mining operations plan mop amendment c
TRANSCRIPT
Wallerawang Quarry
MINING OPERATIONS PLAN – MOP AMENDMENT C (amendments in green text)
MOP AMENDMENT B amendments remain in red text
Name of Mine: Wallerawang Quarry
MOP Commencement Date: 14/08/2016
MOP Completion Date: 31/05/2018
Mining Authorisations: ML 1633
Name of Authorisation holder: Walker Quarries Pty. Ltd.
Mine Operator: Walker Quarries Pty. Ltd.
Name and contact details of the Mine Manager:
Mr. Ray Sharwood - Wallerawang Quarry
Lot 6, Great Western Highway,
WALLERAWANG NSW 2845
M: 0429 272 148 T: (02) 63 24-4066
rays@walkerquarries,com.au
Name and contact details of Environmental Representative:
Ms. Anne Eastwood – Rangott Mineral Exploration
Pty. Ltd.
M: 0408 601006 T: (02) 6362-5155
Name of Representative of the Authorisation Holder:
Mr. David Murray – Managing Director of Walker
Quarries Pty. Ltd.
Signed:…………………………………………………………………………………………………………….
Date: 21.12.2017 Draft 1
Version 1
This MOP has been prepared in accordance with NSW Trade & Investment’s ESG3 Mining Operations
Plan MOP Guidelines September 2013 for a Level 1 mine.
Anne Eastwood
TABLE OF CONTENTS Page
1.0 Introduction 1
1.1 History of Operations 1
1.2 Current Consents, Authorisations and Licences 2
1.3 Land Ownership and Land Use 3
1.4 Stakeholder Consultation 4
2.0 Proposed Mining Activities 4
2.1 Project Description 4
2.2 Asset Register 5
2.3 Activities over the MOP term 7
3.0 Environmental Management 11
2.4 Environmental Risk Assessment 13
2.5 Environmental Risk Management 13
2.5.1 Specific Risks Relating to Rehabilitation 14
4.0 Post-Mining Land Use 17
4.1 Regulatory Requirements 17
4.2 Post-Mining Land Use Goal 17
4.3 Rehabilitation Objectives 18
5.0 Rehabilitation Planning and Management 19
5.1 Domain Selection 19
5.2 Domain Rehabilitation Objectives 20
5.3 Rehabilitation Phases 21
6.0 Performance Indicators, and Completion/Relinquishment Criteria 23
7.0 Rehabilitation Implementation 27
7.1 Status at MOP Commencement 27
7.2 Proposed Rehabilitation Activities in the MOP Term 28
7.3 Summary of Rehabilitation Areas during the MOP Term 30
7.4 Relinquishment Phase Achieved during the MOP Period 31
8.0 Rehabilitation Monitoring and Research 31
8.1 Rehabilitation Monitoring 31
8.2 Research and Rehabilitation Trials and Use of Analogue Sites 31
9.0 Intervention and Adaptive Management 31
9.1 Threats to Rehabilitation 31
9.2 Trigger Action Response Plan 32
10.0 Reporting 32
11.0 Plans 33
Plan 1A – PRE-MINING ENVIRONMENT – PROJECT LOCALITY
Plan 1B –PRE-MINING ENVIRONMENT – NATURAL and BUILT ENVIRONMENT
PLAN 1D – DIAGRAM OF PLANNED WESTERN STOCKPILE AREA
PLAN 2 – MINE DOMAINS AT COMMENCEMENT of MOP
PLAN 2A – MINE DOMAINS SHOWING PLANNED WESTERN STOCKPILE AREA
PLAN 3A – MINING AND REHABILITATION
PLAN 3B – MINNG and REHABILITATION INCLUDING WESTERN STOCKPILE AREA
PLAN 4 – FINAL REHABILITATION AND POST MINING LAND USE
11.4 Colour Coding for Plans
12.0 Review and Implementation of MOP 33
12.1 Review of the MOP 33
12.2 Implementation 33
TABLES
Table 1: Current consents, authorisations and licences 2
Table 2: Land ownership summary 3
Table 2.1 Asset Register 5
Table 2.2 Material production schedule during the MOP term 10
Table 3.1 Risk assessment matrix 11
Table 3.2 Risk matrix explanation 11
Table 3.3 Risk assessment results 12
Table 4.1 Regulatory requirements 17
Table 5.1 Coding for primary (operational) and secondary (post mining land use)
Domains 19
Table 5.2 Domain rehabilitation objectives 20
Table 5.3 Phases of rehabilitation 21
Table 5.4 Summary of rehabilitation phases proposed for completion at the end
of the MOP term 22
Table 6 Rehabilitation table 23
Table 7.1 Estimated disturbance and rehabilitation progression during the
term of the MOP 29
Table 7.2 Rehabilitation data table 30
LIST OF APPENDICES
Appendix I Development consent document
Development Consent – Modification 1
MOP amendment A May 2015
Environmental Protection Licence
Appendix II Environmental Management Plans (updated 2016)
Wallerawang Dam Notification Area Map
Appendix III Threatened species list
AHIMS Aboriginal Heritage Search results
1 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
1.0 Introduction
1.1 History of Operations
The Wallerawang Quarry is located in the Central West region of New South Wales, and lies 2.5km
southeast of the town of Wallerawang (PLAN 1A), in the Lithgow City Council Local Government Area.
Extraction was begun in 2014 by Walker Quarries Pty. Ltd., a subsidiary of Sitegoal Pty. Ltd., and the quarry
was developed to extract quartzite rock, predominantly for use as aggregate and road base. The former
Hoskins Quarry is located adjacent to the current quarry and was last worked in 1927. The Wallerawang
Quarry will produce approximately 3.5Mt of product material over the initial approval period of twenty
years. Annual production will vary between 150,000 tonnes to 500,000 tonnes, depending on market
demand. Although initial approval is for a 20-year period, the mine life is expected to be around 35 years
The quarry is covered by a Mining Lease – ML1633 – held by Walker Quarries Pty. Ltd., and the Mine
Operator is Walker Quarries Pty. Ltd.. The quarry is in the first of the three development stages that were
outlined in the previous (and first) Mining Operations Plan (2009 – 2016). Following the submission of an
Environmental Impact Statement in 2001, and the granting of Development Consent by the NSW Minister
for Infrastructure and Planning in October, 2004, a Mining Lease (ML 1633) was granted to Walker Quarries
by the NSW Minister for Mineral Resources on the 15th July, 2009. Subsequently, in December, 2009,
notification was received from the Director General, Department of Planning, stating that Walker Quarries
Pty. Ltd. had satisfied all the applicable conditions of the Development Consent that was issued in 2004.
Quarry development began in 2014. A modification to the Development Consent (Modification 1) was
approved by the NSW Department of Planning on the 25th August, 2017 (Appendix I). The Mining Lease
covers 44.33 ha and is located adjacent to the Great Western Highway. The Lease area includes Crown Land
administered by Forestry Corporation of New South Wales (Lidsdale State Forest) and other Crown Land,
and private land which is owned by Sitegoal Pty. Ltd.. The current area of disturbance is 11.7 hectares (10.2
hectares not including areas undergoing rehabilitation). The maximum area of disturbance during the
period covered by this Mining Operations Plan (MOP) will be 13.56 ha (12.6 ha not including areas
undergoing rehabilitation).
Walker Quarries is planning to create a new stockpile area to meet increasing demand for the quartzite
product. A Mining Operations Plan (MOP) was previously submitted to the Department of Primary
Industries by Walker Quarries for the period 15th July, 2009 to 14th July, 2016. MOP Amendment A (May,
2015) includes plans for an additional stockpile to be located to the west of the current stockpile, and has
been approved (Appendix I). The amended MOP (Amendment B) makes provision for resource definition
drilling. The planned drilling will not cause an increase in the area of disturbance. An additional activity
2 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
planned for the MOP period is the replacement of the northernmost part of the clean water drain with
encased polypipe, to allow access across the drain to the planned new stockpile area. This planned activity
is within the current area of disturbance.
This MOP Amendment C makes provision for the construction of the Western Stockpile Area (WSA) in
accordance with the WSA approved by the DPE (Modification 1) in the Environmental Assessment
prepared by R.W. Corkery & Co. The WSA as approved by the DPE is of a slightly larger area (0.74 ha
larger) than was approved in the MOP Amendment A, and includes the construction of a visual bund wall
(0.44 ha) to block the WSA visibility from the Great Western Highway. Another change described in this
amendment and approved in the Development Consent is the covering of the clean water drain (adjacent
to the WSA) along most of its length to prevent the inflow of dust and sediment, and to allow truck
movements over the drain. The WSA stockpile area will thus be continuous with the existing Stockpile
pad area.
Water management features in and around the WSA are changed in this amendment to accord with the
approved Development Consent – Modification 1. In particular – the twin pipes described in MOP
Amendment A to carry dirty water from the WSA to the sediment trap dam will not be constructed.
This MOP was prepared in accordance with the ESG3: Mining Operations Plan Guidelines September 2013.
1.2 Current Consents, Authorisations and Licences
ITEM GRANT DATE DURATION
Development Consent DA No. 344-11-2001 granted by the NSW Minister for Infrastructure and Planning for the operation of the quarry (Appendix I) Development Consent DA No. 344-11-2001 Modification 1
19th October, 2004 Approved 25th August 2017
15th July, 2019 (10 years from the grant of the ML)
Mining Lease – ML 1633 granted by the Department of Primary Industries (now NSW Trade & Investment) for the operation of the quarry
15th July, 2009 15th July, 2019
Environment Protection Licence No. 13172 (Appendix II) issued by the Department of Environment and Climate Change (now administered by the Environment Protection Authority) as approval to produce 500,000 tonnes per annum
21st October, 2009
Table 1: Currently held consents, authorisations and licences
3 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
The site is a Level 1 mine as it is classified by the Department of Infrastructure and Planning as State
Significant Development under the Section 76A(7) of the Environmental Planning and Assessment Act 1979
because it is an extractive industry where the proposed extraction rate is greater than 200,000 tonnes per
annum. The construction and operation of the proposed stockpile will be in accordance with the
Development Consent – Modification 1, listed above, and with the EIS titled Proposed Wallerawang
Quarry, Report 01/206.1, dated November 2001 and with the report titled Supplementary Report to the EIS
for the Proposed Wallerawang Quarry, Report 02/206, dated July, 2002, both prepared by Pacrim
Environmental, and with the conditions of the Mining Lease and the Environmental Protection Licence, and
with the approved site management plans.
1.3 Land Ownership and Land Use (Figure 3)
The Mining Lease covers three titles, summarised in Table 2:
Lot DP LGA Parish County Owner Land Use
7071 1201227 Lithgow
City Lidsdale Cook
State of New South Wales – NSW Forestry
Native bushland
7322 1149335 Lithgow
City Lidsdale Cook State of New South Wales
Native bushland
6 872230 Lithgow
City Lidsdale Cook
Sitegoal Pty. Ltd. (Walker Quarries Pty. Ltd. is a subsidiary of Sitegoal Pty. Ltd.)
Quarrying
Table 2: Land ownership summary
The tenure of the general area is forestry- either Pinus radiata plantations or native bushland (Sub Alpine
Eucalypt woodland), large areas of native bushland held as Crown Land, and low-density residential blocks
to the east and north of the quarry. The nearest residence is located 650m northwest of the extraction pit.
The Marrangaroo National Park is located 650m south of the Mining Lease area. A high-voltage overhead
power line and easement traverses the Mining Lease area through its southeast corner. The Wallerawang
Dam (Lake Wallace) is located 1.3km north of the extraction area. Wallerawang Dam is a Prescribed Dam
under the Dams Safety Act 1978, and Condition 28 of the Mining Lease is that no mining is to take place
within the Wallerawang Dam Notification Area (WDNA) without the Minister’s written consent. There are
no plans to extract within the WDNA in the MOP period. A map of the WDNA is included in Appendix II. The
Great Western Highway is the major highway linking Sydney with the western areas of the state, and lies
immediately north of the quarry site. The Cox’s River, which feeds Warragamba Dam many kilometres
downstream on the outskirts of Sydney, lies at a distance from 50m to 400m east of the ML1633 boundary
4 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
(PLAN 1B). The river flows south from the Lease area. The steep slopes and rocky outcrops in the area make
the land generally unsuitable for farming.
Historic land use has been of low intensity, and has consisted of forestry, minor quarrying and limited areas
of grazing and ‘lifestyle blocks’. Tens of small prospecting pits and an abandoned quartzite quarry (Hoskins
Quarry) are present in the ML1633 area. The proposed land use is quarrying and infrastructure
development related to quarrying. Following mine closure, the final end use will be native bushland – sub-
alpine Eucalypt woodland.
1.4 Stakeholder Consultation
The stakeholders are the landholders, the local community, the statutory authorities, including the Division
of Resources & Energy (DRE), NSW Industry.
Consultation took place between Rangott Mineral Exploration on behalf of Walker Quarries and both
Forestry Corporation of New South Wales (Mr. Dan Kirby), and Crown Lands (Orange office). Walker
Quarries’ objectives and plans for land end use and final rehabilitation were discussed with both parties. A
more detailed Final Rehabilitation Plan will be prepared in the MOP period, in consultation with the
landholders, with regard to the fact that the mine life is at least 30 years. Consultants in conjunction with
the Bathurst Local Land Council previously assessed the entire site and identified an aboriginal camp site
north of Hoskins Quarry, and concluded that no other areas of the site were suitable for long-term
occupation. The company signed a deed of agreement with the Gundungurra Tribal Council in 2007.
Consultation with the landholders and the relevant government agencies regarding rehabilitation will be
ongoing until mine closure. The latest development consent document is included in Appendix I of this
MOP. Consultation with the Wollongong Office of the DRE has recently been regular, and included site
visits by Mr. Greg Kininmonth of the DRE’s Environmental Sustainability Unit.
2.0 Proposed Mining Activities
2.1 Project Description
Quartzite rock is extracted from the quarry to produce a variety of products including aggregate, road base
and decorative stone. The proposed activities at the quarry site are a continuation of the quartzite
extraction, crushing and processing activities that occurred previously under ML 1633. Rock is extracted
using drilling, blasting and rock breaking. Quarry product is crushed and stockpiled on site using mobile
equipment. Overburden material is used in silt and sediment control features. The quarrying is now in
Stage 1 of a three stage development plan, as described in the EIS and previous MOP. The three stages
5 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
involve expansion of the pit area (1, 2 & 3) and lowering of the pit floor (3). Two additional activities are
planned for the MOP period. Firstly, Walker Quarries proposes to add a mobile sand-washing plant to
produce a washed sand product, as a processing activity on its existing processing pad.
The Wallerawang Quarry site consists of one extraction pit, stockpiles and working areas for truck
movements, crushing facilities and mobile plant, transportable office and facilities, bituminised entrance
road, weighbridge and wheel wash, four main storage and siltation dams, and water management
structures – clean and dirty water drains. An access road and seagull intersection with the Great Western
Highway facilitates safe entry and departure from the site. Extraction of up to 500,000 tonnes of quartzite
per annum has been approved, the initial approval being for a twenty-year period, ending in 2019.
2.2 Asset Register
No fixed plant is present. There are three separate transportable buildings, incorporating a site office,
present. The following table lists domains and assets which are snapshots of the current disturbance.
Primary Domain
Secondary Domain (Post- mining land use)
Code
Rehabilitation Phases during MOP term
Asset Disturbance Area
Current (hectares)
End of MOP term (hectares)
Infrastructure Area
Infrastructure 1A No rehabilitation – Active Mining Area
Tracks and haul road
Entrance Visual bund
0.648 0.788
Infrastructure Area
Rehabilitation Area - Woodland
1E No rehabilitation – Active Mining Area
Tracks Haul road from
pit Working areas
around entrance
Small laydown area
Office and facilities – transportable buildings
Potable water tanks
Septic system Car park,
weighbridge and wheel wash
Processing pad Mobile
crushers and conveyors
Mobile sand
3.252 3.252
6 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
wash plant Mining
equipment and trucks
Infrastructure Area
Final Void 1I No rehabilitation – Active Mining Area
Roads on pit perimeter that will become part of the void
0 0
Water Management Area
Water Management Area
3B No rehabilitation – Active Mining Area
Main storage dam
Main sediment dam
Top storage dam
Tops sediment dam
3 x small sediment silt cells
Clean and dirty water drains
2.2 2.2
Stockpiled material
Rehabilitation area-woodland
5E No rehabilitation – Active Mining Area
Topsoil stockpile
Product stockpiles
2.343 4
Stockpiled material
Final void 5I No rehabilitation – Active Mining Area
Stockpiled material on the floor of Hoskins Quarry
0.443 0.443
Void Final void 6I No rehabilitation – Active Mining Area
Open cut, around 195m x 90m
1.24 1.24
Rehabilitation Area - pasture
Rehabilitation Area - Woodland
7E Phase –3 Ecosystem and Land Use Establishment
Areas around top dams and seeded slopes
1.525 1.525
Table 2.1: Asset Register
2.3 Activities over the MOP term
7 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Exploration
Exploration activities will be conducted in the Lease area. The activities would include geological mapping
and surface sampling, percussion drilling and diamond drilling (up to twelve drill holes). The drill sites will
not require drill pad construction or dug sumps, and will be rehabilitated within a month following drilling.
All holes will be plugged below surface and recovered with subsoil and topsoil. Therefore, the drilling will
not result in an increase to the area of disturbance, or to the Rehabilitation Security amount.
Construction
The construction planned for the MOP period is the construction of a near- level stockpile pad to the
immediate west of the current stockpiles, in accordance with an amendment to the 2009 - 2016 MOP –
MOP Amendment C December 2017 (Appendix I). This planned stockpile pad will cover an area of up to
1.7 hectares. Also, most of the clean water drain, beginning at its northernmost point adjacent to the
Great Western Highway will be replaced by encased polypipe. The emplacement of the pipe will enable
trucks to cross between the existing stockpile area and the planned western stockpile area, in the future.
This construction will be entirely within the current area of disturbance.
Secondly, a near-level stockpile pad, 1.7 ha in area (the Western Stockpile Area or WSA) is planned to be
made in a cleared area to the immediate west of the existing Stockpile Pad, as described in the
Environmental Assessment document submitted in application for a modification of the Development
Consent, and approved August, 2017. The current area of disturbance is 11.7 hectares (10.2 ha not
including areas undergoing rehabilitation). In addition, a bund wall with vegetation plantings is required
to be built by the Consent conditions between the WSA and the Great Western Highway, and within the
Mining Lease, to provide a visual screen. These features are shown in Plans 1D and 2A in this document.
The features of the planned WSA are as follows:
A two level design has been chosen to replace the one-level design described in MOP
Amendment A. This new design will be safer, leading to less steep faces, and would be easier to
reshape to the original contours at final rehabilitation
Two battered slopes, one at the western edge of the WSA, and one in the centre, will be
constructed and hydromulched with grass seeds
The WSA will cover the current clean water drain, which will be replaced by a buried pipe. The
WSA will become continuous with the current Stockpile Pad
Dirty water will be channelled off the WSA via a constructed dirty water channel as shown in Plan
2A. The channel will join the existing sediment basin at the southern end of the WSA, and
continue through the stockpile areas to the Sediment Trap Dam
A bund wall will be constructed on the western and southern perimeters of the WSA to prevent
erosion and to contain sediment movement
8 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Slopes on the WSA will be formed to assist drainage to the dirty water drain.
The features of the visual bund wall are as follows:
The visual bund will be constructed of excavated materials from the WSA construction
The wall will be up to 100m in length, and vary in height from around 2m to around 4m
Plantings will begin on the bund wall following construction, with plants as per the site
Landscape Planting Plan (R. W. Corkery & Co., 2017).
Mining Operations (including mining purposes)
Mining operations will be carried out complying with the noise, airblast overpressure and ground vibration,
air quality, and hours of operation limits imposed by the Development Consent (344-11-2001). No
explosives or fuel will be stored on site.
Land preparation
Topsoil removal will be done in the MOP period and will be done in accordance with the Flora and Fauna
Management Plan. Topsoil will be removed from the planned western stockpile area as described in an
amendment to the 2009 MOP (MOP Amendment A, May 2015). No topsoil will be removed for pit
expansion.
Extraction
Quartzite will be continue to be extracted from the pit in the MOP period, and mining methods will be
unchanged from the previous MOP period. A maximum of 400,000 tonnes per annum is planned to be
extracted over the MOP period, within the Stage 1 plan outlined in the EIS. Stage 1 involves the
development of an initial trench approximately 350m long, 50m wide and 18m deep, oriented SSE. A haul
road to the trench (pit) was constructed, and the remainder of Stage 1 involves the widening of the trench,
with the quarry perimeter established within a 50m setback from the power transmission line located at
the SW corner of the quarry. Walls of between 6m and 8m height will be left at the southern and northern
extremities of the cut to reduce noise emissions.
Roughly 12% of the extracted material will be overburden (weathered quartzite). Overburden will not be
emplaced on site, except as temporary stockpiles in the stockpiling area, but will be used for hardstand
areas, and for bund walls on the new stockpile pad to be constructed in the MOP period. The highest face
in the pit is currently 15m (benched), and the walls are stable. Extraction will be done by drilling and
blasting (around six blasts per year) and rock breaking. Blasting will be carried out in accordance with the
site Blast Management Plan (including a Blast Monitoring program and Blasting/Vibration Protocol) which is
currently being reviewed and assessed.
Rock/ overburden emplacement
9 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
No overburden emplacements have been made or will be made in the MOP period, as overburden is used
for the maintenance of hardstand areas and sediment control features, and will be used in the MOP period
for bund walls around the new stockpile pad.
Stockpiling and processing
No tailings will be produced in the MOP period. Stockpiles of different size ranges and product type will
continue to be kept in the current stockpile area, in the Hoskins Quarry floor, and on the new stockpile pad
when it is constructed in the MOP period. Crushing and sorting will continue on the processing pad, with
the introduction of a mobile sand washer to produce a sand product. Water from the sand washing plant
will be transported by pipe to the three silt cell dams near the top storage dam, where any contained silt
fraction will settle. Water from these silt cells will then be re-used for further sand washing. Silt will be
dredged from the silt cells regularly, and sold as a product. No residues will be produced from the
processing that are not either sold or used to maintain infrastructure on site.
Waste management
No waste will be produced in the mining operations as reject material is used on site to as constructed
bund walls. Personal waste – e.g. food wrappers, will be removed at the end of each day. In the event that
soil is contaminated by hydrocarbon spills, the affected soil will be removed for disposal at an approved
waste facility. Office waste will be regularly removed to an approved waste facility. The septic system is
pumped out regularly.
Decommissioning and demolition activities
No decommissioning or demolition activities will be done in the MOP period
Temporary stabilisation
Temporary stabilisation will consist of:
Applying timber battering to the bases of slopes on the perimeter of the disturbed areas.
Progressive rehabilitation and completion
Rehabilitation during the MOP period will involve maintenance and monitoring of areas where revegetation
has been initiated (Phase 3 – Ecosystem and Land Use Establishment). No new areas will be rehabilitated
because currently disturbed areas are being used in quarrying operations.
Material Production Schedule during MOP Term
10 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Material production will depend on demand and weather conditions, but is expected to proceed at a
regular pace as shown in Table 2.2, below. Maximum expected figures are given. A density figure of 1.5 t/m3
was used to convert overburden tonnages to cubic metres.
Table 2.2: Material production schedule during the MOP term
Material Unit Year 1 Year 1.5
Stripped topsoil
m
3
0
1,920
Waste rock (overburden) (Maximum)
m3 32,000 16,000
Ore (maximum) t 400,000 200,000
Reject material/ Processing waste
t Minimal Minimal
Product (maximum) t 352,000 176,000
11 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
3 Environmental Issues Management
3.1 Environmental Risk Assessment
Environmental risks were identified and tabulated, as follows.
PROBABILITY
CO
NSE
QU
ENC
E A B C D E
1 H H H H M
2 H H H M M
3 H H M M M
4 M M M L L
5 M L L L L Table 3.1: Risk Assessment Matrix
PROBABILITY
CONSEQUENCES
A
Almost certain Expected to occur, quite common
1 Major Major environmental harm
B
Likely Will probably occur, has happened
2 Significant Long-term or serious environmental damage
C
Possible Might occur at some time
3 Moderate Moderate environmental impact
D
Unlikely Could occur at some time although unlikely
4
Minor Minimal environmental harm
E
Rare Might occur at some time in exceptional circumstances
5 Insignificant Little or no environmental harm
Table 3.2 Risk Matrix Explanation
12 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
ISSUE POTENTIAL IMPACTS
PROBABILITY CONSEQUENCE RISK RATING
Geology and Geochemistry
None E 5 LOW
Soil type and suitability
Erosion, degradation
C 5 LOW
Erosion/sediment control
Soil, stockpile, bunding, rehab area erosion and sedimentation of dams
C 4 MEDIUM
Surface water quality
Sedimentation of dam and drainage
C 4 MEDIUM
Groundwater quality
Contamination and loss of groundwater
E 5 LOW
Air quality Dust sedimentation on neighbouring residences, adverse health effects
E 4 LOW
Soil contamination Soil and overburden contaminated with fuel or oil
D 5 LOW
Flora Significant growth of weed species
C 3
MEDIUM
Fauna Loss of threatened species and significant increase in number of feral species
D 4 LOW
Weed control As for Flora C 3
MEDIUM
Noise Noise impacts closest residents
D 5 LOW
Aboriginal Heritage Heritage objects or places disturbed
D 4 LOW
Bushfire Plant and equipment fire, fire in bush surroundings
C 3 MEDIUM
Public safety Public wander on to site and fall
E 4 LOW
Slope management Slopes over 18° are left unstabilised and are eroded
D 4 LOW
Table 3.3: Risk Assessment Results
13 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
3.2 Environmental Risk Management
Table 3.3, above, lists the identified environmental risks of the proposed mining operation over the MOP
period. The following management plans will be used during the MOP period and have been approved or
are pending approval by the Secretary of the NSW Department of Planning and Environment:
Environmental Management Strategy
Water Management Plan
Noise Management Plan
Blast Management Plan
Air Quality Management Plan
Flora and Fauna Management Plan
Bushfire Management Plan
Environmental Monitoring Program.
Management of environmental impacts during the MOP period will be in accordance with the listed
management plans, and the conditions of the Development Consent and the Environmental Protection
Licence.
3.2.1 Specific Risks relating to Rehabilitation
Geology and geochemistry
The mineral to be extracted – quartzite (SiO2), is generally inert and is non-hazardous to the environment.
The processed product does not differ chemically from the ore.
Soil type(s) and suitability
Two soil landscapes occur at the site – Mount Walker Landscape (8931mw) soils and the Cullen Bullen
Landscape (8931cb) soils. The Cullen Bullen Landscape soils comprise yellow podzolic soils and yellow
earths. The soils are infertile (Land Capability IV) and are suffer localised sheet erosion and gully erosion.
The Mount Walker Landscape soils comprise colluvial yellow podzolic soils, red and yellow earths, and
structured earths on quartzite hills. Moderate sheet erosion and mass movement are present throughout
the landscape. The rural Land Capability is VII. These soils represent a moderate to very high erosion hazard
(e-spade), a low salinity hazard, and have a pH of between 6 and 7.3.
The topsoil stockpile will be managed by maintaining a stockpile height of less than 2m with a side slope of
3:1 (H:V), in accordance with the Flora and Fauna Management Plan. The stockpile will be regularly
monitored for stability and evidence of erosion. Due to the inherent low fertility of the soil, ameliorants will
be added to the soil at such time as it is used for rehabilitation. The topsoil will not be used in the MOP
period.
14 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Erosion and sediment control
Erosion and sediment movement is of medium risk at the site due to the hilly nature of the topography and
the relatively high rainfall events that occur sporadically. Also, revegetation of disturbed areas is at an early
stage, increasing the risk of erosion from these areas. To date, sediment movement mitigation methods
described in the site environmental management plans have been effective in counteracting sediment
movement. Erosion and sediment control will be continued according to the Water Management Plan.
Clean and dirty water diversion channels and silt fences are in place to manage erosion during the MOP
period. Also, maintenance of revegetating slopes will minimise erosion during the MOP period. The planned
WSA will include perimeter bunds and a dirty water diversion channel. New water management features
associated with the planned WSA are approved by the modified Development Consent and are described
in Section 2.2.
Surface water quality
Surface water will be managed according to the site Water Management Plan (an updated version of the
previous plan is awaiting approval from the Secretary of the NSW Department of Planning and
Environment). Surface water drains to one of two sediment dams. The clean water drain releases clean
water to the unnamed creek to the immediate south of the Main Storage Dam. It is noted that the clean
water drain collects some run-off from the Great Western Highway, to the north of the Mining Lease area.
Water in the storage dams is available for irrigation of rehabilitating areas in times of low rainfall. The dirty
water drain on the eastern side of the pit carries any silt-laden run-off north to the top storage dam. There
are no water contaminants on site or in the rock material, therefore, the water quality in the storage dams
is suitable for irrigation and dust suppression. The results of routine water sample analysis during 2015-
2016 of the stored water on site indicate that it is of good quality. The stored (and released) water quality is
expected to remain high in the MOP period and beyond. Regular monitoring of the water quality will
continue in the MOP period, according to the site Environmental Monitoring Program. New water
management features associated with the planned WSA are approved by the modified Development
Consent and are described in Section 2.2.
Ground water
Groundwater is absent from the site at the levels of quartzite extraction and dam construction, and no
groundwater will be extracted for any purpose during the MOP period. The adherence to the Water
Management Plan during the MOP period will prevent contamination of any groundwater that may be
present on site. Contamination or depletion of groundwater in this case is very unlikely.
15 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Dust/ Air quality
Dust levels will be managed to meet the limits imposed by the Development Consent and the
Environmental Protection Licence (EPL). Monthly monitoring of the air quality parameters required by the
conditions of the Development Consent and the EPL will continue in the MOP period, according to the site
Environmental Monitoring Program.
The following dust mitigation methods will be used in the MOP period:
Blasting will be done by a certified shotfirer in such a way as to minimise dust production
A water cart using water stored on site will be used to control dust levels. Any water sprayed will be
sprayed in accordance with the Water Management Plan approved by the Secretary of the NSW
Department of Planning and Environment
Truck loads will be covered when travelling.
The native bush that surrounds the quarry acts as a barrier to the dispersion of dust. Dust levels to date
have not caused a deterioration in the vegetation surrounding the site.
Soil contamination
Care will be taken to avoid fuel spills in the machinery laydown/refuelling area. Any stored fuel will be kept
in an existing concrete containment tank. Any contaminated soil will be removed for disposal at an
approved waste facility.
Flora
Impacts to flora will be mitigated using the site Flora and Fauna Management Plan.
The WSA has been approved for clearing under the Modified Consent.
During the MOP period, the risks to rehabilitation are drought, and proliferation of weeds on the
rehabilitating areas. Using spray irrigation (in accordance with the Water Management Plan) and weed
sprays will manage these risks. The progress of the rehabilitation will be monitored during the MOP period.
Fauna
Impacts to fauna will be mitigated using the site Flora and Fauna Management Plan.
As part of a monitoring programme, any observations of Threatened Species, including the Bathurst Copper
Butterfly Paralucia spinifera, will be recorded. The current mining areas and rehabilitation areas have
limited potential for providing fauna habitats. The WSA has been approved for clearing under the
Modified Consent. During the MOP period, the risk to rehabilitation is the incursion of feral animals.
Ensuring that no food waste is accessible will minimise the risk of feral animals being attracted to the site.
Weed control
Weed growth will be managed according to the Flora and Fauna Management Plan. The main risk to
rehabilitation is significant weed growth dominating the ecosystem of the rehabilitating areas. Weeds will
be identified and sprayed during the MOP period.
16 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Noise
Noise will be monitored in accordance with the conditions of the Development Consent and the EPL, and
according to the site Noise Management Plan. There is a minor risk to rehabilitation posed by noise. The
Threatened Species Yellow Sheath-tailed bat has been found by echo-location in a flora and fauna survey.
However, individuals of this species are able to find alternative roosting places in less noisy areas in the
surrounding bushland.
Aboriginal heritage
The known site of Aboriginal heritage is a mining exclusion zone and will remain undisturbed in the MOP
period and beyond.
Bushfire
The potential for bushfire will be managed according to the site’s Bushfire Management Plan. The site is
not mapped as bushfire-prone by Lithgow Council, however, it is surrounded by native bushland. A bushfire
is unlikely to be started on site because it is a mostly cleared area. The risk to rehabilitation is from a fire
started outside the Mining Lease area. Native vegetation is likely to regenerate quickly after a bushfire, as it
does elsewhere. The Bushfire Management Plan will be followed in the MOP period.
Material prone to spontaneous combustion
No materials prone to spontaneous combustion will be used in the ML area.
Mine Subsidence
The planned mining during the MOP period will not exceed a depth of 25m, will be open-cut, and will
therefore not result in mine subsidence. No subsidence has occurred in the areas previously mined at the
site.
Other Risks
Slope management
Most slopes on site are less than 18°. The pit walls are strong and stable, and the main risk would come
from stockpiles. Stockpile slopes will not exceed 2m in height and will be battered to as low a slope as
possible.
Public safety
During the MOP period, members of the public will continue to be banned from entering site without prior
notice. A warning sign at the entrance gate and a fence along the Lease boundary are in place to help
manage public safety.
17 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
4 Post Mining Land Use
4.1 Regulatory Requirements
SOURCE DOCUMENT POST-MINING LAND USE REQUIREMENT
NSW Minister for Infrastructure and Planning
Development Consent 344-11-2001
Condition 1.9 The Applicant shall ensure that all demolition work is carried out in accordance with AS2601-2001: The Demolition of Structures Condition 2.38 The Applicant shall prepare and implement a Flora and Fauna Management Plan for the development Condition 2.55 The Applicant shall rehabilitate the development site in accordance with the requirements of any Mining Lease granted by the Minister for Mineral Resources
The Minister for Mineral Resources of the State of New South Wales
Mining Lease No. 1633 dated 15th
July 2009
Disturbed land must be rehabilitated to a sustainable/agreed end land use to the satisfaction of the Director-General
Table 4.1 Regulatory requirements
4.2 Post Mining Land Use Goal
The post mining land use goal for the site is for it to be returned to native bushland – sub-alpine Eucalypt
woodland – that is safe, stable, non-polluting and self-sustaining. The 2001 Environmental Impact
Statement and 2009-2016 Mining Operations Plan both state as an objective: “re-establish progressively a
Eucalypt woodland similar to that which currently exists”. This is considered the best option in order to
preserve the local ecological community. The final rehabilitation plan includes:
Retaining, modifying and revegetating the open cut void. The Hoskins Quarry will remain as a void (as it
has been since the 1920s)
Reshaping and revegetating the processing and stockpile pads to replicate the original landform as
much as possible
Retaining two main access roads
Removing, ripping and revegetating hardstand areas, office buildings and weighbridge
Retaining of all water management features, including dams.
18 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
4.3 Rehabilitation Objectives
The objectives of the mine rehabilitation area:
Stabilisation of the land to minimise environmental impacts
1. Reshaping the processing pad and stockpile areas to resemble, as much as possible, the original
landform
2. Establishing a native ecosystem over the entire site (minus the access tracks to be retained and the
water management features) that is self-sustaining, low maintenance, and closely resembling the
ecosystem surrounding the quarry site –that is, sub-alpine Eucalypt woodland
3. Modifying the final void to make it safe and stable
4. Removing stockpiles from Hoskins Quarry
5. Removing all buildings and equipment
6. Removing the bitumen road within the Lease area
7. Retaining all water management features, including drains and dams
8. Ongoing consultation with landholders regarding the final rehabilitation (as the quarry expands).
The long term objective is to restore the site to resemble the surrounding bushland and to not require
maintenance in addition to what may be required in the surrounding bushland.
19 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
5 Rehabilitation Planning and Management
5.1 Domain Selection
Code Primary Domains (Operational) Code Secondary Domains (end Land Use) Code
1 Infrastructure Area (some access tracks)
A Retained as infrastructure for the landowners and to provide access for environmental monitoring
1A
1 Infrastructure Area (hardstand working areas, processing pad, laydown areas)
E Rehabilitation area - Woodland 1E
1 Infrastructure Area (pit perimeter access/haul road)
I Final Void (Expanded void will consume road)
1I
3 Water Management Area B Retained Water Management Area 3B
5 Stockpiled Material E Rehabilitation Area - Woodland 5E
5 Stockpiled material (those stockpiles stored on the floor of the disused Hoskins Quarry)
I Final void (stockpiles removed) 5I
6 Void (open cut) I Modified void remaining with revegetation with native to bushland
6I
7 Rehabilitation Area – Pasture (Seeded banks and other areas that will not require reshaping at mine closure)
E Rehabilitation area – Woodland (Areas will be progressively planted with trees and shrubs)
7E
Table 5.1: Coding for primary (operational) and secondary (post mining land use) domains
20 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
5.2 Domain Rehabilitation Objectives
Primary Domain Secondary domain (Post-mining)
Rehabilitation Objectives
Infrastructure Area (1) Infrastructure Area (A) Selected access tracks will remain
Infrastructure Area (1) Rehabilitation Area – Woodland (E)
All services and infrastructure removed
Surfaces ripped and reshaped as much as possible to the original landform
Establishment of self-sustaining vegetation with a similar density and composition to the surrounding native bushland
Infrastructure Area (1) Final Void (I) As for Final Void (I)
Water Management Area (3) Water Management Area (B) Retention of water management areas to control run-off and to provide water for wildlife
Stockpiled material (5) Rehabilitation Area - Woodland All stockpiles to be removed Surfaces ripped and reshaped
as much as possible to the original landform
Establishment of self-sustaining vegetation with a similar density and composition to the surrounding native bushland
Stockpiled material (I) Final Void (Hoskins Quarry) Remove stockpiles and thereby leave the Hoskins Quarry as it was before the Mining Lease was granted
Void (6) Final Void (I) To be infilled as much overburden material as possible, with overburden and reshaping making safe-angled batters
perimeter bund walls to be retained for public safety
Establishment of self-sustaining vegetation of similar composition to the surrounding native bushland
Rehabilitation Area -Pasture (7) Rehabilitation Area – Woodland (E)
Establishment of self-sustaining vegetation with a similar density and composition to the surrounding native bushland
Table 5.2: Domain Rehabilitation Objectives
21 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
5.3 Rehabilitation Phases
For reference, rehabilitation phases identified in the ESG3 Guidelines are presented in the following table.
Phase No.
Rehabilitation Phase Examples of possible measures
1
Decommissioning Infrastructure removed, contamination remediated, electricity decommissioned, heritage buildings retained
2
Landform Establishment Slope, drainage (characteristics, grade and density), substrate material characterisation, morphology, density, aspect
3
Growth Medium Development
Physical, chemical and biological characteristics (organics, nutrients, soil biota etc.)
4
Ecosystem and Land Use Establishment
Species selection, species presence, and germination rate. OR Subsurface Development
5
Ecosystem and Land Use Sustainability
Floristics and structure, recruitment and recovery, fauna presence, growth, ecosystem resilience OR Infrastructure Development
6
Land Relinquishment Demonstrated ultimate success of rehabilitation process. This may be biophysical or physical.
Table 5.3: Phases of rehabilitation.
22 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
During the MOP term, Phase 3 will be implemented at the quarry site.
DOMAIN
Re
hab
ilita
tio
n
Ph
ase
1A
Infr
astr
uct
ure
1E
Infr
astr
uct
ure
1I I
nfr
astr
uct
ure
3B
Wat
er
Man
agem
en
t
Are
as
3B
Wat
er
Man
agem
ent
Are
as
5E
Sto
ckp
iled
mat
eria
l
5I
6I
7E
Decommissioning
x x x x x x x x
Landform Establishment x x x x x x x x
Growth Medium Development x x x x x x x
Tube stock planting
Ecosystem and Land Use Establishment
x x x x x x x x
Ecosystem and Land Use Sustainability
x x x x x x x x
Land Relinquishment
x x x x x x x x
Table 5.4: Summary of Rehabilitation Phases proposed for completion at the end of
the MOP term
23 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
6 Performance Indicators, and Completion/Relinquishment Criteria
The following is a detailed rehabilitation table for each phase of rehabilitation.
Table 6: Rehabilitation Table
Ob
ject
ive
PI
Co
mp
leti
on
Cri
teri
a
Just
ific
atio
n
Co
mp
lete
?
Lin
k to
TA
RP
Pro
gre
ss a
t
star
t o
f M
OP
REHABILITATION PHASE - DECOMMISSIONING
Domain – Infrastructure (1)
All infrastructure to be removed
Removal of Fixed and
mobile plant, water tanks,
transportable buildings, concrete footings,
weighbridge, Wheel wash,
Lease boundary fence,
Bitumen road, Services
Complete removal of all
items and foundations
Required to achieve
objectives No NA
Not commenced
Domain – Stockpiled material (5E)
All stockpiles to be removed
All Stockpiles removed
Complete removal of all
extracted material
Required to achieve objective
No NA Not
commenced
Domain – Stockpiled material (5I)
All stockpiles to be removed
All Stockpiles removed
Complete removal of all
extracted material
Required to achieve objective
No NA Not
commenced
REHABILITATION PHASE – LANDFORM ESTABLISHMENT
Domain – Infrastructure (1E) Make domain stable
Rip and reshape areas to a slight slope to the WSW
All ripped l areas reshaped to a slope of around 10° to the WSW
Best practice to return the topography to closely resemble the pre-mining topography.
No NA Not commenced
Effective surface water drainage by constructing two contour banks on the slope, and a two water diversion Bunds to direct
Two contour banks are constructed and two water diversion bunds are constructed
Required to achieve objective. Condition 18 of Mining Lease Authority.
No NA Not Commenced
24 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
runoff to the main sediment dam
Domain – Stockpiled materials (5E) Stabilisation of the land
Rip and reshape areas to a slight slope to the WSW (east of clean water drain) and a moderate slope to the east in the area west of the clean water drain.
Ripped areas east of the clean water drain are reshaped to a slope of 10° to the WSW. Ripped areas west of the clean water drain are reshaped to a slope of 25° to the east.
Best practice to return the topography to closely resemble the pre-mining topography.
No NA Not commenced
Effective surface water drainage by constructing four contour banks and four water diversion bunds to channel runoff into the main sediment dam.
Two contour banks are constructed on the slopes each side of the clean water drain Runoff from the slope west of the clean water drain is diverted into the main sediment dam with existing pipes crossing the clean water drain. Two water diversion banks are constructed on this slope. Runoff from the slope east of the clean water drain is diverted into the main sediment dam. Two water diversion bunds are constructed for this purpose
Required to achieve objective. Condition 18 of Mining Lease Authority.
No NA Not Commenced
Domain –Void (6I) Stabilisation of the land
Any available overburden material available and in-pit material has
Batter has a slope of less than 18°.
Best practice low, safe angle. Angle not specified in Mining Lease Authority conditions
No NA Not commenced
25 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
been made to form safe-angled batters at the toes of all faces at all faces
or Development Consent.
A 1m-high bund wall surrounding the pit perimeter is retained to divert runoff from entering the pit and for public safety
Complete, 1m-high bund wall surrounds the void
Required to achieve objectives
No NA Bund wall present
REHABILITATION PHASE – GROWTH MEDIUM DEVELOPMENT
Domain - Infrastructure (1E) Establishment of a native ecosystem that is self-sustaining and closely resembles surrounding bushland
Topsoil applied to reshaped infrastructure areas
Topsoil covers reshaped infrastructure areas with a depth of at least 100mm
Required to achieve stated land end use.
No NA Not commenced
Domain –Stockpiled material (5E) Establishment of self-sustaining vegetation with a similar density and composition to the surrounding native bushland
Topsoil applied to reshaped stockpile areas
Topsoil covers reshaped stockpile areas with a depth of at least 100mm
Required to achieve stated land end use.
No NA Not commenced
Domain – Void (6E) Establishment of a native ecosystem that is self-sustaining and closely resembles surrounding bushland
Topsoil applied to flatter slopes of void
Topsoil covers the flatter slopes of the void to a depth of at least 100mm
Required to achieve stated land end use.
No NA Not commenced
REHABILITATION PHASE – ECOSYSTEM AND LAND USE DEVELOPMENT
Domain – Infrastructure (1E), Stockpiled material (5E), Void (6I) and Rehabilitated Areas – Pasture (7E) Establishment of a native ecosystem that is self-sustaining and closely
Fallen timber is spread over site, some containing
5 x timber logs per hectare, 2 of which are hollow-
Required to achieve stated objective.
No NA Not commenced
26 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
resembles surrounding bushland
hollows for habitat
bearing
Survey domain area to establish types and number of
seeds/tubestock
required
Complete survey , results
depending on density
and diversity of
vegetation
Required to achieve stated objective
No Section 9.2
Not commenced
Grass and tree seeds from species existing in the surrounding bushland are spread over the site.
1 kg seed per hectare. Establishment success 50-70% within 5 years
Required to achieve stated objective
No Section 9.2
Not commenced Seeding with sterile cereal has commenced on Domain 7E
REHABILITATION PHASE – ECOSYSTEM AND LAND USE STABILITY
Domains – Infrastructure (1E), Stockpile material (5E), Void (6I), Rehabilitation Areas (7E)
Establishment of a native ecosystem that is self-sustaining and closely resembles surrounding bushland
Vegetation type, density and diversity is comparable to the surrounding bushland
Ecological consultant confirms comparability to surrounding bushland
Required to achieve stated objective
No Section 9.2
Not commenced
Weed growth is under control
Weed species are not present in greater numbers in the rehabilitated site than in the surrounding bushland
Required to achieve stated objective. Landowners’ requirements
No Section 9.2
Not commenced
REHABILITATION PHASE – LAND RELINQUISHMENT
Entire site Stabilisation of the land to minimise environmental impacts
Objectives for the landform stability met
All land stability criteria met
Requirements of the MOP
No Not commenced
Establishment of a native ecosystem over
Entire site successfully rehabilitated according to
All completion criteria met for all
Requirements of the MOP
No Section 9.2
Not commenced
27 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
the entire site that is self-sustaining, low maintenance and closely resembles the ecosystem surrounding the quarry site
the completion criteria
rehabilitation phases
Table 6: Rehabilitation Table
7 Rehabilitation Implementation
7.1 Status at MOP Commencement
DOMAIN 1 – Infrastructure
This domain is currently active and includes:
Visual bund
Access tracks and haul road
Mobile plant - crushers, conveyors, screens and sand washing machine
Transportable office buildings and amenities – 2 buildings, potable water tanks, septic system, concrete
paving and footings
Electrical services
Car park and hardstand laydown and working areas
Processing pad
Bitumen entrance road with wheel wash and weighbridge
Rehabilitation of the infrastructure areas will not commence until mine closure.
DOMAIN 3 – Water Management Areas
The domain is currently active and comprises two sediment trap dams with rock spillways
Two storage dams
Rock lined water diversion drains and a clean water drain (to unnamed creek) and a dirty water drain (to
top storage dam)
Three small silt settlement dams (silt cells) near the top storage dam
The immediate surroundings of the dams are revegetating naturally. The water management areas will be
retained at mine closure.
This domain will remain active over the MOP period.
28 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
DOMAIN
5 – Stockpiled material
Stockpile pad (main and southern areas) + stockpile storage on the floor of the abandoned Hoskins Quarry
+ Western Stockpile Area + Eastern Stockpile Area.
This domain is currently active and will remain active over the MOP period. No rehabilitation will be done
until mine closure.
DOMAIN 6 –Void (open cut)
This domain is currently active, and is gradually expanding. No rehabilitation has been done or will be done
in the MOP period.
DOMAIN 7 – Rehabilitation Areas –Pasture
This area is gradually revegetating, having been spray-seeded, and stabilising. Rehabilitation work will
continue in the MOP period.
7.2 Proposed Rehabilitation Activities during the MOP Term
DOMAIN 1 – Infrastructure
No rehabilitation activities are planned as the domain areas are active
DOMAIN 3 – Water Management Areas
No rehabilitation activities are planned as the domain areas are active
DOMAIN 5 – Stockpiled materials
No rehabilitation activities are planned as the domain areas are active.
DOMAIN 6 – Void (Open cut)
No rehabilitation activities are planned as the domain area will be active.
DOMAIN 7 – Rehabilitation Areas
1. Ecosystem Establishment
Rehabilitation in the MOP period will involve a site survey of the density and relative abundance
of the revegetation species. The results of the survey will indicate:
1. Which areas need reseeding/planting to progress revegetation
2. Which species, such as native grasses, are predominant, and which species need to be
introduced with seeding or planting to replicate the species diversity of the surrounding bushland.
Fallen timber not currently inhabited will be imported from the surrounding bushland areas and
placed in the rehabilitation areas. Depending on the results of the survey, reseeding and/or
planting of tubestock will be done. Mulch will be placed around the tubestock.
29 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
Year
Total Disturbance area (ha)
Total Rehabilitation Area (ha) (per MOP Year)
Cumulative Rehabilitation Area
Comments/Explanation
At Start of
MOP (14th
August, 2016)
10.1
0
1.525
Total disturbance is 11.7 ha if rehabilitation areas are included Rehabilitation areas will not expand because rehabilitation will progress on existing rehab areas
1
10.1 0 1.525
End of MOP (14
th
February, 2018)
12.6 0 1.525 Extra disturbance will be due to the construction of the new stockpile as per MOP Amendment C (Dec 2017)
Table 7.1: Estimated Disturbance and Rehabilitation progression during the term of the MOP
30 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
7.3 Summary of Rehabilitation Areas during the MOP Term
Primary Domain
Secondary Domain
Code
Rehabilitation Phase
Area at Start of MOP (ha)
Area at end of MOP (ha)
Infrastructure Areas
Rehabilitation Area – Woodland (E) 1E
Active 2.91 2.91
Landform establishment 0 0
Growth Medium Development 0 0
Ecosystem Development 0 0
Infrastructure
1A
Active 0.648 0.788
Landform establishment 0 0
Growth Medium Development 0 0
Ecosystem Development 0 0
Final Void 1I Active 0.293 0.293
Water Management Areas
Water Management Areas
3B Active 2.2 2.2
Stockpile materials
Rehabilitation Area – Woodland (E)
5E
Active
2.3 4
Landform establishment 0 0
Growth Medium Development 0 0
Ecosystem Establishment 0 0
Final Void (I) 5I Active 0.443 0.443
Void (open cut) Final Void (I)
6I
Active 1.24 1.24
Landform establishment 0 0
Growth Medium Development 0 0
Ecosystem Establishment 0 0
Rehabilitation Areas
Rehabilitation Area – Woodland (E)
7E
Active 0 0
Landform establishment 0 0
Growth Medium Development 0 0
Ecosystem Establishment 1.525 1.525
Ecosystem Development 0 0
Relinquished lands 0 0
Table 7.2: Rehabilitation Data Table
31 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
7.4 Relinquishment Phase achieved during the MOP period
No areas of the Relinquished Lands category will be achieved during the MOP period.
8 Rehabilitation Monitoring and Research
8.1 Rehabilitation Monitoring
The following monitoring activities will be used throughout the MOP period to test the success or
otherwise of the rehabilitation:
1. Once every month, an inspection of the rehabilitated (infilled, reshaped, revegetating) areas will be
done to check site stability, erosion and sedimentation, weeds, presence of native animals and the
extent and health of vegetation regrowth. The results will be documented in a diary. Action will be
taken to ameliorate any problems found and to stop them recurring
8.2 Research and Rehabilitation Trials and Use of Analogue Sites
The analogue site is the bushland surrounding the quarry site, as the objective is to restore the
active areas to native bushland closely resembling the bushland surrounding the site.
9 Intervention and Adaptive Management
9.1 Threats to Rehabilitation
Threats to rehabilitation include prolonged drought and insect plagues (e.g. locusts) and disease
(e.g. Phytophera).
32 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
9.2 Trigger Action Response Plan
THREAT TO REHABILITATION SUCCESS
TRIGGER LEVEL
RESPONSE ACTION
REASON/ VALIDITY OF RESPONSE
MITIGATION/ REMEDIATION
Prolonged drought
Over 10% of vegetation on rehabilitation areas is dead.
Buy water and spray weekly over rehabilitating areas. Notify DRE Orange.
Losing vegetation over rehabilitation areas is contrary to the rehabilitation objectives.
Establish vegetation as soon as possible as mature plants are more drought tolerant.
Insect plague or disease
There is evidence of plague or disease in the local area
There is no appropriate response for insect plague. Hygiene protocols to be instigated at entrance to prevent the introduction of disease. Consult the Department (DRE).
Best practice Reset Rehabilitation goals
10 Reporting
The following reporting mechanisms will verify compliance with the MOP and support progression
towards the post-mining land use and rehabilitation objectives:
Progressive rehabilitation tables
Results of progressive rehabilitation, as reported in the Annual Environmental
Management Report.
33 | P a g e Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
11.0 Plans
PLAN 1A- Project Locality
PLAN 1B –Pre-Mining Natural and Built Environment
PLAN 1D – DIAGRAM OF PLANNED WESTERN STOCKPILE AREA
PLAN 2 - Mine Domains at Commencement of MOP
PLAN2A – MINE DOMAINS SHOWING PLANNED WESTERN STOCKPILE AREA
PLAN 3 - Mining and Rehabilitation year 1.5
PLAN 3B – MINING AND REHABILITATION INCLUDING WESTERN STOCKPILE AREA
PLAN 4 - Final Rehabilitation and Post Mining Land Use
11.4 Colour coding and symbols for Plans
12.0 Review and Implementation of the MOP
12.1 Review of the MOP
The MOP will be reviewed by the Titleholder yearly to measure the planned rehabilitation areas against the
areas actually rehabilitated. GPS surveying of the domains will be done regularly to aid in digital mapping
for annual reporting and demonstrating rehabilitation progression.
12.2 Implementation
The titleholder, Walker Quarries Pty. Ltd., is responsible for the monitoring, review and implementation of
this MOP. Anne Eastwood and Max Rangott, geological consultants of Rangott Mineral Exploration Pty.
Ltd., will be available throughout the MOP period to provide technical advice and help with digital mapping
and reporting, if required.
Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
APPENDIX 1 – Development Consent documents from NSW Department of Planning
Environmental Protection Licence
MOP 2009
MOP Amendment A (May 2015)
Mining Operations Plan | Wallerawang Quarry | Walker Quarries Pty. Ltd.
APPENDIX II - Wallerawang Dam Notification Area Map