Page 1: Module: Autonomation Element: Andon Systems Training Pack

Module: Autonomation

Element: Andon Systems

Training Pack

Page 2: Module: Autonomation Element: Andon Systems Training Pack

Target Audience : Operation Management

Purpose of Module : To explain what an Andon system is, and what are it’s links to performance improvements

Aims & Objectives :

• What are the benefits of an Andon system

• Explain the different types of Andon and appropriate uses

• Behaviours required to support Andon

• How to maintain the system

• Explain the importance of a robust escalation procedure

• How to set-up an Andon system

2

Aims & Objectives

Page 3: Module: Autonomation Element: Andon Systems Training Pack

• Current understanding of Andon

• What is Andon?

• Different forms of Andon

• What Andon does and doesn’t do

• Pre-requisites & features of an Andon System

• Types of Andon

• Examples of Andon

• Escalation Procedure

• Setting up an Andon System

• Guidelines

4

Agenda

Page 4: Module: Autonomation Element: Andon Systems Training Pack

5

Current understanding of Andon

Page 5: Module: Autonomation Element: Andon Systems Training Pack

DODO

Mgr

PUM

Shift Leader

Operator

Team Leader

Team Leader

Mgr

PUM

Shift Leader

Operator

SUPPORTHELP!

Andon is a tool for exposing abnormalities within the production process

6

What is Andon

Page 6: Module: Autonomation Element: Andon Systems Training Pack

What is Andon?

Andon is an information tool which provides instant, visible and audible warning to the Operations team that there is a

abnormality within that area.

7

Page 7: Module: Autonomation Element: Andon Systems Training Pack

An Andon can take many different forms from simple indicator to complex control boards. All of them give

‘real time’ status of the performance of the given area

1 2 3 4 5 6

1 2 3 4 5 6

1 2 3 4 5 6

8

NO

A

Different forms of Andon

Page 8: Module: Autonomation Element: Andon Systems Training Pack

Andon allows timely corrective actions by alerting personnel when abnormal conditions occur.

Allows Shop floor T/L’s to spend less time and effort monitoring the situation, and more time solving abnormalities.

Allows Operation teams to monitor equipmentand personnel more effectively.

It can act as a 2 way communication device e.g. When indicator returns to green; this tells everybody it’s ‘back to normal’

9

What an Andon system does..

Page 9: Module: Autonomation Element: Andon Systems Training Pack

Solve Abnormalities

Prevent all defects from being passed forward

Replace good verbal communication between work group

Remove the need for rectification or Customer protection

10

It doesn’t:-

What an Andon system doesn’t do

Page 10: Module: Autonomation Element: Andon Systems Training Pack

Andon will not SOLVE Abnormalities, it can only highlight them

Andon can only be effective if the team leader is backed up by an issue resolution procedure

11

Cell Leader

Team Leader

Team Leader

Team Leader

Team Leader

Team Leader

+Team

J. Bloggs

LogisticsI Moveit

Tel: 12345

MaintenanceM. Fixit

Tel: 24345 EngineerJohn Doe

Tel: 12645

Material MangementTheresa Green

Tel: 90272

Support TeamGeorge Stubbs

Tel: 11145

SLA’s

SLA’s

SLA’s

SLA’s

SLA’s

Pre-requisites for an Andon system

Page 11: Module: Autonomation Element: Andon Systems Training Pack

Visible/Audible - Can be seen and/or heard by entire workgroup and workgroup leader

Concise/Understandable - Primary three conditions (OK, Abnormality, Process stop)

Timely/Responsive - Real-time data

Pertinent - Only shows status of workstations in a particular area

Complete - Provides a complete picture of the overall status of the entire area to enable prioritisation and coordination of corrective efforts

12

Features of an Andon system

Page 12: Module: Autonomation Element: Andon Systems Training Pack

The 2 main types of Andon are activated manually by the operator/ Team leader by either:

i) pressing static button

ii) pulling a cord

It can be used to highlight either production or maintenance concerns.

13

Types of Andon system

Page 13: Module: Autonomation Element: Andon Systems Training Pack

FlowFixed PositionStop switch

Andon Light

14

Used by operators to gain assistance

Once activated the line will stop at a predetermined position

Can be used in sub assembly

Attend button lights, whilst awaiting assistance (main board also activated)

Attend button turned off when Abnormality solved (main board also de-activated)

Fixed Position Stop

Page 14: Module: Autonomation Element: Andon Systems Training Pack

Cords often used on a moving line (7 wastes)

Highlights concern at a specific workstation (Team Beacon)

Andon turned off by pulling cord for a second time(Team Leader or Cell Leader)

If Andon is not turned off, process will stop at the end of the cycle

15

Moving Line stop

Page 15: Module: Autonomation Element: Andon Systems Training Pack

Manual Operator pushes button or pulls a cord - Material call example - Quality check, change over, etc.

Automatic A limit switch on a conveyor or on a chute monitoring movement of parts

Limit switch may monitor time and count the number of parts passing through. (takt time) Andon can be activated by an error proofing device Separate the man from the machine, freeing up the operator to add value else where (Machine shop)

16

Types of Andon Trigger

Page 16: Module: Autonomation Element: Andon Systems Training Pack

Simple Andon System

18

Examples of Andon Boards

Page 17: Module: Autonomation Element: Andon Systems Training Pack

Escalation Procedure

20

An issue has arisen It is threatening process Completion

We need outside help

We are on plan

There are no issues No Action

No Action

No Action GREEN

We will not complete our process on time

T/L turns light on

Mgr calls : Eng / Log / QA / PUM or Recovery Team

Mgr QA……………

RED

CONDITION WHOACTION NAMED RESPONSE

Op turns light on

T/L calls : Eng / Log / QA / PUM or Recovery T/L Ref: SLA

TEAM LEADER

Log…………

Other…………

AMBER

and contacts PUM Eng……………

Andon criteria

Page 18: Module: Autonomation Element: Andon Systems Training Pack

Stage 1Once a abnormality is identified it is escalated to the next level to eliminate itIf next level cannot eliminate it, then raise it to Shift Leader

21

Team Leader

Mgr

D/Mgr

Shift Leader

Operator

HELP! SUPPORT

Escalation process

Page 19: Module: Autonomation Element: Andon Systems Training Pack

Stage 2 Once all effort to solve the problem have been exhausted at Shift Leader level, the problem is escalated to the highest level to avoid the line stopping

22

Team Leader

Mgr

D/Mgr

Shift Leader

Operator

HELP! SUPPORT

Escalation process

Page 20: Module: Autonomation Element: Andon Systems Training Pack

23

WHO - Operations Team

WHAT - Operations team must determine what production conditions need to be monitored, and what Andon system meets their needs.

WHERE - Divide the operation into several processes stations and assign each a process number or code and owner.

• Usually a small team per process number or code• Post process numbers or codes at line side stations

WHEN - The Andon system should only be installed after a robust

escalation procedure has been implemented

WHY - To enable Operation teams to expose abnormalities with their process, to help them eliminate them.

HOW - Document what the characteristics of the production line are and gather data history for the line

• Establish Andon Procedures• Audit procedure

Setting up an Andon system

Page 21: Module: Autonomation Element: Andon Systems Training Pack

Appropriate use of the Andon is fundamental in highlighting Abnormalities.

Ultimately we want to eliminate abnormalities from occurring

• Removing the causes of Abnormalities and not just responding to the effects. • By analysing data and frequency of Andon pulls by operator, the workgroups can identify and focus on improving, abnormality / bottleneck areas.

24

Lean Enterprise function of Andon Systems

Page 22: Module: Autonomation Element: Andon Systems Training Pack

• Andon systems should be thought out and appropriate in design to be effective.

• Andon systems should be implemented when and only when an appropriate support system and escalation procedure is in place (Service Level Agreements, problem solving process etc.)

• Andon signals should be simple and easy to understand

• Avoid spending too much money on a ‘State of the art’ Andon System, prove the system out with a simple manual system to judge it’s worth

25

Guidelines

Page 23: Module: Autonomation Element: Andon Systems Training Pack

Ensure the Andon system is visible / audible from every corner of the workplace, to the relevant work area

Once established, monitor closely the response times from the support functions and Andon pulls

Andon systems don’t solve abnormalities, it only highlights them in time to rectify the situation quickly.

26

Guidelines

Page 24: Module: Autonomation Element: Andon Systems Training Pack

Where do you think Andon Systems could be used?

27

Opportunities