module-6

12
1 Module-6: Environmental Management Plan and Stakeholder Consultation Irfan-ul-Haq & Imran-ul-Haq ENVIRONMENTAL IMPACT ASSESSMENT OBJECTIVES OF EMP Outlining the mitigation measures required for avoiding or minimizing the potential impacts assessed by EIA Developing a monitoring mechanisms and identifying the requisite monitoring parameters to confirm effectiveness of the mitigation measures recommended in the EIA Defining roles and responsibilities of the Project proponent for the implementation of EMP and identifying areas where these roles and responsibilities can be shared with other parties involved in the execution and monitoring of the Project Defining the requirements necessary for documenting compliance with the EMP and communicating it to all the concerned regulatory agencies Prescribing the mechanisms with which consultation with stakeholders during the project will be maintained

Upload: engr-muhammad-sohail

Post on 08-Nov-2015

218 views

Category:

Documents


0 download

DESCRIPTION

GHGHG

TRANSCRIPT

  • 1

    Module-6: Environmental Management Plan and Stakeholder Consultation

    Irfan-ul-Haq & Imran-ul-Haq

    ENVIRONMENTAL IMPACT ASSESSMENT

    OBJECTIVES OF EMP

    Outlining the mitigation measures required for avoiding or minimizing the potential impacts assessed by EIA

    Developing a monitoring mechanisms and identifying the requisite monitoring parameters to confirm effectiveness of the mitigation measures recommended in the EIA

    Defining roles and responsibilities of the Project proponent for the implementation of EMP and identifying areas where these roles and responsibilities can be shared with other parties involved in the execution and monitoring of the Project

    Defining the requirements necessary for documenting compliance with the EMP and communicating it to all the concerned regulatory agencies

    Prescribing the mechanisms with which consultation with stakeholders during the project will be maintained

  • 2

    Legislations and guidelines

    Organizational structure and roles and responsibilities

    Mitigation and management matrix

    Compensation plan

    Environmental monitoring program

    Site Restoration Plan

    Communication and documentation

    Change management plan

    Traffic management plan

    Material transportation plan

    Plantation plan

    Training program

    STRUCTURE OF EMP

    Identification of Environmental Studies related laws

    Identification of implementing agency

    Review of requirements for EIA/IEE

    Review of procedures for carrying out the studies

    Review of documentation requirements

    Review of submission requirements

    Review of procedures for obtaining No Objection Certificate (NOC)

    LEGISLATION AND GUIDELINES

  • 3

    Identification of organizations and their organization structure

    Identification of requirements of Independent Monitoring Consultant (IMC)

    Defining responsibilities during different phases of the project typically:

    Planning and design of operation including the approvals and contractual provisions

    Implementation during the operation including the coordination between stakeholders, EMS, monitoring,, emergency procedures, approvals, training, and communication and documentation, and site restoration

    ROLES AND RESPONSIBILITIES

    The required mitigation measures recommended in EIA The person/organization directly responsible for adhering to or executing the

    required mitigation measures The person/organization responsible for ensuring and monitoring adherence

    to the mitigation measures The parameters which will be monitored to ensure compliance with the

    mitigation measures The timing at which the mitigation or monitoring has to be carried out

    MITIGATION MANAGEMENT MATRIX

  • 4

    MITIGATION MANAGEMENT MATRIX

    COMPENSATION PLAN

    Compensation Plan is required to be developed for:

    Compensate the owners of

    houses, tourists restaurants, agricultural area to be affected

    For transportation of

    shiftable assets like electric poles, transformers, electric wires etc.

  • 5

    SITE RESTORATION PLAN

    Site Restoration Plan will include: Identification of affected areas including construction area, camp sites tracks,

    land used etc . Restoration of affected areas with maximum possible effort May include the following activities: All temporary construction built for the dam construction will be removed. All the toxic and hazardous chemicals/materials will be completely removed

    form the site. Efforts will be made to completely remove the spills during the construction

    All fencing and gates will be removed and pits will be backfilled Whole site will be covered with the original soil and revegetation will be done,

    wherever required Site Inspection by IMC or Client is an important consideration

    To check compliance with the requirements of the EMP by monitoring activities of the project contractors on a daily basis.

    To ascertain residual impacts of the operation. This will be achieved by post-project monitoring

    ENVIRONMENTAL MONITORING PLAN

  • 6

    MONITORING PLAN FOR PHYSICAL ENVIRONMENT

    Kick-off Meeting

    Meetings and Reports

    Monthly Environmental Report

    Effects Monitoring Reports

    Social Complaints Register

    Change Record Register

    Non-Compliance Record Register

    Final Monitoring Report

    Photographic Record

    COMMUNICATION AND DOCUMENTATION PLAN

  • 7

    Additions to the EMP

    Changes to the Operation

    First Order

    Second Order

    Third Order

    CHANGE MANAGEMENT PLAN

    Diversion of traffic (If required)

    Management of construction activities to minimize the traffic problems

    To be discussed with officials before finalization like SSP Traffic Police

    Example of Zero Point Interchange where a three stage TMP has been followed.

    TRAFFIC MANAGEMENT PLAN

  • 8

    Material Transportation Plan is prepared in such a way that there is minimum hindrance to the local communities and to maintain flow of traffic

    HSE arrangements and proper documentation have been planned in order to achieve the above objective as follows:

    Material Transportation HSE Arrangements

    Material Transportation Documentation

    MATERIAL TRANSPORATION PLAN

    Total number of plants alongwith break up

    Following should be specified:

    Location of plantation to be specified

    Species of the plants

    Spacing of the plants

    Plan preferable be presented in the form of a figure

    Cost of plantation should also be estiamted

    PLANTATION PLAN

  • 9

    It should include the following:

    Cost of compliance monitoring

    Cost of effects monitoring

    Cost of tree plantation

    Associated salary and direct costs

    ENVIRONMENTAL COSTS

    The key objective of training program is to ensure that the requirements of the EMP are clearly understood and followed throughout the project. The trainings to the staff will help in communicating environmental related restrictions specified in the EIA and EMP.

    Defining roles and responsibilities

    Developing a programme

    Maintaining a training log

    Training needs assessment and training material

    TRAINING PROGRAMME

  • 10

    TRAINING PROGRAMME

    TYPICAL STAKEHOLDERS Local People Proponent and project beneficiaries Government Agencies NGOs Donors and Private sector Academeies OBJECTIVES OF PUBLIC INVOLVEMENT Informing stakeholders Presentation of views, concerns and values Maximizing benefits Influencing project design Obtaining local knowledge Increasing Public confidence Better transparency and accountability in decision making Less Conflict

    Stakeholder Consultation

  • 11

    LEVELS OF PUBLIC INVOLVEMENT Informing (One way: PROPONENT TO PUBLIC) Consulting (Two way flow: PROPONENT TO

    PUBLIC TO PROPONENT) Opportunities for the public to express views Participating Proponent and the public share analysis and

    agenda setting Public involved in decision making through

    consensus PRINCIPLES FOR SUCCESSFUL PUBLIC

    INVOLVEMENT Provide sufficient relevant info Allow sufficient time to read and discuss Allow sufficient time to present views Provide responses to issues/problems raised Choose venues and times of events to suit

    stakeholders

  • 12

    Thank You