midyear report july to december 2012 final reports... · 2014. 9. 12. · city power midyear report...

64
Midyear Report July to December 2012 Final

Upload: others

Post on 19-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Midyear Report

    July to December 2012

    Final

  • City Power Midyear Report – July - December 2012

    Final Page 2

    Table of Contents

    ABBREVIATIONS/ACRONYMS ......................................................................................................................... 4

    CHAIRPERSON’S REPORT ................................................................................................................................ 5

    COMPANY PERFORMANCE REPORT ................................................................................................................ 6

    1.1 ACHIEVEMENTS ........................................................................................................................................ 6 1.2 CHALLENGES ............................................................................................................................................ 6 1.3 TRENDS .................................................................................................................................................. 7 1.4 INTERVENTIONS ........................................................................................................................................ 7 1.5 RISKS AND MITIGATIONS ............................................................................................................................ 9 1.6 DIVISION PERFORMANCE OVERVIEW .......................................................................................................... 11

    2 SERVICE DELIVERY MONITORING ......................................................................................................... 18

    2.1 CITY POWER GDS AND IDP SCORECARD WITH KEY PERFORMANCE AREAS AND INDICATORS ................................. 18 2.2 CITY POWER BALANCED SCORECARD WITH KEY PERFORMANCE AREAS AND INDICATORS ...................................... 19

    3 PROJECT/INFRASTRUCTURE REPORT ................................................................................................... 26

    3.1 ANALYSIS OF THE MASTER CAPITAL PROGRAMME ......................................................................................... 26 3.2 CAPITAL EXPENDITURE DETAILS ................................................................................................................. 26 3.3 FUNDING CLAIMS .................................................................................................................................... 29 3.4 FUNDING SOURCE................................................................................................................................... 29

    4 HUMAN RESOURCES ............................................................................................................................ 30

    4.1 STAFF COMPLEMENT ............................................................................................................................... 30 4.2 STAFF MOVEMENTS ................................................................................................................................. 30 4.3 EMPLOYMENT EQUITY AND AFFIRMATIVE ACTION PLANS AND PROGRAMMES ...................................................... 30 4.4 SKILLS DEVELOPMENT PLANS .................................................................................................................... 31 4.5 STAFF VERSUS COST OF STAFF TO TOTAL OPEX .............................................................................................. 32 4.6 EMPLOYEES WELLNESS PROGRAMME ......................................................................................................... 32 4.7 THE MANAGEMENT OF HIV/AIDS IN THE WORKPLACE ................................................................................... 33

    5 PROCUREMENT POLICIES AND PRACTICES ........................................................................................... 33

    5.1 BROAD BASED BLACK ECONOMIC EMPOWERMENT ....................................................................................... 33 5.2 EXPANDED PUBLIC WORKS PROGRAMME .................................................................................................... 34

    6 FINANCIAL REVIEW .............................................................................................................................. 35

    6.1 INCOME STATEMENT ............................................................................................................................... 35 6.2 STATEMENT OF FINANCIAL POSITION .......................................................................................................... 39

    6.3 CASH FLOW STATEMENT ..................................................................................................................... 42

    7 RISK MANAGEMENT ............................................................................................................................ 43

    7.1 BACKGROUND ........................................................................................................................................ 43 7.2 UPDATE ON RISK MANAGEMENT PROCESS .................................................................................................. 43 7.3 MONITORING AND REPORTING .................................................................................................................. 43 7.4 AUDITING ............................................................................................................................................. 43

    8 FLEET ................................................................................................................................................... 46

    8.1 THE UTILISATION OF VEHICLES ................................................................................................................... 46 8.2 THE SIZE OF THE CITY POWER FLEET............................................................................................................ 46 8.3 FLEET CONTROLS .................................................................................................................................... 46 8.4 HIRING OF FLEET FROM PRIVATE SECTOR COMPANIES (AVIS & EQSTRA) .......................................................... 46

  • City Power Midyear Report – July - December 2012

    Final Page 3

    8.5 FRAUD AND THEFT IN RESPECT OF FUEL ....................................................................................................... 46

    9 GOVERNANCE ...................................................................................................................................... 47

    9.1 BOARD MEETINGS .................................................................................................................................. 47 9.2 DIRECTORS AND TOP MANAGEMENT REMUNERATION ................................................................................... 47 9.3 BOARD FUNCTIONING AND FINANCIAL MANAGEMENT ................................................................................... 49

    10 LEGISLATIVE ......................................................................................................................................... 50

    10.1 NERSA ................................................................................................................................................ 50 10.2 COMPLIANCE WITH NRS 047 ................................................................................................................... 50 10.3 COMPLIANCE WITH NRS 048 ................................................................................................................... 50

    11 KEY ISSUES WITH RESPECT TO THE AUDIT COMMITTEE ....................................................................... 51

    11.1 STATUS OF FIXED ASSET REGISTER ............................................................................................................... 51 11.2 MATTERS AFFECTING THE AUDIT REPORT ..................................................................................................... 51 11.3 OTHER IMPORTANT MATTERS .................................................................................................................... 52

    1. ANALYSIS OF INTERNAL BUSINESS PROCESSES .................................................................................... 54

    12.1 CUSTOMER RELATIONS MANAGEMENT (IF APPLICABLE) .................................................................................. 54 12.2 SAFETY AND SECURITY STRATEGY ............................................................................................................... 54 12.3 SAFETY, HEALTH, ENVIRONMENT AND QUALITY ............................................................................................ 55 12.4 DISASTER MANAGEMENT ......................................................................................................................... 55 12.5 OPERATIONAL POLICIES AND PROCEDURES ................................................................................................... 55

    13. EXERCISE OF SPECIFIC DELEGATIONS ................................................................................................... 56

    13.1 ATTENDANCE OF TRAINING COURSES .......................................................................................................... 56 13.2 CANCELLED CONTRACTS ........................................................................................................................... 57 13.3 CONTRACT MANAGEMENT ....................................................................................................................... 57

    14. CONCLUSION ....................................................................................................................................... 57

    15. APPENDIX ............................................................................................................................................ 58

    15.1 EMPLOYMENT EQUITY REPORT ......................................................................................................... 58

  • City Power Midyear Report – July - December 2012

    Final Page 4

    ABBREVIATIONS/ACRONYMS

    Abbreviation/ Acronym

    Explanation/ Description

    AA Affirmative Action

    ABC Aerial Bundled Conductor

    ADMD After Diversity Maximum Demand

    AFS Annual Financial Statement

    AG Auditor General

    AMR Automated Meter Reading

    AMI Automated Meter Infrastructure ( Smart meter)

    BBS Behaviour Based Safety

    BBBEE Broad Based Economic Empowerment

    Capex Capital Expenditure

    CCMA Commission for Conciliation, Mediation and Arbitration

    COJ City of Johannesburg

    DIFR Disabling Injury Frequency

    DoE Department of Energy

    DSM Demand Side Management

    EAP Employees Assistant Programme

    EPWP Expanded Public Works Programme

    EWSETA Energy and Water Sector Education and Training Authority

    FY Financial Year

    GDS Growth and Development Strategy

    GRAP Generally Recognised Accounting Practice

    HR Human Resources

    HV High Voltage

    IBT Inclining Block Tariff

    IDP Integrated Development Plan

    ISO Internal Organisation for Standardization

    JMPD Johannesburg Metro Police Department

    KPA Key Performance Area

    KPI Key Performance Indicator

    LPU Large Power User

    MD Managing Director

    MDMS Master Data Management System

    MOE Municipal Owned Entity

    MRQC Meter Reading Quality Control

    MV Medium Voltage

    MYPD Multi Year Price Determination

    NERSA National Energy Regulator of South Africa

    NHIL Noise Induced Hearing Loss NRS National Rationalised Standards

    OPEX Operating Expenditure

    R&CRM Revenue and Customer Relationship Management

    RAC Risk Assurance and Compliance Department

    RAT Remote Access Terminal

    RNC Revenue Nerve Centre

    SABS South African Bureau of Standards

    SAP System Application and Production in Data Processing

    SCM Supply Chain Management

    STEP Service Delivery, Transformation, Excellence, Performance

    SHEQ Safety Health Environment and Quality

    SLA Service Level Agreement

    SWH Solar Water Heating

    USDG Urban Settlement Development Grant

    VDO Vehicle Display Output

    YTD Year to Date

  • City Power Midyear Report – July - December 2012

    Final Page 5

    Chairperson’s Report The first six month of the 2012/13 financial year results of City Power show continued efforts to meet and exceed the expectations of our shareholder as reflected in the service delivery objectives in our company scorecard. The appointment of the Managing Director (MD) for the organisation was finalised. Sicelo Xulu, who has been acting in this position since November 2010, has been appointed as City Power MD from 1 September 2012. The Board has also approved a structure that will support the MD in his endeavours. The appointment and the structure will ensure continued business stability, sustainability and improvement. The strategic priorities of the City of Johannesburg, as the sole shareholder of City Power, drive strategic direction of the company and significant attention is given to ensure that these priorities are implemented in the form of measurable targets and deliverables. The strategic priorities of the City of Johannesburg are contained in the Growth and Development Strategy (GDS) and in the Integrated Development Plan (IDP) of the City of Johannesburg. The first six months have been marked with several achievements on our sustainability journey. City Power has received level 3 Broad-Based Black Economic Empowerment (B-BBEE) status level and disability representation is 3% which is above the National guidelines. There has also been a general improvement in employee safety standards thus there have been no employee fatalities at City Power for the past three years. The company has maintained a DIFR that is below the international standard. An improvement in service delivery has been seen through the organisation exceeding its targets on installation of Solar Water Heating. To achieve our vision statement “To be a world-class electricity distributor” requires long-term planning that takes into account the complex interplay of economic growth, demographic shifts, transmission requirements, protection of the environment by shifting to low carbon infrastructure, improving revenue management and cost recovery. The organisation‟s efforts to improve service delivery and its processes have been recognised by the South African Bureau of Standards (SABS) that has awarded City Power their President‟s Award. Unfortunately City Power has attained a qualified audit for the 2011/12 financial year. However the organisation has put interventions in place to address the qualification, other matters and challenges faced by the company. These interventions are called the STEP Program. This program has 10 targets for the organisation to achieve within the next 3 years to improve service delivery and ensure continuous improvement. In conclusion, City Power will tackle these projects with determination and with the benefit of strong support from our shareholder – the City of Johannesburg. The Board and Management remain committed to continuous improvement in attaining strong financial and operational results and contributing to the vision of a world-class electricity distributor. The strategic priorities of the shareholder, as always, drive our tactical plans. The Board and Management are committed to ensuring good corporate governance and transparent compliance to legislation while delivering an improving, sustainable and reliable service. City Power‟s progress equates to that of City of Johannesburg‟s advancement. In this regard City Power‟s success is crucial.

  • City Power Midyear Report – July - December 2012

    Final Page 6

    COMPANY PERFORMANCE REPORT

    1. EXECUTIVE SUMMARY This report presents the performance of City Power for the first six months, from July to December 2012. The report is divided into sections that cover all operational functions of the company in line with its strategic objectives. City Power has had a mixed performance for the first six months of the 2012/13 financial year. City Power operates in a fairly complex & challenging environment with competing stakeholder expectations, priorities and various operational challenges. Below are some of the organisation‟s major achievements and challenges for the six months.

    1.1 Achievements The organisation has significantly reduced HV outages by using condition monitoring and live-line technology. This is to be expected, as the organisation took a strategic decision to spend most of its Opex and Capex to strengthen and expand its HV network. In contrast, there is a need for more improvement on MV and LV performance.

    Another example of mix performance can be seen in the organisation‟s safety records. Electricity is a very dangerous commodity to work with. For this reason, City Power has always prioritised SHEQ in doing its business. This is evidenced by the following:

    attainment of injury free man hour milestones,

    maintenance of the DIFR below threshold of less than 1 (actual 0.45) and

    no employee fatalities for the six month reporting period.

    This is contrasted by three public fatalities that have happened in the last six months. These fatalities are mainly as a result of illegal connections, thus the company is engaging various stakeholders to combat this situation, including conducting community awareness campaigns to educate the community on the dangers of electricity. Below are some more of the organisation‟s major achievements for the first six months of the 2012/13 financial year:

    Operationalisation of the Board approved structure and establishment of RAC and Retail‟s Services Groups to ensure improvement in service delivery and to address the audit qualification.

    Installation of 22710 solar water geysers in various areas including, Alexandra (5480), Devland (4860), Lehae (3149) and Tshepisong (4350).

    City Power is the winner of the SABS President‟s Award 2012 in recognition of the organisation‟s efforts to improve service delivery and its processes.

    1.2 Challenges Four major challenges have been identified in this financial year. City Power has put mitigations in place to overcome the challenges below:

    The target for midyear was not met; total losses are 22.7% against original budget of 12%. An integrated plan has been developed and will be finalised after incorporating the roll-out of smart meters, installation of RATS and protective structures. Appointed contractors are

  • City Power Midyear Report – July - December 2012

    Final Page 7

    being engaged in finalising the roll-out plan. City Power has also embarked on Zero Based Budgeting and the new losses budget will be used after final approval of budget revisions.

    Reading of meters consistently on a monthly basis is still a challenge. The biggest challenge is getting access to customer‟s properties. City Power has appointed contractors to move meters from inside the properties to the boundary for ease of access. The implementation plan will be finalised and integrated with the smart meter roll-out, with priority being given to meters unread for periods longer than 3 months.

    Three (3) public fatalities occurred in the first six months of the FY. City Power is engaging various stakeholders to combat this situation and conducting community awareness campaigns to educate the community on the dangers of electricity.

    The following mitigating actions are being taken to reduce theft and vandalism: o Replacing overhead copper cables with Arial bundle Cable (ABC), which has less

    copper content o Filling trenches with concrete (makes it difficult for criminals to dig underground

    cables) o Anti-cable theft awareness, by visiting SMD‟s (scrap metal dealers) in the

    surrounding areas and engaging with the local community o Coordination and support initiatives are on-going with other law enforcement

    agencies. 1.3 Trends

    Continuous improvement in employee safety programs. The last employee fatality was in 2009.

    1.4 Interventions To address the challenges and to ensure continuous improvement in the organisation, under the leadership of the MD and the Board, City Power has identified the STEP Program. The STEP program is aligned to what the Executive Mayor said about changing course: “It is about making a conscious decision not to retrofit the old in the Growth and Development Strategy (GDS), but adopting new and ground-breaking methods and initiatives fitting for a World Class African City.”

    1.4.1 10 STEP Programme The ten projects that have been identified as part of the STEP program and their status are outlined below:

    Status Symbol

    Definition Status Symbol

    Definition Status Symbol

    Definition

    On track to be completed by proposed completion date

    Behind schedule, but will catch up to reach proposed completion date

    Behind schedule

  • City Power Midyear Report – July - December 2012

    Final Page 8

    Business initiative Project Stream Status Comments

    Attaining an Unqualified audit in a sustainable

    manner

    Revenue Audit

    Internal Audit Controls City Power has received a qualified audit report for the 2011/2012 financial period. There is a plan and on-going action to address the qualification and other matters. Monthly monitoring and approval of audit reconciliation is done.

    Reduce losses to 10%

    by December 2015 Revenue Step Change

    The target for midyear was not met; total losses are 22.7% against original budget of 12%. An integrated plan has been developed and will be finalised after incorporating the roll-out of smart meters, installation of RATS and Protective structures. Appointed contractors are being engaged in finalising the roll-out plan

    Achieving 98% meter reading by June 2013

    (100% Compliance to the by-law)

    99% Meter Reading AMR LPU customers

    95% AMR and Manual Meter Reading for Domestic customers

    98% Domestic AMR

    This is an on-going process through the meter reading auditors; progress has been seen on improved meter reading performance. For AMR LPU Metering is currently finalising the assessment and ordering of equipment for all faulty meters. Fixing of meters and its ancillaries will commence during the 3rd quarter.

    AMR LPU Customers 75.71%

    Domestic AMR 80.61%

    Manual Meter Reading Domestic 82.62% A meter reading war plan has been developed.

    Achieving 100% payment level for key

    and LPU customer by June 2013

    100% payment level

    The payment level is 87.54% year to date for all customers; City Power is working with R&RCM to separate Key and LPU customer payments, which will be done by the 3

    rd quarter for reporting purposes

    City Power has started with the analysis of collectable and non-collectable debt. Focus will be placed on ensuring that queries are cleared and collectable debt‟s customers are cut-off

    Achieving 90% data accuracy by 2015

    Data Governance

    Customer domain

    Employee domain

    Network domain

    A collaboration committee has be established with CoJ to resolve data issues relating to billing, meter installation and maintenance. Completed the initial desktop analysis of 498 314 records, to resolve AG findings relating to customer data completeness and services provided

    Installing 100 000 SHW

    December 2016 Energy mix

    Megawatts reduced

    In the last six months City Power has installed 22710 SWH, including 3149 in Lehae, 4860 in various areas including, Devland, 4350 in Tshepisong and 5480 in Alexandra. The project is ahead of the target.

    Achieving full compliance to NRS 047

    and 048 immediately

    NRS 047 Frequency of meter reading - Meter reading performance has improved from 75.33% in June 2012 to 81.02% in December 2012. Number of unread meters in the last quarter has dropped from 64 078 to 50 976

    Disconnection and reconnection – All disconnections and reconnections received were actioned according to the NRS standards

    Account queries – Query resolution year to date is 65% as compared to the target of 95% but it should be noted that this is a consolidated figure for all MOE‟s. A request for only electricity related queries has been forwarded to R&CRM.

    Meter Accuracy queries – There is no standard report, engagements with R&CRM have commenced to develop a report.

  • City Power Midyear Report – July - December 2012

    Final Page 9

    Business initiative Project Stream Status Comments

    Customer complaints – Service Level Agreement has been finalised, which will assist in managing performance effectively.

    Customer enquiries – A Service Level Agreement has been finalised, which will assist in managing the performance effectively.

    Customer requests – A Service Level Agreement has been finalised, which will assist in managing performance effectively.

    Call Centre performance - Service Level Agreement has been finalised, which will assist in managing performance effectively.

    Call Centre Availability - R&CRM has increased Call Centre capacity

    On restoration time - three out of the four restoration targets achieved.

    NRS 048 100% compliance to NRS 048.

    Achieving 90:10 Planned: Unplanned by

    December 2015

    Power Outages

    Restoration Times

    48:52 planned:unplanned outages for the midterm was recorded. City Power has not met the target of 70:30 for the year due to an increase in unplanned work during the summer months. This was mainly due to adverse weather conditions.

    Accelerated Visible Service Delivery.

    100% compliance to the SLA,

    A Service Level Agreement has been finalised, which will assist in managing performance effectively. City Power will ensure that all Key Performance Indicators are monitored and reported on regularly.

    Electrification,

    Public Lighting

    1532 houses have been electrified and 1964 public lights have been installed to date. The company will attained its annual targets.

    Institutional renewal

    Structure alignment

    HR Optimisation

    The organisational structure has been approved by the Board and communicated to all staff. The organisation is currently aligning to structure.

    Innovative Product Pricing by 2015

    Introduction of Domestic Time of Use

    Green Tariffs

    The study is currently underway to ensure proper introduction of Domestic Time of Use and green tariffs.

    1.5 Risks and Mitigations The organisation has identified 13 top risks and these are being closely monitored.

    Risk Description Current controls Actions to improve management of the risk

    1 Poor Revenue Collection 1. Conversion from conventional to pre- paid /smart meters 2. Manage the Service Level Agreement with the City. 3. Management of customers in segments with R&CRM

    1. Continuous management of the SLA. 2. Conversion from Conventional to Pre-Paid Meters. 3. Need to segment customers and reintroduce the key customer exec.

    2 Cable theft 1. Improved security in hot spot areas. 2. Implemented Crime Intelligence systems. 3. Crime prevention strategy in place. 4. Implementation of crime prevention technologies.

    Review additional prevention strategies: 1. Replacing overhead copper cables with Arial

    bundle Cable (ABC) which has less copper content

    2. Filling trenches with concrete (makes it difficult for criminals to dig underground cables)

    3. Anti-cable theft awareness by visiting SMD‟s (scrap metal dealers) in the surrounding areas and engaging with community

    4. Coordination and support initiatives are on-going with other law enforcement agencies.

  • City Power Midyear Report – July - December 2012

    Final Page 10

    Risk Description Current controls Actions to improve management of the risk

    3 Customer dissatisfaction. 1. Manage SLA with the City. 2. Working with City to improve processes. 3. Internet faults logging system. 4. BC Forums.

    Reviewing value chains.

    4 High primary energy pass through costs.(OCGT & KPS)

    1. Strict control over PPA and penalties on poor delivery. 2. Hold monthly meeting with Kelvin Management. 3. Limited provision for the gas turbines in the current budget.

    1. Explore additional funding for the gas turbines. (e.g. Off-takers) 2. Engage with 3rd parties to buy power at the cost of generation.

    5 Business's inability to fund high capital and operational requirements out of current cash flows nor future tariff applications

    1. Revenue Generating projects 2. PPP initiatives 3.Sourcing additional Grant Funding

    1. Exploring the off Balance Sheet Arrangements with Funding institutions. 2. See additional grants from National Treasury and other departments.

    6 Non availability and reliability of Information & communication technology (ICT).

    Currently reviewing and updating the Information security policies and the Disaster recovery strategy

    1. Programme to align to King III recommendations. 2. Review and strengthen the current controls. 3. Modernising and upgrading infrastructure.

    7 Fraud & Corruption 1. A fraud Policy has been introduced. 2. A fraud & corruption prevention plan is in place. 3. An illustrative list of strategic fraud risks is in place.

    1. Awareness campaigns on anti-fraud and corruption.

    8 Qualified audit report. 1. Practicing good governance 2. Actively addressing all issues raised in the previous year's Management Report.

    1. Alignment with King lll requirements. 2. Continue to comply with legislation. 3. Implementation of GRAP 4. Integrated Reporting 5. Staff Development

    9 Increase in non-technical losses

    1. Installation of semi AMR, Tamper proof meters and pre-paid meters with protective structures; 2. Removal of illegal Connections and replaced with tamper proof meters with protective structures. 3. Currently utilising JMPD & SAPS to enforce by-laws. 4. Continuous installation audits; 5. Customer education programs;

    Continue with present controls and monitor the effectiveness.

    10 Network interruptions 1. Maintenance & Capital Investment program in place. 2. Asset Management system in place. 3. Crime prevention strategy in place.

    Introduction of condition monitoring project and continue to review additional crime prevention strategies

    11 Inadequate capacity to meet the demand. (Eskom & Kelvin)

    1. City Power has applied for increased capacity from Eskom. 2. Investigating distributed generation options. Implementing DSM Program. Resuscitate Gas Turbines.

    1. Investigating alternative sources of energy e.g. 2. Piloting Solar Powered Streetlights.

    12 Potential impact of HIV and Aids on the workplace and the Business

    1. On-going awareness and education 2. Roll out of planned interventions to address the areas identified e.g. Prevalence study, Cost impact analysis, etc

    1. On-going HCT's 2. Cost impact analysis 3. Stringent disease management. 4. Intervention projects such as education & awareness 5. Enhanced HIV/Aids Policy

    13 Lack of focused development of key skills

    1. Focused and targeted skills development interventions. 2. Increase the number of workplace coaches

    1. Improve needs analysis process - use of Group Skills Plan, 2. Develop and implement annual training calendar 3. Implement controls and reporting measures 4. Increase number of workplace coaches and mentors 5. Implement succession planning

    City Power will ensure continuous business performance improvement and will continue to meet and exceed the expectations of all our stakeholders.

  • City Power Midyear Report – July - December 2012

    Final Page 11

    1.6 Division Performance Overview City Power has Seven Divisions as per the new board approved structure that is outlined below:

    Some of the performance highlights per divisions are outlined below:

    1.6.1 Retail Services

    Interventions o Initiated a metering call centre to deal with unread meters o Initiated disconnection of inaccessible meters not read for more than 3 months

    Achievements o Overall meter reading performance has improved from 75.33% in June 2012 to 81.02%

    in December 2012 o Improved collection levels for November and December 2012 o Non-technical losses for December are below budget.

    Challenges and Mitigations Challenges Mitigation

    1 Streamlining operational relationship with R&CRM

    Planned Integration meetings will be held on monthly basis with R & CRM

    2 System updates not updated on time

    On-going performance meeting are held with R&CRM to discuss progress on job cards submitted

    3 IBT queries – negative publicity Ongoing communication to teach customers about IBT. For the future, there will be a review of how IBT is being implemented.

    4 High number of unread meters due to access, faulty and incorrect data

    Action faulty meters timeously

    Relocation of inaccessible meters to the boundary

    Ensure accurate meter data per serviced stand

    5 Escalated Queries City Power to have access to CRM system to log queries

    6 Debt increase Analysing the debt into collectable, pending investigations and possible write-off.

    Analysed debt will be segmented to customer category and priority will be given to managed accounts

  • City Power Midyear Report – July - December 2012

    Final Page 12

    Trends o Payment level is still below target year to date however we have noticed an

    improvement in collections for November and December. o Call centre performance is not improving

    Risks and mitigations

    Risks Mitigation

    1 Unqualified audit opinion Plan to address unread meters.

    2 Non-compliance to NRS 047, by laws and Customer Charter

    Monitor and Report compliance on a monthly basis

    Engaging affected departments

    Improve City Power visibility to all stakeholders

    3 Revenue completeness SAP CoJ and MRQC Monthly Reconciliation are being done

    Serviced stands meter audit completeness

    1.6.2 Engineering Services

    Interventions o As part of City Power‟s institutional renewal project and the maintenance strategy

    journey map to progress from reactive to preventative maintenance a new Plant Condition Monitoring section has been created within the Engineering Services group. The primary function of this section will be to undertake the condition monitoring of all components forming part of the electricity supply chain. The components to be monitored will be overhead lines, major substations, the distribution networks, secondary plant and public lighting.

    o Normalization of prepaid meters including installation of remote monitoring system and protective structures

    Achievements o Installation of 22710 solar water geysers in various areas including, Alexandra (5480),

    Devland (4860), Lehae (3149) and Tshepisong (4350). o A total of 1532 households have been electrified during this period.

    Challenges o Timeous delivery of equipment such as smart meters and protective structures. This is

    resolved by staying in contact and applying pressure on suppliers for timeous delivery. o Finalisation of the new structures and identifying funding for filling of positions.

    Trends o Theft and vandalism of new infrastructure which result in delaying of projects

    Risks and mitigations Risks Mitigations

    1 Shortage of critical material Engage with Suppliers through SCM

    2 Filling of new structures Reallocation of funding

    3 Theft and vandalism of the network infrastructure and electricity

    Expedite the AMI, AMR and protective structures projects

  • City Power Midyear Report – July - December 2012

    Final Page 13

    1.6.3 Engineering Operations

    Interventions o In order to address the shortage of Appointed Operators the policy document, governing

    the training and authorisation of personnel, has recently been updated and amended. The revised policy document contains proposals to review the allowances paid to Authorised Operators and it is anticipated that this will attract additional candidates for training and final authorisation

    o In support of the company‟s initiative to contain unnecessary expenditure, measures to improve management of Opex spending, particularly in the Salary and Allowances category have been introduced and the results to date have been positive.

    o It has been recognised that there is an urgent need to substantially improve the process of plant condition monitoring to identify potential failures modes and take corrective action prior to actual plant breakdowns. As a result a new independent section has been formed to undertake this function. The responsibility to inspect and condition monitor the electrical infrastructure will now fall within the ambit of the Engineering Services Group.

    Achievements o As part of the on-going Service Improvement Initiative the Operation‟s Group has

    undertaken extensive spotting and repair of street lights along the identified main arterial routes and this has proved very successful. In addition, various types of test instruments, to detect early signs of equipment breakdown, have been purchased and successfully utilised as part of the preventative maintenance strategy. This success will be continued by the newly formulated Plant Condition Monitoring Department.

    o The number of HV NPR outages has reduced and is well within the upper limits set in terms of the company compact.

    o There has been a general improvement in employee safety standards and no serious or fatal incidents have been reported. Several depots have achieved notable injury free man hour milestones.

    Challenges o The incidence of theft and vandalism of the infrastructure continues, which has serious

    financial and outage compliance implications. In addition, this has a detrimental and demoralising effect on staff who are continually called upon to repair or replace repeatedly stolen or damaged infrastructure. In this regard City Power has initiated a phased approach for the installation of modern security measures at its installations. City Power is also investigating other security measures to secure its underground cables and overhead systems.

    o There have been an unacceptable number of MV outages which have exceeded the target set for the period. Severe and unpredictable weather conditions have largely contributed to the increase in the number of MV outages. The increase in MV outages is also indicative of an ageing network and it is anticipated that the newly formed Plant Condition Monitoring department will contribute significantly to detecting possible plant failures and actioning appropriate remedial action, before actual outages occur. In addition, City Power is creating a database of approved jointers to improve and control quality. Going forward, capital funding must be identified to replace and upgrade ageing infrastructure.

  • City Power Midyear Report – July - December 2012

    Final Page 14

    o According to the New SLA sign between COJ and City Power a target of 2 days has been set in the current company‟s performance compact for the resolution of street light related complaints. This target is substantially lower than previously and the attainment of this will be challenging. Following the restructure, the challenges surrounding the quick resolution of street lighting complaints will be reviewed and the processes improved.

    Trends o The on-going prevalence of infrastructure theft and vandalism continues and this

    results in unplanned outages, customer dissatisfaction and unsustainable repair / replacement expenditure.

    Risks and Mitigations o Overtime expenditure continues to be of concern. As electricity is an essential service,

    City Power is allowed to exceed the 40 hour legislation limit to provide an acceptable service. However, an initiative to limit the amount of hours worked to align with the forty hours has now being introduced. This has resulted in certain operational difficulties and solutions to these issues must be identified and agreed with management and labour. One such solution is the proposal to introduce a limited shift system and this is presently being negotiated with the relevant parties.

    o There is an urgent need to replace obsolete low voltage overhead mains with modern Aerial Bundled Conductor (ABC) to reduce the number of outages associated with this poorly performing infrastructure. Several projects to begin the phased replacement of these old networks have been included in the Capital Budget program.

    Risks Mitigations

    1 Overtime Expenditure Cap overtime to align with labour legislation and to ensure the wellbeing of our staff. Initiate a process to introduce shift system. The major overtime expenditure is in attending to „No-light‟ complaints, after hours - if our staff do not undertake this work we will use contractors at a higher cost

    2 Infrastructure theft and Vandalism

    Phased installation of modern security systems

    3 Public Lighting resolution times

    More resources allocated to attend to complaints and performance monitored to identify problems in dispatching process

    4 Obsolete low voltage overhead mains

    Phased replacement program to install ABC

    1.6.4 Human Resources

    Achievements o As part of the City Power institutional renewal project and the new Board approved

    structure, a new training department called the Learning Academy was created on 1 December 2012. The purposes of this department are to co-ordinate and administer technical and non-technical training in line with City Power requirements. This will result in a centralised, co-ordinated and structured training function which will enable the Company to control the awarding of funds in a more manageable way

    o City Power has been accredited by EWSETA to perform Cable Jointing training. This is part of the bigger plan. With full accreditation, City Power will be able to render training services to the private and public sectors and generate income

    o Parties to the Local Labour Forum have revised the current Rules of Engagement which manages the relationship between the parties

  • City Power Midyear Report – July - December 2012

    Final Page 15

    o People with disabilities are currently at 3% of the total staff complement

    Challenges Challenges Interventions

    1 No workforce planning in place Human Resources to implement a workforce plan to enable the demand and supply projections for core , critical and scarce segments and the organisation as a whole by June 2013

    2 Skills competencies are not clearly defined in terms of the different occupational categories

    A competency dictionary was developed and approved by EXCO to ensure alignment

    3 The current HR structure does not support the vision of the business

    Human Resources has developed a new structure that will support the vision of the business. The final approval is envisaged by no later than the end of February 2013

    Risks and Mitigations Risks Mitigations

    1 Excessive overtime spend Strict controls have been put in place to curb overtime expenditure

    2 Non-payment of the 50th percentile for

    grades 13 and above The matter is currently being discussed at the Local Labour Forum level

    3 Non-payment of gratuity / performance bonus for certain categories of employees which may lead to a dispute being declared at the CCMA

    Human Resources is in the process of consulting Legal Services on the handling of the matter and will make recommendations to EXCO

    1.6.5 Finance

    Achievements o Board approval of the zero based budgeting approach for City Power o Training of cost centre owners on zero based budgeting principles o 2011/12 FY asset register has been updated o Enhanced reporting format for financial performance o The creation of a Reverse Logistics plant in SAP has enabled the complete separation

    of usable stock from unusable stock.

    Challenges Interventions

    1 Finalisation of asset register on SAP The reconciliation of the asset register is in progress.

    2 Inability to fill vacancies Interviews are held currently to ensure that all critical vacancies are filled by the financial year end.

    3 Poor availability of materials; particularly luminaires.

    Weekly reporting. In the process of transferring responsibility for call-off purchase orders to Inventory Management.

    4 SAP MM is not designed to maintain a unique value for each inventory item.

    Development of a solution is in process.

    5 The in-house manufacturing solution has resulted in incorrect stock valuations.

    The cause is being investigated.

  • City Power Midyear Report – July - December 2012

    Final Page 16

    1.6.6 Risk, Assurance and Compliance

    Interventions o Development of an Integrated SHEQ Management System which includes the current

    accreditation and the following: SANS 16001:2007 (Health Management System) ISO 31000 (Integrated Risk Management System) ISO 22000 (Food Safety and Hygiene Standards)

    o Development and implementation of data governance policies, standards and procedures for customer, employee, network and regulatory data domains

    o Development and implementation of a Customer Data completeness project (data collection and verification of all stands serviced by City Power)

    o Initiating an enterprise wide data clean-up o Development and implementation of a security strategy and system to combat theft

    and vandalism o Development and implementation of a comprehensive employee wellness program

    Achievements

    o City Power was the winner of the SABS President‟s Award for 2012

    o Maintained ISO 14001:2004 and OHSAS 18001:2007 certification during the surveillance audit November 2012

    o Successful hosting of World Aid Days and 16 Days of Gender Based Violence Commemoration

    o Received Waste licenses for rubble waste collection and disposal, for three City Power Trucks

    o Maintaining DIFR below threshold of 1 (actual 0.45)

    o Established a Data Governance and Compliance department

    o Established a collaboration committee with CoJ to resolve data issues relating to billing, meter installation and maintenance

    o Completed the initial desktop analysis of 498 314 records to resolve AG findings relating to customer data completeness and services provided

    392 134 resolved with desktop analysis

    106 180 scheduled for physical site audits

    14429 properties physically audited from mid-September to December as part of the data completeness project

    Challenges

    o Maintaining the ISO Certificates (9001, 14001, 18001) and accreditation

    o Review and monitor Disaster Management and develop Business Continuity Plan/s

    o Opportunistic diseases for HIV positive clients

    o Lack of understanding by business stakeholders of importance of data governance o Refused entry to properties and non-disclosure of data by customers o There is a lack of understanding by business stakeholders of the importance of data

    governance due to the decentralised ownership and usage of data. City Power has thus resolved to have a centralised data management and governance environment that will allow data to be centrally governed and provide a single view of data.

  • City Power Midyear Report – July - December 2012

    Final Page 17

    o Due to both safety concerns on the customers‟ part and malicious acts like theft of electricity by customers; customers tend to refuse entry to properties and to disclosure of data. City Power has endeavoured and continues to explain the benefits of providing the required data and the dangers of electricity theft (illegal connections) to customers.

    Trends o General continual improvement in SHEQ culture, due to the implementation of

    Behaviour Based Safety (BBS) (last employee fatalities was in 2009)

    1.6.7 Office of the MD

    Interventions o Implemented the business model review project

    Achievements o Operationalisation of the Board approved structure o Finalisation of the Annual Report (AR)

    Risks and mitigations Challenges Interventions

    1 Maintaining a positive company image

    Implementation of the STEP program to improve service delivery Improve relations with the media and other stakeholders

  • City Power Midyear Report – July - December 2012

    Final Page 18

    2 SERVICE DELIVERY MONITORING

    2.1 City Power GDS and IDP Scorecard with Key Performance Areas and

    Indicators Table 2.1: City Power GDS and IDP Scorecard and Mayoral Flagship Programmes and Enablers

    Key Performance Area

    Key Performance Indicator

    Unit

    Baseline Total Target Quarter 1 Quarter 2 YTD

    2011/12 Actual

    Target Target Actual Target Actual Target Actual

    Improve Network Performance

    and Quality Of Supply

    CAIDI Minutes 368.75 140 140

    240.3 140 234.37 140 237.07

    CAIFI Number 0.08 1.4 1.4 0.09 1.4 0.06 1.4 0.07

    SAIDI Minutes 94.98 110 27.5

    255.91 50 312.29 50 568

    SAIFI Number 0.26 2 0.5 1 1 1.33 1 2.4

    Planned: Unplanned

    Maintenance Ratio 62:38 70:30 70:30

    57:43

    70:30 49:51 70:30 48:52

    NRS 047: Compliance: % Customer Restored within:

    1.5 Hours

    %

    30.51 30 30

    31.5 30 30 30 30.6

    3.5 Hours 73.58 60 60

    67.5 60 75.3 60 71.9

    7.5 Hours 90.96 90 90

    87.3 90 86.6 90 86.9

    24 Hours 98.85 98 98

    99.2 98 99.1 98 99.2

    NRS 048 Compliance

    97 100 100 98 100 100 100 100

    Refurbishment of Aging Network

    Average age of infrastructure

    Years 55 53 45 39 39 39 39 39

    Expansion and Strengthening of

    Network

    Additional Capacity

    MW 40 90 0 0 0 0 0 0

    Provision of public lights

    Number 5164 4200 1000 620 1000 1344 2000 1964

    Revenue Step Change: Improve Financial

    Sustainability

    Payment Levels % 92 94 92 83.29 94 96.5 94 87.5

    Meters installed Number New 20000 100 132 1500 1925 3000 2057

    Meter Reading % 98 98 98 76 96 81. 96 81

    Reduction of Area Debt Book

    % 20 50 50 -47 50 0 50 0

    Technical Losses % 9 9 9 9 9 9 9 9

    Nontechnical Losses

    % 8.21 5 2.72 11.42 11.4 16.58 3 13.76

    FBE Maximum

    KWh/ Household

    150 150 150 150 150 150 150 150

    Demand Side Management :

    Reduce Carbon Emissions

    Number of Solar Heaters installed

    Number New 20000

    3000 7200 8000 15510 11000 22710

    After Diversity Maximum

    Demand (ADMD) Kva New 0.12 0.12 0.12 0.12 0.12 0.12 0.12

    Energy Mix % New 0 0 0 1.5 1.5 1.5 1.5

    Energy Efficiency % New 2.3 0 0 0 0 0 0

    Improve Customer Centricity

    EPWP Number 2333 3000 625 598 875 937 1500 1535

    Electrification Number 5610 3200 750 1374 250 158 1000 1532

    Customer Satisfaction

    % 65 70 70 65 70 0 70 0

    Affirmative Action (Supervisory level

    and above) % 79.23 83 83 79.47 83 79.61 83 79.54

  • City Power Midyear Report – July - December 2012

    Final Page 19

    Key Performance Area

    Key Performance Indicator

    Unit

    Baseline Total Target Quarter 1 Quarter 2 YTD

    2011/12 Actual

    Target Target Actual Target Actual Target Actual

    Gender Equity (ALL)

    % 20.91 24 21 22.85 22 22.9 22 22.9

    People with Disability

    % 2.9 2.2 2.2 2.99 2.2 3 2.2 3

    Continuous improvement of

    the Business

    DIFR % 0.51 1 0.5 0.54 0.5 0.54 1 0.54

    ISO Accreditation Unqualified

    Audit Qualified

    Audit Unqualified

    Audit Unqualified

    Audit Unqualified

    Audit Unqualified

    Audit Unqualified

    Audit Unqualified

    Audit Unqualified

    Audit

    Attainment of an Unqualified Audit

    Unqualified Audit

    Qualified Audit

    Unqualified Audit

    Unqualified Audit

    Qualified Audit

    Unqualified Audit

    Qualified Audit

    Unqualified Audit

    Qualified Audit

    2.2 City Power Balanced Scorecard with Key Performance Areas and Indicators

    Figure 2.1 below depicts the company‟s Strategy Map:

  • City Power Midyear Report – July - December 2012

    Final Page 20

    2.2.1 Financial Perspective

    City Power has not done well from a financial perspective and has put interventions in place to ensure improvement going forward these include:

    Non-technical losses are 13.76%; initiatives to reduce losses are continuously actioned which include:

    o Billing completeness monitoring has begun and City Power is tracking unbilled accounts and ensuring that they are linked on the system.

    o Replacement of faulty prepaid meters and installation of protective structures and RATS. Replaced meters are to be commissioned in the 3rd quarter.

    o Plans to install smart meters are being developed and the roll-out is expected to start during the 3rd quarter.

    Payment levels are below target; target is 92% vs. actual 87.56%. To improve this situation, City Power is analysing the debt into „collectable‟, „pending investigation‟ and „possible write-off‟. The analysis will be segmented into customer categories and priority will be given to managed accounts (key accounts, government accounts and corporate accounts) and accounts over 90 days

    Value Propositions

    Key Performance Area

    Key Performance Indicator

    Unit 2011/12 Actual

    Quarter 1 Quarter 2 Year to Date

    Target Actual Target Actual Target Actual

    Sustainable Revenue Growth/ Low Operating Costs

    Effective Financial Management

    Net Profit R‟000 1,413,626 187,416 225,375 562,182 457,398 749,598 682,773

    Gross Margin % 36.22 21.19 23.93 38.82 42.67 28.96 31.88

    Revenue Improvement

    Total Losses % 19.31 11.72 20.42 15.79 25.58 15.79 22.76

    Technical Losses

    % 9.00 9.00 9.00 9.00 9.00 9.00 9.00

    Non - Technical Losses

    % 10.31 2.72 11.42 11.8 16.58 3.0 13.76

    Sustainable Cash Flow

    Effective Financial Management

    Net Cash Flow Position

    R‟000 1,191 1,980 914 2,042 1,495 2,042 1,495

    Improve Revenue Collection

    Revenue Improvement

    Payment Levels – All Customers

    % 92.37 92.00 80.92 92.00 96.52 92.00 87.54

    Reduction of arrear debt

    % New 45.00 0 45.00 0 45.00 0

  • City Power Midyear Report – July - December 2012

    Final Page 21

    2.2.2 Customer Perspective

    City Power has mixed performance in this perspective and has put interventions in place to ensure improvement going forward these include:

    Query resolution year to date is 65% as compared to the 95% but should be noted that it‟s a consolidated report for all MOE‟s. A request for only electricity related queries has been forwarded to R&CRM.

    Value Propositions

    Key Performance Area

    Key Performance Indicator

    Unit

    2011/12 Actual

    Quarter 1 Quarter 2 Year to Date

    Target Actual Target Actual Target Actual

    Quality Service Experience

    Customer satisfaction and responsiveness

    Customer Satisfaction Index Consolidated Customers

    % 65.00 65.00 0 65.00 0 65.00 0

    Quality Service Experience/ Governance

    Regulatory Compliance (NERSA) NRS 047 (Quality of Service)

    CAIDI Minutes 368.73 140.00 240.30 140.00 234.38 140.00 237.07

    CAIFI Number 0.08 1.40 0.09 1.40 0.06 1.40 0.07

    SAIDI Minutes 94.98 27.50 255.91 27.50 312 27.50 568

    SAIFI Number 0.26 0.50 1.06 0.50 1.33 0.50 2.4

    Faults restoration within the specified time frame a percentage of total number of faults reported

    Within 1.5 Hrs % 30.51 30.00 31.55 30.00 29.8 30.00 30.6

    Within 3.5 Hrs % 73.58 60.00 67.54 60.00 75.3 60.00 71.9

    Within 7.5 Hrs % 91.96 90.00 87.34 90.00 86.6 90.00 86.9

    Within 24 Hrs % 98.85 98.00 99.20 98.00 99.1 98.00 99.2

    High Product Availability/ Service Delivery/ shift to low carbon infrastructure

    Regulatory Compliance (NERSA) NRS 048 (Quality of Supply)

    Average age of the network

    Years New 45 39 39 39 39 39

    Quality Service Experience

    Customer satisfaction and responsiveness

    Meter reading performance

    % New 95.00 75.65 95.00 81.0 95.00 81.0

    Socio Economic Development

    Economic Development & Job Creation

    FBE kWh/

    household

    150 150 150 150 150 150 150

    High Product Availability/ Service Delivery/ shift to low carbon infrastructure

    Regulatory Compliance NRS 048 (Quality of Supply)

    After Diversity Maximum Demand (ADMD)

    kVA 0.12 0.12 0.12 0.12 0.12 0.12 0.12

    Energy Mix % New 0 0 1.5 1.5 1.5 1.5

    Energy Efficiency MW New 2.3 0 0 0 0 0

    Positive Company Reputation

    Health and Safety

    Public Fatalities: Controllable

    Number 1 0 0 0 0 0 0

    Public Fatalities: Uncontrollable

    Number 1 0 2 0 1 0 3

    Governance Health and Safety

    Employee job related fatalities

    Number 3 0 0 0 0 0 0

    Socio Economic Development

    Economic Development & Job Creation

    Job opportunities created as per EPWP policy: Temporary jobs.

    Number 2,333 625 598 875 937 1500 1535

    Socio Economic Development/ shift to low carbon infrastructure

    Households with at least basic services

    Number of new electrification customers

    Number 5,610 750 1374 250 158 1000 1,532

    Improve Public Lighting

    Provision of new Public lights in the formal Areas and Informal Areas

    Number 5,164 1,000 620 1,000 1344 2000 1964

  • City Power Midyear Report – July - December 2012

    Final Page 22

    SLA has been finalised, Retail Services is working with R&CRM in ensuring that certain KPI‟s that are currently not reported on are developed and implemented.

    Stakeholder Management department within Retail Services monitors the stakeholder relations and service delivery while ensuring compliance to governance.

    The six month network performance indices (SAIDI, CAIDI, SAIFI, SAIDI) show that City Power has not met all the set targets. The original network performance indices were based on North American standards, which were the only standards available at the time. Experience has shown that this is not suited to a South African climate. City Power is currently busy with a study to determine more appropriate indices. Additionally, severe and unpredictable weather conditions added to the number of unplanned outages and hence affected the indices negatively.

    Below are three public fatalities that happened in the last quarter.

    Date of Incident

    Area where incident occurred

    Name of Deceased

    person Description of incident

    Controllable/ Uncontrollable

    17-Sep-12 Roodetown - Roodepoort

    Unknown male Theft and vandalism Uncontrollable

    17-Sep-12 Prichard Street S/S JHB Town

    Male A contractor fell from a height whilst removing a transformer at the substation

    Uncontrollable – pending investigation

    27-Dec-12 M10 Road and Volta Street in Lenasia

    Unknown female

    Electrocution due to illegal connections, connected to Post Office lines and leading to an informal settlement.

    Uncontrollable

  • City Power Midyear Report – July - December 2012

    Final Page 23

    2.2.3 Internal Perspective

    The month of December 2012 was averaged for the following KPIs:

    Total number of calls answered in 30 seconds as a percentage of calls received

    Number of customer complaints/queries resolved per total queries received SAP CRM

    Average time taken for City Power to resolve queries that are referred to them that require investigation

    Value Propositions

    Key Performance Area

    Key Performance Indicator

    Unit

    2011/12 Actual

    Quarter 1 Quarter 2 Year to Date

    Target Actual Target Actual Target Actual

    Service Delivery Improve Public Lighting Maintenance of Public lights % 98.00 85.00 94.99 85.00 91.2 85.00 87.5

    Service Delivery/ Governance

    Regulatory Compliance (NERSA) NRS 047 (Quality of Service)

    % planned: unplanned maintenance

    Index 62.00 70.00 56.62 70.00 49.2 70.00 48.2

    Total number of calls answered in 30 seconds as a percentage of calls received

    % 50.90 80.00 65.45 80.00 74.27* 80.00 69.79

    Number of customer complaints/queries resolved per total queries received SAP CRM

    % 98.00 90.00 60.01 90.00 59.33* 90.00 61.49

    Average time taken for City Power to resolve queries that are referred to them that require investigations

    days 0.00 10.00 1.12 10.00 -0.08* 10.00 0.39

    Regulatory Compliance (NERSA) NRS 048 (Quality of Supply)

    NRS 048 Compliance – Category 4 - Domestic

    % 100.00 98.00 100.00 98.00 0.00 98.00 100.00

    NRS 048 Compliance - Category 3 - Rural

    % 100.00 98.00 96.60 98.00 0.00 98.00 96.60

    NRS 048 Compliance - Category 2 - Industrial

    % 100.00 98.00 100.00 98.00 0.00 98.00 100.00

    Internal Service Improve Information Technology Management

    Information systems Network availability

    % 94.00 97 98.00 97 99.05 97 98.53

    Information systems Applications availability

    % 98.00 97 99.00 97 99.09 97 99.05

    Internal Service Improve Information Technology Management

    Data Recovery at PC level % 100.00 96.99 100.00 96.99 100.00 96.99 100.00

    Data Recovery at Application (server) level

    % 100.00 96.99 100.00 96.99 100.00 96.99 100.00

    Business Performance

    Effective Financial Management

    Attainment of unqualified audit report

    Index Qualified

    audit report

    Unqualified audit report

    (Full Compliance)

    Qualified audit

    report

    Unqualified audit report

    (Full Compliance)

    Qualified audit

    report

    Unqualified audit report

    (Full Compliance)

    Qualified audit report

    Governance BEE and Engendered Companies empowerment

    Procurement spend from all suppliers

    % New 140.00 148.65 140.00 145.86 140.00 148.10

    Procurement spend from QSE‟s or EME‟s

    % New 4.00 3.67 4.00 12.27 4.00 5.38

    Procurement spend from suppliers that are 50% black owned

    % New 5.00 4.19 5.00 13.07 5.00 5.95

    Environment

    Procurement spend from suppliers that are 30% black women owned

    % New 2.00 2.04 2.00 2.50 2.00 2.13

    ISO Management System Compliance – SHEQ

    Index 6.00 2.00 2.00 2.00 1.50 2.00 3.50

  • City Power Midyear Report – July - December 2012

    Final Page 24

    The table above illustrates that City Power has mixed performance in this perspective and has put interventions in place to ensure improvement going forward, these include:

    To date 2057 meters have been installed compared to the target of 3000, the variance of 31% is as a result of delays in the delivery of the meters however engagements have been strengthened through SCM to ensure timeous delivery of the equipment.

    To date 22710 units of SWH have been installed compared to a target of 11000 units.

    It has been recognised that there is an urgent need to substantially improve the process of plant condition monitoring to identify potential failure modes and to take corrective action prior to actual plant breakdowns, thus improving network performance including the planned: unplanned KPI. As a result, a new independent section has been formed to undertake this function. The responsibility to inspect and condition monitor the electrical infrastructure will now fall within the ambit of the Engineering Services Group.

    2.2.4 Learning and growth Perspective

    Value Propositions

    Key Performance Area

    Key Performance Indicator

    Unit 2011/12 Actual

    Quarter 1 Quarter 2 Year to Date

    Target Actual Target Actual Target Actual

    Optimal Human Capital Utilisation

    Effective Human Resources Management

    Percentage (%) of total grants received back from EW-Seta

    % 74.00 55.00 0.00 55.00 0.00 55.00 0.00

    Total number of performance scores based on performance discussions submitted as a percentage of total staff complement

    % 79.48 80.00 80 80.00 80 80.00 80

    Signed compacts in place as a percentage of total complement

    %

    95.00 85.00 0.00 85.00 0.00 85.00 0.00

    Number of voluntary scarce / critical skills separations as a percentage (%) of total number of separations

    % 47.05 44.00 0.00 44.00 0.00 44.00 0.00

    Service Delivery

    Effective Human Resources Management

    Loss time rate: Number of all leave days taken excluding annual leave x 100 Total work days

    % 3.30 2.20 3.68 2.20 2.80 2.20 3.24

    Individual absenteeism frequency rate: Number of absences (Average number of employees x Annual Individual Working Days) x100

    % 10.14 2.00 8.53 2.00 36.45 2.00 10.34

    Disabling Injury Frequency Ratio (DIFR)

    Ratio 0.51 1 0.50 0.50 0.54 0.50 0.54

    Governance Human Resources Development

    Affirmative Action (Supervisory level and above) % 79.23 83 79.47 83 79.61 83 79.54

    Employment Equity (Gender Equity Ratio)

    % 20.91 22.00 22.85 22.00 22.90 22.00 22.90

    % of People/ Employees with Disabilities

    % 2.89 2.00 2.99 2.00 3.00 2.00 3.00

    Number of tasks undertaken to comply with CoJ environmental management framework

    Number

    0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Socio-economic Development

    Health and Safety HIV/Aids workplace

    interventions executed and achieved the stated results

    Number of

    Projects

    1 Program + 9 Projects

    1 Program

    + 7 Projects

    2 Projects – HV + Cancer

    Screening

    1 Program + 2 Projects

    3 Projects

    1 Program

    + 4 Projects

    5 Projects

  • City Power Midyear Report – July - December 2012

    Final Page 25

    City Power has an internal KPI for AA for supervisory and above level, with an actual of 79.54. While when the entire staff compliment is taken into account the actual is 88.82%

    HIV/Aids workplace interventions executed and achieved the stated results. Integrated wellness strategy which incorporates programs like Wellness Days, Employee Assistance Programs, awareness campaigns, HIV/AIDS education and awareness etc.

    City Power has submitted all the required documents to EWSETA but has not receive any rebates to date

    The organisation is currently reviewing and benchmarking the absenteeism KPIs and targets to align with national norms and standards

    In the last 6 months City Power had only 3 resignations of which none were scares and critical skills. This means the organisations retention strategy is still effective

  • City Power Midyear Report – July - December 2012

    Final Page 26

    3 PROJECT/INFRASTRUCTURE REPORT

    3.1 Analysis of the Master Capital Programme

    The original approved City Power Capital budget for the 2012/13 financial year is R 953 million. The Capital budget comprises of the controllable component which is inclusive of R 399 million worth of loans, R 258 million DSM funding, R 32 million Engineering Services contribution, R 134 million grant funding as well as R 5 million “ Adopt a Light” funding while the non-controllable component is made up of Public Contributions. The second quarter and the year to date expenditure is as shown on the table below: 3.2 Capital Expenditure Details The expenditure for the second quarter amounted to R145 million compared to the quarterly budget of R 287 million which is R 142 million below the quarterly budget. Although the year to date actual expenditure amounted to R 256 million compared to the year to date budget of R 390 million which reflects 34% below the budget, the total year to date expenditure including commitments is R 534 million. This shows that the overall capital expenditure is ahead of the budgeted amount and therefore no risks of under-spending at the end of the financial year exist. Table: A

    Project Detail (By Project)

    Budget for Quarter 2

    Actual for Quarter 2

    Var for the Quarter

    Total Budget for

    the year

    YTD budget YTD Actual Total YTD actual &

    Commitment

    YTD Variance

    R’ ( A) R’ (B) R’ (C) R’ ( D) R’ ( E) R’ ( F ) R’ ( G ) R’ ( E – G )

    Electrification 11,600,000 4,793,491 6,806,509 54,349,000 17,951,000 4,793,491 7,468,829 10,482,171

    Service Connections 37,768,000 13,223,571 24,544,429 125,065,000 54,568,000 29,084,706 33,598,721 20,969,279

    Township Reticulation 1,061,656 -1,061,656 0 0 1,480,655 1,534,358 -1,534,358

    Upgrading of Electrical Network 16,090,000 17,287,879 -1,197,879 90,000,000 30,630,000 35,142,092 88,258,667 -57,628,667

    Network Development 4,480,000 1,040,240 3,439,760 18,000,000 5,880,000 1,040,240 1,456,055 4,423,945

    Building Alterations/ Construction 377,000 0 377,000 2,211,480 679,000 156 21,156 657,844

    Office Equipment/Computers 3,220,000 345,773 2,874,227 11,616,520 4,220,000 1,117,910 1,266,466 2,953,534

    Computer Software 551,000 0 551,000 1,863,900 751,000 0 751,000

    Tools and Loose Gear 1,510,000 563,409 946,591 2,941,000 1,940,000 1,310,516 3,429,340 -1,489,340

    Plant and Machinery 13,123,000 7,977,190 5,145,810 31,347,052 18,623,000 8,245,380 20,322,265 -1,699,265

    Meters and Load Man 148,568,000 68,242,066 80,325,934 425,000,000 171,318,000 132,516,541 285,676,367 -114,358,367

    Protection 5,264,000 2,393,381 2,870,619 12,700,000 6,464,000 3,328,255 8,748,457 -2,284,457

    Furniture 400,000 29,277 370,723 1,043,100 475,000 30,227 480,079 -5,079

    Public Lighting 22,994,000 18,873,453 4,120,547 99,886,000 38,644,000 23,628,065 45,049,763 -6,405,763

    Refurbish of Bulk Infrastructure 21,190,000 7,970,887 13,219,113 76,876,948 37,490,000 13,032,579 30,332,939 7,157,061

    Insurance 833,052 -833,052 0 0 1,073,607 6,404,667 -6,404,667

    TOTAL 287,135,000 144,635,327 142,499,674 952,900,000 389,633,000 255,824,421 534,048,130 -144,415,130

  • City Power Midyear Report – July - December 2012

    Final Page 27

    3.2.1. CONTROLLABLE CAPEX The expenditure for the second quarter on Controllable capital projects, which are projects funded from CoJ loans, DSM levy, Grant funding and Adopt a light funding amounted to R 128 million compared to the budget of R 247 million which is R 119 million below the target. The year to date expenditure amounted to R 221 million compared to the budget of R 335 million which reflects a negative variance of R 114 million. Although the expenditure is behind the budget, the total year to date actual expenditure including commitments amounted to R 490 which is 46% ahead of the year to date budget.

    Table: B

    ( Contrallables) Project Detail (By Project)

    Budget for Quarter 2

    Actual for Quarter 2

    Var for the Quarter

    Total Budget for

    the year

    YTD budget

    YTD Actual Total YTD actual & Committ

    YTD Variance

    R’ ( A) R’ (B) R’ (C) R’ ( D) R’ ( E) R’ ( F ) R’ ( G ) R’ ( E – G )

    Electrification 11,600,000 4,793,491 6,806,509 54,349,000 17,951,000 4,793,491 7,468,829 10,482,171

    Public Lighting 22,994,000 18,203,236 4,790,764 99,886,000 38,644,000 22,563,563 43,985,261 -5,341,261

    Electrical Infrastructure 166,888,000 84,368,031 82,519,969 518,552,672 204,828,000 164,911,940 370,759,554 -165,931,554

    Power Systems 5,264,000 3,433,622 1,830,378 17,700,000 9,464,000 5,358,275 11,565,930 -2,101,930

    Other Capex & asset purchases 19,181,000 8,915,651 10,265,349 51,023,052 26,688,000 10,704,189 25,519,307 1,168,693

    Refurbish of Bulk Infrastructure 21,190,000 7,970,887 13,219,113 86,324,376 37,490,000 13,032,579 30,332,939 7,157,061

    TOTAL 247,117,000 127,684,918 119,432,082 827,835,100 335,065,000 221,364,037 489,631,819 -154,566,819

    ELECTRICAL INFRASTRUCTURE Electrical infrastructure comprises of Upgrade of Electrical Networks, Network development, Meters and Load management. The second quarter expenditure amounted to R84 million which is R 82 million below the budget of R 166 million. The expenditure includes the Solar water heater installations, Metering projects and conversion of LV bare conductor to ABC. The year to date expenditure amounted to R 165 million compared to the year to date budget of R 204 million which is R 40 million below the year to date budget, the negative variance is as a result of the delays in the delivery of critical equipment however the commercial processes are being fast tracked to achieve the target in the third quarter. It should be noted that the total year to date actual expenditure including commitments amounted to R 370 million which is R 165 million ahead of the target. The full year budget will be spent by the end of the financial year. POWER SYSTEMS Power Systems comprises of Protection. The expenditure for the quarter amounted to R 3,4 million compared to the budget of R 5,2 million which is R 1,8 below the budget. The expenditure includes projects such as the 88 kV protection upgrade projects, Power factor correction at Orlando and Installation of new IED‟s in substations. The year to date expenditure amounted to R 5,4 million compared to the year to date budget of R 9,4 million which translates to under spending of R 4 million as a result of the delay in the delivery of critical equipment in the first quarter. It should be noted that the total year to date actual expenditure including commitments amounted to R 11 million which is R 2 million ahead of the target. The full year budget will be spent by the end of the financial year.

  • City Power Midyear Report – July - December 2012

    Final Page 28

    PUBLIC LIGHTING The expenditure for the quarter amounted to R 18 million compared to the quarterly budget of R 23 million. The year to date budget amounted to R 23 million compared to the year to date budget of R 39 million. The negative variance is as a result of the late start of the program. ELECTRIFICATION The expenditure for the second quarter amounted to R 5 million compared to the quarterly budget of R12 million. The year to date expenditure amounted to R 5 million compared to the year to date budget of R 18 million. The negative variance is as a result of the late start of the program, however the program is being fast tracked and the improvement will be realized in the next quarter. The full year budget will be spent by the end of the financial year. BULK INFRASTRUCTURE The expenditure for the second quarter amounted to R 8 million compared to the quarterly budget of R 21 million. The expenditure includes projects such as Sebenza, Transformer program, Upgrade of Kelvin - Cydna substations. The year to date expenditure amounted to R 13 million compared to the year to date budget of R 37 million which reflects a negative variance of R 24 million as a result of delays in the commercial processes of major projects, however the program has since been fast tracked and the expenditure will be realized in the next quarter. The full year budget will be spent by the end of the financial year.

    3.2.2. NON CONTROLLABLE CAPEX The non-controllable capital projects are projects which are funded by public contributions. The expenditure for the quarter amounted to R17 million compared to the quarterly budget of R 38 million. The year to date expenditure amounted to R 34 million compared to the year to date budget of R 55 million and this reflects a negative variance of R 21 million as a result of low levels of service connection applications. Table: C

    (Non - Contrallables) Project Detail (By Project)

    Budget for

    Quarter 2

    Actual for Quarter 2

    Var for the Quarter

    Total Budget for

    the year

    YTD budget

    YTD Actual

    Total YTD actual & Committ

    YTD Variance

    R’ ( A) R’ (B) R’ (C) R’ ( D) R’ ( E) R’ ( F ) R’ ( G ) R’ ( E – G )

    Public Lighting 0 670,216 -670,216 0 0 1,064,503 1,064,503 -1,064,503

    Electrical Infrastructure 0 1,161,914 -1,161,914 0 0 1,756,914 1,814,063 -1,814,063

    Service Connections 37,768,000 13,223,571 24,544,429 125,065,000 54,568,000 29,084,706 33,598,721 20,969,279

    Township Reticulation 0 1,061,656 -1,061,656 0 0 1,480,655 1,534,358 -1,534,358

    Insurance 833,052 -833,052 1,073,607 6,404,667 -6,404,667

    TOTAL 37,768,000 16,950,409 20,817,591 125,065,000 54,568,000 34,460,385 44,416,311 10,151,689

  • City Power Midyear Report – July - December 2012

    Final Page 29

    PUBLIC LIGHTING The year to date expenditure amounted to R 1 million which is as a result of funds received from developers for service connections. ELECTRICAL INFRASTRUCTURE The year to date expenditure amounted to R 1,8 million which is as a result of funds received from developers. SERVICE CONNECTION The year to date expenditure amounted to R 29 million compared to the budget of R 55 million. The funds are received from the public for service connections. INSURANCE The year to date expenditure amounted to R 1 million, these are projects funded through insurance claims.

    3.3 Funding claims

    Project Detail (By Project) Quarter 1 Quarter 2 TOTAL

    R'000 R'000 R'000

    Building alterations loans 156 0 156

    Furniture loans 950 29,277 30,227

    Load management loans 25,971,099 25,971,099

    Meters loans 6,935,420 6,935,420

    Office equipment loans 343,703 345,774 689,477

    Plant and machinery loans 7,977,190 7,977,190

    Protection loans 934,874 2,393,381 3,328,255

    Refurbish of bulk infrastructure - loans 4,759,453 7,298,500 12,057,953

    Tools and loose gear loans 693,030 563,409 1,256,439

    Upgrade of network loans 11,734,115 16,125,965 27,860,080

    TOTAL 18,466,281 67,640,015 86,106,296

    Capex claims are claims done on the loans granted by COJ to City Power as we spend on the loan funding. The year to date Capex claims amounted to R 86 million.

    3.4 Funding Source

    Details (CMIP/CLF)

    Original Budget ( R‟000)

    Proposed Revised Budget ( R‟000)

    Actual ( R‟000)

    Loans 399,100 644,940 154,804

    CRR and cash 258,000 192,397 37,486

    National Grant 53,735 133,735 23,646

    Public contributions & other

    242,065 127,000 39,888

    TOTAL 952,900 1,098,072 255,824

  • City Power Midyear Report – July - December 2012

    Final Page 30

    4 HUMAN RESOURCES

    4.1 Staff Complement

    Occupational Levels Male Female Foreign Nationals

    Total A C I W A C I W Male Female

    Top management 1 0 0 1 1 0 0 0 0 0 3

    Senior management 12 1 2 4 3 0 0 1 0 0 23

    Professionally qualified and experienced specialists and mid-management

    125 5 5 68 107 1 1 7 0 0 319

    Skilled technical and academically qualified workers, junior management, supervisors, foremen, and superintendents

    342 37 8 105 123 9 3 32 0 0 659

    Semi-skilled and discretionary decision making

    508 8 0 5 33 2 0 1 0 0 557

    Unskilled and defined decision making

    16 0 0 0 47 2 0 0 0 0 65

    TOTAL PERMANENT 1004 51 15 183 314 14 4 41 0 0 1626

    Temporary employees 5 1 0 0 1 0 0 0 0 0 7

    GRAND TOTAL 1009 52 15 183 315 14 4 41 0 0 1633

    4.2 Staff movements

    Table below shows Staff Movements (1 July 2012 to 31 December 2012) Staff

    Movements African Coloured Indian Whites

    Male Female Male Female Male Female Male Female

    Appointments 5 2 0 0 0 0 0 0

    Recruitments 2 1 0 0 0 0 0 0

    Resignations 2 0 0 0 1 0 0 0

    Dismissals 0 0 0 0 0 0 0 0

    Retirements 6 0 1 0 0 0 0 0

    Death 6 0 0 0 0 0 0 0

    Medical Boarding

    1 0 0 0 0 0 0 0

    Termination of Contract

    0 0 0 0 0 0 0 1

    Only three employees resigned from the Company‟s service during July 2012 to December

    2012 The employee turnover rate (which is inclusive of resignations, dismissals, death etc) as at

    the end of December 2012 is 1.10%

    4.3 Employment Equity and affirmative action plans and programmes The EE Report for the period 01 July 2011 to 30 June 2012 has been deliberated upon and

    duly signed off by all relevant stakeholders (interim committee made up of management and organised labour representatives)

    The report will be submitted by the prescribed due date – 15 January 2013 The Employment Equity Plan that has been in place (2006 to 2011) has lapsed and the

    committee has recognised the importance and urgency of developing a new EE Plan by the end of February 2013

  • City Power Midyear Report – July - December 2012

    Final Page 31

    The company‟s affirmative action targets are : Affirmative Action = 74%; Gender Equity = 25% and People with Disabilities = 2%

    The company honours the country calendar initiatives, sister company programmes etc, such as:

    o Women‟s Day (9 August) o 16 Days of Gender Based Violence (25 November till 10 December) o The Office of the MD has seconded two HR employees to form part of CoJ

    Gender Forum Committee. This Committee is currently operational o Reasonable accommodation initiatives

    Table 10: Employment Equity – Proposed Targets By race

    Categories Target - Male Target - Female Total

    A C I W A C I W

    Executives Directors 1 0 0 0 0 0 0 0 1

    Directors 0 0 0 1 1 0 0 0 2

    Deputy Director / General Managers

    7 1 1 3 3 0 0 1 16

    Assistant Directors/ Senior Managers

    5 0 1 1 0 0 0 0 7

    Professionals 51 3 5 38 65 1 0 5 168

    Managers 27 2 0 22 11 0 1 2 65

    Technicians 48 1 0 8 31 0 0 0 88

    Operator 30 0 0 0 8 4 0 0 42

    Semiskilled staff 824 45 8 110 149 7 3 33 1179

    Other 16 0 0 0 47 2 0 0 65

    4.4 Skills Development Plans

    Five service providers were appointed during August 2012 for all mandatory training and apprenticeship training over a three year period ending 2015. This directly supports the ISO certification and re-certification and development of our core business units. The literacy and up skilling programmes are underpinned by interventions such as the Adult Education and Training (AET) and Matric Programmes

    Present learning initiatives are pivotal programmes (educational assistance), structured workplace learning (occupational qualification), workplace integrated learning (experimental learners, hosted learners from DoL) and the promotion of learning through the attendance of conferences and seminars

    We have Corporate Social Initiatives in place such as the Bursar Programme and Extended Public Works Programme (EPWP)

    Promotion of learning and development is also supported by the provision of funding for travel and accommodation

    Mandatory Training Providers: Contract Nr: Company Name: Services Contract Value Contract Period:

    4600001484 The Business School Of South Africa

    SHEQ Representative R 197,368.42

    22/08/2012 To 14/08/2015 HIRAC

    Hazmat

    4600001485 Jct Training Consultants Cc

    Signing And Barricading R 701,754.39

    22/08/2012 To 14/08/2015

    Overhead Crane (Full)

    Overhead Crane (Recertification)

    Rigging And Slinging (Full)

    Rigging And Slinging (Recertification)

    Scaffolding

  • City Power Midyear Report – July - December 2012

    Final Page 32

    Contract Nr: Company Name: Services Contract Value Contract Period:

    Stacking & Storing

    Jack Hammer

    Working At Heights

    Working In Confined Spaces

    4600001486 Tasa Training Services

    Basic First Aid R 219,298.25

    22/08/2012 To 14/08/2015

    Fire Fighting

    Forklift (Full)

    Forklift (Recertification)

    Operating Truck M/Crane (Full)

    Operating Truck M/Crane (Recertification)

    4600001487 Ugesi Training Cc

    Ladder R 197,368.42

    22/08/2012 To 14/08/2015

    Battery

    Low Voltage

    4600001488 Industries Education

    Electrical Trade Test Prep R 1,052,631.58

    22/08/2012 To 14/08/2015

    Electrical Trade Test

    Electrical Learnership

    Ntc Electrical Equivalence

    Trade Electrician

    4.5 Staff versus cost of staff to total Opex

    Due to the non-filling of vacancies the % of Salary to Opex (Year to date actual) of 23.77%

    is less budget and less than the CoJ percentage. However as City Power is in the process of restructuring additional positions will be filled, which will result in an increase in the percentage of salaries to Opex.

    Table 11: Percentage of Salary to total Opex

    Actual Budget Variance Actual Budget Variance Actual Budget Variance

    Total Salary

    Cost186,471 193,419 6,948 179,363 193,420 14,057 365,834 386,839 21,005

    Total Opex 761,905 697,629 -64,276 777,397 692,243 -85,154 1,539,302 1,389,872 -149,430

    % of Salary to

    Opex24.47 27.73 3.25 23.07 27.94 4.87 23.77 27.83 4.07

    Quarter 1 Quarter 2 YTD

    R'000 R'000 R'000

    4.6 Employees Wellness Programme Most of the employees on disease management therapy are compliant and progressing

    well health wise During Wellness Open Day on the 20 September 2012 employees were screened for HIV

    and the Employee Assistance Programme provided various educational and information stalls and talks about psychosocial related issues e.g. substance abuse, family and mental life etc.

    On the 3 December 2012 a successful workshop on 16 Days of Gender Based Violence was conducted by the EAP unit, with approximately 400 employees in attendance. The purpose and aim of this campaign was to empower and impart knowledge to employees regarding the impact of violence perpetuated against women and children and challenge perpetrators of these offences to change their behaviour as well as to alleviate psychosocial problems experienced by some employees due to gender based violence which impact negatively in their execu