    Minutes of meeting held on the 20thJanuary 2014

    Date 20th

    January 2014Time 2pm4pm

    Meeting The meeting was organised by the project manager (Utsav Dhakal)

    Present Client: Harith Mbos

    Senior Manager: Dean Walker

    Peer reviewer x2- Daniel Coutinho, Abraham Smith

    End User x2- Tomas Taujanskas, Abimbola Osidele

    Subject Handover and Final Review

    Agenda Item (number) Details of Notes from meeting

    Apology All members of the meeting were able to attend the meeting on

    time, so it wasnt applicable to anyone else as everyone else was

    on time so the meeting went smoothly without any interruption.

    Matters arising The product and the user guides have now been completely

    finished and the project is drawing to a close with this and the

    final last meeting so there are no matters that arose at this point

    in time so the Project Manager asks all members of the meeting if

    there are any matters arising but there is a response of a

    unanimous no.

    Handover Presentation In this section of the meeting the Project Manager(Myself)

    showed all members including the Client the final completed

    Multimedia Product Hp Laptop flash product and the two user

    guides (Technical and Novice). I presents the multimedia on an

    interactive white board showing all members the multimedia

    product going through every single page and showing every

    interactive feature that it has, for all members to see for the first

    time together, I then passed the interactive pen round so that all

    members could have a brief experience of navigating and using

    the product. The project then explains every stage of the

    development and ever motion tween, button and multimedia

    aspect that I had kept into the product referencing the feedback

    they was given to me in the various different emails and meetings

    showing how each stakeholder helped me shape and form this

    final product. Once every member of the meeting have had a brief

    go of using the multimedia product including the end users I thenhanded out a printed copy of the Novice guide to each and every

  • 8/12/2019 Minutes7 (Handover)

    2/3

    Minutes of meeting held on the 20thJanuary 2014

    member of the meeting reading out load what it said, when I

    finished reading the Novice guide I then did the exact same thing

    for the Technical guide reading out load step by step how I was

    able to use action script to enhance the multimedias interactivity.

    After showing all members of the meeting the all of the

    deliverables I then asked if they had any questions, and everyone

    agreed that they did not have any questions and they could

    continue to the next stage of the meeting.

    Final Review This section is the main purpose of the meeting focusing on the

    subject of the meeting the final review of the Multimedia

    Product, the subject of the meeting was based on the review of

    both the project throughout the entire time from the initial

    brainstorm to the final testing of the final product covering all

    areas of development and also all methods of communicationoutside of meetings, the second area that is being reviewed and

    the main purpose of this meeting is the final multimedia product.

    The review is to see how well the Stakeholders preformed their

    roles in the project most importantly focusing on how well the

    product was carried out by the Project Manager (Myself),

    additional to this the review will highlight the resources used and

    whether or not they were the correct resources to used and

    whether or not they were used to their maximum potential. I

    started the final review by presenting the final version of the

    product. This way they all would be able to navigate around the

    multimedia product one last time so that they will have clear

    evidence of what to review. I then gave a final explanation of the

    product for each of the members around the product showing

    every detail of every page and also showing them the final

    deliverable of the project. I talked on brief on basic technical user

    guide of how to install. During the process of talking I showed

    everyone how I was able to uses action script to create more

    interactive features in the multimedia product.

    After this section of the meeting took place the I then proceeded

    to the topic of reviewing the entire project the main purpose of

    the meeting, to being this the Client (Harith Mbos) firstly handed

    out to all the stakeholders a copy of the evaluation of our

    performance, explaining to all the members of the meeting that

    this was an overall evaluation of the product as well as my

    performance throughout the project.

    The Senior Manager was the last to give his comments of the

    overall review of the project. After all members of the meeting

    had given their views of the Project Manager and the project as a

  • 8/12/2019 Minutes7 (Handover)

    3/3

    Minutes of meeting held on the 20thJanuary 2014

    whole the last section of the meeting was to discuss any possible

    improvement that could be made if they were to redo this course,

    it was agreed that all members of the meeting thought that too

    much time was spent on the design production stage and perhaps

    they should have just done all of the product designs should have

    been made in two meetings and by them working together it

    would cut out the need for email communication and reduce the

    time spent on the product design stage by a significant number of

    weeks and then that time could be spent on the implementations

    on flash or even finishing the project before the deadline time.

    Thank you statement I thank all the stake holder on the success of the project. All their

    hard work was not missed out each and every feedback was taken

    into consideration and I kindly respect on their contribution and

    input towards the project to make it a huge success.