Welcome to Worley Parsons Project Management Training

Module 4 – Project Delivery Systems

Page 2: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

INTRODUCTION

Page 3: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

About this training session

Learning objectives

Overview of project delivery systems

Finance, Administration and HR tools

Project Management and Control tools

Engineering and Design tools

Data Management and Communication tools

Selecting appropriate project delivery tools

Project delivery system reports

Page 4: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Learning Objectives

On completion of this module, you will be able to : understand the Project Delivery Systems used at WorleyParsons to

manage projects request and interpret project reports in order to provide status reports and

track progress and performance against budget and schedule identify the key systems and their interfaces (information flows) to enable

effective project management identify, assess and select Project Delivery Systems for specific projects

and be familiar with the functions of these tools explain the functionality of the function specific tools selected by

WorleyParsons to improve the efficiency of project execution and communicate this information to the project team

consult with the location systems support personnel and where required with the Global Project and Improve Systems (PAIS) and Engineering Systems (ES) groups to set-up and configure the project delivery tool(s) for a specific project.

Page 5: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

OVERVIEW OF PROJECT DELIVERY SYSTEMS

Page 6: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

WorleyParsons Strategy

WorleyParsons Executive Committee (Exco) has endorsed the rollout of a consistent set of processes.

• WPMP: WorleyParsons Project Management Process – the WorleyParsons framework for project execution.

• EMS: Enterprise Management System – repository of standard workflows, procedures and templates.

Page 7: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

WorleyParsons Strategy

ExCo has also endorsed the rollout of a consistent suite of project delivery systems with the following strategy:

Reduce the variety of systems, processes and tools

Provide access to WorleyParsons knowledge

Facilitate multiple office work sharing

Page 8: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Overview of Project Delivery Systems

Page 9: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Overview of Project Delivery Systems

Factors that determine choice of tools from WorleyParsons’ suite include:

• type of services

• size of project

• complexity of transactions and data to be managed

Use of standard tool kit will be the most economical and efficient outcome

Customers may have their preferences but any change to the standard tool kit to satisfy customer preferences will have cost and schedule penalties

Page 10: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Overview of Project Delivery Systems

As a Project Manager you will need to know :

what tools to use for different types of projects

what tools to use to complete different functions

how information flows between the tools so that you can use them effectively to manage and control each project

how to work with the systems support personnel to set-up and configure the project delivery tools for each project.

Page 11: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

FINANCE AND ADMINISTRATION TOOLS(Supported by the GBS Team)

Page 12: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems - GBS

Page 13: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

GBS is being rolled out to replace all existing Finance and HR management systems.

Single Environment• “On Demand” service from Oracle• Globally accessible

New modules for • Projects• Finance• HR

Interfaces with Global Standard WorleyParsons systems• InControl (service costs)• Prediction + (contractor costs)• SmartPlant Materials (committed costs and vendor invoices)

Rollout of GBS across the WorleyParsons locations

GBS

Page 14: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Initiate projects and proposals• Classify projects and proposals• Register project data

Time Management System• Collect EPCM service costs through the Time Management

System

Finance Systems• Collate actual service costs• Transfer to payroll and project control systems

HR Systems• Store and manage employee data

What does GBS do?

GBS

Page 15: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

PROJECT MANAGEMENT AND CONTROL TOOLS(Supported by PAIS)

Page 16: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems – Project Controls

Page 17: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems - Estimating

• Aspen Capital Cost Estimator (ACCE) for the SELECT business line Identify and Evaluate Phases

• Quest Capital Cost Estimator for Class 2 to Class 4 estimates

• @Risk for risk modelling and analysis

Phas

eEs

timat

ing

Tool

sEVALUATE DEFINE EXECUTE OPERATEIDENTIFY

Aspen Capital Cost Estimator

Quest

@Risk

Page 18: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

ACCE

What does ACCE do?

Supports the generation of conceptual and detailed cost estimates and schedules over the project lifecycle.

Creates accurate budgets from conceptual definitions

Configured to optimize utilities and piping as well as project relocation and scaling based on plant size.

Its ability to define contract structures for multiple contractors and vendors helps project leaders analyse execution strategies, manage change orders and control costs.

Page 19: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

ACCEWhat are the benefits of ACCE?

Consistency and common knowledge base Speed in calculating and producing estimate with minimal input Area specific estimates (i.e. different specs.) can be combined Built-in “Expert Systems” for equipment foundations and pipe rack design

build Detailed material and labour indexing - easy adjustment of material costs

and labour hours Users can manually add any amount of items required that are not offered by

default Library / manual (user) input info storage Flag “illegal” and “out of range" entries Manpower Productivity Expert (MPE) module to examine productivity

differences due to working conditions, location and environmental factors Output is compatible for use with risk analysis tool Many reports to choose from

Page 20: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Quest

What does Quest do?

Aids in the preparation of major capital cost estimates.

Can help relieve the estimator of much of the number crunching that is inherent in the generation of an estimate.

Enhances the quality of estimates by automating the calculations within a disciplined structure and eliminating a major source of estimate errors.

Page 21: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Quest

What are the benefits of Quest? Automatic retrieval of industry standard information

Maximised computer calculation – reducing possible estimating errors

Automated budget consolidation

Ability to create multiple versions of an estimate to address different cases or options

Can be used to identify estimate trends during project implementation

Incorporates contracting philosophy and procurement plan for easy roll over to Cost Control

Aligned to coding (Code of Accounts) in other systems for easy transfer of data and single point data entry

Page 22: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

@Risk

What does @Risk do?

Aids in the preparation of major capital cost estimates.

An Excel add-in that allows users to perform simulations and is typically used in the Evaluate, Define and Execute phases of a project for risk analysis.

Proven templates and reports – able to be shared between specialists in all WorleyParsons locations. An estimator can assess the likelihood of various best and worst case project budget scenarios.

Uses Monte Carlo-based simulation to run many possible outcomes.

Page 23: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

@Risk

What are the benefits of @Risk ? Adds advanced modelling and risk analysis to Microsoft excel by

allowing:

• Development of the risk model – WorleyParsons uses its own model, tested and proven on many projects

• Identification of uncertainty – risk inputs

• Model analysis by simulation – risk outputs

Page 24: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems – Cost Control

• Services Cost and Progress Control in all phases

• PREDICTION + for TIC Cost Control and Construction Job Card Management

EVALUATE DEFINE EXECUTE OPERATEIDENTIFY

InControl

PREDICTION+

Phas

eC

ost T

ools

Page 25: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

What does InControl do?

Specialist project services cost and progress control tool.

Built around WorleyParsons’ processes and procedures to allow projects to manage costs against budget, track progress, control scope and determine forecast in one place.

Brings together project budget costs, schedule and document data into a single repository.

Provides weekly, monthly and adhoc reports that are the cornerstone for the project controls group to advise project management on its status at any point in time.

InControl

Page 26: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

What are the benefits of InControl?

WBS and discipline level control Detailed deliverable progress and forecast tracking Detailed resource budget control Variation management Productivity, earned value reporting Multi-currency reporting Interfaces with timekeeping and financial systems Interfaces with planning system

InControl

Page 27: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

PREDICTION +

What does PREDICTION + do?

WorleyParsons owned integrated Project Management tool

Manages all aspects of Project controls for standalone projects or program/portfolio works.

Consists of a series of integrated application modules that communicate with each other through a centralised database that controls the flow and management of data.

PCS module provides real-time Total Installed Cost (TIC) and progress measurement management for projects and contracts.

Page 28: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

PREDICTION +

What are the benefits of PREDICTION +? Project/program/portfolio details repository

Activities/transactions/deliverables repository

Total Install Cost (TIC) budget generation, control, forecasting and reporting

Project cost/commitments/expenditure reporting, KPIs and dashboards

Earned value/progress/forecasting

Cash flow management and invoicing

Change/variation management

Interfaces with engineering, materials, time, financial and planning systems

Page 29: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems - Planning

• Oracle Primavera 6 for logic based Planning and Schedule Control for all phases

• Oracle Primavera Risk for Schedule Risk Analysis for all phases

EVALUATE DEFINE EXECUTE OPERATEIDENTIFY

Primavera P6

Primavera Risk

Phas

ePl

anni

ng T

ools

Page 30: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Primavera P6

What does Primavera P6 do? Used for the development of a schedule/program for all

phases of projects.

Industry standard application suite - delivers full enterprise project portfolio management throughout the project lifecycle and across a range of project sizes and complexity.

Commercial planning application with an extensive range of functions including:

• logic based networking • critical path analysis • resource scheduling • import /export capabilities.

Page 31: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Primavera P6

What are the benefits of Primavera P6?

Provides integration capability with other systems

Enables us to deliver projects on time and within budget

Has import / export capabilities

Has powerful and configurable dashboards

Page 32: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Primavera Risk

What does Primavera Risk do? Simulates various scenarios using built-in templates for

qualitative/quantitative risk assessment, like quick risk feature and risk register configured to align to WorleyParsons risk management practices.

Primavera Risk Analysis uses advanced Monte Carlo-based cost and schedule analytics to provide full life-cycle risk management through the following types of risk models:

• estimate uncertainty,• task existence,• probabilistic branching,• fixed-cost uncertainty,• variable-cost uncertainty,• resource uncertainty,• conditional branching,• weather modelling.

Page 33: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Primavera Risk

What are the benefits of Primavera Risk?

Identifies common scheduling pitfalls that may result in misleading schedule or risk analysis results

Provide a comprehensive means of reporting project confidence levels

Page 34: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

COFFEE BREAK

Page 35: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

PROCUREMENT ANDCONTRACTS TOOLS

(Supported by PAIS)

Page 36: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems – Procurement and Contracts

Page 37: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems - Procurement

• SmartPlant Materials (SPM) for Materials Management

• CAMS for detailed administration of contracts

• Supplier Portal - Supplier registration portal for supplier registration, invitation, evaluation and selection

• Trade Wizard – Live solutions to International trade queries and compliance.

• RPS On-Demand – screening of customer, suppliers and other trading partners against restricted party lists from government institutions worldwide.

Page 38: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SmartPlant Materials

What does SmartPlant Materials do?

• SmartPlant Materials (SPM) provides control of materials and equipment through the Engineering, Procurement and Construction (EPCM) phases of a project.

Page 39: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SmartPlant Materials

What are the benefits of SmartPlant Materials? All specialist items, long lead items, large items, including equipment

can be fully managed and include links to specifications, drawing and data sheets.

Consistent equipment and item numbering, including corporate catalogues for bulk materials

Project-specific vendor lists

Totalling of items by part, description and vendor

Separate or multiple fabrication shops for materials supporting projects with multiple fabricators by geographic areas

Continuous material reconciliation

Global project work sharing and execution, using correct, complete, and consistent data.

By using a web-based and centralised environment, SPM allows a central synchronisation of a decentralised project organisation.

Page 40: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SmartPlant Materials (SPM)

4 integrated modules

SPRDSmartP

lant Reference Data

Page 41: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SPRDSmartP

lant Reference Data

SmartPlant Materials (SPM)

Provides material libraries at both corporate and project levels for use for materials revision and change management

Includes a Project Estimating functionality that you can use to generate estimates for new project bids

Historical SmartPlant Materials project data can be accessed to develop first estimates based on previous projects.

Enables corporate (project-independent) material data standardization, especially of bulk material. Data can be organized to suit the required corporate or country standards.

Data can be fed into design systems such as Plant Design System or Plant Design Management System

SmartPlant Reference Data (SPRD)

Page 42: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SPRDSmartP

lant Reference Data

SmartPlant Materials (SPM)Engineering &Procurement

Integration (E&PI)

Presents the most recent status of material items in the project so that you to control the flow of materials to avoid surpluses and shortages

Based on past experience of material usage and requisition patterns, rule-driven processes enable EPIM to automatically create material requisitions, translating the project engineering view into the project procurement view

Page 43: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SPRDSmartP

lant Reference Data

SmartPlant Materials (SPM)Material Supply Chain Management (MSCM)

Integrates interchanges between commodity suppliers, manufacturers, fabricators and freight forwarders

MSCM data can be integrated with the financial systems such as SAP or Oracle to control payment and invoicing

All procurement and relevant supply chain information is in the same database

Paperless integration of supplier performance and history measurement, supplier management, inquiry cycle, bid tabulation, purchase order/award, scheduling, progress/milestone control, tracking/tracing

Page 44: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SPRDSmartP

lant Reference Data

SmartPlant Materials (SPM)

Balances onsite personnel with material availability, assigning material to site inventories in the shortest possible time

Automated material receiving, forecasting, reservation, and allocation routines to control and manage materials in various site warehouses

SITE

Page 45: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

CAMS

What does CAMS do?

Provides visibility into contracts, providing opportunities to identify cost savings, mitigate risk and improve compliance.

Functions include recording invoices, back-charges, claims and field instructions, monitoring compliance items and milestones, generating payment certificates and amending/revising contracts.

Uses task and event management, performance metrics, compliance monitoring, budget analysis, amendments, change orders, and contract correspondence.

Allows projects to centralise all contract packages and information, enabling collaboration across locations, supporting projects to share work across locations using the same core systems.

Page 46: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

CAMS

What are the benefits of CAMS?

Full-scope contract management solution - from ‘request for information’ through the stages of contract creation, administration management, revenue/expense processing, and renewal cycles

The task and event alerts allow the contract manager to monitor the ongoing performance of the contract.

Central control and distributed management – with standard terms and conditions defined centrally and ‘localised’ including the ability to translate the contract into other languages

Management reporting - via the Internet with security access Compliance monitoring - items identified as requiring some form of

compliance can be tracked Generation of payment certificate within the application, tracking total

cost approved, remaining balance, recovery of advance payments, accounting for retention withheld etc.

Page 47: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Supplier Portal

What does Supplier Portal do? Secure online registration process that captures the relevant information

to support Supplier registration, invitation, evaluation and selection through to performance rating.

Page 48: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Supplier PortalWhat are the benefits of Supplier Portal?

Supplier self registration via External Web Portal One global database Web-based application enables easy access remotely Performance rating tracked against Supplier on project Knowledge at hand if Supplier is engaged in another project Follows a step process from Invited to Committed on each

Supplier Instant accessibility for all the project team Quick online training available immediately System Security – granular levels of access Provides a secure and accessible location for approved Supplier

records Supplier information available across locations/countries for

Workshare

Page 49: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Trade Wizard

What does Trade Wizard do? Single function, browser-based interactive query tool that can

provide quick answers to specific international trade related queries.

Powered by the industry's most comprehensive and robust database of global trade content for over 120 countries.

This content is sourced and analysed by the global content team at Management Dynamics Inc.

Page 50: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Trade Wizard

What are the benefits of Trade Wizard? Calculate the landed cost for a transaction including duties,

taxes, custom fees, port charges and all other import taxes Pay correct duties, often reducing total customs charges Take advantage of preferential trade programs

Page 51: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

RPS On-Demand

What does RPS On-Demand do? Restricted Party Screening (RPS) provides a secure and

comprehensive method to quickly screen customers, suppliers and other trading partners against all restricted party lists from government institutions worldwide.

Prevents any illegal transactions with restricted entities or trade parties and avoid penalties.

Significantly reduces our corporate risk, liability and exposure to prohibited transactions.

Page 52: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

RPS On-Demand

What are the benefits of RPS On-Demand? Complies with international trade regulations Accurately identifies restricted parties before goods are

shipped Prevents illegal transactions with band trading partners Preserves a complete audit trail Reduces corporate risk Avoids fines, penalties & sanctions

Page 53: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

CONSTRUCTION ANDCOMPLETIONS TOOLS

(Supported by PAIS)

Page 54: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction and Completions

Page 55: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems:Construction and Completions

• PREDICTION+ JCS - Job Card Management System

• CMT – Completions Management Tool

• RFI – Electronic Management of Site Queries

EVALUATE DEFINE EXECUTE OPERATEIDENTIFY

PREDICTION+ JCS

CMT

Site Query Tool [RFI]

Phas

eC

onst

ruct

ion

&

Com

plet

ions

Too

ls

Page 56: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

PREDICTION+ JCS

What does PREDICTION+ JCS do?

WorleyParsons owned integrated Project Controls tool - manages all aspects of Project controls for standalone projects or program/portfolio works.

Consists of a series of integrated application modules that communicate with each other through a centralised database that controls the flow and management of data.

The Job Card System (JCS) module is a structured low level tool which provides real-time management of the fabrication, construction and commissioning phases of the projects or program/portfolio works.

JCS is also suitable for planning and controlling Turnaround/Shutdown scopes of work.

Page 57: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

PREDICTION+ JCS

What are the benefits of PREDICTION+ JCS?

Acts as a Job Card/Work Pack repository Can manage:

• estimating norms (hours/unit rates) and CTR generation• materials and drawings references/details and attachments • HSE/risk/QA/QC references/details and attachments• plant/equipment and resource allocation/assignment• manhours expenditure and quantities installed• and report on progress, performance and productivity

Page 58: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

PREDICTION+ JCS

What are the benefits of PREDICTION+ JCS?

Acts as a Job Card/Work Pack repository Can manage:

• estimating norms (hours/unit rates) and CTR generation• materials and drawings references/details and attachments • HSE/risk/QA/QC references/details and attachments• plant/equipment and resource allocation/assignment• manhours expenditure and quantities installed• and report on progress, performance and productivity

Page 59: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

CMT

What does CMT do?

An enterprise application system specifically developed to provide preparation and execution management for field commissioning activities and to support the WorleyParsons Completions Framework.

The combination of the Framework and CMT provides the methodology and functionality for a seamless start up on typical projects.

Page 60: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

CMT

What are the benefits of CMT?

It is an enterprise software tool customized for WorleyParsons Built around a SQL database giving access remotely via internet Has layered security – network, SQL, application group and user level Can store and produce completions handover and turnover requirements Can manage test results – ( A&B check sheets etc.) Enables “intelligent” commissioning procedure status reporting Provides a facility for punch list management and tracking Can facilitate the management of equipment preservation Provides facility to manage as-builts

Page 61: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

RFI

What does RFI do?

Electronically manages all technical questions/ queries This system is the vehicle that will circulate the query from

initiation to resolution via the email system Basis for reporting of quality performance via quality codes Basis for change management and claim avoidance

Page 62: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

RFI

What are the benefits of RFI?

Web – Based Access Standard and/or customized reports and forms Reduces technical query turnaround cycle time Captures query details (dates, time, deliveries, categories) Manages all the data connected to all queries Expedites questions and answers to reduce impacts in the field

Page 63: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

ENGINEERING AND DESIGN TOOLS(Supported by ES)

Page 64: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems – Engineering

Page 65: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering Design Systems

Page 66: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

3D Design System example

Page 67: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering & Design Systems

3D CAD

Used for engineering analysis and design. Examples are:

• SACS for Offshore structural design• CAEPIPE / CAESAR II for Pipe Stress Analysis

Aspen Basic Engineering - Used for process & mechanical data management

Used to produce 3D engineering design• PDMS – Primarily used for 3D Offshore Plant Design• AutoPlant – Alternate 3D design system supported by

WorleyParsons

Used to produce 2D engineering design• Microstation – 2D design system supported by

WorleyParsons• AutoCAD – 2D design system supported by WorleyParsons

Discipline Specialist Engineering Software

2D CAD

Page 68: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering & Design Systems: WorleyParsons Preferred Systems

Used for Piping & Instrument Design to develop intelligent P&IDs

Used to complete instrument & control engineering and design activities

Used as an intelligent Document and Data Management System

Used to complete electrical engineering & design activities

Used to produce 3D engineering design

Used to conduct design reviews

Used to produce specifications

Page 69: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Technology Roadmap

Time

Tech

nolo

gy

2D

3D

20001980 19901960

Manual

Integrated

1970

CAD – Computer Aided Drafting (dumb graphics) AutoCAD,

MicroStation, etc.

CADD – Computer Aided Drafting & Design (intelligent graphics)

Enterprise Engineering Software – An Integrated Design Environment

INFORMATION = Document Centric + Data Centric

2010

Drafting Productivity

Improve designReduce field

rework

Improve efficiencyReduce risk

Source: ReVisionz Inc

Page 70: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering & Design Systems: Integration

Page 71: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering & Design Systems

What are the Key Success Factors for successful execution of Engineering Design Systems on a project?

1) Get on to systems set-up early and with some priority – it will pay off!.

2) Engage support groups – do not wait until there is an issue

3) Review the status and application of checking and verification processes regularly

4) Make sure actions from Model Reviews are addressed and closed out

5) If team members suggest system improvements (including project specific reporting), arrange to review the suggestions with your group and the EDS team

Page 72: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Engineering & Design Systems

What are the Key Success Factors for successful execution of Engineering Design Systems on a project (continued)?

6) Ensure MTO development is controlled – on larger projects you may need someone in your team to coordinate this activity

7) Review model progress regularly with your team – don’t wait for the formal reviews

8) Induct your team members on the specific project set-ups and requirements for the EDS tools

9) Encourage interested team members to participate in the Communities of Practice (COPs)

10)If Workshare is involved, verify that the Supporting Office has the set-up information it needs and communication protocols are in place

Page 73: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

DOCUMENT AND DATA MANAGEMENT TOOLS

(Supported by EDM)

Page 74: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems – Document & Data Management

Page 75: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Document & Data Management Systems

• ENCOMPASS for document management

• SPF for Document and Data Management especially when Data Integration is required

EVALUATE DEFINE EXECUTE OPERATEIDENTIFY

ENCOMPASS (Document Management)

SPF (Document & Data Mgt.)

Phas

eD

ocum

ent &

Dat

a M

anag

emen

t Too

ls

Page 76: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Automated project information and document management system Designed to support our workflow processes In-house developed platform using all commercially available

software Designed to facilitate easy participation by external project

stakeholders Rule-based system – totally customizable Built for managing full project life cycle Data delivered to customer structured for upload into their

document management system

Encompass

What does Encompass do?

Page 77: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Encompass

What does Encompass do?

7

Materials ManagementMaterials Management

SCHEDULESCHEDULE

PDSPDS

CIRCUIT CIRCUIT ROUTINGROUTING

Internal, Site, Client, Internal, Site, Client, JV Partners, and VendorsJV Partners, and Vendors

Engineering Design

Secretarial(Correspondence)

Estimating/Monitoring

Drawing/Document

Control

Procurement

Administration

LessonsLearned

SupportTables

USERSUSERS OUTPUT TOOUTPUT TO

ENCOMPASS® Database

Intel. P&IDsIntel. P&IDsPipe AnalysisPipe Analysis

Page 78: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Easy setup and maintenance Flexible document numbering Automated transmittal generation Repository for all project documents, including but not limited to:

• WorleyParsons design documents• Vendor documents• Customer documents• Contractor documents• Correspondence, including emails

Ability to use custom templates for any document type Ability to associate documents to equipment tags Turnover to customer, electronic files and metadata Action item list Drawings hold list Project personnel list Archiving capability

Encompass

What are the benefits of Encompass?

Page 79: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

WorleyParsons’ preferred tool for Document and Data Management on EP & EPCM projects of a size that justify this tool, ie with a large amount of document and data to be managed

Electronic repository and tracking system for all documentation produced by the project

Maintains all document references, document cross-references and revision histories

Can hold all approved versions of documentation in either their native or scanned format

Makes documents available across locations and time zones within a secure document repository

Interfaces directly with MS Office tools and a wide range of other third-party add-ons

SmartPlant Foundation (SPF)

What does SPF do?

Page 80: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SmartPlant Foundation

Page 81: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Allows WorleyParsons to develop a Data Management Plan in conjunction with the owner/customer that enables data to be transferred to the customer’s systems as soon as the data is authorized

Ongoing transfer of information eases the burden and cost of collating data for a single transfer at the end of the project

Secure, managed environment is fully configurable and auditable with full revision history. User access can be controlled by:

• document type

• document attributes

• user groups

SmartPlant Foundation

What are the benefits of SPF?

Page 82: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SPF StructureKey Functionality

Data Management - global, controlled access to project data Document Management - global, controlled access to documentation Workflow - multi-application workflow Change Management - multi-discipline change management Application Integration - vendor neutral application integration Engineering Framework - rules based application integration

DocumentManagement

Workflow

Change Management

DataManagement

‘eEngineering Integration Hub’

ApplicationIntegration

EngineeringFramework

Page 83: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

SmartPlant Foundation

Other Functionality

File management

Search and retrieval

Transmittals

Revision control

Change notification

Easy navigation of “intelligent” links

Consistency reporting

Page 84: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

• Automated creation of graphical hotspots from drawings

Easy navigation of Intelligent Links

Consistency Reporting

Page 85: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

• 160+ formats• No native application required• Pan, zoom, magnify• Print to scale, watermarks, stamps• Mark-ups are separate layers with

own security controls• Multiple redline layers per file

Document Viewing and Markup – SmartPlant Markup Plus

Stores all the data “forever”• “Turn the clock back”

- e.g. to look at what revisions were current at an earlier point in time

Page 86: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

• Graphical process definition• Electronic routing(e-mail) and approval• Progress tracking• Check list• Full audit history retained

Workflow

Page 87: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Data Handover

Data Handover

Page 88: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

LUNCH

Page 89: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

COMMUNICATION TOOLS(Supported by IM)

Page 90: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Safety statistics and incident reporting

Project web-based Intranet environment

Repository for non project, uncontrolled data

Communication tool for user communities

Communication Systems

Repository of all WorleyParsons procedures, workflows, templates, guidelines, forms, checklists and prompt lists

Key internal & external mail communication system

Page 91: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

IMPROVE PORTFOLIO MANAGEMENT TOOLS

(Supported by PAIS)

Page 92: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

Page 93: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Improve Operating Platform (IOP)

Comprises a generic set of methodologies and systems within a defined framework, for the delivery of a portfolio of projects within an Improve Contract.

Based on the WorleyParsons Corporate Standards of the EMS and WPMP, which have been tailored specifically for Improve Contracts.

Put another way, the IOP is essentially a “user front end” for EMS, WPMP and other systems.

Represents what has previously been known as a Contract Execution Plan or Contract Operating Manual.

What does IOP do?

Page 94: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Improve Operating Platform (IOP)

Page 95: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Improve Operating Platform (IOP)

What are the benefits of IOP? The IOP has been developed to support the execution of a portfolio of

smaller projects (< than US$10 million TIC or < than $1 million WorleyParsons contract value), and will also support ‘nano’ projects (< $100K TIC or less than $10K WorleyParsons contract value). 

Addresses both Content and Structure

The Generic IOP will be accessible to WorleyParsons personnel with task sheets stored in EMS. This will ensure that Worleyparsons Process Improvements will be passed on to Improve customers on an ongoing basis.

Will incorporate best practice solutions from existing Improve Contracts thus enhancing standard WorleyParsons Systems and Procedures.

Can be functional at an effective level on (i) WorleyParsons (ii) ‘neutral’ (non WP, non Customer) (iii) Customer systems environments.

IOP sharepoint site has the capability to store/link ‘live contract/project data’ but keeps this displayed separately from ‘reference / procedural data’.

Available for all existing and new Improve Contracts in order to ensure consistency in use of systems and processes while catering for customer specific needs.

Page 96: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

CUSTOMER SYSTEMS

Page 97: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Customer Systems

Customer Systems are important because very often WorleyParsons will be requested to interface with these systems.

The interfaces may be required on an ongoing basis, on agreed frequencies or at the end of the project.

Examples of these interfaces are:• Ongoing downloads of Purchase Order commitments into

customer ERP System, as and when Purchase Orders are placed in the WorleyParsons Procurement system

• Weekly timesheet downloads into customer ERP system

• Weekly cost commitment data into customer ERP system

• Handover of completed Documents and Intelligent Data into the customer ERP system or Document Management system

Page 98: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

SELECTING AND ACCESSING TOOLS

Page 99: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

The appropriate tool(s) will vary according:

• Project size (Major, Minor, Miscellaneous)

• Project phase (Identify, Evaluate, Define, Execute, Operate)

• Scope of service (Engineering, E&P, PMC, EPCM, EPC, Improve)

• Customer Requirements etc.

Work closely with the Project and Improve Systems (PAIS), Engineering Systems (ES) and Engineering Data Management Systems (EDM) Groups to select & configure the systems for your project.

Selecting the Appropriate Project Delivery Tools

Page 100: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 101: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 102: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 103: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 104: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 105: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

What System should I use?

Page 106: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Selecting the Appropriate Project Delivery Tools

Scope of Work E E/P EPCM PMC/TIC Improve

Function/System Phases All Define/Execute Execute Define/Execute Operate

ESTIMATING Description

Aspen Capital Cost Estimator (ACCE) Used in the development of large grass-root projects’ to generate Class 1 (Order of Magnitude) and Class 2 (Screening) estimates. * Identify & Evaluate phases only

Quest Used to estimate Class 2 (Screening), Class 3 (Control) & Class 4 (Definitive) Capital Cost estimates.

@RISK Used for performing quantitative cost risk analysis using the Monte Carlo Simulation model which gives an information rich and accurate representation of potential risk exposures.

PROJECT CONTROLS Description

InControl Used for the management and control of scope, budget, progress, forecasting and cash flow. Predominantly deployed for engineering/services contracts on standalone projects and portfolio scopes of work.

PREDICTION+ PCS Used for the management and control of scope, budget, progress, forecasting and cash flow for standalone EPC/EPCM projects and portfolio scopes and where the customer requires Total Installed Cost (TIC) management.

PLANNING Description

Primavera P6 Used for the development and management of all project schedules through the project lifecycle. Has an extensive range of functionality, some of which are, logic based networking, critical path analysis, resource scheduling and import/export capabilities.

Primavera Risk Used to provide quantitative evaluation of full project life-cycle risks associated with uncertainty in schedule.

PROCUREMENT Description

SmartPlant Materials (SPM) Used for material management work flow from preliminary design through to detailed engineering and purchasing to construction by providing a common collaboration platform and workbench for all stakeholders involved in the supply chain management.

CONTRACTS Description

Contract Administration Management System (CAMS) Used to manage contract formation via standard or imported terms and conditions and the administration cycle including; amendments, progress, claims, back charges, reporting and compliance.

CONSTRUCTION Description

PREDICTION+ JCS

Used to provide real-time management of the fabrication, construction and commissioning phases of the projects or programme/portfolio works via Work Packs & Job Cards.

COMPLETIONS Description

Completions Management Tool (CMT)

Used to generate scope and control the data, information and documentation necessary to successfully manage the field commissioning activities in turn supporting the seamless start up on projects.

IMPROVE Description

Improve Operating Platform (IOP) Used to provide projects with a flexible and customisable operating framework that highlights and allows easy access to WorleyParsons and Customer processes, systems and people. Utilises the Microsoft SharePoint platform for successful delivery of a portfolio of projects.

Page 107: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

EXAMPLES OF SELECTING AND ACCESSING TOOLS

Page 108: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Selecting the Appropriate Project Delivery Systems

Example 1 Project type: Engineering Services

Project phase: Evaluate

Project fee value: US$200,000

Project scope: Conduct feasibility study to extend a gas plant

Answer Project Management tools: Finance and time management system – GBS (if not rolled out

then the existing location time and cost management system) InControl – EPCM service cost control Primavera – planning WPMP – project management process EMS – functional procedures.

Page 109: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Selecting the Appropriate Project Delivery Systems

Example 2 Project type: EPCM contract

Project phase: Execute

Project fee value: US$40,000,000

Project scope: Conduct engineering, procurement and construction management services for the development of an ammonium nitrate plant.

Answer Project Management tools: Finance and time management system – GBS (if not rolled out

then the existing location time and cost management system) InControl – EPCM service cost management and control Primavera – planning Prediction + – TIC cost control SmartPlant Materials (SPM) – materials management CAMS – contracts management SmartPlant Foundation (SPF) – document and data management WPMP – project management process EMS – functional procedures.

Page 110: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

ACTIVITY 1 – SELECTING TOOLS

Page 111: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Activity 1

Select appropriate project delivery systems Working in groups, you will be allocated one of the project

examples below. Select the appropriate project delivery systems for project

management (excludes engineering systems) for your project example (from page 40 of Participant Book).

Develop project-specific system diagrams Develop a project-specific system diagram for your project

example Draw arrows indicating the direction of information flow

• Use solid lines for electronic information flow• Use dotted lines for manual information transfer

Page 112: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Business Management Systems

COFFEE BREAK

Page 113: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Delivery Systems

REPORTS

Page 114: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports are the most important output from the various tools used by WorleyParsons

Project managers rely on reports to: Verify integrity of data

Analyze status of project

Manage change

Make measured decisions

Report on progress to clients

Reports

Page 115: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Hours and Revenue Validation Report:

Finance & Administration Reports – WorleyParsons Business Reporting Tool

Reports

Page 116: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Aged Debtors Summary Report

Reports

Finance & Administration Reports – WorleyParsons Business Reporting Tool

Page 117: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Financial Analysis Reports:

Reports

Finance & Administration Reports – WorleyParsons Business Reporting Tool

Page 118: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Aspen Capital Cost Estimator ReportsProject Management & Control Reports

Reports

Page 119: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

Quest Capital Cost Estimator Reports

Page 120: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

@Risk Reports

Page 121: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - Proposal Report (CTR/Activity Sheet)Project Management & Control Reports

Reports

Page 122: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

122

InControl Activity Register

Project Management & Control Reports

Reports

Page 123: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - PGM Graphical ReportsProject Management & Control Reports

Reports

Page 124: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - Project Summary ReportProject Management & Control Reports

Reports

Page 125: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - Resources Details—Manhour/Quantity ReportProject Management & Control Reports

Reports

Page 126: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Resource Productivity ReportProject Management & Control Reports

Reports

Page 127: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - Resource Progress ReportProject Management & Control Reports

Reports

Page 128: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

InControl - Cost Commitment Report

Project Management & Control Reports

Reports

Page 129: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

PREDICTION+ - Estimate Summary Report

Page 130: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

PREDICTION+ - Detailed Cost Report

Page 131: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

PREDICTION+ - Cost S Curve

Page 132: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

Prediction+ - Variation Report

Page 133: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

Primavera P6 Report

Page 134: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

Primavera Risk Report

Page 135: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Procurement Status Report (Part 1 of 2)Procurement Reports (SmartPlant Materials - SPM)

Reports

Page 136: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Procurement Status Report (Part 2 of 2)Procurement Reports (SmartPlant Materials - SPM)

Reports

Page 137: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Expediting Summary Report

Procurement Reports (SmartPlant Materials - SPM)

Reports

Page 138: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Subcontract Monthly Status Report

CAMS

Reports

Page 139: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Contract Commitment Report

CAMS

Reports

Page 140: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Total Forecast Contract Value – Summary

CAMS

Reports

Page 141: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Procurement Reports

Reports

Supplier Portal

Page 142: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Procurement Reports

Reports

Trade Wizard

Page 143: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

PREDICTION+ Jobcard

Page 144: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

PREDICTION+ Jobcard Hours Progress Reports

Page 145: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Project Management & Control Reports

Reports

PREDICTION+ - Jobcard Quantity Histogram Report

Page 146: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

PREDICTION+ Jobcard Quantity Progress Reports

Page 147: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

Completions Management Tool – Sub System Status Reports

Page 148: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

Completions Management Tool – Object Status Reports

Page 149: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

Completions Management Tool – Progress Reports

Page 150: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Construction Reports

Reports

RFI Tool - Reports

Page 151: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Data Management & Communication ReportsDocument Control Reports

• Master Document Register• Transmittal Reports/Details • Document Expediting

Supplier Data Reports• Supplier Document Register• Supplier Transmittal Details• PO Status Reports• Expediting Reports

Equipment ReportsProject Activity ReportsCustom Reports as required

Page 152: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 153: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 154: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 155: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 156: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 157: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Reports

Page 158: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Document Control Reports

• Master Document Register

• Transmittal Reports

• Document Expediting

Supplier Data Reports

• Supplier Document Register

• Supplier Transmittal Details

• PO Status Reports

• Expediting Reports

Custom Reports as required

Document Management & Communication Reports in SPF

Reports

Page 159: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Document Revision Register

Data Management & Communication Reports

Reports

Page 160: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Internal Transmittal Overdue Report

Data Management & Communication Reports

Reports

Page 161: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Supplier Expediting - External

Data Management & Communication Reports

Reports

Page 162: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Custom Project – Status Report

Data Management & Communication Reports

Reports

Page 163: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Business Management Systems

SUMMARY AND FEEDBACK

Page 164: Module 4 - Project Delivery Systems Slides Rev 7 Read Only

Summary & Feedback

What we covered today

• Overview of Business Management Systems

• Finance, Administration & HR tools

• Project Management and Control tools

• Engineering & Design tools

• Data Management & Communication tools

• Selecting appropriate business system tools

• Business system reports

Questions