  • Process Mechanical Piping Civil/Structural Instrumentation & Control Electrical

    Establish Process Design Basis Preliminary Equipment List - Issue for DBM Preliminary Plot Plan Varification of Site Selection I&C Inputs for DBM - IFRElectrical infrastructure and Requirements

    Defined

    Client business drivers identified Historical mechanical data collected Codes and Standards defined Civil/Structural design criteria definedClient input about Opetations, Control

    Phylosophy receivedCodes and Standards defined

    Site data collected (

    elecations,temperatures)

    Dimensions, weighs rough sized in process

    engineeringFire protection requirements defined Modularization strategy defined Control Phylosophy defined Local site conditions and profile received

    Licensors identified PFD's IFR received Building enclosure philosophy determinedUnderground and above ground existing

    facilities identified

    Preliminary Control system architecture

    issuedPreliminary horsepower data received

    Feedstock information collected (

    composition, rate,etc.)MSD's - IFR Meteorological data received

    Meteorological ( snow, wind etc.)

    information compiledStandard & Specification defined

    Electrical power studies to define

    requirements

    Process design criteria identified Vendor packaged equipments identified Existing facilities information collected Preliminary geotechnical report receicedPreliminary Control systen functional

    specifications definedPreliminery Electrical equipment list

    Product information prepared Critical/long delivery items identified Historical plot plan data collected Land issues involved Control building preliminary sized

    Electrical

    underground,aboveground,substation

    information received

    Sparing phylosophy definedLegal and regulatory requirements

    determined

    Topographic information/ co-ordinates (

    under/above ) ground received

    Regulatory issues (three level government,

    environmental etc.Preliminary PFD's received Electrical design criteria defined

    Environmental consideratuiins identifiedSpacing guidelines (

    Installation,Hazards,etc.) establishedSite infrastructure information collected

    Major equipment process data sheets

    received

    Preliminary Equipment Pricing ( Quotes ) PFD's IFA receivedTransportation/logistic issues information

    collectedCritical inline devices identified Area Classification - IFR

    Process Flow Diagram Functional Mechanical specifications Main piping tie-ins identifiedPreliminary plot plan issued by plant layout

    (with civil/structural inputPFD IFD received

    Licencer information reviewed Mechanical sparing philosophy defined Equipment preliminary data received Preliminary Instrument Index Plot Plan IFR RECEIVED

    Heat and material balance completed Vendor list approvedHazardous equipment location analysis

    completedCivil input for Plot Plan IFR Instrument tagging procedure Process input to area classification received

    Major equipment identified and preliminary

    sizing

    Process data/rouph equipment datasheets

    completed

    Civil/Structural input (

    ditches,roads,drainage,geotechnical, etc.)Preliminary site grading P&ID's IFD received

    Control phylosophy udentified and

    preliminary sizing

    Critical equipments shop fabrication

    milestone identified

    Electrical and instrumentation layout input

    received

    Process input on fire water system and

    drainage receivedInline device data sheets IFR Load list - IFD

    Control Phylosophy decided ( Including

    DCS, PLC etc.Client infrastructurerequirements identified Fire water system layout Area classification IFR received P&ID's IFD received, horsepower defined

    Material selection guideline issuedEquipment data sheets-IFQ/Equipment list -

    IFDConstruction input received Sewers/drainage system layout Pipe specifications received Equipment list - IFD received

    Preliminary tie-in pointsidentifiedMDMT and other temperature design criteria

    defined

    Logistics and Shipping constraints study

    receivedMajor equipment preliminary size received Process and Equipment data received Preliminart electrical vendor information

    Modularizationstrategy received

    Plot Plan - IFD

    Preliminary utility balance MSD's - IFD Spacing guideline/Codes received Control systen I/O Index defined Lighting load estimated

    VIP review and simplification completed PFD's-IFD received Plot Plan - PFD Main pipe racks preliminary sized Control system architecture development Heat tracing load estimated

    P&ID's IFR receivedField survey of geometer reference points

    receivedPreliminary large bore pipe layour received

    Shut-down key matrix ( cause and effects)

    generated from indexAll electrical load defined

    DBM (FEED) items Preliminary hydraulic calculations completed Main pipe racks sizedConstruction and Operational access and

    egress studied

    Package equipment instrument

    specifications issued

    Winterization philosophy decided Plot-plan - IFR receivedModularization execution plan ( racks, etc )

    establishedLay down areas identified Single Line Diagrams IFD

    Start-up/Shutdown philosophy published Sparing philosophy and spare parts definedEquipment datasheets (esp, compressors,

    pumps etc) receivedCable tray routing identified Purchase inline devices Modularization strategy defined

    Preliminary drivers identified Area classification drawing - IFD received P & ID's IFR receivedTransportation, lifting and logistic issues

    definedVendor list approved Eletrical Equipment datasheets IFD

    Process datasheets finished Modularization plan defined Material selection diagram received Process hydraulic calculation received Scope and Specification finalized

    Process hazard analysis completed Battery limit conditions defined Piping studies for critical lines Civil Input for Plot Plan ifd Piping specifications IFD received Electrical bidders list approved

    Process logic discription finished Specification and standards issued Fire hazards areas defined Major building (size, location)finalized Final process data provided to instruments

    data sheetsElectrical control schematics IFD

    Preliminary material selection digram

    issued

    Packaged equipment instrument spacs

    issuedPlot plan client review approval

    Major pipe racks and large bore piping

    design frozen ( including stress design)Area classifications IFD received Electrical control pjhilosophy issued

    Piping material classes published P & ID's IFD receivedUnderground scope, location and services

    identifiedClient review and approval of datasheets

    Mechanical vendor information/packed

    equipment information received

    Stream information firm Equipment issued for purchase All undergrounds receivedElectrical underground, aboneground

    substation information receivedBidder's specifications/vendor data IFD Variable frequency drive requirement defined

    Drafp DBM for reviewAll equipment data sheets issued for

    purchaseHydro test phylosophy defined

    Preliminary vendor data (major vessels,

    equipment )receivedSparing philosophy finalized

    Client/opetations input received Vendor quotes ( data drawings ) finished Major equipment coordinates frozen Access/ egress finalized and confirmed Control system purchase Vendor list approved

    Front-end PFD Frozen Shop fabrication schedule Major cable routing frozen I/O count / loop drawings IFD Area clarricication IFD

    Process flow diagram - IFD Technical evaluation finalized Plot plan - IFC Major equipment coordinates received Shutdowm keys IFC

    DBM Document issuedCommercial review input (bid summaries ,

    reccomendations client approvalFinal vendor dimensional data collected

    Preliminary mechanical equipment loads (

    static and dynamic) and GA's received

    Marshalling Philosophy issued and

    approved Cable and Tray Schedule IFC

    General arrangement - PFD Building sizing and layout receivedPreliminary electrical equipment loads and

    G.A's receivedControl system hardware footprint defined Cable tray routing/location defined

    P&ID's and UFD's - IFR Hydraulic calculations finalizedFinal civil, road and drainage drawing

    received

    Preliminary piping drawing (rack,

    underground stress )receivedPanel layouts / termination issued Plot plan IFC received

    Mechanical equipment identification and

    sized

    Logistics input - lifting,

    transportation,routing,receiving and storageHeat trading LTD's IFD

    Pollution abatement ( equipment and

    facilities definedElectrical equipment layout IFC

    Discipline - Specific specification and

    standards publishedClient operation and maintence review Inline components defined Loading diagrams defined Control room layout IFD Control systems layout IFC received

    Battery limit tables finishedCommissioning support - review of spare

    parts, training process and vendor supportLarge bore stress analysis completed All juction box lacations defined

    All tie-ins identifiedLarge bore piping design and layout

    completedRough Grading Plan IFC Instrument Index - IFC

    Certified packaged equipment Electrical data

    received

    Lines -sized specified Vendor certified data Utility piping definition copleted Logic/control narratives received Piping layout and/3D Model completed

    Relief requirements identified Equipment list finalized Electrical single line IFD received Deep underground IFC FAT procedures and test plan defined Single line diagrams IFC

    Major instrument list commenced Data lists finalizedElectrical, I & C Cable trays requirements

    and data receivedP&ID's IFC received

    Other systems defined (CCTV, fire systems,

    LAN). Third party input completed

    Major valves identified Vendor data finalized Input of plot plan - IFC All I&C Purchase orders issued

    Major control valves identified and sized Scope of specification finalized Tie - in list IFC Electrical Heat Tracing ISO''s

    Licencer P&ID reviewed Start-up and commissioning plan defined P& ID's - IFC received Pilling - IFC FAT Piping ISO's IFC received

    Pressure relief valves preliminary sized LTD's IFC's received Structural pipe rack model All graphics built MSO Material Selection Diagram

    HT- & I requirements identifiedPre-Commissioninf/

    commissioning/Commissioning plan

    Survey of pipe wall thickness - Metallurgy

    receivedPreliminary structural design Configuration completed MTO Material Take Offs

    Manufacturing records ( as built data-

    book,certified perfomance) compiledOperations philosophy received Foundajtions drawings NDE Non Destructive Examination

    P&ID's, UFD's and TD's -IFD Operations manuals finalizedSchedule of plant planned shutdown

    receivedEquipment loads and GA's received GLOSSARY OEM Original Equipment Manufacturer

    Flare and relief calculations and completed OEM supportClient approval for operations and

    engineering

    Underground piping and electrical locations

    fixedDBM Design Basis Memorandum P&ID Process and Instrument Diagram

    All client input completed Large bore pipe stress design frozen CCTV Closed Circuit TV PFD Process Flow Diagram

    Hydraulic calculations finished Final client model/layout reviewInstallation plan (Hoisting and craning

    requirementsdefinedFAT Factory Acceptance Test PRV Pressure Relief Valve

    VIP's implemented as applicable Plot plan IFC FEEDFront End Engineering Design (Includes

    FEL 2 & 3 )SIL Safety, Intergrity Level

    Start - up system defined Large bore piping layout completed Foundations/Sitework Concrete IFC FEL Front End Loading SOC Supplier of Choice

    Shut-down keys defined Large bore stress analysis finishedFinal Mechanical Equipment loads ( static &

    dynamic) and GA's receivedGA Genetal Arrangement UFD Utility Flow Diagram

    Final line sizing by process engineering P&ID's - IFCFinal Electrical equipment loads and GA's

    receivedHAZOP Hazard and Operation analysis IPS Uninterrupted Power Supply

    Final control valve and PRV sizing All hydraulic calculations completedPiping drawings IFC (

    rack,underground,stress) receivedHT&I Heat tracing and Insulation VIP Valve Improving Practices

    HAZOPP review held Structural - pipe racks modeledAll penetrations and embeds identified by

    other disciplinesHVAC Heating, Ventilation, Air Conditioning

    SIL review held ( if applicable) Equipment modules design finalizedVendor package equipment loads and GA's

    CERTIFIEDIFC Issued for Construction

    Vendor data received Building design IFD IFD Issued for Design IPA Definitions

    P&ID's IFC Electrical tray modeled IFQ Issued for Quotation

    Final equipment list applicable Clash analysis completed Structural steel IFC IFR Issued for Review

    Detailed vendor's information (Specification

    sheet,datasheet,auxilaries,utitilities) receivedConstructability review completed

    pIping drawing IFC (RACK,

    underground,stress)IPA Independent Project Analysis Inc. IPA Definitions

    HAZOP issued resolvedOperations and Maintenance (O & M) review

    completedHVAC Drawing IFC ISO Isometric Drawings FEL 1 (Block Flow)

    Vessel levels finalized (Operations &

    Elevations)IFC line list completed Mechanical drawings IFD LAN Local Area Network FEL 2 ( Process Flow)

    Critical small bore piping (high

    pressure,Toxic, utility/tracing etc. identified

    and mideled

    Final electrical epuipment load and gas

    receivedLDT Line Designation Table FEL 3 ( P & ID's)

    Operating guidelines defined Inline componenets includedVendor package equipment loads and GA's

    certifiedMDMT Minimum Design Metal Temperature Detailed Design

    Commussioning/Start-up assistance

    plannedAll large bore valves indicated Building design IFD

    Location for cable trays identified Small bore piping routing completed

    Secondary supports indicated

    Review Structure Steel Shop Drawing

    First ISO Issue

    Certified vendor equipment drawings

    received\Final Grading and Paving IFC

    Welding hydro equipment drawings received Civil drawing IFC (fencing , signage)

    Welding hydro test and NDE specifications

    IFC

    All piping details and standards IFC

    (Supports, hangers,etc)

    MSD IFC

    MILESTONE CHECKLIST

    Contruction Field Rework: Total direct cost of redoing work in the field regardless of initiating cause of saurce

  • Fabrication philosophy determined (

    field/shop)