Apr-12 A 01-Jul-12 214 10-Mar-12 29-Apr-12 10-Mar-12 17-Mar-13 100% 97.7%SubmissionSubmission 50 01-Apr-12 A 10-Jun-12 A 10-Mar-12 09-Apr-12 10-Mar-12 19-Feb-13 100% 100%A125490 Submission of Drainage Layout & Details (Low Level) 11 17-Apr-12 A 29-Apr-12 A 10-Mar-12 21-Mar-12 10-Mar-12 21-Mar-12 0 100% 100%
A125500 Submission of Water Supply Layout & Details 16 14-Apr-12 A 08-May-12 A 22-Mar-12 09-Apr-12 16-Aug-12 05-Sep-12 125 100% 100%
A125510 Submission of Fire Fighting Layout & Details 10 07-May-12 A 19-May-12 A 29-Mar-12 09-Apr-12 05-Sep-12 16-Sep-12 134 100% 100%
A125520 Submission of HVAC Layout & Details 10 21-Apr-12 A 12-May-12 A 29-Mar-12 09-Apr-12 18-Sep-12 29-Sep-12 145 100% 100%
A125630 Submission of MEP Cordination Layout 12 28-May-12 A 10-Jun-12 A 26-Mar-12 08-Apr-12 29-Aug-12 11-Sep-12 131 100% 100%
A125640 Submission of MEP Builder Work Layout 6 22-Apr-12 A 29-Apr-12 A 26-Mar-12 01-Apr-12 26-Mar-12 01-Apr-12 0 100% 100%
A125530 Submission of Lighting Layout & Details 10 05-May-12 A 15-May-12 A 29-Mar-12 09-Apr-12 01-Sep-12 11-Sep-12 130 100% 100%
A125540 Submission of Power Layout & Details 10 29-Apr-12 A 10-May-12 A 29-Mar-12 09-Apr-12 01-Sep-12 11-Sep-12 130 100% 100%
A125570 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Apr-12 A 14-Apr-12 A 29-Mar-12 09-Apr-12 09-Feb-13 19-Feb-13 262 100% 100%
A125590 Submission of BMS Layout & Details 10 21-Apr-12 A 13-May-12 A 29-Mar-12 09-Apr-12 03-Feb-13 13-Feb-13 257 100% 100%
A125600 Submission of Data & Telephone Layout & Details 10 21-Apr-12 A 08-May-12 A 29-Mar-12 09-Apr-12 23-Dec-12 03-Jan-13 223 100% 100%
A125610 Submission of Drainage Layout & Details (High Level) 16 23-May-12 A 10-Jun-12 A 22-Mar-12 09-Apr-12 16-Aug-12 05-Sep-12 125 100% 100%ApprovalApproval 55 15-Apr-12 A 01-Jul-12 178 22-Mar-12 29-Apr-12 02-Apr-12 17-Mar-13 100% 95.83%A125650 Approval of Drainage Layout & Details (Low Level) 14 01-May-12 A 03-Jun-12 A 22-Mar-12 10-Apr-12 04-Sep-12 23-Sep-12 115 100% 100%
A125660 Approval of Water Supply Layout & Details 14 09-May-12 A 20-May-12 A 10-Apr-12 29-Apr-12 06-Sep-12 25-Sep-12 104 100% 100%
A125670 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Apr-12 29-Apr-12 17-Sep-12 04-Oct-12 111 100% 100%
A125680 Approval of HVAC Layout & Details 14 13-May-12 A 27-May-12 A 10-Apr-12 29-Apr-12 30-Sep-12 17-Oct-12 120 100% 100%
A125790 Approval of MEP Cordination Layout 14 10-Jun-12 A 24-Jun-12 A 09-Apr-12 26-Apr-12 12-Sep-12 01-Oct-12 109 100% 100%
A125690 Approval of Lighting Layout & Details 14 16-May-12 A 26-May-12 A 10-Apr-12 29-Apr-12 12-Sep-12 01-Oct-12 108 100% 100%
A125700 Approval of Power Layout & Details 14 13-May-12 A 23-May-12 A 10-Apr-12 29-Apr-12 12-Sep-12 01-Oct-12 108 100% 100%
A125730 Approval of CCTV,Access Control,Intercom Layout & Details 14 15-Apr-12 A 03-May-12 A 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 100%
A125750 Approval of BMS Layout & Details 14 14-May-12 A 23-May-12 A 10-Apr-12 29-Apr-12 18-Feb-13 07-Mar-13 216 100% 100%
A125760 Approval of Data & Telephone Layout & Details 14 09-May-12 A 17-May-12 A 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 100%
A125770 Approval of Drainage Layout & Details (High Level) 14 10-Jun-12 A 20-Jun-12 A 10-Apr-12 29-Apr-12 24-Dec-12 13-Jan-13 178 100% 100%
A125800 Approval of MEP Builder Work Layout 14 30-Apr-12 A 01-Jul-12 20 02-Apr-12 19-Apr-12 02-Apr-12 19-Apr-12 0 100% 50%2nd Floor2nd Floor 46 08-May-12 A 18-Jul-12 194 29-Mar-12 13-May-12 02-Apr-12 11-Mar-13 100% 82.64%SubmissionSubmission 39 08-May-12 A 11-Jun-12 A 29-Mar-12 23-Apr-12 02-Apr-12 19-Feb-13 100% 100%A125810 Submission of Drainage Layout & Details 11 29-May-12 A 10-Jun-12 A 02-Apr-12 14-Apr-12 02-Apr-12 14-Apr-12 0 100% 100%
A125830 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 02-Apr-12 14-Apr-12 21-Aug-12 02-Sep-12 118 100% 100%
A125840 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 03-Apr-12 14-Apr-12 19-Sep-12 30-Sep-12 142 100% 100%
A125850 Submission of HVAC Layout & Details 10 06-Jun-12 A 11-Jun-12 A 03-Apr-12 14-Apr-12 16-Sep-12 26-Sep-12 139 100% 100%
A125960 Submission of MEP Builder Work Layout 7 09-May-12 A 16-May-12 A 16-Apr-12 23-Apr-12 16-Apr-12 23-Apr-12 0 100% 100%
A125860 Submission of Lighting Layout & Details 10 17-May-12 A 28-May-12 A 03-Apr-12 14-Apr-12 28-Aug-12 08-Sep-12 123 100% 100%
A125870 Submission of Power Layout & Details 10 09-May-12 A 20-May-12 A 03-Apr-12 14-Apr-12 28-Aug-12 08-Sep-12 123 100% 100%
A125900 Submission of CCTV,Access Control,Intercom Layout & Details 10 24-May-12 A 04-Jun-12 A 29-Mar-12 09-Apr-12 09-Feb-13 19-Feb-13 262 100% 100%
A125920 Submission of BMS Layout & Details 10 24-May-12 A 04-Jun-12 A 29-Mar-12 09-Apr-12 03-Feb-13 13-Feb-13 257 100% 100%
A125930 Submission of Data & Telephone Layout & Details 10 24-May-12 A 04-Jun-12 A 29-Mar-12 09-Apr-12 09-Feb-13 19-Feb-13 262 100% 100%ApprovalApproval 31 17-May-12 A 18-Jul-12 161 10-Apr-12 13-May-12 24-Apr-12 11-Mar-13 100% 70%A125970 Approval of Drainage Layout & Details 14 10-Jun-12 A 20-Jun-12 A 15-Apr-12 02-May-12 30-Aug-12 18-Sep-12 96 100% 100%
A125990 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 15-Apr-12 02-May-12 03-Sep-12 20-Sep-12 98 100% 100%
A126000 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 15-Apr-12 02-May-12 01-Oct-12 18-Oct-12 118 100% 100%
A126010 Approval of HVAC Layout & Details 4 12-Jun-12 A 27-Jun-12 A 15-Apr-12 02-May-12 27-Sep-12 16-Oct-12 116 100% 100%
A126120 Approval of MEP Builder Work Layout 14 17-May-12 A 26-May-12 A 24-Apr-12 13-May-12 24-Apr-12 13-May-12 0 100% 100%
A126020 Approval of Lighting Layout & Details 14 29-May-12 A 12-Jun-12 A 15-Apr-12 02-May-12 09-Sep-12 26-Sep-12 102 100% 100%
A126030 Approval of Power Layout & Details 14 20-May-12 A 27-May-12 A 15-Apr-12 02-May-12 09-Sep-12 26-Sep-12 102 100% 100%
A126060 Approval of CCTV,Access Control,Intercom Layout & Details 14 05-Jun-12 A 18-Jul-12 161 10-Apr-12 29-Apr-12 20-Feb-13 11-Mar-13 218 100% 0%
A126080 Approval of BMS Layout & Details 14 05-Jun-12 A 18-Jul-12 157 10-Apr-12 29-Apr-12 14-Feb-13 05-Mar-13 214 100% 0%
A126090 Approval of Data & Telephone Layout & Details 14 05-Jun-12 A 18-Jul-12 161 10-Apr-12 29-Apr-12 20-Feb-13 11-Mar-13 218 100% 0%3rd Floor3rd Floor 47 08-May-12 A 27-Jun-12 A 02-Apr-12 13-May-12 02-Apr-12 05-Nov-12 100% 100%SubmissionSubmission 39 08-May-12 A 11-Jun-12 A 02-Apr-12 23-Apr-12 02-Apr-12 15-Oct-12 100% 100%A126180 Submission of Drainage Layout & Details 11 29-May-12 A 10-Jun-12 A 02-Apr-12 14-Apr-12 02-Apr-12 14-Apr-12 0 100% 100%
A126190 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 02-Apr-12 14-Apr-12 06-Sep-12 18-Sep-12 132 100% 100%
A126200 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 03-Apr-12 14-Apr-12 04-Oct-12 15-Oct-12 155 100% 100%
A126210 Submission of HVAC Layout & Details 10 06-Jun-12 A 11-Jun-12 A 03-Apr-12 14-Apr-12 04-Oct-12 15-Oct-12 155 100% 100%
A126270 Submission of MEP Builder Work Layout 7 12-May-12 A 19-May-12 A 16-Apr-12 23-Apr-12 16-Apr-12 23-Apr-12 0 100% 100%
A126220 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 03-Apr-12 14-Apr-12 13-Sep-12 24-Sep-12 137 100% 100%
A126230 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 03-Apr-12 14-Apr-12 13-Sep-12 24-Sep-12 137 100% 100%ApprovalApproval 31 20-May-12 A 27-Jun-12 A 15-Apr-12 13-May-12 24-Apr-12 05-Nov-12 100% 100%A126330 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 15-Apr-12 02-May-12 19-Sep-12 08-Oct-12 110 100% 100%
A126340 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 15-Apr-12 02-May-12 19-Sep-12 08-Oct-12 110 100% 100%
A126350 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 15-Apr-12 02-May-12 16-Oct-12 05-Nov-12 129 100% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Approval of Fire Alarm Layout & Details
Approval of HVAC Layout & Details
t
Approval of MEP Builder Work Layout
s
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 5 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A126360 Approval of HVAC Layout & Details 14 12-Jun-12 A 27-Jun-12 A 15-Apr-12 02-May-12 16-Oct-12 05-Nov-12 129 100% 100%
A126420 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 24-Apr-12 13-May-12 24-Apr-12 13-May-12 0 100% 100%
A126370 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 15-Apr-12 02-May-12 25-Sep-12 14-Oct-12 114 100% 100%
A126380 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 15-Apr-12 02-May-12 25-Sep-12 14-Oct-12 114 100% 100%4th Floor4th Floor 50 03-May-12 A 21-Jun-12 A 14-Apr-12 03-Jun-12 07-May-12 14-Nov-12 100% 100%SubmissionSubmission 33 03-May-12 A 10-Jun-12 A 14-Apr-12 14-May-12 07-May-12 24-Oct-12 100% 100%A126480 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 14-Apr-12 28-Apr-12 07-May-12 21-May-12 20 100% 100%
A126490 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 14-Apr-12 28-Apr-12 11-Sep-12 25-Sep-12 126 100% 100%
A126500 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 17-Apr-12 28-Apr-12 14-Oct-12 24-Oct-12 151 100% 100%
A126570 Submission of MEP Builder Work Layout 14 03-May-12 A 19-May-12 A 29-Apr-12 14-May-12 22-May-12 06-Jun-12 20 100% 100%
A126520 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 17-Apr-12 28-Apr-12 20-Sep-12 01-Oct-12 131 100% 100%
A126530 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 17-Apr-12 28-Apr-12 20-Sep-12 01-Oct-12 131 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 29-Apr-12 03-Jun-12 07-Jun-12 14-Nov-12 100% 100%A126630 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 29-Apr-12 16-May-12 26-Sep-12 15-Oct-12 105 100% 100%
A126640 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 29-Apr-12 16-May-12 26-Sep-12 15-Oct-12 105 100% 100%
A126650 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 29-Apr-12 16-May-12 28-Oct-12 14-Nov-12 126 100% 100%
A126720 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 15-May-12 03-Jun-12 07-Jun-12 27-Jun-12 17 100% 100%
A126670 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 29-Apr-12 16-May-12 02-Oct-12 21-Oct-12 109 100% 100%
A126680 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 29-Apr-12 16-May-12 02-Oct-12 21-Oct-12 109 100% 100%5th Floor5th Floor 46 08-May-12 A 21-Jun-12 A 24-May-12 28-Jun-12 29-May-12 09-Dec-12 100% 100%SubmissionSubmission 29 08-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 29-May-12 18-Nov-12 100% 100%A126780 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 29-May-12 12-Jun-12 4 100% 100%
A126790 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 03-Oct-12 17-Oct-12 110 100% 100%
A126800 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 06-Nov-12 18-Nov-12 134 100% 100%
A126870 Submission of MEP Builder Work Layout 6 13-May-12 A 19-May-12 A 29-May-12 04-Jun-12 03-Jun-12 09-Jun-12 4 100% 100%
A126820 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 13-Oct-12 23-Oct-12 115 100% 100%
A126830 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 13-Oct-12 23-Oct-12 115 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 05-Jun-12 28-Jun-12 10-Jun-12 09-Dec-12 100% 100%A126930 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 15-Oct-12 04-Nov-12 88 100% 100%
A126940 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 18-Oct-12 07-Nov-12 91 100% 100%
A126950 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 19-Nov-12 09-Dec-12 111 100% 100%
A127020 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 05-Jun-12 25-Jun-12 10-Jun-12 28-Jun-12 3 100% 100%
A126970 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 10-Jun-12 28-Jun-12 24-Oct-12 13-Nov-12 95 100% 100%
A126980 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 10-Jun-12 28-Jun-12 24-Oct-12 13-Nov-12 95 100% 100%6th Floor6th Floor 46 08-May-12 A 21-Jun-12 A 24-May-12 24-Jul-12 24-May-12 18-Dec-12 88% 100%SubmissionSubmission 29 08-May-12 A 10-Jun-12 A 24-May-12 04-Jul-12 24-May-12 27-Nov-12 93.94% 100%A127080 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 24-May-12 07-Jun-12 0 100% 100%
A127090 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 17-Oct-12 03-Nov-12 122 100% 100%
A127100 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 17-Nov-12 27-Nov-12 142 100% 100%
A127170 Submission of MEP Builder Work Layout 10 08-May-12 A 19-May-12 A 24-Jun-12 04-Jul-12 24-Jun-12 04-Jul-12 0 60% 100%
A127120 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 21-Oct-12 03-Nov-12 122 100% 100%
A127130 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 21-Oct-12 03-Nov-12 122 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 10-Jun-12 24-Jul-12 05-Jul-12 18-Dec-12 83.33% 100%A127230 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 100%
A127240 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%
A127250 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 100%
A127320 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 05-Jul-12 24-Jul-12 05-Jul-12 24-Jul-12 0 0% 100%
A127270 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%
A127280 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%7th Floor7th Floor 51 07-May-12 A 21-Jun-12 A 11-Jun-12 17-Jul-12 11-Jun-12 13-Dec-12 51.85% 100%SubmissionSubmission 44 07-May-12 A 17-Jun-12 A 11-Jun-12 27-Jun-12 11-Jun-12 24-Nov-12 100% 100%A127380 Submission of Drainage Layout & Details 14 11-Jun-12 A 17-Jun-12 A 11-Jun-12 27-Jun-12 11-Jun-12 27-Jun-12 0 100% 100%
A127390 Submission of Water Supply Layout & Details 14 12-May-12 A 27-May-12 A 11-Jun-12 27-Jun-12 29-Oct-12 13-Nov-12 115 100% 100%
A127400 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 14-Jun-12 27-Jun-12 11-Nov-12 24-Nov-12 123 100% 100%ApprovalApproval 34 20-May-12 A 21-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 13-Dec-12 7.14% 100%A127530 Approval of Drainage Layout & Details 14 18-Jun-12 A 21-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 05-Dec-12 96 7.14% 100%
A127540 Approval of Water Supply Layout & Details 14 28-May-12 A 03-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 05-Dec-12 96 7.14% 100%
A127550 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 28-Jun-12 17-Jul-12 25-Nov-12 13-Dec-12 102 7.14% 100%Roof FloorRoof Floor 27 07-May-12 A 05-Jun-12 A 07-Jul-12 07-Aug-12 06-Nov-12 10-Dec-12 0% 100%SubmissionSubmission 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 06-Nov-12 19-Nov-12 0% 100%A127740 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 06-Nov-12 19-Nov-12 101 0% 100%
ApprovalApproval 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 20-Nov-12 10-Dec-12 0% 100%A127890 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 20-Nov-12 10-Dec-12 84 0% 100%
Hotel (Block Hotel (Block B) 129 08-Feb-12 A 18-Jul-12 205 15-Feb-12 07-Aug-12 15-Feb-12 24-Mar-13 95% 90.74%
2nd Baseme2nd Basement Floor 91 08-Feb-12 A 18-Jul-12 196 15-Feb-12 26-Mar-12 15-Feb-12 13-Mar-13 100% 89.71%SubmissionSubmission 75 08-Feb-12 A 23-Apr-12 A 15-Feb-12 06-Mar-12 15-Feb-12 23-Feb-13 100% 100%A128230 Submission of Drainage Layout & Details 4 10-Mar-12 A 14-Mar-12 A 15-Feb-12 19-Feb-12 15-Feb-12 19-Feb-12 0 100% 100%
A128240 Submission of Water Supply Layout & Details 10 23-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 06-Feb-13 17-Feb-13 295 100% 100%
A128250 Submission of Fire Fighting Layout & Details 10 22-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 17-Jan-13 29-Jan-13 279 100% 100%
A128260 Submission of HVAC Layout & Details 10 07-Mar-12 A 17-Mar-12 A 18-Feb-12 28-Feb-12 27-Jan-13 06-Feb-13 286 100% 100%
A128270 Submission of MEP Cordination Layout 10 12-Apr-12 A 23-Apr-12 A 25-Feb-12 06-Mar-12 24-Dec-12 05-Jan-13 253 100% 100%
A128280 Submission of MEP Builder Work Layout 4 08-Feb-12 A 12-Feb-12 A 15-Feb-12 19-Feb-12 15-Feb-12 19-Feb-12 0 100% 100%
A128290 Submission of Lighting Layout & Details 10 09-Feb-12 A 20-Feb-12 A 18-Feb-12 28-Feb-12 16-Dec-12 26-Dec-12 252 100% 100%
A128300 Submission of Power Layout & Details 10 29-Mar-12 A 09-Apr-12 A 18-Feb-12 28-Feb-12 16-Dec-12 26-Dec-12 252 100% 100%
A128310 Submission of Fire Alarm Layout & Details 10 23-Feb-12 A 07-Mar-12 A 18-Feb-12 28-Feb-12 12-Feb-13 23-Feb-13 300 100% 100%ApprovalApproval 73 13-Feb-12 A 18-Jul-12 163 20-Feb-12 26-Mar-12 20-Feb-12 13-Mar-13 100% 83.33%A128380 Approval of Drainage Layout & Details 14 15-Mar-12 A 17-Mar-12 A 20-Feb-12 08-Mar-12 18-Feb-13 07-Mar-13 252 100% 100%
A128390 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 29-Feb-12 19-Mar-12 18-Feb-13 07-Mar-13 245 100% 100%
A128400 Approval of Fire Fighting Layout & Details 14 04-Mar-12 A 08-Mar-12 A 29-Feb-12 19-Mar-12 30-Jan-13 18-Feb-13 232 100% 100%
A128420 Approval of MEP Cordination Layout 14 24-Apr-12 A 06-May-12 A 07-Mar-12 26-Mar-12 30-Jan-13 18-Feb-13 227 100% 100%
A128430 Approval of MEP Builder Work Layout 14 13-Feb-12 A 05-Mar-12 A 20-Feb-12 08-Mar-12 20-Feb-12 08-Mar-12 0 100% 100%
A128440 Approval of Lighting Layout & Details 14 21-Feb-12 A 29-Feb-12 A 29-Feb-12 19-Mar-12 27-Dec-12 16-Jan-13 210 100% 100%
A135510 Approval of Power Layout & Details 14 10-Apr-12 A 24-Apr-12 A 29-Feb-12 19-Mar-12 27-Dec-12 16-Jan-13 210 100% 100%
A128410 Approval of HVAC Layout & Details 14 18-Mar-12 A 09-Jul-12 159 29-Feb-12 19-Mar-12 07-Feb-13 26-Feb-13 238 100% 50%
A128460 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 163 29-Feb-12 19-Mar-12 24-Feb-13 13-Mar-13 249 100% 0%1st Baseme1st Basement Floor 80 21-Feb-12 A 17-May-12 A 18-Feb-12 16-Apr-12 21-Mar-12 24-Mar-13 100% 100%SubmissionSubmission 80 21-Feb-12 A 21-Apr-12 A 18-Feb-12 27-Mar-12 21-Mar-12 04-Mar-13 100% 100%A128530 Submission of Drainage Layout & Details 10 10-Mar-12 A 18-Mar-12 A 18-Feb-12 28-Feb-12 21-Mar-12 01-Apr-12 28 100% 100%
A128540 Submission of Water Supply Layout & Details 10 21-Feb-12 A 03-Mar-12 A 10-Mar-12 20-Mar-12 13-Nov-12 25-Nov-12 208 100% 100%
A128550 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 10-Mar-12 20-Mar-12 04-Dec-12 15-Dec-12 224 100% 100%
A128560 Submission of HVAC Layout & Details 10 08-Mar-12 A 18-Mar-12 A 10-Mar-12 20-Mar-12 10-Nov-12 21-Nov-12 205 100% 100%
A128570 Submission of MEP Cordination Layout 10 02-Apr-12 A 12-Apr-12 A 17-Mar-12 27-Mar-12 22-Nov-12 04-Dec-12 209 100% 100%
A128580 Submission of MEP Builder Work Layout 10 10-Mar-12 A 18-Mar-12 A 25-Feb-12 06-Mar-12 28-Mar-12 08-Apr-12 28 100% 100%
A128590 Submission of Lighting Layout & Details 10 12-Mar-12 A 22-Mar-12 A 10-Mar-12 20-Mar-12 02-Oct-12 13-Oct-12 174 100% 100%
A128600 Submission of Power Layout & Details 10 18-Mar-12 A 28-Mar-12 A 10-Mar-12 20-Mar-12 02-Oct-12 13-Oct-12 174 100% 100%
A128610 Submission of Fire Alarm Layout & Details 10 04-Mar-12 A 14-Mar-12 A 10-Mar-12 20-Mar-12 10-Feb-13 20-Feb-13 280 100% 100%
A128620 Submission of CBS Layout & Details 10 04-Mar-12 A 14-Mar-12 A 10-Mar-12 20-Mar-12 21-Feb-13 04-Mar-13 290 100% 100%
A128630 Submission of CCTV,Access Control,Intercom Layout & Details 10 11-Apr-12 A 21-Apr-12 A 10-Mar-12 20-Mar-12 13-Nov-12 25-Nov-12 208 100% 100%
A128650 Submission of BMS Layout & Details 10 02-Apr-12 A 12-Apr-12 A 10-Mar-12 20-Mar-12 30-Oct-12 10-Nov-12 196 100% 100%
A128660 Submission of Data & Telephone Layout & Details 10 08-Apr-12 A 18-Apr-12 A 10-Mar-12 20-Mar-12 08-Nov-12 20-Nov-12 204 100% 100%ApprovalApproval 52 28-Feb-12 A 17-May-12 A 29-Feb-12 16-Apr-12 09-Apr-12 24-Mar-13 100% 100%A135520 Approval of Power Layout & Details 6 29-Mar-12 A 05-Apr-12 A 21-Mar-12 09-Apr-12 14-Oct-12 01-Nov-12 144 100% 100%
A128680 Approval of Drainage Layout & Details 14 19-Mar-12 A 27-Mar-12 A 29-Feb-12 19-Mar-12 27-Nov-12 17-Dec-12 189 100% 100%
A128690 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 21-Mar-12 09-Apr-12 26-Nov-12 16-Dec-12 173 100% 100%
A128700 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 18-Mar-12 A 21-Mar-12 09-Apr-12 16-Dec-12 03-Jan-13 186 100% 100%
A128710 Approval of HVAC Layout & Details 14 19-Mar-12 A 29-Mar-12 A 21-Mar-12 09-Apr-12 22-Nov-12 12-Dec-12 171 100% 100%
A128720 Approval of MEP Cordination Layout 14 15-Apr-12 A 24-Apr-12 A 28-Mar-12 16-Apr-12 05-Dec-12 24-Dec-12 174 100% 100%
A128730 Approval of MEP Builder Work Layout 14 28-Feb-12 A 21-Mar-12 A 07-Mar-12 26-Mar-12 09-Apr-12 26-Apr-12 23 100% 100%
A128740 Approval of Lighting Layout & Details 14 25-Mar-12 A 29-Mar-12 A 21-Mar-12 09-Apr-12 14-Oct-12 01-Nov-12 144 100% 100%
A128770 Approval of CBS Layout & Details 14 15-Mar-12 A 21-Mar-12 A 21-Mar-12 09-Apr-12 05-Mar-13 24-Mar-13 241 100% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
s
s
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 6 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A128780 Approval of CCTV,Access Control,Intercom Layout & Details 14 22-Apr-12 A 03-May-12 A 21-Mar-12 09-Apr-12 26-Nov-12 16-Dec-12 173 100% 100%
A128800 Approval of BMS Layout & Details 14 15-Apr-12 A 03-May-12 A 21-Mar-12 09-Apr-12 11-Nov-12 29-Nov-12 163 100% 100%
A128810 Approval of Data & Telephone Layout & Details 14 19-Apr-12 A 17-May-12 A 21-Mar-12 09-Apr-12 21-Nov-12 11-Dec-12 170 100% 100%Ground FloGround Floor 49 01-Mar-12 A 18-Jul-12 203 10-Mar-12 03-May-12 29-Mar-12 21-Mar-13 100% 84.78%SubmissionSubmission 32 01-Mar-12 A 27-May-12 A 10-Mar-12 15-Apr-12 29-Mar-12 03-Mar-13 100% 100%A128830 Submission of Drainage Layout & Details (Low Level) 10 01-Mar-12 A 10-May-12 A 10-Mar-12 20-Mar-12 29-Mar-12 09-Apr-12 17 100% 100%
A128840 Submission of Water Supply Layout & Details 16 01-Apr-12 A 10-May-12 A 21-Mar-12 08-Apr-12 26-Nov-12 15-Dec-12 208 100% 100%
A128850 Submission of Fire Fighting Layout & Details 10 01-May-12 A 19-May-12 A 28-Mar-12 08-Apr-12 23-Jan-13 04-Feb-13 250 100% 100%
A128880 Submission of MEP Builder Work Layout 12 24-Apr-12 A 07-May-12 A 02-Apr-12 15-Apr-12 22-Apr-12 05-May-12 17 100% 100%
A128890 Submission of Lighting Layout & Details 10 16-May-12 A 27-May-12 A 28-Mar-12 08-Apr-12 08-Jan-13 19-Jan-13 237 100% 100%
A128900 Submission of Power Layout & Details 10 06-May-12 A 16-May-12 A 28-Mar-12 08-Apr-12 08-Jan-13 19-Jan-13 237 100% 100%
A128930 Submission of CCTV,Access Control,Intercom Layout & Details 10 29-Apr-12 A 09-May-12 A 28-Mar-12 08-Apr-12 04-Dec-12 15-Dec-12 208 100% 100%
A128960 Submission of Data & Telephone Layout & Details 10 09-May-12 A 20-May-12 A 28-Mar-12 08-Apr-12 20-Feb-13 03-Mar-13 273 100% 100%
A129130 Submission of Drainage Layout & Details (High Level) 16 05-May-12 A 22-May-12 A 21-Mar-12 08-Apr-12 26-Nov-12 15-Dec-12 208 100% 100%ApprovalApproval 31 18-Apr-12 A 18-Jul-12 169 21-Mar-12 03-May-12 06-May-12 21-Mar-13 100% 72.22%A128980 Approval of Drainage Layout & Details (Low Level) 14 13-May-12 A 21-May-12 A 21-Mar-12 09-Apr-12 20-Jan-13 07-Feb-13 210 100% 100%
A128990 Approval of Water Supply Layout & Details 14 18-Apr-12 A 19-May-12 A 09-Apr-12 26-Apr-12 20-Jan-13 07-Feb-13 197 100% 100%
A129000 Approval of Fire Fighting Layout & Details 14 20-May-12 A 26-May-12 A 09-Apr-12 26-Apr-12 05-Feb-13 24-Feb-13 208 100% 100%
A129030 Approval of MEP Builder Work Layout 14 08-May-12 A 17-May-12 A 16-Apr-12 03-May-12 06-May-12 23-May-12 14 100% 100%
A129080 Approval of CCTV,Access Control,Intercom Layout & Details 14 10-May-12 A 17-May-12 A 09-Apr-12 26-Apr-12 16-Dec-12 03-Jan-13 173 100% 100%
A129040 Approval of Lighting Layout & Details 14 28-May-12 A 09-Jul-12 146 09-Apr-12 26-Apr-12 20-Jan-13 07-Feb-13 197 100% 50%
A129050 Approval of Power Layout & Details 14 17-May-12 A 09-Jul-12 146 09-Apr-12 26-Apr-12 20-Jan-13 07-Feb-13 197 100% 50%
A129140 Approval of Drainage Layout & Details (High Level) 14 23-May-12 A 09-Jul-12 160 09-Apr-12 26-Apr-12 10-Feb-13 27-Feb-13 211 100% 50%
A129110 Approval of Data & Telephone Layout & Details 14 21-May-12 A 18-Jul-12 169 09-Apr-12 26-Apr-12 04-Mar-13 21-Mar-13 227 100% 0%1st Floor1st Floor 78 04-Apr-12 A 18-Jul-12 204 27-Mar-12 23-May-12 22-Apr-12 21-Mar-13 100% 79.93%SubmissionSubmission 56 04-Apr-12 A 25-Jun-12 A 27-Mar-12 03-May-12 22-Apr-12 02-Feb-13 100% 100%A129180 Submission of HVAC Layout & Details 10 13-Jun-12 A 25-Jun-12 A 16-Apr-12 26-Apr-12 29-Nov-12 11-Dec-12 189 100% 100%
A129200 Submission of MEP Builder Work Layout 12 06-May-12 A 19-May-12 A 21-Apr-12 03-May-12 16-May-12 29-May-12 22 100% 100%
A129210 Submission of Lighting Layout & Details 10 13-Jun-12 A 25-Jun-12 A 16-Apr-12 26-Apr-12 30-Oct-12 10-Nov-12 164 100% 100%
A129220 Submission of Power Layout & Details 10 22-May-12 A 02-Jun-12 A 16-Apr-12 26-Apr-12 30-Oct-12 10-Nov-12 164 100% 100%
A129250 Submission of CCTV,Access Control,Intercom Layout & Details 10 04-Apr-12 A 14-Apr-12 A 16-Apr-12 26-Apr-12 08-Jan-13 19-Jan-13 221 100% 100%
A129270 Submission of BMS Layout & Details 10 02-May-12 A 13-May-12 A 16-Apr-12 26-Apr-12 17-Dec-12 27-Dec-12 203 100% 100%
A129280 Submission of Data & Telephone Layout & Details 10 28-Apr-12 A 08-May-12 A 16-Apr-12 26-Apr-12 21-Jan-13 02-Feb-13 232 100% 100%
A129450 Submission of Drainage Layout & Details (High Level) 16 17-May-12 A 04-Jun-12 A 09-Apr-12 26-Apr-12 21-Oct-12 10-Nov-12 164 100% 100%
A129150 Submission of Drainage Layout & Details (Low Level) 11 08-May-12 A 20-May-12 A 27-Mar-12 08-Apr-12 22-Apr-12 03-May-12 22 100% 100%
A129160 Submission of Water Supply Layout & Details 16 21-Apr-12 A 08-May-12 A 09-Apr-12 26-Apr-12 21-Oct-12 10-Nov-12 164 100% 100%
A129170 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 16-Apr-12 26-Apr-12 09-Dec-12 19-Dec-12 196 100% 100%ApprovalApproval 65 15-Apr-12 A 18-Jul-12 169 09-Apr-12 23-May-12 30-May-12 21-Mar-13 100% 63.64%A129310 Approval of Water Supply Layout & Details 14 09-May-12 A 20-May-12 A 29-Apr-12 16-May-12 11-Feb-13 28-Feb-13 198 100% 100%
A129320 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 29-Apr-12 16-May-12 20-Dec-12 09-Jan-13 163 100% 100%
A129350 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 06-May-12 23-May-12 30-May-12 19-Jun-12 18 100% 100%
A129400 Approval of CCTV,Access Control,Intercom Layout & Details 14 15-Apr-12 A 03-May-12 A 29-Apr-12 16-May-12 20-Jan-13 07-Feb-13 183 100% 100%
A129420 Approval of BMS Layout & Details 14 14-May-12 A 23-May-12 A 29-Apr-12 16-May-12 20-Jan-13 07-Feb-13 183 100% 100%
A129430 Approval of Data & Telephone Layout & Details 14 09-May-12 A 17-May-12 A 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 100%
A129300 Approval of Drainage Layout & Details (Low Level) 14 21-May-12 A 09-Jul-12 111 09-Apr-12 26-Apr-12 28-Nov-12 18-Dec-12 162 100% 50%
A129460 Approval of Drainage Layout & Details (High Level) 14 05-Jun-12 A 09-Jul-12 111 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 50%
A129330 Approval of HVAC Layout & Details 14 26-Jun-12 A 18-Jul-12 113 29-Apr-12 16-May-12 12-Dec-12 31-Dec-12 157 100% 0%
A129360 Approval of Lighting Layout & Details 14 26-Jun-12 A 18-Jul-12 92 29-Apr-12 16-May-12 11-Nov-12 29-Nov-12 136 100% 0%
A129370 Approval of Power Layout & Details 14 03-Jun-12 A 18-Jul-12 92 29-Apr-12 16-May-12 11-Nov-12 29-Nov-12 136 100% 0%2nd Floor2nd Floor 44 08-May-12 A 09-Jul-12 153 06-May-12 13-Jun-12 05-Jun-12 10-Jan-13 100% 94.07%SubmissionSubmission 44 08-May-12 A 30-Jun-12 A 06-May-12 24-May-12 05-Jun-12 22-Dec-12 100% 100%A129470 Submission of Drainage Layout & Details 11 23-May-12 A 04-Jun-12 A 06-May-12 17-May-12 05-Jun-12 18-Jun-12 26 100% 100%
A129480 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 06-May-12 17-May-12 08-Nov-12 21-Nov-12 155 100% 100%
A129490 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 07-May-12 17-May-12 11-Dec-12 22-Dec-12 180 100% 100%
A129520 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 14-May-12 24-May-12 13-Jun-12 25-Jun-12 26 100% 100%
A129530 Submission of Lighting Layout & Details 10 18-Jun-12 A 30-Jun-12 A 07-May-12 17-May-12 10-Nov-12 21-Nov-12 155 100% 100%
A129540 Submission of Power Layout & Details 10 18-Jun-12 A 28-Jun-12 A 07-May-12 17-May-12 08-Dec-12 18-Dec-12 177 100% 100%ApprovalApproval 26 20-May-12 A 09-Jul-12 127 20-May-12 13-Jun-12 26-Jun-12 10-Jan-13 100% 87.5%A129630 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 20-May-12 06-Jun-12 22-Nov-12 12-Dec-12 129 100% 100%
A129640 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 20-May-12 06-Jun-12 23-Dec-12 10-Jan-13 149 100% 100%
A129670 Approval of MEP Builder Work Layout 14 26-May-12 A 30-May-12 A 27-May-12 13-Jun-12 26-Jun-12 15-Jul-12 21 100% 100%
A129620 Approval of Drainage Layout & Details 14 05-Jun-12 A 09-Jul-12 107 20-May-12 06-Jun-12 22-Nov-12 12-Dec-12 129 100% 50%3rd Floor3rd Floor 66 14-Apr-12 A 09-Jul-12 201 06-May-12 06-Jun-12 15-May-12 10-Mar-13 100% 94.07%SubmissionSubmission 66 14-Apr-12 A 30-Jun-12 A 06-May-12 17-May-12 15-May-12 18-Feb-13 100% 100%A129770 Submission of Drainage Layout & Details 11 23-May-12 A 04-Jun-12 A 06-May-12 17-May-12 15-May-12 27-May-12 8 100% 100%
A129780 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 06-May-12 17-May-12 29-Jan-13 10-Feb-13 221 100% 100%
A129790 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 07-May-12 17-May-12 05-Feb-13 16-Feb-13 226 100% 100%
A129830 Submission of Lighting Layout & Details 10 11-Jun-12 A 30-Jun-12 A 07-May-12 17-May-12 30-Jan-13 10-Feb-13 221 100% 100%
A129840 Submission of Power Layout & Details 10 19-Jun-12 A 30-Jun-12 A 07-May-12 17-May-12 30-Jan-13 10-Feb-13 221 100% 100%
A129860 Submission of CBS Layout & Details 10 14-Apr-12 A 24-Apr-12 A 07-May-12 17-May-12 07-Feb-13 18-Feb-13 228 100% 100%ApprovalApproval 43 25-Apr-12 A 09-Jul-12 167 20-May-12 06-Jun-12 17-Feb-13 10-Mar-13 100% 87.5%A129920 Approval of Drainage Layout & Details 14 05-Jun-12 A 21-Jun-12 A 20-May-12 06-Jun-12 17-Feb-13 06-Mar-13 187 100% 100%
A129930 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 20-May-12 06-Jun-12 17-Feb-13 06-Mar-13 187 100% 100%
A129940 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 20-May-12 06-Jun-12 17-Feb-13 06-Mar-13 187 100% 100%
A130010 Approval of CBS Layout & Details 14 25-Apr-12 A 09-Jul-12 167 20-May-12 06-Jun-12 19-Feb-13 10-Mar-13 189 100% 50%4th Floor4th Floor 65 15-Apr-12 A 09-Jul-12 201 24-May-12 28-Jun-12 28-Jun-12 10-Mar-13 100% 94.26%SubmissionSubmission 65 15-Apr-12 A 30-Jun-12 A 24-May-12 07-Jun-12 28-Jun-12 18-Feb-13 100% 100%A130070 Submission of Drainage Layout & Details 13 21-May-12 A 04-Jun-12 A 24-May-12 07-Jun-12 28-Jun-12 12-Jul-12 29 100% 100%
A130080 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 19-Nov-12 04-Dec-12 147 100% 100%
A130090 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 12-Dec-12 23-Dec-12 163 100% 100%
A130130 Submission of Lighting Layout & Details 10 18-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 22-Nov-12 04-Dec-12 147 100% 100%
A130140 Submission of Power Layout & Details 10 19-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 22-Nov-12 04-Dec-12 147 100% 100%
A130160 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 07-Feb-13 18-Feb-13 210 100% 100%ApprovalApproval 42 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 09-Dec-12 10-Mar-13 100% 87.5%A130220 Approval of Drainage Layout & Details 14 05-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 09-Dec-12 26-Dec-12 124 100% 100%
A130230 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 10-Feb-13 27-Feb-13 167 100% 100%
A130240 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 24-Dec-12 13-Jan-13 135 100% 100%
A130310 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%5th Floor5th Floor 65 15-Apr-12 A 09-Jul-12 201 24-May-12 28-Jun-12 28-Jun-12 10-Mar-13 100% 94.26%SubmissionSubmission 65 15-Apr-12 A 30-Jun-12 A 24-May-12 07-Jun-12 28-Jun-12 18-Feb-13 100% 100%A130370 Submission of Drainage Layout & Details 13 21-May-12 A 04-Jun-12 A 24-May-12 07-Jun-12 28-Jun-12 12-Jul-12 29 100% 100%
A130380 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 08-Dec-12 22-Dec-12 162 100% 100%
A130390 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 12-Dec-12 23-Dec-12 163 100% 100%
A130430 Submission of Lighting Layout & Details 10 19-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 07-Feb-13 18-Feb-13 210 100% 100%
A130440 Submission of Power Layout & Details 10 19-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 07-Feb-13 18-Feb-13 210 100% 100%
A130460 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 07-Feb-13 18-Feb-13 210 100% 100%ApprovalApproval 42 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 13-Dec-12 10-Mar-13 100% 87.5%A130520 Approval of Drainage Layout & Details 14 05-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 13-Dec-12 02-Jan-13 128 100% 100%
A130530 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 11-Feb-13 28-Feb-13 168 100% 100%
A130540 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 24-Dec-12 13-Jan-13 135 100% 100%
A130610 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%6th Floor6th Floor 65 15-Apr-12 A 09-Jul-12 201 24-May-12 28-Jun-12 14-Jul-12 10-Mar-13 100% 94.26%SubmissionSubmission 65 15-Apr-12 A 30-Jun-12 A 24-May-12 07-Jun-12 14-Jul-12 18-Feb-13 100% 100%A130670 Submission of Drainage Layout & Details 13 21-May-12 A 04-Jun-12 A 24-May-12 07-Jun-12 14-Jul-12 28-Jul-12 42 100% 100%
A130680 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 10-Dec-12 24-Dec-12 164 100% 100%
A130690 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 26-Dec-12 07-Jan-13 175 100% 100%
A130730 Submission of Lighting Layout & Details 10 18-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 13-Dec-12 24-Dec-12 164 100% 100%
A130740 Submission of Power Layout & Details 10 19-Jun-12 A 30-Jun-12 A 28-May-12 07-Jun-12 13-Dec-12 24-Dec-12 164 100% 100%
A130760 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 07-Feb-13 18-Feb-13 210 100% 100%ApprovalApproval 42 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 27-Dec-12 10-Mar-13 100% 87.5%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Drainage Layout & Details (High Level)
Approval of Data & Telephone Layout & Details
s
s
Approval of Drainage Layout & Details (Low Level)
Approval of Drainage Layout & Details (High Level)
ails Approval of HVAC Layout & Details
ails Approval of Lighting Layout & Details
Approval of Power Layout & Details
ls
s
Approval of Drainage Layout & Details
s
s
Approval of CBS Layout & Details
ls
s
Approval of CBS Layout & Details
ls
s
Approval of CBS Layout & Details
ls
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 7 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A130820 Approval of Drainage Layout & Details 14 05-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 27-Dec-12 16-Jan-13 138 100% 100%
A130830 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 12-Feb-13 03-Mar-13 169 100% 100%
A130840 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 08-Jan-13 28-Jan-13 145 100% 100%
A130910 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%7th Floor7th Floor 53 15-Apr-12 A 09-Jul-12 201 11-Jun-12 17-Jul-12 16-Dec-12 10-Mar-13 50.65% 90.91%SubmissionSubmission 41 15-Apr-12 A 27-May-12 A 11-Jun-12 27-Jun-12 16-Dec-12 18-Feb-13 100% 100%A130980 Submission of Water Supply Layout & Details 14 16-May-12 A 27-May-12 A 11-Jun-12 27-Jun-12 16-Dec-12 31-Dec-12 154 100% 100%
A130990 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 14-Jun-12 27-Jun-12 30-Dec-12 12-Jan-13 163 100% 100%
A131060 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 14-Jun-12 26-Jun-12 07-Feb-13 18-Feb-13 195 100% 100%ApprovalApproval 36 26-Apr-12 A 09-Jul-12 167 27-Jun-12 17-Jul-12 13-Jan-13 10-Mar-13 9.52% 83.33%A131130 Approval of Water Supply Layout & Details 14 28-May-12 A 03-Jun-12 A 28-Jun-12 17-Jul-12 12-Feb-13 03-Mar-13 156 7.14% 100%
A131140 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 28-Jun-12 17-Jul-12 13-Jan-13 31-Jan-13 135 7.14% 100%
A131210 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 27-Jun-12 16-Jul-12 19-Feb-13 10-Mar-13 162 14.29% 50%Roof FloorRoof Floor 46 15-Apr-12 A 16-Jul-12 202 07-Jul-12 07-Aug-12 09-Jan-13 18-Mar-13 0% 85.71%SubmissionSubmission 30 15-Apr-12 A 19-May-12 A 07-Jul-12 18-Jul-12 09-Jan-13 26-Feb-13 0% 100%A131290 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 14-Feb-13 26-Feb-13 183 0% 100%
A131360 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 07-Jul-12 17-Jul-12 09-Jan-13 20-Jan-13 153 0% 100%ApprovalApproval 30 26-Apr-12 A 16-Jul-12 168 18-Jul-12 07-Aug-12 21-Jan-13 18-Mar-13 0% 75%A131440 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 27-Feb-13 18-Mar-13 152 0% 100%
A131510 Approval of CBS Layout & Details 14 26-Apr-12 A 16-Jul-12 142 18-Jul-12 06-Aug-12 21-Jan-13 10-Feb-13 127 0% 50%
Residential AResidential Apartments (Block C) 126 09-Feb-12 A 18-Jul-12 185 15-Feb-12 07-Aug-12 15-Feb-12 28-Feb-13 93.66% 86.48%
2nd Baseme2nd Basement Floor 91 09-Feb-12 A 18-Jul-12 185 15-Feb-12 25-Mar-12 15-Feb-12 28-Feb-13 100% 89.71%SubmissionSubmission 75 09-Feb-12 A 23-Apr-12 A 15-Feb-12 05-Mar-12 15-Feb-12 30-Jan-13 100% 100%A131870 Submission of Drainage Layout & Details 3 10-Mar-12 A 14-Mar-12 A 15-Feb-12 18-Feb-12 15-Feb-12 18-Feb-12 0 100% 100%
A131880 Submission of Water Supply Layout & Details 10 25-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 05-Jan-13 15-Jan-13 268 100% 100%
A131890 Submission of Fire Fighting Layout & Details 10 25-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 01-Dec-12 12-Dec-12 240 100% 100%
A131900 Submission of HVAC Layout & Details 10 07-Mar-12 A 17-Mar-12 A 18-Feb-12 28-Feb-12 04-Dec-12 15-Dec-12 242 100% 100%
A131910 Submission of MEP Cordination Layout 10 13-Apr-12 A 23-Apr-12 A 23-Feb-12 05-Mar-12 14-Nov-12 26-Nov-12 222 100% 100%
A131920 Submission of MEP Builder Work Layout 3 09-Feb-12 A 12-Feb-12 A 15-Feb-12 18-Feb-12 15-Feb-12 18-Feb-12 0 100% 100%
A131930 Submission of Lighting Layout & Details 10 10-Feb-12 A 20-Feb-12 A 18-Feb-12 28-Feb-12 24-Oct-12 06-Nov-12 211 100% 100%
A131940 Submission of Power Layout & Details 10 01-Apr-12 A 09-Apr-12 A 18-Feb-12 28-Feb-12 24-Oct-12 06-Nov-12 211 100% 100%
A131950 Submission of Fire Alarm Layout & Details 10 25-Feb-12 A 07-Mar-12 A 18-Feb-12 28-Feb-12 19-Jan-13 30-Jan-13 280 100% 100%ApprovalApproval 74 13-Feb-12 A 18-Jul-12 154 19-Feb-12 25-Mar-12 19-Feb-12 28-Feb-13 100% 83.33%A132020 Approval of Drainage Layout & Details 14 15-Mar-12 A 17-Mar-12 A 19-Feb-12 07-Mar-12 11-Feb-13 28-Feb-13 248 100% 100%
A132030 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 29-Feb-12 19-Mar-12 16-Jan-13 05-Feb-13 223 100% 100%
A132040 Approval of Fire Fighting Layout & Details 14 04-Mar-12 A 08-Mar-12 A 29-Feb-12 19-Mar-12 13-Dec-12 02-Jan-13 200 100% 100%
A132060 Approval of MEP Cordination Layout 14 24-Apr-12 A 06-May-12 A 06-Mar-12 25-Mar-12 27-Nov-12 17-Dec-12 185 100% 100%
A132070 Approval of MEP Builder Work Layout 14 13-Feb-12 A 05-Mar-12 A 19-Feb-12 07-Mar-12 19-Feb-12 07-Mar-12 0 100% 100%
A132080 Approval of Lighting Layout & Details 14 21-Feb-12 A 29-Feb-12 A 29-Feb-12 19-Mar-12 07-Nov-12 27-Nov-12 176 100% 100%
A132090 Approval of Power Layout & Details 14 10-Apr-12 A 24-Apr-12 A 29-Feb-12 19-Mar-12 07-Nov-12 27-Nov-12 176 100% 100%
A132050 Approval of HVAC Layout & Details 14 18-Mar-12 A 09-Jul-12 122 29-Feb-12 19-Mar-12 16-Dec-12 03-Jan-13 201 100% 50%
A132100 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 147 29-Feb-12 19-Mar-12 31-Jan-13 19-Feb-13 233 100% 0%1st Baseme1st Basement Floor 103 21-Feb-12 A 18-Jul-12 183 18-Feb-12 29-Apr-12 23-Feb-12 26-Feb-13 100% 93.52%SubmissionSubmission 86 21-Feb-12 A 12-Apr-12 A 18-Feb-12 09-Apr-12 23-Feb-12 06-Feb-13 100% 100%A132170 Submission of Drainage Layout & Details 10 08-Mar-12 A 18-Mar-12 A 18-Feb-12 28-Feb-12 23-Feb-12 05-Mar-12 5 100% 100%
A132180 Submission of Water Supply Layout & Details 10 21-Feb-12 A 03-Mar-12 A 22-Mar-12 02-Apr-12 22-Jan-13 03-Feb-13 254 100% 100%
A132190 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 22-Mar-12 02-Apr-12 12-Nov-12 24-Nov-12 196 100% 100%
A132200 Submission of HVAC Layout & Details 10 08-Mar-12 A 18-Mar-12 A 22-Mar-12 02-Apr-12 26-Nov-12 08-Dec-12 207 100% 100%
A132210 Submission of MEP Cordination Layout 10 02-Apr-12 A 12-Apr-12 A 29-Mar-12 09-Apr-12 26-Nov-12 08-Dec-12 201 100% 100%
A132220 Submission of MEP Builder Work Layout 10 08-Mar-12 A 18-Mar-12 A 08-Mar-12 19-Mar-12 14-Mar-12 25-Mar-12 5 100% 100%
A132230 Submission of Lighting Layout & Details 10 12-Mar-12 A 22-Mar-12 A 22-Mar-12 02-Apr-12 28-Nov-12 10-Dec-12 209 100% 100%
A132240 Submission of Power Layout & Details 10 18-Mar-12 A 28-Mar-12 A 22-Mar-12 02-Apr-12 28-Nov-12 10-Dec-12 209 100% 100%
A132250 Submission of Fire Alarm Layout & Details 10 04-Mar-12 A 14-Mar-12 A 22-Mar-12 02-Apr-12 27-Jan-13 06-Feb-13 257 100% 100%ApprovalApproval 78 04-Mar-12 A 18-Jul-12 152 29-Feb-12 29-Apr-12 26-Mar-12 26-Feb-13 100% 88.89%A132320 Approval of Drainage Layout & Details 14 19-Mar-12 A 27-Mar-12 A 29-Feb-12 19-Mar-12 04-Feb-13 21-Feb-13 235 100% 100%
A132330 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 03-Apr-12 22-Apr-12 04-Feb-13 21-Feb-13 211 100% 100%
A132340 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 17-Mar-12 A 03-Apr-12 22-Apr-12 25-Nov-12 13-Dec-12 163 100% 100%
A132350 Approval of HVAC Layout & Details 14 19-Mar-12 A 29-Mar-12 A 03-Apr-12 22-Apr-12 09-Dec-12 26-Dec-12 172 100% 100%
A132360 Approval of MEP Cordination Layout 14 13-Apr-12 A 24-Apr-12 A 10-Apr-12 29-Apr-12 09-Dec-12 26-Dec-12 167 100% 100%
A132370 Approval of MEP Builder Work Layout 14 19-Mar-12 A 21-Mar-12 A 20-Mar-12 08-Apr-12 26-Mar-12 12-Apr-12 4 100% 100%
A132380 Approval of Lighting Layout & Details 14 24-Mar-12 A 31-Mar-12 A 03-Apr-12 22-Apr-12 11-Dec-12 30-Dec-12 174 100% 100%
A132390 Approval of Power Layout & Details 14 29-Mar-12 A 05-Apr-12 A 03-Apr-12 22-Apr-12 11-Dec-12 30-Dec-12 174 100% 100%
A132400 Approval of Fire Alarm Layout & Details 14 15-Mar-12 A 18-Jul-12 152 03-Apr-12 22-Apr-12 07-Feb-13 26-Feb-13 214 100% 0%Ground FloGround Floor 84 01-Mar-12 A 09-Jul-12 162 10-Mar-12 03-May-12 20-Mar-12 22-Jan-13 100% 97.27%SubmissionSubmission 67 01-Mar-12 A 16-May-12 A 10-Mar-12 15-Apr-12 20-Mar-12 02-Jan-13 100% 100%A132470 Submission of Drainage Layout & Details (Low Level) 10 03-Mar-12 A 12-Mar-12 A 10-Mar-12 20-Mar-12 20-Mar-12 31-Mar-12 9 100% 100%
A132480 Submission of Water Supply Layout & Details 16 01-Apr-12 A 17-Apr-12 A 21-Mar-12 08-Apr-12 12-Nov-12 01-Dec-12 197 100% 100%
A132490 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 28-Mar-12 08-Apr-12 22-Dec-12 02-Jan-13 223 100% 100%
A132500 Submission of HVAC Layout & Details 10 25-Mar-12 A 01-Apr-12 A 28-Mar-12 08-Apr-12 22-Nov-12 04-Dec-12 199 100% 100%
A132510 Submission of MEP Cordination Layout 12 03-May-12 A 16-May-12 A 02-Apr-12 15-Apr-12 18-Nov-12 01-Dec-12 191 100% 100%
A132520 Submission of MEP Builder Work Layout 12 14-Mar-12 A 24-Mar-12 A 02-Apr-12 15-Apr-12 12-Apr-12 25-Apr-12 9 100% 100%
A132530 Submission of Lighting Layout & Details 10 12-Mar-12 A 24-Mar-12 A 28-Mar-12 08-Apr-12 20-Nov-12 01-Dec-12 197 100% 100%
A132540 Submission of Power Layout & Details 10 19-Mar-12 A 29-Mar-12 A 28-Mar-12 08-Apr-12 20-Nov-12 01-Dec-12 197 100% 100%
A132600 Submission of Data & Telephone Layout & Details 10 25-Mar-12 A 04-Apr-12 A 28-Mar-12 08-Apr-12 20-Nov-12 01-Dec-12 197 100% 100%
A132770 Submission of Drainage Layout & Details (High Level) 16 26-Apr-12 A 14-May-12 A 21-Mar-12 08-Apr-12 12-Nov-12 01-Dec-12 197 100% 100%ApprovalApproval 60 11-Mar-12 A 09-Jul-12 135 21-Mar-12 03-May-12 26-Apr-12 22-Jan-13 100% 95%A132620 Approval of Drainage Layout & Details (Low Level) 14 13-Mar-12 A 21-May-12 A 21-Mar-12 09-Apr-12 19-Dec-12 08-Jan-13 189 100% 100%
A132630 Approval of Water Supply Layout & Details 14 18-Apr-12 A 28-Apr-12 A 09-Apr-12 26-Apr-12 13-Dec-12 02-Jan-13 172 100% 100%
A132640 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 26-May-12 A 09-Apr-12 26-Apr-12 03-Jan-13 22-Jan-13 186 100% 100%
A132660 Approval of MEP Cordination Layout 14 17-May-12 A 23-May-12 A 16-Apr-12 03-May-12 03-Dec-12 20-Dec-12 159 100% 100%
A132670 Approval of MEP Builder Work Layout 14 25-Mar-12 A 02-Apr-12 A 16-Apr-12 03-May-12 26-Apr-12 15-May-12 8 100% 100%
A132680 Approval of Lighting Layout & Details 14 25-Mar-12 A 02-Apr-12 A 09-Apr-12 26-Apr-12 03-Dec-12 20-Dec-12 164 100% 100%
A132690 Approval of Power Layout & Details 14 31-Mar-12 A 27-May-12 A 09-Apr-12 26-Apr-12 03-Dec-12 20-Dec-12 164 100% 100%
A132750 Approval of Data & Telephone Layout & Details 14 05-Apr-12 A 03-May-12 A 09-Apr-12 26-Apr-12 03-Dec-12 20-Dec-12 164 100% 100%
A132780 Approval of Drainage Layout & Details (High Level) 14 15-May-12 A 23-May-12 A 09-Apr-12 26-Apr-12 19-Dec-12 08-Jan-13 176 100% 100%
A132650 Approval of HVAC Layout & Details 14 02-Apr-12 A 09-Jul-12 115 09-Apr-12 26-Apr-12 05-Dec-12 24-Dec-12 166 100% 50%1st Floor1st Floor 67 04-Apr-12 A 18-Jul-12 162 27-Mar-12 23-May-12 12-Apr-12 31-Jan-13 100% 94.98%SubmissionSubmission 49 04-Apr-12 A 11-Jun-12 A 27-Mar-12 03-May-12 12-Apr-12 27-Nov-12 100% 100%A133090 Submission of Drainage Layout & Details (High Level) 16 23-May-12 A 10-Jun-12 A 09-Apr-12 26-Apr-12 21-Aug-12 08-Sep-12 112 100% 100%
A132790 Submission of Drainage Layout & Details (Low Level) 11 02-May-12 A 14-May-12 A 27-Mar-12 08-Apr-12 12-Apr-12 24-Apr-12 14 100% 100%
A132800 Submission of Water Supply Layout & Details 16 01-May-12 A 08-May-12 A 09-Apr-12 26-Apr-12 21-Aug-12 08-Sep-12 112 100% 100%
A132810 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 16-Apr-12 26-Apr-12 26-Sep-12 07-Oct-12 137 100% 100%
A132820 Submission of HVAC Layout & Details 10 05-Jun-12 A 11-Jun-12 A 16-Apr-12 26-Apr-12 11-Sep-12 22-Sep-12 124 100% 100%
A132840 Submission of MEP Builder Work Layout 12 26-Apr-12 A 10-May-12 A 21-Apr-12 03-May-12 07-May-12 20-May-12 14 100% 100%
A132850 Submission of Lighting Layout & Details 10 27-May-12 A 06-Jun-12 A 16-Apr-12 26-Apr-12 28-Aug-12 08-Sep-12 112 100% 100%
A132860 Submission of Power Layout & Details 10 14-May-12 A 24-May-12 A 16-Apr-12 26-Apr-12 28-Aug-12 08-Sep-12 112 100% 100%
A132890 Submission of CCTV,Access Control,Intercom Layout & Details 10 04-Apr-12 A 14-Apr-12 A 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 100%
A132910 Submission of BMS Layout & Details 10 01-May-12 A 13-May-12 A 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 100%
A132920 Submission of Data & Telephone Layout & Details 10 04-Jun-12 A 11-Jun-12 A 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 100%ApprovalApproval 56 15-Apr-12 A 18-Jul-12 134 09-Apr-12 23-May-12 21-May-12 31-Jan-13 100% 90.91%A132970 Approval of HVAC Layout & Details 14 12-Jun-12 A 27-Jun-12 A 29-Apr-12 16-May-12 23-Sep-12 10-Oct-12 102 100% 100%
A132990 Approval of MEP Builder Work Layout 14 13-May-12 A 17-May-12 A 06-May-12 23-May-12 21-May-12 07-Jun-12 11 100% 100%
A133000 Approval of Lighting Layout & Details 14 07-Jun-12 A 21-Jun-12 A 29-Apr-12 16-May-12 09-Sep-12 26-Sep-12 92 100% 100%
A133010 Approval of Power Layout & Details 14 26-May-12 A 27-Jun-12 A 29-Apr-12 16-May-12 09-Sep-12 26-Sep-12 92 100% 100%
A133040 Approval of CCTV,Access Control,Intercom Layout & Details 14 15-Apr-12 A 03-May-12 A 29-Apr-12 16-May-12 13-Jan-13 31-Jan-13 178 100% 100%
A133060 Approval of BMS Layout & Details 14 14-May-12 A 23-May-12 A 29-Apr-12 16-May-12 13-Jan-13 31-Jan-13 178 100% 100%
A133100 Approval of Drainage Layout & Details (High Level) 14 10-Jun-12 A 21-Jun-12 A 29-Apr-12 16-May-12 09-Sep-12 26-Sep-12 92 100% 100%
A132940 Approval of Drainage Layout & Details (Low Level) 14 15-May-12 A 23-May-12 A 09-Apr-12 26-Apr-12 09-Sep-12 26-Sep-12 106 100% 100%
A132950 Approval of Water Supply Layout & Details 14 09-May-12 A 20-May-12 A 29-Apr-12 16-May-12 09-Sep-12 26-Sep-12 92 100% 100%
A132960 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 29-Apr-12 16-May-12 08-Oct-12 28-Oct-12 113 100% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Approval of CBS Layout & Details
Approval of CBS Layout & Details
Approval of CBS Layout & Details
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Approval of Fire Alarm Layout & Details
Approval of HVAC Layout & Details
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 8 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A133070 Approval of Data & Telephone Layout & Details 14 12-Jun-12 A 18-Jul-12 134 29-Apr-12 16-May-12 13-Jan-13 31-Jan-13 178 100% 0%2nd Floor2nd Floor 74 15-Apr-12 A 18-Jul-12 181 16-Apr-12 13-Jun-12 16-May-12 24-Feb-13 100% 77.52%SubmissionSubmission 59 15-Apr-12 A 20-Jun-12 A 16-Apr-12 24-May-12 16-May-12 04-Feb-13 100% 100%A133110 Submission of Drainage Layout & Details 11 29-May-12 A 10-Jun-12 A 06-May-12 17-May-12 16-May-12 28-May-12 9 100% 100%
A133120 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 06-May-12 17-May-12 10-Sep-12 22-Sep-12 106 100% 100%
A133130 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 07-May-12 17-May-12 14-Oct-12 24-Oct-12 134 100% 100%
A133160 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 14-May-12 24-May-12 24-May-12 04-Jun-12 9 100% 100%
A133170 Submission of Lighting Layout & Details 10 30-May-12 A 10-Jun-12 A 07-May-12 17-May-12 11-Sep-12 22-Sep-12 106 100% 100%
A133180 Submission of Power Layout & Details 10 30-May-12 A 10-Jun-12 A 07-May-12 17-May-12 11-Sep-12 22-Sep-12 106 100% 100%
A133200 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 07-May-12 17-May-12 23-Jan-13 04-Feb-13 216 100% 100%
A133210 Submission of CCTV,Access Control,Intercom Layout & Details 10 11-Jun-12 A 20-Jun-12 A 16-Apr-12 26-Apr-12 23-Jan-13 04-Feb-13 234 100% 100%
A133230 Submission of BMS Layout & Details 10 05-Jun-12 A 11-Jun-12 A 16-Apr-12 26-Apr-12 23-Jan-13 04-Feb-13 234 100% 100%ApprovalApproval 53 26-Apr-12 A 18-Jul-12 150 29-Apr-12 13-Jun-12 05-Jun-12 24-Feb-13 100% 61.11%A133260 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 20-May-12 06-Jun-12 23-Sep-12 10-Oct-12 87 100% 100%
A133270 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 20-May-12 06-Jun-12 24-Sep-12 11-Oct-12 88 100% 100%
A133280 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 20-May-12 06-Jun-12 28-Oct-12 14-Nov-12 111 100% 100%
A133310 Approval of MEP Builder Work Layout 14 26-May-12 A 30-May-12 A 27-May-12 13-Jun-12 05-Jun-12 25-Jun-12 7 100% 100%
A133380 Approval of BMS Layout & Details 14 12-Jun-12 A 27-Jun-12 A 29-Apr-12 16-May-12 05-Feb-13 24-Feb-13 194 100% 100%
A133350 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 157 20-May-12 06-Jun-12 05-Feb-13 24-Feb-13 179 100% 50%
A133320 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 58 20-May-12 06-Jun-12 23-Sep-12 10-Oct-12 87 100% 0%
A133330 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 58 20-May-12 06-Jun-12 23-Sep-12 10-Oct-12 87 100% 0%
A133360 Approval of CCTV,Access Control,Intercom Layout & Details 14 21-Jun-12 A 18-Jul-12 150 29-Apr-12 16-May-12 05-Feb-13 24-Feb-13 194 100% 0%3rd Floor3rd Floor 66 15-Apr-12 A 18-Jul-12 155 06-May-12 25-Jun-12 06-May-12 23-Jan-13 100% 79.41%SubmissionSubmission 60 15-Apr-12 A 10-Jun-12 A 06-May-12 04-Jun-12 06-May-12 18-Dec-12 100% 100%A133410 Submission of Drainage Layout & Details 11 05-Jun-12 A 10-Jun-12 A 06-May-12 17-May-12 06-May-12 17-May-12 0 100% 100%
A133420 Submission of Water Supply Layout & Details 11 12-May-12 A 23-May-12 A 06-May-12 17-May-12 25-Sep-12 07-Oct-12 119 100% 100%
A133430 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 07-May-12 17-May-12 23-Oct-12 05-Nov-12 142 100% 100%
A133460 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 24-May-12 04-Jun-12 24-May-12 04-Jun-12 0 100% 100%
A133470 Submission of Lighting Layout & Details 10 30-May-12 A 10-Jun-12 A 07-May-12 17-May-12 26-Sep-12 07-Oct-12 119 100% 100%
A133480 Submission of Power Layout & Details 10 30-May-12 A 10-Jun-12 A 07-May-12 17-May-12 26-Sep-12 07-Oct-12 119 100% 100%
A133500 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 07-May-12 17-May-12 08-Dec-12 18-Dec-12 177 100% 100%ApprovalApproval 46 26-Apr-12 A 18-Jul-12 129 20-May-12 25-Jun-12 05-Jun-12 23-Jan-13 100% 64.29%A133560 Approval of Drainage Layout & Details 14 11-Jun-12 A 21-Jun-12 A 20-May-12 06-Jun-12 08-Oct-12 28-Oct-12 98 100% 100%
A133570 Approval of Water Supply Layout & Details 14 24-May-12 A 03-Jun-12 A 20-May-12 06-Jun-12 06-Jan-13 23-Jan-13 158 100% 100%
A133580 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 20-May-12 06-Jun-12 06-Nov-12 26-Nov-12 118 100% 100%
A133610 Approval of MEP Builder Work Layout 14 26-May-12 A 30-May-12 A 05-Jun-12 25-Jun-12 05-Jun-12 25-Jun-12 0 100% 100%
A133650 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 125 20-May-12 06-Jun-12 19-Dec-12 08-Jan-13 147 100% 50%
A133620 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 69 20-May-12 06-Jun-12 08-Oct-12 28-Oct-12 98 100% 0%
A133630 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 69 20-May-12 06-Jun-12 08-Oct-12 28-Oct-12 98 100% 0%4th Floor4th Floor 66 15-Apr-12 A 18-Jul-12 149 24-May-12 05-Jul-12 09-Jun-12 16-Jan-13 97.13% 79.89%SubmissionSubmission 62 15-Apr-12 A 10-Jun-12 A 24-May-12 16-Jun-12 09-Jun-12 26-Dec-12 100% 100%A133710 Submission of Drainage Layout & Details 13 05-Jun-12 A 10-Jun-12 A 24-May-12 07-Jun-12 09-Jun-12 24-Jun-12 13 100% 100%
A133720 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 15-Oct-12 31-Oct-12 120 100% 100%
A133730 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 01-Nov-12 12-Nov-12 130 100% 100%
A133760 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 05-Jun-12 16-Jun-12 21-Jun-12 02-Jul-12 13 100% 100%
A133770 Submission of Lighting Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 18-Oct-12 31-Oct-12 120 100% 100%
A133780 Submission of Power Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 18-Oct-12 31-Oct-12 120 100% 100%
A133800 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 16-Dec-12 26-Dec-12 166 100% 100%ApprovalApproval 46 26-Apr-12 A 18-Jul-12 124 10-Jun-12 05-Jul-12 03-Jul-12 16-Jan-13 94.9% 64.29%A133860 Approval of Drainage Layout & Details 14 11-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 100%
A133870 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 25-Nov-12 13-Dec-12 115 100% 100%
A133880 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 13-Nov-12 04-Dec-12 108 100% 100%
A133910 Approval of MEP Builder Work Layout 14 27-May-12 A 30-May-12 A 18-Jun-12 05-Jul-12 03-Jul-12 22-Jul-12 11 64.29% 100%
A133950 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 131 10-Jun-12 28-Jun-12 27-Dec-12 16-Jan-13 138 100% 50%
A133920 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 86 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 0%
A133930 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 86 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 0%5th Floor5th Floor 66 15-Apr-12 A 18-Jul-12 173 24-May-12 05-Jul-12 09-Jun-12 14-Feb-13 97.13% 79.89%SubmissionSubmission 62 15-Apr-12 A 10-Jun-12 A 24-May-12 16-Jun-12 09-Jun-12 27-Jan-13 100% 100%A134010 Submission of Drainage Layout & Details 13 05-Jun-12 A 10-Jun-12 A 24-May-12 07-Jun-12 09-Jun-12 24-Jun-12 13 100% 100%
A134020 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 01-Nov-12 17-Nov-12 133 100% 100%
A134030 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 22-Nov-12 04-Dec-12 147 100% 100%
A134060 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 05-Jun-12 16-Jun-12 21-Jun-12 02-Jul-12 13 100% 100%
A134070 Submission of Lighting Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 05-Nov-12 17-Nov-12 133 100% 100%
A134080 Submission of Power Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 05-Nov-12 17-Nov-12 133 100% 100%
A134100 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 15-Jan-13 27-Jan-13 191 100% 100%ApprovalApproval 46 26-Apr-12 A 18-Jul-12 144 10-Jun-12 05-Jul-12 03-Jul-12 14-Feb-13 94.9% 64.29%A134160 Approval of Drainage Layout & Details 14 11-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 100%
A134170 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 100%
A134180 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 05-Dec-12 24-Dec-12 122 100% 100%
A134210 Approval of MEP Builder Work Layout 14 26-May-12 A 30-May-12 A 18-Jun-12 05-Jul-12 03-Jul-12 22-Jul-12 11 64.29% 100%
A134250 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 151 10-Jun-12 28-Jun-12 28-Jan-13 14-Feb-13 158 100% 50%
A134220 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 96 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 0%
A134230 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 96 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 0%6th Floor6th Floor 66 15-Apr-12 A 18-Jul-12 139 24-May-12 24-Jul-12 23-Jun-12 03-Jan-13 89.66% 79.89%SubmissionSubmission 62 15-Apr-12 A 10-Jun-12 A 24-May-12 04-Jul-12 23-Jun-12 15-Dec-12 94.74% 100%A134310 Submission of Drainage Layout & Details 13 05-Jun-12 A 10-Jun-12 A 24-May-12 07-Jun-12 23-Jun-12 07-Jul-12 24 100% 100%
A134320 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 12-Nov-12 27-Nov-12 142 100% 100%
A134330 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 04-Dec-12 15-Dec-12 156 100% 100%
A134360 Submission of MEP Builder Work Layout 10 14-May-12 A 24-May-12 A 24-Jun-12 04-Jul-12 22-Jul-12 01-Aug-12 24 60% 100%
A134370 Submission of Lighting Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 17-Nov-12 27-Nov-12 142 100% 100%
A134380 Submission of Power Layout & Details 10 30-May-12 A 10-Jun-12 A 28-May-12 07-Jun-12 17-Nov-12 27-Nov-12 142 100% 100%
A134400 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 28-May-12 07-Jun-12 17-Nov-12 27-Nov-12 142 100% 100%ApprovalApproval 46 26-Apr-12 A 18-Jul-12 115 10-Jun-12 24-Jul-12 02-Aug-12 03-Jan-13 85.71% 64.29%A134460 Approval of Drainage Layout & Details 14 11-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 100%
A134470 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 100%
A134480 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 16-Dec-12 03-Jan-13 129 100% 100%
A134510 Approval of MEP Builder Work Layout 14 26-May-12 A 30-May-12 A 05-Jul-12 24-Jul-12 02-Aug-12 23-Aug-12 20 0% 100%
A134550 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 111 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 50%
A134520 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 104 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 0%
A134530 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 104 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 0%7th Floor7th Floor 75 15-Apr-12 A 18-Jul-12 147 11-Jun-12 17-Jul-12 11-Jul-12 14-Jan-13 51.43% 80%SubmissionSubmission 63 15-Apr-12 A 21-Jun-12 A 11-Jun-12 27-Jun-12 11-Jul-12 24-Dec-12 100% 100%A134610 Submission of Drainage Layout & Details 14 11-Jun-12 A 21-Jun-12 A 11-Jun-12 27-Jun-12 11-Jul-12 26-Jul-12 25 100% 100%
A134620 Submission of Water Supply Layout & Details 14 16-May-12 A 27-May-12 A 11-Jun-12 27-Jun-12 03-Dec-12 18-Dec-12 143 100% 100%
A134630 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 14-Jun-12 27-Jun-12 12-Dec-12 24-Dec-12 148 100% 100%
A134700 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 14-Jun-12 26-Jun-12 13-Dec-12 24-Dec-12 149 100% 100%ApprovalApproval 54 26-Apr-12 A 18-Jul-12 122 27-Jun-12 17-Jul-12 19-Dec-12 14-Jan-13 8.93% 62.5%A134770 Approval of Water Supply Layout & Details 14 28-May-12 A 03-Jun-12 A 28-Jun-12 17-Jul-12 19-Dec-12 08-Jan-13 119 7.14% 100%
A134780 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 28-Jun-12 17-Jul-12 25-Dec-12 14-Jan-13 123 7.14% 100%
A134850 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 129 27-Jun-12 16-Jul-12 25-Dec-12 14-Jan-13 124 14.29% 50%
A134760 Approval of Drainage Layout & Details 14 24-Jun-12 A 18-Jul-12 118 28-Jun-12 17-Jul-12 19-Dec-12 08-Jan-13 119 7.14% 0%Roof FloorRoof Floor 46 15-Apr-12 A 16-Jul-12 170 07-Jul-12 07-Aug-12 31-Dec-12 07-Feb-13 0% 85.71%SubmissionSubmission 30 15-Apr-12 A 19-May-12 A 07-Jul-12 18-Jul-12 31-Dec-12 19-Jan-13 0% 100%A134930 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 07-Jan-13 19-Jan-13 151 0% 100%
A135000 Submission of CBS Layout & Details 10 15-Apr-12 A 25-Apr-12 A 07-Jul-12 17-Jul-12 31-Dec-12 12-Jan-13 146 0% 100%ApprovalApproval 30 26-Apr-12 A 16-Jul-12 141 18-Jul-12 07-Aug-12 13-Jan-13 07-Feb-13 0% 75%A135080 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 20-Jan-13 07-Feb-13 125 0% 100%
A135150 Approval of CBS Layout & Details 14 26-Apr-12 A 16-Jul-12 136 18-Jul-12 06-Aug-12 13-Jan-13 31-Jan-13 121 0% 50%
Speciality WSpeciality Works 27 17-Mar-12 A 16-Apr-12 A 22-Sep-12 30-Oct-12 05-Feb-13 10-Mar-13 0% 100%
Swimming PoSwimming Pool 27 17-Mar-12 A 16-Apr-12 A 22-Sep-12 30-Oct-12 05-Feb-13 10-Mar-13 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s Approval of Data & Telephone Layout & Details
s
s
Approval of CBS Layout & Details
s Approval of Lighting Layout & Details
Approval of Power Layout & Details
ls Approval of CCTV,Access Control,Intercom Layout & Details
s
Approval of CBS Layout & Details
s Approval of Lighting Layout & Details
Approval of Power Layout & Details
s
Approval of CBS Layout & Details
s Approval of Lighting Layout & Details
Approval of Power Layout & Details
s
Approval of CBS Layout & Details
s Approval of Lighting Layout & Details
Approval of Power Layout & Details
s
Approval of CBS Layout & Details
s Approval of Lighting Layout & Details
Approval of Power Layout & Details
s
Approval of CBS Layout & Details
ils Approval of Drainage Layout & Details
Approval of CBS Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 9 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
SubmissionSubmission 27 17-Mar-12 A 16-Apr-12 A 22-Sep-12 30-Oct-12 05-Feb-13 10-Mar-13 0% 100%A53720 Submission of Swimming Pool Layout & Details for Block A 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 19-Feb-13 04-Mar-13 123 0% 100%
A53730 Submission of Swimming Pool 's Water Prrofing for Block A 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 25-Feb-13 10-Mar-13 128 0% 100%
A118850 Submission of Swimming Pool Layout & Details for Block B 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 05-Feb-13 18-Feb-13 111 0% 100%
A118860 Submission of Swimming Pool 's Water Prrofing for Block B 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 11-Feb-13 24-Feb-13 116 0% 100%
A118870 Submission of Swimming Pool Layout & Details for Block C 12 03-Apr-12 A 16-Apr-12 A 15-Oct-12 30-Oct-12 10-Feb-13 23-Feb-13 95 0% 100%
A118880 Submission of Swimming Pool 's Water Prrofing for Block C 12 03-Apr-12 A 16-Apr-12 A 15-Oct-12 30-Oct-12 13-Feb-13 26-Feb-13 98 0% 100%
Method 0f SMethod 0f Statements 130 15-Feb-12 A 28-Jun-12 A 15-Feb-12 08-Aug-12 21-Feb-12 17-Nov-12 88.03% 100%
CivilCivil 130 15-Feb-12 A 25-Jun-12 A 15-Feb-12 24-Jun-12 21-Feb-12 15-Oct-12 100% 100%
A46480 Sub & App- MOS for Raft Slab Construction 4 15-Feb-12 A 23-Feb-12 A 15-Feb-12 19-Feb-12 21-Feb-12 25-Feb-12 5 100% 100%
A46500 Sub & App- MOS for Backfilling 30 15-Feb-12 A 15-Feb-12 A 20-May-12 24-Jun-12 11-Sep-12 15-Oct-12 95 100% 100%
A46510 Sub & App- MOS for Slabs Construction 17 20-Feb-12 A 10-Mar-12 A 20-Feb-12 10-Mar-12 26-Feb-12 15-Mar-12 5 100% 100%
A46520 Sub & App- MOS for Columns Construction 17 18-Feb-12 A 07-Mar-12 A 18-Feb-12 07-Mar-12 23-Feb-12 13-Mar-12 5 100% 100%
A46530 Sub & App- MOS for Retaining Walls Construction 18 18-Feb-12 A 08-Mar-12 A 18-Feb-12 08-Mar-12 22-Feb-12 13-Mar-12 4 100% 100%
A46540 Sub & App- MOS for Ramp Construction 17 21-Feb-12 A 11-Mar-12 A 21-Feb-12 11-Mar-12 14-Mar-12 02-Apr-12 19 100% 100%
A46550 Sub & App- MOS for Staircase Construction 30 11-Jun-12 A 25-Jun-12 A 19-May-12 23-Jun-12 10-Sep-12 14-Oct-12 95 100% 100%
A46560 Sub & App- MOS for Core Walls Constrcution 14 19-Feb-12 A 05-Mar-12 A 19-Feb-12 05-Mar-12 27-Feb-12 13-Mar-12 7 100% 100%
ArchitecturalArchitectural 30 11-Jun-12 A 28-Jun-12 A 30-May-12 08-Aug-12 17-Sep-12 17-Nov-12 43.33% 100%
A46570 Sub & App- MOS for Blocks Works 30 11-Jun-12 A 28-Jun-12 A 30-May-12 04-Jul-12 17-Sep-12 21-Oct-12 91 86.67% 100%
A46580 Sub & App- MOS for Plaster Works 30 11-Jun-12 A 28-Jun-12 A 05-Jul-12 08-Aug-12 10-Oct-12 17-Nov-12 81 0% 100%
ProcuremeProcurement 284 09-Feb-12 A 23-Jan-13 10 15-Feb-12 11-Nov-12 15-Feb-12 05-Feb-13 79.99% 58.75%
Submittion &Submittion & Approval of Prequalification 147 15-Feb-12 A 21-Jul-12 109 15-Feb-12 28-Aug-12 15-Feb-12 26-Nov-12 80.83% 82.71%
Domestic SuDomestic Sub Contractors 147 15-Feb-12 A 21-Jul-12 109 15-Feb-12 28-Aug-12 15-Feb-12 26-Nov-12 79.09% 81.14%
A8470 Sub & App- Elevators Subcontractor 35 23-Feb-12 A 08-Mar-12 A 02-Apr-12 12-May-12 26-Apr-12 05-Jun-12 21 100% 100%
A8490 Sub & App- Swimming Pool Works Subcontractor 35 10-Mar-12 A 17-Mar-12 A 30-May-12 10-Jul-12 30-May-12 10-Jul-12 0 74.29% 100%
A8500 Sub & App- Water Proofing Works Subcontractor 2 15-Feb-12 A 16-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 1 100% 100%
A8510 Sub & App- Facade Cleanining Subcontractor 35 13-Jun-12 A 26-Jun-12 A 05-Jul-12 14-Aug-12 14-Oct-12 26-Nov-12 84 0% 100%
A8520 Sub & App- Aluminum&Glazing Works Subcontractor 35 12-Apr-12 A 25-Apr-12 A 14-Apr-12 23-May-12 24-May-12 04-Jul-12 35 100% 100%
A8590 Sub & App- Landscaping Subcontractor 35 03-Mar-12 A 28-Mar-12 A 30-May-12 10-Jul-12 10-Jul-12 21-Aug-12 34 74.29% 100%
A8600 Sub & App- LPG System Subcontractor 21 17-Apr-12 A 19-May-12 A 15-Feb-12 10-Mar-12 16-May-12 09-Jun-12 78 100% 100%
A8999 Sub & App- Irrigation Works Subcontractor 35 03-Mar-12 A 28-Mar-12 A 17-Jul-12 28-Aug-12 01-Oct-12 12-Nov-12 63 0% 100%
A4579 Sub & App- Steel Structure Subcontractor 35 12-Apr-12 A 25-Apr-12 A 25-Apr-12 04-Jun-12 23-Jun-12 01-Aug-12 49 100% 100%
A136170 Sub & App- MEP Subcontractor 1 15-Feb-12 A 15-Feb-12 A 15-Feb-12 15-Feb-12 15-Feb-12 15-Feb-12 0 100% 100%
A8480 Sub & App- Garbage Chute System Subcontractor 35 10-Apr-12 A 02-Jul-12 -33 21-Mar-12 30-Apr-12 14-Apr-12 23-May-12 20 100% 50%
A8444 Sub & App- Linen Chute System Subcontractor 35 07-Jun-12 A 02-Jul-12 -15 25-Apr-12 04-Jun-12 05-May-12 13-Jun-12 8 100% 50%
A8540 Sub & App- Susbended Ceilings Subcontractor 35 12-Apr-12 A 04-Jul-12 -35 15-Feb-12 26-Mar-12 14-Apr-12 23-May-12 50 100% 50%
A8530 Sub & App- Wood & Joinery Subcontractor 35 26-Jun-12 A 21-Jul-12 23 30-May-12 10-Jul-12 07-Jul-12 15-Aug-12 31 74.29% 50%
A8560 Sub & App- GRP Lining Subcontractor 35 18-Apr-12 A 21-Jul-12 52 25-Apr-12 04-Jun-12 28-Jul-12 08-Sep-12 79 100% 50%
Nominated SNominated Sub Contractors 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 100% 100%
Kitchen EquiKitchen Equipments 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 100% 100%
A8610 Sub & App- Kitchen Equipments Subcontractor 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 0 100% 100%
Lundary EquLundary Equipments 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 100% 100%
A114230 Sub & App- Laundary Equipments Subcontractor 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 0 100% 100%
Submittion &Submittion & Approval of Material Submittal 140 09-Feb-12 A 19-Nov-12 48 15-Feb-12 29-Sep-12 19-Feb-12 15-Jan-13 82.84% 73.82%
CivilCivil 140 12-Feb-12 A 08-Jul-12 62 15-Feb-12 30-Jun-12 19-Feb-12 02-Oct-12 100% 80.56%
A7610 Sub & App- Concerete - 1st Pour 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 21-Feb-12 22-Feb-12 5 100% 100%
A7620 Sub & App- Steel Reinforcement - 1st Patch 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 21-Feb-12 22-Feb-12 5 100% 100%
A7630 Sub & App- Water Proofing for Substructure 2 12-Feb-12 A 20-Feb-12 A 18-Feb-12 19-Feb-12 19-Feb-12 20-Feb-12 1 100% 100%
A113940 Sub & App- Water Proofing for Roof 30 24-Jun-12 A 08-Jul-12 5 15-May-12 19-Jun-12 09-Jun-12 14-Jul-12 21 100% 50%
A7640 Sub & App- GRP Lining 21 18-Apr-12 A 01-May-12 A 05-Jun-12 30-Jun-12 09-Sep-12 02-Oct-12 79 100% 100%
ArchitecturalArchitectural 132 15-Feb-12 A 17-Jul-12 121 04-Mar-12 29-Jul-12 14-Jun-12 11-Dec-12 85.71% 64.29%
Wet WorksWet Works 100 15-Feb-12 A 12-Jul-12 38 04-Mar-12 25-Apr-12 14-Jun-12 27-Aug-12 100% 83.33%
A7300 Sub & App- Plaster Materials 21 16-May-12 A 26-May-12 A 02-Apr-12 25-Apr-12 10-Jul-12 02-Aug-12 84 100% 100%
A7310 Sub & App- Blocks 21 15-Feb-12 A 15-Feb-12 A 04-Mar-12 27-Mar-12 14-Jun-12 09-Jul-12 88 100% 100%
A7240 Sub & App- Paint Materials 21 16-May-12 A 12-Jul-12 38 15-Mar-12 08-Apr-12 01-Aug-12 27-Aug-12 118 100% 50%
Walls & FlooWalls & Floors 58 12-May-12 A 17-Jul-12 121 24-May-12 29-Jul-12 26-Sep-12 11-Dec-12 50% 50%
A7480 Sub & App- Terrazo Tiles 21 25-Jun-12 A 12-Jul-12 84 24-May-12 18-Jun-12 26-Sep-12 20-Oct-12 104 100% 50%
A7670 Sub & App- Precast Conc. Interlocking Paving 21 12-May-12 A 17-Jul-12 121 05-Jul-12 29-Jul-12 17-Nov-12 11-Dec-12 110 0% 50%
Doors & WinDoors & Windows 24 20-Jun-12 A 12-Jul-12 124 10-Mar-12 18-Jun-12 06-Sep-12 10-Dec-12 100% 50%
A7450 Sub & App- Fire Rated Doors 21 24-Jun-12 A 12-Jul-12 124 10-Mar-12 02-Apr-12 14-Nov-12 10-Dec-12 209 100% 50%
A7470 Sub & App- Curtain Wall&Glazing 21 20-Jun-12 A 12-Jul-12 67 24-May-12 18-Jun-12 06-Sep-12 30-Sep-12 87 100% 50%
MechanicalMechanical 111 09-Feb-12 A 15-Jul-12 152 21-Feb-12 29-Sep-12 01-Mar-12 15-Jan-13 96.03% 86.98%
HVACHVAC 99 19-Feb-12 A 15-Jul-12 103 21-Feb-12 01-Jul-12 01-Mar-12 17-Nov-12 99.28% 87.91%
A8060 Sub & App- HAVC Ducts 21 27-Feb-12 A 05-Mar-12 A 28-Mar-12 21-Apr-12 31-May-12 25-Jun-12 55 100% 100%
A8070 Sub & App- FCUs 21 21-Apr-12 A 30-Jun-12 A 17-Mar-12 09-Apr-12 03-Jul-12 26-Jul-12 92 100% 100%
A8100 Sub & App- Chilled Water Pipes-Fittings-Valves 21 07-Mar-12 A 19-May-12 A 17-Mar-12 09-Apr-12 31-May-12 25-Jun-12 65 100% 100%
A8130 Sub & App- Ducts Insulation 21 14-Apr-12 A 28-Apr-12 A 06-Jun-12 01-Jul-12 30-Aug-12 23-Sep-12 70 95.24% 100%
A8140 Sub & App- Chilled Pipes Insulation 21 04-Apr-12 A 14-Apr-12 A 14-May-12 06-Jun-12 11-Aug-12 05-Sep-12 75 100% 100%
A8150 Sub & App- Condensate Pipes Insulation 21 04-Apr-12 A 14-Apr-12 A 06-Jun-12 01-Jul-12 30-Aug-12 23-Sep-12 70 95.24% 100%
A8290 Sub & App- Chiller 21 24-Apr-12 A 14-Jun-12 A 17-Mar-12 09-Apr-12 26-Mar-12 18-Apr-12 8 100% 100%
A8460 Preparing for Material Submittals for MEP 21 21-Feb-12 A 15-Mar-12 A 21-Feb-12 15-Mar-12 01-Mar-12 25-Mar-12 8 100% 100%
A8291 Sub & App- Hangers & Supports 21 19-Apr-12 A 24-May-12 A 17-Mar-12 09-Apr-12 08-Sep-12 01-Oct-12 147 100% 100%
A136200 Sub & App- Fire and Volume Damper 21 04-Apr-12 A 14-Apr-12 A 15-Apr-12 08-May-12 21-Oct-12 17-Nov-12 159 100% 100%
A8080 Sub & App- AHU 21 19-Feb-12 A 12-Jul-12 55 17-Mar-12 09-Apr-12 23-Aug-12 16-Sep-12 134 100% 50%
A8090 Sub & App- FAHU 21 19-Feb-12 A 12-Jul-12 54 09-Apr-12 02-May-12 22-Aug-12 15-Sep-12 113 100% 50%
A8340 Sub & App- Ventilation & Exhuast Fans 25 17-May-12 A 15-Jul-12 100 17-Mar-12 14-Apr-12 13-Oct-12 12-Nov-12 177 100% 50%
PlumbingPlumbing 97 09-Feb-12 A 12-Jul-12 154 17-Mar-12 26-May-12 19-Jul-12 15-Jan-13 100% 66.67%
A7890 Sub & App- uPVC Pipes-Fittings-Valves(Drainge) 21 09-Feb-12 A 29-Feb-12 A 02-May-12 26-May-12 19-Jul-12 12-Aug-12 66 100% 100%
A7900 Sub & App- Floor Drains 21 02-May-12 A 12-Jul-12 154 17-Mar-12 09-Apr-12 22-Dec-12 15-Jan-13 233 100% 50%
A7930 Sub & App- PPR Pipes -Fittings-Valves (Water) 21 26-May-12 A 12-Jul-12 29 27-Mar-12 19-Apr-12 22-Jul-12 14-Aug-12 99 100% 50%
Fire FighitngFire Fighitng 97 29-Mar-12 A 06-Jun-12 A 17-Mar-12 19-Jun-12 27-May-12 16-Dec-12 100% 100%
A7970 Sub & App- Fire Pipes-Fittings-Valves 21 29-Mar-12 A 08-Apr-12 A 17-Mar-12 09-Apr-12 27-May-12 20-Jun-12 61 100% 100%
A7980 Sub & App- Fire Pump 21 28-Apr-12 A 08-May-12 A 28-Mar-12 21-Apr-12 04-Aug-12 29-Aug-12 109 100% 100%
A7990 Sub & App- Sprinklers 21 31-Mar-12 A 04-Apr-12 A 17-Mar-12 09-Apr-12 20-Sep-12 14-Oct-12 158 100% 100%
A8000 Sub & App- Fire Extinguishers & Banket 21 31-Mar-12 A 04-Apr-12 A 02-May-12 26-May-12 04-Oct-12 30-Oct-12 130 100% 100%
A8020 Sub & App- Fire Hose Cabinets 21 31-Mar-12 A 04-Apr-12 A 02-May-12 26-May-12 04-Oct-12 30-Oct-12 130 100% 100%
A8040 Sub & App- Foam Spary System for Generators 21 31-Mar-12 A 15-Apr-12 A 26-May-12 19-Jun-12 21-Nov-12 16-Dec-12 148 100% 100%
A135540 Sub & App- FM 200 System 30 20-May-12 A 06-Jun-12 A 17-Mar-12 19-Apr-12 12-Sep-12 16-Oct-12 151 100% 100%
LPG SystemLPG System 21 24-May-12 A 06-Jun-12 A 14-May-12 29-Sep-12 21-Nov-12 15-Jan-13 50% 100%
A8430 Sub & App- LPG Pipes-Fittings-Valves 21 24-May-12 A 06-Jun-12 A 14-May-12 06-Jun-12 21-Nov-12 16-Dec-12 158 100% 100%
A8440 Sub & App- LPG Tanks( 2000 Gallons) 21 24-May-12 A 06-Jun-12 A 05-Sep-12 29-Sep-12 22-Dec-12 15-Jan-13 88 0% 100%
Coveying SysCoveying System 21 22-Mar-12 A 12-Jul-12 26 13-May-12 05-Jun-12 06-Jun-12 11-Aug-12 100% 50%
A7550 Sub & App- Passenger Lifts 21 22-Mar-12 A 12-Jul-12 26 13-May-12 05-Jun-12 18-Jul-12 11-Aug-12 56 100% 50%
A114290 Sub & App- Brakets,Guide Rails and Others 21 22-Mar-12 A 12-Jul-12 -10 13-May-12 05-Jun-12 06-Jun-12 01-Jul-12 21 100% 50%
ElectricalElectrical 129 15-Feb-12 A 19-Nov-12 22 15-Feb-12 22-Sep-12 26-Feb-12 15-Dec-12 78.7% 64.5%
Cable Trays -Cable Trays - Cables 35 14-May-12 A 06-Jun-12 A 22-Mar-12 01-May-12 11-Jul-12 22-Aug-12 100% 100%
A7760 Sub & App- Cable Trays 30 14-May-12 A 06-Jun-12 A 22-Mar-12 25-Apr-12 17-Jul-12 22-Aug-12 99 100% 100%
A7770 Sub & App- Trunking 35 14-May-12 A 06-Jun-12 A 22-Mar-12 01-May-12 11-Jul-12 22-Aug-12 94 100% 100%
Low Current Low Current Systems 113 03-Mar-12 A 21-Jul-12 83 17-Mar-12 25-Apr-12 02-Jun-12 29-Oct-12 100% 58.33%
A7820 Sub & App- CCTV System 35 28-Mar-12 A 12-Jun-12 A 17-Mar-12 25-Apr-12 05-Jun-12 16-Jul-12 69 100% 100%
A7830 Sub & App- Access Control System 35 02-Jun-12 A 21-Jul-12 -7 17-Mar-12 25-Apr-12 02-Jun-12 12-Jul-12 66 100% 50%
A7840 Sub & App- Central Battery System 35 03-Mar-12 A 21-Jul-12 70 17-Mar-12 25-Apr-12 02-Sep-12 11-Oct-12 142 100% 50%
A7870 Sub & App- BMS 35 27-May-12 A 21-Jul-12 1 17-Mar-12 25-Apr-12 10-Jun-12 21-Jul-12 73 100% 50%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
n
s
s
r
Sub & App- Garbage Chute System Subcontractor
Sub & App- Linen Chute System Subcontractor
Sub & App- Susbended Ceilings Subcontractor
or Sub & App- Wood & Joinery Subcontractor
Sub & App- GRP Lining Subcontractor
r
of Sub & App- Water Proofing for Roof
Sub & App- Paint Materials
es Sub & App- Terrazo Tiles
Sub & App- Precast Conc. Interlocking Paving
rs Sub & App- Fire Rated Doors
ng Sub & App- Curtain Wall&Glazing
Sub & App- AHU
Sub & App- FAHU
Sub & App- Ventilation & Exhuast Fans
Sub & App- Floor Drains
Sub & App- PPR Pipes -Fittings-Valves (Water)
Sub & App- Passenger Lifts
Sub & App- Brakets,Guide Rails and Others
Sub & App- Access Control System
Sub & App- Central Battery System
Sub & App- BMS
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 10 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A8240 Sub & App- GSM System 35 23-May-12 A 21-Jul-12 83 17-Mar-12 25-Apr-12 17-Sep-12 29-Oct-12 155 100% 50%
A8400 Sub & App- MATV/ Interactive TV System 35 26-May-12 A 21-Jul-12 53 17-Mar-12 25-Apr-12 11-Aug-12 22-Sep-12 125 100% 50%
Electrical EquElectrical Equipments 73 19-Apr-12 A 19-Nov-12 22 17-Mar-12 22-Sep-12 22-Jul-12 15-Dec-12 46.43% 55.36%
A8260 Sub & App- Electrical Heaters 21 21-May-12 A 02-Jun-12 A 02-May-12 26-May-12 20-Nov-12 15-Dec-12 167 100% 100%
A7800 Sub & App- Generators 35 19-Apr-12 A 21-Jul-12 52 21-Apr-12 30-May-12 09-Aug-12 20-Sep-12 94 100% 50%
A8670 Sub & App- Telephone System 35 26-May-12 A 21-Jul-12 36 17-Mar-12 25-Apr-12 22-Jul-12 02-Sep-12 108 100% 50%
A7730 Sub & App- DBs 22 04-Jun-12 A 10-Nov-12 -53 11-Aug-12 06-Sep-12 11-Aug-12 06-Sep-12 0 0% 50%
A7710 Sub & App- MDBs 35 04-Jun-12 A 19-Nov-12 -35 11-Aug-12 22-Sep-12 27-Aug-12 06-Oct-12 12 0% 50%
A7720 Sub & App- SMDBs 35 04-Jun-12 A 19-Nov-12 -35 11-Aug-12 22-Sep-12 27-Aug-12 06-Oct-12 12 0% 50%
OthersOthers 20 15-Feb-12 A 08-Mar-12 A 15-Feb-12 08-Apr-12 26-Feb-12 25-Sep-12 100% 100%
A7920 Sub & App- Earthing & Lighting 2 15-Feb-12 A 19-Feb-12 A 15-Feb-12 16-Feb-12 26-Feb-12 27-Feb-12 9 100% 100%
A7881 Sub & App- Conduits and PVC Ducts 20 15-Feb-12 A 08-Mar-12 A 17-Mar-12 08-Apr-12 03-Sep-12 25-Sep-12 143 100% 100%
Speciality WSpeciality Works 24 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 09-Aug-12 12-Dec-12 0% 50%
Swimming PoSwimming Pool 24 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 09-Aug-12 12-Dec-12 0% 50%
A7560 Sub & App- Pool Finishes 21 14-Mar-12 A 12-Jul-12 119 11-Jul-12 04-Aug-12 08-Nov-12 04-Dec-12 99 0% 50%
A7570 Sub & App- Pool Equipments 21 26-Apr-12 A 12-Jul-12 45 11-Jul-12 04-Aug-12 09-Aug-12 04-Sep-12 25 0% 50%
A8180 Sub & App- Water Proofing for Swimming Pool 21 26-Apr-12 A 12-Jul-12 124 11-Jul-12 04-Aug-12 14-Nov-12 10-Dec-12 104 0% 50%
A104220 Sub & App- Pool Electrical Items 21 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 18-Nov-12 12-Dec-12 106 0% 50%
ProcuremenProcurement and Delivery 284 15-Feb-12 A 23-Jan-13 10 18-Feb-12 11-Nov-12 21-Feb-12 05-Feb-13 75.54% 25.13%
CivilCivil 6 15-Feb-12 A 21-Feb-12 A 18-Feb-12 21-Feb-12 21-Feb-12 25-Feb-12 100% 100%
A6370 Order&Delivery- Conceret - 1st Pour 2 16-Feb-12 A 16-Feb-12 A 18-Feb-12 19-Feb-12 23-Feb-12 25-Feb-12 5 100% 100%
A6380 Order&Delivery- Steel Reinforcement - 1st Patch 2 15-Feb-12 A 16-Feb-12 A 18-Feb-12 19-Feb-12 23-Feb-12 25-Feb-12 5 100% 100%
A6390 Order&Delivery- Water Proofing for Substructure 2 20-Feb-12 A 21-Feb-12 A 20-Feb-12 21-Feb-12 21-Feb-12 22-Feb-12 1 100% 100%
ArchitecturalArchitectural 30 11-Jun-12 A 28-Jul-12 35 28-Mar-12 30-May-12 10-Jul-12 09-Sep-12 100% 35%
Wet WorksWet Works 30 11-Jun-12 A 28-Jul-12 35 28-Mar-12 30-May-12 10-Jul-12 09-Sep-12 100% 35%
A5570 Order&Delivery- Plaster Materials 30 11-Jun-12 A 17-Jul-12 44 26-Apr-12 30-May-12 04-Aug-12 09-Sep-12 84 100% 50%
A5580 Order&Delivery- Blocks 30 11-Jun-12 A 28-Jul-12 21 28-Mar-12 01-May-12 10-Jul-12 13-Aug-12 88 100% 20%
MechanicalMechanical 267 06-Mar-12 A 23-Jan-13 10 10-Apr-12 11-Nov-12 19-Apr-12 05-Feb-13 65.65% 21.52%
HVACHVAC 232 16-Apr-12 A 23-Jan-13 -52 10-Apr-12 11-Nov-12 19-Apr-12 21-Nov-12 59.11% 32.67%
A6840 Order&Delivery- Chilled Water Pipes-Fittings-Valves 90 16-Apr-12 A 04-Aug-12 56 10-Apr-12 24-Jul-12 26-Jun-12 10-Oct-12 65 76.67% 66.67%
A6860 Order&Delivery- Condensate Pipes-Fittings-Valves 90 16-Apr-12 A 30-Aug-12 35 10-Apr-12 24-Jul-12 26-Jun-12 10-Oct-12 65 76.67% 66.67%
A6800 Order&Delivery- HAVC Ducts 90 02-Jun-12 A 22-Sep-12 16 22-Apr-12 05-Aug-12 26-Jun-12 10-Oct-12 55 65.56% 0%
A7050 Order&Delivery- Chiller 180 16-Jun-12 A 23-Jan-13 -52 10-Apr-12 11-Nov-12 19-Apr-12 21-Nov-12 8 38.33% 15%
PlumbingPlumbing 107 06-Mar-12 A 04-Aug-12 138 27-May-12 01-Jul-12 13-Aug-12 20-Jan-13 96.67% 2.5%
A6630 Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge) 30 06-Mar-12 A 02-Aug-12 39 27-May-12 01-Jul-12 13-Aug-12 18-Sep-12 66 96.67% 5%
A7020 Order&Delivery- Electrical Heaters 30 03-Jun-12 A 04-Aug-12 138 27-May-12 01-Jul-12 16-Dec-12 20-Jan-13 167 96.67% 0%
Fire FighitngFire Fighitng 95 02-Jun-12 A 15-Oct-12 91 10-Apr-12 04-Aug-12 21-Jun-12 05-Feb-13 71.67% 0%
A6710 Order&Delivery- Fire Pipes-Fittings-Valves 90 02-Jun-12 A 22-Sep-12 12 10-Apr-12 24-Jul-12 21-Jun-12 06-Oct-12 61 76.67% 0%
A9410 Order&Delivery- FM 200 System 90 07-Jun-12 A 15-Oct-12 91 21-Apr-12 04-Aug-12 17-Oct-12 05-Feb-13 151 66.67% 0%
ElectricalElectrical 140 19-Feb-12 A 23-Aug-12 79 18-Feb-12 24-Jun-12 28-Feb-12 13-Nov-12 100% 27.5%
Cable Trays -Cable Trays - Cables 46 07-Jun-12 A 23-Aug-12 44 26-Apr-12 24-Jun-12 23-Aug-12 14-Oct-12 100% 0%
A6500 Order&Delivery- Cable Trays 45 07-Jun-12 A 23-Aug-12 44 26-Apr-12 18-Jun-12 23-Aug-12 14-Oct-12 99 100% 0%
A6510 Order&Delivery- Trunking 45 07-Jun-12 A 23-Aug-12 44 02-May-12 24-Jun-12 23-Aug-12 14-Oct-12 94 100% 0%
OthersOthers 57 19-Feb-12 A 23-Jul-12 104 18-Feb-12 24-May-12 28-Feb-12 13-Nov-12 100% 50%
A136180 Order&Delivery- Earthing & Lightining 7 19-Feb-12 A 04-Jul-12 29 18-Feb-12 25-Feb-12 28-Feb-12 06-Mar-12 9 100% 50%
A6660 Order&Delivery- Conduits & PVC Ducts 40 10-Mar-12 A 23-Jul-12 104 09-Apr-12 24-May-12 26-Sep-12 13-Nov-12 143 100% 50%
ConstructiConstruction 128 15-Feb-12 A 07-Nov-12 121 18-Feb-12 03-Nov-12 18-Feb-12 01-Apr-13 72.58% 97.17%
Civil PackagCivil Package 128 15-Feb-12 A 01-Sep-12 176 18-Feb-12 07-Oct-12 18-Feb-12 01-Apr-13 73.27% 97.63%
Hotel AparteHotel Apartements (Block A) 124 15-Feb-12 A 01-Sep-12 78 18-Feb-12 04-Oct-12 18-Feb-12 28-Nov-12 79.73% 99.43%
Foundation LFoundation Level 13 15-Feb-12 A 28-Feb-12 A 18-Feb-12 11-Mar-12 18-Feb-12 11-Mar-12 100% 100%
Earth WorksEarth Works 8 15-Feb-12 A 15-Feb-12 A 18-Feb-12 28-Feb-12 18-Feb-12 28-Feb-12 100% 100%A1370 Excavation and Compaction 8 15-Feb-12 A 15-Feb-12 A 18-Feb-12 26-Feb-12 18-Feb-12 26-Feb-12 0 100% 100%
A1400 Base Coarse and Compaction 8 15-Feb-12 A 15-Feb-12 A 20-Feb-12 28-Feb-12 20-Feb-12 28-Feb-12 0 100% 100%Deep FoundDeep Foundation 13 15-Feb-12 A 28-Feb-12 A 22-Feb-12 11-Mar-12 22-Feb-12 11-Mar-12 100% 100%A1060 Laying Polythene Sheet & Blinding 7 15-Feb-12 A 15-Feb-12 A 22-Feb-12 29-Feb-12 22-Feb-12 29-Feb-12 0 100% 100%
A1080 Water Proofing & Screed 3 15-Feb-12 A 16-Feb-12 A 23-Feb-12 26-Feb-12 23-Feb-12 26-Feb-12 0 100% 100%
A1100 Raft Slab 1000 mm RC Works 13 15-Feb-12 A 28-Feb-12 A 26-Feb-12 11-Mar-12 26-Feb-12 11-Mar-12 0 100% 100%
A1160 MEP Works inside Raft Slab 4 20-Feb-12 A 23-Feb-12 A 27-Feb-12 01-Mar-12 07-Mar-12 11-Mar-12 8 100% 100%
1st Basemen1st Basement Floor Slab 102 15-Feb-12 A 24-Apr-12 A 12-Mar-12 30-Jun-12 14-Mar-12 21-Oct-12 100% 100%
Walls and CWalls and Columns 15 03-Mar-12 A 19-Mar-12 A 12-Mar-12 28-Mar-12 14-Mar-12 09-Apr-12 100% 100%A1110 Core Wall RC Works 6 13-Mar-12 A 19-Mar-12 A 14-Mar-12 20-Mar-12 14-Mar-12 20-Mar-12 0 100% 100%
A1120 Retaining Wall 250 mm RC Works 15 05-Mar-12 A 12-Mar-12 A 12-Mar-12 28-Mar-12 14-Mar-12 31-Mar-12 2 100% 100%
A1130 Ramp Wall RC Works 6 08-Mar-12 A 13-Mar-12 A 17-Mar-12 22-Mar-12 03-Apr-12 09-Apr-12 15 100% 100%
A1140 Columns RC Works 10 03-Mar-12 A 10-Mar-12 A 13-Mar-12 24-Mar-12 14-Mar-12 25-Mar-12 1 100% 100%SlabSlab 94 15-Feb-12 A 24-Apr-12 A 17-Mar-12 30-Jun-12 17-Mar-12 21-Oct-12 100% 100%A1150 MEP Works inside Slab 6 13-Mar-12 A 19-Mar-12 A 20-Mar-12 26-Mar-12 07-Apr-12 12-Apr-12 15 100% 100%
A1170 1st Basement Floor Slab RC Works 24 13-Mar-12 A 20-Mar-12 A 17-Mar-12 12-Apr-12 17-Mar-12 12-Apr-12 0 100% 100%
A1180 Curing for Slab 3 21-Mar-12 A 27-Mar-12 A 14-Apr-12 16-Apr-12 13-Sep-12 16-Sep-12 128 100% 100%
A1190 Strike Formwork 3 21-Apr-12 A 24-Apr-12 A 12-May-12 14-May-12 17-Sep-12 19-Sep-12 107 100% 100%
A1200 Ramp Slab RC Works 5 15-Mar-12 A 20-Mar-12 A 21-Mar-12 26-Mar-12 08-Apr-12 12-Apr-12 15 100% 100%
A1320 Water Proofing Membrane for Ret. Walls 10 29-Feb-12 A 06-Mar-12 A 17-May-12 28-May-12 23-Sep-12 03-Oct-12 107 100% 100%
A1330 Gunited Concrete 50 mm for Ret. Walls 10 15-Feb-12 A 16-Feb-12 A 29-May-12 09-Jun-12 04-Oct-12 15-Oct-12 107 100% 100%
A1360 Backfilling 5 22-Feb-12 A 22-Feb-12 A 25-Jun-12 30-Jun-12 16-Oct-12 21-Oct-12 95 100% 100%StairsStairs 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 100% 100%Stairs 1Stairs 1 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 100% 100%A1380 Stairs RC Works (2nd Basement to 1st Basement) 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 95 100% 100%
Ground FloorGround Floor Slab 53 15-Feb-12 A 23-May-12 A 14-Apr-12 12-Jul-12 14-Apr-12 24-Oct-12 96.62% 100%
Walls and CWalls and Columns 26 25-Mar-12 A 11-Apr-12 A 14-Apr-12 30-Apr-12 14-Apr-12 03-May-12 100% 100%A1220 Core Wall RC Works 6 25-Mar-12 A 01-Apr-12 A 15-Apr-12 21-Apr-12 15-Apr-12 21-Apr-12 0 100% 100%
A1230 Retaining Wall 250 mm RC Works 15 07-Apr-12 A 11-Apr-12 A 14-Apr-12 30-Apr-12 14-Apr-12 30-Apr-12 0 100% 100%
A1240 Ramp Wall RC Works 7 02-Apr-12 A 03-Apr-12 A 18-Apr-12 25-Apr-12 26-Apr-12 03-May-12 7 100% 100%
A1250 Columns RC Works 10 25-Mar-12 A 27-Mar-12 A 14-Apr-12 24-Apr-12 14-Apr-12 24-Apr-12 0 100% 100%SlabSlab 45 15-Feb-12 A 23-May-12 A 17-Apr-12 09-Jul-12 17-Apr-12 24-Oct-12 97.43% 100%A1260 MEP Works inside Slab 5 10-Apr-12 A 18-Apr-12 A 25-Apr-12 30-Apr-12 02-May-12 07-May-12 6 100% 100%
A1270 Ground Floor Slab RC Works 18 03-Apr-12 A 18-Apr-12 A 17-Apr-12 07-May-12 17-Apr-12 07-May-12 0 100% 100%
A1280 Curing for Slab 3 19-Apr-12 A 25-Apr-12 A 08-May-12 10-May-12 07-Aug-12 09-Aug-12 77 100% 100%
A1290 Strike Formwork 3 03-May-12 A 23-May-12 A 04-Jun-12 06-Jun-12 11-Aug-12 13-Aug-12 57 100% 100%
A1300 Ramp Slab RC Works 6 14-Apr-12 A 14-Apr-12 A 23-Apr-12 29-Apr-12 01-May-12 07-May-12 7 100% 100%
A1340 Water Proofing Membrane for Ret. Walls 10 03-Apr-12 A 10-Apr-12 A 10-Jun-12 21-Jun-12 26-Sep-12 07-Oct-12 90 100% 100%
A1350 Gunited Concrete 50 mm for Ret. Walls 10 15-Feb-12 A 16-Feb-12 A 23-Jun-12 03-Jul-12 08-Oct-12 18-Oct-12 90 70% 100%
A1520 Backfilling 5 15-Feb-12 A 15-Feb-12 A 04-Jul-12 09-Jul-12 20-Oct-12 24-Oct-12 90 0% 100%StairsStairs 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 0% 100%Stair 1Stair 1 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 0% 100%A1530 Stairs RC Works (1st Basement to Ground) 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 87 0% 100%
1st Floor Slab1st Floor Slab 42 22-Apr-12 A 15-Jun-12 A 08-May-12 05-Aug-12 08-May-12 06-Nov-12 90.44% 100%
Walls and CWalls and Columns 10 22-Apr-12 A 01-May-12 A 08-May-12 17-May-12 08-May-12 17-May-12 100% 100%A1390 Core Wall RC Works 6 23-Apr-12 A 28-Apr-12 A 08-May-12 14-May-12 08-May-12 14-May-12 0 100% 100%
A1420 Columns RC Works 9 22-Apr-12 A 01-May-12 A 08-May-12 17-May-12 08-May-12 17-May-12 0 100% 100%SlabSlab 36 29-Apr-12 A 15-Jun-12 A 13-May-12 05-Jul-12 13-May-12 17-Oct-12 96.25% 100%A1430 MEP Works inside Slab 5 06-May-12 A 13-May-12 A 19-May-12 23-May-12 29-May-12 03-Jun-12 9 100% 100%
A1440 1st Floor Slab RC Works 19 29-Apr-12 A 14-May-12 A 13-May-12 03-Jun-12 13-May-12 03-Jun-12 0 100% 100%
A1450 Curing for Slab 3 16-May-12 A 20-May-12 A 04-Jun-12 06-Jun-12 11-Oct-12 14-Oct-12 108 100% 100%
A1460 Strike Formwork 3 06-Jun-12 A 15-Jun-12 A 03-Jul-12 05-Jul-12 15-Oct-12 17-Oct-12 87 0% 100%StairsStairs 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 22-Oct-12 06-Nov-12 0% 100%Stair 1Stair 1 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 22-Oct-12 30-Oct-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Sub & App- GSM System
Sub & App- MATV/ Interactive TV System
Sub & App- Generators
Sub & App- Telephone System
Sub & App- DBs
Sub & App- MDBs
Sub & App- SMDBs
Sub & App- Pool Finishes
Sub & App- Pool Equipments
Sub & App- Water Proofing for Swimming Pool
Sub & App- Pool Electrical Items
s Order&Delivery- Plaster Materials
s Order&Delivery- Blocks
Order&Delivery- Chilled Water Pipes-Fittings-Valves
Order&Delivery- Condensate Pipes-Fittings-Valves
Order&Delivery- HAVC Ducts
er Order&Delivery- Chiller
Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge)
Order&Delivery- Electrical Heaters
Order&Delivery- Fire Pipes-Fittings-Valves
Order&Delivery- FM 200 System
Order&Delivery- Cable Trays
Order&Delivery- Trunking
Order&Delivery- Earthing & Lightining
Order&Delivery- Conduits & PVC Ducts
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 11 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A1540 Stairs RC Works (Ground to 1st floor) 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 22-Oct-12 30-Oct-12 70 0% 100%Stair 2Stair 2 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 28-Oct-12 03-Nov-12 0% 100%A1550 Stairs RC Works (Ground to 1st floor) 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 28-Oct-12 03-Nov-12 73 0% 100%
Stair 3Stair 3 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 31-Oct-12 06-Nov-12 0% 100%A111130 Stairs RC Works (Ground to 1st floor) 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 31-Oct-12 06-Nov-12 76 0% 100%
2nd Floor Sl2nd Floor Slab 33 16-May-12 A 04-Jul-12 103 04-Jun-12 30-Aug-12 04-Jun-12 13-Nov-12 90.34% 100%
Walls and CWalls and Columns 9 16-May-12 A 24-May-12 A 04-Jun-12 13-Jun-12 04-Jun-12 13-Jun-12 100% 100%A1560 Core Wall RC Works 6 17-May-12 A 21-May-12 A 04-Jun-12 10-Jun-12 04-Jun-12 10-Jun-12 0 100% 100%
A1570 Columns RC Works 9 16-May-12 A 24-May-12 A 04-Jun-12 13-Jun-12 04-Jun-12 13-Jun-12 0 100% 100%SlabSlab 31 19-May-12 A 04-Jul-12 55 09-Jun-12 29-Jul-12 09-Jun-12 09-Sep-12 93.47% 100%A1580 MEP Works inside Slab 5 22-May-12 A 30-May-12 A 14-Jun-12 20-Jun-12 26-Jun-12 01-Jul-12 9 100% 100%
A1590 2nd Floor Slab RC Works 19 19-May-12 A 30-May-12 A 09-Jun-12 01-Jul-12 09-Jun-12 01-Jul-12 0 94.74% 100%
A1600 Curing for Slab 3 31-May-12 A 06-Jun-12 A 02-Jul-12 04-Jul-12 03-Sep-12 05-Sep-12 52 0% 100%
A1610 Strike Formwork 3 21-Jun-12 A 04-Jul-12 55 26-Jul-12 29-Jul-12 06-Sep-12 09-Sep-12 34 0% 95%StairsStairs 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 13-Nov-12 0% 100%Stair 1Stair 1 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 10-Nov-12 0% 100%A1630 Stairs RC Works (1st to 2nd) 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 10-Nov-12 59 0% 100%
Stair 2Stair 2 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 07-Nov-12 13-Nov-12 0% 100%A1640 Stairs RC Works (1st to 2nd) 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 07-Nov-12 13-Nov-12 62 0% 100%
3rd Floor Slab3rd Floor Slab 18 02-Jun-12 A 25-Jun-12 A 02-Jul-12 18-Sep-12 02-Jul-12 21-Nov-12 0% 100%
Walls and CWalls and Columns 9 02-Jun-12 A 10-Jun-12 A 02-Jul-12 11-Jul-12 02-Jul-12 11-Jul-12 0% 100%A1650 Core Wall RC Works 6 02-Jun-12 A 05-Jun-12 A 02-Jul-12 08-Jul-12 02-Jul-12 08-Jul-12 0 0% 100%
A1660 Columns RC Works 9 02-Jun-12 A 10-Jun-12 A 02-Jul-12 11-Jul-12 02-Jul-12 11-Jul-12 0 0% 100%SlabSlab 13 07-Jun-12 A 25-Jun-12 A 08-Jul-12 24-Jul-12 08-Jul-12 28-Aug-12 0% 100%A1670 MEP Works inside Slab 4 09-Jun-12 A 16-Jun-12 A 09-Jul-12 12-Jul-12 17-Jul-12 21-Jul-12 7 0% 100%
A1680 3rd Floor Slab RC Works 12 07-Jun-12 A 18-Jun-12 A 08-Jul-12 21-Jul-12 08-Jul-12 21-Jul-12 0 0% 100%
A1690 Curing for Slab 3 19-Jun-12 A 25-Jun-12 A 22-Jul-12 24-Jul-12 26-Aug-12 28-Aug-12 28 0% 100%StairsStairs 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 21-Nov-12 0% 100%Stair 1Stair 1 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 18-Nov-12 0% 100%A1710 Stairs RC Works (2nd to 3rd) 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 18-Nov-12 49 0% 100%
Stair 2Stair 2 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 14-Nov-12 21-Nov-12 0% 100%A1720 Stairs RC Works (2nd to 3rd) 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 14-Nov-12 21-Nov-12 52 0% 100%
4th Floor Slab4th Floor Slab 17 19-Jun-12 A 01-Sep-12 74 22-Jul-12 04-Oct-12 22-Jul-12 28-Nov-12 0% 93.16%
Walls and CWalls and Columns 9 19-Jun-12 A 26-Jun-12 A 22-Jul-12 31-Jul-12 22-Jul-12 31-Jul-12 0% 100%A1730 Core Wall RC Works 6 23-Jun-12 A 26-Jun-12 A 22-Jul-12 28-Jul-12 22-Jul-12 28-Jul-12 0 0% 100%
A1740 Columns RC Works 9 19-Jun-12 A 24-Jun-12 A 22-Jul-12 31-Jul-12 22-Jul-12 31-Jul-12 0 0% 100%SlabSlab 12 25-Jun-12 A 05-Jul-12 29 26-Jul-12 08-Aug-12 26-Jul-12 08-Aug-12 0% 90%A1750 MEP Works inside Slab 4 25-Jun-12 A 04-Jul-12 30 30-Jul-12 02-Aug-12 05-Aug-12 08-Aug-12 5 0% 90%
A1760 4th Slab RC Works 12 25-Jun-12 A 05-Jul-12 29 26-Jul-12 08-Aug-12 26-Jul-12 08-Aug-12 0 0% 90%StairsStairs 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 19-Nov-12 28-Nov-12 0% 90%Stair 1Stair 1 6 25-Jun-12 A 01-Sep-12 71 29-Sep-12 04-Oct-12 19-Nov-12 25-Nov-12 0% 90%A1790 Stairs RC Works (3rd to 4th) 6 25-Jun-12 A 01-Sep-12 71 29-Sep-12 04-Oct-12 19-Nov-12 25-Nov-12 41 0% 90%
Stair 2Stair 2 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 22-Nov-12 28-Nov-12 0% 90%A1800 Stairs RC Works (3rd to 4th) 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 22-Nov-12 28-Nov-12 44 0% 90%
Hotel (BlockHotel (Block B) 114 15-Feb-12 A 09-Jul-12 163 18-Feb-12 07-Oct-12 18-Feb-12 05-Mar-13 70.25% 97.34%
Foundation LFoundation Level 55 03-Mar-12 A 12-Apr-12 A 18-Feb-12 30-Apr-12 18-Feb-12 30-Apr-12 100% 100%
Earth WorksEarth Works 9 03-Mar-12 A 07-Apr-12 A 18-Feb-12 27-Mar-12 18-Feb-12 27-Mar-12 100% 100%Part 1 (B1)Part 1 (B1) 9 03-Mar-12 A 19-Mar-12 A 18-Feb-12 03-Mar-12 18-Feb-12 13-Mar-12 100% 100%A12320 Excavation and Compaction 8 03-Mar-12 A 18-Mar-12 A 18-Feb-12 26-Feb-12 18-Feb-12 26-Feb-12 0 100% 100%
A12330 Base Coarse and Compaction 8 04-Mar-12 A 19-Mar-12 A 23-Feb-12 03-Mar-12 05-Mar-12 13-Mar-12 9 100% 100%Part 2 (B2)Part 2 (B2) 9 03-Mar-12 A 07-Apr-12 A 12-Mar-12 27-Mar-12 12-Mar-12 27-Mar-12 100% 100%A12730 Excavation and Compaction 8 03-Mar-12 A 04-Apr-12 A 12-Mar-12 20-Mar-12 12-Mar-12 20-Mar-12 0 100% 100%
A12740 Base Coarse and Compaction 8 04-Mar-12 A 07-Apr-12 A 19-Mar-12 27-Mar-12 19-Mar-12 27-Mar-12 0 100% 100%Deep FoundDeep Foundation 48 11-Mar-12 A 12-Apr-12 A 01-Mar-12 30-Apr-12 12-Mar-12 30-Apr-12 100% 100%Part 1 (B1)Part 1 (B1) 36 11-Mar-12 A 30-Mar-12 A 01-Mar-12 08-Apr-12 12-Mar-12 18-Apr-12 100% 100%A11520 Laying Polythene Sheet & Blinding 5 11-Mar-12 A 19-Mar-12 A 01-Mar-12 06-Mar-12 12-Mar-12 17-Mar-12 9 100% 100%
A11530 Water Proofing & Screed 7 13-Mar-12 A 20-Mar-12 A 06-Mar-12 13-Mar-12 17-Mar-12 24-Mar-12 9 100% 100%
A11540 Raft Slab 1000 mm RC Works (Part 1) 25 24-Mar-12 A 30-Mar-12 A 11-Mar-12 08-Apr-12 21-Mar-12 18-Apr-12 9 100% 100%
A11580 MEP Works inside Raft Slab 7 25-Mar-12 A 27-Mar-12 A 14-Mar-12 21-Mar-12 11-Apr-12 18-Apr-12 24 100% 100%Part 2 (B2)Part 2 (B2) 42 18-Mar-12 A 12-Apr-12 A 24-Mar-12 30-Apr-12 24-Mar-12 30-Apr-12 100% 100%A12750 Laying Polythene Sheet & Blinding 4 19-Mar-12 A 07-Apr-12 A 24-Mar-12 27-Mar-12 24-Mar-12 27-Mar-12 0 100% 100%
A12760 Water Proofing & Screed 6 18-Mar-12 A 09-Apr-12 A 27-Mar-12 02-Apr-12 27-Mar-12 02-Apr-12 0 100% 100%
A12780 Raft Slab 1000 mm RC Works (Part 2) 25 07-Apr-12 A 12-Apr-12 A 02-Apr-12 30-Apr-12 02-Apr-12 30-Apr-12 0 100% 100%
A12770 MEP Works inside Raft Slab 10 09-Apr-12 A 10-Apr-12 A 03-Apr-12 14-Apr-12 19-Apr-12 30-Apr-12 14 100% 100%
1st Basemen1st Basement Floor Slab 94 15-Feb-12 A 09-Jun-12 A 09-Apr-12 15-Aug-12 02-May-12 05-Mar-13 95.67% 100%
Walls and CWalls and Columns 27 01-Apr-12 A 03-May-12 A 09-Apr-12 12-May-12 02-May-12 16-Jun-12 100% 100%Part 1 (B1)Part 1 (B1) 13 01-Apr-12 A 18-Apr-12 A 09-Apr-12 06-May-12 09-May-12 20-May-12 100% 100%A11550 Core Wall RC Works 8 15-Apr-12 A 18-Apr-12 A 28-Apr-12 06-May-12 12-May-12 20-May-12 12 100% 100%
A11560 Retaining Wall 250 mm RC Works (Part 1) 10 04-Apr-12 A 07-Apr-12 A 09-Apr-12 19-Apr-12 09-May-12 20-May-12 26 100% 100%
A11570 Columns RC Works 6 07-Apr-12 A 15-Apr-12 A 10-Apr-12 16-Apr-12 10-May-12 16-May-12 26 100% 100%
A12340 Tank Wall RC Works 6 01-Apr-12 A 18-Apr-12 A 10-Apr-12 16-Apr-12 10-May-12 16-May-12 26 100% 100%Part 2 (B2)Part 2 (B2) 26 02-Apr-12 A 03-May-12 A 02-May-12 12-May-12 02-May-12 16-Jun-12 100% 100%A12810 Core Wall RC Works 6 16-Apr-12 A 23-Apr-12 A 03-May-12 09-May-12 07-Jun-12 13-Jun-12 30 100% 100%
A12820 Retaining Wall 250 mm RC Works (Part 2) 8 23-Apr-12 A 30-Apr-12 A 03-May-12 12-May-12 07-Jun-12 16-Jun-12 30 100% 100%
A12790 Columns RC Works 8 21-Apr-12 A 01-May-12 A 02-May-12 10-May-12 02-May-12 10-May-12 0 100% 100%
A12800 Tank Wall RC Works 6 02-Apr-12 A 03-May-12 A 02-May-12 08-May-12 07-Jun-12 13-Jun-12 31 100% 100%
A12610 Ramp Wall RC Works 8 16-Apr-12 A 22-Apr-12 A 02-May-12 10-May-12 02-May-12 10-May-12 0 100% 100%SlabSlab 94 15-Feb-12 A 09-Jun-12 A 03-May-12 04-Aug-12 12-May-12 21-Nov-12 97.13% 100%A11590 MEP Works inside Slab 5 23-Apr-12 A 03-May-12 A 03-May-12 08-May-12 07-Jun-12 12-Jun-12 30 100% 100%
A11600 1st Basement Floor Slab RC Works 25 11-Apr-12 A 06-May-12 A 15-May-12 12-Jun-12 15-May-12 12-Jun-12 0 100% 100%
A11610 Curing for Slab 3 26-Apr-12 A 12-May-12 A 13-Jun-12 16-Jun-12 21-Oct-12 23-Oct-12 108 100% 100%
A11620 Strike Formwork 3 20-May-12 A 09-Jun-12 A 10-Jul-12 12-Jul-12 24-Oct-12 29-Oct-12 89 0% 100%
A12200 Ramp Slab RC Works 5 15-Apr-12 A 26-Apr-12 A 12-May-12 16-May-12 12-May-12 16-May-12 0 100% 100%
A11720 Water Proofing Membrane for Ret. Walls 7 10-Mar-12 A 08-Apr-12 A 16-Jul-12 23-Jul-12 01-Nov-12 08-Nov-12 89 0% 100%
A11730 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 24-Jul-12 31-Jul-12 10-Nov-12 18-Nov-12 89 0% 100%
A11820 Backfilling 3 15-Feb-12 A 15-Feb-12 A 01-Aug-12 04-Aug-12 19-Nov-12 21-Nov-12 89 0% 100%StairsStairs 13 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 05-Mar-13 0% 100%Stairs 1Stairs 1 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 21-Nov-12 0% 100%A12350 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 21-Nov-12 79 0% 100%
Stairs 2Stairs 2 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 07-Jan-13 13-Jan-13 0% 100%A12360 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 07-Jan-13 13-Jan-13 122 0% 100%
Stairs 3Stairs 3 6 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 27-Feb-13 05-Mar-13 0% 100%A12370 Stairs RC Works (2nd Basement to 1st Basement) 6 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 27-Feb-13 05-Mar-13 165 0% 100%
Ground FloorGround Floor Slab 65 15-Feb-12 A 10-Jun-12 A 13-Jun-12 15-Sep-12 13-Jun-12 25-Dec-12 63.91% 100%
Walls and CWalls and Columns 21 28-Apr-12 A 30-May-12 A 13-Jun-12 08-Jul-12 13-Jun-12 08-Jul-12 85.65% 100%A11640 Core Wall RC Works 15 28-Apr-12 A 20-May-12 A 14-Jun-12 02-Jul-12 14-Jun-12 02-Jul-12 0 86.67% 100%
A11650 Retaining Wall 250 mm RC Works 21 29-Apr-12 A 29-May-12 A 13-Jun-12 08-Jul-12 13-Jun-12 08-Jul-12 0 66.67% 100%
A11660 Columns RC Works 11 28-Apr-12 A 30-May-12 A 13-Jun-12 26-Jun-12 13-Jun-12 26-Jun-12 0 100% 100%
A117050 Ramp Wall RC Works 6 10-May-12 A 20-May-12 A 13-Jun-12 20-Jun-12 26-Jun-12 02-Jul-12 10 100% 100%SlabSlab 62 15-Feb-12 A 10-Jun-12 A 20-Jun-12 02-Sep-12 20-Jun-12 26-Nov-12 51.53% 100%A11670 MEP Works inside Slab 10 14-May-12 A 02-Jun-12 A 21-Jun-12 02-Jul-12 30-Jun-12 10-Jul-12 7 80% 100%
A11680 Ground Floor Slab RC Works 18 08-May-12 A 03-Jun-12 A 20-Jun-12 10-Jul-12 20-Jun-12 10-Jul-12 0 50% 100%
A11690 Curing for Slab 3 24-May-12 A 10-Jun-12 A 11-Jul-12 14-Jul-12 04-Oct-12 07-Oct-12 71 0% 100%
A117060 Ramp Slab RC Works 7 20-May-12 A 23-May-12 A 21-Jun-12 28-Jun-12 03-Jul-12 10-Jul-12 10 100% 100%
A11740 Water Proofing Membrane for Ret. Walls 7 02-May-12 A 26-May-12 A 12-Aug-12 21-Aug-12 06-Nov-12 13-Nov-12 70 0% 100%
A11750 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 22-Aug-12 29-Aug-12 14-Nov-12 22-Nov-12 70 0% 100%
A11830 Backfilling 3 15-Feb-12 A 15-Feb-12 A 30-Aug-12 02-Sep-12 24-Nov-12 26-Nov-12 70 0% 100%StairsStairs 12 20-May-12 A 03-Jun-12 A 09-Sep-12 15-Sep-12 20-Nov-12 25-Dec-12 0% 100%Stairs 1Stairs 1 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 20-Nov-12 26-Nov-12 0% 100%A12380 Stairs RC Works (1st Basement toGround) 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 20-Nov-12 26-Nov-12 59 0% 100%
Stairs 2Stairs 2 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 05-Dec-12 11-Dec-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
rk Strike Formwork
ab
ks
ks
ab MEP Works inside Slab
ks 4th Slab RC Works
h) Stairs RC Works (3rd to 4th)
h) Stairs RC Works (3rd to 4th)
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 12 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A12390 Stairs RC Works (1st Basement toGround) 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 05-Dec-12 11-Dec-12 71 0% 100%Stairs 3Stairs 3 6 28-May-12 A 03-Jun-12 A 09-Sep-12 15-Sep-12 19-Dec-12 25-Dec-12 0% 100%A12400 Stairs RC Works (1st Basement toGround) 6 28-May-12 A 03-Jun-12 A 09-Sep-12 15-Sep-12 19-Dec-12 25-Dec-12 83 0% 100%
1st Floor Slab1st Floor Slab 26 29-May-12 A 01-Jul-12 147 11-Jul-12 07-Oct-12 11-Jul-12 21-Feb-13 0% 100%
Walls and CWalls and Columns 12 29-May-12 A 20-Jun-12 A 11-Jul-12 21-Jul-12 11-Jul-12 21-Jul-12 0% 100%A11760 Core Wall RC Works 6 29-May-12 A 10-Jun-12 A 11-Jul-12 17-Jul-12 15-Jul-12 21-Jul-12 3 0% 100%
A11770 Columns RC Works 9 03-Jun-12 A 20-Jun-12 A 11-Jul-12 21-Jul-12 11-Jul-12 21-Jul-12 0 0% 100%SlabSlab 19 06-Jun-12 A 01-Jul-12 100 22-Jul-12 08-Aug-12 22-Jul-12 30-Oct-12 0% 100%A11780 MEP Works inside Slab 5 07-Jun-12 A 24-Jun-12 A 22-Jul-12 26-Jul-12 31-Jul-12 05-Aug-12 8 0% 100%
A11790 1st Floor Slab RC Works 13 06-Jun-12 A 25-Jun-12 A 22-Jul-12 05-Aug-12 22-Jul-12 05-Aug-12 0 0% 100%
A11800 Curing for Slab 3 26-Jun-12 A 01-Jul-12 100 06-Aug-12 08-Aug-12 28-Oct-12 30-Oct-12 67 0% 80%StairsStairs 7 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 21-Feb-13 0% 100%Stairs 1Stairs 1 6 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 09-Jan-13 0% 100%A12410 Stairs RC Works (Ground to 1st floor) 6 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 09-Jan-13 76 0% 100%
Stairs 2Stairs 2 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 17-Jan-13 23-Jan-13 0% 100%A12420 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 17-Jan-13 23-Jan-13 88 0% 100%
Stairs 3Stairs 3 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 02-Feb-13 07-Feb-13 0% 100%A12430 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 02-Feb-13 07-Feb-13 100 0% 100%
Stairs 4Stairs 4 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 16-Feb-13 21-Feb-13 0% 100%A109130 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 16-Feb-13 21-Feb-13 112 0% 100%
2nd Floor Sl2nd Floor Slab 9 28-Jun-12 A 09-Jul-12 33 06-Aug-12 15-Aug-12 06-Aug-12 15-Aug-12 0% 27.71%
Walls and CWalls and Columns 9 28-Jun-12 A 09-Jul-12 33 06-Aug-12 15-Aug-12 06-Aug-12 15-Aug-12 0% 27.71%A11840 Core Wall RC Works 6 28-Jun-12 A 04-Jul-12 33 06-Aug-12 12-Aug-12 06-Aug-12 12-Aug-12 0 0% 40%
A11850 Columns RC Works 9 28-Jun-12 A 09-Jul-12 33 06-Aug-12 15-Aug-12 06-Aug-12 15-Aug-12 0 0% 20%
Residential Residential Apartments (Block C) 126 15-Feb-12 A 08-Jul-12 189 18-Feb-12 06-Oct-12 12-Mar-12 01-Apr-13 71.42% 96.52%
Foundation LFoundation Level 36 15-Feb-12 A 04-Apr-12 A 18-Feb-12 30-Apr-12 12-Mar-12 30-Apr-12 100% 100%
Earth WorksEarth Works 8 15-Feb-12 A 18-Feb-12 A 18-Feb-12 25-Mar-12 12-Mar-12 25-Mar-12 100% 100%Part 1 (C1)Part 1 (C1) 8 15-Feb-12 A 18-Feb-12 A 18-Feb-12 28-Feb-12 12-Mar-12 22-Mar-12 100% 100%A12660 Excavation and Compaction 8 15-Feb-12 A 18-Feb-12 A 18-Feb-12 26-Feb-12 12-Mar-12 20-Mar-12 20 100% 100%
A12670 Base Coarse and Compaction 8 15-Feb-12 A 18-Feb-12 A 20-Feb-12 28-Feb-12 14-Mar-12 22-Mar-12 20 100% 100%Part 2 (C2)Part 2 (C2) 5 15-Feb-12 A 18-Feb-12 A 18-Mar-12 25-Mar-12 18-Mar-12 25-Mar-12 100% 100%A11200 Excavation and Compaction 5 15-Feb-12 A 18-Feb-12 A 18-Mar-12 22-Mar-12 18-Mar-12 22-Mar-12 0 100% 100%
A11210 Base Coarse and Compaction 5 15-Feb-12 A 18-Feb-12 A 20-Mar-12 25-Mar-12 20-Mar-12 25-Mar-12 0 100% 100%Deep FoundDeep Foundation 36 15-Feb-12 A 04-Apr-12 A 22-Feb-12 30-Apr-12 17-Mar-12 30-Apr-12 100% 100%Part 1 (C1)Part 1 (C1) 21 15-Feb-12 A 08-Mar-12 A 22-Feb-12 08-Mar-12 17-Mar-12 01-Apr-12 100% 100%A12620 Laying Polythene Sheet & Blinding 5 15-Feb-12 A 25-Feb-12 A 22-Feb-12 27-Feb-12 17-Mar-12 21-Mar-12 20 100% 100%
A12630 Water Proofing & Screed 8 26-Feb-12 A 03-Mar-12 A 25-Feb-12 04-Mar-12 19-Mar-12 27-Mar-12 20 100% 100%
A12650 Raft Slab 1000 mm RC Works (Part 1) 10 28-Feb-12 A 08-Mar-12 A 27-Feb-12 08-Mar-12 21-Mar-12 01-Apr-12 20 100% 100%
A12640 MEP Works inside Raft Slab 4 03-Mar-12 A 06-Mar-12 A 01-Mar-12 05-Mar-12 28-Mar-12 01-Apr-12 23 100% 100%Part 2 (C2)Part 2 (C2) 36 15-Feb-12 A 04-Apr-12 A 26-Mar-12 30-Apr-12 26-Mar-12 30-Apr-12 100% 100%A10170 Laying Polythene Sheet & Blinding 3 15-Feb-12 A 25-Feb-12 A 26-Mar-12 28-Mar-12 26-Mar-12 28-Mar-12 0 100% 100%
A10180 Water Proofing & Screed 5 26-Feb-12 A 03-Mar-12 A 29-Mar-12 03-Apr-12 29-Mar-12 03-Apr-12 0 100% 100%
A10190 Raft Slab 1000 mm RC Works (Part 2) 25 28-Feb-12 A 04-Apr-12 A 02-Apr-12 30-Apr-12 02-Apr-12 30-Apr-12 0 100% 100%
A10240 MEP Works inside Raft Slab 4 03-Mar-12 A 07-Mar-12 A 04-Apr-12 08-Apr-12 26-Apr-12 30-Apr-12 19 100% 100%
1st Basemen1st Basement Floor Slab 93 15-Feb-12 A 07-Jun-12 A 10-Mar-12 11-Aug-12 26-Apr-12 02-Mar-13 96.52% 100%
Walls and CWalls and Columns 41 12-Mar-12 A 23-Apr-12 A 10-Mar-12 12-May-12 26-Apr-12 28-May-12 100% 100%Part 1 (C1)Part 1 (C1) 15 12-Mar-12 A 28-Mar-12 A 10-Mar-12 12-May-12 26-Apr-12 16-May-12 100% 100%A10200 Core Wall RC Works 10 20-Mar-12 A 24-Mar-12 A 01-May-12 12-May-12 02-May-12 13-May-12 1 100% 100%
A10210 Retaining Wall 250 mm RC Works 12 15-Mar-12 A 21-Mar-12 A 05-Apr-12 18-Apr-12 03-May-12 16-May-12 24 100% 100%
A10230 Columns RC Works 8 12-Mar-12 A 15-Mar-12 A 10-Mar-12 18-Mar-12 03-May-12 12-May-12 47 100% 100%
A11220 Tank Wall RC Works 10 14-Mar-12 A 28-Mar-12 A 05-Apr-12 16-Apr-12 26-Apr-12 07-May-12 18 100% 100%Part 2 (C2)Part 2 (C2) 9 17-Apr-12 A 23-Apr-12 A 01-May-12 10-May-12 01-May-12 28-May-12 100% 100%A12710 Core Wall RC Works 6 21-Apr-12 A 23-Apr-12 A 01-May-12 07-May-12 22-May-12 28-May-12 18 100% 100%
A12720 Retaining Wall 250 mm RC Works 9 17-Apr-12 A 21-Apr-12 A 01-May-12 10-May-12 01-May-12 10-May-12 0 100% 100%
A12690 Columns RC Works 4 17-Apr-12 A 21-Apr-12 A 01-May-12 05-May-12 24-May-12 28-May-12 20 100% 100%SlabSlab 93 15-Feb-12 A 07-Jun-12 A 08-May-12 04-Aug-12 08-May-12 18-Nov-12 98.25% 100%A10250 MEP Works inside Slab 8 24-Mar-12 A 28-Apr-12 A 12-May-12 20-May-12 30-May-12 07-Jun-12 16 100% 100%
A10260 1st Basement Floor Slab RC Works 27 21-Mar-12 A 30-Apr-12 A 08-May-12 07-Jun-12 08-May-12 07-Jun-12 0 100% 100%
A10270 Curing for Slab 3 05-Apr-12 A 07-May-12 A 09-Jun-12 11-Jun-12 17-Oct-12 20-Oct-12 109 100% 100%
A10280 Strike Formwork 3 21-Apr-12 A 07-Jun-12 A 10-Jul-12 12-Jul-12 21-Oct-12 23-Oct-12 86 0% 100%
A10410 Water Proofing Membrane for Ret. Walls 7 11-Mar-12 A 14-Mar-12 A 16-Jul-12 23-Jul-12 29-Oct-12 05-Nov-12 86 0% 100%
A10420 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 24-Jul-12 31-Jul-12 06-Nov-12 13-Nov-12 86 0% 100%
A10520 Backfilling 3 15-Feb-12 A 15-Feb-12 A 01-Aug-12 04-Aug-12 14-Nov-12 18-Nov-12 86 0% 100%StairsStairs 23 04-Apr-12 A 30-Apr-12 A 05-Aug-12 11-Aug-12 11-Nov-12 02-Mar-13 0% 100%Stairs 1Stairs 1 6 04-Apr-12 A 04-Apr-12 A 05-Aug-12 11-Aug-12 11-Nov-12 18-Nov-12 0% 100%A11230 Stairs RC Works (2nd Basement to 1st Basement) 6 04-Apr-12 A 04-Apr-12 A 05-Aug-12 11-Aug-12 11-Nov-12 18-Nov-12 80 0% 100%
Stairs 2Stairs 2 6 04-Apr-12 A 04-Apr-12 A 05-Aug-12 11-Aug-12 03-Jan-13 09-Jan-13 0% 100%A11240 Stairs RC Works (2nd Basement to 1st Basement) 6 04-Apr-12 A 04-Apr-12 A 05-Aug-12 11-Aug-12 03-Jan-13 09-Jan-13 123 0% 100%
Stairs 3Stairs 3 6 24-Apr-12 A 30-Apr-12 A 05-Aug-12 11-Aug-12 24-Feb-13 02-Mar-13 0% 100%A11250 Stairs RC Works (2nd Basement to 1st Basement) 6 24-Apr-12 A 30-Apr-12 A 05-Aug-12 11-Aug-12 24-Feb-13 02-Mar-13 166 0% 100%
Ground FloorGround Floor Slab 77 15-Feb-12 A 02-Jul-12 176 09-Jun-12 28-Aug-12 09-Jun-12 02-Mar-13 86.46% 99.18%
Walls and CWalls and Columns 30 12-Apr-12 A 22-May-12 A 09-Jun-12 03-Jul-12 09-Jun-12 03-Jul-12 93.85% 100%A10310 Core Wall RC Works 15 18-Apr-12 A 13-May-12 A 10-Jun-12 27-Jun-12 10-Jun-12 27-Jun-12 0 100% 100%
A10320 Retaining Wall 250 mm RC Works 21 24-Apr-12 A 21-May-12 A 09-Jun-12 03-Jul-12 09-Jun-12 03-Jul-12 0 85.71% 100%
A10340 Columns RC Works 11 12-Apr-12 A 22-May-12 A 09-Jun-12 21-Jun-12 09-Jun-12 21-Jun-12 0 100% 100%SlabSlab 68 15-Feb-12 A 02-Jul-12 198 13-Jun-12 28-Aug-12 13-Jun-12 02-Mar-13 85.33% 98.59%A10350 MEP Works inside Slab 8 14-May-12 A 29-May-12 A 24-Jun-12 02-Jul-12 24-Jun-12 02-Jul-12 0 75% 100%
A10360 Ground Floor Slab RC Works 16 01-May-12 A 29-May-12 A 13-Jun-12 02-Jul-12 13-Jun-12 02-Jul-12 0 87.5% 100%
A10370 Curing for Slab 3 17-May-12 A 30-May-12 A 03-Jul-12 05-Jul-12 24-Oct-12 29-Oct-12 95 0% 100%
A10380 Strike Formwork 3 20-Jun-12 A 02-Jul-12 112 01-Aug-12 04-Aug-12 30-Oct-12 01-Nov-12 73 0% 40%
A10430 Water Proofing Membrane for Ret. Walls 7 19-Apr-12 A 30-Apr-12 A 07-Aug-12 14-Aug-12 11-Feb-13 18-Feb-13 153 0% 100%
A10440 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 15-Aug-12 25-Aug-12 19-Feb-13 26-Feb-13 153 0% 100%
A10530 Backfilling 3 15-Feb-12 A 15-Feb-12 A 26-Aug-12 28-Aug-12 27-Feb-13 02-Mar-13 153 0% 100%StairsStairs 11 09-May-12 A 29-May-12 A 21-Aug-12 28-Aug-12 24-Feb-13 02-Mar-13 0% 100%Stairs 1Stairs 1 6 09-May-12 A 16-May-12 A 22-Aug-12 28-Aug-12 24-Feb-13 02-Mar-13 0% 100%A11260 Stairs RC Works (1st Basement toGround) 6 09-May-12 A 16-May-12 A 22-Aug-12 28-Aug-12 24-Feb-13 02-Mar-13 153 0% 100%
Stairs 2Stairs 2 6 09-May-12 A 16-May-12 A 21-Aug-12 27-Aug-12 24-Feb-13 02-Mar-13 0% 100%A11270 Stairs RC Works (1st Basement toGround) 6 09-May-12 A 16-May-12 A 21-Aug-12 27-Aug-12 24-Feb-13 02-Mar-13 154 0% 100%
Stairs 3Stairs 3 6 20-May-12 A 29-May-12 A 21-Aug-12 27-Aug-12 24-Feb-13 02-Mar-13 0% 100%A11280 Stairs RC Works (1st Basement toGround) 6 20-May-12 A 29-May-12 A 21-Aug-12 27-Aug-12 24-Feb-13 02-Mar-13 154 0% 100%
1st Floor Slab1st Floor Slab 31 19-May-12 A 02-Jul-12 189 03-Jul-12 06-Oct-12 03-Jul-12 01-Apr-13 0% 99.99%
Walls and CWalls and Columns 12 19-May-12 A 23-Jun-12 A 03-Jul-12 12-Jul-12 03-Jul-12 12-Jul-12 0% 100%A10460 Core Wall RC Works 6 26-May-12 A 20-Jun-12 A 03-Jul-12 09-Jul-12 03-Jul-12 09-Jul-12 0 0% 100%
A10470 Columns RC Works 9 19-May-12 A 23-Jun-12 A 03-Jul-12 12-Jul-12 03-Jul-12 12-Jul-12 0 0% 100%SlabSlab 11 02-Jun-12 A 02-Jul-12 100 08-Jul-12 22-Jul-12 08-Jul-12 30-Oct-12 0% 99.99%A10480 MEP Works inside Slab 5 02-Jun-12 A 28-Jun-12 A 14-Jul-12 18-Jul-12 14-Jul-12 18-Jul-12 0 0% 100%
A10490 1st Floor Slab RC Works 10 02-Jun-12 A 30-Jun-12 A 08-Jul-12 18-Jul-12 08-Jul-12 18-Jul-12 0 0% 100%
A10500 Curing for Slab 3 14-Jun-12 A 02-Jul-12 100 19-Jul-12 22-Jul-12 28-Oct-12 30-Oct-12 82 0% 50%StairsStairs 17 04-Jun-12 A 30-Jun-12 A 09-Sep-12 06-Oct-12 13-Dec-12 01-Apr-13 0% 100%Stairs 1Stairs 1 6 04-Jun-12 A 10-Jun-12 A 09-Sep-12 15-Sep-12 13-Dec-12 19-Dec-12 0% 100%A11290 Stairs RC Works (Ground to 1st floor) 6 04-Jun-12 A 10-Jun-12 A 09-Sep-12 15-Sep-12 13-Dec-12 19-Dec-12 78 0% 100%
Stairs 2Stairs 2 6 04-Jun-12 A 09-Jun-12 A 16-Sep-12 22-Sep-12 04-Feb-13 10-Feb-13 0% 100%A11300 Stairs RC Works (Ground to 1st floor) 6 04-Jun-12 A 09-Jun-12 A 16-Sep-12 22-Sep-12 04-Feb-13 10-Feb-13 115 0% 100%
Stairs 3Stairs 3 6 18-Jun-12 A 30-Jun-12 A 23-Sep-12 29-Sep-12 19-Mar-13 25-Mar-13 0% 100%A11310 Stairs RC Works (Ground to 1st floor) 6 18-Jun-12 A 30-Jun-12 A 23-Sep-12 29-Sep-12 19-Mar-13 25-Mar-13 146 0% 100%
Stairs 4Stairs 4 6 18-Jun-12 A 30-Jun-12 A 30-Sep-12 06-Oct-12 26-Mar-13 01-Apr-13 0% 100%A109210 Stairs RC Works (Ground to 1st floor) 6 18-Jun-12 A 30-Jun-12 A 30-Sep-12 06-Oct-12 26-Mar-13 01-Apr-13 146 0% 100%
2nd Floor Sl2nd Floor Slab 9 24-Jun-12 A 08-Jul-12 19 19-Jul-12 29-Jul-12 19-Jul-12 29-Jul-12 0% 30%
Walls and CWalls and Columns 9 24-Jun-12 A 08-Jul-12 19 19-Jul-12 29-Jul-12 19-Jul-12 29-Jul-12 0% 30%A10570 Core Wall RC Works 6 24-Jun-12 A 07-Jul-12 19 21-Jul-12 26-Jul-12 21-Jul-12 26-Jul-12 0 0% 30%
A10580 Columns RC Works 9 24-Jun-12 A 08-Jul-12 19 19-Jul-12 29-Jul-12 19-Jul-12 29-Jul-12 0 0% 30%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
ab Curing for Slab
or)
or)
or)
or)
rks Core Wall RC Works
rks Columns RC Works
rk Strike Formwork
b Curing for Slab
r)
r)
ks Core Wall RC Works
ks Columns RC Works
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 13 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
ArchitecturaArchitectural & MEP Package 23 11-Jun-12 A 07-Nov-12 74 14-Jun-12 03-Nov-12 14-Aug-12 05-Feb-13 9.75% 55.53%
Hotel AparteHotel Apartements (Block A) 23 11-Jun-12 A 07-Nov-12 45 14-Jun-12 01-Nov-12 14-Aug-12 31-Dec-12 11.17% 49.03%
2nd Basemen2nd Basement Floor 13 11-Jun-12 A 07-Nov-12 34 19-Jul-12 14-Oct-12 22-Oct-12 18-Dec-12 0% 80.95%
Public AreaPublic Area 13 11-Jun-12 A 07-Nov-12 34 19-Jul-12 14-Oct-12 22-Oct-12 18-Dec-12 0% 80.95%Lift LobbyLift Lobby 12 11-Jun-12 A 07-Nov-12 34 19-Jul-12 14-Oct-12 22-Oct-12 18-Dec-12 0% 81.33%Finishing Finishing Works 12 11-Jun-12 A 07-Nov-12 34 19-Jul-12 14-Oct-12 22-Oct-12 18-Dec-12 0% 81.33%Wet WorWet Works 12 11-Jun-12 A 07-Nov-12 34 19-Jul-12 14-Oct-12 22-Oct-12 18-Dec-12 0% 81.33%A48140 Block Works 4 11-Jun-12 A 28-Jun-12 A 19-Jul-12 23-Jul-12 22-Oct-12 28-Oct-12 79 0% 100%
A48090 Plaster Works 7 18-Jun-12 A 07-Nov-12 34 07-Oct-12 14-Oct-12 11-Dec-12 18-Dec-12 52 0% 60%GSM RoomGSM Rooms 13 11-Jun-12 A 01-Nov-12 34 24-Jul-12 30-Sep-12 29-Oct-12 04-Dec-12 0% 82.22%Finishing Finishing Works 13 11-Jun-12 A 01-Nov-12 34 24-Jul-12 30-Sep-12 29-Oct-12 04-Dec-12 0% 82.22%Wet WorWet Works 13 11-Jun-12 A 01-Nov-12 34 24-Jul-12 30-Sep-12 29-Oct-12 04-Dec-12 0% 82.22%A47420 Block Works 5 11-Jun-12 A 28-Jun-12 A 24-Jul-12 29-Jul-12 29-Oct-12 03-Nov-12 79 0% 100%
A47370 Plaster Works 8 18-Jun-12 A 01-Nov-12 34 22-Sep-12 30-Sep-12 25-Nov-12 04-Dec-12 52 0% 60%MechanicaMechanical Rooms 10 11-Jun-12 A 04-Nov-12 34 30-Jul-12 06-Oct-12 04-Nov-12 10-Dec-12 0% 77.78%Finishing Finishing Works 10 11-Jun-12 A 04-Nov-12 34 30-Jul-12 06-Oct-12 04-Nov-12 10-Dec-12 0% 77.78%Wet WorWet Works 10 11-Jun-12 A 04-Nov-12 34 30-Jul-12 06-Oct-12 04-Nov-12 10-Dec-12 0% 77.78%A47230 Block Works 2 11-Jun-12 A 28-Jun-12 A 30-Jul-12 31-Jul-12 04-Nov-12 05-Nov-12 79 0% 100%
A47180 Plaster Works 5 18-Jun-12 A 04-Nov-12 34 01-Oct-12 06-Oct-12 05-Dec-12 10-Dec-12 52 0% 60%
1st Basemen1st Basement Floor 6 20-Jun-12 A 31-Jul-12 48 14-Jun-12 18-Jul-12 14-Aug-12 27-Sep-12 44.83% 90%
Public AreaPublic Area 6 20-Jun-12 A 31-Jul-12 48 14-Jun-12 18-Jul-12 14-Aug-12 27-Sep-12 44.83% 90%Genset RoGenset Room 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 0% 90%Finishing Finishing Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 0% 90%Wet WorWet Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 0% 90%A49500 Block Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 54 0% 90%
BMS RoomBMS Room 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 0% 90%Finishing Finishing Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 0% 90%Wet WorWet Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 0% 90%A49690 Block Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 55 0% 90%
CBS RoomCBS Room 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 0% 90%Finishing Finishing Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 0% 90%Wet WorWet Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 0% 90%A48470 Block Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 55 0% 90%
ELV RoomELV Room 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%Finishing Finishing Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%Wet WorWet Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%A49310 Block Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 56 0% 90%
MechanicaMechanical Rooms 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%Finishing Finishing Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%Wet WorWet Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%A49970 Block Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 59 0% 90%
LV Room (LV Room (Block A) 4 20-Jun-12 A 30-Jul-12 29 28-Jun-12 02-Jul-12 30-Aug-12 03-Sep-12 50% 90%Finishing Finishing Works 4 20-Jun-12 A 30-Jul-12 29 28-Jun-12 02-Jul-12 30-Aug-12 03-Sep-12 50% 90%Wet WorWet Works 4 20-Jun-12 A 30-Jul-12 29 28-Jun-12 02-Jul-12 30-Aug-12 03-Sep-12 50% 90%A48640 Block Works 4 20-Jun-12 A 30-Jul-12 29 28-Jun-12 02-Jul-12 30-Aug-12 03-Sep-12 52 50% 90%
Sub-StatioSub-Station 1 6 20-Jun-12 A 30-Jul-12 24 21-Jun-12 27-Jun-12 22-Aug-12 28-Aug-12 100% 90%Finishing Finishing Works 6 20-Jun-12 A 30-Jul-12 24 21-Jun-12 27-Jun-12 22-Aug-12 28-Aug-12 100% 90%Wet WorWet Works 6 20-Jun-12 A 30-Jul-12 24 21-Jun-12 27-Jun-12 22-Aug-12 28-Aug-12 100% 90%A48810 Block Works 6 20-Jun-12 A 30-Jul-12 24 21-Jun-12 27-Jun-12 22-Aug-12 28-Aug-12 51 100% 90%
House keeHouse keeping Room 5 20-Jun-12 A 29-Jul-12 21 14-Jun-12 20-Jun-12 14-Aug-12 21-Aug-12 100% 90%Finishing Finishing Works 5 20-Jun-12 A 29-Jul-12 21 14-Jun-12 20-Jun-12 14-Aug-12 21-Aug-12 100% 90%Wet WorWet Works 5 20-Jun-12 A 29-Jul-12 21 14-Jun-12 20-Jun-12 14-Aug-12 21-Aug-12 100% 90%A49040 Block Works 5 20-Jun-12 A 29-Jul-12 21 14-Jun-12 20-Jun-12 14-Aug-12 21-Aug-12 51 100% 90%
Ground FloorGround Floor 13 24-Jun-12 A 13-Oct-12 64 08-Sep-12 01-Nov-12 06-Nov-12 31-Dec-12 0% 30%
Public AreaPublic Area 13 24-Jun-12 A 13-Oct-12 64 08-Sep-12 01-Nov-12 06-Nov-12 31-Dec-12 0% 30%Retail 1Retail 1 13 24-Jun-12 A 13-Oct-12 64 16-Oct-12 01-Nov-12 17-Dec-12 31-Dec-12 0% 30%Finishing Finishing Works 13 24-Jun-12 A 13-Oct-12 64 16-Oct-12 01-Nov-12 17-Dec-12 31-Dec-12 0% 30%Wet WorWet Works 13 24-Jun-12 A 13-Oct-12 64 16-Oct-12 01-Nov-12 17-Dec-12 31-Dec-12 0% 30%A53150 Block Works 13 24-Jun-12 A 13-Oct-12 64 16-Oct-12 01-Nov-12 17-Dec-12 31-Dec-12 49 0% 30%
Retail 2Retail 2 13 24-Jun-12 A 02-Oct-12 64 01-Oct-12 15-Oct-12 01-Dec-12 16-Dec-12 0% 30%Finishing Finishing Works 13 24-Jun-12 A 02-Oct-12 64 01-Oct-12 15-Oct-12 01-Dec-12 16-Dec-12 0% 30%Wet WorWet Works 13 24-Jun-12 A 02-Oct-12 64 01-Oct-12 15-Oct-12 01-Dec-12 16-Dec-12 0% 30%A53550 Block Works 13 24-Jun-12 A 02-Oct-12 64 01-Oct-12 15-Oct-12 01-Dec-12 16-Dec-12 49 0% 30%
Enterance Enterance & Lift Lobby 5 24-Jun-12 A 22-Sep-12 58 25-Sep-12 30-Sep-12 25-Nov-12 29-Nov-12 0% 30%Finishing Finishing Works 5 24-Jun-12 A 22-Sep-12 58 25-Sep-12 30-Sep-12 25-Nov-12 29-Nov-12 0% 30%Wet WorWet Works 5 24-Jun-12 A 22-Sep-12 58 25-Sep-12 30-Sep-12 25-Nov-12 29-Nov-12 0% 30%A50750 Block Works 5 24-Jun-12 A 22-Sep-12 58 25-Sep-12 30-Sep-12 25-Nov-12 29-Nov-12 49 0% 30%
Electrical -Electrical -Telephone Room 3 24-Jun-12 A 17-Sep-12 58 22-Sep-12 24-Sep-12 21-Nov-12 24-Nov-12 0% 30%Finishing Finishing Works 3 24-Jun-12 A 17-Sep-12 58 22-Sep-12 24-Sep-12 21-Nov-12 24-Nov-12 0% 30%Wet WorWet Works 3 24-Jun-12 A 17-Sep-12 58 22-Sep-12 24-Sep-12 21-Nov-12 24-Nov-12 0% 30%A51610 Block Works 3 24-Jun-12 A 17-Sep-12 58 22-Sep-12 24-Sep-12 21-Nov-12 24-Nov-12 49 0% 30%
Main GarbMain Garbage Room 3 24-Jun-12 A 08-Sep-12 58 08-Sep-12 10-Sep-12 06-Nov-12 08-Nov-12 0% 30%Finishing Finishing Works 3 24-Jun-12 A 08-Sep-12 58 08-Sep-12 10-Sep-12 06-Nov-12 08-Nov-12 0% 30%Wet WorWet Works 3 24-Jun-12 A 08-Sep-12 58 08-Sep-12 10-Sep-12 06-Nov-12 08-Nov-12 0% 30%A51180 Block Works 3 24-Jun-12 A 08-Sep-12 58 08-Sep-12 10-Sep-12 06-Nov-12 08-Nov-12 49 0% 30%
ToiletsToilets 5 24-Jun-12 A 11-Sep-12 58 11-Sep-12 16-Sep-12 10-Nov-12 14-Nov-12 0% 30%Finishing Finishing Works 5 24-Jun-12 A 11-Sep-12 58 11-Sep-12 16-Sep-12 10-Nov-12 14-Nov-12 0% 30%Wet WorWet Works 5 24-Jun-12 A 11-Sep-12 58 11-Sep-12 16-Sep-12 10-Nov-12 14-Nov-12 0% 30%A51870 Block Works 5 24-Jun-12 A 11-Sep-12 58 11-Sep-12 16-Sep-12 10-Nov-12 14-Nov-12 49 0% 30%
OfficeOffice 2 24-Jun-12 A 13-Sep-12 58 17-Sep-12 18-Sep-12 17-Nov-12 18-Nov-12 0% 30%Finishing Finishing Works 2 24-Jun-12 A 13-Sep-12 58 17-Sep-12 18-Sep-12 17-Nov-12 18-Nov-12 0% 30%Wet WorWet Works 2 24-Jun-12 A 13-Sep-12 58 17-Sep-12 18-Sep-12 17-Nov-12 18-Nov-12 0% 30%A52400 Block Works 2 24-Jun-12 A 13-Sep-12 58 17-Sep-12 18-Sep-12 17-Nov-12 18-Nov-12 49 0% 30%
Luggae StoLuggae Storage 2 24-Jun-12 A 15-Sep-12 58 19-Sep-12 20-Sep-12 19-Nov-12 20-Nov-12 0% 30%Finishing Finishing Works 2 24-Jun-12 A 15-Sep-12 58 19-Sep-12 20-Sep-12 19-Nov-12 20-Nov-12 0% 30%Wet WorWet Works 2 24-Jun-12 A 15-Sep-12 58 19-Sep-12 20-Sep-12 19-Nov-12 20-Nov-12 0% 30%A52830 Block Works 2 24-Jun-12 A 15-Sep-12 58 19-Sep-12 20-Sep-12 19-Nov-12 20-Nov-12 49 0% 30%
1st Floor1st Floor 3 24-Jun-12 A 30-Aug-12 42 26-Aug-12 01-Sep-12 11-Oct-12 17-Oct-12 0% 10%
Public AreaPublic Area 3 24-Jun-12 A 30-Aug-12 42 26-Aug-12 01-Sep-12 11-Oct-12 17-Oct-12 0% 10%Garbage RGarbage Room 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%Finishing Finishing Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%Wet WorWet Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%A14500 Block Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 40 0% 10%
Corridor &Corridor & Lift Lobby 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%Finishing Finishing Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%Wet WorWet Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%A9810 Block Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 40 0% 10%
Hotel (BlockHotel (Block B) 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%
2nd Basemen2nd Basement Floor 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%
Public AreaPublic Area 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%Boiler RooBoiler Room 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%Finishing Finishing Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%Wet WorWet Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%A54270 Block Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 77 0% 100%
GSM RoomGSM Rooms 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%Finishing Finishing Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%Wet WorWet Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%A54500 Block Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 69 0% 100%
MechanicaMechanical Room 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%Finishing Finishing Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%Wet WorWet Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%A105090 Block Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 69 0% 100%
Residential Residential Apartments (Block C) 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
2nd Basemen2nd Basement Floor 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
Public AreaPublic Area 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
ks Plaster Works
s
ks Plaster Works
s
ks Plaster Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
s
s
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 14 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Lift LobbyLift Lobby 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%Finishing Finishing Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%Wet WorWet Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%A67580 Block Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 73 0% 100%
MechanicaMechanical Rooms 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%Finishing Finishing Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%Wet WorWet Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%A67170 Block Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 73 0% 100%
Pump RooPump Room 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%Finishing Finishing Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%Wet WorWet Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%A67310 Block Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 73 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
s
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 15 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Completed & In Progress Tasks
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.2 PACKAGES PLANNED VS ACTUAL PERCENTAGES
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Al MuraqqAl Muraqqabat Mixed Use Development 597 06-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 12.78% 13.54%
GeneralGeneral 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 31.32% 21.51%
Contractual Contractual Milestones 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 0% 0%
Control MileControl Milestones 381 31-Jul-12 05-Nov-13 -23 30-Jul-12 21-Aug-13 18-Nov-12 05-Oct-13 0% 0%
Authorities AAuthorities Approvals 477 15-Feb-12 A 07-Sep-13 -18 15-Feb-12 23-Jun-13 15-Feb-12 17-Aug-13 32.56% 12.7%
SwimmimngSwimmimng Pool 32 01-Jul-12 06-Aug-12 98 30-Jul-12 05-Dec-12 30-Jul-12 05-Dec-12 0% 0%
Temporary PTemporary Power Connection 429 15-Feb-12 A 11-Jul-13 -64 15-Feb-12 27-Apr-13 15-Feb-12 27-Apr-13 52.09% 20.32%
OthersOthers 341 25-Jul-12 07-Sep-13 -18 01-Jul-12 23-Jun-13 29-Aug-12 17-Aug-13 0% 0%
Utilities ConUtilities Connection 216 18-Feb-13 03-Nov-13 -64 09-Mar-13 17-Aug-13 21-Apr-13 17-Aug-13 0% 0%
Client SubmClient Submissions 205 10-Jun-12 A 13-Feb-13 21 28-May-12 13-Feb-13 28-May-12 10-Mar-13 0% 0%
MobilizationMobilization 403 15-Feb-12 A 10-Jun-13 -9 15-Feb-12 30-Apr-13 10-Mar-12 29-May-13 62.35% 62.35%
Project SiteProject Site 15 15-Feb-12 A 07-Jun-12 A 15-Feb-12 03-Mar-12 10-Mar-12 07-Apr-12 100% 100%
Tower CraneTower Cranes 400 19-Feb-12 A 10-Jun-13 -9 15-Mar-12 30-Apr-13 03-Apr-12 29-May-13 42.86% 42.86%
PreliminariesPreliminaries 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0% 0%
ASGC SubmASGC Submissions 224 20-Dec-12 11-Sep-13 -27 31-Dec-12 27-Jun-13 27-Apr-13 11-Aug-13 0% 0%
Access to SAccess to Sub-Contractors 167 30-Jul-12 18-Feb-13 50 27-Jun-12 21-Feb-13 28-Aug-12 18-Apr-13 0% 0%
EngineerinEngineering 432 06-Feb-12 A 14-Jul-13 45 15-Feb-12 20-Aug-13 15-Feb-12 05-Sep-13 53.22% 37.7%
Shop DrawinShop Drawings 432 06-Feb-12 A 14-Jul-13 45 15-Feb-12 20-Aug-13 15-Feb-12 05-Sep-13 54.4% 38.06%
CivilCivil 242 06-Feb-12 A 29-Nov-12 179 15-Feb-12 22-Jan-13 15-Feb-12 01-Jul-13 43.56% 75.39%
GeneralGeneral 25 15-Feb-12 A 22-Mar-12 A 15-Feb-12 14-Mar-12 15-Feb-12 02-Apr-12 100% 100%
Hotel ApartemHotel Apartements (Block A) 197 15-Feb-12 A 04-Oct-12 139 15-Feb-12 21-Oct-12 16-Feb-12 21-Mar-13 52.89% 79.55%
Hotel (Block Hotel (Block B) 242 06-Feb-12 A 29-Nov-12 179 15-Feb-12 22-Jan-13 23-Feb-12 01-Jul-13 34.73% 73.72%
Residentail (BResidentail (Block C) 232 15-Feb-12 A 18-Nov-12 189 15-Feb-12 02-Jan-13 26-Feb-12 01-Jul-13 37.68% 70.55%
ArchitecturalArchitectural 395 29-Mar-12 A 14-Jul-13 45 07-May-12 20-Aug-13 07-May-12 05-Sep-13 2.09% 4.47%
Hotel ApartemHotel Apartements (Block A) 395 29-Mar-12 A 14-Jul-13 45 07-May-12 07-Aug-13 07-May-12 05-Sep-13 3.33% 6.1%
Hotel (Block Hotel (Block B) 360 12-Apr-12 A 17-Jun-13 68 19-May-12 13-Aug-13 28-May-12 05-Sep-13 1.43% 3.91%
Residential AResidential Apartments (Block C) 375 12-Apr-12 A 04-Jul-13 53 19-May-12 20-Aug-13 19-May-12 05-Sep-13 1.35% 3.19%
MEPMEP 170 08-Feb-12 A 03-Sep-12 215 15-Feb-12 30-Aug-12 15-Feb-12 19-May-13 83.35% 46.55%
Hotel ApartemHotel Apartements (Block A) 167 11-Feb-12 A 30-Aug-12 203 15-Feb-12 30-Aug-12 16-Feb-12 01-May-13 83.76% 55.43%
Hotel (Block Hotel (Block B) 170 08-Feb-12 A 03-Sep-12 215 15-Feb-12 30-Aug-12 15-Feb-12 19-May-13 83.18% 39.86%
Residential AResidential Apartments (Block C) 167 09-Feb-12 A 30-Aug-12 204 15-Feb-12 30-Aug-12 15-Feb-12 02-May-13 83.12% 44.92%
Speciality WSpeciality Works 279 17-Mar-12 A 14-Feb-13 125 18-Jun-12 03-Apr-13 11-Jul-12 11-Jul-13 1.51% 9.9%
Swimming PoSwimming Pool 106 17-Mar-12 A 18-Jul-12 209 22-Sep-12 20-Nov-12 05-Feb-13 28-Mar-13 0% 46.15%
External FacaExternal Facade 134 05-Sep-12 14-Feb-13 107 03-Oct-12 14-Mar-13 17-Nov-12 20-Jun-13 0% 0%
Facade CleanFacade Cleaning 31 08-Jan-13 13-Feb-13 126 27-Feb-13 03-Apr-13 05-Jun-13 11-Jul-13 0% 0%
Garbage ChuGarbage Chute 141 21-Aug-12 07-Feb-13 -30 18-Jun-12 06-Dec-12 11-Jul-12 02-Jan-13 12.64% 0%
Linen ChuteLinen Chute 31 13-Sep-12 18-Oct-12 60 15-Aug-12 23-Sep-12 25-Nov-12 02-Jan-13 0% 0%
Provisional Provisional Sum 243 01-Jul-12 18-Apr-13 21 24-Jun-12 18-Apr-13 24-Jun-12 13-May-13 7.06% 0%
Kitchen EquiKitchen Equipments 37 01-Jul-12 12-Aug-12 -6 24-Jun-12 05-Aug-12 24-Jun-12 05-Aug-12 17.65% 0%
Lundary EquLundary Equipments 37 01-Jul-12 12-Aug-12 -6 24-Jun-12 05-Aug-12 24-Jun-12 05-Aug-12 17.65% 0%
Facade LightFacade Lighting 38 16-Aug-12 01-Oct-12 5 16-Aug-12 01-Oct-12 25-Aug-12 07-Oct-12 0% 0%
Cooking StatCooking Station 38 25-Jul-12 09-Sep-12 71 09-Jul-12 22-Aug-12 20-Oct-12 05-Dec-12 0% 0%
Gymnasium EGymnasium Equipments 34 11-Mar-13 18-Apr-13 21 11-Mar-13 18-Apr-13 04-Apr-13 13-May-13 0% 0%
Method 0f SMethod 0f Statements 310 15-Feb-12 A 20-Feb-13 121 15-Feb-12 21-Mar-13 21-Feb-12 13-Jul-13 28.18% 30.08%
ProcuremeProcurement 441 09-Feb-12 A 24-Jul-13 19 15-Feb-12 24-Jul-13 15-Feb-12 17-Aug-13 29.69% 10.28%
Submittion &Submittion & Approval of Prequalification 325 15-Feb-12 A 10-Mar-13 21 15-Feb-12 10-Mar-13 15-Feb-12 03-Apr-13 70.03% 69.29%
Domestic SuDomestic Sub Contractors 165 15-Feb-12 A 28-Aug-12 77 15-Feb-12 28-Aug-12 15-Feb-12 26-Nov-12 73.55% 75.45%
Nominated SNominated Sub Contractors 225 10-Jun-12 A 10-Mar-13 21 29-May-12 10-Mar-13 29-May-12 03-Apr-13 53.33% 40%
Kitchen EquiKitchen Equipments 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 100% 100%
Lundary EquLundary Equipments 21 10-Jun-12 A 10-Jun-12 A 29-May-12 23-Jun-12 29-May-12 23-Jun-12 100% 100%
Facade LightFacade Lighting 21 23-Jul-12 15-Aug-12 5 23-Jul-12 15-Aug-12 29-Jul-12 23-Aug-12 0% 0%
Cooking StatCooking Station 21 01-Jul-12 24-Jul-12 72 13-Jun-12 08-Jul-12 25-Sep-12 18-Oct-12 66.67% 0%
Gymnasium EGymnasium Equipments 21 14-Feb-13 10-Mar-13 21 14-Feb-13 10-Mar-13 11-Mar-13 03-Apr-13 0% 0%
Submittion &Submittion & Approval of Material Submittal 346 09-Feb-12 A 03-Apr-13 34 15-Feb-12 03-Apr-13 19-Feb-12 13-May-13 62.77% 32.45%
CivilCivil 186 12-Feb-12 A 22-Sep-12 73 15-Feb-12 22-Sep-12 19-Feb-12 20-Dec-12 80% 41.43%
ArchitecturalArchitectural 321 15-Feb-12 A 05-Mar-13 19 04-Mar-12 05-Mar-13 24-May-12 27-Mar-13 51.68% 9.91%
Wet WorksWet Works 100 15-Feb-12 A 12-Jul-12 38 04-Mar-12 25-Apr-12 14-Jun-12 27-Aug-12 100% 83.33%
CeilingCeiling 21 05-Jul-12 29-Jul-12 -35 27-Mar-12 19-Apr-12 24-May-12 18-Jun-12 100% 0%
Walls & FlooWalls & Floors 199 12-May-12 A 07-Jan-13 4 24-May-12 07-Jan-13 18-Jun-12 12-Jan-13 60.54% 4.76%
Doors & WinDoors & Windows 71 20-Jun-12 A 12-Sep-12 72 10-Mar-12 12-Sep-12 06-Sep-12 10-Dec-12 66.67% 16.67%
MetalMetal 21 01-Jul-12 24-Jul-12 123 19-May-12 05-Jul-12 30-May-12 22-Dec-12 88.1% 0%
FurnitureFurniture 71 11-Dec-12 05-Mar-13 19 11-Dec-12 05-Mar-13 03-Jan-13 27-Mar-13 0% 0%
Soft LandscpSoft Landscping 21 01-Jul-12 24-Jul-12 110 11-Jul-12 29-Aug-12 22-Aug-12 06-Dec-12 0% 0%
OthersOthers 125 01-Jul-12 28-Nov-12 59 05-Jun-12 28-Nov-12 02-Aug-12 09-Feb-13 11.86% 0%
MechanicalMechanical 212 09-Feb-12 A 22-Oct-12 68 21-Feb-12 29-Sep-12 01-Mar-12 15-Jan-13 76.81% 50%
HVACHVAC 186 19-Feb-12 A 27-Sep-12 55 21-Feb-12 27-Sep-12 01-Mar-12 05-Dec-12 71.24% 54.72%
PlumbingPlumbing 187 09-Feb-12 A 23-Sep-12 93 17-Mar-12 23-Sep-12 19-Jul-12 15-Jan-13 74.6% 16.67%
Fire FighitngFire Fighitng 132 29-Mar-12 A 04-Aug-12 109 17-Mar-12 19-Jun-12 27-May-12 16-Dec-12 100% 75.36%
LPG SystemLPG System 127 24-May-12 A 22-Oct-12 68 14-May-12 29-Sep-12 20-Oct-12 15-Jan-13 33.33% 66.67%
Coveying SysCoveying System 21 22-Mar-12 A 12-Jul-12 26 13-May-12 05-Jun-12 06-Jun-12 11-Aug-12 100% 50%
ElectricalElectrical 250 15-Feb-12 A 10-Dec-12 4 15-Feb-12 22-Sep-12 26-Feb-12 15-Dec-12 66.82% 50.24%
Cable Trays -Cable Trays - Cables 174 14-May-12 A 10-Dec-12 -64 22-Mar-12 22-Sep-12 11-Jul-12 22-Sep-12 48.15% 48.15%
Low Current Low Current Systems 113 03-Mar-12 A 21-Jul-12 83 17-Mar-12 25-Apr-12 02-Jun-12 29-Oct-12 100% 58.33%
Electrical EquElectrical Equipments 95 19-Apr-12 A 19-Nov-12 22 17-Mar-12 22-Sep-12 22-Jul-12 15-Dec-12 54.55% 46.97%
OthersOthers 155 15-Feb-12 A 14-Aug-12 65 15-Feb-12 14-Aug-12 26-Feb-12 21-Oct-12 38.6% 38.6%
Speciality WSpeciality Works 100 14-Mar-12 A 18-Aug-12 163 01-May-12 10-Sep-12 11-Jun-12 05-Mar-13 53.71% 14.84%
Swimming PoSwimming Pool 24 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 09-Aug-12 12-Dec-12 0% 50%
Garbage ChuGarbage Chute System 40 03-Jul-12 18-Aug-12 17 01-May-12 16-Jun-12 11-Jun-12 09-Sep-12 100% 0%
Linen Chute Linen Chute System 40 03-Jul-12 18-Aug-12 -9 05-Jun-12 22-Jul-12 14-Jun-12 07-Aug-12 70.79% 0%
Facade CleanFacade Cleaning System 21 01-Jul-12 24-Jul-12 184 15-Aug-12 10-Sep-12 10-Feb-13 05-Mar-13 0% 0%
Provisional Provisional Sum 230 01-Jul-12 03-Apr-13 34 24-Jun-12 03-Apr-13 12-Jul-12 13-May-13 11.43% 0%
Kitchen EquiKitchen Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 28.57% 0%
Laundary EqLaundary Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 28.57% 0%
Facade LightFacade Lighting 21 16-Aug-12 11-Sep-12 22 16-Aug-12 11-Sep-12 13-Sep-12 07-Oct-12 0% 0%
Cooking StatCooking Station 21 25-Jul-12 18-Aug-12 88 09-Jul-12 01-Aug-12 10-Nov-12 05-Dec-12 0% 0%
Gymnasium EGymnasium Equipments 21 11-Mar-13 03-Apr-13 34 11-Mar-13 03-Apr-13 20-Apr-13 13-May-13 0% 0%
ProcuremenProcurement and Delivery 441 15-Feb-12 A 24-Jul-13 19 18-Feb-12 24-Jul-13 21-Feb-12 17-Aug-13 19.56% 1.95%
CivilCivil 276 15-Feb-12 A 10-Jan-13 73 18-Feb-12 10-Jan-13 21-Feb-12 07-Apr-13 10.02% 4.53%
ArchitecturalArchitectural 341 11-Jun-12 A 24-Jul-13 19 28-Mar-12 24-Jul-13 25-Jun-12 17-Aug-13 10.88% 0.45%
Wet WorksWet Works 87 11-Jun-12 A 23-Sep-12 38 28-Mar-12 18-Jun-12 10-Jul-12 07-Nov-12 100% 17.5%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 1 of 3Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Percentage Wise
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
CeilingCeiling 135 01-Jul-12 11-Dec-12 63 07-May-12 14-Nov-12 12-Jul-12 25-Feb-13 28.44% 0%
Walls & FlooWalls & Floors 255 01-Jul-12 02-May-13 6 30-May-12 02-May-13 12-Jul-12 09-May-13 3.33% 0%
Doors & WinDoors & Windows 148 12-Jul-12 09-Jan-13 66 03-Apr-12 29-Dec-12 02-Oct-12 27-Mar-13 35.35% 0%
MetalMetal 120 25-Jul-12 18-Dec-12 123 12-Jun-12 28-Nov-12 25-Jun-12 13-May-13 6.25% 0%
FurnitureFurniture 170 06-Jan-13 24-Jul-13 19 06-Jan-13 24-Jul-13 29-Jan-13 17-Aug-13 0% 0%
Soft LandscpSoft Landscping 110 25-Jul-12 06-Dec-12 110 05-Aug-12 10-Jan-13 16-Sep-12 16-Apr-13 0% 0%
OthersOthers 205 01-Jul-12 05-Mar-13 59 30-Jul-12 05-Mar-13 12-Sep-12 13-May-13 0% 0%
MechanicalMechanical 300 06-Mar-12 A 28-Feb-13 28 10-Apr-12 22-Jan-13 19-Apr-12 01-Apr-13 38.67% 4.1%
HVACHVAC 232 16-Apr-12 A 23-Jan-13 34 10-Apr-12 16-Jan-13 19-Apr-12 05-Mar-13 41.5% 9.61%
PlumbingPlumbing 260 06-Mar-12 A 12-Jan-13 67 10-Apr-12 12-Jan-13 13-Aug-12 01-Apr-13 34.43% 0.17%
Fire FighitngFire Fighitng 154 02-Jun-12 A 05-Dec-12 69 10-Apr-12 23-Sep-12 21-Jun-12 26-Feb-13 51.59% 0%
LPG SystemLPG System 176 01-Jul-12 30-Jan-13 23 07-Jun-12 18-Nov-12 17-Nov-12 26-Feb-13 11.18% 0%
Coveying SysCoveying System 190 12-Jul-12 28-Feb-13 26 06-Jun-12 22-Jan-13 02-Jul-12 30-Mar-13 9.09% 0%
ElectricalElectrical 354 19-Feb-12 A 16-Apr-13 -20 18-Feb-12 04-Feb-13 28-Feb-12 24-Mar-13 25.85% 3.38%
Cable Trays -Cable Trays - Cables 253 07-Jun-12 A 08-Apr-13 -64 26-Apr-12 22-Jan-13 23-Aug-12 22-Jan-13 38.3% 0%
Low Current Low Current Systems 140 21-Jul-12 08-Jan-13 50 26-Apr-12 09-Oct-12 02-Aug-12 07-Mar-13 41.84% 0%
Electrical EquElectrical Equipments 214 01-Aug-12 16-Apr-13 -20 12-Jun-12 04-Feb-13 08-Sep-12 24-Mar-13 2.08% 0%
OthersOthers 222 19-Feb-12 A 08-Nov-12 56 18-Feb-12 08-Nov-12 28-Feb-12 16-Jan-13 61.11% 30.56%
Speciality WSpeciality Works 220 12-Jul-12 03-Apr-13 85 26-May-12 07-Mar-13 29-Jul-12 13-Jul-13 4.48% 0%
Swimming PoSwimming Pool 120 12-Jul-12 06-Dec-12 118 05-Aug-12 29-Dec-12 05-Sep-12 24-Apr-13 0% 0%
External FacaExternal Facade 185 12-Jul-12 21-Feb-13 53 19-Jun-12 21-Feb-13 01-Oct-12 24-Apr-13 5% 0%
Facade CleanFacade Cleaning 110 25-Jul-12 06-Dec-12 184 11-Sep-12 22-Jan-13 06-Mar-13 13-Jul-13 0% 0%
Garbage ChuGarbage Chute 169 28-Jul-12 18-Feb-13 17 26-May-12 16-Dec-12 29-Jul-12 10-Mar-13 16% 0%
Linen ChuteLinen Chute 188 21-Aug-12 03-Apr-13 -4 23-Jul-12 07-Mar-13 08-Aug-12 30-Mar-13 0% 0%
Provisional Provisional Sum 286 13-Aug-12 22-Jul-13 21 06-Aug-12 22-Jul-13 06-Aug-12 17-Aug-13 0% 0%
Kitchen EquiKitchen Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0% 0%
Lundary EquLundary Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0% 0%
Facade LightFacade Lighting 50 02-Oct-12 03-Dec-12 5 02-Oct-12 03-Dec-12 08-Oct-12 09-Dec-12 0% 0%
Cooking StatCooking Station 120 10-Sep-12 03-Feb-13 71 23-Aug-12 15-Jan-13 06-Dec-12 27-Apr-13 0% 0%
Gymnasium EGymnasium Equipments 80 20-Apr-13 22-Jul-13 21 20-Apr-13 22-Jul-13 14-May-13 17-Aug-13 0% 0%
ConstructiConstruction 579 15-Feb-12 A 09-Jan-14 -46 18-Feb-12 27-Oct-13 18-Feb-12 14-Nov-13 10.27% 13.69%
Civil PackagCivil Package 284 15-Feb-12 A 20-Jan-13 147 18-Feb-12 05-Feb-13 18-Feb-12 13-Jul-13 40.66% 54%
Hotel AparteHotel Apartements (Block A) 248 15-Feb-12 A 08-Dec-12 94 18-Feb-12 12-Dec-12 18-Feb-12 28-Mar-13 52.98% 65.38%
Foundation LFoundation Level 13 15-Feb-12 A 28-Feb-12 A 18-Feb-12 11-Mar-12 18-Feb-12 11-Mar-12 100% 100%
1st Basemen1st Basement Floor Slab 108 15-Feb-12 A 07-Jul-12 100 12-Mar-12 30-Jun-12 14-Mar-12 21-Oct-12 100% 99.37%
Ground FloorGround Floor Slab 89 15-Feb-12 A 07-Jul-12 103 14-Apr-12 12-Jul-12 14-Apr-12 24-Oct-12 96.74% 96.34%
1st Floor Slab1st Floor Slab 42 22-Apr-12 A 15-Jun-12 A 08-May-12 05-Aug-12 08-May-12 06-Nov-12 90.44% 100%
2nd Floor Sl2nd Floor Slab 33 16-May-12 A 04-Jul-12 103 04-Jun-12 30-Aug-12 04-Jun-12 13-Nov-12 90.34% 100%
3rd Floor Slab3rd Floor Slab 44 02-Jun-12 A 23-Jul-12 97 02-Jul-12 18-Sep-12 02-Jul-12 21-Nov-12 0% 99.66%
4th Floor Slab4th Floor Slab 41 19-Jun-12 A 01-Sep-12 74 22-Jul-12 04-Oct-12 22-Jul-12 28-Nov-12 0% 93.08%
5th Floor Slab5th Floor Slab 67 05-Jul-12 24-Sep-12 59 09-Aug-12 22-Oct-12 09-Aug-12 06-Dec-12 0% 0%
6th Floor Slab6th Floor Slab 61 29-Jul-12 10-Oct-12 52 29-Aug-12 10-Nov-12 29-Aug-12 15-Dec-12 0% 0%
7th Floor Slab7th Floor Slab 78 16-Aug-12 21-Nov-12 38 17-Sep-12 26-Nov-12 17-Sep-12 06-Jan-13 0% 0%
Roof Floor SlRoof Floor Slab 77 04-Sep-12 08-Dec-12 53 03-Oct-12 12-Dec-12 03-Oct-12 09-Feb-13 0% 0%
Upper Roof LUpper Roof Level 45 11-Oct-12 08-Dec-12 94 17-Oct-12 12-Dec-12 17-Oct-12 28-Mar-13 0% 0%
Hotel (BlockHotel (Block B) 270 15-Feb-12 A 20-Jan-13 147 18-Feb-12 05-Feb-13 18-Feb-12 13-Jul-13 39.84% 55.2%
Foundation LFoundation Level 55 03-Mar-12 A 12-Apr-12 A 18-Feb-12 30-Apr-12 18-Feb-12 30-Apr-12 100% 100%
1st Basemen1st Basement Floor Slab 98 15-Feb-12 A 02-Jul-12 212 09-Apr-12 15-Aug-12 02-May-12 05-Mar-13 95.11% 99.41%
Ground FloorGround Floor Slab 65 15-Feb-12 A 05-Jul-12 135 13-Jun-12 15-Sep-12 13-Jun-12 25-Dec-12 63.05% 98.64%
1st Floor Slab1st Floor Slab 49 29-May-12 A 26-Jul-12 147 11-Jul-12 07-Oct-12 11-Jul-12 21-Feb-13 0% 97.78%
2nd Floor Sl2nd Floor Slab 89 28-Jun-12 A 11-Oct-12 144 06-Aug-12 29-Oct-12 06-Aug-12 04-Apr-13 0% 6.11%
3rd Floor Slab3rd Floor Slab 74 01-Aug-12 30-Oct-12 130 02-Sep-12 14-Nov-12 02-Sep-12 04-Apr-13 0% 0%
4th Floor Slab4th Floor Slab 59 04-Sep-12 13-Nov-12 96 19-Sep-12 29-Nov-12 19-Sep-12 10-Mar-13 0% 0%
5th Floor Slab5th Floor Slab 56 22-Sep-12 28-Nov-12 84 07-Oct-12 15-Dec-12 07-Oct-12 10-Mar-13 0% 0%
6th Floor Slab6th Floor Slab 56 07-Oct-12 15-Dec-12 68 22-Oct-12 30-Dec-12 22-Oct-12 06-Mar-13 0% 0%
7th Floor Slab7th Floor Slab 58 22-Oct-12 02-Jan-13 53 08-Nov-12 22-Jan-13 08-Nov-12 06-Mar-13 0% 0%
Roof Floor SlRoof Floor Slab 59 10-Nov-12 20-Jan-13 147 26-Nov-12 05-Feb-13 26-Nov-12 13-Jul-13 0% 0%
Upper Roof LUpper Roof Level 39 27-Nov-12 13-Jan-13 13 13-Dec-12 29-Jan-13 13-Dec-12 29-Jan-13 0% 0%
Residential Residential Apartments (Block C) 277 15-Feb-12 A 12-Jan-13 154 18-Feb-12 22-Jan-13 12-Mar-12 13-Jul-13 34.37% 46.45%
Foundation LFoundation Level 36 15-Feb-12 A 04-Apr-12 A 18-Feb-12 30-Apr-12 12-Mar-12 30-Apr-12 100% 100%
1st Basemen1st Basement Floor Slab 97 15-Feb-12 A 02-Jul-12 200 10-Mar-12 11-Aug-12 26-Apr-12 02-Mar-13 96.52% 99.99%
Ground FloorGround Floor Slab 77 15-Feb-12 A 04-Jul-12 176 09-Jun-12 28-Aug-12 09-Jun-12 02-Mar-13 86.46% 99.17%
1st Floor Slab1st Floor Slab 62 19-May-12 A 30-Jul-12 189 03-Jul-12 06-Oct-12 03-Jul-12 01-Apr-13 0% 99.98%
2nd Floor Sl2nd Floor Slab 74 24-Jun-12 A 19-Sep-12 151 19-Jul-12 30-Sep-12 19-Jul-12 21-Mar-13 0% 7.83%
3rd Floor Slab3rd Floor Slab 70 14-Jul-12 04-Oct-12 138 05-Aug-12 15-Oct-12 05-Aug-12 21-Mar-13 0% 0%
4th Floor Slab4th Floor Slab 64 13-Aug-12 30-Oct-12 114 26-Aug-12 10-Nov-12 26-Aug-12 17-Mar-13 0% 0%
5th Floor Slab5th Floor Slab 63 01-Sep-12 14-Nov-12 98 11-Sep-12 26-Nov-12 11-Sep-12 13-Mar-13 0% 0%
6th Floor Slab6th Floor Slab 60 22-Sep-12 04-Dec-12 89 02-Oct-12 15-Dec-12 02-Oct-12 20-Mar-13 0% 0%
7th Floor Slab7th Floor Slab 64 08-Oct-12 25-Dec-12 65 18-Oct-12 06-Jan-13 18-Oct-12 13-Mar-13 0% 0%
Roof Floor SlRoof Floor Slab 63 28-Oct-12 12-Jan-13 154 07-Nov-12 22-Jan-13 07-Nov-12 13-Jul-13 0% 0%
Upper Roof LUpper Roof Level 45 19-Nov-12 12-Jan-13 67 29-Nov-12 22-Jan-13 29-Nov-12 01-Apr-13 0% 0%
ArchitecturaArchitectural & MEP Package 479 11-Jun-12 A 09-Jan-14 -46 14-Jun-12 27-Oct-13 14-Aug-12 14-Nov-13 0.03% 0.12%
Hotel AparteHotel Apartements (Block A) 479 11-Jun-12 A 09-Jan-14 -46 14-Jun-12 23-Oct-13 14-Aug-12 14-Nov-13 0.12% 0.32%
2nd Basemen2nd Basement Floor 341 11-Jun-12 A 24-Jul-13 -45 19-Jul-12 09-May-13 22-Oct-12 01-Jun-13 0% 1.76%
1st Basemen1st Basement Floor 334 20-Jun-12 A 24-Jul-13 -45 14-Jun-12 18-May-13 14-Aug-12 01-Jun-13 1.35% 1.63%
Ground FloorGround Floor 469 24-Jun-12 A 09-Jan-14 -46 04-Sep-12 23-Oct-13 06-Nov-12 14-Nov-13 0% 2.05%
1st Floor1st Floor 469 24-Jun-12 A 09-Jan-14 -46 30-Jul-12 23-Oct-13 10-Sep-12 14-Nov-13 0% 0.07%
2nd Floor2nd Floor 439 29-Jul-12 09-Jan-14 -46 01-Sep-12 23-Oct-13 02-Sep-12 14-Nov-13 0% 0%
3rd Floor3rd Floor 431 06-Aug-12 09-Jan-14 -46 22-Sep-12 23-Oct-13 22-Sep-12 14-Nov-13 0% 0%
4th Floor4th Floor 412 30-Aug-12 09-Jan-14 -46 29-Sep-12 23-Oct-13 29-Sep-12 14-Nov-13 0% 0%
5th Floor5th Floor 397 17-Sep-12 09-Jan-14 -46 16-Oct-12 23-Oct-13 16-Oct-12 14-Nov-13 0% 0%
6th Floor6th Floor 383 03-Oct-12 09-Jan-14 -46 04-Nov-12 23-Oct-13 04-Nov-12 14-Nov-13 0% 0%
7th Floor7th Floor 351 13-Nov-12 09-Jan-14 -46 20-Nov-12 23-Oct-13 20-Nov-12 14-Nov-13 0% 0%
Roof LevelRoof Level 369 21-Oct-12 09-Jan-14 -64 29-Oct-12 23-Oct-13 13-Nov-12 23-Oct-13 0% 0%
Upper Roof LUpper Roof Level 361 01-Nov-12 09-Jan-14 -46 07-Nov-12 23-Oct-13 29-Jan-13 14-Nov-13 0% 0%
Hotel (BlockHotel (Block B) 479 11-Jun-12 A 09-Jan-14 -46 09-Aug-12 23-Oct-13 11-Oct-12 14-Nov-13 0% 0.05%
2nd Basemen2nd Basement Floor 333 11-Jun-12 A 15-Jul-13 -33 08-Sep-12 30-Apr-13 05-Dec-12 05-Jun-13 0% 1.16%
1st Basemen1st Basement Floor 295 29-Jul-12 17-Jul-13 -35 09-Aug-12 13-May-13 11-Oct-12 05-Jun-13 0% 0%
Ground FloorGround Floor 438 30-Jul-12 09-Jan-14 -46 17-Sep-12 23-Oct-13 04-Nov-12 14-Nov-13 0% 0%
1st Floor1st Floor 411 02-Sep-12 09-Jan-14 -46 01-Oct-12 23-Oct-13 12-Nov-12 14-Nov-13 0% 0%
2nd Floor2nd Floor 382 06-Oct-12 09-Jan-14 -46 21-Oct-12 23-Oct-13 28-Nov-12 14-Nov-13 0% 0%
3rd Floor3rd Floor 368 22-Oct-12 09-Jan-14 -46 08-Nov-12 23-Oct-13 28-Nov-12 14-Nov-13 0% 0%
4th Floor4th Floor 356 07-Nov-12 09-Jan-14 -46 24-Nov-12 23-Oct-13 17-Dec-12 14-Nov-13 0% 0%
5th Floor5th Floor 344 22-Nov-12 09-Jan-14 -46 09-Dec-12 23-Oct-13 24-Dec-12 14-Nov-13 0% 0%
6th Floor6th Floor 331 09-Dec-12 09-Jan-14 -46 24-Dec-12 23-Oct-13 08-Jan-13 14-Nov-13 0% 0%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 2 of 3Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Percentage Wise
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
7th Floor7th Floor 316 26-Dec-12 09-Jan-14 -46 12-Jan-13 23-Oct-13 12-Jan-13 14-Nov-13 0% 0%
Roof LevelRoof Level 154 13-Dec-12 13-Jun-13 -6 29-Dec-12 07-May-13 29-Dec-12 05-Jun-13 0% 0%
Upper Roof LUpper Roof Level 30 19-Dec-12 23-Jan-13 113 05-Jan-13 09-Feb-13 10-Feb-13 05-Jun-13 0% 0%
Residential Residential Apartments (Block C) 479 11-Jun-12 A 09-Jan-14 -46 05-Aug-12 27-Oct-13 13-Sep-12 14-Nov-13 0% 0.03%
2nd Basemen2nd Basement Floor 351 11-Jun-12 A 05-Aug-13 -64 12-Aug-12 21-May-13 14-Nov-12 21-May-13 0% 1.02%
1st Basemen1st Basement Floor 311 29-Jul-12 05-Aug-13 -64 05-Aug-12 21-May-13 03-Nov-12 21-May-13 0% 0%
Ground FloorGround Floor 254 31-Jul-12 01-Jun-13 -9 05-Sep-12 13-Apr-13 04-Nov-12 21-May-13 0% 0%
1st Floor1st Floor 292 15-Aug-12 31-Jul-13 -60 09-Sep-12 21-May-13 13-Sep-12 21-May-13 0% 0%
2nd Floor2nd Floor 252 13-Sep-12 11-Jul-13 -43 24-Sep-12 21-May-13 24-Sep-12 21-May-13 0% 0%
3rd Floor3rd Floor 231 29-Sep-12 02-Jul-13 -35 09-Oct-12 21-May-13 09-Oct-12 21-May-13 0% 0%
4th Floor4th Floor 202 22-Oct-12 22-Jun-13 -26 04-Nov-12 21-May-13 04-Nov-12 21-May-13 0% 0%
5th Floor5th Floor 175 08-Nov-12 04-Jun-13 -12 20-Nov-12 21-May-13 20-Nov-12 21-May-13 0% 0%
6th Floor6th Floor 160 27-Nov-12 04-Jun-13 -12 09-Dec-12 21-May-13 09-Dec-12 21-May-13 0% 0%
7th Floor7th Floor 125 19-Dec-12 15-May-13 6 30-Dec-12 21-May-13 30-Dec-12 21-May-13 0% 0%
Roof LevelRoof Level 339 28-Nov-12 09-Jan-14 -46 10-Dec-12 27-Oct-13 25-Dec-12 14-Nov-13 0% 0%
Upper Roof LUpper Roof Level 331 09-Dec-12 09-Jan-14 -46 19-Dec-12 23-Oct-13 04-Feb-13 14-Nov-13 0% 0%
Elevators PaElevators Package 199 12-Sep-12 09-May-13 -10 11-Oct-12 28-Apr-13 11-Oct-12 28-Apr-13 0% 0%
External FacExternal Facades Package 214 24-Nov-12 05-Aug-13 5 12-Nov-12 11-Aug-13 21-Jan-13 11-Aug-13 0% 0%
Facade LighFacade Lighting Package 188 04-Dec-12 14-Jul-13 23 10-Dec-12 24-Jul-13 10-Dec-12 11-Aug-13 0% 0%
LPG PackagLPG Package 130 25-Sep-12 02-Mar-13 12 07-Oct-12 10-Mar-13 21-Feb-13 16-Mar-13 0% 0%
Facade CleaFacade Cleaning Package 71 19-Feb-13 12-May-13 77 04-Apr-13 16-May-13 14-Jul-13 11-Aug-13 0% 0%
Garbage & LGarbage & Linen Chute Package 188 27-Nov-12 08-Jul-13 -32 20-Nov-12 30-May-13 23-Dec-12 30-May-13 0% 0%
Handing OHanding Over 481 01-Jul-12 01-Feb-14 -64 10-Jun-12 14-Nov-13 02-Oct-12 14-Nov-13 0% 0%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 3 of 3Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Percentage Wise
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.3 TWO MONTHS LOOKAHEAD PROGRAM
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
Al MuraAl Muraqqabat Mixed Use Development 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 23.29% 5.95%
GeneralGeneral 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 42.55% 18.59%
ContractContractual Milestones 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 0% 0%
A1050 Overall Duration of Phase 1 550 15-Feb-12 A 17-Aug-13 0 15-Feb-12 17-Aug-13 15-Feb-12 17-Aug-13 0 24.91% 24.91%
A1030 Completion Date of Phase 1 0 03-Nov-13* -64 17-Aug-13 17-Aug-13 0 0% 0%
A1020 Overall Duration of Phase 2 411 15-Feb-12 A 15-Nov-13 0 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 0 33.33% 0%
A1010 Completion Date of Phase 2 0 01-Feb-14* -78 15-Nov-13 15-Nov-13 0 0% 0%
Control MControl Milestones 18 31-Jul-12 25-Aug-12 70 30-Jul-12 26-Aug-12 18-Nov-12 18-Nov-12 0% 0%
ArchitecArchitectural Works Milestones 18 31-Jul-12 25-Aug-12 70 30-Jul-12 26-Aug-12 18-Nov-12 18-Nov-12 0% 0%
A9182 Start of Block Works @ Basements 0 31-Jul-12 88 30-Jul-12 18-Nov-12 90 0% 0%
A9183 Start of Block Works @ 1st Floor 0 25-Aug-12 70 26-Aug-12 18-Nov-12 69 0% 0%
AuthoritiAuthorities Approvals 169 16-Feb-12 A 03-Sep-12 76 16-Feb-12 05-Dec-12 16-Feb-12 05-Dec-12 58.14% 25.4%
SwimmiSwimmimng Pool 32 01-Jul-12 06-Aug-12 98 30-Jul-12 05-Dec-12 30-Jul-12 05-Dec-12 0% 0%
A1436 EHS Approval for Pouring Pools Slab - Block A 12 01-Jul-12 14-Jul-12 83 08-Oct-12 21-Oct-12 08-Oct-12 21-Oct-12 0 0% 0%
A1435 EHS Approval for Pouring Pools Slab - Block B 12 01-Jul-12 14-Jul-12 25 30-Jul-12 12-Aug-12 30-Jul-12 12-Aug-12 0 0% 0%
A1438 EHS Approval for Pouring Pools Slab - Block C 11 25-Jul-12 06-Aug-12 98 22-Nov-12 05-Dec-12 22-Nov-12 05-Dec-12 0 0% 0%
TemporaTemporary Power Connection 165 16-Feb-12 A 29-Aug-12 -63 16-Feb-12 13-Jun-12 16-Feb-12 13-Jun-12 100% 43.68%
MEP DraMEP Drawings & Fees 165 16-Feb-12 A 29-Aug-12 -63 16-Feb-12 13-Jun-12 16-Feb-12 13-Jun-12 100% 43.68%
A1516 Submission & Approval of MEP Shop Drawings 78 16-Feb-12 A 30-Jul-12 -63 16-Feb-12 16-May-12 16-Feb-12 16-May-12 0 100% 56%
A1526 Submission of LV Shop Drawing/Load Schedule for Consultant 12 31-Jul-12 13-Aug-12 -63 17-May-12 30-May-12 17-May-12 30-May-12 0 100% 0%
A1536 Consultant Comments on LV Shop Drawing/Load Schedule 10 14-Aug-12 29-Aug-12 -52 31-May-12 13-Jun-12 31-May-12 13-Jun-12 0 100% 0%
OthersOthers 33 25-Jul-12 03-Sep-12 40 01-Jul-12 03-Sep-12 29-Aug-12 20-Oct-12 0% 0%
A1529 Dubai Muncipili ty Approval for Structural Steel Design 25 25-Jul-12 25-Aug-12 28 01-Jul-12 29-Jul-12 29-Aug-12 26-Sep-12 49 0% 0%
A1539 Civil Defence Approval for Drawings 14 16-Aug-12 03-Sep-12 40 16-Aug-12 03-Sep-12 04-Oct-12 20-Oct-12 40 0% 0%
Client SuClient Submissions 41 01-Jul-12 16-Aug-12 161 12-Jun-12 16-Aug-12 23-Jul-12 02-Mar-13 0% 0%
AwardinAwarding of Provisional Sum Packages 19 01-Jul-12 22-Jul-12 53 12-Jun-12 22-Jul-12 28-Jul-12 24-Sep-12 0% 0%
A1489 Awarding of Cooking StationPackage to ASGC 0 01-Jul-12 72 12-Jun-12 24-Sep-12 86 100% 0%
A1476 Awarding of Facade Lighting Package to ASGC 0 22-Jul-12 5 22-Jul-12 28-Jul-12 5 0% 0%
TechnicaTechnical Data for Prime Cost Items 37 05-Jul-12 16-Aug-12 161 05-Jul-12 16-Aug-12 23-Jul-12 02-Mar-13 0% 0%
A1317 Submit the Techincal Data for Loose Furniture 7 05-Jul-12 12-Jul-12 191 05-Jul-12 12-Jul-12 23-Feb-13 02-Mar-13 191 0% 0%
A1327 Submit the Techincal Data for Semi Fixed Accessories 7 05-Jul-12 12-Jul-12 191 05-Jul-12 12-Jul-12 23-Feb-13 02-Mar-13 191 0% 0%
A1277 Submit the Techincal Data for Wooden Parquet 7 05-Jul-12 12-Jul-12 74 05-Jul-12 12-Jul-12 02-Oct-12 09-Oct-12 74 0% 0%
A1287 Submit the Techincal Data for Kitchen Appliances 7 05-Jul-12 12-Jul-12 76 05-Jul-12 12-Jul-12 04-Oct-12 11-Oct-12 76 0% 0%
A1307 Submit the Techincal Data for Light Fittings 7 05-Jul-12 12-Jul-12 56 05-Jul-12 12-Jul-12 11-Sep-12 18-Sep-12 56 0% 0%
A1297 Submit the Techincal Data for Sanitary Items 7 11-Jul-12 18-Jul-12 53 11-Jul-12 18-Jul-12 13-Sep-12 20-Sep-12 53 0% 0%
A1257 Submit the Techincal Data for Porcalin Tiles 7 17-Jul-12 24-Jul-12 12 17-Jul-12 24-Jul-12 31-Jul-12 07-Aug-12 12 0% 0%
A1267 Submit the Techincal Data for Carpet 7 23-Jul-12 30-Jul-12 0 23-Jul-12 30-Jul-12 23-Jul-12 30-Jul-12 0 0% 0%
A1247 Submit the Techincal Data for Ironmongery 7 09-Aug-12 16-Aug-12 63 09-Aug-12 16-Aug-12 24-Oct-12 03-Nov-12 63 0% 0%
PreliminPreliminaries 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0% 0%
Monthly Monthly Preliminaries 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0% 0%
A1766 Preliminaries for Month of Feb-2012 533 15-Feb-12 A 14-Nov-13 0 15-Feb-12 14-Nov-13 15-Feb-12 14-Nov-13 0 21.76% 21.76%
Access tAccess to Sub-Contractors 21 30-Jul-12 25-Aug-12 144 27-Jun-12 02-Oct-12 28-Aug-12 16-Feb-13 0% 0%
MEP (HVMEP (HVAC,Electrical,Plumbing,Fire Fighting) 21 30-Jul-12 25-Aug-12 144 27-Jun-12 02-Oct-12 28-Aug-12 16-Feb-13 0% 0%
Hotel ApHotel Apartements (Block A) 14 30-Jul-12 14-Aug-12 32 27-Jun-12 17-Sep-12 28-Aug-12 23-Sep-12 0% 0%
BasemeBasements 2 30-Jul-12 31-Jul-12 43 27-Jun-12 16-Jul-12 28-Aug-12 22-Sep-12 0% 0%A1332 Access to MEP Sub-Contractor @ Sub-Station 1 0 30-Jul-12 24 27-Jun-12 28-Aug-12 51 100% 0%
A1322 Access to MEP Sub-Contractor @ LV Room 0 30-Jul-12 29 02-Jul-12 03-Sep-12 52 0% 0%
A1352 Access to MEP Sub-Contractor @ Genset Room 0 30-Jul-12 33 05-Jul-12 09-Sep-12 54 0% 0%
A1342 Access to MEP Sub-Contractor @ ELV Room 0 31-Jul-12 43 16-Jul-12 22-Sep-12 56 0% 0%Typical Typical Floors 3 11-Aug-12 14-Aug-12 32 12-Aug-12 17-Sep-12 18-Sep-12 23-Sep-12 0% 0%A1362 Access to MEP Sub-Contractor @ 1st Floor 0 11-Aug-12 35 12-Aug-12 23-Sep-12 34 0% 0%
A1372 Access to MEP Sub-Contractor @ 2nd Floor 0 14-Aug-12 28 17-Sep-12 18-Sep-12 1 0% 0%
Hotel (BlHotel (Block B) 16 04-Aug-12 25-Aug-12 144 15-Aug-12 02-Oct-12 24-Nov-12 16-Feb-13 0% 0%
BasemeBasements 16 04-Aug-12 25-Aug-12 134 15-Aug-12 05-Sep-12 24-Nov-12 04-Feb-13 0% 0%A2362 Access to MEP Sub-Contractor @ Sub-Station 2 & 3 0 04-Aug-12 134 15-Aug-12 15-Jan-13 124 0% 0%
A2392 Access to MEP Sub-Contractor @ AHU Room 0 08-Aug-12 87 22-Aug-12 24-Nov-12 77 0% 0%
A3363 Access to MEP Sub-Contractor @ Genset Room 0 11-Aug-12 144 25-Aug-12 04-Feb-13 134 0% 0%
A2382 Access to MEP Sub-Contractor @ Pump Rooms 0 25-Aug-12 86 05-Sep-12 08-Dec-12 76 0% 0%GroundGround 9 04-Aug-12 14-Aug-12 151 22-Sep-12 02-Oct-12 20-Dec-12 16-Feb-13 0% 0%A7709 Access to MEP Sub-Contractor @ RMU Room 0 04-Aug-12 154 22-Sep-12 09-Feb-13 114 0% 0%
A7729 Access to MEP Sub-Contractor @ Hotel Garbage Room 0 08-Aug-12 156 26-Sep-12 16-Feb-13 116 0% 0%
A7699 Access to MEP Sub-Contractor @ Bussiness Center&Lobby 0 14-Aug-12 104 02-Oct-12 20-Dec-12 64 0% 0%
ResidentResidential Apartments (Block C) 11 08-Aug-12 25-Aug-12 141 02-Sep-12 20-Sep-12 11-Oct-12 11-Feb-13 0% 0%
BasemeBasements 0 08-Aug-12 08-Aug-12 152 02-Sep-12 02-Sep-12 11-Feb-13 11-Feb-13 0% 0%A136370 Access to MEP Sub-Contractor @ Pump Rooms 0 08-Aug-12 152 02-Sep-12 11-Feb-13 133 0% 0%
Typical Typical Floors 0 25-Aug-12 25-Aug-12 41 20-Sep-12 20-Sep-12 11-Oct-12 11-Oct-12 0% 0%A136210 Access to MEP Sub-Contractor @ 1st Floor 0 25-Aug-12 41 20-Sep-12 11-Oct-12 18 0% 0%
EngineeEngineering 168 08-Mar-12 A 15-Sep-12 213 18-Feb-12 09-Jan-13 02-Apr-12 28-May-13 56.05% 3.85%
Shop DraShop Drawings 165 08-Mar-12 A 11-Sep-12 216 18-Feb-12 20-Nov-12 02-Apr-12 28-May-13 56.87% 3.92%
CivilCivil 116 09-Apr-12 A 04-Sep-12 37 26-Jun-12 09-Oct-12 26-Jun-12 17-Oct-12 1.26% 41.57%
Hotel ApHotel Apartements (Block A) 67 29-Apr-12 A 30-Aug-12 29 30-Jun-12 17-Sep-12 30-Jun-12 02-Oct-12 0.89% 51.25%
5th & 6t5th & 6th Floor Slab 58 29-Apr-12 A 15-Jul-12 24 30-Jun-12 12-Aug-12 30-Jun-12 12-Aug-12 2.86% 74%SubmiSubmission 7 29-Apr-12 A 02-Jul-12 24 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 14.29% 90%A1024 Submission of Structural Dwgs. for Core Walls 7 29-Apr-12 A 02-Jul-12 24 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 0 14.29% 90%
ApprovApproval 42 30-Apr-12 A 15-Jul-12 20 08-Jul-12 12-Aug-12 17-Jul-12 12-Aug-12 0% 70%A1024 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 04-Jul-12 23 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 0% 90%
A1024 Approval of Structural Dwgs. for Slab 14 14-Jun-12 A 15-Jul-12 20 24-Jul-12 12-Aug-12 24-Jul-12 12-Aug-12 0 0% 50%7th Floo7th Floor Slab 29 11-Jun-12 A 02-Aug-12 38 25-Jul-12 17-Sep-12 25-Jul-12 17-Sep-12 0% 30%SubmiSubmission 9 11-Jun-12 A 07-Jul-12 37 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0% 50%A1024 Submission of Structural Dwgs. for Core Walls 9 11-Jun-12 A 07-Jul-12 37 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0 0% 50%
ApprovApproval 22 13-Jun-12 A 02-Aug-12 31 05-Aug-12 17-Sep-12 28-Aug-12 17-Sep-12 0% 25%A1025 Approval of Structural Dwgs. for Core Walls 14 13-Jun-12 A 16-Jul-12 42 05-Aug-12 26-Aug-12 28-Aug-12 16-Sep-12 15 0% 50%
A1024 Approval of Structural Dwgs. for Slab 14 26-Jun-12 A 02-Aug-12 31 29-Aug-12 17-Sep-12 29-Aug-12 17-Sep-12 0 0% 0%Roof FRoof Floor Slab 18 18-Jun-12 A 30-Aug-12 29 14-Aug-12 13-Sep-12 14-Aug-12 02-Oct-12 0% 50%SubmiSubmission 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0% 50%A1014 Submission of Structural Dwgs. for Columns 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%
A1014 Submission of Structural Dwgs. for Core Walls 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%ApprovApproval 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 0% 50%A1015 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%
A1015 Approval of Structural Dwgs. for Core Walls 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%
Hotel (BlHotel (Block B) 116 19-Apr-12 A 04-Sep-12 30 23-Jul-12 09-Oct-12 23-Jul-12 09-Oct-12 0% 36.54%
3rd & 4t3rd & 4th Floor Slab 21 11-Jun-12 A 14-Aug-12 16 23-Jul-12 04-Sep-12 23-Jul-12 04-Sep-12 0% 50%SubmiSubmission 8 11-Jun-12 A 05-Aug-12 12 23-Jul-12 31-Jul-12 23-Jul-12 31-Jul-12 0% 50%A1028 Submission of Structural Dwgs. for Core Walls 8 11-Jun-12 A 05-Aug-12 12 23-Jul-12 31-Jul-12 23-Jul-12 31-Jul-12 0 0% 50%
ApprovApproval 17 12-Jun-12 A 14-Aug-12 13 01-Aug-12 04-Sep-12 09-Aug-12 04-Sep-12 0% 50%A1028 Approval of Structural Dwgs. for Slab 14 16-Jun-12 A 14-Aug-12 13 14-Aug-12 04-Sep-12 14-Aug-12 04-Sep-12 0 0% 50%
A1028 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 14-Aug-12 10 01-Aug-12 22-Aug-12 09-Aug-12 30-Aug-12 6 0% 50%5th & 6t5th & 6th Floor Slab 116 19-Apr-12 A 04-Sep-12 30 09-Aug-12 09-Oct-12 09-Aug-12 09-Oct-12 0% 28.13%SubmiSubmission 8 19-Apr-12 A 07-Aug-12 28 09-Aug-12 28-Aug-12 09-Aug-12 28-Aug-12 0% 37.5%A1031 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 05-Aug-12 30 18-Aug-12 28-Aug-12 18-Aug-12 28-Aug-12 0 0% 50%
A1031 Submission of Structural Dwgs. for Columns 8 19-Apr-12 A 07-Aug-12 16 09-Aug-12 18-Aug-12 09-Aug-12 18-Aug-12 0 0% 25%ApprovApproval 90 21-Apr-12 A 04-Sep-12 25 23-Aug-12 09-Oct-12 17-Sep-12 09-Oct-12 0% 25%A1032 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 15-Aug-12 34 30-Aug-12 18-Sep-12 17-Sep-12 04-Oct-12 12 0% 50%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Overall Duration of P
Overa
EHS Approval for Pouring Pools Slab - Block A
EHS Approval for Pouring Pools Slab - Block B
EHS Approval for Pouring Pools Slab - Block C
Submission & Approval of MEP Shop Drawings
Submission of LV Shop Drawing/Load Schedule for Consultant
Consultant Comments on LV Shop Drawing/Load Schedule
Dubai Muncipili ty Approval for Structural Steel Design
Civil Defence Approval for Drawings
Submit the Techincal Data for Loose Furniture
Submit the Techincal Data for Semi Fixed Accessories
Submit the Techincal Data for Wooden Parquet
Submit the Techincal Data for Kitchen Appliances
Submit the Techincal Data for Light Fittings
Submit the Techincal Data for Sanitary Items
Submit the Techincal Data for Porcalin Tiles
Submit the Techincal Data for Carpet
Submit the Techincal Data for Ironmongery
Prelim
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Core Walls
ab Approval of Structural Dwgs. for Slab
s Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 1 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1032 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 28-Aug-12 28 23-Aug-12 11-Sep-12 17-Sep-12 04-Oct-12 17 0% 25%
A1031 Approval of Structural Dwgs. for Slab 14 14-Aug-12 04-Sep-12 25 20-Sep-12 09-Oct-12 20-Sep-12 09-Oct-12 0 0% 0%
ResidentResidentail (Block C) 115 09-Apr-12 A 04-Sep-12 37 26-Jun-12 06-Oct-12 26-Jun-12 17-Oct-12 2.27% 37.5%
3rd & 4t3rd & 4th Floor Slab 55 09-Apr-12 A 24-Jul-12 11 26-Jun-12 24-Jul-12 26-Jun-12 06-Aug-12 10% 40%SubmiSubmission 8 20-Jun-12 A 04-Jul-12 9 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 50% 50%A1036 Submission of Structural Dwgs. for Core Walls 8 20-Jun-12 A 04-Jul-12 9 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 50% 50%
ApprovApproval 46 09-Apr-12 A 24-Jul-12 9 05-Jul-12 24-Jul-12 16-Jul-12 06-Aug-12 0% 37.5%A1036 Approval of Structural Dwgs. for Columns 14 09-Apr-12 A 04-Jul-12 24 05-Jul-12 24-Jul-12 18-Jul-12 06-Aug-12 9 0% 75%
A1036 Approval of Structural Dwgs. for Core Walls 14 21-Jun-12 A 24-Jul-12 7 05-Jul-12 24-Jul-12 16-Jul-12 02-Aug-12 7 0% 0%5th & 6t5th & 6th Floor Slab 67 19-Apr-12 A 29-Jul-12 45 23-Jul-12 20-Sep-12 23-Jul-12 20-Sep-12 0% 34.38%SubmiSubmission 8 19-Apr-12 A 14-Jul-12 39 23-Jul-12 14-Aug-12 23-Jul-12 14-Aug-12 0% 37.5%A1039 Submission of Structural Dwgs. for Columns 7 19-Apr-12 A 11-Jul-12 27 23-Jul-12 30-Jul-12 23-Jul-12 30-Jul-12 0 0% 50%
A1039 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 14-Jul-12 39 06-Aug-12 14-Aug-12 06-Aug-12 14-Aug-12 0 0% 25%ApprovApproval 49 21-Apr-12 A 29-Jul-12 38 31-Jul-12 20-Sep-12 22-Aug-12 20-Sep-12 0% 33.33%A1039 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 22-Jul-12 35 31-Jul-12 21-Aug-12 22-Aug-12 10-Sep-12 14 0% 50%
A1039 Approval of Structural Dwgs. for Slab 14 19-Jun-12 A 25-Jul-12 39 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0 0% 25%
A1039 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 29-Jul-12 33 15-Aug-12 05-Sep-12 27-Aug-12 13-Sep-12 6 0% 25%7th Floo7th Floor Slab 71 11-Jun-12 A 04-Sep-12 37 26-Aug-12 06-Oct-12 26-Aug-12 17-Oct-12 0% 42.86%SubmiSubmission 71 11-Jun-12 A 04-Sep-12 27 26-Aug-12 06-Oct-12 26-Aug-12 06-Oct-12 0% 33.33%A1040 Submission of Structural Dwgs. for Columns 7 11-Jun-12 A 07-Aug-12 27 26-Aug-12 02-Sep-12 26-Aug-12 02-Sep-12 0 0% 50%
A1040 Submission of Structural Dwgs. for Core Walls 7 11-Jun-12 A 07-Aug-12 27 03-Sep-12 10-Sep-12 03-Sep-12 10-Sep-12 0 0% 50%
A1040 Submission of Structural Dwgs. for Slab 14 18-Aug-12 04-Sep-12 27 20-Sep-12 06-Oct-12 20-Sep-12 06-Oct-12 0 0% 0%ApprovApproval 14 12-Jun-12 A 16-Aug-12 42 03-Sep-12 30-Sep-12 30-Sep-12 17-Oct-12 0% 50%A1040 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 16-Aug-12 42 03-Sep-12 20-Sep-12 30-Sep-12 17-Oct-12 19 0% 50%
A1040 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 16-Aug-12 42 11-Sep-12 30-Sep-12 30-Sep-12 17-Oct-12 13 0% 50%Roof FRoof Floor Slab 60 18-Jun-12 A 28-Aug-12 30 13-Sep-12 02-Oct-12 13-Sep-12 02-Oct-12 0% 25%SubmiSubmission 60 18-Jun-12 A 28-Aug-12 30 13-Sep-12 02-Oct-12 13-Sep-12 02-Oct-12 0% 25%A1036 Submission of Structural Dwgs. for Columns 7 18-Jun-12 A 25-Aug-12 30 13-Sep-12 20-Sep-12 13-Sep-12 20-Sep-12 0 0% 50%
A1037 Submission of Structural Dwgs. for Core Walls 7 21-Aug-12 28-Aug-12 30 25-Sep-12 02-Oct-12 25-Sep-12 02-Oct-12 0 0% 0%
ArchitecArchitectural 67 21-Jun-12 A 09-Sep-12 218 23-Jun-12 14-Nov-12 14-Aug-12 28-May-13 0.53% 0%
Hotel ApHotel Apartements (Block A) 59 01-Jul-12 09-Sep-12 168 23-Jun-12 16-Oct-12 25-Aug-12 31-Mar-13 2.48% 0%
2nd Bas2nd Basement Floor 55 01-Jul-12 04-Sep-12 67 23-Jun-12 11-Oct-12 06-Oct-12 25-Nov-12 15.91% 0%SubmiSubmission 38 01-Jul-12 13-Aug-12 67 23-Jun-12 23-Sep-12 06-Oct-12 04-Nov-12 43.75% 0%A1191 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 81 23-Jun-12 01-Jul-12 06-Oct-12 14-Oct-12 88 87.5% 0%
A1191 Submission of Handrail Layout & Details 8 04-Aug-12 13-Aug-12 67 15-Sep-12 23-Sep-12 24-Oct-12 04-Nov-12 34 0% 0%ApprovApproval 39 10-Jul-12 04-Sep-12 56 02-Jul-12 11-Oct-12 15-Oct-12 25-Nov-12 0% 0%A1192 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 67 02-Jul-12 19-Jul-12 15-Oct-12 04-Nov-12 73 0% 0%
A1192 Approval of Handrail Layout & Details 14 13-Aug-12 04-Sep-12 56 24-Sep-12 11-Oct-12 05-Nov-12 25-Nov-12 29 0% 0%1st Bas1st Basement Floor 59 01-Jul-12 09-Sep-12 168 02-Jul-12 27-Sep-12 09-Oct-12 31-Mar-13 0% 0%SubmiSubmission 41 01-Jul-12 16-Aug-12 169 02-Jul-12 09-Sep-12 09-Oct-12 11-Mar-13 0% 0%A1195 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 84 02-Jul-12 10-Jul-12 09-Oct-12 17-Oct-12 83 0% 0%
A1194 Submission of Reflected Ceil ing Layout 8 16-Jul-12 24-Jul-12 109 06-Aug-12 14-Aug-12 26-Nov-12 05-Dec-12 91 0% 0%
A1194 Submission of Flooring 8 02-Aug-12 11-Aug-12 149 26-Aug-12 03-Sep-12 02-Feb-13 10-Feb-13 131 0% 0%
A1194 Submission of Doors Details 8 08-Aug-12 16-Aug-12 169 01-Sep-12 09-Sep-12 03-Mar-13 11-Mar-13 151 0% 0%ApprovApproval 42 10-Jul-12 09-Sep-12 140 11-Jul-12 27-Sep-12 18-Oct-12 31-Mar-13 0% 0%A1196 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 70 11-Jul-12 30-Jul-12 18-Oct-12 07-Nov-12 69 0% 0%
A1195 Approval of Reflected Ceiling Layout 14 25-Jul-12 13-Aug-12 91 15-Aug-12 05-Sep-12 06-Dec-12 25-Dec-12 76 0% 0%
A1195 Approval of Flooring 14 12-Aug-12 02-Sep-12 124 04-Sep-12 23-Sep-12 11-Feb-13 28-Feb-13 109 0% 0%
A1196 Approval of Doors Details 14 21-Aug-12 09-Sep-12 140 10-Sep-12 27-Sep-12 12-Mar-13 31-Mar-13 126 0% 0%GroundGround Floor 26 25-Jul-12 26-Aug-12 64 04-Aug-12 03-Sep-12 13-Oct-12 11-Nov-12 0% 0%SubmiSubmission 8 25-Jul-12 02-Aug-12 66 04-Aug-12 12-Aug-12 13-Oct-12 21-Oct-12 0% 0%A1191 Submission of Staircase Layout & Details 8 25-Jul-12 02-Aug-12 66 04-Aug-12 12-Aug-12 13-Oct-12 21-Oct-12 58 0% 0%
ApprovApproval 14 05-Aug-12 26-Aug-12 54 13-Aug-12 03-Sep-12 22-Oct-12 11-Nov-12 0% 0%A1192 Approval of Staircase Layout & Details 14 05-Aug-12 26-Aug-12 54 13-Aug-12 03-Sep-12 22-Oct-12 11-Nov-12 48 0% 0%
Typical Typical Floors 56 01-Jul-12 05-Sep-12 119 25-Aug-12 16-Oct-12 25-Aug-12 29-Jan-13 0% 0%GeneralGeneral 46 01-Jul-12 25-Aug-12 62 25-Aug-12 16-Oct-12 25-Aug-12 07-Nov-12 0% 0%SubmSubmission 46 01-Jul-12 25-Aug-12 62 25-Aug-12 16-Oct-12 25-Aug-12 07-Nov-12 0% 0%A1172 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 01-Jul-12 09-Jul-12 45 25-Aug-12 02-Sep-12 25-Aug-12 02-Sep-12 0 0% 0%
A1172 Submission of Block Work Setting Out Plan for 7th Floor 8 14-Aug-12 25-Aug-12 62 08-Oct-12 16-Oct-12 30-Oct-12 07-Nov-12 17 0% 0%ApproApproval 14 10-Jul-12 29-Jul-12 37 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0% 0%A1175 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 10-Jul-12 29-Jul-12 37 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0 0% 0%
CorridCorridor / General 35 25-Jul-12 05-Sep-12 119 27-Aug-12 04-Oct-12 23-Oct-12 29-Jan-13 0% 0%SubmSubmission 18 25-Jul-12 14-Aug-12 119 27-Aug-12 16-Sep-12 23-Oct-12 08-Jan-13 0% 0%A1191 Submission of Staircase Layout & Details 8 25-Jul-12 02-Aug-12 75 27-Aug-12 04-Sep-12 23-Oct-12 03-Nov-12 49 0% 0%
A1174 Submission of Reflected Ceil ing Layout 8 06-Aug-12 14-Aug-12 119 08-Sep-12 16-Sep-12 30-Dec-12 08-Jan-13 93 0% 0%ApproApproval 22 05-Aug-12 05-Sep-12 99 05-Sep-12 04-Oct-12 04-Nov-12 29-Jan-13 0% 0%A1192 Approval of Staircase Layout & Details 14 05-Aug-12 26-Aug-12 62 05-Sep-12 24-Sep-12 04-Nov-12 22-Nov-12 41 0% 0%
A1175 Approval of Reflected Ceiling Layout 14 15-Aug-12 05-Sep-12 99 17-Sep-12 04-Oct-12 09-Jan-13 29-Jan-13 78 0% 0%StudioStudio Apartements 28 25-Jul-12 28-Aug-12 84 27-Aug-12 27-Sep-12 28-Oct-12 09-Dec-12 0% 0%SubmSubmission 28 25-Jul-12 28-Aug-12 67 27-Aug-12 27-Sep-12 28-Oct-12 18-Nov-12 0% 0%A1173 Submission of Wet Area Ceramic & Pocalin Layout 8 25-Jul-12 02-Aug-12 87 27-Aug-12 04-Sep-12 08-Nov-12 18-Nov-12 61 0% 0%
A1173 Submission of Reflected Ceil ing Layout 8 18-Aug-12 28-Aug-12 57 19-Sep-12 27-Sep-12 28-Oct-12 05-Nov-12 31 0% 0%ApproApproval 14 05-Aug-12 26-Aug-12 72 05-Sep-12 24-Sep-12 19-Nov-12 09-Dec-12 0% 0%A1176 Approval of Wet Area Ceramic & Pocalin Layout 14 05-Aug-12 26-Aug-12 72 05-Sep-12 24-Sep-12 19-Nov-12 09-Dec-12 51 0% 0%
One BeOne Bed Room Apartements 8 18-Aug-12 28-Aug-12 52 19-Sep-12 27-Sep-12 20-Oct-12 30-Oct-12 0% 0%SubmSubmission 8 18-Aug-12 28-Aug-12 52 19-Sep-12 27-Sep-12 20-Oct-12 30-Oct-12 0% 0%A1177 Submission of Reflected Ceil ing Layout 8 18-Aug-12 28-Aug-12 52 19-Sep-12 27-Sep-12 20-Oct-12 30-Oct-12 26 0% 0%
Two BTwo Bed Room Apartements 8 18-Aug-12 28-Aug-12 35 19-Sep-12 27-Sep-12 30-Sep-12 08-Oct-12 0% 0%SubmSubmission 8 18-Aug-12 28-Aug-12 35 19-Sep-12 27-Sep-12 30-Sep-12 08-Oct-12 0% 0%A1180 Submission of Reflected Ceil ing Layout 8 18-Aug-12 28-Aug-12 35 19-Sep-12 27-Sep-12 30-Sep-12 08-Oct-12 9 0% 0%
Roof - URoof - Upper Roof Floor 8 18-Aug-12 28-Aug-12 32 19-Sep-12 27-Sep-12 26-Sep-12 04-Oct-12 0% 0%GeneralGeneral 8 18-Aug-12 28-Aug-12 32 19-Sep-12 27-Sep-12 26-Sep-12 04-Oct-12 0% 0%SubmSubmission 8 18-Aug-12 28-Aug-12 32 19-Sep-12 27-Sep-12 26-Sep-12 04-Oct-12 0% 0%A1186 Submission of Block Work Setting Out Plan for Roof & upper... 8 18-Aug-12 28-Aug-12 32 19-Sep-12 27-Sep-12 26-Sep-12 04-Oct-12 6 0% 0%
Hotel (BlHotel (Block B) 67 21-Jun-12 A 09-Sep-12 218 05-Aug-12 14-Nov-12 28-Aug-12 28-May-13 0% 0%
2nd Bas2nd Basement Floor 48 02-Jul-12 28-Aug-12 178 07-Aug-12 03-Oct-12 04-Nov-12 31-Mar-13 0% 0%SubmiSubmission 48 02-Jul-12 28-Aug-12 178 07-Aug-12 03-Oct-12 04-Nov-12 31-Mar-13 0% 0%A1233 Submission of Staircase Layout & Details 8 02-Jul-12 10-Jul-12 103 07-Aug-12 15-Aug-12 04-Nov-12 12-Nov-12 72 0% 0%
A1233 Submission of Handrail Layout & Details 8 02-Jul-12 10-Jul-12 106 07-Aug-12 15-Aug-12 07-Nov-12 17-Nov-12 75 0% 0%
A1232 Submission of Flooring 8 18-Aug-12 28-Aug-12 175 25-Sep-12 03-Oct-12 19-Mar-13 27-Mar-13 144 0% 0%
A1232 Submission of Doors Details 8 18-Aug-12 28-Aug-12 178 25-Sep-12 03-Oct-12 23-Mar-13 31-Mar-13 147 0% 0%ApprovApproval 14 11-Jul-12 30-Jul-12 88 16-Aug-12 06-Sep-12 13-Nov-12 06-Dec-12 0% 0%A1234 Approval of Staircase Layout & Details 14 11-Jul-12 30-Jul-12 86 16-Aug-12 06-Sep-12 13-Nov-12 04-Dec-12 60 0% 0%
A1234 Approval of Handrail Layout & Details 14 11-Jul-12 30-Jul-12 88 16-Aug-12 06-Sep-12 18-Nov-12 06-Dec-12 62 0% 0%1st Bas1st Basement Floor 59 01-Jul-12 09-Sep-12 218 05-Aug-12 14-Nov-12 08-Nov-12 28-May-13 0% 0%SubmiSubmission 41 01-Jul-12 16-Aug-12 219 05-Aug-12 24-Oct-12 08-Nov-12 08-May-13 0% 0%A1236 Submission of Flooring 8 01-Jul-12 09-Jul-12 177 30-Aug-12 08-Sep-12 02-Feb-13 10-Feb-13 127 0% 0%
A1236 Submission of Doors Details 8 01-Jul-12 09-Jul-12 225 05-Aug-12 13-Aug-12 30-Mar-13 07-Apr-13 195 0% 0%
A1236 Submission of Reflected Ceil ing Layout 8 01-Jul-12 09-Jul-12 150 16-Aug-12 27-Aug-12 30-Dec-12 08-Jan-13 110 0% 0%
A1237 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 108 16-Aug-12 27-Aug-12 08-Nov-12 18-Nov-12 68 0% 0%
A1237 Submission of Handrail Layout & Details 8 01-Jul-12 09-Jul-12 111 30-Aug-12 08-Sep-12 12-Nov-12 21-Nov-12 61 0% 0%
A1237 Submission of Sinage Layout and Details 8 08-Aug-12 16-Aug-12 219 16-Oct-12 24-Oct-12 30-Apr-13 08-May-13 162 0% 0%ApprovApproval 42 10-Jul-12 09-Sep-12 182 14-Aug-12 14-Nov-12 19-Nov-12 28-May-13 0% 0%A1237 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 90 28-Aug-12 16-Sep-12 19-Nov-12 09-Dec-12 57 0% 0%
A1237 Approval of Handrail Layout & Details 14 10-Jul-12 29-Jul-12 93 09-Sep-12 26-Sep-12 22-Nov-12 12-Dec-12 52 0% 0%
A1238 Approval of Flooring 14 10-Jul-12 29-Jul-12 147 09-Sep-12 26-Sep-12 11-Feb-13 28-Feb-13 106 0% 0%
A1238 Approval of Doors Details 14 10-Jul-12 29-Jul-12 187 14-Aug-12 04-Sep-12 08-Apr-13 25-Apr-13 162 0% 0%
A1238 Approval of Reflected Ceiling Layout 14 10-Jul-12 29-Jul-12 125 28-Aug-12 16-Sep-12 09-Jan-13 29-Jan-13 92 0% 0%
A1238 Approval of Sinage Layout and Details 14 21-Aug-12 09-Sep-12 182 28-Oct-12 14-Nov-12 09-May-13 28-May-13 135 0% 0%GroundGround Floor 53 01-Jul-12 02-Sep-12 150 16-Aug-12 17-Oct-12 28-Aug-12 03-Mar-13 0% 0%Public Public Areas 53 01-Jul-12 02-Sep-12 150 16-Aug-12 17-Oct-12 28-Aug-12 03-Mar-13 0% 0%SubmSubmission 46 01-Jul-12 25-Aug-12 140 16-Aug-12 10-Oct-12 28-Aug-12 11-Feb-13 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Slab
s Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
b Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
s Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Submission of Staircase Layout & Details
Submission of Reflected Ceil ing Layout
Submission of Flooring
Submission of Doors Details
Approval of Staircase Layout & Details
Approval of Reflected Cei ling Layout
Approval of Flooring
Approval of Doors Details
Submission of Staircase Layout & Details
Approval of Staircase Layout & Details
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Block Work Setting Out Plan for 7th Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Staircase Layout & Details
Submission of Reflected Ceil ing Layout
Approval of Staircase Layout & Details
Approval of Reflected Ceiling Layout
Submission of Wet Area Ceramic & Pocal in Layout
Submission of Reflected Ceil ing Layout
Approval of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceil ing Layout
Submission of Reflected Ceil ing Layout
Submission of Block Work Setting Out Plan for Roof & upper Roof
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Flooring
Submission of Doors Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Submission of Flooring
Submission of Doors Details
Submission of Reflected Ceil ing Layout
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Sinage Layout and Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Flooring
Approval of Doors Details
Approval of Reflected Ceiling Layout
Approval of Sinage Layout and Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 2 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1228 Submission of Block Work Setting Out Plan for Ground 8 01-Jul-12 09-Jul-12 61 16-Aug-12 27-Aug-12 28-Aug-12 05-Sep-12 8 0% 0%
A1228 Submission of Reflected Ceil ing Layout 8 02-Aug-12 11-Aug-12 131 20-Sep-12 29-Sep-12 10-Jan-13 19-Jan-13 91 0% 0%
A1228 Submission of Flooring Layout 8 02-Aug-12 11-Aug-12 150 20-Sep-12 29-Sep-12 03-Feb-13 11-Feb-13 110 0% 0%
A1228 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 02-Aug-12 11-Aug-12 149 20-Sep-12 29-Sep-12 02-Feb-13 10-Feb-13 109 0% 0%
A1233 Submission of Staircase Layout & Details 8 14-Aug-12 25-Aug-12 106 02-Oct-12 10-Oct-12 23-Dec-12 31-Dec-12 66 0% 0%
A1233 Submission of Handrail Layout & Details 8 14-Aug-12 25-Aug-12 109 02-Oct-12 10-Oct-12 26-Dec-12 05-Jan-13 69 0% 0%ApproApproval 37 10-Jul-12 02-Sep-12 125 28-Aug-12 17-Oct-12 04-Oct-12 03-Mar-13 0% 0%A1229 Approval of Block Work Setting Out Plan for Ground 14 10-Jul-12 29-Jul-12 60 28-Aug-12 16-Sep-12 04-Oct-12 23-Oct-12 27 0% 0%
A1229 Approval of Reflected Ceiling Layout 14 12-Aug-12 02-Sep-12 109 30-Sep-12 17-Oct-12 20-Jan-13 07-Feb-13 76 0% 0%
A1229 Approval of Flooring Layout 14 12-Aug-12 02-Sep-12 125 30-Sep-12 17-Oct-12 12-Feb-13 03-Mar-13 92 0% 0%
A1229 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 12-Aug-12 02-Sep-12 124 30-Sep-12 17-Oct-12 11-Feb-13 28-Feb-13 91 0% 0%RestauRestaurant 25 30-Jul-12 29-Aug-12 148 17-Sep-12 15-Oct-12 28-Jan-13 25-Feb-13 0% 0%SubmSubmission 8 30-Jul-12 07-Aug-12 148 17-Sep-12 25-Sep-12 28-Jan-13 05-Feb-13 0% 0%A1239 Submission of Reflected Ceil ing Layout 8 30-Jul-12 07-Aug-12 148 17-Sep-12 25-Sep-12 28-Jan-13 05-Feb-13 108 0% 0%
ApproApproval 14 08-Aug-12 29-Aug-12 123 26-Sep-12 15-Oct-12 06-Feb-13 25-Feb-13 0% 0%A1240 Approval of Reflected Ceiling Layout 14 08-Aug-12 29-Aug-12 123 26-Sep-12 15-Oct-12 06-Feb-13 25-Feb-13 90 0% 0%
BussinBussiness Center & Retail 25 10-Jul-12 07-Aug-12 152 28-Aug-12 25-Sep-12 12-Jan-13 10-Feb-13 0% 0%SubmSubmission 8 10-Jul-12 18-Jul-12 152 28-Aug-12 05-Sep-12 12-Jan-13 20-Jan-13 0% 0%A1240 Submission of Reflected Ceil ing Layout 8 10-Jul-12 18-Jul-12 152 28-Aug-12 05-Sep-12 12-Jan-13 20-Jan-13 112 0% 0%
ApproApproval 14 19-Jul-12 07-Aug-12 126 06-Sep-12 25-Sep-12 21-Jan-13 10-Feb-13 0% 0%A1240 Approval of Reflected Ceiling Layout 14 19-Jul-12 07-Aug-12 126 06-Sep-12 25-Sep-12 21-Jan-13 10-Feb-13 93 0% 0%
Typical Typical Floors 63 21-Jun-12 A 04-Sep-12 164 06-Sep-12 08-Nov-12 22-Oct-12 21-Mar-13 0% 0%GeneralGeneral 57 21-Jun-12 A 28-Aug-12 148 06-Sep-12 04-Nov-12 22-Oct-12 24-Feb-13 0% 0%SubmSubmission 41 10-Jul-12 28-Aug-12 131 16-Sep-12 04-Nov-12 17-Dec-12 04-Feb-13 0% 0%A1218 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 10-Jul-12 18-Jul-12 131 16-Sep-12 24-Sep-12 17-Dec-12 25-Dec-12 75 0% 0%
A1218 Submission of Block Work Setting Out Plan for 7th Floor 8 18-Aug-12 28-Aug-12 131 24-Oct-12 04-Nov-12 27-Jan-13 04-Feb-13 75 0% 0%ApproApproval 34 21-Jun-12 A 07-Aug-12 136 06-Sep-12 14-Oct-12 22-Oct-12 24-Feb-13 0% 0%A1220 Approval of Block Work Setting Out Plan for 2nd Floor 14 30-Jun-12 A 29-Jul-12 133 16-Sep-12 03-Oct-12 21-Jan-13 10-Feb-13 87 0% 0%
A1220 Approval of Block Work Setting Out Plan for 1st Floor 14 21-Jun-12 A 29-Jul-12 72 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32 0% 0%
A1220 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 19-Jul-12 07-Aug-12 136 25-Sep-12 14-Oct-12 05-Feb-13 24-Feb-13 90 0% 0%CorridCorridor / Public Areas 47 10-Jul-12 04-Sep-12 164 06-Sep-12 08-Nov-12 22-Nov-12 21-Mar-13 0% 0%SubmSubmission 40 10-Jul-12 27-Aug-12 155 06-Sep-12 03-Nov-12 22-Nov-12 03-Mar-13 0% 0%A1223 Submission of Landscaping's Water Proofing Details 8 10-Jul-12 18-Jul-12 111 06-Sep-12 15-Sep-12 22-Nov-12 01-Dec-12 63 0% 0%
A1219 Submission of Reflected Ceil ing Layout 8 24-Jul-12 01-Aug-12 165 30-Sep-12 08-Oct-12 11-Feb-13 19-Feb-13 109 0% 0%
A1222 Submission of Landscaping Layout & Details 8 30-Jul-12 07-Aug-12 134 06-Oct-12 14-Oct-12 10-Jan-13 19-Jan-13 78 0% 0%
A1233 Submission of Staircase Layout & Details 8 05-Aug-12 13-Aug-12 161 11-Oct-12 20-Oct-12 18-Feb-13 26-Feb-13 105 0% 0%
A1233 Submission of Handrail Layout & Details 8 05-Aug-12 13-Aug-12 165 11-Oct-12 20-Oct-12 23-Feb-13 03-Mar-13 109 0% 0%
A1238 Submission of Pool Deck Layout 8 16-Aug-12 27-Aug-12 146 23-Oct-12 03-Nov-12 12-Feb-13 20-Feb-13 90 0% 0%ApproApproval 32 19-Jul-12 04-Sep-12 137 16-Sep-12 08-Nov-12 03-Dec-12 21-Mar-13 0% 0%A1239 Approval of Landscaping's Water Proofing Details 14 19-Jul-12 07-Aug-12 92 16-Sep-12 03-Oct-12 03-Dec-12 20-Dec-12 53 0% 0%
A1221 Approval of Reflected Ceiling Layout 14 02-Aug-12 23-Aug-12 137 09-Oct-12 29-Oct-12 20-Feb-13 11-Mar-13 91 0% 0%
A1239 Approval of Landscaping Layout & Details 14 08-Aug-12 29-Aug-12 111 15-Oct-12 04-Nov-12 20-Jan-13 07-Feb-13 65 0% 0%
A1234 Approval of Staircase Layout & Details 14 14-Aug-12 04-Sep-12 134 21-Oct-12 08-Nov-12 27-Feb-13 18-Mar-13 88 0% 0%
A1234 Approval of Handrail Layout & Details 14 14-Aug-12 04-Sep-12 137 21-Oct-12 08-Nov-12 04-Mar-13 21-Mar-13 91 0% 0%Hotel RHotel Rooms 25 05-Aug-12 04-Sep-12 127 11-Oct-12 08-Nov-12 26-Dec-12 06-Feb-13 0% 0%SubmSubmission 8 05-Aug-12 13-Aug-12 127 11-Oct-12 20-Oct-12 26-Dec-12 16-Jan-13 0% 0%A1218 Submission of Reflected Ceil ing Layout 8 05-Aug-12 13-Aug-12 117 11-Oct-12 20-Oct-12 26-Dec-12 05-Jan-13 61 0% 0%
A1219 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 05-Aug-12 13-Aug-12 127 11-Oct-12 20-Oct-12 08-Jan-13 16-Jan-13 71 0% 0%ApproApproval 14 14-Aug-12 04-Sep-12 106 21-Oct-12 08-Nov-12 06-Jan-13 06-Feb-13 0% 0%A1222 Approval of Reflected Ceiling Layout 14 14-Aug-12 04-Sep-12 97 21-Oct-12 08-Nov-12 06-Jan-13 23-Jan-13 51 0% 0%
A1222 Approval of Wet Area Ceramic & Pocalin Layout 14 14-Aug-12 04-Sep-12 106 21-Oct-12 08-Nov-12 17-Jan-13 06-Feb-13 60 0% 0%Roof - URoof - Upper Roof Floor 25 05-Aug-12 04-Sep-12 138 11-Oct-12 08-Nov-12 29-Nov-12 19-Feb-13 0% 0%GeneralGeneral 25 05-Aug-12 04-Sep-12 138 11-Oct-12 08-Nov-12 29-Nov-12 19-Feb-13 0% 0%SubmSubmission 16 05-Aug-12 25-Aug-12 147 11-Oct-12 31-Oct-12 29-Nov-12 19-Feb-13 0% 0%A1230 Submission of Block Work Setting Out Plan for Roof&Upper ... 8 05-Aug-12 13-Aug-12 95 11-Oct-12 20-Oct-12 29-Nov-12 09-Dec-12 39 0% 0%
A1229 Submission of Roof's Water Proofing System 8 14-Aug-12 25-Aug-12 121 21-Oct-12 31-Oct-12 10-Jan-13 19-Jan-13 65 0% 0%
A1230 Submission of Flooring Layout 8 14-Aug-12 25-Aug-12 147 21-Oct-12 31-Oct-12 11-Feb-13 19-Feb-13 91 0% 0%ApproApproval 14 14-Aug-12 04-Sep-12 79 21-Oct-12 08-Nov-12 10-Dec-12 27-Dec-12 0% 0%A1231 Approval of Block Work Setting Out Plan for for Roof&Upper ... 14 14-Aug-12 04-Sep-12 79 21-Oct-12 08-Nov-12 10-Dec-12 27-Dec-12 33 0% 0%
ResidentResidential Apartments (Block C) 55 01-Jul-12 04-Sep-12 174 03-Jul-12 17-Oct-12 14-Aug-12 02-Apr-13 0% 0%
2nd Bas2nd Basement Floor 49 01-Jul-12 28-Aug-12 156 03-Jul-12 03-Oct-12 17-Oct-12 05-Mar-13 0% 0%SubmiSubmission 49 01-Jul-12 28-Aug-12 156 03-Jul-12 03-Oct-12 17-Oct-12 05-Mar-13 0% 0%A1212 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 91 03-Jul-12 11-Jul-12 17-Oct-12 28-Oct-12 89 0% 0%
A1212 Submission of Handrail Layout & Details 8 01-Jul-12 09-Jul-12 94 15-Jul-12 23-Jul-12 21-Oct-12 31-Oct-12 82 0% 0%
A1211 Submission of Reflected Ceil ing Layout 8 02-Jul-12 10-Jul-12 141 07-Aug-12 15-Aug-12 20-Dec-12 29-Dec-12 110 0% 0%
A1211 Submission of Flooring 8 18-Aug-12 28-Aug-12 154 25-Sep-12 03-Oct-12 23-Feb-13 03-Mar-13 123 0% 0%
A1211 Submission of Doors Details 8 18-Aug-12 28-Aug-12 156 25-Sep-12 03-Oct-12 25-Feb-13 05-Mar-13 125 0% 0%ApprovApproval 15 10-Jul-12 30-Jul-12 117 12-Jul-12 06-Sep-12 29-Oct-12 17-Jan-13 0% 0%A1213 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 76 12-Jul-12 31-Jul-12 29-Oct-12 18-Nov-12 74 0% 0%
A1213 Approval of Handrail Layout & Details 14 10-Jul-12 29-Jul-12 79 24-Jul-12 12-Aug-12 01-Nov-12 21-Nov-12 69 0% 0%
A1214 Approval of Reflected Ceiling Layout 14 11-Jul-12 30-Jul-12 117 16-Aug-12 06-Sep-12 30-Dec-12 17-Jan-13 91 0% 0%1st Bas1st Basement Floor 25 01-Jul-12 29-Jul-12 193 05-Aug-12 26-Sep-12 31-Dec-12 20-Mar-13 0% 0%SubmiSubmission 8 01-Jul-12 09-Jul-12 194 05-Aug-12 08-Sep-12 31-Dec-12 02-Mar-13 0% 0%A1216 Submission of Handrail Layout & Details 8 01-Jul-12 09-Jul-12 180 05-Aug-12 13-Aug-12 05-Feb-13 13-Feb-13 150 0% 0%
A1215 Submission of Flooring 8 01-Jul-12 09-Jul-12 189 16-Aug-12 27-Aug-12 16-Feb-13 24-Feb-13 149 0% 0%
A1215 Submission of Doors Details 8 01-Jul-12 09-Jul-12 194 30-Aug-12 08-Sep-12 21-Feb-13 02-Mar-13 144 0% 0%
A1215 Submission of Reflected Ceil ing Layout 8 01-Jul-12 09-Jul-12 151 05-Aug-12 13-Aug-12 31-Dec-12 09-Jan-13 121 0% 0%
A1216 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 177 05-Aug-12 13-Aug-12 02-Feb-13 10-Feb-13 147 0% 0%ApprovApproval 14 10-Jul-12 29-Jul-12 161 14-Aug-12 26-Sep-12 10-Jan-13 20-Mar-13 0% 0%A1216 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 147 14-Aug-12 04-Sep-12 11-Feb-13 28-Feb-13 122 0% 0%
A1216 Approval of Handrail Layout & Details 14 10-Jul-12 29-Jul-12 150 14-Aug-12 04-Sep-12 14-Feb-13 05-Mar-13 125 0% 0%
A1217 Approval of Flooring 14 10-Jul-12 29-Jul-12 157 28-Aug-12 16-Sep-12 25-Feb-13 14-Mar-13 124 0% 0%
A1217 Approval of Doors Details 14 10-Jul-12 29-Jul-12 161 09-Sep-12 26-Sep-12 03-Mar-13 20-Mar-13 120 0% 0%
A1217 Approval of Reflected Ceiling Layout 14 10-Jul-12 29-Jul-12 126 14-Aug-12 04-Sep-12 10-Jan-13 30-Jan-13 101 0% 0%GroundGround Floor 55 01-Jul-12 04-Sep-12 174 14-Aug-12 17-Oct-12 14-Oct-12 02-Apr-13 0% 0%SubmiSubmission 38 01-Jul-12 13-Aug-12 174 14-Aug-12 29-Sep-12 20-Nov-12 13-Mar-13 0% 0%A1212 Submission of Staircase Layout & Details 8 01-Jul-12 09-Jul-12 117 14-Aug-12 25-Aug-12 20-Nov-12 28-Nov-12 79 0% 0%
A1207 Submission of Reflected Ceil ing Layout 8 18-Jul-12 26-Jul-12 152 03-Sep-12 11-Sep-12 20-Jan-13 29-Jan-13 114 0% 0%
A1212 Submission of Handrail Layout & Details 8 18-Jul-12 26-Jul-12 105 03-Sep-12 11-Sep-12 24-Nov-12 03-Dec-12 67 0% 0%
A1207 Submission of Flooring Layout 8 25-Jul-12 02-Aug-12 136 22-Aug-12 30-Aug-12 08-Jan-13 16-Jan-13 114 0% 0%
A1207 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 05-Aug-12 13-Aug-12 174 20-Sep-12 29-Sep-12 05-Mar-13 13-Mar-13 136 0% 0%ApprovApproval 46 01-Jul-12 04-Sep-12 145 14-Aug-12 17-Oct-12 14-Oct-12 02-Apr-13 0% 0%A1208 Approval of Block Work Setting Out Plan for Ground 14 01-Jul-12 18-Jul-12 73 14-Aug-12 04-Sep-12 14-Oct-12 01-Nov-12 41 0% 0%
A1213 Approval of Staircase Layout & Details 14 10-Jul-12 29-Jul-12 98 26-Aug-12 12-Sep-12 29-Nov-12 19-Dec-12 67 0% 0%
A1208 Approval of Reflected Ceiling Layout 14 29-Jul-12 15-Aug-12 126 12-Sep-12 01-Oct-12 30-Jan-13 18-Feb-13 95 0% 0%
A1213 Approval of Handrail Layout & Details 14 29-Jul-12 15-Aug-12 87 12-Sep-12 01-Oct-12 04-Dec-12 23-Dec-12 56 0% 0%
A1208 Approval of Flooring Layout 14 05-Aug-12 26-Aug-12 113 02-Sep-12 19-Sep-12 17-Jan-13 06-Feb-13 95 0% 0%
A1208 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 14-Aug-12 04-Sep-12 145 30-Sep-12 17-Oct-12 14-Mar-13 02-Apr-13 114 0% 0%Typical Typical Floors 53 01-Jul-12 02-Sep-12 162 14-Aug-12 16-Oct-12 14-Aug-12 17-Mar-13 0% 0%GeneralGeneral 40 01-Jul-12 15-Aug-12 44 14-Aug-12 02-Oct-12 14-Aug-12 08-Oct-12 0% 0%SubmSubmission 24 01-Jul-12 28-Jul-12 43 14-Aug-12 12-Sep-12 14-Aug-12 18-Sep-12 0% 0%A1199 Submission of Block Work Setting Out Plan for 1st Floor 8 01-Jul-12 09-Jul-12 38 14-Aug-12 25-Aug-12 14-Aug-12 25-Aug-12 0 0% 0%
A1196 Submission of Block Work Setting Out Plan for 2nd Floor 8 10-Jul-12 18-Jul-12 38 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0 0% 0%
A1197 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 19-Jul-12 28-Jul-12 43 04-Sep-12 12-Sep-12 10-Sep-12 18-Sep-12 5 0% 0%ApproApproval 27 10-Jul-12 15-Aug-12 36 26-Aug-12 02-Oct-12 26-Aug-12 08-Oct-12 0% 0%A1199 Approval of Block Work Setting Out Plan for 1st Floor 14 10-Jul-12 29-Jul-12 31 26-Aug-12 12-Sep-12 26-Aug-12 12-Sep-12 0 0% 0%
A1199 Approval of Block Work Setting Out Plan for 2nd Floor 14 19-Jul-12 07-Aug-12 31 04-Sep-12 23-Sep-12 04-Sep-12 23-Sep-12 0 0% 0%
A1199 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 29-Jul-12 15-Aug-12 36 13-Sep-12 02-Oct-12 19-Sep-12 08-Oct-12 4 0% 0%CorridCorridor / General 25 02-Aug-12 02-Sep-12 162 18-Sep-12 16-Oct-12 14-Feb-13 17-Mar-13 0% 0%SubmSubmission 8 02-Aug-12 11-Aug-12 162 18-Sep-12 26-Sep-12 14-Feb-13 25-Feb-13 0% 0%A1212 Submission of Staircase Layout & Details 8 02-Aug-12 11-Aug-12 160 18-Sep-12 26-Sep-12 14-Feb-13 23-Feb-13 122 0% 0%
A1212 Submission of Handrail Layout & Details 8 02-Aug-12 11-Aug-12 162 18-Sep-12 26-Sep-12 17-Feb-13 25-Feb-13 124 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Block Work Setting Out Plan for Ground
Submission of Reflected Ceil ing Layout
Submission of Flooring Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Approval of Block Work Setting Out Plan for Ground
Approval of Reflected Cei ling Layout
Approval of Flooring Layout
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Reflected Ceil ing Layout
Approval of Reflected Ceiling Layout
Submission of Reflected Ceil ing Layout
Approval of Reflected Ceiling Layout
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Block Work Setting Out Plan for 7th Floor
oor Approval of Block Work Setting Out Plan for 2nd Floor
r Approval of Block Work Setting Out Plan for 1st Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Landscaping's Water Proofing Details
Submission of Reflected Ceil ing Layout
Submission of Landscaping Layout & Details
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Pool Deck Layout
Approval of Landscaping's Water Proofing Details
Approval of Reflected Ceiling Layout
Approval of Landscaping Layout & Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Submission of Reflected Ceil ing Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Reflected Cei ling Layout
Approval of Wet Area Ceramic & Pocalin Layout
Submission of Block Work Setting Out Plan for Roof&Upper Roof
Submission of Roof's Water Proofing System
Submission of Flooring Layout
Approval of Block Work Setting Out Plan for for Roof&Upper Roo
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Reflected Ceil ing Layout
Submission of Flooring
Submission of Doors Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Reflected Ceiling Layout
Submission of Handrail Layout & Details
Submission of Flooring
Submission of Doors Details
Submission of Reflected Ceil ing Layout
Submission of Staircase Layout & Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Flooring
Approval of Doors Details
Approval of Reflected Cei ling Layout
Submission of Staircase Layout & Details
Submission of Reflected Ceil ing Layout
Submission of Handrail Layout & Details
Submission of Flooring Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Block Work Setting Out Plan for Ground
Approval of Staircase Layout & Details
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Flooring Layout
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Block Work Setting Out Plan for 1st Floor
Submission of Block Work Setting Out Plan for 2nd Floor
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Approval of Block Work Setting Out Plan for 1st Floor
Approval of Block Work Setting Out Plan for 2nd Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 3 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
ApproApproval 14 12-Aug-12 02-Sep-12 135 27-Sep-12 16-Oct-12 24-Feb-13 17-Mar-13 0% 0%A1213 Approval of Staircase Layout & Details 14 12-Aug-12 02-Sep-12 133 27-Sep-12 16-Oct-12 24-Feb-13 13-Mar-13 101 0% 0%
A1213 Approval of Handrail Layout & Details 14 12-Aug-12 02-Sep-12 135 27-Sep-12 16-Oct-12 26-Feb-13 17-Mar-13 103 0% 0%Two BTwo Bed Room Apartements 8 14-Aug-12 25-Aug-12 145 30-Sep-12 08-Oct-12 09-Feb-13 17-Feb-13 0% 0%SubmSubmission 8 14-Aug-12 25-Aug-12 145 30-Sep-12 08-Oct-12 09-Feb-13 17-Feb-13 0% 0%A1202 Submission of Wet Area Ceramic & Pocalin Layout 8 14-Aug-12 25-Aug-12 145 30-Sep-12 08-Oct-12 09-Feb-13 17-Feb-13 107 0% 0%
Three Three Bed Room Apartements 8 14-Aug-12 25-Aug-12 138 30-Sep-12 08-Oct-12 31-Jan-13 09-Feb-13 0% 0%SubmSubmission 8 14-Aug-12 25-Aug-12 138 30-Sep-12 08-Oct-12 31-Jan-13 09-Feb-13 0% 0%A1205 Submission of Wet Area Ceramic & Pocalin Layout 8 14-Aug-12 25-Aug-12 138 30-Sep-12 08-Oct-12 31-Jan-13 09-Feb-13 100 0% 0%
MEPMEP 158 08-Mar-12 A 03-Sep-12 215 18-Feb-12 30-Aug-12 02-Apr-12 19-May-13 73.36% 2.76%
Hotel ApHotel Apartements (Block A) 155 08-Mar-12 A 30-Aug-12 203 18-Feb-12 30-Aug-12 02-Apr-12 01-May-13 68.94% 1.26%
2nd Bas2nd Basement Floor 131 08-Mar-12 A 31-Jul-12 180 18-Feb-12 26-Apr-12 31-Oct-12 07-Mar-13 100% 9.21%SubmiSubmission 10 01-Jul-12 11-Jul-12 175 18-Feb-12 08-Apr-12 28-Nov-12 10-Feb-13 100% 0%A1355 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 124 18-Feb-12 28-Feb-12 28-Nov-12 10-Dec-12 238 100% 0%
A1385 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 28-Mar-12 08-Apr-12 30-Jan-13 10-Feb-13 255 100% 0%ApprovApproval 109 08-Mar-12 A 31-Jul-12 150 29-Feb-12 26-Apr-12 31-Oct-12 07-Mar-13 100% 12.5%A1247 Approval of HVAC Layout & Details 14 19-Mar-12 A 09-Jul-12 92 29-Feb-12 19-Mar-12 31-Oct-12 20-Nov-12 171 100% 50%
A1248 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 159 29-Feb-12 19-Mar-12 18-Feb-13 07-Mar-13 245 100% 0%
A1248 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 103 29-Feb-12 19-Mar-12 11-Dec-12 30-Dec-12 198 100% 0%
A1248 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 09-Apr-12 26-Apr-12 11-Feb-13 28-Feb-13 212 100% 0%1st Bas1st Basement Floor 119 15-Mar-12 A 31-Jul-12 154 03-Mar-12 02-Apr-12 28-Nov-12 05-Feb-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 124 03-Mar-12 13-Mar-12 28-Nov-12 10-Dec-12 100% 0%A1249 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 124 03-Mar-12 13-Mar-12 28-Nov-12 10-Dec-12 226 100% 0%
ApprovApproval 99 15-Mar-12 A 31-Jul-12 128 14-Mar-12 02-Apr-12 11-Dec-12 05-Feb-13 100% 0%A1250 Approval of Fire Alarm Layout & Details 14 15-Mar-12 A 18-Jul-12 137 14-Mar-12 02-Apr-12 16-Jan-13 05-Feb-13 213 100% 0%
A1251 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 103 14-Mar-12 02-Apr-12 11-Dec-12 30-Dec-12 188 100% 0%GroundGround Floor 107 02-Apr-12 A 31-Jul-12 160 17-Mar-12 16-Apr-12 01-Nov-12 12-Feb-13 100% 18.42%SubmiSubmission 10 01-Jul-12 11-Jul-12 160 17-Mar-12 27-Mar-12 12-Jan-13 22-Jan-13 100% 0%A1252 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 160 17-Mar-12 27-Mar-12 12-Jan-13 22-Jan-13 250 100% 0%
ApprovApproval 89 02-Apr-12 A 31-Jul-12 133 28-Mar-12 16-Apr-12 01-Nov-12 12-Feb-13 100% 25%A1253 Approval of HVAC Layout & Details 14 02-Apr-12 A 09-Jul-12 93 28-Mar-12 16-Apr-12 01-Nov-12 21-Nov-12 152 100% 50%
A1253 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 133 28-Mar-12 16-Apr-12 23-Jan-13 12-Feb-13 208 100% 0%1st Floor1st Floor 80 30-Apr-12 A 31-Jul-12 192 13-Mar-12 29-Apr-12 02-Apr-12 21-Mar-13 100% 8.14%SubmiSubmission 10 01-Jul-12 11-Jul-12 193 13-Mar-12 09-Apr-12 30-Jan-13 03-Mar-13 100% 0%A1255 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 193 29-Mar-12 09-Apr-12 20-Feb-13 03-Mar-13 272 100% 0%
A1255 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 183 29-Mar-12 09-Apr-12 09-Feb-13 19-Feb-13 262 100% 0%
A1256 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 13-Mar-12 24-Mar-12 30-Jan-13 10-Feb-13 268 100% 0%ApprovApproval 67 30-Apr-12 A 31-Jul-12 160 25-Mar-12 29-Apr-12 02-Apr-12 21-Mar-13 100% 12.5%A1258 Approval of MEP Builder Work Layout 14 30-Apr-12 A 01-Jul-12 20 02-Apr-12 19-Apr-12 02-Apr-12 19-Apr-12 0 100% 50%
A1257 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 160 10-Apr-12 29-Apr-12 04-Mar-13 21-Mar-13 226 100% 0%
A1257 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1257 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 25-Mar-12 11-Apr-12 11-Feb-13 28-Feb-13 223 100% 0%2nd Flo2nd Floor 48 05-Jun-12 A 31-Jul-12 183 29-Mar-12 16-May-12 28-Aug-12 11-Mar-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 183 29-Mar-12 26-Apr-12 28-Aug-12 19-Feb-13 100% 0%A1259 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 48 16-Apr-12 26-Apr-12 28-Aug-12 08-Sep-12 112 100% 0%
A1258 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 163 03-Apr-12 14-Apr-12 15-Jan-13 27-Jan-13 238 100% 0%
A1259 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 183 29-Mar-12 09-Apr-12 09-Feb-13 19-Feb-13 262 100% 0%ApprovApproval 40 05-Jun-12 A 31-Jul-12 152 10-Apr-12 16-May-12 09-Sep-12 11-Mar-13 100% 0%A1260 Approval of CCTV,Access Control,Intercom Layout & Details 14 05-Jun-12 A 18-Jul-12 161 10-Apr-12 29-Apr-12 20-Feb-13 11-Mar-13 218 100% 0%
A1260 Approval of BMS Layout & Details 14 05-Jun-12 A 18-Jul-12 157 10-Apr-12 29-Apr-12 14-Feb-13 05-Mar-13 214 100% 0%
A1260 Approval of Data & Telephone Layout & Details 14 05-Jun-12 A 18-Jul-12 161 10-Apr-12 29-Apr-12 20-Feb-13 11-Mar-13 218 100% 0%
A1261 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 39 29-Apr-12 16-May-12 09-Sep-12 26-Sep-12 92 100% 0%
A1260 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 135 15-Apr-12 02-May-12 28-Jan-13 14-Feb-13 198 100% 0%
A1260 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 152 10-Apr-12 29-Apr-12 20-Feb-13 11-Mar-13 218 100% 0%3rd Floor3rd Floor 27 01-Jul-12 31-Jul-12 188 29-Mar-12 16-May-12 13-Sep-12 17-Mar-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 188 29-Mar-12 26-Apr-12 13-Sep-12 25-Feb-13 100% 0%A1262 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 62 16-Apr-12 26-Apr-12 13-Sep-12 24-Sep-12 126 100% 0%
A1262 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 172 03-Apr-12 14-Apr-12 27-Jan-13 06-Feb-13 247 100% 0%
A1261 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1261 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1261 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 29-Mar-12 09-Apr-12 07-Feb-13 18-Feb-13 261 100% 0%
A1261 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 29-Mar-12 09-Apr-12 13-Feb-13 24-Feb-13 266 100% 0%ApprovApproval 14 12-Jul-12 31-Jul-12 156 10-Apr-12 16-May-12 25-Sep-12 17-Mar-13 100% 0%A1264 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 51 29-Apr-12 16-May-12 25-Sep-12 14-Oct-12 104 100% 0%
A1263 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 143 15-Apr-12 02-May-12 07-Feb-13 26-Feb-13 206 100% 0%
A1262 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1263 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1263 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 10-Apr-12 29-Apr-12 19-Feb-13 10-Mar-13 217 100% 0%
A1263 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 0%4th Floor4th Floor 27 01-Jul-12 31-Jul-12 203 29-Mar-12 29-May-12 20-Sep-12 03-Apr-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 204 29-Mar-12 09-May-12 20-Sep-12 16-Mar-13 100% 0%A1265 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 86 17-Apr-12 28-Apr-12 11-Oct-12 22-Oct-12 149 100% 0%
A1265 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 68 29-Apr-12 09-May-12 20-Sep-12 01-Oct-12 121 100% 0%
A1265 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 204 17-Apr-12 28-Apr-12 05-Mar-13 16-Mar-13 267 100% 0%
A1264 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1264 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1264 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 29-Mar-12 09-Apr-12 07-Feb-13 18-Feb-13 261 100% 0%
A1264 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 29-Mar-12 09-Apr-12 13-Feb-13 24-Feb-13 266 100% 0%ApprovApproval 14 12-Jul-12 31-Jul-12 169 10-Apr-12 29-May-12 02-Oct-12 03-Apr-13 100% 0%A1266 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 71 29-Apr-12 16-May-12 23-Oct-12 12-Nov-12 124 100% 0%
A1267 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 56 10-May-12 29-May-12 02-Oct-12 21-Oct-12 100 100% 0%
A1266 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 169 29-Apr-12 16-May-12 17-Mar-13 03-Apr-13 222 100% 0%
A1265 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1266 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1266 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 10-Apr-12 29-Apr-12 19-Feb-13 10-Mar-13 217 100% 0%
A1266 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 0%5th Floor5th Floor 27 01-Jul-12 31-Jul-12 222 29-Mar-12 28-Jun-12 13-Oct-12 25-Apr-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 223 29-Mar-12 09-Jun-12 13-Oct-12 07-Apr-13 100% 0%A1268 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 103 28-May-12 07-Jun-12 03-Nov-12 13-Nov-12 131 100% 0%
A1268 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 87 29-May-12 09-Jun-12 13-Oct-12 23-Oct-12 114 100% 0%
A1268 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 223 28-May-12 07-Jun-12 27-Mar-13 07-Apr-13 251 100% 0%
A1267 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1267 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1267 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 29-Mar-12 09-Apr-12 07-Feb-13 18-Feb-13 261 100% 0%
A1267 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 29-Mar-12 09-Apr-12 13-Feb-13 24-Feb-13 266 100% 0%ApprovApproval 14 12-Jul-12 31-Jul-12 185 10-Apr-12 28-Jun-12 24-Oct-12 25-Apr-13 100% 0%A1269 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 86 10-Jun-12 28-Jun-12 14-Nov-12 05-Dec-12 109 100% 0%
A1270 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 72 10-Jun-12 28-Jun-12 24-Oct-12 13-Nov-12 95 100% 0%
A1269 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 185 10-Jun-12 28-Jun-12 08-Apr-13 25-Apr-13 208 100% 0%
A1268 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1269 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1269 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 10-Apr-12 29-Apr-12 19-Feb-13 10-Mar-13 217 100% 0%
A1269 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 0%6th Floor6th Floor 27 01-Jul-12 31-Jul-12 188 29-Mar-12 24-Jul-12 10-Nov-12 17-Mar-13 89.29% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 188 29-Mar-12 04-Jul-12 10-Nov-12 25-Feb-13 94.29% 0%A1271 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 109 28-May-12 07-Jun-12 10-Nov-12 21-Nov-12 137 100% 0%
A1271 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 111 24-Jun-12 04-Jul-12 12-Nov-12 24-Nov-12 117 60% 0%
A1271 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 172 28-May-12 07-Jun-12 27-Jan-13 06-Feb-13 200 100% 0%
A1270 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1270 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1270 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 29-Mar-12 09-Apr-12 07-Feb-13 18-Feb-13 261 100% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Wet Area Ceramic & Pocalin Layout
Submission of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of ELV Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Submission of Fire Alarm Layout & Details
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of MEP Builder Work Layout
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 4 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1270 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 29-Mar-12 09-Apr-12 13-Feb-13 24-Feb-13 266 100% 0%ApprovApproval 14 12-Jul-12 31-Jul-12 156 10-Apr-12 24-Jul-12 22-Nov-12 17-Mar-13 85.71% 0%A1272 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 91 10-Jun-12 28-Jun-12 22-Nov-12 12-Dec-12 114 100% 0%
A1273 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 92 05-Jul-12 24-Jul-12 25-Nov-12 13-Dec-12 97 0% 0%
A1272 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 143 10-Jun-12 28-Jun-12 07-Feb-13 26-Feb-13 166 100% 0%
A1271 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1272 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1272 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 10-Apr-12 29-Apr-12 19-Feb-13 10-Mar-13 217 100% 0%
A1272 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 0%7th Floor7th Floor 38 01-Jul-12 13-Aug-12 177 29-Mar-12 13-Aug-12 14-Jul-12 17-Mar-13 59.75% 0%SubmiSubmission 21 01-Jul-12 24-Jul-12 177 29-Mar-12 24-Jul-12 14-Jul-12 25-Feb-13 80.2% 0%A1274 Submission of Lighting Layout & Details 10 01-Jul-12 11-Jul-12 103 14-Jun-12 26-Jun-12 03-Nov-12 13-Nov-12 116 100% 0%
A1274 Submission of Power Layout & Details 10 01-Jul-12 11-Jul-12 103 14-Jun-12 26-Jun-12 03-Nov-12 13-Nov-12 116 100% 0%
A1274 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 181 14-Jun-12 26-Jun-12 06-Feb-13 17-Feb-13 194 100% 0%
A1273 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1273 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 188 29-Mar-12 09-Apr-12 14-Feb-13 25-Feb-13 267 100% 0%
A1273 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 178 29-Mar-12 09-Apr-12 03-Feb-13 13-Feb-13 257 100% 0%
A1273 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 29-Mar-12 09-Apr-12 13-Feb-13 24-Feb-13 266 100% 0%
A1274 Submission of HVAC Layout & Details 11 01-Jul-12 12-Jul-12 110 14-Jun-12 27-Jun-12 11-Nov-12 24-Nov-12 123 100% 0%
A1274 Submission of MEP Cordination Layout 10 14-Jul-12 24-Jul-12 103 14-Jul-12 24-Jul-12 17-Nov-12 27-Nov-12 103 0% 0%
A1274 Submission of MEP Builder Work Layout 10 14-Jul-12 24-Jul-12 5 14-Jul-12 24-Jul-12 14-Jul-12 24-Jul-12 0 0% 0%ApprovApproval 23 12-Jul-12 13-Aug-12 147 10-Apr-12 13-Aug-12 25-Jul-12 17-Mar-13 45% 0%A1275 Approval of Lighting Layout & Details 14 12-Jul-12 31-Jul-12 86 27-Jun-12 16-Jul-12 14-Nov-12 05-Dec-12 97 14.29% 0%
A1275 Approval of Power Layout & Details 14 12-Jul-12 31-Jul-12 86 27-Jun-12 16-Jul-12 14-Nov-12 05-Dec-12 97 14.29% 0%
A1275 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 150 27-Jun-12 16-Jul-12 18-Feb-13 07-Mar-13 161 14.29% 0%
A1274 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1275 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 156 10-Apr-12 29-Apr-12 26-Feb-13 17-Mar-13 222 100% 0%
A1275 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 148 10-Apr-12 29-Apr-12 14-Feb-13 05-Mar-13 214 100% 0%
A1275 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 10-Apr-12 29-Apr-12 25-Feb-13 14-Mar-13 221 100% 0%
A1275 Approval of HVAC Layout & Details 14 15-Jul-12 01-Aug-12 91 28-Jun-12 17-Jul-12 25-Nov-12 13-Dec-12 102 7.14% 0%
A1276 Approval of MEP Cordination Layout 14 25-Jul-12 13-Aug-12 86 25-Jul-12 13-Aug-12 28-Nov-12 18-Dec-12 86 0% 0%
A1276 Approval of MEP Builder Work Layout 14 25-Jul-12 13-Aug-12 4 25-Jul-12 13-Aug-12 25-Jul-12 13-Aug-12 0 0% 0%Roof FRoof Floor 47 01-Jul-12 26-Aug-12 207 21-Apr-12 26-Aug-12 23-Jul-12 01-May-13 10.67% 0%SubmiSubmission 30 01-Jul-12 04-Aug-12 208 21-Apr-12 04-Aug-12 23-Jul-12 13-Apr-13 10.1% 0%A1276 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 163 21-Apr-12 01-May-12 15-Jan-13 27-Jan-13 223 100% 0%
A1276 Submission of Lighting Layout & Details 10 07-Jul-12 17-Jul-12 120 07-Jul-12 17-Jul-12 29-Nov-12 11-Dec-12 120 0% 0%
A1276 Submission of Power Layout & Details 10 07-Jul-12 17-Jul-12 120 07-Jul-12 17-Jul-12 29-Nov-12 11-Dec-12 120 0% 0%
A1277 Submission of Fire Alarm Layout & Details 10 07-Jul-12 17-Jul-12 223 07-Jul-12 17-Jul-12 02-Apr-13 13-Apr-13 223 0% 0%
A1277 Submission of Drainage Layout & Details 14 03-Jul-12 18-Jul-12 17 03-Jul-12 18-Jul-12 23-Jul-12 07-Aug-12 17 0% 0%
A1277 Submission of Water Supply Layout & Details 14 03-Jul-12 18-Jul-12 101 03-Jul-12 18-Jul-12 03-Nov-12 19-Nov-12 101 0% 0%
A1277 Submission of HVAC Layout & Details 11 07-Jul-12 18-Jul-12 101 07-Jul-12 18-Jul-12 06-Nov-12 19-Nov-12 101 0% 0%
A1277 Submission of MEP Cordination Layout 10 24-Jul-12 04-Aug-12 87 24-Jul-12 04-Aug-12 07-Nov-12 19-Nov-12 87 0% 0%
A1277 Submission of MEP Builder Work Layout 10 24-Jul-12 04-Aug-12 17 24-Jul-12 04-Aug-12 13-Aug-12 26-Aug-12 17 0% 0%ApprovApproval 30 12-Jul-12 26-Aug-12 173 02-May-12 26-Aug-12 27-Aug-12 01-May-13 11.11% 0%A1278 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 135 02-May-12 21-May-12 28-Jan-13 14-Feb-13 185 100% 0%
A1278 Approval of Lighting Layout & Details 14 18-Jul-12 06-Aug-12 100 18-Jul-12 06-Aug-12 12-Dec-12 31-Dec-12 100 0% 0%
A1278 Approval of Power Layout & Details 14 18-Jul-12 06-Aug-12 100 18-Jul-12 06-Aug-12 12-Dec-12 31-Dec-12 100 0% 0%
A1278 Approval of Fire Alarm Layout & Details 14 18-Jul-12 06-Aug-12 185 18-Jul-12 06-Aug-12 14-Apr-13 01-May-13 185 0% 0%
A1278 Approval of Drainage Layout & Details 14 19-Jul-12 07-Aug-12 106 19-Jul-12 07-Aug-12 23-Dec-12 10-Jan-13 106 0% 0%
A1278 Approval of Water Supply Layout & Details 14 19-Jul-12 07-Aug-12 99 19-Jul-12 07-Aug-12 12-Dec-12 31-Dec-12 99 0% 0%
A1279 Approval of HVAC Layout & Details 14 19-Jul-12 07-Aug-12 84 19-Jul-12 07-Aug-12 20-Nov-12 10-Dec-12 84 0% 0%
A1279 Approval of MEP Cordination Layout 14 05-Aug-12 26-Aug-12 73 05-Aug-12 26-Aug-12 20-Nov-12 10-Dec-12 73 0% 0%
A1279 Approval of MEP Builder Work Layout 14 05-Aug-12 26-Aug-12 14 05-Aug-12 26-Aug-12 27-Aug-12 13-Sep-12 14 0% 0%Upper RUpper Roof Floor 41 12-Jul-12 30-Aug-12 172 12-Jul-12 30-Aug-12 30-Aug-12 26-Mar-13 0% 0%SubmiSubmission 24 12-Jul-12 08-Aug-12 163 12-Jul-12 08-Aug-12 30-Aug-12 24-Feb-13 0% 0%A1279 Submission of Lighting Layout & Details 10 16-Jul-12 26-Jul-12 174 16-Jul-12 26-Jul-12 13-Feb-13 24-Feb-13 174 0% 0%
A1279 Submission of Power Layout & Details 10 16-Jul-12 26-Jul-12 174 16-Jul-12 26-Jul-12 13-Feb-13 24-Feb-13 174 0% 0%
A1280 Submission of Fire Alarm Layout & Details 10 16-Jul-12 26-Jul-12 41 16-Jul-12 26-Jul-12 04-Sep-12 15-Sep-12 41 0% 0%
A1280 Submission of Drainage Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1280 Submission of Water Supply Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1280 Submission of Fire Fighting Layout & Details 11 16-Jul-12 28-Jul-12 40 16-Jul-12 28-Jul-12 03-Sep-12 15-Sep-12 40 0% 0%
A1280 Submission of HVAC Layout & Details 11 16-Jul-12 28-Jul-12 163 16-Jul-12 28-Jul-12 31-Jan-13 12-Feb-13 163 0% 0%
A1280 Submission of MEP Cordination Layout 10 29-Jul-12 08-Aug-12 163 29-Jul-12 08-Aug-12 13-Feb-13 24-Feb-13 163 0% 0%ApprovApproval 23 29-Jul-12 30-Aug-12 143 29-Jul-12 30-Aug-12 16-Sep-12 26-Mar-13 0% 0%A1281 Approval of Drainage Layout & Details 14 29-Jul-12 15-Aug-12 152 29-Jul-12 15-Aug-12 07-Mar-13 26-Mar-13 152 0% 0%
A1281 Approval of Water Supply Layout & Details 14 29-Jul-12 15-Aug-12 152 29-Jul-12 15-Aug-12 07-Mar-13 26-Mar-13 152 0% 0%
A1281 Approval of Fire Fighting Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1282 Approval of HVAC Layout & Details 14 29-Jul-12 15-Aug-12 144 29-Jul-12 15-Aug-12 25-Feb-13 14-Mar-13 144 0% 0%
A1281 Approval of Lighting Layout & Details 14 29-Jul-12 15-Aug-12 144 29-Jul-12 15-Aug-12 25-Feb-13 14-Mar-13 144 0% 0%
A1281 Approval of Power Layout & Details 14 29-Jul-12 15-Aug-12 144 29-Jul-12 15-Aug-12 25-Feb-13 14-Mar-13 144 0% 0%
A1281 Approval of Fire Alarm Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1282 Approval of MEP Cordination Layout 14 09-Aug-12 30-Aug-12 135 09-Aug-12 30-Aug-12 25-Feb-13 14-Mar-13 135 0% 0%
Hotel (BlHotel (Block B) 110 08-Mar-12 A 03-Sep-12 215 29-Feb-12 30-Aug-12 13-Jun-12 19-May-13 75.53% 3.68%
2nd Bas2nd Basement Floor 68 08-Mar-12 A 31-Jul-12 185 29-Feb-12 30-Apr-12 30-Jan-13 13-Mar-13 100% 13.46%SubmiSubmission 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 100% 0%A1283 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%
ApprovApproval 57 08-Mar-12 A 31-Jul-12 154 29-Feb-12 30-Apr-12 07-Feb-13 13-Mar-13 100% 16.67%A1284 Approval of HVAC Layout & Details 14 18-Mar-12 A 09-Jul-12 159 29-Feb-12 19-Mar-12 07-Feb-13 26-Feb-13 238 100% 50%
A1284 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 163 29-Feb-12 19-Mar-12 24-Feb-13 13-Mar-13 249 100% 0%
A1285 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%1st Bas1st Basement Floor 27 01-Jul-12 31-Jul-12 184 10-Mar-12 30-Apr-12 04-Dec-12 12-Mar-13 100% 0%SubmiSubmission 10 01-Jul-12 11-Jul-12 175 10-Mar-12 10-Apr-12 04-Dec-12 10-Feb-13 100% 0%A1286 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 128 10-Mar-12 20-Mar-12 04-Dec-12 15-Dec-12 224 100% 0%
A1286 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 23 01-Jul-12 31-Jul-12 153 21-Mar-12 30-Apr-12 16-Dec-12 12-Mar-13 100% 0%A1287 Approval of Fire Alarm Layout & Details 14 01-Jul-12 18-Jul-12 162 21-Mar-12 09-Apr-12 21-Feb-13 12-Mar-13 233 100% 0%
A1287 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 106 21-Mar-12 09-Apr-12 16-Dec-12 03-Jan-13 186 100% 0%
A1288 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%GroundGround Floor 65 17-May-12 A 01-Aug-12 236 28-Mar-12 03-May-12 04-Dec-12 13-May-13 100% 11.93%SubmiSubmission 12 01-Jul-12 14-Jul-12 235 28-Mar-12 15-Apr-12 04-Dec-12 23-Apr-13 100% 0%A1289 Submission of LPG & Gas Detection Layout & Details 8 01-Jul-12 09-Jul-12 177 02-Apr-12 10-Apr-12 02-Feb-13 10-Feb-13 253 100% 0%
A1288 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 166 28-Mar-12 08-Apr-12 19-Jan-13 30-Jan-13 246 100% 0%
A1289 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 237 28-Mar-12 08-Apr-12 13-Apr-13 23-Apr-13 317 100% 0%
A1289 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 128 28-Mar-12 08-Apr-12 04-Dec-12 15-Dec-12 208 100% 0%
A1288 Submission of MEP Cordination Layout 12 01-Jul-12 14-Jul-12 155 02-Apr-12 15-Apr-12 06-Jan-13 19-Jan-13 231 100% 0%ApprovApproval 54 17-May-12 A 01-Aug-12 196 09-Apr-12 03-May-12 16-Dec-12 13-May-13 100% 16.67%A1290 Approval of Lighting Layout & Details 14 28-May-12 A 09-Jul-12 146 09-Apr-12 26-Apr-12 20-Jan-13 07-Feb-13 197 100% 50%
A1290 Approval of Power Layout & Details 14 17-May-12 A 09-Jul-12 146 09-Apr-12 26-Apr-12 20-Jan-13 07-Feb-13 197 100% 50%
A1291 Approval of Drainage Layout & Details (High Level) 14 23-May-12 A 09-Jul-12 160 09-Apr-12 26-Apr-12 10-Feb-13 27-Feb-13 211 100% 50%
A1291 Approval of Data & Telephone Layout & Details 14 21-May-12 A 18-Jul-12 169 09-Apr-12 26-Apr-12 04-Mar-13 21-Mar-13 227 100% 0%
A1291 Approval of LPG & Gas Detection Layout & Details 14 10-Jul-12 29-Jul-12 147 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1290 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 138 09-Apr-12 26-Apr-12 31-Jan-13 19-Feb-13 205 100% 0%
A1290 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 197 09-Apr-12 26-Apr-12 24-Apr-13 13-May-13 264 100% 0%
A1290 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 106 09-Apr-12 26-Apr-12 16-Dec-12 03-Jan-13 173 100% 0%
A1290 Approval of MEP Cordination Layout 14 15-Jul-12 01-Aug-12 129 16-Apr-12 03-May-12 20-Jan-13 07-Feb-13 192 100% 0%1st Floor1st Floor 62 21-May-12 A 01-Aug-12 225 31-Mar-12 23-May-12 28-Oct-12 30-Apr-13 100% 8.33%SubmiSubmission 12 01-Jul-12 14-Jul-12 224 31-Mar-12 03-May-12 28-Oct-12 10-Apr-13 100% 0%A1292 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 226 16-Apr-12 26-Apr-12 31-Mar-13 10-Apr-13 290 100% 0%
A1292 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 139 16-Apr-12 26-Apr-12 17-Dec-12 27-Dec-12 203 100% 0%
A1292 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Data & Telephone Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Submission of Data & Telephone Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Approval of Data & Telephone Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of Fire Fighting Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of Fire Fighting Layout & Details
Approval of HVAC Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of MEP Cordination Layout
Submission of LPG & Gas Detection Layout & Details
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Submission of MEP Cordination Layout
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Drainage Layout & Details (High Level)
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 5 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1291 Submission of MEP Cordination Layout 12 01-Jul-12 14-Jul-12 98 21-Apr-12 03-May-12 28-Oct-12 10-Nov-12 158 100% 0%ApprovApproval 52 21-May-12 A 01-Aug-12 187 09-Apr-12 23-May-12 11-Nov-12 30-Apr-13 100% 11.11%A1293 Approval of Drainage Layout & Details (Low Level) 14 21-May-12 A 09-Jul-12 111 09-Apr-12 26-Apr-12 28-Nov-12 18-Dec-12 162 100% 50%
A1294 Approval of Drainage Layout & Details (High Level) 14 05-Jun-12 A 09-Jul-12 111 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 50%
A1293 Approval of HVAC Layout & Details 14 26-Jun-12 A 18-Jul-12 113 29-Apr-12 16-May-12 12-Dec-12 31-Dec-12 157 100% 0%
A1293 Approval of Lighting Layout & Details 14 26-Jun-12 A 18-Jul-12 92 29-Apr-12 16-May-12 11-Nov-12 29-Nov-12 136 100% 0%
A1293 Approval of Power Layout & Details 14 03-Jun-12 A 18-Jul-12 92 29-Apr-12 16-May-12 11-Nov-12 29-Nov-12 136 100% 0%
A1293 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 188 29-Apr-12 16-May-12 11-Apr-13 30-Apr-13 241 100% 0%
A1294 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 130 29-Apr-12 16-May-12 20-Jan-13 07-Feb-13 183 100% 0%
A1294 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1293 Approval of MEP Cordination Layout 14 15-Jul-12 01-Aug-12 82 06-May-12 23-May-12 11-Nov-12 29-Nov-12 131 100% 0%2nd Flo2nd Floor 48 05-Jun-12 A 31-Jul-12 234 31-Mar-12 13-Jun-12 10-Nov-12 09-May-13 100% 5.07%SubmiSubmission 10 01-Jul-12 11-Jul-12 235 31-Mar-12 24-May-12 10-Nov-12 21-Apr-13 100% 0%A1295 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 128 07-May-12 17-May-12 04-Dec-12 15-Dec-12 174 100% 0%
A1295 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 109 14-May-12 24-May-12 10-Nov-12 21-Nov-12 149 100% 0%
A1295 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 235 07-May-12 17-May-12 10-Apr-13 21-Apr-13 281 100% 0%
A1296 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 40 05-Jun-12 A 31-Jul-12 195 11-Apr-12 13-Jun-12 22-Nov-12 09-May-13 100% 7.14%A1296 Approval of Drainage Layout & Details 14 05-Jun-12 A 09-Jul-12 107 20-May-12 06-Jun-12 22-Nov-12 12-Dec-12 129 100% 50%
A1296 Approval of Lighting Layout & Details 14 01-Jul-12 18-Jul-12 100 20-May-12 06-Jun-12 22-Nov-12 12-Dec-12 129 100% 0%
A1296 Approval of Power Layout & Details 14 01-Jul-12 18-Jul-12 118 20-May-12 06-Jun-12 19-Dec-12 08-Jan-13 147 100% 0%
A1296 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 106 20-May-12 06-Jun-12 16-Dec-12 03-Jan-13 144 100% 0%
A1296 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 91 27-May-12 13-Jun-12 22-Nov-12 12-Dec-12 124 100% 0%
A1297 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 195 20-May-12 06-Jun-12 22-Apr-13 09-May-13 233 100% 0%
A1297 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%3rd Floor3rd Floor 83 25-Apr-12 A 31-Jul-12 224 31-Mar-12 05-Jul-12 13-Jun-12 28-Apr-13 96.12% 2.71%SubmiSubmission 10 01-Jul-12 11-Jul-12 224 31-Mar-12 14-Jun-12 13-Jun-12 08-Apr-13 100% 0%A1298 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 177 07-May-12 17-May-12 02-Feb-13 12-Feb-13 223 100% 0%
A1298 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 109 04-Jun-12 14-Jun-12 10-Nov-12 21-Nov-12 131 100% 0%
A1298 Submission of MEP Builder Work Layout 10 01-Jul-12 11-Jul-12 12 04-Jun-12 14-Jun-12 13-Jun-12 25-Jun-12 8 100% 0%
A1298 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 224 07-May-12 17-May-12 28-Mar-13 08-Apr-13 270 100% 0%
A1298 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1298 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1298 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1299 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 193 16-Apr-12 26-Apr-12 20-Feb-13 03-Mar-13 257 100% 0%
A1299 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 69 25-Apr-12 A 31-Jul-12 186 11-Apr-12 05-Jul-12 26-Jun-12 28-Apr-13 94.05% 4.17%A1300 Approval of CBS Layout & Details 14 25-Apr-12 A 09-Jul-12 167 20-May-12 06-Jun-12 19-Feb-13 10-Mar-13 189 100% 50%
A1299 Approval of Lighting Layout & Details 14 01-Jul-12 18-Jul-12 154 20-May-12 06-Jun-12 11-Feb-13 28-Feb-13 183 100% 0%
A1299 Approval of Power Layout & Details 14 01-Jul-12 18-Jul-12 154 20-May-12 06-Jun-12 11-Feb-13 28-Feb-13 183 100% 0%
A1299 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 147 20-May-12 06-Jun-12 13-Feb-13 04-Mar-13 185 100% 0%
A1299 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 91 18-Jun-12 05-Jul-12 22-Nov-12 12-Dec-12 109 64.29% 0%
A1299 Approval of MEP Builder Work Layout 14 12-Jul-12 31-Jul-12 10 18-Jun-12 05-Jul-12 26-Jun-12 15-Jul-12 6 64.29% 0%
A1300 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 186 20-May-12 06-Jun-12 09-Apr-13 28-Apr-13 224 100% 0%
A1300 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1300 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1300 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1300 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 160 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 0%
A1300 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%4th Floor4th Floor 82 26-Apr-12 A 31-Jul-12 219 31-Mar-12 05-Jul-12 10-Jul-12 22-Apr-13 96.12% 2.71%SubmiSubmission 10 01-Jul-12 11-Jul-12 219 31-Mar-12 16-Jun-12 10-Jul-12 02-Apr-13 100% 0%A1301 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 128 28-May-12 07-Jun-12 04-Dec-12 15-Dec-12 156 100% 0%
A1301 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 119 05-Jun-12 16-Jun-12 22-Nov-12 04-Dec-12 140 100% 0%
A1301 Submission of MEP Builder Work Layout 10 01-Jul-12 11-Jul-12 16 05-Jun-12 16-Jun-12 10-Jul-12 21-Jul-12 29 100% 0%
A1301 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 219 28-May-12 07-Jun-12 23-Mar-13 02-Apr-13 247 100% 0%
A1301 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1301 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1301 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1302 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 193 16-Apr-12 26-Apr-12 20-Feb-13 03-Mar-13 257 100% 0%
A1302 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 182 11-Apr-12 05-Jul-12 22-Jul-12 22-Apr-13 94.05% 4.17%A1303 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%
A1302 Approval of Lighting Layout & Details 14 01-Jul-12 18-Jul-12 108 10-Jun-12 28-Jun-12 05-Dec-12 24-Dec-12 122 100% 0%
A1302 Approval of Power Layout & Details 14 01-Jul-12 18-Jul-12 108 10-Jun-12 28-Jun-12 05-Dec-12 24-Dec-12 122 100% 0%
A1302 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 106 10-Jun-12 28-Jun-12 16-Dec-12 03-Jan-13 129 100% 0%
A1302 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 99 18-Jun-12 05-Jul-12 05-Dec-12 24-Dec-12 117 64.29% 0%
A1302 Approval of MEP Builder Work Layout 14 12-Jul-12 31-Jul-12 13 18-Jun-12 05-Jul-12 22-Jul-12 08-Aug-12 24 64.29% 0%
A1303 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 182 10-Jun-12 28-Jun-12 03-Apr-13 22-Apr-13 205 100% 0%
A1303 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1303 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1303 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1303 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 160 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 0%
A1303 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%5th Floor5th Floor 82 26-Apr-12 A 31-Jul-12 213 31-Mar-12 05-Jul-12 10-Jul-12 15-Apr-13 96.12% 2.71%SubmiSubmission 10 01-Jul-12 11-Jul-12 213 31-Mar-12 16-Jun-12 10-Jul-12 26-Mar-13 100% 0%A1304 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 134 28-May-12 07-Jun-12 11-Dec-12 22-Dec-12 162 100% 0%
A1304 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 124 05-Jun-12 16-Jun-12 28-Nov-12 10-Dec-12 145 100% 0%
A1304 Submission of MEP Builder Work Layout 10 01-Jul-12 11-Jul-12 16 05-Jun-12 16-Jun-12 10-Jul-12 21-Jul-12 29 100% 0%
A1304 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 213 28-May-12 07-Jun-12 16-Mar-13 26-Mar-13 241 100% 0%
A1304 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1304 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1304 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1305 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 193 16-Apr-12 26-Apr-12 20-Feb-13 03-Mar-13 257 100% 0%
A1305 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 177 11-Apr-12 05-Jul-12 22-Jul-12 15-Apr-13 94.05% 4.17%A1306 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%
A1305 Approval of Lighting Layout & Details 14 01-Jul-12 18-Jul-12 160 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 0%
A1305 Approval of Power Layout & Details 14 01-Jul-12 18-Jul-12 160 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 0%
A1305 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 111 10-Jun-12 28-Jun-12 23-Dec-12 10-Jan-13 134 100% 0%
A1305 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 103 18-Jun-12 05-Jul-12 11-Dec-12 30-Dec-12 121 64.29% 0%
A1305 Approval of MEP Builder Work Layout 14 12-Jul-12 31-Jul-12 13 18-Jun-12 05-Jul-12 22-Jul-12 08-Aug-12 24 64.29% 0%
A1306 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 177 10-Jun-12 28-Jun-12 27-Mar-13 15-Apr-13 200 100% 0%
A1306 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1306 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1306 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1306 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 160 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 0%
A1306 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%6th Floor6th Floor 82 26-Apr-12 A 31-Jul-12 216 31-Mar-12 24-Jul-12 12-Aug-12 18-Apr-13 86.05% 2.71%SubmiSubmission 10 01-Jul-12 11-Jul-12 217 31-Mar-12 04-Jul-12 12-Aug-12 31-Mar-13 91.11% 0%A1307 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 143 28-May-12 07-Jun-12 22-Dec-12 02-Jan-13 171 100% 0%
A1307 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 136 24-Jun-12 04-Jul-12 13-Dec-12 24-Dec-12 142 60% 0%
A1307 Submission of MEP Builder Work Layout 10 01-Jul-12 11-Jul-12 43 24-Jun-12 04-Jul-12 12-Aug-12 25-Aug-12 42 60% 0%
A1307 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 217 28-May-12 07-Jun-12 20-Mar-13 31-Mar-13 245 100% 0%
A1307 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1307 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1307 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1308 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 193 16-Apr-12 26-Apr-12 20-Feb-13 03-Mar-13 257 100% 0%
A1308 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 180 11-Apr-12 24-Jul-12 26-Aug-12 18-Apr-13 83.33% 4.17%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of MEP Cordination Layout
Approval of Drainage Layout & Details (Low Level)
Approval of Drainage Layout & Details (High Level)
Approval of HVAC Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of MEP Cordination Layout
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of Drainage Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 6 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1309 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 10-Jun-12 28-Jun-12 19-Feb-13 10-Mar-13 174 100% 50%
A1308 Approval of Lighting Layout & Details 14 01-Jul-12 18-Jul-12 122 10-Jun-12 28-Jun-12 25-Dec-12 14-Jan-13 136 100% 0%
A1308 Approval of Power Layout & Details 14 01-Jul-12 18-Jul-12 122 10-Jun-12 28-Jun-12 25-Dec-12 14-Jan-13 136 100% 0%
A1308 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 119 10-Jun-12 28-Jun-12 03-Jan-13 22-Jan-13 142 100% 0%
A1308 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 113 05-Jul-12 24-Jul-12 25-Dec-12 14-Jan-13 118 0% 0%
A1308 Approval of MEP Builder Work Layout 14 12-Jul-12 31-Jul-12 35 05-Jul-12 24-Jul-12 26-Aug-12 12-Sep-12 34 0% 0%
A1309 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 180 10-Jun-12 28-Jun-12 01-Apr-13 18-Apr-13 203 100% 0%
A1309 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1309 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1309 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1309 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 160 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 0%
A1309 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%7th Floor7th Floor 109 26-Apr-12 A 03-Sep-12 189 31-Mar-12 13-Aug-12 30-Jul-12 18-Apr-13 60.26% 2.28%SubmiSubmission 37 01-Jul-12 12-Aug-12 190 31-Mar-12 24-Jul-12 30-Jul-12 31-Mar-13 84% 0%A1310 Submission of Lighting Layout & Details 10 01-Jul-12 11-Jul-12 141 14-Jun-12 26-Jun-12 19-Dec-12 30-Dec-12 154 100% 0%
A1310 Submission of Power Layout & Details 10 01-Jul-12 11-Jul-12 141 14-Jun-12 26-Jun-12 19-Dec-12 30-Dec-12 154 100% 0%
A1310 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 217 14-Jun-12 26-Jun-12 20-Mar-13 31-Mar-13 230 100% 0%
A1310 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1310 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1310 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 182 16-Apr-12 26-Apr-12 07-Feb-13 18-Feb-13 246 100% 0%
A1311 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 193 16-Apr-12 26-Apr-12 20-Feb-13 03-Mar-13 257 100% 0%
A1311 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%
A1310 Submission of HVAC Layout & Details 11 01-Jul-12 12-Jul-12 154 14-Jun-12 27-Jun-12 05-Jan-13 16-Jan-13 167 100% 0%
A1309 Submission of Drainage Layout & Details 14 01-Jul-12 16-Jul-12 29 11-Jun-12 27-Jun-12 30-Jul-12 14-Aug-12 41 100% 0%
A1310 Submission of MEP Cordination Layout 10 01-Aug-12 12-Aug-12 114 14-Jul-12 24-Jul-12 19-Dec-12 30-Dec-12 130 0% 0%
A1310 Submission of MEP Builder Work Layout 10 01-Aug-12 12-Aug-12 29 14-Jul-12 24-Jul-12 02-Sep-12 12-Sep-12 41 0% 0%ApprovApproval 90 26-Apr-12 A 03-Sep-12 158 11-Apr-12 13-Aug-12 13-Sep-12 18-Apr-13 43.96% 3.85%A1312 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 167 27-Jun-12 16-Jul-12 19-Feb-13 10-Mar-13 162 14.29% 50%
A1311 Approval of Lighting Layout & Details 14 12-Jul-12 31-Jul-12 117 27-Jun-12 16-Jul-12 31-Dec-12 20-Jan-13 128 14.29% 0%
A1311 Approval of Power Layout & Details 14 12-Jul-12 31-Jul-12 117 27-Jun-12 16-Jul-12 31-Dec-12 20-Jan-13 128 14.29% 0%
A1312 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 180 27-Jun-12 16-Jul-12 01-Apr-13 18-Apr-13 191 14.29% 0%
A1312 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1312 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1312 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 151 29-Apr-12 16-May-12 19-Feb-13 10-Mar-13 204 100% 0%
A1312 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 160 29-Apr-12 16-May-12 04-Mar-13 21-Mar-13 213 100% 0%
A1312 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1311 Approval of HVAC Layout & Details 14 15-Jul-12 01-Aug-12 128 28-Jun-12 17-Jul-12 17-Jan-13 06-Feb-13 139 7.14% 0%
A1311 Approval of Drainage Layout & Details 14 17-Jul-12 05-Aug-12 146 28-Jun-12 17-Jul-12 17-Feb-13 06-Mar-13 159 7.14% 0%
A1311 Approval of MEP Cordination Layout 14 13-Aug-12 03-Sep-12 95 25-Jul-12 13-Aug-12 31-Dec-12 20-Jan-13 108 0% 0%
A1311 Approval of MEP Builder Work Layout 14 13-Aug-12 03-Sep-12 24 25-Jul-12 13-Aug-12 13-Sep-12 02-Oct-12 34 0% 0%Roof FRoof Floor 102 26-Apr-12 A 26-Aug-12 222 31-Mar-12 26-Aug-12 18-Sep-12 19-May-13 30.87% 2.25%SubmiSubmission 30 01-Jul-12 04-Aug-12 222 31-Mar-12 04-Aug-12 18-Sep-12 29-Apr-13 31.01% 0%A1313 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 158 08-May-12 19-May-12 09-Jan-13 20-Jan-13 203 100% 0%
A1314 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 187 08-May-12 19-May-12 13-Feb-13 24-Feb-13 232 100% 0%
A1314 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
A1313 Submission of Lighting Layout & Details 10 07-Jul-12 17-Jul-12 153 07-Jul-12 17-Jul-12 09-Jan-13 20-Jan-13 153 0% 0%
A1313 Submission of Power Layout & Details 10 07-Jul-12 17-Jul-12 153 07-Jul-12 17-Jul-12 09-Jan-13 20-Jan-13 153 0% 0%
A1313 Submission of Fire Alarm Layout & Details 10 07-Jul-12 17-Jul-12 237 07-Jul-12 17-Jul-12 18-Apr-13 29-Apr-13 237 0% 0%
A1312 Submission of Drainage Layout & Details 14 03-Jul-12 18-Jul-12 64 03-Jul-12 18-Jul-12 18-Sep-12 03-Oct-12 64 0% 0%
A1312 Submission of Water Supply Layout & Details 14 03-Jul-12 18-Jul-12 153 03-Jul-12 18-Jul-12 06-Jan-13 21-Jan-13 153 0% 0%
A1313 Submission of HVAC Layout & Details 11 07-Jul-12 18-Jul-12 183 07-Jul-12 18-Jul-12 14-Feb-13 26-Feb-13 183 0% 0%
A1313 Submission of ELV Layout & Details 10 23-Jul-12 02-Aug-12 139 08-May-12 19-May-12 09-Jan-13 20-Jan-13 203 100% 0%
A1313 Submission of MEP Cordination Layout 10 24-Jul-12 04-Aug-12 169 24-Jul-12 04-Aug-12 16-Feb-13 26-Feb-13 169 0% 0%
A1313 Submission of MEP Builder Work Layout 10 24-Jul-12 04-Aug-12 64 24-Jul-12 04-Aug-12 09-Oct-12 20-Oct-12 64 0% 0%ApprovApproval 84 26-Apr-12 A 26-Aug-12 185 11-Apr-12 26-Aug-12 21-Oct-12 19-May-13 30.77% 3.85%A1315 Approval of CBS Layout & Details 14 26-Apr-12 A 16-Jul-12 142 18-Jul-12 06-Aug-12 21-Jan-13 10-Feb-13 127 0% 50%
A1315 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 131 20-May-12 06-Jun-12 21-Jan-13 10-Feb-13 169 100% 0%
A1315 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 155 20-May-12 06-Jun-12 25-Feb-13 14-Mar-13 193 100% 0%
A1315 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 143 11-Apr-12 30-Apr-12 07-Feb-13 26-Feb-13 208 100% 0%
A1314 Approval of Lighting Layout & Details 14 18-Jul-12 06-Aug-12 127 18-Jul-12 06-Aug-12 21-Jan-13 10-Feb-13 127 0% 0%
A1314 Approval of Power Layout & Details 14 18-Jul-12 06-Aug-12 127 18-Jul-12 06-Aug-12 21-Jan-13 10-Feb-13 127 0% 0%
A1315 Approval of Fire Alarm Layout & Details 14 18-Jul-12 06-Aug-12 197 18-Jul-12 06-Aug-12 30-Apr-13 19-May-13 197 0% 0%
A1314 Approval of Drainage Layout & Details 14 19-Jul-12 07-Aug-12 160 19-Jul-12 07-Aug-12 11-Mar-13 28-Mar-13 160 0% 0%
A1314 Approval of Water Supply Layout & Details 14 19-Jul-12 07-Aug-12 157 19-Jul-12 07-Aug-12 06-Mar-13 25-Mar-13 157 0% 0%
A1314 Approval of HVAC Layout & Details 14 19-Jul-12 07-Aug-12 152 19-Jul-12 07-Aug-12 27-Feb-13 18-Mar-13 152 0% 0%
A1314 Approval of MEP Cordination Layout 14 05-Aug-12 26-Aug-12 141 05-Aug-12 26-Aug-12 27-Feb-13 18-Mar-13 141 0% 0%
A1314 Approval of MEP Builder Work Layout 14 05-Aug-12 26-Aug-12 53 05-Aug-12 26-Aug-12 21-Oct-12 08-Nov-12 53 0% 0%
A1315 Approval of ELV Layout & Details 14 05-Aug-12 26-Aug-12 115 20-May-12 06-Jun-12 21-Jan-13 10-Feb-13 169 100% 0%Upper RUpper Roof Floor 51 01-Jul-12 30-Aug-12 148 31-Mar-12 30-Aug-12 30-Aug-12 26-Feb-13 10.62% 0%SubmiSubmission 34 01-Jul-12 08-Aug-12 148 31-Mar-12 08-Aug-12 30-Aug-12 06-Feb-13 10% 0%A1317 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
A1316 Submission of Lighting Layout & Details 10 16-Jul-12 26-Jul-12 144 16-Jul-12 26-Jul-12 08-Jan-13 19-Jan-13 144 0% 0%
A1316 Submission of Power Layout & Details 10 16-Jul-12 26-Jul-12 144 16-Jul-12 26-Jul-12 08-Jan-13 19-Jan-13 144 0% 0%
A1316 Submission of Fire Alarm Layout & Details 10 16-Jul-12 26-Jul-12 41 16-Jul-12 26-Jul-12 04-Sep-12 15-Sep-12 41 0% 0%
A1315 Submission of Drainage Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1315 Submission of Water Supply Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1315 Submission of Fire Fighting Layout & Details 11 16-Jul-12 28-Jul-12 40 16-Jul-12 28-Jul-12 03-Sep-12 15-Sep-12 40 0% 0%
A1316 Submission of HVAC Layout & Details 11 16-Jul-12 28-Jul-12 133 16-Jul-12 28-Jul-12 25-Dec-12 07-Jan-13 133 0% 0%
A1316 Submission of MEP Cordination Layout 10 29-Jul-12 08-Aug-12 133 29-Jul-12 08-Aug-12 08-Jan-13 19-Jan-13 133 0% 0%ApprovApproval 34 12-Jul-12 30-Aug-12 123 11-Apr-12 30-Aug-12 16-Sep-12 26-Feb-13 11.11% 0%A1318 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 143 11-Apr-12 30-Apr-12 07-Feb-13 26-Feb-13 208 100% 0%
A1317 Approval of Drainage Layout & Details 14 29-Jul-12 15-Aug-12 119 29-Jul-12 15-Aug-12 20-Jan-13 07-Feb-13 119 0% 0%
A1317 Approval of Water Supply Layout & Details 14 29-Jul-12 15-Aug-12 119 29-Jul-12 15-Aug-12 20-Jan-13 07-Feb-13 119 0% 0%
A1317 Approval of Fire Fighting Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1317 Approval of HVAC Layout & Details 14 29-Jul-12 15-Aug-12 119 29-Jul-12 15-Aug-12 20-Jan-13 07-Feb-13 119 0% 0%
A1317 Approval of Lighting Layout & Details 14 29-Jul-12 15-Aug-12 119 29-Jul-12 15-Aug-12 20-Jan-13 07-Feb-13 119 0% 0%
A1317 Approval of Power Layout & Details 14 29-Jul-12 15-Aug-12 119 29-Jul-12 15-Aug-12 20-Jan-13 07-Feb-13 119 0% 0%
A1318 Approval of Fire Alarm Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1317 Approval of MEP Cordination Layout 14 09-Aug-12 30-Aug-12 110 09-Aug-12 30-Aug-12 20-Jan-13 07-Feb-13 110 0% 0%
ResidentResidential Apartments (Block C) 106 08-Mar-12 A 30-Aug-12 204 29-Feb-12 30-Aug-12 12-Aug-12 02-May-13 74.27% 2.86%
2nd Bas2nd Basement Floor 14 08-Mar-12 A 18-Jul-12 147 29-Feb-12 19-Mar-12 16-Dec-12 19-Feb-13 100% 25%ApprovApproval 14 08-Mar-12 A 18-Jul-12 147 29-Feb-12 19-Mar-12 16-Dec-12 19-Feb-13 100% 25%A1320 Approval of HVAC Layout & Details 14 18-Mar-12 A 09-Jul-12 122 29-Feb-12 19-Mar-12 16-Dec-12 03-Jan-13 201 100% 50%
A1321 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 147 29-Feb-12 19-Mar-12 31-Jan-13 19-Feb-13 233 100% 0%1st Bas1st Basement Floor 14 15-Mar-12 A 18-Jul-12 152 03-Apr-12 22-Apr-12 07-Feb-13 26-Feb-13 100% 0%ApprovApproval 14 15-Mar-12 A 18-Jul-12 152 03-Apr-12 22-Apr-12 07-Feb-13 26-Feb-13 100% 0%A1324 Approval of Fire Alarm Layout & Details 14 15-Mar-12 A 18-Jul-12 152 03-Apr-12 22-Apr-12 07-Feb-13 26-Feb-13 214 100% 0%
GroundGround Floor 52 02-Apr-12 A 31-Jul-12 195 28-Mar-12 30-Apr-12 05-Dec-12 25-Mar-13 100% 11.67%SubmiSubmission 10 01-Jul-12 11-Jul-12 195 28-Mar-12 10-Apr-12 02-Feb-13 05-Mar-13 100% 0%A1326 Submission of LPG & Gas Detection Layout & Details 8 01-Jul-12 09-Jul-12 177 02-Apr-12 10-Apr-12 02-Feb-13 10-Feb-13 253 100% 0%
A1325 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 195 28-Mar-12 08-Apr-12 23-Feb-13 05-Mar-13 275 100% 0%ApprovApproval 43 02-Apr-12 A 31-Jul-12 162 09-Apr-12 30-Apr-12 05-Dec-12 25-Mar-13 100% 16.67%A1326 Approval of HVAC Layout & Details 14 02-Apr-12 A 09-Jul-12 115 09-Apr-12 26-Apr-12 05-Dec-12 24-Dec-12 166 100% 50%
A1327 Approval of LPG & Gas Detection Layout & Details 14 10-Jul-12 29-Jul-12 147 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1327 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 162 09-Apr-12 26-Apr-12 06-Mar-13 25-Mar-13 229 100% 0%1st Floor1st Floor 43 12-Jun-12 A 01-Aug-12 179 31-Mar-12 23-May-12 17-Sep-12 07-Mar-13 100% 0%SubmiSubmission 12 01-Jul-12 14-Jul-12 179 31-Mar-12 03-May-12 17-Sep-12 17-Feb-13 100% 0%A1328 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 181 16-Apr-12 26-Apr-12 06-Feb-13 17-Feb-13 245 100% 0%
A1329 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 114 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 0%
A1329 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of Drainage Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Bui lder Work Layout
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of HVAC Layout & Details
Approval of Drainage Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of HVAC Layout & Details
Submission of ELV Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Approval of CBS Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of Fire Fighting Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Approval of LPG & Gas Detection Layout & Details
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of Fire Fighting Layout & Details
Approval of HVAC Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of MEP Cordination Layout
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Approval of Fire Alarm Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of Fire Alarm Layout & Details
Approval of HVAC Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of Fire Alarm Layout & Details
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 7 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1328 Submission of MEP Cordination Layout 12 01-Jul-12 14-Jul-12 65 21-Apr-12 03-May-12 17-Sep-12 30-Sep-12 125 100% 0%ApprovApproval 36 12-Jun-12 A 01-Aug-12 149 11-Apr-12 23-May-12 01-Oct-12 07-Mar-13 100% 0%A1330 Approval of Data & Telephone Layout & Details 14 12-Jun-12 A 18-Jul-12 134 29-Apr-12 16-May-12 13-Jan-13 31-Jan-13 178 100% 0%
A1330 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 150 29-Apr-12 16-May-12 18-Feb-13 07-Mar-13 203 100% 0%
A1330 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 125 29-Apr-12 16-May-12 13-Jan-13 31-Jan-13 178 100% 0%
A1330 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1329 Approval of MEP Cordination Layout 14 15-Jul-12 01-Aug-12 54 06-May-12 23-May-12 01-Oct-12 18-Oct-12 103 100% 0%2nd Flo2nd Floor 82 26-Apr-12 A 31-Jul-12 207 31-Mar-12 13-Jun-12 11-Sep-12 08-Apr-13 100% 3.5%SubmiSubmission 10 01-Jul-12 11-Jul-12 207 31-Mar-12 24-May-12 11-Sep-12 19-Mar-13 100% 0%A1331 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 76 07-May-12 17-May-12 30-Sep-12 10-Oct-12 122 100% 0%
A1331 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 60 14-May-12 24-May-12 11-Sep-12 22-Sep-12 100 100% 0%
A1331 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 207 07-May-12 17-May-12 09-Mar-13 19-Mar-13 253 100% 0%
A1332 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 170 16-Apr-12 26-Apr-12 23-Jan-13 04-Feb-13 234 100% 0%
A1332 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 170 16-Apr-12 26-Apr-12 23-Jan-13 04-Feb-13 234 100% 0%
A1332 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 172 11-Apr-12 13-Jun-12 23-Sep-12 08-Apr-13 100% 5%A1333 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 157 20-May-12 06-Jun-12 05-Feb-13 24-Feb-13 179 100% 50%
A1333 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 58 20-May-12 06-Jun-12 23-Sep-12 10-Oct-12 87 100% 0%
A1333 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 58 20-May-12 06-Jun-12 23-Sep-12 10-Oct-12 87 100% 0%
A1333 Approval of CCTV,Access Control,Intercom Layout & Details 14 21-Jun-12 A 18-Jul-12 150 29-Apr-12 16-May-12 05-Feb-13 24-Feb-13 194 100% 0%
A1332 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 63 20-May-12 06-Jun-12 11-Oct-12 31-Oct-12 101 100% 0%
A1333 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 49 27-May-12 13-Jun-12 23-Sep-12 10-Oct-12 82 100% 0%
A1333 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 172 20-May-12 06-Jun-12 20-Mar-13 08-Apr-13 210 100% 0%
A1333 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 141 29-Apr-12 16-May-12 05-Feb-13 24-Feb-13 194 100% 0%
A1333 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 141 29-Apr-12 16-May-12 05-Feb-13 24-Feb-13 194 100% 0%
A1334 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%3rd Floor3rd Floor 82 26-Apr-12 A 31-Jul-12 180 31-Mar-12 25-Jun-12 03-Oct-12 07-Mar-13 100% 2.99%SubmiSubmission 10 01-Jul-12 11-Jul-12 181 31-Mar-12 04-Jun-12 03-Oct-12 17-Feb-13 100% 0%A1334 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 85 07-May-12 17-May-12 10-Oct-12 21-Oct-12 131 100% 0%
A1334 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 79 24-May-12 04-Jun-12 03-Oct-12 14-Oct-12 110 100% 0%
A1334 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 181 07-May-12 17-May-12 06-Feb-13 17-Feb-13 227 100% 0%
A1335 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 131 16-Apr-12 26-Apr-12 08-Dec-12 18-Dec-12 195 100% 0%
A1335 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 131 16-Apr-12 26-Apr-12 08-Dec-12 18-Dec-12 195 100% 0%
A1335 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 131 16-Apr-12 26-Apr-12 08-Dec-12 18-Dec-12 195 100% 0%
A1335 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 131 16-Apr-12 26-Apr-12 08-Dec-12 18-Dec-12 195 100% 0%
A1335 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 150 11-Apr-12 25-Jun-12 08-Oct-12 07-Mar-13 100% 4.55%A1336 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 125 20-May-12 06-Jun-12 19-Dec-12 08-Jan-13 147 100% 50%
A1336 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 69 20-May-12 06-Jun-12 08-Oct-12 28-Oct-12 98 100% 0%
A1336 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 69 20-May-12 06-Jun-12 08-Oct-12 28-Oct-12 98 100% 0%
A1335 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 70 20-May-12 06-Jun-12 22-Oct-12 11-Nov-12 108 100% 0%
A1336 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 65 05-Jun-12 25-Jun-12 15-Oct-12 04-Nov-12 91 100% 0%
A1336 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 150 20-May-12 06-Jun-12 18-Feb-13 07-Mar-13 188 100% 0%
A1336 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 109 29-Apr-12 16-May-12 19-Dec-12 08-Jan-13 162 100% 0%
A1336 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 109 29-Apr-12 16-May-12 19-Dec-12 08-Jan-13 162 100% 0%
A1336 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 109 29-Apr-12 16-May-12 19-Dec-12 08-Jan-13 162 100% 0%
A1336 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 109 29-Apr-12 16-May-12 19-Dec-12 08-Jan-13 162 100% 0%
A1337 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%4th Floor4th Floor 82 26-Apr-12 A 31-Jul-12 190 31-Mar-12 05-Jul-12 18-Oct-12 19-Mar-13 97.86% 2.99%SubmiSubmission 10 01-Jul-12 11-Jul-12 190 31-Mar-12 16-Jun-12 18-Oct-12 27-Feb-13 100% 0%A1337 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 92 28-May-12 07-Jun-12 18-Oct-12 31-Oct-12 120 100% 0%
A1337 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 92 05-Jun-12 16-Jun-12 18-Oct-12 31-Oct-12 113 100% 0%
A1337 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 190 28-May-12 07-Jun-12 17-Feb-13 27-Feb-13 218 100% 0%
A1338 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 138 16-Apr-12 26-Apr-12 16-Dec-12 26-Dec-12 202 100% 0%
A1338 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 138 16-Apr-12 26-Apr-12 16-Dec-12 26-Dec-12 202 100% 0%
A1338 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 138 16-Apr-12 26-Apr-12 16-Dec-12 26-Dec-12 202 100% 0%
A1338 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 138 16-Apr-12 26-Apr-12 16-Dec-12 26-Dec-12 202 100% 0%
A1338 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 158 11-Apr-12 05-Jul-12 01-Nov-12 19-Mar-13 96.75% 4.55%A1339 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 131 10-Jun-12 28-Jun-12 27-Dec-12 16-Jan-13 138 100% 50%
A1339 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 86 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 0%
A1339 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 86 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 0%
A1338 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 77 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 0%
A1339 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 77 18-Jun-12 05-Jul-12 01-Nov-12 21-Nov-12 95 64.29% 0%
A1339 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 158 10-Jun-12 28-Jun-12 28-Feb-13 19-Mar-13 181 100% 0%
A1339 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 115 29-Apr-12 16-May-12 27-Dec-12 16-Jan-13 168 100% 0%
A1339 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 115 29-Apr-12 16-May-12 27-Dec-12 16-Jan-13 168 100% 0%
A1339 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 115 29-Apr-12 16-May-12 27-Dec-12 16-Jan-13 168 100% 0%
A1339 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 115 29-Apr-12 16-May-12 27-Dec-12 16-Jan-13 168 100% 0%
A1340 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%5th Floor5th Floor 82 26-Apr-12 A 31-Jul-12 200 31-Mar-12 05-Jul-12 05-Nov-12 31-Mar-13 97.86% 2.99%SubmiSubmission 10 01-Jul-12 11-Jul-12 200 31-Mar-12 16-Jun-12 05-Nov-12 11-Mar-13 100% 0%A1340 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 106 28-May-12 07-Jun-12 06-Nov-12 18-Nov-12 134 100% 0%
A1340 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 105 05-Jun-12 16-Jun-12 05-Nov-12 17-Nov-12 126 100% 0%
A1340 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 200 28-May-12 07-Jun-12 28-Feb-13 11-Mar-13 228 100% 0%
A1341 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 163 16-Apr-12 26-Apr-12 15-Jan-13 27-Jan-13 227 100% 0%
A1341 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 163 16-Apr-12 26-Apr-12 15-Jan-13 27-Jan-13 227 100% 0%
A1341 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 163 16-Apr-12 26-Apr-12 15-Jan-13 27-Jan-13 227 100% 0%
A1341 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 163 16-Apr-12 26-Apr-12 15-Jan-13 27-Jan-13 227 100% 0%
A1341 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 166 11-Apr-12 05-Jul-12 18-Nov-12 31-Mar-13 96.75% 4.55%A1342 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 151 10-Jun-12 28-Jun-12 28-Jan-13 14-Feb-13 158 100% 50%
A1342 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 96 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 0%
A1342 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 96 10-Jun-12 28-Jun-12 18-Nov-12 06-Dec-12 110 100% 0%
A1341 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 88 10-Jun-12 28-Jun-12 19-Nov-12 09-Dec-12 111 100% 0%
A1342 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 87 18-Jun-12 05-Jul-12 18-Nov-12 06-Dec-12 105 64.29% 0%
A1342 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 166 10-Jun-12 28-Jun-12 12-Mar-13 31-Mar-13 189 100% 0%
A1342 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 135 29-Apr-12 16-May-12 28-Jan-13 14-Feb-13 188 100% 0%
A1342 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 135 29-Apr-12 16-May-12 28-Jan-13 14-Feb-13 188 100% 0%
A1342 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 135 29-Apr-12 16-May-12 28-Jan-13 14-Feb-13 188 100% 0%
A1342 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 135 29-Apr-12 16-May-12 28-Jan-13 14-Feb-13 188 100% 0%
A1343 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%6th Floor6th Floor 82 26-Apr-12 A 31-Jul-12 198 31-Mar-12 24-Jul-12 17-Nov-12 28-Mar-13 92.31% 2.99%SubmiSubmission 10 01-Jul-12 11-Jul-12 199 31-Mar-12 04-Jul-12 17-Nov-12 10-Mar-13 95% 0%A1343 Submission of HVAC Layout & Details 10 01-Jul-12 11-Jul-12 123 28-May-12 07-Jun-12 27-Nov-12 09-Dec-12 151 100% 0%
A1343 Submission of MEP Cordination Layout 10 01-Jul-12 11-Jul-12 114 24-Jun-12 04-Jul-12 17-Nov-12 27-Nov-12 120 60% 0%
A1343 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 199 28-May-12 07-Jun-12 27-Feb-13 10-Mar-13 227 100% 0%
A1344 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 114 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 0%
A1344 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 114 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 0%
A1344 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 114 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 0%
A1344 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 114 16-Apr-12 26-Apr-12 17-Nov-12 27-Nov-12 178 100% 0%
A1344 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%ApprovApproval 68 26-Apr-12 A 31-Jul-12 165 11-Apr-12 24-Jul-12 28-Nov-12 28-Mar-13 90.91% 4.55%A1345 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 111 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 50%
A1345 Approval of Lighting Layout & Details 14 10-Jun-12 A 18-Jul-12 104 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 0%
A1345 Approval of Power Layout & Details 14 10-Jun-12 A 18-Jul-12 104 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 0%
A1344 Approval of HVAC Layout & Details 14 12-Jul-12 31-Jul-12 102 10-Jun-12 28-Jun-12 10-Dec-12 27-Dec-12 125 100% 0%
A1345 Approval of MEP Cordination Layout 14 12-Jul-12 31-Jul-12 95 05-Jul-12 24-Jul-12 28-Nov-12 18-Dec-12 100 0% 0%
A1345 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 165 10-Jun-12 28-Jun-12 11-Mar-13 28-Mar-13 188 100% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of MEP Cordination Layout
Approval of Data & Telephone Layout & Details
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of MEP Cordination Layout
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of ELV Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of ELV Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Approval of CBS Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of Fire Alarm Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 8 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A1345 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 95 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 0%
A1345 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 95 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 0%
A1345 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 95 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 0%
A1345 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 95 29-Apr-12 16-May-12 28-Nov-12 18-Dec-12 148 100% 0%
A1346 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%7th Floor7th Floor 93 26-Apr-12 A 13-Aug-12 197 31-Mar-12 13-Aug-12 12-Aug-12 09-Apr-13 58.36% 2.39%SubmiSubmission 21 01-Jul-12 24-Jul-12 197 31-Mar-12 24-Jul-12 12-Aug-12 20-Mar-13 81.98% 0%A1346 Submission of Lighting Layout & Details 10 01-Jul-12 11-Jul-12 131 14-Jun-12 26-Jun-12 08-Dec-12 18-Dec-12 144 100% 0%
A1346 Submission of Power Layout & Details 10 01-Jul-12 11-Jul-12 131 14-Jun-12 26-Jun-12 08-Dec-12 18-Dec-12 144 100% 0%
A1346 Submission of Fire Alarm Layout & Details 10 01-Jul-12 11-Jul-12 208 14-Jun-12 26-Jun-12 10-Mar-13 20-Mar-13 221 100% 0%
A1347 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 136 16-Apr-12 26-Apr-12 13-Dec-12 24-Dec-12 200 100% 0%
A1347 Submission of ELV Layout & Details 10 01-Jul-12 11-Jul-12 136 16-Apr-12 26-Apr-12 13-Dec-12 24-Dec-12 200 100% 0%
A1347 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 136 16-Apr-12 26-Apr-12 13-Dec-12 24-Dec-12 200 100% 0%
A1347 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 136 16-Apr-12 26-Apr-12 13-Dec-12 24-Dec-12 200 100% 0%
A1347 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 175 31-Mar-12 10-Apr-12 30-Jan-13 10-Feb-13 253 100% 0%
A1346 Submission of HVAC Layout & Details 11 01-Jul-12 12-Jul-12 139 14-Jun-12 27-Jun-12 17-Dec-12 29-Dec-12 152 100% 0%
A1346 Submission of MEP Cordination Layout 10 14-Jul-12 24-Jul-12 120 14-Jul-12 24-Jul-12 08-Dec-12 18-Dec-12 120 0% 0%
A1346 Submission of MEP Builder Work Layout 10 14-Jul-12 24-Jul-12 34 14-Jul-12 24-Jul-12 12-Aug-12 25-Aug-12 25 0% 0%ApprovApproval 77 26-Apr-12 A 13-Aug-12 164 11-Apr-12 13-Aug-12 26-Aug-12 09-Apr-13 43.96% 3.85%A1348 Approval of CBS Layout & Details 14 26-Apr-12 A 09-Jul-12 129 27-Jun-12 16-Jul-12 25-Dec-12 14-Jan-13 124 14.29% 50%
A1347 Approval of Drainage Layout & Details 14 24-Jun-12 A 18-Jul-12 118 28-Jun-12 17-Jul-12 19-Dec-12 08-Jan-13 119 7.14% 0%
A1348 Approval of Lighting Layout & Details 14 12-Jul-12 31-Jul-12 109 27-Jun-12 16-Jul-12 19-Dec-12 08-Jan-13 120 14.29% 0%
A1348 Approval of Power Layout & Details 14 12-Jul-12 31-Jul-12 109 27-Jun-12 16-Jul-12 19-Dec-12 08-Jan-13 120 14.29% 0%
A1348 Approval of Fire Alarm Layout & Details 14 12-Jul-12 31-Jul-12 173 27-Jun-12 16-Jul-12 21-Mar-13 09-Apr-13 184 14.29% 0%
A1348 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 113 29-Apr-12 16-May-12 25-Dec-12 14-Jan-13 166 100% 0%
A1348 Approval of ELV Layout & Details 14 12-Jul-12 31-Jul-12 113 29-Apr-12 16-May-12 25-Dec-12 14-Jan-13 166 100% 0%
A1348 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 113 29-Apr-12 16-May-12 25-Dec-12 14-Jan-13 166 100% 0%
A1348 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 113 29-Apr-12 16-May-12 25-Dec-12 14-Jan-13 166 100% 0%
A1349 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 145 11-Apr-12 30-Apr-12 11-Feb-13 28-Feb-13 210 100% 0%
A1347 Approval of HVAC Layout & Details 14 15-Jul-12 01-Aug-12 115 28-Jun-12 17-Jul-12 30-Dec-12 17-Jan-13 126 7.14% 0%
A1348 Approval of MEP Cordination Layout 14 25-Jul-12 13-Aug-12 100 25-Jul-12 13-Aug-12 19-Dec-12 08-Jan-13 100 0% 0%
A1348 Approval of MEP Builder Work Layout 14 25-Jul-12 13-Aug-12 28 25-Jul-12 13-Aug-12 26-Aug-12 12-Sep-12 20 0% 0%Roof FRoof Floor 102 26-Apr-12 A 26-Aug-12 208 31-Mar-12 26-Aug-12 05-Sep-12 02-May-13 35.82% 2.09%SubmiSubmission 30 01-Jul-12 04-Aug-12 209 31-Mar-12 04-Aug-12 05-Sep-12 14-Apr-13 35.97% 0%A1350 Submission of CCTV,Access Control,Intercom Layout & Details 10 01-Jul-12 11-Jul-12 151 08-May-12 19-May-12 31-Dec-12 12-Jan-13 196 100% 0%
A1350 Submission of BMS Layout & Details 10 01-Jul-12 11-Jul-12 151 08-May-12 19-May-12 31-Dec-12 12-Jan-13 196 100% 0%
A1350 Submission of Data & Telephone Layout & Details 10 01-Jul-12 11-Jul-12 151 08-May-12 19-May-12 31-Dec-12 12-Jan-13 196 100% 0%
A1350 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
A1349 Submission of Lighting Layout & Details 10 07-Jul-12 17-Jul-12 135 07-Jul-12 17-Jul-12 18-Dec-12 29-Dec-12 135 0% 0%
A1349 Submission of Power Layout & Details 10 07-Jul-12 17-Jul-12 135 07-Jul-12 17-Jul-12 18-Dec-12 29-Dec-12 135 0% 0%
A1349 Submission of Fire Alarm Layout & Details 10 07-Jul-12 17-Jul-12 224 07-Jul-12 17-Jul-12 03-Apr-13 14-Apr-13 224 0% 0%
A1349 Submission of Drainage Layout & Details 14 03-Jul-12 18-Jul-12 53 03-Jul-12 18-Jul-12 05-Sep-12 20-Sep-12 53 0% 0%
A1349 Submission of Water Supply Layout & Details 14 03-Jul-12 18-Jul-12 119 03-Jul-12 18-Jul-12 25-Nov-12 11-Dec-12 119 0% 0%
A1349 Submission of HVAC Layout & Details 11 07-Jul-12 18-Jul-12 119 07-Jul-12 18-Jul-12 28-Nov-12 11-Dec-12 119 0% 0%
A1350 Submission of ELV Layout & Details 10 23-Jul-12 02-Aug-12 121 08-May-12 19-May-12 18-Dec-12 29-Dec-12 185 100% 0%
A1349 Submission of MEP Cordination Layout 10 24-Jul-12 04-Aug-12 120 24-Jul-12 04-Aug-12 18-Dec-12 29-Dec-12 120 0% 0%
A1349 Submission of MEP Builder Work Layout 10 24-Jul-12 04-Aug-12 53 24-Jul-12 04-Aug-12 26-Sep-12 07-Oct-12 53 0% 0%ApprovApproval 84 26-Apr-12 A 26-Aug-12 174 11-Apr-12 26-Aug-12 08-Oct-12 02-May-13 35.71% 3.57%A1351 Approval of CBS Layout & Details 14 26-Apr-12 A 16-Jul-12 136 18-Jul-12 06-Aug-12 13-Jan-13 31-Jan-13 121 0% 50%
A1351 Approval of CCTV,Access Control,Intercom Layout & Details 14 12-Jul-12 31-Jul-12 125 20-May-12 06-Jun-12 13-Jan-13 31-Jan-13 163 100% 0%
A1351 Approval of BMS Layout & Details 14 12-Jul-12 31-Jul-12 125 20-May-12 06-Jun-12 13-Jan-13 31-Jan-13 163 100% 0%
A1351 Approval of Data & Telephone Layout & Details 14 12-Jul-12 31-Jul-12 125 20-May-12 06-Jun-12 13-Jan-13 31-Jan-13 163 100% 0%
A1352 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 143 11-Apr-12 30-Apr-12 07-Feb-13 26-Feb-13 208 100% 0%
A1364 Approval of Power Layout & Details 14 18-Jul-12 06-Aug-12 112 18-Jul-12 06-Aug-12 30-Dec-12 17-Jan-13 112 0% 0%
A1351 Approval of Lighting Layout & Details 14 18-Jul-12 06-Aug-12 112 18-Jul-12 06-Aug-12 30-Dec-12 17-Jan-13 112 0% 0%
A1351 Approval of Fire Alarm Layout & Details 14 18-Jul-12 06-Aug-12 186 18-Jul-12 06-Aug-12 15-Apr-13 02-May-13 186 0% 0%
A1350 Approval of Drainage Layout & Details 14 19-Jul-12 07-Aug-12 116 19-Jul-12 07-Aug-12 07-Jan-13 27-Jan-13 116 0% 0%
A1350 Approval of Water Supply Layout & Details 14 19-Jul-12 07-Aug-12 116 19-Jul-12 07-Aug-12 07-Jan-13 27-Jan-13 116 0% 0%
A1350 Approval of HVAC Layout & Details 14 19-Jul-12 07-Aug-12 99 19-Jul-12 07-Aug-12 12-Dec-12 31-Dec-12 99 0% 0%
A1351 Approval of MEP Cordination Layout 14 05-Aug-12 26-Aug-12 100 05-Aug-12 26-Aug-12 30-Dec-12 17-Jan-13 100 0% 0%
A1351 Approval of MEP Builder Work Layout 14 05-Aug-12 26-Aug-12 44 05-Aug-12 26-Aug-12 08-Oct-12 28-Oct-12 44 0% 0%
A1351 Approval of ELV Layout & Details 14 05-Aug-12 26-Aug-12 100 20-May-12 06-Jun-12 30-Dec-12 17-Jan-13 154 100% 0%Upper RUpper Roof Floor 51 01-Jul-12 30-Aug-12 177 31-Mar-12 30-Aug-12 30-Aug-12 01-Apr-13 10.62% 0%SubmiSubmission 34 01-Jul-12 08-Aug-12 177 31-Mar-12 08-Aug-12 30-Aug-12 12-Mar-13 10% 0%A1353 Submission of LPG & Gas Detection Layout & Details 10 01-Jul-12 11-Jul-12 172 31-Mar-12 10-Apr-12 27-Jan-13 06-Feb-13 250 100% 0%
A1352 Submission of Lighting Layout & Details 10 16-Jul-12 26-Jul-12 188 16-Jul-12 26-Jul-12 02-Mar-13 12-Mar-13 188 0% 0%
A1352 Submission of Power Layout & Details 10 16-Jul-12 26-Jul-12 188 16-Jul-12 26-Jul-12 02-Mar-13 12-Mar-13 188 0% 0%
A1352 Submission of Fire Alarm Layout & Details 10 16-Jul-12 26-Jul-12 41 16-Jul-12 26-Jul-12 04-Sep-12 15-Sep-12 41 0% 0%
A1352 Submission of Drainage Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1352 Submission of Water Supply Layout & Details 14 12-Jul-12 28-Jul-12 40 12-Jul-12 28-Jul-12 30-Aug-12 15-Sep-12 40 0% 0%
A1352 Submission of Fire Fighting Layout & Details 11 16-Jul-12 28-Jul-12 40 16-Jul-12 28-Jul-12 03-Sep-12 15-Sep-12 40 0% 0%
A1352 Submission of HVAC Layout & Details 11 16-Jul-12 28-Jul-12 177 16-Jul-12 28-Jul-12 17-Feb-13 28-Feb-13 177 0% 0%
A1352 Submission of MEP Cordination Layout 10 29-Jul-12 08-Aug-12 177 29-Jul-12 08-Aug-12 02-Mar-13 12-Mar-13 177 0% 0%ApprovApproval 34 12-Jul-12 30-Aug-12 147 11-Apr-12 30-Aug-12 16-Sep-12 01-Apr-13 11.11% 0%A1355 Approval of LPG & Gas Detection Layout & Details 14 12-Jul-12 31-Jul-12 143 11-Apr-12 30-Apr-12 07-Feb-13 26-Feb-13 208 100% 0%
A1353 Approval of Drainage Layout & Details 14 29-Jul-12 15-Aug-12 156 29-Jul-12 15-Aug-12 13-Mar-13 01-Apr-13 156 0% 0%
A1353 Approval of Water Supply Layout & Details 14 29-Jul-12 15-Aug-12 156 29-Jul-12 15-Aug-12 13-Mar-13 01-Apr-13 156 0% 0%
A1353 Approval of Fire Fighting Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1353 Approval of HVAC Layout & Details 14 29-Jul-12 15-Aug-12 156 29-Jul-12 15-Aug-12 13-Mar-13 01-Apr-13 156 0% 0%
A1354 Approval of Lighting Layout & Details 14 29-Jul-12 15-Aug-12 156 29-Jul-12 15-Aug-12 13-Mar-13 01-Apr-13 156 0% 0%
A1354 Approval of Power Layout & Details 14 29-Jul-12 15-Aug-12 156 29-Jul-12 15-Aug-12 13-Mar-13 01-Apr-13 156 0% 0%
A1354 Approval of Fire Alarm Layout & Details 14 29-Jul-12 15-Aug-12 33 29-Jul-12 15-Aug-12 16-Sep-12 03-Oct-12 33 0% 0%
A1354 Approval of MEP Cordination Layout 14 09-Aug-12 30-Aug-12 147 09-Aug-12 30-Aug-12 13-Mar-13 01-Apr-13 147 0% 0%
SpecialitSpeciality Works 57 01-Jul-12 06-Sep-12 168 18-Jun-12 20-Nov-12 11-Jul-12 28-Mar-13 11.11% 0%
SwimminSwimming Pool 14 01-Jul-12 18-Jul-12 174 07-Oct-12 20-Nov-12 19-Feb-13 28-Mar-13 0% 0%
ApprovalApproval 14 01-Jul-12 18-Jul-12 174 07-Oct-12 20-Nov-12 19-Feb-13 28-Mar-13 0% 0%A118900 Approval of Swimming Pool Layout & Details for Block A 14 01-Jul-12 18-Jul-12 170 07-Oct-12 24-Oct-12 05-Mar-13 24-Mar-13 102 0% 0%
A118910 Approval of Swimming Pool 's Water Prrofing for Block A 14 01-Jul-12 18-Jul-12 174 07-Oct-12 24-Oct-12 11-Mar-13 28-Mar-13 106 0% 0%
A118920 Approval of Swimming Pool Layout & Details for Block B 14 01-Jul-12 18-Jul-12 160 07-Oct-12 24-Oct-12 19-Feb-13 10-Mar-13 92 0% 0%
A118930 Approval of Swimming Pool 's Water Proofing for Block B 14 01-Jul-12 18-Jul-12 164 07-Oct-12 24-Oct-12 25-Feb-13 14-Mar-13 96 0% 0%
A118940 Approval of Swimming Pool Layout & Details for Block C 14 01-Jul-12 18-Jul-12 163 31-Oct-12 20-Nov-12 24-Feb-13 13-Mar-13 78 0% 0%
A118950 Approval of Swimming Pool 's Water Proofing for Block C 14 01-Jul-12 18-Jul-12 166 31-Oct-12 20-Nov-12 27-Feb-13 18-Mar-13 81 0% 0%
Garbage Garbage Chute 15 21-Aug-12 06-Sep-12 -33 18-Jun-12 04-Jul-12 11-Jul-12 28-Jul-12 73.33% 0%
SubmisSubmission 15 21-Aug-12 06-Sep-12 -33 18-Jun-12 04-Jul-12 11-Jul-12 28-Jul-12 73.33% 0%A118810 Submission of Garbage Chute Layout & Details for Block A 15 21-Aug-12 06-Sep-12 -33 18-Jun-12 04-Jul-12 11-Jul-12 28-Jul-12 20 73.33% 0%
ProvisioProvisional Sum 61 01-Jul-12 11-Sep-12 69 24-Jun-12 11-Sep-12 24-Jun-12 05-Dec-12 9.84% 0%
Kitchen EKitchen Equipments 37 01-Jul-12 12-Aug-12 -6 24-Jun-12 05-Aug-12 24-Jun-12 05-Aug-12 17.65% 0%
SubmisSubmission 20 01-Jul-12 23-Jul-12 -6 24-Jun-12 16-Jul-12 24-Jun-12 16-Jul-12 30% 0%A9983 Submission of Kitchen Equipments Drawings 20 01-Jul-12 23-Jul-12 -6 24-Jun-12 16-Jul-12 24-Jun-12 16-Jul-12 0 30% 0%
ApprovalApproval 14 24-Jul-12 12-Aug-12 -5 17-Jul-12 05-Aug-12 17-Jul-12 05-Aug-12 0% 0%A9984 Approval of Kitchen Equipments Drawings 14 24-Jul-12 12-Aug-12 -5 17-Jul-12 05-Aug-12 17-Jul-12 05-Aug-12 0 0% 0%
Lundary Lundary Equipments 37 01-Jul-12 12-Aug-12 -6 24-Jun-12 05-Aug-12 24-Jun-12 05-Aug-12 17.65% 0%
SubmisSubmission 20 01-Jul-12 23-Jul-12 -6 24-Jun-12 16-Jul-12 24-Jun-12 16-Jul-12 30% 0%A9986 Submission of Laundary Equipments Drawings 20 01-Jul-12 23-Jul-12 -6 24-Jun-12 16-Jul-12 24-Jun-12 16-Jul-12 0 30% 0%
ApprovalApproval 14 24-Jul-12 12-Aug-12 -5 17-Jul-12 05-Aug-12 17-Jul-12 05-Aug-12 0% 0%A9987 Approval of Laundary Equipments Drawings 14 24-Jul-12 12-Aug-12 -5 17-Jul-12 05-Aug-12 17-Jul-12 05-Aug-12 0 0% 0%
Facade LFacade Lighting 21 16-Aug-12 11-Sep-12 5 16-Aug-12 11-Sep-12 25-Aug-12 17-Sep-12 0% 0%
SubmisSubmission 21 16-Aug-12 11-Sep-12 5 16-Aug-12 11-Sep-12 25-Aug-12 17-Sep-12 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of ELV Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Approval of CBS Layout & Details
s Approval of Drainage Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of ELV Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Submission of CCTV,Access Control,Intercom Layout & Details
Submission of BMS Layout & Details
Submission of Data & Telephone Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of HVAC Layout & Details
Submission of ELV Layout & Details
Submission of MEP Cordination Layout
Submission of MEP Builder Work Layout
Approval of CBS Layout & Details
Approval of CCTV,Access Control,Intercom Layout & Details
Approval of BMS Layout & Details
Approval of Data & Telephone Layout & Details
Approval of LPG & Gas Detection Layout & Details
Approval of Power Layout & Details
Approval of Lighting Layout & Details
Approval of Fire Alarm Layout & Details
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of HVAC Layout & Details
Approval of MEP Cordination Layout
Approval of MEP Builder Work Layout
Approval of ELV Layout & Details
Submission of LPG & Gas Detection Layout & Details
Submission of Lighting Layout & Details
Submission of Power Layout & Details
Submission of Fire Alarm Layout & Details
Submission of Drainage Layout & Details
Submission of Water Supply Layout & Details
Submission of Fire Fighting Layout & Details
Submission of HVAC Layout & Details
Submission of MEP Cordination Layout
Approval of LPG & Gas Detection Layout & Details
Approval of Drainage Layout & Details
Approval of Water Supply Layout & Details
Approval of Fire Fighting Layout & Details
Approval of HVAC Layout & Details
Approval of Lighting Layout & Details
Approval of Power Layout & Details
Approval of Fire Alarm Layout & Details
Approval of MEP Cordination Layout
Approval of Swimming Pool Layout & Details for Block A
Approval of Swimming Pool 's Water Prrofing for Block A
Approval of Swimming Pool Layout & Details for Block B
Approval of Swimming Pool 's Water Proofing for Block B
Approval of Swimming Pool Layout & Details for Block C
Approval of Swimming Pool 's Water Proofing for Block C
Submission of Garbage Chute Layout & Details for Block A
Submission of Kitchen Equipments Drawings
Approval of Kitchen Equipments Drawings
Submission of Laundary Equipments Drawings
Approval of Laundary Equipments Drawings
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 9 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A9988 Submission of Facade Lighitng Drawings 21 16-Aug-12 11-Sep-12 5 16-Aug-12 11-Sep-12 25-Aug-12 17-Sep-12 5 0% 0%
Cooking Cooking Station 38 25-Jul-12 09-Sep-12 71 09-Jul-12 22-Aug-12 20-Oct-12 05-Dec-12 0% 0%
SubmisSubmission 20 25-Jul-12 16-Aug-12 72 09-Jul-12 31-Jul-12 20-Oct-12 13-Nov-12 0% 0%A124680 Submission of Cooking Station Drawings 20 25-Jul-12 16-Aug-12 72 09-Jul-12 31-Jul-12 20-Oct-12 13-Nov-12 86 0% 0%
ApprovalApproval 14 21-Aug-12 09-Sep-12 60 01-Aug-12 22-Aug-12 14-Nov-12 05-Dec-12 0% 0%A124690 Approval of Cooking Station Drawings 14 21-Aug-12 09-Sep-12 60 01-Aug-12 22-Aug-12 14-Nov-12 05-Dec-12 72 0% 0%
Method 0Method 0f Statements 64 01-Jul-12 15-Sep-12 180 11-Jun-12 09-Jan-13 29-Sep-12 20-Apr-13 10.67% 0%
ArchitecArchitectural 64 01-Jul-12 15-Sep-12 83 11-Jun-12 15-Sep-12 29-Sep-12 25-Dec-12 26.67% 0%
A46610 Sub & App- MOS for Wall&Floor Tiles 30 01-Jul-12 04-Aug-12 75 11-Jun-12 16-Jul-12 29-Sep-12 04-Nov-12 91 53.33% 0%
A46600 Sub & App- MOS for Panintng 30 09-Aug-12 15-Sep-12 83 09-Aug-12 15-Sep-12 20-Nov-12 25-Dec-12 83 0% 0%
MEPMEP 30 05-Jul-12 09-Aug-12 90 07-Jul-12 09-Aug-12 22-Oct-12 28-Nov-12 0% 0%
HVACHVAC 30 05-Jul-12 09-Aug-12 90 07-Jul-12 09-Aug-12 22-Oct-12 28-Nov-12 0% 0%
A113860 Sub & App- MOS for Piping Works 30 05-Jul-12 09-Aug-12 90 07-Jul-12 09-Aug-12 22-Oct-12 28-Nov-12 90 0% 0%
SpecialitSpeciality Works 61 01-Jul-12 11-Sep-12 183 03-Oct-12 09-Jan-13 10-Feb-13 20-Apr-13 0% 0%
SwimmimSwimmimng Pool 61 01-Jul-12 11-Sep-12 183 03-Oct-12 09-Jan-13 10-Feb-13 20-Apr-13 0% 0%
A113810 Sub & App- MOS for Water Proofing 30 01-Jul-12 04-Aug-12 184 03-Oct-12 08-Nov-12 10-Feb-13 16-Mar-13 105 0% 0%
A113820 Sub & App- MOS for Tiling 30 06-Aug-12 11-Sep-12 183 05-Dec-12 09-Jan-13 17-Mar-13 20-Apr-13 85 0% 0%
ProcureProcurement 305 19-Feb-12 A 18-Feb-13 123 15-Feb-12 22-Jan-13 28-Feb-12 13-Jul-13 34.11% 5.39%
SubmittiSubmittion & Approval of Prequalification 118 10-Apr-12 A 28-Aug-12 73 15-Feb-12 28-Aug-12 14-Apr-12 25-Nov-12 71.43% 34.72%
DomestiDomestic Sub Contractors 118 10-Apr-12 A 28-Aug-12 73 15-Feb-12 28-Aug-12 14-Apr-12 25-Nov-12 79.05% 41.67%
A8480 Sub & App- Garbage Chute System Subcontractor 35 10-Apr-12 A 02-Jul-12 -33 21-Mar-12 30-Apr-12 14-Apr-12 23-May-12 20 100% 50%
A8444 Sub & App- Linen Chute System Subcontractor 35 07-Jun-12 A 02-Jul-12 -15 25-Apr-12 04-Jun-12 05-May-12 13-Jun-12 8 100% 50%
A8540 Sub & App- Susbended Ceilings Subcontractor 35 12-Apr-12 A 04-Jul-12 -35 15-Feb-12 26-Mar-12 14-Apr-12 23-May-12 50 100% 50%
A8530 Sub & App- Wood & Joinery Subcontractor 35 26-Jun-12 A 21-Jul-12 23 30-May-12 10-Jul-12 07-Jul-12 15-Aug-12 31 74.29% 50%
A8560 Sub & App- GRP Lining Subcontractor 35 18-Apr-12 A 21-Jul-12 52 25-Apr-12 04-Jun-12 28-Jul-12 08-Sep-12 79 100% 50%
A8580 Sub & App- Traffic Deck Coating Subcontractor 35 17-Jul-12 28-Aug-12 73 17-Jul-12 28-Aug-12 13-Oct-12 25-Nov-12 73 0% 0%
NominatNominated Sub Contractors 40 01-Jul-12 15-Aug-12 53 13-Jun-12 15-Aug-12 29-Jul-12 18-Oct-12 33.33% 0%
Facade LFacade Lighting 21 23-Jul-12 15-Aug-12 5 23-Jul-12 15-Aug-12 29-Jul-12 23-Aug-12 0% 0%
A8533 Sub & App- Facade Lighting Subcontractor 21 23-Jul-12 15-Aug-12 5 23-Jul-12 15-Aug-12 29-Jul-12 23-Aug-12 5 0% 0%
Cooking Cooking Station 21 01-Jul-12 24-Jul-12 72 13-Jun-12 08-Jul-12 25-Sep-12 18-Oct-12 66.67% 0%
A124700 Sub & App- Cooking Station Subcontractor 21 01-Jul-12 24-Jul-12 72 13-Jun-12 08-Jul-12 25-Sep-12 18-Oct-12 86 66.67% 0%
SubmittiSubmittion & Approval of Material Submittal 177 19-Feb-12 A 27-Sep-12 130 10-Mar-12 27-Sep-12 24-May-12 05-Mar-13 65.26% 15.04%
CivilCivil 36 24-Jun-12 A 04-Aug-12 46 09-May-12 19-Jun-12 09-Jun-12 29-Sep-12 100% 20.59%
A113940 Sub & App- Water Proofing for Roof 30 24-Jun-12 A 08-Jul-12 5 15-May-12 19-Jun-12 09-Jun-12 14-Jul-12 21 100% 50%
A8190 Sub & App- Water Proofing for Wet Areas 30 01-Jul-12 04-Aug-12 46 09-May-12 12-Jun-12 26-Aug-12 29-Sep-12 90 100% 0%
ArchitecArchitectural 104 12-May-12 A 12-Sep-12 99 10-Mar-12 12-Sep-12 24-May-12 12-Jan-13 55.89% 6.51%
Wet WorkWet Works 21 16-May-12 A 12-Jul-12 38 15-Mar-12 08-Apr-12 01-Aug-12 27-Aug-12 100% 50%
A7240 Sub & App- Paint Materials 21 16-May-12 A 12-Jul-12 38 15-Mar-12 08-Apr-12 01-Aug-12 27-Aug-12 118 100% 50%
CeilingCeiling 21 05-Jul-12 29-Jul-12 -35 27-Mar-12 19-Apr-12 24-May-12 18-Jun-12 100% 0%
A7260 Sub & App- Ceiling Suspension System 21 05-Jul-12 29-Jul-12 -35 27-Mar-12 19-Apr-12 24-May-12 18-Jun-12 50 100% 0%
Walls & FWalls & Floors 84 12-May-12 A 18-Aug-12 119 24-May-12 18-Aug-12 18-Jun-12 12-Jan-13 63.57% 5%
A7480 Sub & App- Terrazo Tiles 21 25-Jun-12 A 12-Jul-12 84 24-May-12 18-Jun-12 26-Sep-12 20-Oct-12 104 100% 50%
A7670 Sub & App- Precast Conc. Interlocking Paving 21 12-May-12 A 17-Jul-12 121 05-Jul-12 29-Jul-12 17-Nov-12 11-Dec-12 110 0% 50%
A7270 Sub & App- Granite Tiles 21 01-Jul-12 24-Jul-12 55 07-Jun-12 02-Jul-12 05-Sep-12 29-Sep-12 74 90.48% 0%
A7490 Sub & App- Ceramic Tiles 21 01-Jul-12 24-Jul-12 -11 30-May-12 24-Jun-12 18-Jun-12 11-Jul-12 15 100% 0%
A7500 Sub & App- Marble Tiles 21 01-Jul-12 24-Jul-12 40 30-May-12 24-Jun-12 16-Aug-12 11-Sep-12 66 100% 0%
A7660 Sub & App- Vinyel Sheet 21 01-Jul-12 24-Jul-12 119 05-Jun-12 30-Jun-12 22-Nov-12 17-Dec-12 140 100% 0%
A8370 Sub & App- MDF Cladding 21 01-Jul-12 24-Jul-12 64 11-Jun-12 05-Jul-12 16-Sep-12 09-Oct-12 80 76.19% 0%
A113970 Sub & App- Carpet Tiles 21 01-Jul-12 24-Jul-12 112 30-May-12 24-Jun-12 13-Nov-12 09-Dec-12 138 100% 0%
A113990 Sub & App- Honed Limestone 21 01-Jul-12 24-Jul-12 67 05-Jun-12 30-Jun-12 19-Sep-12 13-Oct-12 88 100% 0%
A114000 Sub & App- Mosiac Tiles 21 01-Jul-12 24-Jul-12 -9 30-May-12 24-Jun-12 20-Jun-12 14-Jul-12 17 100% 0%
A114010 Sub & App- Natural Stone 21 01-Jul-12 24-Jul-12 57 11-Jun-12 05-Jul-12 08-Sep-12 01-Oct-12 73 76.19% 0%
A114020 Sub & App- Polished Moche Tiles 21 01-Jul-12 24-Jul-12 57 30-May-12 24-Jun-12 08-Sep-12 01-Oct-12 83 100% 0%
A114030 Sub & App- Raised Floor Tiles 21 01-Jul-12 24-Jul-12 137 30-May-12 24-Jun-12 15-Dec-12 08-Jan-13 163 100% 0%
A114040 Sub & App- Veneer Cladding 21 01-Jul-12 24-Jul-12 71 30-May-12 24-Jun-12 24-Sep-12 17-Oct-12 97 100% 0%
A114050 Sub & App- Wenge cCladding 21 01-Jul-12 24-Jul-12 59 24-Jun-12 17-Jul-12 10-Sep-12 03-Oct-12 65 28.57% 0%
A7680 Sub & App- Precast Conc. Kerbs 21 05-Jul-12 29-Jul-12 102 05-Jul-12 29-Jul-12 06-Nov-12 01-Dec-12 102 0% 0%
A8360 Sub & App- Vinyl Wall Covering 21 05-Jul-12 29-Jul-12 136 05-Jul-12 29-Jul-12 18-Dec-12 12-Jan-13 136 0% 0%
A113950 Sub & App- Heavy Duty Tiles 21 05-Jul-12 29-Jul-12 76 05-Jul-12 29-Jul-12 04-Oct-12 30-Oct-12 76 0% 0%
A7520 Sub & App- Wooden Floor 21 21-Jul-12 14-Aug-12 68 14-Jul-12 06-Aug-12 10-Oct-12 05-Nov-12 74 0% 0%
A7230 Sub & App- Porcelain Tiles 21 25-Jul-12 18-Aug-12 12 25-Jul-12 18-Aug-12 08-Aug-12 03-Sep-12 12 0% 0%
Doors & Doors & Windows 71 20-Jun-12 A 12-Sep-12 72 10-Mar-12 12-Sep-12 06-Sep-12 10-Dec-12 66.67% 16.67%
A7450 Sub & App- Fire Rated Doors 21 24-Jun-12 A 12-Jul-12 124 10-Mar-12 02-Apr-12 14-Nov-12 10-Dec-12 209 100% 50%
A7470 Sub & App- Curtain Wall&Glazing 21 20-Jun-12 A 12-Jul-12 67 24-May-12 18-Jun-12 06-Sep-12 30-Sep-12 87 100% 50%
A7350 Sub & App- Galzed Aluminum Doors 21 01-Jul-12 24-Jul-12 107 07-May-12 30-May-12 07-Nov-12 03-Dec-12 153 100% 0%
A7430 Sub & App- Aluminum Louver Doors 21 01-Jul-12 24-Jul-12 111 10-Mar-12 02-Apr-12 12-Nov-12 08-Dec-12 207 100% 0%
A7340 Sub & App- Wooden Doors 21 21-Jul-12 14-Aug-12 40 11-Jul-12 04-Aug-12 08-Sep-12 01-Oct-12 48 0% 0%
A114060 Sub & App- Ironmongery 21 18-Aug-12 12-Sep-12 63 18-Aug-12 12-Sep-12 04-Nov-12 28-Nov-12 63 0% 0%
MetalMetal 21 01-Jul-12 24-Jul-12 123 19-May-12 05-Jul-12 30-May-12 22-Dec-12 88.1% 0%
A7280 Sub & App- Sinages 21 01-Jul-12 24-Jul-12 123 11-Jun-12 05-Jul-12 27-Nov-12 22-Dec-12 139 76.19% 0%
A7420 Sub & App- Balustrades and Handrails 21 01-Jul-12 24-Jul-12 -26 19-May-12 11-Jun-12 30-May-12 24-Jun-12 10 100% 0%
Soft LandSoft Landscping 21 01-Jul-12 24-Jul-12 110 11-Jul-12 29-Aug-12 22-Aug-12 06-Dec-12 0% 0%
A8390 Sub & App- Landscaping Light 21 01-Jul-12 24-Jul-12 110 04-Aug-12 29-Aug-12 11-Nov-12 06-Dec-12 81 0% 0%
A114080 Sub & App- Soft Landscping Items 21 01-Jul-12 24-Jul-12 43 11-Jul-12 04-Aug-12 22-Aug-12 15-Sep-12 34 0% 0%
OthersOthers 59 01-Jul-12 09-Sep-12 59 05-Jun-12 03-Sep-12 02-Aug-12 19-Nov-12 15.56% 0%
A124220 Sub & App- Sky Light 21 01-Jul-12 24-Jul-12 28 05-Jun-12 30-Jun-12 02-Aug-12 28-Aug-12 49 100% 0%
A7250 Sub & App- Toliets Accessories 21 05-Jul-12 29-Jul-12 84 05-Jul-12 29-Jul-12 14-Oct-12 08-Nov-12 84 0% 0%
A7370 Sub & App- Waredrobes 21 21-Jul-12 14-Aug-12 23 11-Jul-12 04-Aug-12 16-Aug-12 11-Sep-12 31 0% 0%
A7360 Sub & App- Kitchen Cabinets 30 21-Jul-12 27-Aug-12 70 14-Jul-12 16-Aug-12 13-Oct-12 19-Nov-12 76 0% 0%
A7290 Sub & App- Mirrors & Glasses 21 08-Aug-12 03-Sep-12 56 08-Aug-12 03-Sep-12 15-Oct-12 10-Nov-12 56 0% 0%
A7380 Sub & App- Vanity Counters 21 13-Aug-12 09-Sep-12 49 04-Aug-12 29-Aug-12 11-Oct-12 06-Nov-12 57 0% 0%
MechaniMechanical 155 19-Feb-12 A 27-Sep-12 89 17-Mar-12 27-Sep-12 31-May-12 15-Jan-13 77.68% 15.89%
HVACHVAC 155 19-Feb-12 A 27-Sep-12 55 17-Mar-12 27-Sep-12 31-May-12 05-Dec-12 56.48% 17.36%
A8080 Sub & App- AHU 21 19-Feb-12 A 12-Jul-12 55 17-Mar-12 09-Apr-12 23-Aug-12 16-Sep-12 134 100% 50%
A8090 Sub & App- FAHU 21 19-Feb-12 A 12-Jul-12 54 09-Apr-12 02-May-12 22-Aug-12 15-Sep-12 113 100% 50%
A8340 Sub & App- Ventilation & Exhuast Fans 25 17-May-12 A 15-Jul-12 100 17-Mar-12 14-Apr-12 13-Oct-12 12-Nov-12 177 100% 50%
A8120 Sub & App- Condensate Pipes-Fittings-Valves 21 01-Jul-12 24-Jul-12 35 17-Mar-12 09-Apr-12 31-May-12 25-Jun-12 65 100% 0%
A8160 Sub & App- Air Oulets 21 01-Jul-12 24-Jul-12 109 21-Apr-12 14-May-12 10-Nov-12 05-Dec-12 169 100% 0%
A8320 Sub & App- Variable Frequency Drive 28 01-Jul-12 01-Aug-12 67 01-Jul-12 01-Aug-12 19-Sep-12 21-Oct-12 67 0% 0%
A8270 Sub & App- Heat Exchanger (HEX) 21 23-Aug-12 17-Sep-12 39 25-Aug-12 17-Sep-12 09-Oct-12 04-Nov-12 39 0% 0%
A8300 Sub & App- Primary Chil led Water Pump 35 15-Aug-12 27-Sep-12 30 16-Aug-12 27-Sep-12 23-Sep-12 04-Nov-12 30 0% 0%
PlumbingPlumbing 71 02-May-12 A 24-Jul-12 143 17-Mar-12 24-Jul-12 22-Jul-12 15-Jan-13 88.36% 11.11%
A7900 Sub & App- Floor Drains 21 02-May-12 A 12-Jul-12 154 17-Mar-12 09-Apr-12 22-Dec-12 15-Jan-13 233 100% 50%
A7930 Sub & App- PPR Pipes -Fittings-Valves (Water) 21 26-May-12 A 12-Jul-12 29 27-Mar-12 19-Apr-12 22-Jul-12 14-Aug-12 99 100% 50%
A7910 Sub & App- Sump Pump 21 01-Jul-12 24-Jul-12 128 28-Mar-12 21-Apr-12 04-Dec-12 27-Dec-12 208 100% 0%
A7940 Sub & App- Transfer Pump 21 01-Jul-12 24-Jul-12 109 09-Apr-12 02-May-12 10-Nov-12 05-Dec-12 179 100% 0%
A7960 Sub & App- Steam Pipes for Boilers 21 01-Jul-12 24-Jul-12 117 26-May-12 19-Jun-12 20-Nov-12 15-Dec-12 147 100% 0%
A104340 Sub & App- GRP Water Tank 21 01-Jul-12 24-Jul-12 99 01-Jul-12 24-Jul-12 29-Oct-12 22-Nov-12 99 0% 0%
A104240 Sub & App- Water Boiler Tank 21 01-Jul-12 24-Jul-12 103 14-May-12 06-Jun-12 03-Nov-12 27-Nov-12 143 100% 0%
A104260 Sub & App- Water Boiler 21 01-Jul-12 24-Jul-12 96 09-Apr-12 02-May-12 23-Oct-12 19-Nov-12 166 100% 0%
A104270 Sub & App- Water Boiler Pump 21 01-Jul-12 24-Jul-12 140 06-Jun-12 01-Jul-12 18-Dec-12 12-Jan-13 160 95.24% 0%
Fire FighFire Fighitng 30 01-Jul-12 04-Aug-12 71 17-Mar-12 14-May-12 06-Sep-12 30-Oct-12 100% 0%
A8010 Sub & App- Landing Valves 21 01-Jul-12 24-Jul-12 80 21-Apr-12 14-May-12 04-Oct-12 30-Oct-12 140 100% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Facade Lighitng Drawings
Submission of Cooking Station Drawings
Approval of Cooking Station Drawings
Sub & App- MOS for Wall&Floor Tiles
Sub & App- MOS for Panintng
Sub & App- MOS for Piping Works
Sub & App- MOS for Water Proofing
Sub & App- MOS for Tiling
Sub & App- Garbage Chute System Subcontractor
Sub & App- Linen Chute System Subcontractor
Sub & App- Susbended Ceilings Subcontractor
Sub & App- Wood & Joinery Subcontractor
Sub & App- GRP Lining Subcontractor
Sub & App- Traffic Deck Coating Subcontractor
Sub & App- Facade Lighting Subcontractor
Sub & App- Cooking Station Subcontractor
Sub & App- Water Proofing for Roof
Sub & App- Water Proofing for Wet Areas
Sub & App- Paint Materials
Sub & App- Ceiling Suspension System
Sub & App- Terrazo Tiles
Sub & App- Precast Conc. Interlocking Paving
Sub & App- Granite Tiles
Sub & App- Ceramic Tiles
Sub & App- Marble Tiles
Sub & App- Vinyel Sheet
Sub & App- MDF Cladding
Sub & App- Carpet Tiles
Sub & App- Honed Limestone
Sub & App- Mosiac Tiles
Sub & App- Natural Stone
Sub & App- Polished Moche Tiles
Sub & App- Raised Floor Tiles
Sub & App- Veneer Cladding
Sub & App- Wenge cCladding
Sub & App- Precast Conc. Kerbs
Sub & App- Vinyl Wall Covering
Sub & App- Heavy Duty Tiles
Sub & App- Wooden Floor
Sub & App- Porcelain Tiles
Sub & App- Fire Rated Doors
Sub & App- Curtain Wall&Glazing
Sub & App- Galzed Aluminum Doors
Sub & App- Aluminum Louver Doors
Sub & App- Wooden Doors
Sub & App- Ironmongery
Sub & App- Sinages
Sub & App- Balustrades and Handrails
Sub & App- Landscaping Light
Sub & App- Soft Landscping Items
Sub & App- Sky Light
Sub & App- Toliets Accessories
Sub & App- Waredrobes
Sub & App- Kitchen Cabinets
Sub & App- Mirrors & Glasses
Sub & App- Vanity Counters
Sub & App- AHU
Sub & App- FAHU
Sub & App- Ventilation & Exhuast Fans
Sub & App- Condensate Pipes-Fittings-Valves
Sub & App- Air Oulets
Sub & App- Variable Frequency Drive
Sub & App- Heat Exchanger (HEX)
Sub & App- Primary Chil led Water Pump
Sub & App- Floor Drains
Sub & App- PPR Pipes -Fittings-Valves (Water)
Sub & App- Sump Pump
Sub & App- Transfer Pump
Sub & App- Steam Pipes for Boilers
Sub & App- GRP Water Tank
Sub & App- Water Boiler Tank
Sub & App- Water Boiler
Sub & App- Water Boiler Pump
Sub & App- Landing Valves
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 10 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A7780 Sub & App- Fire Alram Devices 30 01-Jul-12 04-Aug-12 56 17-Mar-12 19-Apr-12 06-Sep-12 10-Oct-12 146 100% 0%
CoveyingCoveying System 21 22-Mar-12 A 12-Jul-12 26 13-May-12 05-Jun-12 06-Jun-12 11-Aug-12 100% 50%
A7550 Sub & App- Passenger Lifts 21 22-Mar-12 A 12-Jul-12 26 13-May-12 05-Jun-12 18-Jul-12 11-Aug-12 56 100% 50%
A114290 Sub & App- Brakets,Guide Rails and Others 21 22-Mar-12 A 12-Jul-12 -10 13-May-12 05-Jun-12 06-Jun-12 01-Jul-12 21 100% 50%
ElectricalElectrical 141 03-Mar-12 A 14-Aug-12 61 17-Mar-12 14-Aug-12 02-Jun-12 29-Oct-12 88.89% 38.89%
Low CurrLow Current Systems 113 03-Mar-12 A 21-Jul-12 83 17-Mar-12 25-Apr-12 02-Jun-12 29-Oct-12 100% 50%
A7830 Sub & App- Access Control System 35 02-Jun-12 A 21-Jul-12 -7 17-Mar-12 25-Apr-12 02-Jun-12 12-Jul-12 66 100% 50%
A7840 Sub & App- Central Battery System 35 03-Mar-12 A 21-Jul-12 70 17-Mar-12 25-Apr-12 02-Sep-12 11-Oct-12 142 100% 50%
A7870 Sub & App- BMS 35 27-May-12 A 21-Jul-12 1 17-Mar-12 25-Apr-12 10-Jun-12 21-Jul-12 73 100% 50%
A8240 Sub & App- GSM System 35 23-May-12 A 21-Jul-12 83 17-Mar-12 25-Apr-12 17-Sep-12 29-Oct-12 155 100% 50%
A8400 Sub & App- MATV/ Interactive TV System 35 26-May-12 A 21-Jul-12 53 17-Mar-12 25-Apr-12 11-Aug-12 22-Sep-12 125 100% 50%
ElectricaElectrical Equipments 95 19-Apr-12 A 09-Aug-12 39 17-Mar-12 30-May-12 22-Jul-12 26-Sep-12 100% 33.33%
A7800 Sub & App- Generators 35 19-Apr-12 A 21-Jul-12 52 21-Apr-12 30-May-12 09-Aug-12 20-Sep-12 94 100% 50%
A8670 Sub & App- Telephone System 35 26-May-12 A 21-Jul-12 36 17-Mar-12 25-Apr-12 22-Jul-12 02-Sep-12 108 100% 50%
A7860 Sub & App- UPS 35 01-Jul-12 09-Aug-12 39 17-Mar-12 25-Apr-12 15-Aug-12 26-Sep-12 129 100% 0%
OthersOthers 35 05-Jul-12 14-Aug-12 56 05-Jul-12 14-Aug-12 11-Sep-12 21-Oct-12 0% 0%
A7880 Sub & App- Light Fixtures 35 05-Jul-12 14-Aug-12 56 05-Jul-12 14-Aug-12 11-Sep-12 21-Oct-12 56 0% 0%
SpecialitSpeciality Works 100 14-Mar-12 A 18-Aug-12 163 01-May-12 10-Sep-12 11-Jun-12 05-Mar-13 53.71% 14.84%
SwimminSwimming Pool 24 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 09-Aug-12 12-Dec-12 0% 50%
A7560 Sub & App- Pool Finishes 21 14-Mar-12 A 12-Jul-12 119 11-Jul-12 04-Aug-12 08-Nov-12 04-Dec-12 99 0% 50%
A7570 Sub & App- Pool Equipments 21 26-Apr-12 A 12-Jul-12 45 11-Jul-12 04-Aug-12 09-Aug-12 04-Sep-12 25 0% 50%
A8180 Sub & App- Water Proofing for Swimming Pool 21 26-Apr-12 A 12-Jul-12 124 11-Jul-12 04-Aug-12 14-Nov-12 10-Dec-12 104 0% 50%
A104220 Sub & App- Pool Electrical Items 21 14-Mar-12 A 12-Jul-12 126 11-Jul-12 04-Aug-12 18-Nov-12 12-Dec-12 106 0% 50%
Garbage Garbage Chute System 40 03-Jul-12 18-Aug-12 17 01-May-12 16-Jun-12 11-Jun-12 09-Sep-12 100% 0%
A7580 Sub & App- Pipes & Fittings 21 03-Jul-12 26-Jul-12 21 01-May-12 24-May-12 28-Jul-12 22-Aug-12 74 100% 0%
A104180 Sub & App- Equipments 28 03-Jul-12 04-Aug-12 29 01-May-12 02-Jun-12 06-Aug-12 09-Sep-12 82 100% 0%
A104190 Sub & App- Garbage Chutes 40 03-Jul-12 18-Aug-12 -18 01-May-12 16-Jun-12 11-Jun-12 28-Jul-12 35 100% 0%
Linen ChLinen Chute System 40 03-Jul-12 18-Aug-12 -9 05-Jun-12 22-Jul-12 14-Jun-12 07-Aug-12 70.79% 0%
A114140 Sub & App- Pipes & Fittings 21 03-Jul-12 26-Jul-12 -15 05-Jun-12 30-Jun-12 14-Jun-12 09-Jul-12 8 100% 0%
A114120 Sub & App- Equipments 28 03-Jul-12 04-Aug-12 -4 05-Jun-12 08-Jul-12 28-Jun-12 30-Jul-12 19 75% 0%
A114130 Sub & App- Linen Chutes 40 03-Jul-12 18-Aug-12 -9 05-Jun-12 22-Jul-12 23-Jun-12 07-Aug-12 14 52.5% 0%
Facade CFacade Cleaning System 21 01-Jul-12 24-Jul-12 184 15-Aug-12 10-Sep-12 10-Feb-13 05-Mar-13 0% 0%
A7600 Sub & App- Cleaning System 21 01-Jul-12 24-Jul-12 184 15-Aug-12 10-Sep-12 10-Feb-13 05-Mar-13 145 0% 0%
ProvisioProvisional Sum 61 01-Jul-12 11-Sep-12 69 24-Jun-12 11-Sep-12 12-Jul-12 05-Dec-12 14.29% 0%
Kitchen EKitchen Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 28.57% 0%
A8650 Sub & App- Kitchen Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 16 28.57% 0%
LaundaryLaundary Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 28.57% 0%
A114220 Sub & App- Laundary Equipments 21 01-Jul-12 24-Jul-12 10 24-Jun-12 17-Jul-12 12-Jul-12 05-Aug-12 16 28.57% 0%
Facade LFacade Lighting 21 16-Aug-12 11-Sep-12 22 16-Aug-12 11-Sep-12 13-Sep-12 07-Oct-12 0% 0%
A115260 Sub & App- Facade Lighting 21 16-Aug-12 11-Sep-12 22 16-Aug-12 11-Sep-12 13-Sep-12 07-Oct-12 22 0% 0%
Cooking Cooking Station 21 25-Jul-12 18-Aug-12 88 09-Jul-12 01-Aug-12 10-Nov-12 05-Dec-12 0% 0%
A124710 Sub & App- Cooking Station 21 25-Jul-12 18-Aug-12 88 09-Jul-12 01-Aug-12 10-Nov-12 05-Dec-12 102 0% 0%
ProcuremProcurement and Delivery 305 19-Feb-12 A 18-Feb-13 123 18-Feb-12 22-Jan-13 28-Feb-12 13-Jul-13 26.21% 2.46%
CivilCivil 113 09-Jul-12 22-Nov-12 46 13-Jun-12 16-Oct-12 15-Jul-12 17-Jan-13 7.42% 0%
A6400 Order&Delivery- GRP Lining 60 21-Jul-12 01-Oct-12 62 01-Jul-12 10-Sep-12 03-Oct-12 16-Dec-12 79 0% 0%
A9170 Order&Delivery- Reinforced Plastic 60 21-Jul-12 01-Oct-12 76 01-Jul-12 10-Sep-12 20-Oct-12 02-Jan-13 93 0% 0%
A46460 Order&Delivery- Water Proofing for Roof 100 09-Jul-12 06-Nov-12 5 20-Jun-12 16-Oct-12 15-Jul-12 12-Nov-12 21 9% 0%
A6930 Order&Delivery- Water Proofing for Wet Areas 90 05-Aug-12 22-Nov-12 46 13-Jun-12 29-Sep-12 30-Sep-12 17-Jan-13 90 15.56% 0%
ArchitecArchitectural 175 11-Jun-12 A 09-Jan-13 106 28-Mar-12 10-Jan-13 25-Jun-12 13-May-13 13.66% 0.56%
Wet WorkWet Works 87 11-Jun-12 A 23-Sep-12 38 28-Mar-12 18-Jun-12 10-Jul-12 07-Nov-12 100% 17.5%
A5570 Order&Delivery- Plaster Materials 30 11-Jun-12 A 17-Jul-12 44 26-Apr-12 30-May-12 04-Aug-12 09-Sep-12 84 100% 50%
A5580 Order&Delivery- Blocks 30 11-Jun-12 A 28-Jul-12 21 28-Mar-12 01-May-12 10-Jul-12 13-Aug-12 88 100% 20%
A5510 Order&Delivery- Paint Materials 60 12-Jul-12 23-Sep-12 38 09-Apr-12 18-Jun-12 28-Aug-12 07-Nov-12 118 100% 0%
CeilingCeiling 135 01-Jul-12 11-Dec-12 63 07-May-12 14-Nov-12 12-Jul-12 25-Feb-13 28.44% 0%
A5720 Order&Delivery- Fibre Celing System 90 01-Jul-12 15-Oct-12 91 07-May-12 22-Aug-12 17-Oct-12 05-Feb-13 137 51.11% 0%
A9130 Order&Delivery- Metal Celing System 90 01-Jul-12 15-Oct-12 57 19-May-12 03-Sep-12 08-Sep-12 25-Dec-12 93 40% 0%
A9330 Order&Delivery- MDF Ceiling System 90 01-Jul-12 15-Oct-12 108 24-Jun-12 08-Oct-12 08-Nov-12 25-Feb-13 114 6.67% 0%
A9270 Order&Delivery- Aluminum Ceiling Tiles 90 29-Jul-12 14-Nov-12 78 29-Jul-12 14-Nov-12 01-Nov-12 18-Feb-13 78 0% 0%
A5530 Order&Delivery- Gybsum Ceiling System 90 25-Aug-12 11-Dec-12 -35 14-May-12 29-Aug-12 12-Jul-12 29-Oct-12 50 44.44% 0%
Walls & FWalls & Floors 135 01-Jul-12 11-Dec-12 126 30-May-12 11-Dec-12 12-Jul-12 09-May-13 3.49% 0%
A9310 Order&Delivery- Water Jet Limestone Tiles 90 01-Jul-12 15-Oct-12 78 30-May-12 15-Sep-12 02-Oct-12 20-Jan-13 104 28.89% 0%
A5750 Order&Delivery- Terrazo Tiles 90 12-Jul-12 30-Oct-12 84 19-Jun-12 03-Oct-12 21-Oct-12 09-Feb-13 104 11.11% 0%
A6320 Order&Delivery- Precast Conc. Interlocking Paving 90 17-Jul-12 04-Nov-12 121 30-Jul-12 17-Nov-12 12-Dec-12 28-Mar-13 110 0% 0%
A5500 Order&Delivery- Porcelain Tiles 69 21-Aug-12 11-Nov-12 12 21-Aug-12 11-Nov-12 04-Sep-12 26-Nov-12 12 0% 0%
A9290 Order&Delivery- Honed Limestone Tiles 90 25-Jul-12 11-Nov-12 67 01-Jul-12 15-Oct-12 14-Oct-12 02-Feb-13 88 0% 0%
A9300 Order&Delivery- Polished Moche Tiles 90 25-Jul-12 11-Nov-12 57 25-Jun-12 09-Oct-12 02-Oct-12 20-Jan-13 83 5.56% 0%
A9240 Order&Delivery- Raised Floor Tiles 90 25-Jul-12 11-Nov-12 137 25-Jun-12 09-Oct-12 09-Jan-13 24-Apr-13 163 5.56% 0%
A6420 Order&Delivery- Precast Conc. Kerbs 90 30-Jul-12 17-Nov-12 102 30-Jul-12 17-Nov-12 03-Dec-12 19-Mar-13 102 0% 0%
A6110 Order&Delivery- Vinyel Sheet 95 25-Jul-12 18-Nov-12 119 01-Jul-12 21-Oct-12 18-Dec-12 09-Apr-13 140 0% 0%
A9320 Order&Delivery- Wenge Cladding 95 25-Jul-12 18-Nov-12 59 18-Jul-12 10-Nov-12 04-Oct-12 29-Jan-13 65 0% 0%
A5840 Order&Delivery- Natural Stone 95 25-Jul-12 18-Nov-12 57 07-Jul-12 29-Oct-12 02-Oct-12 27-Jan-13 73 0% 0%
A9140 Order&Delivery- Carpet Tiles 95 25-Jul-12 18-Nov-12 112 25-Jun-12 15-Oct-12 10-Dec-12 01-Apr-13 138 5.26% 0%
A7120 Order&Delivery- MDF Cladding 100 25-Jul-12 24-Nov-12 64 07-Jul-12 04-Nov-12 10-Oct-12 10-Feb-13 80 0% 0%
A7110 Order&Delivery- Vinyl Wall Covering 100 30-Jul-12 28-Nov-12 136 30-Jul-12 28-Nov-12 13-Jan-13 09-May-13 136 0% 0%
A5540 Order&Delivery- Granite Tiles 105 25-Jul-12 29-Nov-12 55 03-Jul-12 06-Nov-12 30-Sep-12 05-Feb-13 74 0% 0%
A5760 Order&Delivery- Ceramic Ti les 105 25-Jul-12 29-Nov-12 -11 25-Jun-12 29-Oct-12 12-Jul-12 17-Nov-12 15 4.76% 0%
A5770 Order&Delivery- Marble Tiles 105 25-Jul-12 29-Nov-12 40 25-Jun-12 29-Oct-12 12-Sep-12 17-Jan-13 66 4.76% 0%
A9120 Order&Delivery- Mosiac Tiles 105 25-Jul-12 29-Nov-12 -9 25-Jun-12 29-Oct-12 15-Jul-12 19-Nov-12 17 4.76% 0%
A9250 Order&Delivery- Veneer Cladding 110 25-Jul-12 06-Dec-12 71 25-Jun-12 04-Nov-12 18-Oct-12 02-Mar-13 97 4.55% 0%
A5790 Order&Delivery- Wooden Floor 95 14-Aug-12 10-Dec-12 68 07-Aug-12 01-Dec-12 06-Nov-12 28-Feb-13 74 0% 0%
A9260 Order&Delivery- Heavy Duty Tiles 110 30-Jul-12 11-Dec-12 76 30-Jul-12 11-Dec-12 31-Oct-12 12-Mar-13 76 0% 0%
Doors & Doors & Windows 148 12-Jul-12 09-Jan-13 66 03-Apr-12 29-Dec-12 02-Oct-12 27-Mar-13 44.87% 0%
A5710 Order&Delivery- Fire Rated Doors 90 12-Jul-12 30-Oct-12 124 03-Apr-12 17-Jul-12 11-Dec-12 27-Mar-13 209 83.33% 0%
A5620 Order&Delivery- Galzed Aluminum Doors 90 25-Jul-12 11-Nov-12 107 31-May-12 16-Sep-12 04-Dec-12 20-Mar-13 153 27.78% 0%
A5700 Order&Delivery- Aluminum Louver Doors 90 25-Jul-12 11-Nov-12 111 03-Apr-12 17-Jul-12 09-Dec-12 25-Mar-13 207 83.33% 0%
A5610 Order&Delivery- Wooden Doors 120 14-Aug-12 09-Jan-13 40 05-Aug-12 29-Dec-12 02-Oct-12 25-Feb-13 48 0% 0%
MetalMetal 120 25-Jul-12 18-Dec-12 123 12-Jun-12 28-Nov-12 25-Jun-12 13-May-13 6.25% 0%
A5550 Order&Delivery- Sinages 120 25-Jul-12 18-Dec-12 123 07-Jul-12 28-Nov-12 23-Dec-12 13-May-13 139 0% 0%
A5690 Order&Delivery- Balustrades and Handrails 120 25-Jul-12 18-Dec-12 -26 12-Jun-12 04-Nov-12 25-Jun-12 17-Nov-12 10 12.5% 0%
Soft LandSoft Landscping 110 25-Jul-12 06-Dec-12 110 05-Aug-12 10-Jan-13 16-Sep-12 16-Apr-13 0% 0%
A5590 Order&Delivery- Soft Landscping Items 100 25-Jul-12 24-Nov-12 43 05-Aug-12 05-Dec-12 16-Sep-12 15-Jan-13 34 0% 0%
A7140 Order&Delivery- Landscaping Light 110 25-Jul-12 06-Dec-12 110 30-Aug-12 10-Jan-13 08-Dec-12 16-Apr-13 81 0% 0%
OthersOthers 129 01-Jul-12 04-Dec-12 81 30-Jul-12 16-Dec-12 12-Sep-12 10-Mar-13 0% 0%
A51060 Order&Delivery- Irrigation System 90 01-Jul-12 15-Oct-12 112 29-Aug-12 16-Dec-12 13-Nov-12 02-Mar-13 63 0% 0%
A5520 Order&Delivery- Toliets Accessories 100 30-Jul-12 28-Nov-12 84 30-Jul-12 28-Nov-12 10-Nov-12 10-Mar-13 84 0% 0%
A5640 Order&Delivery- Waredrobes 90 14-Aug-12 04-Dec-12 23 05-Aug-12 22-Nov-12 12-Sep-12 30-Dec-12 31 0% 0%
MechaniMechanical 267 06-Mar-12 A 23-Jan-13 57 10-Apr-12 03-Dec-12 19-Apr-12 01-Apr-13 48.61% 5.16%
HVACHVAC 232 16-Apr-12 A 23-Jan-13 34 10-Apr-12 03-Dec-12 19-Apr-12 05-Mar-13 54.27% 12.56%
A6870 Order&Delivery- Ducts Insulation 15 01-Jul-12 17-Jul-12 71 02-Jul-12 18-Jul-12 24-Sep-12 10-Oct-12 70 0% 0%
A6890 Order&Delivery- Condensate Pipes Insulation 15 01-Jul-12 17-Jul-12 71 02-Jul-12 18-Jul-12 24-Sep-12 10-Oct-12 70 0% 0%
A6840 Order&Delivery- Chilled Water Pipes-Fittings-Valves 90 16-Apr-12 A 04-Aug-12 56 10-Apr-12 24-Jul-12 26-Jun-12 10-Oct-12 65 76.67% 66.67%
A6880 Order&Delivery- Chilled Pipes Insulation 30 01-Jul-12 04-Aug-12 56 07-Jun-12 12-Jul-12 06-Sep-12 10-Oct-12 75 63.33% 0%
A136190 Order&Delivery- Hangers & Supports 40 01-Jul-12 15-Aug-12 78 10-Apr-12 26-May-12 02-Oct-12 20-Nov-12 147 100% 0%
A6860 Order&Delivery- Condensate Pipes-Fittings-Valves 90 16-Apr-12 A 30-Aug-12 35 10-Apr-12 24-Jul-12 26-Jun-12 10-Oct-12 65 76.67% 66.67%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Sub & App- Fire Alram Devices
Sub & App- Passenger Lifts
Sub & App- Brakets,Guide Rails and Others
Sub & App- Access Control System
Sub & App- Central Battery System
Sub & App- BMS
Sub & App- GSM System
Sub & App- MATV/ Interactive TV System
Sub & App- Generators
Sub & App- Telephone System
Sub & App- UPS
Sub & App- Light Fixtures
Sub & App- Pool Finishes
Sub & App- Pool Equipments
Sub & App- Water Proofing for Swimming Pool
Sub & App- Pool Electrical Items
Sub & App- Pipes & Fittings
Sub & App- Equipments
Sub & App- Garbage Chutes
Sub & App- Pipes & Fittings
Sub & App- Equipments
Sub & App- Linen Chutes
Sub & App- Cleaning System
Sub & App- Kitchen Equipments
Sub & App- Laundary Equipments
Sub & App- Facade Lighting
Sub & App- Cooking Station
Order&Delivery- GRP Lining
Order&Delivery- Reinforced Plastic
Order&Delivery- Water Proofing for Roof
Order&Delivery- Water Proofing for Wet Areas
Order&Delivery- Plaster Materials
Order&Delivery- Blocks
Order&Delivery- Paint Materials
Order&Delivery- Fibre Celing System
Order&Delivery- Metal Celing System
Order&Delivery- MDF Ceiling System
Order&Delivery- Aluminum Ceiling Tiles
Order&Delivery- Gybsum Ceiling System
Order&Delivery- Water Jet Limestone Tiles
Order&Delivery- Terrazo Tiles
Order&Delivery- Precast Conc. Interlocking Paving
Order&Delivery- Porcelain Tiles
Order&Delivery- Honed Limestone Tiles
Order&Delivery- Polished Moche Tiles
Order&Delivery- Raised Floor Tiles
Order&Delivery- Precast Conc. Kerbs
Order&Delivery- Vinyel Sheet
Order&Delivery- Wenge Cladding
Order&Delivery- Natural Stone
Order&Delivery- Carpet Tiles
Order&Delivery- MDF Cladding
Order&Delivery- Vinyl Wall Covering
Order&Delivery- Granite Tiles
Order&Delivery- Ceramic Tiles
Order&Delivery- Marble Tiles
Order&Delivery- Mosiac Tiles
Order&Delivery- Veneer Cladding
Order&Delivery- Wooden Floor
Order&Delivery- Heavy Duty Tiles
Order&Delivery- Fire Rated Doors
Order&Delivery- Galzed Aluminum Doors
Order&Delivery- Aluminum Louver Doors
Order&Delivery- Wooden Doors
Order&Delivery- Sinages
Order&Delivery- Balustrades and Handrails
Order&Delivery- Soft Landscping Items
Order&Delivery- Landscaping Light
Order&Delivery- Irrigation System
Order&Delivery- Toliets Accessories
Order&Delivery- Waredrobes
Order&Delivery- Ducts Insulation
Order&Delivery- Condensate Pipes Insulation
Order&Delivery- Chilled Water Pipes-Fittings-Valves
Order&Delivery- Chilled Pipes Insulation
Order&Delivery- Hangers & Supports
Order&Delivery- Condensate Pipes-Fittings-Valves
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 11 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A6910 Order&Delivery- Fire and Volume Damper 60 01-Jul-12 10-Sep-12 115 09-May-12 18-Jul-12 18-Nov-12 29-Jan-13 159 73.33% 0%
A6800 Order&Delivery- HAVC Ducts 90 02-Jun-12 A 22-Sep-12 16 22-Apr-12 05-Aug-12 26-Jun-12 10-Oct-12 55 65.56% 0%
A6810 Order&Delivery- FCUs 75 01-Jul-12 27-Sep-12 23 10-Apr-12 07-Jul-12 28-Jul-12 24-Oct-12 92 92% 0%
A6900 Order&Delivery- Air Oulets 60 25-Jul-12 04-Oct-12 109 15-May-12 24-Jul-12 06-Dec-12 16-Feb-13 169 65% 0%
A7052 Order&Delivery- Ventilation & Exhuast Fans 90 15-Jul-12 01-Nov-12 100 15-Apr-12 29-Jul-12 13-Nov-12 02-Mar-13 177 72.22% 0%
A7051 Order&Delivery- Variable Frequency Drive 100 02-Aug-12 03-Dec-12 67 02-Aug-12 03-Dec-12 22-Oct-12 21-Feb-13 67 0% 0%
A6830 Order&Delivery- FAHU 100 16-Aug-12 18-Dec-12 54 07-Jun-12 04-Oct-12 21-Oct-12 20-Feb-13 113 19% 0%
A6820 Order&Delivery- AHU 110 16-Aug-12 30-Dec-12 55 15-May-12 23-Sep-12 22-Oct-12 05-Mar-13 134 35.45% 0%
A7050 Order&Delivery- Chiller 180 16-Jun-12 A 23-Jan-13 -52 10-Apr-12 11-Nov-12 19-Apr-12 21-Nov-12 8 38.33% 15%
PlumbingPlumbing 220 06-Mar-12 A 24-Nov-12 107 10-Apr-12 24-Nov-12 13-Aug-12 01-Apr-13 43.29% 0.21%
A6630 Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge) 30 06-Mar-12 A 02-Aug-12 39 27-May-12 01-Jul-12 13-Aug-12 18-Sep-12 66 96.67% 5%
A7020 Order&Delivery- Electrical Heaters 30 03-Jun-12 A 04-Aug-12 138 27-May-12 01-Jul-12 16-Dec-12 20-Jan-13 167 96.67% 0%
A6640 Order&Delivery- Floor Drains 30 12-Jul-12 16-Aug-12 154 10-Apr-12 14-May-12 16-Jan-13 20-Feb-13 233 100% 0%
A6670 Order&Delivery-PPR Pipes -Fittings-Valves (Water) 30 12-Jul-12 16-Aug-12 29 21-Apr-12 24-May-12 15-Aug-12 20-Sep-12 99 100% 0%
A6650 Order&Delivery- Sump Pump 60 25-Jul-12 04-Oct-12 128 22-Apr-12 01-Jul-12 29-Dec-12 10-Mar-13 208 98.33% 0%
A9200 Order&Delivery- Water Boiler Pump 60 25-Jul-12 04-Oct-12 140 02-Jul-12 11-Sep-12 13-Jan-13 24-Mar-13 160 0% 0%
A9220 Order&Delivery- Transfer Pump 90 25-Jul-12 11-Nov-12 109 03-May-12 16-Aug-12 06-Dec-12 23-Mar-13 179 54.44% 0%
A9180 Order&Delivery- Water Boiler 90 25-Jul-12 11-Nov-12 96 03-May-12 16-Aug-12 20-Nov-12 07-Mar-13 166 54.44% 0%
A9190 Order&Delivery- Water Boiler Tank 90 25-Jul-12 11-Nov-12 103 07-Jun-12 23-Sep-12 28-Nov-12 16-Mar-13 143 21.11% 0%
A9210 Order&Delivery- Steam Pipes for Boilers 90 25-Jul-12 11-Nov-12 117 20-Jun-12 04-Oct-12 16-Dec-12 01-Apr-13 147 10% 0%
A9400 Order&Delivery- GRP Water Tank 100 25-Jul-12 24-Nov-12 99 25-Jul-12 24-Nov-12 24-Nov-12 23-Mar-13 99 0% 0%
Fire FighFire Fighitng 154 02-Jun-12 A 05-Dec-12 69 10-Apr-12 23-Sep-12 21-Jun-12 26-Feb-13 51.59% 0%
A6780 Order&Delivery- Foam Spary System for Generators 60 01-Jul-12 10-Sep-12 139 20-Jun-12 30-Aug-12 17-Dec-12 26-Feb-13 148 15% 0%
A6710 Order&Delivery- Fire Pipes-Fittings-Valves 90 02-Jun-12 A 22-Sep-12 12 10-Apr-12 24-Jul-12 21-Jun-12 06-Oct-12 61 76.67% 0%
A6730 Order&Delivery- Sprinklers 90 01-Jul-12 15-Oct-12 89 10-Apr-12 24-Jul-12 15-Oct-12 03-Feb-13 158 76.67% 0%
A6740 Order&Delivery- Fire Extinguishers & Banket 90 01-Jul-12 15-Oct-12 101 27-May-12 11-Sep-12 31-Oct-12 17-Feb-13 130 32.22% 0%
A6760 Order&Delivery- Fire Hose Cabinets 90 01-Jul-12 15-Oct-12 101 27-May-12 11-Sep-12 31-Oct-12 17-Feb-13 130 32.22% 0%
A9410 Order&Delivery- FM 200 System 90 07-Jun-12 A 15-Oct-12 91 21-Apr-12 04-Aug-12 17-Oct-12 05-Feb-13 151 66.67% 0%
A6750 Order&Delivery- Landing Valves 90 25-Jul-12 11-Nov-12 80 15-May-12 30-Aug-12 31-Oct-12 17-Feb-13 140 43.33% 0%
A9000 Order&Delivery- Fire Alarm Devices 90 05-Aug-12 22-Nov-12 56 21-Apr-12 04-Aug-12 11-Oct-12 30-Jan-13 146 66.67% 0%
A9230 Order&Delivery- Fire Fighting Pump 130 01-Jul-12 05-Dec-12 50 22-Apr-12 23-Sep-12 30-Aug-12 04-Feb-13 109 45.38% 0%
LPG SysLPG System 60 01-Jul-12 10-Sep-12 139 07-Jun-12 05-Nov-12 17-Dec-12 26-Feb-13 21.11% 0%
A7190 Order&Delivery- LPG Tanks( 2000 Gallons) 30 01-Jul-12 04-Aug-12 164 30-Sep-12 05-Nov-12 16-Jan-13 20-Feb-13 88 0% 0%
A7180 Order&Delivery- LPG Pipes-Fittings-Valves 60 01-Jul-12 10-Sep-12 139 07-Jun-12 16-Aug-12 17-Dec-12 26-Feb-13 158 31.67% 0%
CoveyingCoveying System 100 12-Jul-12 11-Nov-12 -10 06-Jun-12 03-Oct-12 02-Jul-12 30-Oct-12 20% 0%
A1143 Order&Delivery- Brakets,Guide Rails and Others 100 12-Jul-12 11-Nov-12 -10 06-Jun-12 03-Oct-12 02-Jul-12 30-Oct-12 21 20% 0%
ElectricalElectrical 261 19-Feb-12 A 26-Dec-12 52 18-Feb-12 08-Nov-12 28-Feb-12 26-Feb-13 55.71% 7.86%
Cable TraCable Trays - Cables 46 07-Jun-12 A 23-Aug-12 44 26-Apr-12 24-Jun-12 23-Aug-12 14-Oct-12 100% 0%
A6500 Order&Delivery- Cable Trays 45 07-Jun-12 A 23-Aug-12 44 26-Apr-12 18-Jun-12 23-Aug-12 14-Oct-12 99 100% 0%
A6510 Order&Delivery- Trunking 45 07-Jun-12 A 23-Aug-12 44 02-May-12 24-Jun-12 23-Aug-12 14-Oct-12 94 100% 0%
Low CurrLow Current Systems 94 21-Jul-12 11-Nov-12 79 26-Apr-12 22-Sep-12 02-Aug-12 16-Feb-13 56.45% 0%
A7150 Order&Delivery- MATV/ Interactive TV System 60 21-Jul-12 01-Oct-12 53 26-Apr-12 05-Jul-12 23-Sep-12 05-Dec-12 125 91.67% 0%
A6610 Order&Delivery- BMS 70 01-Aug-12 24-Oct-12 1 08-May-12 29-Jul-12 02-Aug-12 24-Oct-12 73 64.29% 0%
A6990 Order&Delivery- GSM System 90 21-Jul-12 07-Nov-12 83 26-Apr-12 09-Aug-12 30-Oct-12 16-Feb-13 155 61.11% 0%
A6560 Order&Delivery- CCTV System 90 25-Jul-12 11-Nov-12 28 06-Jun-12 22-Sep-12 29-Aug-12 16-Dec-12 69 22.22% 0%
ElectricaElectrical Equipments 120 01-Aug-12 26-Dec-12 52 12-Jun-12 04-Nov-12 03-Oct-12 26-Feb-13 12.5% 0%
A6540 Order&Delivery- Generators 120 01-Aug-12 26-Dec-12 52 12-Jun-12 04-Nov-12 03-Oct-12 26-Feb-13 94 12.5% 0%
OthersOthers 222 19-Feb-12 A 08-Nov-12 56 18-Feb-12 08-Nov-12 28-Feb-12 16-Jan-13 61.11% 30.56%
A136180 Order&Delivery- Earthing & Lightining 7 19-Feb-12 A 04-Jul-12 29 18-Feb-12 25-Feb-12 28-Feb-12 06-Mar-12 9 100% 50%
A6660 Order&Delivery- Conduits & PVC Ducts 40 10-Mar-12 A 23-Jul-12 104 09-Apr-12 24-May-12 26-Sep-12 13-Nov-12 143 100% 50%
A6620 Order&Delivery- Light Fixtures 70 15-Aug-12 08-Nov-12 56 15-Aug-12 08-Nov-12 22-Oct-12 16-Jan-13 56 0% 0%
SpecialitSpeciality Works 182 12-Jul-12 18-Feb-13 123 26-May-12 22-Jan-13 29-Jul-12 13-Jul-13 5.65% 0%
SwimminSwimming Pool 120 12-Jul-12 06-Dec-12 118 05-Aug-12 29-Dec-12 05-Sep-12 24-Apr-13 0% 0%
A5830 Order&Delivery- Finishes Items 80 12-Jul-12 16-Oct-12 119 05-Aug-12 10-Nov-12 05-Dec-12 10-Mar-13 99 0% 0%
A6920 Order&Delivery- Water Proofing for Swimming Pool 80 12-Jul-12 16-Oct-12 124 05-Aug-12 10-Nov-12 11-Dec-12 16-Mar-13 104 0% 0%
A9150 Order&Delivery- Electrical Items 80 12-Jul-12 16-Oct-12 126 05-Aug-12 10-Nov-12 13-Dec-12 18-Mar-13 106 0% 0%
A9280 Order&Delivery- Sand Stone Pavers 80 12-Jul-12 16-Oct-12 129 05-Aug-12 10-Nov-12 17-Dec-12 21-Mar-13 109 0% 0%
A9160 Order&Delivery- Pocalin for Pool Deck 100 12-Jul-12 11-Nov-12 138 05-Aug-12 05-Dec-12 27-Dec-12 24-Apr-13 118 0% 0%
A44340 Order&Delivery- Swimming Pool Equipments 120 12-Jul-12 06-Dec-12 45 05-Aug-12 29-Dec-12 05-Sep-12 29-Jan-13 25 0% 0%
External External Facade 110 12-Jul-12 24-Nov-12 67 19-Jun-12 29-Oct-12 01-Oct-12 12-Feb-13 9.09% 0%
A5740 Order&Delivery- Curtain Wall&Glazing 110 12-Jul-12 24-Nov-12 67 19-Jun-12 29-Oct-12 01-Oct-12 12-Feb-13 87 9.09% 0%
Facade CFacade Cleaning 110 25-Jul-12 06-Dec-12 184 11-Sep-12 22-Jan-13 06-Mar-13 13-Jul-13 0% 0%
A5870 Order&Delivery- Facade Cleaning System 110 25-Jul-12 06-Dec-12 184 11-Sep-12 22-Jan-13 06-Mar-13 13-Jul-13 145 0% 0%
Garbage Garbage Chute 169 28-Jul-12 18-Feb-13 17 26-May-12 16-Dec-12 29-Jul-12 10-Mar-13 16% 0%
A5850 Order&Delivery- Pipes & Fittings 100 28-Jul-12 26-Nov-12 21 26-May-12 22-Sep-12 23-Aug-12 22-Dec-12 74 30% 0%
A9380 Order&Delivery- Equipments 150 05-Aug-12 04-Feb-13 29 03-Jun-12 01-Dec-12 10-Sep-12 10-Mar-13 82 15.33% 0%
A9390 Order&Delivery- Garbage Chutes 150 21-Aug-12 18-Feb-13 -18 18-Jun-12 16-Dec-12 29-Jul-12 28-Jan-13 35 7.33% 0%
Linen ChLinen Chute 150 21-Aug-12 18-Feb-13 -9 23-Jul-12 21-Jan-13 08-Aug-12 07-Feb-13 0% 0%
A114200 Order&Delivery- Linen Chutes 150 21-Aug-12 18-Feb-13 -9 23-Jul-12 21-Jan-13 08-Aug-12 07-Feb-13 14 0% 0%
ProvisioProvisional Sum 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0% 0%
Kitchen EKitchen Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0% 0%
A8640 Order&Delivery- Kitchen Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0 0% 0%
Lundary Lundary Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0% 0%
A114210 Order&Delivery- Laundary Equipments 108 13-Aug-12 23-Dec-12 -6 06-Aug-12 16-Dec-12 06-Aug-12 16-Dec-12 0 0% 0%
ConstruConstruction 83 14-Jun-12 A 19-Sep-12 200 15-May-12 04-Nov-12 19-Jul-12 16-May-13 0.92% 5.4%
Civil PacCivil Package 71 14-Jun-12 A 04-Sep-12 147 15-May-12 02-Oct-12 19-Jul-12 10-Feb-13 0.71% 6.68%
Hotel ApHotel Apartements (Block A) 63 21-Jun-12 A 04-Sep-12 53 15-May-12 02-Oct-12 26-Jul-12 11-Oct-12 2.67% 14.47%
1st Base1st Basement Floor Slab 2 04-Jul-12 07-Jul-12 100 15-May-12 16-May-12 20-Sep-12 22-Sep-12 100% 0%
SlabSlab 2 04-Jul-12 07-Jul-12 100 15-May-12 16-May-12 20-Sep-12 22-Sep-12 100% 0%A1210 Pouring of Light Weight Concrete 2 04-Jul-12 07-Jul-12 100 15-May-12 16-May-12 20-Sep-12 22-Sep-12 107 100% 0%
Ground FGround Floor Slab 2 04-Jul-12 07-Jul-12 103 07-Jun-12 09-Jun-12 24-Sep-12 25-Sep-12 100% 0%
SlabSlab 2 04-Jul-12 07-Jul-12 103 07-Jun-12 09-Jun-12 24-Sep-12 25-Sep-12 100% 0%A1310 Pouring of Light Weight Concrete 2 04-Jul-12 07-Jul-12 103 07-Jun-12 09-Jun-12 24-Sep-12 25-Sep-12 90 100% 0%
2nd Floo2nd Floor Slab 3 21-Jun-12 A 04-Jul-12 55 26-Jul-12 29-Jul-12 06-Sep-12 09-Sep-12 0% 95%
SlabSlab 3 21-Jun-12 A 04-Jul-12 55 26-Jul-12 29-Jul-12 06-Sep-12 09-Sep-12 0% 95%A1610 Strike Formwork 3 21-Jun-12 A 04-Jul-12 55 26-Jul-12 29-Jul-12 06-Sep-12 09-Sep-12 34 0% 95%
3rd Floor3rd Floor Slab 3 21-Jul-12 23-Jul-12 32 21-Aug-12 23-Aug-12 29-Aug-12 01-Sep-12 0% 0%
SlabSlab 3 21-Jul-12 23-Jul-12 32 21-Aug-12 23-Aug-12 29-Aug-12 01-Sep-12 0% 0%A1700 Strike Formwork 3 21-Jul-12 23-Jul-12 32 21-Aug-12 23-Aug-12 29-Aug-12 01-Sep-12 7 0% 0%
4th Floor4th Floor Slab 36 25-Jun-12 A 06-Aug-12 37 26-Jul-12 11-Sep-12 26-Jul-12 20-Sep-12 0% 89.87%
SlabSlab 36 25-Jun-12 A 06-Aug-12 37 26-Jul-12 11-Sep-12 26-Jul-12 20-Sep-12 0% 89.87%A1750 MEP Works inside Slab 4 25-Jun-12 A 04-Jul-12 30 30-Jul-12 02-Aug-12 05-Aug-12 08-Aug-12 5 0% 90%
A1760 4th Slab RC Works 12 25-Jun-12 A 05-Jul-12 29 26-Jul-12 08-Aug-12 26-Jul-12 08-Aug-12 0 0% 90%
A1770 Curing for Slab 3 05-Jul-12 09-Jul-12 58 09-Aug-12 12-Aug-12 15-Sep-12 17-Sep-12 29 0% 0%
A1780 Strike Formwork 3 02-Aug-12 06-Aug-12 37 09-Sep-12 11-Sep-12 18-Sep-12 20-Sep-12 8 0% 0%
5th Floor5th Floor Slab 23 05-Jul-12 01-Aug-12 44 09-Aug-12 01-Sep-12 09-Aug-12 24-Sep-12 0% 0%
Walls aWalls and Columns 9 05-Jul-12 16-Jul-12 29 09-Aug-12 21-Aug-12 09-Aug-12 21-Aug-12 0% 0%A1810 Core Wall RC Works 6 09-Jul-12 16-Jul-12 27 09-Aug-12 15-Aug-12 09-Aug-12 15-Aug-12 0 0% 0%
A1820 Columns RC Works 9 05-Jul-12 16-Jul-12 29 09-Aug-12 21-Aug-12 09-Aug-12 21-Aug-12 0 0% 0%SlabSlab 16 14-Jul-12 01-Aug-12 44 13-Aug-12 01-Sep-12 13-Aug-12 24-Sep-12 0% 0%A1830 MEP Works inside Slab 5 14-Jul-12 19-Jul-12 32 18-Aug-12 25-Aug-12 23-Aug-12 28-Aug-12 3 0% 0%
A1840 5th Slab RC Works 12 15-Jul-12 29-Jul-12 24 13-Aug-12 28-Aug-12 13-Aug-12 28-Aug-12 0 0% 0%
A1850 Curing for Slab 3 29-Jul-12 01-Aug-12 44 29-Aug-12 01-Sep-12 22-Sep-12 24-Sep-12 20 0% 0%
6th Floor6th Floor Slab 19 29-Jul-12 22-Aug-12 43 29-Aug-12 19-Sep-12 29-Aug-12 11-Oct-12 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Order&Delivery- Fire and Volume Damper
Order&Delivery- HAVC Ducts
Order&Delivery- FCUs
Order&Delivery- Air Oulets
Order&Delivery- Ventilation & Exhuast Fans
Order&Delivery- Variable Frequency Drive
Order&Delivery- FAHU
Order&Delivery- AHU
Order&Delivery- Chiller
Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge)
Order&Delivery- Electrical Heaters
Order&Delivery- Floor Drains
Order&Delivery-PPR Pipes -Fittings-Valves (Water)
Order&Delivery- Sump Pump
Order&Delivery- Water Boiler Pump
Order&Delivery- Transfer Pump
Order&Delivery- Water Boiler
Order&Delivery- Water Boiler Tank
Order&Delivery- Steam Pipes for Boilers
Order&Delivery- GRP Water Tank
Order&Delivery- Foam Spary System for Generators
Order&Delivery- Fire Pipes-Fittings-Valves
Order&Delivery- Sprinklers
Order&Delivery- Fire Extinguishers & Banket
Order&Delivery- Fire Hose Cabinets
Order&Delivery- FM 200 System
Order&Delivery- Landing Valves
Order&Delivery- Fire Alarm Devices
Order&Delivery- Fire Fighting Pump
Order&Delivery- LPG Tanks( 2000 Gallons)
Order&Delivery- LPG Pipes-Fittings-Valves
Order&Delivery- Brakets,Guide Rails and Others
Order&Delivery- Cable Trays
Order&Delivery- Trunking
Order&Delivery- MATV/ Interactive TV System
Order&Delivery- BMS
Order&Delivery- GSM System
Order&Delivery- CCTV System
Order&Delivery- Generators
Order&Delivery- Earthing & Lightining
Order&Delivery- Conduits & PVC Ducts
Order&Delivery- Light Fixtures
Order&Delivery- Finishes Items
Order&Delivery- Water Proofing for Swimming Pool
Order&Delivery- Electrical Items
Order&Delivery- Sand Stone Pavers
Order&Delivery- Pocal in for Pool Deck
Order&Delivery- Swimming Pool Equipments
Order&Delivery- Curtain Wall&Glazing
Order&Delivery- Facade Cleaning System
Order&Delivery- Pipes & Fittings
Order&Delivery- Equipments
Order&Delivery- Garbage Chutes
Order&Delivery- Linen Chutes
Order&Delivery- Kitchen Equipments
Order&Delivery- Laundary Equipments
Pouring of Light Weight Concrete
Pouring of Light Weight Concrete
k Strike Formwork
Strike Formwork
ab MEP Works inside Slab
ks 4th Slab RC Works
Curing for Slab
Strike Formwork
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
5th Slab RC Works
Curing for Slab
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 12 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
Walls aWalls and Columns 9 29-Jul-12 08-Aug-12 24 29-Aug-12 08-Sep-12 29-Aug-12 08-Sep-12 0% 0%A1890 Core Wall RC Works 6 29-Jul-12 05-Aug-12 24 29-Aug-12 04-Sep-12 29-Aug-12 04-Sep-12 0 0% 0%
A1900 Columns RC Works 9 29-Jul-12 08-Aug-12 24 29-Aug-12 08-Sep-12 29-Aug-12 08-Sep-12 0 0% 0%SlabSlab 15 02-Aug-12 22-Aug-12 43 03-Sep-12 19-Sep-12 03-Sep-12 11-Oct-12 0% 0%A1910 MEP Works inside Slab 5 06-Aug-12 12-Aug-12 28 06-Sep-12 11-Sep-12 11-Sep-12 16-Sep-12 4 0% 0%
A1920 6th Slab RC Works (L + 9.20) 12 02-Aug-12 16-Aug-12 24 03-Sep-12 16-Sep-12 03-Sep-12 16-Sep-12 0 0% 0%
A1930 Curing for Slab 3 16-Aug-12 22-Aug-12 43 17-Sep-12 19-Sep-12 09-Oct-12 11-Oct-12 19 0% 0%
7th Floor7th Floor Slab 14 16-Aug-12 04-Sep-12 24 17-Sep-12 02-Oct-12 17-Sep-12 02-Oct-12 0% 0%
Walls aWalls and Columns 9 16-Aug-12 29-Aug-12 24 17-Sep-12 26-Sep-12 17-Sep-12 26-Sep-12 0% 0%A1970 Core Wall RC Works 6 16-Aug-12 26-Aug-12 24 17-Sep-12 23-Sep-12 17-Sep-12 23-Sep-12 0 0% 0%
A1980 Columns RC Works 9 16-Aug-12 29-Aug-12 24 17-Sep-12 26-Sep-12 17-Sep-12 26-Sep-12 0 0% 0%SlabSlab 10 23-Aug-12 04-Sep-12 24 22-Sep-12 02-Oct-12 22-Sep-12 02-Oct-12 0% 0%A2000 7th Slab RC Works 10 23-Aug-12 04-Sep-12 24 22-Sep-12 02-Oct-12 22-Sep-12 02-Oct-12 0 0% 0%
Hotel (BHotel (Block B) 58 26-Jun-12 A 03-Sep-12 79 14-Jul-12 18-Sep-12 06-Aug-12 07-Nov-12 0% 4.15%
1st Base1st Basement Floor Slab 2 01-Jul-12 02-Jul-12 127 14-Jul-12 15-Jul-12 30-Oct-12 31-Oct-12 0% 0%
SlabSlab 2 01-Jul-12 02-Jul-12 127 14-Jul-12 15-Jul-12 30-Oct-12 31-Oct-12 0% 0%A11630 Pouring of Light Weight Concrete 2 01-Jul-12 02-Jul-12 127 14-Jul-12 15-Jul-12 30-Oct-12 31-Oct-12 89 0% 0%
Ground FGround Floor Slab 5 01-Jul-12 05-Jul-12 128 06-Aug-12 11-Aug-12 08-Oct-12 05-Nov-12 0% 0%
SlabSlab 5 01-Jul-12 05-Jul-12 128 06-Aug-12 11-Aug-12 08-Oct-12 05-Nov-12 0% 0%A11700 Strike Formwork 3 01-Jul-12 03-Jul-12 83 06-Aug-12 08-Aug-12 08-Oct-12 10-Oct-12 52 0% 0%
A11710 Pouring of Light Weight Concrete 2 04-Jul-12 05-Jul-12 128 09-Aug-12 11-Aug-12 04-Nov-12 05-Nov-12 70 0% 0%
1st Floor1st Floor Slab 26 26-Jun-12 A 26-Jul-12 82 06-Aug-12 08-Sep-12 28-Oct-12 03-Nov-12 0% 0.62%
SlabSlab 26 26-Jun-12 A 26-Jul-12 82 06-Aug-12 08-Sep-12 28-Oct-12 03-Nov-12 0% 0.62%A11800 Curing for Slab 3 26-Jun-12 A 01-Jul-12 100 06-Aug-12 08-Aug-12 28-Oct-12 30-Oct-12 67 0% 80%
A11810 Strike Formwork 3 23-Jul-12 26-Jul-12 82 05-Sep-12 08-Sep-12 31-Oct-12 03-Nov-12 46 0% 0%
2nd Floo2nd Floor Slab 32 28-Jun-12 A 04-Aug-12 78 06-Aug-12 04-Sep-12 06-Aug-12 07-Nov-12 0% 6.51%
Walls aWalls and Columns 9 28-Jun-12 A 09-Jul-12 33 06-Aug-12 15-Aug-12 06-Aug-12 15-Aug-12 0% 27.71%A11840 Core Wall RC Works 6 28-Jun-12 A 04-Jul-12 33 06-Aug-12 12-Aug-12 06-Aug-12 12-Aug-12 0 0% 40%
A11850 Columns RC Works 9 28-Jun-12 A 09-Jul-12 33 06-Aug-12 15-Aug-12 06-Aug-12 15-Aug-12 0 0% 20%SlabSlab 23 09-Jul-12 04-Aug-12 78 13-Aug-12 04-Sep-12 13-Aug-12 07-Nov-12 0% 0%A11860 MEP Works inside Slab 5 09-Jul-12 15-Jul-12 40 16-Aug-12 23-Aug-12 27-Aug-12 01-Sep-12 7 0% 0%
A11870 2nd Floor Slab RC Works 15 15-Jul-12 31-Jul-12 25 13-Aug-12 01-Sep-12 13-Aug-12 01-Sep-12 0 0% 0%
A11880 Curing for Slab 3 01-Aug-12 04-Aug-12 78 02-Sep-12 04-Sep-12 05-Nov-12 07-Nov-12 53 0% 0%
3rd Floor3rd Floor Slab 27 01-Aug-12 03-Sep-12 13 02-Sep-12 18-Sep-12 02-Sep-12 18-Sep-12 0% 0%
Walls aWalls and Columns 15 01-Aug-12 18-Aug-12 16 02-Sep-12 08-Sep-12 02-Sep-12 08-Sep-12 0% 0%A11910 Columns RC Works 6 01-Aug-12 07-Aug-12 25 02-Sep-12 08-Sep-12 02-Sep-12 08-Sep-12 0 0% 0%
A11900 Core Wall RC Works 3 15-Aug-12 18-Aug-12 13 02-Sep-12 04-Sep-12 02-Sep-12 04-Sep-12 0 0% 0%SlabSlab 21 08-Aug-12 03-Sep-12 13 05-Sep-12 18-Sep-12 05-Sep-12 18-Sep-12 0% 0%A11920 MEP Works inside Slab 4 08-Aug-12 12-Aug-12 30 09-Sep-12 12-Sep-12 15-Sep-12 18-Sep-12 5 0% 0%
A11930 3rd Floor Slab RC Works 12 21-Aug-12 03-Sep-12 13 05-Sep-12 18-Sep-12 05-Sep-12 18-Sep-12 0 0% 0%
ResidenResidential Apartments (Block C) 67 14-Jun-12 A 30-Aug-12 151 14-Jul-12 10-Sep-12 19-Jul-12 10-Feb-13 0% 3.7%
1st Base1st Basement Floor Slab 2 01-Jul-12 02-Jul-12 114 14-Jul-12 15-Jul-12 24-Oct-12 28-Oct-12 0% 0%
SlabSlab 2 01-Jul-12 02-Jul-12 114 14-Jul-12 15-Jul-12 24-Oct-12 28-Oct-12 0% 0%A10300 Pouring of Light Weight Concrete 2 01-Jul-12 02-Jul-12 114 14-Jul-12 15-Jul-12 24-Oct-12 28-Oct-12 86 0% 0%
Ground FGround Floor Slab 13 20-Jun-12 A 04-Jul-12 198 01-Aug-12 06-Aug-12 30-Oct-12 10-Feb-13 0% 39.79%
SlabSlab 13 20-Jun-12 A 04-Jul-12 198 01-Aug-12 06-Aug-12 30-Oct-12 10-Feb-13 0% 39.79%A10380 Strike Formwork 3 20-Jun-12 A 02-Jul-12 112 01-Aug-12 04-Aug-12 30-Oct-12 01-Nov-12 73 0% 40%
A10400 Pouring of Light Weight Concrete 2 02-Jul-12 04-Jul-12 198 05-Aug-12 06-Aug-12 09-Feb-13 10-Feb-13 153 0% 0%
1st Floor1st Floor Slab 42 14-Jun-12 A 30-Jul-12 78 19-Jul-12 18-Aug-12 28-Oct-12 03-Nov-12 0% 25%
SlabSlab 42 14-Jun-12 A 30-Jul-12 78 19-Jul-12 18-Aug-12 28-Oct-12 03-Nov-12 0% 25%A10500 Curing for Slab 3 14-Jun-12 A 02-Jul-12 100 19-Jul-12 22-Jul-12 28-Oct-12 30-Oct-12 82 0% 50%
A10510 Strike Formwork 3 28-Jul-12 30-Jul-12 78 15-Aug-12 18-Aug-12 31-Oct-12 03-Nov-12 62 0% 0%
2nd Floo2nd Floor Slab 45 24-Jun-12 A 15-Aug-12 23 19-Jul-12 08-Sep-12 19-Jul-12 12-Sep-12 0% 8.15%
Walls aWalls and Columns 9 24-Jun-12 A 08-Jul-12 19 19-Jul-12 29-Jul-12 19-Jul-12 29-Jul-12 0% 30%A10570 Core Wall RC Works 6 24-Jun-12 A 07-Jul-12 19 21-Jul-12 26-Jul-12 21-Jul-12 26-Jul-12 0 0% 30%
A10580 Columns RC Works 9 24-Jun-12 A 08-Jul-12 19 19-Jul-12 29-Jul-12 19-Jul-12 29-Jul-12 0 0% 30%SlabSlab 38 02-Jul-12 15-Aug-12 23 24-Jul-12 08-Sep-12 24-Jul-12 12-Sep-12 0% 0%A10590 MEP Works inside Slab 5 08-Jul-12 14-Jul-12 19 30-Jul-12 04-Aug-12 30-Jul-12 04-Aug-12 0 0% 0%
A10600 2nd Floor Slab RC Works 10 02-Jul-12 14-Jul-12 19 24-Jul-12 04-Aug-12 24-Jul-12 04-Aug-12 0 0% 0%
A10610 Curing for Slab 3 14-Jul-12 17-Jul-12 44 05-Aug-12 07-Aug-12 05-Sep-12 08-Sep-12 25 0% 0%
A10620 Strike Formwork 4 11-Aug-12 15-Aug-12 23 04-Sep-12 08-Sep-12 09-Sep-12 12-Sep-12 4 0% 0%
3rd Floor3rd Floor Slab 29 14-Jul-12 15-Aug-12 28 05-Aug-12 28-Aug-12 05-Aug-12 19-Sep-12 0% 0%
Walls aWalls and Columns 16 14-Jul-12 31-Jul-12 14 05-Aug-12 14-Aug-12 05-Aug-12 16-Aug-12 0% 0%A10660 Columns RC Works 9 14-Jul-12 24-Jul-12 21 05-Aug-12 14-Aug-12 07-Aug-12 16-Aug-12 2 0% 0%
A10650 Core Wall RC Works 6 25-Jul-12 31-Jul-12 9 05-Aug-12 11-Aug-12 05-Aug-12 11-Aug-12 0 0% 0%SlabSlab 23 21-Jul-12 15-Aug-12 28 12-Aug-12 28-Aug-12 12-Aug-12 19-Sep-12 0% 0%A10670 MEP Works inside Slab 5 21-Jul-12 26-Jul-12 24 12-Aug-12 16-Aug-12 18-Aug-12 25-Aug-12 5 0% 0%
A10680 3rd Floor Slab RC Works 10 01-Aug-12 12-Aug-12 9 12-Aug-12 25-Aug-12 12-Aug-12 25-Aug-12 0 0% 0%
A10690 Curing for Slab 3 13-Aug-12 15-Aug-12 28 26-Aug-12 28-Aug-12 17-Sep-12 19-Sep-12 19 0% 0%
4th Floor4th Floor Slab 14 13-Aug-12 30-Aug-12 9 26-Aug-12 10-Sep-12 26-Aug-12 10-Sep-12 0% 0%
Walls aWalls and Columns 9 13-Aug-12 25-Aug-12 9 26-Aug-12 04-Sep-12 26-Aug-12 04-Sep-12 0% 0%A10730 Core Wall RC Works 6 14-Aug-12 22-Aug-12 9 27-Aug-12 02-Sep-12 27-Aug-12 02-Sep-12 0 0% 0%
A10740 Columns RC Works 9 13-Aug-12 25-Aug-12 9 26-Aug-12 04-Sep-12 26-Aug-12 04-Sep-12 0 0% 0%SlabSlab 9 21-Aug-12 30-Aug-12 9 01-Sep-12 10-Sep-12 01-Sep-12 10-Sep-12 0% 0%A10750 MEP Works inside Slab 5 25-Aug-12 29-Aug-12 10 04-Sep-12 09-Sep-12 05-Sep-12 10-Sep-12 1 0% 0%
A10760 4th Slab RC Works 9 21-Aug-12 30-Aug-12 9 01-Sep-12 10-Sep-12 01-Sep-12 10-Sep-12 0 0% 0%
ArchitecArchitectural & MEP Package 76 20-Jun-12 A 19-Sep-12 200 14-Jun-12 04-Nov-12 14-Aug-12 16-May-13 1.5% 1.88%
Hotel ApHotel Apartements (Block A) 64 20-Jun-12 A 04-Sep-12 98 14-Jun-12 08-Oct-12 14-Aug-12 02-Jan-13 3.42% 4.28%
2nd Base2nd Basement Floor 28 31-Jul-12 04-Sep-12 81 21-Jul-12 12-Aug-12 05-Nov-12 06-Dec-12 0% 0%
Public APublic Area 28 31-Jul-12 04-Sep-12 81 21-Jul-12 12-Aug-12 05-Nov-12 06-Dec-12 0% 0%ParkinParking Area 15 16-Aug-12 04-Sep-12 76 01-Aug-12 12-Aug-12 21-Nov-12 06-Dec-12 0% 0%MEP WMEP Works 15 16-Aug-12 04-Sep-12 76 01-Aug-12 12-Aug-12 21-Nov-12 06-Dec-12 0% 0%HVACHVAC 7 16-Aug-12 26-Aug-12 78 01-Aug-12 08-Aug-12 21-Nov-12 28-Nov-12 0% 0%A479 Chilled Water Pipe Installation & Insulation 7 16-Aug-12 26-Aug-12 78 01-Aug-12 08-Aug-12 21-Nov-12 28-Nov-12 91 0% 0%
ElectElectrical 10 25-Aug-12 04-Sep-12 76 01-Aug-12 12-Aug-12 25-Nov-12 06-Dec-12 0% 0%A480 Installation of Cable Trays 10 25-Aug-12 04-Sep-12 76 01-Aug-12 12-Aug-12 25-Nov-12 06-Dec-12 94 0% 0%
Lift LoLift Lobby 3 31-Jul-12 04-Aug-12 97 24-Jul-12 26-Jul-12 14-Nov-12 18-Nov-12 0% 0%MEP WMEP Works 3 31-Jul-12 04-Aug-12 97 24-Jul-12 26-Jul-12 14-Nov-12 18-Nov-12 0% 0%ElectElectrical 3 31-Jul-12 04-Aug-12 97 24-Jul-12 26-Jul-12 14-Nov-12 18-Nov-12 0% 0%A482 Install Conduits in Wall 3 31-Jul-12 04-Aug-12 97 24-Jul-12 26-Jul-12 14-Nov-12 18-Nov-12 93 0% 0%
GSM RGSM Rooms 5 04-Aug-12 09-Aug-12 97 30-Jul-12 04-Aug-12 19-Nov-12 24-Nov-12 0% 0%MEP WMEP Works 5 04-Aug-12 09-Aug-12 97 30-Jul-12 04-Aug-12 19-Nov-12 24-Nov-12 0% 0%ElectElectrical 5 04-Aug-12 09-Aug-12 97 30-Jul-12 04-Aug-12 19-Nov-12 24-Nov-12 0% 0%A474 Install Conduits in Wall 5 04-Aug-12 09-Aug-12 97 30-Jul-12 04-Aug-12 19-Nov-12 24-Nov-12 91 0% 0%
MechaMechanical Rooms 4 09-Aug-12 14-Aug-12 97 05-Aug-12 08-Aug-12 29-Nov-12 04-Dec-12 0% 0%MEP WMEP Works 4 09-Aug-12 14-Aug-12 97 05-Aug-12 08-Aug-12 29-Nov-12 04-Dec-12 0% 0%ElectElectrical 4 09-Aug-12 14-Aug-12 97 05-Aug-12 08-Aug-12 29-Nov-12 04-Dec-12 0% 0%A472 Install Conduits in Wall 4 09-Aug-12 14-Aug-12 97 05-Aug-12 08-Aug-12 29-Nov-12 04-Dec-12 95 0% 0%
StaircaStaircase 3 05-Aug-12 07-Aug-12 75 21-Jul-12 23-Jul-12 05-Nov-12 07-Nov-12 0% 0%Stair 1Stair 1 3 05-Aug-12 07-Aug-12 75 21-Jul-12 23-Jul-12 05-Nov-12 07-Nov-12 0% 0%A1079 Floor Screed 3 05-Aug-12 07-Aug-12 75 21-Jul-12 23-Jul-12 05-Nov-12 07-Nov-12 88 0% 0%
1st Base1st Basement Floor 59 20-Jun-12 A 29-Aug-12 67 14-Jun-12 02-Aug-12 14-Aug-12 18-Nov-12 29.15% 35.11%
Public APublic Area 59 20-Jun-12 A 29-Aug-12 67 14-Jun-12 02-Aug-12 14-Aug-12 18-Nov-12 29.15% 35.11%GenseGenset Room 52 20-Jun-12 A 21-Aug-12 21 03-Jul-12 14-Jul-12 06-Sep-12 13-Sep-12 0% 38.57%FinishFinishing Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 0% 90%Wet Wet Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 0% 90%A495 Block Works 3 20-Jun-12 A 30-Jul-12 33 03-Jul-12 05-Jul-12 06-Sep-12 09-Sep-12 54 0% 90%
MEP WMEP Works 4 14-Aug-12 21-Aug-12 21 10-Jul-12 14-Jul-12 10-Sep-12 13-Sep-12 0% 0%ElectElectrical 4 14-Aug-12 21-Aug-12 21 10-Jul-12 14-Jul-12 10-Sep-12 13-Sep-12 0% 0%A495 Install Conduits in Wall 4 14-Aug-12 21-Aug-12 21 10-Jul-12 14-Jul-12 10-Sep-12 13-Sep-12 51 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
6th Slab RC Works (L + 9.20)
Curing for Slab
Core Wall RC Works
Columns RC Works
7th Slab RC Works
Pouring of Light Weight Concrete
Strike Formwork
Pouring of Light Weight Concrete
ab Curing for Slab
Strike Formwork
ks Core Wall RC Works
ks Columns RC Works
MEP Works inside Slab
2nd Floor Slab RC Works
Curing for Slab
Columns RC Works
Core Wall RC Works
MEP Works inside Slab
3rd Floor Slab RC Works
Pouring of Light Weight Concrete
k Strike Formwork
Pouring of Light Weight Concrete
Curing for Slab
Strike Formwork
ks Core Wall RC Works
ks Columns RC Works
MEP Works inside Slab
2nd Floor Slab RC Works
Curing for Slab
Strike Formwork
Columns RC Works
Core Wall RC Works
MEP Works inside Slab
3rd Floor Slab RC Works
Curing for Slab
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
4th Slab RC Works
Chilled Water Pipe Installation & Insulation
Installation of Cable Trays
Install Conduits in Wall
Install Conduits in Wall
Install Conduits in Wall
Floor Screed
s Block Works
Install Conduits in Wall
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 13 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
BMS RBMS Room 54 20-Jun-12 A 23-Aug-12 21 07-Jul-12 16-Jul-12 11-Sep-12 16-Sep-12 0% 45%FinishFinishing Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 0% 90%Wet Wet Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 0% 90%A496 Block Works 2 20-Jun-12 A 30-Jul-12 37 07-Jul-12 08-Jul-12 11-Sep-12 12-Sep-12 55 0% 90%
MEP WMEP Works 2 21-Aug-12 23-Aug-12 21 15-Jul-12 16-Jul-12 15-Sep-12 16-Sep-12 0% 0%ElectElectrical 2 21-Aug-12 23-Aug-12 21 15-Jul-12 16-Jul-12 15-Sep-12 16-Sep-12 0% 0%A497 Install Conduits in Wall 2 21-Aug-12 23-Aug-12 21 15-Jul-12 16-Jul-12 15-Sep-12 16-Sep-12 51 0% 0%
CBS RCBS Room 59 20-Jun-12 A 29-Aug-12 21 09-Jul-12 22-Jul-12 13-Sep-12 22-Sep-12 0% 33.75%FinishFinishing Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 0% 90%Wet Wet Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 0% 90%A484 Block Works 3 20-Jun-12 A 31-Jul-12 39 09-Jul-12 11-Jul-12 13-Sep-12 16-Sep-12 55 0% 90%
MEP WMEP Works 5 23-Aug-12 29-Aug-12 21 17-Jul-12 22-Jul-12 17-Sep-12 22-Sep-12 0% 0%ElectElectrical 5 23-Aug-12 29-Aug-12 21 17-Jul-12 22-Jul-12 17-Sep-12 22-Sep-12 0% 0%A484 Install Conduits in Wall 5 23-Aug-12 29-Aug-12 21 17-Jul-12 22-Jul-12 17-Sep-12 22-Sep-12 51 0% 0%
ELV RoELV Room 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%FinishFinishing Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%Wet Wet Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 0% 90%A493 Block Works 4 20-Jun-12 A 31-Jul-12 43 12-Jul-12 16-Jul-12 18-Sep-12 22-Sep-12 56 0% 90%
MechaMechanical Rooms 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%FinishFinishing Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%Wet Wet Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 0% 90%A499 Block Works 2 20-Jun-12 A 31-Jul-12 48 17-Jul-12 18-Jul-12 26-Sep-12 27-Sep-12 59 0% 90%
LV RooLV Room (Block A) 58 20-Jun-12 A 28-Aug-12 31 28-Jun-12 18-Jul-12 30-Aug-12 02-Oct-12 17.65% 31.76%FinishFinishing Works 58 20-Jun-12 A 28-Aug-12 31 28-Jun-12 18-Jul-12 30-Aug-12 02-Oct-12 25% 45%Wet Wet Works 58 20-Jun-12 A 28-Aug-12 31 28-Jun-12 18-Jul-12 30-Aug-12 02-Oct-12 25% 45%A486 Block Works 4 20-Jun-12 A 30-Jul-12 29 28-Jun-12 02-Jul-12 30-Aug-12 03-Sep-12 52 50% 90%
A485 Plaster Works 6 21-Aug-12 28-Aug-12 31 12-Jul-12 18-Jul-12 26-Sep-12 02-Oct-12 63 0% 0%MEP WMEP Works 5 08-Aug-12 14-Aug-12 21 04-Jul-12 09-Jul-12 04-Sep-12 09-Sep-12 0% 0%ElectElectrical 5 08-Aug-12 14-Aug-12 21 04-Jul-12 09-Jul-12 04-Sep-12 09-Sep-12 0% 0%A486 Install Conduits in Wall 5 08-Aug-12 14-Aug-12 21 04-Jul-12 09-Jul-12 04-Sep-12 09-Sep-12 51 0% 0%
Sub-StSub-Station 1 57 20-Jun-12 A 27-Aug-12 69 21-Jun-12 17-Jul-12 22-Aug-12 18-Nov-12 38.1% 25.71%FinishFinishing Works 52 20-Jun-12 A 21-Aug-12 31 21-Jun-12 11-Jul-12 22-Aug-12 25-Sep-12 54.55% 49.09%Wet Wet Works 52 20-Jun-12 A 21-Aug-12 31 21-Jun-12 11-Jul-12 22-Aug-12 25-Sep-12 54.55% 49.09%A488 Block Works 6 20-Jun-12 A 30-Jul-12 24 21-Jun-12 27-Jun-12 22-Aug-12 28-Aug-12 51 100% 90%
A487 Plaster Works 5 13-Aug-12 21-Aug-12 31 07-Jul-12 11-Jul-12 20-Sep-12 25-Sep-12 63 0% 0%MEP WMEP Works 19 02-Aug-12 27-Aug-12 69 28-Jun-12 17-Jul-12 29-Aug-12 18-Nov-12 20% 0%ElectElectrical 19 02-Aug-12 27-Aug-12 69 28-Jun-12 17-Jul-12 29-Aug-12 18-Nov-12 20% 0%LighLight & Power 19 02-Aug-12 27-Aug-12 69 28-Jun-12 17-Jul-12 29-Aug-12 18-Nov-12 20% 0%A48 Install Conduits in Wall 5 02-Aug-12 08-Aug-12 21 28-Jun-12 03-Jul-12 29-Aug-12 03-Sep-12 51 40% 0%
A48 Wiring for Lighting & Power 5 21-Aug-12 27-Aug-12 69 12-Jul-12 17-Jul-12 12-Nov-12 18-Nov-12 101 0% 0%House House keeping Room 51 20-Jun-12 A 18-Aug-12 70 14-Jun-12 10-Jul-12 14-Aug-12 11-Nov-12 72.92% 28.13%FinishFinishing Works 47 20-Jun-12 A 13-Aug-12 31 14-Jun-12 05-Jul-12 14-Aug-12 19-Sep-12 79.17% 56.25%Wet Wet Works 47 20-Jun-12 A 13-Aug-12 31 14-Jun-12 05-Jul-12 14-Aug-12 19-Sep-12 79.17% 56.25%A490 Block Works 5 20-Jun-12 A 29-Jul-12 21 14-Jun-12 20-Jun-12 14-Aug-12 21-Aug-12 51 100% 90%
A489 Plaster Works 9 02-Aug-12 13-Aug-12 31 26-Jun-12 05-Jul-12 10-Sep-12 19-Sep-12 63 44.44% 0%MEP WMEP Works 17 29-Jul-12 18-Aug-12 70 21-Jun-12 10-Jul-12 25-Aug-12 11-Nov-12 66.67% 0%ElectElectrical 17 29-Jul-12 18-Aug-12 70 21-Jun-12 10-Jul-12 25-Aug-12 11-Nov-12 66.67% 0%A490 Install Conduits in Wall 4 29-Jul-12 02-Aug-12 21 21-Jun-12 25-Jun-12 25-Aug-12 28-Aug-12 53 100% 0%
A490 Wiring for Lighting & Power 4 13-Aug-12 18-Aug-12 70 07-Jul-12 10-Jul-12 07-Nov-12 11-Nov-12 102 0% 0%StaircaStaircase 3 08-Aug-12 11-Aug-12 75 31-Jul-12 02-Aug-12 08-Nov-12 11-Nov-12 0% 0%Stair 1Stair 1 3 08-Aug-12 11-Aug-12 75 31-Jul-12 02-Aug-12 08-Nov-12 11-Nov-12 0% 0%A1079 Floor Screed 3 08-Aug-12 11-Aug-12 75 31-Jul-12 02-Aug-12 08-Nov-12 11-Nov-12 82 0% 0%
1st Floor1st Floor 56 24-Jun-12 A 29-Aug-12 66 30-Jul-12 30-Aug-12 10-Sep-12 18-Nov-12 0% 0.42%
Public APublic Area 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%CorridCorridor & Lift Lobby 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%FinishFinishing Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%Wet Wet Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%A981 Block Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 40 0% 10%
ApartemApartements 26 29-Jul-12 29-Aug-12 66 30-Jul-12 30-Aug-12 10-Sep-12 18-Nov-12 0% 0%StudioStudio Flats 7 21-Aug-12 28-Aug-12 67 22-Aug-12 29-Aug-12 08-Oct-12 18-Nov-12 0% 0%ApartApartement .1 - 2 - 3 (Studio) 7 21-Aug-12 28-Aug-12 67 22-Aug-12 29-Aug-12 08-Oct-12 18-Nov-12 0% 0%FinisFinishing Works 3 21-Aug-12 23-Aug-12 42 22-Aug-12 25-Aug-12 08-Oct-12 10-Oct-12 0% 0%WetWet Works 3 21-Aug-12 23-Aug-12 42 22-Aug-12 25-Aug-12 08-Oct-12 10-Oct-12 0% 0%A60 Block Works 3 21-Aug-12 23-Aug-12 42 22-Aug-12 25-Aug-12 08-Oct-12 10-Oct-12 40 0% 0%
MEPMEP Works 7 21-Aug-12 28-Aug-12 67 22-Aug-12 29-Aug-12 13-Nov-12 18-Nov-12 0% 0%ElecElectrical 3 25-Aug-12 27-Aug-12 67 26-Aug-12 28-Aug-12 13-Nov-12 17-Nov-12 0% 0%A61 Install Conduits in Wall 3 25-Aug-12 27-Aug-12 67 26-Aug-12 28-Aug-12 13-Nov-12 17-Nov-12 66 0% 0%
PlumPlumbing 4 25-Aug-12 28-Aug-12 67 26-Aug-12 29-Aug-12 13-Nov-12 18-Nov-12 0% 0%A62 Drainge Pipes in Wall 4 25-Aug-12 28-Aug-12 67 26-Aug-12 29-Aug-12 13-Nov-12 18-Nov-12 66 0% 0%
A63 Water Pipes in Wall 4 25-Aug-12 28-Aug-12 67 26-Aug-12 29-Aug-12 13-Nov-12 18-Nov-12 66 0% 0%ShaShafts 3 21-Aug-12 23-Aug-12 70 22-Aug-12 25-Aug-12 13-Nov-12 17-Nov-12 0% 0%A12 MEP Works inside Shafts 3 21-Aug-12 23-Aug-12 70 22-Aug-12 25-Aug-12 13-Nov-12 17-Nov-12 69 0% 0%
One BeOne Bedroom Flats 14 12-Aug-12 29-Aug-12 64 13-Aug-12 30-Aug-12 01-Oct-12 14-Nov-12 0% 0%ApartApartement .1 - 2 - 3 - 4 (1 BR) 14 12-Aug-12 29-Aug-12 64 13-Aug-12 30-Aug-12 01-Oct-12 14-Nov-12 0% 0%FinisFinishing Works 6 12-Aug-12 18-Aug-12 42 13-Aug-12 21-Aug-12 01-Oct-12 07-Oct-12 0% 0%WetWet Works 6 12-Aug-12 18-Aug-12 42 13-Aug-12 21-Aug-12 01-Oct-12 07-Oct-12 0% 0%A22 Block Works 6 12-Aug-12 18-Aug-12 42 13-Aug-12 21-Aug-12 01-Oct-12 07-Oct-12 40 0% 0%
MEPMEP Works 14 12-Aug-12 29-Aug-12 64 13-Aug-12 30-Aug-12 23-Oct-12 14-Nov-12 0% 0%HVAHVAC 7 22-Aug-12 29-Aug-12 64 23-Aug-12 30-Aug-12 07-Nov-12 14-Nov-12 0% 0%A22 Chilled Water Pipe Installation & Insulation 7 22-Aug-12 29-Aug-12 64 23-Aug-12 30-Aug-12 07-Nov-12 14-Nov-12 63 0% 0%
ElecElectrical 3 21-Aug-12 23-Aug-12 61 22-Aug-12 25-Aug-12 03-Nov-12 05-Nov-12 0% 0%A22 Install Conduits in Wall 3 21-Aug-12 23-Aug-12 61 22-Aug-12 25-Aug-12 03-Nov-12 05-Nov-12 60 0% 0%
PlumPlumbing 8 21-Aug-12 29-Aug-12 56 22-Aug-12 30-Aug-12 28-Oct-12 05-Nov-12 0% 0%A22 Drainge Pipes in Wall 8 21-Aug-12 29-Aug-12 56 22-Aug-12 30-Aug-12 28-Oct-12 05-Nov-12 55 0% 0%
A22 Water Pipes in Wall 8 21-Aug-12 29-Aug-12 56 22-Aug-12 30-Aug-12 28-Oct-12 05-Nov-12 55 0% 0%ShaShafts 10 12-Aug-12 25-Aug-12 60 13-Aug-12 26-Aug-12 23-Oct-12 05-Nov-12 0% 0%A13 MEP Works inside Shafts 10 12-Aug-12 25-Aug-12 60 13-Aug-12 26-Aug-12 23-Oct-12 05-Nov-12 59 0% 0%
Two BTwo Bedroom Flats 25 29-Jul-12 28-Aug-12 50 30-Jul-12 26-Aug-12 10-Sep-12 28-Oct-12 0% 0%ApartApartement .1 - 2 - 3 - 4 - 5 (2 BR) 25 29-Jul-12 28-Aug-12 50 30-Jul-12 26-Aug-12 10-Sep-12 28-Oct-12 0% 0%FinisFinishing Works 12 29-Jul-12 11-Aug-12 35 30-Jul-12 12-Aug-12 10-Sep-12 23-Sep-12 0% 0%WetWet Works 12 29-Jul-12 11-Aug-12 35 30-Jul-12 12-Aug-12 10-Sep-12 23-Sep-12 0% 0%A24 Block Works 12 29-Jul-12 11-Aug-12 35 30-Jul-12 12-Aug-12 10-Sep-12 23-Sep-12 34 0% 0%
MEPMEP Works 25 29-Jul-12 28-Aug-12 50 30-Jul-12 26-Aug-12 24-Sep-12 28-Oct-12 0% 0%HVAHVAC 7 12-Aug-12 21-Aug-12 56 13-Aug-12 22-Aug-12 18-Oct-12 28-Oct-12 0% 0%A24 Chilled Water Pipe Installation & Insulation 7 12-Aug-12 21-Aug-12 56 13-Aug-12 22-Aug-12 18-Oct-12 28-Oct-12 55 0% 0%
ElecElectrical 13 12-Aug-12 28-Aug-12 47 13-Aug-12 16-Aug-12 02-Oct-12 22-Oct-12 0% 0%A24 Install Conduits in Wall 3 12-Aug-12 14-Aug-12 42 13-Aug-12 15-Aug-12 02-Oct-12 04-Oct-12 41 0% 0%
A24 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 47 13-Aug-12 16-Aug-12 18-Oct-12 22-Oct-12 55 0% 0%PlumPlumbing 13 12-Aug-12 28-Aug-12 33 13-Aug-12 26-Aug-12 24-Sep-12 04-Oct-12 0% 0%A24 Drainge Pipes in Wall 10 12-Aug-12 25-Aug-12 35 13-Aug-12 26-Aug-12 24-Sep-12 04-Oct-12 34 0% 0%
A24 Water Pipes in Wall 8 16-Aug-12 28-Aug-12 33 13-Aug-12 23-Aug-12 26-Sep-12 04-Oct-12 36 0% 0%ShaShafts 10 29-Jul-12 08-Aug-12 47 30-Jul-12 09-Aug-12 24-Sep-12 04-Oct-12 0% 0%A13 MEP Works inside Shafts 10 29-Jul-12 08-Aug-12 47 30-Jul-12 09-Aug-12 24-Sep-12 04-Oct-12 46 0% 0%
2nd Floor2nd Floor 29 29-Jul-12 02-Sep-12 100 01-Sep-12 03-Oct-12 02-Sep-12 02-Jan-13 0% 0%
ApartemApartements 29 29-Jul-12 02-Sep-12 100 01-Sep-12 03-Oct-12 02-Sep-12 02-Jan-13 0% 0%StudioStudio Flats 3 25-Aug-12 27-Aug-12 69 25-Sep-12 27-Sep-12 11-Nov-12 19-Nov-12 0% 0%ApartApartement .1 - 2 - 3 (Studio) 3 25-Aug-12 27-Aug-12 69 25-Sep-12 27-Sep-12 11-Nov-12 19-Nov-12 0% 0%FinisFinishing Works 3 25-Aug-12 27-Aug-12 65 25-Sep-12 27-Sep-12 11-Nov-12 13-Nov-12 0% 0%WetWet Works 3 25-Aug-12 27-Aug-12 65 25-Sep-12 27-Sep-12 11-Nov-12 13-Nov-12 0% 0%A34 Block Works 3 25-Aug-12 27-Aug-12 65 25-Sep-12 27-Sep-12 11-Nov-12 13-Nov-12 38 0% 0%
MEPMEP Works 3 25-Aug-12 27-Aug-12 69 25-Sep-12 27-Sep-12 17-Nov-12 19-Nov-12 0% 0%ShaShafts 3 25-Aug-12 27-Aug-12 69 25-Sep-12 27-Sep-12 17-Nov-12 19-Nov-12 0% 0%A13 MEP Works inside Shafts 3 25-Aug-12 27-Aug-12 69 25-Sep-12 27-Sep-12 17-Nov-12 19-Nov-12 42 0% 0%
One BeOne Bedroom Flats 14 15-Aug-12 02-Sep-12 100 18-Sep-12 03-Oct-12 28-Oct-12 02-Jan-13 0% 0%ApartApartement .1 - 2 - 3 (1 BR) 14 15-Aug-12 02-Sep-12 100 18-Sep-12 03-Oct-12 28-Oct-12 02-Jan-13 0% 0%FinisFinishing Works 6 15-Aug-12 23-Aug-12 59 18-Sep-12 24-Sep-12 28-Oct-12 03-Nov-12 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
s Block Works
Install Conduits in Wall
s Block Works
Install Conduits in Wall
s Block Works
s Block Works
s Block Works
Plaster Works
Install Conduits in Wall
s Block Works
Plaster Works
Install Conduits in Wall
Wiring for Lighting & Power
Block Works
Plaster Works
Install Conduits in Wall
Wiring for Lighting & Power
Floor Screed
ks Block Works
Block Works
Install Conduits in Wall
Drainge Pipes in Wall
Water Pipes in Wall
MEP Works inside Shafts
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Drainge Pipes in Wall
Water Pipes in Wall
MEP Works inside Shafts
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Install Cable Trays & Trunking
Drainge Pipes in Wall
Water Pipes in Wall
MEP Works inside Shafts
Block Works
MEP Works inside Shafts
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 14 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
WetWet Works 6 15-Aug-12 23-Aug-12 59 18-Sep-12 24-Sep-12 28-Oct-12 03-Nov-12 0% 0%A35 Block Works 6 15-Aug-12 23-Aug-12 59 18-Sep-12 24-Sep-12 28-Oct-12 03-Nov-12 32 0% 0%
MEPMEP Works 14 15-Aug-12 02-Sep-12 100 18-Sep-12 03-Oct-12 01-Nov-12 02-Jan-13 0% 0%ElecElectrical 4 25-Aug-12 28-Aug-12 68 25-Sep-12 29-Sep-12 10-Nov-12 19-Nov-12 0% 0%A35 Install Conduits in Wall 3 25-Aug-12 27-Aug-12 64 25-Sep-12 27-Sep-12 10-Nov-12 12-Nov-12 37 0% 0%
A35 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 68 25-Sep-12 29-Sep-12 14-Nov-12 19-Nov-12 41 0% 0%PlumPlumbing 8 25-Aug-12 02-Sep-12 100 25-Sep-12 03-Oct-12 04-Nov-12 02-Jan-13 0% 0%A35 H/L Hot&Cold Water Pipe Installation 4 25-Aug-12 28-Aug-12 104 25-Sep-12 29-Sep-12 29-Dec-12 02-Jan-13 77 0% 0%
A35 Drainge Pipes in Wall 8 25-Aug-12 02-Sep-12 59 25-Sep-12 03-Oct-12 04-Nov-12 12-Nov-12 32 0% 0%
A35 Water Pipes in Wall 8 25-Aug-12 02-Sep-12 59 25-Sep-12 03-Oct-12 04-Nov-12 12-Nov-12 32 0% 0%ShaShafts 10 15-Aug-12 28-Aug-12 63 18-Sep-12 29-Sep-12 01-Nov-12 12-Nov-12 0% 0%A13 MEP Works inside Shafts 10 15-Aug-12 28-Aug-12 63 18-Sep-12 29-Sep-12 01-Nov-12 12-Nov-12 36 0% 0%
Two BTwo Bedroom Flats 25 29-Jul-12 28-Aug-12 100 01-Sep-12 29-Sep-12 02-Sep-12 27-Dec-12 0% 0%ApartApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 25 29-Jul-12 28-Aug-12 100 01-Sep-12 29-Sep-12 02-Sep-12 27-Dec-12 0% 0%FinisFinishing Works 15 29-Jul-12 14-Aug-12 28 01-Sep-12 17-Sep-12 02-Sep-12 18-Sep-12 0% 0%WetWet Works 15 29-Jul-12 14-Aug-12 28 01-Sep-12 17-Sep-12 02-Sep-12 18-Sep-12 0% 0%A35 Block Works 15 29-Jul-12 14-Aug-12 28 01-Sep-12 17-Sep-12 02-Sep-12 18-Sep-12 1 0% 0%
MEPMEP Works 25 29-Jul-12 28-Aug-12 100 01-Sep-12 29-Sep-12 19-Sep-12 27-Dec-12 0% 0%HVAHVAC 7 15-Aug-12 25-Aug-12 52 18-Sep-12 25-Sep-12 17-Oct-12 24-Oct-12 0% 0%A35 Chilled Water Pipe Installation & Insulation 7 15-Aug-12 25-Aug-12 52 18-Sep-12 25-Sep-12 17-Oct-12 24-Oct-12 25 0% 0%
ElecElectrical 10 15-Aug-12 28-Aug-12 46 18-Sep-12 22-Sep-12 27-Sep-12 21-Oct-12 0% 0%A35 Install Conduits in Wall 3 15-Aug-12 18-Aug-12 35 18-Sep-12 20-Sep-12 27-Sep-12 30-Sep-12 8 0% 0%
A35 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 46 18-Sep-12 22-Sep-12 17-Oct-12 21-Oct-12 25 0% 0%PlumPlumbing 10 15-Aug-12 28-Aug-12 100 18-Sep-12 29-Sep-12 19-Sep-12 27-Dec-12 0% 0%A36 H/L Hot&Cold Water Pipe Installation 4 16-Aug-12 23-Aug-12 105 18-Sep-12 22-Sep-12 24-Dec-12 27-Dec-12 79 0% 0%
A36 Drainge Pipes in Wall 10 15-Aug-12 28-Aug-12 28 18-Sep-12 29-Sep-12 19-Sep-12 30-Sep-12 1 0% 0%
A36 Water Pipes in Wall 8 18-Aug-12 28-Aug-12 28 20-Sep-12 29-Sep-12 22-Sep-12 30-Sep-12 1 0% 0%ShaShafts 10 29-Jul-12 08-Aug-12 43 01-Sep-12 11-Sep-12 19-Sep-12 30-Sep-12 0% 0%A13 MEP Works inside Shafts 10 29-Jul-12 08-Aug-12 43 01-Sep-12 11-Sep-12 19-Sep-12 30-Sep-12 16 0% 0%
3rd Floor3rd Floor 15 06-Aug-12 26-Aug-12 45 22-Sep-12 08-Oct-12 22-Sep-12 17-Oct-12 0% 0%
ApartemApartements 15 06-Aug-12 26-Aug-12 45 22-Sep-12 08-Oct-12 22-Sep-12 17-Oct-12 0% 0%Two BTwo Bedroom Flats 15 06-Aug-12 26-Aug-12 45 22-Sep-12 08-Oct-12 22-Sep-12 17-Oct-12 0% 0%ApartApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 15 06-Aug-12 26-Aug-12 45 22-Sep-12 08-Oct-12 22-Sep-12 17-Oct-12 0% 0%FinisFinishing Works 15 06-Aug-12 26-Aug-12 37 22-Sep-12 08-Oct-12 22-Sep-12 08-Oct-12 0% 0%WetWet Works 15 06-Aug-12 26-Aug-12 37 22-Sep-12 08-Oct-12 22-Sep-12 08-Oct-12 0% 0%A37 Block Works 15 06-Aug-12 26-Aug-12 37 22-Sep-12 08-Oct-12 22-Sep-12 08-Oct-12 0 0% 0%
MEPMEP Works 10 06-Aug-12 18-Aug-12 50 22-Sep-12 02-Oct-12 07-Oct-12 17-Oct-12 0% 0%ShaShafts 10 06-Aug-12 18-Aug-12 50 22-Sep-12 02-Oct-12 07-Oct-12 17-Oct-12 0% 0%A13 Install Conduits in Wall 10 06-Aug-12 18-Aug-12 50 22-Sep-12 02-Oct-12 07-Oct-12 17-Oct-12 13 0% 0%
Hotel (BHotel (Block B) 33 29-Jul-12 06-Sep-12 210 09-Aug-12 04-Nov-12 11-Oct-12 16-May-13 0% 0%
2nd Base2nd Basement Floor 31 31-Jul-12 06-Sep-12 103 08-Sep-12 13-Oct-12 05-Dec-12 10-Jan-13 0% 0%
Public APublic Area 31 31-Jul-12 06-Sep-12 103 08-Sep-12 13-Oct-12 05-Dec-12 10-Jan-13 0% 0%StaircaStaircase 31 31-Jul-12 06-Sep-12 103 08-Sep-12 13-Oct-12 05-Dec-12 10-Jan-13 0% 0%StairsStairs 1 31 31-Jul-12 06-Sep-12 103 08-Sep-12 13-Oct-12 05-Dec-12 10-Jan-13 0% 0%A1092 Floor Screed 3 31-Jul-12 02-Aug-12 103 08-Sep-12 10-Sep-12 05-Dec-12 08-Dec-12 72 0% 0%
A1092 Install Handrails 4 04-Aug-12 07-Aug-12 103 11-Sep-12 15-Sep-12 09-Dec-12 12-Dec-12 72 0% 0%
A1092 Ceiling 1st Coat Paint 12 08-Aug-12 23-Aug-12 103 16-Sep-12 29-Sep-12 13-Dec-12 26-Dec-12 72 0% 0%
A1093 Wall 1st Coat Paint 12 08-Aug-12 23-Aug-12 103 16-Sep-12 29-Sep-12 13-Dec-12 26-Dec-12 72 0% 0%
A1093 Install Granite/Terrazo 12 25-Aug-12 06-Sep-12 103 30-Sep-12 13-Oct-12 27-Dec-12 10-Jan-13 72 0% 0%
1st Base1st Basement Floor 32 29-Jul-12 05-Sep-12 194 09-Aug-12 04-Nov-12 11-Oct-12 27-Apr-13 0% 0%
Public APublic Area 32 29-Jul-12 05-Sep-12 194 09-Aug-12 04-Nov-12 11-Oct-12 27-Apr-13 0% 0%Pump Pump Room 1 6 16-Aug-12 25-Aug-12 64 30-Aug-12 05-Sep-12 04-Nov-12 10-Nov-12 0% 0%FinishFinishing Works 6 16-Aug-12 25-Aug-12 64 30-Aug-12 05-Sep-12 04-Nov-12 10-Nov-12 0% 0%Wet Wet Works 6 16-Aug-12 25-Aug-12 64 30-Aug-12 05-Sep-12 04-Nov-12 10-Nov-12 0% 0%A550 Block Works 6 16-Aug-12 25-Aug-12 64 30-Aug-12 05-Sep-12 04-Nov-12 10-Nov-12 54 0% 0%
Pump Pump Room 2 6 09-Aug-12 15-Aug-12 64 23-Aug-12 29-Aug-12 28-Oct-12 03-Nov-12 0% 0%FinishFinishing Works 6 09-Aug-12 15-Aug-12 64 23-Aug-12 29-Aug-12 28-Oct-12 03-Nov-12 0% 0%Wet Wet Works 6 09-Aug-12 15-Aug-12 64 23-Aug-12 29-Aug-12 28-Oct-12 03-Nov-12 0% 0%A555 Block Works 6 09-Aug-12 15-Aug-12 64 23-Aug-12 29-Aug-12 28-Oct-12 03-Nov-12 54 0% 0%
AHU RAHU Room 15 31-Jul-12 16-Aug-12 87 12-Aug-12 30-Aug-12 16-Oct-12 03-Dec-12 0% 0%FinishFinishing Works 8 31-Jul-12 08-Aug-12 64 12-Aug-12 22-Aug-12 16-Oct-12 24-Oct-12 0% 0%Wet Wet Works 8 31-Jul-12 08-Aug-12 64 12-Aug-12 22-Aug-12 16-Oct-12 24-Oct-12 0% 0%A558 Block Works 8 31-Jul-12 08-Aug-12 64 12-Aug-12 22-Aug-12 16-Oct-12 24-Oct-12 54 0% 0%
MEP WMEP Works 7 09-Aug-12 16-Aug-12 87 23-Aug-12 30-Aug-12 25-Nov-12 03-Dec-12 0% 0%ElectElectrical 7 09-Aug-12 16-Aug-12 87 23-Aug-12 30-Aug-12 25-Nov-12 03-Dec-12 0% 0%A558 Install Conduits in Wall 7 09-Aug-12 16-Aug-12 87 23-Aug-12 30-Aug-12 25-Nov-12 03-Dec-12 77 0% 0%
BMS RBMS Room 4 29-Jul-12 01-Aug-12 91 09-Aug-12 13-Aug-12 14-Oct-12 21-Nov-12 0% 0%FinishFinishing Works 2 29-Jul-12 30-Jul-12 64 09-Aug-12 11-Aug-12 14-Oct-12 15-Oct-12 0% 0%Wet Wet Works 2 29-Jul-12 30-Jul-12 64 09-Aug-12 11-Aug-12 14-Oct-12 15-Oct-12 0% 0%A585 Block Works 2 29-Jul-12 30-Jul-12 64 09-Aug-12 11-Aug-12 14-Oct-12 15-Oct-12 54 0% 0%
MEP WMEP Works 2 31-Jul-12 01-Aug-12 91 12-Aug-12 13-Aug-12 20-Nov-12 21-Nov-12 0% 0%ElectElectrical 2 31-Jul-12 01-Aug-12 91 12-Aug-12 13-Aug-12 20-Nov-12 21-Nov-12 0% 0%A585 Install Conduits in Wall 2 31-Jul-12 01-Aug-12 91 12-Aug-12 13-Aug-12 20-Nov-12 21-Nov-12 81 0% 0%
ServerServer Room 10 12-Aug-12 25-Aug-12 62 26-Aug-12 05-Sep-12 28-Oct-12 07-Nov-12 0% 0%FinishFinishing Works 6 12-Aug-12 18-Aug-12 62 26-Aug-12 01-Sep-12 28-Oct-12 03-Nov-12 0% 0%Wet Wet Works 6 12-Aug-12 18-Aug-12 62 26-Aug-12 01-Sep-12 28-Oct-12 03-Nov-12 0% 0%A573 Block Works 6 12-Aug-12 18-Aug-12 62 26-Aug-12 01-Sep-12 28-Oct-12 03-Nov-12 52 0% 0%
MEP WMEP Works 4 21-Aug-12 25-Aug-12 62 02-Sep-12 05-Sep-12 04-Nov-12 07-Nov-12 0% 0%ElectElectrical 4 21-Aug-12 25-Aug-12 62 02-Sep-12 05-Sep-12 04-Nov-12 07-Nov-12 0% 0%A574 Install Conduits in Wall 4 21-Aug-12 25-Aug-12 62 02-Sep-12 05-Sep-12 04-Nov-12 07-Nov-12 52 0% 0%
Sub-StSub-Station 2 21 29-Jul-12 23-Aug-12 205 09-Aug-12 04-Sep-12 18-Oct-12 27-Apr-13 0% 0%FinishFinishing Works 16 29-Jul-12 15-Aug-12 210 09-Aug-12 29-Aug-12 18-Oct-12 27-Apr-13 0% 0%Wet Wet Works 16 29-Jul-12 15-Aug-12 210 09-Aug-12 29-Aug-12 18-Oct-12 27-Apr-13 0% 0%A561 Block Works 6 29-Jul-12 04-Aug-12 68 09-Aug-12 15-Aug-12 18-Oct-12 24-Oct-12 58 0% 0%
A560 Installation of Doors& Windows Sub-frame 2 11-Aug-12 12-Aug-12 213 25-Aug-12 26-Aug-12 25-Apr-13 27-Apr-13 203 0% 0%
A560 Plaster Works 5 11-Aug-12 15-Aug-12 134 25-Aug-12 29-Aug-12 22-Jan-13 28-Jan-13 124 0% 0%MEP WMEP Works 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%ElectElectrical 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%LightLight 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%A56 Install Conduits in Wall 5 05-Aug-12 09-Aug-12 134 16-Aug-12 23-Aug-12 16-Jan-13 21-Jan-13 124 0% 0%
A56 Wiring for Lighting & Power 5 16-Aug-12 23-Aug-12 134 30-Aug-12 04-Sep-12 29-Jan-13 03-Feb-13 124 0% 0%Sub-StSub-Station 3 21 29-Jul-12 23-Aug-12 205 09-Aug-12 04-Sep-12 09-Jan-13 27-Apr-13 0% 0%FinishFinishing Works 16 29-Jul-12 15-Aug-12 210 09-Aug-12 29-Aug-12 09-Jan-13 27-Apr-13 0% 0%Wet Wet Works 16 29-Jul-12 15-Aug-12 210 09-Aug-12 29-Aug-12 09-Jan-13 27-Apr-13 0% 0%A563 Block Works 6 29-Jul-12 04-Aug-12 134 09-Aug-12 15-Aug-12 09-Jan-13 15-Jan-13 124 0% 0%
A562 Installation of Doors& Windows Sub-frame 2 11-Aug-12 12-Aug-12 213 25-Aug-12 26-Aug-12 25-Apr-13 27-Apr-13 203 0% 0%
A562 Plaster Works 5 11-Aug-12 15-Aug-12 134 25-Aug-12 29-Aug-12 22-Jan-13 28-Jan-13 124 0% 0%MEP WMEP Works 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%ElectElectrical 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%LightLight 15 05-Aug-12 23-Aug-12 134 16-Aug-12 04-Sep-12 16-Jan-13 03-Feb-13 0% 0%A56 Install Conduits in Wall 5 05-Aug-12 09-Aug-12 134 16-Aug-12 23-Aug-12 16-Jan-13 21-Jan-13 124 0% 0%
A56 Wiring for Lighting & Power 5 16-Aug-12 23-Aug-12 134 30-Aug-12 04-Sep-12 29-Jan-13 03-Feb-13 124 0% 0%GenseGenset Rooms 8 07-Aug-12 15-Aug-12 144 21-Aug-12 29-Aug-12 21-Oct-12 09-Feb-13 0% 0%FinishFinishing Works 4 07-Aug-12 11-Aug-12 62 21-Aug-12 25-Aug-12 21-Oct-12 24-Oct-12 0% 0%Wet Wet Works 4 07-Aug-12 11-Aug-12 62 21-Aug-12 25-Aug-12 21-Oct-12 24-Oct-12 0% 0%A572 Block Works 4 07-Aug-12 11-Aug-12 62 21-Aug-12 25-Aug-12 21-Oct-12 24-Oct-12 52 0% 0%
MEP WMEP Works 4 12-Aug-12 15-Aug-12 144 26-Aug-12 29-Aug-12 05-Feb-13 09-Feb-13 0% 0%ElectElectrical 4 12-Aug-12 15-Aug-12 144 26-Aug-12 29-Aug-12 05-Feb-13 09-Feb-13 0% 0%A572 Install Conduits in Wall 4 12-Aug-12 15-Aug-12 144 26-Aug-12 29-Aug-12 05-Feb-13 09-Feb-13 134 0% 0%
CBS RCBS Room 8 04-Aug-12 12-Aug-12 141 15-Aug-12 26-Aug-12 17-Oct-12 02-Feb-13 0% 0%FinishFinishing Works 3 04-Aug-12 06-Aug-12 62 15-Aug-12 18-Aug-12 17-Oct-12 20-Oct-12 0% 0%Wet Wet Works 3 04-Aug-12 06-Aug-12 62 15-Aug-12 18-Aug-12 17-Oct-12 20-Oct-12 0% 0%A570 Block Works 3 04-Aug-12 06-Aug-12 62 15-Aug-12 18-Aug-12 17-Oct-12 20-Oct-12 52 0% 0%
MEP WMEP Works 5 07-Aug-12 12-Aug-12 141 21-Aug-12 26-Aug-12 28-Jan-13 02-Feb-13 0% 0%ElectElectrical 5 07-Aug-12 12-Aug-12 141 21-Aug-12 26-Aug-12 28-Jan-13 02-Feb-13 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Install Conduits in Wall
Install Cable Trays & Trunking
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
MEP Works inside Shafts
Block Works
Chilled Water Pipe Instal lation & Insulation
Install Conduits in Wall
Install Cable Trays & Trunking
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
MEP Works inside Shafts
Block Works
Install Conduits in Wall
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Block Works
Block Works
Block Works
Install Conduits in Wall
Block Works
Install Conduits in Wall
Block Works
Install Conduits in Wall
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Install Conduits in Wall
Wiring for Lighting & Power
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Install Conduits in Wall
Wiring for Lighting & Power
Block Works
Install Conduits in Wall
Block Works
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 15 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
A570 Install Conduits in Wall 5 07-Aug-12 12-Aug-12 141 21-Aug-12 26-Aug-12 28-Jan-13 02-Feb-13 131 0% 0%CCTV CCTV Control Room 12 29-Jul-12 11-Aug-12 82 09-Aug-12 25-Aug-12 11-Oct-12 20-Nov-12 0% 0%FinishFinishing Works 5 29-Jul-12 02-Aug-12 62 09-Aug-12 14-Aug-12 11-Oct-12 16-Oct-12 0% 0%Wet Wet Works 5 29-Jul-12 02-Aug-12 62 09-Aug-12 14-Aug-12 11-Oct-12 16-Oct-12 0% 0%A576 Block Works 5 29-Jul-12 02-Aug-12 62 09-Aug-12 14-Aug-12 11-Oct-12 16-Oct-12 52 0% 0%
MEP WMEP Works 7 04-Aug-12 11-Aug-12 82 15-Aug-12 25-Aug-12 12-Nov-12 20-Nov-12 0% 0%ElectElectrical 7 04-Aug-12 11-Aug-12 82 15-Aug-12 25-Aug-12 12-Nov-12 20-Nov-12 0% 0%A577 Install Conduits in Wall 7 04-Aug-12 11-Aug-12 82 15-Aug-12 25-Aug-12 12-Nov-12 20-Nov-12 72 0% 0%
StaircaStaircase 31 30-Jul-12 05-Sep-12 132 27-Sep-12 04-Nov-12 10-Dec-12 13-Feb-13 0% 0%StairsStairs 1 31 30-Jul-12 05-Sep-12 108 27-Sep-12 04-Nov-12 10-Dec-12 15-Jan-13 0% 0%A1094 Floor Screed 3 30-Jul-12 01-Aug-12 108 27-Sep-12 30-Sep-12 10-Dec-12 12-Dec-12 59 0% 0%
A1094 Install Handrails 4 02-Aug-12 06-Aug-12 108 01-Oct-12 04-Oct-12 13-Dec-12 17-Dec-12 59 0% 0%
A1094 Ceiling 1st Coat Paint 12 07-Aug-12 22-Aug-12 108 06-Oct-12 18-Oct-12 18-Dec-12 31-Dec-12 59 0% 0%
A1094 Wall 1st Coat Paint 12 07-Aug-12 22-Aug-12 108 06-Oct-12 18-Oct-12 18-Dec-12 31-Dec-12 59 0% 0%
A1094 Install Granite/Terrazo 12 23-Aug-12 05-Sep-12 108 20-Oct-12 04-Nov-12 02-Jan-13 15-Jan-13 59 0% 0%StairsStairs 2 31 30-Jul-12 05-Sep-12 120 27-Sep-12 04-Nov-12 24-Dec-12 30-Jan-13 0% 0%A1095 Floor Screed 3 30-Jul-12 01-Aug-12 120 27-Sep-12 30-Sep-12 24-Dec-12 26-Dec-12 71 0% 0%
A1095 Install Handrails 4 02-Aug-12 06-Aug-12 120 01-Oct-12 04-Oct-12 27-Dec-12 31-Dec-12 71 0% 0%
A1095 Ceiling 1st Coat Paint 12 07-Aug-12 22-Aug-12 120 06-Oct-12 18-Oct-12 02-Jan-13 15-Jan-13 71 0% 0%
A1095 Wall 1st Coat Paint 12 07-Aug-12 22-Aug-12 120 06-Oct-12 18-Oct-12 02-Jan-13 15-Jan-13 71 0% 0%
A1095 Install Granite/Terrazo 12 23-Aug-12 05-Sep-12 120 20-Oct-12 04-Nov-12 16-Jan-13 30-Jan-13 71 0% 0%StairsStairs 3 31 30-Jul-12 05-Sep-12 132 27-Sep-12 04-Nov-12 08-Jan-13 13-Feb-13 0% 0%A1095 Floor Screed 3 30-Jul-12 01-Aug-12 132 27-Sep-12 30-Sep-12 08-Jan-13 10-Jan-13 83 0% 0%
A1095 Install Handrails 4 02-Aug-12 06-Aug-12 132 01-Oct-12 04-Oct-12 12-Jan-13 15-Jan-13 83 0% 0%
A1095 Ceiling 1st Coat Paint 12 07-Aug-12 22-Aug-12 132 06-Oct-12 18-Oct-12 16-Jan-13 30-Jan-13 83 0% 0%
A1096 Wall 1st Coat Paint 12 07-Aug-12 22-Aug-12 132 06-Oct-12 18-Oct-12 16-Jan-13 30-Jan-13 83 0% 0%
A1096 Install Granite/Terrazo 12 23-Aug-12 05-Sep-12 132 20-Oct-12 04-Nov-12 31-Jan-13 13-Feb-13 83 0% 0%
Ground FGround Floor 30 30-Jul-12 04-Sep-12 212 17-Sep-12 17-Oct-12 04-Nov-12 16-May-13 0% 0%
Public APublic Area 30 30-Jul-12 04-Sep-12 212 17-Sep-12 17-Oct-12 04-Nov-12 16-May-13 0% 0%Coffe aCoffe and Baverage Bar (Lounge) 9 22-Aug-12 01-Sep-12 107 08-Oct-12 17-Oct-12 30-Dec-12 09-Jan-13 0% 0%FinishFinishing Works 9 22-Aug-12 01-Sep-12 107 08-Oct-12 17-Oct-12 30-Dec-12 09-Jan-13 0% 0%Wet Wet Works 9 22-Aug-12 01-Sep-12 107 08-Oct-12 17-Oct-12 30-Dec-12 09-Jan-13 0% 0%A660 Block Works 9 22-Aug-12 01-Sep-12 107 08-Oct-12 17-Oct-12 30-Dec-12 09-Jan-13 67 0% 0%
VestibVestibule 11 15-Aug-12 29-Aug-12 164 03-Oct-12 13-Oct-12 25-Dec-12 16-Mar-13 0% 0%FinishFinishing Works 4 15-Aug-12 21-Aug-12 107 03-Oct-12 07-Oct-12 25-Dec-12 29-Dec-12 0% 0%Wet Wet Works 4 15-Aug-12 21-Aug-12 107 03-Oct-12 07-Oct-12 25-Dec-12 29-Dec-12 0% 0%A650 Block Works 4 15-Aug-12 21-Aug-12 107 03-Oct-12 07-Oct-12 25-Dec-12 29-Dec-12 67 0% 0%
MEP WMEP Works 7 22-Aug-12 29-Aug-12 164 08-Oct-12 13-Oct-12 13-Jan-13 16-Mar-13 0% 0%HVACHVAC 4 22-Aug-12 26-Aug-12 167 08-Oct-12 11-Oct-12 12-Mar-13 16-Mar-13 0% 0%A651 Chilled Water Pipe Installation & Insulation 4 22-Aug-12 26-Aug-12 167 08-Oct-12 11-Oct-12 12-Mar-13 16-Mar-13 127 0% 0%
ElectElectrical 7 22-Aug-12 29-Aug-12 120 08-Oct-12 13-Oct-12 13-Jan-13 22-Jan-13 0% 0%A651 Install Conduits in Wall 5 22-Aug-12 27-Aug-12 118 08-Oct-12 13-Oct-12 13-Jan-13 17-Jan-13 78 0% 0%
A651 Install Cable Trays & Trunking 5 25-Aug-12 29-Aug-12 120 08-Oct-12 13-Oct-12 17-Jan-13 22-Jan-13 82 0% 0%BussinBussiniss Centre & Lobby 30 30-Jul-12 04-Sep-12 123 17-Sep-12 14-Oct-12 05-Dec-12 02-Feb-13 0% 0%FinishFinishing Works 14 30-Jul-12 14-Aug-12 104 17-Sep-12 02-Oct-12 05-Dec-12 20-Dec-12 0% 0%Wet Wet Works 14 30-Jul-12 14-Aug-12 104 17-Sep-12 02-Oct-12 05-Dec-12 20-Dec-12 0% 0%A643 Block Works 14 30-Jul-12 14-Aug-12 104 17-Sep-12 02-Oct-12 05-Dec-12 20-Dec-12 64 0% 0%
MEP WMEP Works 16 15-Aug-12 04-Sep-12 123 03-Oct-12 14-Oct-12 22-Dec-12 02-Feb-13 0% 0%HVACHVAC 5 15-Aug-12 22-Aug-12 134 03-Oct-12 08-Oct-12 28-Jan-13 02-Feb-13 0% 0%A644 Chilled Water Pipe Installation & Insulation 5 15-Aug-12 22-Aug-12 134 03-Oct-12 08-Oct-12 28-Jan-13 02-Feb-13 94 0% 0%
ElectElectrical 16 15-Aug-12 04-Sep-12 109 03-Oct-12 14-Oct-12 22-Dec-12 15-Jan-13 0% 0%A644 Install Conduits in Wall 10 15-Aug-12 28-Aug-12 104 03-Oct-12 14-Oct-12 22-Dec-12 02-Jan-13 64 0% 0%
A644 Install Cable Trays & Trunking 10 25-Aug-12 04-Sep-12 109 03-Oct-12 14-Oct-12 05-Jan-13 15-Jan-13 75 0% 0%PlumPlumbing 7 15-Aug-12 25-Aug-12 132 03-Oct-12 10-Oct-12 26-Jan-13 02-Feb-13 0% 0%A646 H/L Drainage Pipes Installation 7 15-Aug-12 25-Aug-12 132 03-Oct-12 10-Oct-12 26-Jan-13 02-Feb-13 92 0% 0%
RMU RRMU Room 27 30-Jul-12 01-Sep-12 215 17-Sep-12 06-Oct-12 27-Jan-13 16-May-13 0% 0%FinishFinishing Works 15 30-Jul-12 15-Aug-12 227 17-Sep-12 03-Oct-12 27-Jan-13 16-May-13 0% 0%Wet Wet Works 15 30-Jul-12 15-Aug-12 227 17-Sep-12 03-Oct-12 27-Jan-13 16-May-13 0% 0%A631 Block Works 5 30-Jul-12 04-Aug-12 147 17-Sep-12 22-Sep-12 27-Jan-13 31-Jan-13 107 0% 0%
A631 Installation of Doors& Windows Sub-frame 2 08-Aug-12 09-Aug-12 232 26-Sep-12 27-Sep-12 15-May-13 16-May-13 192 0% 0%
A631 Plaster Works 7 08-Aug-12 15-Aug-12 147 26-Sep-12 03-Oct-12 05-Feb-13 12-Feb-13 107 0% 0%MEP WMEP Works 24 02-Aug-12 01-Sep-12 144 20-Sep-12 06-Oct-12 30-Jan-13 23-Feb-13 0% 0%HVACHVAC 7 05-Aug-12 12-Aug-12 154 23-Sep-12 30-Sep-12 10-Feb-13 17-Feb-13 0% 0%A632 Chilled Water Pipe Installation & Insulation 7 05-Aug-12 12-Aug-12 154 23-Sep-12 30-Sep-12 10-Feb-13 17-Feb-13 114 0% 0%
ElectElectrical 24 02-Aug-12 01-Sep-12 144 20-Sep-12 06-Oct-12 30-Jan-13 23-Feb-13 0% 0%LighLight & Power 24 02-Aug-12 01-Sep-12 144 20-Sep-12 06-Oct-12 30-Jan-13 23-Feb-13 0% 0%A63 Install Conduits in Wall 5 02-Aug-12 07-Aug-12 147 20-Sep-12 25-Sep-12 30-Jan-13 04-Feb-13 107 0% 0%
A63 Wiring for Lighting & Power 4 14-Aug-12 18-Aug-12 147 02-Oct-12 06-Oct-12 11-Feb-13 14-Feb-13 107 0% 0%
A63 Install Cable Trays & Trunking 7 25-Aug-12 01-Sep-12 144 23-Sep-12 30-Sep-12 16-Feb-13 23-Feb-13 119 0% 0%ElectriElectrical / Telephone Rooms 3 25-Aug-12 27-Aug-12 79 10-Oct-12 13-Oct-12 28-Nov-12 01-Dec-12 0% 0%FinishFinishing Works 3 25-Aug-12 27-Aug-12 79 10-Oct-12 13-Oct-12 28-Nov-12 01-Dec-12 0% 0%Wet Wet Works 3 25-Aug-12 27-Aug-12 79 10-Oct-12 13-Oct-12 28-Nov-12 01-Dec-12 0% 0%A624 Block Works 3 25-Aug-12 27-Aug-12 79 10-Oct-12 13-Oct-12 28-Nov-12 01-Dec-12 39 0% 0%
LuggaLuggage Room 10 16-Aug-12 29-Aug-12 131 04-Oct-12 15-Oct-12 22-Nov-12 05-Feb-13 0% 0%FinishFinishing Works 5 16-Aug-12 23-Aug-12 79 04-Oct-12 09-Oct-12 22-Nov-12 27-Nov-12 0% 0%Wet Wet Works 5 16-Aug-12 23-Aug-12 79 04-Oct-12 09-Oct-12 22-Nov-12 27-Nov-12 0% 0%A639 Block Works 5 16-Aug-12 23-Aug-12 79 04-Oct-12 09-Oct-12 22-Nov-12 27-Nov-12 39 0% 0%
MEP WMEP Works 5 25-Aug-12 29-Aug-12 131 10-Oct-12 15-Oct-12 23-Jan-13 05-Feb-13 0% 0%HVACHVAC 5 25-Aug-12 29-Aug-12 125 10-Oct-12 15-Oct-12 23-Jan-13 29-Jan-13 0% 0%A639 Chilled Water Pipe Installation & Insulation 5 25-Aug-12 29-Aug-12 125 10-Oct-12 15-Oct-12 23-Jan-13 29-Jan-13 85 0% 0%
ElectElectrical 2 25-Aug-12 26-Aug-12 134 10-Oct-12 11-Oct-12 04-Feb-13 05-Feb-13 0% 0%A639 Install Conduits in Wall 2 25-Aug-12 26-Aug-12 134 10-Oct-12 11-Oct-12 04-Feb-13 05-Feb-13 94 0% 0%
LoadinLoading Dock Area 13 09-Aug-12 26-Aug-12 139 27-Sep-12 11-Oct-12 14-Nov-12 11-Feb-13 0% 0%FinishFinishing Works 6 09-Aug-12 15-Aug-12 79 27-Sep-12 03-Oct-12 14-Nov-12 21-Nov-12 0% 0%Wet Wet Works 6 09-Aug-12 15-Aug-12 79 27-Sep-12 03-Oct-12 14-Nov-12 21-Nov-12 0% 0%A641 Block Works 6 09-Aug-12 15-Aug-12 79 27-Sep-12 03-Oct-12 14-Nov-12 21-Nov-12 39 0% 0%
MEP WMEP Works 7 16-Aug-12 26-Aug-12 139 04-Oct-12 11-Oct-12 04-Feb-13 11-Feb-13 0% 0%ElectElectrical 7 16-Aug-12 26-Aug-12 139 04-Oct-12 11-Oct-12 04-Feb-13 11-Feb-13 0% 0%A642 Install Conduits in Wall 7 16-Aug-12 26-Aug-12 139 04-Oct-12 11-Oct-12 04-Feb-13 11-Feb-13 99 0% 0%
Hotel GHotel Garbage Room 16 30-Jul-12 16-Aug-12 156 17-Sep-12 04-Oct-12 04-Nov-12 24-Feb-13 0% 0%FinishFinishing Works 9 30-Jul-12 08-Aug-12 79 17-Sep-12 26-Sep-12 04-Nov-12 13-Nov-12 0% 0%Wet Wet Works 9 30-Jul-12 08-Aug-12 79 17-Sep-12 26-Sep-12 04-Nov-12 13-Nov-12 0% 0%A616 Block Works 9 30-Jul-12 08-Aug-12 79 17-Sep-12 26-Sep-12 04-Nov-12 13-Nov-12 39 0% 0%
MEP WMEP Works 7 09-Aug-12 16-Aug-12 156 27-Sep-12 04-Oct-12 17-Feb-13 24-Feb-13 0% 0%ElectElectrical 7 09-Aug-12 16-Aug-12 156 27-Sep-12 04-Oct-12 17-Feb-13 24-Feb-13 0% 0%A616 Install Conduits in Wall 7 09-Aug-12 16-Aug-12 156 27-Sep-12 04-Oct-12 17-Feb-13 24-Feb-13 116 0% 0%
ResidenResidential Apartments (Block C) 43 29-Jul-12 19-Sep-12 168 05-Aug-12 20-Oct-12 13-Sep-12 09-Apr-13 0% 0%
2nd Base2nd Basement Floor 31 30-Jul-12 05-Sep-12 149 12-Aug-12 18-Sep-12 19-Nov-12 05-Mar-13 0% 0%
Public APublic Area 31 30-Jul-12 05-Sep-12 149 12-Aug-12 18-Sep-12 19-Nov-12 05-Mar-13 0% 0%ParkinParking Area 21 09-Aug-12 04-Sep-12 150 03-Sep-12 13-Sep-12 01-Dec-12 05-Mar-13 0% 0%FinishFinishing Works 5 09-Aug-12 14-Aug-12 92 03-Sep-12 08-Sep-12 01-Dec-12 06-Dec-12 0% 0%Wet Wet Works 5 09-Aug-12 14-Aug-12 92 03-Sep-12 08-Sep-12 01-Dec-12 06-Dec-12 0% 0%A679 Plaster Works 5 09-Aug-12 14-Aug-12 92 03-Sep-12 08-Sep-12 01-Dec-12 06-Dec-12 73 0% 0%
MEP WMEP Works 10 25-Aug-12 04-Sep-12 150 03-Sep-12 13-Sep-12 17-Jan-13 05-Mar-13 0% 0%ElectElectrical 10 25-Aug-12 04-Sep-12 120 03-Sep-12 13-Sep-12 17-Jan-13 29-Jan-13 0% 0%A116 Instalaltion of Cable Trays 10 25-Aug-12 04-Sep-12 120 03-Sep-12 13-Sep-12 17-Jan-13 29-Jan-13 112 0% 0%
PlumPlumbing 4 25-Aug-12 28-Aug-12 156 03-Sep-12 06-Sep-12 02-Mar-13 05-Mar-13 0% 0%A680 Floor Drain Fixning 4 25-Aug-12 28-Aug-12 156 03-Sep-12 06-Sep-12 02-Mar-13 05-Mar-13 148 0% 0%
Lift LoLift Lobby 18 09-Aug-12 01-Sep-12 84 25-Aug-12 01-Sep-12 28-Nov-12 12-Dec-12 0% 0%MEP WMEP Works 18 09-Aug-12 01-Sep-12 84 25-Aug-12 01-Sep-12 28-Nov-12 12-Dec-12 0% 0%ElectElectrical 18 09-Aug-12 01-Sep-12 84 25-Aug-12 01-Sep-12 28-Nov-12 12-Dec-12 0% 0%A676 Install Conduits in Wall 7 09-Aug-12 16-Aug-12 90 25-Aug-12 01-Sep-12 28-Nov-12 06-Dec-12 79 0% 0%
A676 Install Cable Trays & Trunking 7 25-Aug-12 01-Sep-12 84 25-Aug-12 01-Sep-12 05-Dec-12 12-Dec-12 84 0% 0%MechaMechanical Rooms 4 18-Aug-12 23-Aug-12 93 02-Sep-12 05-Sep-12 11-Dec-12 15-Dec-12 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Conduits in Wall
Block Works
Install Conduits in Wall
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Block Works
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Install Cable Trays & Trunking
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Install Cable Trays & Trunking
H/L Drainage Pipes Installation
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Wiring for Lighting & Power
Install Cable Trays & Trunking
Block Works
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Block Works
Install Conduits in Wall
Block Works
Install Conduits in Wall
Plaster Works
Instalaltion of Cable Trays
Floor Drain Fixning
Install Conduits in Wall
Install Cable Trays & Trunking
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 16 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
MEP WMEP Works 4 18-Aug-12 23-Aug-12 93 02-Sep-12 05-Sep-12 11-Dec-12 15-Dec-12 0% 0%ElectElectrical 4 18-Aug-12 23-Aug-12 93 02-Sep-12 05-Sep-12 11-Dec-12 15-Dec-12 0% 0%A671 Install Conduits in Wall 4 18-Aug-12 23-Aug-12 93 02-Sep-12 05-Sep-12 11-Dec-12 15-Dec-12 82 0% 0%
Pump Pump Room 3 25-Aug-12 27-Aug-12 95 06-Sep-12 09-Sep-12 18-Dec-12 20-Dec-12 0% 0%MEP WMEP Works 3 25-Aug-12 27-Aug-12 95 06-Sep-12 09-Sep-12 18-Dec-12 20-Dec-12 0% 0%ElectElectrical 3 25-Aug-12 27-Aug-12 95 06-Sep-12 09-Sep-12 18-Dec-12 20-Dec-12 0% 0%A673 Install Conduits in Wall 3 25-Aug-12 27-Aug-12 95 06-Sep-12 09-Sep-12 18-Dec-12 20-Dec-12 84 0% 0%
StaircaStaircase 31 30-Jul-12 05-Sep-12 91 12-Aug-12 18-Sep-12 19-Nov-12 25-Dec-12 0% 0%StairsStairs 1 31 30-Jul-12 05-Sep-12 91 12-Aug-12 18-Sep-12 19-Nov-12 25-Dec-12 0% 0%A1112 Floor Screed 3 30-Jul-12 01-Aug-12 91 12-Aug-12 14-Aug-12 19-Nov-12 21-Nov-12 80 0% 0%
A1112 Install Handrails 4 02-Aug-12 06-Aug-12 91 15-Aug-12 21-Aug-12 22-Nov-12 26-Nov-12 80 0% 0%
A1112 Ceiling 1st Coat Paint 12 07-Aug-12 22-Aug-12 91 22-Aug-12 04-Sep-12 27-Nov-12 11-Dec-12 80 0% 0%
A1112 Wall 1st Coat Paint 12 07-Aug-12 22-Aug-12 91 22-Aug-12 04-Sep-12 27-Nov-12 11-Dec-12 80 0% 0%
A1112 Install Granite/Terrazo 12 23-Aug-12 05-Sep-12 91 05-Sep-12 18-Sep-12 12-Dec-12 25-Dec-12 80 0% 0%
1st Base1st Basement Floor 33 29-Jul-12 06-Sep-12 176 05-Aug-12 10-Oct-12 03-Nov-12 07-Apr-13 0% 0%
Public APublic Area 33 29-Jul-12 06-Sep-12 176 05-Aug-12 10-Oct-12 03-Nov-12 07-Apr-13 0% 0%ParkinParking Area 16 15-Aug-12 04-Sep-12 150 16-Aug-12 01-Sep-12 24-Dec-12 05-Mar-13 0% 0%MEP WMEP Works 16 15-Aug-12 04-Sep-12 150 16-Aug-12 01-Sep-12 24-Dec-12 05-Mar-13 0% 0%HVACHVAC 7 15-Aug-12 25-Aug-12 109 25-Aug-12 01-Sep-12 27-Dec-12 05-Jan-13 0% 0%A690 Chilled Water Pipe Installation & Insulation 7 15-Aug-12 25-Aug-12 109 25-Aug-12 01-Sep-12 27-Dec-12 05-Jan-13 103 0% 0%
ElectElectrical 10 25-Aug-12 04-Sep-12 100 16-Aug-12 29-Aug-12 24-Dec-12 05-Jan-13 0% 0%A116 Instalaltion of Cable Trays 10 25-Aug-12 04-Sep-12 100 16-Aug-12 29-Aug-12 24-Dec-12 05-Jan-13 105 0% 0%
PlumPlumbing 7 25-Aug-12 01-Sep-12 153 16-Aug-12 26-Aug-12 23-Feb-13 05-Mar-13 0% 0%A691 Floor Drain Fixning 7 25-Aug-12 01-Sep-12 153 16-Aug-12 26-Aug-12 26-Feb-13 05-Mar-13 158 0% 0%
A691 H/L Drainage Pipes Installation 7 25-Aug-12 01-Sep-12 150 16-Aug-12 26-Aug-12 23-Feb-13 02-Mar-13 155 0% 0%Lift LoLift Lobby 21 02-Aug-12 28-Aug-12 110 09-Aug-12 23-Aug-12 07-Nov-12 09-Jan-13 0% 0%FinishFinishing Works 6 02-Aug-12 08-Aug-12 90 09-Aug-12 15-Aug-12 07-Nov-12 13-Nov-12 0% 0%Wet Wet Works 6 02-Aug-12 08-Aug-12 90 09-Aug-12 15-Aug-12 07-Nov-12 13-Nov-12 0% 0%A686 Block Works 6 02-Aug-12 08-Aug-12 90 09-Aug-12 15-Aug-12 07-Nov-12 13-Nov-12 73 0% 0%
MEP WMEP Works 15 09-Aug-12 28-Aug-12 110 16-Aug-12 23-Aug-12 22-Dec-12 09-Jan-13 0% 0%HVACHVAC 5 09-Aug-12 14-Aug-12 109 16-Aug-12 23-Aug-12 22-Dec-12 26-Dec-12 0% 0%A686 Chilled Water Pipe Installation & Insulation 5 09-Aug-12 14-Aug-12 109 16-Aug-12 23-Aug-12 22-Dec-12 26-Dec-12 103 0% 0%
ElectElectrical 15 09-Aug-12 28-Aug-12 110 16-Aug-12 22-Aug-12 31-Dec-12 09-Jan-13 0% 0%A687 Install Conduits in Wall 3 09-Aug-12 12-Aug-12 117 16-Aug-12 21-Aug-12 31-Dec-12 03-Jan-13 111 0% 0%
A687 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 110 16-Aug-12 22-Aug-12 06-Jan-13 09-Jan-13 115 0% 0%MechaMechanical Rooms 8 29-Jul-12 06-Aug-12 129 05-Aug-12 13-Aug-12 03-Nov-12 12-Jan-13 0% 0%FinishFinishing Works 4 29-Jul-12 01-Aug-12 90 05-Aug-12 08-Aug-12 03-Nov-12 06-Nov-12 0% 0%Wet Wet Works 4 29-Jul-12 01-Aug-12 90 05-Aug-12 08-Aug-12 03-Nov-12 06-Nov-12 0% 0%A681 Block Works 4 29-Jul-12 01-Aug-12 90 05-Aug-12 08-Aug-12 03-Nov-12 06-Nov-12 73 0% 0%
MEP WMEP Works 4 02-Aug-12 06-Aug-12 129 09-Aug-12 13-Aug-12 08-Jan-13 12-Jan-13 0% 0%ElectElectrical 4 02-Aug-12 06-Aug-12 129 09-Aug-12 13-Aug-12 08-Jan-13 12-Jan-13 0% 0%A681 Install Conduits in Wall 4 02-Aug-12 06-Aug-12 129 09-Aug-12 13-Aug-12 08-Jan-13 12-Jan-13 123 0% 0%
StaircaStaircase 31 31-Jul-12 06-Sep-12 176 05-Sep-12 10-Oct-12 03-Mar-13 07-Apr-13 0% 0%StairsStairs 1 31 31-Jul-12 06-Sep-12 176 05-Sep-12 10-Oct-12 03-Mar-13 07-Apr-13 0% 0%A1113 Floor Screed 3 31-Jul-12 02-Aug-12 176 05-Sep-12 08-Sep-12 03-Mar-13 05-Mar-13 147 0% 0%
A1114 Install Handrails 4 04-Aug-12 07-Aug-12 176 09-Sep-12 12-Sep-12 06-Mar-13 10-Mar-13 147 0% 0%
A1114 Ceiling 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1114 Wall 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1114 Install Granite/Terrazo 12 25-Aug-12 06-Sep-12 176 27-Sep-12 10-Oct-12 25-Mar-13 07-Apr-13 147 0% 0%StairsStairs 2 31 31-Jul-12 06-Sep-12 176 05-Sep-12 10-Oct-12 03-Mar-13 07-Apr-13 0% 0%A1114 Floor Screed 3 31-Jul-12 02-Aug-12 176 05-Sep-12 08-Sep-12 03-Mar-13 05-Mar-13 147 0% 0%
A1114 Install Handrails 4 04-Aug-12 07-Aug-12 176 09-Sep-12 12-Sep-12 06-Mar-13 10-Mar-13 147 0% 0%
A1114 Ceiling 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1114 Wall 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1114 Install Granite/Terrazo 12 25-Aug-12 06-Sep-12 176 27-Sep-12 10-Oct-12 25-Mar-13 07-Apr-13 147 0% 0%StairsStairs 3 31 31-Jul-12 06-Sep-12 176 05-Sep-12 10-Oct-12 03-Mar-13 07-Apr-13 0% 0%A1115 Floor Screed 3 31-Jul-12 02-Aug-12 176 05-Sep-12 08-Sep-12 03-Mar-13 05-Mar-13 147 0% 0%
A1115 Install Handrails 4 04-Aug-12 07-Aug-12 176 09-Sep-12 12-Sep-12 06-Mar-13 10-Mar-13 147 0% 0%
A1115 Ceiling 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1115 Wall 1st Coat Paint 12 08-Aug-12 23-Aug-12 176 13-Sep-12 26-Sep-12 11-Mar-13 24-Mar-13 147 0% 0%
A1115 Install Granite/Terrazo 12 25-Aug-12 06-Sep-12 176 27-Sep-12 10-Oct-12 25-Mar-13 07-Apr-13 147 0% 0%
Ground FGround Floor 28 31-Jul-12 03-Sep-12 181 05-Sep-12 14-Oct-12 04-Nov-12 09-Apr-13 0% 0%
Public APublic Area 28 31-Jul-12 03-Sep-12 181 05-Sep-12 14-Oct-12 04-Nov-12 09-Apr-13 0% 0%ElectriElectrical /Telephone / GSM Rooms 28 31-Jul-12 03-Sep-12 171 05-Sep-12 07-Oct-12 04-Nov-12 28-Mar-13 0% 0%FinishFinishing Works 28 31-Jul-12 03-Sep-12 171 05-Sep-12 07-Oct-12 04-Nov-12 28-Mar-13 0% 0%Wet Wet Works 28 31-Jul-12 03-Sep-12 171 05-Sep-12 07-Oct-12 04-Nov-12 28-Mar-13 0% 0%A708 Block Works 15 31-Jul-12 16-Aug-12 78 05-Sep-12 22-Sep-12 04-Nov-12 21-Nov-12 49 0% 0%
A707 Installation of Doors& Windows Sub-frame 2 23-Aug-12 25-Aug-12 179 26-Sep-12 27-Sep-12 27-Mar-13 28-Mar-13 150 0% 0%
A707 Plaster Works 10 23-Aug-12 03-Sep-12 102 26-Sep-12 07-Oct-12 25-Dec-12 06-Jan-13 73 0% 0%MEP WMEP Works 3 18-Aug-12 22-Aug-12 102 23-Sep-12 25-Sep-12 22-Dec-12 24-Dec-12 0% 0%ElectElectrical 3 18-Aug-12 22-Aug-12 102 23-Sep-12 25-Sep-12 22-Dec-12 24-Dec-12 0% 0%A708 Install Conduits in Wall 3 18-Aug-12 22-Aug-12 102 23-Sep-12 25-Sep-12 22-Dec-12 24-Dec-12 73 0% 0%
Main GMain Garbage Room 12 18-Aug-12 02-Sep-12 78 23-Sep-12 06-Oct-12 22-Nov-12 06-Dec-12 0% 0%FinishFinishing Works 12 18-Aug-12 02-Sep-12 78 23-Sep-12 06-Oct-12 22-Nov-12 06-Dec-12 0% 0%Wet Wet Works 12 18-Aug-12 02-Sep-12 78 23-Sep-12 06-Oct-12 22-Nov-12 06-Dec-12 0% 0%A709 Block Works 12 18-Aug-12 02-Sep-12 78 23-Sep-12 06-Oct-12 22-Nov-12 06-Dec-12 49 0% 0%
StaircaStaircase 7 15-Aug-12 26-Aug-12 189 16-Sep-12 14-Oct-12 20-Dec-12 09-Apr-13 0% 0%StairsStairs 1 7 15-Aug-12 26-Aug-12 103 16-Sep-12 06-Oct-12 20-Dec-12 27-Dec-12 0% 0%A1115 Floor Screed 3 15-Aug-12 21-Aug-12 103 16-Sep-12 18-Sep-12 20-Dec-12 23-Dec-12 78 0% 0%
A1116 Install Handrails 4 21-Aug-12 26-Aug-12 103 02-Oct-12 06-Oct-12 24-Dec-12 27-Dec-12 67 0% 0%StairsStairs 4 7 15-Aug-12 26-Aug-12 189 07-Oct-12 14-Oct-12 02-Apr-13 09-Apr-13 0% 0%A1121 Floor Screed 3 15-Aug-12 21-Aug-12 189 07-Oct-12 09-Oct-12 02-Apr-13 04-Apr-13 146 0% 0%
A1121 Install Handrails 4 21-Aug-12 26-Aug-12 189 10-Oct-12 14-Oct-12 06-Apr-13 09-Apr-13 146 0% 0%
1st Floor1st Floor 28 15-Aug-12 19-Sep-12 99 09-Sep-12 20-Oct-12 13-Sep-12 17-Jan-13 0% 0%
Public APublic Area 12 15-Aug-12 01-Sep-12 115 09-Sep-12 22-Sep-12 05-Jan-13 17-Jan-13 0% 0%PlantePlanters 12 15-Aug-12 01-Sep-12 115 09-Sep-12 22-Sep-12 05-Jan-13 17-Jan-13 0% 0%FinishFinishing Works 12 15-Aug-12 01-Sep-12 115 09-Sep-12 22-Sep-12 05-Jan-13 17-Jan-13 0% 0%A1050 Water Proof Membrane 12 15-Aug-12 01-Sep-12 115 09-Sep-12 22-Sep-12 05-Jan-13 17-Jan-13 96 0% 0%
ApartemApartements 28 15-Aug-12 19-Sep-12 39 13-Sep-12 20-Oct-12 13-Sep-12 05-Nov-12 0% 0%Two BTwo Bedroom Flats 28 15-Aug-12 19-Sep-12 39 18-Sep-12 20-Oct-12 18-Sep-12 05-Nov-12 0% 0%ApartApartement .1 -11 (2 BR) 28 15-Aug-12 19-Sep-12 39 18-Sep-12 20-Oct-12 18-Sep-12 05-Nov-12 0% 0%FinisFinishing Works 28 15-Aug-12 19-Sep-12 27 18-Sep-12 20-Oct-12 18-Sep-12 20-Oct-12 0% 0%WetWet Works 28 15-Aug-12 19-Sep-12 27 18-Sep-12 20-Oct-12 18-Sep-12 20-Oct-12 0% 0%A74 Block Works 28 15-Aug-12 19-Sep-12 27 18-Sep-12 20-Oct-12 18-Sep-12 20-Oct-12 0 0% 0%
MEPMEP Works 12 15-Aug-12 01-Sep-12 55 18-Sep-12 01-Oct-12 21-Oct-12 05-Nov-12 0% 0%ShaShafts 12 15-Aug-12 01-Sep-12 55 18-Sep-12 01-Oct-12 21-Oct-12 05-Nov-12 0% 0%A13 MEP Works inside Shafts 12 15-Aug-12 01-Sep-12 55 18-Sep-12 01-Oct-12 21-Oct-12 05-Nov-12 28 0% 0%
Three Three Bedroom Flats 18 15-Aug-12 08-Sep-12 29 13-Sep-12 03-Oct-12 13-Sep-12 10-Oct-12 0% 0%ApartApartement .1 -3 (3 BR) 18 15-Aug-12 08-Sep-12 29 13-Sep-12 03-Oct-12 13-Sep-12 10-Oct-12 0% 0%FinisFinishing Works 12 15-Aug-12 01-Sep-12 23 13-Sep-12 26-Sep-12 13-Sep-12 26-Sep-12 0% 0%WetWet Works 12 15-Aug-12 01-Sep-12 23 13-Sep-12 26-Sep-12 13-Sep-12 26-Sep-12 0% 0%A74 Block Works 12 15-Aug-12 01-Sep-12 23 13-Sep-12 26-Sep-12 13-Sep-12 26-Sep-12 0 0% 0%
MEPMEP Works 18 15-Aug-12 08-Sep-12 29 13-Sep-12 03-Oct-12 27-Sep-12 10-Oct-12 0% 0%ElecElectrical 12 25-Aug-12 08-Sep-12 29 20-Sep-12 03-Oct-12 27-Sep-12 10-Oct-12 0% 0%A74 Install Conduits in Wall 12 25-Aug-12 08-Sep-12 29 20-Sep-12 03-Oct-12 27-Sep-12 10-Oct-12 6 0% 0%
ShaShafts 12 15-Aug-12 01-Sep-12 35 13-Sep-12 26-Sep-12 27-Sep-12 10-Oct-12 0% 0%A13 MEP Works inside Shafts 12 15-Aug-12 01-Sep-12 35 13-Sep-12 26-Sep-12 27-Sep-12 10-Oct-12 12 0% 0%
HandingHanding Over 70 01-Jul-12 22-Sep-12 79 10-Jun-12 10-Oct-12 02-Oct-12 27-Dec-12 0% 0%
InspectioInspections 70 01-Jul-12 22-Sep-12 79 10-Jun-12 10-Oct-12 02-Oct-12 27-Dec-12 0% 0%
DrainageDrainage 70 01-Jul-12 22-Sep-12 79 10-Jun-12 10-Oct-12 02-Oct-12 27-Dec-12 0% 0%
A1234 Receipt of Design NOC for Drainage 0 01-Jul-12 79 10-Jun-12 02-Oct-12 95 100% 0%
A1244 FIC Chambers - RC Works ( 4 Chambers) 55 18-Jul-12 22-Sep-12 79 06-Aug-12 10-Oct-12 21-Oct-12 27-Dec-12 63 0% 0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Conduits in Wall
Install Conduits in Wall
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Chilled Water Pipe Installation & Insulation
Instalaltion of Cable Trays
Floor Drain Fixning
H/L Drainage Pipes Installation
Block Works
Chilled Water Pipe Installation & Insulation
Install Conduits in Wall
Install Cable Trays & Trunking
Block Works
Install Conduits in Wall
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Install Conduits in Wall
Block Works
Floor Screed
Install Handrails
Floor Screed
Install Handrails
Water Proof Membrane
Block Works
MEP Works inside Shafts
Block Works
Install Conduits in Wall
MEP Works inside Shafts
FIC Chambers - RC Works ( 4 Chambers)
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 17 of 17Printed On : 05-Jul-12
Baseline
Actual Work
Remaining Work
Critical ... Project Implementation ScheduleUpdate as of 30-June-12
2 Months Lookahead
Date Revision Chec... Approved
15-Feb-12 Project Implementation Schedule - Rev 00
24-Mar-12 Project Implementation Schedule - Rev 01 11th Apri...
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
7.0 PROCUREMENT LOG
7.1 CIVIL & ARCHITECTURAL LOG
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00Civil and Architectural Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
ActualDays
Origin Method Arrival Custom PlannedExpected‐Actual
Civil Package
Civil Works
1 Water Proofing for Sub-Structure Al Shirawi Contracting Co. LLC 03-Feb-12 03-Feb-12 18-Feb-12 12-Feb-12 19-Feb-12 20-Feb-12 20-Feb-12 21-Feb-12 01-Mar-12 22-Feb-12 2 3 21-Feb-12 24-Feb-12
SPECSSection
MATERIAL DESCRIPTIONSupplier/Subcont.
Decision Material Submittal Submittal Approval Purchase Order N.T.PFabrication and Delivery
PeriodSHIPMENT
Required On Site(Delivery Date)
REMARKS
2 Water Proofing for Wet Area 08-May-12 29-May-12 12-Jun-12 13-Jun-12 23-Jun-12 90 29-Sep-12
3 GRP Lining Aromatic Fiber Glass Factory LLC 01-Jun-12 04-Apr-12 16-Jun-12 18-Apr-12 30-Jun-12 01-May-12 01-Jul-12 11-Jul-12 60 10-Sep-12 C
4 Water Proofing for Roof Al Shirawi Contracting Co. LLC 11-May-12 05-Jun-12 24-Jun-12 19-Jun-12 20-Jun-12 30-Jun-12 100 16-Oct-12
5 Traffic Coating for Parking 24-Aug-12 08-Sep-12 22-Sep-12 23-Sep-12 03-Oct-12 90 10-Jan-13
Architectural PackageWet Works
1 Block (Type.1) Hard Block Factory 27-Feb-12 01-Jan-12 13-Mar-12 09-Jan-12 27-Mar-12 26-Jan-12 28-Mar-12 30-Jan-12 07-Apr-12 01-Feb-12 30 01-May-12 B
2 Block (Type.2) Hard Block Factory 27-Feb-12 24-Mar-12 13-Mar-12 07-Apr-12 27-Mar-12 28-Mar-12 07-Apr-12 30 01-May-12 B/C
3 Block (Type.3) Phoenix 27-Feb-12 08-Apr-12 13-Mar-12 22-Apr-12 27-Mar-12 28-Mar-12 07-Apr-12 30 01-May-12 B/C
4 Plaster Accessories Sodamco 27-Mar-12 02-May-12 11-Apr-12 16-May-12 25-Apr-12 26-May-12 26-Apr-12 06-May-12 30 30-May-12
5 Paint (Internal) National Paint 10-Mar-12 02-May-12 25-Mar-12 16-May-12 08-Apr-12 21-May-12 09-Apr-12 19-Apr-12 60 18-Jun-12 BCeiling Works
G C1 Gypsum Ceiling 21-Mar-12 20-Jun-12 05-Apr-12 19-Apr-12 20-Apr-12 30-Apr-12 90 29-Aug-12
2 Aluminium Ceiling 21-Mar-12 20-Jun-12 05-Apr-12 19-Apr-12 20-Apr-12 30-Apr-12 90 14-Nov-12
3 Fibre Ceiling 21-Mar-12 20-Jun-12 05-Apr-12 19-Apr-12 07-May-12 17-May-12 90 22-Aug-12
4 Metal Ceiling 21-Mar-12 20-Jun-12 05-Apr-12 19-Apr-12 19-May-12 29-May-12 90 03-Sep-12
5 MDF Ceiling 21-Mar-12 20-Jun-12 05-Apr-12 19-Apr-12 24-Jun-12 04-Jul-12 90 08-Oct-12
Wall & Floor Works1 Porcelain Tiles 20-Jul-12 04-Aug-12 18-Aug-12 21-Aug-12 31-Aug-12 69 11-Nov-12
2 Ceramic Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 105 29-Oct-12
3 Natural Stone Tiles 06-Jun-12 21-Jun-12 05-Jul-12 07-Jul-12 17-Jul-12 95 29-Oct-12
4 MDF Cladding 06-Jun-12 21-Jun-12 05-Jul-12 07-Jul-12 17-Jul-12 100 04-Nov-12
5 Granite Tiles 03-Jun-12 18-Jun-12 02-Jul-12 03-Jul-12 13-Jul-12 105 06-Nov-12
6 Carpet Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 95 15-Oct-12
7 Terrazzo Tiles Tarrazzo 20-May-12 04-Jun-12 25-Jun-12 18-Jun-12 19-Jun-12 29-Jun-12 90 03-Oct-12
8 Raised Floor Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 90 09-Oct-12
9 Veneer Cladding 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 110 04-Nov-12
Alshafar Special Material
9 Veneer Cladding 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 110 04-Nov-12
10 Vinyl Sheet 01-Jun-12 16-Jun-12 30-Jun-12 01-Jul-12 11-Jul-12 95 21-Oct-12
11 Wenge Cladding 18-Jun-12 03-Jul-12 17-Jul-12 18-Jul-12 28-Jul-12 95 10-Nov-12
12 Marble Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 105 29-Oct-12
13 Honed Limestone Tiles 01-Jun-12 16-Jun-12 30-Jun-12 01-Jul-12 11-Jul-12 90 15-Oct-12
14 Wooden Tiles 08-Jul-12 23-Jul-12 06-Aug-12 07-Aug-12 17-Aug-12 95 01-Dec-12
15 Polished Moche Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 90 09-Oct-12
16 Mosaic Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 105 29-Oct-12
17 Water Jet Limestone Tiles 26-May-12 10-Jun-12 24-Jun-12 25-Jun-12 05-Jul-12 90 05-Oct-12
18 Precast Conc. Interlocking Paving Hard Block Factory 30-Jun-12 28-Apr-12 15-Jul-12 12-May-12 29-Jul-12 30-Jul-12 09-Aug-12 90 17-Nov-12 B/C19 Precast Conc. Kerbs 30-Jun-12 15-Jul-12 29-Jul-12 30-Jul-12 09-Aug-12 90 17-Nov-12
20 Heavy Duty Tiles 30-Jun-12 15-Jul-12 29-Jul-12 30-Jul-12 09-Aug-12 110 11-Dec-12
21 Vinyl Wall Covering 30-Jun-12 15-Jul-12 29-Jul-12 30-Jul-12 09-Aug-12 100 28-Nov-12
22 Carpet 09-Dec-12 24-Dec-12 07-Jan-13 08-Jan-13 18-Jan-13 98 02-May-13
File :- Material Status Report - Rev 00 Page 1 of 2 Printed On :- 05/07/2012 at 08:09
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00Civil and Architectural Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
ActualDays
Origin Method Arrival Custom PlannedExpected/Actual
Architectural Package
Doors & Ironmongery1 Aluminium Louver Doors 04-Mar-12 19-Mar-12 02-Apr-12 03-Apr-12 13-Apr-12 90 17-Jul-12
SPECSSection
MATERIAL DESCRIPTIONSupplier/Subcont.
Decision Material SubmittalREMARKS
Submittal Approval Purchase Order N.T.PFabrication and Delivery
PeriodSHIPMENT
Required On Site(Delivery Date)
2 Fire Rated Doors Bin Ghurair Trading 04-Mar-12 24-Jun-12 19-Mar-12 02-Apr-12 03-Apr-12 13-Apr-12 90 17-Jul-12 & Pre.Qualif. Was submitted on 24-Jun
3 Glazed Aluminium Doors 01-May-12 16-May-12 30-May-12 31-May-12 10-Jun-12 90 16-Sep-12
4 Ironmongery 14-Aug-12 29-Aug-12 12-Sep-12 13-Sep-12 23-Sep-12 85 25-Dec-12
5 Wooden Doors ASI 06-Jul-12 26-Jun-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 120 29-Dec-12
Others1 Toilets Accessories 30-Jun-12 15-Jul-12 29-Jul-12 30-Jul-12 09-Aug-12 100 28-Nov-12
2 Sky Light 01-Jun-12 16-Jun-12 30-Jun-12 30-Jul-12 09-Aug-12 90 17-Nov-12
3 Mirrors & Glasses 05-Aug-12 20-Aug-12 03-Sep-12 04-Sep-12 14-Sep-12 100 03-Jan-13
4 Wardrobes ASI 06-Jul-12 26-Jun-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 90 22-Nov-12
5 Kitchen Cabinets ASI 12-Jul-12 26-Jun-12 02-Aug-12 16-Aug-12 18-Aug-12 28-Aug-12 90 06-Dec-12
6 GRC 06-Oct-12 21-Oct-12 04-Nov-12 05-Nov-12 15-Nov-12 90 21-Feb-13
7 Vanity Counters ASI 31-Jul-12 26-Jun-12 15-Aug-12 29-Aug-12 30-Aug-12 09-Sep-12 100 29-Dec-12
8 Hump 30-Oct-12 14-Nov-12 28-Nov-12 29-Nov-12 09-Dec-12 80 05-Mar-13
Metal1 Balustrades and Handrails 13-May-12 28-May-12 11-Jun-12 12-Jun-12 22-Jun-12 120 04-Nov-12
2 Sinages 06-Jun-12 21-Jun-12 05-Jul-12 07-Jul-12 17-Jul-12 120 28-Nov-12
Furniture1 Reception Counter 04-Feb-13 19-Feb-13 05-Mar-13 06-Mar-13 16-Mar-13 120 24-Jul-13
2 Furniture 07-Dec-12 22-Dec-12 05-Jan-13 06-Jan-13 16-Jan-13 170 24-Jul-13
Landscaping 1 Soft Landscping Items 06-Jul-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 100 05-Dec-12
2 Landscaping Light 31-Jul-12 15-Aug-12 29-Aug-12 30-Aug-12 09-Sep-12 110 10-Jan-13
Speciality Items1 Curtain Wall&Glazing Alico 01-May-12 16-May-12 20-Jun-12 30-May-12 31-May-12 10-Jun-12 90 16-Sep-12 &
2 Swimming Pool2.1 Finishes Items United Technology 06-Jul-12 02-Mar-12 21-Jul-12 14-Mar-12 04-Aug-12 28-Mar-12 05-Aug-12 15-Aug-12 80 10-Nov-12 B/C
2.2 Water Proofing for Swimming Pool United Technology 06-Jul-12 02-Mar-12 21-Jul-12 14-Mar-12 04-Aug-12 28-Mar-12 05-Aug-12 15-Aug-12 80 10-Nov-12 B/C
2.3 Electrical Items United Technology 06-Jul-12 12-Apr-12 21-Jul-12 26-Apr-12 04-Aug-12 05-Aug-12 15-Aug-12 80 10-Nov-12 C2.3 Electrical Items United Technology 06 Jul 12 12 Apr 12 21 Jul 12 26 Apr 12 04 Aug 12 05 Aug 12 15 Aug 12 80 10 Nov 12 C
2.4 Sand Stone Pavers 06-Jul-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 80 10-Nov-12
2.5 Pocalin for Pool Deck 06-Jul-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 100 05-Dec-12
2.6 Swimming Pool Equipments United Technology 06-Jul-12 12-Apr-12 21-Jul-12 26-Apr-12 04-Aug-12 05-Aug-12 15-Aug-12 120 29-Dec-12 C
3 Façade Cleaning System Danway 12-Aug-12 13-Jun-12 27-Aug-12 10-Sep-12 11-Sep-12 21-Sep-12 110 22-Jan-13 Code B on 26June-2012
4 Irrigation System Green Dunes for Irrigation Works 15-Jul-12 30-Mar-12 14-Aug-12 03-Apr-12 28-Aug-12 29-Aug-12 08-Sep-12 90 16-Dec-12 C
File :- Material Status Report - Rev 00 Page 2 of 2 Printed On :- 05/07/2012 at 08:09
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
7.0 PROCUREMENT LOG
7.2 MEP & SPECIALITY WORKS LOG
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00MEP and Speciality Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
ActualDays
Origin Method Arrival Custom PlannedExpected‐Actual
Mechanical
HVAC Works
1 AHU 11-Mar-12 26-Mar-12 26-Apr-12 09-Apr-12 10-Apr-12 20-Apr-12 110 23-Sep-12 B
Purchase Order N.T.PFabrication and Delivery
PeriodSHIPMENT
Required On Site(Delivery Date)
REMARKSSPECSSection
MATERIAL DESCRIPTIONSupplier/Subcont.
Decision Material Submittal Submittal Approval
2 Air Oulets 15-Apr-12 30-Apr-12 14-May-12 15-May-12 25-May-12 60 24-Jul-12
3 Chilled Pipes Insulation ARMA FLEX 08-May-12 23-May-12 4-Apr-12 06-Jun-12 14-Apr-12 07-Jun-12 17-Jun-12 30 12-Jul-12 B
4 Chilled Water Pipes-Fittings-Valves CRANE 11-Mar-12 26-Mar-12 10-May-12 09-Apr-12 19-May-12 10-Apr-12 20-Apr-12 90 24-Jul-12 B
5 Chiller TRANE 11-Mar-12 26-Mar-12 8-May-12 09-Apr-12 14-Jun-12 10-Apr-12 20-Apr-12 180 11-Nov-12 B
6 Condensate Pipes Insulation ARMA FLEX 02-Jun-12 17-Jun-12 4-Apr-12 01-Jul-12 14-Apr-12 02-Jul-12 12-Jul-12 15 18-Jul-12 B
7 Condensate Pipes-Fittings-Valves 11-Mar-12 26-Mar-12 09-Apr-12 10-Apr-12 20-Apr-12 90 24-Jul-12
8 Ducts Insulation THERMOBREAK 02-Jun-12 17-Jun-12 14-Apr-12 01-Jul-12 29-Apr-12 02-Jul-12 12-Jul-12 15 18-Jul-12 B
9 FAHU 03-Apr-12 18-Apr-12 26-Apr-12 02-May-12 03-May-12 13-May-12 100 04-Oct-12 B
10 FCUs YORK 11-Mar-12 26-Mar-12 20-May-12 09-Apr-12 30-Jun-12 10-Apr-12 20-Apr-12 75 07-Jul-12 &11 Fire and Volume Damper GMAMCO 09-Apr-12 24-Apr-12 4-Apr-12 08-May-12 14-Apr-12 09-May-12 19-May-12 60 18-Jul-12 B
12 Hangers & Supports WEICCO 11-Mar-12 26-Mar-12 19-Apr-12 09-Apr-12 24-May-12 10-Apr-12 20-Apr-12 40 26-May-12 B
13 HAVC Ducts NISSHIN - JAPAN 23-Mar-12 07-Apr-12 27-Feb-12 21-Apr-12 5-Mar-12 22-Apr-12 02-May-12 90 05-Aug-12 B
14 Heat Exchanger (HEX) 19-Aug-12 03-Sep-12 17-Sep-12 18-Sep-12 28-Sep-12 90 06-Jan-13
15 Primary Chilled Water Pump 14-Aug-12 13-Sep-12 27-Sep-12 28-Sep-12 08-Oct-12 90 16-Jan-13
16 Pumps for HEX 25-Aug-12 09-Sep-12 23-Sep-12 24-Sep-12 04-Oct-12 90 12-Jan-13
17 Secpndry Chilled Water Pump 25-Aug-12 09-Sep-12 23-Sep-12 24-Sep-12 04-Oct-12 90 12-Jan-13
18 Variable Frequency Drive 27-Jun-12 18-Jul-12 01-Aug-12 02-Aug-12 12-Aug-12 100 03-Dec-12
19 Ventilation & Exhuast Fans NUAIRE 16-Mar-12 31-Mar-12 17-May-12 14-Apr-12 30-May-12 15-Apr-12 25-Apr-12 90 29-Jul-12
Plumbing
1 GRP Water Tank 25-Jun-12 10-Jul-12 24-Jul-12 25-Jul-12 04-Aug-12 100 24-Nov-12
2 Sanitarywares 20-Aug-12 04-Sep-12 18-Sep-12 19-Sep-12 29-Sep-12 90 07-Jan-13
3 Water Boiler 03-Apr-12 18-Apr-12 02-May-12 03-May-12 13-May-12 90 16-Aug-12
4 Water Boiler Pump 02-Jun-12 17-Jun-12 01-Jul-12 02-Jul-12 12-Jul-12 60 11-Sep-12
5 Water Boiler Tank 08-May-12 23-May-12 06-Jun-12 07-Jun-12 17-Jun-12 90 23-Sep-12
6 Booster Pump 25-Aug-12 09-Sep-12 23-Sep-12 24-Sep-12 04-Oct-12 90 12-Jan-13
7 Floor Drains AQUA 11-Mar-12 26-Mar-12 3-May-12 09-Apr-12 6-Jun-12 10-Apr-12 20-Apr-12 30 14-May-12
PPR Pi Fi i V l (W ) 21 M 12 0 A 12 26 M 12 19 A 12 24 J 12 20 A 12 30 A 12 30 24 M 128 PPR Pipes -Fittings-Valves (Water) 21-Mar-12 05-Apr-12 26-May-12 19-Apr-12 24-Jun-12 20-Apr-12 30-Apr-12 30 24-May-12
9 Steam Pipes for Boilers 21-May-12 05-Jun-12 19-Jun-12 20-Jun-12 30-Jun-12 90 04-Oct-12
10 Sump Pump 23-Mar-12 07-Apr-12 21-Apr-12 22-Apr-12 02-May-12 60 01-Jul-12
11 Transfer Pump 03-Apr-12 18-Apr-12 02-May-12 03-May-12 13-May-12 90 16-Aug-12
12 uPVC Pipes-Fittings-Valves(Drainge) HEPWORTH 27-Apr-12 12-May-12 9-Feb-12 26-May-12 29-Feb-12 27-May-12 06-Jun-12 30 01-Jul-12 B
Fire Fighting
1 Fire Alram Devices 15-Mar-12 05-Apr-12 19-Apr-12 20-Apr-12 30-Apr-12 90 04-Aug-12
2 Fire Extinguishers & Banket AL ARABIA 27-Apr-12 12-May-12 31-Mar-12 26-May-12 4-Apr-12 27-May-12 06-Jun-12 90 11-Sep-12 B
3 Fire Hose Cabinets AL ARABIA 27-Apr-12 12-May-12 31-Mar-12 26-May-12 4-Apr-12 27-May-12 06-Jun-12 90 11-Sep-12 B
4 Fire Pipes-Fittings-Valves WEICCO 11-Mar-12 26-Mar-12 29-Mar-12 09-Apr-12 8-Apr-12 10-Apr-12 20-Apr-12 90 24-Jul-12 B
5 Fire Pump PEERLESS 23-Mar-12 07-Apr-12 28-Apr-12 21-Apr-12 8-May-12 22-Apr-12 02-May-12 130 23-Sep-12 B
6 FM 200 System 15-Mar-12 05-Apr-12 20-May-12 19-Apr-12 6-Jun-12 20-Apr-12 30-Apr-12 90 04-Aug-12
7 Foam Spary System for Generators AL ARABIA 21-May-12 05-Jun-12 31-Mar-12 19-Jun-12 15-Apr-12 20-Jun-12 30-Jun-12 60 30-Aug-12 B
8 Landing Valves 15-Apr-12 30-Apr-12 14-May-12 15-May-12 25-May-12 90 30-Aug-12
9 Sprinklers AL ARABIA 11-Mar-12 26-Mar-12 31-Mar-12 09-Apr-12 4-Apr-12 10-Apr-12 20-Apr-12 90 24-Jul-12 B
LPG System
1 LPG Pipes-Fittings-Valves GULF GAS 08-May-12 23-May-12 24-May-12 06-Jun-12 06-Jun-12 07-Jun-12 17-Jun-12 60 16-Aug-12
File :- Material Status Report - Rev 00 Page 1 of 2 Printed On :- 05/07/2012 at 08:09
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00MEP and Speciality Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
2 LPG Tanks( 2000 Gallons) GULF GAS 31-Aug-12 15-Sep-12 24-May-12 29-Sep-12 06-Jun-12 30-Sep-12 10-Oct-12 30 05-Nov-12
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
ActualDays
Origin Method Arrival Custom PlannedExpected‐Actual
Mechanical
LPG System
Fabrication and Delivery Period
SHIPMENTRequired On Site(Delivery Date)
REMARKSSPECSSection
MATERIAL DESCRIPTIONSupplier/Subcont.
Decision Material Submittal Submittal Approval Purchase Order N.T.P
1 Water Deluge System GULF GAS 13-Jul-12 28-Jul-12 11-Aug-12 12-Aug-12 22-Aug-12 80 18-Nov-12
Elevators
1 Brakets,Guide Rails and Others 07-May-12 05-Mar-12 22-May-12 22-Mar-12 05-Jun-12 06-Jun-12 16-Jun-12 100 03-Oct-12
2 Passenger Lifts 07-May-12 05-Mar-12 22-May-12 22-Mar-12 05-Jun-12 06-Jun-12 16-Jun-12 120 22-Jan-13
ElectricalCable Trays - Cables
1 Bus Bars 09-Aug-12 08-Sep-12 22-Sep-12 23-Sep-12 03-Oct-12 100 22-Jan-13
2 Cable Trays CLIPSAL 12-Mar-12 11-Apr-12 14-May-12 25-Apr-12 06-Jun-12 26-Apr-12 06-May-12 45 18-Jun-12
3 LV Cable 09-Aug-12 08-Sep-12 22-Sep-12 23-Sep-12 03-Oct-12 35 04-Nov-12
4 Trunking CLIPSAL 18-Mar-12 17-Apr-12 14-May-12 01-May-12 06-Jun-12 02-May-12 12-May-12 45 24-Jun-12
Low Current System1 Access Control System 12-Mar-12 11-Apr-12 02-Jun-12 25-Apr-12 26-Apr-12 06-May-12 90 09-Oct-12
2 BMS SAUTER 12-Mar-12 11-Apr-12 27-May-12 25-Apr-12 26-Apr-12 06-May-12 70 29-Jul-12
3 CCTV System SIS 12 Mar 12 11 Apr 12 24 May 12 25 Apr 12 12 Jun 12 26 Apr 12 06 May 12 90 22 Sep 12
Schindler B/C
3 CCTV System SIS 12-Mar-12 11-Apr-12 24-May-12 25-Apr-12 12-Jun-12 26-Apr-12 06-May-12 90 22-Sep-12
4 Central Battery System BAHRI & MAZROUI 12-Mar-12 11-Apr-12 25-Apr-12 26-Apr-12 06-May-12 90 16-Sep-12
5 GSM System 12-Mar-12 11-Apr-12 23-May-12 25-Apr-12 26-Apr-12 06-May-12 90 09-Aug-12
6 MATV/ Interactive TV System 12-Mar-12 11-Apr-12 26-May-12 25-Apr-12 26-Apr-12 06-May-12 60 05-Jul-12
Electrical Equipments1 DBs 08-Aug-12 23-Aug-12 4-Jun-12 06-Sep-12 07-Sep-12 17-Sep-12 78 11-Dec-12
2 Electrical Heaters ZENITH 27-Apr-12 12-May-12 21-May-12 26-May-12 2-Jun-12 27-May-12 06-Jun-12 30 01-Jul-12
3 Generators CATERPILLAR 16-Apr-12 16-May-12 30-May-12 31-May-12 10-Jun-12 120 04-Nov-12
4 MDBs 09-Aug-12 08-Sep-12 4-Jun-12 22-Sep-12 23-Sep-12 03-Oct-12 110 04-Feb-13
5 SMDBs 09-Aug-12 08-Sep-12 4-Jun-12 22-Sep-12 23-Sep-12 03-Oct-12 110 04-Feb-13
6 Telephone System 12-Mar-12 11-Apr-12 26-May-12 25-Apr-12 26-Apr-12 06-May-12 60 27-Sep-12
7 UPS 12-Mar-12 11-Apr-12 25-Apr-12 26-Apr-12 06-May-12 60 27-Sep-12
Others1 Conduits and PVC Ducts MK-SAUDI EGA 10-Mar-12 25-Mar-12 16-Jan-12 08-Apr-12 29-Jan-12 09-Apr-12 19-Apr-12 40 24-May-12 B
2 Earthing & Lighting TECTRONICS 18-Jan-12 02-Feb-12 18-May-12 16-Feb-12 20-May-12 17-Feb-12 27-Feb-12 7 25-Feb-12 B2 Earthing & Lighting TECTRONICS 18 Jan 12 02 Feb 12 18 May 12 16 Feb 12 20 May 12 17 Feb 12 27 Feb 12 7 25 Feb 12 B
3 Light Fixtures 01-Jul-12 31-Jul-12 14-Aug-12 15-Aug-12 25-Aug-12 70 08-Nov-12
Speciality Works
Garbage Chute 1 Equipments Mohammed Tayyeb Khoory 19-Apr-12 18-Jun-12 19-May-12 02-Jun-12 03-Jun-12 13-Jun-12 150 01-Dec-12 & submitted on 18-June
2 Garbage Chutes 28-Apr-12 02-Jun-12 16-Jun-12 17-Jun-12 27-Jun-12 150 16-Dec-12
3 Pipes & Fittings 10-Apr-12 10-May-12 24-May-12 25-May-12 04-Jun-12 100 22-Sep-12
Linen Chute1 Equipments Mohammed Tayyeb Khoory 25-May-12 18-Jun-12 24-Jun-12 08-Jul-12 09-Jul-12 19-Jul-12 150 07-Mar-13 & submitted on 18-June
2 Linen Chutes 03-Jun-12 08-Jul-12 22-Jul-12 23-Jul-12 02-Aug-12 150 21-Jan-13
3 Pipes & Fittings 01-Jun-12 16-Jun-12 30-Jun-12 01-Jul-12 11-Jul-12 100 23-Dec-12
File :- Material Status Report - Rev 00 Page 2 of 2 Printed On :- 05/07/2012 at 08:09
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
8.0 ENGINEERING LOG
8.1 CIVIL - ARCHITECTURAL – SPECIALITY – PS LOG
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OT
B-SHOP DRAWINGS . . . . .
B.1- Civil Shop DrawingsB.1.1- General
Program Activity C General Excavation Level X 15-Feb-12 16-Feb-12 8-Jan-12 22-Feb-12 B Closed
Program Activity C General Water Proofing Details X 18-Feb-12 20-Feb-12 20-Jan-12 22-Mar-12 B Closed
Program Activity C General Raft Construction Joint Layout X 18-Feb-12 20-Feb-12 24-Jan-12 10-Mar-12 B Closed
Program Activity C General Retaining Wall Joint Layout X 19-Feb-12 6-Mar-12 20-Jan-12 18-Mar-12 B Closed
Program Activity C General Tower Crane Layout X 25-Feb-12 14-Mar-12 5-Jan-12 19-Feb-12 B Closed
B.1.2- Hotel Apartements (Block A)Deep Foundation
C Block A Structural Dwgs. for Raft X 18-Feb-12 23-Feb-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block A Structural Dwgs. for Ret. Walls -Columns X 21-Feb-12 6-Mar-12 23-Jan-12 26-Jan-12 B Closed
269-S-RF-CL-009 C Block A Columns Reinforcement From 2nd Basement to 1st Basement X 23-Jan-12 26-Jan-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 25-Feb-12 8-Mar-12 1-Feb-12 29-Feb-12 B Closed
269-S-GE-FW-26 C Block A Core wall (CW1) formwork – Block (A) X 1-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-CW-021 C Block A Core wall reinforcement CW1 From 2nd Basement to 1st Basement X 5-Feb-12 14-Feb-12 B Closed
Program Activity C Block A Structural Dwgs. for Ramp X 21-Feb-12 12-Mar-12 8-Feb-12 10-Mar-12 B Closed
269-S-BB-RP-017 C Block A Ramp Reinforcement – Block (A) From 2nd Basement to 1st Basement X 8-Feb-12 10-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 26-Feb-12 15-Mar-12 20-Feb-12 18-Mar-12 B Closed
Notes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
g y
269-S-GN-CD-029 C Block A Concrete dimension for slab at 1st Basement Slab - Block (A) X 20-Feb-12 18-Mar-12 B Closed
269-S-RE-B1-042 C Block A 1st Basement slab reinforcement and details - Block (A) X 26-Feb-12 10-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 7-Apr-12 25-Apr-12 12-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
Ground Floor Slab
Program Activity C Block A Structural Dwgs. for Ret. Walls -Columns X 24-Mar-12 11-Apr-12 10-Mar-12 22-Mar-12 B Closed
269-S-RF-CL-049 C Block A Columns Reinforcement - Block (A) Form 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
269-S-GE-R-RW-0059 C Block A Retaining Wall Reinforcement From 1st Basement to Ground Floor Plan & X 12-Mar-12 22-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 24-Mar-12 11-Apr-12 10-Mar-12 19-Mar-12 B Closed
269-S-BA-CW-053 C Block A Core Wall Reinforcement - (CW1) Form 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 31-Mar-12 16-Apr-12 25-Jan-12 27-Mar-12 B Closed
269-S-BA-CD-054 C Block A Concrete Dimension for Slab & Beam at Ground Floor - Block - A X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-B1-062 C Block A Shop Drawing for Ground Floor Slab Reinforcement and Details X 15-Mar-12 27-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Ramp X 31-Mar-12 17-Apr-12 25-Jan-12 19-Mar-12 B Closed
269-S-BA-RMP-013 C Block A Ramp Concrete Dimension From 1st Basement to Ground Floor X 25-Jan-12 8-Mar-12 B Closed
269-S-BA-RP-056 C Block A Ramp reinforcement - Block (A) 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 7-May-12 27-May-12 12-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
1st Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 8-Apr-12 26-Apr-12 25-Feb-12 5-Apr-12 B Closed
269-S-BA-CL-44 C Block A Ground Floor Columns Layout Block - A X 25-Feb-12 22-Mar-12 B Closed269 S BA CL 44 y
S-RF-CL-072 C Block A Shop drawing for Column reinforcement ground floor to first floor Block X 25-Mar-12 5-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 8-Apr-12 26-Apr-12 14-Mar-12 27-Mar-12 B Closed
269-S-BA-ST-CW-067 C Block A Shop Drawing for Core Wall Reinforcement CW1 – Ground to First Floor X 14-Mar-12 27-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 22-Apr-12 10-May-12 8-Apr-12 2-May-12 B Closed
269-S-RE-FF-087 C Block A Shop drawing for 1st Floor Slab Reinforcement and Details (Block A) X 9-Apr-12 2-May-12 B Closed
269-S-BA-CL-092 C Block A Shop drawing for Concrete Dimension for Slab & Beam at 1st Floor X 8-Apr-12 2-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 21-May-12 10-Jun-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
2nd Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 25-Apr-12 15-May-12 14-Mar-12 19-Apr-12 B Closed
269-S-RF-CL-083 C Block A Shop dwg. for Column Reinforcement from 01st Floor to 02nd Floor X 7-Apr-12 19-Apr-12 B Closed
269-S-BB-CL-061 C Block A Shop Drawing for Column Layout at Fist Floor Block- A X 14-Mar-12 11-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 6-May-12 24-May-12 10-Mar-12 19-Mar-12 B Closed
C Block A
C Block A
Program Activity C Block A Structural Dwgs. for Slab X 20-May-12 7-Jun-12 21-Apr-12 22-May-12 B Closed
269-S-RE-SF-106 C Block A Shop drawing for 02nd Floor Slab Reinforcement and Details X 23-Apr-12 22-May-12 B Closed
269-S-BA-CD-110 C Block A Shop drawing for Concrete Dimension for Slab and Beam at 02 Floor X 21-Apr-12 22-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 17-Jun-12 5-Jul-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed269-S-BA-ST-30 C Block A Concrete dimension for stair case S1 X 12 Feb 12 29 Feb 12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - S1 X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
269-S-BA-ST C Block A Shop drawing for Concrete Dimension for Staircase – S8 X 26-Mar-12 7-Apr-12 B Closed
269-S-RE-SR-84 C Block A Shop drawing for Rein forcement Details for staircase – S 8 X 1-Apr-12 11-Apr-12 B Closed
3rd & 4th Floor Slab
File : -Engineering Tracking Chart - Rev 00 1 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity C Block A Structural Dwgs. for Columns X 23-May-12 12-Jun-12 1-Apr-12 22-May-12 B Closed
269-S-BA-CL--082 C Block A Shop drawing for Column Layout (2nd Floor) - Block- (A) X 1-Apr-12 11-Apr-12 B Closed
269-S-BB-CL-096 C Block A Shop drawing for Column Layout @ Third Floor Block A X 9-Apr-12 2-May-12 B Closed
269-S-RF-CL-109 C Block A Shop drawing for Column Reinforcement Block A, 2nd to 3rd Floor X 21-Apr-12 2-May-12 B Closed
269-S-RF-CL-110 C Block A Shop drawing for Column Reinforcement 03rd to 04th Floor – Block “A” 21-Apr-12 22-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 23-May-12 12-Jun-12 22-Apr-12 2-May-12 B Closed
269-S-BA-CW-111 C Block A Shop drawing for Core Wall Reinforcement (CW1) from 02nd to 3rd Floor X 22-Apr-12 2-May-12 B Closed
269-S-BA-ST-CW-112 C Block A Shop drawing for Core Wall Reinforcement (CW1) from 03rd to 04th X 23-Apr-12 2-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 17-Jun-12 5-Jul-12 26-Apr-12 13-Jun-12 B Closed &
269-S-BA-CD-114 2 C Block A Shop drawing for Concrete Dimension for Slab & Beam at 03rd Floor - X 26-Apr-12 12-Jun-12 B Closed &
269-S-RE-SF-129 C Block A Shop Drawing for 3rd Floor Slab Reinforcement and Details X 6-May-12 17-May-12 B Closed
269-S-RE-FF-151 0 C Block A Shop Drawing For 4th Floor Slab Reinforcement Details – Block “A" X 7-Jun-12 12-Jun-12 B Closed &
269-S-BA-CD-117 2 C Block A Shop drawing for Concrete Dimension for slab & Beam at 04th Floor X 26-Apr-12 13-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Staircase X 14-Jul-12 1-Aug-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
5th & 6th Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 7-Jul-12 25-Jul-12 19-Apr-12 26-Jun-12 B Closed &
269-S-BA-CL-103 C Block A Shop drawing for Column Layout @ Fourth (4th) Floor Block-A X 19-Apr-12 17-May-12 B Closed269 S BA CL 103 C Block A Shop drawing for Column Layout @ Fourth (4th) Floor Block A p y C osed
269-S-BA-CL-119 C Block A Shop drawing for Column / Core Wall Layout at 05th Floor X 29-Apr-12 13-May-12 B Closed
269-S-RE-CL-161 1 C Block A Shop Drawing for Column Reinforcement 4th Floor to 5th Floor Block- A X 12-Jun-12 16-Jun-12 B Closed &
269-S-RF-CL-170 1 C Block A Shop drawing for Column Reinforcement 05th to 06th Floor – Block “A” 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 7-Jul-12 25-Jul-12 29-Apr-12 Opened
269-S-BA-CL-119 C Block A Shop drawing for Column / Core Wall Layout at 05th Floor X 29-Apr-12 13-May-12 B Closed
269-S-BA-CW-179 C Block A Shop Drawing for Core Wall (CW1) Reinforcement from 05th to 06th X 18-Jun-12 26-Jun-12 B Closed &
269-S-BA-ST-CW-166 C Block A Shop Drawing For Core wall (CW1) Reinforcement 4th Floor to 5th floor X 13-Jun-12 25-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Slab X 23-Jul-12 12-Aug-12 11-Jun-12
269-S-RE-5F-164 0 C Block A Shop Drawing for 5th floor Slab Reinforcement Details Block – “A” X 13-Jun-12 25-Jun-12 B Closed &
269-S-RE-6F-165 0 C Block A Shop Drawing for 6th floor Slab Reinforcement Details Block – “A” X 13-Jun-12 25-Jun-12 B Closed &
269-S-BA-CD-163 1 C Block A Shop Drawing for Concrete Dimension for Slab & Beam at 6th Floor - X 12-Jun-12 UR Opened &
269-S-BA-CD-156 C Block A Shop Drawing For Concrete Dimension for Slab & Beam at 5th Floor - X 11-Jun-12 UR Opened &
Program Activity C Block A Structural Dwgs. for Staircase X 25-Aug-12 12-Sep-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
7th Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 4-Aug-12 26-Aug-12 11-Jun-12 28-Jun-12 B Closed &
269-S-RF-CL-171 C Block A Shop Drawing for Column Reinforcement from 06th to 07th Floor – Block 18-Jun-12 28-Jun-12 B Closed &
269-S-BA-CL-157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 4-Aug-12 26-Aug-12 11-Jun-12
269 S BA CL 157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &269-S-BA-CL-157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11 Jun 12 25 Jun 12 B Closed &
Program Activity C Block A Structural Dwgs. for Slab X 28-Aug-12 17-Sep-12 24-Jun-12 &
269-S-BA-CD-186 C Block A Shop Drawing for Concrete Dimension for Slab & Beam at 7th Floor 24-Jun-12 UR Opened &
269-S-RE-7F-187 C Block A Shop Drawing for 7th Floor Slab Reinforcement and Details 25-Jun-12 UR Opened &
Program Activity C Block A Structural Dwgs. for Staircase X 15-Sep-12 3-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
Roof Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 26-Aug-12 13-Sep-12 18-Jun-12
269-S-BA-CL-172 C Block A Shop drawing for Column / Core wall Layout at 7th Floor – Block “A” X 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 26-Aug-12 13-Sep-12 18-Jun-12
269-S-BA-CL-172 C Block A Shop drawing for Column / Core wall Layout at 7th Floor – Block “A” X 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Staircase X 12-Sep-12 2-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 16-Sep-12 4-Oct-12
Program Activity C Block A Structural Dwgs. for Chillers Foundations X 18-Sep-12 8-Oct-12
Program Activity C Block A Structural Dwgs. for Parapets X 29-Sep-12 17-Oct-12
Upper Roof Floor Slab
P A ti it C Block A Structural Dwgs for Columns X 12 Sep 12 2 Oct 12Program Activity C Block A Structural Dwgs. for Columns X 12-Sep-12 2-Oct-12
Program Activity C Block A Structural Dwgs. for Slab X 22-Sep-12 10-Oct-12
Program Activity C Block A Structural Dwgs. for Staircase X 1-Oct-12 21-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
B.1.3- Hotel (Block B)Deep Foundation
File : -Engineering Tracking Chart - Rev 00 2 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
C Block B Structural Dwgs. for Raft X 18-Feb-12 7-Mar-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block B Structural Dwgs. for Ret. Walls -Columns X 12-Mar-12 29-Mar-12 23-Jan-12 26-Jan-12 B Closed
269-S-RF-CL-010 C Block B Columns Reinforcement (Block-B) From 2nd Basement to 1st Basement X 23-Jan-12 26-Jan-12 B Closed
Program Activity C Block B Structural Dwgs. for Water Tank X 12-Mar-12 1-Apr-12 20-Feb-12 10-Mar-12 B Closed
269-S-GEN-ST-WT-025 C Block B 2nd Basement water tank reinforcement and details – Block (B&C) X 26-Feb-12 10-Mar-12 B Closed
269-S-GN-FW-40 C Block B Water Tank no. (2&3) formwork Block -B X 20-Feb-12 25-Feb-12 B Closed
Program Activity C Block B Structural Dwgs. for Ramp X 24-Mar-12 11-Apr-12 8-Feb-12 28-Mar-12 B Closed
269-S-BB-RP-018 C Block B Ramp Reinforcement – Block (B) From 2nd Basement to 1st Basement X 8-Feb-12 28-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 8-Apr-12 26-Apr-12 5-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-CW-022 C Block B Core wall reinforcement CW 5,6 &7 Block (B) X 5-Feb-12 14-Feb-12 B Closed
269-S-GN-FW-39 C Block B Core wall (CW5, CW6, CW7) formwork, Block -B X 20-Feb-12 29-Feb-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 24-Apr-12 14-May-12 20-Feb-12 31-Mar-12 B Closed
269-S-GN-CD-037 C Block B Concrete dimension for slab at 1st Basement– Block (B) X 20-Feb-12 20-Mar-12 B Closed
269-S-RE-B1-048 C Block B 1st Basement Slab Reinforcement and details - Block (B) X 1-Mar-12 31-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 28-May-12 18-Jun-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B ClosedS S ,
Ground Floor Slab
Program Activity C Block B Structural Dwgs. for Ret. Walls -Columns X 6-May-12 24-May-12 18-Mar-12 1-May-12 B Closed
269-S-RF-CL-070 C Block B Shop Drawing for Column Reinforcement 1st Basement to Ground floor - X 18-Mar-12 28-Mar-12 B Closed
269-S-GE-R-RW-0081 C Block B Shop drawing for Retaining Wall Reinf.t from 1st Basement to Ground X 28-Mar-12 1-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Ramp X 6-May-12 24-May-12 7-Apr-12 21-Apr-12 B Closed
269-S-BB-RP-089 C Block B Shop drawing for Ramp Reinforcement from 01st Basement to Ground X 7-Apr-12 21-Apr-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 21-May-12 10-Jun-12 1-Apr-12 1-May-12 B Closed
269-S-BB-ST-CW-073 C Block B Shop drawing for Core Wall Reinforcement CW 5, 6 & 7 from 1st X 1-Apr-12 1-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 29-May-12 19-Jun-12 26-Mar-12 26-Apr-12 B Closed
269-S-RE-GF-099 C Block B Shop Drawing for Ground Floor Slab Reinforcement and Details X 12-Apr-12 26-Apr-12 B Closed
269-S-BC-CD-076 C Block B Shop Drawing for Concrete Dimension for Slab and Beam at Ground Floor X 26-Mar-12 7-Apr-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 7-Jul-12 25-Jul-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
1st Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 2-Jun-12 21-Jun-12 25-Feb-12 24-May-12 B Closed
269-S-BA-CL-45 C Block B Ground Floor Columns Layout Block - B X 25-Feb-12 22-Mar-12 B Closed
269-S-RF-CL-122 C Block B Shop drawing for Column Reinforcement from Ground Floor to 01st Floor X 30-Apr-12 24-May-12 B CLosed
Program Activity C Block B Structural Dwgs. for Core Walls X 13-Jun-12 4-Jul-12 2-May-12 14-May-12 B Closed
269-S-BB-ST-CW-123 C Block B Shop drawing for Core Wall Reinforcement CW5 & 6 from Ground Floor X 2-May-12 14-May-12 B Closed269 S BB ST CW 123 C Block B S p g C W CW & G y y B Closed
Program Activity C Block B Structural Dwgs. for Slab X 1-Jul-12 19-Jul-12 5-May-12 16-Jun-12 B Closed &
269-S-BA-CD-128 3 C Block B Shop Drawing for Concrete Dimension for Slab & Beam at 1st Floor X 5-May-12 16-Jun-12 B Closed &
269-S-RE-GF-131 0 C Block B Shop Drawing for 1st Floor Reinforcement and Details – Block - B X 23-May-12 31-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 11-Aug-12 2-Sep-12 20-Feb-12 16-Jun-12 B Closed &
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
269-S-BA-ST-142 0 C Block B Shop Drawing for Concrete Dimension for Staircase from Ground Floor to X 3-Jun-12 16-Jun-12 B Closed &
269-S-RE-SR-143 0 C Block B Shop Drawing for Reinforcement Details for Stair case (Grid-20-22/J-K) X 2-Jun-12 12-Jun-12 B Closed &
2nd Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 27-Jun-12 17-Jul-12 14-Mar-12 4-Jun-12 B Closed
269-S-BB-CL--065 C Block B Shop Drawing for Column Layout at Fist Floor Block- B X 14-Mar-12 11-Apr-12 B Closed
269-S-RF-CL-136 0 C Block B Shop Drawing For column Reinforcement from 1st floor to 2nd floor – X 30-May-12 4-Jun-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 8-Jul-12 26-Jul-12 24-May-12 4-Jun-12 B Closed
269-S-BB-ST-CW-13 0 C Block B Shop Drawing for Corewall Reinforcement (CW5, CW6 & CW7) from 1st X 24-May-12 4-Jun-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 23-Jul-12 12-Aug-12 23-May-12 21-Jun-12 B Closed &
269-S-BA-CD-137 1 C Block B Shop Drawing for 2nd Floor Concrete Dimension for Slab & Beam – X 23-May-12 16-Jun-12 B Closed &
269-S-RE-GF-138 0 C Block B Shop Drawing For 2nd Floor Slab Reinforcement Details – Block “B” X 7-Jun-12 21-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 16-Sep-12 4-Oct-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269 S BB ST 033 C Block B Concrete dimension for stair case S3 Block B X 20-Feb-12 29-Feb-12 B Closed269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
3rd & 4th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 25-Jul-12 14-Aug-12 8-Apr-12 16-Jun-12 B Closed &
269-S-BB-CL-094 C Block B Shop drawing for Column Layout @ Second Floor - Block-B X 8-Apr-12 1-May-12 B Closed
File : -Engineering Tracking Chart - Rev 00 3 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
269-S-BB-CL-097 C Block B Shop drawing for Column Layout @ Third Floor Block B X 9-Apr-12 19-Apr-12 B Closed
269-S-RF-CL-147 0 C Block B Shop Drawing For column Reinforcement from 3rd floor to 4th floor – 7-Jun-12 16-Jun-12 B Closed &
269-S-RF-CL-146 0 C Block B Shop Drawing For column Reinforcement from 2nd floor to 3rd floor – 7-Jun-12 16-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Core Walls X 31-Jul-12 22-Aug-12 11-Jun-12
269-S-BB-ST-CW-153 Shop Drawing for Core wall Reinforcement (CW5&CW6) from 2nd to 3rd 11-Jun-12 23-Jun-12 B Closed &
269-S-BB-ST-CW-154 Shop Drawing for Core wall Reinforcement (CW5&CW6) from 3rd to 4th 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Slab X 13-Aug-12 4-Sep-12
269-S-BA-CD-178 C Block B Shop Drawing for Concrete Dimension for Slab & Beam at 4th Floor – 19-Jun-12 UR Opened &
269-S-RE-4F-184 C Block B Shop Drawing for 4th Floor Slab Reinforcement and Details 20-Jun-12 UR Opened &
269-S-BA-CD-169 C Block B Shop Drawing for Concrete Dimension Slab & Beam at 3rd Floor Block – 14-Jun-12 30-Jun-12 B Closed &
269-S-RE-3F-168 C Block B Shop drawing for 03rd Floor Slab Reinforcement and Details – Block “B” 18-Jun-12 28-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 8-Oct-12 29-Oct-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
5th & 6th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 22-Aug-12 11-Sep-12 19-Apr-12 Opened
269-S-BB-CL-104 1 C Block B Shop drawing for Column Layout @ Fourth (4th) Floor Block-B X 19-Apr-12 17-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 29-Aug-12 18-Sep-12 29-Apr-12 Openedg y g p
269-S-BA-CL-120 C Block B Shop drawing for Column / Core Wall Layout at 05th Floor - Block “B” X 29-Apr-12 13-May-12 B CLosed
269-S-BB-ST-CW-190 C Block B Shop Drawing for Core Wall (CW5, CW6&CW7) Reinforcement from 26-Jun-12 UR Opened &
Program Activity C Block B Structural Dwgs. for Slab X 19-Sep-12 9-Oct-12 26-Jun-12
269-S-RE-6F-195 Shop Drawing for 6th Floor Slab Reinforcement and Details - Block “B” 30-Jun-12 UR Opened &
269-S-BA-CD-197 Shop Drawing for Concrete Dimension for Slab & Beam at 6th Floor - 30-Jun-12 UR Opened &
269-S-RE-5F-189 Shop Drawing for 5th Floor Slab Reinforcement and Details– Block “B” 26-Jun-12 UR Opened &
269-S-BA-CD-191 Shop Drawing for Concrete Dimension for Slab & Beam at 5th Floor 26-Jun-12 UR Opened &
Program Activity C Block B Structural Dwgs. for Staircase X 13-Nov-12 5-Dec-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
7th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 22-Sep-12 10-Oct-12
Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Core Walls X 29-Sep-12 17-Oct-12
Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Slab X 23-Oct-12 13-Nov-12
Program Activity C Block B Structural Dwgs. for Staircase X 25-Dec-12 15-Jan-13 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed269 S RE SR 55 C Block B Stair case reinforcement no. (3) Block (B) B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
Roof Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 10-Oct-12 31-Oct-12 18-Jun-12
269-S-BB-CL-173 Shop drawing for Column / Core wall Layout at 7th Floor – Block “B” 18-Jun-12 27-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 4-Nov-12 25-Nov-12 20-Feb-12 17-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 10-Nov-12 29-Nov-12
Program Activity C Block B Structural Dwgs. for Chillers Foundations X 19-Nov-12 10-Dec-12
Program Activity C Block B Structural Dwgs. for Parapets X 13-Jan-13 22-Jan-13
Upper Roof Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 18-Nov-12 9-Dec-12
Program Activity C Block B Structural Dwgs. for Slab X 28-Nov-12 19-Dec-12
B.1.4- Residential (Block C)Deep Foundation
Program Activity C Block C Structural Dwgs. for Raft X 18-Feb-12 23-Feb-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block C Structural Dwgs. for Ret. Walls -Columns X 17-Mar-12 4-Apr-12 24-Jan-12 31-Jan-12 B Closed
269-S-RF-CL-011 C Block C Columns Reinforcement (Block-C) From 2nd Basement to 1st Basement X 24-Jan-12 31-Jan-12 B Closed
Program Activity C Block C Structural Dwgs. for Water Tank X 17-Mar-12 4-Apr-12 5-Feb-12 10-Mar-12 B Closed
269 S GEN ST WT 025 C Block C 2nd Basement water tank reinforcement and details Block (B&C) X 5-Feb-12 10-Mar-12 B Closed269-S-GEN-ST-WT-025 C Block C 2nd Basement water tank reinforcement and details – Block (B&C) X 5-Feb-12 10-Mar-12 B Closed
269-S-GN-FW-32 C Block C Formwork for Water tank – Block C. X 13-Feb-12 22-Feb-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 10-Apr-12 30-Apr-12 5-Feb-12 21-Feb-12 B Closed
269-S-BC-ST-CW-023 C Block C Core wall reinforcement CW 8&9&10&11 Block (C) X 5-Feb-12 14-Feb-12 B Closed
269-S-GN-FW-31 C Block C Formwork for core walls (CW8, CW9, CW10, CW11) – Block C. X 13-Feb-12 21-Feb-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 17-Apr-12 7-May-12 20-Feb-12 22-Mar-12 B Closed
269-S-RE-B1-047 C Block C 1st Basement Slab Reinforcement - Block (C ) X 1-Mar-12 22-Mar-12 B Closed
File : -Engineering Tracking Chart - Rev 00 4 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
269-S-GN-CD-038 C Block C Concrete dimension for slab at 1st Basement– Block (C ) X 20-Feb-12 18-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Staircase X 16-May-12 5-Jun-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
Ground Floor Slab
Program Activity C Block C Structural Dwgs. for Ret. Walls -Columns X 22-Apr-12 10-May-12 12-Mar-12 29-Mar-12 B Closed
269-S-RF-CL-057 C Block C Column Reinforcement for 1st Basement to Ground floor - Block - C 12-Mar-12 22-Mar-12 B Closed
269-S-GE-R-RW-071 C Block C Shop Drawing for Retaining Wall Rein. from 1ST Basement to Ground 18-Mar-12 29-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 6-May-12 24-May-12 14-Mar-12 27-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Core Wall Reinf. from 1st Bas. to Ground Floor CW 8, 14-Mar-12 27-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 23-May-12 12-Jun-12 18-Mar-12 11-Apr-12 B Closed
S-RE-GF-074 C Block C Shop drawing for ground floor slab reinforcement details Block - C 25-Mar-12 5-Apr-12 B Closed
269-S-G-CJ-068 C Block C Shop Drawing for Concrete Dimension for Slab & Beam at Ground Floor 18-Mar-12 11-Apr-12 B Closed
Program Activity C Block C Structural Dwgs. for Staircase X 10-Jun-12 1-Jul-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B ClosedS CW ( )
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
1st Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 23-May-12 12-Jun-12 25-Mar-12 7-Apr-12 B Closed
269-S-BA-CL-46 C Block C Ground Floor Columns Layout Block - C 25-Feb-12 26-Mar-12 B Closed
269- S-RF-CL-075 C Block C Shop drawing for column reinforcement Ground floor to 1st floor. Block- 25-Mar-12 7-Apr-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 2-Jun-12 21-Jun-12 28-Mar-12 8-Apr-12 B Closed
269-S-BC-ST-CW-078 C Block C Shop drawing for Core Wall Reinforcement CW 8 & 9 from Ground to 28-Mar-12 8-Apr-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 17-Jun-12 5-Jul-12 18-Apr-12 26-May-12 B Closed
269-S-BA-CD-102 C Block C Shop drawing for concrete dimension for slab & Beam at 1st floor. Block - 18-Apr-12 22-May-12 B Closed
269-S-RE-FF-116 C Block C Shop drawing for Slab Reinforcement and Details at First Floor - Block 26-Apr-12 26-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Staircase X 15-Jul-12 2-Aug-12 18-Feb-12 11-Apr-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
269-S-BA-ST-080 C Block C Shop drawing for Concrete Dimension for Staircase – S7 X 18-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-85 C Block C Shop drawing for Rein forcement Details for staircase – S 7 X 1-Apr-12 11-Apr-12 B Closed
2nd Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 17-Jun-12 5-Jul-12 17-Apr-12 1-May-12 B Closed
269-S-RF-CL-093 C Block C Shop drawing for Column Reinforcement Block-C from 1st Floor to 2nd X 17-Apr-12 1-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 17-Jun-12 5-Jul-12 17-Apr-12 1-May-12 B Closed
269-S-BA-ST-CW-086 C Block C Shop drawing for Core Wall Reinforcement CW1 – First Floor to Second X 17-Apr-12 1-May-12 B Closed269 S BA ST CW 086 C Block C S p g C W CW S p y B Closed
269-S-BC-ST-CW-091 C Block C Shop drawing for core wall reinforcement CW 8,CW9,CW10 from 1st to X 17-Apr-12 1-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 3-Jul-12 23-Jul-12 23-Apr-12 19-Jun-12 B Closed &
269-S-BA-CD-113 C Block C Shop drawing for Concrete Dimension for Slab & Beam at 02nd Floor - X 23-Apr-12 9-Jun-12 B Closed
269-S-RE-SF-145 C Block C Shop Drawing for 2nd Floor Slab Reinforcement Details – Block “C” X 11-Jun-12 19-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Staircase X 7-Aug-12 29-Aug-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
3rd & 4th Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 4-Jul-12 24-Jul-12 8-Apr-12 Opened
269-S-BC-CL-095 C Block C Shop drawing for Column Layout @ Second Floor Block-C X 8-Apr-12 21-Apr-12 B Closed
269-S-BC-CL-098 C Block C Shop drawing for Column Layout @ Third Floor Block C X 9-Apr-12 19-Apr-12 B Closed
269-S-RF-CL-176 C Block C Shop Drawing for Column Reinforcement 3rd to 4th Floor 20-Jun-12 UR Opened &
269-S-RF-CL-175 C Block C Shop Drawing for Column Reinforcement from 2nd to 3rd Floor – Block 20-Jun-12 UR Opened &
Program Activity C Block C Structural Dwgs. for Core Walls X 4-Jul-12 24-Jul-12
269-S-B-ST-CW-181 C Block C Shop Drawing for Core Wall Reinforcement (CW 8 & 9) from 2nd to 3rd X 20-Jun-12 UR Opened &
269-S-BC-ST-CW-188 C Block C Shop Drawing for Core Wall (CW 8 & 9) Reinforcement from 3rd to 4th X 25-Jun-12 UR Opened &
Program Activity C Block C Structural Dwgs. for Slab X 22-Jul-12 9-Aug-12 26-Apr-12 25-Jun-12 B Closed &
269-S-BA-CD-115 C Block C Shop drawing for Concrete Dimension for Slab & Beam at 03rd Floor - 26-Apr-12 13-May-12 B Closed
269-S-BA-CD-118 C Block C Shop drawing for Concrete Dimension for slab & Beam at 04th Floor - 29-Apr-12 16-Jun-12 B Closed &
269 S RE 4F 162 C Block C Shop Drawing For 4th Floor Slab Reinforcement Details Block “C” 11-Jun-12 25-Jun-12 B Closed &269-S-RE-4F-162 C Block C Shop Drawing For 4th Floor Slab Reinforcement Details - Block C 11-Jun-12 25-Jun-12 B Closed &
269-S-RE-SF-160 C Block C Shop Drawing for Slab Reinforcement Details from 3rd Floor- Block “C” 11-Jun-12 21-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Staircase X 8-Sep-12 26-Sep-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
File : -Engineering Tracking Chart - Rev 00 5 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
5th & 6th Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 30-Jul-12 21-Aug-12 19-Apr-12 Opened
269-S-BC-CL-105 C Block C Shop drawing for Column Layout @ Fourth (4th) Floor Block-C 19-Apr-12 17-May-12 B Closed
269-S-BA-CL-121 C Block C Shop drawing for Column / Core Wall Layout at 05th Floor - Block “C” 29-Apr-12 6-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 14-Aug-12 5-Sep-12 29-Apr-12 Opened
269-S-BA-CL-121 C Block C Shop drawing for Column / Core Wall Layout at 05th Floor - Block “C” 29-Apr-12 6-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 2-Sep-12 20-Sep-12 18-Jun-12
269-S-BA-CD-196 Shop Drawing for Concrete Dimension for Slab & Beam at 6th Floor - 30-Jun-12 UR Opened &
269-S-RE-6F-199 Shop Drawing for 6th Floor Slab Reinforcement and Details - Block “C” 28-Jun-12 UR Opened &
269-S-BA-CD-177 Shop Drawing for Concrete Dimension for Slab & Beam at 5th Floor – 18-Jun-12 30-Jun-12 B Closed &
269-S-RE-5F-185 Shop Drawing for 5th Floor Slab Reinforcement and Details 24-Jun-12 UR Opened &
Program Activity C Block C Structural Dwgs. for Staircase X 6-Oct-12 24-Oct-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
7th Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 2-Sep-12 20-Sep-12 11-Jun-12
269-S-BC-CL-159 Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &S C C p g y
Program Activity C Block C Structural Dwgs. for Core Walls X 10-Sep-12 30-Sep-12 11-Jun-12
269-S-BC-CL-159 Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Slab X 6-Oct-12 24-Oct-12
Program Activity C Block C Structural Dwgs. for Staircase X 4-Nov-12 25-Nov-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
Roof Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 22-Sep-12 10-Oct-12
269-S-BC-CL-174 Shop drawing for Column / Core wall Layout at 7th Floor – Block “C” 18-Jun-12 27-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Core Walls X 2-Oct-12 22-Oct-12
269-S-BC-CL-174 Shop drawing for Column / Core wall Layout at 7th Floor – Block “C” 18-Jun-12 27-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Slab X 28-Oct-12 18-Nov-12
Program Activity C Block C Structural Dwgs. for Chillers Foundations X 30-Oct-12 20-Nov-12
Program Activity C Block C Structural Dwgs. for Staircase X 4-Dec-12 24-Dec-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-RE-SR-50 C Block C Stair case Reinforcement details – Stair case –S6 - Block © X 10-Mar-12 31-Mar-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Parapets X 12-Dec-12 2-Jan-13Program Activity C Block C Structural Dwgs. for Parapets
Upper Roof Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 15-Oct-12 5-Nov-12
Program Activity C Block C Structural Dwgs. for Slab X 23-Oct-12 13-Nov-12
Program Activity C Block C Structural Dwgs. for Staircase X 2-Dec-12 20-Dec-12
B.2- Architectural Shop DrawingsB.2.1- Hotel Apartments (Block A)2nd Basement Floor
Program Activity A Block A Block Work Setting Out Plan for 2nd Basement X 16-May-12 5-Jun-12 12-Apr-12 26-Apr-12 B Closed
269-S-BA-Bl-101 A Block A Shop Drawing for 2nd Basement Block Work Setting-out Plan - block A 12-Apr-12 26-Apr-12 B Closed
Program Activity A Block A Staircase Layout & Details X 1-Jul-12 19-Jul-12
Program Activity A Block A Handrail Layout & Details X 23-Sep-12 11-Oct-12
Program Activity A Block A Reflected Ceiling Layout X 16-Oct-12 6-Nov-12
Program Activity A Block A Flooring X 18-Dec-12 8-Jan-13
Program Activity A Block A Doors Details X 18-Dec-12 8-Jan-13
Program Activity A Block A Sinage Layout and Details X 30-Dec-12 20-Jan-13
Program Activity A Block A Parking Layout X 12-Jan-13 31-Jan-13
Program Activity A Block A Traffic Sign Layout X 12-Jan-13 31-Jan-13
1st Basement Floor
Program Activity A Block A Block Work Setting Out Plan for 1st Basement X 26-May-12 13-Jun-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-124 A Block A Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block A Staircase Layout & Details X 10-Jul-12 30-Jul-12
Program Activity A Block A Reflected Ceiling Layout X 14-Aug-12 5-Sep-12
Program Activity A Block A Flooring X 3-Sep-12 23-Sep-12Program Activity A Block A Flooring X 3-Sep-12 23-Sep-12
Program Activity A Block A Doors Details X 9-Sep-12 27-Sep-12
Program Activity A Block A Handrail Layout & Details X 2-Oct-12 22-Oct-12
Program Activity A Block A Sinage Layout and Details X 28-Oct-12 18-Nov-12
Program Activity A Block A Parking Layout X 21-Jan-13 11-Feb-13
Program Activity A Block A Traffic Sign Layout X 21-Jan-13 11-Feb-13
Ground Floor
File : -Engineering Tracking Chart - Rev 00 6 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block A Block Work Setting Out Plan for Ground X 30-Jun-12 18-Jul-12 19-Jun-12 24-Jun-12 B Closed
269-A-BA-BL-182 Shop Drawing for Ground Floor Block Work Setting Out Plan – Block “A” 19-Jun-12 24-Jun-12 B Closed &
Program Activity A Block A Staircase Layout & Details X 12-Aug-12 3-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 30-Sep-12 18-Oct-12
Program Activity A Block A Flooring Layout X 30-Sep-12 18-Oct-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout for Toilets X 6-Nov-12 27-Nov-12
Program Activity A Block A Handrail Layout & Details X 6-Nov-12 27-Nov-12
Program Activity A Block A Doors Details X 15-Dec-12 3-Jan-13
Program Activity A Block A Sinage Layout and Details X 25-Dec-12 15-Jan-13
Program Activity A Block A Furniture Layout and Details X 3-Jul-13 23-Jul-13
Typical Floors
General
Program Activity A Block A Block Work Setting Out Plan for 1st Floor X 8-Jul-12 26-Jul-12 7-Jun-12 25-Jun-12 B Closed
269-S-BA-BL-149 0 A Block A Shop Drawing for 1st floor Block work Setting out plan Block - A X 7-Jun-12 25-Jun-12 B Closed &
Program Activity A Block A Block Work Setting Out Plan for 2nd Floor X 4-Aug-12 26-Aug-12 7-Jun-12 23-Jun-12 B Closed
269-A-BA-BL-150 0 A Block A Shop Drawing for 2nd floor Block work Setting out plan Block - A X 7-Jun-12 23-Jun-12 B Closed &
Program Activity A Block A Block Work Setting Out Plan for 3rd to 6th Floor X 2-Sep-12 20-Sep-12
Program Activity A Block A Block Work Setting Out Plan for 7th Floor X 16-Oct-12 6-Nov-12
Corridor / General
Program Activity A Block A Staircase Layout & Details X 4-Sep-12 24-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 16-Sep-12 4-Oct-12Program Activity A Block A Reflected Ceiling Layout p
Program Activity A Block A Handrail Layout & Details X 21-Oct-12 11-Nov-12
Program Activity A Block A Flooring Layout X 17-Nov-12 6-Dec-12
Program Activity A Block A Doors Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Sinage Layout and Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Studio Apartements
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 4-Sep-12 24-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wardrobe Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Sinage Layout and Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
One Bed Room Apartements
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 21-Oct-12 11-Nov-12
Program Activity A Block A Wardrobe Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Sinage Layout and Details X 10-Feb-13 28-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
Two Bed Room Apartements
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wardrobe Details X 4-Nov-12 25-Nov-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 4-Nov-12 25-Nov-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Sinage Layout and Details X 10-Feb-13 28-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
Roof - Upper Roof Floor
General
Program Activity A Block A Block Work Setting Out Plan for Roof & Upper Roof X 29-Sep-12 17-Oct-12
Program Activity A Block A Roof's Water Proofing System X 7-Oct-12 28-Oct-12
P A ti it A Block A Pool Deck Layout X 26 No 12 17 Dec 12Program Activity A Block A Pool Deck Layout X 26-Nov-12 17-Dec-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout for Toilets X 27-Jan-13 14-Feb-13
Program Activity A Block A Flooring Layout X 27-Jan-13 14-Feb-13
Program Activity A Block A Staircase Layout & Details X 27-Jan-13 14-Feb-13
Program Activity A Block A Handrail Layout & Details X 27-Jan-13 14-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Gymnasium
File : -Engineering Tracking Chart - Rev 00 7 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block A Reflected Ceiling Layout X 3-Nov-12 22-Nov-12
Program Activity A Block A Vinyl Floor Detals X 9-Feb-13 27-Feb-13
Program Activity A Block A Furniture Layout and Detals X 20-Jul-13 7-Aug-13
B.2.2- Hotel (Block B)2nd Basement Floor
Program Activity A Block B Block Work Setting Out Plan for 2nd Basement X 27-May-12 14-Jun-12 21-Apr-12 2-May-12 B Closed
269-S-BB-BL-107 A Block B Shop drawing for 2nd Basement BlockWork Setting Out Plan (Block-B) 21-Apr-12 2-May-12 B Closed
Program Activity A Block B Staircase Layout & Details X 15-Aug-12 6-Sep-12
Program Activity A Block B Handrail Layout & Details X 15-Aug-12 6-Sep-12
Program Activity A Block B Flooring X 3-Oct-12 23-Oct-12
Program Activity A Block B Doors Details X 3-Oct-12 23-Oct-12
Program Activity A Block B Sinage Layout and Details X 24-Nov-12 13-Dec-12
Program Activity A Block B Parking Layout X 22-Jan-13 12-Feb-13
Program Activity A Block B Traffic Sign Layout X 22-Jan-13 12-Feb-13
1st Basement Floor
Program Activity A Block B Block Work Setting Out Plan for 1st Basement X 11-Jul-12 31-Jul-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-125 A Block B Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block B Doors Details X 13-Aug-12 4-Sep-12
Program Activity A Block B Staircase Layout & Details X 27-Aug-12 16-Sep-12
Program Activity A Block B Reflected Ceiling Layout X 27-Aug-12 16-Sep-12
Program Activity A Block B Handrail Layout & Details X 8-Sep-12 26-Sep-12g y y
Program Activity A Block B Flooring X 8-Sep-12 26-Sep-12
Program Activity A Block B Sinage Layout and Details X 27-Oct-12 14-Nov-12
Program Activity A Block B Parking Layout X 2-Feb-13 20-Feb-13
Program Activity A Block B Traffic Sign Layout X 2-Feb-13 20-Feb-13
Ground Floor
Public Areas
Program Activity A Block B Block Work Setting Out Plan for Ground X 27-Aug-12 16-Sep-12
Program Activity A Block B Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block B Flooring Layout X 29-Sep-12 17-Oct-12
Program Activity A Block B Wet Area Ceramic & Pocalin Layout for Toilets X 29-Sep-12 17-Oct-12
Program Activity A Block B Staircase Layout & Details X 10-Oct-12 31-Oct-12
Program Activity A Block B Handrail Layout & Details X 10-Oct-12 31-Oct-12
Program Activity A Block B Doors Details X 18-Nov-12 9-Dec-12
Program Activity A Block B Sinage Layout and Details X 18-Nov-12 9-Dec-12
Program Activity A Block B Carpet Flooring Details X 30-Mar-13 17-Apr-13
Program Activity A Block B Furniture Layout and Detals X 2-Jul-13 22-Jul-13
Restaurant
Program Activity A Block B Reflected Ceiling Layout X 25-Sep-12 15-Oct-12
Program Activity A Block B Flooring Layout X 22-Dec-12 10-Jan-13
Program Activity A Block B Sinage Layout and Details X 19-Feb-13 11-Mar-13
Program Activity A Block B Furniture Layout and Detals X 10-Jul-13 30-Jul-13
Bussiness Center & Retail
Program Activity A Block B Reflected Ceiling Layout X 5-Sep-12 25-Sep-12Program Activity A Block B Reflected Ceiling Layout p p
Program Activity A Block B Flooring Layout X 5-Nov-12 26-Nov-12
Program Activity A Block B Sinage Layout and Details X 10-Apr-13 30-Apr-13
Program Activity A Block B Furniture Layout and Detals X 2-Jul-13 22-Jul-13
Enterance Lobby & Lounge
Program Activity A Block B Reflected Ceiling Layout X 18-Nov-12 9-Dec-12
Program Activity A Block B Flooring Layout X 11-Dec-12 31-Dec-12
Program Activity A Block B Sinage Layout and Details X 10-Apr-13 30-Apr-13
Program Activity A Block B Furniture Layout and Detals X 14-Jul-13 1-Aug-13
Typical Floors
General
Program Activity A Block B Block Work Setting Out Plan for 1st Floor X 5-Sep-12 25-Sep-12 13-Jun-12
269-A-BB-BL-155 Shop Drawing for 1st Floor Block Work Setting Out Plan Block – “B” 13-Jun-12 UR Opened &
Program Activity A Block B Block Work Setting Out Plan for 2nd Floor X 15-Sep-12 3-Oct-12 28-Jun-12
269-A-BB-BL-192 A Block B Shop Drawing for Second Floor Block Work Setting Out Plan - Block “B” 28-Jun-12 UR Opened &
Program Activity A Block B Block Work Setting Out Plan for 3rd to 6th Floor X 24-Sep-12 14-Oct-12
Program Activity A Block B Block Work Setting Out Plan for 7th Floor X 4-Nov-12 25-Nov-12
Corridor / Public Areas
Program Activity A Block B Landscaping's Water Proofing Details X 15-Sep-12 3-Oct-12
Program Activity A Block B Reflected Ceiling Layout X 8-Oct-12 29-Oct-12
Program Activity A Block B Landscaping Layout & Details X 14-Oct-12 4-Nov-12
Program Activity A Block B Staircase Layout & Details X 20-Oct-12 8-Nov-12
Program Activity A Block B Handrail Layout & Details X 20-Oct-12 8-Nov-12
Program Activity A Block B Pool Deck Layout X 3-Nov-12 13-Nov-12Program Activity A Block B Pool Deck Layout X 3-Nov-12 13-Nov-12
Program Activity A Block B Doors Details X 17-Nov-12 6-Dec-12
Program Activity A Block B Sinage Layout and Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Flooring Layout X 10-Dec-12 30-Dec-12
Program Activity A Block B Irrigation Layout & Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Sky Light Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Carpet Flooring Details X 8-Apr-13 28-Apr-13
File : -Engineering Tracking Chart - Rev 00 8 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block B Furniture Layout and Detals X 23-Jul-13 13-Aug-13
Hotel Rooms
Program Activity A Block B Reflected Ceiling Layout X 20-Oct-12 8-Nov-12
Program Activity A Block B Wet Area Ceramic & Pocalin Layout X 20-Oct-12 8-Nov-12
Program Activity A Block B Wardrobe Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Floors Layout and Details X 22-Dec-12 10-Jan-13
Program Activity A Block B Mirror Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Doors Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Vanity Counter Details X 9-Feb-13 27-Feb-13
Program Activity A Block B Carpet Flooring Details X 8-Apr-13 28-Apr-13
Program Activity A Block B Sinage Layout and Details X 8-Apr-13 28-Apr-13
Program Activity A Block B Furniture Layout and Detals X 23-Jul-13 13-Aug-13
Roof - Upper Roof Floor
General
Program Activity A Block B Block Work Setting Out Plan for for Roof&Upper Roof X 20-Oct-12 8-Nov-12
Program Activity A Block B Roof's Water Proofing System X 31-Oct-12 21-Nov-12
Program Activity A Block B Flooring Layout X 31-Oct-12 21-Nov-12
Program Activity A Block B Doors Details X 19-Dec-12 9-Jan-13
B.2.3- Residential (Block C)2nd Basement Floor
Program Activity A Block C Block Work Setting Out Plan for 2nd Basement X 27-May-12 14-Jun-12 21-Apr-12 11-Jun-12 B Closedg y g
269-S-BC-BL-108 Shop drawing for 2nd Basement BlockWork Setting Out Plan (Block-C) 21-Apr-12 11-Jun-12 B Closed &
Program Activity A Block C Staircase Layout & Details X 11-Jul-12 31-Jul-12
Program Activity A Block C Handrail Layout & Details X 23-Jul-12 12-Aug-12
Program Activity A Block C Reflected Ceiling Layout X 15-Aug-12 6-Sep-12
Program Activity A Block C Flooring X 3-Oct-12 23-Oct-12
Program Activity A Block C Doors Details X 3-Oct-12 23-Oct-12
Program Activity A Block C Sinage Layout and Details X 17-Nov-12 6-Dec-12
Program Activity A Block C Parking Layout X 22-Jan-13 12-Feb-13
Program Activity A Block C Traffic Sign Layout X 22-Jan-13 12-Feb-13
1st Basement Floor
Program Activity A Block C Block Work Setting Out Plan for 1st Basement X 11-Jul-12 31-Jul-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-126 Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block C Staircase Layout & Details X 13-Aug-12 4-Sep-12
Program Activity A Block C Handrail Layout & Details X 13-Aug-12 4-Sep-12
Program Activity A Block C Reflected Ceiling Layout X 13-Aug-12 4-Sep-12
Program Activity A Block C Flooring X 27-Aug-12 16-Sep-12
Program Activity A Block C Doors Details X 8-Sep-12 26-Sep-12
Program Activity A Block C Sinage Layout and Details X 15-Dec-12 3-Jan-13
Program Activity A Block C Parking Layout X 13-Feb-13 5-Mar-13
Program Activity A Block C Traffic Sign Layout X 13-Feb-13 5-Mar-13
Ground Floor
Program Activity A Block C Block Work Setting Out Plan for Ground X 13-Aug-12 4-Sep-12 30-Jun-12
269-A-BA-Bl-188 Shop Drawing for Ground Floor Block Work Setting Out Plan - Block “C” X 30-Jun-12 UR Opened &269 A BA Bl 188 Shop Drawing for Ground Floor Block Work Setting Out Plan Block C UR Opened &
Program Activity A Block C Staircase Layout & Details X 25-Aug-12 12-Sep-12
Program Activity A Block C Flooring Layout X 1-Sep-12 19-Sep-12
Program Activity A Block C Reflected Ceiling Layout X 11-Sep-12 1-Oct-12
Program Activity A Block C Handrail Layout & Details X 11-Sep-12 1-Oct-12
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for Toilets X 29-Sep-12 17-Oct-12
Program Activity A Block C Doors Details X 22-Oct-12 12-Nov-12
Program Activity A Block C Sinage Layout and Details X 24-Dec-12 14-Jan-13
Typical Floors
General
Program Activity A Block C Block Work Setting Out Plan for 1st Floor X 25-Aug-12 12-Sep-12
Program Activity A Block C Block Work Setting Out Plan for 2nd Floor X 3-Sep-12 23-Sep-12
Program Activity A Block C Block Work Setting Out Plan for 3rd to 6th Floor X 12-Sep-12 2-Oct-12
Program Activity A Block C Block Work Setting Out Plan for 7th Floor X 29-Oct-12 19-Nov-12
Corridor / Public Areas
Program Activity A Block C Staircase Layout & Details X 26-Sep-12 16-Oct-12
Program Activity A Block C Handrail Layout & Details X 26-Sep-12 16-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 10-Nov-12 29-Nov-12
Program Activity A Block C Doors Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Sinage Layout and Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Flooring Layout X 5-Jan-13 23-Jan-13
One Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout X 3-Nov-12 22-Nov-12
Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
File : -Engineering Tracking Chart - Rev 00 9 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13
Two Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout X 8-Oct-12 29-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13
Three Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for X 8-Oct-12 29-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 20-Oct-12 8-Nov-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13g yRoof - Upper Roof Floor
General
Program Activity A Block C Block Work Setting Out Plan for Ground X 17-Nov-12 6-Dec-12
Program Activity A Block C Roof's Water Proofing System X 25-Nov-12 16-Dec-12
Program Activity A Block C Pool Deck Layout X 2-Dec-12 20-Dec-12
Program Activity A Block C Doors Details X 1-Jan-13 21-Jan-13
Program Activity A Block C Staircase Layout & Details X 1-Jan-13 21-Jan-13
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for Toilets X 26-Jan-13 13-Feb-13
Program Activity A Block C Flooring Layout X 26-Jan-13 13-Feb-13
Program Activity A Block C Handrail Layout & Details X 26-Jan-13 13-Feb-13
Gymnasium
Program Activity A Block C Reflected Ceiling Layout X 19-Dec-12 9-Jan-13
Program Activity A Block C Vinyl Floor Detals X 2-Mar-13 20-Mar-13
Program Activity A Block C Furniture Layout and Detals X 30-Jul-13 20-Aug-13
B.4- Speciality Works DrawingsB.4.1- Swimming PoolsAll Buildings
Program Activity 0 SP Block A Swimming Pool Layout & Details for Block A X 6-Oct-12 24-Oct-12 18-Apr-12 3-May-12 C Opened
Program Activity 0 SP Block A Swimming Pool 's Water Prrofing for Block A X 6-Oct-12 24-Oct-12
Program Activity 0 SP Block B Swimming Pool Layout & Details for Block B X 6-Oct-12 24-Oct-12 12-Apr-12 26-Apr-12 C Opened
Program Activity 0 SP Block B Swimming Pool 's Water Proofing for Block B X 6-Oct-12 24-Oct-12
Program Activity 0 SP Block C Swimming Pool Layout & Details for Block C X 30-Oct-12 20-Nov-12 17-Apr-12 3-May-12 C Opened
Program Activity 0 SP Block C Swimming Pool 's Water Proofing for Block C X 30-Oct-12 20-Nov-12Program Activity 0 SP Block C Swimming Pool s Water Proofing for Block C
B.4.2- External FaçadeHotel Apartments (Block A)
Program Activity 0 SP Block A External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block A External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block A GRC Layout & Details X 24-Feb-13 14-Mar-13
Hotel (Block B)
Program Activity 0 SP Block B External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block B External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block B GRC Layout & Details X 24-Feb-13 14-Mar-13
Residential (Block C)
Program Activity 0 SP Block C External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block C External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block C GRC Layout & Details X 24-Feb-13 14-Mar-13
B 4 3 Façade CleaningB.4.3- Façade CleaningAll Buildings
Program Activity 0 SP Block A Glass Cleaning Machine X 16-Mar-13 3-Apr-13
Program Activity 0 SP Block B Glass Cleaning Machine X 16-Mar-13 3-Apr-13
Program Activity 0 SP Block C Glass Cleaning Machine X 16-Mar-13 3-Apr-13
B.4.4- Garbage ChutesAll Buildings
File : -Engineering Tracking Chart - Rev 00 10 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity 0 SP Block A Garbage Chute Layout & Details for Block A X 4-Jul-12 24-Jul-12
Program Activity 0 SP Block B Garbage Chute Layout & Details for Block B X 9-Sep-12 27-Sep-12
Program Activity 0 SP Block C Garbage Chute Layout & Details for Block C X 17-Nov-12 6-Dec-12
B.4.5- Linen ChutesHotel (Block B)
Program Activity 0 SP Block B Linen Chute Layout & Details for Block B X 3-Sep-12 23-Sep-12
B.5- Provisional Sum DrawingsB.5.1- Kitchen EquipmentsHotel (Block B)
Program Activity 0 SP Block B Kitchen Equipments Drawings X 16-Jul-12 5-Aug-12
B.5.2- Laundary EquipmentsHotel (Block B)
Program Activity 0 SP Block B Laundary Equipments Drawings X 16-Jul-12 5-Aug-12
B.5.3- Façade LightingAll Buildings
Program Activity 0 SP Block A Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
Program Activity 0 SP Block B Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
Program Activity 0 SP Block C Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
B.5.4- Cooking StationHotel (Block B)
Program Activity 0 SP Block B Cooking Station Drawings X 31-Jul-12 22-Aug-12g y g g
B.5.5- Gymnasium EquipmentsAll Buildings
Program Activity 0 SP Block A Gymnasium Drawings 2-Apr-13 18-Apr-13
Program Activity 0 SP Block B Gymnasium Drawings 2-Apr-13 18-Apr-13
Program Activity 0 SP Block C Gymnasium Drawings 2-Apr-13 18-Apr-13
File : -Engineering Tracking Chart - Rev 00 11 of 11 Printed On :- 05/07/2012 at 08:07
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
8.0 ENGINEERINGT LOG
8.2 MEP LOG
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
B-SHOP DRAWINGS . . . . .
B.3- Electromechanical DrawingsB.3.1- Hotel Apartments (Block A)2nd Basement Floor
1 1 M Block A MEP Builder Work Layout X 1 18-Feb-12 22-Feb-12 12-Feb-12 5-Mar-12 B Closed
2 1 M Block A Drainage Layout & Details X 1 19-Feb-12 8-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block A Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block A Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Apr-12 8-Apr-12 B Closed
2 1 M Block A HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B/C Opened
1 1 M Block A Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
2 1 M Block A Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block A Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
1 1 M Block A CBS Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 20-Mar-12 B Closed
1 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 28-Feb-12 19-Mar-12 25-Feb-12 5-Mar-12 B Closed
0 1 M Block A ELV Layout & Details X 1 28-Feb-12 19-Mar-12
2 1 M Block A BMS Layout & Details X 1 28-Feb-12 19-Mar-12 12-Apr-12 3-May-12 B Closed
0 1 M Block A Data & Telephone Layout & Details X 1 28-Feb-12 19-Mar-12 14-Mar-12 7-Apr-12 B Closed
1 1 M Block A MEP Cordination Layout X 1 4-Mar-12 22-Mar-12 23-Apr-12 3-May-12 B Closed
0 1 M Block A LPG & Gas Detection Layout & Details X 1 8-Apr-12 26-Apr-12
1st Basement Floor
l k ild k
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
2 1 M Block A MEP Builder Work Layout X 1 26-Feb-12 15-Mar-12 18-Mar-12 21-Mar-12 B Closed
2 1 M Block A Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
1 1 M Block A Water Supply Layout & Details X 1 13-Mar-12 2-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 13-Mar-12 2-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block A HVAC Layout & Details X 1 13-Mar-12 2-Apr-12 18-Mar-12 29-Mar-12 B Closed
1 1 M Block A Lighting Layout & Details X 1 13-Mar-12 2-Apr-12 22-Mar-12 31-Mar-12 B Closed
1 1 M Block A Power Layout & Details X 1 13-Mar-12 2-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 13-Mar-12 2-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block A CBS Layout & Details X 1 13-Mar-12 2-Apr-12 14-Mar-12 21-Mar-12 B Closed
3 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 13-Mar-12 2-Apr-12 21-Apr-12 3-May-12 B Closed
0 1 M Block A ELV Layout & Details X 1 13-Mar-12 2-Apr-12
2 1 M Block A BMS Layout & Details X 1 13-Mar-12 2-Apr-12 12-Apr-12 3-May-12 B Closed
2 1 M Block A Data & Telephone Layout & Details X 1 13-Mar-12 2-Apr-12 18-Apr-12 17-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 18-Mar-12 5-Apr-12 12-Apr-12 24-Apr-12 B Closed
Ground Floor
1 1 M Block A Drainage Layout & Details (Low Level) X 1 3-Mar-12 21-Mar-12 10-May-12 21-May-12 B Closed
1 1 M Block A MEP Builder Work Layout X 1 11-Mar-12 29-Mar-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 21-Mar-12 10-Apr-12 29-Apr-12 24-Jun-12 B Closed &
1 1 M Block A Water Supply Layout & Details X 1 27-Mar-12 16-Apr-12 17-Apr-12 28-Apr-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 27-Mar-12 16-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 27-Mar-12 16-Apr-12 1-Apr-12 16-Apr-12 B/C Opened
0 1 M Block A Lighting Layout & Details X 1 27-Mar-12 16-Apr-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block A Power Layout & Details X 1 27-Mar-12 16-Apr-12 16-May-12 27-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 27-Mar-12 16-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 27-Mar-12 16-Apr-12 4-Apr-12 3-May-12 B Closed
0 1 M Block A Drainage Layout & Details (High Level) X 1 27-Mar-12 16-Apr-12 29-Apr-12 3-Jun-12 B Closed
1st Floor
0 1 M Block A Drainage Layout & Details (Low Level) X 1 21-Mar-12 10-Apr-12 29-Apr-12 3-Jun-12 B Closed
0 1 M Block A LPG & Gas Detection Layout & Details X 1 24-Mar-12 11-Apr-12
0 1 M Block A MEP Builder Work Layout X 1 1-Apr-12 19-Apr-12 29-Apr-12 3-May-12 B/C Opened
0 1 M Block A MEP Cordination Layout X 1 8-Apr-12 26-Apr-12 10-Jun-12 24-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Apr-12 29-Apr-12 8-May-12 20-May-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Apr-12 29-Apr-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Apr-12 29-Apr-12 12-May-12 27-May-12 B Closed
0 1 M Block A Lighting Layout & Details X 1 9-Apr-12 29-Apr-12 15-May-12 26-May-12 B Closed
1 1 M Block A Power Layout & Details X 1 9-Apr-12 29-Apr-12 10-May-12 23-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12 14-Apr-12 3-May-12 B Closed
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12 13-May-12 23-May-12 B Closed
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12 8-May-12 17-May-12 B Closed
0 1 M Block A Drainage Layout & Details (High Level) X 1 9-Apr-12 29-Apr-12 10-Jun-12 20-Jun-12 B Closed &
2nd Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 UR Opened
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 C Opened &
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 C Opened &
0 1 M Block A Drainage Layout & Details X 1 14-Apr-12 2-May-12 10-Jun-12 20-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 14-Apr-12 2-May-12 23-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 14-Apr-12 2-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 14-Apr-12 2-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block A Lighting Layout & Details X 1 14-Apr-12 2-May-12 28-May-12 12-Jun-12 B Closed &
File : -Engineering Tracking Chart - Rev 00 1 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block A Power Layout & Details X 1 14-Apr-12 2-May-12 20-May-12 27-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 14-Apr-12 2-May-12
0 1 M Block A MEP Builder Work Layout X 1 23-Apr-12 13-May-12 16-May-12 26-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 28-Apr-12 16-May-12
3rd Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 14-Apr-12 2-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 14-Apr-12 2-May-12 23-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 14-Apr-12 2-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 14-Apr-12 2-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block A Lighting Layout & Details X 1 14-Apr-12 2-May-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 14-Apr-12 2-May-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 14-Apr-12 2-May-12
0 1 M Block A MEP Builder Work Layout X 1 23-Apr-12 13-May-12 19-May-12 26-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 28-Apr-12 16-May-12
4th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 28-Apr-12 16-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 28-Apr-12 16-May-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block A Lighting Layout & Details X 1 28-Apr-12 16-May-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 28-Apr-12 16-May-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block A MEP Cordination Layout X 1 9-May-12 29-May-12
0 1 M Block A MEP Builder Work Layout X 1 14-May-12 3-Jun-12 19-May-12 26-May-12 B Closed
5th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A MEP Builder Work Layout X 1 4-Jun-12 25-Jun-12 19-May-12 26-May-12 B Closed
0 1 M Block A Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A MEP Cordination Layout X 1 9-Jun-12 28-Jun-12
0 1 M Block A Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
6th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block A MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12 19-May-12 26-May-12 B Closed
7th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block A Power Layout & Details X 1 26-Jun-12 16-Jul-12y
0 1 M Block A Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block A Drainage Layout & Details X 1 27-Jun-12 17-Jul-12 17-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block A MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
File : -Engineering Tracking Chart - Rev 00 2 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block A MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block A Data & Telephone Layout & Details X 1 1-May-12 21-May-12
0 1 M Block A Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block A MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floor
0 1 M Block A Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
B.3.2- Hotel Apartments (Block B)2nd Basement Floor
2 1 M Block B Drainage Layout & Details X 1 19-Feb-12 8-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block B MEP Builder Work Layout X 1 19-Feb-12 8-Mar-12 12-Feb-12 5-Mar-12 B Closed
1 1 M Block B Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block B Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 8-Mar-12 B Closed
2 1 M Block B HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 17-Mar-12 28-Mar-12 B/C Opened
1 1 M Block B Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
1 1 M Block B Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
2 1 M Block B Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block B MEP Cordination Layout X 1 6-Mar-12 26-Mar-12 23-Apr-12 6-May-12 B Closed
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
1st Basement Floor
2 1 M Block B Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
2 1 M Block B MEP Builder Work Layout X 1 6-Mar-12 26-Mar-12 18-Mar-12 21-Mar-12 B Closed
1 1 M Block B Water Supply Layout & Details X 1 20-Mar-12 9-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 20-Mar-12 9-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block B HVAC Layout & Details X 1 20-Mar-12 9-Apr-12 18-Mar-12 29-Mar-12 B Closed
1 1 M Block B Lighting Layout & Details X 1 20-Mar-12 9-Apr-12 22-Mar-12 31-Mar-12 B Closed
0 1 M Block B Fire Alarm Layout & Details X 1 20-Mar-12 9-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block B CBS Layout & Details X 1 20-Mar-12 9-Apr-12 14-Mar-12 21-Mar-12 B Closed
3 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 20-Mar-12 9-Apr-12 21-Apr-12 3-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 20-Mar-12 9-Apr-12
2 1 M Block B BMS Layout & Details X 1 20-Mar-12 9-Apr-12 12-Apr-12 3-May-12 B Closed
2 1 M Block B Data & Telephone Layout & Details X 1 20-Mar-12 9-Apr-12 18-Apr-12 17-May-12 B Closed
1 1 M Block B Power Layout & Details X 1 20-Mar-12 9-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block B MEP Cordination Layout X 1 27-Mar-12 16-Apr-12 12-Apr-12 24-Apr-12 B Closed
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
Ground Floor1 1 M Block B Drainage Layout & Details (Low Level) X 1 20-Mar-12 9-Apr-12 10-May-12 21-May-12 B Closed
2 1 M Block B Water Supply Layout & Details X 1 8-Apr-12 26-Apr-12 10-May-12 19-May-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 8-Apr-12 26-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B Lighting Layout & Details X 1 8-Apr-12 26-Apr-12 27-May-12 B/C Opened &
0 1 M Block B Power Layout & Details X 1 8-Apr-12 26-Apr-12 16-May-12 23-May-12 B/C Opened
0 1 M Block B Fire Alarm Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 8-Apr-12 26-Apr-12 10-May-12 17-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B Data & Telephone Layout & Details X 1 8-Apr-12 26-Apr-12 20-May-12 C Opened &
0 1 M Block B Drainage Layout & Details (High Level) X 1 8-Apr-12 26-Apr-12 22-May-12 3-Jun-12 B/C Opened
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B MEP Cordination Layout X 1 15-Apr-12 3-May-12
0 1 M Block B MEP Builder Work Layout X 1 15-Apr-12 3-May-12 7-May-12 17-May-12 B Closed
1st Floor
0 1 M Block B Drainage Layout & Details (Low Level) X 1 8-Apr-12 26-Apr-12 20-May-12 3-Jun-12 B/C Opened
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Water Supply Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 20-May-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 28-Apr-12 16-May-12 25-Jun-12 UR Opened &
0 1 M Block B Lighting Layout & Details X 1 28-Apr-12 16-May-12 25-Jun-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 28-Apr-12 16-May-12 2-Jun-12 C Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
File : -Engineering Tracking Chart - Rev 00 3 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 14-Apr-12 3-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12 13-May-12 23-May-12 B Closed
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 17-May-12 B Closed
0 1 M Block B Drainage Layout & Details (High Level) X 1 28-Apr-12 16-May-12 4-Jun-12 20-Jun-12 B/C Opened &
0 1 M Block B MEP Cordination Layout X 1 5-May-12 23-May-12
0 1 M Block B MEP Builder Work Layout X 1 5-May-12 23-May-12 19-May-12 26-May-12 B Closed
2nd Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Drainage Layout & Details X 1 19-May-12 6-Jun-12 4-Jun-12 20-Jun-12 B/C Opened &
0 1 M Block B Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 1 19-May-12 6-Jun-12 30-Jun-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 19-May-12 6-Jun-12 28-Jun-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B MEP Cordination Layout X 1 26-May-12 13-Jun-12
0 1 M Block B MEP Builder Work Layout X 1 26-May-12 13-Jun-12 24-May-12 30-May-12 B Closed
3rd Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 19-May-12 6-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 1 19-May-12 6-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 19-May-12 6-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
4th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
5th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
6th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
File : -Engineering Tracking Chart - Rev 00 4 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block B MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12
7th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B Power Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B CBS Layout & Details X 1 26-Jun-12 16-Jul-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B Drainage Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block B Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block B MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
0 1 M Block B MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B ELV Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B BMS Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Data & Telephone Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B CBS Layout & Details X 0 17-Jul-12 6-Aug-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block B MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
B.3.3- Residentail (Block C)2nd Basement Floor
2 1 M Block C Drainage Layout & Details X 1 18-Feb-12 7-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block C MEP Builder Work Layout X 1 18-Feb-12 7-Mar-12 12-Feb-12 5-Mar-12 B Closed
1 1 M Block C Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block C Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 8-Mar-12 B Closed
2 1 M Block C HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 17-Mar-12 27-Mar-12 B/C Opened
1 1 M Block C Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
2 1 M Block C Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block C Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
1 1 M Block C MEP Cordination Layout X 1 5-Mar-12 25-Mar-12 23-Apr-12 6-May-12 B Closed
1st Basement Floor
2 1 M Block C Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
2 1 M Block C MEP Builder Work Layout X 1 19-Mar-12 8-Apr-12 18-Mar-12 21-Mar-12 B Closed
1 1 M Block C Water Supply Layout & Details X 1 2-Apr-12 22-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 2-Apr-12 22-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block C HVAC Layout & Details X 1 2-Apr-12 22-Apr-12 18-Mar-12 29-Mar-12 B Closedy
1 1 M Block C Lighting Layout & Details X 1 2-Apr-12 22-Apr-12 22-Mar-12 31-Mar-12 B Closed
1 1 M Block C Power Layout & Details X 1 2-Apr-12 22-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block C Fire Alarm Layout & Details X 1 2-Apr-12 22-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block C MEP Cordination Layout X 1 9-Apr-12 29-Apr-12 12-Apr-12 24-Apr-12 B Closed
Ground Floor
0 1 M Block C Drainage Layout & Details (Low Level) X 1 20-Mar-12 9-Apr-12 10-May-12 21-May-12 B Closed
File : -Engineering Tracking Chart - Rev 00 5 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C Water Supply Layout & Details X 1 8-Apr-12 26-Apr-12 17-Apr-12 28-Apr-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 8-Apr-12 26-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 8-Apr-12 26-Apr-12 1-Apr-12 16-Apr-12 B/C Opened
0 1 M Block C Lighting Layout & Details X 1 8-Apr-12 26-Apr-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block C Power Layout & Details X 1 8-Apr-12 26-Apr-12 16-May-12 27-May-12 B Closed
0 1 M Block C Fire Alarm Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block C Data & Telephone Layout & Details X 1 8-Apr-12 26-Apr-12 4-Apr-12 3-May-12 B Closed
0 1 M Block C Drainage Layout & Details (High Level) X 1 8-Apr-12 26-Apr-12 14-May-12 23-May-12 B Closed
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C MEP Cordination Layout X 1 15-Apr-12 3-May-12 16-May-12 23-May-12 B Closed
1 1 M Block C MEP Builder Work Layout X 1 15-Apr-12 3-May-12 24-Mar-12 2-Apr-12 B Closed
1st Floor
0 1 M Block C Drainage Layout & Details (Low Level) X 1 8-Apr-12 26-Apr-12 14-May-12 23-May-12 B Closed
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C Water Supply Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 20-May-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block C Lighting Layout & Details X 1 28-Apr-12 16-May-12 6-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Power Layout & Details X 1 28-Apr-12 16-May-12 24-May-12 27-Jun-12 B Closed &
0 1 M Block C Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 14-Apr-12 3-May-12 B Closed
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12 13-May-12 23-May-12 B Closed
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 UR Opened &
0 1 M Block C Drainage Layout & Details (High Level) X 1 28-Apr-12 16-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C MEP Cordination Layout X 1 5-May-12 23-May-12
0 1 M Block C MEP Builder Work Layout X 1 5-May-12 23-May-12 10-May-12 17-May-12 B Closed
2nd Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 20-Jun-12 UR Opened &
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 26-May-12 13-Jun-12
0 1 M Block C MEP Builder Work Layout X 1 26-May-12 13-Jun-12 24-May-12 30-May-12 B Closed
3rd Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 24-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 28-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 4-Jun-12 25-Jun-12
0 1 M Block C MEP Builder Work Layout X 1 4-Jun-12 25-Jun-12 24-May-12 30-May-12 B Closed
4th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closedpp y y
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
File : -Engineering Tracking Chart - Rev 00 6 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block C MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12 24-May-12 30-May-12 B Closed
5th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block C MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12 24-May-12 30-May-12 B Closed
6th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block C MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12 24-May-12 30-May-12 B Closed
7th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C Power Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C CBS Layout & Details X 1 26-Jun-12 16-Jul-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C Drainage Layout & Details X 1 27-Jun-12 17-Jul-12 21-Jun-12 UR Opened &
0 1 M Block C Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block C MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
0 1 M Block C MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C ELV Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C BMS Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Data & Telephone Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C CBS Layout & Details X 0 17-Jul-12 6-Aug-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block C MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floorpp
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
File : -Engineering Tracking Chart - Rev 00 7 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
File : -Engineering Tracking Chart - Rev 00 8 of 8 Printed On :- 05/07/2012 at 08:08
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
9.0 SAFETY REPORT
9.1 HSE PROGRESS STATUS
May 31, 2012 HSE PROGRESS REPORT
1 ASGC
CONTENTS
‐ EXECUTIVE SUMMARY
‐ TOTAL NO. OF SITE EMPLOYEES
‐ MAN HOURS EXPENDED
‐ LOSS TIME ACCIDENTS & REPORTS
‐ MONTHLY ACCIDENT/NEARMISS/INCIDENT STATISTICAL ANALYSIS
‐ MEDICAL TREATMENT CASES & FIRST AID CASES
‐ EQUIPMENT INSPECTION REPORT
‐ SCAFFOLDING WEEKLY INSPECTION
‐ CRANE MONTHLY INSPECTION
‐ TEMPORARY SITE FACILITY INSPECTION
‐ SITE ACCESS CONTROL ACTIVITIES
‐ HAZARDOUS MATERIAL REPORT
‐ RECORD OF SAFETY INDUCTION TRAINING
‐ TRAINING ACTIVITIES & REPORT
‐ TOOL BOX MEETINGS
‐ RECORD OF DISCIPLINARY ACTIONS
‐ PROPERTY DAMAGE REPORT
‐ REVISIONS TO GUIDELINES
‐ SAFETY AUDIT INSPECTION REPORT
May 31, 2012 HSE PROGRESS REPORT
2 ASGC
EXECUTIVE SUMMARY
1. Weekly safety meeting & Regular tool box talks was conducted to all levels of all site staff & workers
2. Importance of near miss reporting was explained to several levels of supervisory and non supervisory staff.
3. Supervisor and foreman safety meeting was conducted to discuss site safety issues.
4. Routine inspection of heavy equipment, scaffolding, hand tools, power tools, fire extinguisher etc.
5. Continuous monitoring of construction activities for better implementation of safety practices
6. Summary of HSE performance is attached
May 31, 2012 HSE PROGRESS REPORT
3 ASGC
Number of Site Employees
Average manpower per day for the month ‐ 583
Number of Employees per day since inception‐ 404
Man‐Hours Expended
Total man‐hours for the month‐ 151,580
Total man‐hours since inception‐ 630,670
Loss Time Accidents & Reports
No loss time accidents reported till date‐0
Monthly Accident/Near Miss/Incident Statistical Analysis
Accident Record
Accident for the month 0
Accidents since inception 0
Near Miss Record
Near miss for the month 0
Near miss since inception 0
Medical Treatment Cases & First Aid Cases
Medical Treatment Case Record
Medical cases for the month 02
Medical treatment cases since inception 04
First Aid Cases Record
First aid cases for the month 0
First aid cases since inception 10
May 31, 2012 HSE PROGRESS REPORT
4 ASGC
Equipment Inspection Report
Monthly Equipment Inspections were carried out along with the progress of the Project.
Scaffolding Inspection Report
Scaffoldings erected & Dismantled by trained personnel are being used in the site.
Equipments Monthly Inspection Report
Company owned equipments and subcontractor‘s equipments are used for the project during this month.
Temporary Site Facility Inspection Report
Temporary site facility include below mentioned inspections
1. Fire Prevention/fire extinguisher check list
2. DB check List
3. Water Cooler
Site Access Control Activities
Below mentioned steps has been taken to control access
1. Security Guards assigned at main site access
2. Sign board installed at main access and on several locations at site
3. PPE strictly implemented to site
4. Traffic control team (flagmen) provided at service roads.
5. Housekeeping team has been involved for cleaning of access road.
6. New signage’s arrangements ongoing.
May 31, 2012 HSE PROGRESS REPORT
5 ASGC
Hazardous Material Report
Below mentioned hazardous material available at site.
1. Cement
2. Diesel
3. Thinner
4. Conrep.360 FFR
5. Nitobond EP Base
6. Nitoproof 600
7. Reebol WB
8. Lkfix P80 Base
9. Concure WB clear
10. Synthetic Enamel Gloss I
Note: Above mentioned all chemical MSDS are in office file.
Record of Safety Induction Training
Safety induction for new employees (Main and subcontractor) were conducted during the month
Total number of Safety induction during the Project ‐ 1079
Training Activities & Report
Several Safety trainings were given to the site workers during the course of the project in order to maintain the Safety
Rules & Regulations as per DM.
General safety training conducted (weekly bases) for all site staff, workers, Flagman, Operator & raggers.
Heat Stress Awareness Training Conducted for all site staff and site workers. The training was conducted by the
PROLYTE distributor
Emergency Evacuation Drill Conducted 0n 23rd June 2012
Power tool awareness training on 18th June 2012
May 31, 2012 HSE PROGRESS REPORT
6 ASGC
Tool Box Talks
Following tool box topics were discussed during the course of the Project
Total number of tool box talks for the project – 318
1. Emergency evacuation procedure
2. Lifeline system
3. Working at Height
4. Portable electrical tools
5. Safe access and egress
6. Working on Scaffolding
7. Manual handling
8. Safe erection procedure for the erection of placing boom.
9. Guard rail system /barricading.
10. Safe lifting procedure.
11. Heat Stress awareness training
12. Scaffolding erecting and dismantling
13. p
Record of Disciplinary Actions
1. Issuance of warning letters
2. Deduction of salary
3. Internal memos.
4. Safety Correction Active Report.
Property Damage Report
No property damage case is reported for the Project
Revisions to The Safety Guidelines
No Amendments or Revision to HSE Guidelines
Safety Audits
Didn’t started the audit in the site
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
9.0 SAFETY REPORT
9.2 MANHOURS & FIRST AID HISTOGRAMS
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Manhours Histogram
700,000
800,000
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:51
329,210
479,090
630,670
300,000
400,000
500,000
600,000
Man
hour
s
Early Monthly
Accu. Early Monthly
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
190,710
-
100,000
200,000
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Months
Early Monthly 12,600 41,440 136,670 138,500 149,880 151,580
Accu. Early Monthly 12,600 54,040 190,710 329,210 479,090 630,670
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:51
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
First Aid Histogram
16
18
20
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:53
8
11
12
14
6
8
10
12
14
16
Fisr
t Aid
Early Monthly
Accu. Early Monthly
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
1
2
5
3
1
2
-
2
4
Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Months
Early Monthly 1 2 5 3 1 2
Accu. Early Monthly 1 3 8 11 12 14
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:53
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
10.0 QUALITY REPORT
10.1 COMPRESSIVE STRENGTH RESULTS FOR CONCRETE
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm258.5605956
52.555
44 6646 60.544 61.551 64.5
45.5 63.546.5 6440 50.5
45.5 55.5
A2
A2 35
45B
62.5
64OPC + GGPS + MS 12/02/2012Crane Foundation (TC3 & TC4) 47.5Block A & B
Block C 5320/02/2012 42
15/02/2012 44.5
13/02/2012
08/02/2012
11/03/201219/02/2012
12/03/2012
A2 01/03/2012
Blinding Concrete under Raft Block A
Block A 02/02/201235 OPC + GGPS + MS+WP Blinding Concrete under Raft
07/03/201235 OPC + GGPS + MS+WP Blinding Concrete under Raft Block C
OPC + GGPS + MS+WP Blinding Concrete under Raft
35 OPC + GGPS + MS+WP 27/02/2012 5930/01/2012A2
54.5
40.5 53.548.5 6755 6756 64
3235.534.532
33.535.5
49.5 5846 6350 66.549 66.5
Crane Foundation (TC1) Block C
Block A25 Protection screed for waterproofing
Protection screed for waterproofing Block C
34
13/02/2012OPC + GGPS + MSB 45
A1 25
A1
25/02/2012 33.5
20/02/2012 53 12/03/2012 66
24/03/2012
15/03/2012
MS+WP g
OPC + GGBS 16/02/2012
OPC + GGBS
51.5 65.547 61.5
51.5 66.552.5 6547 6847 66.5
52.5 6645.5 6560.5 76.566 79.562 77.5
45.5 53.542 5544 53
53 5 62
Block A
31/03/2012
14/03/2012
45
78
A2 35 OPC + GGPS + MS+WP Blinding Concrete under Raft
Block A
Block B 44 04/04/2012
Retaining wall from basement 2 to basement 1
64.5
10/03/2012
27/02/2012
03/03/2012
26/03/201205/03/2012 49.5
54
63 02/04/2012
6648.5
05/03/2012
B 45 OPC + GGPS + MS
D 45OPC + GGPS + MS + self complacting
admixer
07/03/2012
12/03/2012
Block A
OPC + GGPS + MS Raft foundation
Columns from basement 2 to basement 1 (B2-B1)
B
53.5 6250.5 6044.5 5851.5 56.551 60.5 60Block C 08/03/2012 15/03/2012 5145 05/04/2012B OPC + GGPS + MS Raft foundation
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm252 5853 59.553 63.5
51.5 59.568 8367 77.570 7746 6448 6246 58
343334
71 82
79
17/03/2012 46.5 61.5
33.509/04/201225 OPC + GGBS Protection screed for waterproofing
D 45OPC + GGPS + MS + self complacting
admixer
Core wall & Retaining wall from basement 2 to basement 1 Block A
12/03/2012
10/03/2012 17/03/2012 68 07/04/2012
Block B
OPC + GGPS + MS R ll & Sh ll f
A1
A2 35 OPC + GGPS + MS+WP Blinding Concrete under Raft Block B 10/03/2012 07/04/2012
66.5 8872.5 83.556 67.549 66.5
51.5 6271 83.567 8563 80.5
51.5 65.553 6552 63
4241.544
7020/03/2012 10/04/2012
Block C 13/03/2012
Block C
D 45OPC GGPS MS + self complacting
admixer
Ramp wall & Shear wall from basement 2 to basement 1
B 45 OPC + GGPS + MS Columns from basement 2 to basement 1 (B2-B1)
15/03/2012 22/03/2012
A2 35
67D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 2 to basement 1
OPC + GGPS + MS+WP Blinding Concrete under Raft Block B
A1 25 OPC + GGBS Protection screed for waterproofing
64.5
83
22/03/2012 12/04/2012
Block B 15/03/2012 42.5
65.5
12/04/2012
84.5
10/04/2012
15/03/2012
Block A 13/03/2012
20/03/2012 52
52
12/04/2012
55.5 71.557.5 7357 66
78.5 8078.5 8671 85
4949
51.558 74.561 70.560 73.576 83
69.5 8175 82 5
82
testing after 5 days
17/04/2012 73
28/03/2012 73.5
50
18/04/2012
25/03/2012
45OPC + GGPS + MS + self complacting
admixer
Retaining wall & Stiarcase wall from basement 2 to basement 1
Block A 20/03/2012 27/03/2012
Block C 21/03/2012
B 45 OPC + GGPS + MSSlab at Basement 1 & Ramp Slab from basement 2 to basement 1
D
Block A 20/03/2012
Block C 19/03/2012
Slab at Basement 1 & Ramp Slab from basement 2 to basement 1
B 45 OPC + GGPS + MS
OPC + GGPS + MS Columns from basement 2 to basement 1 (B2-B1) Block C 15/03/2012 22/03/2012
45OPC + GGPS + MS + self complacting
admixer
Retaining wall & Core wall from basement 2 to basement 1
B 45
83.5
56.5 12/04/2012 70
D
59.5
76 16/04/201226/03/2012
75 82.565 7164 71.565 79
28/03/2012 64.5 18/04/2012 74Block B 21/03/2012B 45 OPC + GGPS + MS Crane Foundation (TC2)
admixer
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
53.5 60.5
50 67
49.5 62
54.5 73.554.5 66.558 76.5
63.5 79.566.5 80.560.5 83.556.5 63.558.5 63
D 45OPC + GGPS + MS + self complacting
admixer
Water tank wall from basement 2 to basement 1 Block C 27/03/2012 81
01/04/2012 55.5 22/04/2012 72
24/04/201203/04/2012 63.5
31/03/2012 51 21/04/2012 Blinding Concrete under Raft Block B2 24/03/2012 63
B 45 OPC + GGPS + MS Columns from basement 1 to ground floor (B1-G) Block A 25/03/2012
A2 35 OPC + GGPS + MS+WP
56 65.554 63.555 6951 6755 67.5
57.5 7056.5 7051 63.555 61.554 62.5
60.5 74.564 7761 76
32.5
26/04/2012 65.5
Protection screed for
08/04/2012 62Block A 01/04/2012 29/04/2012 76D 45OPC + GGPS + MS + self complacting
admixer
Core wall & Ramp wall from basement 1 to ground floor
45B 05/04/2012Raft foundation Block B-1OPC + GGPS + MS 29/03/2012 55
3331.5
55.5 6856 66
52.5 7343.5 53.542.5 5344.5 55
4141.542514548
51 5 56 5
B 45 OPC + GGPS + MS
01/05/201203/04/2012 10/04/2012 43.5
testing after 6 days 10/04/2012
04/04/2012
54
B 45 OPC + GGPS + MS Slab at Basement 1 Block C 09/04/2012 41.5testing after 5 days
Block B-2A2 35 OPC + GGPS + MS+WP Blinding Concrete under Raft
10/04/2012 54.5 01/05/2012 69
29/04/2012 32.5
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 2 to basement 1 Block B 03/04/2012
A1 25 OPC + GGBS Protection screed for waterproofing Block B-2 01/04/2012
48Slab at Basement 1 Block C 04/04/2012
51.5 56.547 53.5
51.5 5567 71.5
62.5 7267 73.5
D 45OPC + GGPS + MS + self complacting
admixer 14/04/2012 65.5 05/05/2012 72.5
5502/05/201204/04/2012 11/04/2012 50B 45 OPC + GGPS + MS Slab at Basement 1
Retaining wall from basement 1 to ground floor
Block C
Block A 07/04/2012
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm260 68.5
63.5 70.562.5 70.555 62.552 6156 64.551 62
55.5 6356 60.5
49.5 64.554.5 61.550 60.5
56.5 6552 61
19/04/2012 53.5Raft foundation 10/05/2012 62.3Block B-2 12/04/2012B 45 OPC + GGPS + MS
09/04/2012 16/04/2012 62 70D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 1 to ground floor Block A 07/05/2012
56 61.552 6659 65
57.5 66.550.5 6559 66.557 65.5
56.5 73.5
58 72.5
13/05/2012 66
21/04/2012 56 12/05/2012 66
Block B 15/04/2012 22/04/2012 55.5B 45 OPC + GGPS + MS Columns from basement 2 to basement 1 (B2 to B1)
B 45 OPC + GGPS + MS Ramp slab from Basement 1 to Ground floor Block A 14/04/2012
B 45 OPC + GGPS + MS Columns from Basement 1 to Ground floor 22/04/2012 57.5Block C 15/04/2012 13/05/2012 72
58 70
58.5 73.560.5 7458.5 6854.5 70.562 7259 7165 74.563 7263 73
47.5 5450.5 53.516/05/2012 54.5
16/05/2012 73
B 45 OPC + GGPS + MS Slab at Ground floor level Block A 18/04/2012 25/04/2012 49.5
14/05/2012 71
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 2 to basement 1 Block C-2 18/04/2012 25/04/2012 63.5
14/05/2012 72
D 45OPC + GGPS + MS + self complacting
admixer
Core wall, Staircase wall & Water tank wall from basement 2 to basement 1 floor
Block B 16/04/2012 23/04/2012 58.5
Block C 16/04/2012 23/04/2012 59B 45 OPC + GGPS + MS Columns from Basement 1 to Ground floor
51.5 5661 65.5
58.5 63.560.5 67.5
16/05/2012 65.5D 45OPC + GGPS + MS + self complacting
admixer
Core wall from basement 1 to ground floor Block C-1 18/04/2012 25/04/2012 60
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
56.5 70.5
57.5 68.5
56.5 69.5
54.5 59.5
46 58.5
43 61
58.5 66
60.5 67
62 6657 60.5
25/04/2012 48 16/05/2012 59.5OPC + GGPS + MS + self complacting
admixer
Core wall & Staircase wall from 2nd basement to 1st basement at Block B-1
Block B-1 18/04/2012
B 45
D 45
25/04/2012 57 16/05/2012 69.5OPC + GGPS + MS
Columns from 2nd basement to 1st basement at Block C-2 & Columns from 2nd basement to 1st basement at Block B-1
Block C-2 & Block B-1 18/04/2012
19/05/2012 66.5D 45OPC + GGPS + MS + self complacting
admixer
Ramp wall from basement 2 to basement 1 flor @ block B and Core wall, retaining wall from basement 2 to basement 1 floor @ Block C2
Block B & C-2 21/04/2012 28/04/2012 60.5
57 60.557.5 6156.5 60.552.5 58.550 61.553 6151 66
50.5 64.554 65.5
52.5 67.551.5 63.551 6248 62.553 58.550 63 5
23/05/2012 61.5
22/05/2012 64
E 45 OPC + GGPS Columns from Ground to 1st floor Block A 25/04/2012 02/05/2012 50
21/05/2012 65
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 2 to basement 1 flor @ block B2 and retaining wall from basement 1 to Ground floor @
Block B-2 & C-1 24/04/2012 01/05/2012 51.5
20/05/2012 60
D 45OPC + GGPS + MS + self complacting
admixer
Core wall from basement 2 to basement 1 flor @ block C2 and Staircase wall from basement 2 to basement 1 floor @ Block B2
Block B-2 & C-2 23/04/2012 30/04/2012 52
20/05/2012 60.5
E 45 OPC + GGPS Columns from Ground to 1st floor Block A 22/04/2012 29/04/2012 52
B 45 OPC + GGPS + MS Columns from basement 2 to basement 1 (B2 to B1) floor Block B-2 22/04/2012 29/04/2012 57
50 63.5424742
56 68.555.5 62.557 67.5
49.5 6545 67.550 63.550 62.557 56.5
50.5 6469 73.5
64.5 75D 45OPC + GGPS + MS + self complacting Retaining wall from basement 2
t b t 1 fl @ bl k B2 Block B-2 30/04/2012 07/05/2012 66.5 28/05/2012 74
OPC + GGPS + MS Slab at Basement 1 floor level
OPC + GGPS Columns & Core wall from Ground to 1st floorE 45
B 45
Block A 28/04/2012
Block C-2 30/04/2012
26/05/2012 65
06/05/2012 52.5 28/05/2012 61
66
testing after 5 days 01/05/2012 43.5
03/05/2012
05/05/2012 48.5
Block B-1 26/04/2012 56 24/05/2012B 45 OPC + GGPS + MS Slab at Basement 1 floor level
B 45 OPC + GGPS + MS Slab at Basement 1 floor level Block B-1 26/04/2012
64.5 7566 72.558 6759 65.559 67
66.508/05/2012 59 29/05/2012
45 p gadmixer to basement 1 flor @ block B2 66.5 74
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from basement 1 to Ground floor @ Block C1 Block C-1 01/05/2012
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
52.5 56.554.5 5747 59.546 56
47.5 5449.5 5643 60
40.5 57.545.5 58.555.5 70
49 68
51 73 5
D 45OPC + GGPS + MS + self complacting
admixer
Staircase wall (CW6) from 1st basement to Ground floor at Block B-1 & Staircase wall (CW10) from 1st basement to
d fl t Bl k C 1
04/06/2012 70.5
12/05/2012 43
Block B-1 & Block C-1 07/05/2012 14/05/2012 52
Block B-2 06/05/2012
Block C-2 02/05/2012
03/06/2012 59
10/05/2012 48
B 45 OPC + GGPS + MS Slab at Basement 1 floor level
30/05/2012 58
Block B-1 03/05/2012 31/05/2012 55B 45 OPC + GGPS + MS Columns from 1st basement to Ground floor
09/05/2012 51B 45 OPC + GGPS + MS Columns from 1st basement to Ground floor
51 73.5
54.5 59
55 56.5
54.5 57.5
58.5 73
58 73
64.5 71.5
66.5 79
73.5 7917/05/2012 71.5 07/06/2012 79
16/05/2012 60 06/06/2012 72.5
D 45OPC + GGPS + MS + self complacting
admixer
Staircase wall (CW5) ,Ramp wall, Retaining wall from 1st basement to ground floor at Block B-1 & Core wall (CW8) from 1st basement to ground
Block B-1 & Block C-2 10/05/2012
15/05/2012 55 05/06/2012 58
D 45OPC + GGPS + MS + self complacting
admixer
Core wall (CW6) from 1st basement to ground floor at Block B-1 & Core wall & Staircase wall (CW9) from 1st basement to ground floor at Block C 2
Block B-1 & Block C-2 09/05/2012
B 45 OPC + GGPS + MS
Columns from 1st basement to Ground floor at Block B-1 & Columns from 1st basement to Ground floor at Block C-2
Block B-1 & Block C-2 08/05/2012
ground floor at Block C-1
74.5 79.5
54 6049 60.5
50.5 5844 53.5
43.5 57.546 5850 66
55.5 66
56 63.5
54 6557 6523/05/2012 54 13/06/2012 66
23/05/2012 54 13/06/2012 65
B 45 OPC + GGPS + MS Slab - Ground floor at Block C-1 Block C-1 16/05/2012
22/05/2012 44.5 12/06/2012 56
E 45 OPC + GGPS Core wall & Columns from 1st floor to 2nd floor at Block A Block A 16/05/2012
21/05/2012 51 11/06/2012 59.5
B 45 OPC + GGPS + MS Columns from 1st basement to ground floor at Block B-2 Block B-2 15/05/2012
E 45 OPC + GGPS Slab - 1st floor at Block A Block A 14/05/2012
from 1st basement to ground floor at Block C-2
51 6849 61.5
49.5 66.550.5 61.5
24/05/2012 50 14/06/2012 63D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall & Ramp wall from 1st basement to Ground floor at Block B-1
Block B-1 17/05/2012
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
56.5 59
53.5 61
56.5 59.5
61.5 75
66 74.5
65.5 7544 5448 57
49.5 5657 69.5
715945 Columns from Ground to 1st
29/05/2012 47
26/05/2012 64 16/06/2012 75
E 45 OPC + GGPS Columns from Ground to 1st floor at Block C-1 Block C-1 22/05/2012 19/06/2012 56
24/05/2012 55.5 14/06/2012 60
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from 1st basement to ground floor at Block C-2 & Staircase wall (CW7) from 1st basement to ground floor at Block B-2
Block C-2 & Block B-2 19/05/2012
E 45 OPC + GGPS Columns from 1st to 2nd floor at Block A Block A 17/05/2012
60.5 73.559.5 7056 74.561 71.5
59.5 6749 71
54.5 6853 69.563 7161 70.561 7358
57 5
71Block C-1 23/05/2012 30/05/2012 59E 45 OPC + GGPS Columns from Ground to 1st floor at Block C-1
29/05/2012 05/06/2012 57 26/06/2012
26/05/2012 02/06/2012 62 23/06/2012 71.5
B 45 OPC + GGPS + MS Slab Ground floor at Block C 2 Block C 2
24/05/2012 31/05/2012 52 21/06/2012 69.5
B 45 OPC + GGPS + MS Columns from 1st basement to ground floor at Block B-2 Block B-2
20/06/2012
30/05/2012 59 20/06/2012 71
D 45OPC + GGPS + MS + self complacting
admixer
Retaining wall from 1st basement to ground floor at Block B-2
Block B-2
B 45 OPC + GGPS + MS Slab - Ground floor at Block B-1 Block B-1 23/05/2012
57.55642 4740 53
41.5 48.558 66
59.5 6860.5 6762.5 7455.5 7358.5 744645
43 504/06/2012 11/06/2012 45 02/07/2012
03/06/2012 10/06/2012 59 01/07/2012 73.5
E 45 OPC + GGPS Staircase wall (CW5) & Columns from Ground floor to 1st floor at Block B
Block B
30/05/2012 06/06/2012 41 27/06/2012 49.5
B 45 OPC + GGPS + MS Slab - Ground floor at Block B-2 Block B-2
29/05/2012 05/06/2012 57 26/06/2012
E 45 OPC + GGPS Slab - 2nd floor at Block A Block - A
B 45 OPC + GGPS + MS Slab - Ground floor at Block C-2 Block C-2
09/06/2012 59 30/06/2012 67E 45 OPC + GGPS
Staircase wall (CW5) at Block B,(CW10) & Core wall (CW11) at Block C from ground to 1st floor
Block B & C 02/06/2012
43.552
48.551
05/06/2012 12/06/2012 50.5 03/07/2012E 45 OPC + GGPS
Core wall & columns from 2nd to 3rd floor at Block A & Columns from Ground to 1st floor at Block B
Block A & B
Block B
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
49.5
51.5
54.5
51.5
55
56.5
4949.548.555.5
09/07/201218/06/2012 4911/06/2012
09/06/2012 16/06/2012 54 07/07/2012
E 45 OPC + GGPS Columns from Ground to 1st floor at Block C-2 Block C-2
06/06/2012 13/06/2012 52 04/07/2012
E 45 OPC + GGPS
Columns from 2nd to 3rd floor at Block A, Core wall (CW6) & Columns from Ground to 1st floor at Block B & Columns from Ground to 1st floor at Block C-2 & Attic slab at 1st floor at Block -
Block A,Block B, Block C-2 &
Block C
E 45 OPC + GGPS Core wall (CW-6) & columns from Ground floor to 1st floor at Block B
Block B
5351.548.550.548
35.535
36.546.54746
42.544 5
testing after 3 days 21/06/2012 36
16/07/2012
11/07/2012
E 45 OPC + GGPSCore wall (CW8) & columns from Ground floor to 1st Block C-2 20/06/2012 27/06/2012 43 18/07/2012
45 OPC + GGPS Slab - 3rd floor at Block A Block A 18/06/2012 16/07/201225/06/2012 46.5
E 45 OPC + GGPS Slab - 3rd floor at Block A Block A 18/06/2012
49
E
53
E 45 OPC + GGPS Columns & Core wall (CW9) from Ground to 1st floor at Block C-2
Block C-2 18/06/2012 25/06/2012
E 45 OPC + GGPS Slab - 1st floor at Block C-1 Block C-1 13/06/2012 20/06/2012
44.541
47.553.552.544
46.544.5
3228.530
testing after 3 days
23/07/2012
28/06/2012 30
E 45 OPC + GGPS Slab - 1st floor at Block B Block B 25/06/2012 02/07/2012
19/07/2012
E 45 OPC + GGPS Slab - 1st floor at Block B Block B 25/06/2012
E 45 OPC + GGPS Columns & wall from 3rd to 4th floor at Block A Block A 21/06/2012 28/06/2012 45
E 45 OPC + GGPS Columns from 3rd to 4th floor at Block A Block A 20/06/2012 27/06/2012 51 18/07/2012
E 45 OPC + GGPS from Ground floor to 1st floor,Block C-2
Block C-2 20/06/2012 27/06/2012 43 18/07/2012
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
10.0 QUALITY REPORT
10.2 NCR & SITE INSTRUCTIONS LOG
Al Muraqqabat Mixed Use DevelopmentMonthly Progress ReportNCR Tracking & Site Instructions Log - Rev 00
DATA DATE
Description
NCR
SI
S.N
StatusIssue Date
30-Jun-12
Notes
Sit
e In
stru
ctio
ns
COLOR CODING
Opened
CLOSED
Actual Closure Date
ASGC Reply Date
Type of Submittal
Returned Date
No
n C
on
firm
Rep
ort
Statusopened/Clo
sed
Area
A-NCR
1 Gen. Concrete Cover X 13-Feb-12 13-Feb-12 13-Feb-12 CL Closed
2 Gen. Supervision of Work - Skilled Staff Attendance X 21-Feb-12 11-Mar-12 01-Apr-12 CL Closed
3 Gen. Supervision of Work X 22-Feb-12 29-Feb-12 18-Mar-12 CL Closed
3 Gen. Development length for columns X 29-Feb-12 13-Mar-12 CL Closed
5 Gen. Earthlings Incomplete Works X 07-Mar-12 26-Mar-12 01-Apr-12 CL Closed
6 Gen. Non Compliance to our site instruction X 15-Mar-12 26-Mar-12 01-Apr-12 CL Closed
7 Gen. Non Compliance to our site instruction X 18-Mar-12 OP Opened
8 Gen. Non Compliance for quality assurance to the cast placement X 30-Apr-12 03-May-12 12-May-12 Closed
B-Site Instructions
1 QC/CM Leakages - Water proofing works X 21-Feb-12 29-Feb-12 18-Mar-12 C Closed
1 QC,CM, TM, Q Assessemnt Bases for Mock-up Work X 06-Mar-12 O Opened
2 QC/CM Waterproofing work System X 22-Feb-12 29-Feb-12 18-Mar-12 C Closed
3 QC/CM Steel Chairs for Raft X 23-Feb-12 27-Feb-12 18-Mar-12 C Closed
4 QC/CM Engineer's Concern over Excavation Near Lift Pit X 27-Feb-12 11-Mar-12 13-Mar-12 C Closed
5 CM Curing work - Curing for Raft (Part A) X 29-Feb-12 11-Mar-12 13-Mar-12 C Closed
6 QC/CM Steel reinforcement Missed Connections X 03-Mar-12 28-May-12 28-Jun-12 C Closed
7 CM Excavation works - Engineer's Concern over Excavation near lift pit X 29-Feb-12 11-Mar-12 15-Mar-12 C Closed
8 PM Space for Car Parking X 13-Mar-12 01-Apr-12 15-Apr-12 C Closed
9 CM/QC Lack of Coordination Between site team and surveyor X 13-Mar-12 28-May-12 28-Jun-12 C Closed
11 QC Excavation Work at Block C X 15-Mar-12 28-May-12 28-Jun-12 C Closed
12 CM/QC Development Length of Pullout Bar of Staircase X 18-Mar-12 02-Apr-12 08-Apr-12 C Closed
13 TM/QC Undertaking Letter X 09-Apr-12 O Opened
14 CM/QC Site Observation - to complied by Contractor X 09-Apr-12 14-Apr-12 08-May-12 C Closed
15 QC Casting without Information X 12-Apr-12 14-Apr-12 15-Apr-12 C Closed
16 CM Authorities Approval X 16-Apr-12 02-May-12 05-May-12 C Closed
17 Quality of Works X 23-Apr-12 30-Apr-12 13-May-12 C Closed
18 Lack of Attendance X 25-Apr-12 30-Apr-12 28-Jun-12 C Closed
19 Etisalat Dead Junction Box X 30-Apr-12 O Opened
20 CM & QA/QC Quality of Works X 03-May-12 28-May-12 28-Jun-12 C Closed
21 CM & QA/QC Rusted Old Scaffolding Material Used for Slab X 03-May-12 28-May-12 28-Jun-12 C Closed
22 CM & QA/QC More Cracks Observed on "C2" at 1st Basement Slab X 09-May-12 19-May-12 C Closed
File : -Engineering Tracking Chart 1 of 1 Printed On :- 05/07/2012 at 08:37
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
11.0 FINANCIAL REPORT
11.1 SCHEDULE OF PAYMENTS
11.2 SUMMARY OF VO’S
11.3 SUMMARY OF CLIAMS
11.4 SUMMARY OF PROVISIONAL SUM
11.5 FORECASTING OF MONTHLY INVOICES (BASELINE)
Al Muraqqabat Mixed Use Development Monthly Progress Report
Schedule of Payments
Date Date :- 30-Jun-2012
CLIENT PAYMENT CERTIFICATE
Payment Gross Net Work Done Net Amount
No. Amount Amount up to Certified
1 28,500,000.00 28,500,000.00 Adv. Payment 08-Jan-12 10-Jan-12 28,500,000.00 - - - 29-Jan-12 0 28,500,000.00 18-Jan-12 Progress Payment - 01
2 318,815.00 318,815.00 31,881.50 - 30-Dec-11 03-Jan-12 14-Feb-12 286,933.50 - 31,881.50 - 28-Feb-12 33 286,933.50 01-Apr-12 Progress Payment - 02
RemarksAdvance Payment Recovery
Advance Payment Recovery
Due for Payments
Payments Received DateRetention Money
RecoveryRetention Money
AppliedRetention Money
Applied
Delays Recorded
Net Amount ReceivedDate of Application
submission
CONTRACTORS PAYMENT APPLICATION
Date of Certification submission
Retention Money Recovery
3 8,951,396.02 8,377,380.03 927,021.10 - 28-Feb-12 29-Feb-12 21-Mar-12 7,938,105.33 - 822,503.88 822,503.88 24-Apr-12 5 7,938,105.33 29-Apr-12 Progress Payment - 03
4 6,996,437.47 6,838,549.54 1,515,962.19 822,503.88 20-Mar-12 22-Mar-12 4-Apr-12 5,247,823.93 - 1,378,688.21 822,503.88 17-May-12 0 5,247,823.93 14-May-12 Progress Payment - 04
5 9,662,419.05 10,192,883.30 2,226,912.17 1,378,688.21 20-Apr-12 22-Apr-12 3-May-12 9,243,778.62 - 2,214,757.63 1,378,688.21 17-Jun-12 0 9,014,584.61 17-Jun-12 Progress Payment - 05
6 7,177,209.51 7,304,138.58 2,923,897.98 2,214,757.63 20-May-12 22-May-12 05-Jun-12 6,466,340.42 - 2,833,159.85 2,214,757.63 17-Jul-12 Progress Payment - 06
7 9,528,958.52 7,484,602.48 3,725,725.77 2,833,159.85 20-Jun-12 21-Jun-12 16-Aug-12 Progress Payment - 07
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Total 69,016,368.93 - 11,351,400.71 7,249,109.57 57,682,981.80 - 2,833,159.85 2,214,757.63 50,987,447.37
File Name:01 Payments Log 30.06.2012 Page 1 of 1 Printed On :05/07/2012 at08:12
Date Date :- 30-Jun-2012
Date Reference Date Reference
1Changes in Contract Drawings toincorporate the Authorities requirements(DM & DEWA)
27/Nov/11BY/Dr.A/1252/T
rans/269/11ASGC/L/DB/117/17/1
1 2,372,782.95 2,188,032.58 VOR # 01
2Reimbursement of Building permit fees andthe Drainage fees
19/Dec/11BY/1252/Sd/Sz/
1193/11ASGC/P269/LT-
0018/2011 318,815.00 318,815.00 VOR # 02
3PS adjustment for hiring of Mock-uplocation
3/Jan/12BY/1252/Dr.A/S
k/009/12- (70,806.00) (70,806.00) VOR # 03
4Mockup Works - Carpet & KitchenAppliances
6/Mar/12SI: AK/MO-up/001/12
ASGC/P269/BY/LT-51 & 58/2012
(1,263,283.72) (1,265,362.00) VOR # 04R
5Mockup Works - Ironmongery & WoodenFlooring
6/Mar/12SI: AK/MO-up/001/12
ASGC/P269/BY/LT-57 & 65/2012
21,138.52 19,942.00 VOR # 05R
M k W k D k (Bl k k SI AK/MO ASGC/P269/DT
No. SubjectASGC Estimated
Amount (AED)Approved Amount
(AED)Remark
ASGC's SubmissionEngineer's Instruction
Al Muraqqabat Mixed Use Development Monthly Progress Report
(Clause 13.1) SUMMARY OF VO's
6Mockup Works - Dayworks (Blockwork,Plaster & RCC)
6/Mar/12SI: AK/MO-up/001/12
ASGC/P269/DT-014/2012
200,491.58 174,340.50 VOR # 06R
7 Mockup Works - Tiles 6/Mar/12SI: AK/MO-up/001/12
ASGC/P269/BY/LT-0063/2012
66,401.58 62,643.00 VOR # 07R
8 IT Equipments for Engineer/ Employer 1/Feb/13BY/1252/Vq/Sz/
LT-0006/12ASGC/P269/BY/LT-
0070/2012 (537,425.68) (546,628.00) VOR # 08R
9 Sanitary Ware & Accessories 6/Mar/12SI: AK/MO-up/001/12
ASGC/P269/BY/LT-0098/2012
24,543.51 23,154.25 VOR # 09
10 Mockup Works - Light Fittings (Huda) 6/Mar/12SI: AK/MO-up/001/12
26/Apr/12ASGC/P269-BY/LT-
146/2012 34,430.00 34,430.00 VOR # 10
11Mockup Works - Loose Furniture (CasaShamuzzi)
6/Mar/12SI: AK/MO-up/001/12
25/Apr/12ASGC/P269-BY/LT-
0143/2012 100,000.00
12Mockup Works - Loose Furniture (FourFrontiers)
6/Mar/12SI: AK/MO-up/001/12
26/Apr/12ASGC/P269-BY/LT-
0145/2012 87,620.00
13 Mockup Works - Dayworks (March 2012) 6/Mar/12SI: AK/MO-up/001/12
12/Apr/12ASGC/P269/DT-
022/2012 48,823.25
14 Mockup Works - Dayworks (20th April 2012) 6/Mar/12SI: AK/MO-up/001/12
21/Apr/12ASGC/P269/DT-
024/2012 78,350.68
15 Mockup Works - DEWA Bill Payment 6/Mar/12SI: AK/MO-up/001/12
19/Apr/12ASGC/P269/LT-
0133/2012 3,400.00
16Mockup Works - Staff Salary (Jan'12 toMar'12)
6/Mar/12SI: AK/MO-up/001/12
9/Apr/12ASGC/P269/LT-
0124/2012 240,000.00 Submitted
S / O SGC/ /
VOR # 11 (Amount to
be corrected) 169,775.35
VOR # 12 133,986.03
17Mockup Works - Staff Salary (Apr'12 toMay'12)
6/Mar/12SI: AK/MO-up/001/12
19/May/12ASGC/P269-BY/LT-
0163/2012 157,500.00 Submitted
18 Mockup Works - Dayworks (20th May 2012) 6/Mar/12SI: AK/MO-up/001/12
28/May/12ASGC/P269/DT-
030/2012 89,854.22 Submitted
19Mockup Works - Glass & Mirror (Al SabiGlass)
6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 8,530.00 Submitted
20Mockup Works - Aluminium & Glazing(Alumco)
6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 39,917.00 Submitted
21Mockup Works - Thresholds (LeaderMarble)
6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 1,240.00 Submitted
22Mockup Works - False Ceiling Works(ASSM)
6/Mar/12SI: AK/MO-up/001/12
5/Mar/12ASGC/P269-BY/LT-
0071/2012 16,086.00 Submitted
23 Mockup Works - Painting (Al Shafar Paint) 6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 14,300.00 Submitted
24Mockup Works - Wall Cover (Vescom,Omnova, Trident)
6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 4,388.00 Submitted
25 Mockup Works - Curtains (Ixsa Trading) 6/Mar/12SI: AK/MO-up/001/12
1/May/12ASGC/P269-BY/LT-
0152/2012 39,040.44 Submitted
26Mockup Works - Loose Fabric (IxsaTrading)
6/Mar/12SI: AK/MO-up/001/12
1/May/12ASGC/P269-BY/LT-
0151/2012 11,367.00 Submitted
27 Mockup Works - Wooden & Joinery (ASI) 6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 146,570.00 Submitted
28 Mockup Works - MEP (ASU) 6/Mar/12SI: AK/MO-up/001/12
22/Apr/12ASGC/P269-BY/LT-
134/2012 87,594.00 Submitted
29 Mockup Works - Safe & Mini Bar (VingCard) 6/Mar/12SI: AK/MO-up/001/12
26/May/12ASGC/P269-BY/LT-
0172/2012 3,130.00 Submitted
30 Mockup Works - TV (Eurostar) 6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 4,400.00 Submitted
31Mockup Works - Wastebin, Scale, Hairdryer(Sultaco)
6/Mar/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0180/2012 2,200.00 Submitted
32IT Equipment Consumables for Engineer/Employer for March'12, April'12 & May'12
1/Feb/13BY/1252/Vq/Sz/
LT-0006/1213/Jun/12
ASGC/P269-BY/LT-0188/2012
21,132.00 Submitted
33Mockup Works - Corner Sofa, Ottoman(Four Frontiers)
24/Jun/12SI: AK/MO-up/001/12
6/Jun/12ASGC/P269-BY/LT-
0198/2012 11,598.00 Submitted
34Revised 1st Basement & Ground Floor Plan -Additional CBS Room and Gate Barriers
8/Mar/12BY/1252/AK/SZ/
Trans/0026 & 24/Jun/12
ASGC/P269-BY/LT-0167/2012
67,063.24 Submitted
2,451,191.57 1,242,322.71
285,000,000.00
287,451,191.57
Original Contract Amount (AED)
Estimated Final Contract Amount (AED)
Total Amount (AED)
File :- 02 Variation Orders Log 30.06.2012 Page 1 of 1 Printed On :- 05/07/2012 at 08:12
Date Date :- 30-Jun-2012
Date Reference Date Reference
1 1 4-Jan-12 BY/Mz/1252/Trans/0009/11 8-Feb-12 ASGC/P269-BY/LT-
0048/2012Additional works due to Issued for ConstructionDrawings NA 16/Feb/12 BY/1252/Vq/Sz/
LT-0008/12 Rejected by the Engineer
2 Mockup Works - Staff Salary
2 1 8 A 12 ASGC/P269-BY/LT- Actual Cost of Staff allocated for Mockup NA 24/A /12 BY/1252/Vq/Sz/ 240 000 00 R j d b h E i
Al Muraqqabat Mixed Use Development Monthly Progress Report
(Clause 13.1 & 20) SUMMARY OF NOTICES
Engineer's InstructionRemarkSr No. Event Description
Contractor's Notice EOT Claim if any
Date on Engineer Replied
Reference for Engineer's
Reply
Variation Claim if any
2.1 8-Apr-12 ASGC/P269 BY/LT0124/2012
Actual Cost of Staff allocated for MockupWorks (Jan'12, Feb'12 & Mar'12) NA 24/Apr/12 BY/1252/Vq/Sz/
LT-0028/12 240,000.00 Rejected by the Engineer
2.2 19-May-12 ASGC/P269-BY/LT-0163/2012
Actual Cost of Staff allocated for MockupWorks (Apr'12 & May'12) NA 24/May/12 BY/1252/Vq/Sz/
LT-0052/12 157,000.00 Rejected by the Engineer
3 3 21-Mar-12 BY/1252/AK/SZ/Trans/0036/12 17-Apr-12 ASGC/P269/BY/LT-
0104/2012
Additional and/or Varied works due to RevisedConstruction Drawings for 1st Basement &Ground Floor
NA 67,063.24 Variation submitted
Engineer's response to mitigate
Under review by ASGC
5 21-May-12 ASGC/P269-BY/LT-0164/2012
Additional and/or Varied works due to RevisedIssued for Construction Drawings
5.1 8-May-12 ASGC/P269/DT-027/2012
Extension of Time Particulars as of end of April2012
5.2 31-May-12 ASGC/P269-BY/LT-0176/2012 Variation Particulars Submitted Variation to be submitted5
24-Apr-12 BY/1252/VQ/SZ/Trans/55 to 66/12
BY/1252/Vq/Sz/LT-0032/1218-Apr-12 ASGC/P269/LT-
0115/2012
Major Conflicts between Architectural, MEP &Interior Design Drawings issued forConstruction
27 Days 1/May/124 21-Mar-12 BY/1252/Vq/Sz/LT-0019/12
6-Mar-12 AK/MO-up/001/122
4
y 0176/2012
5.3 4-Jun-12 ASGC/P269/DT-033/2012
Extension of Time Particulars as of end of May2012 45 Days Engineer's response under review
5.4 28-Jun-12 BY/1252/Vq/Sz/LT-0076/12 3-Jul-12 ASGC/P269-BY/LT-
0210/2012Additional and/or Varied works due to RevisedID Specifications
6 6 8-May-12 RFI-078 & 098 23-May-12 ASGC/P269-BY/LT-0170/2012
Addition &/or Varied Works due to Changes inUpstand at Planter Area & Increase in Parapet NA 31/May/12 BY/1252/Vq/Sz/
LT-0056/12 Rejected by the Engineer
7 7 Program of Works 9-Jun-12 ASGC/P269-BY/LT-0181/2012
Outstanding Nomination by the Engineer for theLaundry & Main Kitchen equipments for Block 10/Jun/12 BY/1252/Vq/Sz/
LT-0063/12 Engineer's response under review
8 8 Program of Works 25-Jun-12 ASGC/P269-BY/LT-0192/2013
Disruption &/or delay to progress of the worksdue to Civil Defence Rejection of CentralBattery Shop Drawings
464,063.24 Total for Claims
03 Notices Log 30.06.2012 Page 1 of 1 Printed On :- 05/07/2012 at 08:13
Date Date :- 25-Jun-2012
Date Reference
1 P1/8R1-A to K IT Equipments for Engineer/ Employer 13-Feb-12 BY/1252/Vq/Sz/0006/12 700,000.00 153,372.00 VO # 08R (to be finalised)
2 P1/12-A Mockup Warehouse Hire Charges 3-Jan-12 BY/1252/Dr.A/Sk/0009/12 300,000.00 229,194.00 VO # 03
3 P1/12 C to J Mockup Works 6 Mar 12 AK/MO up/001/12 1 300 000 00 314 717 75 VO # 04R, 05R,
Al Muraqqabat Mixed Use Development Monthly Progress Report
(Clause 13.4 b) SUMMARY OF PROVISIONAL SUMS
RemarkSr No. Item DescriptionEngineer's Instruction Provisional Amount
(AED)Approved Amount
(AED)Expected Date of
Nomination
3 P1/12-C to J Mockup Works 6-Mar-12 AK/MO-up/001/12 1,300,000.00 314,717.75 , ,06R, 07R, 09 (to be
P.2/1-A Laundry & Main Kitchen for Block B 10,600,000.00 6,700,000.00
P.2/1-B Allow for Attendance; MEP Provisions, Builders Work &Co-ordination 149,563.00
P.2/1-C Allow for OH & P -
P.2/1-D Cooking Station at Public Area - Block B 20,000.00
P.2/1-E Allow for Attendance; MEP Provisions, Builders Work &Co-ordination 2,119.00
P.2/1-F Allow for OH & P -
P.2/2-A Counters at Public Areas - Block B 95,000.00
P 2/2 B All f Att d B ild W k & C di ti 7 162 00
4
5
6
28/May/12
12/Jun/12
12/Jun/12
10-Jun-12 BY/1252/Vq/Sz/LT-0061/2012
Incomplete Nomination, VO to
be issued
P.2/2-B Allow for Attendance; Builders Work & Co-ordination 7,162.00
P.2/2-C Allow for OH & P -
P.2/2-D External & Internal Signages and PromotionalSignages
1,500,000.00
P.2/2-E Allow for Attendance; Builders Work & Co-ordination 31,619.00
P.2/2-F Allow for OH & P -
P.2/2-G Façade Lighting 500,000.00
P.2/2-H Allow for Attendance; Builders Work & Co-ordination 15,032.00
P.2/2-J Allow for OH & P -
P 2/3 A G i E i t & A i Bl k C 500 000 00
6
7
8
12/Jun/12
10/Jun/12
22/Jul/12
P.2/3-A Gymnassium Equipments & Accessories - Block C 500,000.00
P.2/3-B Allow for Attendance; Builders Work & Co-ordination 13,203.00
P.2/3-C Allow for OH & P -
15,733,698.00 7,397,283.75 Total Amount (AED)
9 13/Feb/13
04 Provisional Sums Log 30.06.2012 Page 1 of 1 Printed On :- 05/07/2012 at 08:13
Contract Amount : Advance Payment ( 10 % ) : 28,800,000.00 Advance Payment Bond Date :Change Orders Approved to Date : Retention Amount ( 10 % ) : 14,400,000.00 Performance Bond Date :Current Contract Amount : Contract Start Date : 15-Feb-12 Other Bonds :Invoice Currency : AED Contract Completion Date : 15-Nov-13
Due Date Duration after Approval is : 56 Days
288,000,000.00
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Forecasting of Monthly Invoices
288,000,000.00
Value of Work (Monthly)
Value of Work (Accum.) Retention Release Advance Payment Retention Money Others Total Deduction Net Invoice Actual
A B C D E F (G)=D+E+F Net =(A+C-G) Date Amount Difference(Days)
1 Advance Payment 28,800,000 0 28,800,000 28,800,000 15-Feb-12 31-Mar-122 29-Feb-2012 6,332,858 6,332,858 - 633,286 - 633,286 5,699,572 34,499,572 29-Feb-12 25-Apr-123 30-Mar-2012 7,606,199 13,939,057 633,285.80 760,620 - 760,620 7,478,865 41,978,437 30-Mar-12 25-May-124 30-Apr-2012 6,361,512 20,300,569 760,619.90 636,151 - 636,151 6,485,981 48,464,418 30-Apr-12 25-Jun-125 30-May-2012 3,468,385 23,768,954 636,151.20 346,839 - 346,839 3,757,698 52,222,116 30-May-12 25-Jul-126 30-Jun-2012 4,204,325 27,973,279 346,838.50 420,433 - 420,433 4,130,731 56,352,847 30-Jun-12 25-Aug-127 30-Jul-2012 6,666,989 34,640,268 420,432.50 1,666,747 666,699 - 2,333,446 4,753,975 61,106,822 30-Jul-12 24-Sep-128 30-Aug-2012 7,509,703 42,149,971 666,698.90 1,877,426 750,970 - 2,628,396 5,548,006 66,654,828 30-Aug-12 25-Oct-129 30 Sep 2012 9 658 502 51 808 473 750 970 30 2 414 626 965 850 3 380 476 7 028 997 73 683 824 30 Sep 12 25 Nov 12
Cert. / Invoice
No.Month Cumulative Invoice Submitted
Date
Forcast Date of Releasing the
Invoices
GROSS INVOICE DEDUCTIONS
Remarks
9 30-Sep-2012 9,658,502 51,808,473 750,970.30 2,414,626 965,850 - 3,380,476 7,028,997 73,683,824 30-Sep-12 25-Nov-1210 30-Oct-2012 17,791,959 69,600,432 965,850.20 4,447,990 1,779,196 - 6,227,186 12,530,624 86,214,448 30-Oct-12 25-Dec-1211 30-Nov-2012 29,804,859 99,405,291 1,779,195.90 7,451,215 2,980,486 - 10,431,701 21,152,354 107,366,802 30-Nov-12 25-Jan-1312 30-Dec-2012 30,623,988 130,029,279 2,980,485.90 7,655,997 3,062,399 - 10,718,396 22,886,078 130,252,880 30-Dec-12 24-Feb-1313 30-Jan-2013 33,447,904 163,477,183 3,062,398.80 3,286,000 3,344,790 - 6,630,790 29,879,512 160,132,393 30-Jan-13 27-Mar-1314 28-Feb-2013 33,732,851 197,210,034 3,344,790.40 3,373,285 - 3,373,285 33,704,356 193,836,749 28-Feb-13 25-Apr-1315 30-Mar-2013 33,436,034 230,646,068 3,373,285.10 3,343,603 - 3,343,603 33,465,716 227,302,465 30-Mar-13 25-May-1316 30-Apr-2013 26,162,126 256,808,194 3,343,603.40 2,616,213 - 2,616,213 26,889,517 254,191,981 30-Apr-13 25-Jun-1317 30-May-2013 6,466,792 263,274,986 2,616,212.60 646,679 - 646,679 8,436,325 262,628,307 30-May-13 25-Jul-1318 30-Jun-2013 1,947,358 265,222,344 646,679.20 194,736 - 194,736 2,399,301 265,027,608 30-Jun-13 25-Aug-1319 30-Jul-2013 1,030,287 266,252,631 194,735.80 103,029 - 103,029 1,121,994 266,149,602 30-Jul-13 24-Sep-1320 30-Aug-2013 4,732,320 270,984,951 103,028.70 473,232 - 473,232 4,362,117 270,511,719 30-Aug-13 25-Oct-1321 30-Sep-2013 9,343,675 280,328,626 473,232.00 934,368 - 934,368 8,882,540 279,394,259 30-Sep-13 25-Nov-1322 30-Oct-2013 6,547,074 286,875,700 934,367.50 654,707 - 654,707 6,826,734 286,220,993 30-Oct-13 25-Dec-1323 30-Nov-2013 1,124,302 288,000,002 654,707.40 112,430 - 112,430 1,666,579 287,887,572 30-Nov-13 25-Jan-1424 30-Dec-2013 112,430.20 112,430 288,000,002 30-Dec-13 24-Feb-14
288,000,002 - 28,800,000.00 28,800,000.20 - 57,600,000 288,000,002Total
File : 05. Monthly Invoice Status Page 1 of 2 Printed On :14/04/2012 at 10:28
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Forecasting of Monthly Invoices
AED 35,000,000.00
AED 40,000,000.00
File: 05. Monthly Invoice Status Page 2 of 2 Printed On : 14/04/2012 at 10:28
28,80
0,000
21,15
2,354 22
,886,0
78
29,87
9,512
33,70
4,356
33,46
5,716
26,88
9,517
AED 15,000,000.00
AED 20,000,000.00
AED 25,000,000.00
AED 30,000,000.00
, ,
Mont
lhy P
aym
ent
5,699
,572 7,4
78,86
5
6,485
,981
3,757
,698
4,130
,731
4,753
,975
5,548
,006 7,0
28,99
7
12,53
0,624
8,436
,325
2,399
,301 4,3
62,11
7
8,882
,540
6,826
,734
112,4
30
AED 0.00
AED 5,000,000.00
AED 10,000,000.00
Forecast Date of Releasing the Invoices
Planned Monthly 28,800,000 5,699,572 7,478,865 6,485,981 3,757,698 4,130,731 4,753,975 5,548,006 7,028,997 12,530,624 21,152,354 22,886,078 29,879,512 33,704,356 33,465,716 26,889,517 8,436,325 2,399,301 1,121,994 4,362,117 8,882,540 6,826,734 1,666,579 112,430
Planned Accum. 28,800,000 34,499,572 41,978,437 48,464,418 52,222,116 56,352,847 61,106,822 66,654,828 73,683,824 86,214,448 107,366,802 130,252,880 160,132,393 193,836,749 227,302,465 254,191,981 262,628,307 265,027,608 266,149,602 270,511,719 279,394,259 286,220,993 287,887,572 288,000,002
Actual Monthly
Actual Accum.
Forecast Monthly
Forecast Accum.
Aug-12 Nov-12Oct-12Sep-12Mar-12 Apr-12 May-12
ForecastPlanned
Actual
Jun-12 Jul-12Feb-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Dec-13 Jan-14 Feb-14Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13
Forecast Accum. t
File: 05. Monthly Invoice Status Page 2 of 2 Printed On : 14/04/2012 at 10:28
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
12.0 PROGRESS PHOTOS
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Progress Photos for Block A
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:40
Elements Planned Pouring Date Actual Pouring Date Progress
Raft 11 March 2012 28 February 2012 100%
1st Basement Slab 12 April 2012 20 March 2012 100%
Ground Flor Slab 07 May 2012 18 April 2012 100%
1st Floor Slab 03 June 2012 14 May 2012 100%
2nd Floor Slab 01 July 2012 30 May 2012 100%
3rd Floor Slab 21 July 2012 18 June 2012 100%
4th Floor Slab 08 August 2012 In Progress 80%
Elements Planned Pouring Date Actual Pouring Date Progress
Columns at GF 17 May 2012 01 May 2012 100%
Core Walls at GF 14 May 2012 28 April 2012 100%
Columns at 1st Floor 13 June 2012 24 May 2012 100%
Core Walls at 1st Floor 10 June 2012 21 May 2012 100%
Columns at 2nd Floor 11 July 2012 05 June 2012 100%
Core Walls at 2nd Floor 08 July 2012 10 June 2012 100%
01. Third Floor Slab at Building A
ildi
Civil Work Architectural MEP (Incl. LPG)
Elevators External Facade
Façade Lighting
Façade Cleaning
Garbage & Linen Chute
52.98%
0% 0% 0% 0% 0% 0% 0%
65.39%
%Pld %Act
Building ‐ A
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:40
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Progress Photos for Block B
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:41
Elements Planned Pouring Date Actual Pouring Date Progress
Raft - B1 08 April 2012 30 March 2012 100%
Raft - B2 30 April 2012 12 April 2012 100%
1st Basement Slab - B1 26 April 2012 100%
1st Basement Slab - B2 06 May 2012 100%
Gound Floor Slab - B1 23 May 2012 100%
12 June 2012
10 July 2012Gound Floor Slab - B2 03 June 2012 100%
1st Floor Slab 05 August 2012 25 June 2012 100%
Elements Planned Pouring Date Actual Pouring Date Progress
Columns at 1st Bas. B1 26 June 2012 13 May 2012 100%
Core Walls at 1st Bas. B1 02 July 2012 10 May 2012 100%
Columns at 1st Bas. B2 26 June 2012 30 May 2012 100%
Core Walls at 1st Bas. B2 02 July 2012 20 May 2012 100%
Columns at Ground Floor 21 July 2012 20 June 2012 100%
Cores at Ground Floor 17 July 2012 10 June 2012 100%
10 July 2012
01. 1st Floor Slab at Building B
Building ‐ B
Civil Work Architectural MEP (Incl. LPG) Elevators External Facade Façade Lighting Façade Cleaning Garbage & Linen Chute
39.83%
0% 0% 0% 0% 0% 0% 0%
55.20%
%Pld %Act
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:41
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Progress Photos for Block C
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:41
Elements Planned Pouring Date Actual Pouring Date Progress
Raft - C1 08 March 2012 08 March 2012 100%
Raft - C2 30 April 2012 04 April 2012 100%
1st Basement Slab - C1 04 April 2012 100%
1st Basement Slab - C2 30 April 2012 100%
Gound Floor Slab - C1 16 May 2012 100%
07 June 2012
02 July 2012Gound Floor Slab - C2 29 May 2012 100%
1st Floor Slab - C1 13 June 2012 100%
1st Floor Slab - C2 30 June 2012 100%
Elements Planned Pouring Date Actual Pouring Date Progress
Columns at 1st Bas. C1 21 June 2012 16 April 2012 100%
Core Walls at 1st Bas. C1 27 June 2012 06 May 2012 100%
Columns at 1st Bas. C2 21 June 2012 22 May 2012 100%
Core Walls at 1st Bas. C2 27 June 2012 13 May 2012 100%
Columns at GF. C1 12 July 2012 02 June 2012 100%
Core Wall at GF. C1 09 July 2012 31 May 2012 100%
Columns at GF. C2 12 July 2012 23 June 2012 100%
Core Wall at GF. C2 09 July 2012 20 June 2012 100%
01. First Floor Slab at Building C - Part C1
02 July 2012
18 July 2012
02. First Floor Slab at Building C - Part C2
Civil Work Architectural MEP (Incl. LPG)
Elevators External Facade
Façade Lighting
Façade Cleaning
Garbage & Linen Chute
34.37%
0% 0% 0% 0% 0% 0% 0%
46.45%
%Pld %Act
Building ‐ C
02. First Floor Slab at Building C Part C2
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:41