minutes of the 202th meeting

36
1 Minutes of the 202 nd meeting of the State Level Expert Appraisal Committee held on 31/07/2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. The 202 nd meeting of the State Level Expert Appraisal Committee (SEAC) was held on 31 st July, 2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Dr. Nikhil Desai, Member, SEAC. 2. Shri R.I.Shah, Member, SEAC. 3. Shri V.C.Soni, Member, SEAC. 4. Shri R.J.Shah, Member, SEAC. 5. Shri Hardik Shah, Secretary, SEAC. The agenda with reference to the applications received for TOR (Terms of Reference) finalization along with appraisal cases, EC amendment case and TOR reconsideration case was taken up. Three appraisal cases, two EC amendment cases, one TOR reconsideration case and eight scoping / TOR cases i.e. total fourteen cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports. Appraisal Cases: [1] Aarti Industries Ltd., Unit-III, Plot No.756/6, GIDC Jhagadia, Dist:Bharuch. The project was taken up for scoping and TOR finalization in the SEAC meeting held on 13/02/2013. After detailed discussion during the meeting held on 13/02/2013, certain additional TOR was prescribed for the EIA study to be done covering 10 km radius from the project boundary. This is a new unit proposing to manufacture Single Super Phosphate (powder/granulated)-24,000 MT/month and Hydro Fluoro Silicic acid-1,800 MT/month or Sodium Silica Fluoride-188.4 MT/month. The proposed production of Single Super Phosphate falls in the project/activity 5(a) as per the schedule of EIA Notificaiton-2006. Total plot area for the proposed project is 25,976 m 2 and expected cost of the proposed project is Rs. 35 crores. Estimated water requirement for the proposed project will be 260 KL/day (in case 98% sulphuric acid is used as raw material) and it will be met through GIDC water supply. There will not be any industrial waste water generation and for domestic effluent (30 KL/day), the unit has proposed to install Sewage Treatment Plant. The treated sewage will be utilized for green belt development. Sources of flue gas emission are 1 Boiler (9 ton/hr) using natural gas-400 kg/day and 2 nos. of D.G.sets (each of 750 KVA) each using Diesel-150 L/hr. Adequate stack height will be provided. The process emission will be from stack attached to Ball mills & its associated furnaces, Den mixture reactor and GSSP dryers (02 nos.). Coal will be used in Ball mills & its associated Furnaces (11.8 MT/day) and GSSP dryers (2×8 MT/day). APCMs proposed for control of the process emission are as under: Sr.No. Stack attached to APCM 1. Ball mills & its Associated furnaces Bag Filter 2. Den/Mixture Reactor Ejector, Ventury scrubber, Cyclone separator, Absorption tower with

Upload: ngokhue

Post on 05-Feb-2017

227 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Minutes of the 202th meeting

1  

Minutes of the 202nd meeting of the State Level Expert Appraisal Committee held on 31/07/2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.

The 202nd meeting of the State Level Expert Appraisal Committee (SEAC) was held on 31st July, 2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting:

1. Dr. Nikhil Desai, Member, SEAC.

2. Shri R.I.Shah, Member, SEAC.

3. Shri V.C.Soni, Member, SEAC.

4. Shri R.J.Shah, Member, SEAC.

5. Shri Hardik Shah, Secretary, SEAC.

The agenda with reference to the applications received for TOR (Terms of Reference) finalization along with appraisal cases, EC amendment case and TOR reconsideration case was taken up. Three appraisal cases, two EC amendment cases, one TOR reconsideration case and eight scoping / TOR cases i.e. total fourteen cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports.

Appraisal Cases:

[1] Aarti Industries Ltd., Unit-III, Plot No.756/6, GIDC Jhagadia, Dist:Bharuch.

The project was taken up for scoping and TOR finalization in the SEAC meeting held on 13/02/2013. After detailed discussion during the meeting held on 13/02/2013, certain additional TOR was prescribed for the EIA study to be done covering 10 km radius from the project boundary.

This is a new unit proposing to manufacture Single Super Phosphate (powder/granulated)-24,000 MT/month and Hydro Fluoro Silicic acid-1,800 MT/month or Sodium Silica Fluoride-188.4 MT/month. The proposed production of Single Super Phosphate falls in the project/activity 5(a) as per the schedule of EIA Notificaiton-2006.

Total plot area for the proposed project is 25,976 m2 and expected cost of the proposed project is Rs. 35 crores. Estimated water requirement for the proposed project will be 260 KL/day (in case 98% sulphuric acid is used as raw material) and it will be met through GIDC water supply. There will not be any industrial waste water generation and for domestic effluent (30 KL/day), the unit has proposed to install Sewage Treatment Plant. The treated sewage will be utilized for green belt development. Sources of flue gas emission are 1 Boiler (9 ton/hr) using natural gas-400 kg/day and 2 nos. of D.G.sets (each of 750 KVA) each using Diesel-150 L/hr. Adequate stack height will be provided. The process emission will be from stack attached to Ball mills & its associated furnaces, Den mixture reactor and GSSP dryers (02 nos.). Coal will be used in Ball mills & its associated Furnaces (11.8 MT/day) and GSSP dryers (2×8 MT/day). APCMs proposed for control of the process emission are as under:

Sr.No. Stack attached to APCM 1. Ball mills & its

Associated furnacesBag Filter

2. Den/Mixture Reactor

Ejector, Ventury scrubber, Cyclone separator, Absorption tower with

Page 2: Minutes of the 202th meeting

2  

water absorbing media and Alkali scrubber

3. GSSP Dryer Twin cyclone separator 4. GSSP Dryer Twin cyclone separator

Hazardous wastes to be generated are discarded bags-27 MT/year, discarded containers-6 MT/year, used oil-5.5 MT/year, fly ash-540 MT/year and insulation, electrical & office waste-25 MT/year. Hazardous waste to be generated will be disposed by selling to registered recyclers.

It is proposed to use spent sulphuric acid generated from its sister concern through pipeline as well as from other industries. The minimum concentration of spent sulfuric acid required is 70%. In case when ever, spent acid is not available, unit will use pure sulfuric acid of 98% purity. Closed/covered conveyors, covered area for storage, automated & remote control handling, adequate ventilation, dust extraction system, use of PPEs etc are proposed for control of fugitive emission. 4,680.0 m2 area will be developed as green belt and it is proposed to plant 825 trees and shrubs in the green area.

During the meeting, the committee was of the view that the project proponent will have to carry out public hearing in view of the MoEF’s O.M. No.-11013/36/2014-IA-I dated 16/05/2014. It was decided to further appraise the project only after carrying out public hearing of the project and submission of the following:

1. Complete fly ash management plan along with the exact quantity of fly ash generation, its handling, storage, end use etc. Copy of agreement letter from the end users of fly ash clearly indicating the quantity of fly ash to be purchased by them.

2. Revised EIA report incorporating a tabular chart for the issues raised and addressed during public hearing/consultation and commitment of the project proponent on the same should be provided. An action plan to address the issues raised during public hearing and the necessary allocation of funds for the same should be provided.

3. Source of rock phosphate and copy of agreement / linkage with respective mine.

[2] Suramya Abode (Phase-II) (Synthesis Spacelinks), Block No.218,219,220,221,224, 237,251,264,292,297,410,411,416,417,423,424, Village:Rethal, Taluka:Sanand, Dist: Ahmedabad.

This is an expansion of weekend residential plotting & housing project. Total plot area of the project is 12,53,073 m2 out of which phase-I comprises of an area of 3,54,727.0 m2 and phase II comprises of an area of 8,98,346.0 m2. The project falls in the project activity 8(b) as per the schedule of the EIA Notification-2006.

The project was considered for TOR/scoping during the SEAC meeting held on 27/12/2012 and the project proponent was asked to carry out EIA study covering 5 km radial distance from the project boundary considering the TOR prescribed during the SEAC meeting.

The proposed project, “Suramya Abode” – Phase II, comprises of total 1,700 residential plots. The total plot area is 12,53,073 m2 (125 ha) out of which Phase I comprises an area of 3,54,727 m2 (35 ha) and Phase II comprises an area of 8,98,346 m2 (89 ha). The net plot area after deduction of road and common plot area is 6,27,786 m2. The proposed FSI area is 2,69,503 m2 against the permissible FSI area of 10,78,015 m2. Nalsarovar bird sanctuary is at a distance of approximately 14.7 Km in

Page 3: Minutes of the 202th meeting

3  

WSW direction from the project site. The required quantity of water i.e. 29 KLD will be sourced from Tankers during construction phase. Water requirement, during operational phase is 1,614 KLD will be met by bore well water. Wastewater generation during construction phase will be 11.65 KLD. During operation phase waste water generation will be 924.37 KLD. For disposal of domestic sewage, soak pit and septic tanks are proposed. During Operation phase, solid waste to be generated will consist of Biodegradable (Vegetable & Food waste) and Non-biodegradable waste (cartons, thermocol, plastics, polythene bags, etc.). It would be approximately 2,650 kg/day. 2 bins per unit will be provided. Waste from such bins will be collected separately twice a week. Area of 300 m2 will be allocated for segregation and storage of waste. The recyclable waste will be sold to recyclers. The biodegradable waste will be collected in separate bins and it shall be used as manure. About 1,02,100 m2 area will be provided for Green belt development out of which 19,723 m2 will be used for tree plantation and 82,377 m2 will be used for shrubs and lawn. Around 13,350 numbers of trees will be planted. Baseline information with respect to land, air, noise and water quality in the study area were collected by conducting primary sampling / field studies during post-monsoon season i.e. October’12 –December’12. The study area considered is 5 km radial distance from the project site. At all monitored locations, average concentration of PM10,PM2.5 levels and average concentrations of SO2 and NOX were observed to be less than the NAAQM standards. From analysis results of groundwater quality, it is observed that the parameters are below/within permissible limits except ground water of Kundal Village, where TDS, Sulphate and Chlorides are above permissible limits. Basic facilities such as on site sanitation facilities – additional toilets for women, hygienic condition will be maintained to avoid any health problems-proper cleaning facilities provided and spraying of anti mosquito solution at required places, PPEs will be provided-during construction work, proper water supply for workers-domestic and drinking water availability, First aid room with first aid kit-all required and necessary medicines provided in kit, Crèches for small children, educational facilities for children, canteen and dining facility at nominal rates-affordable to workers, fuel for cooking, solid waste collection and disposal facility-to prevent health hazards to workers and their children. Nearest Fire Station of I.O.C Sanand is ~20 km away. The Fire Tender will take 50 minutes to reach the project site during an emergency. Energy consumption shall be reduced by using energy efficient features as CFL lighting fixtures in the common light, rooftop thermal insulation, maximum utilization of natural light, solar street light and use of LED. About 1,02,100 m2 area will be provided for Green belt development out of which 19,723 m2 will be used for tree plantation and 82,377 m2 will be used for shrubs and lawn. Around 13,350 numbers of trees will be planted.

During the meeting, it was noticed by the committee that the project proponent at the time of TOR/Scoping presentation proposed STP and now they have come with the proposal to discharge domestic effluent into septic tank/soak pit system during the operation phase. The project proponent was asked to install STP of adequate capacity and to submit the details thereof along with the revised water balance diagram. Further, while discussing about the flora & fauna of the area, it was observed by the committee that some of the species, which are found in this area, have not been shown deliberately. After detailed deliberation, it was decided to further appraise the project only after submission of the following: 1. Exact aerial distance of the project site from Nalsarovar and letter from concerned authority in

this regard.

2. Copy of permission obtained for Non agricultural use of the land area of the project site.

3. Explore the possibility of getting surface water supply for the proposed project.

Page 4: Minutes of the 202th meeting

4  

4. Status of permission from Central Ground Water Authority for ground water abstraction and copy

of correspondences made in this regard.

5. Details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its

location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation

phase.

6. Revised water balance details considering the reuse of treated water after provision of STP in

operation phase.

7. Complete treated water management plan along with the application wise breakup of treated

water utilization. Management plan of treated sewage during rainy season when utilization of

treated water for gardening/plantation purpose is not possible.

8. Detail & design of dual plumbing system to be provided for reuse of treated waste water.

9. STP sludge management plan.

10. Check list of the flora and fauna in the area, impact on them due to the proposed project and

mitigation measures thereof.

11. Base line ecological status. In case of any scheduled fauna, conservation plan should be

provided.

12. Detailed survey of endangered species including their habitat, if any in the study area, impacts of

the proposed project on the same along with mitigation measures and conservation measures

like proposal for creating wetland patches, artificial nests etc. in the project.

13. Details of the management of the surface run off / rainwater flowing through the existing natural

drain / nallah / stream passing through the project site, if any. Impacts on the surface hydrology

pattern due to the proposed project. Details of measures proposed to ensure that natural

drainage of the site will not be disturbed/ obstructed and measures proposed to protect existing

natural drain / nallah / streams within the project site.

14. Details of the Organic Waste Convertor (capacity, location etc.) installed in the existing Phase – I

of the project along with the photographs.

[3] Bhadbhut Barrage Project (Proposed by Kalpasar Department of Government of Gujarat), Near Bhadbhut Village , Tal. Vagra, Dist. Bharuch.

The Kalpsar Department, Government of Gujarat has proposed to construct a barrage across

Narmada river near Bhadbhut village. Barrage Project has not been included in the specified list.

However the proposed barrage will provide irrigation to about 1136 ha of land. Accordingly, the

project falls under category B of the project / activity no. 1(c) [i.e. the project having irrigation

command area less than 10,000 ha] in the schedule of the EIA Notification, 2006.

Earlier, the project was considered for screening /scoping in the meeting of the SEAC held on

05.01.2012 and 48 TOR were prescribed for the EIA study. Subsequently, additional 6 TOR were

prescribed in the meeting of the SEAC held on 06.02.2013. Public hearing for the project was

organized by the GPCB on 19.07.2013 at Bhadbhut village. Final EIA of the project was submitted in

February, 2014.

During the meeting, the project was appraised based on the information contained in the EIA Report

and the details presented before the committee.

Page 5: Minutes of the 202th meeting

5  

The Kalpsar Department, Government of Gujarat has proposed to construct a barrage across river

Narmada near village Bhadbhut in Bharuch district with the following objectives :

a) Protection of water quality of river Narmada from salinity due to tidal water influence and

salinity ingress for achieving improvement of ground water quality in the upper reaches of

the river Narmada

b) Storage of regulated release of water from SSP including free-catchment, if available, for

domestic, irrigation and industrial needs

c) Protection of low lying areas affected by high flood of River Narmada on the left bank

d) Reduction in traffic congestion between Surat (Hazira) & Bharuch (Dahej) with an alternative

route and also reduction in travel distance by about 18 km by constructing a six lane road on

the top of the barrage

e) Assured water for existing defunct lift irrigation schemes

The basic data for design of proposed Bhadbhut Barrage are shown in table below:

Barrage

River gorge width at Bhadbhut barrage location

: 1700 m

Bed material property : Silty sand Type of barrage : Barrage on permeable foundation Design flood ( 1 in 100) : 81717 cumecs Discharge through barrage (SPF) : 101,300 cumecs

Total Length of barrage : 1663 m Crest level of barrage bays : (-) 2.0 m FRL of the storage : (+) 7.5 m Clear span between piers : 15.50 m Nos. of gates : 90 Top road bridge width : 33 m Road bridge top level : (+) 12.85 m Size of gates : 15.5 m x 9.5 m (vertical gates)

Fish Passage : 5 m width Ship Lock : 15.5 m width Approach embankment Type of embankment : Earth embankment Length of embankment : 6.90 km on right side + 7.31 km on left side Top width : 30.0 m Side slopes U/S and D/S : 2.5 (H):1 (V) Average height : 6.50 m Protection of side slopes : Gabion on both sides.

Left bank protective embankment Type of embankment : Earth embankment Length of embankment (Barrage to Golden bridge)

: 24.05 km

Top width : 30 m Side slopes U/S and D/S : 2.5 (H):1 (V) Average height : 6.50 m Protection of side slopes : Gabion on both sides.

Page 6: Minutes of the 202th meeting

6  

Irrigation command area : Existing L.I. Schemes 1. Angareshwar : 568 ha. 2. Zanor scheme : 568 ha. Total area : 1136 ha.

The barrage will be constructed in downstream of village Bhadbhut to segregate Narmada river water

in the upper reach from tidal water of estuary, while allowing the environmental flow to pass through

the downstream estuary. The site for barrage construction is the river gorge of about 1700 m width,

5.15 Km downstream from village Bhadbhut (21 km downstream of Bharuch city and about 25 km

upstream of the river mouth). Main objectives of constructing the barrage are checking the problems

of salinity ingress and deterioration of ground water quality in upper reaches of Narmada, storage of

fresh river water for irrigation, domestic and industrial water supply, to provide lift irrigation facility to

about 1136 ha agricultural land along the river bank, flood protection of about 400 sq. km of low lying

area of 17 villages on left bank of river Narmada, road connectivity through alternative shorter route

from Surat-Hazira-Olpad-Hansot-Bhadbhut-Dahej by about 16 km. There will be provision of fish

passage for unobstructed migration of fishery species and ship lock-type arrangement for allowing

boat passage between upstream and downstream of the barrage. Construction of Bhadbhut barrage

on Narmada river will create 500 MCM fresh water reservoir. Two defunct lift irrigation schemes will

get rejuvenated due to the project. Further higher elevation areas, which are not getting benefits of

canal irrigation, will be benefited by new lift irrigation schemes and more area will be brought under

lift irrigation.

The barrage project due to its location in the estuarine zone of Narmada river attracts provisions of

CRZ Notification, 2011 and accordingly Kalpasar department has applied for CRZ clearance for the

proposed project. It was presented that the project was discussed in the meeting of GCZMA held on

25/03/2013.

EIA Report has been prepared by NEERI, Nagpur. The baseline environmental quality data was

collected within the project impact zone during summer, monsoon and winter of 2010-11. The

methodology included reconnaissance, collection of primary and secondary data through field

monitoring and other sources, micro-meteorological data (wind speed and wind direction) of the

project region was also collected simultaneously through a weather monitoring station installed at the

project site.

Salinity ingress in Narmada river takes place upto 70 km u/s and makes the river water saline and

unusable for domestic, irrigation, and industrial purposes. As a result, water for Dahej and PCPIR

region is supplied from Angreshwar (which is 70 km upstream), Narmada canal and Ukai canal. The

saline water has also rendered two lift irrigation schemes namely Zanor and Angreshwar defunct.

The Bhadbhut barrage, in addition to be a fresh water source for domestic, agriculture and industrial

requirement, will revive the two lift irrigation schemes and also make water available for agricultural

areas at higher elevation.

Data collected from the Assistant Director of Fisheries, Bharuch depict a declining trend of Hilsa fish

production from a high of 16646 MT in the year 1990-91 to the low 693 MT in the year 2010-11. The

production data of Prawn over the period 2004-05 to 2011-12 indicate a fluctuating trend (going up

Page 7: Minutes of the 202th meeting

7  

and down) in Prawn production over these years. The measures proposed to avoid impact on fishery

have been narrated below:

(a) Fish hatcheries with modern technology tools would be set up at various locations in u/s and d/s

of the barrage to enhance the fish production in the area.

(b) There will be provision of fish pass, gates as well as navigation ship locks together with crane in

the proposed barrage. The fish pass would facilitate Hilsa to ascend in the river and Prawn in d/s

of barrage. Similarly, the barrage gates will be opened in the monsoon for movement of fish both

ways.

(c) Release of environmental flow: To maintain the ecological conditions in the river d/s of barrage,

600 cusecs of water (as decided by NCA) will be released from Sardar Sarovar Project (SSP) as

environmental flow

(d) Fishing rights would be ensured to local fishermen for their livelihood in consultation with

Fisheries Department.

(e) A ship lock in the design of barrage is planned for easy movement of boats from reservoir to

estuary and vice versa. In addition to ship lock, provision of crane is also made in the design of

barrage as an additional measure for lifting and shifting of the boats as being practiced presently

at Veraval and Mangrol fishing ports.

Erosion and morphological changes with and without Barrage have been narrated below:

(a) Erosion of upstream left bank agricultural land areas: Ankleshwar to Hansot left bank is at level 4

to 7 m only hence, during monsoon the flood water gets aggravated and encroaches upon 400

sq. km agricultural land on left bank affecting 17 villages partially / fully. There is continuous

erosion of agricultural land. Land in some villages is entirely eroded which have been shifted to

higher elevation.

(b) Erosion of downstream right bank village land areas: Water channel of Narmada river from

Dhanturia up to Kantiyajal on the left bank is silted up. Consequently, the entire Narmada flow is

shifted towards the right bank d/s of village Bhadbhut. During the neap tide periods, the tidal

flow and the river flow are unidirectional and therefore attains higher velocity causing erosion of

right bank in d/s of village Bhadbhut.

(c) Silting in right bank from Bharuch to Bhadbhut: Due to prevailing hydraulic conditions, silt

deposition has taken place from Bharuch upto Bhadbhut village on right bank. The formation of

Dhanturia island is also due to silt deposition, causing obstruction to the river flow.

(d) Morphological situations of the downstream estuary: The flow of tidal water during ebb tide is

opposite to river flow which carries large sediment load and attains erosivity. Since opposite

flows cause reduction in velocity, the deposition and erosion take place depending on hydraulic

conditions. Formation of Dhanturia island and erosion of left bank are testimony to these

phenomena. The existing mud island Aliabet is at EL 4.0 m to 7.0 m, form the left bank of the

estuary and is stabilized. Of these two Narmada estuary channels, the western Aliabet channel

is completely silted up and is non-functional.

(e) Sedimentation: The total sediment contribution to Bhadbhut Barrage from the intercepted and

catchment works out to 24 Mm3. However this sediment yield is only indicative and depends on

factors like sediment capture by upstream reservoirs, construction of flood protection

Page 8: Minutes of the 202th meeting

8  

embankment, erosion of left bank area, actual sediment deposit in proportion to reservoir volume

capacity (500 Mm3) to total inflow volume (6068 Mm3 @50% dependability as per NIH study).

Sediment load during monsoon will be disposed off by opening the barrage gate. In addition,

provision of silt excluders at the base of the barrage would facilitate continuous passage of

sediment even when the barrage gates remain closed during the flood-free period.

A three dimensional physical model of Barrage and river covering 700 sq. km area from Shuklatirth

upto Luwara point is constructed at Gujarat Engineering Research Institute, Vadodara. The physical

model was run at a different flood velocities without Bhadbhut barrage and the outcome shows the

shifting of the Narmada river towards left side. The physical model was also run with Barrage and the

impact of flood on u/s and d/s of barrage were monitored. Thereafter, the model has been run with

barrage as well as left bank flood protection embankment between Hansot and golden bridge (24 km

long) and observations have been taken at various flood frequencies. The physical model is useful

for locating and designing the left bank flood protection embankment as well as constructing right

bank protection in d/s of barrage as well as for deciding various issues like operation of gates,

providing fish passage and shiplock etc.

Kalpasar Department has entrusted Mathematical Model Study for Kalpasar Project as well as

Bhadbhut Barrage to NIOT, Chennai at a cost of 22 crores. NIOT has tied up with DHI, Netherlands

and the mathematical model of entire gulf of Khambhat without Kalpasar Dam and Bhadbhut Barrage

have been run recently to observe tide, current, erosion, sediment etc. phenomena occurring in gulf.

Now the model will also be run with Bhadbhut Barrage to observe / monitor the impact on Aliabet /

Kantiyajal as well as right bank.

As per study carried out by NIO, Goa, There will be 0.4 m rise in tidal water level on downstream of

the barrage. With the construction of barrage, the volume of tidal prism d/s as well as current/ velocity

will get reduced, thereby reducing tide induced sediment generation, as indicated by the study

carried out by NIO, Goa. To check the negative impacts due to rise in tidal water level, the estuary

banks will be trimmed to widen horizontal space in order to increase spread of tidal water. In addition,

a protective embankment for downstream estuary banks will be provided. Deepening and widening of

estuary channels and also opening of Aliabet channel are proposed for facilitating estuary water exit.

As per GEC Mangroves Atlas-2010 of Bharuch district, the mangrove patches which are stunted and

sparse are far away from the Bhadbhut barrage site (from 25 to 35 km, at village Devla, near Dahej

and near Vamleshwar). No mangroves exist in the close proximity of the project site and therefore

there would be no impact of the project on mangroves. Further, as per the Coral Atlas of Gujarat

State - 2011, Corals are absent from Gulf of Khambhat. Only Gulf of Kachchh holds coral formations.

Aliabet lies at the confluence of the river Narmada and the Arabian Sea in Gulf of Khambhat. It is

about 7 km from Hansot town. Because of salinity, there are no agricultural activities on the land, a

part of which is also prone to submergence during high tide. Bhadbhut barrage alignment is fixed in

such a way that the Aliabet will remain downstream of barrage. In addition, barrage has the provision

of guide bund as well as flood protection embankment to store the water in the barrage only with

limited spread beyond Narmada river. Thus, Aliabet will not come under submergence due to the

proposed barrage project. Barrage left bank approach involves 31.40 ha of forest land for which the

Page 9: Minutes of the 202th meeting

9  

Kalpasar Department had made request to Forest Department to acquire this piece of land in lieu of

equal government land in Bhavnagar District as compensatory land. The approval to the above

proposal has been received from the Collector, Bhavnagar vide letter dtd. 23.06.2014 and sent to

Forest department by the Kalpasar department on 10.07.2014 for acquiring the land. Barrage left

bank flood protection embankment requires about 15 ha land which falls under forest land. The

Kalpasar department has initiated action for acquiring this land from the forest department.

During the meeting, issues raised during the public hearing were discussed at length. The main

issues raised during Public Hearing encompassed fisheries, river/estuary erosion, sedimentation and

submergence, river water quality as well as impacts of barrage on mangroves and Aliabet island. The

committee asked the project proponent to submit action plan to address each of the issues raised

during the public consultation. While inquiring about impact on drainage of water shed area

upstream of the Barrage, the project proponent informed that there will be provision of drain parallel

to the embankment and it will be having discharge in downstream of the Barrage. The committee

asked the project proponent to give details of drainage plan in writing. While asking about reasons of

proposing fish pass instead of fish ladder, the project proponent informed that fish pass has lesser

steep slope and it facilitated easy to & fro pass of fish than the fish ladder. He added that fish pass

provided at Naraj weir on Mahanadi is proved successful. The committee concerned about breeding

of Hilsa fish considering that Hilsa fish is saline water fish coming to fresh water of Narmada estuary

for breeding in monsoon. At this, the project proponent informed that Hilsa migrates to estuary water

for breeding only during high tides in monsoon when gates of the barrage will be kept open. The

committee asked the project proponent to take into account the ecological factors including migration

of Hilsa while deciding when to open / close gates of Barrage in monsoon and also to work out

detailed SOPs in this regard. The committee also asked the project proponent to give scientific

justification supporting that environment flow of 600 cusecs would be sufficient to sustain ecology of

Narmada estuary. While envisaging chances of erosion in downstream banks of Narmada estuary,

the project proponent informed that there will be provision of guide bund in downstream to avoid bank

erosion and moreover gate openings will be based on the physical model study to avoid erosion in

downstream. On inquiring about impact of 0.4 m rise in tidal water level in down-stream in terms of

submergence of land area if any going under submergence, the project proponent informed that no

area would go under submergence as they are going to do dredging in about 25 km stretch in

downstream. The committee asked the project proponent to submit details on need for capital and

maintenance dredging, disposal of dredge material and exact expected rise in tidal water level taking

into account proposed dredging. The committee noted that Environmental Management Plan

together with Environmental Monitoring Program have been formulated and incorporated in the EIA

report in order to minimize the negative impacts and maximize the positive impacts. After deliberation

on various aspects, it was decided to appraise the project further after satisfactory submission of

following additional information / documents :

1) Time bound action plan for addressing each of the issues raised during the public consultation

process.

2) Exact extent of forest area required to be diverted for various components of the project.

Page 10: Minutes of the 202th meeting

10  

3) Status of Stage-I forestry clearance for diversion of 31.40 ha of forest land required for Barrage

left bank approach and about 15 ha of forest land required for Barrage left bank flood protection

embankment.

4) Exact status of application made for CRZ clearance along with supporting documents.

5) Details on outputs of physical model and mathematical model studies. Correlation between

outputs and details on remedial measures proposed based on the outputs for preventing

ecological impacts including bank erosion, drainage, submergence, impact on migration of Hilsa

fish, etc.

6) Impact of construction of left bank protective embankment on drainage of water shed area.

Detailed on the drainage plan considering the construction of left bank protective embankment.

7) Scientific base for deriving 600 cusec as environmental flow and proper justification supporting

that environment flow of 600 cusecs would be sufficient to sustain ecology of Narmada estuary.

8) Detailed SOPs for opening or closing of barrage gates taking into account the ecological factors

including migration of Hilsa in monsoon. Details of proposed fish pass and detailed plan for

ensuring that migration of Hilsa fish would not be affected due to the proposed barrage project.

9) Exact rise in tidal water level at the barrage at the time of highest of high tide and its impact in

terms of submergence of area downstream of the barrage. Whether any land area would go

under submergence due to this rise in tidal water level?

10) Impact of the barrage in terms of erosion in downstream banks of Narmada estuary. Details on

measures proposed to avoid chances of bank erosion in downstream including provision of guide

bund, gate opening based on physical model study, etc.

11) Details on need of capital and maintenance dredging in estuary stretch in downstream of the

barrage, expected quantity of dredge material and where it will be disposed.

The project shall be appraised further after submission of above cited additional details.

TOR Reconsideration case:

[4] Chaitanya Life Science Pvt. Ltd., Plot No. D-2/CH/215, GIDC Industrial Estate, Dahej, Tal. Vagra, Dist. Bharuch. 

It is a new project proposing to manufacture pharmaceutical bulk drugs and intermediates (30 products with total production capacity of 169 MT/Month) at Plot No. D-2/CH/215, GIDC Industrial Estate, Dahej, Tal. Vagra, Dist. Bharuch. GIDC allotted the plot to the unit in March 2011.The proposed project falls under project / activity no. 5(f) in the schedule of the EIA Notification, 2006.

Earlier this project was taken up during SEAC meeting held on 29/11/2012. During the meeting, the committee felt that effluent discharge in GIDC drainage line should not be allowed from bulk drugs & intermediates manufacturing unit having high water pollution potential. The project proponent was asked to either devise a system to achieve zero effluent discharge or shift the project to other location where facility of CETP is available and to approach the committee thereafter along with a revised proposal.

Unit has submitted revised proposal with zero effluent discharge scheme. They have also submitted revised water balance diagram showing zero effluent discharge & details of proposed effluent treatment plant.

Page 11: Minutes of the 202th meeting

11  

Plot area will be 4,842.33 m2. Total project cost will be Rs 220 Lacs. Proposed total production will be carried out in 2 phases as shown below

Sr. no. Name of the Product Quantity Phase I 1 Oxyclozanide

150 MT/Month

2 Pyroxicam 3 Tizanidine 4 PiperazineHexahydrate 5 Piperazine Citrate 6 PiperazineAdipate 7 PiperazineDihydrochloride 8 Piperazine Phosphate 9 Povidone Iodine 10 Potassium Citrate 11 Potassium Iodide 10 MT/Month 12 Sodium Iodide Total Production of Phase-I 160 MT/Month Phase-II 13 Carvedilol 0.1 MT/Month 14 Olanzapine

0.4 MT/Month

15 Ondansetron Hydrochloride 16 Pregabaline 17 Amlodipine Besylate 18 Glimepiride

1.0 MT/Month

19 Lacidipine 20 Venlafaxin Hydrochloride 21 Losarton Potassium 22 Lidocaine Hydrochloride

7.5 MT/Month

23 Glibenclamide 24 Niclosamide 25 Metaxalone 26 Benzarone 27 Benzbromarone 28 Ethenzamide 29 Aceclofenac 30 Pentaprazole Sodium Total Production of Phase-II 9 MT/Month Total Production of Phase- I & II 169 MT/Month

There will be no industrial effluent generation from the Phase-I production. Water requirement for the project will be 30 KL/day and it will be met through GIDC water supply. Industrial effluent generation will be 18 KL/day. Previously it was proposed to treat industrial effluent in ETP and to discharge treated effluent into GIDC underground drainage line. Now as per the revised proposal industrial effluent will be treated in ETP comprising of Primary, Secondary and Tertiary treatment units and treated effluent will be taken to the RO system. R.O. Permeate (12 KLD) will be reused and Reject stream (4.5 KLD) will be treated in Multiple Effect Evaporator (MEE). Domestic wastewater generation will be 1.5 KL/day and it will be disposed off through septic tank – soak pit system. One steam boiler with cap. 0.8 TPH and one TFH with cap. 1.0 Lac Kcal/Hr are proposed. Natural gas (400 SCM/day) will be used in Boiler and TFH. One DG set with capacity 50 KVA is proposed as standby facility during power cut in which LDO – 10 LPD will be used as fuel and adequate stack

Page 12: Minutes of the 202th meeting

12  

height will be provided. There will be process gas emissions of NH3, HCl & SO2 from the manufacturing of various products. They have proposed to provide water scrubber followed by alkali scrubber to control HCl & SO2 emission and Two Stage Water Scrubber to control NH3 gas emission.

ETP sludge (24 MT/Annum), Spent Carbon (32.4 MT/Annum), Distillation residue (351 MT/Annum), Spent Solvent (7420 MT/Annum), Inorganic Process waste (142.5 MT/Annum), Discarded drums/bags (1000 Nos./Annum) and Used/spent oil (0.05 KL/Annum) will be generated as hazardous wastes. It is proposed to develop 500 m2 area as Green Belt.

During presentation committee asked about details of actual users of by-products, efficiency of scrubbing system, effluent characteristic of different streams of w/w and segregation system etc. After deliberation on various aspects regarding the project, the following Terms of Reference were prescribed for the EIA study to be done covering 5 Km radial distance from the project boundary.

1. Copy of plot holding certificate obtained from GIDC Dahej.

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all

round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders

without reversing back. Mark the same in the plant layout.

4. Details of manufacturing process / operations of each product along with chemical reactions,

mass balance, consumption of raw materials etc. Details on strategy for the implementation of

cleaner production activities.

5. Chemical name of each proposed product to be manufactured. Details on end use of each

product.

6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative

and quantitative analysis of the each waste stream from the processes.

7. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from the GIDC for supply of raw water.

Undertaking stating that no bore well shall be dug within the premises.

8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation.

9. Quality and quantity of waste water to be generated from the manufacturing process of each

product to be manufactured along with mass balance.

10. Stream wise qualitative & quantitative analysis of each waste stream (including process water,

cooling tower blow down, boiler blow down, MEE condensate, RO permeate & reject, washing

effluent etc.) to be generated. Characteristics of untreated and treated wastewater. A detailed

effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed

for the wastewater to be generated. The characteristic on which treatability is based shall also be

stated.

11. Details of the ETP units including its capacity, size of each unit, retention time and other technical

parameters.

12. Technical details of R.O system along with the quality and quantity of effluent at the inlet and outlet from R.O. Application wise break up for the quantities of RO permeate reuse should also be submitted.

Page 13: Minutes of the 202th meeting

13  

13. Technical details of the MEE including evaporation capacity, steam required for evaporation,

adequacy of the boilers to supply steam for evaporation in addition to the steam required for the

process etc.

14. Economical and technical viability of the effluent treatment system.

15. Plans for management, collection and disposal of waste streams to be generated from spillage,

leakages, vessel washing, used container washing etc. Measures proposed for preventing

effluent discharge during unforeseen circumstances.

16. Undertaking stating that a separate electric meter will be provided for the R.O. and MEE.

17. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly

wind speed and direction and rainfall should be incorporated.

18. Anticipated environmental impacts due to the proposed project/production may be evaluated for

significance and based on corresponding likely impacts VECs (Valued Environmental

Components) may be identified. Baseline studies may be conducted within the study area of 5 km

for all the concerned/identified VECs and likely impacts will have to be assessed for their

magnitude in order to identify mitigation measures.

19. One complete season base line ambient air quality data (except monsoon) to be given along with

the dates of monitoring. The parameters to be covered shall be in accordance with the revised

National Ambient Air Quality Standards as well as project specific parameters like NH3, HCl.

Locations of the monitoring stations should be so decided so as to take into consideration the

pre-dominant downwind direction, population zone and sensitive receptors. There should be at

least one monitoring station in the upwind direction. There should be at least one monitoring

station in the pre dominant downwind direction at a location where maximum ground level

concentration is likely to occur.

20. Modeling indicating the likely impact on ambient air quality due to proposed activities. The details

of model used and input parameters used for modeling should be provided. The air quality

contours may be shown on location map clearly indicating the location of sensitive receptors, if

any, and the habitation. The wind rose showing pre-dominant wind direction should also be

indicated on the map. Impact due to vehicular movement shall also be included into the prediction

using suitable model. Results of Air dispersion modeling should be superimposed on google map

/ geographical area map.

21. Base line status of the noise environment, impact of noise on present environment due to the

project and proposed measures for noise reduction including engineering controls.

22. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of

the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission

rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with

its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed

measures to control it.

23. Details on management of the hazardous wastes including MEE residue to be generated from the

project stating detail of storage area for each type of waste including MEE residue/salt, its

Page 14: Minutes of the 202th meeting

14  

handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will

be minimized. Methodology of de-contamination and disposal of discarded containers and its

record keeping.

24. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration

Facility, if any.

25. Management plan for By-products to be generated, along with the name and address of end

consumers to whom the by-product/s will be sold. Copies of agreement / MoU / letter of intent

from them, showing their willingness to purchase said by-product/s from the proposed project.

26. Name and quantity of each type of solvents to be used for proposed production. Details of solvent

recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing

the recovered solvents etc. for each type of solvent.

27. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed

for implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimization, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

28. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

29. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided. Provision of

industrial hygienist and monitoring of the occupational injury to workers as well as impact on the

workers. Plan for periodic medical checkup of the workers exposed. Details of work place

ambient air quality monitoring plan as per Gujarat Factories Rules.

30. Risk assessment including prediction of the worst-case scenario and maximum credible accident

scenarios should be carried out. The worst-case scenario should take into account the maximum

inventory of storage at site at any point of time. The risk contours should be plotted on the plant

layout map clearly showing which of the facilities would be affected in case of an accident taking

place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency

Plan should be provided.

31. MSDS of all the products and raw materials.

32. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

33. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of

Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity

as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major

hazardous chemicals, size of the biggest storage tank to be provided for each raw material &

product etc. How the manual handling of the hazardous chemicals will be minimized?

34. Details of the separate isolated storage area for flammable chemicals. Details of flame proof

electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control

Page 15: Minutes of the 202th meeting

15  

plan for flammable substances and processes showing hydrant pipeline network, provision of DG

Sets, fire pumps, jockey pump, toxic gas detectors etc.

35. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

manufacturing utility staff for safety related measures.

36. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

37. Detailed socio-economic development measures including community welfare program most

useful in the project area for the overall improvement of the environment. Submit a detailed plan

for social corporate responsibilities, with appropriate budgetary provisions for the next five years

and activities proposed to be carried out; specific to the current demographic status of the area.

38. A tabular chart for the issues raised and addressed during public hearing/consultation and

commitment of the project proponent on the same should be provided. An action plan to address

the issues raised during public hearing and the necessary allocation of funds for the same should

be provided.

39. (a) Does the company have a well laid down Environment Policy approved by its Board of

Directors? If so, it may be detailed in the EIA report.

(b). Does the Environment Policy prescribe for standard operating process / procedures to bring

into focus any infringement / deviation / violation of the environmental or forest norms / conditions

? If so, it may be detailed in the EIA.

40. What is the hierarchical system or administrative order of the company to deal with the

environmental issues and for ensuring compliance with the EC conditions. Details of this system

may be given.

41. Does the company have a system of reporting of non compliances / violations of environmental

norms to the Board of Directors of the company and / or shareholders or stakeholders at large?

This reporting mechanism should be detailed in the EIA Report.

42. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be

incorporated in the EIA Report.

43. A tabular chart with index for point-wise compliance of above TORs.

The above TORs should be considered for the preparation of the draft EIA report in addition to all the relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the public consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report.

EC Amendment Cases:

[5]Sheraton Luxury, (Raghuvir Developers&Builders), T.P.S.No.5, Block No.69, O.P. No.86, F.P.No.86, Moje Bhimrad, Dist:Surat.

The SEIAA, Gujarat has accorded environmental clearance to M/s Raghuvir Developers & Builders for residential building construction project “Sheraton Luxury” vide order no. SEIAA/GUJ/EC/8(a)/

Page 16: Minutes of the 202th meeting

16  

162/2012 dated 31/05/2013 for the built-up area of 28,703.70 m2 at O.P. No.86, F.P.No.86, T.P.S.No.5, Vill. Bhimrad, Dist. Surat.

Now, the project proponent vide their letter dated 07/08/2013, stated that the built up area of the project is increasing due to increase in basement area as well as due to addition of the area of club house. Due to increase in basement area and additional area of club house, built up area of the project will be 30,450.32 m2 which was 28,703.70 m2 as per the Environmental Clearance granted by the SEIAA. The project proponent requested to amend the EC order dated 31/05/2013 with reference to the increased built up area of the project.

The request of amendment was considered during the meeting and it was presented that the basement area of the project which was 2,403.55 m2 as per the Environmental Clearance granted, has now increased to 3,856.30 m2. Due to increase in basement area and addition of built up area of club house-293.39 m2, the built up area will be 30,450.32 m2 which was 28,703.70 m2 as per the Environmental Clearance granted by the SEIAA. While asking by the committee, the project proponent replied that, the basement will be used for parking purpose and the club house will be provided for internal use of residents of the proposed project only. The project proponent has submitted the revised project plans and it was presented that the revised project plans have been approved by SMC.

Looking to the fact that the proposed increase in built up area does not lead to any increase in number of residential units, resource requirement or parking requirement for the project, it was decided to amend the EC order no. SEIAA/GUJ/EC/8(a)/162/2012 dated 31/05/2013 for the proposed change in built up area i.e 30,450.32 m2 instead of 28,703.70 m2.

[6] Panoli Intermediates (I) Pvt. Ltd(U-II), P.No 159/5 A, GIDC Nandesari, Dist Vadodara.

This is an existing chemical manufacturing unit which was accorded Environmental Clearance vide letter no. SEIAA/GUJ/EC/5(f) & 1(d)/147/2013 dated 15/07/2013. Environmental Clearance was granted with a condition to use Natural gas to the tune of 28,000 Nm3/day as a fuel in a Boiler (20 TPH) whereas natural gas to the tune of 6,000 Nm3/day shall be used as a fuel in new Power Plant (1.4 MW).

The project proponent vide their letter dated 20/07/2013 requested for amendment in Environmental Clearance order dated 15/07/2013 with respect to the change in fuel from natural gas to Coal.

The request was considered during the meeting and it was presented that due to steep increase in Natural Gas price, the natural gas utilization for the project became much costlier than what was estimated at the time of getting Environmental Clearance. As the energy is one of the vital cost factors in survival of the project, they need to change the fuel from natural gas to coal, which is five times cheaper than the natural gas. They are now planning to install a coal fired boiler of 20 MT capacity with ESP as APCM. 60 MT/day of coal will be used in the proposed coal fired boiler.

During the meeting, after detailed discussion on the matter, It was decided to further appraise the project only after submission of the following:

1. Detailed justification for proposed change in fuel.

2. Specific details on (i) Type, quantity and quality (CV, Sulphur content, Ash content, etc,) of fuel to

be used (iii) Flue gas emission details (iv) Air pollution Control Measures along with its adequacy

Page 17: Minutes of the 202th meeting

17  

to achieve the GPCB Norms. (v) List the sources of fugitive emission from the unit along with its

quantification and proposed measures to control it.

3. Base line status of ambient air quality and its comparison with ambient air quality results

mentioned in previous EIA Report for assessing change in ambient air quality.

4. Prediction of likely impacts on ambient air quality due to change of fuel by use of modeling. Air

quality modeling to be carried out considering the worst case scenario partial and complete

failure of the ESP. The details of model used and input parameters used for modeling should be

provided. The air quality contours may be shown on location map clearly indicating the location of

sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction

should also be indicated on the map.

5. Technical details of ESP along with its adequacy, details of its operational controls with DCS,

system for online monitoring of the pollutants from the stack etc. Details of provisions to be kept

in ESP to ensure that in any case the air emission does not cross the GPCB norms including

provision of standby field in the ESP, preventive maintenance, failure / tripping control system,

guarantee from the ESP supplier, alternative arrangements in case of the failure / tripping of the

ESP etc.

6. Plan for compliance to coal handling guidelines of the GPCB. Detailed plan for prevention and

control of fugitive emission / dusting at each and every stage of coal handling including unloading

/ loading, transportation, stacking/storage/conveyance/ transfer within the plant along with

detailed specifications & schematic diagram of water sprinkler system arrangement.

7. A detailed EMP including the protection and mitigation measures for the impacts on human

health and environment due to this proposed change as well as detailed monitoring plan.

Screening / Scoping Cases:

[7] Rajem Pharmascience Pvt. Ltd., Plot no. D-III/143,124/P,129/P,130/P,131/P, Vill. Samantpor, Ta: Vagra, GIDC-Dahej, Dist:Bharuch.

This is a new unit proposing to manufacture bulk drugs & drug intermediates with production capacity of 500 MT/Month. The proposed production falls in the category-5(f) of the schedule of the EIA Notification-2006.

Plot area will be 14,157 m2. Total project cost will be Rs 8.40 Crores. Total fresh water consumption will be 70 KLD during the operation phase, which will be sourced from GIDC water supply. Industrial effluent generation will be 40 KLD whereas domestic wastewater generation will be 8 KLD. Industrial effluent will be treated in the ETP prior to its discharge to the GIDC underground drainage system for its final disposal into Gulf of Khambhat. ETP having P+S treatment facilities is proposed to be installed. One steam boiler (cap. 1 TPH) using Coal-2 TPD as a fuel is proposed to be installed. Multi Cyclone as an Air Pollution Control Measure and stack with 30 m height is proposed. One DG set with capacity 250 KVA is proposed as standby facility during power cut in which LDO – 25 LPD will be used as fuel and stack with adequate height will be provided. Caustic and Water scrubbers are proposed as Air Pollution Control Measures for the process vent attached to Reactor for control of HCl, Cl2 & SO2 emission. Process Residues & Wastes (1,096 MT/Annum), Spent Carbon (260 MT/Annum), Spent Catalyst (120 MT/Annum), Spent Organic Solvent, Spent Acid (1,057 MT/Annum), Liquor Ammonia (100%) ( 1267.89 MT/Annum), Off Specification Products, ETP Sludge

Page 18: Minutes of the 202th meeting

18  

(2,500 MT/Annum), Spent Ion Exchange resin containing Toxic metals ( 0.5 MT/Annum), Used / Spent Oil( 12 MT/Annum), Discarded Containers/Barrels/Liners contaminated with hazardous wastes /chemicals are the hazardous waste to be generated from the proposed production. It is proposed to develop 35% of the total plot area as Green Belt.

During the meeting, the project proponent was asked not to discharge effluent into the GIDC pipeline and to achieve zero effluent discharge status by reusing the treated effluent completely within the premises. After detailed discussion, the following Terms of Reference were prescribed for the EIA study to be done covering 5 Km radial distance from the project boundary.

1. Copy of plot holding certificate obtained from GIDC Dahej.

2. Exact aerial distance of the project site from the nearest village.

3. Present land use pattern of the study area shall be given based on satellite imagery.

4. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all

round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders

without reversing back. Mark the same in the plant layout.

5. Details of manufacturing process / operations of each product along with chemical reactions,

mass balance, consumption of raw materials etc. Details on strategy for the implementation of

cleaner production activities.

6. Chemical name of each proposed product to be manufactured. Details on end use of each

product.

7. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative

and quantitative analysis of the each waste stream from the processes.

8. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from the GIDC for supply of raw water.

Undertaking stating that no bore well shall be dug within the premises.

9. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation.

10. Quality and quantity of waste water to be generated from the manufacturing process of each

product to be manufactured along with mass balance.

11. Proposal for achieving the zero effluent discharge outside the premises and details on application

wise break up of treated water utilization. Complete waste water management plan along with the

detailed effluent treatment scheme and disposal method in such a manner to achieve zero

effluent discharge outside the premises. Technical details of the ETP including size of each unit,

retention time etc. Provision of online flow meter at the final outlet of the ETP.

12. Stream wise qualitative & quantitative analysis of each waste stream to be generated.

Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-

vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be

generated. The characteristic on which treatability is based shall also be stated.

13. Plans for management, collection and disposal of waste streams to be generated from spillage,

leakages, vessel washing, used container washing etc. Measures proposed for preventing

effluent discharge during unforeseen circumstances.

Page 19: Minutes of the 202th meeting

19  

14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly

wind speed and direction and rainfall should be incorporated.

15. Anticipated environmental impacts due to the proposed project/production may be evaluated for

significance and based on corresponding likely impacts VECs (Valued Environmental

Components) may be identified. Baseline studies may be conducted within the study area of 10

km for all the concerned/identified VECs and likely impacts will have to be assessed for their

magnitude in order to identify mitigation measures.

16. One complete season base line ambient air quality data (except monsoon) to be given along with

the dates of monitoring. The parameters to be covered shall be in accordance with the revised

National Ambient Air Quality Standards as well as project specific parameters like Cl2, HCl. The

location of the monitoring stations should be so decided so as to take into consideration the pre-

dominant downwind direction, population zone and sensitive receptors. There should be at least

one monitoring station in the upwind direction. There should be at least one monitoring station in

the pre dominant downwind direction at a location where maximum ground level concentration is

likely to occur.

17. Modeling indicating the likely impact on ambient air quality due to proposed activities. The details

of model used and input parameters used for modeling should be provided. The air quality

contours may be shown on location map clearly indicating the location of sensitive receptors, if

any, and the habitation. The wind rose showing pre-dominant wind direction should also be

indicated on the map. Impact due to vehicular movement shall also be included into the prediction

using suitable model. Results of Air dispersion modeling should be superimposed on google map

/ geographical area map.

18. Base line status of the noise environment, impact of noise on present environment due to the

project and proposed measures for noise reduction including engineering controls.

19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of

the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission

rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with

its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed

measures to control it.

20. Details on management of the hazardous wastes to be generated from the project stating detail

of storage area for each type of waste, its handling, its utilization and disposal etc. How the

manual handling of the hazardous wastes will be minimized. Methodology of de-contamination

and disposal of discarded containers and its record keeping.

21. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration

Facility, if any.

22. Management plan for By-products to be generated, (if any) along with the name and address of

end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent

from them, showing their willingness to purchase said by-product from the proposed project.

Page 20: Minutes of the 202th meeting

20  

23. Name and quantity of each type of solvents to be used for proposed production. Details of solvent

recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing

the recovered solvents etc. for each type of solvent.

24. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed

for implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimization, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

25. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

26. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided. Provision of

industrial hygienist and monitoring of the occupational injury to workers as well as impact on the

workers. Plan for periodic medical checkup of the workers exposed. Details of work place

ambient air quality monitoring plan as per Gujarat Factories Rules.

27. Risk assessment including prediction of the worst-case scenario and maximum credible accident

scenarios should be carried out. The worst-case scenario should take into account the maximum

inventory of storage at site at any point of time. The risk contours should be plotted on the plant

layout map clearly showing which of the facilities would be affected in case of an accident taking

place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency

Plan should be provided.

28. MSDS of all the products and raw materials.

29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

30. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of

Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity

as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major

hazardous chemicals, size of the biggest storage tank to be provided for each raw material &

product etc. How the manual handling of the hazardous chemicals will be minimized?

31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof

electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control

plan for flammable substances and processes showing hydrant pipeline network, provision of DG

Sets, fire pumps, jockey pump, toxic gas detectors etc.

32. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

manufacturing utility staff for safety related measures.

33. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

Page 21: Minutes of the 202th meeting

21  

34. Detailed socio-economic development measures including community welfare program most

useful in the project area for the overall improvement of the environment. Submit a detailed plan

for social corporate responsibilities, with appropriate budgetary provisions for the next five years

and activities proposed to be carried out; specific to the current demographic status of the area.

35. A tabular chart for the issues raised and addressed during public hearing/consultation and

commitment of the project proponent on the same should be provided. An action plan to address

the issues raised during public hearing and the necessary allocation of funds for the same should

be provided.

36. (a) Does the company have a well laid down Environment Policy approved by its Board of

Directors? If so, it may be detailed in the EIA report.

(b). Does the Environment Policy prescribe for standard operating process / procedures to bring

into focus any infringement / deviation / violation of the environmental or forest norms / conditions

? If so, it may be detailed in the EIA.

37. What is the hierarchical system or administrative order of the company to deal with the

environmental issues and for ensuring compliance with the EC conditions. Details of this system

may be given.

38. Does the company have a system of reporting of non compliances / violations of environmental

norms to the Board of Directors of the company and / or shareholders or stakeholders at large?

This reporting mechanism should be detailed in the EIA Report.

39. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be

incorporated in the EIA Report.

40. A tabular chart with index for point-wise compliance of above TORs.

The above TORs should be considered for the preparation of the draft EIA report in addition to all the relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the public consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report.

[8] Vaibhav Villa, Block No: 23,24,25,26, O.P.No:115, F.P.No:115, T.P.S. No:25, Tehsil: Mota Varchha, Dist:Surat.

This is a new building construction project with plot area of 33,270.0 m2 and the proposed built up area of 45,854.70 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

It was presented that river Tapi is at a distance of 250 m from the project site. The project will comprise of total 139 bungalows of Ground floor + 3 floors with building height 14.6 m. Water requirement during the construction phase will be 15.0 KL/day and it will be obtained from SMC water supply. Domestic waste water generation during the construction phase will be 2.1 KL/day and it will be disposed off into the drainage line of SMC. Water requirement during operation phase will be 115.0 KL/day and it will be met through water supply from SMC. Domestic water-70.0 KL/day to be generated during the operation phase will be discharged into the drainage line of SMC. Municipal solid waste to the tune of 375 Kg/day will generate during the operation phase which will be collected by SMC and will be disposed at their sanitary waste dumping site. Total parking space of 9,915.21

Page 22: Minutes of the 202th meeting

22  

m2 equivalent to 354 CPS will be provided as open surface parking and is more than the parking requirement of 139 ECS as per NBC.

Proposed dust control measures during the construction phase are loading & transportation through covered trucks, covered shed for cement unloading, temporary wind screen around the project site, sprinkling of water on roads & in vicinity of storage area etc. Two nos. of D.G Sets having capacity of 30 KVA each using diesel (@ 10 liter/hour) as fuel will be provided for power back up. Energy conservation measures proposed include maximum use of natural light through architectural design, use of energy efficient motor and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, use of solar energy in external lighting & landscape lighting, rooftop thermal insulation etc. Provision of aerated coke (foam type) in wash basins & kitchen, low flush water closets in toilet, pressure reducing valves in pipeline etc. have been proposed as water conservation measures. The nearest fire station at Varachha is approx. 4 Km away from the project site. Fire extinguishers, and manually operated electric fire alarm system will be provided as fire fighting facilities. Area provision for green belt development is 7,000 m2 with 1000 nos. of trees. Personal Protective Equipments, provision of first aid box, free medicine, doctor service, along with the basic amenities like tap water, sanitation & drinking water facilities etc. will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 09 nos. of percolating wells is proposed to be carried out. The project site is having direct access through 36 m and 12 m wide roads on northern and southern sides respectively.

During the meeting, while asking by the committee, it was replied by the project proponent that the water supply and drainage lines are available in the area and same will be available for the project at the time of getting B.U. permission from SMC. After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of Environmental Clearance.

[9] Vikash H. Aahir, F.P.No.67,O.P.No.67, New R.S.No.252-1+254 +257, Moje:Vesu, Draft T.P.S.No.75, Vill:Vesu-Magdalla-Gavier-Abhava, Dist:Surat.

This is a new building construction project having plot area of 31,550.0 m2 and the proposed built up area of 69,188.39 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

This is a proposed building construction project having plot area of 31,550.0 m2 and the proposed built up area of 69,188.39 m2. The project will comprise of 14 buildings housing total 222 nos. of flats. From the total fourteen buildings, scope of five buildings will be hollow plinth + 10 floors, scope of four buildings will be hollow plinth + 6 floors, scope of one building will be hollow plinth + 9 floors and scope of four buildings will be hollow plinth + 7 floors. Maximum building height in the project will be 36.65 m.

During construction phase, water requirement of 10.3 KL/day will be met through water supply from Surat Municipal Corporation (SMC) and domestic wastewater to be generated will be disposed off through septic tank/soak pit system. During operation phase, 153.0 KL/day of water requirement will be met through water supply from SMC and it is proposed that the domestic waste water – 128 KL/day will be discharged through underground drainage line of SMC. Municipal solid waste to the tune of 600.0 Kg/day to be generated will be finally disposed off as per the provisions made by the SMC. Total parking space 10,643.83 m2 [7,717.52 m2 as ground floor covered parking + 2,926.31 m2 as open surface parking] will be provided, which is equivalent to 402 ECS. Parking area to be

Page 23: Minutes of the 202th meeting

23  

provided is more than the GDCR requirement of 8,518.50 m2 and NBC requirement of 222 ECS. Measures like vertical curtails, regular water sprinkling, covered shed for cement unloading, covering construction material with tarpaulin sheet have been proposed as dust control measures during construction phase. Energy conservation measures like maximum utilization of natural light, roof top thermal insulation, CFL lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc. has been proposed during construction phase. Terrace fire water tanks, underground fire water storage tank of 75 KL capacity, manually operated electric fire alarm system, fire extinguishers, hose reel etc. are proposed as fire safety measures. The nearest fire station of Majuragate is @ 8-9 Km away from the project site and the fire tender will take about 15-20 minutes to reach the project site. Provision of Personal Protective Equipments, first aid kit along with the provision of basic amenities like tap water, sanitation & drinking water, free medicines & doctor service will be made for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 8 nos. of percolating wells is proposed to be carried out. It is proposed to develop 2,862.08 m2 green area including 580.66 m2 tree covered area and 2,281.42 m2 lawn covered area. The project site is accessible through 18 m wide road on northern side. It is proposed to provide 9 m wide internal roads, two separate gates and atleast 7 m wide open peripheral margin all along the boundary wall.

During the meeting, looking to the large scale of the project, the project proponent was suggested to provide STP for treatment of domestic sewage to be generated during the operation phase of the project. Further they were asked to ensure that the water of fire water storage tanks will not be utilized for any purpose other than the fire fighting. After detailed discussion, it was decided to recommend the project for grant of Environmental Clearance only after submission of the following:

1. Details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its

location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation

phase.

2. Revised water balance details considering the reuse of treated water after provision of STP in

operation phase.

3. Complete treated water management plan along with the application wise breakup of treated

water utilization. Management plan of treated sewage during rainy season when utilization of

treated water for gardening/plantation purpose is not possible.

4. Detail & design of dual plumbing system to be provided for reuse of treated waste water.

5. STP sludge management plan.

[10] Hasmukhbhai R. Aahir, Sub Div No.2, F.P.No. 59/A/Paikee, O.P.59, New 248+260+ 261+264/1 Paikee Sub Plot No:2 Paikee Sub Div No.6, Moje-Vesu, Draft T.P.S.No. 75, Vill : Vesu-Magdalla-Gavier-Abhava, Dist :Surat.

This is a new building construction project having plot area of 46,935.0 m2 and the proposed built up area of 1,01,845.61 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

This is a proposed building construction project having plot area of 46,935.0 m2 and the proposed built up area of 1,01,845.61 m2. The project will comprise of 20 buildings housing total 330 nos. of

Page 24: Minutes of the 202th meeting

24  

flats. Scope of five buildings will be hollow plinth + 9 floors and scope of fifteen buildings will be hollow plinth + 8 floors. Maximum building height in the project will be 33.30 m.

During construction phase, water requirement of 10.3 KL/day will be met through Surat Municipal Corporation (SMC) water supply and domestic wastewater to be generated will be disposed off through septic tank/soak pit system. During operation phase, 223.0 KL/day of water requirement will be met through water supply from SMC and it is proposed that the domestic waste water – 186 KL/day will be discharged through underground drainage line of SMC. Municipal solid waste to the tune of 891.0 Kg/day to be generated will be finally disposed off as per the provisions made by the SMC. Measures like vertical curtails, regular water sprinkling, covered shed for cement unloading, covering construction material with tarpaulin sheet have been proposed as dust control measures during construction phase. Energy conservation measures like maximum utilization of natural light, roof top thermal insulation, CFL lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc. has been proposed during construction phase. Terrace fire water tanks, underground fire water storage tank of 75 KL capacity, manually operated electric fire alarm system, fire extinguishers, hose reel etc. are proposed as fire safety measures. The nearest fire station of Majuragate is @ 8 Km away from the project site and the fire tender will take about 15-20 minutes to reach the project site. Provision of Personal Protective Equipments, first aid kit along with the provision of basic amenities like tap water, sanitation & drinking water, free medicines & doctor service will be made for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 12 nos. of percolating wells is proposed to be carried out. It is proposed to develop 3,239.21 m2 green area including 892.12 m2 tree covered area and 2,347.09 m2 lawn covered area. The project site is accessible through 18 m wide road on northern side. It is proposed to provide 12 m and 9 m wide internal roads, two separate gates and atleast 7 m wide open peripheral margin all along the boundary wall.

During the meeting, looking to the large scale of the project, the project proponent was suggested to provide full fledged STP for treatment of entire quantity of domestic sewage to be generated during the operation phase of the project. Further they were asked to ensure that the water of fire water storage tanks will not be utilized for any purpose other than the fire fighting. It was noticed by the committee that the proposed parking area shown in hollow plinth is more than the actual area available in the hollow plinth as per the project plans submitted and so the project proponent was asked to submit the realistic details on parking area provision for the proposed project. After detailed discussion, it was decided to recommend the project for grant of Environmental Clearance only after submission of the following:

1. Realistic details on parking area to be provided for the proposed project as per NBC norms taking

into consideration the actual area available in hollow plinth.

2. Details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its

location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation

phase.

3. Revised water balance details considering the reuse of treated water after provision of STP in

operation phase.

Page 25: Minutes of the 202th meeting

25  

4. Complete treated water management plan along with the application wise breakup of treated

water utilization. Management plan of treated sewage during rainy season when utilization of

treated water for gardening/plantation purpose is not possible.

5. Detail & design of dual plumbing system to be provided for reuse of treated waste water.

6. STP sludge management plan.

[11] BMS Chemie, Plot no. 47/1/16 & 17, GIDC Nandesari, Vill.Nandesari, Ta. & Dist. Vadodara.

It is an existing unit proposing the expansion by augmentation in production capacity of four of the existing products as well as by manufacturing of four new products. Two of the existing products will not be manufactured after the proposed expansion. The production activity falls in the project activity 5(f) as per the schedule of EIA Notification,2006.

Details of production capacity after the proposed expansion is tabulated below.

Sr. no. Name of Products Production (MT/Month) Existing Proposed Total 1. Trichloro Salicylic Acid 1.5 -1.5 00 2. N-Pentyl Trichlorosalicylate 0.1 -0.1 00 3. Organic Compounds

Oxyclozanide (by purification)* 1.0 0.25

1.5 Benz - Bromarone 0.25

Oxalamine Citrate 0.00 4. Tartaric Acid Derivatives

Para Ditoluoyl Tartaric Acid 1.0 13.0 14.0 Dibenzoyl Tartaric Acid 0.0

5. 2-Acetylamino-5- mercapto-1,3,4-thiadiazole

0.0 1.5

6. Water Based Polymethane Resins (D Pure 163, D Pure 170, R Modi 2015, others)

0.0 20.0 20.0

7. Solvent Based Resins (1K PU, RSC - 2012, others)

0.0 16.0 16.0

* The existing process for manufacturing Oxyclozanide is changed from synthesis to Purification

This is an expansion project and will take place within the existing premises. No additional land is required for the proposed expansion. Plot area is approx.1,318 sq.m. Estimated cost of proposed expansion is Rs. 19.1 Lacs. Fresh water requirement will be increased from 32.2 KLD to 48 KLD. (Additional 24.8 KLD). Additional water requirement will be supplied by the GIDC. Wastewater generation after the expansion will be increased from 12.5 KLD to 21.5 KLD (Additional 9 KLD).The industry proposes to establish an adequate ETP comprising primary and secondary treatment facilities with recycling of additional 8.5 KLD of industrial effluent and dispose only 11.5 KLD of treated effluent to CETP, till the CETP expansion is complete. CETP membership certificate for disposal of 20 KLD treated effluent has been obtained.

Consumption of natural gas 5 SCM/hr in existing steam boiler (cap. 0.8 TPH) will remain same. Unit is having one DG set with capacity 50 KVA as standby facility to be used in case of power failure. Emission of HCl & SO2 is envisaged from the manufacturing process and 2 nos. of primary water

Page 26: Minutes of the 202th meeting

26  

scrubbers followed by one secondary caustic scrubber are proposed as Air Pollution Control Measures.

ETP Sludge, Distillation residue, Spent Carbon, Discarded bags/containers/barrels/liners, Spent solvent and used oil will be generated as hazardous wastes.

During the meeting, the project proponent was asked not to sell spent solvent outside the premises. After detailed discussion, the following Terms of Reference were prescribed for the EIA study to be done covering 5 km radial distance from the boundary of the project site.

1. Need for the proposed expansion should be justified in detail. 2. Demarcation of proposed expansion activities in lay out of the existing premises. 3. Exact details about additional infrastructural facilities, plant machineries etc. required for the

proposed expansion. 4. Detailed manufacturing process along with chemical reactions and mass balance (including reuse-

recycle, if any). 5. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the proposed expansion. Copy of permission obtained from GIDC for additional water supply.

6. Water consumption and consumption of each raw material per MT of each product. 7. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative

analysis of the each waste stream to be generated. A detailed treatability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated.

8. Complete waste water management plan for existing as well as proposed production. Detailed effluent treatment scheme and disposal method. Technical details of the ETP including size of each unit, retention time etc. including modifications / up gradation to be done in existing ETP to take care of increased effluent quantity along with its adequacy report. Provision of online flow meter at the final outlet of the ETP.

9. Application wise breakup of treated water utilization. 10. Plan for management and disposal of waste streams to be generated from spillage, leakages,

occasional reactor washing and exhausted media from Scrubber etc. 11. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation. 12. One season site-specific meteorological data including temperature, relative humidity, hourly

wind speed and direction and rainfall shall be provided 13. One complete season AAQ data (except monsoon) to be given along with the dates of

monitoring. Parameters to be considered shall be in accordance with the revised national ambient air quality standards. Project specific parameters shall be considered in addition to general parameters. The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

14. Impact of the project on the AAQ of the area. Details of the model used and the input parameters used for modeling should be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation, sensitive receptors, if any. The wind roses should also be shown on this map.

Page 27: Minutes of the 202th meeting

27  

15. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate emission from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.

16. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized.

17. Methodology of de-contamination and disposal of discarded containers and its record keeping. 18. Membership of Common Environmental Infrastructure including the TSDF / Common Hazardous

Waste Incineration facility along with an assessment to accommodate the additional quantity of wastes to be generated.

19. Management plan for By-products to be generated, (if any) along with the name and address of

end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent

from them, showing their willingness to purchase said by-product from the proposed project.

20. Name and quantity of each type of solvents to be used for proposed production. Details of solvent

recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing

the recovered solvents etc. for each type of solvent.

21. Management plan for By-products to be generated, (if any) along with the name and address of

end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent

from them, showing their willingness to purchase said by-product from the proposed project.

22. Name and quantity of each type of solvents to be used for proposed production. Details of solvent

recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing

the recovered solvents etc. for each type of solvent.

23. Data on air emissions, wastewater generation and solid / hazardous waste generation and management for the existing plant should also be incorporated.

24. Details of measures proposed for the noise pollution abatement and its monitoring. 25. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

26. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided to the workers. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.

27. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impact.

28. Details of quantity of each hazardous chemical to be stored, material of construction of major hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals.

Page 28: Minutes of the 202th meeting

28  

29. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the map clearly showing which of the facilities and surrounding units would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.

30. Details of fire fighting system including provision for flame detectors, temperature actuated heat detectors with alarms, automatic sprinkler system, location of fire water tanks & capacity, separate power system for fire fighting, details of qualified and trained fire personnel & their job specifications, nearest fire station & time required to reach the proposed site. Submit line diagram of the fire hydrant network.

31. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.

32. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.

33. Copies of analysis report of the water samples of final outlet of ETP collected by GPCB. 34. Consent to Establish, Consent to Operate orders obtained in past along with point wise

compliance status of all the conditions stipulated therein. 35. Copy of Environmental Clearance obtained for the existing project and a certified report of the

status of compliance of the conditions stipulated in the environmental clearance for the existing operation of the project by the Regional Office of the MoEF.

36. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure notices etc. served by the GPCB to the existing unit in last five years and actions taken then after for prevention of pollution.

37. Details of fatal / non-fatal accidents, loss of life or man hours, if any, occurred in the existing unit in last three years and measures proposed to be taken for avoiding reoccurrence of such accidents in future.

38. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.

39. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

40. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.

41. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.

42. A tabular chart with index for point-wise compliance of above TORs.

The above TORs should be considered for preparation of the EIA report in addition to all relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the public

Page 29: Minutes of the 202th meeting

29  

consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report.

[12] Saurashtra Township, Block No;44, Navgam, Kamraj, Surat.

This is a new building construction project with plot area of 10,722.60 m2 and the proposed built up area of 26,757.49 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project will comprise of total 9 building blocks housing total 388 residential units and 37 commercial units. Scope of 6 buildings will be ground floor + 4 floors and scope of remaining 3 buildings will be ground floor + 5 floors. Maximum building height will be 23.25 m. Water requirement during the construction phase will be 30.0 KL/day and it will be obtained from water supply system of GWSSB (Juth Yojana). Domestic waste water generation during the construction phase will be 4.2 KL/day and it will be disposed off into septic tank/soak pit system. Total water requirement during operation phase will be 256.0 KL/day, out of which 156 KL/day of fresh water requirement will be obtained from water supply system of GWSSB (Juth Yojana) and 100 KL/day of water requirement for gardening & flushing will be met through treated water. Domestic water-200.0 KL/day to be generated during the operation phase will be treated in the proposed onsite STP. Treated water will be utilized for gardening purpose as well as flushing purpose and it is proposed that the remaining quantity of treated sewage will be used for irrigation purpose in nearby areas. Municipal solid waste to the tune of 1,096.5 Kg/day will generate during the operation phase which will be disposed off at the nearest sanitary waste dumping site. Total parking space of 5,793.69 m2 [2,116.08 m2 in hollow plinth + 3,677.61 m2 as open surface parking] equivalent to 234 CPS will be provided which is more than parking requirement of 208 ECS as per NBC.

Proposed dust control measures during the construction phase are loading & transportation through covered trucks, covered shed for cement unloading, temporary wind screen around the project site, sprinkling of water on roads & in vicinity of storage area etc. D.G Sets- 4 × 60 KVA each using diesel (@ 10 liter/hour) as fuel will be provided as power back up arrangement. Energy conservation measures proposed include maximum use of natural light through architectural design, use of energy efficient motors and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, use of solar energy in external lighting & landscape lighting, rooftop thermal insulation etc. Provision of aerated coke (foam type) in wash basins & kitchen, low flush water closets in toilet, pressure reducing valves in pipeline etc. have been proposed as water conservation measures. Seven buildings will be provided with 2 nos. of staircases and two buildings will be provided with 3 no. of staircases. The nearest Varachha fire station is approx.5 Km away from the project site. Fire extinguishers, hose reel, wet riser, manually operated electric fire alarm system, terrace fire water storage tank of 15 KL capacity, underground fire water storage tank of 100 KL capacity will be provided as fire fighting facilities. Area provision for green belt development is 1,100.0 m2 with 200 nos. of trees. Personal Protective Equipments, provision of first aid box, free medicine, doctor service, along with the basic amenities like tap water, sanitation & drinking water facilities etc. will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 03 nos. of percolating wells is proposed to be carried out. The project site is having direct access through 12 m wide road on eastern side.

Page 30: Minutes of the 202th meeting

30  

During the meeting, the project proponent was asked to increase the parking area provision. After detailed discussion, it was decided to recommend the project only after satisfactory submission of the following:

1. Copy of permission obtained for non agricultural use of the project site. 2. Revised details on increased parking area provision with complete back up calculation. In case, a

basement is to be provided for increasing the parking area, the basement parking plan, revised project plans showing provision of basement with two separate ramps & increased built up area table (due to additional built up area of the basement) shall also be submitted.

3. Number of trees existing at the project site, number of trees to be retained and number of trees to be cut along with the copy of permission obtained from concerned authority for cutting the trees.

4. Copy of permission obtained from concerned authority for water supply to the proposed project. 5. Application wise break up of treated water utilization and treated water management plan during

the monsoon season when the treated water utilization for irrigation purpose is not feasible. Copy of agreement letters from nearby farmers regarding utilization of treated water from the proposed project for irrigation purpose.

[13] Ambay Valley heights, Bloak No:182+147 K, R.S.No.205/3+169/3, O.P.No.72&73, F.P.No.72,83 (as per draft),F.P.No.51,89(as per preliminary)T.P.S.No.27,Uttran-Kosad, Surat.

This is a new building construction project with plot area of 17,032.0 m2 and the proposed built up area of 57,534.42 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project will comprise of total 9 buildings (8 residential buildings and 1 commercial building) housing total 384 residential units and 264 commercial units. Scope of 8 residential buildings will be hollow plinth + 12 floors and scope of commercial building will be ground floor + 5 floors. Maximum building height will be 44.75 m. Water requirement during the construction phase will be 30.0 KL/day and it will be obtained from SMC water supply. Domestic waste water generation during the construction phase will be 4.2 KL/day and it will be disposed off into the drainage line of SMC. Water requirement during operation phase will be 295.0 KL/day and it will be met through water supply from SMC. Domestic water-236.0 KL/day to be generated during the operation phase will be treated in the proposed onsite STP. Treated water will be utilized for gardening purpose and the remaining quantity of treated sewage will be discharged into the drainage line of SMC. Municipal solid waste to the tune of 1,392.4 Kg/day will generate during the operation phase which will be disposed off as per the provisions made by SMC. Total parking space of 11,811.80 m2 equivalent to 415 CPS will be provided which is more than parking requirement of 412 ECS as per NBC.

Proposed dust control measures during the construction phase are loading & transportation through covered trucks, covered shed for cement unloading, temporary wind screen around the project site, sprinkling of water on roads & in vicinity of storage area etc. Four D.G Sets having capacity of 60 KVA each using diesel (@ 10 liter/hour) as fuel will be provided for power back up. Energy conservation measures proposed include maximum use of natural light through architectural design, use of energy efficient motors and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, use of solar energy in external lighting & landscape lighting, rooftop thermal insulation etc. Provision of aerated coke (foam type) in wash basins & kitchen, low flush water closets in toilet, pressure reducing valves in pipeline etc. have been proposed as water conservation measures. One

Page 31: Minutes of the 202th meeting

31  

staircase of 2.03 m width will be provided for each block. The nearest fire station at Kosad is approx. 4.5 Km away from the project site. Fire extinguishers, hose reel, wet riser, manually operated electric fire alarm system, terrace fire water storage tank of 15 KL capacity, underground fire water storage tank of 100 KL capacity will be provided as fire fighting facilities. Area provision for green belt development is 1,700.0 m2 with 180 nos. of trees. Personal Protective Equipments, provision of first aid box, free medicine, doctor service, along with the basic amenities like tap water, sanitation & drinking water facilities etc. will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 05 nos. of percolating wells is proposed to be carried out. The project site is having direct access through 36 m and 12 m wide roads on northern and eastern sides respectively.

During the meeting, the project proponent was asked to plant trees on the periphery all along the boundary wall as well as on the boundaries of the common open plot. While asking by the committee, the project proponent replied that the project site is within the limits of Surat Municipal Corporation and will get the water supply as well as drainage connection at the time of getting BU permission for the project. After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance only after submission of the following:

1. Details on the highest of the high flood level of the area recorded in the past and details regarding existing ground level, proposed ground level and plinth level for ensuring that the project won’t be affected by flood.

[14] Polyols & Polymer, Plot no. D-2/CH/266,267&268, Dahej-II, Notified Industrial Estate, Jolva, Ta: Vagra, Dist.: Bharuch.

This is a new unit proposing to manufacture Synthetic Organic Products (Synthetic Resins) with production capacity of 5917 MT/Month (As mentioned in application form). The proposed production activity falls in the category-5(f) of the schedule of the EIA Notification-2006. Plot area will be 14,347 m2. Total project cost will be Rs 4,194 Lacs. Total fresh water consumption will be 125 KLD during the operation phase, which will be sourced from GIDC water supply. Industrial effluent generation will be 138 KLD. Domestic wastewater generation will be 12 KLD, which will be disposed off into soak pit via septic tank. ETP having primary, secondary and tertiary treatment facilities is proposed to be installed. It is proposed that the treated effluent will be discharged into deep sea through u/g pipeline of GIDC. Two nos. of steam boilers (Cap. 2 TPH & 3 TPH) and two nos. of Thermic Fluid heaters (Cap.1000U & 1500U) are proposed. Coal-35 MT/day or Briquettes-45 MT/day or Natural Gas -16000 SCM/day will be used as fuel. Bag filters as Air Pollution Control Measures and stacks with 21 m height are proposed. One DG set with capacity 250 KVA is proposed as standby facility during power cut in which Diesel – 40 L/hr will be used as fuel and adequate stack height will be provided. No process gas emission is envisaged. ETP Sludge (360 MT/Annum), Used oil (400 Liters/Annum), Discarded Containers (2,000 drums/Annum) & bags/liners (20,000 bags/Annum), Spent Catalyst (5.3 MT/Month), Resin waste (80 MT/Month) will be generated as hazardous wastes. It is proposed to develop 4,735.5 m2 area as Green Belt.

Technical presentation by the project proponent included introduction of the company, highlights of the proposed project, project location, Google image showing surrounding area of the project site, breakup of the proposed land use, capital cost of the project, product details, manufacturing process, raw material requirement, product & raw material storage details, details of equipments, resource consumption, details of water consumption and wastewater generation, wastewater management

Page 32: Minutes of the 202th meeting

32  

system, air pollution & management system, hazardous waste generation & its management, recurring cost of EMP, safety measures, environmental impact & conclusion, proposed TOR for scoping of EIA study etc.

During the meeting, the project proponent requested to allow them to use primary baseline data collected during the November-2013 to January 2014 for preparation of EIA report. The request was considered by the committee, as the baseline data collected by them are not older than two years. Further the project proponent was asked to explore the possibility of achieving zero effluent discharge status by reusing/recycling the treated effluent within the premises. After detailed discussion, the following Terms of Reference were prescribed for the EIA study to be done covering 10 Km radial distance from the boundary wall of the project site.

1. Copy of plot holding certificate obtained from GIDC Dahej.

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all

round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders

without reversing back. Mark the same in the plant layout.

4. Details of manufacturing process / operations of each product along with chemical reactions,

mass balance, consumption of raw materials etc. Details on strategy for the implementation of

cleaner production activities.

5. Chemical name of each proposed product to be manufactured. Details on end use of each

product.

6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative

and quantitative analysis of each waste stream from the processes.

7. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from the GIDC for supply of raw water.

Undertaking stating that no bore well shall be dug within the premises.

8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation.

9. Quality and quantity of waste water to be generated from the manufacturing process of each

product to be manufactured along with mass balance.

10. Stream wise qualitative & quantitative analysis of waste streams to be generated. Characteristics

of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy

and efficacy of the treatment facilities proposed for the wastewater to be generated. The

characteristic on which treatability is based shall also be stated.

11. Details of the ETP units including its capacity, size of each unit, retention time and other technical

parameters.

12. Explore the possibility of achieving zero effluent discharge status by reusing /recycling the treated

effluent for various purposes within the premises.

13. Plans for management, collection and disposal of waste streams to be generated from spillage,

leakages, vessel washing, used container washing etc. Measures proposed for preventing

effluent discharge during unforeseen circumstances.

14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly

wind speed and direction and rainfall should be incorporated.

Page 33: Minutes of the 202th meeting

33  

15. Anticipated environmental impacts due to the proposed project/production may be evaluated for

significance and based on corresponding likely impacts VECs (Valued Environmental

Components) may be identified. Baseline studies may be conducted within the study area of 10

km for all the concerned/identified VECs and likely impacts will have to be assessed for their

magnitude in order to identify mitigation measures.

16. One complete season base line ambient air quality data (except monsoon) to be given along with

the dates of monitoring. The parameters to be covered shall be in accordance with the revised

National Ambient Air Quality Standards as well as project specific parameters. Location of the

monitoring stations should be so decided so as to take into consideration the pre-dominant

downwind direction, population zone and sensitive receptors. There should be at least one

monitoring station in the upwind direction. There should be at least one monitoring station in the

pre dominant downwind direction at a location where maximum ground level concentration is

likely to occur.

17. Modeling indicating the likely impact on ambient air quality due to proposed activities. The details

of model used and input parameters used for modeling should be provided. The air quality

contours may be shown on location map clearly indicating the location of sensitive receptors, if

any, and the habitation. The wind rose showing pre-dominant wind direction should also be

indicated on the map. Impact due to vehicular movement shall also be included into the prediction

using suitable model. Results of Air dispersion modeling should be superimposed on google map

/ geographical area map.

18. Base line status of the noise environment, impact of noise on present environment due to the

project and proposed measures for noise reduction including engineering controls.

19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of

the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission

rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with

its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed

measures to control it.

20. Details on management of the hazardous wastes to be generated from the project stating detail

of storage area for each type of waste, its handling, its utilization and disposal etc. How the

manual handling of the hazardous wastes will be minimized. Methodology of de-contamination

and disposal of discarded containers and its record keeping.

21. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration

Facility, if any.

22. Management plan for By-products (if any) to be generated, along with the name and address of

end consumers to whom the by-product/s will be sold. Copies of agreement / MoU / letter of

intent from them, showing their willingness to purchase said by-product/s from the proposed

project.

Page 34: Minutes of the 202th meeting

34  

23. Name and quantity of each type of solvents to be used for proposed production. Details of solvent

recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing

the recovered solvents etc. for each type of solvent.

24. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed

for implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimization, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

25. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

26. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided. Provision of

industrial hygienist and monitoring of the occupational injury to workers as well as impact on the

workers. Plan for periodic medical checkup of the workers exposed. Details of work place

ambient air quality monitoring plan as per Gujarat Factories Rules.

27. Risk assessment including prediction of the worst-case scenario and maximum credible accident

scenarios should be carried out. The worst-case scenario should take into account the maximum

inventory of storage at site at any point of time. The risk contours should be plotted on the plant

layout map clearly showing which of the facilities would be affected in case of an accident taking

place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency

Plan should be provided.

28. MSDS of all the products and raw materials.

29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

30. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of

Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity

as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major

hazardous chemicals, size of the biggest storage tank to be provided for each raw material &

product etc. How the manual handling of the hazardous chemicals will be minimized?

31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof

electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control

plan for flammable substances and processes showing hydrant pipeline network, provision of DG

Sets, fire pumps, jockey pump, toxic gas detectors etc.

32. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

manufacturing utility staff for safety related measures.

33. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

Page 35: Minutes of the 202th meeting

35  

34. Detailed socio-economic development measures including community welfare program most

useful in the project area for the overall improvement of the environment. Submit a detailed plan

for social corporate responsibilities, with appropriate budgetary provisions for the next five years

and activities proposed to be carried out; specific to the current demographic status of the area.

35. A tabular chart for the issues raised and addressed during public hearing/consultation and

commitment of the project proponent on the same should be provided. An action plan to address

the issues raised during public hearing and the necessary allocation of funds for the same should

be provided.

36. (a) Does the company have a well laid down Environment Policy approved by its Board of

Directors? If so, it may be detailed in the EIA report.

(b). Does the Environment Policy prescribe for standard operating process / procedures to bring

into focus any infringement / deviation / violation of the environmental or forest norms / conditions

? If so, it may be detailed in the EIA.

37. What is the hierarchical system or administrative order of the company to deal with the

environmental issues and for ensuring compliance with the EC conditions. Details of this system

may be given.

38. Does the company have a system of reporting of non compliances / violations of environmental

norms to the Board of Directors of the company and / or shareholders or stakeholders at large?

This reporting mechanism should be detailed in the EIA Report.

39. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be

incorporated in the EIA Report.

40. A tabular chart with index for point-wise compliance of above TORs.

The above TORs should be considered for the preparation of the draft EIA report in addition to all the relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the public consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report.

The following proponents did not remain present during the meeting:

1. Sahara City Homes, (Sahara Prime City Ltd), Survey.No.28,29,23,25/1,27, 25/2, 24, 21/P,22/4,22/3,22/3,22/1,Vill : Sidsar Ta : Bhavnagar Dist : Bhavnagar.

2. Indian Oil Corporation Ltd., Gujarat Refinery, Indian Oil Corporation Ltd., Jawaharnagar, Dist: Vadodara

3. Shridhar Residency, F.P.No.28, T.P.S. No .24, Vill: Tandalja, Ta : Vadodara. Dist : Vadodara 4. Pramukhyog (Ganshyam K. Kevadiya), T.P.No.26 ,R.S.No.139, O.P.No.69, F.P.No. 105/1, Vill :

Singanpore, Tehsil : Surat, Dist : Surat 5. Vandemataram Homes (Trilok (Vikas)Co.Op.Housing Society), Survey No.69/1+70/1, Vill :

Chenpur, Tehsil : City, Dist : Ahmedabad 6. Synthetic Organic Chemicals (Rossari Biotech Ltd), Plot No : D-II/CH/223, Dahej-II, Industrial

Estate Tehsil : Vagra, Dist : Bharuch 7. Shyam Residency – 63, Survey No : 591, O.P. No : 63, F.P. No : 63, Vill : Kathwada, Ta : Daskroi,

Dist:Ahmedabad 8. Green Fortune, (K. L. Lathiya), R.S. No : 340, 321, OP. No : 34, 41, F.P. No : 38, 42/Paikee, Sub

Page 36: Minutes of the 202th meeting

36  

Plot No : 1, Vill : Vesu, Ta : Choryasi, Dist :Surat. 9. V3 World (Shaan Leisure Ltd), Survey No : 504/1/P, 505/P, 558/P, and 559/p, F.P. No : 76/1, TPS

No : 63, Vill:Khoraj, Ta: Dascroi, Dist:Ahmedabad 10. Ramanbhai Maganbhai Patel, Survey No:1021, Ta:Kalol, Dist:Gandhinagar. 11. Rishi Kiran Logistics Pvt. Ltd., Plot No:7, Link Road, Vill:Old Kandla,Ta:Gandhidham, Dist: Kutch 12. The Parkway, Block No:120,62 paiky 1, 134/1 /1, 130, 117,119,118 Paiky-1, 128 116-

1,111,112,129,63, Vill : Sandalpore, Ta:Jalalpore, Dist : Navsari. 13. Shiv Vandan (Shiv Developers), S.No.153, F.P.No.48, Ta : Chiloda,Dist : Ahmedabad. 14. Jai Swaminarayan Company, Plot No:7,GIDC Nagor, Ta: Bhuj,Dist:Kutch. 15. Union Residency (Sumangal Corporation ), T.P.S.No.28(Rundh-Vesu), F.P.No.16,Vill : Opp.

Happy Home, Udhana-Magdalla Road),Ta:Choryasi, Dist:Surat. 16. Garden Silk Mills Ltd., Plot No:1 & 2, GIDC Valia, Vill:Valia, Dist:Bharuch.

It was decided to call them in the upcoming meeting of SEAC.

Minutes approved by :

1. Dr. Nikhil Desai, Member, SEAC.

2. Shri R.I.Shah, Member, SEAC.

3. Shri V.C.Soni, Member, SEAC.

4. Shri R.J.Shah, Member, SEAC.

5. Shri Hardik Shah, Secretary, SEAC.