monthly long term transmission plan project status report · sub was energized on 5/27/15 with...
TRANSCRIPT
Monthly Long Term Transmission Plan Project Status ReportReport Date: 7/9/2015
Operating Company Major UpdatesEAI Three projects completedEMI One project added (MTEP15)ELL Two projects added (MTEP15)ENOI One project completedEGSL One project completedETI One project completed. Nine projects added (MTEP15)ELL/ENOI No major changesALL No major changes
General Latest report is considered to be the most current updated Long Term Transmission Plan. Report also includes MISO MTEP proposed project designations.
Highlights Page 1 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
11-EAI-007 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Hot Springs Milton (Albright) - Carpenter Dam: Construct new 115 kV Line and convert Mountain Pine South to ring bus
EAI Summer 2015 Approved Design/Construction Outage scheduling requirements at MT. Pine South will require the ISD to move to 6/1/16 from 12/31/15. The Albright Substation and the portion of line from Carpenter to Albright has been placed
in service.
6/1/16 Planned NCLL until project completed
11-EAI-008 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Pine Bluff Voltage Support Project: Phase 2 Woodward: Construct 230 kV ring bus and construct new White Bluff to Woodward 230 kV line
EAI Summer 2015 Approved Construction CECPN approved by the APSC Summer 2016 Planned NCLL until project completed
11-EAI-015 4669 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Jim Hill Area UpgradesRebuild Jim Hill - Datto line and convert from 115kV to 161kV. Install breakers at Datto
EAI Winter 2018 Conceptual Scoping Scoping visit scheduled for 7/14/15. Winter 2018 N/A
11-EAI-017 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
White Bluff: Reconfigure 500 kV Station and construct 230 kV ring bus
EAI Summer 2015 Approved Design/Construction Foundations are almost complete. All contracts are in place for construction activities through the end of Summer
2015. Relay constructability review has been completed for Phase 2 - 4. Steel
erection has begun. No issues are being addressed at this time.
6/1/16 Planned NCLL until project completed
11-EAI-025 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Norfork-Calico Rock : Upgrade 161 kV Line EAI Summer 2016 Approved Design Final transmission line design is complete.
Summer 2016 N/A
11-EAI-027 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
AECC L&D 2 to Gillett: Construct new 115 kV Line EAI Summer 2016 Approved Scoping CECPN has been issued. Row acquired. Working on permitting with
USACE.
6/1/16 Planned NCLL until project completed
12-EAI-003 4660 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
Woodward-115 kV Bus Reconfiguration EAI Summer 2016 Approved Design / Construction P.B. South line at the Woodward 115kV sub was energized on 5/27/15 with existing breaker B2847 and some updates to the status and control points. Carpenter Dam line at the Woodward sub was energized on
6/5/15 with existing breaker B8647 and new line panel.
3/1/16 Planned NCLL until project completed
12-EAI-005 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Camden McGuire - Camden North 115kV Line: Construct New Line
EAI Summer 2014 Approved Complete In-service 6/30/15 7/9/15 N/A Yes
12-EAI-008-02 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Macon Lake to Reed: Construct new 230 kV line and operate at 115 kV
EAI Summer 2017 Approved Design/Construction Phase I (Lake Village to Macon Lake) complete. Design for Phase II, III
complete.
6/1/17 N/A
12-EAI-014 4666 Appendix B Transmission Reliability - Meeting Planning Criteria
Mabelvale-Bryant: Reconductor 115kV line EAI Summer 2024 Conceptual Conceptual Conceptual Summer 2024 N/A
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
Long Term Projects Page 2 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
12-EAI-016 4657 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
HS EHV-HS Industrial: Upgrade Terminal Equipment EAI Summer 2015 Proposed & In Target
Scoping Under Review Summer 2015 N/A
12-EAI-017 4658 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
HS Industrial-HS Union Carbide: Upgrade Terminal Equipment
EAI Summer 2015 Approved Scoping Under Review Summer 2015 N/A
12-EAI-018 4659 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
HS Union Carbide-HS East: Upgrade Terminal Equipment
EAI Summer 2015 Approved Scoping Under Review Summer 2015 N/A
12-EAI-019 4665 Appendix B Transmission Reliability - Meeting Planning Criteria
Mabelvale: Replace 500-115 Autos EAI Summer 2025 Proposed & In Target
Scoping Under Review Summer 2025 N/A
12-EAI-040 4739 A in MTEP14 Load Growth Cofer Road New Substation EAI 2015 Approved Construction Site work and foundation work are complete, and electrical work has
begun.
8/25/15 N/A
13-EAI-003 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Monticello East to Reed: Construct new 115 kV transmission line. Construct to 230 kV but operate at 115 kV.
EAI Summer 2020 Approved Design CECPN approved by the APSC Reed Substation
6/1/17Line 6/1/20
N/A
13-EAI-011 4741 A in MTEP14 Load Growth H.S. Albright: New Distribution Substation EAI 2015 Approved Complete In-service 7/1/15 6/10/15 N/A Yes
14-EAI-005 4664 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Holland Bottoms - Beebe: Build new 161kV line, Install 161/115kV auto
EAI Summer 2019 Proposed & In Target
Scoping Construction alternatives under review Summer 2019 N/A
14-EAI-006 4681 Appendix B Transmission Reliability - Meeting Planning Criteria
Beebe - Garner: Build new 161kV line, Build new 161kV Garner sub - tap Copper Springs-Searcy S. line section
EAI Summer 2025 Conceptual Conceptual Conceptual Summer 2025 N/A
14-EAI-011 4671 Appendix B Transmission Reliability - Meeting Planning Criteria
El Dorado - Add 2nd 500-115 kV auto (utilize auto removed from Mabelvale)
EAI Summer 2025 Conceptual Conceptual Conceptual Summer 2025 N/A
14-EAI-012 4672 Appendix B Transmission Reliability - Meeting Planning Criteria
McNeil - Add 2nd 500-115 kV auto (utilize auto removed from Mabelvale)
EAI Summer 2025 Conceptual Conceptual Conceptual Summer 2025 N/A
14-EAI-017 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Driver 500-230 kV Substation: Construct new substation and loop in and out of San Souci to Shelby 500 kV line
EAI Summer 2015 Approved Construction Projected ISD TBD based on customer inputs and requirements. Projected
ISD moved to Summer 2016.
Summer 2016 N/A
Long Term Projects Page 3 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EAI-018 4742 A in MTEP14 Load Growth Macedonia: Build New 115 kV Substation EAI 2015 Approved Scoping Interim Substation energized, resolving issues on land purchase for permanent
solution.
Spring 2016 N/A
14-EAI-020-1 4744 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: P.B. 34 & Main 115 kV B0957-CBO
EAI Winter 2014 Approved Complete In-service 2015 6/2/15 N/A N/A
14-EAI-020-10 4753 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: Carpenter 115 kV B1686-TCO
EAI Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EAI-020-4 4747 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: L.R. Industrial 115 kV B0591-CBO
EAI Winter 2014 Approved Design Began design phase of project, wrote requisitions for the major equipment,
and are putting together the Foundation and Electrical design packages.
2015 N/A N/A
14-EAI-020-7 4750 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: McAlmont 115 kV B0980-CO
EAI Winter 2014 Approved Design Began design phase of project, wrote requisitions for the major equipment,
and are putting together the Foundation and Electrical design packages.
2015 N/A N/A
14-EAI-020-8 4751 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: Jacksonville North 115 kV B3621-CBO
EAI Winter 2015 Approved Design Began design phase of project 2016 N/A N/A
14-EAI-020-9 8660 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: Paragould 115 kV B7315-TCO
EAI Winter 2016 Approved Design Began design phase of project. The scope has changed to remove/bypass B7315, and modify the relaying for the protection of the autotransformer, bus,
and the line to Walnut Ridge.
2016 N/A N/A
14-EAI-021 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Trumann Substation - Add Capacitor Bank EAI Winter 2014 Approved Construction The property needed for the site expansion has been acquired. It was
found that a natural gas pipeline crosses through the middle of the
acquired property. Project re-engineered to account for pipeline
location on property. The ISD of 9/1/15 reflects a delay in receiving the
capacitor bank.
9/1/2015 N/A
14-EAI-022-1 4754 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI SPOF Projects: Modify relaying at White Bluff 500 kV
EAI Summer 2016 Approved Scoping Additional modifications are being incorporated based on comments received during project evaluation
planning.
Summer 2016 N/A N/A
Long Term Projects Page 4 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EAI-022-2 4755 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI SPOF Projects: Modify relaying at ISES 500/161 kV
EAI Summer 2016 Approved Design/Construction Moving forward with detailed design and ordering of long lead materials.
Construction projected to begin in the fall with control house expansion. ISD of Summer 2016 dependent on outage
availability.
Summer 2016 N/A N/A
14-EAI-022-3 4756 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI SPOF Projects: Modify relaying at Mabelvale 500 kV
EAI Summer 2016 Approved Scoping Scoping trips have been completed and the project execution plan is in
progress. Construction expected to begin in the summer of 2015 with the
control house addition and junction box replacements.
Summer 2016 N/A N/A
14-EAI-022-4 4757 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI SPOF Projects: Modify relaying at El Dorado 500 kV
EAI Summer 2016 Approved Scoping Scope of work still underdevelopment Summer 2016 N/A N/A
14-EAI-022-5 4758 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI SPOF Projects: Modify relaying at Hot Springs 500 kV
EAI Summer 2016 Approved Scoping Project evaluation plan completed. Summer 2016 N/A N/A
14-EAI-026 7925 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Black Rock to Imboden: Construct new 69 kV transmission line
EAI Summer 2016 Proposed & In Target
Scoping Project execution plan under development
Summer 2016 N/A
14-EAI-027 7761 A in MTEP14(OOC)
Transmission Reliability - Meeting Planning Criteria
Datto: Add 161 kV capacitor bank. Adjust taps on Datto transformer and reduce size of Pocahontas North capacitor bank
EAI Summer 2015 Approved Scoping Projected ISD has moved from July 1, 2015 to Dec 1, 2015.
12/1/2015 N/A
14-EAI-028 8040 A in MTEP14 Economic ANO - Mabelvale 500kV: Replace Substation Equipment EAI Summer 2017 Approved Scoping New project (Economic MTEP 14) Summer 2017 N/A
14-EAI-029 8041 A in MTEP14 Economic ANO - Pleasant Hill 500kV: Replace Substation Equipment
EAI Summer 2017 Approved Scoping New project (Economic MTEP 14) Summer 2017 N/A
15-EAI-001 7927 Appendix B Transmission Reliability - Meeting Planning Criteria
Newport - Newport Ind: Upgrade station equipment EAI Summer 2017 Proposed & In Target
Scoping Summer 2017 N/A
15-EAI-002 7928 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Jonesboro EHV: Tap ISES - Dell 500kV line and build 500/161kV station near Hergett station
EAI Summer 2020 Proposed & In Target
Scoping Summer 2020 Planned NCLL until project completed
15-EAI-003 7941 Appendix B Transmission Reliability - Meeting Planning Criteria
Bull Shoals - Midway Jordan: Rebuild 161kV line EAI Summer 2020 Proposed & In Target
Scoping Summer 2020 Planned NCLL until project completed
15-EAI-004 7942 Appendix B Transmission Reliability - Meeting Planning Criteria
Mayflower - Morgan: Rebuild 115kV line EAI Summer 2020 Proposed & In Target
Scoping Summer 2020 Planned NCLL until project completed
15-EAI-005 7943 Appendix B Transmission Reliability - Meeting Planning Criteria
Morrilton E. - Gleason: Rebuild 161kV line EAI Winter 2021 Proposed & In Target
Scoping Winter 2021 N/A
Long Term Projects Page 5 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-EAI-006 7945 Appendix B Transmission Reliability - Meeting Planning Criteria
Hot Springs EHV: Replace 500/115kV autos EAI Summer 2023 Conceptual Conceptual Conceptual Summer 2023 N/A
15-EAI-007 7944 Appendix B Transmission Reliability - Meeting Planning Criteria
Stuttgart Ricuskey - Stuttgart Ind: Rebuild 115kV line EAI Summer 2024 Conceptual Conceptual Conceptual Summer 2024 N/A
15-EAI-008 8680 Target Appendix A in MTEP15 (OOC)
Customer Driven Conway Middle Road: Construct new 161 kV substation EAI Spring 2016 Approved Scoping EPC Agreement Completed 12/30/2014 Spring 2016 N/a
15-EAI-009 8681 Target Appendix A in MTEP15 (OOC)
Customer Driven Jefferson Industrial: Construct new 115 kV substation EAI Summer 2016 Approved Scoping Waiting for customer information relating to load, transformer rating, 911 address matching to coordinates and timing for building SS pad and access road. When that is made available, transformer will be ordered.
6/1/16 N/a
15-EAI-010 8940 Target Appendix A in MTEP15
Transmission Service White Bluff - Keo 500 kV: Upgrade terminal equipment EAI Winter 2016 Proposed & In Target
Scoping New Project Summer 2016 N/a
15-EAI-011 8960 Target Appendix A in MTEP15 (OOC)
Customer Driven Driver 230 kV: Construct new 230/13.8 kV distribution substation
EAI Spring 2016 Proposed & In Target
Scoping New Project 5/1/16 N/a
11-EGL-007 4602 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Moril to Delcambre 138 kV line: Upgrade station equipment
EGSL-F Summer 2016 Proposed & In Target
Scoping Scoping to begin 3rd Quarter 2014 Summer 2016 N/A
11-EGL-017 4608 Appendix B Transmission Reliability - Meeting Planning Criteria
Five Points to Line 281 Tap to Line 247 Tap- Upgrade 69 kV line
EGSL-F Summer 2019 Proposed & In Target
Scoping Summer 2019 N/A
11-EGL-018 4630 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Francis to Marydale: Upgrade 69 kV line EGSL-B Summer 2017 Proposed & In Target
Scoping Accelerated Need By Date from 2023 to Summer 2017
Summer 2017 N/A
12-EGL-004 4603 Appendix B Transmission Reliability - Meeting Planning Criteria
McManus to Brady Heights - Upgrade 69 kV line EGSL-B Winter 2023 Conceptual Conceptual ConceptualMoved out from 2016 to 2023
Winter 2023 N/A
12-EGL-010 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Kirk Substation: Construct new 138-69 kV substation near St. Martinville(Formerly New Iberia: Add 138-69 kV substation)
EGSL-F Summer 2015 Approved Design Final design configuration approved. Projected ISD of 12/5/16
12/5/2016 Planned NCLL until project completed
14-EGL-002 4611 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Construct new Waddill 230-69 kV Substation (formerly referred to as Flannery Area Project) Also reconfigure 69 kV lines 340 and 749
EGSL-B Summer 2017 Proposed & In Target
Scoping Accelerated Need By Date from 2020 to 2017
Summer 2017 N/A
14-EGL-003 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Willow Glenn: Upgrade 500-230 kV single phase transformer bank with 1200 MVA single phase bank
EGSL-B Summer 2016 Approved Design/Construction Autotransformer and breakers have been ordered and are scheduled to be
delivered to support EGSL Construction; January 2016 (Auto) and
June 2015 (breakers).
6/1/2016 Planned NCLL until project completed
14-EGL-004 4606 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Fancy Point: Add 2nd 500-230 kV, 1200 MVA transformer
EGSL-B Summer 2017 Proposed & In Target
Scoping Detailed scoping to begin 3rd Quarter 2014
Summer 2017 Planned NCLL until project completed
Long Term Projects Page 6 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EGL-006 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
LeBlanc - New Cap Bank #1 (Now referred to as Conrad)
EGSL-F Summer 2015 Approved Complete In-service 6/26/2015 7/7/15 N/A Yes
14-EGL-007 4610 Appendix B Transmission Reliability - Meeting Planning Criteria
Chlomal to Lacassine - Upgrade Line EGSL-C Winter 2023 Conceptual Conceptual ConceptualMoved out from 2019 to 2023
Winter 2023 N/A
14-EGL-008 4609 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Krotz Springs - New Cap Bank EGSL-F Summer 2016 Proposed & In Target
Scoping Property acquisition discussions are ongoing with Colonial Pipeline to locate at Colonial Springs PL substation. The
project evaluation plan has been submitted for approval.
Summer 2016 N/A
14-EGL-010 4626 Appendix B Transmission Reliability - Meeting Planning Criteria
Meaux to Abbeville - Upgrade Meaux Line bay bus EGSL-F Summer 2024 Conceptual Conceptual ConceptualProject need date moved out from 2020
to 2024
Summer 2024 N/A
14-EGL-012 4628 Appendix B Transmission Reliability - Meeting Planning Criteria
LeBlanc - New Cap Bank #2 EGSL-F Summer 2021 Conceptual Conceptual ConceptualAccelerated one year from 2022 to
2021
Summer 2021 N/A
14-EGL-016 4604 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Port Hudson to Zachary REA 69 kV Line Reconductor EGSL-B Summer 2016 Proposed & In Target
Scoping Accelerated Need By Date to Summer 2016
Summer 2016 N/A
14-EGL-017 8861 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
Horseshoe Substation (Crown Zellerbach Area): Construct new 230-138 kV substation on the Fancy Point to Enjay 230 kV line
EGSL-B Summer 2017 Proposed & In Target
Scoping Site acquisition activities underway Summer 2017 N/A
14-EGL-019 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Mud Lake 230 kV Substation: Loop Sabine to Big 3 230 kV Line into new Mud Lake 230 kV substation and add (2) 230 kV capacitor banks at Mud Lake
EGSL-C Fall 2016 Approved Design/Construction EPC Agreement Completed. Design and construction underway. Project experienced some delays due to the
amount of rain experienced in the area.
Summer 2016 N/A
14-EGL-020 4719 A in MTEP14 Transmission Service PPG to Rosebluff 230 kV Line: Upgrade line to increase capacity
EGSL-C Summer 2015 Approved Design Scheduled outages have been denied. Re-evaluating Projected ISD.
Projected ISD moved from July to early November.
11/5/15 N/A
14-EGL-022-1 4761 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL SPOF Projects: Modify relaying at Willow Glen 500 kV
EGSL-B Summer 2015 Proposed & In Target
Scoping PEP was completed in February 2015. Due to the need to change 21 panels, add new relay room, replacement of
transformer under another capital project, etc. and uncertainty in
availability of outages, Projected ISD expected by April 2018.
4/25/2018 N/A N/A
14-EGL-022-2 4762 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL SPOF Projects: Modify relaying at Fancy Point 500kV
EGSL-B Summer 2015 Proposed & In Target
Scoping Project being coordinated with Fancy Auto Project and breaker replacements. Projected ISD expected to be Summer 2017 due to outage coordination among
multiple area projects.
Summer 2017 N/A N/A
14-EGL-023 4720 A in MTEP14(OOC)
Customer Driven Michigan 230 kV substation: Construct new Michigan 230 kV substation and cut in to the Nelson to Verdine 230 kV line
EGSL-C Summer 2015 Approved Construction Construction in progress and on schedule.
10/2/2015 N/A
Long Term Projects Page 7 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EGL-024-1 4763 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL Underrated Breaker Project: Jaguar 69 kV 20940-CO
EGSL-B Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EGL-024-2 4764 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL Underrated Breaker Project: Jaguar 69 kV 20905-CO
EGSL-B Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EGL-024-3 4765 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL Underrated Breaker Project: Blount 69 kV 14105-TC
EGSL-B Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EGL-024-4 4766 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL Underrated Breaker Project: Coly 230 kV 21825-C
EGSL-B Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EGL-024-5 4767 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EGSL Underrated Breaker Project: Coly 230 kV 21830-C
EGSL-B Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EGL-026 8284 A in MTEP14 Economic LETP: Coly - Add 2nd 500-230 kV, 1200 MVA Autotransformer
EGSL-B Summer 2018 Approved Scoping New project (Economic MTEP 14) Summer 2018 N/A N/A
15-EGL-001 7917 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Gillis 230 kV Substation: Add 61 MVAR capacitor bank EGSL-C Summer 2016 Proposed & In Target
Scoping Design resource team working on developing project execution plan
6/1/2016 N/A
15-EGL-002 7919 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Pecan Grove 230 kV Substation: Add 61 MVAR capacitor bank
EGSL-C Summer 2016 Proposed & In Target
Scoping New Project Summer 2016
15-EGL-003 7920 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Carlyss to Boudoin 230 kV Line: Upgrade station equipment at Carlyss
EGSL-C Summer 2016 Proposed & In Target
Scoping New Project Summer 2016
15-EGL-004 7921 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Nelson to Michigan 230 kV line: Upgrade line to minimum of 2000A
EGSL-C Summer 2016 Proposed & In Target
Scoping New Project Summer 2016
15-EGL-005 7923 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Lake Charles Bulk to Chlomal 69 kV Line: Reconductor line
EGSL-C Summer 2017 Proposed & In Target
Scoping New Project Summer 2017
15-EGL-006 7924 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Goosport Substation: Install 138-69 kV autotransformer EGSL-C Summer 2017 Proposed & In Target
Scoping New Project Summer 2017
15-EGL-009 7948 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Scott to Carencro 69 kV line: Reconductor Line EGSL-F Summer 2017 Proposed & In Target
Scoping New Project Summer 2017
15-EGL-010 7949 Appendix B Transmission Reliability - Meeting Planning Criteria
Solac: Add 3rd Autotransformer EGSL-C Summer 2023 Conceptual Conceptual New Project Summer 2023
15-EGL-011 7950 Appendix B Transmission Reliability - Meeting Planning Criteria
East Broad to Ford 69 kV line: Reconductor line EGSL-C Summer 2020 Proposed & In Target
Scoping New Project Summer 2020
Long Term Projects Page 8 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-EGL-012 7952 Appendix B Transmission Reliability - Meeting Planning Criteria
Contraband to Solac 69 kV line: Reconductor line EGSL-C Summer 2023 Conceptual Conceptual New Project Summer 2023
15-EGL-013 7954 Appendix B Transmission Reliability - Meeting Planning Criteria
Mossville to Alfol 69 kV line: Reconductor line EGSL-C Summer 2023 Conceptual Conceptual New Project Summer 2023
15-EGL-014 7960 Appendix B Transmission Reliability - Meeting Planning Criteria
Chlomal to Iowa 69 kV line: Reconductor line EGSL-C Summer 2024 Conceptual Conceptual New Project Summer 2024
15-EGL-015 7965 Appendix B Transmission Reliability - Meeting Planning Criteria
Lake Charles Bulk to L673 TP 69 kV line: Reconductor line
EGSL-C Summer 2025 Conceptual Conceptual New Project Summer 2025
15-EGL-016 8585 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Construct new Sulphur Lane 500 kV switching station
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-017-01 8586 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Construct new 500-230 kV Bulk Substation west of Carlyss. Install new 500-230 kV, 1200 MVA autotransformer composed of three single phase units.
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-017-02 8587 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Construct new 500 kV transmission line from Sulphur Lane to new 500/230 kV Bulk Substation west of Carlyss
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-017-03 8588 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Construct new 230 kV line from new Bulk Substation to Carlyss 230 kV substation
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-018 8589 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Reconfigure Carlyss 230 kV substation into a breaker and a half configuration
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-019 8590 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
LCTP: Construct new 12 mile 230 kV line from Carlyss to new 230 kV substation adjacent to Graywood.
EGSL-C Summer 2018 Approved Scoping New Project to address reliability needs in the Lake Charles area due to
projected growth. Being submitted to MISO as out of cycle
Summer 2018
15-EGL-020 8683 Target Appendix A in MTEP15 (OOC)
Customer Driven Intracoastal 69 kV Substation: Install 150 MVA, 230-69 kV autotransformer at Intracoastal and connect to Mud Lake 230 kV substation
EGSL-C Summer 2016 Approved Scoping New customer requested project to provide an additional source into the
Intracoastal 69 kV substation
Summer 2016 N/A
15-EGL-021 8684 Target Appendix A in MTEP15 (OOC)
Transmission Reliability - Meeting Planning Criteria
Carlyss to Sweet Crude Tap (L-238): Reconductor 69 kV line (0.94 miles) to a minimum of 1200A.
EGSL-C Summer 2016 Approved Scoping New customer requested project to provide an additional source into the
Intracoastal 69 kV substation
Summer 2016 N/A
15-EGL-022 8700 Target Appendix A in MTEP15 (OOC)
Customer Driven Spanish Trail: Construct new 138 kV Substation EGSL-C Winter 2015 Approved Scoping New Customer requested project to provide a 138 kV connection on the
Nelson to Mossville 138 kV line.
1/1/2016 N/A
Long Term Projects Page 9 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EGL-027 8284 A in MTEP14 Economic LETP: Richardson to Iberville - Construct new Richardson 230 kV substation new Dow Meter and construct new 230 kV line from Richardson to Iberville 230 kV substation. (EGSL Portion of project)
EGSL-B/ELL-S Winter 2018 Approved Scoping New project (Economic MTEP 14) Winter 2018 N/A N/A
14-ELL-019 8284 A in MTEP14 Economic LETP - Richardson to Iberville - Construct new Richardson 230 kV substation new Dow Meter and construct new 230 kV line from Richardson to Iberville 230 kV substation. (ELL Portion of project)
EGSL-B/ELL-S Winter 2018 Approved Scoping New project (Economic MTEP 14) Winter 2018 N/A N/A
10-ELL-008 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Southeast LA Coastal Improvement Plan: Phase 3 Construct Oakville to Alliance 230kV Line Add 230 - 115 kV Autotransformer at Alliance Substation
ELL-S Summer 2013 Approved Scoping Oakville Substation expansion placed into service 9/3/12. Alliance Substation expansion and 230/115kV Auto placed
into service 1/16/14. T-Line routing challenges continue to delay start of
ROW acquisition. Projected ISD delayed from 6/1/15 to 6/1/18. Awaiting
conditional permit approval from LADOTD to construct line within their ROW for Hwy 23. Identifying location of two Parish water lines along west side of Hwy, continue discussions on
options for relocating one line.
6/1/18 Planned NCLL until project completed
11-ELL-004 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Northeast LA Improvement Project Phase 3 Upgrade Sterlington to Oakridge to Dunn 115 kV Line
ELL-N Summer 2015 Approved Construction All materials received, pre-construction activities completed, Re-conducting
activities is 100% complete and rebuild of the line is 41% complete.
12/30/15 Planned NCLL until project completed
12-ELL-004 4769 A in MTEP14 Load Growth Schriever: Construct new 230 kV substation ELL-S 2017 Proposed & In Target
Scoping Under Review 3/31/17 N/A
13-ELL-004 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Minden Improvement Project Ph. 1-Place cap bank at Minden REA
ELL-N Summer 2015 Approved Construction Overall construction activities – 20% Summer 2015 N/A
13-ELL-006 4634 Appendix B Transmission Reliability - Meeting Planning Criteria
Ninemile to Westwego 115 kV: Reconductor Line ELL-S Summer 2020 Conceptual Conceptual Conceptual Summer 2020 N/A
14-ELL-002 4635 Appendix B Transmission Reliability - Meeting Planning Criteria
Sterlington 115 kV Substation: Upgrade jumpers on the Sterlington to Walnut Grove 115 kV line (line 107)
ELL-N Summer 2024 Conceptual Conceptual Conceptual Summer 2024 N/A
Long Term Projects Page 10 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-ELL-006 4639 Appendix B Transmission Reliability - Meeting Planning Criteria
Ninemile to Harvey2 115 kV: Reconductor line and change station limiting elements
ELL-S Summer 2025 Conceptual Conceptual ConceptualMoved ISD back to from 2022 to 2025
Summer 2025 N/A
14-ELL-008-1 4770 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL Underrated Breaker Project: Waterford 230 kV S7145-CO
ELL-S Winter 2016 Proposed & In Target
Scoping Under Review 12/31/2016 N/A N/A
14-ELL-008-2 4771 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL Underrated Breaker Project: Waterford 230 kV S7154-CO
ELL-S Winter 2016 Proposed & In Target
Scoping Under Review 12/31/2016 N/A N/A
14-ELL-009-1 4773 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL SPOF Projects: Modify relaying at Ninemile 230 kV
ELL-S Summer 2015 Proposed & In Target
Design Project is in Design Phase - Material being ordered. To be completed by
November 2016 barring availability of outages.
11/11/2016 N/A N/A
14-ELL-009-2 4774 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL SPOF Projects: Modify relaying at Southport 230 kV
ELL-S Summer 2015 Proposed & In Target
Design Project is in Design Phase - Material being ordered. To be completed by
November 2016 barring availability of outages.
11/23/2016 N/A N/A
14-ELL-009-3 4775 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL SPOF Projects: Modify relaying at Labarre 230 kV ELL-S Summer 2015 Proposed & In Target
Design Project is in Design Phase - Material being ordered. To be completed by February 2017 barring availability of
outages.
2/17/2017 N/A N/A
14-ELL-009-4 4776 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL SPOF Projects: Modify relaying at Harahan 230 kV
ELL-S Summer 2015 Proposed & In Target
Design Project is in Design Phase - Material being ordered. To be completed by October 2016 barring availability of
outages.
Summer 2016 N/A N/A
14-ELL-009-5 4777 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ELL SPOF Projects: Modify relaying at Paris 230 kV ELL-S Summer 2015 Proposed & In Target
Design Project is in Design Phase - Material being ordered. To be completed by Summer 2016 barring availability of
outages.
Summer 2016 N/A N/A
14-ELL-020 8284 A in MTEP14 Economic LETP: Panama Substation: Cut-in Bagatelle to Sorrento 230 kV line
ELL-S Winter 2018 Approved Scoping New project (Economic MTEP 14) Winter 2018 N/A N/A
14-ELL-021 8284 A in MTEP14 Economic LETP: Romeville Substation: Upgrade line bay bus. ELL-S Winter 2017 Approved Scoping New project (Economic MTEP 14) Winter 2017 N/A N/A
Long Term Projects Page 11 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-ELL-001 7988 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Schriever to Bayou Vista (Cleco): Construct new 230 kV line. Entergy Portion: Add breakers at Schriever and construct new 230 kV line from Schriever to near Amelia, LA and connect to Cleco new line.Cleco Portion: Construct new 230 kV line from Bayou Vista to near Amelia, LA and connect to Entergy line. Add 230/138 kV auto at Bayou Vista
ELL-S Summer 2018 Proposed & In Target
Scoping Modified New ProjectProject was originally to construct a new 230 kV line from Terrebonne to
Gibson and operate at 115 kV. Entergy, Cleco, and MISO modified project to construct a new line from
Schriever to Bayou Vista. Project has been submitted into MISO project
database
Summer 2018
15-ELL-002 7970 Appendix B Transmission Reliability - Meeting Planning Criteria
Minden Area Improvement Ph. 2: Construct new 115 kV substation east of Minden REA and cut-in Minden REA to Arcadia 115 kV line and construct new 115 kV lines to cut the Minden to Sailes 115 kV line in and out of the new substation.
ELL-N Summer 2020 Proposed & In Target
Scoping New Project Summer 2020
15-ELL-004 8682 Target Appendix A in MTEP15 (OOC)
Customer Driven Woods: Construct new 230 kV substation ELL-N Fall 2015 Approved Design/Construction Design and procurement are in progress. Construction has begun.
8/1/15 N/A
15-ELL-005 9285 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Waterford to Vachierie 230 kV line: Reconductor line ELL-S Winter 2018 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
10/31/18 N/A
15-ELL-006 9284 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Bayou Verret 230 kV Substation: Add (2) 40 MVAR capacitor banks
ELL-S Summer 2017 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
8/31/17 N/A
14-ELL-012 4779 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Ninemile to Derbigny: Upgrade 230 kV line ELL-S/ENOI Summer 2016 Approved Scoping/Design Project evaluation plan scope is complete.
6/1/2016 N/A
14-ELL-013 4780 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Ninemile to Napoleon: Upgrade 230 kV line ELL-S/ENOI Summer 2016 Approved Scoping/Design Project evaluation plan scope is complete.
6/1/2016 N/A
11-EMI-007 4613 Appendix B Transmission Reliability - Meeting Planning Criteria
Breakers at Hollandale and Belzoni Tap SS (close normally-open point)
EMI Summer 2019 Proposed & In Target
Scoping Project need date has moved to Summer 2019
Summer 2019 N/A
12-EMI-001 4614 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
Franklin - McComb build new 115 kV line (230 kV construction)
EMI Summer 2018 Proposed & In Target
Scoping Project Scope of Work completed. Summer 2018 N/A
14-EMI-002 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Bozeman Rd to Tinnin Rd 230kV: Build new 230kV line from Bozeman Road to GASES-Ray Braswell 230kV and add new breaker station
EMI Summer 2017 Approved Scoping Project Scope of Work completed. Spring 2018 N/A
14-EMI-003 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Southwest Mississippi Reliability Improvement Project: Baxter Wilson to Natchez SES 115kV Build new 115kV line rated 260MVA (230kV constructed)
EMI Summer 2018 Proposed & In Target
Scoping Project Scope of Work completed. Fall 2018 N/A
14-EMI-005 N/A Pre-Planned Enhanced Transmission Reliability Vicksburg Area Improvement Project: Build new 115kV switching station and rebuild E.Vicksburg-R.Braswell 115kV and SE Vicksburg-new switching station. Upgrade station equipment at SE Vicksburg and Bovina
EMI Summer 2018 Proposed & In Target
Scoping Project Scope of Work completed. Spring 2018 N/A
Long Term Projects Page 12 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
14-EMI-008-1 4786 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J6797-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-2 4787 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J7497-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-3 4788 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J9732-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-4 4789 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J9742-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-5 4790 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J9743-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-6 4791 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J9759-CO
EMI Winter 2015 Approved Scoping Under Review Winter 2015 N/A N/A
14-EMI-008-7 4792 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Rex Brown 115 kV J9753-CO
EMI Winter 2016 Approved Scoping Under Review Winter 2016 N/A N/A
14-EMI-008-8 4793 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EMI Underrated Breaker Project: Greenville 115 kV J9942-CO
EMI Winter 2016 Proposed & In Target
Scoping Under Review Winter 2016 N/A N/A
14-EMI-009 7760 A in MTEP14(OOC)
Load Growth Madison Avenue: Construct new substation EMI Summer 2016 Proposed & In Target
Scoping Under Review 6/1/2016 N/A
15-EMI-001 7898 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Greenville - E Greenville 115 kV: Replace switches at Greenville
EMI Summer 2016 Proposed & In Target
Scoping Under Review Summer 2016 N/A
15-EMI-002 7901 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Natchez - Natchez SES: Upgrade relays at Natchez SES and Natchez for line 168 and 169
EMI Summer 2018 Proposed & In Target
Scoping Under Review Summer 2018 N/A
Long Term Projects Page 13 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-EMI-004 7906 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Greenwood - Greenwood SS 115 kV: Rebuild line EMI Summer 2019 Proposed & In Target
Scoping Under Review Summer 2019 N/A
15-EMI-005 7907 Appendix B Transmission Reliability - Meeting Planning Criteria
Attala - Conehoma Creek 115 kV: Rebuild 115 kV line EMI Summer 2019 Proposed & In Target
Scoping Under Review Summer 2019 N/A
15-EMI-006 7908 Appendix B Transmission Reliability - Meeting Planning Criteria
Pelahatchie - Morton: Install line RX EMI Winter 2020 Proposed & In Target
Scoping Under Review Winter 2020 N/A
15-EMI-007 7909 Appendix B Transmission Reliability - Meeting Planning Criteria
Centreville: Add 10.2MVAR capacitor bank EMI Summer 2023 Proposed & In Target
Scoping Under Review Summer 2023 N/A
15-EMI-008 7914 Appendix B Transmission Reliability - Meeting Planning Criteria
Medical Center Solution: Install new 115 kV substation on Monument St - Fondren 115 kV and build new Rex Brown - new substation
EMI Summer 2020 Proposed & In Target
Scoping Under Review Summer 2020 N/A
15-EMI-009 8520 Appendix B Transmission Reliability - Meeting Planning Criteria
Indianola: Install 2nd 230/115 kV autotransformer EMI Summer 2020 Proposed & In Target
Scoping Under Review Summer 2020 N/A
15-EMI-010 8900 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Rex Brown 115 kV Breaker: Replace J9752 EMI Summer 2016 Proposed & In Target
Scoping Preliminarily Identified in MISO Att Y study
Summer 2016 N/A N/A
15-EMI-003 7904 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Natchez SES - Redgum: Rebuild 115 kV line EMI/ELL-N Summer 2018 Proposed & In Target
Scoping Site visit in June. Summer 2018 N/A
15-EMI-011 9300 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Franklin 115 kV: Reconfigure substation to double bus-double breaker
EMI Summer 2016 Proposed & In Target
Scoping New Project identified in Att Y study 6/1/16 N/A N/A
14-ENO-001-1 4795 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ENOI Underrated Breaker Project: Claiborne 115 kV N0143-ICBO
ENOI Winter 2014 Approved Design/Construction PEP underway Fall 2015 N/A N/A
14-ENO-001-2 4796 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ENOI Underrated Breaker Project: Claiborne 115 kV N0123-ICBO
ENOI Winter 2014 Approved Complete In-service Fall 2015 6/2/15 N/A N/A
14-ENO-003-1 4778 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ENO SPOF Projects: Modify relaying at Market Street 230 kV
ENOI Summer 2015 Approved Design Project is in Design Phase - Material being ordered. To be completed by October 2016 barring availability of
outages.
10/7/2016 N/A N/A
Long Term Projects Page 14 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
11-ETI-002 7947 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Reconductor Sabine to Port Neches Bulk (Line 515) ETI Summer 2018 Proposed & In Target
Scoping Design resource team working on developing project execution plan, Soil
boring and survey for T -Line
6/1/2018 N/A
11-ETI-018 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Construct new China to Amelia 230kV line ETI Summer 2016 Approved Design/Scoping Received final CCN order. Working on securing line ROW and property for
extension of Amelia SS.
Summer 2016 N/A
11-ETI-023 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Orange County 230kV Project: Construct new Chisholm Road 230 kV substation, Construct new line from Hartburg to Chisholm Road, add 2nd Hartburg 500-230 kV auto
ETI Summer 2017 Approved Design EPC contractor under contract and working through design; Project
schedule accelerated from 6/1/17 to 11/30/16.
11/31/16 N/A
11-ETI-033 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leach 138 kV - Upgrade line ETI Fall 2014 Approved Construction Transmission line upgrade/reconductor work completed. CT installation at
Toledo Bend substation to be completed coinciding with the Leach
138 kV Substation: DTEC add 138 kV breakers customer project in
September 2015.
9/30/2015 N/A
11-ETI-038 4653 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Reconductor Sabine to Port Neches Bulk (via Linde Line 516)
ETI Summer 2017 Proposed & In Target
Scoping Design resource team working on developing project execution plan, Soil
boring and survey for T -Line
6/1/2017 N/A
11-ETI-039 7972 Appendix B Transmission Reliability - Meeting Planning Criteria
Upgrade Jacinto - Splendora 138 kV Line ETI Summer 2023 Conceptual Conceptual Conceptual(Project Need has shifted to Long Term
from Near Term)
Summer 2023 N/A
11-ETI-042 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
New 50.2 MVAR Cap Bank at Parkway 138kV(Formerly expand Cap Bank at New Caney 138kV)
ETI Summer 2014 Approved Complete In-service 6/19/2015 6/22/15 N/A Yes
12-ETI-006 4620 Appendix B Transmission Reliability - Meeting Planning Criteria
Kolbs 230 kV - Add capacitor bank ETI Summer 2018 Proposed & In Target
Scoping Scoping to begin in early 2014. Summer 2018 N/A
12-ETI-007 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Alden 138 kV Substation: Add Capacitor Bank ETI Summer 2015 Approved Design Projected ISD being timed with bus work associated with the SVC addition at Alden. Projected ISD of 12/15/15
12/15/2015 N/A
12-ETI-010 4651 Appendix B Transmission Reliability - Meeting Planning Criteria
Buna: Add capacitor bank ETI Summer 2020 Conceptual Conceptual ConceptualAccelerated from 2023 to 2020 based
on need
Summer 2020 N/A
12-ETI-017 4621 Appendix B Transmission Reliability - Meeting Planning Criteria
Gulfway 230 kV substation: Upgrade equipment on VFW Park 230 kV line bay
ETI Summer 2018 Proposed & In Target
Scoping Summer 2018 N/A
Long Term Projects Page 15 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
12-ETI-018 4798 Target Appendix A in MTEP15
Load Growth Forest: Construct new distribution substation ETI 2016 Proposed & In Target
Design Design is in progress Summer 2016 N/A
13-ETI-009-01 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Ponderosa to Grimes: Construct new 230 kV LineAdd 345-230 kV Auto at GrimesAdd 230-138 kV Auto at Ponderosa
ETI Summer 2016 Approved Design/Construction EPC partner under contract and working through design; ROW
activities continue.
Summer 2016 N/A
13-ETI-009-02 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Conroe to Ponderosa 138 kV line: Upgrade Line ETI Summer 2016 Approved Design/Construction Included in 13-ETI-009-01 Summer 2016 N/A
13-ETI-013 4617 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Egypt to Panorama 138 kV Line: Reconductor line ETI Summer 2017 Proposed & In Target
Design/Scoping Summer 2017 N/A
13-ETI-014 4623 Appendix B Transmission Reliability - Meeting Planning Criteria
Panorama to Longmire 138 kV Line: Reconductor ETI Summer 2019 Proposed & In Target
Scoping Summer 2019 N/A
13-ETI-021 4799 Appendix B Load Growth Dishman: Construct new substation ETI 2019 Proposed & In Target
Scoping Under Review 2019 N/A
14-ETI-001-01 4619 Appendix B Transmission Reliability - Meeting Planning Criteria
Raywood Area Improvements Add 2nd 138-69 kV Auto at Raywood
ETI Summer 2018 Proposed & In Target
Scoping Summer 2018 N/A
14-ETI-001-02 4624 Appendix B Transmission Reliability - Meeting Planning Criteria
Raywood Area Improvements Construct 2nd Raywood to Daisetta 69 kV line (extend line 440 approximately 2.2 miles to Daisetta substation)
ETI Summer 2019 Proposed & In Target
Scoping Summer 2019 N/A
14-ETI-004 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Leach 138 kV Substation: DTEC add 138 kV breakers(To accommodate DTEC/TEXLA Tie Project to close normally open point)
ETI Fall 2014 Approved Construction Customer has changed completion date of work at Leach SS to 30 Sept 2015. Relaying work at Newton and Leach will be done with line outages
just prior to DETEC installing line breakers and relaying at Leach SS.
9/30/2015 N/A
14-ETI-006-1 4801 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ETI SPOF Projects: Modify relaying at Sabine 230/138 kV
ETI Summer 2015 Proposed & In Target
Design Design is in progress 12/31/2015 N/A N/A
14-ETI-006-2 4802 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
ETI SPOF Projects: Modify relaying at VFW Park 230 kV
ETI Summer 2015 Proposed & In Target
Design Design is in progress 12/31/2015 N/A N/A
15-ETI-001 7897 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
South Beaumont: Install 3rd 138-69 autotransformer ETI Summer 2016 Proposed & In Target
Scoping New Project Summer 2016 N/A N/A
15-ETI-002 7900 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
South Beaumont to Winshire: Reconductor 69 kV lines 62 and 63
ETI Summer 2018 Proposed & In Target
Scoping New ProjectReplaces 11-ETI-037
Summer 2018 N/A N/A
15-ETI-003 7915 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Raywood: Add 138 kV, 37 MVAR capacitor bank ETI Summer 2016 Proposed & In Target
Scoping New Project Summer 2016 N/A N/A
Long Term Projects Page 16 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-ETI-004 7916 Appendix B Transmission Reliability - Meeting Planning Criteria
Cut 138 kV line 571 into New Caney Substation ETI Summer 2018 Proposed & In Target
Scoping New Project Summer 2018 N/A N/A
15-ETI-005 7922 Appendix B Transmission Reliability - Meeting Planning Criteria
Stowell: Replace 138/69 kV autotransformer #4 ETI Summer 2018 Proposed & In Target
Scoping New Project Summer 2018 N/A N/A
15-ETI-007-01 8582 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Alden 138 kV Substation: Add 200 MVAR SVC ETI Summer 2016 Proposed & In Target
Scoping New Project Replaces Porter to Forest 138 kV line
pre-planned project
Summer 2016 N/A N/A
15-ETI-007-02 8583 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Oakridge 138 kV Substation: Add Capacitor Bank ETI Summer 2016 Proposed & In Target
Scoping New ProjectAssociated with Alden SVC
Summer 2016 N/A N/A
15-ETI-007-03 8584 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Forest 138 kV Substation: Add Capacitor Bank ETI Summer 2016 Proposed & In Target
Scoping New ProjectAssociated with Alden SVC
Timing dependent on construction of new Forest Substation.
Project accelerated to coincide with Forest Substation project.
Summer 2016 N/A N/A
15-ETI-008 7930 Appendix B Load Growth Ranch: Construct new 138 kV substation ETI Winter 2018 Proposed & In Target
Scoping Under Review 5/1/2019 N/A N/A
15-ETI-009 7958 Appendix B Load Growth Linscomb: Construct new 230 kV substation ETI Summer 2018 Proposed & In Target
Scoping New Project Summer 2018 N/A N/A
15-ETI-011 8212 A in MTEP15 (OOC) Customer Driven Flatland: Construct new 138 kV substation ETI Summer 2015 Approved Construction Construction has begun. Contractor is 60% through site and foundation work.
7/15/2015 N/A N/A
15-ETI-012 8213 A in MTEP15 (OOC) Transmission Reliability - Meeting Planning Criteria
Upgrade 138 kV line 518 from Port Neches Bulk to new Flatland 138 kV Substation
ETI Summer 2015 Approved Construction Construction has begun. Contractor is 40% through t-line installation.
7/15/2015 N/A N/A
15-ETI-014 9281 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Cleveland to Tarkington 138 kV Line: Reconductor line ETI Summer 2018 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
8/31/2018 N/A
15-ETI-015-1 9282 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Carroll Street to South Beaumont 138 kV line (L-465): Reconductor Line
ETI Summer 2017 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
6/1/2017 N/A
15-ETI-015-2 9283 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Carroll Street to South Beaumont 138 kV line (L-828): Reconductor Line
ETI Summer 2017 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
6/1/2017 N/A
15-ETI-016 9280 Target Appendix A in MTEP15
Transmission Reliability - Meeting Planning Criteria
Cypress Substation: Add 2nd 500-138 kV autotransformer
ETI Summer 2020 Proposed & In Target
Scoping New Project Identified in MISO VLR Study
6/1/2020 N/A
15-ETI-018 9240 Target Appendix A in MTEP15
Customer Driven McFadden Bend 230 kV: Construct New Substation ETI Summer 2016 Approved Scoping/Design New Project 10/1/2015 N/A
15-ETI-019 9241 Target Appendix A in MTEP15
Customer Driven Deer Lake (Brazos) 138 kV: Cut-in New Substation ETI Winter 2016 Approved Scoping/Design New Project N/A
Long Term Projects Page 17 of 31
Report Date: July 9, 2015
Entergy Project ID MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportEntergy Long Term Transmission Plan
15-ETI-020 9242 Target Appendix A in MTEP15
Customer Driven Wildcat 69 kV: Construct New Substation ETI Winter 2016 Approved Scoping/Design New Project N/A
15-ETI-021 9243 Target Appendix A in MTEP15
Customer Driven Stilson 138 kV: Construct New Substation ETI Summer 2016 Approved Scoping/Design New Project 6/1/2016 N/A
15-ETI-022 9244 Target Appendix A in MTEP15
Customer Driven Seaward 230 kV: Construct New Substation ETI Summer 2016 Approved Scoping/Design New Project 9/30/2016 N/A
Long Term Projects Page 18 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
10CP-EAI-001 Transmission Reliability - Meeting Planning Criteria
Hamlet 161 kV Substation: Install 161 kV Breaker on Conway Industrial Line
EAI Summer 2009 Approved Complete In-service 12/4/09 12/4/09 Complete Yes
10CP-EAI-002 Transmission Reliability - Meeting Planning Criteria
Gillette 115 kV Substation: Install 10.8 MVAR Capacitor Bank
EAI Summer 2009 Approved Complete In-service 7/1/09 5/16/09 Complete Yes
10CP-EAI-003 Transmission Reliability - Meeting Planning Criteria
Conway West - Donaghey 161 kV Line: Reconductor with 666 ACSS
EAI Summer 2009 Approved Complete In-service 3/24/09 Complete Yes
10CP-EAI-004 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 10.8 MVAR capacitor bank at Emerson 115 kV substation
EAI Summer 2009 Approved Complete In-service 12/31/09 10/8/09 Complete Yes
10CP-EAI-005 Transmission Reliability - Meeting Planning Criteria
Danville 161 kV Substation: Upgrade Terminal Equipment to match or exceed Magazine line ratings
EAI Fall 2009 Approved Complete In-service 8/14/09 8/14/09 Complete Yes
10CP-EAI-006 Transmission Reliability - Meeting Planning Criteria
Donaghey - Conway South 161 kV Line: Reconductor with 666 ACSS
EAI Spring 2010 Approved Complete In-service 4/21/10 Complete Yes
10CP-EAI-007-1 Transmission Service SMEPA (Plum Point): * Dell - Manilla 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Approved Complete In-service 4/5/10 4/2/10 Complete Yes
10CP-EAI-007-2 Transmission Service SMEPA (Plum Point): * Manilla - Monette 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Approved Complete In-service 12/26/08 12/22/08 Complete Yes
10CP-EAI-007-3 Transmission Service SMEPA (Plum Point): * Jonesboro North - Paragould South 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Approved Complete In-service 5/29/09 5/14/09 Complete Yes
10CP-EAI-007-4 Transmission Service SMEPA (Plum Point): * Jonesboro North - Jonesboro 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Approved Complete In-service 1/8/10 1/9/10 Complete Yes
10CP-EAI-008 Transmission Reliability - Meeting Planning Criteria
Beebe 115 kV Substation: Install 21.6 MVAR Capacitor Bank
EAI Summer 2010 Approved Complete In-service 6/1/10 4/21/10 Complete Yes
10CP-EAI-009 Transmission Reliability - Meeting Planning Criteria
Melbourne - Sage 161 kV Line: Upgrade line to at least 1200 A
EAI Summer 2010 Approved Complete In-service 6/1/10 6/19/10 Complete Yes
10CP-EAI-010 Transmission Reliability - Meeting Planning Criteria
Warren East 115 kV Substation: Install 10.8 MVAR Capacitor Bank
EAI Summer 2010 Approved Complete In-service 8/6/10 7/18/10 Complete Yes
10CP-EAI-011 Transmission Reliability - Meeting Planning Criteria
Parkin to Twist 161 kV - Replace line trap at Parkin (increase rating of line segment)
EAI Winter 2010 Approved Complete In-service 12/31/10 12/22/10 Complete Yes
10CP-EAI-012-1 Transmission Service Transmission Service (OG&E) Upgrade ANO - Russelville North 161 kV Line to 546 MVA
EAI Summer 2010 Approved Complete In-service 6/1/10 5/18/10 Complete Yes
10CP-EAI-012-2 Transmission Service Transmission Service (OG&E) Upgrade Russelville East - Russelville South 161 kV Line to 448 MVA
EAI Summer 2010 Approved Complete In-service 9/30/10 8/12/10 Complete Yes
10-EAI-013-CP Transmission Reliability - Meeting Planning Criteria
Osage Creek-Grandview New Line Build new 161 kV (At Least 1200 A) line from Grandview (Planned SPA 161 kV Substation tapped on the Eureka - Table Rock 161 kV Line) to Osage Creek
EAI Summer 2011 Approved Complete In-service 12/15/11 11/28/11 Complete Yes
10CP-EAI-014 Transmission Reliability - Meeting Planning Criteria
Harrison East to Everton Road 161 kV Line: Upgrade Harrison East Terminal Equipment to 1200 A
EAI Winter 2009 Approved Complete In-service 12/15/09 12/15/09 Complete Yes
10CP-EAI-016-1 Transmission Service Transmission Service (Aquila) Upgrade Hot Springs - Bismark 115 kV Line to 176 MVA
EAI Winter 2011 Approved Complete In-service 6/1/11 10/20/10 Complete Yes
10-EAI-015-1-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 1 Projects Tap the Keo - ISES 500 kV Line Tap the Cabot - Jacksonville North 115 kV Line Install 500 kV and 115 kV Busses and a 600 MVA 500 kV / 115 kV Autotransformer
EAI Summer 2011 Approved Complete In-service 12/31/11 1/6/12 Complete Yes
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
Completed Projects Page 19 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10-EAI-015-2-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 2 Projects Install 161 kV Bus and a 600 MVA 500 kV / 161 kV Autotransformer
EAI Summer 2012 Approved Complete In-service 6/1/12 5/23/12 Complete Yes
10CP-EAI-016-2 Transmission Service Transmission Service (Aquila) Upgrade Bismark - Alpine 115 kV Line to 176 MVA
EAI Winter 2011 Approved Complete In-service 2/28/11 3/2/11 Complete Yes
10CP-EAI-016-3 Transmission Service Transmission Service (Aquila) Upgrade Alpine - Amity 115 kV Line to 176 MVA
EAI Winter 2011 Approved Complete In-service 3/31/11 3/22/11 Complete Yes
10-EAI-017-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms - Hamlet 161 kV Line: Construct new 161 kV Line Convert Hamlet SS to a breaker station (Single Bus Single Breaker Scheme) Move the Quitman line from Gold Creek to Hamlet SS Move the Gravel Ridge line from Gold Creek to Hamlet SS Construct a line rated at least 1200 A from Hamlet SS to Holland Bottoms
EAI Summer 2012 Approved Complete In-service 6/1/12 5/23/12 Complete Yes
10-EAI-018-CP Transmission Reliability - Meeting Planning Criteria
Ebony 161 kV Switching Station: Install 5 Breaker Ring Bus Lines Terminating Into New Ebony Substation (ratings unchanged): Ebony - Kuhn Road 161 kV Line Ebony - WM Lehi - WM Polk - WM EHV 161 kV Line Ebony - WM Dover - WM Gateway 161 kV Line Ebony - Marked Tree 161 kV Line Ebony - WM Lehi - WM EHV 161 kV Line
EAI Summer 2012 Approved Complete In-service 12/31/12 11/16/12 Complete Yes
10-EAI-019-CP Transmission Reliability - Meeting Planning Criteria
Jonesboro to Hergett 161 kV Line: Upgrade 161 kV Line to at least 240 MVA
EAI Summer 2012 Approved Complete In-service 5/1/12 5/3/12 Complete Yes
10-EAI-020-CP Transmission Reliability - Meeting Planning Criteria
Benton North to Benton South: Construct New 115 kV Line Rated at least 170 MVA Install Switching Stations at Benton North and Benton South
EAI Winter 2012 Approved Complete In-service 6/30/13 4/22/13 Complete Yes
10-EAI-022-1-CP Transmission Service Westar Transmission Service Monette - Paragould 161kV Line: Upgrade to at least 246 MVA
EAI Summer 2012 Approved Complete In-service 12/30/11 1/10/12 Complete Yes
10-EAI-022-2-CP Transmission Service Westar Transmission Service Paragould Substation: Upgrade the switch B6673 from 600A to 2000A
EAI Summer 2012 Approved Complete In-service 10/16/11 9/29/11 Complete Yes
10-EAI-022-3-CP Transmission Service Westar Transmission Service Russellville South - Dardanelle Dam (SPA) 161kV Line: Replace switch
EAI Summer 2012 Approved Complete In-service 12/31/11 10/31/11 Complete Yes
14-EAI-020-5 4748 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: L.R. Alexander 115 kV B0639-CBO
EAI Winter 2014 Approved Complete In service. 2015 5/14/15 N/A N/A
14-EAI-020-6 4749 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: Searcy Price 115 kV B5310-ICBO
EAI Winter 2014 Approved Complete In service. 2015 5/14/15 N/A N/A
10CP-EAI-023 Transmission Reliability - Meeting Planning Criteria
Couch to McNeil 115kV Line: Upgrade jumpers at Couch
EAI Summer 2011 Approved Complete In-service Winter 2010 1/20/11 Complete Yes
10CP-EAI-024 Transmission Reliability - Meeting Planning Criteria
Lake Catherine 4 to Arklahoma 115 kV line: Upgrade risers at Arklahoma
EAI Summer 2011 Approved Complete In-service Spring 2011 1/24/11 Complete Yes
14-EAI-025 4759 A in MTEP14 Customer Driven Smackover Industrial 115 kV Substation: Construct new substation
EAI Spring 2015 Approved Complete In-service 2/15/2015 2/18/15 N/A Yes
10CP-EAI-026 Transmission Reliability - Meeting Planning Criteria
Mablevale to LR Alexander 115 kV line: Replace switches and risers at Mablevale and upgrade bus at LR Mann Road
EAI Winter 2010 Approved Complete In-service 4/6/11 4/13/11 Complete Yes
Completed Projects Page 20 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10CP-EAI-027 Transmission Reliability - Meeting Planning Criteria
Russelville North to Russelville East 115 kV line: Replace jumpers at Russellville East
EAI Spring 2011 Approved Complete In-service Winter 2010 1/17/10 Complete Yes
10CP-EAI-028 Transmission Reliability - Meeting Planning Criteria
Morgan to Mayflower 115 kV line: Replace jumpers and bus at Mayflower
EAI Summer 2011 Approved Complete In-service 2/4/11 2/8/11 Complete Yes
10CP-EAI-029 Transmission Reliability - Meeting Planning Criteria
Maumelle East SS to Morgan 115 kV line: Replace switch and bus at Maumelle East SS
EAI Summer 2011 Approved Complete In-service Spring 2011 4/12/11 Complete Yes
10CP-EAI-030 Transmission Reliability - Meeting Planning Criteria
Heber Springs South to Heber Springs Industrial 161 kV line: Replace bus at Heber Springs South
EAI Summer 2011 Approved Complete In-service 4/7/11 4/25/11 Complete Yes
10-EAI-031-CP Economic West Memphis to Birmingham Steel 500 kV line flowgate: Replace 500 kV breaker, six line traps, and 2 switches at West Memphis 500 kV substation
EAI Winter 2011 Approved Complete In-service 3/5/12 2/28/12 Complete Yes
11-EAI-001-CP Transmission Reliability - Meeting Planning Criteria
Pine Bluff Voltage Support Project - Phase 1 Poyen 115 kV Substation: Add 21.6 MVAR Capacitor Bank
EAI Summer 2012 Approved Complete In-service 6/15/12 5/31/12 Complete Yes
11-EAI-003-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Fordyce: Relocate capacitor bank to 115 kV bus. Install switch on line side of capacitor bank.
EAI Summer 2014 Approved Complete In-service 6/1/14 2/18/14 N/A Yes
11-EAI-004-1-CP N/A Pre-Planned Economic Sheridan South 500 kV FG Upgrade: Mabelvale 500 kV Substation replace 3 breakers, 13 switches, and 2 line traps
EAI Summer 2014 Approved Complete In-service 6/1/14 12/5/13 N/A Yes
11-EAI-004-2-CP N/A Pre-Planned Economic Sheridan South 500 kV FG Upgrade: Sheridan 500 kV Substation replace 11 switches, and 6 line traps
EAI Summer 2014 Approved Complete In-service 6/1/14 12/5/13 Complete Yes
11-EAI-004-4-CP N/A Pre-Planned Economic Sheridan South 500 kV FG Upgrade: Eldorado 500 kV Substation replace 1 switch and 2 line traps
EAI Summer 2014 Approved Complete In-Service. Work completed at El Dorado 4/19/13. Work completed at Sheridan end.
6/1/14 12/5/13 Complete Yes
11-EAI-004-3-CP N/A Pre-Planned Economic Sheridan South 500 kV FG Upgrade: White Bluff 500 kV Substation replace 5 switches
EAI Summer 2014 Approved Complete In-Service. Construction at White Bluff Complete 3/16/13. Work completed on White Bluff end 10/8/13. Complete Sheridan to White Bluff 500 kV line upgrade complete 10/8/13.
6/1/14 10/8/13 Complete Yes
11-EAI-006-CP Transmission Reliability - Meeting Planning Criteria
Ebony 161 kV Switching Station: Add 36 MVAR Capacitor Bank
EAI Winter 2012 Approved Complete In-service 12/31/12 11/30/12 Complete Yes
11-EAI-010-CP Transmission Reliability - Meeting Planning Criteria
Wilmar Substation: Add 21.6 MVAR Capacitor Bank (Formerly Hilo Substation)
EAI Winter 2012 Approved Complete In-service 2/15/13 1/21/13 Complete Yes
11CP-EAI-011 Transmission Reliability - Meeting Planning Criteria
Pangburn 161 kV Substation: Relocate Rutherford 161 kV Cap Bank to Pangburn
EAI Summer 2011 Approved Complete In-service 8/22/11 8/31/11 Complete Yes
11-EAI-012-CP Transmission Reliability - Meeting Planning Criteria
Stuttgart Ricuskey 115 kV Substation: Expand Capacitor Bank to 39 MVAR
EAI Summer 2013 Approved Complete In-service Summer 2013 6/3/13 Complete Yes
11CP-EAI-013 Transmission Reliability - Meeting Planning Criteria
Woodward to Pine Bluff Watson Chapel: Upgrade bus at PB Watson Chapel
EAI Summer 2011 Approved Complete In-service 5/1/11 4/26/11 Complete Yes
11-EAI-026-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
NLR Westgate - NLR Levy: Reconductor 115 kV Line EAI Summer 2013 Approved Complete In-Service 12/31/13 12/5/13 Complete Yes
12-EAI-001 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Calico Rock-Melbourne - Upgrade 161kV Line EAI Winter 2014 Approved Complete In-Service 12/31/14 12/22/14 N/A Yes
12-EAI-002-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Woodward - Pine Bluff West - Pine Bluff McCamant: Reconductor 115 kV
EAI Summer 2014 Approved Complete In-service 6/1/14 1/15/14 N/A Yes
Completed Projects Page 21 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
12-EAI-008-01 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
LV Bagby to Macon Lake: Construct new 230 kV line and operate at 115 kV
EAI Summer 2014 Approved Complete In-Service 6/1/14 5/8/14 N/A Yes
12-EAI-020-CP Transmission Reliability - Meeting Planning Criteria
Mabelvale: Change 500-115 NLTC from 487.5kV tap to 512.5kV tap
EAI Summer 2013 Approved Complete In-service 5/10/12 5/10/12 Complete Yes
12-EAI-023 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Woodward to Pine Bluff Watson Chapel: Rebuild line to 230 kV construction and operate at 115 kV.
EAI Summer 2014 Approved Complete In-Service 6/1/14 6/17/14 N/A
12-EAI-028-CP Transmission Reliability - Meeting Planning Criteria
Quitman to Bee Branch: Replace 600A switch(Formerly upgrade line project)
EAI Winter 2012 Approved Complete In-service 12/31/12 10/23/12 Complete Yes
12-EAI-036-CP N/A N/A Load Growth Fountain Lake 115 kV New Substation EAI 2013 Approved Complete In-service 2013 1/24/13 N/A Yes12-EAI-039-CP N/A N/A Transmission Service AECI: Steele Substation EAI 2013 Approved Complete In-service 2013 3/7/13 N/A Yes12-EAI-041-CP N/A N/A Load Growth Vilonia: Build New Substation EAI 2014 Approved Complete In-service 2014 12/13/13 N/A Yes13-EAI-004-CP Transmission Reliability - Meeting
Planning CriteriaMonticello East - Add 21.6 MVAR capacitor bank EAI Summer 2013 Approved Complete In-service Summer 2013 5/29/13 Complete Yes
13-EAI-007-CP Transmission Reliability - Meeting Planning Criteria
Jim Hill to St. Francis 161 kV line: Upgrade terminal equiment at Jim Hill
EAI Fall 2012 Approved Complete In-service 12/1/12 10/23/12 Complete Yes
13-EAI-008-CP Transmission Reliability - Meeting Planning Criteria
Hot Springs EHV Substation: Replace two 115 kV autotransformer breakers
EAI Summer 2013 Approved Complete In-service 6/30/13 6/20/13 Complete Yes
13-EAI-009-CP N/A Pre-Planned Transmission Service Hot Spring Transmission Service: White Bluff to Pine Bluff Arsenal C - Upgrade terminal equipment at White Bluff
EAI Winter 2013 Approved Complete In-Service Winter 2013 11/26/13 Complete Yes
13-EAI-010 4740 A in MTEP14 Load Growth Lawson Road: Build new substation EAI 2014 Approved Complete In Service. 2014 10/17/14 N/A Yes
14-EAI-002 N/A Pre-Planned Transmission Service Hot Springs Transmission Service:McCrory-Bailey: Upgrade line to 100C
EAI Summer 2014 Approved Complete In-Service Summer 2014 5/20/14 N/A Yes
14-EAI-008 N/A Pre-Planned Transmission Service Haskell to Woodlawn 115 kV line - Upgrade line EAI Winter 2014 Approved Complete In-service 12/1/2014 12/4/14 N/A Yes
14-EAI-020-2 4745 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: P.B. Dierks 115 kV B0938-CBO
EAI Winter 2014 Approved Complete In-service Winter 2014 7/15/14 N/A N/A
14-EAI-020-3 4746 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
EAI Underrated Breaker Project: L.R. Hindman 115 kV B0988-CBO
EAI Winter 2014 Approved Complete In-service 2015 11/24/14 N/A N/A
14-EAI-023 4738 A in MTEP14 Customer Driven AECC Shaw POD (Woodlawn Expansion) EAI 2014 Approved Complete In service. Spring 2015 4/9/15 N/A Yes
Completed Projects Page 22 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
14-EAI-024-CP TBD A in MTEP14 Customer Driven Benton West 115 kV Substation: Construct new substation
EAI Spring 2014 Approved Complete In-service 5/1/2014 1/17/14 N/A Yes
10CP-EGL-001 Transmission Reliability - Meeting Planning Criteria
Acadia 138 kV Substation: Install 36 MVAR Capacitor Bank
EGSL-F Summer 2009 Approved Complete In-service 6/19/09 Complete Yes
10CP-EGL-002 Transmission Reliability - Meeting Planning Criteria
Addis to Cajun 230 kV line - Upgrade Limiting Section With Double-Bundled 649.5 ACAR (654 MVA)
EGSL-B Winter 2010 Approved Complete In-service 12/31/10 12/15/10 Complete Yes
10CP-EGL-003 Transmission Reliability - Meeting Planning Criteria
Carter and Elton Capacitor Banks: Upgrade 69 kV capacitor bank at Elton to 14 MVAR, Add 69 kV, 14 MVAR capacitor bank at Carter
EGSL-C Fall 2010 Approved Complete In-service 12/3/10 10/27/10 Complete Yes
10-EGL-004-CP Transmission Reliability - Meeting Planning Criteria
Construct New Youngsville 138 kV Distribution Substation
EGSL-F Winter 2011 Approved Complete In-service 12/31/11 11/21/11 Complete Yes
10CP-EGL-005 Transmission Reliability - Meeting Planning Criteria
Alchem - Monochem 138 kV Line: Upgrade 138 kV line to 275 MVA
EGSL-B Summer 2011 Approved Complete In-service 5/1/11 5/24/11 Complete Yes
10CP-EGL-006-1 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Construct new Sellers Road to Meaux 230 kV Line
EGSL-F Summer 2011 Approved Complete In-service 5/6/11 5/6/11 Complete Yes
10CP-EGL-006-2 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add 450 MVA, 230-138 kV auto at Meaux
EGSL-F Summer 2011 Approved Complete In-service 5/2/11 5/6/11 Complete Yes
10CP-EGL-006-3 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add new 138 kV line bay at Moril (Segura Line)
EGSL-F Summer 2011 Approved Complete In-service 5/5/10 Complete Yes
10CP-EGL-006-4 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add new 500 kV position for Cleco autotransformer at Richard
EGSL-F Summer 2011 Approved Complete In-service 11/22/10 5/6/11 Complete Yes
10-EGL-007-1-CP Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 2 Projects Construct new Labbe to Sellers Road 230 kV Line
EGSL-F Summer 2012 Approved Complete In-service 6/29/12 6/28/12 Complete Yes
10-EGL-007-2-CP Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 2 Projects Add new 500 kV position for Cleco autotransformer at Wells
EGSL-F Summer 2012 Approved Complete In-service 3/19/12 3/16/12 Complete Yes
10-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Construct new Nelson to Moss Bluff 230 kV line Disconnect existing Nelson to Moss Bluff 230 kV line Will be used in the future to create a Nelson to new Lake Charles 230 kV line
EGSL-C Summer 2012 Approved Complete In-service 5/31/12 5/12/12 Complete Yes
10-EGL-009-CP Transmission Reliability - Meeting Planning Criteria
Tejac to Marydale: Upgrade 69 kV transmission line EGSL-B Summer 2012 Approved Complete In-service 1/31/12 2/15/12 Complete Yes
10-EGL-010-CP Transmission Reliability - Meeting Planning Criteria
Loblolly-Hammond Build 230 kV Line EGSL-B/ELL-S Summer 2012 Approved Complete In-service 6/1/12 12/16/11 Complete Yes
10-EGL-011-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Mossville - Cut-in line 616 (Nelson to Carlyss 138 kV) into Mossville 138 kV Substation
EGSL-C Summer 2013 Approved Complete In-service 12/5/13 12/12/13 N/A Yes
10CP-EGL-013 Transmission Reliability - Meeting Planning Criteria
Krotz Springs to Line 642 Tap 138 kV line: Upgrade bus at Colonial Springs Tap
EGSL-F Summer 2013 Approved Complete In-service Spring 2011 3/14/11 Complete Yes
10CP-EGL-014 Transmission Reliability - Meeting Planning Criteria
Livonia to Line 643 Tap 138 kV line: Upgrade riser at Livonia
EGSL-F Winter 2010 Approved Complete In-service Spring 2011 3/16/11 Complete Yes
10CP-EGL-015 Transmission Reliability - Meeting Planning Criteria
Wilbert to Livonia 138 kV line: Upgrade risers at Wilbert and Livonia
EGSL-F Summer 2011 Approved Complete In-service Spring 2011 1/25/11 Complete Yes
10CP-EGL-016 Transmission Reliability - Meeting Planning Criteria
Big Three to Carlyss 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation
EGSL-C Summer 2011 Approved Complete In-service 5/6/11 6/9/11 Complete Yes
Completed Projects Page 23 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10-EGL-017-CP Transmission Reliability - Meeting Planning Criteria
Richard to Habetz 138 kV line: Upgrade bus at Richard EGSL-F Winter 2010 Approved Complete In-service 11/30/11 10/10/11 Complete Yes
10-EGL-018-CP Transmission Reliability - Meeting Planning Criteria
Willow Glen to Bayou LaButte 500 kV line: Replace/change line relay CT and ratio at Willow Glen (Formerly Willow Glen to Webre)
EGSL-B Summer 2011 Approved Complete In-service 3/31/12 2/27/12 Complete Yes
10CP-EGL-019 Transmission Reliability - Meeting Planning Criteria
Willow Glen to Geismar 138 kV line: Upgrade risers at Willow Glen and Geismar
EGSL-B Summer 2011 Approved Complete In-service Summer 2011 1/20/11 Complete Yes
10CP-EGL-020 Transmission Reliability - Meeting Planning Criteria
Port Hudson to Fancy Point 230 kV line: Upgrade bus at Fancy Point
EGSL-B Winter 2010 Approved Complete In-service Winter 2010 12/20/10 Complete Yes
10CP-EGL-021 Transmission Reliability - Meeting Planning Criteria
Richard to Scott 1 138kV segment: Replace/change CT ratio at Richard and upgrade bus at Scott
EGSL-F Winter 2010 Approved Complete In-service Winter 2010 1/7/11 Complete Yes
10CP-EGL-022 Transmission Reliability - Meeting Planning Criteria
Carlyss to Rose Bluff 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation
EGSL-C Winter 2010 Approved Complete In-service Spring 2011 5/23/11 Complete Yes
11-EGL-010 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Sorrento Upgrade 138/115 kV Auto and upgrade Gonzales - Sorrento 138 kV Line
EGSL-B/ELL-S Summer 2014 Approved Complete In-Service 6/1/14 4/30/14 N/A Yes
11-EGL-004-CP Transmission Reliability - Meeting Planning Criteria
Bloomfield to Bosco 138 kV line (formerly Vatican project) Construct new Bloomfield 138 kV SS north of Vatican Construct new Bosco 138 kV SS on Scott to Scanlan 138 kV line Construct new Bloomfield to Bosco 138 kV line Install 5 ohm reactor at Bosco substation
EGSL-F Summer 2013 Approved Complete In-service 12/31/12 12/20/12 Complete Yes
11-EGL-005-CP Transmission Reliability - Meeting Planning Criteria
Jackson to Tejac: Upgrade 69 kV transmission line EGSL-B Summer 2012 Approved Complete In-service 6/15/12 6/5/12 Complete Yes
11-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Francis 69 kV substation - Add 14.4 MVAR, 69 kV capacitor bank (Previously considered Marydale as alternate location)
EGSL-B Summer 2013 Approved Complete In-service 3/29/13 3/25/13 Complete Yes
11CP-EGL-011 Transmission Reliability - Meeting Planning Criteria
Carlyss to Citcon West 138 kV: Upgrade station equipment
EGSL-C Winter 2011 Approved Complete In-service 9/29/11 9/28/11 Complete Yes
11CP-EGL-012 Transmission Reliability - Meeting Planning Criteria
Carlyss to Nelson 230 kV: Upgrade station equipment at Carlyss
EGSL-C Winter 2013 Approved Complete In-service Spring 2011 6/9/11 Complete Yes
11-EGL-013-CP Transmission Reliability - Meeting Planning Criteria
Fireco to Copol 69 kV line: Upgrade switches and line trap
EGSL-B Summer 2012 Approved Complete In-service 6/1/12 5/21/12 Complete Yes
11-EGL-013-1-CP Transmission Reliability - Meeting Planning Criteria
Fireco to Copol 69 kV line: Upgrade line conductor EGSL-B Winter 2012 Approved Complete In-service 12/31/12 12/17/12 Complete Yes
11-EGL-014-CP Transmission Reliability - Meeting Planning Criteria
Addis 69 kV Substation: Upgrade 69 kV switches and line trap
EGSL-B Summer 2012 Approved Complete In-service 6/1/12 5/21/12 Complete Yes
11-EGL-015-1-CP Transmission Service Acadia Generation - Reconfigure Richard 138 kV substation (Upgrade ckts 3 and 4 and Richard relaying work)
EGSL-F Summer 2013 Approved Complete In-service 6/15/12 5/15/12 Complete Yes
11-EGL-015-3-CP Transmission Service Acadia Generation - Upgrade Moril to Hopkins 138 kV line
EGSL-F Summer 2013 Approved Complete In-service 11/15/12 10/30/12 Complete Yes
11-EGL-015-4-CP Transmission Service Acadia Generation - Upgrade 69 kV breaker at Scott 18220
EGSL-F Summer 2013 Approved Complete In-service 10/28/12 10/11/12 Complete N/A
11-EGL-016-01-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Mossville to Canal - Phase 1: Upgrade 69 kV Line EGSL-C Winter 2013 Approved Complete In-service 1/30/14 1/26/14 N/A Yes
11-EGL-016-02 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Mossville to Canal - Phase 2: Upgrade 69 kV Line EGSL-C Winter 2014 Approved Complete In-service 3/15/15 3/13/15 N/A Yes
12-EGL-003-CP Transmission Reliability - Meeting Planning Criteria
Champagne to Plaisance 138 kV line - Modify/Replace CTs at Champagne
EGSL-F Summer 2013 Approved Complete In-service 6/1/13 12/26/12 Complete Yes
12-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Copol to Bourbeaux: Upgrade 69 kV line EGSL-B Winter 2014 Approved Complete In-service 4/3/13 4/18/13 Complete Yes
Completed Projects Page 24 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
12-EGL-014-CP Transmission Reliability - Meeting Planning Criteria
Lake Charles Bulk Substation: Replace four 69 kV, 600 A switches on transformers and bus section breaker with 1200 A switches
EGSL-C Fall 2012 Approved Complete In-service 12/1/12 1/28/13 Complete Yes
12-EGL-015 N/A Pre-Planned Economic Willow Glen to Conway - Construct new 230 kV line EGSL-B Spring 2014 Approved Complete In-service. 10/1/14 10/7/14 N/A Yes
13-EGL-004-CP N/A N/A Customer Driven Brittany 230 kV Substation: Construct new substation and cut-in to Willow Glen to Conway 230 kV line
EGSL-B 2013 Approved Complete In-service 2013 10/21/13 N/A
14-EGL-005 4625 A in MTEP14(OOC)
Transmission Reliability - Meeting Planning Criteria
Nelson: Upgrade 500-230 kV single phase transformer bank with 1200 MVA transformer bank
EGSL-C Winter 2015 Approved Complete In-Service Spring 2015 4/28/15 N/A Yes
14-EGL-025 4768 A in MTEP14 Customer Driven Boxwood 230 kV Substation: Cut-in new substation on the Willow Glen to Brittany 230 kV line
EGSL-B Winter 2014 Approved Complete In Service. Winter 2014 10/17/14 N/A Yes
10CP-ELL-001 Transmission Reliability - Meeting Planning Criteria
Snakefarm to Kenner 115 kV line: Upgrade to 359 MVA ELL-S Spring 2010 Approved Complete In-service 3/25/10 Complete Yes
10CP-ELL-002 Transmission Reliability - Meeting Planning Criteria
Bogalusa to Adams Creek 230 kV No. 2 - Upgrade terminal equipment at Bogalusa
ELL-S Winter 2009 Approved Complete In-service 1/18/10 Complete Yes
10CP-ELL-003 Transmission Reliability - Meeting Planning Criteria
Delhi 115 kV Substation - Add 30.5 MVAR Capacitor Bank
ELL-N Winter 2009 Approved Complete In-service 10/21/09 Complete Yes
10CP-ELL-004 Economic Delhi 115 kV Substation - Add 10 Ohm series reactor ELL-N Spring 2010 Approved Complete In-service 5/28/10 5/20/10 Complete Yes
10CP-ELL-005-1 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Construct a new 345-115 kV substation consisting of a 500 MVA auto. Cut station into EL Dorado to Longwood 345 kV line.
ELL-N Summer 2011 Approved Complete In-service 6/1/11 6/15/11 Complete Yes
10CP-ELL-005-2 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Lucky 115 kV substation
ELL-N Summer 2011 Approved Complete In-service 3/1/09 Complete Yes
10CP-ELL-005-3 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Vienna 115 kV substation
ELL-N Summer 2011 Approved Complete In-service 10/1/09 Complete Yes
10-ELL-006-CP Transmission Reliability - Meeting Planning Criteria
Bayou LaButte: Construct new 500-230 kV Substation Install 800 MVA, 500-230 kV autotransformer Cut in Webre to Willow Glen 500 kV line Construct new 230 kV line from Bayou LaBoutte to Iberville 230 kV substation
ELL-S Winter 2011 Approved Complete In-service 12/15/11 11/22/11 Complete Yes
10-ELL-007-CP Transmission Reliability - Meeting Planning Criteria
Southeast LA Coastal Improvement Plan: Phase 2 Build Peters Road-Oakville 230kV Line and Substation
ELL-S Summer 2012 Approved Complete In-service 9/20/12 9/6/12 Complete Yes
10-ELL-009 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Iron Man to Tezcuco 230 kV line - Construct new line ELL-S Summer 2015 Approved Complete In-service 12/31/14 12/9/14 N/A Yes
10-ELL-010-1-CP Transmission Service Ouachita Transmission Service Split Sterlington 115 kV bus and replace 500-115 auto #2 with 750 MVA
ELL-N Summer 2012 Approved Complete In-service 3/9/12 3/12/12 Complete Yes
10-ELL-010-2-CP Transmission Service Ouachita Transmission Service Upgrade Walnut Grove to Swartz 115 kV line
ELL-N Spring 2013 Approved Complete In-service 5/18/12 4/17/12 Complete Yes
10CP-ELL-010-3 Transmission Service Ouachita Transmission Service Upgrade Frostkraft to Rilla 115 kV line
ELL-N Summer 2012 Approved Complete In-service 6/4/10 6/14/10 Complete Yes
Completed Projects Page 25 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10-ELL-010-4-CP Transmission Service Ouachita Transmission Service Upgrade Sterlington to Log Cabin 115 kV line
ELL-N Summer 2012 Approved Complete In-service 6/1/12 12/20/11 Complete Yes
10CP-ELL-010-5 Transmission Reliability - Meeting Planning Criteria
Ouachita Transmission Service Loop Sterlington to North Crossett into North Bastrop
ELL-N Summer 2012 Approved Complete In-service 6/1/11 6/15/11 Complete Yes
10CP-ELL-010-6 Transmission Service Ouachita Transmission Service Add 43 MVAR, 115 kV capacitor bank at Riser
ELL-N Summer 2012 Approved Complete In-service 11/1/10 11/23/10 Complete Yes
10CP-ELL-011 Transmission Reliability - Meeting Planning Criteria
Barataria to Ninemile 115 kV line: Replace line Trap ELL-S Winter 2010 Approved Complete In-service 3/31/11 4/11/11 Complete Yes
10CP-ELL-012 Transmission Reliability - Meeting Planning Criteria
Waterford to Ninemile 230 kV line: Replace line trap, switches, and jumpers at Ninemile
ELL-S Summer 2011 Approved Complete In-service 5/31/11 5/31/11 Complete Yes
10CP-ELL-013 Transmission Reliability - Meeting Planning Criteria
Raceland to Couteau 115 kV line: Replace switch, jumpers and line trap
ELL-S Winter 2010 Approved Complete In-service Winter 2010 10/25/10 Complete Yes
11-ELL-001 N/A Pre-Planned Enhanced Transmission Reliability Golden Meadow to Leeville 115 kV - Rebuild/relocate 115 kV transmission line
ELL-S Spring 2014 Approved Complete In-service 3/31/15 3/23/15 N/A Yes
11-ELL-002-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Mt. Olive: Add Shunt Reactor ELL-N Winter 2013 Approved Complete In-service 12/13/13 12/19/13 Complete Yes
11-ELL-003-1-CP Transmission Reliability - Meeting Planning Criteria
NE Louisiana Improvement Project - Phase 1 Swartz to Oak Ridge - Construct new 115 kV Line (1272 ACSS) Operate Sterlington to Oak Ridge normally open
ELL-N Summer 2013 Approved Complete In-service 5/24/13 3/22/13 Complete Yes
11-ELL-003-2 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
NE Louisiana Improvement Project - Phase 2 Oak Ridge to new Dunn Substation - Construct new 115 kV Line (1272 ACSS) Add 115 kV breakers at Dunn
ELL-N Summer 2014 Approved Complete In Service 12/19/14 11/13/14 N/A Yes
11CP-ELL-006 Transmission Reliability - Meeting Planning Criteria
Hooker to Waterford 230 kV line - Upgrade station equipment
ELL-S Spring 2011 Approved Complete In-service Spring 2011 5/17/11 Complete Yes
11CP-ELL-007 Transmission Reliability - Meeting Planning Criteria
Waterford to Union Carbide 230 kV line - Upgrade station equipment
ELL-S Spring 2011 Approved Complete In-service Spring 2011 5/26/11 Complete Yes
11CP-ELL-008 Transmission Reliability - Meeting Planning Criteria
Union Carbide to Hooker 230 kV line - Upgrade station equipment
ELL-S Spring 2011 Approved Complete In-service Spring 2011 4/12/11 Complete Yes
11-ELL-009-1 N/A Pre-Planned Generation Interconnection NM6: Modify Ninemile switchyard for interconnection ELL-S Winter 2014 Approved Complete In-service (Transmission work) 12/1/14 6A&6B on 1/31/14; 6C on
05/14/14
N/A Yes
11-ELL-010-1-CP N/A Pre-Planned Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.1
ELL-S Winter 2014 Approved Complete In-Service 12/31/13 11/25/13 Complete Yes
11-ELL-010-2-CP N/A Pre-Planned Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.2
ELL-S Winter 2014 Approved Complete In-Service 12/31/13 11/19/13 Complete Yes
11-ELL-012 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Valentine to Clovelly 115 kV upgrade ELL-S Summer 2015 Approved Complete In service. 5/1/15 4/14/15 Planned NCLL until project completed Yes
12-ELL-001-CP Transmission Reliability - Meeting Planning Criteria
Gypsy to Luling: Upgrade line bay bus and jumpers at Luling
ELL-S Summer 2012 Approved Complete In-service 6/1/12 12/22/11 Complete Yes
13-ELL-001-CP Transmission Reliability - Meeting Planning Criteria
Golden Meadow to Barataria: Upgrade switch ELL-S Summer 2013 Approved Complete In-service 4/30/13 4/25/13 Complete Yes
13-ELL-002-CP Transmission Reliability - Meeting Planning Criteria
McCall 115 kV Substation: Add 20.4 MVAR Capacitor Bank (Formerly Napoleonville add capacitor bank)
ELL-S Fall 2013 Approved Complete In-service 9/25/13 8/19/13 Complete Yes
13-ELL-009-CP N/A N/A Customer Driven Ormond: Construct new 115 kV substation ELL-S 2014 Approved Complete In-service 2014 11/11/13 N/A14-ELL-008-3 4772 A in MTEP14 Transmission Reliability - Meeting
Planning CriteriaELL Underrated Breaker Project: Ninemile 115 kV S6342-CO
ELL-S Winter 2016 Approved Complete In-Service. Breaker was completed during Ninemile
generation project
Winter 2016 10/18/13 N/A N/A
14-ELL-016 4783 A in MTEP14 Customer Driven Haute 115 kV Substation: Construct new substation and cut into existing Lutcher to Belle Point 115 kV line
ELL-S Summer 2014 Approved Complete In-Service 4/1/2015 3/31/15 N/A N/A
Completed Projects Page 26 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
14-ELL-017 4784 A in MTEP14 Customer Driven Derrick 230 kV Substation: Construct new 230 kV substation and cut into Iberville to Chenago 230 kV line
ELL-S Fall 2014 Approved Complete In-Service 10/1/2014 5/6/14 N/A Yes
14-ELL-018 7841 A in MTEP14 (OOC)
Customer Driven Reese Substation: Construct new 115 kV substations ELL-N Spring 2015 Approved Complete In-Service Spring 2015 12/17/14 N/A Yes
10CP-EMI-001 Transmission Reliability - Meeting Planning Criteria
Liberty-Gloster: Upgrade 115 kV Line For Natchez De-listing
EMI Summer 2009 Approved Complete In-service 4/25/09 Complete Yes
10CP-EMI-002 Transmission Reliability - Meeting Planning Criteria
Indianola-Greenwood 115 kV Line: Upgrade line to 161 MVA Upgrade Terminal Equipment at Morehead, Itta Bena, and Greenwood
EMI Summer 2010 Approved Complete In-service 5/26/10 6/10/10 Complete Yes
10-EMI-003-CP Transmission Reliability - Meeting Planning Criteria
Magee 115 kV Substation: Replace Switches EMI Winter 2011 Approved Complete In-service 12/15/11 11/30/11 Complete Yes
10CP-EMI-004-1 Transmission Service TVA Affected System Upgrades Morton 115 kV Substation: Upgrade 600 A Switches to 1200A
EMI Spring 2010 Approved Complete In-service 11/6/09 Complete Yes
10CP-EMI-004-2 Transmission Service TVA Affected System Upgrades South Jackson - Florence 115 kV Line: Upgrade to at least 240 MVA
EMI Spring 2010 Approved Complete In-service 4/23/10 Complete Yes
10CP-EMI-005 Transmission Service Grand Gulf Uprate Project Baxter Wilson - Ray Braswell 500 kV Line: Upgrade Breakers and Switches to 3000 A
EMI Summer 2010 Approved Complete In-service 4/9/10 Complete Yes
10CP-EMI-006-1 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Winona 115 kV Substation: Install 21.6 MVAR Capacitor Bank
EMI Winter 2009 Approved Complete In-service 12/15/09 11/30/09 Complete Yes
10CP-EMI-006-2 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Greenwood 115 kV Substation: Upgrade 21.6 MVAR Capacitor Bank to 32.4 MVAR
EMI Winter 2009 Approved Complete In-service 12/15/09 10/28/09 Complete Yes
10CP-EMI-006-3 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Schlater 115 kV substation: Install 21.6 MVAR Capacitor Bank
EMI Winter 2009 Approved Complete In-service 12/15/09 10/21/09 Complete Yes
10-EMI-007-01-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Rolling Fork
EMI Spring 2011 Approved Complete In-service 2/17/12 1/9/12 Complete Yes
10-EMI-007-02-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Yazoo City Municipal
EMI Spring 2011 Approved Complete In-service 2/1/12 1/26/12 Complete Yes
10-EMI-007-03-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Carthage
EMI Spring 2011 Approved Complete In-service 1/11/12 12/8/11 Complete Yes
10-EMI-007-04-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Tylertown
EMI Spring 2011 Approved Complete In-service 10/24/11 12/8/11 Complete Yes
10CP-EMI-007-05 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Senatobia
EMI Spring 2011 Approved Complete In-service 6/1/11 6/6/11 Complete Yes
10CP-EMI-007-06 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Plum Point
EMI Spring 2011 Approved Complete In-service 6/1/11 6/6/11 Complete Yes
10-EMI-007-07-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Upgrade 21.6 MVAR capacitor bank at McComb to 32.4 MVAR.
EMI Spring 2011 Approved Complete In-service 12/19/11 1/30/12 Complete Yes
Completed Projects Page 27 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10CP-EMI-007-08 Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hernando into (2) 21 MVAR cap banks.\
EMI Spring 2011 Approved Complete In-service 6/1/11 6/6/11 Complete Yes
10-EMI-007-09-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hollandale into (2) 21 MVAR cap banks.
EMI Spring 2011 Approved Complete In-service 10/28/11 11/30/11 Complete Yes
10-EMI-007-10-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Port Gibson into (2) 21 MVAR cap banks.
EMI Spring 2011 Approved Complete In-service 2/17/12 1/24/12 Complete Yes
10-EMI-007-11-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Fayette into (2) 21 MVAR cap banks.
EMI Spring 2011 Approved Complete In-service 2/17/12 12/16/11 Complete Yes
10-EMI-007-12-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install 115 kV, 32.4 MVAR capacitor bank at Magee.
EMI Spring 2011 Approved Complete In-service 3/1/12 3/2/12 Complete Yes
10CP-EMI-008 Transmission Reliability - Meeting Planning Criteria
Florence - Florence SS - Star 115 kV Line: Upgrade to at least 240 MVA
EMI Spring 2011 Approved Complete In-service 1/31/11 4/7/11 Complete Yes
10CP-EMI-009 Transmission Reliability - Meeting Planning Criteria
Waterways - Vicksburg East 115 kV Line: Upgrade to at least 240 MVA
EMI Summer 2011 Approved Complete In-service 6/1/11 4/27/11 Complete Yes
10CP-EMI-011-1 Transmission Reliability - Meeting Planning Criteria
McAdams Area Upgrades McAdams Substation: Add 2nd 560 MVA 500 kV / 230 kV Autotransformer (Hartburg Spare single phase units)
EMI Summer 2011 Approved Complete In-service 6/1/11 6/2/11 Complete Yes
10CP-EMI-011-2 Transmission Reliability - Meeting Planning Criteria
McAdams Area Upgrades McAdams - Pickens 230 kV line: Upgrade to Double-Bundled 954 ACSR (880 MVA)
EMI Summer 2011 Approved Complete In-service 6/1/11 5/18/11 Complete Yes
10-EMI-012-1-CP Transmission Reliability - Meeting Planning Criteria
Ridgeland-Madison Reliability Improvement Rebuild Lakeover - Ridgeland Line
EMI Summer 2012 Approved Complete In-service 6/1/12 5/30/12 Complete Yes
10-EMI-012-2-CP Transmission Reliability - Meeting Planning Criteria
Ridgeland-Madison Reliability Improvement Build Lakeover - Sunnybrook - Northpark 115 kV Line
EMI Summer 2012 Approved Complete In-service 6/1/12 5/30/12 Complete Yes
10-EMI-013-CP Transmission Service Ouachita Transmission Service Move Sterlington 600 MVA auto to Baxter Wilson 500 (Second 500-115 kV auto)
EMI Summer 2012 Approved Complete In-service 6/15/12 6/26/12 Complete Yes
10-EMI-014-1-CP Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects Tillatoba to South Grenada 230 kV Line: Construct New 520 MVA Line
EMI Summer 2012 Approved Complete In-service 6/15/12 6/11/12 Complete Yes
10-EMI-014-2-CP Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects South Grenada 115 kV Substation: Install 230 kV Bus and a 400 MVA 230-115 kV Autotransformer
EMI Summer 2012 Approved Complete In-service 6/15/12 6/11/12 Complete Yes
10-EMI-017-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Ray Braswell - Wynndale 115kV Line: Construct New 260 MVAConstruct new 115 kV Switching Station between Byram and Terry. Wynndale SS to be designed for future 230-115 kV auto and distribution facilities
EMI Summer 2013 Approved Complete In-Service 12/1/13 11/19/13 Complete Yes
10-EMI-017-01-CP Transmission Reliability - Meeting Planning Criteria
Ray Braswell to Spring Ridge Road 115kV line upgrade EMI Summer 2013 Approved Complete In-service 6/1/13 5/16/13 Complete Yes
10-EMI-018-CP Transmission Reliability - Meeting Planning Criteria
Getwell to Church Road 230 kV construct new 230 kV Transmission Line
EMI Summer 2013 Approved Complete In-service 6/1/13 5/10/13 Complete Yes
10CP-EMI-020 Transmission Reliability - Meeting Planning Criteria
Ray Braswell to Clinton 115 kV line: Upgrade switch at Clinton and riser at Ray Braswell
EMI Summer 2011 Approved Complete In-service Spring 2011 2/10/11 Complete Yes
10CP-EMI-021 Transmission Reliability - Meeting Planning Criteria
Clinton to Jackson NW 115 kV line: Upgrade switch at Clinton
EMI Summer 2011 Approved Complete In-service Spring 2011 2/10/11 Complete Yes
Completed Projects Page 28 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
11-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Rankin Industrial - Airport: Reconductor to bring complete line up to 1272 ACSR
EMI Winter 2011 Approved Complete In-service 12/22/11 1/10/12 Complete Yes
11-EMI-002 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Baxter Wilson to S.E. Vicksburg - Upgrade 115 kV line EMI Summer 2015 Approved Complete In service. 8/1/15 6/3/15 N/A Yes
11CP-EMI-003 Transmission Reliability - Meeting Planning Criteria
Upgrade Terminal Equipment on Vicksburg - Waterway 115kV
EMI Summer 2011 Approved Complete In-service Summer 2011 1/24/11 Complete Yes
11-EMI-004-CP Transmission Reliability - Meeting Planning Criteria
Ray Braswell to West Jackson 115 kV line: Reconductor line
EMI Summer 2012 Approved Complete In-service Winter 2012 11/21/12 Complete Yes
11CP-EMI-005 Transmission Reliability - Meeting Planning Criteria
Miami to Monument Street: Upgrade line trap at Monument Street
EMI Summer 2012 Approved Complete In-service 6/1/11 5/26/11 Complete Yes
12-EMI-003-CP Transmission Reliability - Meeting Planning Criteria
Northeast Jackson to Klean Steel - Upgrade CT and Jumpers/Risers at NE Jackson
EMI Summer 2012 Approved Complete In-service 6/1/12 12/7/11 Complete Yes
13-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Upgrade CTs at Vicksburg for Vicksburg-B.Wilson ckt 1 (ckt without Spencer Potash on it)
EMI Summer 2013 Approved Complete In-service Summer 2013 6/13/13 Complete Yes
13-EMI-004-CP Transmission Service SMEPA Plum Point Transmission Service: Horn Lake to Greenbrook 115 kV line: Upgrade station equipment at Horn Lake
EMI Summer 2013 Approved Complete In-service Summer 2013 4/19/13 Complete Yes
13-EMI-006-CP Enhanced Transmission Reliability Bolton 115 kV Substation: Add 115 kV breakers EMI Summer 2013 Approved Complete In-service Summer 2014 3/28/13 Complete N/A (No model effect)
14-EMI-001-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Horn Lake to Greenbrook 115kV line: Upgrade 4 switches
EMI Summer 2013 Approved Complete In Service Fall 2013 11/6/13 Complete Yes
14-EMI-006 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Horn Lake Substation: Upgrade 115 kV switch J0966 LAB to 1200 A.
EMI Summer 2014 Proposed & In Target
Complete In-Service Summer 2014 4/21/14 N/A Yes
10CP-ENO-001 Transmission Reliability - Meeting Planning Criteria
Paterson 115kV: Restore 4 breakers ENOI Summer 2009 Approved Complete In-service 1/29/09 Complete Yes
11-ENO-001-CP Generation Interconnection NM6: Upgrade Michoud breaker N9803 ENOI Winter 2014 Approved Complete In-service 9/16/13 7/18/13 Complete N/A12-ENO-001 4794 A in MTEP14 Load Growth Midtown: Add 230 kV distribution transformers ENOI 2014 Approved Complete In-Service 4/1/14 6/1/14 N/A Yes
14-ENO-002 4797 A in MTEP14 Transmission Reliability - Meeting Planning Criteria
Market Street Substation: Upgrade bus and jumpers ENOI Summer 2016 Approved Complete In service. Summer 2016 5/27/15 N/A Yes
10CP-ETI-001 Transmission Reliability - Meeting Planning Criteria
Newton Bulk: Replace/Re-tap CT to increase rating on Holly Springs line
ETI Summer 2009 Approved Complete In-service Winter 2009 Complete Yes
10CP-ETI-002 Transmission Reliability - Meeting Planning Criteria
Beaumont 69 kV Improvement Plan: Option 2 ETI Summer 2009 Approved Complete In-service 6/19/09 Complete Yes
10CP-ETI-003 Generation Interconnection Sheco Jacinto - Generator Interconnection ETI Summer 2009 Approved Complete In-service 7/3/09 Complete Yes10CP-ETI-004 Transmission Reliability - Meeting
Planning CriteriaGulfway 230 kV Substation Construct new Gulfway 230 kV Substation Cut new Substation into existing VFW to Kolbs 230 kV Line Construct new Sabine to Gulfway 230 kV line
ETI Fall 2009 Approved Complete In-service 10/13/09 Complete Yes
10CP-ETI-005 Transmission Reliability - Meeting Planning Criteria
Fawil: Upgrade 138/69 kV Auto ETI Winter 2009 Approved Complete In-service 1/23/10 Complete Yes
10CP-ETI-006 Transmission Reliability - Meeting Planning Criteria
Porter - Tamina: Replace Breaker/Switches ETI Summer 2009 Approved Complete In-service 10/22/09 Complete Yes
10CP-ETI-007 Enhanced Transmission Reliability Warren Substation - Add two breakers ETI Winter 2009 Approved Complete In-service 1/2/08 Complete N/A (No model effect)
10CP-ETI-008-1 Transmission Reliability - Meeting Planning Criteria
Temco and Shepherd 138 kV Substations - Upgrade CTs at Temco
ETI Summer 2010 Approved Complete In-service 9/30/10 10/26/10 Complete Yes
10CP-ETI-008-2 Transmission Reliability - Meeting Planning Criteria
Temco and Shepherd 138 kV Substations - Upgrade CTs at Shepherd
ETI Summer 2010 Approved Complete In-service 9/30/10 10/26/10 Complete Yes
10CP-ETI-009 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 1) Relocate Sheco's Caney Creek 138 kV Substation
ETI Summer 2010 Approved Complete In-service 10/10/10 1/21/10 Complete Yes
Completed Projects Page 29 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
10CP-ETI-010 Transmission Reliability - Meeting Planning Criteria
College Station 138kV Switching Station Construct new 3 terminal 138 kV Switching Station Close normally open switch at Speedway
ETI Spring 2011 Approved Complete In-service 12/31/10 11/29/10 Complete Yes
10CP-ETI-011 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 3). Upgrade South Beaumont to Fontenot Corner 138 kV line
ETI Winter 2010 Approved Complete In-service 4/21/11 5/24/11 Complete Yes
10CP-ETI-012 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 2) Jacinto-Lewis Creek: Convert to 230 kV operation. Add 450 MVA 230-138 Auto at Lewis Creek
ETI Summer 2011 Approved Complete In-service 2/25/11 3/2/11 Complete Yes
10-ETI-013-CP Transmission Service Grand Gulf Uprate Project Upgrade Hartburg to Inland Orange to McLewis 230 kV line
ETI Winter 2011 Approved Complete In-service 12/16/11 12/28/11 Complete Yes
10-ETI-017-CP Transmission Reliability - Meeting Planning Criteria
Jasper to Rayburn 138 kV line: Upgrade ETI Summer 2013 Approved Complete In-service 5/31/13 5/14/13 Complete Yes
10CP-ETI-020 Transmission Reliability - Meeting Planning Criteria
Inland Orange to McLewis 230 kV line: Upgrade risers at Inland Orange and switch 22628 at McLewis
ETI Winter 2010 Approved Complete In-service 4/23/11 5/11/11 Complete Yes
10CP-ETI-021 Transmission Reliability - Meeting Planning Criteria
Hartburg to Inland Orange 230 kV line: Upgrade risers at Inland Orange
ETI Winter 2010 Approved Complete In-service 12/16/11 2/18/11 Complete Yes
10-ETI-022-CP Transmission Reliability - Meeting Planning Criteria
McLewis to Helbig 230 kV line: Upgrade bus and switches 22627 & 22628 at McLewis
ETI Winter 2011 Approved Complete In-service 12/16/11 1/4/12 Complete Yes
10CP-ETI-023 Transmission Reliability - Meeting Planning Criteria
Sabine to Linde 138 kV line: Upgrade bus and risers at Sabine and Linde
ETI Winter 2010 Approved Complete In-service Winter 2010 2/1/11 Complete Yes
10CP-ETI-024 Transmission Reliability - Meeting Planning Criteria
Sabine to Mid County 230 kV line: Upgrade bus and jumpers at Mid County
ETI Winter 2010 Approved Complete In-service Winter 2010 11/22/10 Complete Yes
10CP-ETI-025 Transmission Reliability - Meeting Planning Criteria
Chem Rd to Dupont Sabine 3 138 kV line: Upgrade metering CT at Dupont Sabine
ETI Summer 2011 Approved Complete In-service Summer 2011 3/7/11 Complete Yes
10CP-ETI-026 Transmission Reliability - Meeting Planning Criteria
Orange to Bunch Gully 138 kV line: Upgrade bus and risers at Orange
ETI Winter 2010 Approved Complete In-service 5/20/11 5/25/11 Complete Yes
10-ETI-027-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leesville 138 kV line: Upgrade CT at Toledo Bend
ETI Summer 2011 Approved Complete In-service 12/15/11 12/1/11 Complete Yes
10-ETI-028-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Van Ply 138 kV line: Upgrade CT at Toledo Bend
ETI Summer 2011 Approved Complete In-service 12/15/11 12/14/11 Complete Yes
10CP-ETI-029 Transmission Reliability - Meeting Planning Criteria
Cypress to Lumberton 138 kV line: Upgrade bus at Lumberton and Cypress
ETI Summer 2011 Approved Complete In-service 3/1/11 3/21/11 Complete Yes
10CP-ETI-030 Transmission Reliability - Meeting Planning Criteria
Goslin to Conroe Bulk 138 kV line: Upgrade bus differential at Conroe.
ETI Summer 2011 Approved Complete In-service 5/13/11 5/26/11 Complete Yes
11CP-ETI-001 Transmission Reliability - Meeting Planning Criteria
Hearne to Calvert - Uprate 69 kV line ETI Summer 2011 Approved Complete In-service 6/24/11 6/28/11 Complete Yes
11CP-ETI-004 Transmission Reliability - Meeting Planning Criteria
Elizabeth to Gallier - Uprate 69 kV line 2.5 miles ETI Summer 2012 Approved Complete In-service TBD 9/14/11 Complete Yes
11-ETI-006-CP Transmission Reliability - Meeting Planning Criteria
Somerville 69 kV: Expand capacitor bank ETI Summer 2012 Approved Complete In-service 5/3/12 5/15/12 Complete Yes
11CP-ETI-007 Transmission Reliability - Meeting Planning Criteria
Navasota to Magnolia Anderson 138kV: Upgrade relay CT
ETI Summer 2011 Approved Complete In-service 7/14/11 7/18/11 Complete Yes
11-ETI-008-CP Transmission Reliability - Meeting Planning Criteria
Cedar Hill to Plantation 138 kV line: Upgrade line conductor and station equipment at Plantation
ETI Summer 2013 Approved Complete In-service 4/12/13 2/21/13 Complete Yes
11-ETI-008-01-CP Transmission Reliability - Meeting Planning Criteria
Plantation to Conroe 138 kV line: Upgrade station equipment at Plantation
ETI Summer 2013 Approved Complete In-service 4/12/13 4/4/13 Complete Yes
11-ETI-009-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leach 138 kV line: Upgrade station equipment at Toledo Bend
ETI Winter 2013 Approved Complete In-service 12/15/11 11/28/11 Complete Yes
11-ETI-010-CP Transmission Reliability - Meeting Planning Criteria
Leach to Newton Bulk 138 kV line: Upgrade terminal equipment at Newton Bulk
ETI Winter 2013 Approved Complete In-service 3/18/13 3/18/13 Complete Yes
11CP-ETI-011 Transmission Reliability - Meeting Planning Criteria
Port Neches to Linde: Upgrade station equipment at Port Neches
ETI Summer 2011 Approved Complete In-service 5/5/11 5/2/11 Complete Yes
11-ETI-020-CP Transmission Reliability - Meeting Planning Criteria
Hickory Ridge-Eastgate 138kV: Upgrade terminal equipment at Eastgate
ETI Summer 2016 Approved Complete In-service 5/1/13 4/5/13 Complete Yes
11-ETI-036-CP Transmission Reliability - Meeting Planning Criteria
Plantation to Conroe 138 kV line: Reconductor Line ETI Summer 2013 Approved Complete In-service 4/12/13 4/4/13 Complete Yes
Completed Projects Page 30 of 31
Report Date: July 9, 2015
Construction Plan ID
MTEP Project ID
MTEP Designation Project Driver Project Name Operating
CompanyProposed ISD
(Planning)
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in
Model? (Yes/No)
Monthly Long Term Transmission Plan Project Status ReportPREVIOUSLY COMPLETED PROJECTS
11-ETI-041-CP Transmission Reliability - Meeting Planning Criteria
Eastgate to Dayton Bulk 138kV: Upgrade terminal equipment at Eastgate (formerly reconductor).
ETI Summer 2013 Approved Complete In-service 5/1/13 4/19/13 Complete Yes
11-ETI-043-CP Transmission Reliability - Meeting Planning Criteria
Expand Cap Bank at Calvert 69kV ETI Summer 2013 Approved Complete In-service 6/1/13 5/8/13 Complete Yes
12-ETI-003-CP Transmission Reliability - Meeting Planning Criteria
Bentwater Substation: Add 138 kV Capacitor Bank ETI Summer 2013 Approved Complete In-service 2013 Summer 5/1/13 Complete Yes
12-ETI-004-CP N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Ponderosa Switching Station: tie lines Longmire to Fish Creek and Conroe to Woodhaven into new switching station (Formerly referred to as Conroe Area SS)
ETI Winter 2013 Approved Complete In-service 12/21/13 12/23/13 N/A Yes
12-ETI-015-CP Enhanced Transmission Reliability College Station SS: Create emergency tie point with ERCOT (asynchronous)
ETI Fall 2012 Approved Complete In-service 7/31/13 7/3/13 Complete N/A
13-ETI-010-01 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Pansy to Lovells Lake 69 kV line: Upgrade line to 100 deg design
ETI Summer 2014 Approved Complete In-Service Summer 2014 7/8/14 N/A
13-ETI-010-02 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Lovells Lake to Texas Hillebrandt 69 kV line: Upgrade line to 100 deg design
ETI Summer 2014 Approved Complete In-Service Summer 2014 7/8/14 N/A
13-ETI-010-03 N/A N/A Transmission Reliability - Meeting Planning Criteria
South Beaumont to Texas Hillebrandt 69 kV line: Upgrade line to 100 deg design
ETI Summer 2014 Approved Complete In-Service Summer 2014 7/8/14 N/A
13-ETI-011 N/A Pre-Planned Transmission Reliability - Meeting Planning Criteria
Lewis Creek to Egypt 138 kV line: Reconductor ETI Summer 2014 Approved Complete In-Service 12/31/2014 12/22/14 N/A Yes
14-ETI-005 4800 A in MTEP14 Load Growth Parkway: Construct new substation ETI 2015 Approved Complete In service. 5/29/2015 5/27/15 N/A Yes
14-ETI-007 4803 A in MTEP14 Customer Driven Nederland 230 kV Substation: Construct new substation
ETI Fall 2014 Approved Complete In-service 10/10/2014 10/23/14 N/A Yes
14-ETI-008 4804 A in MTEP14 Customer Driven Petry Woods 138 kV Substation: Construct new substation
ETI Summer 2014 Approved Complete In-Service 6/30/2014 6/30/14 N/A Yes
14-ETI-009 4805 A in MTEP14 Customer Driven Ranchland 69 kV Substation: Construct new substation ETI Winter 2014 Approved Complete In-Service 12/19/2014 12/22/14 N/A Yes
15-ETI-013 8214 A in MTEP15 (OOC) Customer Driven Boomtown: Construct new 69 kV substation ETI Spring 2015 Approved Complete In-service 2/1/2015 2/12/15 N/A Yes
Completed Projects Page 31 of 31