Module : PP (Production Planning)

Page 2: Module : PP (Production Planning)

The SAP PP business processes uses the following organizational elements:

– Client

– Company Code

– Plant

– Storage Location

Organizational Elements

Page 3: Module : PP (Production Planning)

Organizational ElementsClient

A Highest Hierarchical Level in SAP (e.g. a corporation)

Used to Differentiate between a Development, Quality Assurance, and Production System within SAP R/3

Common Set of Rules Common Tables Common Master Files Common Data Bases

Standardized data across the client A vendor number and name is common across the client A customer is common across the client A material number and description is common across the client

Page 4: Module : PP (Production Planning)

BALANCING / (LEGAL)BALANCING / (LEGAL)ENTITYENTITY

==Company Code ****

AssetsLiabilitiesRevenues

- Expenses

Profit/Loss

Organizational ElementsCompany Code

A company code represents an independent balancing/legal accounting entity, for example, a company within a corporate group.

Balance sheets and profit & loss statements, required by law, can be created at the company code level.

Page 5: Module : PP (Production Planning)

Organizational ElementsPlant

Usually a manufacturing facility, a warehouse, or a location that stocks , manages, and valuates inventory

May be a physical site with multiple manufacturing/production lines

May be multiple manufacturing/production lines at one physical site

Can be a physical location (cost centers may or may not be associated to a plant i.e. Administrative vs. Manufacturing cost centers)

Links to production (PP), materials management (MM), and sales and distribution (SD)

A plant is assigned to a company code

Purchasing organization are assigned to plants.

Page 6: Module : PP (Production Planning)

Organizational ElementsStorage Locations

A storage location is the place where stock is physically kept within a plantA storage location has the following attributes:

There may be one or more storage locations within a plant.

Stocks are managed only on a quantity basis and not on a value basis at storage location level.

Physical inventories are carried out at storage location level.

Storage locations are always created for a plant.

Page 7: Module : PP (Production Planning)
Page 8: Module : PP (Production Planning)

Master DataList of Master Data in SAP PP Module are:

– Material Master– Bills Of Material– Work Centers– Routings

Page 9: Module : PP (Production Planning)

Master DataMaterial Master

Page 10: Module : PP (Production Planning)

Material Master

Page 11: Module : PP (Production Planning)

Material master record is a company's main source of material-specific data. It is used by all components in the R/3 Logistics System.

The integration of all material data in a single database object prevents the problem of data redundancy. Every area, such as Purchasing, Inventory Management, Materials Planning, and Invoice Verification can use the data stored.

Material Master

Page 12: Module : PP (Production Planning)

Since materials are processed by various user departments within a company and each department stores different information for the materials, the material master is subdivided into information grouped by user departments.

Each user department has a different view of the material master record and is responsible for maintaining the data to support its function.

The data maintained within a view may be valid for more than one organizational level.

Material Master

Page 13: Module : PP (Production Planning)

Material Master

Page 14: Module : PP (Production Planning)

Material Master

Page 15: Module : PP (Production Planning)

Material Master

Page 16: Module : PP (Production Planning)

Material Master

Page 17: Module : PP (Production Planning)

Material Master

Page 18: Module : PP (Production Planning)

Material Master

Page 19: Module : PP (Production Planning)

Base unit: Piece

Box(unit of issue)

Crate(order unit)

Pallet(sales unit)

4

16 72

Material Master – Units of Measure

Page 20: Module : PP (Production Planning)

Material Master

Page 21: Module : PP (Production Planning)

Material Master

Page 22: Module : PP (Production Planning)

Master DataBills Of Material

Page 23: Module : PP (Production Planning)

Bills Of Material

Page 24: Module : PP (Production Planning)

Bills Of Material

Page 25: Module : PP (Production Planning)

Bills Of Material

Page 26: Module : PP (Production Planning)

Bills Of Material

Page 27: Module : PP (Production Planning)

Bills Of Material

Page 28: Module : PP (Production Planning)

Bills Of Material

Page 29: Module : PP (Production Planning)

Bills Of Material

Page 30: Module : PP (Production Planning)

Bills Of Material

Page 31: Module : PP (Production Planning)

Bills Of Material

Page 32: Module : PP (Production Planning)

Bills Of Material

Page 33: Module : PP (Production Planning)

Bills Of Material

Page 34: Module : PP (Production Planning)

Bills Of Material

Page 35: Module : PP (Production Planning)

Bills Of Material

Page 36: Module : PP (Production Planning)

Bills Of Material

Page 37: Module : PP (Production Planning)

Bills Of Material

Page 38: Module : PP (Production Planning)

Bills Of Material

Page 39: Module : PP (Production Planning)

Master DataWork Centers

Page 40: Module : PP (Production Planning)

Work Center

Page 41: Module : PP (Production Planning)

Work Center

Page 42: Module : PP (Production Planning)

Work Center

Page 43: Module : PP (Production Planning)

Work Center

Page 44: Module : PP (Production Planning)

Work Center

Page 45: Module : PP (Production Planning)

Work Center

Page 46: Module : PP (Production Planning)

Work Center

Page 47: Module : PP (Production Planning)

Work Center

Page 48: Module : PP (Production Planning)

Work Center

Page 49: Module : PP (Production Planning)

Work Center

Page 50: Module : PP (Production Planning)

Work Center

Page 51: Module : PP (Production Planning)

Work Center

Page 52: Module : PP (Production Planning)

Work Center

Page 53: Module : PP (Production Planning)

Work Center

Page 54: Module : PP (Production Planning)

Work Center

Page 55: Module : PP (Production Planning)

Work Center

Page 56: Module : PP (Production Planning)

Work Center

Page 57: Module : PP (Production Planning)

Work Center

Page 58: Module : PP (Production Planning)

Master DataRoutings

Page 59: Module : PP (Production Planning)

Routing

Page 60: Module : PP (Production Planning)

Routings - Components

Page 61: Module : PP (Production Planning)

Routing - Components

Page 62: Module : PP (Production Planning)

Routings

Page 63: Module : PP (Production Planning)

Routing - Group

Page 64: Module : PP (Production Planning)

Routing - Group

Page 65: Module : PP (Production Planning)

Material Allocation

Page 66: Module : PP (Production Planning)

PRT Assignments

Page 67: Module : PP (Production Planning)

Sequences in Routing

Page 68: Module : PP (Production Planning)

Parallel Sequences

Page 69: Module : PP (Production Planning)

Scheduling in PP

Page 70: Module : PP (Production Planning)

Scheduling

Page 71: Module : PP (Production Planning)

Sub Operations in Routing

Page 72: Module : PP (Production Planning)

Scheduling

Page 73: Module : PP (Production Planning)

Production Planning

• Demand Management• Material Requirement Planning

−Planning of Purchased parts

−Planning of in house assemblies

Page 74: Module : PP (Production Planning)

Planning Process: Process flow

Demand planning cell

PPC

Production

MRP Run

Third Party Log

Vendor Web site

Demand (Weekly)

Production Requirement (Week wise, Model wise)

Planned Prod.

Confirmed Production

Planned Vendor Schedule

Confirmed Vendor Schedule

Dispatch plan

Central marketing office

Dispatch sheet

Page 75: Module : PP (Production Planning)

While doing planning, you need to decide which planning strategy to use when the customer places their order.

• Make-to-Stock Production− Make-to-stock production means we build stock in anticipation of customer

demand. We ship the customer order from our stock of finished goods

• Make-to-order Production− We wait for a customer order before we start production/procurement. i.e. We

produce as per demand from customer

Planning Process: Strategies

Page 76: Module : PP (Production Planning)

Dealer

Territory office

Area Office Area Office Area Office Area Office

Zonal

Central Marketing office

Consolidation of Demand

Territory office

PPC

Dealer Dealer Dealer Dealer Dealer

Planning process: Demand Planning

Page 77: Module : PP (Production Planning)

Demand management is the link between top-level requirements planning (SOP) and materials planning (MRP).Input for the demand program can come from several sources:

Planning Process: Demand Management

Page 78: Module : PP (Production Planning)

Materials Requirement Planning

Page 79: Module : PP (Production Planning)

MRP Overview

Page 80: Module : PP (Production Planning)

Uses of MRP

Page 81: Module : PP (Production Planning)

MRP Functions

Page 82: Module : PP (Production Planning)

MRP Prerequisites

Page 83: Module : PP (Production Planning)

Planning Run

Page 84: Module : PP (Production Planning)

Planning Run - Types

Page 85: Module : PP (Production Planning)

MRP - Control Parameters

Page 86: Module : PP (Production Planning)

Net Change Planning

Page 87: Module : PP (Production Planning)

Planning in Planning Horizon

Page 88: Module : PP (Production Planning)

Planning Run - Single Item

Page 89: Module : PP (Production Planning)

Single-item, Multi-Level Planning

Page 90: Module : PP (Production Planning)

Single-Level MRP

Page 91: Module : PP (Production Planning)

Multi-Level MRP

Page 92: Module : PP (Production Planning)

Total Planning

Page 93: Module : PP (Production Planning)

MRP Procedure

Page 94: Module : PP (Production Planning)

MRP Control Parameters

Page 95: Module : PP (Production Planning)

MRP Control Parameters

Page 96: Module : PP (Production Planning)

MRP Control Parameters

Page 97: Module : PP (Production Planning)

MRP Control Parameters

Page 98: Module : PP (Production Planning)

MRP Control Parameters

Page 99: Module : PP (Production Planning)

MRP Control Parameters

Page 100: Module : PP (Production Planning)

Net Requirements Calculation

Page 101: Module : PP (Production Planning)

Requirement Quantities

Page 102: Module : PP (Production Planning)

Safety Stock

Page 103: Module : PP (Production Planning)

Safety Time

Page 104: Module : PP (Production Planning)

Safety Time in Production

Page 105: Module : PP (Production Planning)

Lot Size Calculation

Page 106: Module : PP (Production Planning)

Lot Sizing - Overview

Page 107: Module : PP (Production Planning)

Static Lot Sizing

Page 108: Module : PP (Production Planning)

Period Lot - Sizing Procedure

Page 109: Module : PP (Production Planning)

Optimum Lot Sizing

Page 110: Module : PP (Production Planning)

Long Term Lot Sizing

Page 111: Module : PP (Production Planning)

Other Lot Sizing Features

Page 112: Module : PP (Production Planning)

Lot Size Rounding Profiles

Page 113: Module : PP (Production Planning)

Layout of MRP List

Page 114: Module : PP (Production Planning)

Stock Req. List - Layout

Page 115: Module : PP (Production Planning)

MRP List - Collective Display

Page 116: Module : PP (Production Planning)

MRP List - Functions

Page 117: Module : PP (Production Planning)

Exception Messages

Page 118: Module : PP (Production Planning)

Rescheduling Checks

Page 119: Module : PP (Production Planning)

Old / New Exception Message

Page 120: Module : PP (Production Planning)

Planned New Exception Message Order Conversion

Page 121: Module : PP (Production Planning)

Material Supply for Production

Page 122: Module : PP (Production Planning)

Collective Display

Page 123: Module : PP (Production Planning)

Search in Individual List

Page 124: Module : PP (Production Planning)

Current List - Functions

Page 125: Module : PP (Production Planning)

Pegged Requirements

Page 126: Module : PP (Production Planning)

Order Report

Page 127: Module : PP (Production Planning)

Planning Time Fence

Page 128: Module : PP (Production Planning)

Planning Time Fence

Page 129: Module : PP (Production Planning)

Scheduling in PP

Page 130: Module : PP (Production Planning)

Scheduling - Basic Dates

Page 131: Module : PP (Production Planning)

Scheduling - Production Time

Page 132: Module : PP (Production Planning)

Planning Process

PlantStockPlantStock

MRP

OrderProposalExternal

ProcurementIn-HouseProduction

SupplySupply

DemandDemand

PlanningParameters

PlanningParameters

Page 133: Module : PP (Production Planning)

Planning Process

Page 134: Module : PP (Production Planning)

Production Execution

• Stock transfer to WIP location• Order Execution

−Production confirmation

−Error handling

Page 135: Module : PP (Production Planning)

Planning Process

Page 136: Module : PP (Production Planning)

Planning Process

Page 137: Module : PP (Production Planning)

Production Execution

Physical MovementStorage Loc MAINStorage Loc MAINStorage Loc MAINStorage Loc MAIN Storage Loc WIPStorage Loc WIPStorage Loc WIPStorage Loc WIP

Page 138: Module : PP (Production Planning)

ProductionOrder

BOM

Work Center

Routings

Release Avail check

Goods issue

Production

Goods receiptConfirmation

TECO

Movefloorstock

Planned Order

Availability Check

Convert Order

Production Execution

Page 139: Module : PP (Production Planning)

Best PracticesLogistics PlanningMake-To-Stock Discrete ManufacturingProduction Subcontracting (External

Processing)Rework Processing (Stock-Manufactured

Material)Rework Processing (Work-In-Process)

Page 140: Module : PP (Production Planning)

Logistics Planning

• Purpose − The purpose of logistics planning is to make sure that future demand can be

satisfied by your company’s available resources and to point out situations where demand cannot be met in time or in the desired quantities.

• Benefits − Seamless Integration in complete planning cycle

• CO-PA SOP LTP Demand Planning

• Key process flows covered− Sales and Operation Planning

− Long Term Planning

Purpose and Benefits:

Page 141: Module : PP (Production Planning)

Logistics Planning

•This process sometimes is called ‘Sales and Operations Planning’. The process usually takes place in a simulative mode and at an aggregated (usually product group rather than end-item) level. Once a feasible production plan is found that satisfies demand it can be used as the basis for operational production planning (MRP and Detailed Capacity Scheduling).•The Best Practice scenarios in this section cover the following planning workflow: Planning/forecasting of future demand Aggregated production planning including capacity check in order to check at

product group level if demand can be satisfied (using the SOP functionality) Transfer of results to Long Term Planning (using the LTP module) to enable

simulation of material requirements, based on the production plan (s) Planning takes place in separate (simulative) planning versions within LTP Review and adjustments of planned requirements as needed Once the simulated requirements are accepted, the demand (independent

requirements) is then transferred to active demand management for detailed MRP and Production Planning / Scheduling in the active version.

Detailed Process Description:

Page 142: Module : PP (Production Planning)

Logistics Planning – Process Flow DiagramR

even

ue

Pla

nn

er

Str

ate

gic

Pla

nn

er

Even

t

Acceptable Plan

Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172)

Operational Production Planning & Control(Production scenarios)

SOP Verification Demand Verification (Check Sales Plan)

Create Rough-Cut Production Plan

Periodic Sales and Operations Meeting

Operative Production Data

CO-PA = Profitability Analysis, SOP = Sales and Operations Planning, LTP = Long Term Planning, MRP = Material Requirements Planning

Transfer Rough Cut Production Plan to Inactive Demand Management

Copy to Active Demand Management

Execute LTP MRP

Create LTP Planning Scenario

No

Yes

Evaluate Capacity Planning

Sales Quantity forecast (179)

Page 143: Module : PP (Production Planning)

Make-To-Stock Production with Discrete Manufacturing

• Purpose

− This scenario describes a business process, which is typical for companies with lot-size oriented production.

− The production scenario produces a finished good and all dependent components in make-to-stock production (MTS).

− Furthermore, the scenario is supported by the main cost object controlling functions required, such as preliminary costing and period-end closing.

• Benefits

− Production triggered by a production plan

− Serial number and batch management included

− Optional with: quality management, consigned inventory, external processing• Key process flows covered

− Creating Planned Independent Requirements

− Material Requirements Planning at Plant Level

− In-House Production (subassembly)

− In-House final assembly (Finished Good)

− Capacity Leveling

− Confirming Assembly Activities

Purpose and Benefits:

Page 144: Module : PP (Production Planning)

Make-To-Stock Production with Discrete Manufacturing

This scenario describes a business process, which is typical for companies with lot size oriented production. The production scenarios consist of both goods movements (goods issues and receipts) and confirmation of completion of the production order.

Furthermore, the scenario is supported by the main cost object controlling functions required, such as preliminary costing and period-end closing.

The typical planning process starts with sales quantity planning. The previous period’s actual sales figures can be used as a basis for future planning.

In Sales and Operations Planning, you ensure that production stays in line with sales so that you may create the production plan synchronously to sales. The planning data is transferred from Sales and Operations Planning to Demand Management. Demand Management generates independent requirements, which are used in the subsequent Material Requirements Planning (MRP) run.

In material requirements planning, the bill of materials (BOM) for the top-level material demand gets exploded and production is planned right down to procured component level. MRP results in planned orders being generated for the material to be produced.

If insufficient warehouse stock is available, purchase requisitions are created for the raw materials required. When the order is created, target costs are calculated for the order lot size (preliminary costing).

During the production process, costs incurred are updated on the order, which enables you to keep track of and compare target costs and actual costs at any time.

Period-end-closing activities are applied to the order. This includes Work In Progress calculation and variance calculation.

After this, Work in Progress is settled to financial accounting and production variances are settled to management and financial accounting.

Detailed Process Description:

Page 145: Module : PP (Production Planning)

Make-to-Stock Production – Discrete Industry – Process Flow Diagram

Man

ufa

ctu

rin

gEven

t

Pla

nt

Con

tro

ller

Period End Closing “General” Plant(181)

Material Requirements Planning at Plant Level & Evaluation of Stock / Requirement List

Beginning of Planning Cycle

Purchase Requisition

MRP List

Inventory @ Standard. Cost

Pro

du

ctio

n P

lan

ner

Periodic Plan Revision

Release Production Order

Capacity Leveling

Material Staging for Planned Orders

Confirming Assembly Activities/ Final Confirmation

Semi-Finished Goods Receipt

Goods Issue/ Back flush

Update Capacity

Goods Receipt Slip

Pick List

Order PrintPlanned Orders

Capacity Leveling O.k.?

Material Available?

Bu

ye

rW

are

-h

ou

se

Cle

rk

Goods Receipt Slip

Procurement of Stock Material with QM (127)

Procurement & Consumption of Cosigned Inventory (139)

Str

ate

gi

c Pla

nn

er

Creating Planned Independent Requirements

ConvertPlanned Order to Production Order

Inventory Consumption @ Standard. Cost

Procurement w/o QM(130)

Finished Goods Receipt

MM Subcontracting (138)

PP-Subcontracting (External Processing)(150)

No

Yes

No

Yes

Logistics Planning (144)

1

Page 146: Module : PP (Production Planning)

Make-to-Stock Production – Discrete Industry – Process Flow DiagramPro

du

ctio

n

Su

perv

isor

1 Review Operation List

Even

t

Page 147: Module : PP (Production Planning)

Production Subcontracting (External Processing)

• Purpose − During the Manufacturing process, when a "Planned Order" for Production is

converted to a "Production Order", the system will check to see if there are any routing/work-center operations which require external processing. External processing is when you have individual production steps, that are operations or sub-operations, which are performed outside of your company by a vendor. This type of processing is particularly important for subcontracting. It can also provide a company with a feasible alternative to in-house processing, if capacity bottlenecks occur.

• Benefits − An outline agreement can specify that a certain operation of the production order

is executed by an external subcontractor on a regular basis− In the case of capacity bottlenecks, the assembly procedure of the finished

product can be assigned to a subcontractor• Key process flows covered

− Creating Purchase Order for External Processing− Goods Receipt for “subcontracting” Purchase Order− Enter Invoice− Periodic Payment

Purpose and Benefits:

Page 148: Module : PP (Production Planning)

Production Subcontracting (External Processing)

•Production Subcontracting (External Processing)− When a Production Order is scheduled, external operations need to be taken into account. The

duration of an external operation is calculated either by using the planned delivery time or using the standard values. The system automatically creates a purchase requisition for the operation or sub-operation that requires external processing. The Production scheduler should inform the buyer they need to check the workload for requisitions that require external processing.

− When data is maintained for an external activity, a cost element is specified. The cost element determines how the external activity is to be valuated. A decision needs to be made as to whether an operation or sub-operation is processed externally via its control key. In the control key, it is determined whether externally processed operations are scheduled on the basis of their standard values or the planned delivery time. This information is needed to settle externally processed operations and sub-operations that have been marked as relevant for costing in their control keys.

− Purchasing should not convert the purchase requisition until the external processing is required. The reason for this is that any quantity changes on the production order will automatically update the requisition.

− Once the purchase order is created it is printed and sent to the vendor. The purchase order informs the vendor which service is required. The buyer/planner/scheduler creates a manual shipping document and provides the information to the shipping department on what components need to be gathered for the external processing and ships the components to the vendor.

− When the vendor has completed the external processing, the material is shipped back. The warehouse clerk receives the externally processed goods back into the warehouse. The vendor service is reflected on the production order via an operation confirmation. The purchase order and the production order show the quantity received.

− The goods receipt of an externally processed material causes the status of the operation to be updated: For a partial delivery of an external process operation, the status is: EOPD (External operation - partial delivery) and for final delivery of a external process operation the status is: EOFD (External operation - final delivery).

Detailed Process Description:

Page 149: Module : PP (Production Planning)

Production Subcontracting (External Processing) – Process Flow DiagramP

urc

haser

Ven

do

rW

are

hou

se

Cle

rk

Create PO from Purchase Req (Vendor assigned by Info record)

Vendor Receives Material and Performs External Services

Ship Material to Vendor

Print Purchase Order

Subcontract Services GR/IR

PP = Production Planning, RFQ = Request for Quotation, PO = Purchase Order, GR/IR = Goods Receipt/Invoice Receipt, PPV = Purchase Price Variance

Ship External Material Back to Plant

Incoming Vendor Invoice

Completion Confirmation of Production Order

Production Order Generates Purchase Requisition for External Services

Goods Receipt for Subcontracting PO

Deliver Material Back to Shop Floor

Accou

nts

P

ayab

le

Accou

nta

nt

Even

t

Invoice Receipt

GR/IR PPV Vendor

Periodic Payment: Accounts Payable (158)

Perform External Services

Pro

du

cti

on

S

up

erv

isor

Check Order Operations

Page 150: Module : PP (Production Planning)

Rework Processing (Work-In-Process)

• Purpose − Processing of defective material on a production order.

• Benefits − Scraps at defined operation automatically trigger rework process.

− After rework, additional activity and material consumption can be confirmed.

− Fully integrated in the production process

• Key process flows covered− Confirming Production Activities

− Confirm Scrap defective material

− Confirm Parent Order at Rework Operation

− Continue Shop floor-Activities

Purpose and Benefits:

Page 151: Module : PP (Production Planning)

Rework Processing (Work-In-Process)

This scenario focuses on a rework process within production. All required rework activities are related to the parent production order. For this reason, errors are recognized and corrections initiated such as insertion of a rework operation within the same production order. The additional rework operation is confirmed and settled within the original production order, causing production variances within controlling and price differences for the dedicated product.

Detailed Process Description:

Page 152: Module : PP (Production Planning)

Rework Processing (Work-in-Process) – Process Flow DiagramS

hop

Flo

or

Sp

ecia

list

Even

t

Any Complaint Quantity to Be Scrapped?

Confirm Scrap Defective Material

Confirming Production Activities

No

End Process

Insert Rework Operation on Parent Production Order Automatically

Confirm Parent Production Order at Rework Operation for Non-Defective Quantity

Scrap Defective Quantity that Can’t Be Reworked

Confirm Parent Production Order for Reworked Quantity That Can Proceed to Subsequent Operations

Continue Shop-Floor-Activities for Non-Defective-Quantity

Yes

Page 153: Module : PP (Production Planning)

Rework Processing (Stock-Manufactured Material)

• Purpose − This process covers the rework of defective manufactured materials

that are found in the warehouse.

• Benefits − Transparent costs for rework activities

− Use of all standard shop-floor control functionalities is possible

• Key process flows covered− Create rework production order

− Goods issue for defective material

− Confirmation of rework production activities

− Posting goods receipt for rework production order

Purpose and Benefits:

Page 154: Module : PP (Production Planning)

Rework Processing (Stock-Manufactured Material)

•Rework Processing (Stock-Manufactured Material)•For materials that can be reworked, a production order is created for correcting the defect. The costs associated with the rework production order will be settled to profitability as a material variance.

Detailed Process Description:

Page 155: Module : PP (Production Planning)

Rework Processing (Stock-Manufactured Material) – Process Flow DiagramEven

tP

rod

ucti

on

P

lan

ner

Pro

du

cti

on

S

up

erv

isor

Ware

hou

se

Cle

rk

Create Rework Production Order

Identified Component in Stock Requires Changes

End Process

Confirmation of Rework Production Activities

Posting Goods Receipt for Rework Production Order

Goods Issue for defective Material

Sh

op

floor

Sp

ecia

list

Review Order Confirmations

Release Rework Production Order