MONMOUTHSHIRE COUNTY COUNCIL
JOINT HOUSING LAND AVAILABILITY STUDY 2019
DRAFT STATEMENT OF COMMON GROUND
BETWEEN MONMOUTHSHIRE COUNTY COUNCIL, THE
HOME BUILDERS FEDERATION AND THE STUDY
GROUP
May 2019
CONTENTS 1 Introduction
2 Study Group 3 Process to Date 4 Agreed Matters 5 5 Year Land Supply Calculation
Appendix 1 - Amended Site Schedule
Appendix 2 - Amended Site Proformas
Appendix 3 - Responses to initial consultation
Appendix 4 - Minutes of Study Group Meeting
Appendix 5 - Agreed Changes / Amendments
Monmouthshire County Council Joint Housing Land Availability Study 2019 1 Draft Statement of Common Ground
1.0 INTRODUCTION
1.1 This is a Draft Statement of Common Ground (SoCG) prepared by
Monmouthshire County Council, the Home Builders Federation (HBF), the
Study Group, Welsh Water and Local Housing Associations, for the 01st
April 2019 Joint Housing Land Availability Study (JHLAS) for
Monmouthshire County Council for 2018/2019.
1.2 This Draft SoCG follows the process set out in the agreed delivery timetable
for the preparation of Monmouthshire County Council JHLAS for 2018/2019
and has been prepared in accordance with the requirements of Planning
Policy Wales and Technical Advice Note 1, Joint Housing Land
Availability Studies, (TAN 1) .
1.3 This Draft SoCG has been prepared for the Welsh Government.
2.0 STUDY GROUP
2.1 The Study Group for the Monmouthshire County Council 2018/19
JHLAs is comprised of the following members:
Mark Hand Monmouthshire County Council
Rachel Lewis Monmouthshire County Council
William Miles Monmouthshire County Council
Ben Winstanley Monmouthshire County Council
Nick Keyse Monmouthshire County Council
Shirley Wiggam Monmouthshire County Council
Louise Corbett Monmouthshire County Council
Craig O’Connor Monmouthshire County Council
Mark Harris Home Builders Federation
Ryan Norman Dwr Cymru / Welsh Water
Emyr Davies Redrow Homes
Zoe Aubrey Barratt Homes
Rhian Powell Bellway Homes
Karen Tarbox Monmouthshire Housing
Jeremy Baker Monmouthshire Housing
Katie Knill Monmouthshire Housing
Scott Rooks Candlestone Homes
Nigel Lush Bovis Homes
Scott Rooks Candleston Homes
Lyndon Griffiths Melin Homes
Gerrard Williams Melin Homes
Gavin Howells Pobl Group
David James Rural Housing Enabler
2 Monmouthshire County Council Joint Housing Land Availability Study 2019 Draft Statement of Common Ground
Michael Gooch Boyer
Michael Rees LRM Planning
2.2 The HBF circulate all details of consultations to their members, with
comments either fed back through the HBF representative or made on an
individual basis.
3.0 PROCESS TO DATE
3.1 A survey of all housing sites with an extant planning permission was
undertaken by Monmouthshire County Council between the 25th March 2019
and 5th April 2019. Following the completed housing survey site schedules
were prepared with an update of progress on each site and estimated
completion forecasts for all sites included on the schedule. Those sites with
planning permission, both outline and full, those sites which are the subject
of a resolution to grant planning permission for housing subject to the signing
of a Section 106 agreement and those identified for residential purposes in
the Adopted Local Development Plan were included as required by
paragraph 4.3.1 of the TAN.
3.2 Monmouthshire County Council published t h e d r a f t site schedule
and site proformas for the 2018/2019 JHLAS report for consultation
with the study group between the 15 t h Apri l 2019 and the 3rd May
2019.
3.3 Written comments in response to the consultation were received from
the Home Builders Federation, Dwr Cymru / Welsh Water and a
number of other members of the Study Group. These responses are
included at Appendix 3. Following the consultation a study group meeting
was held on 9th May 2019 to discuss those sites which were the subject of
disagreement. A note of the meeting is provided at Appendix 4.
Monmouthshire County Council Joint Housing Land Availability Study 2019 3 Draft Statement of Common Ground
4.0 AGREED MATTERS Completions Large and Small Site Completions
Completions 1st April
2018 –31st March 2019
Large Site Completions
Small Site Completions
443 359 84
5 Year Land Supply Sites Agreed Sites
4.1 Amended site proformas and a site schedule have been prepared to take
into account the outcome of the Study Group Meeting. These are included at
Appendices 1 and 2.
4.2 The amendments that have been made to the initial site schedule in
response to comments received from the Study Group and discussion
at the Study Group meeting are set out in Appendix 5.
4.3 All details within the amended site schedule are agreed by the HBF
and members of the Study Group.
4 Monmouthshire County Council Joint Housing Land Availability Study 2019 Draft Statement of Common Ground
5.0 FIVE YEAR LAND SUPPLY CALCULATIONS
Agreed Position
5.1 All site specific details have been agreed subject to the amendments set out
in Appendix 5.
Monmouthshire County Council 5 Year Land Supply Calculation
Housing Land Supply 01st April 2019 (Large Sites)
5 Year Land Supply (TAN 1
categories)
Beyond 5 Years
Proposed
homes
Under
construction
Category 1
Category
2
Category
3
Category
4
Homes
Completed
Since last study
Total 3313 155 2305 0 355 359
Five year land supply on large sites (i.e. Categories 1 and 2) is 2,460. Small Site and Conversion Completions for previous 5 years
Small Site Completions
2014/15 2015/16 2016/17 2017/18 2018/19 Total
99 99 86 83 84 451
Total Dwellings Available: Large sites 2460
Forecast contribution by small
sites
451
Large and Small Site 5 year total 2911
Monmouthshire County Council Joint Housing Land Availability Study 2019 5 Draft Statement of Common Ground
LDP Housing Provision 2011-2021
Completions 1st April 2011- 31st March 2019 8 Years
Remainder 1st April 2019 -2021 2 Years
5 Year Requirement
Total Annual Building Requirement
Total Land Available
Total Land Supply in Years
A B C D E F G
C = (A-B) *D
= D/5 F G = F/E
4500 2225 2275 3625 725 2911 4.0 years
*Based upon the LDP allocation less completions (column C – 2275 units) = 2 years; plus the annual average requirement (4,500/10 = 450) x 3 = 1350
Appendix 1
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans ABERGAVENNY
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2007/01679 Ross Road 0 9 9 0.55 0 0 0 0 0 0 0 9
DC/2008/00024(O/L) Ross Road 0 9 9 0.41 0 0 0 0 0 0 0 9
DC/2014/01015 Mulberry House 0 25 25 0.7 7 0 18 0 0 0 0 0
DC/2015/01585 The Hill 20 44 0 3.95 0 0 0 0 0 0 0 0
DC/2015/01587 Coed Glas 0 51 51 1.9 28 23 0 0 0 0 0 0
DC/2014/01360 Deri Farm 32 250 218 8.7 39 11 50 50 50 18 0 0
DM/2018/00007 Magistrates Court 0 47 47 0.46 0 0 47 0 0 0 0 0
TOTAL 52 435 359 16.67 74 34 115 50 50 18 0 18
CALDICOT
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2016/01453 Brookside 25 25 0 0.97 0 0 0 0 0 0 0 0
DC/2013/00796 Former White Hart Inn, Sandy Lane 0 16 16 0.17 0 0 16 0 0 0 0 0
DM/2018/00880 (O/L) Church Road 0 130 130 10.36 0 0 30 40 40 20 0 0
TOTAL 25 171 146 11.5 0 0 46 40 40 20 0 0
CHEPSTOW
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2009/00910 Osborn International 35 169 129 2.4 4 26 30 30 30 9 0 0
DC/2014/01290(O/L) Fairfield Mabey 0 450 450 9.5 0 0 45 70 105 105 0 125
TOTAL 35 619 579 11.9 4 26 75 100 135 114 0 125
Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
CategorisationLPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
1
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans DINGESTOW
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DM/2018/01404 Land to south east of Dingestow 0 15 15 0.51 0 5 10 0 0 0 0 0
TOTAL 0 15 15 0.51 0 5 10 0 0 0 0 0
LLANELLEN
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2015/00474 Llanellen Court Farm 0 14 14 0.7 14 0 0 0 0 0 0 0
DC/2015/00983 Llanellen Court Farm 0 14 14 0.32 0 0 0 14 0 0 0 0
TOTAL 0 28 28 1.02 14 0 0 14 0 0 0 0
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
2
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans LLANFAIR KILGEDDIN
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DM/2018/02001(O/L) Land north of Llanfair Kilgeddin 0 5 5 0.17 0 0 0 5 0 0 0 0
TOTAL 0 5 5 0.17 0 0 0 5 0 0 0 0
LLANFOIST
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2016/00880(O/L) Land at Grove Farm 0 115 115 5.24 0 0 10 35 35 26 0 9
TOTAL 0 115 115 5.24 0 0 10 35 35 26 0 9
LLANISHEN
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2016/00415(O/L) Land rear Carpenters Arms Llanishen 0 8 8 0.23 0 0 3 5 0 0 0 0
TOTAL 0 8 8 0.23 0 0 3 5 0 0 0 0
MAGOR/UNDY
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2016/00883(O/L) Rockfield Farm 0 122* 122 2.8 0 0 18 35 35 34 0 0
DM/2018/01606 (RM) Rockfield Farm (Phase 1) 0 144 144 5.4 0 22 44 44 34 0 0 0
MON LDP Land at Vinegar Hill 0 225 225 7.81 0 0 25 50 50 50 0 50
TOTAL 0 491 491 16.01 0 22 87 129 119 84 0 50
* Original outline permission for 266 units, phase 1 has come in for 144
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
CategorisationLPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
3
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans MONMOUTH
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2012/00754 Hillcrest Road Wyesham 0 11 11 0.5 0 0 11 0 0 0 0 0
DC/2015/00390 Wonastow Road (Taylor Wimpey) 81 166 34 4.53 31 3 0 0 0 0 0 0
DC/2015/00392 Wonastow Road (Barratt) 64 173 52 4.49 15 25 12 0 0 0 0 0
DC/2017/00539(O/L) Land west Rockfield Road 0 70 70 2.86 0 0 10 30 30 0 0 0
MON LDP Wonastow Road (LDP) 0 110 110 5.75 0 0 15 45 50 0 0 0
MON LDP Tudor Road Wyesham 0 35 35 2.05 0 0 0 0 15 20 0 0
TOTAL 145 565 312 20.18 46 28 48 75 95 20 0 0
PENALLT
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2015/00606 Land to the south west of Penallt 0 10 10 0.41 0 0 10 0 0 0 0 0
TOTAL 0 10 10 0.41 0 0 10 0 0 0 0 0
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
CategorisationLPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
4
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans PENPERLLENI
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2013/01001 Land south of Usk Road (Phase 1) 39 40 1 1.34 1 0 0 0 0 0 0 0
DC/2014/00468 Land south of Usk Road (Phase 2) 25 25 0 1.6 0 0 0 0 0 0 0 0
TOTAL 64 65 1 2.94 1 0 0 0 0 0 0 0
PORTSKEWETT
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DM/2018/00696 (O/L) Crick Road 0 291 291 7.77 0 0 29 58 58 58 0 88
TOTAL 0 291 291 7.77 0 0 29 58 58 58 0 88
PWLLMEYRIC
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2016/00953(O/L) Hill Farm Pwllmeyric 0 17 17 0.92 0 0 7 10 0 0 0 0
TOTAL 0 17 17 0.92 0 0 7 10 0 0 0 0
RAGLAN
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DM/2018/00769 (O/L) Land at Chepstow Road 0 45 45 2.18 0 0 12 12 12 9 0 0
TOTAL 0 45 45 2.18 0 0 12 12 12 9 0 0
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
CategorisationLPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
5
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans
ROGIET
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2015/01328 Green Farm 0 11 11 0.7 0 0 5 6 0 0 0 0
TOTAL 0 11 11 0.7 0 0 5 6 0 0 0 0
SHIRENEWTON
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2015/00688 Land to east (north of minor road) 5 5 0 0.17 0 0 0 0 0 0 0 0
TOTAL 5 5 0 0.17 0 0 0 0 0 0 0 0
SUDBROOK
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2011/00607(O/L) Old Shipyard 0 46 46 1 0 0 10 36 0 0 0 0
DC/2015/01184 Former Paper Mill 33 210 175 6.6 16 19 35 35 35 35 0 0
TOTAL 33 256 221 7.6 16 19 45 71 35 35 0 0
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
6
Monmouthshire County CouncilResidential Land Availability Schedule
as at 01-04-2019Sites with Planning Permission or in Adopted Plans
TINTERN
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
DC/2012/00620 Former Abbey Hotel 0 11 11 0.5 0 0 11 0 0 0 0 0
TOTAL 0 11 11 0.5 0 0 11 0 0 0 0 0
USK
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
MON LDP Cwrt Burrium 0 20 20 0.66 0 0 13 7 0 0 0 0
TOTAL 0 20 20 0.66 0 0 13 7 0 0 0 0
VILLAGE SITES
U/C
2019/20 2020/21 2021/22 2022/23 2023/24 3 4
MON LDP Land adj Village Hall Cross Ash 0 10 10 0.41 10
MON LDP Land adj Cross Ash Garage 0 5 5 0.2 5
MON LDP Land at Well Lane Devauden 0 15 15 0.56 7 8
MON LDP Land to west of Grosmont 0 15 15 0.6 15
MON LDP Land north of Little Mill 0 15 15 0.51 15
MON LDP Land rear Village Hall Llanddewi Rhydderch 0 5 5 0.17 5
MON LDP Land to north west of Llanellen 0 15 15 0.55 15
MON LDP Land at Ton Road Llangybi 0 10 10 0.34 10
MON LDP Land adj Church Road Llanishen 0 5 5 0.17 5
MON LDP Land west of Mathern 0 15 15 0.5 15
MON LDP Land east Shirenewton (south of minor road) 0 5 5 0.17 5
MON LDP Land adj Werngifford Pandy 0 15 15 0.65 5 10
TOTAL 0 130 130 4.83 0 5 12 48 0 0 0 65
TOTAL 359 3313 2815 112.11 155 139 538 665 579 384 0 355
CategorisationLPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA Categorisation
LPA Ref No. AddressUnits Built Since Last
Study
Total Units Capacity
Units Rmng
HA
7
Appendix 2
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Croesonen Site Address Ross Road (part)
Land Off Ross Road Abergavenny Monmouthshire
LPA Reference DC/2007/01679 Grid Reference Easting 330835 Northing 215151 Market Type (Private, Public, RSL)
Private
Owner Developer Redrow Homes (South Wales) Ltd
Redrow House Copse Walk Cardiff Gate Business Park Cardiff CF23 8RH
Agent Urban Illustrate Ltd 10 Tulip Walk Afon Village Rogerstone Newport Gwent NP10 9LF
Landowner / developer intentions
Description of Development
Erection of 9 dwellings and associated works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 07.04.09 07.04.14 DC/2007/01679 UDP Alloc – H2c
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
Planning consent secured by construction of access
JHLAS History
First recorded as forming part of the five year housing land supply = 2006/07
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.55 16.36 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
9 0 0 9 0 0 0 9
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2007/01679 - Ross Road, Abergavenny
Wi
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Croesonen Site Address Ross Road
Land Off Ross Road Abergavenny Monmouthshire
LPA Reference DC/2008/00024 Grid Reference Easting 330835 Northing 215151 Market Type (Private, Public, RSL)
Private – 7 dwellings Public – 2 dwellings
Owner Western Power Distrbution Investments Ltd Developer Agent RPS Cardiff
Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Outline planning application for residential development.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 25/10/2013 25/10/2016 DC/2008/00024 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Access / Highways Comment
Utilities / Services Comment
Constraints
Comment Capital Works Comment
Planning consent secured by construction of access to neighbouring site.
JHLAS History
First recorded as forming part of the five year housing land supply = 2006/07
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.41 31.7 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
9 0 0 9 0 0 0 9
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2008/00024 (O/L) - Ross Road, Abergavenny
Wi
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Lansdown Site Address Mulberry House
Pen y Pound Abergavenny NP7 5UD
LPA Reference DC/2014/01015 Grid Reference Easting 329667 Northing 214589 Market Type (Private, Public, RSL)
Private – 16 units Public – 9 units
Owner Sennybridge Ltd Developer Agent Indigo Planning
87 Chancery Lane London WC2A 1ET
Landowner / developer intentions
Description of Development
Conversion of Mulberry House to provide 16 apartments within the 1950's Annex, conversion of Mulberry House and the chapel into 2x dwellings and erection of six houses and one flat on land to the rear of Mulberry Court including, 34 car park spaces and associated landscaping works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 29.03.2017 29.03.2022 DC/2014/01015 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru Welsh Water –conditions and advisory notes to be included within the consent to ensure no detriment to existing residents or the environment and to Dwr Cymru Welsh Water’s assets.
Access / Highways Comment
The main issue presented with this application in highway terms relates to the parking, however the Council’s Highways Engineer has recognised that the relaxation in numbers has been supported by a transport statement.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Whilst the planning permission has been implemented by the current developer, works have now stopped. Forecast completions reflect this.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.7 35.7 0 18 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
25 0 0 25 7 18 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1500 Date
Rev
No.
Edge.J 4/7/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2014/01015 - Mulberry House, Abergavenny
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Lansdown Site Address The Hill
Pen-Y-Pound Abergavenny NP7 7RP
LPA Reference DC/2015/01585 Grid Reference Easting 329 564 Northing 215403 Market Type (Private, Public, RSL)
Private – 32 units Public – 12 units
Owner Coleg Gwent Developer Edenstone Homes Ltd Agent RPS Group PLC
Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Conversion of original house to 5 apartments; conversion of coach house, garden cottage and stables into separate residential units. Demolition of 1970's extension block, erection of 36 new build residential units (including 10 affordable retirement apartments and 2 affordable retirement bungalows).
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 11.10.2016 11.10.2021 DC/2015/01585 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru-Welsh Water – No objection subject to conditions and advisory notes.
Access / Highways MCC Highways – No objection. Main part of access
Comment road to be adopted Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other An ecological objection was offered for the scheme based on insufficient assessment of impacts of development on habitats and species and loss of woodland habitat. As such an Ecological Impact Assessment (EcIA) has been submitted to support the application.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
3.95 11.1 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
44 24 20 0 0 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/7/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/01585 - The Hill, Abergavenny
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Castle Site Address Coed Glas LPA Reference DC/2015/01587 Grid Reference Easting 330539 Northing 214089 Market Type (Private, Public, RSL)
Private – 34 units Public – 17 units
Owner Monmouthshire County Council Developer Candleston Homes Agent Asbri Planning Ltd
Unit 9 Oak Tree Court Cardiff Gate Business Park Cardiff CF23 8RS
Landowner / developer intentions
Planning application approved for demolition of the existing buildings, and re-development of the site to include 51 residential dwellings, and associated works.
Description of Development
Site allocated in LDP for residential development
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 03.11.2016 03.11.2021 DC/2015/01587 LDP Alloc – SAH9
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
No objections. DCWW have met developers to discuss the drainage scheme for this proposed development and have agreed upon a strategy which will create sufficient capacity in the local sewer network to accommodate the development.
Access / Highways Comment
Utilities / Services
Comment Constraints Comment
There are a number of mature trees on the site that will need to be taken into account in any development proposal.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Housing mix changed via Non-material Amendment. Deed of Variation to S106 agreement signed in regard to name change of developer name. Development undertaken by Candleston (market homes) and Melin (AH). Developer advises (April 2019) that the market houses will be completed by December 2019 and the AH by February 2020.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
1.9 26.8 23 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
51 0 o 51 28 23 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/01587 - Coed Glas, Abergavenny
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Mardy Site Address Deri Farm LPA Reference DC/2014/01360 Grid Reference Easting 330819 Northing 216266 Market Type (Private, Public, RSL)
Private – 201 units Public – 49 units
Owner Developer Persimmon Homes East Wales
Llantrisant Business Park Llantrisant Rhondda Cynon Taff CF72 8YP
Agent Landowner / developer intentions
Persimmon Homes submitted a planning application on the site, DC/2014/01360, for the construction of 250 residential units with associated demolition and infrastructure works. This has been approved and a S106 Agreement signed.
Description of Development
Site allocated for residential development in LDP. Development to be phased. Development begun in 2018/19 JHLAS Survey period.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 19.01.2018 19.01.2023 DC/2014/01360 LDP Alloc – SAH1
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water (DCWW) – No objection subject to two conditions: 1. No beneficial use of or occupation of any of the dwellings until such a time that any necessary foul sewerage infrastructure works required by the
Hydraulic Modelling Assessment SE186b dated July 2014 have been completed and approved by the LPA. 2. No development shall commence until a drainage scheme for the site has been submitted to and approved by the LPA.
Access / Highways Comment
MCC Highways – No objection in principle. Requested the following Section 106 financial contributions: The sum of £40,000 to be used by the Council
towards the provision of a public transport service. The sum of £40,000 to be used to provide a
footpath link along Hereford Road between the site entrance and Greystones Close and an improved footpath link to the school.
Issues such as the footway along the site frontage, provision of bus stops, and the extension of the 30mph speed limit will be secured via the S278 Highways agreement.
Utilities / Services Comment
Discussions held with Persimmon and MCC to amend S106 to allow additional homes to be commenced before the pylons are undergrounded (slight delay to undergrounding due to ecology issue).
Constraints Comment
Capital Works Comment
The undergrounding of the overhead electricity cables has been agreed with Western.
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Provision to be made in any detailed scheme for a strong landscape buffer along the northern edge of the site in order to minimise the impacts of the development on the landscape character of the adjoining Brecon Beacons National Park.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
9.1 27.5 11 50 50 50 18
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
250 0 32 218 39 179 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4000 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2014/01360 - Deri Farm, Abergavenny
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Abergavenny Ward Grofield Site Address Magistrates Court and Police Station LPA Reference DM/2018/00007 Grid Reference Easting 329696 Northing 214175 Market Type (Private, Public, RSL)
Private – 47 units
Owner Developer McCarthy and Stone Retirement Lifestyles Agent The Planning Bureau Limited
First Floor, Blackbrook Gate 1 Blackbrook Park Avenue Taunton TA1 2PX
Landowner / developer intentions
Planning application approved for demolition of magistrates court and police station building and erection of a building comprising 47 retirement living apartments.
Description of Development
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 15.03.2019 15.03.2024 DM/2018/00007 CAC 22.03.2019 23.03.2024 DM/2018/00008
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
No objections. DCWW have requested that the developer looks into the use of Sustainable Drainage Systems before contacting DCWW regarding a surface water sewage connection. Subject to conditions and advisory notes.
Access / Highways Comment
Utilities / Services
Comment Constraints Comment
The site is within a Conservation Area and Area of Archaeological Sensitivity.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2018/19
Other Conservation Area Consent approved 22nd March 2019.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.46 97.9 0 47 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
47 0 0 47 0 47 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:6000 Date
Rev
No.
miles.w 4/15/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DM/2018/00007 - Magistrates Court, Abergavenny
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Caldicot Ward Dewstow Site Address Brookside
Neddern Way Caldicot NP26 4RJ
LPA Reference DC/2016/01453 Grid Reference Easting 347745 Northing 189062 Market Type (Private, Public, RSL)
RSL
Owner Developer Monmouthshire Housing Association Agent LRM Planning Ltd
22 Cathedral Road Cardiff CF11 9LJ
Landowner / developer intentions
Description of Development
Demolition of existing structures on site, construction of 25 new dwellings and associated works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 06.04.2017 06.04.2022 DC/2016/01453 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru Welsh Water (DCWW) – Condition requested for drainage strategy to be approved prior to works commencing
Access / Highways Comment
MCC Highways Officer - No Objections. There are no highway grounds to sustain an objection to the application subject to conditions
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.97 25.8 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
25 0 25 0 0 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1500 Date
Rev
No.
Edge.J 4/7/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2016/01453 - Brookside, Caldicot
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Caldicot Ward Caldicot Castle Site Address Former White Hart Inn, Sandy Lane LPA Reference DC/2013/00796 Grid Reference 347888,188505 Market Type (Private, Public, RSL)
Private – 12 Public - 4
Owner Developer Worthy Developments
Millennium House Severn Link Distribution Centre Chepstow, Monmouthshire NP16 6UN
Agent Barton Willmore Greyfriars House Greyfriars Road Cardiff, CF10 3AL
Landowner / developer intentions
Description of Development
Erection of 16 no. dwellings with associated parking, access, landscaping and engineering works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 09.01.2019 09.01.2019 DC/2013/00796 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW – Recommended conditions on approval that foul and sewerage water be drained separately from the site in order to protect the public sewerage system. Unless approved in writing by the LPA, no surface water will connect to the public sewerage system. No land drainage run off shall be allowed to discharge into the public sewers either directly or indirectly.
DCWW – Advise that the applicant applies to DCWW for any connection to the public sewer under S106 of the Water industry Act 1991. If the connection to the public sewer network is either via a lateral drain or via a new sewer. The design of the sewers and lateral drains must also conform to the Welsh Ministers Standards for Gravity Foul Sewers and Lateral Drains.
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2018/19
Other Recent planning approval. Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20
2020/21
2021/22 2022/23 2023/24
0.17 94.1 0 16 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
Units U/C
1 2 3 4
16 0 0 16 0 0 16 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1000 Date
Rev
No.
miles.w 4/11/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DC/2013/00796 - Former White Heart Inn, Sandy Lane, Caldicot
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Caldicot Ward Caldicot Castle Site Address Land to East of Church Road LPA Reference DM/2018/00880 Grid Reference Easting 348312,Northing 189378 Market Type (Private, Public, RSL)
Private – 84 Public - 46
Owner Developer Agent HGH Consulting
45 Welbeck Street Marylebone London, W1G 8DZ
Landowner / developer intentions
Description of Development
Outline application (with all matters other than access reserved for future determination) for the erection of up to 130 dwellings, provision of new open space including a new community park and other amenity space, engineering and landscaping works including sustainable urban drainage system and enabling works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 05.03.2019 05.03.2022 DM/2018/00880 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW – Object. Made applicant aware that the proposed development is in an area where there are water supply problems, for which there are no improvements planned within the current Capital Investment Programme. Advice was given to complete a hydraulic modelling assessment of the surrounding
potable water supply network, which the applicant has instructed DCWW to conduct. Welsh Water will review their position post any modelling and identification of potential solutions. Welsh Water have now removed their objection following the completion of hydraulicmodelling and the identification of connection options.
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
NRW – Permission should only be grated provided the following conditions are imposed; 1) a Construction and Environmental Management Plan is submitted 2) a Landscape and Ecological Management Plan is submitted and details of the foul and surface water drainage disposal are submitted. PROW – Public Rights of Way Team at Monmouthshire suggest that whilst existing active travel links nearby to the site could be improved, they currently suffice. However the requirement to make these links up to appropriate standards, protected and maintained for the public should form part of any consent. The developer must be sure that the development accommodates the existing network or will have to apply for a path order to divert them.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2018/19.
Other Build rates and forecasts based on discussions with developer (April 2019).
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph) 2019/20
2020/21
2021/22 2022/23 2023/24
10.36 12.55 0 30 40 40 20 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
Units U/C
1 2 3 4
130 0 0 130 0 0 130 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:6000 Date
Rev
No.
miles.w 4/15/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DM/2018/00880 - Church Road, Caldicot
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Chepstow Ward St Marys Site Address Osborn International
Lower Church Street Chepstow NP16 5HJ
LPA Reference DC/2009/00910 Grid Reference Easting 353753 Northing 194109 Market Type (Private, Public, RSL)
Private – 135 dwellings Public – 34 dwellings
Owner Developer Chepstow Properties Ltd Agent Grass Roots Planning Ltd
11 Olveston Road Ashley Down Bristol BS7 9PB
Landowner / developer intentions
Description of Development
Demolition of existing industrial buildings, furniture showroom and gas depot and the erection of 169 dwellings, B1 office space, an A3 cafe/restaurant, provision of public open space, parking and associated engineering works and infrastructure
Planning Status:
Planning Consent Date Consent Expiry Date Application/Plan ref.
Full 12.09.11 12.09.16 DC/2009/00910 Approved subject to S106 – never signed
DC/2007/00800
Withdrawn DC/2005/00590
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Mains sewer
Access / Highways Comment
No major concerns over increase in traffic over immediate highway network, existing traffic lights on junctions on A48 at capacity. S278 required for improvements.
Utilities / Services Comment
Constraints Comment
Site lies within Zone C1, Environment Agency has no objection if measures detailed in the Flood Consequences Assessment are conditioned.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2011/12
Other 5 houses along the front of the site completed in the 2017/18 survey. The large factory buildings on site had been demolished and construction had begun on a block of 35 apartments during the 2017/18 survey. These had been completed in the 2018/19 survey. 4 houses were under construction at the time of the most recent survey.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20
2020/21
2021/22
2022/23
2023/24
2.4 70.4 26 30 30 30 9 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
169 5 35 129 4 125 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2009/00910 - Osborn International, Chepstow
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Chepstow Ward St Mary’s Site Address Mabey Bridge Ltd
Station Road Chepstow NP16 5YL
LPA Reference DC/2014/01290 Grid Reference Easting 353770 Northing 193570 Market Type (Private, Public, RSL)
Allocated in the LDP for in the region of 350 units during the plan period of which 35% will be affordable.
Owner Mabey Holdings Developer Barratt/David Wilson Homes Agent Barratt/David Wilson Homes
Oak House Village Way Tongwynlais, Cardiff CF15 7NE
Landowner / developer intentions
Landowner has submitted an outline application for redevelopment of the site to provide up to 450 residential units, offices, workshops, commercial and leisure facilities, including the change of use of Brunel House. A network of open spaces, footpaths, highway infrastructure, new services and infrastructure, creation of a new treatment/amenity wetlands and drainage channels, ecological mitigation and enhancement works. Alterations to the highway network and other ancillary works. An Environmental Impact Assessment was submitted with this application. Reserved Matters application for 345 dwellings submitted (DM/2019/00001) and is due to be reported to Planning Committee in May 2019.
Description of Development
Allocated for a mixed use residential and employment development, provision made within the site for 3ha of serviced land for industrial and business development
(Class B1) Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 27.11.17 27.11.20 DC/2014/01290 LDP Alloc – SAH3
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru/Welsh Water - Have significant concerns regarding the presence of several strategic assets within the development site which have not been addressed in the proposals. MCC have provided assurances that through the imposition of suitably worded conditions, the investigations and delivery of any solutions and/or reinforcement works required to fully assess and resolve any potential impact on the assets, can be undertaken post determination. SEWERAGE All surface water, land and highway water will utilise sustainable drainage techniques and eventually discharge to the adjacent watercourse. Whilst this approach is welcomed, the presence of swales and other attenuation features should be afforded careful consideration in terms of their proximity to any public sewers and water mains. Any SUDs feature should allow for sufficient access to ensure Dwr Cymru can maintain their duties to repair and replace assets where necessary. A Hydraulic Modelling Assessment has been undertaken to assess the ability of the existing public sewerage infrastructure off site to accommodate the proposed development. The assessment identified that reinforcement works are required in order to prevent detriment to the existing sewerage network. A number of solutions have been shared and progress of any such solution will be the developer’s responsibility to fund. WATER SUPPLY The existing infrastructure can accommodate the proposed development, therefore remove any previous holding objection to the potable water supply element of the application.
Access / Highways Comment
The principles and the means of access and the sustainability of the proposed development have been the subject of extensive discussion with the applicant’s
consultants and various officers of the Council both pre Local Development Plan and post Local Development Plan allocation in determining the viability and suitability of the proposed development and its impact on the immediate environment. MCC Higways offered no objections to the proposed development and the proposed means of access, but questioned the level of detail submitted in support of the application and the need to enter into additional agreements to secure and provide the means of access. They therefore wished to see significant and robust planning conditions attached to the decision notice and Section 106 agreement provisions and the need to enter into a S278 agreement with both the Welsh Government and Monmouthshire County Council Highways to control the delivery of the highway and transportation infrastructure in a timely manner Welsh Government, as highway authority for motorway and trunk roads, have no objection to this development, subject to the new phasing highway mitigation proposals.
Utilities / Services Comment
Constraints Comment
No highly vulnerable development shall take place in those parts of the site that are within the designated C2 flood zone. No other development shall take place in those parts of the site that are within the designated C2 flood zone unless a flood consequences assessment has been carried out that demonstrates that the consequences of flooding in these areas are acceptable. Project level HRA to satisfactorily demonstrate that appropriate mitigation can be taken during construction and operation of the scheme to avoid adverse effects (either direct or indirect) on the integrity of the River Wye SAC. The proposal to include a buffer strip of undeveloped land between the River Wye SAC and any development. The exact size and position of the buffer strip in relation to the development and SAC to be determined through the detailed project level HRA and in consultation with NRW.
Capital Works Comment
Provision to be made within the site for 3 hectares of serviced land for industrial and business development (Class B1 of the Town and Country Planning (Use
Classes) Order), unless it can be demonstrated that a reduced area would be appropriate by means of an equivalent amount of other employment and wealth creating opportunities contributing to sustainable economic growth being provided within the development proposals.
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Hydraulic modelling has been completed, and whilst there are site contamination issues required remediation works are not substantial and can be undertaken as one contract so will not affect sales of the first phase of development. Reserved Matters application for 345 dwellings submitted (DM/2019/00001) and is due to be reported to Planning Committee in May 2019. This covers the whole site excluding Brunel House and the 1.5 acres of affordable housing land which is estimated to provide an additional 18 dwellings in 2023/24. The balance of 87 dwellings (450 outline minus 345 RM (current application) minus 18 AH) are shown in Category 4 for completeness. Build rates provided by Barratt/David Wilson Homes.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
9.5 36.8 0 45 70 105 105 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
450 0 0 450 0 325 0 125
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:5000 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2014/01290(O/L) - Fairfield Mabey, Chepstow
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Dingestow Ward Mitchel Troy Site Address Land to the South East LPA Reference DM/2018/01404 Grid Reference Easting 345919, Northing 209960 Market Type (Private, Public, RSL)
Private – 6 Public - 9
Owner Developer Monmouthshire Housing Association Agent LRM Planning
22 Cathedral Road Cardiff CF11 9LJ
Landowner / developer intentions
Description of Development
Development of 15 dwellings (including 4no. 2 bedroom units, 5no. 3 bedroom units and 6no. 4 bedroom units), landscape buffer, car parking and associated works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 19.02.2019 19.02.2024 DM/2018/01404 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW – No objections. DCWW have confirmed they can accept foul water only and are satisfied with the use of SuDS for the for surface water disposal. A condition stating that no surface or land drainage shall connect directly or indirectly with the public sewerage network.
Access / Highways Comment
Utilities / Services
Comment Constraints Comment
NRW – No objections.
Capital Works Comment
JHLAS History
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20
2020/21
2020/21 2021/22 2023/24
0.51 29.41 5 10 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
Units U/C
1 2 3 4
15 0 0 15 0 0 15 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DM/2018/01404 - Land to south easr of Dingestow
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Llanellen Ward Llanfoist Fawr Site Address Unit 1
Llanellen Court Farm Llanellen Abergavenny NP7 HT
LPA Reference DC/2015/00474 Grid Reference Easting 330207 Northing 210385 Market Type (Private, Public, RSL)
Private
Owner Morspan Holdings Ltd Developer Agent Buckle Chamberlain Partnership
Mill House Llancayo Court Llancayo Usk NP15 1HY
Landowner / developer intentions
Original application submitted for the development of 14 close care apartments together with a warden apartment. Latest application is approved for 14 apartments for those over 55 years in age.
Description of Development
Proposed conversion of redundant agricultural building into a mix of one and two bedroom apartments.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 15.05.2015 15.05.2020 DC/2015/00474 Full DC/2010/00981
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water made no comments as a private means of foul drainage is proposed
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2015/16
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.7 20 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
14 0 0 14 14 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/5/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00474 - Llanellen Court Farm, Llanellen
New Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Llanellen Ward Llanfoist Fawr Site Address Unit 2
Llanellen Court Farm Llanellen Abergavenny NP7 HT
LPA Reference DC/2015/00983 Grid Reference Easting 330202 Northing 210416 Market Type (Private, Public, RSL)
Private – 9 units Public – 5 units
Owner Morspan Holdings Ltd Developer Agent Buckle Chamberlain Partnership
Mill House Llancayo Court Llancayo Usk NP15 1HY
Landowner / developer intentions
Description of Development
Proposed change of use of redundant agricultural buildings to 14no. close care dwellings for persons over 55 years of age, plus associated works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 26.04.2017 26.04.2022 DC/2015/00983 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water had no objection as a private means of foul drainage is proposed
Access / Highways No objections subject to the condition that prior to the
Comment commencement of development the proposed new access shall be completed to the written satisfaction of the Local Planning Authority.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2017/18
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.32 44 0 0 14 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
14 0 0 14 0 14 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 12/21/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00983 - Llanellen Court Farm
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Llanfair Kilgeddin Ward Llanover Site Address Land north of Llanfair Kilgeddin SAH11(x) LPA Reference DM/2018/02001 Grid Reference Easting 334850, Northing 207160 Market Type (Private, Public, RSL)
Private – 2 Public - 3
Owner Developer Agent Landowner / developer intentions
Description of Development
Outline Planning for development of 5 new dwellings, 2 market, 3 affordable, access from existing residential road.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 19.03.2019 19.03.2022 DM/2018/02001 SAH11(x)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW – No objection. DCWW advise the applicant to exhaust the use of SuDS and advise that sewerage network surrounding the development is for foul water only and therefore surface water would not be accepted into this network. Conditions and advisory notes include; the submission and approval of a drainage plan for the disposal of foul, surface and land water and the potential for disposal by sustainable means, prior to any works.
Access / Highways Comment
No objection. Conditions upon approval include; Submission and approval of detailed design, safety and technical audits for the proposed means of access
prior to any works. Details of off street parking provision for 13-15 Gethin Place will be provided and approved prior to any works. A Construction Traffic Management Plan (CTMP) shall be submitted to and approved by the local planning authority prior to any works. This will take into account the specific environmental and physical constraints of local networks and the adjoining highway network. The CTMP shall include traffic management measures, hours of working, measures to control dust, noise and related nuisances, measures to protect adjoining users from construction works, provision for the unloading and loading of construction materials and waste within the curtilage of the site, the parking of all associated construction vehicles. Prior to any building construction works turning provision shall be provided to enable all delivery, construction and contractors vehicles to turn within the curtilage of the site as well as providing for suitable levels of onsite parking. Parking provisions in accordance with supplementary planning guidance, Monmouthshire Parking Standards 2012, shall be provided within the site and retained thereafter.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2018/19
Other Recent outline planning approval. The landowner is now marketing the site.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph)
2019/20
2020/21
2021/22 2022/23 2023/24
0.17 29.41 0 0 5 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
Units U/C
1 2 3 4
5 0 0 5 0 0 5 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:6000 Date
Rev
No.
miles.w 4/15/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DM/2018/02001 (O/L) - Land north of Llanfair Kilgeddin
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Llanfoist Ward Llanfoist Fawr Site Address Land at Grove Farm
(Off Gypsy Lane) Llanfoist NP7 9FF
LPA Reference DC/2016/00880 Grid Reference Easting 329045 Northing 212947 Market Type (Private, Public, RSL)
Up to 115 dwellings of which 35% to be affordable
Owner Mr Ben Jones Developer Candleston Homes Agent Nathaniel Lichfield & Partners Ltd
Helmont House Churchill Way Cardiff CF10 2HE
Landowner / developer intentions
Description of Development
Development of up to 115 residential dwellings (C3), open space, landscaping, vehicular access off Gypsy Lane, pedestrian accesses and related infrastructure and engineering works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Reserved Matters
Not determined as yet
DM/2019/00346
Outline 28.03.18 28.03.21 DC/2016/00880 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru – Welsh Water (DCWW) – No objection subject to no dwelling being occupied until an agreed foul drainage system has been constructed, completed
and brought into use in accordance with an approved scheme.
Access / Highways Comment
MCC Highways – No objection. There will be no significant impact on the local highway network to the detriment of highway safety. Therefore, there are no highway grounds to sustain an objection to the application subject to conditions being applied to any grant of planning approval or included in a Section 106 Agreement.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
The site is crossed by a public sewer with known flooding incidents in the past. It is likely that this will need to be diverted to facilitate a new housing layout the assessment of which would need to be carefully considered by DCWW engineers.
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other The standard condition whereby there are normally three years in which the reserved matters are to be submitted following the grant of outline permission has been reduced to allow twelve months for submission of reserved matters. The reason for this is that the site, which is in open countryside and not a housing allocation in the adopted LDP, is only approved on the basis that it will help reduce the shortfall in the Council’s five year housing land supply. For similar reasons the period in which the development must be commenced has been reduced from five years from the date of the outline permission to three years. The reserved matters application for 106 dwellings has now been submitted and is under consideration. Reserved Matters application submitted (DM/2019/00346) for 106 dwellings under consideration. Developer keen to get on site. Site is being developed by Candleston (market housing) and Melin (AH). Developer advises (April 2019) that they will be on site January 2020 with first completions in July 2020, with 35 completions in a full year thereafter. Note: 9 units have been moved to Category 4 to account for the known difference between the outline planning permission and the current RM application.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
5.24 5.24 21.9 0 10 35 35 26 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
115 0 0 115 0 106 0 9
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:3500 Date
Rev
No.
Edge.J 4/7/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2016/00880 (O/L) - Land at Grove Farm, Llanfoist
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Llanishen Ward Trellech United Site Address Site adjacent to the B4293 and Church Road,
Llanishen LPA Reference DC/2016/00415(O/L) Grid Reference Easting 347816 Northing 203288 Market Type (Private, Public, RSL)
Private – 3 dwellings Public – 5 dwellings
Owner Developer Agent Studio 4b Architects
4 Castle Parade Usk NP15 1AA
Landowner / developer intentions
Description of Development
Outline planning consent for the construction of eight dwellings on allocated housing site SAH11 (ix)(a)
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 09.06.2017 09.06.2020 DC/2016/00415 LDP Alloc -
SAH11(ix)(a) Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water - no objections provided that surface water and land drainage are disposed of separately from foul water and that an 8 metre wide easement is left for the water main that crosses the site.
Access / Highways Comment
No objection - the applicant shall apply for permission prior to commencement of access works via Monmouthshire County Council Highways.
Utilities / Services
Comment Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Site is currently being marketed, however there has not been much progress to date.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.23 34.78 0 3 5 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
8 0 0 8 0 8 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1750 Date
Rev
No.
Edge.J 4/12/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2016/00415(O/L) - Land rear Carpenters Arms Llanishen
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Undy Ward The Elms Site Address Rockfield Farm LPA Reference DC/2016/00883 Grid Reference Easting 343705 Northing 187663 Market Type (Private, Public, RSL)
Estimated will deliver circa. 266 units on current design of which 25% will be affordable. (Allocated in LDP for 270 units)
Owner Monmouthshire County Council Developer Phase 1 – Bellway Homes Agent Landowner / developer intentions
Master planned development of 13.8 hectares of land for residential use and employment use; up to 266 proposed residential units and approximately 5575 square meters of B1 floor space.
Description of Development
Allocated in the LDP for mixed use residential and employment development.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 20.03.18 20.03.21 DC/2016/00883 LDP Alloc – SAH5
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Hydraulic Modelling Assessments complete and drainage strategy outlined. Any planning decision is subject to appropriate conditions to ensure that the development does not commence until the strategy has been developed and approved and the status of the on-site sustainable drainage systems and surface water sewers has been agreed.
Access / Highways Comment
MCC Highways - no objections to the proposal from a traffic impact perspective subject to suitable conditions imposed to control the design and construction of the means of access. Updated Traffic Assessment completed. Assessment has
determined the Magor/Undy by-pass is not required and that a local link road will be sufficient. The assessment has also taken account of the proposed new M4. Any land take for the new M4 route will also not affect either of the sites in Magor/Undy as the proposed route is north of the existing route.
Utilities / Services Comment
Mains services available in the area. Hydraulic modelling assessment for clean water has been undertaken and solution identified. A Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for making an enhanced financial contribution to community facilities in the Magor/Undy area.
Constraints Comment
The master plan for the development takes account of the SINC at the site. Archaeological investigation on site has uncovered an archaeological constraint of “regional importance” within one of the parcels. Recommendation that a condition requiring the applicant to submit a detailed written scheme of investigation for a programme of archaeological work to protect the archaeological resource should be attached to any consent.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Bellway Homes are the developer for Phase 1 of the development. Proposed trajectory provided by Bellway Homes and MCC Estates. This is calculated as follows:
19/20 – 3.66 units per month x 6 months (October 19 onward= 22 units on Phase 1 20/21 – 3.66 x 12 months = 44 on Phase 1 + Phase 2 can commence after Sept 2020 when utilities must be completed, assuming conservative 35/yr per outlet for 6 months = 44 Phase 1 + 18 Phase 2 = 62 21/22 – 3.66 x 12 months = 44 phase 1 + 35 phase 2 = 79 22/23 – 34 remaining phase 1 + 35 phase 2 = 69 23/24 – 34 remaining units on phase 2
A reserved matters application has been submitted and was approved on 22.02.19 for phase 1 (144 units of the development) The forecasts below are for the remaining 122 units subsequently left after the reserved matters approval. There is a separate proforma, for the reserved matters application.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
2.8 43.6 0 18 35 35 34 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
122 0 0 122 0 122 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:3000 Date
Rev
No.
miles.w 4/16/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DC/2016/00883 (O/L) - Rockfield Farm
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Undy Ward The Elms Site Address Rockfield Farm (Phase 1) LPA Reference DM/2018/01606 Grid Reference Easting 343759, Northing 187702 Market Type (Private, Public, RSL)
Private – 108 Public - 36
Owner Monmouthshire County Council Developer Bellway Homes
Building One Eastern Business Park St. Mellon’s Cardiff, CF3 5EA
Agent Hammond Architectural Ltd. 10 Gold Tops Newport, NP20 4PH
Landowner / developer intentions
Description of Development
Reserved matters application (pursuant to outline application DC/2016/00883) for the development of 144 dwellings and associated engineering works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Reserved Matters
22.02.2019 20.03.2023 DM/2018/01606
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW – No objection. Updates to hydraulic modelling assessment carried out as part of the outline proposal, are required to inform DCWW of the capacity for 144 dwellings at connection point 1, identified in the initial assessment. DCWW also request that condition no.15 attached to outline consent DC/2016/00883 is
transferred to the reserved matters application as it does not meet the condition of providing a potable water scheme.
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Ecology – No objection. Conditions and advisory notices relate to the development being carried out in strict accordance with the approved Construction Environmental Management Plan. Ecology advised that enhancements based on priority species identified during the outline application surveys and data search e.g. Starling and crevice dwelling bat species, may be necessary. Environmental Health – No objection. Conditions regarding noise mitigation are to be met as per the approved Environmental Noise Assessment. Green Infrastructure – No objection. Requirement that the Maintenance plan state clearly that all plant failures will be addressed during the 5 year maintenance period. NRW – No comment, but advised that it is the responsibility of the applicant to ensure that they secure all other permits/consents relevant to their development.
Capital Works Comment
JHLAS History
Other Reserved matters application DM/2018/01606 is pursuant to and phase 1 of the outline application DM/2016/00883 for the Rockfield Farm site. Proposed trajectory provided by Bellway Homes and MCC Estates is calculated as follows:
19/20 – 3.66 units per month x 6 months (October 1onwards) = 22 units on Phase 1 20/21 – 3.66 x 12 months = 44 on Phase 1 + Phase 2 can commence after Sept 2020 when utilities must be completed, assuming conservative 35/yr per outlet for 6 months = 44 Phase 1 + 18 Phase 2 = 62 21/22 – 3.66 x 12 months = 44 phase 1 + 35 phase 2 = 79 22/23 – 34 remaining phase 1 + 35 phase 2 = 69
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20
2020/21
2021/22 2022/23 2023/24
5.4 26.7 22 44 44 34 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
Units U/C
1 2 3 4
144 0 0 144 0 0 144 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:3000 Date
Rev
No.
miles.w 4/16/2019
Details Details of the plan © Hawlfraint y Goron a hawliau cronfa ddata 2011 Arolwg Ordnans 100023415© Crown copyright and database rights 2011 Ordnance Survey 100023415
County HallCwmbranNP44 2XHwww.monmouthshire.gov.uk/maps
DM/2018/01606 - Rockfield Farm (Phase 1)
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Undy Ward The Elms Site Address Land at Vinegar Hill
Undy LPA Reference SAH6 Grid Reference Easting 343199 Northing 187653 Market Type (Private, Public, RSL)
Estimated will deliver in the region of 225 units of which 25% will be affordable.
Owner Developer Bovis Homes Agent Landowner / developer intentions
PAC commencing May 2019, hybrid full and outline application expected August 2019.
Description of Development
Allocated in LDP for residential development.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
LDP Alloc – SAH6 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Access / Highways Comment
A Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary off-site highway improvements to the highway network through Magor/Undy. Whilst the access for part of the site does depend on the Rockfield Farm Site there is also access from the west for a large area of the site so can be commenced independently.
Utilities / Services
Comment Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other A Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for making an enhanced financial contribution to community facilities in the Magor/Undy area. The site has been the subject of a pre-app and the developer is asking for a Planning Performance Agreement so the process should be quicker. The pre-app customer has provided the proposed trajectory. PAC commencing May 2019, hybrid full and outline application expected August 2019.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
7.81 28.8 0 25 50 50 50 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
225 0 0 225 0 175 0 50
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4500 Date
Rev
No.
edge.j 4/14/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH6 - Land at Vinegar Hill, Undy
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Wyesham Site Address 38 Hillcrest Road
Wyesham Monmouth NP25 3LH
LPA Reference DC/2012/00754 Grid Reference Easting 351491 Northing 212520 Market Type (Private, Public, RSL)
Private – 7 units Public – 4 units
Owner The Diocese of Hereford and Western Power Distribution The Diocesan Office The Palace Hereford HR4 9BL
Developer Agent Hook Mason Limited
41 Widemarsh Street Hereford HR4 9EA
Landowner / developer intentions
Description of Development
Proposed demolition of existing vicarage and the construction of a new vicarage and development of 11 new houses including four units of affordable housing - amended scheme featuring revised parking arrangement, revised elevations, structural engineer's report and ground investigation (contamination) report
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 07.09.2017 07.09.2022 DC/2012/00754
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water has no objection to the proposal. In terms of sewerage treatment, no problems are envisaged with the Waste Water Treatment Works for the treatment of domestic discharges from the site. No problems are envisaged with the water supply for the development.
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Gwent Wildlife Trust issued a holding objection initially on the basis that they considered there to be several biodiversity and protected species issues, measures need to be put in place to protect the wildlife corridor from damage and disturbance.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.5 22 0 11 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
11 0 0 11 0 11 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1750 Date
Rev
No.
Edge.J 4/12/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2012/00754 - Hillcrest Road Wyesham
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Drybridge/Overmonnow Site Address Wonastow Road (Part)
Monmouth LPA Reference DC/2015/00390 Grid Reference Easting 349320 Northing 212280 Market Type (Private, Public, RSL)
Private – 116 Public - 50
Owner Developer Taylor Wimpey South Wales
Building 2, Eastern Business Park Wern Fawr Lane St. Melons Cardiff CF3 5EA
Agent RPS Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Allocated in LDP for a mixed use residential and employment development. Provision within the site for 6.5ha of serviced land for high quality industrial and business development (Class B1)
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Reserved Matters 17.11.2015 19.12.2019 DC/2015/00390 Outline 19.12.2014 19.12.2017 DC/2013/00368
LDP Alloc – SAH4
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
To be satisfactorily demonstrated that the site can be developed with no adverse consequences from surface water flooding and no worsening of flooding conditions in the vicinity of the site and a Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary works to achieve these requirements.
Access / Highways Comment
To be demonstrated that traffic can be satisfactorily accommodated in relation to the highway network leading to the site and a Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary off-site highway works to ensure that this is achieved. A Section 106 Agreement to be signed that, in addition to standard requirements, makes provision for any necessary off-site works to improve pedestrian access to and from the site.
Utilities / Services Comment
Constraints Comment
The master plan for the development to take account of the SINC at the site. No highly vulnerable development to take place in those parts of the site that are within the designated C2 flood zone. No other development to take place in those parts of the site that are within the designated C2 flood zone unless a flood consequences assessment has been carried out that demonstrates that the consequences of flooding in these areas are acceptable.
Capital Works Comment
Provision to be made within the site for 6.5 hectares of serviced land for high quality industrial and business development (Class B1 of the Town and Country Planning (Use Classes) Order)
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
4.53 37 3 0 0 0 0
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
166 51 81 34 31 3 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4000 Date
Rev
No.
Edge.J 2/23/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00390 - Wonastow Road, Monmouth (Taylor Wimpey)
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Drybridge/Overmonnow Site Address Wonastow Road (Part)
Monmouth LPA Reference DC/2015/00392 Grid Reference Easting 349320 Northing 212280 Market Type (Private, Public, RSL)
Private – 122 Public - 51
Owner Developer Barratt David Wilson Homes
Oak House Village Way Tongwynlais Cardiff CF15 7NE
Agent RPS Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Allocated in LDP for a mixed use residential and employment development. Provision within the site for 6.5ha of serviced land for high quality industrial and business development (Class B1)
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Non Material Ammendment
08.02.2019 DM/2019/00180
Reserved Matters 17.11.2015 19.12.2019 DC/2015/00392 Outline 19.12.2014 19.12.2017 DC/2013/00368
LDP Alloc – SAH4
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
To be satisfactorily demonstrated that the site can be developed with no adverse consequences from surface water flooding and no worsening of flooding conditions in the vicinity of the site and a Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary works to achieve these requirements.
Access / Highways Comment
To be demonstrated that traffic can be satisfactorily accommodated in relation to the highway network leading to the site and a Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary off-site highway works to ensure that this is achieved. A Section 106 Agreement to be signed that, in addition to standard requirements, makes provision for any necessary off-site works to improve pedestrian access to and from the site.
Utilities / Services Comment
Constraints Comment
The master plan for the development to take account of the SINC at the site. No highly vulnerable development to take place in those parts of the site that are within the designated C2 flood zone. No other development to take place in those parts of the site that are within the designated C2 flood zone unless a flood consequences assessment has been carried out that demonstrates that the consequences of flooding in these areas are acceptable.
Capital Works Comment
Provision to be made within the site for 6.5 hectares of serviced land for high quality industrial and business development (Class B1 of the Town and Country Planning (Use Classes) Order)
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other DM/2019/00180 is a NMA seeking approval for the substitution of plots 167,168, 176 and 177. This was approved on 08.02.2019 and resulted in the loss of 1 unit from the overall site.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
4.49 39 25 12 0 0 0
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
173 57 64 52 15 37 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4000 Date
Rev
No.
Edge.J 2/23/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00392 - Wonastow Road, Monmouth (Barratt/David Wilson)
New Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Drybridge Site Address Land West of Rockfield Road
Rockfield Road Monmouth NP25 5DS
LPA Reference DC/2017/00539 Grid Reference Easting 349562 Northing 213475 Market Type (Private, Public, RSL)
70 units of which 35% will be affordable
Owner Hallam Land Management Ltd Developer Agent Boyer
Third Floor Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Outline planning permission for the construction of up to 70 dwellings, open space, play space provision, landscaping and associated infrastructure.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 05.02.2019 05.02.2022 DC/2017/00539 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru/Welsh Water - No objection to the proposed development subject to relevant conditions being imposed.
Access / Highways Comment
MCC Highways - No objections to the proposed development on highway grounds, subject to relevant conditions being imposed and heads of terms secured as part of the Section 106 Agreement.
Utilities / Services Comment
Constraints Comment
Natural Resources Wales – No objection subject to relevant conditions being attached to the planning approval to secure a Dormouse Conservation Strategy to minimise the impact of the development on dormice. Condition 19 of the approval notice requires the submission of a Doormouse Conservation Startegy
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2018/19
Other Section 106 signed on 31.01.2019.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2022/23
2.86 24 0 10 30 30 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
70 0 0 70 0 70 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 12/21/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2017/00539 (O/L) - Land west Rockfield Road
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Drybridge/Overmonnow Site Address Wonastow Road (LDP)
Monmouth LPA Reference SAH4 Grid Reference Easting 349320 Northing 212280 Market Type (Private, Public, RSL)
Estimated will deliver in the region of 110 units, of which 35% will be affordable.
Owner South Wales Land Developments Ltd Developer Bovis Agent Landowner / developer intentions
Description of Development
Whole site allocated in LDP for a mixed use residential and employment development. Provision within the site for 6.5ha of serviced land for high quality industrial and business development (Class B1)
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
LDP Alloc – SAH4 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
To be satisfactorily demonstrated that the site can be developed with no adverse consequences from surface water flooding and no worsening of flooding conditions in the vicinity of the site and a Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary works to achieve these requirements.
Access / Highways Comment
To be demonstrated that traffic can be satisfactorily accommodated in relation to the highway network leading to the site and a Section 106 Agreement to be signed that, in addition to standard requirements,
includes provision for any necessary off-site highway works to ensure that this is achieved. A Section 106 Agreement to be signed that, in addition to standard requirements, makes provision for any necessary off-site works to improve pedestrian access to and from the site.
Utilities / Services Comment
Constraints Comment
The master plan for the development to take account of the SINC at the site. No highly vulnerable development to take place in those parts of the site that are within the designated C2 flood zone. No other development to take place in those parts of the site that are within the designated C2 flood zone unless a flood consequences assessment has been carried out that demonstrates that the consequences of flooding in these areas are acceptable.
Capital Works Comment
Provision to be made within the site for 6.5 hectares of serviced land for high quality industrial and business development (Class B1 of the Town and Country Planning (Use Classes) Order)
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Remainder of the LDP allocated site, Bovis are keen to progress the site but are dependent on Taylor Wimpey and Barratt for the access. The access road is due for completion in December 2019, as per the phasing plan, so no completions likely before this date although Bovis could be on site. Developer advised (March 2019) PAC due to commence 24th May 2019 with outline application submitted Summer 2019.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
5.75 19 0 15 45 50 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
110 0 0 110 0 110 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH4 - Wonastow Road (Part), Monmouth
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Monmouth Ward Wyesham Site Address Tudor Road
Wyesham LPA Reference SAH8 Grid Reference Easting 352147 Northing 212249 Market Type (Private, Public, RSL)
Estimated will deliver in the region of 35 units of which 35% will be affordable.
Owner Developer Agent Landowner / developer intentions
Description of Development
Allocated in LDP for residential development.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
LDP Alloc – SAH8 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
The layout of any proposal to make provision for an appropriate buffer zone between any residential development and the boundary of the Wye Valley Area of Outstanding Natural Beauty and ensure that no development takes place on the higher slopes of the site or on that part of the site designated as a SINC.
Capital Works
Comment JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site has been the subject of pre app discussion with the Council. Edenstone Homes are the interested developer. Proposed forecast completions provided by Edenstone. There has not been much progress on site, due to Welsh Water capacity issues.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
2.05 17.1 0 0 0 15 20 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
35 0 0 35 0 35 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH8 - Tudor Road, Wyesham
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Penallt Ward Trellech United Site Address Land to the South West of Penallt
Penallt Monmouth NP25 4SB
LPA Reference DC/2015/00606 Grid Reference Easting 351875 Northing 208880 Market Type (Private, Public, RSL)
Private – 4 dwellings Public – 6 dwellings
Owner Developer Mike Etheridge Construction Ltd Agent Paul Thornton Building Design Ltd
85 Park Road Berry Hill Coleford GL16 7AG
Landowner / developer intentions
Description of Development
Residential development of allocation site SAH11 (xii) to provide 10 dwellings (including 60% affordable housing).
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 21.11.2016 21.11.2021 DC/2015/00606 LDP Alloc -
SAH11(xii) Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
This proposal is located in an area where there is no mains drainage so an on-site sewage treatment plant is proposed. Welsh Water commented to this effect during the Local Development Plan process but did not raise any concern. Natural Resources Wales - No
objection to proposed foul water drainage or ecology of the site subject to relevant planning conditions being imposed.
Access / Highways Comment
Monmouthshire Highways and Drainage Officer - The proposal has been revised to satisfy highway and drainage concerns. The details submitted are now satisfactory, no objections to the proposed development from a highway standpoint subject to certain conditions.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2015/16
Other Brideoak Homes are the developer and intend to start this site soon once they have finished the site at Shirenewton.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.4 25 0 10 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining @ 01st April
2019
1 2 3 4
10 0 0 10 0 10 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00606 - Land to south west of Penallt
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Penperlleni Ward Goetre Fawr Site Address Land South of Usk Road LPA Reference DC/2013/01001 (Phase 1) Grid Reference Easting 332222 Northing 204388 Market Type (Private, Public, RSL)
Private – 26 units Public – 14 units
Owner Developer BDW South Wales
4a Oak House Village Way Tongwynlais Cardiff CF15 7NE
Agent Landowner / developer intentions
Description of Development
3 ha allocated in LDP for residential development, subject to the net developable area being no more than 2.2ha with the remainder being utilised to provide a landscape/ecological zone.
Planning Status:
Planning Consent Date Consent Expiry Date Application/Plan ref.
Variation or Removal of Condition
DC/2017/00193
Full 15.04.2015 15.04.2020 DC/2013/01001 (Taylor Wimpey)
LDP Alloc – SAH10 (ii)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
The principles for the management of surface water were subject to pre-application discussion in 2013 with
both the Council and Natural Resources Wales. The drainage proposal for the site is to store surface water within a drainage pond that would be located to the south-west of the site, subject to confirmation from the Land Drainage Authority. The Council’s Drainage Officer has reviewed the proposals and is of the view that the proposed means of dealing with surface water is acceptable subject to a s106 agreement/ conditions. Welsh Water/Dwr Cymru - The proposed new development site at Usk Road cannot be developed without upgrades to the Goytre WwTW first being undertaken. A feasibility study has been undertaken and a subsequent Section 106 Agreement signed between the developer, LPA and Welsh Water. Welsh Water have recently received the monies in order to progress the upgrade to the WwTW. In line with the provisions of the Section 106 Agreement the development at Usk Road can come forward on completion of the upgrade works which are anticipated for mid-2018.
Access / Highways Comment
Welsh Government has not raised any objection to the proposed access arrangements. The Council’s Highways department has reviewed the submitted information and has no objection to the principle of the proposed access. The proposed scheme is not considered to have an unacceptable impact on highway safety and the proposed development is considered to meet the requirements of the Highway Authority.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
1.34 30 0 0 0 0 0
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
40 0 39 1 1 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 2/23/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2013/01001 - Land South of Usk Road, Penperlleni (Phase 1)
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Penperlleni Ward Goetre Fawr Site Address Land South of Usk Road LPA Reference DC/2014/00468 (Phase 2) Grid Reference Easting 332222 Northing 204388 Market Type (Private, Public, RSL)
Private – 16 units Public – 9 units
Owner Developer BDW South Wales
4a Oak House Village Way Tongwynlais Cardiff CF15 7NE
Agent Landowner / developer intentions
This application refers to what would be phase 2 of the development.
Description of Development
3 ha allocated in LDP for residential development, subject to the net developable area being no more than 2.2ha with the remainder being utilised to provide a landscape/ecological zone.
Planning Status:
Planning Consent Date Consent Expiry Date Application/Plan ref.
Variation or Removal of Condition
DC/2017/00195
Full 15.04.2015 15.04.2020 DC/2014/00468 LDP Alloc –
SAH10 (ii) Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
The principles for the management of surface water were subject to pre-application discussion in 2013 with
both the Council and Natural Resources Wales. The drainage proposal for the site is to store surface water within a drainage pond that would be located to the south-west of the site, subject to confirmation from the Land Drainage Authority. The Council’s Drainage Officer has reviewed the proposals and is of the view that the proposed means of dealing with surface water is acceptable subject to a s106 agreement/ conditions. Welsh Water/Dwr Cymru - The proposed new development site at Usk Road cannot be developed without upgrades to the Goytre WwTW first being undertaken. A feasibility study has been undertaken and a subsequent Section 106 Agreement signed between the developer, LPA and Welsh Water. Welsh Water have recently received the monies in order to progress the upgrade to the WwTW. In line with the provisions of the Section 106 Agreement the development at Usk Road can come forward on completion of the upgrade works which are anticipated for mid-2018.
Access / Highways Comment
Welsh Government has not raised any objection to the proposed access arrangements. The Council’s Highways department has reviewed the submitted information and has no objection to the principle of the proposed access. The proposed scheme is not considered to have an unacceptable impact on highway safety and the proposed development is considered to meet the requirements of the Highway Authority.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
1.6 16 0 0 0 0 0
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
25 0 25 0 0 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 2/23/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2014/00468 - Land South of Usk Road, Penperlleni (Phase 2)
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 12/04/2019
TAN(W) 1
Site Details:
Settlement Portskewett Ward Portskewett Site Address Crick Road LPA Reference DM/2018/00696 Grid Reference Easting 349386 Northing 188493 Market Type (Private, Public, RSL)
Private – 218 Public - 73
Owner Melin Homes and Monmouthshire County Council Developer Melin Homes Agent Asbri Planning
Unit 9 Oak Tree Court Cardiff Gate Business Park Cardiff, CF23 8RS
Landowner / developer intentions
Outline application (with all matters reserved, except for access) for residential development of up to 291 dwellings, a care home and public open space, landscaping and associated infrastructure works.
Description of Development
Allocated in the LDP for a mixed use residential and employment development. Provision for 1ha of serviced land for industrial and business development (Class B1) The application submitted is for residential development and a care home.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 30.03.2019 30.03.2022 DM/2018/00696(LDP Alloc – SAH2)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW - no objections, on the back of completed foul and water hydraulic modelling assessments, which have identified several network reinforcement solutions, and one developed for the surrounding
water mains network. The network reinforcement works will need to be completed prior to any sewerage or water connections being made. This will be controlled through a number of conditions including the submission of foul water drainage scheme and approval by the local planning authority before any development commences. No part of the development shall be brought into use and no dwelling shall be occupied until the approved foul drainage system has been constructed, completed and brought into use in accordance with the approved scheme. No development shall take place until a potable water network scheme to satisfactorily accommodate the potable water demand from the site has been submitted to and approved in writing by the local planning authority. No part of the development shall be brought into use and no dwelling shall be occupied until the approved water network scheme has been constructed, completed and brought into use in accordance with the approved scheme.
Access / Highways Comment
A Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for any necessary off-site works to improve pedestrian access to and from the site, particularly in relation to the centre of Portskewett and to employment, shopping and community facilities in nearby Caldicot. TA commissioned to update the existing report which did not account for Sudbrook.
Utilities / Services Comment
Drainage solution being designed, offsite connection required.
Constraints Comment
Ground Condition, Ecological and Archaeological reports completed with no known issues.
Capital Works Comment
A Section 106 Agreement to be signed that, in addition to standard requirements, includes provision for 1 hectare of serviced land for industrial and business development (Class B1 of the Town and Country (Use Classes) Order)
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site is being developed by Melin Homes. Developer advises (April 2019) that they will be on site February 2020 with first completions in August 2020, with 67 completions in a full year thereafter.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
7.77 37.5 0 29 58 58 58 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
291 0 0 291 0 203 0 88
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:4000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DM/2018/00696 (O/L) - Crick Road, Portskewett
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Pwllmeyric Ward Shirenewton Site Address Hill Farm
Pwllmeyric Chepstow NP16 6LA
LPA Reference DC/2016/00953(O/L) Grid Reference Easting 351951 Northing 192660 Market Type (Private, Public, RSL)
Private – 8 units Public – 9 units
Owner Developer Agent M John Crowther & Associates
82 Cobb House Newport Road Caldicot NP26 4BR
Landowner / developer intentions
Description of Development
Outline application for housing development - 17 houses (15 on the 60/40 site and 2 on adjacent land within the development boundary)
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 07.03.2017 – approved subject to a S106 Agreement
DC/2016/00953
LDP Alloc -SAH11(xiii)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water – No Objection subject to conditions - It is proposed that foul sewerage will be disposed of via
mains sewers and that surface water will be disposed of through a sustainable drainage system.
Access / Highways Comment
No objection - the submission of a transport assessment is not deemed necessary as the site was subject to detailed review and scrutiny during the LDP site allocation process and Inspector’s determination.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2015/16
Other The landowner met with the RSL, however, no agreement was reached. There has been no progress on this site otherwise. The landowner has been issued with a timeline for signing the S106 until the end of May 2019, or risk refusal.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.92 15.64 0 7 10 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
17 0 0 17 0 17 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1500 Date
Rev
No.
Edge.J 4/13/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2016/00953(O/L) - Hill Farm Pwllmeyric
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Raglan Ward Raglan Site Address Land at Chepstow Road LPA Reference DM/2018/00769 (O/L) (SAH10(iii)) Grid Reference Easting 341359 Northing 207376 Market Type (Private, Public, RSL)
Private – 29 Public - 16
Owner Monmouthshire County Council Developer Agent Alder King
Pembroke House 15 Pembroke Road Clifton Bristol, BS8 3BA
Landowner / developer intentions
Outline development of up to 45 dwellings with details of access.
Description of Development
Allocated for residential development, subject to no highly vulnerable development taking place in those parts of the site that are within the designated C2 flood zone.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 27.02.2019 27.02.2022 DM/2018/00769 LDP Alloc – SAH10(iii)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
DCWW- No Objection. Advised applicant that current infrastructure could accept foul water only flows from the development and also made the applicant aware of a number of sewerage and water assets crossing the site and that these would need to be safeguarded. A condition relating to the submission of a construction design method statement and risk assessment for the
protection of the structural condition of the strategic rising main crossing the site has been submitted to and approved in writing by the local planning authority prior to development commencing. In addition, a drainage scheme for the site must be submitted to and approved in writing by the local planning authority prior to any development. The scheme shall provide for the disposal of foul, surface and land water, and include an assessment of the potential to dispose of surface and land water by sustainable means. Thereafter the scheme shall be implemented in accordance with the approved details prior to the occupation of the development and no further foul water, surface water and land drainage shall be allowed to connect directly or indirectly with the public sewerage system.
Access / Highways Comment
No objection. Advisory notes include the applicant reviewing the transport assessment and submit details of the means of access should they want them to be considered at this stage. Any S106 agreement should enable the delivery of the means of access pursuant to S278 Agreement, Highways Act 1980 and off site improvements namely, footpath connections.
Utilities / Services Comment
Constraints Comment
No highly vulnerable development to take place in those parts of the site that are within the designated C2 flood zone, and no other development to take place in those parts of the site that are within the designated C2 flood zone unless a flood consequences assessment has been carried out that demonstrates that the consequences of flooding in these areas are acceptable. Green Infrastructure – No objections. Conditions relating to the submission of full details of both hard and soft landscaping and earthworks and approval from the LPA prior to any development. A schedule of landscape maintenance and a green infrastructure management plan are also to be submitted and approved in writing, prior to any development. Any Unilateral Undertaking agreed instead of a S106 would need to include a combined off-site and play contribution. Biodiversity – No objection, but require the submission of a Construction Environment Management Plan (Biodiversity) prior to any development.
Capital Works
Comment JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density (Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
2.18 20.6 0 12 12 12 9 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
45 0 0 45 0 45 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:3000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DM/2018/00769 (O/L) - Land at Chepstow Road, Raglan
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Rogiet Ward Rogiet Site Address Green Farm
Caldicot Road Rogiet NP26 3UR
LPA Reference DC/2015/01328 Grid Reference Easting 345237 Northing 187838 Market Type (Private, Public, RSL)
Private - 11
Owner Green Farm Estates Developer Agent RPS
Park House Greyfriars Road Cardiff CF10 3AF
Landowner / developer intentions
Description of Development
Demolition of existing modern steel and concrete agricultural buildings and the conversion of existing farm buildings (excluding the farm house) to 11 residential dwellings, associated residential curtilages, public open space, parking areas and other infrastructure works.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 31.01.2017 31.01.2022 DC/2015/01328 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
The applicants intend to use a private treatment works so NRW have been consulted. No problems are envisaged with the provision of the water supply for
the development. Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.7 15.7 0 5 6 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
11 0 0 11 0 11 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1500 Date
Rev
No.
Edge.J 4/7/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/01328 - Green Farm, Rogiet
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Shirenewton Ward Shirenewton Site Address Land to the East of Shirenewton
Monmouthshire NP16 6AQ
LPA Reference DC/2015/0688 Grid Reference Easting 348217 Northing 193710 Market Type (Private, Public, RSL)
Private – 2 units Public – 3 units
Owner Developer Mike Etheridge Construction Ltd Agent Paul Thornton Building Design Ltd
85 Park Road Berry Hill Coleford GL16 7AG
Landowner / developer intentions
Description of Development
Residential development of LDP allocation site SAH11 (xiv)(b) to provide 5 dwellings (including 60% affordable housing) and associated works. Provision of vehicular access.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 25.10.2016 25.10.2021 DC/2015/00688 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Dwr Cymru-Welsh Water – no problems are envisaged with sewage treatment or water supply; foul and surface water to be drained separately.
Access / Highways Comment
Satisfied that the traffic generated from a small development of 5 units will have no negative impact on highway safety and that there is sufficient capacity on
the local highway network to accommodate it. Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2016/17
Other Brideoak Homes is the developer of the site. Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.17 29.4 0 0 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
5 0 5 0 0 0 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1000 Date
Rev
No.
Edge.J 4/13/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2015/00688 - Land east (north of minor road) Shirenewton
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Sudbrook Ward Portskewett Site Address The Old Shipyard
Sudbrook Road Sudbrook Portskewett Monmouthshire
LPA Reference DC/2011/00607 Grid Reference Easting 350833 Northing 187618 Market Type (Private, Public, RSL)
Private – 41 dwellings Public – 5 dwellings
Owner St Maurs Estate Ltd Beachley Road Chepstow Monmouthshire NP16 7DL
Developer Agent Heidi Davis
Itton Chepstow Monmouthshire NP16 6BR
Landowner / developer intentions
Demolition of existing buildings and redevelopment of site with 46 dwellings (including 5 affordable units) associated highway works, landscaping and car park (outline application with access considered at this outline stage).
Description of Development
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Outline 26.04.2016 26.04.2019 DC/2011/00607
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water have no objection subject to the upsizing of 230 metres of inlet main funded by the developer, and separate foul and surface water drainage arrangements.
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Environment Agency have no objection subject to conditions addressing ground contamination, investigation, remediation and monitoring, and the submission of details of drainage arrangements.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2015/16
Other The site is no longer in the ownership of Pobl. The landowner is believed to have sold the site to Enzos Homes in Llanelli, who are advertising new homes on the site. RM application DM/2018/01828 been submitted.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
1.0 46 0 10 36 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
46 0 0 46 0 46 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/5/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2011/00607 - The Old Shipyard, Sudbrook
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Sudbrook Ward Portskewett Site Address Former Paper Mill LPA Reference DC/2015/01184 (SAH7) Grid Reference Easting 350254 Northing 187474 Market Type (Private, Public, RSL)
Private – 190 units Public – 20 units
Owner Developer Redrow Homes (South Wales) Ltd
Redrow House Copse Walk Cardiff Gate Business Park Cardiff CF23 8RH
Agent Landowner / developer intentions
A planning application was approved for 212 dwellings, including 20 affordable units. a reconfigured access and creation of new emergency access route; new internal roads, footpaths/cycleways, car parking and highway improvements; a network of public open spaces, including landscaping, recreation space, public realm and biodiversity enhancement; and other ancillary works and activities requiring: site preparation, demolition and clearance, treatment, re-profiling and the installation of new services and infrastructure. An Environmental Impact Assessment was submitted with the application.
Description of Development
Allocated for residential development in the adopted LDP
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 11.11.2016 11.11.2021 DC/2015/01184 Full Refused DC/2014/01468
LDP Alloc – SAH7
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
No problems are envisaged with the Waste Water Treatment Works for the treatment of domestic discharge from the site. The development site is partially within the NRW Internal Drainage District (IDD) boundary. The FCA states that surface water will be discharged via an existing pumped sewer network that discharges into the estuary. Should it be proposed to discharge any surcharge of the system during an extreme event to a watercourse then this will require a Flood Defence or Land Drainage consent.
Access / Highways Comment
The site was subject to previous applications for the development of 340 residential properties, following a detailed review highways offered no objections to the proposed development on traffic capacity / impact grounds subject to specific and significant mitigation measures These measures were subject to detailed scrutiny and agreement by way of a statement of common ground and draft unilateral undertakings prepared and agreed during a subsequent planning appeal (DC/2012/00307) and inspector`s decision.
Utilities / Services Comment
The proposed development is in an area where there are water supply problems for which there are no improvements planned within the Capital Investment Programme AMP4 (years 2005 to 2010). In order to establish what would be required to serve the site with an adequate water supply, the developer will need to fund the undertaking of a hydraulic modelling assessment on the water supply network.
Constraints Comment
An Environmental Statement was submitted with the application due to the site’s proximity to the Severn Estuary. The Statement covers landscape and visual impact, biodiversity, transport and access. Land is partially within Zone C1 of the Development Advice Map (DAM) contained in TAN15. A Flood Consequences Assessment (FCA) was submitted with the application.
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
6.6 32.1 19 35 35 35 35 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
210 2 33 175 16 159 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:3500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC2015/01184 - Former Paper Mill site, Sudbrook
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Tintern Ward St Arvans Site Address The Abbey Hotel Tintern Ltd
Tintern Chepstow NP16 6SF
LPA Reference DC/2012/00620 Grid Reference Easting 353224 Northing 199896 Market Type (Private, Public, RSL)
Private – 9 units Public – 2 units
Owner Tintern Hotels Larchfield House Pregge Lane Crickhowell Powys NP8 1SE
Developer Agent Milsom Architects
The Orchard Studio Llangattock Lingoed Abergavenny NP7 8NS
Landowner / developer intentions
Description of Development
Conversion of hotel into 7 dwellings; demolition of part; and four new dwellings
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
Full 20.11.2013 20.11.2018 DC/2012/00620
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water – no objections, requests conditions in relation to the control of foul and surface water discharges
Access / Highways Comment
As it is a private residential development traffic movements are not expected to be significantly greater than those associated with the current use.
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.50 22 0 11 0 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
11 0 0 11 0 11 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
DC/2012/00620 - Former Abbey Hotel, Tintern
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Usk Ward Usk Site Address Cwrt Burrium
Monmouth Road Usk
LPA Reference SAH10(i) Grid Reference Easting 338423 Northing 201380 Market Type (Private, Public, RSL)
Estimated will deliver in the region of 20 units of which 35% will be affordable.
Owner Developer Agent Landowner / developer intentions
Description of Development
Allocated for residential development in LDP.
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
LDP Alloc – SAH10(i)
Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Welsh Water/Dwr Cymru - There are capacity restrictions at the Usk WwTW, dependant therefore on the scale and pace of growth within the settlement there will come a time where they will be objecting to development. Should a developer wish to progress a site prior to any future investment, they may pay for a feasibility study of the WwTW which would identify the level of upgrades required, and then enter into a Section 106 Agreement with Welsh Water to undertake the
required upgrades. Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other There remain significant flooding issues on site. Recent Meetings between the applicant and MCC Drainage team have confirmed this, and it was left with the applicant to consider options.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
0.66 30.3 0 13 7 0 0 Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
20 0 0 20 0 20 0 0
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH10 (i) - Cwrt Burrium, Usk
No Window
Site Proforma Monmouthshire County Council Joint Housing Land Availability
Base Date 01/04/2019
TAN(W) 1
Site Details:
Settlement Various Ward Site Address LPA Reference SAH11 Grid Reference Market Type (Private, Public, RSL)
Estimated remaining 12 sites will deliver in the region of 130 units of which 60% will be affordable
Owner Developer Agent Landowner / developer intentions
Description of Development
Sites allocated for development in named main villages in the LDP
Planning Status:
Planning Consent
Date Consent Expiry Date Application/Plan ref.
LDP Alloc – SAH11 Site Analysis:
Drainage /Sewerage Capacity (SW/FW)
Access / Highways Comment
Utilities / Services Comment
Constraints Comment
Capital Works Comment
JHLAS History
First recorded as forming part of the five year housing land supply = 2013/14
Other Land adjacent to village hall, Cross Ash - 10 dwellings (4 market, 6 affordable) Community consultation event
held. Landowner is no longer wishing to bring this land forward. Land adjacent to Cross Ash Garage - 5 dwellings (2 market, 3 affordable) Both Melin and Monmouthshire Housing Association have worked with the landowner. A planning application (DC/2017/01335) has been submitted but is yet to be determined. Land at Well Lane, Devauden - 15 dwellings (6 market, 9 affordable) (DM/2018/01741). This site was approved subject to a S106 at Planning Committee on Tuesday 2nd April, 2019. Land to west of Grosmont - 15 dwellings (6 market, 9 affordable). Access issues to the site remain and no progress has been made to date. No consultation and no mix agreed yet. Land to north of Little Mill - 15 dwellings (6 market, 9 affordable). Melin and MHA have approached the landowner. No community consultation as yet. Land to rear of village Hall, Llanddewi Rhydderch - 5 dwellings (2 market, 3 affordable) – No progress on site. Land to the north west of Llanellen - 15 dwellings (6 market, 9 affordable). Despite RSL interest, there has been no progress to date on this site. Land at Ton Road, Llangybi - 10 dwellings (4 market, 6 affordable). There has been no progress or community consultation as yet on this site. Land adjacent to Church Road, Llanishen - 5 dwellings. There has been no progress on this site to date. Land to west of Mathern - 15 dwellings RSLs are trying to progress this site, however there is no progress to report to date. Land to east of Shirenewton (south of minor road) - 5 dwellings. This site is being incorporated into the Clearview Court application, in order to provide a better access. Land adjacent to Werngifford, Pandy – Viability issues on this site. However, other alternatives are being assessed for which a community consultation has taken place.
Site Size / Capacity: Forecast Completions:
Total Area
Remaining Area
Ave Density(Dph)
2019/20 2020/21 2021/22 2022/23 2023/24
4.83 27 5 12 48 0 0
Categorisation:
Units capacity
Units Completed
Prior To Last Study
Units Completed Since last
Study
Units Remaining
@ 01st April 2019
1 2 3 4
130 0 0 130 0 65 0 65
SAH11(i)(a)
SAH11(i)(b)
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1750 Date
Rev
No.
Edge.J 4/5/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11(i)(a) - Land adjacent Village Hall, Cross AshLDP Allocation SAH11(i)(b) - Land adjacent Cross Ash Garage
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (ii) - Land at Well Lane Devauden
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (iv) - Land to west of Grosmont
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (v) - Land north of Little Mill
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1500 Date
Rev
No.
Edge.J 4/5/2016
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2016 Arolwg Ordnans 100023415© Crown copyright and database rights 2016 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11(vi) - Land to rear of village hall, Llanddewi Rhydderch
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (vii) - Land to north west of Llanellen
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2000 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (viii) - Land at Ton Road Llangybi
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1000 Date
Rev
No.
Edge.J 4/13/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11(ix)(b) - Land adjacent Church Road Llanishen
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (xi) - Land west of Mathern
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:1000 Date
Rev
No.
Edge.J 4/13/2017
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2017 Arolwg Ordnans 100023415© Crown copyright and database rights 2017 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11(xiv)(a) - Land east of Shirenewton (south of minor road)
Drawn byMonmouthshire County Council
Scale
File Pathname / Project / Drawing No.
1:2500 Date
Rev
No.
Edge.J 4/15/2015
Details JHLA Site Plan © Hawlfraint y Goron a hawliau cronfa ddata 2015 Arolwg Ordnans 100023415© Crown copyright and database rights 2015 Ordnance Survey 100023415
County HallUskNP15 1GAwww.monmouthshire.gov.uk/maps
LDP Allocation SAH11 (xvi) - Land adj Werngifford Pandy
Appendix 3
1
Miles, William
From: Mark Harris <[email protected]>Sent: 25 April 2019 08:23To: Miles, WilliamSubject: RE: Monmouthshire County Council 2018/19 Joint Housing land Availability StudyAttachments: Monmouth JHLAS comments HBF 2019.xlsx
Please find HBF comments attached, I have also received the following site specific comments from the developer. Mabey Bridge Ltd, Station Road, Chepstow The site will be dual branded but the RM application is for only 345 units. Due to the site only having one access and the split of the brands, there will be a delay in two outlets operating from the site which is reflected in the figures below. There is also a requirement for 30 Ah units so in total the site will only deliver 375.
In terms of delivery, I would state the following: 2019/20 – 0 2020/21 – 25 2021/22 – 70 2022/23 – 90 2023/24 – 90 2024/25 – 70
Happy to discuss as always. Mark Mark Harris Planning & Policy Advisor Wales
HOME BUILDERS FEDERATION m: 07770 752 884 e: [email protected] a: HBF Wales. PO Box 201. Barry. CF63 9FA
This e-mail is confidential, and may be legally privileged. If you are not the intended recipient, do not copy, use or disclose its content, but contact the sender immediately. Whilst we run anti-virus software on all Internet emails we are not liable for any loss or damage sustained as a result of software viruses. The recipient is advised to run their own anti-virus software. Registered in England and Wales | Registered office: 27 Broadwall, London, SE1 9PL Company Reg No. 276 4757 | Vat No. 882 6294
From: Miles, William <[email protected]> Sent: 16 April 2019 17:21 To: Mark Harris <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; Wiggam, Shirley <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; Keyse, Nicholas <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]> Cc: Hand, Mark <[email protected]>; Lewis, Rachel <[email protected]> Subject: Monmouthshire County Council 2018/19 Joint Housing land Availability Study
2
Dear All, Please find attached the proposed housing land supply for the 2018/19 Monmouthshire JHLA Study. The table shows that the land supply in the County stands at 4.2 years. The draft site schedule, together with proformas for all of the sites included in the study, are available to view via the Council’s website using the link below. https://www.monmouthshire.gov.uk/planning-policy/housing-land-supply/ There are four new sites on the schedule this year, Magistrates Court Abergavenny, Church Road Caldicot, Former White Hart Inn Caldicot, and Rockfield Farm (Phase 1) Magor/Undy. Two allocated village sites have also received planning approval since the last study, Land north of Llanfair Kilgeddin and Land to south east of Dingestow. These sites contribute a further 193 (*excludes Rockfield Farm phase 1 and both Village sites) units to the land supply. Total completions in the year to 01/04/2019 stand at 443 units, with 359 on large sites and 84 completions on small sites. As per the agreed timetable can you please return any comments that you have on the draft site schedule, site proformas and the proposed housing land supply to me by Friday 3rd May 2019. I have adjusted the timetable slightly to allow for a longer time due to the Easter break. The aim is for agreement on those sites where there is no dispute to be reached in advance of a Study Group meeting. If there are any areas of dispute which necessitate a Study Group Meeting can you please confirm your attendance. The Study Group meeting will be held on Thursday 9th May 2017 at 2.00pm at our Usk offices. Thank you Kind Regards William Miles Planning Policy Research Officer/ Swyddog Ymchwil Polisi Cynllunio Monmouthshire County Council/ Cyngor Sir Fynwy Phone / Ffon: 01633 644832 Email / Ebost: [email protected] Website / Gwefan: www.monmouthshire/planning-policy.gov.uk Planning Policy Privacy Notice / Hysbysiad Preifatrwydd Polisi Cynllunio: http://www.monmouthshire.gov.uk/your-privacy/your-council
Follow us on Twitter / Dilynwch ni ar Twitter: @MCCPlanning Mae’r neges e-bost yma a’r ffeiliau a anfonir gyda hi yn gyfrinachol ac fe’i bwriedir ar gyfer yr unigolyn neu gorff y’u cyfeiriwyd atynt yn unig. Gall gynnwys gwybodaeth freintiedig a chyfrinachol ac os nad chi yw’r derbynnydd bwriadedig, rhaid i chi beidio copïo, dosbarthu neu gymryd unrhyw gamau yn seiliedig arni. Os cawsoch y neges e-bost yma drwy gamgymeriad hysbyswch ni cyn gynted ag sydd modd os gwelwch yn dda drwy ffonio 01633 644644. Cafodd y neges e-bost yma sgan firws Microsoft Exchange Online Protection. This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. It may contain privileged and confidential information and if you are not the intended
3
recipient, you must not copy, distribute or take any action in reliance on it. If you have received this email in error please notify us as soon as possible by telephone on 01633 644644. This email has been virus scanned by Microsoft Exchange Online Protection. Mae’r Cyngor yn croesawu gohebiaeth yn Gymraeg, Saesneg neu yn y ddwy iaith. Byddwn yn cyfathrebu â chi yn ôl eich dewis. Ni fydd gohebu yn Gymraeg yn arwain at oedi. The Council welcomes correspondence in English or Welsh or both, and will respond to you according to your preference. Corresponding in Welsh will not lead to delay.
HBF Comments
Monmouth JHLAS 2019
LPA Ref Site Address Comments
DC/2009/00910 Osborn International Lower Church Street
Only 4 started since last study and historically slow before that so how is 30 units a year justified?
DC/2016/00953(O/L) Hill Farm Pwllmeyric If S106 taken longer than 1 year move to Cat3.
DC/2012/00620 The Abbey Hotel Tintern Ltd Any contact with developer ?
SAH10(i) Cwrt Burrium Monmouth Road
If know flood issues move to Cat3/4.
SAH11 Various sites
Based on last few years delivery is it realistic to retain proposed levels of delivery, what will change over next few years?
Redrow Homes South Wales – 01/05/19 – Comments to Monmouthshire JHLAS site schedule
NB. Comments made below in relation to annual unit completions on sites are based on
open market and affordable housing units combined.
Address Comments
Fairfield Mabey - The delivery rates appear high and higher than the rates set by Barratt / David Wilson last year. Happy to follow what annual completions are forecasted by Barratt / David Wilson.
Land at Grove Farm - Unsure of RM status. Reference on proforma sheet is not recognised via the online search. On basis that RM is not yet in place and then likely discharge of conditions then suggest pushing back 1 year. All would remain in the 5 yr supply.
- Are the 9 units really remaining or is it just the case that the detailed layout shows less units that the outline envisaged?
Rockfield Farm / Vinegar Hill
- The delivery rates appear high and higher than previously suggested. Is Bellway on Phase 1 and another developer for phase 2?
- Considering this location and with site two outlets 70 per annum would be at the upper end of delivery. Another developer and competition from land at Vinegar Hill would also be a factor.
- Suggest that the delivery rates for 3no. sites in Magor/Undy do not exceed 105 completions per annum and the build up rates are reduced accordingly. This would be comparable with previous study years. Suggested as below:
- Please note that the total units figures (yellow above should
be correct) on the issued schedule does not total correctly.
Vinegar Hill - Based on a planning application being submitted in August this year then a full year of housing delivery in 2020/21 is unlikely. For example, 6 months for planning, signing of S106, site purchase, conditions and then start of site is likely to be Spring/Summer 2020. Likely to be no more than 6 months of completions in 2020/21. This is reflected in the suggested figures above.
Tudor Road, Wyesham
- Is the foul capacity issue in Monmouth a physical constraint that will prevent site completions within the 5years?
Land to the south west of Penallt
- Proforma says, and did last year, that this would be a follow on site for Brideoak Homes after they completed at Shirenewton. They have completed at Shirenewton. Any update?
- The site has no mains drainage, is only for 4no. private units so is it viable to come forward following a grant of planning permission that was two and a half year ago?
Crick Road - The site proforma says Melin forecast a site start in February 2020 and 1st legal completions from August 2020. Once up a
Redrow Homes South Wales – 01/05/19 – Comments to Monmouthshire JHLAS site schedule
running 67 completions a year. Suggested changes to reflect Melin’s comments:
Hill Farm, Pwllmeyric
- As per TAN1 guidance the S106 was not signed within 12 months of resolution to grant. It should not be included in the 5yr supply.
Green Farm - What are the intentions of the landowner? Has it been marketed? Planning permission has been in place for 2 years and no signs of it coming forward so should be moved out of category 2.
Old Shipyard - Whilst planning permission was extant at the base date it has now lapsed. The ‘register interest’ tab on the Enzo Homes website is not sufficient to include in category 2. A land deal could not be done with Pobl with limited affordable housing provision. There does not appear to be sign of a new planning application. A new application would need to be be subject to SAB approval requirements and a fresh viability review. Is the site viable, and evidence of this available, to stay in category 2? If not it should be moved from category 2.
Former Abbey Hotel - Planning permission lapsed prior to the base date and not an allocated site. The site does not qualify for inclusion.
Cwrt Burrium - The site proforma identifies significant flooding issues. DCWW appear to be objecting unless a feasibility study is undertaken at the cost of the landowner to demonstrate if upgrades are possible to address current concerns. This study will be costly and coupled with the flooding issues it is considered unlikely that the site would come forward for housing completions within the next five years, noting that it has been included since 2013/14 with no planning progression.
1
Miles, William
Subject: FW: Housing trajectory
From: Hand, Mark <[email protected]> Sent: 25 April 2019 13:59 To: Miles, William <[email protected]> Subject: FW: Housing trajectory
Mark Hand Mark Hand MRTPI Head of Planning, Housing and Place-Shaping / Pennaeth Cynllunio, Tai a Llunio Lle Monmouthshire County Council / Cyngor Sir Fynwy ---------------------------------------------------------------------------- : 07773 478579 : [email protected] : www.monmouthshire.gov.uk
Follow us on Twitter / dilynwch ni ar Twitter: @MCCPlanning @MCC_Careline @MonLettings
From: Scott Rooks MRICS <[email protected]> Sent: 25 April 2019 13:58 To: Hand, Mark <[email protected]> Subject: RE: Housing trajectory Hi Mark, That’s fine. Regards Scott
From: Hand, Mark <[email protected]> Sent: 25 April 2019 13:50 To: Scott Rooks MRICS <[email protected]> Subject: RE: Housing trajectory Hi Scott, For Grove Farm we have: 19/20 – 0 units 20/21 – 10 units 21/22 – 35 units 22/23 – 35 units 23/24 – 26 units = 106 as per the RM Mark
2
Mark Hand Mark Hand MRTPI Head of Planning, Housing and Place-Shaping / Pennaeth Cynllunio, Tai a Llunio Lle Monmouthshire County Council / Cyngor Sir Fynwy ---------------------------------------------------------------------------- : 07773 478579 : [email protected] : www.monmouthshire.gov.uk
Follow us on Twitter / dilynwch ni ar Twitter: @MCCPlanning @MCC_Careline @MonLettings
From: Scott Rooks MRICS <[email protected]> Sent: 25 April 2019 13:35 To: Hand, Mark <[email protected]> Subject: RE: Housing trajectory Hi Mark, We won’t have any completions by March 2020 on Crick Road, therefore our predictions are as follows: 20/21 – 29 units 21/22 – 58 units 22/23 – 58 units 23/24 – 58 units 24/25 – 58 units 25/26 – 30 units What have you got in for Grove Farm? Regards Scott
From: Hand, Mark <[email protected]> Sent: 25 April 2019 13:05 To: Scott Rooks MRICS <[email protected]> Subject: Housing trajectory Sorry Scott, me again. I was just reviewing the trajectory we have put forward for Crick Road and wanted a sanity check as it seems pretty ambitious given that you have only got outline pp at present. This is bound to be challenged by other developers present so better to be clear now, and agree a different trajectory if needed. I’d noted from our conversation: Reserved Matters submitted June 2019 (are you on track for this), on site January 2020 (achievable), then 23 completions by 31st March 2020 (sounds tight)? The 67 per annum thereafter. You’d said the scheme needs to be built out at pace within a 5 year programme. (This total adds up to 291 which is what the outline pp is for: I know the RM is likely to be nearer 275 but until that is submitted we need to stick with the 291 total). Let me know if this needs any changes. Thanks, Mark
3
Mark Hand
Mark Hand MRTPI Head of Planning, Housing and Place-Shaping / Pennaeth Cynllunio, Tai a Llunio Lle Monmouthshire County Council / Cyngor Sir Fynwy ---------------------------------------------------------------------------- : 07773 478579 : [email protected] : www.monmouthshire.gov.uk
Follow us on Twitter / dilynwch ni ar Twitter: @MCCPlanning @MCC_Careline @MonLettings
Mae’r neges e-bost yma a’r ffeiliau a anfonir gyda hi yn gyfrinachol ac fe’i bwriedir ar gyfer yr unigolyn neu gorff y’u cyfeiriwyd atynt yn unig. Gall gynnwys gwybodaeth freintiedig a chyfrinachol ac os nad chi yw’r derbynnydd bwriadedig, rhaid i chi beidio copïo, dosbarthu neu gymryd unrhyw gamau yn seiliedig arni. Os cawsoch y neges e-bost yma drwy gamgymeriad hysbyswch ni cyn gynted ag sydd modd os gwelwch yn dda drwy ffonio 01633 644644. Cafodd y neges e-bost yma sgan firws Microsoft Exchange Online Protection. This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. It may contain privileged and confidential information and if you are not the intended recipient, you must not copy, distribute or take any action in reliance on it. If you have received this email in error please notify us as soon as possible by telephone on 01633 644644. This email has been virus scanned by Microsoft Exchange Online Protection. Mae’r Cyngor yn croesawu gohebiaeth yn Gymraeg, Saesneg neu yn y ddwy iaith. Byddwn yn cyfathrebu â chi yn ôl eich dewis. Ni fydd gohebu yn Gymraeg yn arwain at oedi. The Council welcomes correspondence in English or Welsh or both, and will respond to you according to your preference. Corresponding in Welsh will not lead to delay.
Scott Rooks MRICS Commercial Director 07824 772 303 candlestonhomes.co.uk Candleston Homes (Part of the Melin Homes Group)- Registered office Ty'r Efail, Lower Mill Field, Pontypool, Torfaen NP4 0XJ. ------------------------------------------- The information in this email is confidential and is intended solely for the addressee. Access by anyone else is unauthorised. If you are not the intended recipient, any disclosure, copying, distribution, or any action taken in reliance on it, is prohibited and unlawful. Opinions, conclusions and other information in this message that do not relate to our business shall be understood as neither given nor endorsed by it. We may for operational or business reasons monitor replies to this email. ------------------------------------------- Save resources: think before you print. Mae’r neges e-bost yma a’r ffeiliau a anfonir gyda hi yn gyfrinachol ac fe’i bwriedir ar gyfer yr unigolyn neu gorff y’u cyfeiriwyd atynt yn unig. Gall gynnwys gwybodaeth freintiedig a chyfrinachol ac os nad chi yw’r derbynnydd bwriadedig, rhaid i chi beidio copïo, dosbarthu neu gymryd unrhyw gamau yn seiliedig arni. Os cawsoch y neges e-bost yma drwy gamgymeriad hysbyswch ni cyn gynted ag sydd modd os gwelwch yn dda drwy ffonio 01633 644644.
4
Cafodd y neges e-bost yma sgan firws Microsoft Exchange Online Protection. This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. It may contain privileged and confidential information and if you are not the intended recipient, you must not copy, distribute or take any action in reliance on it. If you have received this email in error please notify us as soon as possible by telephone on 01633 644644. This email has been virus scanned by Microsoft Exchange Online Protection. Mae’r Cyngor yn croesawu gohebiaeth yn Gymraeg, Saesneg neu yn y ddwy iaith. Byddwn yn cyfathrebu â chi yn ôl eich dewis. Ni fydd gohebu yn Gymraeg yn arwain at oedi. The Council welcomes correspondence in English or Welsh or both, and will respond to you according to your preference. Corresponding in Welsh will not lead to delay.
1
Miles, William
From: Michael Rees <[email protected]>Sent: 03 May 2019 14:18To: Miles, WilliamSubject: Monmouthshire JHLAS Comments
Importance: High
Dear William, Further to your request for comments on the draft schedule, please see below our comments / queries on behalf of our clients the Llanarth Estate. For background, our clients are a significant land and property owner within the County and are in the process of reviewing their properties and assets with a view to assisting the Authority in meeting their existing and future housing requirements (at varying scales). Their particular focus is meeting needs beyond the M4 corridor in the central / northern parts of the Authority, particularly associated with the rural economy (including the provision of start-up units and encouraging younger families and workers). They are currently looking at sustainable / low carbon, affordable and innovative / modern methods of construction to assist in meeting future housing needs. Our comments / queries on the schedule are as follows:
1. East of Church Road, Caldicot – from the information provided it is not clear whether there is a timeframe for s106, marketing, legal work with preferred developer, preparation of a detailed scheme, determination and 4/6 lead in to first completions from commencement. It could take well over two years until 1st completions are made for these elements, whereas the forecast relies upon 30 completions within 22 months (so a start on site during the summer of 2020).
2. Fairfield Mabey – we wanted clarification that this was categorised correctly, particularly for year 1 as there is often a build up associated with such sites and infrastructure provision / remediation? Is there a timeframe for how long remediation will take?
3. Land at Grove Farm – it seems that the schedule should be pushed back 1 year - the developer indicates that first completions will be July 2020 (so they ought to be within 2020/21 rather than 2019/20)
4. Land West of Rockfield Road – has the site been marketed? Is there a timeframe for RM’s? 5. Tudor Road, Wyesham – please can the Council confirm what work is being undertaken to remove the drainage issue? 6. Crick Road, Portskewett – There doesn’t appear to be a s106 signed or RM submitted, the comments indicate that first
completions will be August 2020 (year 2 of the 5 year period) therefore the schedule should be pushed back 1 year. 7. Hill Farm – given the viability issues, should the site be recategorized as 4 until either the s106 is signed (given the
length of time this has been awaited in line with TAN 1) or there is a confirmed RSL on board? 8. Land at Chepstow Road – is there a timeframe for s106 to be signed, marketing and RM’s to support first completions
within 20 months? 9. Green Farm – is there progress on the timeframe? 10. Old Shipyard – can the timeframe be confirmed as the permission seems to have lapsed? 11. Former Abbey Hotel – the permission seems to have lapsed? 12. Cwrt Burrium – given the constraints and that it has been within the supply for in excess of five years with no signs of
progress, should the site be re-categorised as 4? 13. NW of Llanellen – given that there is no progress there doesn’t seem to be justification for its classification.
I look forward to confirmation of receipt and whether the group meeting will proceed. Kind regards Michael Michael Rees MRTPI Director t: 02920 349 737 m: 07788 277 150
2
website: lrmplanning.com twitter: @lrmplanning Correspondence Address: 22 Cathedral Road, Cardiff, CF11 9LJ Registered Address: Nyewood Court, Brookers Road, Billingshurst, RH14 9RZ
DISCLAIMER: The contents of this e-mail and of any attachments, are confidential and may be privileged. If you have received this e-mail in error you should not disclose, disseminate, distribute or copy this communication or it's substance. Please inform the sender and delete it from your mailbox and/or any other storage device. LRM Planning Limited does not accept liability for any statements made which are the sender's own and not expressly made on behalf of LRM Planning Limited or one of its agents. Please note that neither LRM Planning Limited nor any of its agents accept any responsibility for viruses that may be contained in this e-mail or its attachments and it is your responsibility to scan the e-mail and attachments (if any).
1
Miles, William
From: Norman Ryan <[email protected]>Sent: 29 April 2019 16:28To: Miles, WilliamSubject: RE: Monmouthshire County Council 2018/19 Joint Housing land Availability Study
Dear William, I refer to the below JHLAS consultation and would like to thank you for allowing Welsh Water the opportunity to respond. I am pleased to note that the most up-to-date information with regard to Welsh Water’s planning application/LDP representations on the specific sites has been considered, and is included within the site proformas. I would however point out that for ‘Land to East of Church Road’, we have now removed our objection following completion of the hydraulic modelling assessment and identification of connection options. I would also advise that for the settlement of Monmouth, aside from what already has extant planning consent, any further development would require reinforcement works at the Wastewater Treatment Works (WwTW). There is no scheme proposed within our current Capital Investment Programme (AMP6 – 2015-2020) but a scheme will be considered for inclusion with AMP7 (2020-2025). If you require any further comments on any specific sites then please let me know. Kind regards,
Ryan Norman Forward Plans Officer | Developer Services | Dwr Cymru Welsh Water Linea | Cardiff | CF3 0LT | T: 0800 917 2652| www.dwrcymru.com
We will respond to your email as soon as possible but you should allow up to 10 working days to receive a response. For most of the services we offer we set out the timescales that we work to on our Developer Services section of our website. Just follow this link http://www.dwrcymru.com/en/Developer-Services.aspx and select the service you require where you will find more information and guidance notes which should assist you. If you cannot find the information you are looking for then please call us on 0800 917 2652 as we can normally deal with any questions you have during the call. If we’ve gone the extra mile to provide you with excellent service, let us know. You can nominate an individual or team for a Diolch award through our website.
From: Miles, William [mailto:[email protected]] Sent: 16 April 2019 17:21 To: 'Mark Harris ([email protected])' <[email protected]>; '[email protected]' <[email protected]>; Forward Plans <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; Wiggam, Shirley <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>; Keyse, Nicholas <[email protected]>; '[email protected]' <[email protected]>; '[email protected]' <[email protected]>
2
Cc: Hand, Mark <[email protected]>; Lewis, Rachel <[email protected]> Subject: Monmouthshire County Council 2018/19 Joint Housing land Availability Study ******** External Mail ******** Dear All, Please find attached the proposed housing land supply for the 2018/19 Monmouthshire JHLA Study. The table shows that the land supply in the County stands at 4.2 years. The draft site schedule, together with proformas for all of the sites included in the study, are available to view via the Council’s website using the link below. https://www.monmouthshire.gov.uk/planning-policy/housing-land-supply/ There are four new sites on the schedule this year, Magistrates Court Abergavenny, Church Road Caldicot, Former White Hart Inn Caldicot, and Rockfield Farm (Phase 1) Magor/Undy. Two allocated village sites have also received planning approval since the last study, Land north of Llanfair Kilgeddin and Land to south east of Dingestow. These sites contribute a further 193 (*excludes Rockfield Farm phase 1 and both Village sites) units to the land supply. Total completions in the year to 01/04/2019 stand at 443 units, with 359 on large sites and 84 completions on small sites. As per the agreed timetable can you please return any comments that you have on the draft site schedule, site proformas and the proposed housing land supply to me by Friday 3rd May 2019. I have adjusted the timetable slightly to allow for a longer time due to the Easter break. The aim is for agreement on those sites where there is no dispute to be reached in advance of a Study Group meeting. If there are any areas of dispute which necessitate a Study Group Meeting can you please confirm your attendance. The Study Group meeting will be held on Thursday 9th May 2017 at 2.00pm at our Usk offices. Thank you Kind Regards William Miles Planning Policy Research Officer/ Swyddog Ymchwil Polisi Cynllunio Monmouthshire County Council/ Cyngor Sir Fynwy Phone / Ffon: 01633 644832 Email / Ebost: [email protected] Website / Gwefan: www.monmouthshire/planning-policy.gov.uk Planning Policy Privacy Notice / Hysbysiad Preifatrwydd Polisi Cynllunio: http://www.monmouthshire.gov.uk/your-privacy/your-council
Follow us on Twitter / Dilynwch ni ar Twitter: @MCCPlanning Mae’r neges e-bost yma a’r ffeiliau a anfonir gyda hi yn gyfrinachol ac fe’i bwriedir ar gyfer yr unigolyn neu gorff y’u cyfeiriwyd atynt yn unig. Gall gynnwys gwybodaeth freintiedig a chyfrinachol ac os nad chi yw’r derbynnydd bwriadedig, rhaid i chi beidio copïo, dosbarthu neu gymryd unrhyw gamau yn seiliedig
3
arni. Os cawsoch y neges e-bost yma drwy gamgymeriad hysbyswch ni cyn gynted ag sydd modd os gwelwch yn dda drwy ffonio 01633 644644. Cafodd y neges e-bost yma sgan firws Microsoft Exchange Online Protection. This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. It may contain privileged and confidential information and if you are not the intended recipient, you must not copy, distribute or take any action in reliance on it. If you have received this email in error please notify us as soon as possible by telephone on 01633 644644. This email has been virus scanned by Microsoft Exchange Online Protection. Mae’r Cyngor yn croesawu gohebiaeth yn Gymraeg, Saesneg neu yn y ddwy iaith. Byddwn yn cyfathrebu â chi yn ôl eich dewis. Ni fydd gohebu yn Gymraeg yn arwain at oedi. The Council welcomes correspondence in English or Welsh or both, and will respond to you according to your preference. Corresponding in Welsh will not lead to delay. _______________________________________________________ Dwr Cymru Welsh Water is firmly committed to water conservation and promoting water efficiency. Please log on to our website www.dwrcymru.com/waterefficiency to find out how you can become water wise. Mae Dwr Cymru Welsh Water wedi ymrwymo i warchod adnoddau dwr a hyrwyddo defnydd dwr effeithiol. Mae cyngor i' ch helpu i ddefnyddio dwr yn ddoeth yn www.dwrcymru.com/waterefficiency ________________________________________________________ ********************************************************************** This email and any file attached is confidential. If you are not a named recipient or believe you may have received this email in error please delete from your system and promptly inform the sender. Dwr Cymru Cyf (trading as Welsh Water) is a company registered in England and Wales, number 02366777, registered office Pentwyn Road, Nelson, Treharris, Mid Glamorgan CF46 6LY. Mae’r neges e-bost yma ac unrhyw ffeil sydd ynghlwm wrthi'n gyfrinachol. Os nad chi yw’r derbynnydd a enwir, neu os ydych chi’n credu eich bod wedi derbyn y neges yma ar gam, dylech ei dileu o’ch system ar unwaith a hysbysu’r anfonwr. Cwmni sydd wedi ei gofrestru yng Nghymru yw Dŵr Cymru Cyf (yn masnachu fel Dŵr Cymru), ei rif cofrestredig yw 02366777, ac mae ei swyddfa gofrestredig yn Heol Pentwyn, Nelson, Treharris, Morgannwg Ganol CF46 6LY. **********************************************************************
Appendix 4
1 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
Monmouthshire County Council
JHLA Study Group Meeting
9th May 2019
Present:
Mark Hand MCC Planning Emyr Davies Redrow Homes
Rachel Lewis MCC Planning Nigel Lush Bovis Homes
William Miles MCC Planning Scott Rooks Candlestone
Craig O’Connor MCC Planning Michael Rees LRM Planning
Shirley Wiggam MCC Housing Karen Tarbox MHA
Louise Corbett MCC Housing Katie Knill MHA
Nick Keyse MCC Estates Michael Gooch Boyer Planning
A Study Group Meeting was held on Thursday 9th May 2019. The consultation on the draft site
schedule and proformas ran from 15th April 2018 until 3rd May 2019 with written comments
in response to the consultation received from a number of members of the Study Group.
The draft Site Schedule formed the basis of the agenda for the meeting, only those sites which
the Study Group had commented on were discussed, all other sites are agreed as per the draft
Schedule.
1. Caldicot
DM/2018/00880 (O/L) – Church Road – LRM Planning enquired as to the timescales regarding
a Section 106 Agreement, marketing, legal work with the preferred developer.
Monmouthshire County Council confirmed that a Section 106 Agreement had been signed
and that there is now a developer on board, who provided the trajectory published in the
draft schedule. Monmouthshire County Council added that a reserved matters application
was expected in August 2019. LRM Planning confirmed that they were happy their query had
been answered. The Study Group agreed to the proposed build rate as per the draft site
schedule
2. Chepstow
DC/2009/00910 – Osborn International – HBF provided comments prior to the Study Group
meeting enquiring how 30 completions per annum were justified on a site which has been
historically slow and where only 4 units had been started since the last study. Monmouthshire
County Council explained to those present at the Study Group meeting that this was based
on the fact that there had been 35 completions since the last study on a site that is largely
comprised of apartments. The Study Group agreed to the proposed build rate as per the draft
site schedule.
2 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
DC/2014/01290 (O/L) – Mon LDP Fairfield Mabey – Redrow and LRM Planning both
submitted comments prior to the Study Group meeting. Redrow suggested that delivery rates
appeared high, but also suggested that they were happy to follow forecasts from the
developer; Barratt David Wilson Homes. LRM Planning also wanted an explanation of the
trajectory in the draft site schedule. Monmouthshire County Council explained that the
trajectory was based on 450 units under the outline planning permission as opposed to the
reserved matters application as this was not determined by 1st April 2019. Monmouthshire
County Council agreed a revised trajectory prior to the Study Group meeting with Barratt
David Wilson Homes which was published with the list of comments received for the Study
Group to inspect. The Study Group agreed to the trajectory put forward by Barratt David
Wilson Homes.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 45, Yr3 – 70, Yr 4 – 105, Yr5 – 105, 125 outside the 5 year supply.
3. Llanfoist
DC/2016/00880 – Grove Farm – Redrow submitted comments suggesting that as the
reserved matters application had not yet been determined, that the schedule published in
the draft site schedule be pushed back by a year. Redrow also raised concerns about the 9
units in category 4 and outside the 5 year supply. LRM Planning also suggested the schedule
be pushed back a year. Monmouthshire County Council clarified that the 9 units in category
4, outside the 5 years, accounted for the difference between the outline permission and the
reserved matters application yet to be determined. A revised trajectory was agreed between
Monmouthshire County Council and Candlestone prior to the Study Group meeting. The
revised schedule was published with the list of comments received for the Study Group to
inspect. The Study Group agreed to the revised schedule which had been pushed back a year,
and Candlestone confirmed they were happy with the revised trajectory.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 10, Yr3 – 35, Yr 4 – 35, Yr5 – 26, 9 outside the 5 year supply.
4. Magor/Undy
DC/2016/00883 (O/L) & DM/2018/01606 (RM) – Rockfield Farm – Redrow submitted
comments prior to the Study Group meeting raising concerns that delivery rates appeared
high, and enquiring as to the developer for phase 1 and phase 2 of development on this site.
Redrow comments submitted prior to the Study Group meeting, also raised concerns about
the delivery of 70 units per annum across the whole site. Redrow were concerned that there
would also be competition from the site at Vinegar Hill. Redrow’s comments suggested that
delivery rates across the 3 sites in Magor/Undy did not exceed 105 units per annum.
Monmouthshire County Council confirmed that figures for both phase 1 and phase 2 were
provided by Bellway and confirmed that they were the developer for phase 1. Equally
Monmouthshire County Council confirmed that phase 2 was going to be marketed in the
3 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
autumn of 2020. Upon clarification from Monmouthshire County Council the Study Group
agreed to the proposed build rates as per the draft site schedule for both parts of the
Rockfield Farm site on the schedule.
MON LDP – Land at Vinegar Hill – Redrow submitted comments prior to the Study Group
meeting, suggesting that the trajectory submitted in the draft site schedule may be
unrealistic. Monmouthshire County Council agreed a revised trajectory with Bovis prior to the
Study Group meeting which was published with the list of comments received for the Study
Group to inspect. The Study Group agreed to the revised schedule which had also been agreed
with Bovis who were represented at the meeting.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 25, Yr3 – 50, Yr 4 – 50, Yr5 – 50, 50 outside the 5 year supply.
5. Monmouth
DC/2017/00539 (O/L) – Land West of Rockfield Road – LRM Planning submitted comments
prior to the Study Group meeting enquiring as to whether the site had been marketed and
timeframes for reserved matters applications. Monmouthshire County Council confirmed
that there were 12 months in which to submit a reserved matters application from outline
approval in February 2019 and then 12 months from reserved matters approval to start on
site. LRM were happy that their query was answered and the Study Group agreed to the
proposed build rate as per the draft site schedule.
MON LDP – Tudor Road, Wyesham – Redrow enquired as to whether the foul capacity issue
in Monmouth would prevent site completion within the 5 year land supply. LRM Planning also
asked for clarification on this issue. Monmouthshire County Council confirmed that Welsh
Water confirmed that their current Capital Investment Programme does not account for
reinforcement works at the Wastewater Treatment Works. Monmouthshire County Council
revised the trajectory prior to the Study Group meeting given this information and published
the revised trajectory with the list of comments received for the Study Group to inspect. The
Study Group agreed with the revised trajectory put forward by Monmouthshire County
Council, which pushes delivery back by 2 years.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 0, Yr3 – 0, Yr 4 – 15, Yr5 – 20, 0 outside the 5 year supply.
MON LDP – Wonastow Road – Bovis confirmed at the Study Group meeting that this site was
running behind the Vinegar Hill site in Magor. They put forward a revised trajectory at the
meeting, which was agreed by members of the Study Group.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 15, Yr3 – 45, Yr 4 – 50, Yr5 – 0, 0 outside the 5 year supply.
4 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
6. Penallt
DC/2015/00606 – Land to the South West – Redrow submitted comments prior to the Study
Group meeting requesting any updates for the site, as the developer (Brideoak Homes) had
now finished the development in Shirenewton. Redrow further questioned the deliverability
of the site at the Study Group meeting. Monmouthshire County Council confirmed that the
developer intends to start on site this September. The Study Group agreed to the proposed
build rate as per the draft site schedule.
7. Portskewett
DM/2018/00696 (O/L) – Crick Road – Redrow submitted comments prior to the Study Group
meeting suggesting that the trajectory follows comments from Melin on the proforma more
closely. LRM Planning query the signing of a Section 106 Agreement and timescales for a
reserved matters application, and suggest that, based on comments on the site proforma that
the schedule be pushed back by a year. Monmouthshire County Council and Candlestone
confirm that a Section 106 Agreement had been signed and that a reserved matters
application was expected in June 2019. Candlestone submitted a revised trajectory prior to
the Study Group meeting, pushing the schedule back by 1 year and marginally lowering
completion rates. The revised trajectory submitted by Candlestone Homes was published
with the list of comments received for the Study Group to inspect The Study Group agreed to
the revised schedule as put forward by Candlestone.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 29, Yr3 – 58, Yr 4 – 58, Yr5 – 58, 88 outside the 5 year supply.
8. Pwllmeyric
DC/2016/00953 (O/L) – Hill Farm – HBF submitted comments prior to the Study Group
meeting enquiring as to the inclusion of this site in the trajectory due to the lack of a Section
106 Agreement, suggesting the 17 units should be moved to category 3. Redrow raised similar
concerns in comments submitted prior to the Study Group, suggesting the site should not be
included in the trajectory. LRM Planning, in comments provided prior to the Study Group
meeting suggested that the units be moved to category 4 until a Section 106 Agreement had
been signed. Monmouthshire County Council clarified that the site remained on the schedule
as the site had been allocated for housing in the adopted Local Development Plan as a Main
Village Site. Redrow and LRM Planning were both happy that this answered their query and
the Study Group agreed to the proposed build rate as per the draft site schedule.
9. Raglan
DM/2018/00769 (O/L) – Chepstow Road – LRM Planning enquired in comments submitted
prior to the Study Group meeting, about timescales for the signing of a Section 106
Agreement, marketing of the site and reserved matters applications. Monmouthshire County
Council confirmed that a Section 106 Agreement had been signed in December 2018 and that
work on a reserved matters application was ongoing. The Study Group agreed to the proposed
build rate as per the draft site schedule but to continue to monitor progress going forward.
5 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
10. Rogiet
DC/2015/01326 – Green Farm – Redrow enquired as to the intentions of the landowner and
an update on deliverability. LRM Planning enquire as to any progress on the timeframe.
Monmouthshire County Council provided an update on progress and the landowner
intentions. The Study Group agreed to the proposed build rate as per the draft site schedule.
11. Sudbrook
DC/2011/00607 – Old Shipyard – Redrow submitted comments prior to the Study Group
meeting querying any progress on site suggesting that planning permission had now lapsed.
LRM Planning submitted comments prior to the Study Group suggesting that planning
permission had now lapsed. Monmouthshire County Council confirmed that a reserved
matters application had been submitted in October 2018 and was pending a decision. The
Study Group agreed to the proposed build rate as per the draft site schedule but to continue
to monitor progress going forward.
12. Tintern
DC/2012/00620 – Former Abbey Hotel – Redrow and LRM Planning raised queries over the
inclusion of this particular site suggesting that planning permission had lapsed prior to the
base date of the study. Monmouthshire County Council confirmed that planning permission
had been implemented and several conditions had been discharged. The Study Group agreed
to the proposed build rate as per the draft site schedule.
13. Usk
MON LDP – Cwrt Burrium – HBF submitted comments prior to the Study Group meeting
suggesting that due to the flood issues the 20 units should be moved to category 3 or 4.
Redrow submitted comments prior to the Study Group meeting querying the flooding issues
and questioning whether the site would come forward, due to Welsh Water objections unless
the landowner carried out studies at their own expense. Redrow were also concerned that
the site had been in the 5 year supply since 2013/14 with no progress. LRM Planning also
submitted comments prior to the Study Group meeting relating to the length of time that the
site had been in the 5 year supply and suggested re-categorising it as category 4.
Monmouthshire County Council confirmed that they would like to leave the site in the 5 year
supply and that there were no comments from Welsh Water regarding this site when
consulted and that Welsh Water had removed their original objection. The Study Group
agreed to the proposed build rate as per the draft site schedule but to continue to monitor
progress going forward.
6 Monmouthshire County Council JHLAs Study Group Meeting Thursday 9th May 2019
14. Village Sites
HBF submitted comments prior to the Study Group meeting enquiring as to whether
proposed levels of delivery were realistic, based on delivery over the past few years. LRM
Planning submitted comments prior to the Study Group meeting concerning the Village Site
in Llanellen, questioning the categorisation based on the lack of progress. Monmouthshire
County Council explained the different approach taken with regards to Village Sites in the
draft schedule this year. Monmouthshire County Council confirm that each respective site has
been given a trajectory as opposed to referring to the sites as a whole in years gone by.
Monmouthshire County Council confirm that any sites which are unlikely to come forward
have been placed in category 4, whilst other sites likely to come forward in the 5 year supply
have their own trajectory within category 2. The Study Group approved of this approach but
queried a couple of sites. Monmouthshire Housing Association queried the site at Dingestow,
which Monmouthshire County Council confirmed was further up the schedule as it now had
planning permission. Monmouthshire Housing Association also queried the two sites in Cross
Ash and whether there had been any progress. Monmouthshire County Council confirmed
that there had been no progress on either of the sites and hence their categorization outside
of the 5 year supply in Category 4. Monmouthshire County Council confirmed that letters had
gone out to respective landowners that week, asking for any updates and stating the position
of Monmouthshire County Council in deallocating any of the respective Village Sites where
no progress had been made during the adopted Local Development Plan period. The Study
Group agreed to the proposed build rate as per the draft site schedule but to continue to
monitor progress on all Village Sites going forward.
15. Post Study Group Meeting
Monmouthshire County Council confirmed that a Draft Statement of Common Ground with
any revisions and a revised schedule with all agreed changes, as well as revised proformas
would be circulated to the group for consultation in the week following the Study Group
meeting.
Appendix 5
Appendix 5
Agreed Changes / Amendments
The following amendments have been made to the schedule in light of discussion at
the Study Group Meeting.
1. DC/2014/01290 (O/L) – Mon LDP Fairfield Mabey, Chepstow – Members of the Study Group submitted comments prior to the Study Group meeting suggesting that build rates appeared to be high, but that they were happy to agree with what the developer had put forward. Since the publication of the draft schedule, Barratt
David Wilson Homes, developers of the site, submitted a proposed build trajectory for the site, prior to the Study Group meeting. This revised trajectory was published with a list of comments received and distributed at the Group meeting for discussion. It was agreed at the Study Group meeting to amend the schedule to include these. Agreed revised trajectory: Yr1 – 0, Yr2 – 45, Yr3 – 70, Yr4 – 105, Yr5 – 105, 125 outside the 5 year supply.
2. DC/2016/00880 (O/L) – Grove Farm, Llanfoist – Members of the Study Group
submitted comments prior to the Study Group meeting concerning the fact that due to the lack of a reserved matters application, that build rates seemed high and queried the 9 units outside the 5 year supply. Monmouthshire County Council clarified that the 9 units in category 4, outside the 5 years, accounted for the difference between the outline permission and the reserved matters application yet to be determined. Since the publication of the draft schedule,
Candlestone Homes, developers of the site, submitted a proposed build trajectory for the site, prior to the Study Group meeting. This revised trajectory was published with a list of comments received and distributed at the Study Group meeting for discussion. It was agreed at the Study Group meeting to amend the schedule to include these. Agreed revised trajectory: Yr1 – 0, Yr2 – 10, Yr3 – 35, Yr4 – 35, Yr5 – 26, 9 outside the 5 year supply.
3. MON LDP – Land at Vinegar Hill, Undy – Members of the Study Group submitted comments prior to the Study Group meeting concerning whether the build rates published in the draft site schedule were realistic. Since the publication of the draft schedule, Bovis Homes, developers of the site, submitted a proposed build trajectory for the site, prior to the Study Group meeting. This revised trajectory was published with a list of comments received and distributed at the Study Group meeting for discussion. It was agreed at the Study Group meeting to amend the schedule to include these. Agreed revised trajectory: Yr1 – 0, Yr2 – 25, Yr3 – 50, Yr4 – 50, Yr5 – 50, 50 outside the 5 year supply
4. MON LDP – Wonastow Road (LDP) – Bovis Homes confirmed at the Study Group meeting that this site was running behind the Vinegar Hill site in Magor. They put forward a revised trajectory at the meeting, which was agreed by members of the Study Group. It was agreed at the Study Group meeting to amend the schedule to include these. Agreed revised trajectory:
Yr1 – 0, Yr2 – 15, Yr3 – 45, Yr 4 – 50, Yr5 – 0, 0 outside the 5 year supply.
5. MON LDP – Tudor Road, Wyesham – Members of the Study Group submitted comments prior to the Study Group meeting concerning the foul capacity issue in Monmouth, and whether or not this would impact upon the site coming forward within the 5 year supply. Monmouthshire County Council confirmed that Welsh Water confirmed that their current Capital Investment Programme does not account for reinforcement works at the Wastewater Treatment Works. Monmouthshire County Council revised the trajectory prior to the Study Group meeting given this information and published the revised trajectory with a list of comments received, and distributed this at the Study Group meeting for discussion. The Study Group agreed with the revised trajectory put forward by Monmouthshire County Council, which pushes delivery back by 2 years. It was agreed at the Study Group meeting to amend the schedule to include these.
Agreed revised trajectory:
Yr1 – 0, Yr2 – 0, Yr3 – 0, Yr 4 – 15, Yr5 – 20, 0 outside the 5 year supply.
6. DM/2018/00696 (O/L) – Crick Road, Portskewett – Members of the Study Group submitted comments prior to the Study Group meeting concerning the build rates published in the draft site schedule and whether they corresponded to comments from the developer published on the respective site proforma. Other comments received from the Study Group concerned whether a Section 106 Agreement had been signed and the timescales for the submission of a reserved matters application. Monmouthshire County Council confirmed that a Section 106 Agreement had been signed and that a reserved matters application was expected in June 2019. Since the publication of the draft schedule, Candlestone Homes, developers of the site, submitted a proposed build trajectory for the site, prior to the Study Group meeting pushing the schedule back by 1 year and marginally lowering completion rates. This revised trajectory was published with a list of comments received and distributed at the Group meeting for discussion. It was agreed at the Study Group meeting to revise the draft schedule to reflect the Candlestone Homes trajectory. It was agreed at the Study Group meeting to amend the schedule to include these. Agreed revised trajectory: Yr1 – 0, Yr2 – 29, Yr3 – 58, Yr 4 – 58, Yr5 – 58, 88 outside the 5 year supply.