module-6
DESCRIPTION
GHGHGTRANSCRIPT
-
1
Module-6: Environmental Management Plan and Stakeholder Consultation
Irfan-ul-Haq & Imran-ul-Haq
ENVIRONMENTAL IMPACT ASSESSMENT
OBJECTIVES OF EMP
Outlining the mitigation measures required for avoiding or minimizing the potential impacts assessed by EIA
Developing a monitoring mechanisms and identifying the requisite monitoring parameters to confirm effectiveness of the mitigation measures recommended in the EIA
Defining roles and responsibilities of the Project proponent for the implementation of EMP and identifying areas where these roles and responsibilities can be shared with other parties involved in the execution and monitoring of the Project
Defining the requirements necessary for documenting compliance with the EMP and communicating it to all the concerned regulatory agencies
Prescribing the mechanisms with which consultation with stakeholders during the project will be maintained
-
2
Legislations and guidelines
Organizational structure and roles and responsibilities
Mitigation and management matrix
Compensation plan
Environmental monitoring program
Site Restoration Plan
Communication and documentation
Change management plan
Traffic management plan
Material transportation plan
Plantation plan
Training program
STRUCTURE OF EMP
Identification of Environmental Studies related laws
Identification of implementing agency
Review of requirements for EIA/IEE
Review of procedures for carrying out the studies
Review of documentation requirements
Review of submission requirements
Review of procedures for obtaining No Objection Certificate (NOC)
LEGISLATION AND GUIDELINES
-
3
Identification of organizations and their organization structure
Identification of requirements of Independent Monitoring Consultant (IMC)
Defining responsibilities during different phases of the project typically:
Planning and design of operation including the approvals and contractual provisions
Implementation during the operation including the coordination between stakeholders, EMS, monitoring,, emergency procedures, approvals, training, and communication and documentation, and site restoration
ROLES AND RESPONSIBILITIES
The required mitigation measures recommended in EIA The person/organization directly responsible for adhering to or executing the
required mitigation measures The person/organization responsible for ensuring and monitoring adherence
to the mitigation measures The parameters which will be monitored to ensure compliance with the
mitigation measures The timing at which the mitigation or monitoring has to be carried out
MITIGATION MANAGEMENT MATRIX
-
4
MITIGATION MANAGEMENT MATRIX
COMPENSATION PLAN
Compensation Plan is required to be developed for:
Compensate the owners of
houses, tourists restaurants, agricultural area to be affected
For transportation of
shiftable assets like electric poles, transformers, electric wires etc.
-
5
SITE RESTORATION PLAN
Site Restoration Plan will include: Identification of affected areas including construction area, camp sites tracks,
land used etc . Restoration of affected areas with maximum possible effort May include the following activities: All temporary construction built for the dam construction will be removed. All the toxic and hazardous chemicals/materials will be completely removed
form the site. Efforts will be made to completely remove the spills during the construction
All fencing and gates will be removed and pits will be backfilled Whole site will be covered with the original soil and revegetation will be done,
wherever required Site Inspection by IMC or Client is an important consideration
To check compliance with the requirements of the EMP by monitoring activities of the project contractors on a daily basis.
To ascertain residual impacts of the operation. This will be achieved by post-project monitoring
ENVIRONMENTAL MONITORING PLAN
-
6
MONITORING PLAN FOR PHYSICAL ENVIRONMENT
Kick-off Meeting
Meetings and Reports
Monthly Environmental Report
Effects Monitoring Reports
Social Complaints Register
Change Record Register
Non-Compliance Record Register
Final Monitoring Report
Photographic Record
COMMUNICATION AND DOCUMENTATION PLAN
-
7
Additions to the EMP
Changes to the Operation
First Order
Second Order
Third Order
CHANGE MANAGEMENT PLAN
Diversion of traffic (If required)
Management of construction activities to minimize the traffic problems
To be discussed with officials before finalization like SSP Traffic Police
Example of Zero Point Interchange where a three stage TMP has been followed.
TRAFFIC MANAGEMENT PLAN
-
8
Material Transportation Plan is prepared in such a way that there is minimum hindrance to the local communities and to maintain flow of traffic
HSE arrangements and proper documentation have been planned in order to achieve the above objective as follows:
Material Transportation HSE Arrangements
Material Transportation Documentation
MATERIAL TRANSPORATION PLAN
Total number of plants alongwith break up
Following should be specified:
Location of plantation to be specified
Species of the plants
Spacing of the plants
Plan preferable be presented in the form of a figure
Cost of plantation should also be estiamted
PLANTATION PLAN
-
9
It should include the following:
Cost of compliance monitoring
Cost of effects monitoring
Cost of tree plantation
Associated salary and direct costs
ENVIRONMENTAL COSTS
The key objective of training program is to ensure that the requirements of the EMP are clearly understood and followed throughout the project. The trainings to the staff will help in communicating environmental related restrictions specified in the EIA and EMP.
Defining roles and responsibilities
Developing a programme
Maintaining a training log
Training needs assessment and training material
TRAINING PROGRAMME
-
10
TRAINING PROGRAMME
TYPICAL STAKEHOLDERS Local People Proponent and project beneficiaries Government Agencies NGOs Donors and Private sector Academeies OBJECTIVES OF PUBLIC INVOLVEMENT Informing stakeholders Presentation of views, concerns and values Maximizing benefits Influencing project design Obtaining local knowledge Increasing Public confidence Better transparency and accountability in decision making Less Conflict
Stakeholder Consultation
-
11
LEVELS OF PUBLIC INVOLVEMENT Informing (One way: PROPONENT TO PUBLIC) Consulting (Two way flow: PROPONENT TO
PUBLIC TO PROPONENT) Opportunities for the public to express views Participating Proponent and the public share analysis and
agenda setting Public involved in decision making through
consensus PRINCIPLES FOR SUCCESSFUL PUBLIC
INVOLVEMENT Provide sufficient relevant info Allow sufficient time to read and discuss Allow sufficient time to present views Provide responses to issues/problems raised Choose venues and times of events to suit
stakeholders
-
12
Thank You