microsoft project – tutorial 4 leveling overallocations in some cases, a resource could be...
TRANSCRIPT
Microsoft Project – Tutorial 4Leveling Overallocations
In some cases, a resource could be assigned more work in a given time period than it has working hours
leveling means correcting such overallocations
open LAN-4-3save as usualchange Your Name to your namefilter for Overallocated Resources
Microsoft Project – Tutorial 4Leveling Overallocations
notice the yellow overallocation markers (!)View > Toolbars > Resource Managementclick the Resource Allocation View on the toolbar
(first button)filter for Overallocated ResourcesProject > Sort > by nameexpand Gabriel Mitchellreduce his tasks Test Software (4h), Test Hardware
(2h) and Test Security (2h)notice the changes
Microsoft Project – Tutorial 4Leveling Overallocations
switch to the Task Entry View on the Resource Management toolbar
click the go to next task overallocation button several times until you reach task 16
notice that you are scheduled to do other tasks that day too
increase the General Labour hours to 16 and decrease your own to zero
you are no longer overallocated for this task
Microsoft Project – Tutorial 4Leveling Overallocations
go to task 26notice that the same resources are assigned to tasks
26 and 27 on overlapping daysdouble click Contract Trainer to open Resource infonotice that 200% units are indicatedthis means that two contact trainers were to be hiredhowever, only one was availablereduce the units to 100%go back to the Resource Allocation View and notice
that the Contract Trainer is now overallocated
Microsoft Project – Tutorial 4The Leveling Tool
Project includes a sophisticated leveling tookit levels work resources, though not material
resourcesdoes not adjust task durations, work entries or
resource assignmentslevels by delaying or splitting tasks so that work can
be completed by the assigned resource during available working time
Microsoft Project – Tutorial 4The Leveling Tool
splits tasks so that they are interruptedwork starts and stops on the task so that there is a
period of time when no work is being done on the task
introduces delays to a projectdelay is the amount of time between the scheduled
start of a task and the time when work actually begins on the task
usually extends the project’s length as it moves tasks into time periods when a resource is available
Microsoft Project – Tutorial 4Material Costs
so far we have entered work resources into our project
open LAN-4-3-YourInitials from last week (or the one I have put in the common directory LAN-4-3-sample)
note the seven work resources entered thereenter the five material resources on the screen at the
front of the classdon’t forget to change the Type to Material instead of
Worknotice that some of these will be paid for at the end of
the project, while others will be prorated
Microsoft Project – Tutorial 4Assigning Material Resources to Tasks
select the Gantt Chart viewgo to Window>Split right-click the bottom form and change it to Resource Costselect task 11 (install cabling)click the second cell in the Resource cost formselect Cabling from the list arrow type 250 units and then click okay the cost is calculated and the Gantt chart reflects the
assignmentclick Next to go to Install Hardwareassign six computers, three printers and one file server to this
tasksave your work
Microsoft Project – Tutorial 4Assigning Fixed Costs
remove the Split Window right click the Select All button and click costas there is a fixed room rental, add a fixed cost of $500 to
tasks 26 and 27 (Train Management and Train Users)Save your work
Microsoft Project – Tutorial 4Viewing Project Properties
Project Properties present summary cost and date statistics for the entire project
File > Properties and click the Contents tabview the other tabs for additional information about the
project
Microsoft Project – Tutorial 5Working with a Baseline
a baseline is a record of the scheduled dates and costs of each task of a project at a particular point in time
as a project progresses, baseline data and actual data will differ
this difference is called variance
Microsoft Project – Tutorial 5Working with a Baseline
open LAN-5 and save it with your initialsgo to Resource Sheet viewchange Your Name to your name and YN to your
initialsProject>Project Informationclick the Statistics button; note that baseline data is
zero or N/A because a baseline has not yet been saved
close the dialog box
Microsoft Project – Tutorial 5Working with a Baseline
Tools > Tracking > Set Baselineclick okay to save the current data as a BaselineIn the Gantt Chart view, right-click on the Select All
button and choose Variancenote the column headings towards the end of the
sheet view
Microsoft Project – Tutorial 5Tracking and Updating Progress
in order to track progress, you must enter a project Status Date
we want to update progress as of 17/08/07Project > Project Informationchange the current date to 20/08/07change the Status date to 17/08/07click okay
Microsoft Project – Tutorial 5Tracking Progress with the Tracking Toolbar
open the tracking toolbar (right-click or from the menu)
Tools > Optionsclick the View tab and Show the Project Summary
Barchange the name of the Summary bar to LAN
Installation
Microsoft Project – Tutorial 5Tracking Progress with the Tracking ToolbarProject Statistics
click the Project Statistics button on the left side of the Tracking Toolbar
note that there is no variance because no changes have been made as no progress has been tracked yet
Microsoft Project – Tutorial 5Updating the Tracking Table
Variance=Current (date) – Baseline (date)Projects that are ahead of schedule have a negative
varianceProjects that are behind schedule have a positive
varianceProject Managers will enter actual information such
as actual start and finish dates for tasks into the tracking table
Microsoft Project will then automatically update other information and statistics
Microsoft Project – Tutorial 5Updating the Tracking Table
right-click Select All and choose Trackinghere you can update actual task information manuallychange the remaining duration for task 2 (Document
Current Environment) from 4 to 2 daysnote that the Remaining Duration for the whole
project updates automaticallyhowever, it is better to use the Tracking Toolbar
whenever possible
Microsoft Project – Tutorial 5Updating tasks that are on schedule
select task 2 (Document Current Environment) click the Update as Scheduled button on the Tracking
toolbarnote the changes that occurselect tasks 3 through 6 and update them as
schedulednote the changessome of the tasks are not changed because they
have not started as of the Status Date
Microsoft Project – Tutorial 5Updating tasks that are ahead of schedule
if a task is being worked on ahead of schedule, you can update it even if its scheduled for the future
you can enter the progress dates manually or use the tracking toolbar
select task 7 (gather vendor bids) and then click the 25% complete button on the Tracking Toolbar
change the % Comp. cell for tasks 6 and 8 (Build Request for Proposal and Choose Vendors) to 10%
make task 3 100% completedrag the Fill Handle to copy this completion to task 4
Microsoft Project – Tutorial 5Updating tasks that are behind schedule
open Project Information and change the Current Date to 24/09/07 and the Status Date to 21/09/07
make task 12 (Install Hardware) 25% completedouble click task 12 to view Task Information and
click the General tabnotice that the scheduled Finish Date is 21/09/07this task is behind schedule
Microsoft Project – Tutorial 5Rescheduling tasks that are behind schedule
you can reschedule tasks using the Tracking Toolbarselect task 12 and click the Reschedule Work button
on the Tracking Toolbarthe task is split and rescheduled to begin on the
current date other tasks that have relationships to this task will
also be rescheduled as necessary