KOUKAMMA MUNICIPALITY
MID - YEAR PERFORMANCE ASSESSMENT
REPORT
2015 / 2016
Due Date: 25 January 2016
![Page 2: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/2.jpg)
Mid-Year Performance Assessment Report 2015/2016
1. INTRODUCTION
In terms Section 72(1) (a) of the Municipal Finance Management Act No. 56
of 2003 the accounting officer must submit an assessment report on the
Municipalities Performance to the Mayor, National and Provincial Treasury by
the 25th of January each year.
2. PURPOSE
This report will serve as an update on the performance of Koukamma
Municipality for the first half of the financial year based on the predetermined
objectives as set out in the Integrated Development Plan (IDP) and the
Service Delivery Budget Implementation Plan (SDBIP) in conjunction to the
set Budget.
3. LEGISLATIVE REQUIREMENTS
Municipal Systems Act, 32 of 2000
Municipal Performance Regulations for Municipal Managers and Managers
Directly Accountable to Municipal Managers, 2006
Municipal Finance Management Act, 56 of 2003
MFMA Circular No. 13
Municipal Planning and Performance Management Regulations, 2001
4. PERFORMANCE PROCESS
The predetermined objectives as set out in the IDP are converted into
measurable objectives and indicators with set targets. Targets are set per
quarter. At the end of each quarter a departmental SDBIP with actual
performance against set targets are submitted and analysed by the person
accountable for reporting purposes.
The consolidated organisational quarterly report on performance is sent to
audit committee to verify correctness and is later submitted to MPAC and
Council for reporting and monitoring purposes.
![Page 3: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/3.jpg)
5. SDBIP 2015/16
KPA 1: Municipal Transformation and Institutional Development
Ref: Objectives Strategy KPI Annual Target
Quarter 1 Targets (July – Sept)
Actual Performance
Reason for variance and remedial Actions
Quarter 2 Targets
(Oct – Dec 2015)
Actual Performan
ce
Reason for variance and
remedial Actions
OPERATIONAL MTID/01 Improve
employee wellness and assistance programme for the 2015/16 Financial Year
Implement Employee wellness programme
Conduct 4 Employee Counselling on Social and health related problems 1) Alcohol abuse 2) Financial Planning 3) HIV/Aids 4) Women and Children abuse
Conduct 4 Employee Counselling Sessions for 2015/16 FY
Conduct 1 counselling sessions on alcohol abuse
1 counselling session on Alcohol Abuse conducted
1 counselling sessions on financial planning conducted
1 counselling sessions on financial planning conducted
MTID/02 Implement the Employment Equity plan for the first 6 months for the 2015/17 Financial
Implement equity in the work place
Implementation of 60% of numerical goals in the Employment Equity Plan
60% of Numerical goals in the Employment Equity Plan achieved
Achieve 15% of Numerical goals in the Employment Equity Plan
15% of the numerical goals in the EEP achieved
Achieve 15% of Numerical goals in the Employment Equity Plan
15% of the numerical goals in the EEP achieved
![Page 4: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/4.jpg)
Mid-Year Performance Assessment Report 2015/2016
Year MTID/03 Councillor
development for 11 councillors in the 2015/16 Financial Year
Implement skills development and training Support for Councillors
Facilitate 4 training programmes for Councillors 1) Project Management 2)Project Management 3)National Certificate through INTEC 4)National Certicate through INTEC
Facilitation of 4 Training Programmes for Councillors
Facilitate 1 training for Councillors on Project Management
1 Training for Councillors on Project Management facilitated
Facilitate 1 training for Councillors on Project Management
2 Trainings for Councillors on Coincillor Development Proggramme and Project Management
MTID/04 Reduction of litigation cases by 50% in the 2015/16 Financial Year
Respond to all issued summons and letters of demand
Reduce Litigation cases by 50% of the baseline of 2014/15 FY (14 Cases)
50% reduction of Litigation cases of the 2014/15 baseline
12.5% reduction of litigation cases
Achieved 12.5% reduction of litigation cases
Achieved
MTID/05 Human capital development to meet IDP objectives in the 2015/16 Financial Year
Implementation of Workplace skills plan
Implement 80% of the Training Implementation Plan
80% of the Training Implementation Plan implemented
Implement 20% of the Training Implementation Plan
20% of the TIP implemented
Implement 20% of the Training Implementation Plan
20% of the TIP implemented
MTID/06 Enhancement of Human Capital Development
Recruit 60 interns and learners
Recruit 60 interns and learners in the
Recruit 15 interns and learners in
15 interns and learners
Recruit 15 interns and learners in
35 Learners recruited
![Page 5: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/5.jpg)
Mid-Year Performance Assessment Report 2015/2016
through learnerships and internships
2015/16 Financial Year
Q 1 recruited Q 2
MTID/07 Upgrading of ICT Infrastructure in the 2015/16 Financial Year
Implementation of the ICT Business Plan
Upgrading of the ICT infrastructure based on the Business Plan 1) Installation of windows server 2) UPS installation 3) Intranet 4) Installation of retrofills
Upgrade 4 Infrastructure programmes based on the ICT business plan
Installation of windows server 2012
ICT Business Plan presented to Management for comments and submitted to SBDM to source funding
Installation of the UPS
UPS Installed
MTID/08 Establishment of Power Backup equipment in the server room in the 2015/16 Financial Year
Implementation of the ICT Business Plan
Installation of power backup equipment in the server room
facilitate the installation of power backup equipment in the server room
Table the proposal for Implementation of Power Backup equipment in the Server Room to management for comments
ICT Business Plan presented to Management for comments and submitted to SBDM to source funding
Source Funding for Installation of Power Backup Equipment for the server room from SBDM
Not Achieved
Awaiting Response from SBDM
MTID/09 Effective functioning
Improve oversight
Sitting of 4 Council
4 Seated Council
1 Council meeting
Special Council
1 Council meeting
Special Council
![Page 6: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/6.jpg)
Mid-Year Performance Assessment Report 2015/2016
of Council meeting for the 2015/16 Financial Year
function Meetings for 2015/16 FY
Meetings Meetings sat on 22/07; 7/08; Ordinary Council meeting sat on 27/08; Special Council meeting sat on 23/09
Meetings sat on 30/10; Ordinary Council meeting sat on 08/12
MTID/10 Effective functioning of Standing Committees for the 2015/16 Financial Year
Ensure the sitting of 20 Standing Committee Meetings for the 2015/16 FY
20 seated Standing Committee meetings per financial year
5 Standing Committees per 12 weeks
5 Standing Committee Meetings sat on 11/08(3); 24/08 (2);
5 Standing Committees per 12 weeks
4 Standing Committee Meetings sat on 13/10(4); 23/11; 24/11 (3);25/11 (1);
MTID/11 Effective functioning of MPAC in the 2015/16 Financial Year
Improved oversight role of MPAC
Sitting of 4 MPAC meetings for 2015/16 FY
4 MPAC meetings
1 MPAC Meeting
1 MPAC Meeting sat on 25/08
1 MPAC Meeting
1 MPAC Meeting sat on 03/12
MTID/12 Effective functioning of Audit Committee in the 2015/16
Improved advisory role to Council
Sitting of 4 Audit Committee meetings for the 2015/16 FY
4 Audit Committee meetings
1 Audit Committee meeting
1 Audit Committee meeting sat on 28/09
1 Audit Committee meeting
Not Achieved
Facilitate 1 Audit Committee Meeting
![Page 7: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/7.jpg)
Mid-Year Performance Assessment Report 2015/2016
Financial Year
MTID/13 Effective functioning of the Risk Management Committee in the 2015/16 Financial Year
Improved control environment
Sitting of 4 Risk Management meetings for the 2015/16 FY
4 Risk Management meetings
1 Risk Committee meeting
1 Risk Committee meeting sat on 29/09
1 Risk Committee meeting
1 Risk Committee meeting sat on 3/11
MTID/14 Effective functioning of ICT Steering Committee in the 2015/16 Financial Year
Improved oversight role of ICT Steering Committee
Sitting of 4 ICT Steering Committee meetings for the 2015/16 FY
4 ICT Steering Committee meetings
1 ICT Steering Committee meeting
1 ICT Steering Committee set on 30/09
1 ICT Steering Committee meeting
1 ICT Steering Committee set on 30/10
MTID/15
Effective functioning of the Local Labour Forum in the 2015/16 Financial Year
Improved oversight role of Local Labour Forum
8 LLF meetings for the 2015/16 FY
4 Healthy and Safety Committee meetings
1 Health and Safety Committee Meeting
Not Achieved
Conduct 1 Health and Safety Committee Meeting
1 Health and Safety Committee Meeting
1 Health and Safety Committee Meeting on 7/10
MTID/16 4 Skills Development Employment Equity Committee meetings
1 Skills Development Employment Equity Committee Meeting
Not Achieved
Skills Development Employment Equity Committee postponed and set on
1 Skills Development Employment Equity Committee Meeting
Not Achieved
Facilitate 1 Skills Development Employment Equity Committee Meeting
![Page 8: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/8.jpg)
Mid-Year Performance Assessment Report 2015/2016
8/10
MTID/17 Execution of Internal Audit Action Plan for the 2015/16 Financial Year
Implementation of Internal Audit Action Plan
Ensure 4 Audits carried out based on the Internal Audit Plan 1) ICT Audit 2) Assets Audit 3) HR Audit 4) SCM Audit
Execute 4 Audits based on the Internal Audit Plan
1 Audit ICT executed
1 ICT Audit Executed
1 Audit on Assets executed
1 SCM Audit Executed
Execute 1 Audit based on the Internal Audit Plan
MTID/18 Compilation of the Annual Report 2014/15
Ensure compliance to the MSA
Development of the Annual Report 2014/15 FY
Approved Annual Report for 2014/15 FY
Completion of the Draft Annual Report
Draft Annual Report Completed
Submission of the Draft annual report to Audit Committee
Draft Annual submitted to Audit Committee
![Page 9: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/9.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 2 - Basic Service Delivery and Infrastructure Investment (Technical Services)
Ref: Objectives Strategy KPI Annual Target Quarter 1 Targets (July – Sept)
Actual Performance
Reason for variance and
remedial Actions
Quarter 2 Targets
(Oct – Dec 2015)
Actual Performance
Reason for variance and remedial Actions
CAPITAL PROJECTS
TS/01 Effective water conservation and water demand management
Implementation of the recommendations from WC/WDM strategy
Reduction of 30% water losses in rand value
Reduce water losses by 30% in rand value
Reduce water losses by 5% through the repair of water leakage pipes in WTW in Coldstream
Lagging Action plan in place but no capacity for implementation
Reduce water losses by 10% through the replacement of water leaking elevated tank in Coldstream
Lagging Contractor appointed towards the end of November 2015
TS/02 Ensure water storage facility in Clarkson
Implementation of the WC and WDM
Installation of 256 water harvesting tanks in Clarkson
Install 256 water harvesting tanks in Clarkson
Install 125 rainwater haversting tanks in Clarkson
On Target Install 131 rainwater haversting tanks in Clarkson
On Target
TS/03 Ensure water storage facility in Krakeel
Implementation of the WC and WDM
Installation of 370 water harvesting tanks in Krakeel
Install 370 water harvesting tanks in Krakeel
Install 185 rainwater haversting tanks in Krakeel
Lagging Project commenced on the 05th October 2015
Install 185 rainwater haversting tanks in Krakeel
Lagging 81 tanks completed ,Contruction delays due to delaysin material delivery and weather
![Page 10: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/10.jpg)
Mid-Year Performance Assessment Report 2015/2016
conditions
TS/04 Effective water conservation and water demand management
Implementation of the Water Audit Report
Installation of 8000 Smart water meters
Install 8000 Smart water meters
Submit a business plan to source funding for Smart meter installation
On Target Submitted application to the Department of Budget and treasury
Follow up on funding application with DWAS and Treasury
Lagging Follow up correspodence to Department of treasury
TS/05
Effective Waste Management
Refurbishment of Louterwater WWTW (ponds)
100% completion of the Refurbishment of the Waste water works in Louterwater
100% Complete refurbishment of Louterwater WWTW by end of 2015/16 FY
Site clearance,draining of all ponds,remove sludge and clean out of interconnecting pipeworks
On Target Assessment done and submitted business plan to DWS
Construct new sludge beds,replacement of sewer reticulation mains
On target
TS/06 Refurbish RBC wasterwater works at Plantjiesdorp
100% Complete with the refurbishment of the Plantjiesdorp WWTW
100% complete with the Refurbishment of RBC wastewater works at Plantjiesdorp by end of 2015/16 FY
Conduct an assessment ot produce a technical Report
On Target Assessment done and submitted business plan to DWS
Plan and source funds for refurbishment of Plantjiesdorp WWTW
On target Business plan submitted to DWS for sourcing of funds
TS/07 Refurbishment of wastewater treatment
100% complete with the
100% Complete with the
Plan and Source funds for
On Target Assessment done and submitted
Procure service provider and
Lagging Business plan submitted
![Page 11: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/11.jpg)
Mid-Year Performance Assessment Report 2015/2016
componets in Tweereviere WWTW (Joubrtina)
Refurbishment of Wastewater treatment components in Tweeriviere to Improve compliance with green drop requirements for 2015/16
Refurbishment of wastewater treatment components at Tweereviere WWTW by end of 2015/16
refurbishment of treatment componets at tweeriviere WWTW
business plan to DWS
refurbish treatment components in Tweereviere WWTW
to DWS for sourcing of funds
TS/08
Upgrading and Rectification of
Houses in Cluster 1,2,3
Rectification of 500 houses in Cluster 1
Rectification of 500 houses in Cluster 1
Rectification of 500 houses in Cluster 1 in 2015/16 FY
Rectification of 50 houses
Lagging Awaiting feedback from Department of Human Settlement
Rectification of 150 houses
Lagging Awaiting feedback from Department of Human Settlement
TS/09 Rectification of 500 houses in Cluster 2
Rectification of 500 houses in Cluster 2
Rectification of 500 houses in Cluster 2 in 2015/16 FY
Rectification of 50 houses
Lagging Awaiting feedback from Department of Human Settlement
Rectification of 150 houses
Lagging Awaiting feedback from Department of Human Settlement
TS/10 Rectification of500 houses in cluster 3
Rectification of 500 houses in Cluster 3
Rectification of 500 houses in Cluster 3 in 2015/16 FY
Rectification of 50 houses
Lagging Awaiting feedback from Department of Human Settlement
Rectification of 150 houses
Lagging Awaiting feedback from Department of Human Settlement
TS/11 Provision of Formal Houses
Construction of destitute
Construction of 166
Construction of 166
Construction of 30
Lagging Awaiting feedback from
Construction of 45 destitute
Lagging Awaiting feedback
![Page 12: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/12.jpg)
Mid-Year Performance Assessment Report 2015/2016
in Informal Settlements
houses destitute houses
destitute houses in 2015/16
destitute houses
Department of Human Settlement
houses from Department of Human Settlement
TS/12
Improvement, Management
and maintenance
of Roads
Regravelling of Public Works roads
Regravelling and patching DR 1809(Walletjies -13km);DR1795 (Suuranys/Boplaas -18km);DR 1792 (Onverwagslaagte- 21km)
Total of 52kms of roads regravelled
13km regravelled and patched
Lagging Awaiting procurement process from Department of Roads and Public Works to appoint a service provider
13km regravelled and patched
Lagging Awaiting procurement process from Department of Roads and Public Works to appoint a service provider
TS/13 Upgrading of the R62
Upgrading of the R62
100% Complete with the Upgrading of the R62 Signage and Pothole patching
Replacement of Sign Boards on the R 62
On Target Road reserve bush clearance
On target
TS/14 Upgrading of Electrical Bulk infrastructure at kareedouw
Upgrading of the Substation and pole mounted transformer in Kareedouw
Upgrade the Substation and pole mounted transformer in Kareedouw
100% complete with the upgrding of the Substation and pole mounted transformer in Kareedouw
Procurement and appointment of service providers
Lagging In procurement
50% progress on construction of the projects
Lagging Still on procurement
![Page 13: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/13.jpg)
Mid-Year Performance Assessment Report 2015/2016
TS/15 Provision of Electricity in settlements of Komasbos and Hermanuskraal
Electrification of Koomasbos and Hermanuskraal
Coordinate the electrification of Koomasbos and Hermanuskraal
Electrification of 66 houses in Koomasbos and 20 houses in Hermanuskraal
Monitoring electrification of 20 houses Hermanuskraal
Lagging Awaiting appointment of service provider by Eskom
Monitoring the electrification of 66 houses in Koomasbos
Lagging Awaiting appointment of service provider by Eskom
TS/16 Provision of adequate Streetlighting
Reparation of streetlights in Coldstream and Clarkson
100% Complete with the repairs to Coldstream and Clarkson Street lights
100% Completion of repairs on the Coldstream and Clarkson Streetlights
50% Complete with the repairs of the Coldstream streetlights
Lagging Contractor still waiting for material to be provided by the supplier
95% Complete with the repairs of the Clarkson Streetlights
On target
OPERATIONAL
TS/17 Effective water conservation and water demand management
Construction of a Krakeel Water Storage Resevoir
Funding Application for the Construction of a Krakeel Water Storage Resevoir
Approved funding and Design of the Krakeel water storage resevoir
Follow up on application to RBIG
Lagging Continuos follow ups with the Department of Water and Sanitation and the project is in the RBIG masterplan
Approval of RBIG funding for the Misgund bulk supply
Lagging Continuous follow ups with the Department of Water and Sanitation and the project is in the RBIG master plan
TS/18 Create an enabling environment to provide bulk
Water Service Development Plan
Source RBIG funding to facilitate the bulk water
Approval of RBIG funding to facilitate the bulk water
Submit the final feasibility study with
Lagging Will be submitted next quarter
Confirm RBIG funding Approval through
on target
![Page 14: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/14.jpg)
Mid-Year Performance Assessment Report 2015/2016
water supply infrastructure network in Misgund
supply infrastructure network in Misgund
supply infrastructure network in Misgund
amendments to obtain RBIG funding approval
official correspondence by DWS
TS/19 Create an enabling environment to provide bulk water supply infrastructure network in Coldstream, Louterwater and Stormsriver
Water Service Development Plan
Source MIG funding to facilitate the bulk water supply infrastructure network in Coldstream, Louterwater and Stormsriver
Approval of MIG funding to facilitate the bulk water supply infrastructure network in Coldstream, Louterwater and Stormsriver
Submit MIG funding application to Cogta
Lagging Will be submitted next quarter
Develop and submit a technical report to support the MIG funding application to Cogta
On target
TS/20 Ensure complaince with water quality standards
monthly compliance monitoring and daily operational monitoring of wastewater quality at all wastewater works in Koukamma LM
100% compliance with National Water Quality Standards (SANS 241) throughout the year (2015/16)
100% complaince with SANS 241 water quality standards for the year 2015/16
100% compliance with water quality standards for all WTWs
Lagging July and August 2015 was 100% compliant but September 2015 was 85% compliant. Joubertina- had supply interruptions because of broken pipe. Coldstream- dosing pump not functional and currently applying
100% compliance with water quality standards for all WTWs
Lagging 64% compliance, Mandela Park and Coldstream WTW had a challenge of dosing pumps that were not functioning thus the failures
![Page 15: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/15.jpg)
Mid-Year Performance Assessment Report 2015/2016
chlorine manually
TS/21
Ensure compliance
with effluent discharge
authorisation conditions for all the systems
Replace callapsed small bore system with full water borne system in Clarkson, Woodlands, Stormsriver and Newrest
Source funding to Replace callapsed small bore system with full water borne system in Clarkson, Woodlands, Stormsriver and Newrest
Source Funding to replace Small bore system with a full water borne system in Clarkson, Woodlands, Stormsriver and Newrest
Assess and compile technical Report
Lagging Sites not assesed yet
Source funding from DWAS
Lagging
TS/22 Monthly compliance monitoring and daily operational monitoring of effluent quality at all wastewater works in Koukamma LM
100% compliance with effluent discharge conditions of all WWTWs throughout the year (2015/16)
100% complaince with effluent discharge conditions of all WWTWs for the year 2015/16
100% compliance with effluent discharge conditions for all WWTWs
Lagging Initiated the testing of effluent in September 2015,43% compliance, remedial action plan will be drawn up as per results
100% compliance with effluent discharge conditions for all WWTWs
Lagging 88% compliance, still have a challenge with waste works that do not have process controllers
TS/23 Improvement, Management and maintenance of Roads
Paving of all areas in Koukamma
Paving of all areas in Koukamma
Submission of Final Design Report to the Municipality
Source Funding
On Target To be presented at the next DAC in November 2015
N/A N/A N/A
![Page 16: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/16.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 2 - Basic Service Delivery and Infrastructure Investment (Community Services)
Ref: Objectives Strategy KPI Annual Target Quarter 1 Targets (July – Sept)
Actual Performance
Reason for variance and remedial Actions
Quarter 2 Targets
(Oct – Dec 2015)
Actual Performance
Reason for variance
and remedial Actions
CAPITAL PROJECTS
CS/01 Caring and Management of grave sites
Implementation of the Grave Policy
Extension of Krakeel R63 cemetery by adding 250 square meters area
Extension of the Krakeel cemetery by 250 square meters
Submission of an offer to Purchase to the Owner
On Target. Received an offer to sell from land owner
Submission of the report to council to approve the offer to purchase
Lagging Service provider to conduct the report will be appointed in January 2016
CS/02 Establish new Stormsriver cemetery
The Establishment of 1 new cemetery in Stromsriver
The construction of the phase two projects
Submission of a business plan to Cape Pine for financial assistant
On Target. Designing of the Plans for Construction of a portable ablution block ,paving and fencing
On Target Quotation requested from service providers
CS/03 Establish new Ravinia cemetery
The Establishment of 1 new cemetery in Ravinia
100% Complete with the planning the establishment of Ravinia cemetery
Submit request to National Government DR LDA for the transfer of the
Lagging. Will implement in second quarter.
Submit to council a report regarding status of Mooiuitsig farm
Lagging Last report submitted in the 2014/15 FY
![Page 17: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/17.jpg)
Mid-Year Performance Assessment Report 2015/2016
MOOIUITSIG FARM to koukamma municipality
CS/04 Provision of main Fire Station in Blekkiesdorp
Construction of a Fire Station in Blikkiesdorp
Complete the construction of a Fire Station in Blikkies dorp 2015/16
100% complete with the Fire Station construction in Blikkiesdorp (Sandrift)
Completion of the Blikkiesdorp Fire station (Sandrift)
Lagging Project will be completed in second quarter. Expected completion Date: 17 December 2015.
100% complete (Handing over and close out report of the project)
Lagging Project will be handed over in February 2016
CS/05 Provision of the Disaster centre in Blikkiesdorp
Construction of a Disaster Management Centre in Blikkiesdorp
Complete the construction of a Disaster Management Centre in Blikkies dorp 2015/16
100% completion of the Disaster Management Centre constructed in Blikkiesdorp
Completion of the Blikkiesdorp Disaster Management Centre (Sandrift)
Lagging Project will be completed in second quarter. Expected completion Date: 17 December 2015.
100% Complete (Handing over and close out report of the project)
Lagging Project will be handed over in February 2016
CS/06 Provision of satellite Fire Stations
Construction of satellite Fire Stations in Jouberina
Construct of 1 Satelite Fire Stations Joubertina
Construction of 1 satellite fire station in Joubertina
Identify the sites and seek council approval
On Target Develop the design for the Joubertina Satelite Stations
Lagging Funding approval has not been received
CS/07 Construction of satellite Fire Station in
Construct 1 Satellite Fire Stations
Complete with the construction
Identify the sites and seek
On Target Upgrading of the Joubertina existing
Lagging Funding approval has not
![Page 18: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/18.jpg)
Mid-Year Performance Assessment Report 2015/2016
Kareedouw Kareedoouw of 1 new satelite fire station in Kareedouw
council approval
buildings been received
CS/08 Upgrading of the Joubertina Drivers License and Test Station
Upgrading of the Drivers License and Testing Centre
Upgrade the Joubertina DLTC in 2015/16 FY
100% Complete with the upgrade of the DLTC in Joubertina
100% Completion of the construction and handover to KKM
Not Achieved
Project will only be concluded at the end of October
N/A N/A Project was completed in December and will be handed over in January 2016
CS/09 Conversation and management of natural Environment
Close and Rehabilitate the Landfill sites at Clarkson
Close and Rehabilitate 1 Landfill site at Clarkson
Closure and rehabilitation of 1 Landfill site in Clarkson
Removal of alien vegetation and cleaning of the wetland by removing grossly dumped refuse
On Target N/A N/A N/A
CS/10 Close and Rehabilitate the Landfill sites at Uitkyk
Close and Rehabilitate 1 Landfill site at Uitkyk
Closure and rehabilitation of 1 Landfill site at Uitkyk
Closure and filling of the existing uitkyk landfill site cells
Lagging. Submitted busness plan, but no response as yet
Busy following upp: will report in next quarter.
Provide cover material and Level the landfill site cells ,put no dumping signs and close the site permanently
Target Achieved
CS/11 Provision of Compliance to Conduct Inspection of Inspection On Target Inspection of 20 On Target
![Page 19: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/19.jpg)
Mid-Year Performance Assessment Report 2015/2016
adiquate effective and efficient Municipal Services
Environmental Health Legislation
inspection of 35 Business Premises, 20 dwellings that keep animals and 3 health sessions on Communicable disease
35 Business Premises, 20 dwellings that keep animals and 3 health sessions on Communicable disease
of 15 business premises in the KKM area and provision certificate of acceptability
business premises in the KKM area and provision certificate of acceptability
CS/12 Provision of Coastal Managemnet services
Implementation of the Intergrated Coastal Management Act
Improvement coastal environment
Management of the coastal environment
Submission of the business plans to DEA requesting financial assistance
Lagging Implementation of W.F.T.C. Project will commence in November 2015 only. Furthermore, DEA pointed out at that an agreement between the Oceans and Coast Department and the owners of Eersterivier and Skuitbaai Trusts first have to be
Submit to council a report regarding status of the approved funding and milestone to be implemented
Lagging DEA advised that an agreement between the Oceans and Coast Department and the owners of Eersterivier and Skuitbaai Trusts must first be finalised before we can commence with this project
![Page 20: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/20.jpg)
Mid-Year Performance Assessment Report 2015/2016
finalised.
CS/13 Provision of Libraries services
Provision of Ravinia Library
Upgrade the Ravinia Library
100% complete with the upgrading of the Ravinia Library
Commence with the upgrade of Ravinia Library
Lagging Legal issue regarding the occupation rights at the building needs to be finalised first.
Handing over and Close out Report
Lagging Legal issue regarding the occupation rights at the building need to be finalised first
CS/14 Construction of Kareedouw Library
Construction of the Kareedouw Library
100 % complete with the Kareedouw Library
Facilitate the appointment of a service provider
On Target. Procurement processes have been instituted by the Department of Public Works. The succesful contractor will be appointed during the second quarter.
An official hand over of the site to the newly appointed service provider .
Lagging Service provider was appointed by DSRAC and DPW. Work will commence in the 3rd Quarter
CS/15 Consrtuction of Stormsriver West Library
Construction of the Stormsriver Library
100 % complete with the Stormsriver Library
Handing over and Close out Report
Lagging Slow progress by contractor
Submit the progress report to Council
Lagging Slow progress by contractor
CS/16 Provision of Construction of Complete 100% 100% Lagging Slow N/A N/A N/A
![Page 21: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/21.jpg)
Mid-Year Performance Assessment Report 2015/2016
the Multi-Purpose Centre Services
Misgund MPCC the Misgund MPCC
complete with the construction of the Misgund MPCC
Complete (Handing over and close out reportof the Misgund project )
progress by contractor
CS/17 Construction of Ravinia MPCC
Complete the Ravinia MPCC
100% complete with the construction of the the Ravinia MPCC
100% Complete (Handing over and close out reportof the Ravinia project)
Lagging Slow progress by contractor
N/A N/A N/A
CS/18 Construction of MPCC in Coldstream
Complete of the Coldstream MPCC
100% complete with the construction of the Coldstream MPCC
100% Complete (Handing over and close out report of the Misgund project)
On Target N/A N/A N/A
CS/19 Provision of Play Parks 1 Misgiund 1 Kareedouw and Establish 8 new play parks to KKM Human
Construct a Playpark in Misgund
Construct 1 Playpark in Misgund
1 playpark in Midgund
Submit Requests to Sea View Construction to construct a new Misgund
On Target Submit to council a report regarding s the approval of the Misgund donation
Lagging No notification of approval of project was received
![Page 22: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/22.jpg)
Mid-Year Performance Assessment Report 2015/2016
Settlement Playpark
CS/20 Establishment of Recreational Facilities in all other Human Settlements
Facilitate the establishment of Recreational Facilities in 8 Human Settlements
Establishment of Recreational Facilities in 8 Human Settlements (Coldstream, Stormsriver, Mandela Park, Woodlands, Clarkson, Ravinia, Louterwater, Krakeel)
Submission of a Business plan requesting for funding for the 8 KKM Human Settlement and submitting letters to the Seaview Civils
On Target Submit to council a report regarding s the request to Human settlement
Lagging No notification of approval of project was received
CS/21 Re-construction of the Playpark in Kareedouw
Construct 1 Playpark in Kareedouw
100% complete with the construction of 1 Playpark in Kareedouw
N/A Lagging Project will be undertaking upon appoint new contractor
N/A N/A N/A
CS/22 Upgrading of the existing sportfields
Upgrading of Kareedouw sports field
100% complete with the upgrading of Phase 2 Kareedouw sportefield
100% completed the upgrading of Phase 2 Kareedouw sportefield
Complete the upgrading of the Kareedouw 2nd Sports Field
Lagging Submitted business plan to Dept of Human Settlements and MIG
100% Complete (Close out report and handing over of the Sports Field)
Lagging No notification of approval of project was received
CS/23 Upgrading of the Woodlands Sportsfield
Upgrade the Woodlands Sportsfield
100% Complete with the upgrade of
100% complete (Handing
Lagging Slow progress from
N/A N/A N/A
![Page 23: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/23.jpg)
Mid-Year Performance Assessment Report 2015/2016
the Woodlands Sports field
Over and close out report)
contractor
CS/24 Upgrading of the Ravinia Sports field
Upgrade the Ravinia Sports field
100% Completion of the Ravinia Sports field, handing over and closeout Report
100% Complete (Handing Over and closeout report)
Lagging Slow progress from contractor
N/A N/A N/A
CS/25 Upgrading of the Krakeel Sportsfield
Complete the upgrading of the Krakeel Sportsfield
100% Complete with the construction of an ablution block and the upgrading of the Krakeel Sports field
Submission of a Business plan to sourcing funding from Cenergi
On Target Submit to council a report regarding status of upgrading of Krakeel sportsfield
Lagging Cenergi advised that their priorities have changed
CS/26 Upgrading of the Harmanuskraal sportsfield
Complete the upgrading of the Harmanuskraal sportsfield
100% Complete with the erection of ablution blocks and upgrading of the Hermanuskraal Sports field
Submission of Business plan to Human Settlement
On Target Submit to council a report regarding status of upgrading of Harmanuskraal sportsfield
Lagging Submitted scope of works with the business plan to MM
CS/27 Upgrading of the Clarkson Sportsfield
Complete the upgrading of the Netball
100% complete with the Resurfacing,
Submission of a Business plan to
On Target Submit to council a report regarding status of upgrading of
Lagging Submitted scope of works with the
![Page 24: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/24.jpg)
Mid-Year Performance Assessment Report 2015/2016
field and the construction of Basket ball court in Clarkson
Painting and erection of ablution blocks at the clarkson Netball and Basketball Count
sourcing funding from Cenergi
Clarkson sportsfield
business plan to MM
OPERATIONAL
CS/28 Upgrading of Community Halls
Upgading of Woodlands Community Hall
Source funds for the Upgrading of Woodlands Community Hall
Source funds for the upgrade the Woodlands Community Hall
Submission of funding application to MIG
On Target N/A N/A N/A
CS/29 Improve Joubertina Drivers License and Test Station Operations
100% collection on fine issued ensuring collection on Vehicle test and Licesings
Improve the building used for revenue collection for 2015/16
Improved revenue collection facility
Commencing the construction of the Joubertina DLTC
On Target Submit to council a report regarding status of upgrading of Joubertina DLTC
On Target – Went to council in December 2015
CS/30 Provision of Waste Managemnet services
Review the intergrated waste management plan
Facilitate the reviewal of the Intergrated Waste Management Plan
IWMP reviewed and Implemented in 2015/16
Conduct a Gap analysis on the Intergtrated waste management plan of KKM
Lagging. Sarah Baartman District informed Koukamma Municipality that tghey (SBDM) has resolved to appoint a service provider to
Submission of a Draft Intergrated Waste Management Plan with Recommendations to KKM council via IDP for approval
On Target
![Page 25: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/25.jpg)
Mid-Year Performance Assessment Report 2015/2016
develop IWMP's for locals
CS/31 Improvement of Waste Removal Services
Upgrade the woodlands and Tweeriviere landfill sitesand improve the operations
Re-establishment and construction of tweeriviere and woodlands landfill sites
Source funding for the re-establishment of the tweeriviere and woodlands landfill sites
Submission oof business plan for sourcing of funding to MISA,DEDEAT and DEA
On target. Developed business plan and submitted to DEA, MIG and SBDM as funding proposal. Await response
Submission of Progress Report to council
On Target Operational license has been issued by DEA
CS/32 Facilitate establishment of the transfer stations of the at Louterwater and Coldstream ,Kareedouw ,Clarkson
Facilitate establishment of the transfer stations of the at Louterwater and Coldstream ,Kareedouw ,Clarkson
Source Funding for the establishment of new transfer stations and recycling centres
Develop a business plan and submit to MISA,DEDEAT and DEA requesting funding
On Target Identify suitable land for establishment of Transfer Station
On Target Louterwater and Coldstream sites are closed. Waste dumped at Tweeriviere and Woodlands respectively. Entered into SLA with land owner in Kareedouw for the establishment of the
![Page 26: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/26.jpg)
Mid-Year Performance Assessment Report 2015/2016
new site.
CS/33 Provision of adequate effective and efficient Municipal Services
Development of Municipal Health strategies and Operational plan
Development of Municipal Health strategies and Operational plan for 100% compliance of water standarts through the testing of Drinkable Water Sources
Developed Municipal Health strategies and Operational plan for 100% compliance of water standarts through the testing of Drinkable Water Sources
Testing of Palatable Water Sources to meet the acceptable standards
On Target Testing of Palatable Water Sources to meet the acceptable standards
On Target
CS/34 Provision of the Multi-Purpose Centre Services
Construction of Stormsriver MPCC
Appoint a Construction company to complete the construction of the Stormsriver MPCC
Appointment of a Construction company to complete the Stormsriver MPCC
Submission of MIG application for Registration and approval with MIG
On Target Submit MIG outcome to council for noting
Lagging No notification of approval of project was received
![Page 27: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/27.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 3 -Local Economic Development
Ref: Objectives Strategy KPI Annual Target Quarter 1 Targets (July
–Sept)
Actual Performance
Reason for variance and remedial Actions
Quarter 2 Targets
(Oct – Dec 2015)
Actual Performan
ce
Reason for variance and
remedial Actions
CAPITAL PROJECTS
LED/01 Ensure a functional Honey Bush Tea Project
Fully operational plant, harvesting and packaging of 5 tons honeybush for 2015/16 FY
Ensure a functional Honey Bush Tea Project
Fully operational plant, harvesting and packaging of 5 tons honeybush for 2015/16 FY
Launch of a fully-functional processing plant
Lagging LRED funding proposal not yet approved.
5 tons harvested as per the estimates on the business plan
Lagging Fully- Functional Proccessing Plant not completed due to delays in the approval of the LRED funding
LED/02 Ensure the establishment of an operational Essential Oil processing plant
100% Operational Essential Oils Project
Ensure the establishment of an operational Essential Oil processing plant
100% Operational Essential Oils Project
Official Launch of Essential Oils Project in Woodlands
Lagging Termination of the mentorship programme by SBDM
Solicit funding for the development of a fully-fledged processing plant
Lagging Cooperative failed to submit a close-out report to DEDEAT
LED/03 Implementation of the Mixed Development Concept on Farm 496
100% implementation of the mixed-development concept on Farm 496 for 2015/16
Implementation of the Mixed Development Concept on Farm 496
100% implementation of the mixed-development concept on Farm 496 for 2015/16
Appointment of the Developer for the mixed-development on farm 496 in
Lagging Developer not yet appointed
Final Business plan submitted and adopted by council
Lagging Appointment of a competitive developer not yet finalized
![Page 28: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/28.jpg)
Mid-Year Performance Assessment Report 2015/2016
Tsitsikamma
LED/04 Implementation of the Agro Processing Plant in the Langkloof
100% Implementation of the Agro Processing Plant
Implementation of the Agro Processing Plant in the Langkloof
100% Implementation of the Agro Processing Plant
Appoint Developer for the Agri-processing plant
Lagging Developer not yet appointed
Submit Final write-up concept on agro-processing plant to council
Lagging Koukamma has entered into an agreement with Centre for Small Town Regeneration (CSTR) for the development of Business Plans for all Capital Projects. Business plans will be submitted to Council upon completion.
LED/05 Implement the 5 Hectare Vegetable Production Project
5 hectares of vegetables plantation
Implement the 5 Hectare Vegetable Production Project
5 hectares of vegetables plantation
Appointment of the consultant
Lagging Consultant not yet appointed
Planning and Design
Lagging Business Plan not yet developed due to lack of funds for the appointment of a competent Consultant
LED/06 Coordinate the 20 Hectare Medicinal Plantation Project
20 Hectares of Herbal Medicinal Plantation
Coordinate the 20 Hectare Medicinal Plantation
20 Hectares of Herbal Medicinal Plantation
Official Launch of Herbal Medicinal Plants
Lagging Funding not yet transferred to the account of PHM
7 hectares plantation
Lagging Pure Herbal Medicine (PHM) and African Enterprise
![Page 29: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/29.jpg)
Mid-Year Performance Assessment Report 2015/2016
Project Project Network are in the process of soliciting investment from Industrial Development Corporation (IDC)
LED/07 Ensure Youth Development through the implementation of the Youth Brick and Paving Coorperative
100% implementation of the Youth Brick and Paving Cooperative
Ensure Youth Development through the implementation of the Youth Brick and Paving Coorperative
100% implementation of the Youth Brick and Paving Cooperative
Business Plan Developed
Lagging Consultant not yet appointed
Business Plan adopted by Council
Lagging Business Plan not yet developed due to lack of funds for the appointment of a competent Consultant
LED/08 Coordinate the Huisklip hand-over to Koukamma
Appointment of a developer for Huisklip nature reserve
Coordinate the Huisklip hand-over to Koukamma
Appointment of a developer for Huisklip nature reserve
Stakeholder engagement on the development of Huisklip nature reserve
Lagging Consultant not yet appointed
Table the refined Huisklip nature reserve development concept to management
Lagging Koukamma has entered into an agreement with Centre for Small Town Regeneration (CSTR) for the development of Business Plans for all Capital Projects. Business plans will be submitted to
![Page 30: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/30.jpg)
Mid-Year Performance Assessment Report 2015/2016
Council upon completion.
LED/09 Implementation of the Small Scale Fisheries concept for 2015/16 Fy
Issuing of permit to recreational fishers and the development of a Management Plan for all fishery management areas
Implementation of the Small Scale Fisheries concept for 2015/16 Fy
Issuing of permit to recreational fishers and the development of a Management Plan for all fishery management areas
Approval of funding for pedestrian bridge in Eersterivier
Lagging Office of the Mayor deals with this project
Issuing out of permits to recreational fishers.
Lagging The Office of the Mayor regularly interact with the office of the Minister of the Department of Agriculture, Forestry and Fisheries.
LED/10 Implementation of a vegetable plantation in Koomansbos
100% implementation of the vegetable plantation in koomansbos 2015/16
Implementation of a vegetable plantation in Koomansbos
100% implementation of the vegetable plantation in koomansbos 2015/16
Stakeholder engagement on the development of a Landcare Programme in Koomansbos
On Target 1st Round of Stakeholder engagement conducted
Table a comprehensive business plan for council approval
Lagging Business Plan not yet developed
LED/11 Coordinate the implementation of the biochar product project
Biochar product production
Coordinate the implementation of the biochar product project
Biochar product production
Investigate alternative business opportunities for the sawdust in Kareedouw
Lagging Loss of intrest by JNS Manufacturing Pty (Ltd).
Table proposals on the Biochar production concept for council approval
On target - Tabled to council on the ………….
LED/12 Creat local jobs through EPWP
Create 116 local Job opportunities through EPWP 2015/16
Creat local jobs through EPWP
Create 116 local Job opportunities through EPWP 2015/16
Appoint 116 unemployed people in Koukamma through
On target 52 EPWP Casuals and 1 Data Capturer appointed
Implement EPWP Business - Cut grass and collect refuse
On target 52 EPWP Casuals and 1 Data Capturer appointed
![Page 31: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/31.jpg)
Mid-Year Performance Assessment Report 2015/2016
EPWP in all areas
LED/13 Commercialize Honey Bush Tea Project and ensure local beneficiation for the 2015/16 financial year.
Implementation of the business plan on honey bush tea
Establishment of a agri-tourism centre
Functional Agri-tourism centre
Official Launch of a fully-functional Agri-tourism centre
Lagging LRED funding proposal not yet approved.
Full implementation
Lagging Fully- Functional Proccessing Plant not completed due to delays in the approval of the LRED funding
OPERATIONAL
LED/14 Facilitate funding Support for the recycling cooperative in Coldstream for the 2015/16 financial year.
Implementation of the LED Strategy
Secure funding for the Recycling cooperative in coldstream 2015/16
Secure R200,000.00 for the recycling cooperative in coldstream
Submit Business Plan to secure funding for the recycling cooperative in Coldstream
Lagging Funding proposal not submitted
Approval of funding based on the business plan for the recycling cooperative in Coldstream
Lagging Funding appication submitted to DEDEAT but no progress on application as yet.
![Page 32: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/32.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 4 - Financial Viability and Management and Sustainability
Ref: Objectives Strategy KPI Annual Target Quarter 1 (July – Sept)
Actual Performance
Reason for variance and remedial Actions
Quarter 2 Targets
(Oct – Dec 2015)
Actual Performan
ce
Reason for variance and
remedial Actions
OPERATIONAL
FV/01 Establishment of a Cuctomer Care System
Establishment of a Cuctomer Care System
Establisment of a fully functional customer care centre for the 2015/16 FY
Attending to 100% queries within 14 Days after query logged
Establishment of the Customer call centre
Care centre estrablised. Register compiled. Printed query forms created.
Intergration of the exisitng iCOMMS call system with the customer care centre systems
Achieved. 1 System in place
FV/02
Improvement of the revenue
collection rate for the 2015/16 Financial year
To comply with the
MFMA and Municipal
Property Rates Act
Ensure a 50% Increase in Revenue collection
Increase Service Revenue collection of R3 483 327 by 50% for 2015/16
12.5 % improvement on revenue Collection for Services
Collection for this period R691 805. Should be R1 306 247
12.5 % improvement on revenue Collection for Services
Collection for this period R1 325 460 . Should be R1 306 247. Achieved
FV/03 Increase Rates Revenue collection of R5 719 174 by 50% for 2015/16
12.5 % improvement on revenue collection on rates
Collection for this period R1 235 038. Should be R2 144 690.
12.5 % improvement on revenue collection on rates
Collection for this period R3 962 359. Should be R2 144 690. Achieved
FV/04 Increase Traffic Fines Revenue collection of
12.5 % improvement on revenue collection for
R254 100 Traffic Fines collected. Achieved
12.5 % improvement on revenue collection for
R351 136 Traffic Fines collected
![Page 33: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/33.jpg)
Mid-Year Performance Assessment Report 2015/2016
R671 463 by 50% for 2015/16
Traffic Fines increase of 50% of collection for 1st Quarter should have been R251 798
Traffic Fines this quarter, total collected R605 236. Achieved increase of 50% of collection for 2nd Quarter should have been R503 597
FV/05 Implementation of the Valuation roll
To comply with the municipal rates act and its amendments
Ensure 100% implementation and finalisation of the valuation roll
100% completed valuation roll
Publish the valuation roll to call for objections
Not achied. GV only completed and presented to the MM after end of quarter.
Receive, record and refer objections to the appeal board
GV Completed, objections called. Awaiting valuator’s response to objections received. Referral to appeal board not achieved.
The GV was completed late, only after first quarter. Legislation require that objections must be called within a specific timeframe. This could not be achieved.
FV/06 Improve the Fleet Management System
Managing and reporting on Council Fleet
Managing and reporting on Council Fleet
12 Reports on Fleet Management submitted to
Submission of 3 reports (July, Aug, Sept) on
Report completed and submitted
Submission of 3 reports (Oct, Nov, Dec) on Fleet
Achieved
![Page 34: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/34.jpg)
Mid-Year Performance Assessment Report 2015/2016
on a monthly basis
council for the 2015/16 FY
Fleet Management to Council
Management to council
FV/07 Minimize over expenditure of votes
Implementation of the Virement policy
Ensure implementation of the Virement Policy for 2015/16 FY
100% maintained budget virement Register
Train PA's on how to check available budget and set-up Promun to cap votes
Promun loaded for all PA's. PA's were trained how to use it.
Set up a budget virement register
Register for Q1 done and signed by Mayor, Q2 to be provided by 30 January
FV/08
GRAP compliant Submissions in
accordance with the MFMA
Accurate Reporting in Compliance
with Legislation
Submission of accurate
Grap compliant
AFS
Oversight Report Submitted to Council and Treasury
Submit accurate GRAP compliant AFS to AG
Achieved Develop a draft audit action plan based on AG findings
Draft action plan developed, will be tabled to council on the 25 January 2016
FV/09 Populate the Schedule B returns and submit to treasury
Submit pre-audited Schedule B to Provincial and National Treasury
Achieved Populate the Schedule B returns and submit to treasury
Submitted to the National and relevent Provincilal Treasuries.
FV/10 Quarterly financial reporting to Treasury
Submission of accurate Section 52 Reporting
Submit section 52 report for Jul - Sept 2015
Information still outstanding
Submit section 52 report for Oct - Dec 2015
In progress. Q1 completed.
Sept 2015 information wil only be available during the next Q
![Page 35: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/35.jpg)
Mid-Year Performance Assessment Report 2015/2016
FV/11 Monthly financial Reporting to Treasury
Submission of accurate Section 71 Reporting
Submit monthly section 71 Reports (July, Aug, Sept)
Information still outstanding
Submit monthly section 71 Reports (Oct, Nov, Dec)
In progress. Q1 completed.
Dec 2015 information wil only be available during the next Q
FV/12 Submission of section 72 Reports
Submission of accurate section 72 Reporting
N/A N/A N/A N/A
FV/13 Compile and submit SCOA report in line with the MFMA
Compile and submit SCOA report in line with the MFMA
SCOA Compliant Financial System and Final Budget
SCOA Compliant Financial System and Final Budget
Upgrade Promun to generate mSCOA compliant financial reports
Not achievable. These reports have to be in current format till 2017.
Map out the KKM chart of accounts to mSCOA protocols
Not achieved.
Promun not upgraded due to financial constraints, therefore mapping cannot proceed.
FV/14 Annual Budget compiled in line with the MFMA
Compilation and submission of the Annual Budget
Submission of Final Budget to Council and Treasury for 2016/17
Submission of Final Budget to Council and Treasury for 2016/17
Submit a budget plan linked to the IDP for Council Approval
Achieved Compare Budget baseline 2014/15 against 2013/14 and develop a forecast budget for 2015/16, 2016/17 and 2017/18
s72 report to be tabled to council 25 January 2016
FV/15 Adjustments Budget
Compilation of Adjustments
Submission of
Submission of Adjustments
N/A N/A N/A N/A
![Page 36: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/36.jpg)
Mid-Year Performance Assessment Report 2015/2016
compiled inine with the MFMA
Budget Adjustments Budget to Council and Treasury
Budget to Council and Treasury
FV/16 MFMA and Supply Chain Management Compliance
Supply Chain reporting and management
as per the MFMA
Submission of Quarterky SCM reports
Accurate Quarterly SCM Reports submitted to Council
Submit quarterly SCM reports to Council (July - Sept 2015)
Achieved Submit quarterly SCM reports to Council (Oct - Dec 2015)
Achieved
FV/17 Improve the Management of Awarded Contracts
Performance Assessment of Appointed Contractors based on Contract Agreements
Performance Assessment of Appointed Contractors based on Contract Agreements
Assess Performance of appointed contractors based on contract agreements
Performance of contractors reviewed. Report submitted.
Assess Performance of appointed contractors based on contract agreements
Performance of contractors reviewed. Report submitted.
FV/18 Improve SCM Review the SCM policy in line with the MFMA
Reviewal of the SCM Policy
Final SCM Policy
Identify Policy areas for review
Policy reviewed, no amendments required
Identify Policy areas for review
Policy reviewed, no amendments required
![Page 37: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/37.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 5 - Good Governance
Ref: Objectives Strategy KPI Annual Target Quarter 1 Targets (July –
Sept)
Actual Performance
Reason for variance and remedial Actions
Quarter 2 Targets
(Oct –Dec 2015)
Actual Performance
Reason for variance
and remedial Actions
CAPITAL PROJECTS
GG/01 Nelson Mandela Day Celebration
Celebrate Nelson Mandela Day in July 2015
Coordinate the Nelson Mandela Day in Kareedouw
Nelson Mandela Day Celebration 2015/16
Nelson Mandela Day Celebration on the 17th of July 2015
On Target - Nelson Mandela Day held on the 18th July 2015
N/A N/A N/A
GG/02 Womens Day Celebration
Celebrate Womens Day in August 2015
Coordinate the Womens Day Celebration in Koukamma for 2015/16
Womens Day Celebration for 2015/16
Womens day Celebration to be held in August 2015
On Target - Womens day Celebration held on the 25th Aug 2015
N/A N/A N/A
GG/03 16 Days Of Activism Celebration
Celebrate 16 Days of Activism in November 2015
Coordinate the 16 Days of Activism Celebration in Koukamma for2015/16
16 Days of Activism Celebration in Koukamma for2015/16
N/A N/A 16 Days of Activism Celebrations in 25th November 2015
On Target - Held on the 26th November 2015
GG/04 World Aids Day Awareness Campaign
World Aids Day Campaign in December 2015
Coordinate the World Aids Day Canpaign in Koukamma for 2015/16
World Aids Day Campaign in Koukamma for 2015/16
N/A N/A World Aids Day Campaign in December 2015
On Target - Held on the 10 December 2015
![Page 38: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/38.jpg)
Mid-Year Performance Assessment Report 2015/2016
GG/05 Event for the Disabled
Event for the Disabled in October 2015
Coordinate a event for the Disabled in October 2015
Disabled Event 2015/16
N/A N/A Event for the Disable in Koukamma in October 2015
On Target - collaboration with the 16 Days of Activism held on the 26th November 2015
GG/06 Elderly Golden Games
Collaboration with Social Development in preparation for the Elderly Golden Games
Coordinate the Golden Games in May 2016
Golden Games 2015/16
N/A N/A N/A N/A N/A
OPERATIONAL
GG/07 IDP Review Development for the 2016/17 financial year in 2015/16 financial year.
Implementation of the Municipal Systems Act
Facilitate the Reviewal of the 1016/17 IDP
Final of the reviewed IDP 2016/17
Conduct Situation Analysis of adopted IDP 2015/16
Lagging Situation Analysis only due in Quarter 2. IDP process plan has been developed.
N/A N/A N/A
GG/08 Functional Mayoral Imbizo's in the Koukamma area 2015/16
Implementation of the Municipal Systems Act
Conduct 4 Mayoral Imbizos for 2015/16
Conduct 4 Mayoral Imbizo's for 2015/16 FY
Conduct 1 Mayoral Imbizo
Not Achieved Roadshows will start in Quarter 2
Conduct 1 Mayoral Imbizo
Not Achieved
GG/09 Functional Ward Committees throughout
Implementation of the Municipal Systems Act
Conduct 12 Ward Committee Meetings For
12 Ward Committee Meetings for 2015/16
Conduct 3 Ward Committee Meetings
On Target Conduct 3 Ward Committee Meetings
On Target
![Page 39: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/39.jpg)
Mid-Year Performance Assessment Report 2015/2016
Koukamma 2015/16
2015/16 FY
GG/10 Develop and institutionalize innovative performance management systems for the organization for the year 2015/16.
Comply with PMS Regulations
Ensure that all Performance Requirements adhered to for 2015/16
Ensure that all Institutional Performance measures are in place and operating for 2015/16 FY
Introduction of the PMS system and user training with Directors
OnTarget - introduction to the System and PMS login details provided at the ICT steering committee meeting held on the Sept 2015
N/A N/A N/A
GG/11
Improve Performance Management
Systems
Comply with PMS
Regulations
Ensure that Peformance reviews are conducted for each quarter
Coordinate 4 Performance Reviews
Conduct 2014/15 Quarter 4 Performance review
On Target- 4th Quarter and Annual Performance Reviews Conducted
Conduct quarter 1 Performance Review
Lagging Quarter 1 reviews were conducted in time, but due to changes on the SDBIP and PMS system the information was removed. Needs to be redone.
GG/12 Consolidate 4 SDBIP quaterly reports
SDBIP 4th Quarter Report for 2014/15
4th Quarter SDBIP information consolidated
SDBIP 1st Quarter Report for 2015/16
1st quarter PMS report was done and sent to
![Page 40: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/40.jpg)
Mid-Year Performance Assessment Report 2015/2016
and POE's available
council and to Audit Committee on the 14 January 2016
GG/13 Provide an Old Age Home for the elderly of Koukamma
Establishment of an Old Age Home in Kareedouw
Coordinate the Establishment of the Old Age Home in Kareedouw
Registration of Old Age Home for Kareedouw
Election of a Governing Body/Steering Committee
On Target - Governing body established
Registration of the NPO
Registered with Social Development on the 08/12/2015
Christmas Party was held for the elderly in KKM on the 22/12/2015
GG/14
Generate publicity and awareness
through communication platforms for 2015/16
financial year.
Implementation of the
Communication Policy
Develop a Municipal newsletter
Develop 3 newsletters for 2015/16 FY
N/A done 1 newsletter Lagging Draft newsletter was presented and is still awaiting approval
GG/15 Arrange Radio Slots
Arrange 8 Radio Slots for 2015/16 FY
Arrange 2 radio slots
5 Radio Slots Arranged
Arrange 2 radio slots
4 radio slots arranged
GG/16 Facilitate Press releases
12 Articles for 2015/16 FY
Place 3 Articles
4 Articles placed
Place 3 Articles
4 press releases
GG/17 Develope a Facebook page
Upload 48 social media updates on the FB page for the 2015/16 FY
12 social media updates on Facebook page
10 Social Media Updates on FB
New page opened in July 2015 - more uploads to the page once it is fully
12 social media updates on Facebook page
14 social media updates
![Page 41: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/41.jpg)
Mid-Year Performance Assessment Report 2015/2016
operating
GG/18 Development and updating of a newsroom page
12 news items uploaded on the page for 2015/16 FY
Upload 3 items on Newsroom page
4 Newsroom Updates
Upload 3 items on Newsroom page
3 items uploaded
GG/19 Respond to 100% of the queries that relate to the municipality by the end of the 2015/16 financial year.
Update the presidential hotline on a daily basis.
Facilitate the Complaints Resolution Process
Resolve 100% of the Complaints Lodged in 2015/16
Resolve 100% of the complaints on the system for Quarter 1
not done- research period lapsed and no personnel to capture the complaints
Dedicated Person needs to be placed to control ICOMMS
Resolve 100% of the complaints on the system for Quarter 2
Lagging - research period lapsed
![Page 42: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/42.jpg)
6. ANALYSIS OF MID YEAR PERFORMANCE
KPA 1: MUNICIPAL TRANSFORMATION AND INSTITUTIONAL DEVELOPMENT
Number of projects = 18
Quarter 1 Quarter 2
Number of projects On Target/Completed
16 15
Number of projects Lagging/Not started
2 3
Number of projects not applicable this quarter
0 0
Percentage on Target
88.88% 83.33%
Percentage lagging
11.12% 16.67%
Percentage not applicable
0 0
KPA 2: BASIC SERVICE DELIVERY AND INFRASTRUCTURE INVESTMENT
(TECHNICAL SERVICES)
Number of projects = 23
Quarter 1 Quarter 2
Number of projects On Target/Completed
7 7
Number of projects Lagging/Not started
16 15
Number of projects not applicable this quarter
0 1
Percentage on Target
30.43% 30.43%
Percentage lagging
69.56% 65.21%
Percentage not applicable
0 4.35%
KPA 2: BASIC SERVICE DELIVERY AND INFRASTRUCTURE INVESTMENT
(COMMUNITY SERVICES)
Number of projects = 34
Quarter 1 Quarter 2
Number of projects On Target/Completed
19 8
Number of projects Lagging/Not started 15 17
![Page 43: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/43.jpg)
Mid-Year Performance Assessment Report 2015/2016
Number of projects not applicable this quarter
0 9
Percentage on Target
55.88% 23.53%
Percentage lagging
44.11% 50%
Percentage not applicable
0 26.47%
KPA 3: LOCAL ECONOMIC DEVELOPMENT
Number of projects = 14
Quarter 1 Quarter 2
Number of projects On Target/Completed 2 2
Number of projects Lagging/Not started 12 12
Number of projects not applicable this quarter 0 0
Percentage on Target 14.29% 14.29%
Percentage lagging 85.71% 85.71%
Percentage not applicable 0 0
KPA 4: FINANCIAL VIABILITY, MANAGEMENT AND SUSTAINABILITY
Number of projects = 18
Quarter 1 Quarter 2
Number of projects On Target/Completed 9
13
Number of projects Lagging/Not started 7
3
Number of projects not applicable this quarter 2
2
Percentage on Target 50%
72.23%
Percentage lagging 38.88%
16.66%
Percentage not applicable 11.11%
11.11%
![Page 44: MID - YEAR PERFORMANCE ASSESSMENT REPORT …...Mid-Year Performance Assessment Report 2015/2016 1. INTRODUCTION In terms Section 72(1) (a) of the Municipal Finance Management Act No](https://reader033.vdocuments.us/reader033/viewer/2022043001/5f79e008e956b71b660330b2/html5/thumbnails/44.jpg)
Mid-Year Performance Assessment Report 2015/2016
KPA 5: GOOD GOVERNANCE
Number of projects = 19
Quarter 1 Quarter 2
Number of projects On Target/Completed
12 10
Number of projects Lagging/Not started
3 4
Number of projects not applicable this quarter
4 5
Percentage on Target
63.15% 52.63%
Percentage lagging
15.78% 21.05%
Percentage not applicable
21.07% 26.31%
OVERALL TOTALS
Total number of projects = 126
Quarter 1 Quarter 2
Number of projects On Target/Completed
65 55
Number of projects Lagging/Not started
55 54
Number of projects not applicable this quarter
6 17
Percentage on Target
51.59% 43.65%
Percentage lagging
43.65% 42.86%
Percentage not applicable
4.76% 13.49%
7. CONCLUSION
This report consolidates the Mid-Year (Quarter 1 and 2) performance of the
organisation and individual departments for the 2015/16 Financial Year. Remedial
actions are provided for projects that do not meet the required targets.