middle tamor hydropower project (73 mw) progress report ......project key dates 4 s.n. activities...

42
SEPTEMBER, 2020 SANIMA MIDDLE TAMOR HYDROPOWER LIMITED Shankha park, Dhumbarahi, Kathmandu, Nepal

Upload: others

Post on 02-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • SEPTEMBER, 2020

    SANIMA MIDDLE TAMOR HYDROPOWER LIMITED

    Shankha park, Dhumbarahi, Kathmandu, Nepal

  • SEPTEMBER, 2020

    SANIMA MIDDLE TAMOR HYDROPOWER LIMITED

    Shankha park, Dhumbarahi, Kathmandu, Nepal

  • GENERAL PROJECT OVERVIEW

    3

    GENERAL INFORMATION:COMPANY :

    Name : Sanima Middle Tamor Hydropower Limited (SMTHL)

    Registration date : Registration No. 148796 (Baisakh 23 2073)

    PROJECT :

    Name : Middle Tamor Hydropower Project

    River :Tamor River

    Location : Phaktanglung Rural Municipality, Phungling Municipality,

    Mikwa khola Rural Municipality, Taplejung, Province 1

    Installed capacity : 73 MW

    Gross head : 132 m

    Design Discharge : 73.71 m3/sec

    Annual Energy : 429.41 GWh

    (Dry Energy 64.48 GWh & Wet Energy 364.93 GWh)

    GENERATION LICENSE :

    License Number : Bi. Bi. Bi. /073/74 Bi. U. 198

    Issue Date : 25 Mangsir 2075 B.S.

  • PROJECT KEY DATES

    4

    S.N. Activities Dates

    1 Survey license to SHEPL 14 Feb 2008

    2 Transfer of survey license from SHEPL to TSE 07 Jul 2011

    3 Feasibility Study (75 MW cascade option) Sept 2013

    4 Supplementary Feasibility Study (54 MW independent option) July 2016

    5 EIA approval (75 MW cascade option) June 2013

    6 Grid Connection Agreement 9 Mar 2015

    7 Supplementary EIA approval (54 MW independent option) Nov 2016

    8 Power Purchase Agreement (52.1 MW independent option) 10 Jan 2017

    9 Generation License (54 MW independent option) 5 June 2017

    10 Transfer of Generation License (From TSE to SMTHL) 06 Nov 2017

    11 Consent Letter for expansion of Capacity from 54 to 73 MW from DoED 09 Oct 2017

    12 Consent Letter for Supplementary EIA of the capacity-upgraded (73 MW) Project from Ministry of Environment 22 Dec 2017

    13 Financial Closure with a Consortium of 8 Banks Feb 10, 2019

    14 Main Civil Contract awarded to Zhejiang First Hydro & Power Construction Group Co. Ltd. 12 Apr 2018

    15 SEIA approval for 73MW 23 Oct 2018

    16 Power Purchase Agreement (PPA) for additional 20.9 MW 30 Nov 2018

    17 Generation License received for 73 MW 10 Dec 2018

    18 Land Ceiling Approval 4 July 2019

    19 Award of Hydromechanical Contract to Machhapuchhre Metal and Machinery Works Pvt. Ltd 11 July 2019

    20 Award of Electro-mechanical Works Contract to Chongqing Water Turbine Works Co. (CWTW), Ltd. 23 Dec 2019

    21 Award of Transmission Line Works Contract to Cosmic Electrical Engineering Associates Pvt. Ltd. 07 June 2020

  • PROJECT KEY DATES

    5

    Power

    Purchase

    Agreement for

    73 MW signed

    with Nepal

    Electricity

    Authority

    2075/08/14

    (Nov 30, 2018)

    PPA Generation

    License

    Financial

    Closure

    Proposed

    RCOD

    Generation

    License for 73

    MW received

    from

    Department of

    Electricity

    Authority

    (DoED)

    2075/08/25

    (Dec 11, 2018)

    Agreement for

    the Loan

    Facility with

    consortium of 8

    Banks

    Lead Bank:

    NIBL

    Co Lead: Nabil,

    Global IME

    Commercial

    Operation of

    the Plant

    2079/04/01

    (July 17, 2022)

    Supplementary

    Environment

    Impact

    Assessment for

    73 MW

    approved by

    the Ministry of

    Forests and

    Environment

    2075/07/06

    (Oct 23, 2018)

    SEIA

    2075/10/27

    (Feb 10, 2019)

  • CONSTRUCTION MANAGEMENT

    6

    CONTRACT PACKAGES AND CONSULTANTS/CONTRACTORS:

    Contract Package Award Date Contractor/ Supplier

    The Engineer/ Consultant September 21, 2017 Sanima Hydro and Engineering (P.) Ltd., Nepal

    Main Civil Works Construction April 12, 2018Zhejiang First Hydro & Power Construction Group

    Co. Ltd., China

    Hydro-mechanical Works July 11, 2019Machhapuchhre Metal and Machinery Works Pvt.

    Ltd., Nepal

    Electro-mechanical Works December 23, 2019 Chongqing Water Turbine Works Co., Ltd., China

    Transmission Line Works June 07, 2020Cosmic Electrical Engineering Associates Pvt. Ltd.,

    Nepal

  • PROGRESS AT MAIN CIVIL WORKS

    7

    Civil Structure at Headworks (Sept. 2020)

    • Contractor: Zhejiang First Hydro & Power Construction Group Co. Ltd.

    • Contract Award Date: 12 April 2018

  • CONSTRUCTION PROGRESS

    8

    PROGRESS AT HEADWORKS TILL DATE:

  • PROGRESS WORKS AT HEADWORKS

    9

    • 96.40% of total concrete works at Headworks have been completed as of 13

    Sept. 2020 in (INTAKE, UNDERSLUICE, FLOODWALL & CUTOFF SECTION)

    Progress Status at Headworks of MTHP

    Structures Works CompletedWorks

    RemainingRemarks

    Undersluice 98.00% 2% Ongoing

    Intake 96.50% 3.50% Ongoing

    U/s Floodwall 87.50% 12.50% Ongoing

    D/s Floodwall 100% 0% Completed

    U/s Cutoff Wall 100% 0% Completed

    Total Concrete Progress at H/W 96.40% (ExcludingWeir)

  • PROGRESS AT HEADWORKS

    10

    Intake Structure Front View Intake Structure Back View

  • PROGRESS AT HEADWORKS

    11

    Intake and Undersluice Structure from Front View

    Intake

    Undersluice

    Cutoff Wall

    Coffer Dam

  • PROGRESS AT HEADWORKS

    12

    Intake Structure from Back View

    Intake

    U/s Floodwall

    Undersluice

  • PROGRESS AT HEADWORKS

    13

    A view of Undersluice from Weir Side Top Slab of Undersluice

  • PROGRESS AT HEADWORKS

    14

    Intake and Undersluice (A view from Hillside) Undersluice Panel-03

  • PROGRESS AT HEADWORKS

    15

    Undersluice StructureU/s Floodwall View

  • PROGRESS AT UNDERGROUND WORKS

    16

    • 64% by length and 47% by Volume of total tunnel works have

    been excavated till date

    • Length of tunnel has reached a total of 4241 meters (6634m Total)

    Works Completed

    • Approach Tunnel from Inlet

    • Approach Tunnel-01

    • Approach Tunnel-02

    • Approach Tunnel-03

    • Inspection Tunnel-01

    • Inspection Tunnel-02

    • Adit-01

    • Connecting Tunnel to Surge Shaft

    • Ventilation Tunnel

    Works Ongoing

    • Settling Basin Bay-01

    • Settling Basin Bay-02

    • Settling Basin Bay-03

    • Connecting Tunnel-01

    • Connecting Tunnel-02

    • Connecting Tunnel-03

    • Sediment Flushing Tunnel

    • Gate Shaft (Inspection Tunnel to SB)

    • Surge Shaft

    • HRT• From Adit

    • From Outlet

  • TUNNEL EXCAVATION WORKS TILL DATE

    17

    Middle Tamor Hydropower Project (73 MW)Tunnel Excavation

    S.N TunnelTotal Length

    (m)Completed length (m)

    Total Volume (m3)

    Excavated Volume (m3)

    Status

    1 Approach Tunnel from Inlet 247.06 247.06 9292.92 9292.92 Completed2 Approach Tunnel-01 151.34 151.34 3363.12 3363.12 Completed3 Approach Tunnel-02 113.17 113.17 2505.37 2505.37 Completed4 Approach Tunnel-03 131.50 131.50 3025.22 3025.22 Completed5 Settling Basin Bay-01 150.00 59.60 29669.13 3143.70 Pending6 Settling Basin Bay-02 150.00 92.98 29669.13 5396.51 Active7 Settling Basin Bay-03 150.00 72.93 29669.13 4043.34 Active8 Connecting Tunnel-01 138.30 132.35 3002.49 2867.36 Pending9 Connecting Tunnel-02 117.37 112.50 2749.25 2638.66 Pending

    10 Connecting Tunnel-03 121.32 104.60 2630.97 2251.25 Pending11 Inspection Tunnel-01 274.67 274.67 6068.56 6068.56 Completed12 Inspection Tunnel-02 289.52 289.52 7420.23 7420.23 Completed13 Adit-01 299.47 299.47 6782.49 6782.49 Completed14 Sediment Flushing Tunnel 506.36 5.00 3600.00 35.40 Pending15 Gate Shaft (Inspection Tunnel to SB) 66.00 SB-gate 4551.86 1106.05 Pending16 Connecting Tunnel to Surge Shaft 70.20 70.20 2765.88 2765.88 Completed17 Surge Shaft 87.73 8.00 16880.38 1312.98 Active18 Ventilation Tunnel 199.75 199.75 2560.64 2560.64 Completed

    19.1HRT

    From Adit3369.96

    683.73133248.58

    27411.12 Pending19.2 From Outlet 1192.43 46981.74 Pending

    Total 6633.718 4240.80 299455.349 140972.54 47.08%

    63.93% 47.08%Completed by length Completed by Volume

  • TUNNEL EXCAVATION WORKS NEAR H/D TILL DATE

    18

  • PROGRESS AT TUNNEL

    19

    A view of Connecting Tunnel Junction

  • PROGRESS AT TUNNEL

    20

    A view of Surge Shaft CrownA view of HRT from Adit

  • PROGRESS AT TUNNEL

    21

    A view of SB-03A view of SB-02

  • PROGRESS AT TUNNEL

    22

    A view of HRT from OutletInstallation of Ribs

  • CONSTRUCTION PROGRESS

    23

    PROGRESS AT POWERHOUSE:

  • SUMMARY OF WORK PROGRESS

    24

    PreConstruction

    Works

    U/SFloodwall

    D/SFloodwall

    U/S Cutoffwall

    Intake UndersluiceSettling Basin

    by lengthSettling Basin

    by volume

    TotalUnderground

    works bylength

    TotalUnderground

    works byvolume

    Surge Shaft

    % Remaining 0 13 0 0 4 2 50 86 36 53 92

    % Completed 100 87.5 100 100 96.50 98 50 14 64 47 8

    0

    20

    40

    60

    80

    100

    120

    Work Progress Chart at Active Work Fronts

    % Completed % Remaining

  • PROGRESS IN HYDRO-MECHANICAL (HM) WORKS

    25

    • Contractor: Machhapuchhre Metal and Machinery Works Pvt. Ltd.

    • Contract Award Date: 11 July 2019

    Hydro-Mechanical (HM) Works

    • Hydro Mechanical works are on going simultaneously with the Main Civil

    Contractor

    • Installation of steel lining in Intake/Bed load sluice (Status: Completed)

    • Installation of steel lining in Undersluice (Status: Ongoing)

    • Radial Gate Frame erection (Status: Completed)

    • Erection of Undersluice stoplog frame (Status: Completed)

    • Installation of bedload sluice gate/ stoplog frame (Status: Completed)

    • Rolling of Approach Pipes and Penstock Pipes (Status: Started from Aug. 09)

  • 26

    Pipes for Inlet PortalRolling of Pipes at HM Contractor Workshop

    PROGRESS IN HYDRO-MECHANICAL (HM) WORKS

  • PROGRESS IN HYDRO-MECHANICAL (HM) WORKS

    27

    Erection of Radial Gate FrameFabrication of Approach Pipes at 3MW Workshop

  • PROGRESS IN HYDRO-MECHANICAL (HM) WORKS

    28

    Steel Lining at UndersluiceTrunnion Box Fixing

  • PROGRESS IN ELECTRO-MECHANICAL (EM) WORKS

    29

    • Contractor: Chongqing Water Turbine Works Co. (CWTW), Ltd., China

    • Contract Award Date: 23 July 2019

    Electro-Mechanical (EM) Works

    • Electromechanical Contractor will mobilize as soon as the International Flights

    are permitted

    • Construction design and drawings (Status: 80% Completed)

    • Construction of Draft tube elbow is ongoing in China (Status: 90% Completed)

  • PROGRESS IN ELECTRO-MECHANICAL (EM) WORKS

    30

    Grinding and Painting of Draft Tube Components in ChinaFabrication of Draft Tube Elbow in Contractor’s Workshop in China

  • PROGRESS IN TRANSMISSION LINE (TL) WORKS

    31

    • Contractor: Cosmic Electrical Engineering Associates Pvt. Ltd.

    • Contract Award Date: 07 June 2020

    Transmission Line (TL) Works

    • Detailed survey of finalized Transmission Line route has been carried out

    • IEE study is in progress

    • Final alignment for transmission line is finalized

    • Feasibility study of Transmission Line have been completed and submitted to DoED

    • Engineering Design (Status: Complete)

    • Check Survey (Status: Complete)

    • Soil Investigation(Status: Complete)

  • PROGRESS IN TRANSMISSION LINE (TL) WORKS

    32

    TL Contract Award (June 07, 2020) Detail Survey along the TL alignment

  • PROGRESS IN TRANSMISSION LINE (TL) WORKS

    33

    Excavation works at Dhunge-Sanghu substation of NEA (Koshi Corridor)Geotechnical Investigation for Transmission Line

  • FINANCIAL PROGRESS

    34

    • Till Date Expenditure: 29% Financial Progress has been achieved till date

    Major Contract Packages% Financial

    Progress

    % Remaining

    Budget

    Main Civil Works 42% 58%

    Hydro-

    Mechanical

    Works

    Design and Fabrication

    41% 59%

    Steel Plates Procurement

    100% 0%

    Electro-Mechanical Works 7% 93%

    Transmission Line Works 7% 93%

    Financial Progress of MTHP 29% 71%

    29%

    Overall Financial Progress of MTHP

    % Expense TillDate

  • OVERALL CONSTRUCTION PROGRESS TILL DATE

    35

    40%

    Overall Progress of Project = 40%

    OverallProgress ofProject

    45%40%

    10% 10%

    55%60%

    90% 90%

    0%

    20%

    40%

    60%

    80%

    100%

    120%

    Main Civil Works Hydro-Mechanical Works Electromechanical Works Transmission Line Works

    Construction Porgress

    Works Completed Works Remaining

    Particulars Works Completed Works Remaining

    Main Civil Works 45% 55%

    Hydro-Mechanical Works 40% 60%

    Electromechanical Works 10% 90%

    Transmission Line Works 10% 90%

    Overall Construction Progress

    of the Project: 40%

  • PHOTOGRAPHS OF ONGOING WORKS

    36

    Intake

    Undersluice

    Coffer Dam

    Tamor River

    Cutoff Wall

    Flood Wall

    View of Headworks from Upstream side

  • PHOTOGRAPHS OF ONGOING WORKS

    37

    Temporary diversion wall constructed from panel 08 to DS cutoffUndersluice Panel 04-08

  • PHOTOGRAPHS OF ONGOING WORKS

    38

    Third stage temporary cofferdam preparation for Construction of WeirUndersluice and Weir Construction Area

    Weir Axis

    Tamor River

  • PHOTOGRAPHS OF ONGOING WORKS

    39

    Undersluice from D/sA view of Undersluice

  • PHOTOGRAPHS OF ONGOING WORKS

    40

    Undersluice Panel 03Intake and Undersluice Construction

  • PHOTOGRAPHS OF ONGOING WORKS

    41

    A view of U/s FloodwallConstruction of Guard House (Near Simle Camp Area)

  • PHOTOGRAPHS OF ONGOING WORKS

    42

    HRT from Adit-01Niche at HRT Outlet