Middle Harbor Redevelopment Project. WEDA Conference November 5, 2009. Existing Middle Harbor Terminals. California United Terminals (CUT) 170-acre break-bulk/container terminal at Piers D and E on the north - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/1.jpg)
Middle Harbor Redevelopment Project
WEDA ConferenceNovember 5, 2009
![Page 2: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/2.jpg)
Existing Middle Harbor Terminals
● California United Terminals (CUT) 170-acre break-bulk/container terminal at Piers D and E on the north
● Long Beach Container Terminal (LBCT) 101-acre container terminal at Pier F on the south
![Page 3: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/3.jpg)
Proposed Middle Harbor Terminal
● Consolidate two older facilities into one efficient, 345-acre rectangular-shaped terminal
● Construction will occur in multiple stages over a 10-year period
![Page 4: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/4.jpg)
Dredging and Excavation
● Demolish existing Pier D & Pier E wharves
● Widen and deepen Slip 3
● Construct rock containment dike
● Excavate portion of Pier F
![Page 5: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/5.jpg)
Middle Harbor Fill Site
● Fill Pier E Extension, wedge fill, and portion of Slip 1
● Complete fill of Slip 1 and portion of East Basin
● Connect Pier E terminal to Pier F terminal with a fill
EAST BASIN
![Page 6: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/6.jpg)
Project Timing
● Estimated to start in Spring 2010
● Require approx. 4,800,000 cy of fill material
● Project will generate 2,200,000 cy
● Fills will accommodate an additional 2,600,000 cy from other Port and outside sources
● Window of opportunity for acceptance of third party fill material between late 2010 to mid 2012
![Page 7: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/7.jpg)
Sediment Management Plan
Goals● Illustrate Port’s decision process for sediment
management
● Define management priorities for contaminated and uncontaminated sediments
● Define procedures for the movement of sediment
● Guidance document for Port Engineering and Environmental Planning throughout the life of the project
● Living-document to be continually updated
![Page 8: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/8.jpg)
Sediment Management Plan
● Components include a description of the project, a fill plan, priority of acceptance of third party material, and environmental controls to protect water quality
![Page 9: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/9.jpg)
Nature of Fill Material
The Port will NOT accept material that:
1. Constitutes “hazardous waste” as termed by USEPA or CA DTSC
2. Deemed unsuitable for confined aquatic disposal by USEPA
3. Has or will have land use restrictions or other requirements imposed by DTSC or other regulatory agencies
![Page 10: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/10.jpg)
Third Party Fill Material Criteria
Acceptance of third party fill material based on four criteria:
1. Schedule– Delivery timing relative to fill construction progress
2. Fill Composition– Chemical and geotechnical nature
3. Documentation– Required permits, insurance, licenses, & agreements (MOA)
4. Fill Source– Geographic source of material
![Page 11: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/11.jpg)
Geographic Source Priority
1. From other elements of the project
2. From other POLB dredging projects
3. City of Long Beach material unsuitable for unconfined aquatic disposal
4. POLA remedial dredging projects material
5. City of Long Beach material suitable for unconfined aquatic disposal but cannot be beneficially re-used
6. POLA material unsuitable for unconfined aquatic disposal
![Page 12: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/12.jpg)
Geographic Source Priority
7. Western Anchorage Sediment Storage and Disposal Site
8. From dredging projects within Los Angeles County unsuitable for unconfined aquatic disposal
9. From dredging projects outside Los Angeles County unsuitable for unconfined aquatic disposal
10. POLA dredging projects suitable for unconfined aquatic disposal but cannot be beneficially re-used
11. Sand borrow from within the Port of Long Beach
![Page 13: Middle Harbor Redevelopment Project](https://reader035.vdocuments.us/reader035/viewer/2022062812/568163dd550346895dd5372a/html5/thumbnails/13.jpg)