MGPEC’s Slurry Seal Specification Tweaks For
Scott WengerCity of Thornton
Monday, March 11, 13
MGPEC’s Goal For • Uniform standardized specifications• Uniform design• Uniform construction and maintenance
practices• To advance improvements together
through positive working relationships
Monday, March 11, 13
Why the changes?
• Last version was 2001• Update to current industry standards
and practices– Contractors and suppliers reviewed and
commented as the changes progressed• Uniform quality control• To provide helpful information for
Monday, March 11, 13
16.2 MATERIALS
• 16.21 Emulsified Asphalt– CQS1hL Emulsion is the only choice for
emulsion– The other two choices were deleted since
they were never used
Monday, March 11, 13
Changes to the Emulsified Asphalt Table
Test Quality Specification
AASHTO T59
ASTM D88
ASTM D6933ASTM D6934
AASHTO T49 1
ASTM D5¹
ASTM D113 ¹
ASTM D2042 ¹
AASHTO T 53 ¹
ASTM D36 ¹
Saybolt Furol Viscosity
at 77° F (25° C)20 to 100 Sec.
Storage Stability See 16.22 StorageSieve Test 0.10 Max
Residue From Evaporation
60%Penetration at 77° F
(25°C)
100 g, 5 Sec.
40 to 90 **
Ductility at 77° F (25° C)
5 cm/min. cm
40 Min.
Solubility in Trichloroethylene 97.5 Min.
Softening Point 3% Latex, 148° F Min.
1 Test on residue from evaporation.**Climate conditions should be considered when using this range. The mix designer may suggest a range higher or lower than the suggested range.
Monday, March 11, 13
Changes to the Aggregates Table (16.23)
Test Quality Specification
AASHTO T176 **ASTM D2419 **
AASHTO T104ASTM C88
AASHTO T96
ASTM 131
Sand Equivalent 60 Min. Method B (wet)
Soundness15% Max. using NA2 SO4
Or 25% Max. using MgSO4
Abrasion Resistance
25% Max. Grading D
Sand Equivalent changed from 55 Min. to 60 Min. Method B (Wet)
Monday, March 11, 13
POLYMER MODIFIER16.27 - 3% Polymer Modifier Was Added for Better Performance
Slurry Sealed 10 years agoMonday, March 11, 13
16.3 MIX DESIGNMIXTURE PROPERITIES
Test Description Specification
ISSA T-106
ISSA TB-139(for quick-traffic systems)
Additives
ISSA TB-109
ISSA TB-114
ISSA TB-100
ISSA TB-113
Residual Asphalt
Mineral Filler
Emulsion Content
Slurry Seal Consistency
.079 – 1.18 inches(2.0 – 3.0 cm)
Wet Cohesion 30 minutes minimum
(set)Wet Cohesion 60 minutes Minimum
12 kg-cm Minimum
20 kg-cm Minimum
As neededExcess Asphalt
By LWT Sand Adhesion50 g/ft2 Max. (538 g/m2 max)
Wet Stripping Pass(10 minutes boiling
water)
Pass (90% Min.)Wet Track Abrasion
Loss(6-Day soak)
75 g/ft2 Max. (807 g/m2)
Mix Time 180 seconds min. AT 77° F **70 seconds min. at 100° F **
10 – 16% (for type I)7.5 – 13.5% (for type II)6.5 – 12 % (for type III)
Based on dry weight of aggregate.
0.0% to 3.0% Based on dry weight of aggregate13 – 18% (for type I)
12.4 – 22.5% (for type II)
10.8 – 20% (for type
Based on dry weight of aggregate plus any mineral filler
Emulsion Content will vary based on the mix design.
Monday, March 11, 13
16.5 CALIBRATION• Slurry Calibration Procedures were
added to the end of the specification.• Accurate Calibration is crucial for
Slurry Seal performance• Will provide information for inspection
but could change in the field.
Monday, March 11, 13
CALIBRATION
Monday, March 11, 13
16.6 WEATHER LIMATIONS
• Slurry may be applied when air or surface temperature is 45 degrees and rising– Deleted 50 degrees and falling.
• Note: The contractor is still liable for the slurry seal warranty per bid specifications.
Monday, March 11, 13
16.82 REMOVAL OF PAVEMENT MARKINGS
• ITEMS ADDED:• Removal of Thermo Plastic pavement
markings.• Removal of Preformed pavement
markings.– Removal due to thickness of markings.
• PAINT DOES NOT NEED REMOVAL– This includes temporary paint during
Monday, March 11, 13
16.9 APPLICATION
AGGREGATE TYPE LOCATION
APPLICATION RATE(Dry weight of
aggregate)
Type I
Type II
Type III
Parking areasLocal and Secondary Roadways
Airport Runways10 - 14 lb/yd²
Parking areasLocal and Secondary Roadways
Airport Runways17 - 20 lb/yd²
Primary and Interstate Roadways 15 - 22 lb/yd²
Monday, March 11, 13
16.15 CLEAN UP• The CONTRACTOR shall expose utility
access points and remove any debris associated with the performance of the work on a daily basis.– Added to keep the project safe, clean and
accessible for utility operations.– If utility access points are covered for a
few weeks it can lead to unwanted issues for emergency and maintenance crews.
Monday, March 11, 13
16.16 TOLERANCESUNIT PRICE REDUCTIONS
Variation Below Specifications
Unit Price Reduction
Emulsion 1 – 5% 5% 6 – 10% 10% 11 – 15% 15% 16%+ 20%
Aggregate 1 – 5% 5% 6 – 10% 10% 11 – 15% 15% 16%+ 20%
• PRIOR SPECIFICATIONS HAD NO PRICE REDUCTIONS.
Monday, March 11, 13
16.17 MEASUREMENT• Slurry seal will be measured and paid
by the square yard placed.• The CONTRACTOR shall provide
aggregate and emulsion tickets on a daily basis.– This is an aid for checking the quantities.
• The CONTRACTOR shall provide a daily log of the square yards placed and
Monday, March 11, 13
16.18 TESTING AND QUALITY ASSURANCE SAMPLING AND
TESTINGTest Type Test Standard Recommended Frequency
Residue From Evaporation1 Qt. sample
Aggregate Gradation
Polymer Content1 Qt. sample
Separation Test
Sand Equivalent
Soundness of Aggregate
Abrasion Resistance of Aggregate
Application Rate
ASTM 6934 1 / Batch
AASHTO T 2ASTM D 75
1 / Source
AASHTO T 302 1 / Batch
Observation¹ DailyAASHTO T 176*ASTM D 2419*
60 Min. Method B (wet)1 / Source
AASHTO T 104ASTM C 88
1 / Source
ASHTO T 96ASTM C 131Grading D
1 / Source
Daily
Monday, March 11, 13
Recommended publications• www.mgpec.org• www.slurry.org