monitoring system updated feb 26
TRANSCRIPT
![Page 1: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/1.jpg)
PROJECT : 53 BENITEZ ROCKWELL PRIMARIES
OWNER : ROCKWELL PRIMARIES
CONTRACTOR : MCDC
DATE : FEBRUARY 26,2016 ITEM NO
NO. SCOPE OF WORKSFIFTH FLOOR
1 2 3 5 6 7 8 9 10 11 12 15 16 17 18 19 20 21 23 25
DRY WORKS1
DRY WALL
FRAMING
2 1-PHASE
3 2-PHASE
4 FRAMING
5 ENCLOSURE
6CEILING MR
FRAMING
7 ENCLOSURE
8BULKHEAD
FRAMING
9 ENCLOSURE
SEALANT APPLICATIONS10 CONCEALED SEALANT APPL.
11 EXPOSED SEALANT APPLICATION
PAINTING WORKS12 SKIMCOAT PUTTY
13 BORAL PUTTY
14 SANDING
15 PRIMER
16 FIRST COAT
17 FINAL COAT
THRESHOLDS18 MAINDOOR THRESHOLD
19 COMMON T&B THRESHOLD
20 MASTERS T&B THRESHOLD
CEILING ORDINARY
![Page 2: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/2.jpg)
NO. SCOPE OF WORKSFIFTH FLOOR
1 2 3 5 6 7 8 9 10 11 12 15 16 17 18 19 20 21 23 25
DOOR INSTALLATIONS & PAINTING21
MAINDOOR
DOOR INSTALLATION
22 DOOR PAINTING
23 LOCKSET INSTALLATION
24 SEALANT APPLICATION
25
BEDROOM-1
DOOR INSTALLATION
26 DOOR PAINTING
27 LOCKSET INSTALLATION
28 SEALANT APPLICATION
29
BEDROON-2
DOOR INSTALLATION
N / A N / A N /A30 DOOR PAINTING
31 LOCKSET INSTALLATION
32 SEALANT APPLICATION
33 DOOR INSTALLATION
34 DOOR PAINTING
35 LOCKSET INSTALLATION
36 SEALANT APPLICATION
37 DOOR INSTALLATION
38 DOOR PAINTING
39 LOCKSET INSTALLATION
40 SEALANT APPLICATION
41 DOOR INSTALLATION
42 DOOR PAINTING
43 LOCKSET INSTALLATION
44 SEALANT APPLICATION
45 DOOR INSTALLATION
46 DOOR PAINTING
47 LOCKSET INSTALLATION
48 SEALANT APPLICATION
49 DOOR INSTALLATION
N / A N / A N /A50 DOOR PAINTING
51 LOCKSET INSTALLATION
MASTERS BEDROOM
COMMON T&B DOOR
MASTERS T&B DOOR
UTILITY ROOM DOOR
MAIDS T&B DOOR
![Page 3: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/3.jpg)
52 SEALANT APPLICATION
N / A N / A N /A
NO. SCOPE OF WORKSFIFTH FLOOR
1 2 3 5 6 7 8 9 10 11 12 15 16 17 18 19 20 21 23 25
WET WORKS53 COMMON T&B PIPE CHASE
54 MASTERS T&B PIPE CHASE
55 PANEL BOARD PIPE CHASE
TILE WORKS56
COMMON T&BWALL TILES
57 FLOOR TILES
58MASTERS T&B
WALL TILES
59 FLOOR TILES
60 LIVING/DINNING/KITCHEN TILES
61 MAIDS ROOM FLOOR TILES
CONCRETE TOPPING62 BEDROOM 1
63 BEDROOM 2 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
64 MASTERS BEDROOM
65 BALCONY AREA ( W.O.P.)
METROLINK CONSTRUCTION & DEVELOPMENT CORP. ROCKWELL PRIMARIES
PREPARED BY: CHECKED BY: CHECKED BY: NOTED BY:
MAIDS T&B DOOR
![Page 4: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/4.jpg)
PROJECT IN CHARGE PROJECT MANAGER INSPECTOR COORDINATOR
![Page 5: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/5.jpg)
FIFTH FLOOR
26 27 28 29 30 31 32 33
![Page 6: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/6.jpg)
FIFTH FLOOR
26 27 28 29 30 31 32 33
N / A
N / A
![Page 7: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/7.jpg)
N / A
FIFTH FLOOR
26 27 28 29 30 31 32 33
N/A N/A N/A N/A N/A N/A N/A N/A
LEGEND :
ON GOING
INCOMPLETE
DONE
![Page 8: Monitoring System Updated Feb 26](https://reader036.vdocuments.us/reader036/viewer/2022080317/577c7ed41a28abe054a27d05/html5/thumbnails/8.jpg)
CLOSED OUT
PRIORITY UNITS
COORDINATOR