Office of the Prime Minister
Planning and Priorities Co-ordination Department
MONITORING COMMITTEE for Operational Programme II
Empowering People for More Jobs and a Better Quality of Life
Cohesion Policy (2007-2013)
Implementation Update17th November 2010
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Overview
• Update on projects under implementation
• Update on Calls
• Update on Aid Schemes
- Training Aid Framework
- Employment Aid Programme
• Examples of ESF-funded activities
• Lisbon Agenda – Earmarking
• Monitoring and Reporting Structures
• Financial Control – On-the-Spot Checks
• Structural Funds Database (SFD)
• Information and Publicity
• Evaluation Activities
• Training and Capacity Building
• Concluding Remarks
Office of the Prime Minister
Planning and Priorities Co-ordination Department
A Snapshot of the current OPII Projects
• OPII currently has 42 approved projects and 2 Aid Schemes as illustrated below:
PA 1 13 projects
PA 2 9 projects + 1 Aid Scheme
PA 3 14 projects + 1 Aid Scheme
PA 4 6 projects
TOTAL 42 projects + 2 Aid Schemes
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Comparative Data Analysis
Description Total May Total November Progress
OP Allocation €131,764,705 €131,764,705 N/a
Committed Allocation €77,126,175 €76,673,282 - €452,893
% of OP allocation 58.5% 58.2% -0.3%
Contracted Value €27,268,781 €37,504,356 + €10,235,575
% of Committed Allocation 35.4% 49% + 13.6%
Disbursed Value €5,216,241 €10,653,673 + €5,437,432
% of Contracted Amounts 19.1% 28.4% + 9.3%
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Comparative Data per PA (Committed Values)
€ 0.00
€ 5.00
€ 10.00
€ 15.00
€ 20.00
€ 25.00
€ 30.00
€ 35.00
€ 40.00
PA 1 PA 2 PA 3 PA 4 PA 5
OP Allocation
Committed Values asat May 2010Committed Values asat October 2010
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Comparative Data per PA (Contracted Values)
€ 0.00
€ 3.00
€ 6.00
€ 9.00
€ 12.00
€ 15.00
€ 18.00
PA 1 PA 2 PA 3 PA 4 PA 5
Contracted Values asat May 2010Contracted Values asat October 2010
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Comparative Data per PA (Disbursed Values)
€ 0.00
€ 1.00
€ 2.00
€ 3.00
€ 4.00
€ 5.00
€ 6.00
€ 7.00
€ 8.00
€ 9.00
PA 1 PA 2 PA 3 PA 4 PA 5
Disbursed Values asat May 2010Disbursed Values asat October 2010
Office of the Prime Minister
Planning and Priorities Co-ordination Department
PA 1 – Financial Management
Description PA 1
Financial Allocation €37,400,000
Committed Value €26,987,782
% of Financial allocation 72.16%
Contracted Value €16,031,228
% of Committed Allocation 59.4%
Disbursed Value €6,755,653
% of Contracted Amounts 42.1%
Office of the Prime Minister
Planning and Priorities Co-ordination Department
PA 2 – Financial Management
Description PA 2
Financial Allocation €30,995,000
Committed Value €20,555,795
% of Financial allocation 66.32%
Contracted Value €8,764,509
% of Committed Allocation 42.6%
Disbursed Value €1,647,913
% of Contracted Amounts 18.8%
Office of the Prime Minister
Planning and Priorities Co-ordination Department
PA 3 – Financial Management
Description PA 3
Financial Allocation €36,900,000
Committed Value €16,355,965
% of Financial allocation 44.3%
Contracted Value €10,221,420
% of Committed Allocation 62.5%
Disbursed Value €1,682,386
% of Contracted Amounts 16.5%
Office of the Prime Minister
Planning and Priorities Co-ordination Department
PA 4 – Financial Management
Description PA 4
Financial Allocation €21,405,000
Committed Value €7,709,035
% of Financial allocation 36%
Contracted Value €613,914
% of Committed Allocation 8%
Disbursed Value €25,272
% of Contracted Amounts 4.1%
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Update on Calls
Call Value (€)No. of project
proposals submitted
Value of eligible costs of the projects submitted (€)
Call 6 PA 1 €10 million 15 €28,942,108
Call 6 PA 3 €20 million 19 €22,333,997
The Project Selection Committee is currently at evaluation stage.
Call 6 was issued on 26.07.2010 with a closing date of 24.09.2010.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Update on Calls (2)
Call Priority AxisIndicative Financial
Threshold (€)
Call 7PA 2 €10 million
PA 4 €13.5 million
Call 7 was issued on 22.10.2010 with a closing date of 03.12.2010.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Aid schemes
Training Aid Framework ESF2.65
• 1996 applications have been received to-date.
• The number of Grant Agreements signed to-date totals 1248:
– 393 from small enterprises (31%)– 299 from medium undertakings (24%)– 556 from large undertakings (45%)
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Aid schemes (2)
Employment Aid Programme ESF3.64
• 2144 Applications have been received to-date.
To date, 896 Grant Agreements (totalling €3,807,239.51) have been signed:
- 522 (58%) males- 374 (42%) females
Out of the 896 participants:- 276 (31%) Gozo (amounting to €1,451,510.53)- 620 (69%) Malta (amounting to €2,355,728.98)
The 896 signed Grant Agreements represent 852 (95%) disadvantaged participants and 44 (5%) disabled participants.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Examples of ESF-funded activities
ESF1.23 Higher Education Courses to Address Skill Mismatches in Gozo
ESF3.64Employment Aid Programme
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Examples of ESF-funded activities
ESF2.4Employability Programme
ESF1.21Parents and Teachers Fusion ICTTraining Programme
ESF2.65 Training Aid Framework
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Examples of ESF-funded activities
ESF3.66Ic-Cavetta -Maltese Literacy Toolkitfor employment and educationinclusion
ESF1.40 Science Popularisation Campaign
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Lisbon Agenda - Earmarking
• €92,500,800 are earmarked for Lisbon Agenda related
projects.
• 44 Projects/schemes (totalling €56,721,196) under
implementation are contributing to the earmarked categories.
• This is equivalent to 61.3% of the earmarked amount.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Monitoring
• Monitoring Committee Meetings – 27th May 2010 & 17th November 2010
• Inter-Ministerial Co-ordination Committee (IMCC) - 13th September
• PPS high level meetings held monthly – 9 projects reviewed between June and October 2010
• IB Network – 13th September 2010
• Intermediate Bodies Steering Committee (IBSC) – 23rd June 2010.
• Ministerial Projects Steering Committee (MPSC)– 11 meetings (MEEF, MRRA, MITC, MGOZ, OPM, MHEC)
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Reporting
• Annual Implementation Report (OPII) for the year 2009 was approved by CION on the 24th of September 2010.
• Project Progress Reports requested 3 times per year
• MA Project Briefs (updated monthly)
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Financial ControlOn-the-Spot Checks & Audits
• 57 Documentary OTS undertaken by MA (OPII)
• 9 Documentary OTS undertaken by IBs (OPII)
• 71 Physical OTS undertaken by MA (OPII)
• 2828 Physical OTS / monitoring visits undertaken by IBs (OPII)
• 2 Audits on operations carried out (OPII)
• Systems’ Audits (OPII)
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Structural Funds Database
• New Modules released between June and August 2010
- Irregularities module
- Debtor’s Ledger Report;
- On the Spot module;
- Annex III of Regulation EC1828/2006 – Data on Operations;
- System has been updated to capture Expenditure Type related to payments.
Furthermore, the system was enhanced to capture more fields required under the Regulation
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Structural Funds Database (2)
• New SFD Intermediate Level Courses for the SFD Trainers
- 25th August 2010 – Intermediate Bodies;
- 2nd & 29th September 2010 – Beneficiary Level; and
- 20th September 2010 – Line Ministry Level
• System Manuals updated:
– Manuals related to the Project, Commitment, Contract and Invoice levels.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Information and Publicity 2010 Annual Event
The annual information event mE&U fest was held in Gozo on the 5th of September and in Malta on the 8th of September.
The Festival focused on 4 Main Themes:
• Employment Opportunities
• Built and Natural Environment
• Science and Technology
• Education and Health
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Information and Publicity (2)2010 Annual Event
Activities:
• Interactive Project Exhibitions and PPCD Info stand
• Family Entertainment with Eurovision Singers, Folk-Rock Band, Magician, Interactive Ballroom Dancers, and ‘Ghannejja’ amongst others
• Kids’ corner with animation and drawing competition
• Information Leaflet distributed to all households prior to the event to generate interest
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Evaluation ActivitiesMid-Term Evaluation
• Inception Report approved by the MA on 23rd August 2010
• On line beneficiary survey of MTE between 27th September and 15th October 2010
• Consultative interviews were carried out with key policy makers and experts between 8th October and 15th November 2010
• Between 10th and 26th November 2010 interviews are ongoing with project leaders selected in a sample of circa 46 projects (including some of the Aid Schemes )
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Evaluation Activities (2)Mid-Term Evaluation
Next Steps:
• Internal Factors Workshop
This will lead KPMG to gain an in-depth understanding of outstanding issues and to verify certain hypotheses based on previous research methods such as the interviews. It will be held on 20th December with a number of horizontal stakeholders such as MEPA and DoC.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Evaluation Activities (3)Other evaluation Activities:
The MA was involved in a number of evaluations carried out by DG EMPL:– Evaluation of the ESF`s support to Gender Equality; – Evaluation of the Contribution of ESF to EES;
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Training and Capacity Building
• Training on the Structural Funds Database held in April/June 2010 (12 OPII participants)
• Start-Up Training for New Beneficiaries held in July/Aug 2010 (39 participants)
• Training on “Eligibility: Simplified Costs” in June 2010
• Training in October 2010 on Monitoring of EU Cohesion Policy Funds’ horizontal policies: environment, gender and non-discrimination rules
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Concluding Remarks on latter half of 2010
• Programming implementation is clearly gaining pace.
• Horizontal activities such as evaluation, financial control, monitoring and reporting are increasing and will require additional capacity.
• Challenges for 2011 will focus mainly on speeding up payments.
Office of the Prime Minister
Planning and Priorities Co-ordination Department
Operational Programme II – Cohesion Policy 2007-2013Empowering People for More Jobs and a Better Quality of Life
Event part-financed by the European UnionEuropean Social Fund (ESF)
Co-financing rate: 85% EU Funds; 15% National Funds
Investing in your future