MONTHLY MAJOR PROJECTS REPORT FOR

OCTOBER 2015

NANOENGINEERING & SCIENCE BUILDING – ARTIST RENDERING

PREPARED BY

TABLE OF CONTENTS

Project Number

Project Title Page

Glossary of Acronyms i

Major Projects Executive Summary iii

203928 Animal Research and Care Facility – Kurt Jensen 1

203835 Bothell Activities and Recreation Center – Eric McArthur 8

203801 Burke-Gilman Trail Corridor – Victoria Morris 15

202039 Denny Hall Renovation – Randy Everett 20

203880 Fluke Hall Renovation – Kurt Jensen 26

203512 Housing-Maple and Terry Halls – Will Sigman 30

204746 Life Sciences Building – Troy Stahlecker 37

204110 Medical Center Expansion Phase II–Montlake Tower – Ross Pouley 43

203593 Montlake Triangle Project – Andy Casillas 50

204878 NanoEngineering and Sciences Building (NESB) – Eric McArthur 56

203007 New Burke Museum – Eldon Tam/Ken Kubota 62

204350 North Campus Student Housing – Victoria Morris 66

203612 Police Department Facility – Ken Kubota 70

204701 Tacoma Urban Solutions Center – Jeannie Natta 77

204685 West Campus Utility Plant – Steve Harrison 81

Revised 1/9/14 i

GLOSSARY OF ACRONYMS FROM MONTHLY REPORT

AC Architectural Commission A/E Architect/engineer AHU Air handling unit ASF Assignable square feet ASI Architect’s supplemental

information BEST Budget Evaluation Study Team BIM Building information modeling CAD Computer-aided design CD Construction document CDF Controlled density fill CMU Concrete masonry unit CO Certificate of Occupancy COP Change order proposal COR Change order request CPM Critical path method CPO Capital Projects Office CUP Central Utility Plant CSSCR Center for Social Science and

Research CUCAC City-University Community

Advisory Committee CY Cubic yard (also CUYD) DAHP WA State Department of

Archeology and Historic Preservation

D-B Design-build DBOM Design/build/operate/maintain DD Design development DPD Seattle Department of Planning

and Development DRB Disputes Resolution Board EH&S Environmental Health & Safety EIS Environmental Impact Statement ESCO Energy Services Company FRP Fiberglass reinforced polymer FCUFS Faculty Council on University

Facilities and Services FF&E Furnishings, fixtures and

equipment GC/CM General contractor/construction

manager GCC Guaranteed construction cost

GSF Gross square feet HFS Housing and Food Services HVAC Heating, ventilation, and air

conditioning JOC Job order contracting ICA Intercollegiate Athletics LEED Leadership in Energy and

Environmental Design MACC Maximum allowable construction

cost MEP Mechanical, electrical and

plumbing MHSC Magnuson Health Sciences

Center MOA Memorandum of Agreement MOC Management Oversight

Committee MNS Mass notification system MTP Montlake Triangle Project MUP Master use permit NIH National Institutes of Health NTP Notice to proceed OFM Office of Financial Management

(Olympia) OPB Office of Planning and Budgeting OUA Office of the University Architect PA Project Agreement PRB Project Review Board PT Post-tensioned PUD Planned Unit Development RFI Request for Information RFP Request for Proposal RFFP Request for Final Proposal RFQ Request for Qualifications SEIS Supplemental Environmental

Impact Statement SEPA State Environmental Policy Act SD Schematic design SDOT Seattle Department of

Transportation SFD Seattle Fire Department TCC Total contract cost

ii

TCO Temporary Certificate of Occupancy

TI Tenant improvement TRIR Total recordable incident rate ULAC University Landscape Advisory

Committee UWMC UW Medical Center VRF Variable refrigerant flow WSDOT Washington State Department of

Transportation UWIT UW Information Technology UWPD UW Police Department UWTS UW Transportation Services

iii

MAJOR PROJECTS EXECUTIVE SUMMARY October 2015

· Safety – The total recordable incident rates (TRIR) for calendar years 2013 and 2014

were .98 and 2.74 respectively. The TRIR to date for 2015 is 1.64 with 1,218,000 hours worked. CPO and its contractors have worked 301,000 hours without a lost time incident since July 27, 2015.

· Animal Research and Care Facility – The structures and waterproofing phase of work has commenced. Horizontal rat slabs, waterproofing and protection slabs are in place throughout the building footprint. The structural mat foundation installation in the first zone is complete. Work on columns and reinforcing continues in the first and second zones. The Building Information Modeling (BIM) coordination efforts continue, along with MEP and vivarium equipment submittals processing in order to support the ARCF prefabricated building components, detailing, and the procurement activities. The project team has been reviewing and responding to the bid and procurement activities and working with the management team on budget control strategies.

· Bothell Activities and Recreation Center – The work this period included remaining punch list and commissioning items.

· Burke-Gilman Trail Corridor Phase I Campus Reach – An updated easement was finalized with Puget Sound Energy (PSE) and UW regarding the 12” gas line along the Lewis Lane Bridge. Site Fencing was installed around the site with heavy equipment mobilized for demo/excavation scopes. Clearing and grubbing is in process, but only in areas of immediate work to minimize the erosion control measures required during wet weather.

· Denny Hall Renovation – The construction of the new shear walls has progressed according to schedule. The temporary shoring material was erected. Heavy structural slab removal has begun in preparation for the demolition required for creation of the new interior skylight/stair core and was completed through Level 3.

· Fluke Hall Renovation – Back check of the construction document set delivered in September revealed that the documents were not ready to bid. The design team and GC/CM have been working to revise the documents to assure that all requested revisions have been incorporated and cross checked between disciplines.

· Housing-Maple and Terry Halls – The project is in closeout. The buildings are fully occupied.

· Life Sciences Building – The design development documents were distributed for project stakeholder review and comments were returned to the design team as planned. Cost estimates and reconciliation of the project scope with the project

iv

budget began. The preliminary subcontract buyout plan, negotiated support service, and logistics plan were prepared by Skanska and reviewed by the University. The presentation for the Board of Regents October meeting was finalized. LEAN pull planning activities occurred with the overall project schedule had been informed by the LEAN pull planning.

· Medical Center Expansion Phase II – Design Package 04 -Testing, commissioning and owner training are underway for all work installed in DP04. The work in 7EE is nearing completion and final cleaning is scheduled to begin 11/7/15.

Montlake Tower work - For 2SA - the 7 Operating Rooms and associated support areas went live on 11/2/15. Nineteen surgeries were performed on the first day, and the surgical staff is pleased with the new spaces. For 5SA work is nearing completion. The UWMC is moving furniture into the space beginning on 11/7/15. For 6SA the flooring work is complete, and punch list activities are underway. For 7SA, the flooring contactor has worked overtime for several weeks to recover schedule time. Electrical trim work, painting, ceramic tile, ceiling work and casework activities continue. The terrazzo flooring work was completed.

Design Package 07 - The contractors have mobilized in the Minus 1 level and 2nd floor L2B Prep/Hold/Recovery South areas. Containment infection control walls have been installed and demolition/abatement activities should commence, as planned, the first week in November. The work in Minus 1 includes relocation of duct and piping systems to support the Central Sterile Core Renovation and the new Soiled Lift. The renovation of 5NN has been added to the project and is due to start the first week of December.

· Montlake Triangle Project – Punch list activities continued. Close out is in progress.

· NanoEngineering and Sciences Building (NESB) – The ground floor slab was placed on the east side. The work continues to be scheduled to accommodate the research taking place in the adjoining Molecular Engineering & Sciences Building with the contractor bringing forces in at 4am and suspending operations by 3pm.

· New Burke Museum Renovation – OKA and Skanska were placed on hold for the month of October pending resolution of project timeline. The Master Use Permit process is near completion with issuance expected in November 2015. A decision to consider moving forward with the shell & core portion of the new building was made as there is enough funding in place. A decision was made to authorize OKA to produce permit drawings and to submit for the building permit.

· North Campus Student Housing – The Design Development (DD) phase has continued with KT/OLIN exploring various programmatic revisions as required to meet overall budget

· UW Police Department Facility – The ground floor CMU wall continued to be placed including door frames and electrical boxes. Level 1 and Level 2 metal studs and door frames were installed. Exterior wall sheathing is complete and being damp

v

proofed. The exterior motor court perimeter wall is being installed and bullet resistant board is being installed. The north stair was installed and is not being used for vertical access. The south west entry is being framed.

· Tacoma Urban Solutions Center – The project team reached an agreement with the city of Tacoma for a two phased permit process. This will allow construction to start in January when the tenant has fully vacated. The design team released 30% construction documents for core and shell and 100% design development documents for interiors on October 9th. This document set incorporated additional research laboratories. The GCCM is revising the estimate and updating the cost log to ensure the project scope remains within budget. UW Tacoma Facilities and Environmental Health and Safety reviewed the documents in an over-the-shoulder review meeting. The commissioning agent, EEI, also reviewed and commented on the October 8th design documents. The second half of October was focused to prepare documents for submission for the phase 1 permit, as well as the final approval meeting for the City of Tacoma Landmarks Commission.

· West Campus Utility Plant – The installation of the new chilled-water distribution system piping continued. Detailed design continued in support of trade work packages, the plant electrical design and permit application, and the sequence-of-operations including controls and instrumentation.

1

Animal Research and Care Facility Project #203928

October 2015 Project Manager: Kurt Jensen

Construction Manager: Jeff Angeley

PROJECT DESCRIPTION In 2010, the University of Washington identified the need to develop future facilities capable of supporting the UW’s commitment to outstanding research, education and animal care. Also identified was the need to increase the animal census at the UW and to implement a centralized operating model for animal care and procedures. As a result of the UW’s Animal Care Facilities Master Plan Feasibility Study, it was recommended the UW construct a new Animal Research and Care Facility (ARCF). This project is intended to provide a capacity solution for UW animal research for the next ten years.

The feasibility study identified a site in the Portage Bay Vista, just east of the William H. Foege Building, for a new, state-of-the-art ARCF. The concept plan for this facility is a two-story, below-grade building, connecting to both the Foege building and Hitchcock Hall at the first level below grade. The building will provide flexible housing

Animal Research and Care Facility, #203928

2

for large and small animals (principally rodents) and non-human primates. The study also identified a preliminary program of space types, including laboratories, procedure rooms, imaging facilities; cage and equipment wash facilities, storage, and other support spaces. The planned size of the ARCF is 83,000 gross square feet (GSF). The project architect is a partnership of Zimmer-Gunsul-Frasca (ZGF) of Seattle, Washington and Flad Architect of San Francisco, California. The General Contractor/Construction Manager (GC/CM) is Skanska USA Building, located in Seattle WA. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project team has recovered the entirety of previous schedule delay (due to the site ground water, the soil condition impacts to the installation of the shoring and underpinning piles, and the removal of a previously undiscovered underground storage tank and associated contaminated soils). The team continues to work to minimize impacts associated with the resultant extra work activities by utilizing overtime allowances where appropriate for value-added opportunities to re-sequence the work. For example, a revision to the installation plan for under slab piping and structural matt foundation assembly is responsible for a significant portion of the schedule recovery. Work Accomplished This Period The structures and waterproofing phase of work has commenced. The horizontal rat slabs, waterproofing and protection slabs are in place throughout the building footprint. The structural mat foundation installation in the first zone is complete. The

Animal Research and Care Facility, #203928

3

work on the columns and reinforcing continues in the first and second zones. The Building Information Modeling (BIM) coordination efforts continue, along with MEP and vivarium equipment submittals processing in order to support the ARCF prefabricated building components, detailing, and the procurement activities.

The project team has been reviewing and responding to the bid and procurement activities and working with the management team on budget control strategies.

Plans for Next 30 Days The project structural and waterproofing phase work will continue. The mat foundation is separated into four zones and will be worked in a counterclockwise sequence. The planning for both occupant and contractor operations and logistics at Foege, Hitchcock, J, K, and I wing loading dock will continue. The redesign of the landscape and site work to reduce the cost of that scope will continue and new bid documents will be issued.

PROJECT BUDGET & COST Cost Overview There is no change to the project budget. However, the ARCF GC/CM’s scope of work has been modified to construct a new section of utility tunnel in order to support the distribution of utilities from the new West Central Utility Plant (West CUP). This work also includes replacing the existing PCB-contaminated transformers in Hitchcock Hall. This added work can be most cost-effectively delivered by the ARCF project, and additional funding from other UW sources will be provided to cover the cost. The cost of the additional scope of work is carried in other project budgets and is not included in the budget forecast below. We recently opened bids on a revision to a portion of the interior finishes and have realized substantial savings due to the changes the team has made to the design.

Animal Research and Care Facility, #203928

4

CHANGES IN SCOPE The ARCF GC/CM is now under contract to construct a new section of utility tunnel to provide a new pathway from the West CUP to the ARCF project and other buildings in the Magnuson Health Sciences Center. It is anticipated that the ARCF GC/CM will also install connecting utilities in the new tunnel section. The GC/CM will also replace existing PCB contaminated transformers in Hitchcock Hall. It has been determined that both of these scopes of work can be best coordinated with the ARCF site logistics and performed most cost effectively by the ARCF GC/CM. BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$71,579,165 $17,597,889 $89,177,854 80%

Variance to Date (+ over / – under)

$11,671,854

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 95 58

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 16,677 100,223

Total Recordable Incident Rate 0 0

Animal Research and Care Facility, #203928

5

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 54 $3,062,050

Change Order Proposals Pending 61 $3,775,125

Change Order Requests Pending 8 $707,464

PROJECT COMMUNICATIONS Number Average Turnaround

Requests for Information to Date 497 8 days

Submittals to Date (not including LEED) 314 12.5 days OPPORTUNITIES & CHALLENGES The site has subsurface water runoff from upper campus, and much of the finished building will be below the water table. This will require special consideration by the design team relating to the building envelope and waterproofing systems, as well as additional efforts by the contractor during construction. The sloping site provides opportunities to bring natural light into the facility at strategic locations to improve the work environment for the staff. The below-grade construction will connect to the Foege Building, the Foege loading dock, and potentially Hitchcock Hall. The project team will need to address the potential impact on these existing buildings and associated operations during construction. The air intake locations and building exhaust is a challenge with a below-grade building. The building design must respect long-term plans for expanding the underground facility and for a future above-grade building adjacent to Hitchcock Hall. The facility design will need to be flexible to adapt to future trends in animal research and to changing regulatory requirements. It will be challenging to find the right balance between optimum flexibility and project budget constraints. This project also presents opportunities to enhance and enliven the Portage Bay Vista open space that will be restored following the building construction and to improve the connection across NE Pacific Street to the upper campus. The project is facing budget challenges due to the active Seattle construction market and bidding climate. Skanska and the project team are actively monitoring the situation and working with subcontractors to encourage broad subcontractor participation and competitive bidding.

PROJECT PHOTOS

Animal Research and Care Facility, #203928

6

Zone one reinforcing, formwork and sub-mat utility installations

Animal Research and Care Facility, #203928

7

Zone one mat foundation placed column and reinforcing work in progress.

Site photo looking west toward the Foege building

8

Bothell Activities and Recreation Center Project #203835

October 2015 Project Manager: Eric McArthur

Construction Manager: Jeff Johnson

PROJECT DESCRIPTION This project will construct a new Student Activities Center (SAC) at UW Bothell (UWB) to provide spaces for food service, student leadership offices and clubs, fitness and recreation, casual study, and, potentially an events center. The facility will serve both UWB and Cascadia College. UWB has a growing enrollment of over 4,200 students (3,800 FTE) and has rapidly evolved into a four-year institution after initially accepting only upperclassmen and graduate students. The campus has opened its first student housing facility. The newly leased and renovated spaces in both the Beardslee Building and Husky Hall have further expanded the campus footprint. Given the enrollment growth and expanded facilities, the student population is currently underserved by traditional campus amenities, such as a student union building and fitness facilities. The proposed building is to be located immediately south of (and connected) to the existing North Creek Events Center (NCEC), and will be approximately 35,000 gross square feet (gsf).

UW Bothell SAC, #203835

9

LMN Architects of Seattle is the project architect. The General Contractor/Construction Manager (GC/CM) is Skanska USA Building, Inc. of Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance None at this time. Work Accomplished This Period The substantial completion date was reached on August 6, 2015. The work this period included occupancy, furniture move-in and finalizing remaining punch list and commissioning items. Plans for the Next 30 Days The punch list work and commissioning will be finalized, and move-in activities will be completed. The building Grand Opening ceremony took place October 7, 2015.

UW Bothell SAC, #203835

10

PROJECT BUDGET AND COST Cost Overview The project was slightly over budget prior to buying out the work, and it was hoped that favorable bid results would make up for the estimated overage. Unfortunately, the buyout results added to the overage, and UWB and Cascadia College (CC) students and administration were advised that either additional funds would be required to deliver their intended scope, or the scope would need to be reduced. Further, the bid scope included elements added to the construction project in lieu of being provided separately, and the project budget needed to be adjusted to reflect those costs. The administration, UWB and CC students agreed to fund up to the revised forecast. CPO focused the team on managing construction to minimize the use of the construction contingency. That effort has born fruit and with construction complete, the construction contingencies have covered the added cost of construction. The student funds will be used to cover scope that was for student-requested items that were purchased through the construction contract. Utilizing these two sources, the project will be delivered on time and on budget.

UW Bothell SAC, #203835

11

CHANGES IN SCOPE None. BUYOUT STATUS Buyout is complete.

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts $12,913,770 0 $12,913,770 100% Variance to Date (+ over / – under)

+$808,538

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 40

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 50,873

Total Recordable Incident Rate 0.0 0.0

CONSTRUCTION ADMINISTRATION

Change Documents Number Value Change Orders Approved to Date 22 $160,273.00 Change Order Proposals Pending 31 $132,627.00 Change Order Requests Pending 0

Project Communications Number Average Turnaround Requests for information to date 186 9 days Submittals to Date 247 11 days

OPPORTUNITIES AND CHALLENGES The project successfully addressed a budget challenge through restraint, good construction documents, and creative problem-solving. The tight site logistics were also successfully addressed with minimal impact to campus operations. Importantly, the project was delivered injury-free, which is a testament to both the excellent site supervision and good corporate safety program Skanska provides.

PROJECT PHOTOS

UW Bothell SAC, #203835

12

ARC - Front Entry

Main Level – Student Club and Government Shared Work Space

UW Bothell SAC, #203835

13

Main Level - Student Alcove

Lower Level - Cardio Weight Area

UW Bothell SAC, #203835

14

Upper Level – Student Commons & Events Area, with divider wall partially closed

15

Burke-Gilman Trail Corridor Phase I Campus Reach Project #203801

October 2015 Project Manager: Victoria Morris

Construction Manager: Jeff Johnson

PROJECT DESCRIPTION The Burke-Gilman Trail Corridor (BGTC), constructed in 1978, is a rails-to-trails bicycle and pedestrian thoroughfare that runs through the Seattle Campus west of Montlake Boulevard and north of NE Pacific Street. The trail is widely used by bicycle commuters coming to the University and passing through campus, and it serves as the backbone of a regional bicycling and pedestrian network in the northern part of Seattle. These multiple uses and cross-traffic between the campus community and the BGTC create conflicts and safety issues that need to be addressed for effective pedestrian and bicycle movement on and around the trail. The number of users on the trail has far exceeded initial projections. The Phase I, Campus Reach, Project which will improve the trail from a point just west of the Rainier Vista to the east side of the 15th Avenue NE intersection of the University-owned portion of the BGTC. The construction will begin on October 12th, 2015 with a Ground-breaking ceremony held by Transportation Services on Oct. 6, 2015.

Burke-Gilman Trail Corridor, #203801

16

The project prime is KPFF Consulting Engineers (KPFF) of Seattle, Washington and PLACE Studio, LLC is the landscape design firm from Portland, Oregon. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance This project is behind the revised schedule with construction scheduled for completion in early June, 2016. Work Accomplished This Period A Notice-to-Proceed was issued to C.A. Carey, with a start date of October 12th, 2015. An updated easement was finalized with Puget Sound Energy (PSE) and UW related to the 12” gas line along the Lewis Lane Bridge. The construction fencing was installed around the site with heavy equipment mobilized for demo/excavation scopes. The clearing and grubbing is in process, but only in areas of immediate work to minimize the erosion control measures required during wet weather. The construction communication outreach regarding trail closure and detours has been updated on both the CPO and Transportation Services websites.

Burke-Gilman Trail Corridor, #203801

17

Plans for Next 30 Days The closure of the Burke-Gilman trail between 15th Ave. NE and the Rainier Vista is complete with detour signage and pathway identification posted. The construction work will continue with for demolition, clearing and grubbing as well as deep utility work by the Hitchcock Bridge. PROJECT BUDGET & COST Cost Overview The original project budget for Phase I design and construction was estimated at $4.73 million, as part of the larger previous project that included the design of phase 2. The current cost forecast is $6.2 million, which is approximately 30 percent over budget. The elements of the increased project cost include; higher than anticipated costs for the base scope of work, redesign costs, bicycle shelter and enclosures, ADA upgrades, and escalation. The funding for this project is provided by UW Transportation Services (UWTS). With $3 million in federal grant funding, UW Transportation Services has confirmed that additional funding will be provided to cover the higher estimated project cost. The current funding is $6.2 million.

The reduction in funding and costs to date in July 2015 reflect separating the design costs for Phase 2 into a separat project.

Burke-Gilman Trail Corridor, #203801

18

CHANGES IN SCOPE None this period. BUYOUT STATUS The Phase 1 (Campus Reach) was awarded to CA Carey. SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 0

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 0

Total Recordable Incident Rate 0 0 CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 0 $0

Change Order Proposals Pending 0 $0

Change Order Requests Pending 0 $0

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 0 0 days Submittals to Date (not including LEED) 0 0 days

OPPORTUNITIES & CHALLENGES Completing this work will provide a tremendous asset to the University with improved safety and mobility along the trail. The delay in bidding and the late bidding in the season will shift more work into the wet season and increase the construction duration. It is anticipated that the wet weather will lower productivity and the weather may delay the work further, increasing costs. The outreach and logistics remain a high priority based on the volume of pedestrian traffic anticipated in south campus with the closure of Hitchcock Bridge.

PROJECT PHOTOS

Burke-Gilman Trail Corridor, #203801

19

20

Denny Hall Renovation Project #202039

October 2015 Project Manager: Randy Everett

PROJECT DESCRIPTION Constructed in 1895, Denny Hall is the oldest building on the Seattle campus and is eligible to be listed in the Washington State Heritage Register. Denny Hall was prioritized as part of the University’s “Restore the Core” renovation program to restore and modernize buildings in greatest need of renovation. The last major structural and interior renovation of this 120-year-old building occurred in 1956-57. The slate roof was replaced and the cupola was restored in 2005. The 86,414 gross square foot building will continue to house offices and programs for the College of Arts and Sciences, including the Departments of Anthropology, Classics, Germanics, and Near Eastern Languages & Civilization, as well as the College’s Language Learning Center. Denny will also house general assignment classrooms and a large active learning classroom. This project will upgrade all major building systems, correct seismic deficiencies, improve accessibility, and abate hazardous materials. In accordance with the

Denny Hall Renovation, #202039

21

requirements of the State of Washington, the project will be designed to achieve Leadership in Energy and Environmental Design (LEED) Silver certification. Hacker of Portland, Oregon, is the project architect. SiteWorkshop is the landscape architect, and BNBuilders (BNB) is the General Contractor/Construction Manager (GC/CM). Both are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project remains on schedule for occupancy at the start of Autumn Quarter 2016 based on an accelerated construction schedule. Work Accomplished This Period The conformed drawing set, including addenda from all bid packages issued to date, was issued. BNB advertised and received bids for architectural casework, lab casework & equipment, and floorcoverings. The GC/CM Contract Amendment #3 was issued. The electrical permit package was submitted to the City. The construction of the new shear walls progressed according to schedule. The temporary shoring material was erected. The heavy structural slab removal began in preparation for the demolition required for the creation of the new interior skylight/stair core and was completed through L 3.

Denny Hall Renovation, #202039

22

Plans for Next 30 Days The reconciliation pricing for bid packages will take place based on the conformed set. The architectural casework will be revised and rebid as original bids were over budget. BNB will advertise the remaining bid packages, including polished concrete, window treatments, and irrigation/landscape work. The demolition required for the new interior skylight/stair will continue as will construction of the new shear walls. PROJECT BUDGET & COST Cost Overview The project is on budget with the bidding phase going well. The project is fully funded for $52,892,000.

CHANGES IN SCOPE None this month.

Denny Hall Renovation, #202039

23

BUYOUT STATUS The current forecast for the buyout is under the construction budget.

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$25,931,146 $2,807,647 $28,738,793 90%

Variance to Date (+ over / – under)

$50,458

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 77 70

Lost Time Incidents 0 0

Recordable Incidents 0 1

Total Hours Worked 13,552 48,078

Total Recordable Incident Rate 0 4.2

CONSTRUCTION CONTRACT ADMINISTRATION

OPPORTUNITIES & CHALLENGES BNB with the support of Hacker continues to meet the accelerated construction schedule for completing the renovation of this 120 year old building by the start of Autumn Quarter 2016. The new interior will reflect the timeless beauty of the exterior, but will update the infrastructure, meeting the needs of research and teaching for years to come.

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 0 0

Change Order Proposals Pending 8 $90,000

Change Order Requests Pending 2 $10,183

PROJECT COMMUNICATIONS

Number Average

Turnaround

Requests for Information to Date 144 5 days Submittals to Date (not including LEED)

219

10 days

PROJECT PHOTOS

Denny Hall Renovation, #202039

24

Demolition Activity on the 4th Floor

Demolition Activities on the 4th Floor

Denny Hall Renovation, #202039

25

Demolition at 2nd Floor looking north

Demolition Activity Looking north on the 3rd Floor

26

Fluke Hall Renovation Project #203880

October 2015 Project Manager: Kurt Jensen

Construction Manager: Jim Vincent

PROJECT DESCRIPTION This project will renovate the Washington Nano Fabrication Facility (WNF) located on the first floor of Fluke Hall. The scope of work includes roof replacement and refurbishment of other existing building infrastructure to allow the building to serve as a long-term core UW research facility supporting academic research, industry partnership, and a commercialization incubator. The renovations of the existing second floor laboratories have been removed from the original scope of work in order to achieve project budgetary goals. The portions of this building will remain occupied during construction, requiring the work to be performed in multiple phases. The project architect is HDR Architecture of Seattle. The new General Contractor/Construction Manager (GC/CM) is Hoffman Construction also of Seattle. Holiday Parks is the new MC/CM (Mechanical Contractor/Construction Manager) on the project.

Fluke Hall, #203880

27

PROJECT STATUS SUMMARY Preliminary Schedule Overview

Schedule Variance

The completion date for the Construction Documents was extended to 11/6/2015 to allow for better coordination between disciplines. Work Accomplished This Period The back check of the Construction Document set delivered in September revealed that the documents were not ready to bid. The design team and the GC/CM have been working to revise the documents to assure that all requested revisions have been incorporated and cross-coordinated between disciplines. The submittals for the long lead equipment have been received and are in review. The Capital Project Office (CPO) and the GC/CM continue to refine the construction phasing plan and the construction schedule for the project. Plans for Next 30 Days The final Construction Documents are now scheduled for completion on 11/6/2015. The final back-check and quality assurance will be performed while the GC/CM prepares the individual bid packages. The review of the long lead equipment submittals will be completed and the equipment will be released for fabrication.

Fluke Hall, #203880

28

PROJECT BUDGET & COST Cost Overview The Board of Regents (BOR) approved a project budget of $28.5 million in May 2012 with the understanding that this preliminary budget may change following completion of the schematic design phase. The administration committed to returning to the BOR for final budget approval prior to the start of construction. The predesign study indicated all of the planned scope may not be achievable within the available funding, which was later confirmed. The cost reduction alternatives have been developed through value engineering (VE). The project team agreed to accept the majority of the VE recommendations, resulting in a total project cost forecast and new target budget of $31.5 million. At the end of the design development (DD) phase, the cost estimate, along with code interpretations from the City, showed that the anticipated VE cost savings could not be fully realized. In addition, the result of the field investigation by the MC/CM and the Electrical Contractor/Construction Manager (EC/CM) subcontractors discovered additional information that has also added to the estimated construction cost. The estimated total project cost at the end of the DD phase was approximately $38 million. The project scope has now been significantly reduced and the new cost estimate and budget forecast is $37M.

Fluke Hall, #203880

29

CHANGES IN SCOPE No changes in the scope this period. BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES This project presents an opportunity to improve the quality and reliability of the mechanical and electrical systems supporting the cleanroom and laboratory uses as well as reduce the ongoing facility operations and maintenance costs. The use of Building Information Modeling (BIM) and the collaborative GC/CM process during design and construction enhance the opportunity for the design team to maximize the project scope, quality, and schedule to avoid changes during construction. The challenges include successfully implementing the scope and cost reduction measures required to bring the project cost within budget. The requirement for the existing occupants to remain in the building during construction is a significant challenge for the design team and the contractors. Developing a phasing plan and strategy to allow for continued operation of the labs and cleanrooms during the renovation is complicating the design and puts added pressure on the project budget and schedule. The continuing schedule delays are increasing the risk that uncertain market conditions and escalating construction costs will further impact the project budget.

30

Housing–Maple and Terry Halls Project #203512

October 2015 Project Manager: Will Sigman

Construction Manager: Steve Folk

Perspective of Maple Hall, looking toward northwest from Lincoln Ave PROJECT DESCRIPTION The project scope includes demolition of the existing Center Building and Terry Hall and the construction of two new residential buildings named Maple and Terry Halls. The new seven-story buildings will include five stories of housing consisting of two-bedroom suites with private bathrooms. The lower two floors of each building will be occupied by Housing and Food Services (HFS) administrative offices, common space for students, and some additional two-bedroom suites. A below-grade parking garage connecting to the Lander Hall garage and loading dock will extend below Maple and Terry Halls. The new facility will total 390,000 gross square feet and provide 1,090 beds. The sustainability goal is to achieve Leadership in Energy and Environmental Design (LEED) silver certification. Originally, Terry Hall and the 1101 Café/Center building located on NE Campus Parkway, immediately west of Lander Hall were planned as a renovation. The buildings were constructed in 1952 and needed substantial infrastructure replacement and improvements. The costly seismic and infrastructure upgrades, as well as the current high-rise code requirements, demonstrated that new construction would be a more cost-effective option. This change also presents an opportunity to

Maple-Terry Halls, #203512

31

better integrate these facilities into the vision of the west of 15th Avenue NE master plan and to significantly improve the student life experience in the residence halls. Mithun is the project and landscape architects. W.G. Clark is the General Contractor/Construction Manager (GC/CM). Both firms are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance Phase 1 (HFS offices in Terry Hall) substantial completion was achieved June 5, 2015 and Phase 2, substantial completion was completed on August 7, 2015. Housing & Food Services occupied the Phase 1 area in June. The students moved into the residence halls on schedule. Work Accomplished This Period The project is in closeout. The buildings are fully occupied. Plans for Next 30 Days Project is in closeout.

Maple-Terry Halls, #203512

32

PROJECT BUDGET AND COST Cost Overview The forecast cost to complete is $13.6M below the budget a result of an excellent team effort to manage the project and costs. The budget includes HFS costs for furnishings, fixtures, and equipment. The project funding is from the University’s Internal Lending Program to be repaid with HFS revenues.

CHANGES IN SCOPE None this period BUYOUT STATUS The buyout was completed 0.5% below the construction budget.

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$70,573,535 0 $70,573,535 100%

Variance to Date (+ over / – under)

($3,455.725)

Maple-Terry Halls, #203512

33

SAFETY STATISTICS WG Clark and its team achieved a TRIR of less than 1.0. This is a tremendous achievement and reflects the commitment of the entire team to creating a safe work environment.

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 172

Lost Time Incidents 0 1

Recordable Incidents 0 3

Total Hours Worked 0 520,821

Total Recordable Incident Rate 0 0.81

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 360 $6,036,159 Change Order Proposals Pending 5 $30,000 Change Order Requests Pending 0

$0

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 1,247 5 days Submittals to Date (not including

782 10 days

OPPORTUNITIES AND CHALLENGES The project is in closeout. Our goal is to receive the final redline drawings by the end of October and begin the final record drawings.

PROJECT PHOTOS

Maple-Terry Halls, #203512

34

Maple Hall Courtyard with “Spinners”

Maple Hall great room

Maple-Terry Halls, #203512

35

Maple Hall Level 1 Game Pod Entry

Maple Hall Level 8 Lounge

Maple-Terry Halls, #203512

36

Terry Hall Roof Terrace

37

Life Sciences Building Project #204746

October 2015 Project Manager: Troy Stahlecker

PROJECT DESCRIPTION The Life Sciences Building (LSB) project will provide new laboratory and office space to allow the Department of Biology to increase its faculty size to meet major increases in undergraduate student demand. In addition, a new greenhouse of approximately 18,000 gross square feet (GSF) will be constructed as part of the LSB project. The project site is a combination of existing greenhouses and landscaped area located east of Kincaid Hall, and the area bounded by NE East Stevens Way to the north, the landscaped area just north of the MHSC T-Wing overpass, and the Burke Gilman Trail to the south. The existing greenhouse and associated buildings will be demolished and the LSB of approximately 193,600 GSF will be constructed on the site. The LSB will have five floors above grade with a mechanical penthouse and two below-grade floors to support up to 40 principal investigators with laboratory space, associated offices and conference spaces, three authentic undergraduate research/teaching laboratories, growth chambers, and animal care facilities. The LSB, together with a new, larger greenhouse, which will replace the current 65-year old greenhouse, offers the Department of Biology and its faculty the opportunity to take its truly integrated approach to Biology and its highly collaborative culture to a new level. The LSB allows Biology the opportunity to hire 10-12 new faculty members

Life Sciences Building, #204746

38

and strengthen key areas of interdisciplinary research by bringing together faculty, postdocs, graduate students, and undergraduates with overlapping research interests. Perkins + Will is the project architect, Gustafson Guthrie Nichol (GGN) is the Landscape Architects, and Skanska USA is the General Contractor / Construction Manager (GC/CM). All firms are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project is on schedule. Work Accomplished This Period The design development documents were distributed for project stakeholder review and the comments were returned to the design team as planned. The cost estimates and reconciliation of the project scope with the project budget began. The preliminary subcontract buyout plan, negotiated support service, and logistics plan were prepared by Skanska and reviewed by the University. The presentation for the Board of Regents October meeting was finalized. The project schedule was refined using a Pull Planning session.

Life Sciences Building, #204746

39

Plans for Next 30 Days The Design Development (DD) phase of the project will conclude and the Construction Document (CD) phase will begin. The DD phase cost estimate will be reconciled with the project scope. The conformed DD phase documents will integrate all UW Stakeholder review comments, constructability comments by Skanska, McKinstry, and VECA. The elevator, greenhouse, fire sprinkler and curtain wall subcontract bid packages will be finalized for advertisement in December 2015. The sub contract bid package buyout plan, negotiated support services and logistics plan will be finalized. Skanska, P+W, and AECOM weekly cost log meetings will focus on reconciling the design development cost and the budget control log. The Building Information Modeling (BIM) phase of the project will continue with Skanska, McKinstry, and Veca leading the process. PROJECT BUDGET & COST Cost Overview The current project forecast is $164.755 million of which $4.1 million has been funded. The increase in the project forecast by $4.25 million is for the additional space and infrastructure for the growth chambers. The increased forecast was approved by the Administration and will be presented to the Board of Regents in October.

Life Sciences Building, #204746

40

CHANGES IN SCOPE The additional scopes of work include: changes to the mechanical systems for improved long term cost savings, flexibility, and occupancy comfort; expanded utility infrastructure and increased building size to support additional planned growth chambers; an additional learning space; and shelling an electron microscope and low vibration room. BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The building was sited to preserve the deodar cedars along East Stevens Way NE (Stevens Way) and the grove of trees adjacent to Garfield Lane between Stevens Way and the Burke-Gilman trail. These trees are significant and are character-defining features of the site. An opportunity to enhance pedestrian access includes improvements to the Lewis Lane pedestrian path from Stevens Way to the Hitchcock Overpass on the east side of Kincaid Hall. The integration of the LSB and greenhouse within the existing campus connectivity is being designed. Other opportunities include integrating the Life Science Building with the greenhouse and the Burke Gilman Trail improvements into a cohesive plan. Maintaining the project cost within the forecast budget will be a challenge given the tight market place for construction.

PROJECT PHOTOS

Life Sciences Building, #204746

41

Rendered Image West Elevation – View from Kincaid

Rendered Image East Elevation

Life Sciences Building, #204746

42

Rendered Image North Elevation – View from Stevens Way

43

UWMC Expansion Phase II Montlake Tower Project #204110

October 2015 Project Manager: Ross Pouley

Construction Manager: Bob Dillon

PROJECT DESCRIPTION This project will provide the interior structure, systems, and finishes for a second phase of expansion at the University of Washington Medical Center (UWMC). This phase will increase safety and quality of service to patients in a modern, high-performance environment. It will allow a more streamlined, integrated organizational structure for the interventional services, including surgery, cardiology, and diagnostic radiology, as well as peripheral supporting areas. Additional in-patient beds will also be provided. To support this goal, the Phase II project will build out 107,000 gross square feet (GSF) of shelled spaces within the new Montlake Tower and will renovate 137,000 GSF for both inpatient and outpatient services in the Pacific and Muilenburg Towers. The scope will include new operating rooms (ORs) on Level 2 and intensive care or medical surgery units on Levels 5, 6, and 7. The renovation work will consolidate and organize clinics in wings 7EE and 8SE and will provide the support space and infrastructure necessary to make each component fully operational. To maintain continuous hospital operations throughout construction, the project has been organized sequentially in multiple construction phases. These incremental

UWMC Expansion Phase I, Montlake Tower, #204110

44

occupancy milestones may be adjusted to allow for patient and operational needs or infrastructure requirements. The project architect is NBBJ of Seattle, and the General Contractor/Construction Manager (GC/CM) is Mortenson Construction of Kirkland. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance Design Package 01 (3EE, 7NN, 7SE & 8SE): The DP01 work was substantially completed on June 22, 2015. Design Package 04 (Montlake Tower Floors & 7EE): The construction completion for the entire Design Package is scheduled for 2/17. For 7EE EEG; the substantial completion is scheduled for 11/11/15. For 2SA; the seven ORs were completed and the Temporary Certificate of Occupancy was received on 8/26/15. The “Go Live” date of 11/2/15 was accomplished. For 5SA ICU Bed Floor; the substantial completion is scheduled for 12/2/25. The “Go Live” date is 2/23/16. For 6SA ICU Bed Floor; the substantial completion is scheduled for 12/29/15. The “Go Live” date is 1/26/16. For 7SA Bed Floor; the substantial completion is scheduled for 2/17/16. The “Go Live” date is 4/5/16. Design Package 07: The second floor work in the Pacific & Muilenburg Towers is planned for a phased renovation (L2B, C & D). The construction completion for the

UWMC Expansion Phase I, Montlake Tower, #204110

45

entire Design Package is 10/22/17. The incremental dates for the phased areas are as follows: For L2B Prep Hold Recovery North & South; will start on 12/3/15 and will complete on 7/22/16. For L2C ORs 1-4, Locker Rm, Frozen Section; will start on 7/25/16 and will complete on 6/05/17. For L2D Prep Hold Recovery Central & West Corridor; will start on 3/20/17 and will complete on 10/18/17. Work Accomplished This Period Design Package 01 The final elements of DP01 work was completed on 6/22/15. Design Package 04 The testing, commissioning and owner training are underway for all work installed in DP04. The work in 7EE is nearing completion and final cleaning is scheduled to begin 11/7/15. Montlake Tower work:

1. For 2SA - the 7 Operating Rooms and associated support areas went live on 11/2/15. Nineteen surgeries were performed on the first day, and the surgical staff is pleased with the new spaces.

2. For 5SA, work is nearing completion. The UWMC is moving furniture into the space beginning on 11/7/15.

3. For 6SA, the flooring work is complete, and the punch list activities are underway.

4. For 7SA, the flooring contactor has worked overtime for several weeks to recover schedule time. The electrical trim work, painting, ceramic tile, ceiling work and casework activities continue. The Terrazzo flooring work was completed.

Design Package 07 The contractors have mobilized in the Minus 1 level and the 2nd floor L2B prep/hold/recovery south areas. The containment infection control walls have been installed, and the demolition/abatement activities will commence the first week in November, as planned. The work in Minus 1 includes relocation of duct and piping systems to support the Central Sterile Core Renovation and the new Soiled Lift. The renovation of 5NN has been added to the project and is due to start the first week of December. Plans for Next 30 Days The testing, commissioning and owner training activities related to the MLT floors and the new equipment in the Central Utility Plant will continue. The punch list will

UWMC Expansion Phase I, Montlake Tower, #204110

46

continue on 6SA and 7EE. The flooring and finish work on 7SA will continue. The demolition and abatement work will continue on the Minus 1 Level and the 1st and 2nd floors related to the DP07 work. PROJECT BUDGET & COST Cost Overview The project forecast is on budget at $186.3 million. The early estimates for DP07 which forecast higher costs than originally anticipated did materialize in the bid process. The budget analysis/reconciliation and VE procedures employed to mitigate the overage on this specific package of work have succeeded in preserving the overall budget.

CHANGES IN SCOPE The Design Package 8 scope will be reconsidered to maintain the overall project budget. BUYOUT STATUS The buyout for the first three major phases of construction are now complete. This work represents approximately ninety-seven percent of the total value of all subcontracts.

UWMC Expansion Phase I, Montlake Tower, #204110

47

BUYOUT STATISTICS Awarded Remaining Total %

Complete

Dollar Value of Subcontracts

$75,474,138 $2,363,809 $77,837,947 97%

Variance to Date (+ over / – under)

+$3,966,897

SAFETY STATISTICS

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 264 $9,885,510 Change Order Proposals Pending 177 $10,656,212

Change Order Requests Pending (included in COPs)

PROJECT COMMUNICATIONS Number Average Turnaround

Requests for Information to Date 1,495 7 days Submittals to Date 821 14 days

The change orders include $523,071 related to 7SE & $4,762,362 related to a sterile cart wash & 5NN renovation. OPPORTUNITIES AND CHALLENGES The new work for DP07 will introduce a new group of subcontractors into the Medical Center in the months ahead, and they will be trained on our culture of safety and quiet.

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 100 170

Lost Time Incidents 0 1

Recordable Incidents 0 13

Total Hours Worked 17,471 529,169

Total Recordable Incident Rate 0 4.9

PROJECT PHOTOS

UWMC Expansion Phase I, Montlake Tower, #204110

48

5SA Nurse Station 5SA Nurse Station

5SA Nurse Station 5SA Patient Room

UWMC Expansion Phase I, Montlake Tower, #204110

49

7EE Conference Room 7EE Ceiling in Shielded Room

7EE Shielded Room 7EE Exam Room

50

Montlake Triangle Project Project #203593

October 2015 Project Manager: Andy Casillas

Construction Manager: Andy Casillas

PROJECT DESCRIPTION The Montlake Triangle Project (MTP) is a multi-agency effort consisting of three subprojects centered on the intersection of Pacific Street and Montlake Boulevard. The project scope includes lowering NE Pacific Place and constructing a land bridge that will connect the Montlake Triangle and the lower Rainier Vista with a seamless pedestrian experience. Transit patrons will access the triangle via a combination of existing crosswalks and a new bridge across Montlake Boulevard. The MTP subprojects will be constructed sequentially and scheduled to minimize impact to adjacent work projects. These subprojects consist of the following elements: · Montlake Pedestrian Bridge--Subproject 1 (SP1) – This project will provide

pedestrian and bicycle connections between the future light rail station at Husky Stadium and the Montlake Triangle. Sound Transit is managing design and construction of this $11.4 million project.

· Rainier Vista Land Bridge--Subproject 2 (SP2) – This bridge will span Pacific Place and connect the Montlake Triangle to Rainier Vista. The UW is managing design and construction of this $20.8 million project.

· Rainier Vista Land Bridge Site Improvements--Subproject 3 (SP3) – This project will provide landscaping, hard surfacing, lighting, and other site improvements from Stevens Way through the Montlake Triangle. The UW is managing design and construction of this $4.5 million project.

Montlake Triangle Project, #203593

51

The funding for these projects will be provided by the Washington State Department of Transportation (WSDOT) ($22M), Sound Transit ($12M), and the University ($4M), with an additional $5 million in contingency reserve funded by WSDOT. The designer is KPFF Consulting Engineers of Seattle. The landscape architect is Gustafson Guthrie Nichol. The General Contractor/Construction Manager (GC/CM) is a joint venture of Sellen Construction and Gary Merlino Construction, both located in Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project is complete with Beneficial Occupancy achieved on June 30, 2015. Work Accomplished This Period All major construction activities were completed in June. The punch list activity continues with the majority of the punch list items addressed. There is a potential for some late added work by SDOT on NE Pacific Street for road repair and along Montlake Blvd for game day bus loading activities. The discussions continue with SDOT. Plans for Next 30 Days The work will focus on project closeout, including finalizing punch list and project documentation.

Montlake Triangle Project, #203593

52

PROJECT BUDGET AND COST Cost Overview The following are the approved subproject budgets:

Montlake Pedestrian Bridge—SP1 (by Sound Transit): $13.9 million Rainier Vista Land Bridge—SP2: $23.3 million Rainier Vista Land Bridge Site Improvements—SP3: $4.5 million The project budget includes two subproject components as outlined above. The combined SP2/3 budget is $27.8 million. With the numerous changes encountered, the team reviewed the project estimate to complete forecasting along with the updated Risk Register Log. Based on these updates, the project requested and received additional funding up to $2.5M from WSDOT. A MOU Amendment was executed modifying the funding agreement to increase the project funding up to an additional $2.5M.

CHANGES IN SCOPE Currently, the project is awaiting direction from SDOT on NE Pacific Place roadway repairs outside the project limits.

Montlake Triangle Project, #203593

53

BUYOUT STATUS The full GC/CM contract was executed in December 2013. The subcontractor’s buyout total is over the MACC. SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 30

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 92,304

Total Recordable Incident Rate 0 0

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value Change Orders Approved to Date 138 $2,680,840 Change Order Proposals Pending 10 $183,426 Change Order Requests Pending 1 $40,000

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 268 7 days Submittals to Date 136 12 days

OPPORTUNITIES AND CHALLENGES The project is proceeding quickly as anticipated. The submittals and closeout documentation is in progress. However, minor additional work items may slow down the quick closeout that was anticipated.

PROJECT PHOTOS

Montlake Triangle Project, #203593

54

An aerial view of the site from the southeast – May 14, 2015.

The view looking northeast showing completed work on Pacific Place and Triangle area – July 7, 2015.

Montlake Triangle Project, #203593

55

The view of Pacific Place looking east is showing the completed work along Pacific Place, the Burke Gilman Trail, and Triangle Garage entry– July 7, 2015.

56

NanoEngineering & Sciences Building Project #204878

October 2015 Project Manager – Eric McArthur

Construction Manager – Mark Sweeters

PROJECT DESCRIPTION The Nano Engineering & Science Building (NESB) project will consist of a new, approximately 78,000 gross square foot, 6-story building adjacent and connected to the existing Molecular Engineering & Sciences Building (MolES) on the main University of Washington campus. The project was initially established to construct a warm shell building and complete the build-out of 13,000 assignable square feet (asf) to accommodate the research on campus affected by the tunneling and operation of the Sound Transit light rail tunnel. The first floor of 12,000 gross square feet will be constructed as a warm shell for anticipated future completion for academic general purpose use. This warm shell work will be funded by Central Funds. To offset this loss of floor space, the currently designed basement level floor will expand to the north and add 9,000 gross square feet of ground contact area. In the September 2015 Board of Regents meeting, the project was authorized to build out the remaining portion of Level G, 3 for College of Engineering vibration and EMI sensitive programs, and Level 4 to expand the Institute for Protein Design currently housed on Level 4 of MolES. The current projected assignable square feet will be 45,000 when complete in 2016.

NanoEngineering and Sciences Building (NESB), #204878

57

The project architect is a partnership of Zimmer-Gunsul-Frasca (ZGF) of Seattle, Washington and Flad Architect of San Francisco, California. The General Contractor/Construction Manager (GC/CM) is Hoffman Construction Co, located in Seattle WA. PROJECT STATUS SUMMARY Schedule Overview

SCHEDULE VARIANCE The substantial completion has a current contract date of November 1, 2016. The GC/CM is currently showing a variance of 8 days on the construction schedule due to sequencing issues during the excavation and shoring of the below-grade work as well as excessive rain on 8/14/2015 which impacted the site excavation. All trades suspended work that afternoon and the following Saturday was used to dewater the site. The GC/CM is currently working on resequencing the work to bring the schedule back into alignment. The rain incident will be tracked throughout construction to determine if a contract day is required to be added to the construction contract. WORK ACCOMPLISHED THIS PERIOD With the exception of the lab casework, all remaining bid packages have been bid during this period. An amendment to incorporate these bids is currently being prepared.

NanoEngineering and Sciences Building (NESB), #204878

58

The ground floor slab has been placed on the east side. The work continues to be scheduled to accommodate the research taking place in the adjoining Molecular Engineering & Sciences Building with the contractor bringing forces in at 4am and suspending operations by 3pm. This follows the agreement between the construction team and the MolES researchers established to end disruptive construction activities by 3 pm each day and to resume no earlier than 8 pm in the evening. PLANS FOR NEXT 30 DAYS The design work continues on the expanded scope of work to plan out the fit-out of levels G, 3, & 4. The design team is facilitating planning sessions with the College and the IPD. This design and documentation work will continue through the end of the year.

The construction activities are continuing on the lower level and level G. The basement and remaining portion of the ground floor slabs will be poured and the remaining walls will be backfilled to grade.

PROJECT BUDGET & COST Cost Overview The current budget and forecast cost is $81.9 million, with $28.9M to cover the prior budget shortfall and the expanded scope. Currently, $53 million is in hand. The most recent bidding has been on budget. The project team continues to review opportunities for cost reduction while still maintaining the approved project scope.

NanoEngineering and Sciences Building (NESB), #204878

59

CHANGES IN SCOPE The Board of Regents approved the following at their September 2015 meeting:

1. The ground floor and floor 3 will be fully built out to house research space for the College of Engineering. Level G will accommodate vibration and EMI-sensitive equipment, and associated support spaces. Level 3 will include laboratory space for both wet and dry research and is designed to be shared by multiple faculty members/research groups. Level 3 will also provide office and support space for 6 faculty members along with their associated students/researchers.

2. The full build-out of Floor 4 will house the Institute for Protein Design – The layout and build-out will generally replicate that of Floors 2 and 3.

BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$21,584,458 $18,323,358 $39,907,816 54%

Variance to Date (+ over / – under)

$8,114,197

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 50 36

Lost Time Incidents 0 0

Recordable Incidents 0 1

Total Hours Worked 10,581 52,283

Total Recordable Incident Rate 0 3.8

NanoEngineering and Sciences Building (NESB), #204878

60

CONSTRUCTION ADMINISTRATION

Change Documents Number Value Change Orders Approved to Date 11 $638,785 Change Order Proposals Pending 18 -$880,000 Change Order Requests Pending 1 $ 20,000

Project Communications Number Average

Turnaround Requests for information to date 73 3 days Submittals to Date 120 11 days

OPPORTUNITIES & CHALLENGES The construction market is currently experiencing increased escalation and volatile market conditions as the Seattle economy continues to boom. This climate is straining the construction labor pool and limiting the pool of bidders able to perform the work. This project, like others locally, is seeing younger craft labor on the jobsite, which can affect the quality of work and the project schedule. The Construction Manager is aware of this and is actively monitoring and working with their subcontractors to manage this issue. These market conditions are also significantly impacting the bid results of the project.

The site is restricted and will be affecting vehicular circulation around the site. The tight fence boundaries and the increasing number of students that flow through this area of the campus present a challenge to the contracting team to preserve safety while still maintaining traffic and the ingress of materials. A UWPD officer has been retained to help direct traffic through the Grant Lane and Stevens Way intersection. This is the primary point for materials to enter the site and is also where most pedestrian traffic will cross.

PROJECT PHOTOS

NanoEngineering and Sciences Building (NESB), #204878

61

Waterproofing in place, ready for placement of Level G slab on grade

62

New Burke Museum Project #203007

October 2015 Project Manager: Eldon Tam/Ken Kubota

PROJECT DESCRIPTION This project will construct a new Burke Museum located along NE 15th Ave NE to the west of the existing Burke Museum within a development site identified in the UW Campus Master Plan. The new museum will be approximately 110,000 gross square feet with three-stories and a partial daylight basement. This project will replace the existing Burke Museum, constructed in 1962. This project will address the limitations and shortcomings of the existing building, which are no longer adequate to meet the programmatic vision, capacity for research collections, public outreach, and education missions of the Burke Museum. The new building will celebrate the museum’s goals to foster understanding and inspire wonder about the Northwest and our place in the world. It will emphasize the power of object-based learning to inspire curiosity, generate new knowledge, foster understanding of the role that collections play in our shared natural and cultural heritage, and highlight the connection between people and the environment in every aspect of the museum, from research, exhibits, and programming to the museum’s building, grounds, and business practices. The project is expected to result in an architecturally noteworthy facility that: 1) enables the Burke to simultaneously protect and share collections that constitute the natural and cultural heritage of the people of Washington state; 2) facilitates

New Burke Museum, #203007

63

meaningful visitor engagement with Burke Museum research and collections; and 3) creates a valued public amenity that connects the community to both the mission and campus of the University of Washington. The project will also address issues of long-term flexibility in the design of galleries and public spaces, and will implement sustainable design practices to achieve a facility that functions efficiently and can be maintained with limited resources. Leadership in Energy and Environmental Design (LEED) Platinum is an aspirational certification goal. Accessibility will be integrated into the new facility to provide ADA compliance. The project architect is Olson Kundig Architects (OKA), Gustafson Guthrie Nichol (GGN) is the Landscape Architects, and Skanska USA is the General Contactor/ Construction Manager (GC/CM), all are located in Seattle. PROJECT STATUS SUMMARY Schedule Overview

Receiving less than the full amount of state funding needed from the 2015 legislative session delayed the start of construction. The University is now targeting a summer 2016 groundbreaking, pending Regents’ approval and fundraising status. Schedule Variance The project design was put on hold pending resolution of the timeline for groundbreaking. The project is coming off hold status in November 2015. There is funding to consider constructing the shell & core portion of the building now and consider the tenant improvement later when additional funding is available.

New Burke Museum, #203007

64

Work Accomplished This Period OKA and Skanska were placed on hold for the month of October pending resolution of project timeline. The Master Use Permit process is near completion with issuance expected in November 2015. A decision to consider moving forward with the shell & core portion of the new building was made as there is enough funding in place. OKA was authorized to produce permit drawings and to submit for the building permit. Plans for Next 30 Days The project will restart in November. A revised project schedule will be developed looking toward a permit submittal in January 2016 and a start of construction on July 1, 2016. Skanska will complete constructability reviews. OKA will address Process Partners 50% CD reviews. OKA will restart the process for completing the building permit submission. PROJECT BUDGET & COST Cost Overview The legislature approved $26 million of the $46.2 million of state funding needed for the project. The University has submitted a request for the 2016 legislative session for the remaining funding. If the funding is not approved a new funding request will be submitted for the 2017 biennium request. The language in the 2015-17 biennium budget recognizes the need for increased project funding due to a delayed start date.

New Burke Museum, #203007

65

CHANGES IN SCOPE None anticipated this period. BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES Matching the project timeline to the timeline for securing state funds is a challenge. The private fundraising and fundraising from other sources has strong momentum. It will be a major challenge to plan for the displacement of staff and collections during the transition phase when they move from the existing facility into the new building. The project budget did not support Leadership in Energy & Environmental Design (LEED) Platinum certification; the project team will continue to work towards a LEED Gold certification. The project will meet LEED Silver certification standards at a minimum.

66

North Campus Student Housing Project #204350

October 2015 Project Manager: Victoria Morris and Shane Ruegamer

Construction Manager: Steve Folk

PROJECT DESCRIPTION The North Campus Student Housing project Phase IV (will replace McCarty Hall with three buildings, identified as buildings B, C and D with occupancy planned for the start of Autumn Quarter 2018. The construction typology of buildings B, C, and D will be 5-stories of wood-frame construction above a two-story concrete podium. The steeply sloped site makes it challenging to achieve the desired 1,870 beds programmed for these buildings. The lower concrete levels of the building will include residence hall amenities such as entry lobbies, regional desk, dining, game center, and meeting rooms. The upper wood framed levels will be residential suites with private or communal bathrooms. The landscape improvements include internal courtyards, a central urban plaza, an entry court, new and refreshed pedestrian access and circulation from the north, south, east and west. There will be open spaces for wide- ranging passive and active recreational uses, and the relocation of a portion of Whitman Court roadway. The cumulative changes are designed to create a new character for this part of the

North Campus Housing, #204350

67

campus that retains the woodland nature of the existing area. It will be better served by connections within it and connecting to the broader campus. The project is targeting, at a minimum, a Silver level certification for new construction through the U.S. Green Building Council’s Leadership in Energy & Environmental Design (LEED). Kieran Timberlake is the architect, Olin Studios is the Landscape Architect, both are of Philadelphia, Pennsylvania, and W.G. Clark of Seattle is the General Contractor/Construction Manager (GC/CM). PROJECT STATUS SUMMARY Schedule Overview

Phase IV (a)

Schedule Variance None, the project remains on schedule. Work Accomplished This Period The Design Development (DD) phase continued with KT/OLIN exploring various programmatic revisions to meet overall budget. Plans for Next 30 Days The design development phase continues with refinement to program elements, building fenestration studies, material selections and site landscape refinements. The demolition and early works permit packages are being compiled for submission on November 4th to the City of Seattle. The construction fencing and security will be installed around McCarty in anticipation of the scheduled 1st responder training starting the week of November 16th. The project will be presented to the Board of

North Campus Housing, #204350

68

Regents as an informational item in preparation for presentation on January for funding, budget, and site approval. PROJECT BUDGET AND COST Cost Overview The project forecast is $240 million. The current funding is from HFS reserves, the remainder of the funding will be from the Internal Lending Program (ILP). The ILP will be paid from HFS revenues.

CHANGES IN SCOPE Not applicable at this time. BUYOUT STATUS, SAFETY STATISTICS, CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES AND CHALLENGES The early selection of the general contractor along with early selections of the mechanical and electrical subcontractors, follow the successful format of the design participation that occurred on the West Campus Housing projects. This early involvement has proven to enhance the 3D modeling and coordination of the design.

North Campus Housing, #204350

69

The project will be challenging with the cost of construction increasing and shortages of qualified craft trade workers to construct the project due to the increase in construction activity in the Seattle area. It is an exciting opportunity to create a new vision for the residential housing village for this part of the campus that retains the woodland nature, which better serves internal and external connections to the campus and the connecting community.

70

UW Police Department Facility Project #203612

October 2015 Project Manager: Ken Kubota

Construction Manager: Jeff Huebler

PROJECT DESCRIPTION This project will provide a new upgraded University of Washington Police Department (UWPD) facility in a more central location that will facilitate greater accessibility to the University community. The project site is just south of Gould Hall, occupying a portion of the W14 Parking Lot and the 3945 and 3937 buildings on 15th Avenue NE. The building will be located in the growing and increasingly lively west campus and near a primary campus entrance; the site offers improved visibility and access to the police station. The approximately 29,000 gross square foot building is envisioned to be architecturally significant, with a program that features to support a modern and highly capable UWPD operation for decades to come. The conceptual design envisions a two-story building with a basement level. The program includes; police offices, a dispatch and communications center, records storage, evidence room and lab, suspect processing, interview rooms, report taking rooms, juvenile waiting rooms, police lockers, fitness rooms, a community multipurpose meeting/training room, and fleet parking. The project sustainability goal is to achieve Leadership in Energy & Environmental Design (LEED) silver certification.

UW Police Department Facility, #203612

71

The architect is the Miller Hull Partnership of Seattle. The police facilities consultant is McClaren, Wilson & Lawrie of Phoenix, Arizona. The General Contractor/Construction Manager (GC/CM) is BNBuilders of Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance There are no changes this period. The project remains on schedule. Work Accomplished This Period At the ground floor CMU walls continue to be placed including door frames and electrical boxes. The level 1 and level 2 metal studs and door frames are being installed. The exterior wall sheathing is complete and being damp proofed. The north stair was installed, but is not yet being used for vertical access. The southwest entry is being framed. The exterior motor court perimeter walls are being constructed with bullet resistant board. Plans for Next 30 Days The ground level CMU will be completed and prepared for finish work; the ceiling rough-in work continues; and the perimeter insulation work is starting. The level 1 and level 2 framing will be completed with electrical work and ready for gypsum wallboard work to start. The mechanical/plumbing rough-in work continues and the exterior walls will be insulated and vapor barrier installed. The roofing work will be completed. The motor court walls will continue with bullet resistant board and plywood installation. The southwest stair will be installed and exterior wall sheathing installed and sealed.

UW Police Department Facility, #203612

72

PROJECT BUDGET AND COST Cost Overview The project cost forecast remains on budget at $19.5 million.

CHANGES IN SCOPE None this period. BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$11,882,124 $ <123,600> $11,758,524 100%

Variance to Date (+ over / – under)

+$300,901

UW Police Department Facility, #203612

73

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 30 17

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 5,306 26,485

Total Recordable Incident Rate 0 0

CONSTRUCTION ADMINISTRATION

OPPORTUNITIES AND CHALLENGES The UW Police Department facility is one of the few buildings on campus that is open 24-hours a day, seven days a week. This project will make the UW Police Department more visible, as many students, faculty, and staff do not know its current location at the Bryants Building. The design team and the contractor are managing the project to stay within the available budget. Just south of the UWPD site is the site of the separate West Campus Utility Plant (WCUP) project that will require close coordination. The WCUP project is no longer providing the emergency power to the UWPD. The WCUP project is funding the emergency power coming from the West Receiving Station. The increasing construction costs as well keeping the project on budget will be challenging.

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 11 437,214

Change Order Proposals Pending 9 -27,390

Change Order Requests Pending 8 246,000

PROJECT COMMUNICATIONS

Number Average

Turnaround

Requests for Information to Date 168 4 days

Submittals to Date (not including LEED)

246 9 days

PROJECT PHOTOS

UW Police Department Facility, #203612

74

North Elevation – Framing and Ballistic Layer installation

North Elevation – Waterproofing and clips

UW Police Department Facility, #203612

75

Interior Mechanical and Framing.

Interior Framing, MEP Rough-in

UW Police Department Facility, #203612

76

Looking West from L2 at Alley

Mechanical and Metal Framing at Level 2

77

UW Tacoma Urban Solutions Center Project #204701

October 2015 Project Manager: Jeannie Natta

PROJECT DESCRIPTION The former Tacoma Paper and Stationery Building is the last of the historic large warehouse buildings on the UW Tacoma campus to be renovated. The building features a 10,000 gross square foot daylight basement and three upper floors for a total of 40,000 gross square feet. The building has been unoccupied other than for storage uses and by the Old Spaghetti Factory restaurant, which has been a mainstay in downtown Tacoma for decades and which will be moving to a nearby location. Consistent with its mission as an urban-serving university, the UW Tacoma seeks to renovate this building to further preserve the historic fabric of its downtown Tacoma environs, and to ultimately house programs in the building which bring together academic, commercial, non-profit, government, and student entities in one place to study, research, analyze, debate, and develop solutions for a variety of issues in the South Sound region. Originally, the project was to be completed in two phases: (1) a ‘warm shell’ and core renovation, (2) a full build-out of the interior space. Driven by UW Tacoma’s current projections of 4%-6% student growth per year, the UW Tacoma Campus Planning Office now intends to complete the project in a single phase. The pre-design and design work has been funded by a $1.9M capital request in the 2013 Legislative session. A capital request for core and shell construction was funded by the Legislature at $16M. The UW Tacoma funded the interior design and construction at $10.1M from UW Tacoma Reserves.

UW Tacoma Urban Solutions Center, #204701

78

The architect is the Miller Hull Partnership, located in Seattle. Mortenson Construction, located in Kirkland, Washington, is the General Contractor/Construction Manager (GC/CM). PROJECT STATUS SUMMARY

Schedule Variance The schedule has been revised based on the building being vacated before January 2016. Work Accomplished This Period The project team reached an agreement with the city of Tacoma for a two phased permit process. This will allow for construction to start in January, as soon as the tenant has fully vacated. The design team released 30% construction documents for core and shell and 100% design development documents for interiors. This document set incorporated additional research laboratories requested by UWT. The GCCM is revising the estimate and updating the cost log to ensure the project scope remains within budget.

UW Tacoma Urban Solutions Center, #204701

79

UW Tacoma Facilities and Environmental Health and Safety reviewed the documents in an ‘over the shoulder’ review meeting. The commissioning agent, EEI, also reviewed and commented on the latest design documents. The focus for the second half of October was to prepare documents for submission for the phase 1 permit, as well as the final approval meeting for the City of Tacoma Landmarks Commission. Plans for Next 30 Days The team will submit documents to the City of Tacoma for the phase 1 permit and will respond to permit review comments in mid-November. The team will also submit documentation for final design approval to City of Tacoma Landmarks Commission and is on the agenda for the commission meeting on November 18. The project team will rectify the cost estimate with the project budget by identifying cost saving measures to ensure the project achieves the best value. A meeting with UW Tacoma is scheduled for November 10 to review these options. The GCCM team is preparing site logistic plans for review by UW Tacoma and the team will plan for construction mobilization. The project team will meet with the commissioning agent on November 17 to address design comments and plan for commissioning. The design for the phase 2 permit will continue. The goal is to submit for the phase 2 permit in mid January, 2016. PROJECT BUDGET & COST Cost Overview The total project budget is $28,000,000. The Board of Regents approved the budget on September 10, 2015. $1,900,000 was appropriated by the Legislature in the 2013-2015 budget for predesign and design of the core and shell. $16,000,000 has been appropriated by the Legislature in the 2015-2017 budget for construction of the core and shell. $10,100,000 has been appropriated from UW Tacoma Reserves in 2015 to complete the design and construction of the interior.

UW Tacoma Urban Solutions Center, #204701

80

CHANGES IN SCOPE The team is working to incorporate research laboratories into the building without increasing the budget. BUYOUT STATUS Not applicable at this time. SAFETY STATISTICS Not applicable at this time. CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The project offers the chance to complete the major renovation of UW Tacoma’s warehouse building stock and fill in a ‘missing tooth’ in the heart of the campus. The building has a number of infrastructure challenges to overcome. There is also known contaminated soil within the footprint of the building and economically addressing that issue is an additional challenge. The predesign provided a strong foundation moving forward. Now that the Prairie Line Trail is completed, the design team is also able to envision how the new Urban Solutions Center will tie into the Trail.

81

West Campus Utility Plant Project #204685

October 2015 Project Manager: Steve Harrison

PROJECT DESCRIPTION This current project includes a building of approximately 17,000 gross square feet (GSF) containing generators, chillers, cooling towers, and associated equipment. The building will be constructed above the existing campus utility tunnel, allowing direct access to the tunnel for distribution of electrical cabling and chilled water (CW) piping. When fully built out, the plant will have capacity to produce 12 megawatts (MW) of emergency power and 10,500 tons of CW. In phase 1 the construction of the building will be complete as well as the installation of equipment to produce 6 MW and 3,000 tons of CW. This phase will also provide space and infrastructure for the future full equipment build-out, and run distribution systems to the south campus. The emergency power and CW will be distributed to the tunnel intersection vault SW-1, at which point the ARCF project will pick up those services for connection and distribution within the facility and to the existing distribution lines nearby. The West Campus Utility Plant (WCUP) is envisioned to be an architecturally significant building, given its prominent location on the west campus. The careful attention given will ensure that the design fits contextually with the surrounding community and is representative of its importance as a gateway building at the southwest approach to the campus. The design will incorporate a demonstration

West Campus Utility Plant, #204685

82

display element that will enable access by students and the public to gain an understanding of the University’s commitment to the environment and energy conservation. The Board of Regents authorized the use of the design-build (D-B) contracting method for this project. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance None this period. Work Accomplished This Period The installation of the new chilled-water distribution system piping continued. Accessible portions of the supply pipe have been ongoing, but demolition of existing lines and start on the return line had to wait until mid-October. The necessary shutdowns for most of the work were accomplished and good progress was made on demolition of the existing lines. The submittal process for equipment aimed at the plant began in earnest. The electrical work in the adjacent alley, which is by others and on which the start of plant construction depends, was partially completed. The

West Campus Utility Plant, #204685

83

design and permitting tasks were also ongoing or completed during October. The final coordinated design build drawings were published and the sequences-of-operation for the plant mechanical and power-generation/electrical systems were advanced along with further details and some equipment selection for controls. The MUP and the building permit reviews by the City were tracked and facilitated. The University commitments regarding alley dedications and the recording of Rights-of-way were completed or advanced, and University-contracted services necessary for construction such as geotech, testing, and dispute resolution professionals were retained. The procurement efforts and construction-logistics planning were ongoing and continue. Plans for Next 30 Days The distribution system pipeline installation will continue. The MUP and Building Permits will be issued. The preparations for plant construction will continue, and at some point construction of the plant will begin. The detailed work on the system controls will continue and the professional firms will begin their construction administration duties. A handful of change orders will be advanced and possibly executed including 4 scopes of work that were originally envisioned to be part of the future phases of the WCUP. The associated distribution systems upgrades or represent utility upgrades generated by the spatial conflict between the West CUP improvements and power cables to safely move out of the way. PROJECT BUDGET & COST Cost Overview There is no change to the project budget. However, the Design Builder’s scope of work will be modified in November to include switchgear, and associated electrical equipment build-out originally envisioned as part of Phase 2 of the CUP development. The replacement of normal power feeder cables that cannot be otherwise modified due to safety concerns will also be added. This added work can be most cost-effectively delivered by the West CUP project, and additional funding from other UW sources will be provided to cover the cost. The cost of the additional scope of work is carried in other project budgets and is not included in the budget forecast below. The current approved budget is $36.2 million. The increase from the original project budget of $30.5 million was approved by the Board of Regents at the March 2015 meeting. Adding a number of identified scope enhancements will provide flexibility for the future by increasing the building footprint, a partial basement and equipment enhancements. This increase will better allow the facility to respond to potential future sustainability initiatives such as thermal storage, lake water cooling and campus system conversion from steam to hot water.

West Campus Utility Plant, #204685

84

CHANGES IN SCOPE An increase in mechanical and electrical scopes is anticipated within the next 30 days. This is the primarily ‘accelerated Phase 2 scope’, see discussion above. An increase in the chilled water distribution system (pipeline) scope is also anticipated, but not for several months. BUYOUT STATUS Not applicable at this time. SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 0

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 0

Total Recordable Incident Rate 0 0

West Campus Utility Plant, #204685

85

CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The budget risks generally associated with assuring quality and completeness in the constructed product under a design-build delivery system while market costs are escalating are beginning to emerge. However, the collaborative design effort has effectively controlled them to date. The ‘accelerated Phase 2’ scopes of work discussed above are important opportunities in that they have the capacity to save money in other projects and in regard to future plant and distribution build out. The previously identified risk associated with work by another UW project in the alley adjacent to the WCUP site, which involves the undergrounding of power lines, still exists. The work in general is advancing at an acceptable rate, but there is a nexus with, and reliance on, Seattle City Light that could delay some of the earliest tasks of construction if SCL is unresponsive.