miso overview - southeastern wind coalition · – miso has multi-value project portfolio that was...
TRANSCRIPT
MISO Overview Southeastern Wind
Coalition
March 30, 2016
Market Footprint by
Region Genera&onCapacity
178,808MW(market)189,390MW(reliability)
HistoricPeakLoad(July20,2011)
127,125MW(market)131,181MW(reliability)
HistoricWindPeak(February19,2016)
13,088MW65,800milesoftransmissionFootprint
15States1CanadianProvinceCityofNewOrleans
2
Scope of Operations – Market Operations
• 5-minute dispatch • 2,439 pricing nodes
• $24.7 billion gross market charges (2015)
• 425 market participants
• 42 million end-use customers
3
• MISO is a service company that provides reliability to the electric grid
• MISO administers the market for electricity producers and users on a wholesale level
• MISO does not generate or buy electricity
Our Role
• Monitor energy transfers on the high voltage transmission system
• Schedule transmission service • Manage power congestion through security-
constrained economic dispatch • Operate day-ahead and real-time
energy and operating reserves markets • Regional transmission planning
What We Do
MISO Evolution
6
7
Yearly Wind Growth at MISO
1,1122,462
4,861
7,625
9,22110,601
12,27113,035 13,726
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
DEC2006 DEC2007 DEC2008 DEC2009 DEC2010 DEC2011 DEC2012 DEC2013 DEC2014
MW
YEARLYWINDGROWTHATMISOINMW
WINDGROWTHATMISO
8
Projected Wind Growth at MISO
15,08116,650
18,17519,700
21,010
0
5,000
10,000
15,000
20,000
25,000
DEC2015 DEC2016 DEC2017 DEC2018 DEC2019
MW
PROJECTEDWINDGROWTHATMISOINMW
PROJECTEDWINDGROWTHATMISO
Current Wind Capacity • Registered Wind March 2016 Commercial Model = 15,111 MW • Registered Wind In-service as of 3/25/2016 = 14,773 MW • Registered as a Dispatchable Intermittent Resource (DIR) = 12,623 MW (84%) • Registered DIRs In-service as of 3/25/2016 = 12,285 MW • DIR Exempt = 2,488 MW (16%)
RegisteredDIR,12,623MW(84%)
DIRExempt,2488MW(16%)
March2016RegisteredWind,15,111MW
9
MonthlyWindEnergyGenera&on
10
MonthlyDIRWindEnergyGenera&on
11
DispatchedGenera&onFuelMixbyRegion
12
Projected Solar Growth at MISO • Approximately 1700 MW of Solar Generation in
various stages of the Interconnection Queue
13
14
How are wind integration costs spread over large market footprints and regions? • Wind Integration Costs
– Costs of transmission infrastructure necessary to interconnect the wind generation to the BES
– Costs of delivering wind generation across the footprint • Infrastructure investment • Operational costs
• Interconnection costs – Local interconnection upgrades paid for largely by generator; 10% of 345 kV and
above upgrades postage stamped across footprint • Delivery costs – infrastructure investment
– MISO has multi-value project portfolio that was primarily driven by the Renewable Portfolio Standards mandated within the MISO states – 17 EHV transmission projects
– Costs are postage stamped across the footprint
15
Are Operating Reserves additions needed • MISO’s geographic diversity, large Balancing Area,
and Dispatchable Intermittent Resource Product have allowed MISO to not increase Operating Reserves to date
16
How do operators ensure reliability in a low load situation
• MISO uses advance notice of potential Minimum Generation situations to allow generators to choose to do maintenance
• When in a Minimum Generation situation: – MISO can use Dispatchable Intermittent Resources to dispatch
down – MISO can use emergency ranges of generation