mining plan -...
TRANSCRIPT
MINING PLANFOR
GEVRA OPENCAST PROJECTGEVRA AREA
FOR
ENHANCEMENT OF PRODUCTIONFROM 35.00 MTY TO 50.00 MTY
(APPROVED EC CLEARANCE 41.0MTY)
MAY, 2016
SOUTH EASTERN COALFIELDS LIMITED(A MINI RATNA COMPANY)
(A Subsidiary of Coal India Limited)SECL COMPLEX, SEEPAT ROAD
BILASPUR - (C.G.) 495006
MINING PLAN FORGEVRA OPENCAST EXPANSION PROJECT (35 to 50 Mty)
CONTENTS
CONTENTSSL NO PARTICULARS PAGE NOPART-I
Chapter-1 Introduction 1-2
Chapter-2 Salient feature of Approved PR of Gevra OCExpn (35-70Mty)
1-12
Chapter-3 Performance of Existing Mine 1- 4
Chapter-4 Proposal for enhancement of production from35.00 Mty to 50.00 Mty.
1-5
Chapter-5 Environment Management 1-21
PART-II PLATES1 Existing Plan showing quarry stage as on
01.04.2016Plate – I
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------1
CHAPTER – 1
INTRODUCTION
1.0 BACKGROUND OF THE REPORTThe Gevra OCM is an existing mega opencast project in the thick seam zone
of Korba coalfields in SECL command area. It is under the administrative control of
Gevra Area of SECL. The Project Report for Gevra Expansion Opencast Project
(25.0 to 35.0 Mty) was approved in June 2010 for a normative production of 35.0
Mty. Presently, Gevra Expn. OCM is having Environment Clearance for a peak coal
production of 41.0Mty against the normative production of 35.0 Mty. The mine has
achieved the coal production of 41.0 Mty in the year 2015-16. Recently the Project
Report for Gevra Expansion Opencast Project (35.0 to 70.0 Mty) was approved by
CIL Board on dated 5th March 2016.
Based on “Road Map for Enhancement Coal Production of CIL” the target of
SECL for the year 2016-17 has been projected as 149.70 Mt. To meet this growth in
production of SECL in the year 2016-17, Gevra OC has been identified for
enhancement of production from peak production of 41.0 Mty to proposed
normative production of 50.0 Mty due to unavoidable delay in opening of other new
projects.
Accordingly this mining plan for enhancement of production from 35.0 Mty to
50.0 Mty has been prepared to produce 50.0 Mty of coal from Gevra Expn.
Opencast Project. As on 01.04.2016, the balance coal within the approved quarry
boundary is 568.86 Mt and balance OB within the approved quarry boundary is
947.76 Mcum. Based on this balance coal and OB the revised production
programme has been worked out to estimate the required OB quantity to produce
the proposed production of 50.0 Mty. As per the revised production programme the
balance life of the project works out to about 12 years considering normative coal
production of 50.0 Mty.
1.1 ENVIRONMENTAL CLEARENCEPresently, under sec 7(ii) of EIA Notification 2006, Gevra OCP is having
Environment Clearance for a peak coal production of 41.0Mty for an area of
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------2
4058.146 Ha of land issued vide letter No. J-11015/85/2010-IA-II(M) DT. 06-02-
2015.
The proposed mining plan for enhancement of production from 35.0 Mty to
50.0 Mty, EMP would be prepared for a normative coal production of 50.0 Mty,
within the area of already acquired 4184.486 Ha land.
1.2 PREPARATION OF MINING PLANThe mining plan for enhancement of production from 35.0 Mty to 50.0 Mty has
been prepared in three parts, which are as given below
1. Coal production programme: To deal with enhancement of coal production
to 50.0mty.
2. Despatch capacity: To have dispatch arrangement for the proposed
enhancement of coal production.
3. Time line for gradual shifting of the mine production to 70Mty (Peak
production 87.5Mty) as per the Approved project report of Gevra OC
Expansion (35.0-70.0Mty).
The mining plan has been prepared as stop gap arrangement to produce
50.0 Mty of production to cater the increased production of SECL. All efforts would
be made to acquire the additional land and obtain EC as soon as possible so that the
mine produces 70Mty as projected in the PR, preferably within 3 years time.
*******
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------1
CHAPTER – 2SALIENT FEATURE OF APPROVED PR
OF GEVRA OC EXPANSION (35.0-70.0 Mty)
2.0 APPROVED REPORTSProject Report for Gevra Opencast Project for an annual capacity of 6.00 Mt
of coal was prepared by CMPDI in March 1979. This was to meet the coal
requirement of Korba Super Thermal Power Stations (KSTPS) of NTPC (first stage)
for 1100 MW, amounting to about 4.25 Mty of coal. The excess capacity was
envisaged to meet a part of the demand for expansion of KSTPS by 1000 MW.
However, the Government approved the Project Report in December 1979 for an
annual capacity of 5 Mt at an estimated capital of Rs.50.08 crores.
Later, after the approval of Gevra Opencast Project, coal clearance was
given to NTPC for expansion of the MSTPS by 2 x 500 = 1000 MW. Thus, the total
capacity of the power house became 2100 MW and the ultimate annual coal
requirement was estimated at about 8 Mt. PR for Gevra Opencast Project
(Expansion) was prepared in March 1982 for an annual production of 10.0 Mt, to
meet the ultimate requirement of coal of KSTPS and to bridge the general shortfall of
coal supply in Western India. The report was approved by Government of India on
18.9.85 for a capital investment of Rs.224.39 crores.
In the year 1992-93, a scheme for Gevra OCM was prepared for
augmentation of production by another 2.0 Mty with a proposed capital investment of
Rs.39.62 crores. This scheme was sanctioned on 19.9.92 by CIL Board. The
balance reserves as per the scheme (as on 1.4.92) were estimated as 496.31 Mt.
The corresponding OBR was estimated as 533.79 Mcum at an average stripping
ratio of 1.08 cum/t. (The scheme incorporated the additional provision of HEMM for
removing the additional volume of overburden. The balance life of the project was
estimated as 42 years at the enhanced capacity of 12 Mty). The scheme was
declared completed on 31.3.95.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------2
A capacity augmentation scheme for Gevra CHP (from 10 Mty to 12 Mty)was also prepared and sanctioned on 31.7.92 for a capital investment ofRs.13.63 crores. Thus, the total sanctioned capital for Gevra OC (12.00 Mty)became Rs.277.64 crores (Rs.224.39 cr. + Rs.39.62 cr. + Rs.13.63 cr.).
The Project report for Gevra O/C Expansion (25 Mty) was prepared byCMPDI and approved by GOI on 12.07.05. Working group/X Plan document hadindicated the demand of non-coking coal for XI Plan as 580 Mt and indigenoussupply of non-coking coal from CIL as 445 Mt. The updated production of May 2005have indicated the demand of non-coking coal for the XI plan as 622 Mt andindigenous supply of non-coking coal from CIL as 508 Mt. Projection of totalindigenous supply of non-coking coal as 562.32Mt leaves a gap of 59.68 Mt forwhich Emergency Coal Production Plan of CIL has been formulated.
Gevra Opencast has been identified as one of the project in the EmergencyCoal Production Plan of CIL. Thus the Expansion project report (25.0-35.0Mty) forGevra OC was prepared. The incremental capital estimated for Project Report (25 to35 Mty) dated October 2006 was Rs.618.16 crores. The updated capital estimatedfor the approved project was Rs.1008.12 crores in the month of September 2009.The salient features of this sanctioned Project Report (25-35 Mty) project is asfollows:-
Date of sanction - 01.06.2010
Mineable reserves(As on 1.04.06) - 975.00Mt
Total OBR(As on 1.04.06) - 1266.98 Mcum
Av. Stripping Ratio - 1.30 cum/t
Target production - 35.00 Mty
Life - 29 years
Seams to be worked Thickness range
a) Composite D - 6.13 -12.26
b) E&F - 8.57 m -14.87 m
c) Upper Kusmunda (UK) - 15.96 m - 30.20 m
d) Lower Kusmunda (LK) - 27.11 m - 42.65 m
e) Lower Kusmunda Bottom (LKB) - 3.14 m - 8.67 m
f) Lower Kusmunda (Composite) - 55.05 - 57.86
Gradient - 1 in 6 -1 in 12
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------3
Due to increase in the demand for power grade coal, Gevra OC has been
identified as one of the coal mines where production can be enhanced. Moreover, it
has been projected that SECL as a whole has to produce 250Mt in the year 2019-20.
As such it was decided to prepare an Expansion project report for Gevra OC
and the same was included in the Annual Action Plan for the year 2014-15.
The Project report was prepared to enhance the capacity from 35.0Mty to
70.0Mty and the same was approved by CIL Board on 5th March 2016 for a
estimated additional capital investment of 9943.55 crores.
2.1 SALIENT FEATURE OF LAST APPROVED PR (35.0-70.0Mty)
The salient features of the 35.0-70.0 Mty sanctioned project were as follows:
Sl.No. Particulars Unit Option - (Coal
Contractual OB Deptt.)1 Total Mineable Reserves(As on 1/04/2014) M Te. 1337.682 GCV/Band Kcal/kg 4338.00/G-10
3 Volume of OB(including inseam band)(As on1/04/2014) M.Cum 2166.61
4 Stripping Ratio (Av.) Cum/t 1.625 Target Output Mt/Yr. 70.006 Peak OBR Mcum/yr. 122.007 Peak OBR( including inseam band) Mcum/yr. 125.548 Project life Year 22
9 a) Total add.capital investmentb) Capital outlay /te of annual output
`. crores`./t
9943.551562.02
10 a) Capital requirement of P&Mb) Per tonne of annual output
`. crores`./t
7535.781076.54
11 Selling price (95% of notified selling price) ofprocessed ROM Coal.(G-10) `./ t 922.00
12Estimated cost of productiona) at 100% levelb) at 85% level
`./t`./t
566.02634.00
13 Profit per tonne a) at 100% levelb) at 85% level
`./t`./t
355.98289.64
14 Break-even-point (%)(Mty)
51.3635.95
15 No. of personnel 439116 OMS Te 55.5717 EMS `. 3185.3018 Anticipated year of achieving target Year 7th
19 IRR at 100% level of production % 42.1620 IRR at 85% level of production % 28.4521 Completion capital `. crores 12109.2722 NPV @ 12% at 100% level of production `. crores 9837.2323 NPV @ 12% at 85% level of production `. crores 5644.97
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------4
2.2 MINE BOUNDARY OF APPROVED PRThe quarry boundary for the complete mine have been fixed in the following
manner:-
West - Based on the existing boundaries between Gevra Mine and DipkaMine.
North - Based on out-crop of LK Seam and boundary Fault F10-F10.
East - Based on 50 m barrier distance from the Western geological blockboundary of Resdi and Amgaon.
South - Based on the combined Southern most geological block boundaryof Ponri and Naraibodh II.
2.3 MINING METHODAs per approved PR shovel-dumper mining system has been adopted to
excavate OB by departmental HEMM, while extraction of coal is being done by
Surface Miner on outsourced basis.
2.4 HEMM PROVISIONThe HEMM as proposed in PR are shown in the following table: -
Sl.No.
Particulars Unit Size/Capacity
Existing AdditionalProvision
YEAR1/4/2015 1st 2nd 3rd 4th 5th 6th 7th
Coal(Mt)40.00 41.00 41.00 45.00 45.00 65.00 70.00OB(Mcum) 71.0 71.0 72.0 80.0 80.0 110.0 122.0
A. OVERBURDEN1 Electric Rope Shovel Cum 42 3 7 3 1 2 12 Electric Rope Shovel Cum 9/10 7
3Electric HydraulicShovel Cum 15 2 5 2 2 1
4 Hydraulic Shovel Cum 3.6 15 Rear Dumper T 35 36 Rear Dumper T 240 16 124 68 14 28 147 Rear Dumper T 150 95 28 19 2 36 108 Rear Dumper T 120 139 Rear Dumper T 100 47
10 Elect.RBH Drill mm 381 3 7 3 1 2 111 Elect.RBH Drill mm 250 912 Dozer with Ripper HP 850 4 6 1 1 1 1 1 113 Dozer HP 410 914 Wheel Dozer HP 450 3 3 1 1 115 Dozer HP 320 6B. COAL1 Surface Miner MT About 8MT2 Diesel RBH Drill mm 160 73 FE Loader Cum 104 Truck (Coal Body) T 60 12 125 Diesel Hyd. Backhoe Cum 5 2 2
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------5
Sl.No.
Particulars Unit Size/Capacity
Existing AdditionalProvision
YEAR1/4/2015 1st 2nd 3rd 4th 5th 6th 7th
Coal(Mt)40.00 41.00 41.00 45.00 45.00 65.00 70.00OB(Mcum) 71.0 71.0 72.0 80.0 80.0 110.0 122.0
6 Water Sprinkler KL 28 57 Diesel Bouser KL 22 2 28 Dozer with Ripper HP 850 5 1 1 1 1 1
C. RECLAMATION1 Dozer HP 410 102 Dozer with Ripper HP 850 3 6 1 1 1 1 1 13 Water Sprinkler KL 60-70 9 6 1 1 1 1 1 1D. COMMON1 Grader HP 500 6 3 1 1 12 Grader HP 280 53 Diesel Hyd. Backhoe Cum 1.5 TO 2.5 3 3 1 1 14 Tyre handler T 6.0 3 2 1 1
5 Crane T 190/150/75/100 2 2 2
6 Crane T 40-60 4 1 17 Crane T 20 2 3 1 1 18 Crane T 8-10 4 6 2 1 1 1 19 Fork lifter T 5 1 1
10 Diesel Bouser KL 22 5 9 3 1 1 1 1 1 111 Vibratory compactor T 25 3 1 1 1
12 Mobile FieldWorkstation 4 1 1 1 1
13 F.E.L 8
2.5 COAL TRANSPORT SYSTEM AS PER APPROVED PR
2.5.1 Present System of Coal Handling & Dispatch
Silo No.1&2 with storage capacity of 2400 te each are the existing silos of the
Gevra project. These silos are working with MGR system for delivery of coal to NTPC
Korba. Both, J-K series and L/R stream of belt conveyors feed coal to Silo No.1&2 via
a 30000 te ground bunker with C-series of conveyors and a 5000 te surge bunker
respectively. Thus, the existing silos with J-K series and L/R stream of belt conveyors
are engaged in dispatch of coal to NTPC Korba only. Coal from both Lower
Kusmunda and Upper Kusmunda seams comes to the existing silos through the J-K
series and L/R stream of belt conveyors. Designed coal handling capacity of this
system is 15 Mty.
There are five number of sidings with wharf wall loading system in the project.
Junadih Siding Nos. I&II are used by SECL for dispatch of coal to various consumers
whereas Siding Nos. III&IV (ACB sidings) and Siding No. V (GEB siding) have been
leased out to the washery holders for dispatch of washed coal by them. Each wharf
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------6
wall siding has coal handling capacity of around 5 Mty. In addition, there are eight
number of mini CHPs with Feeder Breaker/ crusher and road weigh bridges for
dispatch of coal to various consumers by trucks through road sales.
2.5.2 PROPOSED COAL HANDLING AND DISPATCH SYSTEM2.5.2.1 In-pit Conveying System (Central Sector)
Coal won by surface miners in the lower Kusmunda seam will be transported
by two pairs of series of belt conveyors viz. J-K series and A-B series located in the
central corridor left for belt conveyors and haul road in the central sector.
J-K Series : J-K series will consist of conveyors J1/K1, J2/K2, J3/K3, J4/k4, J5/K5
and J6/K6. All the conveyors of this series will be with 1600 mm belting. Modified
J1/K1 & J32/K2 and new J3/k3 is expected to be commissioned by the end of 2015.
Conveyors J4/K4, J5/K5 and J6/K6 will be additional provision for the 70 Mty
expansion project and will be installed in phases. Accordingly, the truck receiving
station at the tail of conveyors J3/K3 will be shifted at the tail of the last pair of
conveyors. Each of J and K series will be of 2300 TPH capacity. One of them will be
working while the other will be stand by. However, in case of peak demand or failure
of other circuit, both J and K series may be required to run simultaneously.
A-B Series : A-B series will be a new set of conveyors consisting of A1/B1, A2/B2,
A3/B3, A4/B4 and A5/B5 conveyors with 2000 mm width belting and 5000 TPH
capacity. A-B series will be installed in the central corridor adjacent to the J-K series.
A series and B series will parallel to each other. One of the A and B series of
conveyors will be working while the other series will be stand by. However, in case of
peak demand or failure of other circuit, both A and B series may be required to run
simultaneously. Conveyors A1/B1, A2/B2, A3/B3 & A4/B4 will be installed in the first
phase whereas conveyors A5/B5 will be installed at a later stage. Conveyors A4/B4
will be fed by shiftable conveyors from the face. However, conveyors A4/B4 will be
directly fed by Chain Feeders installed near the tail of the conveyors which will be
shifted to the tail of A5/B5 after its installation at a later stage. These Chain Feeders
will be partially used to receive coal from the nearby locations by trucks and will be
fully utilized in case of any breakdown in the shiftable conveyors circuit. Conveyor A1
will discharge coal either on TH-2 through a fixed tripper or on the existing L-series of
conveyors of 1400mm belt width and 3 m/s speed, whereas conveyor B1 after
crossing the L-series will discharge coal to conveyor B0 of 2000 mm belting and 5000
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------7
TPH capacity. Conveyor B0 will discharge coal through a two-way chute to the tripper
conveyors D7/D8 over the 50000 te overhead RCC bunker of the western circuit.
Shiftable Face Conveyors : Shiftable conveyors S1, S2 and S3 will be installed in
series at the face for transportation of coal from face to A-B series of conveyors. S1
and S2 will be of fixed length whereas length of S3 will vary according to the position
of the conveyors S1 and S2 with respect of the transfer point at the A-B series of
conveyors. Conveyor S3 will be provided with a radial swiveling belt conveyor S0 with
discharge chute which can be set to discharge coal onto either A or B conveyor. The
radial swiveling belt conveyor for transfer of coal from conveyor S3 to A or B conveyor
will be shifted from A4/B4 conveyors to A5/B5 conveyors after few extensions of the
shiftable conveyor S3. After installation of conveyor A5/B5, orientation of conveyor S3
may change and it may also become almost in-line with S1 and S2 conveyors. In that
case, location of the two truck receiving stations at the coal face may be spread out to
bring one of them nearer to S3. All the shiftable conveyors will mounted on slippers
and rail tracks will be laid along the conveyors to facilitate their shifting. Shifting of the
conveyors will be done with the help of crawler mounted conveyor shifting machine.
Coal won by surface miners will be loaded into trucks by pay loaders and dumped into
Chain Feeders of about 2000 TPH capacity. Two number of Chain Feeders will be
provided with each of the shiftable conveyors S1 & S2 for receipt of coal from the
trucks (Ref. Plate No. M6). Three out of the four Chain Feeders will be working
whereas one will be stand by. In case of concentration of coal winning in a smaller
patch, all the three working Chain Feeders may be deployed to discharge coal onto
either of S1 and S2 conveyors. Shifting of the conveyors S1 & S2 along with the
Chain Feeders and extension/shifting of the conveyor S3 will be done to maintain a
minimum clearance between the OB dump and the conveyors and an optimum lead
for the tipping trucks.
2.5.2.2 Surface Conveying SystemTwo circuits of surface belt conveyors along with bunkers and silos have been
envisaged along the western and eastern boundaries of the mine in the western and
eastern sectors respectively for transportation of coal won by surface miners in the
Upper Kusmunda seam and other upper seams viz. D (Bottom) & D (Top) seams and
E, F & EF seams. Coal from the face will be transported by trucks upto the truck
receiving stations of both the circuits.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------8
2.5.2.2.1 Western CircuitWestern circuit of surface conveyors will consist a truck receiving station
with two sets of 5 x 8m x 8m x 120 te steel hoppers (4 working & 1 standby) along
with 1000 TPH vibratory feeders, two series of belt conveyors (D series) of 2000 mm
belting parallel to each other, one overhead RCC bunker of 50000 te capacity and two
silos of 4000 te capacity each. One of the five hoppers in each set will be standby
One series of surface conveyors will consist of conveyors D1 & D3 whereas the other
series will consist of surface conveyors D2 & D4 of 4000 TPH capacity each. One of
them will be working while the other will be stand by. However, in case of peak
demand or failure of other circuit both the series may be required to run
simultaneously. Conveyors D3/D4 will discharge coal onto the tripper conveyors
D5/D6 of 5000 TPH capacity each over the 50000 te bunker. Coal from the bunker will
be reclaimed by plough feeders of 5000 TPH capacity and will be discharged onto the
reclaim conveyors D7/D8 of 5000 TPH capacity each. Two number plough feeders will
be installed over each of the two reclaim conveyors D7 & D8. Conveyors D7/D8 will
discharge coal into Silo No.5 through two-way chutes. Conveyors D9/D10 of 5000
TPH capacity each will receive coal from the two-way chutes at Silo No.5 and
discharge it to the adjoining Silo No.6. Both the silos i.e. Silo No.5 and Silo No.6 will
be fitted with double discharge chutes and pre-weigh hoppers. Minimum self-flowing
capacity of the pre-weigh hoppers will be 72 te each. Double railway lines will pass
under each of the silos such that each of the chutes of the silos will be placed over
separate railway lines.
2.5.2.2.2 Eastern CircuitEastern circuit of surface conveyors will consist a truck receiving station
with two sets of 4 x 8m x 8m x 120 te steel hoppers (3 working & 1 standby) along
with 1000 TPH vibratory feeders, two series of belt conveyors (G series) of 1600 mm
belting and 2800 TPH capacity parallel to each other, one overhead RCC bunker of
30000 te capacity and two numbers rail load out systems with 500 te capacity surge
bin and 100 te capacity weigh bin each. One series of surface conveyors will consist
of conveyors G1 & G3 whereas the other series will consist of surface conveyors G2
& G4. One of them will be working while the other will be stand by. However, in case
of peak demand or failure of other circuit both the series may be required to run
simultaneously. Conveyors G3/G4 will discharge coal onto the tripper conveyors
G5/G6 over the 30000 te bunker. However, Conveyors G1/G2 & G3/G4 will come
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------9
after about ten years, the tripper conveyors G5/G6 will be fed by another pair of belt
conveyors G9/G10 which will reclaim coal from a nearby truck receiving station
consisting of two sets of 4 x 8m x 8m x 120 te steel hoppers (3 working & 1 standby)
along with 1000 TPH vibratory feeders. This truck receiving station will be dismantled
after installation of conveyors G1/G2 & G3/G4 and reinstalled at the tail end of G1/G2.
Coal from the bunker will be reclaimed by plough feeders of 4000 TPH capacity and
will be discharged onto the reclaim conveyors G7/G8. Conveyors G7/G8 will be of
4000 TPH nominal capacity. Two number plough feeders of 4000 TPH nominal
capacity each will be installed over each of the two reclaim conveyors G7 & G8.
Conveyors G7/G8 will discharge coal into the surge bins of the two numbers rail load
out systems. The surge bins will be fitted with weigh bins and telescopic chutes for
discharge of coal into rail wagons.
2.5.3 Coal Storage and Dispatch System2.5.3.1 Overhead RCC Bunkers
Two no. of overhead RCC bunkers of 50000 te and 30000 te capacity have
been envisaged in the western and eastern sectors of the mine respectively. The
tripper conveyors, reclaim conveyors and plough feeders of the 50000 te bunker will
of 5000 TPH capacity whereas tripper conveyors for the 30000 te bunker will be of
2800 TPH capacity and the plough feeders and the reclaim conveyors of this bunker
will be of 4000 TPH capacity. The 50000 te bunker will be attached to Silo No. 5&6
whereas the 30000 te bunker will be attached to two numbers 500 te surge bins of
two numbers rail load out systems. The bunkers will be fitted with high level and low
level indicator switches.
2.5.3.2 Rapid Loading Systems2.5.3.2.1 Western Sector
Rapid Loading Systems in the western sector will consist of two numbers of
silos i.e. Silo No.5&6 of 4000 te capacity each. The silos will be of RCC construction
and fitted with double discharge chutes and pre-weigh hoppers for weighment of coal.
The RLS will load coal into railway wagons.
The slanting surface of the silos will be lined with 10 mm thick stainless
steel liners (SS 409) and will be extended upto 3 m in vertical section. The remaining
vertical portion will be lined with epoxy based ferrosite/ ironite lining of 25 mm thick for
easy flow of coal. The silos will be designed and constructed on mass flow concept to
reduce the possibility of rat holing /arching taking place during the evacuation /loading
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------10
process. For this, proper slopes will be provided in the slanting faces of the silos.
Provision for installation of air blasters/ air cannons will be made at suitable locations
to keep the coal agitated to avoid rat holing and arching inside the silo so that
continuous coal flow is ensured. Both the silos will be fitted with ultrasonic type high
level limit switches to stop the plough feeder below the bunker if a pre-determined
high level is reached in the silo. Low level limit switches will be provided to close the
silo discharge gates if a predetermined low level is reached i.e. approx. 600 te in the
silo. Temperature monitoring devices will also be provided at various levels in the silo
to monitor temperature of coal inside the silo and give audio-visual alarms in the
control room for necessary action. These will operate through battery in case of power
failure. Inspection trolley with cage will be provided above the silo for inspection of
outer and inner surfaces of the silo.
Below each silo eight numbers of hydraulically operated emergency gates
will be provided. This will be used in emergencies during the maintenance of the
equipment below the silos. Eight numbers of hydraulically operated silo discharge
gates will be provided below the emergency gates. Discharge through the silo
discharge gates will be into two nos. of steel hopper of minimum 72 te live capacity
mounted on four numbers of load cells to weigh the coal before it is discharged. Under
each pre-weigh hopper a telescopic chute gate with a flow control valve will be
provided by which the wagons will be loaded. The wagons will be moved by means of
a creep controlled diesel engine/ electric engine while they are being loaded. Track
logic system will be provided on the rail lines to identify the rail wagons and send
signal to the central processing unit for operating the chute. During the period when
there is no wagon loading the pre-weigh hopper will be filled in. LED based aviation
light will be provided over one of the two silos in the western circuit. Lightning
arrestors will also be provided on the silos.
2.5.3.2.2 Eastern SectorRapid Loading Systems in the eastern sector will consist of two numbers of
load out systems each primarily consisting of one surge bin of 500 te capacity, one
weigh bin of 100 te capacity and a traversing/telescoping chute (Plate no.M9). Coal
will flow into the weigh bin from the surge bin through four numbers bin charging gates
and will be loaded into rail wagons through the telescopic chute. The telescopic chute
will be of traversing type and will be parked aside for allowing loco to pass and then
will be brought to the central position for facilitating coal loading into the wagons.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------11
The surge bins and the weigh bins will be fabricated of minimum 10 mm
thick carbon steel plates and will be lined with minimum 12 mm thick chromium
carbide wear liner. The chute will be of heavy duty design for coal application. The
structure will be designed to be in compliance with the current Indian standards and
specifications. The structural system will include stairs system, access floors as well
as the floor where the system feed conveyors lands on the building etc. All structural
steel design will be as per suitable IS. All structural connections will be designed to be
field bolted. All structural framing connections shall utilize high tensile strength bolts.
All bracings girt connections will be designed and fabricated for field bolting. Proper
sheeting of the building shall be done and a roof over the structure will be provided.
Inspection trolley with cage will be provided above the surge bins for
inspection of outer and inner surfaces of the surge bins.
A high wagon/collision sensor will be attached to the load out chute which will
automatically close (if open) the control gate above the load out chute and retract the
chute in up position to allow passage of a high wagon. Suitable calibration/testing
systems will be provided with the load out systems. In general a load out system will
consist of the following (the list is not comprehensive rather a general overview):
a. One 500 metric tonne capacity surge bin
b. One 100 metric tonne capacity weigh bin
c. Four dual ended shear beam load cells of required capacity with mounting
assemblies
d. One digital weigh indicator
e. One surge bin level monitoring system
f. One batch controller system with HMI located in the control room for controlling
and monitoring the loading process
g. Four dustless double bladed surge bin discharge control gates
h. One double bladed, dustless weigh bin discharge gate
i. One traversing/telescopic load out chute with collision sensor and breakaway
section
A suitable self-contained hydraulic power unit consisting of the reservoir of
required capacity and all necessary components will be provided to operate the
system and provide sufficient energy reserve to perform failsafe operation of the
system (close/open discharge gates, raising/lowering/traversing of the discharge
chute).
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------12
The load out system is a computer controlled operator attended - automatic
weighing and loading system capable of static loading accuracies within ±0.05%. The
load out system will feature three modes of attended operation: automatic, semi-
automatic and manual. The wagons will be moved by means of a creep controlled
diesel engine/ electric engine while they are being loaded. Track logic system will be
provided on the rail lines to identify the rail wagons and send signal to the central
processing unit for operating the chute. During the period when there is no wagon
loading the weigh bin will be filled in.
Control logics and associated I/O modules will be provided in the Main Loadout
PLC Control Cabinet to operate all load out I/O, including load out gates, hydraulic
power unit and load out chute. This unit will interface with the load out application
software. This system will communicate the surge bin level signal, plus the tonnes
required to complete the loading of the rake ("Tons to Go"), to the PLC of the reclaim
system of the associated bunker i.e. the plough feeders and the reclaim conveyors, to
enable proper control and to coordinate the reclaim rate with the loading rate of the
load out chute. A modem with the necessary software will be provided for remote
support of the load out system and for providing system upgrades without a service
man requiring to attend the site. Lightning arrestors will also be provided on the surge
bins. All limit switches, pressure switches, temperature switches and all other
electrical components and enclosures will have a IP65 or better rating.
Two train traffic light signals, each traffic light consisting of one red and one
green light with mounting assembly will be provided. One train traffic control light
system will be mounted prior to the entrance to the load out facility. The second train
traffic control light will be mounted on the exit end of the load out structure. These
lights will provide the train driver an indication of when it is safe to begin loading. Upon
approach of train, signal will be set to red, signaling the train to stop prior to the load
out station. When the system is set and ready to load, the control room operator will
notify the train driver by switching the traffic signal to green, signaling the train driver
to spot the first wagon under the loading position. Once the train is in position and the
load out chute is positioned out over the rail wagon, the second train traffic light
control will signal the train driver to begin the loading process.
**********
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------1
CHAPTER – 3PERFORMANCE OF EXISTING MINE
3.0 PRODUCTION PERFORMANCEAs already explained in previous chapter that the existing Gevra OCM is
having an approval for normative capacity of 35.0 Mty and peak capacity of 41.0 Mty.
The yearwise coal and OB production from Gevra OC Project for the last thirty five
years is as tabulated below.Year Coal Production, t OB Removal, M3
1980-81 NIL 25000.001981-82 46500.00 274000.001982-83 320500.00 660500.001983-84 1437100.00 1762300.001984-85 3282150.00 2500800.001985-86 4211000.00 2502100.001986-87 5001000.00 3002000.001988-89 6500000.00 3010150.001988-89 8210000.00 4201000.001989-90 9700000.00 6644000.001990-91 11211500.00 7840500.001991-92 13200000.00 9670500.001992-93 13302000.00 9700000.001993-94 14045000.00 10628000.001994-95 14629000.00 11318500.001995-96 15445000.00 12889000.001996-97 16832500.00 13540000.001997-98 17881000.00 13240000.001998-99 17289000.00 13780636.001999-00 18017600.00 12661357.002000-01 18887000.00 13150297.002001-02 18968000.00 11255305.002002-03 19541200.00 10265200.002003-04 21886000.00 11692100.002004-05 26157000.00 12503100.002005-06 26464000.00 12129500.002006-07 27222000.00 12385800.002007-08 29055000.00 11465000.002008-09 32103600.00 17579850.002009-10 35000000.00 22328000.002010-11 35000000.00 30592500.002011-12 35000000.00 22000843.002012-13 35000000.00 23264000.002013-14 38700662.00 35125500.002014-15 41000000.00 45440000.002015-16 41000000.00 44150000.00
Total 671.545MT 474.88MT
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------2
3.1 MAJOR HEMMThe extraction of coal from mine is being done through Surface Miner on outsourcing
basis. Excavation and transport of OB will be done departmentally by deploying
departmental HEMM. The Gap in capacity of OB is being removed by outsourcing.
The population of major HEMM for OB removal are as given in the following table: -
Population of major HEMM for OB removal
S.N. Particulars of HEMM Size/Capacity TotalProvision
Existing as on01.04.2016
1 Elect. rope shovel 42 cum 10 32 Elect. rope shovel 10 cum 7 73 Elect. hydraulic shovel 15 cum 7 24 Rear Dumper 240 T 140 165 Rear Dumper 150 T 95 -6 Rear Dumper 120 T 13 137 Rear Dumper 100T 47 47
3.2 BALANCE RESERVES IN THE EXISTING ACQUIRED LAND:-
The Mineable reserves and volume of OB estimated for Gevra OC Exp (25.0-
35.0Mty) was 975.00 Mt and 1266.99Mm3 as on 1/04/2006.The coal and OB
extracted from 1/04/2006 to 1/04/2016 from Gevra OC (35MTY) . is as follows:-
Gevra OC - Coal - 349.07 Mt ; OB- 264.29Mm3.
Additional Coal and OB extracted from erstwhile Laxman OC is as follows:-
Coal - 57.07Mt ; OB- 54.94Mm3.
Balance Mineable reserves and volume of OB in Gevra OC Exp (25.0-
35.0Mty) as on 1/04/2016 is 568.86Mt and 947.76Mm3. The following table
summarises the utilization of reserves.
Particulars Coal in Mt. OB in Mm3
Reserves as per sanctioned PR of Gevra 35Mty 975.00 1266.99Reserves extracted between 1/4/2006 and 1/4/2016 349.07 264.29
Reserves extracted from Laxman OC 57.07 54.94
Balance Mineable Reserves in the presently acquired land of4184.486Ha as on 1/4/2016 568.86 947.76
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------3
3.3 PAST PERFORMANCE AND PROFITABILITYPast performance of the mine showing yearwise coal, OB removal, cost of
production and profitability of mine for last few years are as given in the table.
Sl.No. Particulars Unit 09-10 10-11 11-12 12-13 13-14 14-15 15-16
1 Coal production Mt 35.00 35.00 35.00 35.00 38.70 41.00 41.002 OB removal Mm3 24.83 30.70 22.00 23.26 35.12 45.44 44.153 Stripping ratio Cum/t 0.71 0.88 0.63 0.66 0.90 1.10 1.074 OMS t 36.55 40.39 34.14 35.93 47.18 54.99 53.585 Average Grade F F F G-11 G-11 G-11 G-116 Cost of
productionRs./t 281.39 309.00 392.97 456.18 423.62 383.08405.80
7 Av. selling price Rs./t 614.52 693.62 753.57 868.12 865.93 809.03880.428 Profit/loss Rs./t 333.13 384.62 360.61 411.94 442.36 459.46474.37
3.4 MODE WISE DISPATCH OF COALPresently the Gevra OCM is having a capacity to dispatch coal upto about 50
Mty. Last year the mine has despatched about 44.42 Mt of coal through existing
infrastructure available.
The NTPC Korba is connected to the dispatch system of the mine by means
of MGR and two numbers of silos have been provided for loading of rake in this
MGR. The Rail Platform 1, 2, 3, 4 and 5 is used to dispatch coal by rail to distant
consumers. Remaining coal is being dispatched by road. The modewise dispatch of
coal for last three years are as given below.
S.No Customers Despatch duringthe year 2013-14
Despatch duringthe year 2014-15
Despatch duringthe year 2015-16
1 NTPC Korba through SiloNo.1&2 15.26 Mt 14.24 Mt 13.24 Mt
2Other power houses andconsumers through JunadihSidings I&II
9.89 Mt 7.93 Mt 9.75 Mt
3 Power plants by Rail(through Washeries) 8.24 Mt 11.64 Mt 14.91 Mt
4 Road sales by trucks/Others 3.98 Mt 3.32 Mt 5.69 Mt
5 Transfer to Dipka Area - - 0.83 Mt
6 Total Despatch 37.39 Mt 37.15 Mt 44.42 Mt
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------4
3.5 DETAILS OF LANDThe total land acquired by Gevra OC till date is 4184.486 Ha. Environment
clearance under section 7(ii) for coal extraction upto 41.0 Mty is available. The type
wise breakup of the acquired land is as tabulated below :-
SL NO TYPE OF LAND QUANTITY OF LAND(Ha)1 Forest Land 1038.6302 Tenancy/Agriculture land 2520.5713 Govt Land 625.285
Total 4184.486
The proposed mine plan envisaged to enhance the production within the landalready notified i.e. 4184.486 Ha of land. No additional land is proposed to beacquired for the enhancement of the production to 50 Mty.
*******
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------1
CHAPTER – 4PROPOSAL FOR ENHANCEMENT OF PRODUCTION
FROM 35.00 Mty TO 50.00 Mty4.1 NEED FOR ENHANCEMENT
As already explained based on “Road Map for Enhancement Coal Production of
CIL” the targeted production of SECL for the year 2016-17 is 149.70 Mt. Gevra OC
has been identified to produce 50.0 Mty to meet this growth in demand of SECL.
Accordingly this mining plan for enhancement of production has been prepared to
produce 50.0 Mty of coal (normative capacity) from Gevra Opencast Project. The
mining plan envisages to produce the enhanced capacity of coal from the land
already notified i.e. 4184.486 Ha, no additional land is being proposed to be acquired
in the mining plan.
As on 01.04.2016, the balance coal within the approved quarry boundary is
568.86 Mt and balance OB within the approved quarry boundary is 947.76 Mcum.
Based on this balance coal and OB the revised production programme is calculated
to estimate the required OB quantity to produce 50.0 Mty of coal. As per the revised
production programme the balance life of the project works out to about 12 years
considering normative coal production of 50.0 Mty.
4.2 FEASIBILITY FOR ENHANCEMENTThe existing Gevra OCM is producing 41.00 Mty coal since last two years i.e. in the
year 2014-15 and 2015-16, which is the limiting capacity of production as per
approved EC conditions. The mine is having potential of enhancement of production
beyond 41 Mty by deploying additional resources considering the present geo-mining
conditions. It may also be noted from the available records that in the year 2015-16
Gevra OC has dispatched 44.42 Mt of coal with the existing infrastructure available.
In the year 2015-16, NTPC Seepat has consumed coal 13.24 Mt of coal from this
mine. There is a possibility that NTPC Korba may consume coal 8.00 Mty from
Gevra OC. SILO 3 & 4 and related inpit conveyor system are in construction stage
and are likely to be commissioned by 31st Dec 2016.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------2
Besides this there are five nos. of sidings for dispatch of coal through rail. The
proposed dispatch modes alongwith the quantities after commissioning of silo 3 and
4 is as follows:-
4.3 BALANCE COAL AND OB REMOVALAs on 01.04.2016 balance coal is estimated about 568.86 Mt and balance OB
is estimated about 947.76 Mcum within approved mine boundary of EC.
The stripping ratio of balance coal reserve and balance OB removal works out
to 1.67 cum/t.
4.4 PRODUCTION PROGRAMME FOR 50.0 MTYCalendar programme calculated based on estimated balance coal and OB to
produce 50 Mty of coal within the mine boundary approved for EC, which is as given
below.
S.No Customers Quantity proposedto be dispatched
1 NTPC Korba through Silo No.1&2 15.00Mt
2 Public silo No. 3& 4 13.00Mt
2 Other power houses and consumersthrough Junadih Sidings I&II by rail 10.00Mt
3 Power plants by rail using Junadih siding 3,4&5.(through Washeries) 10.00Mt
4 By Road to miscellaneous customers 2.00Mt
6 Total proposed Despatch 50.00Mt
YEAR Total coal Total OB SR1 45.00 80.00 1.782 45.00 80.00 1.783 50.00 82.00 1.644 50.00 82.00 1.645 50.00 82.00 1.646 50.00 82.00 1.647 50.00 82.00 1.648 50.00 82.00 1.649 50.00 82.00 1.64
10 50.00 82.00 1.6411 50.00 82.00 1.6412 28.86 49.76 1.72
TOTAL 568.86 947.76 1.67
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------3
The peak annual OB removal will be maximum 82.00 Mcum. The calendar
programme shows that the OB removal required to produce enhanced capacity of
coal, beyond Departmental capacity for OB removal as per approved PR, would
proposed to be outsourced. It is envisaged that all the OB would be dumped
internally in the individual benches of 30 m (maximum proposed dump height 90 m)
and the ultimate slope angle is proposed to be 280.
4.5 SCOPE OF WORK FOR PRODUCTION ENHANCEMENT TO 50.0 MTYThe scope of work for enhancement of production from existing acquired land
of 4184.486 Ha of land will be in line with the approved Project report of Gevra OC
Expansion (35.0-70.0Mty)
1. Additional Quantity of OB removal
The calendar programme shows that there is requirement for additional quantity
of OB removal to mine out 50.0 Mty of coal. As per approved PR of Gevra OC
Expansion (35.0-70.0Mty), removal of OB was proposed to be done by departmental
HEMM. Procurement and Deployment of departmental HEMM would take time. In
case of delay in the procurement of additional HEMMs, OB equivalent to capacity of
delayed HEMM can be outsourced till the procurement of these HEMMs.
2. Additional Quantity of Coal extraction
As per approved PR of Gevra OCM (35-70Mty), extraction of coal to be done by
Surface Miner on outsourcing basis. The same would be continued for this mining
plan also.
3. Infrastructures for Transportation and Dispatch of coal.
Development of Infrastructures for transportation and dispatch of coal will be as
per the Project report of Gevra OC Expansion (35.0-70.0Mty)
4. Other Developmental activities and manpower requirement.
As per the Project report of Gevra OC Expansion (35.0-70.0Mty).
5. Mine closure activities
As per the Project report of Gevra OC Expansion (35.0-70.0Mty).
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------4
4.6 FUTURE PLANNINGThe approved PR has been planned to produce 70.0Mty of coal. The strike
length of 9.5 km has been planned in the approved PR. The mining plan has been
prepared as stop gap arrangement to produce 50.0 Mty of production to cater the
increased production of SECL. All efforts would be made to acquire the additional
land and obtain EC as soon as possible so that the mine produces 70Mty as
projected in the PR, preferably within 3 years time. The time line for major activities
to implement approved 70 Mty PR is as indicated in following paras.
The schedule for acquisition of land is as follows:
Completion of section 11 for land acquisition as per CBA Act of remaining
land -2017-18
Forestry clearance of forest land within the approved PR of Gevra OC
Expansion (35.0-70.0Mty)-2018-19.
All the major infrastructures as per the approved PR for Gevra OC Expansion (35.0-
70.0Mty) are to be constructed within the approved EC land of 4184.486Ha. The
schedule for the infrastructure development would be as follows:
Construction of silo nos. 5&6 and inpit conveyors/surface conveyors:-2018-19
Construction of load out system and inpit conveyors/surface conveyors-2018-19
In addition to this all out efforts will be made for commencement of EAST-WEST Rail
corridor by 2018-19.
After completion of major activities and forestry clearance application will be
processed for EC of 87.5Mty later on.
4.7 CONCLUSIONThis mining plan would facilitate Gevra OCM to gradually reach to its projected
approved target of 70 Mty from the existing approved EC capacity of 41 Mty. It is
proposed that production of 50 Mty would be reached by gainful utilisation of the
existing infrastructure however, as the infrastructure to produce & handle 70 Mty is
available in due course of time, the mine would produce its projected approved
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------5
target of 70 Mty. It is envisaged that the required infrastructure to produce & handle
70 Mty would be constructed within 3 years time frame.
Considering the feasibility to produce and dispatch 50 Mty by utilising existing
infrastructure within existing acquired land, the mining plan to Gevra Expn. OCP may
be considered for approval by competent authority.
*******
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
1
CHAPTER- 5
ENVIRONMENT MANAGEMENT
5.1 Existing Environment Quality:
Gevra OCP is an operating mine under Gevra Area, SECL and comprises mostly
of agricultural land. Presently, 41 Mty of coal is being extracted from 4184.486 Ha of
land. In order to enhance coal production of Gevra OC, it was planned to acquire
additional land. But this additional land to be acquired contains forest right at the
boundary of expansion. Obtaining forest clearance for this forest land would take
considerable amount of time, so it has been proposed by competent authority that coal
production be enhanced in the present acquired land (4184.486 Ha.). Availability of
sufficient coal reserves in the present land in use makes this proposal feasible for
enhancement of coal production from 41 Mty to 50 Mty.
Environmental base line data for Gevra OC Expansion was generated in the year
of 2008 and subsequently monitoring data is carried out at different locations in core &
buffer zones. These data have been used in the preparation of this chapter. These data
will enable in obtaining a comprehensive idea of environmental quality in and around the
proposed project area in respect to air quality, water quality, noise level, flora fauna,
socio economic data etc. Detail existing environmental base line data is being generated
for the season April-June 2016. This data will be incorporated in the final EIA/EMP
report, which will be submitted to MoEF & CC.
5.1.1 Ambient Air quality in core and buffer zone:
To assess the ambient air quality, eight monitoring stations were fixed on the basis
of physiography of the area, meteorological parameters like predominant wind direction,
wind speed etc. The details of air quality monitoring locations are given below in Table
5.1
Table 5.1 SOURCE AND LOCATION OF THE AIR QUALITY MONITORINGSl. No. Name of Location Details of Location1 DETP/TA Core zone
2 Shakti Nagar Core zone
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
2
3 Urja Nagar Core zone
4 Dy. GM Office Core zone
5. Bhilai Bazar Village Buffer zone (0.7 km SSE w.r.t core zone)
6 Dhurena Village Buffer zone (0.5 km North w.r.t core zone)
7 Ganga Nagar Village Buffer zone (1.2 km NE w.r.t core zone)
8 Ralia Village Buffer zone (1.0 km South w.r.t core zone)
Table – 5.2 AIR QUALITY DATA (Values In µg / cum)Period: Jan - Mar Year- 2016
SL.NO. STATIONS
SPM RPM SO2 NOXMin Max Min Max Min Max Min Max
1 DETP/TA 392 422 189 232 3 11 17 24
2 Shakti Nagar 144 168 40 64 5 10 9 21
3 Urja Nagar 151 183 49 75 2 18 10 25
4 Dy. GM Office 420 484 208 264 2 6 10 25
5 Bhilai Bazar Village 141 185 43 79 6 10 12 21
6 Dhurena Village 142 188 49 76 3 7 12 18
7 Ganga Nagar Village 143 162 40 74 3 9 8 19
8 Ralia Village 159 187 60 60 2 6 10 18
The National Ambient Air Quality Standards (NAAQS) as per CPCB norms is given
below in table 5.3
Table 5.3STANDARDS CATEGORY SPM RPM SO2 NOX
NAAQS Industrial (A) 500 150 120 120
Residential (B) 200 100 80 80
Sensitive (C) 100 75 30 30
As per MOEF notification GSR
742(E), dated 25th Sep’2000
Old mines (A-O) 600 300 120 120
New mines (A-N) 500 250 120 120
5.1.2 Water QualityThe summarized water quality data are given below in Table 5.5. The water quality
data of different locations are found to be within the permissible limit of CPCB. Details of
sampling locations are given below in table 5.4.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
3
Table 5.4SlNo.
Name of the Station Details
1 4.5 MLD Water Filter Plant( Water After Treatment) Core Zone2 Well Water of Executive Colony Near Shivmandir, Urja Nagar Core Zone3 Water of Workers Colony near AjadChowk from Tube Well Core Zone4 Colony Tap Water DAV Public School, Gevra Core Zone5 Well Water Of Vijay Nagar- Rehabilitation Village Buffer Zone (0.5 Km
North w.r.t core zone)6 Drinking Water ,Ganga Nagar Hand Pump Govt. School Buffer Zone (0.8 Km NE
w.r.t core zone)7 Drinking Water, Nehru Nagar Hand Pump Govt. School Buffer Zone (1.2 Km NW
w.r.t core zone)
The summarized Drinking Water Quality and Effluent Water Quality data generated for
the period Jan – Mar 2016 is given below in Tables 5.5 & 5.6
Table 5.5 DRINKING WATER QUALITY DATASl.No.
Parameter Sampling Stations IS:10500 BDL
1 2 3 4 5 6 7 Desirable Limit
1 Colour,Hazen
3 9.87 11 8.86 11.67 14.2 5.2 5 <1.0Hazen
2 Odour Unobjectionable
Unobjectionable
Unobjectionable
Unobjectionable
Unobjectionable
Unobjectionable
Unobjectionable
Unobjectionable
---
3 Taste Agreeable
Agreeable
Agreeable
Agreeable
Agreeable
Agreeable
Agreeable
Agreeable
---
4 Turbidity,NTU
1.08 1.95 1.29 3.74 3.74 9.39 1.8 5 <1.0NTU
5 pH 7.51 6.82 7.50 7.45 6.50 6.43 7.37 6.5-8.5 <0.01
6 Alkalinity asCaCO3
83.33 33.33 66 66.67 41.67 40 238.33 200 <0.5
7 TotalHardness as
CaCO3
126 46.67 101.33 105.33 104 42 152.33 300 <0.5
8 Iron 0.063 0.22 0.27 0.42 0.10 1.67 0.24 0.3 <0.05
9 Chlorides 19.51 26.10 27.47 18.62 52.86 8.7 46.42 250 <0.25
10 ResidualFree
Chlorine, min
0.05 0.05 0.06 0.04 0.06 0.03 0.03 0.2 <0.04
11 DissolvedSolids 199 94.67 177.33 190.67 329.34 88 432.67 500 <5.0
12 Calcium 46.24 26.32 50.56 44.88 40.58 20.72 54.25 75 <0.02
13 Copper BDL BDL BDL BDL BDL BDL BDL 0.05 <0.02
14 Manganese 0.04 0.04 0.03 0.29 0.17 0.03 0.02 0.1 <0.05
15 Sulphate 41.42 21 34.71 38.17 10.14 2.87 40.77 200 <1.0
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
4
16 Nitrate BDL 2.33 BDL 0.25 8.91 2.87 0.83 45 <0.01
17 Fluoride 0.43 0.18 0.63 0.57 0.13 0.08 0.56 1 <0.01
18 Selenium BDL BDL BDL BDL BDL BDL BDL 0.01 <0.01
19 Arsenic BDL BDL BDL BDL BDL BDL BDL 0.05 <0.01
20 Lead BDL BDL BDL BDL BDL BDL BDL 0.05 <0.05
21 Zinc 0.7 0.04 0.35 0.16 0.04 0.71 0.15 5 <0.005
22 HexavalentChromium
BDL BDL BDL BDL BDL BDL BDL 0.05 <0.01
23 FaecalColiform,
MPN/100ml
Nil Nil Nil Nil Nil Nil Nil Nil _
24 Boron BDL BDL BDL BDL BDL BDL BDL 1 <0.01
25 Phenolics BDL BDL BDL BDL BDL BDL BDL 0.001 <0.001
Table – 5.6 EFFLUENT WATER QUALITY DATA (Values In µg / cum)Sl.No. SAMPLING STATIONS PARAMETERS (Max.)
pH TSS COD O&G1 Mine water at discharge point 7.91 38 28 <1.0
2 WS effluent before treatment at O&Gtrap 6.91 81 32 14.2
3 WS effluent after treatment at O&G trap 7.45 39 40 6.84 Discharge of DETP, Gevra Area 7.51 37 40 <1.0
5 OB dump run off and mine dischargewater after treatment at settling pond 6.99 18 28 <1.0
6 U/S of LaxmanNalla 7.26 61 16 <1.07 D/S of LaxmanNalla 6.88 64 24 <1.08 Mine sump water 6.79 82 32 <1.0
5.1.3 Noise level
The summarized noise data of Gevra OCP for the period Jan-Mar for year 2016,
at different locations as shown in Table 5.7 for different categories of area is given in
Table 5.8. The locations were selected on the basis of wind pattern of the area.
Table 5.7 SOURCE AND LOCATION OF THE NOISE MONITORINGSl. No. Name of Location Details of Location1 DETP/TA Core zone2 Shakti Nagar Core zone3 Urja Nagar Core zone4 Dy. GM Office Core zone5. Bhilai Bazar Village Buffer zone (0.7 km SSE w.r.t core zone)6 Dhurena Village Buffer zone (0.5 km North w.r.t core zone)7 Ganga Nagar Village Buffer zone (1.2 km NE w.r.t core zone)8 Ralia Village Buffer zone (1.0 km South w.r.t core zone)
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
5
Table 5.8 SUMMARIZED NOISE DATA
Period: Jan - Mar Year: 2016
Sl.No. NAME OF STATION NOISE LEVEL [dB(A)]DAY TIME NIGHT TIME
1 DETP Control Room 64.30 52.4069.60 62.60
2 Shakti Nagar 43.90 40.3052.10 42.70
3 Urja Nagar 46.80 41.9051.70 43.50
4 Dy.GM Office 67.70 53.8072.90 70.50
5 Bhilai Bazar Village 49.70 39.8049.70 43.90
6 Dhurena Village 45.20 36.1050.50 41.60
7 Ganga Nagar village 44.80 35.7051.20 43.30
8 Ralia village 44.20 40.6052.70 42.80
Table 5.9 NOISE LEVELS STANDARDSl.NO.
CATEGORY OFAREA
LIMITS IN dB(A)Day time(6.00 am to 10.00 pm)
Night time(10.00 pm to 6.00 am)
1 Industrial Area 75 702 Commercial Area 65 553 Residential Area 55 45
The noise levels recorded at all the locations during the season were within the
permissible limits.
5.1.4 Flora and FaunaForest, Flora & Fauna
Baseline data for Flora & Fauna for Gevra OC have been generated in June-
August 2015 and the same has been taken as a reference for this section. The study
area for the Flora & Fauna covers 10 KM radius from periphery of the Core Zone of the
Gevra OCP in the Gevra area of South Eastern Coalfield Limited (SECL). The flora and
fauna report of Gevra OC generated reveals the following summarized list of flora and
fauna normally found in that forest.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
6
Conservation and Management of Biological diversity:There are no reserve forests either in the core area (MLA) or in the buffer area
(Area enclosed within 10 Km radius from periphery of core zone of Gevra OCO). But
there are a few Protected Sal forests are found in the buffer zone of the mine lease
area (MLA). The reserve forests were dominated by Sal (Shorearobusta) with Butea
monospermaand Madhucalongifoliaas the codominant species. They are open with tree
density ranging from a low of 36 to a high of 340 trees per hectare. A few areas were
colonized by Bamboo (Dendrocalamusstrictus). Lantana camaraalong with the coppiced
shoots of Butea monospermawas the most widely scattered shrubs in the gaps within
the reserve forests. The protected Sal plantations are harvested periodically for timber.
Conservation of Flora & Fauna:Open cast Mining iscapable of causing extensive
damage to the flora and the associated fauna of the mining site. But the impacts can be
reversed and the flora and fauna can be rehabilitated and restored through location and
site specific eco-restoration process. The floral conservation plan is mainly focused on
artificial regeneration of a good tree cover through afforestation of the overburden
dumps, back filled sites and the abandoned vacant areas. Water available in the mine
pits could be diverted for sapling nursery and plantations. The restored areas will be
protected from biotic pressure by fencing. It is evident from the baseline data of the flora
and fauna of the core area as well as from the eye witness accounts that no Rare or
endangered or endemic or threatened (REET) species or species included in Schedule I
of the Wildlife Protection Act of 1972 were spotted in the Mine lease area (MLA) during
the past 10 years by the local observers. The presence of such species in the buffer
area is also unlikely.
However, the buffer zone is covered by a good diversity of plant species that
comprised of herbs, shrubs and tree species. The small plants such as herbs, medicinal
herbs and commonly available weeds were found to be good in number and these
plants were having the potential of rapid regeneration and spread. Due to self-
regenerative capacity of these plants, the propagation strategy is not required. Except
for a few plant species, all the plant species found in this region were found to be
commonly available flora of all the regions. To improve the vegetation cover, it is
suggested that the saplings of diverse tree species such as Acacia catechu,
Anogeissuslatifolia, Butea monosperma, Diospyrosmelanoxylon, Madhucalongifolia,
Lagerstroemia parviflora, Lanneacoromandelica, Shorearobusta, Terminalia bellirica,
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
7
Boswelliaserrata, Dendrocalamusstrictus, Cassia siamea, Eucalyptus globules, Acacia
auriculiformis, Albizialebbeck, Azadirachtaindica, Dalbergiasisoo, Gmelinaarborea,
Phyllanthusemblica, Pongamiapinnataand Tectonagrandiscould be planted to fill the
gaps at a regular intervals. The natural forests should be protected as envisaged by the
forest conservation act.The flora & fauna identified in the study area is summarized below.
Summarized List of flora & fauna
Flora
Sl.No
Particulars NamesLocal English Botanical
1 Agricultural crops – Corezone
Lady’sfinger
Abelmoschusesculentus Malvaceae
Dhan Paddy Oryze sativaMakka Maize Zea maysKaddu Cucumber CucumissativusKarela Bitter groud Momordica charantia, LPeas Fabaceae PisumsativumGuava Myrtaceae PsidiumguajavaPotato Solanaceae Solanumtuberosum
Agricultural crops- Bufferzone
All above
Garlic Allium sativum LiliaceaeOnion Allium sepa LiliaceaeMango Mangiferaindica Anacardiaceae- Black gram Phaseiolus mungo, L.Kela Banana Musa spPumpkin Cucurbitamoschata Cucurbitaceae(Sweetgourd)Countrybean
Dolichos lablab Fabaceae
2 Commercial crops – Corezone
Aam Mango MangiferaindicaPapita Papaya Carica papayaKela Banana Musa spJamun Myrtaceae SyzigiumcuminiImli Caesalpiniaceae TamarindusindicaAmba /Mango
Anacardiaceae Mangiferaindica
Commercial crops – Bufferzone
Same asabove
3 Plantation-Core & buffer Coconut Arecaceae Cocosnucifera
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
8
Sl.No
Particulars NamesLocal English Botanical
Babul/Babool
Mimosaceae Acacia nilotica
Tendu(Kendu)
Ebenaceae Diospyrosmelanoxlyon
Pipal /Aswatha
Moraceae Ficusreligiosa
Mahuva /Mahul
Sapotaceae Madhucalongifolia
Amba /Mango
Anacardiaceae Mangiferaindica
Amla Euphorbiaceae Phyllanthusemblica4 Natural vegetation/ forest
type-IV A & IV B
i)a Tree – Core zone Sal Shorea robusta RothSagwan - Tectona grandis, L.Pipal Ficus religiosa, LAsok Polyalthialongifolia,
Hk.F&T.ArjunKahua Terminaliaarjuna, W.&A.
i)b Tree – Buffer zone As aboveNimb Azadirachta indica, A.
Juss. NeemKadam Anthocephalus indicusBaheda - Terminaliabellarica, Roxb.Seesam Dalbergiasissoo, Roxb.Gumhar - GmelinaarboreaRoxb.
ii)a Herbs and Surubs – Corezone
Arakha Asclepiadaceae Calotropisprocera
Roilei -- DesmodiumgyransNagabari Verbenaceae Lantana camaraRaktchita Plumbaginaceae PlumbagoindicaBegunia Verbenaceae Vitex negundo
ii)b Herbs and Surubs – Bufferzone
As above
Gangasiuli Oleaceae Nyctanthes arbortristisIron wood Mimosaceae Acacia chundraKurein(Kuduchi)
Apocynaceae Holarrhenaantidysenterica
iii)a Climbers – Core zone -- Vitaceae Cissusvitiginea-- Apocynaceae PergulariademiaAnantamul Apocynaceae Hemidesmusindicus-- Periplocaceae Decalepishamiltoni
iii)b Climbers – Buffer zone All above-- Vitaceae Ampelocissustomentosa-- Vitaceae Cissusvitiginea
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
9
Sl.No
Particulars NamesLocal English Botanical
Atundi Combretaceae Combretumdecandrum-- Periplocaceae DecalepishamiltoniHarad Mai Fabaceae Millettiaauriculata
iv) Epiphytes and parasites –Core& Buffer zone
-- -- --
5 Grass lands:- Core& BufferZone
No grass land of worth mentioned in the area.
6 Endangered species:- Core &Buffer Zone
None
7 Endemic species:- Core &Buffer Zone
None
Fauna
SL.No.
Particulars / Local names Englishnames
Zoological names Satus in W.Lprotection Act.1972)Schedule Part
1 Endangered species –Core &Buffer ZoneBandar Resus
monkeyMacacamulatta(Zimmermann)
II I
Jackal - Canis aureus II IRuddy mongoose - Herpestessmithii II IThree striped squirrel - Funambuluspalmarum II IChameleon - Chameleozeylanicus II IINag Cobra Najanaja II II
2 Endemic species None3 Migratory species None4 Details of aquatic fauna, if
applicableKeu Anabas testudine - -Catfish (Mangur) Clariasbatrachus - -Singhi Heteropneustesfossilies - -Kari Labeocalbasu - -Kotri Puntius sophoro - -
5.1.5 Ground Water Resource
The net groundwater recharge, as estimated by rainfall infiltration method, and draft
for the buffer zone were estimated at 67.97 M.Cum and 27.778M.Cum respectively.
Thus, the balance available annual ground water recharge in the study area was
assessed as 40.192 M.Cum. The detailed groundwater balance with recharge and
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
10
discharge estimates is shown in the following pie diagram, Fig-5.1 (Reference: Approved
EMP of Gevra OC 47.25 Mty, 2014).
Figure 5.1
5.2 Environment Impact Assessment5.2.1 Noise Impact
Noise impact assessment has been shown in the following table 5. 10
Table -5.10Sl.No.
Parameters Impacts Assessment
1.00 Increase in Noise Levels atdrilling and blasting
May have impact upon the workers and the nearbyhabitants. The impact of noise more thanpermissible dosage may cause Annoyance andirritation, Mental and Physical fatigue,Interference in normal activities, Health hazardsresulting from impaired hearing. In extreme cases,cardio-vascular diseases etc., Task interference,Interference with communication i.e., masking.
2.00 Increase in Noise Levels atOperation of HEMMs likeshovel, dumper, dozer,excavator etc.
Same as above
3.00 Increase in Noise Levels atOperation of equipment inCHP, workshop etc
Same as above
4.00 Increase in Noise Levelsdue to transport system
Same as above
Net Annual Groundwater Recharge Balance, Study AreaGevra OCP, Gevra Area, SECL
Balance, 40.192,50.27%
Irrigation , 3.44,4.30%
Natural losses ,11.99, 14.99%
Mine Discharge,9.53, 11.92%
Domestic, 14.81,18.52%
(M.Cum, %)
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
11
5.2.2 Flora and Fauna
Impact assessment on flora & fauna has been shown below in Table 5.11.
Table 5.11Sl. No. Parameters Impact Assessment
1.00 Negative1.01 Vegetation Cover Except the area such as used for quarry excavation,
erection & development of plants, service & alliedstructures, colony, roads, diversions, culverts, etc, noother area is going to affected directly or indirectly bymining activities .Hence, impact on flora and fauna will not be ofappreciable level.
1.02 Forestsdegradation
Forests are going to be affected to a small extent i.e.1038.630Ha, 24.82%, of total project area of 4184.486Ha. Due to coal &OB transportation, air pollution may becaused which in turn might affect the process ofphotosynthesis and transpiration in plants by pluggingtheir leaves pores. SO2 causes Necrosis disease inplants. Hence, major impact on flora and fauna.
1.03 Ecologicalchange
The project being an opencast, there is no majorchange expected in ecological parameters on whichsurvival of flora and fauna depends directly or indirectly,and hence, no major impact on flora and fauna.
1.04 Hydro-geologicalaspects
Owing to opencast project, water level and draw downare likely to be affected to a nominal value; groundwater and surface water on which the flora and fauna ofthe area directly or indirectly depend upon are not goingto be affected to an appreciable level.
2.00 Positive2.01 Plantation work
and forest & wildlife conservation
Plantation work and forest & wild life conservation in ascientific way by project authorities in mine area willincrease aestheticism of the area.
5.2.3 Land UseImpact assessment on land use has been shown below in Table 5.12.
Table 5.12Sl.No.
Parameters Impact AssessmentWithin mining area Outside mining area
1.0 Topography In the quarry area, thedump area and themining equipmentarea, there will be a
No appreciable damage isenvisaged.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
12
Sl.No.
Parameters Impact AssessmentWithin mining area Outside mining area
marked change intopography.
2.0 Change in Landscape andLand use pattern thanpre-mining scenario suchas visual impact-loss ofaesthetic beauty, uglyscar on land;deforestation-loss ofsurface soil andvegetation cover
Total scenario of land-scape land use patternwill undergo a starkchange.
Landscape and land usepattern will change whereerection and developmentof plants, service /alliedservices buildings areestablished.
3.0 Change in SurfaceDrainage.
There will be a starkchange in surfacedrainage; rather newpattern of drainage willbe developed.
Surface drainage is likely tochange where constructionof colony, roads anddrainage are to beexecuted.
5.2.4 Socio-Economic StatusThe project involves atotal of 4184.486 Haof land for quarry, industrial and
residential complex, safety zone etc. The total no. of PAPs and PAFs are 6158 and
1920 respectively from following villagesviz. Amgaon, Bahanpat, Bhatora, Naraibodh,
Gevra, Ralia and Bhilai Bazar.
The PAFs and PAPs will be rehabilitated and paid economic compensation /
employment as per State Govt. R&R package.
Table-5.13Sl.No. Impact on Socio-Economic Status
1 Population Growth & In-migration2 Human Settlement & Resettlement / Rehabilitation3 Transport & Communication4 Income & Employment5 Civic Amenities& Community Development6 Educational facilities &Literacy Drive7 Economic growth8 Growth of Financial Revenues (State & Central)9 Social status growth
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
13
5.3 Environnent Management5.3.1Air Quality Management
Following air pollution control measures are will be practiced within the mining area
and at coal handling plants and railway siding.
1. Water spraying will be done regularly on approach roads within the mining area to
minimise the dust generation.
2. Mist sprinkling arrangement will be provided at the transfer point of coal.
3. Intensive plantation of adequate width all along the haul road and other road will be
raised to minimise transport generated pollutants.
4. Crusher house of CHP will be provided with dust extraction arrangements.
5. Minimising the transport of coal from the crusher house to silo loading system, belt
conveyor has been provided.
6. Coal transportation to railway siding will be done in covered trucks.
7. Exposed overburden dumps will be covered through an appropriate plantation
8. The drills will be equipped with dust arresting devices or wet drilling arrangement.
9. Optimum blast-hole geometry will be followed to reduce the dust during blasting.
10. Regular monitoring of ambient air quality of project area.
5.3.2 Water Quality Management
Management of surface water drainage: -
Garland drainage will be made around the periphery of the quarry. These drains
will be connected to Laxmannala, flowing in the north side of the mine. In the workings,
heavy duty pumps will be deployed in rainy season which after passing through settling
ponds will throw the accumulated water from the working face into these garland
drains.
Mine Water Discharge
The collected water at the floor of mine sump will be pumped to the settling tank
where suspended solids will get settled. The clear water after sedimentation & treatment
will be reused for water sprinkling, plantation & agriculture purpose, ground water
recharge & for use by the local villagers etc. Workshop effluents will be discharged
through Oil and Grease trap and sedimentation tank.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
14
Domestic Effluent Treatment: -DETP has been provided for treatment of domestic effluent from the colony.
Water Conservation: -
The waste water recycling after due treatment will enable conservation of water.
Storage of conserved water in mine pits would be given due emphasis to provide water
round the year and the quality of water would be maintained. The balance left mined out
area of 659.25. Ha. would be treated as water body after mine closure. This would serve
as a considerable source of water for the use of local population.
Control measures adopted against impact on ground water regime:-
i) The impact will be limited to a smaller distance and for a temporary period. The
effected habitation will be provided with suitable drinking water supply by sinking
hand pumps in the habitat.
ii) The entire mine industrial water demand, would be met from the treated mine
discharge. The wastage of water will be minimized.
iii) The surplus treated mine water will be discharge into the agricultural fields.
Thereby, the mine water will behave as constant source of recharge and
improves the water levels in the mine area. This will also become a resource for
the local public and increase agriculture output.
iv) So also, after cessation of mining, part of the quarry area will be reclaimed with
highly permeable OB material. The final void would be converted into a water
reservoir. Thus, in post-mining, the recharge and source potential in core zone
will be much higher than the existing.
v) With the increase in secondary porosity, a significant improvement in the rainfall
infiltration rate, close to the mine area can be anticipated.
5.3.3 Noise ManagementThe present noise levels are below the prescribed limits. If the impulsive noise
levels increase due to mining operation, suitable measures will be adopted to maintain
the noise level within permissible limits at working zone. The following measures are
adopted and will be continued:
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
15
1. Planting of rows of trees with thick foliage along roads and other noise
generating centers to act as acoustic barriers.
2. Isolating/enclosing the noisy machines/sources by using resilient
mounting/altering structures.
3. Routine maintenance schedules for HEMM and other machineries to eliminate
noise as far as possible.
4. Balanced and properly aligned conditioning of machines to reduce vibration.
5. Provision of ear muffs/ear plugs to workers subjected to noise level above
recommended limits.
6. Controlled blasting.
7. Regular monitoring of noise level of project area.
5.3.4 Flora and Fauna Management
The location of Gevra OC Block does not have any importance as a holiday
resort. The surface to be disturbed by open cast mining operation does contain any rare
variety of flora or fauna. As such, consequent to the opencast mining operation,
deterioration in quality of life or loss of amenity is not envisaged. Conservation plans of
schedule I & II animals, if any, will be prepared and implemented.
Compensatory afforestation and Strengthening of safety zone will be done. SECL
will develop this integrated area, as habitat for the fauna. The following steps will be
taken for development of habitat:
Reclamation of mine void:
In the core zone, after the cessation of mining activity a void will be created. This
void will be used as a water body. This will be graded to a gentle slope so that it acts as
a safe approach / access to the water body for the faunal species. Through Community
development work in villages existing in the buffer zone existing water sources
particularly the village tanks will be improved to provide drinking water to the local
community so that biotic pressure on water resources present in the forest areas and
used by fauna is gradually reduced.
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
16
Control of forest fire, fire in coal seam and coal stock.
Fire can destroy the entire habitats (micro and macro) and its life supporting
potential in a forest area.Fire does not spare fauna also.SECL will implement the
existing DGMS stipulated fire protection norms on coal seams and coal stock. This will
ensure that a congenial atmosphere is created and fire does not affect the fauna and
flora as well.
5.3.5 Land Resource Management
The existing land use and post-mining land use are shown below:
Existing Land Use:
It is estimated that 4184.486 Ha. of land will be required for Gevra Opencast Project (50
Mty) including land for quarry, external dumps, industrial and residential complex, road
diversion, safety zone and rehabilitation colonies.
The break-up of land use is given below and shown in Table- 5.14.
Table- 5.14 Existing Land Use
Stages ofmining
Activity Types of land area Total areaForest Agricultural Govt. Total
PRE-MINING
Nil 1038.63 2520.571 625.285 4184.486
DURINGMINING
Quarry 463.628 1273.426 300.196 2037.250External OBdump
Nil 291.31 188.69 480.00
Infrastructures
515.434 504.509 73.169 1093.112
Roaddiversion
Nil 6.00 Nil 6.00
Rehabilitation site
Nil 134.28 Nil 134.28
Safety Zone 59.568 311.046 63.23 433.844Total 1038.63 2520.571 625.285 4184.486*
Post Mining Land Use:
There would be a creation of about 2438.672 Ha. of forest by way of compensatory
afforestation , reclamation of dumps etc. against a degradation of 1038.63 Ha. of forest
by the mining activity. This is a positive impact. Details of plantation nos. as well as
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
17
expenditure incurred are given in the six monthly monitoring report attached with the
compliance report of environmental clearance. Conceptual post mining land use pattern
is as follows:
Table – 5.15 Post-Mining Land Use
Stages ofmining
Activity Types of land area (Ha.) Total area (Ha.)Forest Agricultural Govt. Total
POSTMINING
Void / Waterbody
Nil Nil 659.25 659.250
Reclaimedinternal OBdump area
1378 Nil Nil 1378.000
Reclaimedexternal OBdump area
480 Nil Nil 480.000
Green belt 5.67 Nil Nil 5.670Rehabilitation
siteNil 134.28 Nil 134.28
Infrastructures 515.434 504.509 73.169 1093.112Road diversion Nil 6.00 Nil 6.00Safety zone 59.568 311.046 57.56 428.174Total 2438.672 955.835 789.979 4184.486
5.4 Environment Management System
Monitoring Schedule
Environmental monitoring will be carried out following the monitoring schedule for
Air, Water, and Noise levels as per Standards of MOEF (Vide GSR 742 (E) dated
25.9.2000)
Plantation Monitoring
The project authority at field level will continuously monitor the growth and
survival/mortality rates of the plantations till the end of 3 years. Once trees attain
desired growth, no further monitoring will be required.
Action Plan for Land Reclamation and Plantation
A total of 1661850 no. of plants is estimated to be planted in the reclamation of
internal dumps. An area of 659.25Ha would be left as final void/water body after mine
closure. The dump surface would be maintained flat and top soil would be spread over it
as a part of final reclamation.Year wise programme of OB removal, dumping, &
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
18
plantation has been given in table 5.16. Details of action plan proposed for systematic
land reclamation and plantation on a regular time schedule is given in figure-5.2.
Table 5.16PROGRAMME OF O.B. REMOVAL, DUMPING & PLANTATION:
YearCoal
production
(MTes)
OBremoval(Mcum)
Dump plan( Mcum)
Dump area availablefor reclamation (Ha.)
No. of plantation@ 2500 Nos / Ha.
Totalplantation
@ 2500 Nos/ Ha.Extern
al Internal External Internal External Internal
1 45 80.00 0 80.00 0 0 0 0 02 45 80.00 0 80.00 0 0 0 0 03 50 82.00 0 82.00 0 0 0 0 04 50 82.00 0 82.00 0 0 0 0 05 50 82.00 0 82.00 0 0 0 0 06 50 82.00 0 82.00 0 166.30 0 415750 4157507 50 82.00 0 82.00 0 166.30 0 415750 415750
8 50 82.00 0 82.00 0 166.30 0 415750 415750
9 50 82.00 0 82.00 0 166.30 0 415750 415750
10 50 82.00 0 82.00 0 166.30 0 415750 415750
11 50 82.00 0 82.00 0 273.25 0 683125 68312512 28.86 49.76 0 49.76 0 273.25 0 683125 683125
Total 568.86 947.76 0 947.76 0 1378.00 0 1661850 1661850
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
19
ACTION PROGRAMME FOR EMP IMPLEMENTATIONGevra OCP (50 Mty), Gevra Area.
NO. DURATION/ ACTIVITIES 1 2 3 4 5 6 7 8 9 10 11 121 REHABILITATION & RESETTLEMENT OF
PROJECT AFFECTED FAMILIES/ PERSONS
2 ANTICIPATORY AFFORESTATION/ PLANTATION
3 COMPENSATORY AFFORESTATION4 DUMP RECLAMATIONA. Internal Dump
a. Filling
b. Reclamation(Technical)
d. Plantation
5 ENV.MONITORING / HEALTH MONITORING
6 OPERATION/ MAINTENANCE OF OIL, GREASE TRAPDETP.
7 WATER SPRINKLING ON HAUL ROADS, CHP
8 COMMUNITY DEVELOPMENT IN VILLAGES
9 FINAL MINE CLOSURE ACTIVITY
Figure-5.2The proposed enhancement of production (50 Mty) is planned within the existing land area of 4184.486 Ha.
Later on the mine would be further expanded to produce 70 Mty as per approved PR, for which additional
land has to be acquired. This additional land for expansion contains forest land. Once this forest land is
acquired, production capacity of the mine will be further enhanced to 70 Mty as per the approved PR Gevra
Expn. OC Mine. The capital requirement to fulfill environment related activities is to be provided from the
approved Project Report for Gevra Expansion Opencast Project (35.0 to 70.0 MTY)
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
20
MINING PLAN FOR GEVRA OC EXPANSION (35-50 MTY)
21