middle school expansion august 11, 2003. 8-11-03 brick going up on north side next to classrooms

13
Middle School Expansion August 11, 2003

Upload: morgan-carson

Post on 18-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Middle School Expansion August 11, 2003

Page 2: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

8-11-03 Brick going up on north side next to classrooms.

Page 3: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Rain test on new roof. Roof at 60% completion.

Page 4: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Main east west corridor.

Page 5: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Typical entrance detail to classrooms.

Page 6: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Main north south corridor. Looking to the the south.

Page 7: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Main east west corridor looking toward the west.

Page 8: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Vestibule looking toward the southwest.

Page 9: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Profile of building from the southwest corner.

Page 10: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

Brickwork at about 20%.

Page 11: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

View from Amethyst.

Page 12: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

The Project is going well. We will be ready for students to use the modular at the start of the school year.

Page 13: Middle School Expansion August 11, 2003. 8-11-03 Brick going up on north side next to classrooms

The six-classroom addition is on budget and on schedule. It will be ready for occupation as

scheduled in early 2004.

Rick Denney, Facilities Director 8-11-03