8-11-03 Brick going up on north side next to classrooms.
![Page 3: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/3.jpg)
Rain test on new roof. Roof at 60% completion.
![Page 4: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/4.jpg)
Main east west corridor.
![Page 5: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/5.jpg)
Typical entrance detail to classrooms.
![Page 6: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/6.jpg)
Main north south corridor. Looking to the the south.
![Page 7: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/7.jpg)
Main east west corridor looking toward the west.
![Page 8: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/8.jpg)
Vestibule looking toward the southwest.
![Page 9: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/9.jpg)
Profile of building from the southwest corner.
![Page 10: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/10.jpg)
Brickwork at about 20%.
![Page 11: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/11.jpg)
View from Amethyst.
![Page 12: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/12.jpg)
The Project is going well. We will be ready for students to use the modular at the start of the school year.
![Page 13: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfb81a28abf838c9f81e/html5/thumbnails/13.jpg)
The six-classroom addition is on budget and on schedule. It will be ready for occupation as
scheduled in early 2004.
Rick Denney, Facilities Director 8-11-03