monday 04 august 2003 welcome haivan pass tunnel construction project
TRANSCRIPT
Background of Project
North – South longitudinal arterial in the country as the most important transport infrastructure of the national economy
An integral part of international gateway – “East-West Corridor” connecting Thailand through Laos to Danang Port and Dung Quat Industrial Zone
Important role of National Highway No. 1
Background of Project Traffic on Haivan pass
Results of Origin-Destination Survey during July 2002
Ho Chi Minh
Hanoi
20 % of traffic volumes are between Ho Chi Minh City - Hanoi
Danang
Hue 30 % of traffic volumes are between Danang - Hue
Description of Project
Begins at Km. 894+000 near Lang Co Town (Thua Thien–Hue Province)
Ends at Km. 914+450 just north of Danang City
Runs across the Haivan Pass peak at with an elevation of 475m, with a distance of 20.45 km
Haivan Pass section is a very low standard highway. In spite of many efforts of Vietnamese government on upgrading this section, it is still a dangerous highway to drive and many lives lost each year in accidents on this section
The Haivan pass section of the National Highway No. 1
Description of Project
Estimated Total Amount: USD 143,375,000
Implementation Program: Design stage: July 1998 – July 1999Tendering stage: June 1999 – presentConstruction stage: October 2000 – April 2005
Design Standards: TCVN (Vietnam), JHPC (Japan) and AASHTO-1994 (USA)
Design Life: Permanent
Design Speed: 80 km/h
Design Load: H30 – XB80
Construction Contract Packages: 9 packages
Project Outline
Description of Project
Financing Agency:Japan Bank for International Cooperation (JBIC) L/A No. VNIV-5, March 26, 1997, Loan Amount JPY 5.5 billion L/A No. VNVI-5, March 30, 1999, Loan Amount JPY 10.0 billion L/A No. VNIX-4, March 29, 2002, Loan Amount JPY 3.359 billion
Executing Agency:Ministry of Transport and Communication (MOT)Represented by Project Management Unit 85 (PMU85)
ConsultantJoint Venture of Nippon Koei Co., Ltd (Japan) and Louis Berger International Inc.
(USA) In association with Transport Engineering Design Incorporation (TEDI) Vietnam
Organization Structure
Description of Project
1. Total Project Length: 12,182 m2. Number of Traffic Lanes: 2 lanes 3. Tunnel Construction:Main Tunnel: 6,274m long, 2 lanes (3.75m wide/each) , 89.0 m2
Evacuation Tunnel: 6,286m long, 15.5 m2
Ventilation Adit: 1895m long, 36.2 m2
4. Bridge Construction: 8 bridges, 1,653 in total length5. Highway Construction: 4,273m in total length
Major Features
Description of Project Contract Packages
Name Title ContractorAmount
(1000 USD)Period
(month)
Construction Services 14 724
PKIA
North Tunnel Section JV Hazama – Cienco 6 43 256 48
PKIB North Tunnel Section JV Dong Ah – Song Da 27 863 48
PKIIA Lang Co Bridge SectionJV Thang Long – Truong Son 4 633 30
PKIIB Southern Highway SectionJV Cienco 1 – Lung Lo – Vinawaco 3 920 30
PKIII Electrical WorksJO of ABB – Kinden – Vinainco 20 686 26
PKIV Mechanical WorksMatsushita – Itochu Consortium 23 055 32
PKV110/22kV Substation and 110kV Transmission Line
JO of ABB – Kinden – Vinainco 7 256 18
PKVIProcurement of Maintenance Vehicles 2 000
PKVIIInfrastructure Development in the Resettlement Areas
Construction Company No. 185 413 08
TOTAL 133 082
Description of Project Implementation Program
Tunnel Civil 1A
Works 1B
Road and 2A
Bridge Works 2B
Package I I :
Package I :
2005
Package VI I :Infrastructure Development in the
1998
Consulting Services
Package I I I : Electrical Works
Package IV: Mechanical WorksPackage V: 110/22kV Substation and 110kV Trans. LinePackage VI :Procurement of Maintenance Vehicles
200420031999 2000 2001 2002
Package IA – North Tunnel Section
Name of Contractor: Hazama (Japan) – Cienco 6 (Vietnam) Joint Venture
Contract Amount: US$ 43,256,000
Contract Period: 48 months (10/2000 – 10/2004)
Contract Chronicle:
Contract Signing Date: August 17, 2000
Notice of Proceed: September 01, 2000
Commencement of Works: October 01, 2000
Location: Sta. 1+515 to Sta. 5+500
Contract Data and Chronicle
Package IA – North Tunnel Section
A 3,857m long 2-lane main tunnel with 73.26 m2 cross-section
A 3,857m long evacuation tunnel with 15.47 m2 cross-section parallel to the mail tunnel
Two (02) vehicular cross-passageways with 15.47 m2
cross-section, and seven (07) pedestrian cross-passageways with 8.12 m2 cross-section
A 1,810m long tunnel ventilation adit with 36.20 m2
cross-section
Two 153 meters long each, by-pass type electrostatic precipitator tunnels (north & central) with 57.69m2 cross-section
A 128 meters 2-lane tunnel approach
A 403 meters long access road to adit building
A 80m2, one-story substation structure (building only)
A north tunnel portal plaza and a ventilation adit portal plaza
Scope of Work
Package IB – South Tunnel Section
Name of Contractor: Dong Ah (Korea) – Song Da (Vietnam) Joint Venture
Contract Amount: US$ 27,863,000
Contract Period: 48 months (10/2000 – 10/2004)
Contract Chronicle:
Contract Signing Date: August 17, 2000
Notice of Proceed: September 01, 2000
Commencement of Works: October 01, 2000
Location: Sta. 5+500 to Sta. 8+125
Contract Data and Chronicle
Package IB – South Tunnel Section
A 2,417 meters long 2-lane main tunnel with 73.26m2 cross-section
A 2,429m long evacuation tunnel with 15.47 m2 cross-section parallel to the mail tunnel
Two (02) vehicular cross-passageways with 15.47 m2
cross-section, and four (04) pedestrian cross-passageways with 8.12 m2 cross-section
A 153 meters long by-pass type electrostatic precipitator tunnels (south) with 57.69m2 cross-section
A 208 meters 2-lane tunnel approach
A 817 meters long access road to high water reservoir
A 1,400m2, one-story, vehicular maintenance building
A south tunnel portal plaza
A 58.45 meters long, 2-lane, 2-span post-tensioned girder bridge
Scope of Work
Package IIA – Lang Co Bridge Section
Name of Contractor: Thang Long – Truong Son Joint Venture
Contract Amount: US$ 4,633,000
Contract Period: 30 months (07/2001 – 12/2003)
Contract Chronicle:
Contract Signing Date: May 03, 2001
Notice of Proceed: June 01, 2001
Commencement of Works: July 01,2001
Location: Sta. –1+8650 to Sta. 1+515
Contract Data and Chronicle
Package IIA – Lang Co Bridge Section
Lang Co Bridge, 876.390 meters total length;
Two lane roadway, 782.610 meters total length
A northern toll plaza; and
Construction of 187m2 area enclosed car port
Scope of Work
Package IIB – Southern Highway Section
Name of Contractor: Cienco 1 – Lung Lo - Vinawaco Joint Venture
Contract Amount: US$ 3,920,000
Contract Period: 32 months (07/2001 – 03/2004)
Contract Chronicle:
Contract Signing Date: May 28, 2001
Notice of Proceed: June 26, 2001
Commencement of Works: July 26,2001
Location: Sta. 8+125 to Sta. 12+047
Contract Data and Chronicle
Package IIB – Southern Highway Section
Scope of Work
Six bridges, totaling 959.390 meters length; in which
Bridge No. 2 : 334m
Bridge No. 3 : 33 m
Bridge No. 4 : 175 m
Bridge No. 5 : 133 m
Bridge No. 6 : 150 m
Bridge No. 7 : 133 m
Two lane roadway, totaling 2963.067 meters length
A southern toll plaza
Package III – Electrical Works
Name of Contractor: JO of ABB – Kinden - VINAINCO
Contract Amount: US$ 20,686,000
Contract Period: 26 months (02/2003 – 04/2005)
Contract Chronicle:
Pre-bid Conference: April 18, 2001
Bid Opening Date: June 26, 2001
Bid Evaluation: June 27 – July 11, 2001
Contract Data and Chronicle
Package III – Electrical Works
Scope of Work
Electrical Systems : Medium Voltage System
MV/LV Substations
MV Power Distribution Lines Low Voltage Switchboards
Low Voltage Switchboards
LV Power Distribution Lines
Interior Tunnel Lighting System
Exterior (Road and Area) Lighting System
Power Supply for the Ventilation and Water Supply Systems CCTV System Lighting Control System Fire Alarm and Detection System Telecom System Traffic Control System Radio Rebroadcast System Tunnel Power Distribution Monitoring and Control System Main Supervised Control and Data Acquisition (SCADA) System
Package IV – Mechanical Works
Name of Contractor: Matsushita – Itochu Consortium
Contract Amount: US$ 23,055,000
Contract Period: 36 months (03/2002 – 03/2005)
Contract Chronicle:
Contract Signing Date: January 18, 2002
Notice of Proceed: February 12, 2002
Commencement of Works: March 12, 2002
Commencement of Works: November 01, 2002
Contract Data and Chronicle
Package IV – Mechanical Works
Scope of Work
Water Supply and Treatment System consisting of
Water catchment and pre-treatment system
Pump station and treatment system
High water reservoir
Fire suppression pipe with hydrans
Tunnel Ventilation System consisting of
Three (03)sets of electrostatic precipitator
Two (02)sets of air supply fans and exhaust fans
Thirty-two (32) sets of jet fans
Ventilation control system
Ventilation building
Package V – 110/22kV Substation and 110kV Transmission Line
Name of Contractor: Joint Operation of ABB – Kinden - Vinainco
Contract Amount: US$ 7,256,000
Contract Period: 18 months (12/2001 – 06/2003)
Contract Chronicle:
Contract Signing Date: September 15, 2001
Notice of Proceed: October 18, 2001
Commencement of Works: December 21, 2001
Contract Data and Chronicle
Package V – 110/22kV Substation and 110kV Transmission Line
Scope of Work
Construction of 110/22 KV indoor substation and tunnel control system
Design, manufacture, install, erect and commission a 110/22KV Gas Insulated Switchgear (GIS) substation and substation control center
Design, manufacture, install, erect and commission a 110 Transmission Line
Package VI – Procurement of Maintenance Vehicles
Contract Data and Scope of Work
Contract Amount: US$ 2,000,000 (estimated)
The equipment and vehicles to be supplied
1. Tunnel Superintendent Staff Car : 03 units
2. Patrol Car : 02 units
3. Road Maintenance Vehicle (Van Type) : 02 units
4. Road Maintenance Vehicle (Station Wagon Type) : 01 unit
5. Water Sprinkler Truck : 01 unit
6. Road Sweeper : 01 unit
7. Vacuum Cleaner with High Pressure Washer : 01 unit
8. Sign Truck : 01 unit
9. Lift Truck : 01 unit
10. Aerial Platform Truck : 01 unit
11. Multi Service Vehicle with Side Wall Cleaning Attachment : 01 unit
12. Cargo Truck with 3-ton Crane : 01 unit
13. Wrecker Truck : 01 unit
14. Ambulance Car (Van Type) : 01 unit
15. Fire Fighting Car (Pickup Truck Type) : 01 unit
16. Workshop Equipment and Tools : 01 lot
Package VII – Infrastructure of Resettlement Area
Construction of Treatment Reservoir – November 2001
Package VII – Infrastructure of Resettlement Area
Name of Contractor: Construction Company No. 185
Contract Amount: US$ 413,000
Contract Period: 8 months (09/2001 – 04/2002)
Contract Chronicle:
Contract Signing Date: June 09, 2001
Notice of Proceed: August 01, 2001
Commencement of Works: August 31, 2001
Issuance of Taking-over Certificate: April 29, 2002
Contract Data and Chronicle
Package VII – Infrastructure of Resettlement Area
Scope of Work
Construction of Internal Road
Construction of Embankment
Construction of Water Supply System
Construction of Drainage System
Construction of Electricity System
Construction of Treatment Reservoir
Construction of Kindergarten
ConclusionConclusion
This Presentation is made for purpose to give out a basic
introduction of Haivan Pass Tunnel Construction Project
Hoping that this Presentation will be of some help toward better
implementation of the Project