modular slab track - permanent way institution

33
www.rhomberg-sersa.com Modular Slab Track Asfordby Slab Installation IVES – PORR – V-Tras PWI Winter Conference December 2014

Upload: others

Post on 31-Oct-2021

22 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Modular Slab Track - Permanent Way Institution

1 www.rhomberg-sersa.com

Modular Slab Track Asfordby Slab Installation IVES – PORR – V-Tras

PWI Winter Conference December 2014

Page 2: Modular Slab Track - Permanent Way Institution

Although many forms of slab track have been developed it can be argued that the birthplace of high speed slab system is Japan.

1965 JNR started to develop “new track structures”, the design specification being

Ø  Construction cost being less than twice that of ballasted track Ø  Elasticity and lateral/vertical strength be greater than that of

ballasted track Ø  Construction rate of >200m per day

In 1972 the ballastless track structure was named “Slab Track” and first applied on the Sanyo Shinkansen line

Development of the Modular concept

Page 3: Modular Slab Track - Permanent Way Institution

Development of the Modular concept

Ø  Slab dimensions 5m x 2.2m x 0.19m

Ø  Stopper gives lateral stability

Page 4: Modular Slab Track - Permanent Way Institution

Life Cycle Cost

Page 5: Modular Slab Track - Permanent Way Institution

Life Cycle Cost

Page 6: Modular Slab Track - Permanent Way Institution

Many variations have since been developed as well as alternative slab systems

Continued Development

Standard Frame Slabs - Japan

Rheda 2000 - Germany

Page 7: Modular Slab Track - Permanent Way Institution

Continued Development

Bogl - Germany

PORR - Austria

Page 8: Modular Slab Track - Permanent Way Institution

Network Rail made the decision to undertake a trial of two slab track forms in 2013 with the addition of a new form of transition module Ø System 1 – Rhomberg Sersa IVES

Asfordby

Page 9: Modular Slab Track - Permanent Way Institution

System specifics

Asfordby

Page 10: Modular Slab Track - Permanent Way Institution

Asfordby

Page 11: Modular Slab Track - Permanent Way Institution

Asfordby

Page 12: Modular Slab Track - Permanent Way Institution

Ø System 2 – PORR

Asfordby

Page 13: Modular Slab Track - Permanent Way Institution

Asfordby

Page 14: Modular Slab Track - Permanent Way Institution

Ø  Transition Module – Rhomberg Sersa V-Tras

Asfordby

Page 15: Modular Slab Track - Permanent Way Institution

Asfordby

Page 16: Modular Slab Track - Permanent Way Institution

Asfordby

Page 17: Modular Slab Track - Permanent Way Institution

Asfordby

LH Curve radius 1655m 70m transition

180m straight

50m transition LH Curve radius 1785m

V-Tras 165 IVES Blocks 24 PORR Slabs 209 IVES Blocks

Page 18: Modular Slab Track - Permanent Way Institution

Sequence of works; Ø  Formation prepared with 100mm of Type 1 material compacted to achieve

a minimum stiffness of 30kN/mm Ø  Using standard highways asphalt machine (laser controlled) lay two

layers of hot rolled asphalt, total depth is 250mm with a minimum width of 2700mm Tolerance of Asphalt layer +0mm / -10mm

Asfordby

Page 19: Modular Slab Track - Permanent Way Institution

Installation of IVES; Ø  IVES blocks are lifted and placed on the Asphalt layer

Asfordby

Total accuracy of the vertical and horizontal alignment is not required at this stage.

Page 20: Modular Slab Track - Permanent Way Institution

Ø  Baseplates are laid in

readiness for rail installation

Asfordby

Page 21: Modular Slab Track - Permanent Way Institution

Ø  Rails are installed and clipped up

Ø  RhoTas system is installed

Ø  Rail and Baseplate are lifted and aligned to the final design

Asfordby

Page 22: Modular Slab Track - Permanent Way Institution

Ø  Rails are installed and clipped up

Ø  RhoTas system is installed

Ø  Rail and Baseplate are lifted and aligned to the final design

Asfordby

Ø  Hergie measuring system is used to measure the track position / gauge / super elevation

Ø  Accuracy of +/- 1mm is achievable

Page 23: Modular Slab Track - Permanent Way Institution

Ø  Shutters are fitted to the Baseplates

Ø  Grout is poured through the grout aperture to fill the void below the Baseplate

Asfordby

Page 24: Modular Slab Track - Permanent Way Institution

Installation of PORR; Ø  PORR slabs are lifted and placed on the Asphalt layer

Asfordby

Ø  Wire mesh is laid / supported 50mm above the Asphalt layer

Ø  Five threaded support bars hold the slab to design height

Page 25: Modular Slab Track - Permanent Way Institution

Asfordby

Ø  Reinforcement cages are fitted in the slab recesses

Ø  Shuttering is fitted to the sides of the slab

Ø  Rails are installed and clipped up

Ø  Final design is achieved by adjusting the threaded support bars

Page 26: Modular Slab Track - Permanent Way Institution

Asfordby

Ø  Self Compacting Concrete is poured to fill the void below the slab

Page 27: Modular Slab Track - Permanent Way Institution

Installation V-Tras;

Asfordby

Ø  Concrete slab is cast to hold the pivot rail

Page 28: Modular Slab Track - Permanent Way Institution

Installation V-Tras;

Asfordby

Ø  V-Tras unit is lifted into place

Page 29: Modular Slab Track - Permanent Way Institution

Installation V-Tras;

Asfordby

Ø  V-Tras is lifted to final design

Ø  Sleepers are placed on V-Tras

Ø  Ballast is placed and compacted in layers

Page 30: Modular Slab Track - Permanent Way Institution

Installation V-Tras;

Asfordby

Ø  Rail is installed and clipped up

Ø  Adjustment made to the horizontal alignment

Ø  Horizontal alignment is fixed

Ø  V-Tras is lifted to final vertical alignment and ballast compacted

Page 31: Modular Slab Track - Permanent Way Institution

Simple and robust structure Ø Use existing sub structure Ø Standard asphalt / concrete formation layer Ø Single design of pre stressed concrete bearer for straight and curved track Ø Low surface pressure

Fast and simple construction Ø Simplicity and robustness of the “bottom up” system with accuracy of the “top down” rail positioning Ø Only the final rail positioning requires time consuming accuracy Ø Mechanised construction Ø Single line working construction Ø Simple and effective surface drainage Ø Low surface pressure

Summary of Benefits

Page 32: Modular Slab Track - Permanent Way Institution

Efficiency in design Ø Long term track stability Ø Designed and managed track stiffness Ø Improved track drainage – eliminates drainage faults such as wet beds Ø Low ground bearing forces Ø High accuracy of rail positioning with long term stability of the rail geometry – thus reduction a in track component failure.

Summary of Benefits

Page 33: Modular Slab Track - Permanent Way Institution

Efficiency in operation Ø Line speed handback Ø Increased infrastructure performance Ø Reduced impact on operational running Ø Reduced faults

Ø  ballast deterioration Ø  drainage failure Ø  reduced rail wear – therefore increased rail life (+25%) Ø  eliminates maintenance interventions Ø  reduced renewal interventions Ø  increase in S+T performance

Ø System will allow for track lowering in tunnels for gauging or OLE installations – fixed geometry allowing reduced gauge clearances

Summary of Benefits