meyer glitzenstein & eubanks llp william s. … · michael black, director, bureau ... new...
TRANSCRIPT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
MEYER GLITZENSTEIN & EUBANKS LLP William S. Eubanks II, DC Bar No. 987036 (pro hac vice) [email protected] 245 Cajetan Street Fort Collins, CO 80524 Telephone: (970) 703-6060 Facsimile: (202) 588-5049 Eric Glitzenstein, DC Bar No. 358287 (pro hac vice) [email protected] 4115 Wisconsin Ave. N.W. Suite 210 Washington, DC 20016 Telephone: (202) 588-5206 Facsimile: (202) 588-5049 Attorneys for Plaintiffs PROTECT OUR COMMUNITIES FOUNDATION, DAVID HOGAN, and NICA KNITE
UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF CALIFORNIA
PROTECT OUR COMMUNITIES FOUNDATION, DAVID HOGAN, and NICA KNITE,
Plaintiffs,
v. MICHAEL BLACK, Director, Bureau of Indian Affairs; SALLY JEWELL, Secretary, Department of the Interior; KEVIN WASHBURN, Assistant Secretary for Indian Affairs, Department of the Interior; AMY DUTSCHKE, Regional Director, Bureau of Indian Affairs Pacific Region; JOHN RYDZIK, Chief, Bureau of Indian Affairs Pacific Region Division of Environmental, Cultural Resources Management & Safety,
Defendants.
Case No. 3:14-cv-02261-JLS-JMA Plaintiffs’ Memorandum Of Points And Authorities In Support Of Their Motion For Summary Judgment
Hearing Date: Feb. 16, 2017
Time: 1:30 p.m.
Place: 4A
Judge: Hon. Janis L. Sammartino
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.768 Page 1 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-ii-
TABLE OF CONTENTS
PAGE
TABLE OF AUTHORITIES ................................................................................... iv INTRODUCTION .................................................................................................... 1 BACKGROUND ...................................................................................................... 2
A. PERTINENT LEGAL BACKGROUND .................................. 2
1. Administrative Procedure Act ......................................... 2
2. NEPA ............................................................................... 2
B. PERTINENT FACTUAL BACKGROUND ............................. 5
1. The Tule Wind Project .................................................... 5
2. BLM’s December 2011 ROD Authorizing Tule Wind
Phase I ............................................................................. 6
3. BIA’s September 2012 Tule Wind Phase II NOA .......... 9
4. BIA’s December 2013 Tule Wind Phase II ROD ......... 13
5. Plaintiffs’ Lawsuit And Proceedings To Date .............. 16
LEGAL STANDARD ............................................................................................ 17 ARGUMENT .......................................................................................................... 18
I. BIA VIOLATED NEPA BY RELYING ON BLM’S EIS UNDER THE CIRCUMSTANCES, RATHER THAN PREPARING ITS OWN INDEPENDENT NEPA REVIEW IN CONNECTION WITH ITS LEASE APPROVAL TO TULE WIND LLC. ........................................................ 18
A. BECAUSE BIA AUTHORIZED ACTIVITIES IN A MANNER
DIRECTLY AT ODDS WITH BLM’S OCTOBER 2011 EIS,
BIA’S LEASE APPROVAL REQUIRED INDEPENDENT
NEPA REVIEW TO ANALYZE THIS ACTION. ................. 18
B. BECAUSE BLM’S OCTOBER 2011 EIS DOES NOT
CONSIDER A REASONABLE RANGE OF ALTERNATIVES
WITH RESPECT TO TULE WIND PHASE II, BIA WAS
OBLIGATED TO PREPARE NEPA REVIEW IN
CONNECTION WITH ITS LEASE APPROVAL. ................ 24
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.769 Page 2 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-iii-
II. EVEN IF IT WERE APPROPRIATE UNDER THE CIRCUMSTANCES
FOR BIA TO RELY ON BLM’S OCTOBER 2011 EIS, BIA WAS
NEVERTHELESS OBLIGATED TO PREPARE SUPPLEMENTAL
NEPA REVIEW TO ANALYZE SIGNIFICANT POST-2011 DATA
AND INFORMATION, AS WELL AS SUBSTANTIAL CHANGES IN
THE PROJECT DESIGN, BEFORE APPROVING THE LEASE. .......... 29
A. CRITICAL NEW INFORMATION RELEVANT TO
ENVIRONMENTAL CONCERNS AND BEARING ON BIA’S
ACTION AND ITS IMPACTS TRIGGERED BIA’S DUTY TO
PREPARE SUPPLEMENTAL NEPA REVIEW TO UPDATE
THE OCTOBER 2011 EIS. ..................................................... 30
B. SUBSTANTIAL CHANGES IN THE PROJECT
CONFIGURATION ALSO TRIGGERED BIA’S DUTY TO
PREPARE SUPPLEMENTAL NEPA REVIEW. .................. 37
III. BY RELYING ON BLM’S EIS AND PREPARING NO INDEPENDENT NEPA REVIEW IN CONNECTION WITH ITS DECEMBER 2013 ROD, BIA VIOLATED NEPA’S PUBLIC DISCLOSURE AND PUBLIC PARTICIPATION REQUIREMENTS. .................................................................................... 40
CONCLUSION ....................................................................................................... 44
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.770 Page 3 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
iv
TABLE OF AUTHORITIES
CASES PAGE
Ariz. Cattle Growers Ass’n. v. U.S. Fish & Wildlife Serv., 273 F.3d 1229 (9th Cir. 2001) ................................................................................. 2
Baltimore Gas and Elec. Co. v. Natural Res. Def. Council, 462 U.S. 87 (1983) ............................................................................................... 3, 4
Center for Biological Diversity v. U.S. Forest Serv., 349 F.3d 1157 (9th Cir. 2003) ............................................................................... 43
Citizens for a Better Henderson v. Hodel, 768 F.2d 1051 (9th Cir. 1985) ............................................................................... 25
City of Sausalito v. O’Neill, 386 F.3d 1186 (9th Cir. 2004) ............................................................................... 42
Davis v. Coleman, 521 F.2d 661 (9th Cir. 1975) ................................................................................. 43
Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752 (2004) ............................................................................................. 2, 3
Dubois v. U.S. Dep’t of Agric., 102 F.3d 1273 (1st Cir. 1996) ................................................................................ 40
Envtl. Def. Fund v. Marsh, 651 F.2d 983 (5th Cir. 1981) ................................................................................. 38
Envtl. Prot. Info. Ctr. v. U.S. Forest Serv., 234 Fed. Appx. 440 (9th Cir. 2007) ...................................................................... 27
Friends of Animals v. BLM, CV-15-59, 2016 WL 4082631 (D. Mont. July 29, 2016) ...................................... 20
Friends of the Clearwater v. Dombeck, 222 F.3d 552 (9th Cir. 2000) ..................................................................... 31, 34, 42
Friends of the Earth v. Hall, 693 F. Supp. 904 (W.D. Wash. 1988) ................................................................... 43
Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 528 U.S. 167 (2000) ............................................................................................... 18
Friends of Yosemite Valley v. Kempthorne, 520 F.3d 1024 (9th Cir. 2008) ......................................................................... 25, 26
Idaho Sporting Cong. Inc. v. Alexander, 222 F.3d 562 (9th Cir. 2000) ........................................................................... 26, 34
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.771 Page 4 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
v
League of Wilderness Defenders / Blue Mountains Biodiversity Project v. Connaughton, No. 3:12-cv-2271, 2014 WL 697761119 (D. Or. Dec. 9, 2014) ........................... 43
Lee v. U.S. Air Force, 220 F. Supp. 2d 1229 (D.N.M. 2002) .................................................................... 20
Marsh v. Or. Natural Res. Council, 490 U.S. 360 (1989) ......................................................................... 5, 30, 31, 35, 38
Massachusetts v. Watt, 716 F.2d 946 (1st Cir. 1983) .................................................................................. 38
Metcalf v. Daley, 214 F.3d 1135 (9th Cir. 2000) ............................................................................... 23
Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) ........................................................................................... 17, 23
Muckleshoot Indian Tribe v. U.S. Forest Serv., 177 F.3d 800 (9th Cir. 1999) ..................................................................... 25, 26, 29
Neighbors United, Inc. v. Jewell, No. 15-5147, __ F.3d ___, 2016 WL 4151237 (D.C. Cir. Aug. 5, 2016) ............. 28
New England Coal. on Nuclear Pollution v. NRC, 727 F.2d 1127 (D.C. Cir. 1984) ............................................................................. 22
New Mexico ex rel. Richardson v. Bureau of Land Mgmt., 565 F.3d 683 (10th Cir. 2009) ......................................................................... 40, 42
Portland Audubon Soc’y v. Babbitt, 998 F.2d 705 (9th Cir. 1993) ................................................................................. 36
Protect Our Communities Found. v. Jewell, 825 F.3d 571 (9th Cir. 2016) ............................................................................. 9, 37
Protect Our Communities Found. v. Jewell, No. 13-cv-575, 2014 WL 1364453 (S.D. Cal. Mar. 25, 2014) ............................... 9
Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (1989) ............................................................................................... 41
Sierra Club v. Jacobs, No. 04-cv-374, 2005 WL 6247793 (S.D. Tex. Sept. 30, 2005) ............................ 20
Siskiyou Wildlands Ctr. v. Boody, 468 F.3d 549 (9th Cir. 2006) ................................................................................. 38
Tyler v. Cisneros, 136 F.3d 603 (9th Cir. 1998) ................................................................................. 20
W. Watersheds Project v. Abbey, 719 F.3d 1035 (9th Cir. 2013) ............................................................................... 25
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.772 Page 5 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
vi
Warm Springs Dam Task Force v. Gribble, 621 F.2d 1017 (9th Cir. 1980) ......................................................................... 31, 36
STATUTES
5 U.S.C. § 706 ........................................................................................................ 2, 17
16 U.S.C. §§ 668-668d ................................................................................................ 1
16 U.S.C. §§ 703-712 .................................................................................................. 1
42 U.S.C. §§ 4321-4370m ........................................................................................... 1
REGULATIONS
40 C.F.R. § 1500.2 ................................................................................................. 4, 41
40 C.F.R. § 1500.3 ....................................................................................................... 3
40 C.F.R. § 1501.5 ....................................................................................................... 4
40 C.F.R. § 1501.6 ....................................................................................................... 4
40 C.F.R. § 1502.2(g) ................................................................................................ 23
40 C.F.R. § 1502.9(b) ................................................................................................ 43
40 C.F.R. § 1502.9(c)(1) ................................................................ 5, 30, 32, 35, 37, 40
40 C.F.R. § 1505.2 ....................................................................................................... 4
40 C.F.R. § 1505.3 ................................................................................................. 5, 20
40 C.F.R. § 1508.8 ....................................................................................................... 4
40 C.F.R. § 1508.26 ................................................................................................... 36
OTHER AUTHORITIES
46 Fed. Reg. 18026 (Mar. 23, 1981) ................................................................... 4, 23, 30
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.773 Page 6 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-1-
INTRODUCTION
Plaintiffs Protect Our Communities Foundation (“POC”), David Hogan, and
Nica Knite challenge the Bureau of Indian Affairs’ (“BIA”) December 16, 2013
Record of Decision (“ROD”) approving a lease to Tule Wind LLC to construct and
operate twenty industrial wind turbines on a ridgeline on the Ewiiaapaayp Indian
Reservation administered by BIA in San Diego County, California (“the project” or
“Tule Wind Phase II”). According to the U.S. Fish and Wildlife Service (“Service”
or “FWS”)—the expert federal wildlife agency that Congress tasked with
administering the Bald and Golden Eagle Protection Act (“BGEPA”), 16 U.S.C. §§
668-668d, and the Migratory Bird Treaty Act (“MBTA”), 16 U.S.C. §§ 703-712—
this project, as approved by BIA, presents an extremely high risk to federally
protected golden eagles, is anticipated to kill many golden eagles during the
project’s lifespan, and is highly likely to cause the loss of at least one golden eagle
breeding territory. In addition, this project will also kill many federally protected
migratory birds, such as red-tailed hawks.
Despite the exceptionally high risk that this project poses to federally
protected golden eagles and migratory birds, BIA issued its December 2013 ROD
and the associated lease without conducting any independent review whatsoever
under the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-4370m.
Instead, in authorizing Tule Wind Phase II, BIA relied entirely on an October 2011
Environmental Impact Statement (“EIS”) prepared by a different agency—the
Bureau of Land Management (“BLM”)—and in the process ignored critically
important information and recommendations concerning the project’s impacts and
configuration that the Service provided to BIA after BLM completed its October
2011 EIS. Due to the existence of this significant new information concerning the
project’s impacts to eagles and reasonable alternatives to the project layout that were
never considered in any prior NEPA document by BLM or any other agency, as well
as other reasons described below, BIA’s failure to prepare any independent NEPA
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.774 Page 7 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-2-
review in connection with its December 2013 ROD was arbitrary and capricious,
and contrary to NEPA and its implementing regulations. Accordingly, this Court
should set aside the December 2013 lease approval and ROD, and remand to BIA
for further proceedings consistent with NEPA.
BACKGROUND
The following legal and factual background is necessary to place Plaintiffs’
NEPA claims in proper context.
A. Pertinent Legal Background
1. Administrative Procedure Act
Pursuant to the Administrative Procedure Act (“APA”), a “reviewing court
shall . . . hold unlawful and set aside agency action . . . found to be arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law. . . [or]
without observance of procedure required by law.” 5 U.S.C. § 706(2)(A), (D). The
Ninth Circuit has held that under the APA, “[j]udicial review is meaningless . . .
unless [courts] carefully review the record to ensure that agency decisions are
founded on a reasoned evaluation of the relevant factors.” Ariz. Cattle Growers
Ass’n. v. U.S. Fish & Wildlife Serv., 273 F.3d 1229, 1236 (9th Cir. 2001).
Accordingly, courts “must not rubber-stamp administrative decisions that they deem
inconsistent with a statutory mandate or that frustrate the congressional policy
underlying a statute.” Id.
2. NEPA
Congress enacted NEPA more than four decades ago “[t]o declare a national
policy which will encourage productive and enjoyable harmony between man and
his environment; [and] to promote efforts which will prevent or eliminate damage to
the environment . . . .” 42 U.S.C. § 4321. In light of this mandate, the Supreme
Court has explained that NEPA is “intended to reduce or eliminate environmental
damage and to promote ‘the understanding of the ecological systems and natural
resources important to’ the United States.” Dep’t of Transp. v. Pub. Citizen, 541
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.775 Page 8 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-3-
U.S. 752, 756 (2004) (quoting 42 U.S.C. § 4321). The Court has further explained
that “NEPA has twin aims . . . [of] plac[ing] upon an agency the obligation to
consider every significant aspect of the environmental impact of a proposed action
. . . [and of] ensur[ing] that the agency will inform the public that it has indeed
considered environmental concerns in its decisionmaking process.” Baltimore Gas
and Elec. Co. v. Natural Res. Def. Council, 462 U.S. 87, 97 (1983).
To achieve NEPA’s substantive goals, Congress created specific mechanisms
whereby federal agencies must evaluate the environmental and related impacts of,
and reasonable alternatives to, a particular federal action. The regulations
implementing NEPA define two such mechanisms as the Environmental Impact
Statement (“EIS”) and the Environmental Assessment (“EA”). These procedural
mechanisms are designed to inject environmental considerations “in the agency
decisionmaking process itself,” and to “‘help public officials make decisions that are
based on understanding of environmental consequences, and take actions that
protect, restore, and enhance the environment.’” Pub. Citizen, 541 U.S. at 768-69
(emphasis added) (quoting 40 C.F.R. § 1500.1(c)). Therefore, “NEPA’s core focus
[is] on improving agency decisionmaking,” Pub. Citizen, 541 U.S. at 769 n.2, and
specifically on ensuring that agencies take a “hard look” at potential environmental
impacts and environmentally enhancing alternatives—and publicly disclose all such
information in order to foster meaningful public participation—“as part of the
agency’s process of deciding whether to pursue a particular federal action.”
Baltimore Gas, 462 U.S. at 100.
The Council on Environmental Quality (“CEQ”) has promulgated regulations
implementing NEPA that are “binding on all Federal agencies.” 40 C.F.R. § 1500.3.
These regulations provide that the agency’s alternatives analysis “is the heart” of an
EIS or EA. Id. § 1502.14. The regulations require that the decisionmaking agency
“present the environmental impacts of the proposal and the alternatives in
comparative form, thus sharply defining the issues and providing a clear basis for
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.776 Page 9 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-4-
choice among options by the decisionmaker and the public.” Id. In addition to
analyzing reasonable alternatives to the proposed action, an EIS or EA must
thoroughly analyze the direct, indirect, and cumulative environmental impacts of the
proposed action and any alternatives considered by the agency. See id. § 1508.8.
Federal agencies “shall to the fullest extent possible . . . encourage and
facilitate public involvement in decisions which affect the quality of the human
environment.” 40 C.F.R. § 1500.2. The discovery of significant new circumstances
or information must be made “available to public officials and citizens before
decisions are made and before actions are taken,” because “public scrutiny [is]
essential to implementing NEPA.” Id. § 1500.1(b) (emphases added). “In the case
of an action with effects of national concern notice shall include publication in the
Federal Register,” as well as other means of reasonably informing the interested
public of the proposed decision. Id. § 1506.6(b). At the conclusion of the NEPA
process—once all minimization and mitigation measures have been considered and
certain measures have been adopted as enforceable conditions of the decision under
review—the agency issues a ROD. See id. § 1505.2.
Where more than one agency has jurisdiction over portions of a federal
project, the agencies may work collaboratively with one agency serving as the “lead
agency” and all other agencies serving as “cooperating agencies.” See 40 C.F.R. §§
1501.5, 1501.6. As CEQ has explained, “[a] cooperating agency with jurisdiction
by law . . . has an independent legal obligation to comply with NEPA.” Forty Most
Asked Questions Concerning CEQ’s NEPA Regulations (“Forty Questions”), 46
Fed. Reg. 18026, 18035 (Mar. 23, 1981). “[I]f the cooperating agency determines
that the [lead agency’s] EIS is wrong or inadequate, it must prepare a supplement to
the EIS, replacing or adding any needed information, and must circulate the
supplement as a draft for public and agency review and comment.” Id. Thus, “[a]
final supplemental EIS would be required before the agency could take action.” Id.
“A cooperating agency with jurisdiction by law will have to prepare its own Record
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.777 Page 10 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-5-
of Decision for its action, in which it must explain how it reached its conclusions.”
Id. “Each agency should explain how and why its conclusions differ, if that is the
case, from those of other agencies which issued their Records of Decision earlier.”
Id. Further, the CEQ regulations dictate that “[m]itigation and other conditions
established in the environmental impact statement or during its review and
committed as part of the decision shall be implemented by the lead agency or other
appropriate consenting agency.” 40 C.F.R. § 1505.3.
When a federal action or its impacts present “significant new circumstances
or information relevant to environmental concerns and bearing on the proposed
action or its impacts” or “[t]he agency makes substantial changes in the proposed
action that are relevant to environmental concerns,” the agency must supplement a
pre-existing EIS or EA, regardless of whether that NEPA document was prepared by
the agency itself or by a lead agency in which this agency participated as a
cooperating agency. 40 C.F.R. § 1502.9(c)(1). “Whether to prepare a supplemental
EIS is similar to the decision whether to prepare an EIS in the first instance: If there
remains ‘major Federal action’ to occur, and if the new information is sufficient to
show that the remaining action will ‘affect the quality of the human environment’ in
a significant manner or to a significant extent not already considered, a
supplemental EIS must be prepared.” Marsh v. Or. Natural Res. Council, 490 U.S.
360, 374 (1989).
B. Pertinent Factual Background
1. The Tule Wind Project
The Tule Wind Project is proposed for construction in southeastern San Diego
County. See TULE9756.1 The Tule Wind Project comprises two distinct
components—a 65-turbine project that BLM authorized in December 2011 on
BLM-administered lands in the McCain Valley (“Tule Wind Phase I”), see
1 All administrative record citations refer to the Bates-stamped pages of the record lodged with the Court by Federal Defendants as follows: TULEXXXX (single page cited) or TULEXXXX-XX (multiple pages cited).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.778 Page 11 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-6-
TULE9789, and the 20-turbine project that BIA separately authorized in December
2013 on trust lands administered by BIA for the Ewiiaapaayp Band of Kumeyaay
Indians (“Tribe”) on ridgelines located above the McCain Valley (“Tule Wind Phase
II”) which is the subject of this lawsuit, see TULE105453-54.
Initially, BLM intended to serve as the lead agency authorizing both phases of
the Tule Wind Project for a combined build-out of up to 134 turbines on lands
administered by BLM, BIA, and California state agencies. See TULE6986.
However, as explained below, after FWS expressed concerns that the proposed
ridgeline turbines would kill many golden eagles, BLM deliberately chose not to
authorize any turbines on BIA trust land and instead ultimately ceded responsibility
to BIA for authorizing Tule Wind Phase II. See TULE9756 (“Through this ROD,
the BLM makes no decision regarding those portions of the Tule Wind Project that
are not located on BLM-managed lands.”)
2. BLM’s December 2011 ROD Authorizing Tule Wind Phase I
In November 2010, BLM issued its Draft EIS, which analyzed five
alternatives for the Tule Wind project, four of which proposed constructing all 134
turbines (including all 18 turbines proposed on the tribal ridgeline) and one
alternative proposing to reduce the overall turbine layout by eliminating 62 turbines,
including all of those on the tribal ridgeline. See TULE6995-96. With regard to the
ridgeline turbines, none of the Draft EIS alternatives considered modifications to the
project’s layout or any other alternatives that could avoid or minimize those
turbines’ lethal impacts on eagles, birds, and other wildlife. Id. Ultimately, BLM’s
Draft EIS selected a preferred alternative that did not authorize any turbines on the
tribal ridgeline because under that alternative “impacts to golden eagles would be
reduced with the removal of turbines within areas considered high risk [for] any
known active golden eagle nest”—i.e., the ridgeline on BIA trust lands. TULE7001.
BLM acknowledged that “[t]he proximity of active golden eagle nests to the
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.779 Page 12 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-7-
proposed turbines in the western portion of the project area makes it probable that an
adult or juvenile eagle could collide with the turbines at some point within the
lifetime of the project”; thus, “[i]n the worst case, this western area of the project
could become a continuing sink for golden eagles attempting to use nesting sites
west of the project area.” TULE7492. BLM therefore explained that “[t]his
alternative would reduce impacts to golden eagles by siting turbines farther away
from nesting eagles,” and would avoid the potential loss of the Canebrake eagle
territory. TULE7001.
Plaintiff POC, FWS, and others submitted comments on the Draft EIS
criticizing the Tule Wind Project and in particular the high risk posed to golden
eagles by the project’s tribal ridgeline turbines. See, e.g., TULE20611-31. In
response to these comments, and in consultation with the Service, BLM, BIA, and
Tule Wind LLC decided to divide the project into two separate phases with BLM
authorizing turbines on its lands in the McCain Valley and BIA being responsible
for any subsequent review or authorization of turbines on the ridgeline’s tribal trust
land, with the specific duty to “avoid[] or offset” adverse effects to golden eagles.
See TULE21774 (explaining that Tule Wind LLC “agreed to phase the project”
whereby “[t]he second (northern) phase would be built if and when monitoring
results and/or conservation measures indicate that [eagle] take would either avoided
or offset” because “[t]he Service believes that phasing the project in this manner
would substantially reduce the risk of take of golden eagles”).
On October 14, 2011, BLM issued its Tule Wind Phase I Final EIS, see
TULE1-5877, for which BIA served as a cooperating agency, see TULE6. The EIS
reiterated the risks to eagles—particularly on the ridgeline on BIA trust land, see,
e.g., TULE620—and endorsed as the preferred BLM action a reduced turbine
alternative authorizing construction only of 65 turbines in the McCain Valley (i.e.,
Phase I) but specifically not authorizing any turbines on the ridgeline administered
by BIA on behalf of the Tribe. TULE89-90. The only alternatives considered in the
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.780 Page 13 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-8-
Final EIS with respect to the Tule Wind Project other than the preferred alternative
(which contemplated zero turbines on the tribal ridgeline) would have contained 128
turbines, including all 18 turbines on the tribal ridgeline. TULE74-76. None of the
alternatives considered any number of turbines between the minimum number (zero)
and the maximum number (18) of turbines on the tribal ridgeline, nor did any
alternative specifically consider macrositing changes (i.e., moving the entire
ridgeline turbine project to a new location) or micrositing changes (i.e., eliminating
or at least moving the location of specific turbines within the ridgeline project
footprint) which could reduce the grave risk to eagles. In the Final EIS, BLM
explained that “[t]urbines removed under this alternative include the turbines
presenting high risk of collision for golden eagles based on topography, landforms,
and distance to known active nests.” TULE672. “Removed turbines were those
turbines along the entire northwestern ridgeline east of the known active golden
eagle territories within the potential use areas of these eagles.” Id. BLM’s Final
EIS also emphasized the high mortality risk to other migratory birds if the ridgeline
turbines were ultimately constructed. TULE672-73.
One of the key mitigation measures that BLM built into its EIS to bring the
project’s environmental impacts to a permissible level—identified as “MM BIO-
f10”—was that “[c]onstruction of the Tule Wind project would be authorized in two
portions.” TULE624. Importantly, as part of that mitigation measure, BLM—and
BIA as a cooperating agency on the Final EIS—explained:
Construction of the second portion of the project would occur at those
turbine locations that show reduced risk to the eagle population
following analysis of detailed behavior studies of known eagles in the
vicinity of the Tule Wind project. Pending the outcome of eagle
behavior studies, all, none or part of the second portion of the project
would be authorized. . . . The final criteria determining the risk each
location presents to eagles will be determined by the BLM or the
appropriate land management agency, in consultation with the required
resource agencies, tribes, and other relevant permitting entities . . . .
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.781 Page 14 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-9-
Turbine locations exceeding the acceptable risk levels to golden eagles
based on these final criteria will not be authorized for construction.
TULE624-25 (emphases added). In other words, BLM and BIA committed in the
October 2011 Final EIS that BIA would not subsequently authorize any ridgeline
turbines for construction until and unless the relevant resource agency—FWS—
determined that each turbine location would not pose an unacceptable level of risk
to golden eagles. Id.
In December 2011, BLM released its ROD for Tule Wind Phase I, adopting
as its Selected Alternative the preferred action from the Final EIS authorizing the
construction and operation of 65 turbines, but authorizing none on the tribal
ridgeline. See TULE9750-95. BLM emphasized that “[t]hrough this ROD, the
BLM makes no decision regarding those portions of the Tule Wind Project that are
not located on BLM-managed lands.” TULE9756 (emphasis added).2
3. BIA’s September 2012 Tule Wind Phase II NOA
Immediately after issuance of BLM’s Phase I ROD, BIA set in motion the
separate process by which BIA would issue a lease to Tule Wind LLC to construct
Phase II of the project on the tribal ridgeline. Tule Wind LLC and its contractors
2 Conservation organizations challenged BLM’s 2011 EIS in this Court. In March 2014, the Court granted BLM’s motion for summary judgment on all claims. See Protect Our Communities Found. v. Jewell, No. 13-cv-575, 2014 WL 1364453 (S.D. Cal. Mar. 25, 2014). In reviewing BLM’s EIS, the Court noted that “the Court is deeply troubled by the Project’s potential to injure golden eagles and other rare and special-status birds,” id. at 21, but explained that “BLM selected the ‘Reduction in Turbines’ alternative, which calls for the removal of 63 turbines from the proposed Project”—including those on BIA-administered trust lands—because “BLM determined that removing the selected wind turbines would substantially reduce adverse impacts to golden eagles and other rare and special-status birds.” Id. at *6 (emphases added). Thus, in light of BLM adopting a reduced-risk alternative and several bird-protective mitigation measures, the Court ultimately held that BLM’s EIS complied with NEPA because “BLM provided more than sufficient discussion and analysis” of impacts and alternatives with respect to the valley turbines authorized by BLM through its EIS and ROD. Id. at *7. On appeal, the Ninth Circuit affirmed this Court’s summary judgment ruling, relying both on the fact that BLM “drafted a comprehensive set of mitigation measures” in its EIS to reduce risks to birds and also because “BLM chose to reposition turbines in valleys rather than on top of ridgelines, which would lessen any risk to” birds and especially golden eagles. Protect Our Communities Found. v. Jewell, 825 F.3d 571, 582-83 (9th Cir. 2016) (emphasis added).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.782 Page 15 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-10-
began drafting a Tule Wind Phase II Avian and Bat Protection Plan (“ABPP”),
which does not supplant the permitting requirements under BGEPA or the MBTA
when a project will kill or otherwise “take” eagles or other migratory birds. The
only mechanism for obtaining legal authorization to take eagles and other migratory
birds is by obtaining from FWS both an eagle take permit under BGEPA and a
special purpose permit or other migratory bird take authorization under the
MBTA—neither of which BIA or Tule Wind LLC has obtained to date for Phase II.
From the outset, FWS raised numerous concerns with Tule Wind LLC’s
Phase II Draft ABPP and its underlying data concerning the risk to golden eagles.
For example, while noting in April 2012 that FWS received some new data
concerning eagle telemetry and use of the ridgelines, a Service official indicated that
the agency needed to review “the full data set on eagles as part of our review of the
ABPP.” TULE107160. In addition, in light of the information that Tule Wind LLC
had provided at that time, the FWS official explained that because “the project
description includes turbines in close proximity to an eagle nest (an active eagle
territory), the Service has concerns that operation of this facility will result in the
loss of a golden eagle breeding territory.” Id.
In June 2012, the FWS Regional Director sent a formal memorandum to BIA
raising serious concerns with the Phase II Draft ABPP and the viability of the
ridgeline turbines at the locations contemplated by BIA and Tule Wind LLC.
TULE106445-50. In that letter, FWS stated in unequivocal terms the agency’s
expert determination that “construction and operation of Phase II of the Tule Wind
facility has a high potential to result in injury or mortality of golden eagles, and
the loss of golden eagle breeding territories.” TULE106445 (emphasis added).
While noting that the “Draft ABPP states that Tule Wind LLC has agreed to apply
for a programmatic eagle take permit prior to operation of the Reduced Ridgeline
Project,” the Service explained that “[t]he conditions outlined in the Draft ABPP as
presented would not likely meet the conservation standard of [BGEPA].”
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.783 Page 16 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-11-
TULE106445-46 (emphasis added). Accordingly, the Service strongly
“recommend[ed] the Bureau of Indian Affairs and the project proponent consider a
different turbine siting design or moving the project to another location to minimize
and avoid eagle take”—i.e., the types of micrositing or macrositing changes that
were not analyzed for Phase II in BLM’s EIS. TULE106446 (emphasis added).
Despite the proposed curtailment and other mitigation measures contained in
the Draft ABPP, the Service explained that there is “great potential to cause the loss
of a territory and would likely cause ongoing mortality of breeding eagles and their
offspring,” and “[t]he options proposed in the draft ABPP to curtail up to 4 turbines
near this nest site, would not alleviate the potential loss of this territory” because the
“curtailment options presented do not span enough of the golden eagle breeding
season and fledgling period to avoid loss of the Cane Brake nest territory.”
TULE106447 (emphasis added). Finally, the Service explained that it “does not
agree with the project proponent’s assertion that risk of taking eagles from project
operations of Phase II would be low to moderate”; instead, the Service formally
determined that “Phase II of this project represents a high risk for golden eagle
mortality.” TULE106446-47 (emphasis added).
In addition to FWS’s specific concerns about impacts to golden eagles, the
Service instructed that BIA also needed “to address and reduce potential risk to
other species of birds protected under the [MBTA].” TULE106646. In reviewing
the Draft ABPP, the Service stated that “[t]he project proponent present little data to
analyze the impact of the project to other species of birds, including passerines and
raptors.” TULE106449-50. FWS criticized the Draft ABPP because it “does not
include an evaluation of potential rates of mortality for other avifauna, specific
advanced conservation practices and/or propose any adaptive management
measures, which can be used to lessen impacts to migratory birds.” Id.
Undeterred by FWS’s concerns and its formal scientific determination that the
Phase II turbines present a high risk to eagles and other birds, BIA issued a brief
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.784 Page 17 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-12-
Notice of Availability of the Phase II Draft ABPP and the Phase II Fire Plan for a
30-day comment period on September 19, 2012. TULE107639-41. BIA did not
publish this notice in the Federal Register. Nor did BIA issue for public comment
any draft EIS or EA—supplemental or otherwise—analyzing the environmental
impacts of constructing up to 20 tribal ridgeline turbines (a more than 10% increase
over the largest Phase II configuration contemplated by BLM in its October 2011
EIS) or considering reasonable alternatives to constructing all 20 turbines, such as
the micrositing and macrositing options urged by FWS in June 2012. Id. Instead,
anomalously, BIA stated in the Notice of Availability that the proposed action is
somehow “consistent with” the Final EIS prepared by BLM in 2011, and thus that
BIA would rely on BLM’s EIS as “the primary NEPA document used in the
decisionmaking process” for BIA’s lease approval for Tule Wind Phase II, despite
acknowledging that BLM’s “ROD made no decisions for lands under the
jurisdiction of BIA . . . [and] made no decision to move forward with the wind
turbines on the ridgeline portion of project,” and therefore did not consider any
alternatives to that action or any information, data, or evidence compiled after
BLM’s October 2011 EIS. Id.
In response to the Notice of Availability and the Phase II Draft ABPP
contained therein, the FWS Regional Director reiterated the agency’s serious
concerns with the methodologies and conclusions of the Draft ABPP, and criticized
the Draft ABPP’s refusal to acknowledge the high eagle mortality risk and the
highly likely loss of an eagle breeding territory that will occur if the project is
constructed as planned. See TULE106452-53. For example, FWS explained that
Tule Wind Phase II has “a high potential for ongoing take of eagles and the loss of a
productive golden eagle breeding territory” and also expressed concerns that “there
is a potential for this territory to become an ecological trap by attracting eagles into
a desirable nest site that possess high risk for both breeding eagles and any young
they produce.” TULE106453. The Service also explained that the revised Draft
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.785 Page 18 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-13-
ABPP did not “sufficiently address our [previous’ concerns” because “[a]
comparison of documents revealed minimal changes were made.” TULE106453.
Thus, the Service explained that “[t]he conditions outlined in the ABPP, as
presented, would not likely meet the conservation standard of [BGEPA].” Id. In
turn, FWS continued to urge “BIA, the Ewiiaapaayp Band of Kumeyaay Indians,
and the project proponent [to] consider a different turbine siting design or moving
the project to another location to minimize and avoid eagle take”—i.e., micrositing
or macrositing changes to reduce eagle mortality risk. Id. Echoing FWS’s
recommendation that BIA consider micrositing alternatives, the California
Department of Fish and Game (“CDFG”)—the state wildlife agency with
jurisdiction over migratory birds (including golden eagles)—stated that “[d]ue to
their proximity to the nest site, the relative nest density, overall productivity of the
Cane Brake nests, and the overlap of the estimated home range with the Reduced
Ridgeline Project, the Department recommends the BIA remove turbines H-1 and
H-2 as part of the Reduced Ridgeline Project.” TULE111549.3
4. BIA’s December 2013 Tule Wind Phase II ROD
After receiving critical comments on the Notice of Availability from FWS,
CDFG, and members of the public, BIA and Tule Wind LLC never meaningfully
addressed the golden eagle and bird mortality concerns repeatedly raised by FWS,
CDFG, and others. Nor did BIA conduct any NEPA review whatsoever to analyze:
(1) the serious impacts to eagles and other birds that FWS and others predicted if
BIA followed through with authorizing Tule Wind Phase II on the ridgeline in its
current alignment, or (2) reasonable Tule Wind Phase II alternatives, such as
macrositing or micrositing changes, urged by FWS and CDFG to avoid or at least
3 Plaintiff POC also submitted detailed comments in response to BIA’s Notice of Availability. See TULE107663-69. In addition to raising serious concerns with the Phase II Draft ABPP, its methodologies, and its inadequate mitigation measures, POC also explained that, under NEPA, “BIA must rectify the . . . deficient environmental review, and require or conduct additional impact analysis before deciding whether to approve the Project lease.” TULE107669.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.786 Page 19 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-14-
reduce the anticipated impacts to golden eagles and other birds. Neither of these
issues—which had arisen after BLM’s October 2011 Final EIS—was analyzed in
any way in BLM’s EIS or ROD, meaning that they entirely escaped review under
NEPA. However, on March 8, 2013, Tule Wind LLC finalized its Phase II ABPP
(“Final ABPP”), which continued to rely on the same outdated methodologies that
FWS had harshly criticized. TULE110297-392.
Despite the serious concerns about the high risk of eagle mortality held by the
federal (FWS) and state (CDFG) expert wildlife agencies that had never been
addressed by BIA and Tule Wind LLC, on December 16, 2013, BIA issued its ROD
authorizing a lease to Tule Wind LLC to construct and operate up to 20 turbines on
the ridgelines on BIA trust land—i.e., two turbines more than BLM’s EIS ever
contemplated (but still never thoroughly analyzed) on BIA trust land. See
TULE110190-235. Thus, instead of altering the project to reduce its documented
negative impacts on eagles, BIA expanded the project by more than 10% without
even considering the expanded project’s negative impacts in any NEPA document.
BIA’s ROD relied heavily on the Final ABPP in reaching an extremely low
prediction of eagle mortality compared to FWS’s estimate of high mortality and the
disturbance or complete loss of an eagle breeding territory, while nevertheless
conceding that Tule Wind Phase II will kill several golden eagles during the
anticipated 20-year project operation. See TULE110332.
Despite acknowledging that this project will inevitably kill golden eagles and
other migratory birds, BIA issued its December 2013 ROD authorizing construction
and operation without preparing any independent NEPA review in connection with
approving the lease to Tule Wind LLC to construct and operate 20 turbines on the
tribal ridgeline. Rather than preparing its own NEPA review to analyze the impacts
of construction and operation of the 20 ridgeline turbines, BIA relied solely on
BLM’s October 2011 EIS for BIA’s own NEPA compliance in issuing the lease.
See TULE110192 (“Consistent with the Tule Wind Energy Project FEIS/EIS, the
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.787 Page 20 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-15-
BIA is relying on that document for decisionmaking purposes for approval of the
lease with the Tribe.”).
Although BIA admitted that it “must comply with NEPA” in issuing this
lease, BIA asserted that it “can adopt another agency’s environmental review to
meet those requirements if it has addressed all the environmental issues associated
with the trust land action,” and in BIA’s view, “[t]he BLM’s [FEIS] fully addressed
all of the environmental issues for the Proposed Action,” TULE110199. BIA did
not mention the fact that BLM explicitly did not endorse the ridgeline part of the
project in the EIS precisely because of the extremely high risk to golden eagles and,
instead, BLM incorporated a mitigation measure aimed at ensuring that no ridgeline
turbines would be constructed without a determination by FWS that they posed a
low risk to eagles—i.e., the opposite conclusion from what the Service actually
found. Importantly, in relying on BLM’s EIS in its December 2013 ROD, BIA did
not disavow the mitigation measure that BLM had included requiring that BIA
would not authorize the construction of any ridgeline turbine unless FWS
determined that a particular turbine location demonstrated an acceptable level of risk
to eagles, TULE624-25. To the contrary, BIA expressly adopted as part of its ROD
most mitigation measures contained in BLM’s EIS, including the measure requiring
FWS’s approval of turbine sites on the ridgeline. See TULE110218-19.
Despite the existence of important post-2011 information at the time that BIA
issued its December 2013 ROD that necessarily was not considered in BLM’s
October 2011 EIS—such as the Phase II Final ABPP, new eagle use data and
telemetry information, and recent expert comments from FWS and CDFG
concerning impacts to birds (including eagles) and reasonable project alternatives
that BIA should consider—BIA gave none of that information a “hard look,” or, for
that matter, even a sideways glance, in any NEPA document, much less provided
that information to the public as part of any formal NEPA process subject to public
comment. Nor, for that matter, did BIA supplement BLM’s October 2011 EIS by
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.788 Page 21 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-16-
analyzing the impacts of authorizing 20 turbines on the tribal ridgeline, rather than
18 turbines previously contemplated (though not analyzed) by BLM; BIA instead
merely asserted that BLM’s EIS analyzed the impacts of these two turbines “in areas
straddling BLM and trust lands” but the final siting of those turbines “may actually
be on trust land within the area analyzed in the [EIS].” TULE110192. Nowhere in
its ROD did BIA explain how its approval of turbine construction and operation in
these specific areas demonstrated an acceptable level of risk to eagles—as required
by the mitigation measure developed by BLM in its October 2011 EIS and expressly
adopted by BIA in its subsequent ROD. Nor did BIA even purport in the ROD to
reference the views of the relevant resource agencies (FWS and CDFG) with respect
to whether these turbine locations pose an acceptable level of risk to eagles.4
5. Plaintiffs’ Lawsuit And Proceedings To Date
Plaintiffs filed their Complaint on September 24, 2014, raising claims under
three statutes: NEPA, BGEPA, and the MBTA. In response to Defendants’ motions
for partial judgment on the pleadings, the Court dismissed with prejudice Plaintiffs’
BGEPA and MBTA claims, as well as “Plaintiffs’ NEPA claim to the extent it seeks
a remedy for BIA’s refusal to supplement the EIS after it had approved the lease.”
ECF No. 50 at 19-20. Thus, Plaintiffs’ remaining NEPA claims—as set forth in
4 Because the Phase II ABPP only looked narrowly at the minimization measure of curtailment—rather than macrositing and micrositing alternatives urged by the Service and CDFG—the Phase II ABPP, at best, only adopted a curtailment strategy for two of the 20 turbines that would only minimally reduce eagle and bird mortality risk. See TULE110334 (“Curtailing turbines during the period of highest activity (February – April) resulted in the largest reduction in the number of predicted fatalities per curtailed turbine compared to the other seasonal curtailment options. . . . [t]he most effective curtailment scenario, based on these data, is curtailment of turbines H1 and H2 during February – April.”). And even then, the Phase II ABPP made clear that “Tule Wind will curtail turbines H1 and H2 during daylight hours” only when “one of the two nearest Cane Brake nests is active”—meaning that this measure will not be implemented for the life of the project but only if certain triggering conditions are met—which the company made clear was to further the company’s own profit incentives. Id. (explaining that this is “the curtailment scenario that produces the greatest reduction in fatality risk with the least reduction in energy production”) (emphasis added). Moreover, the Phase II ABPP conditioned this curtailment strategy on only being triggered after “one eagle [is] taken,” TULE110371, meaning that the measure will not even be implemented until the project has already killed at least one federally protected eagle.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.789 Page 22 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-17-
Claim 1 of their Complaint, ECF No. 1 ¶¶ 59-63—are appropriate for summary
judgment and serve as the basis of this motion.
To be clear, to the extent that the instant motion contends that BIA had a legal
duty to prepare its own EIS and/or to supplement BLM’s October 2011 EIS before
BIA issued its December 2013 ROD and lease approval, see infra at 18-44,
Plaintiffs only rely on materials in the administrative record that BIA received
before issuing its final decision on December 16, 2013—i.e., at a time when BIA
retained full discretion as to whether it would issue the lease and conduct NEPA
review in connection with that decision. In contrast, the supplemental NEPA sub-
claim dismissed by this Court focused on materials that BIA did not obtain until
after issuing its final decision on December 16, 2013, at which time the Court has
held there was “no remaining major federal action” for purposes of NEPA. ECF
No. 50 at 19.
LEGAL STANDARD
Because NEPA does not contain a private right of action, the APA governs
judicial review of agency action pursuant to NEPA. Based on its review of the
“whole record,” the Court “shall . . . hold unlawful and set aside agency action,
findings, and conclusions found to be . . . arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law . . . [or] without observance of
procedure required by law.” 5 U.S.C. § 706(2)(A), (D). An “agency must cogently
explain why it has exercised its discretion in a given manner,” Motor Vehicle Mfrs.
Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 48 (1983)), and “[n]ormally,
an agency [decision] would be arbitrary and capricious if the agency has . . . entirely
failed to consider an important aspect of the problem, [or] offered an explanation for
its decision that runs counter to the evidence before the agency.” Id. at 43. The
reviewing court “may not supply a reasoned basis for the agency’s action itself has
not given.” Id.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.790 Page 23 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-18-
ARGUMENT
For the reasons explained in detail below, in issuing its December 2013 ROD
and accompanying lease approval, BIA violated NEPA in myriad ways by failing to
prepare any NEPA review whatsoever independent of BLM’s October 2011 EIS,
and in the process failing to take a “hard look” at critically significant post-2011
information from the expert wildlife agencies concerning bird (including eagle)
mortality risks and reasonable alternatives to reduce such risk, among other highly
pertinent materials, thereby rendering BIA’s ROD and lease approval arbitrary and
capricious. Accordingly, this Court must set aside these agency decisions.5 I. BIA VIOLATED NEPA BY RELYING ON BLM’S EIS UNDER THE
CIRCUMSTANCES, RATHER THAN PREPARING ITS OWN
INDEPENDENT NEPA REVIEW IN CONNECTION WITH ITS
LEASE APPROVAL TO TULE WIND LLC.
Although, as explained above, there are certain scenarios under which a
cooperating agency may rely on a lead agency’s EIS to satisfy its own NEPA
compliance obligations when issuing a separate ROD, see supra at 4, under the
circumstances present here, BIA’s exclusive reliance on BLM’s October 2011 EIS
when issuing its December 2013 ROD and lease approval was arbitrary and
capricious and otherwise contrary to NEPA and its implementing regulations.
A. Because BIA Authorized Activities In A Manner Directly At
Odds With BLM’s October 2011 EIS, BIA’s Lease Approval
Required Independent NEPA Review To Analyze This Action.
As described, BIA deliberately opted to forgo preparing any independent
NEPA review in approving its December 2013 lease to Tule Wind LLC to construct
5 As set forth in the accompanying standing declarations, see Exhibits A-C, Plaintiffs have standing to assert the claims raised herein. As explained in these declarations, Plaintiffs possess the requisite recreational, aesthetic, professional, and other cognizable interests to challenge BIA’s decision to approve the Tule Wind Phase II lease without conducting any independent NEPA review in connection with that decision. See Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 528 U.S. 167, 180-81 (2000) (explaining the requirements for Article III standing).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.791 Page 24 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-19-
and operate 20 turbines on the tribal ridgeline, and instead chose to “rely[] on” “the
Tule Wind Energy Project FEIS/EIS . . . for decisionmaking purposes for approval
of the lease with the Tribe.” TULE110192. However, as explained above, BLM’s
October 2011 EIS—and BIA’s 2013 ROD reliance on the prior EIS—expressly
adopted a key mitigation measure requiring that: (1) BIA would “consult[] with the
required resource agencies” concerning the project’s risks to eagles; (2) after such
consultation, BIA would only authorize construction of Phase II turbines on the
tribal ridgeline “at those turbine locations that show reduced risk to the eagle
population”; and (3) “[t]urbine locations exceeding the acceptable risk levels to
golden eagles . . . will not be authorized for construction.” TULE624-25 (emphasis
added). Thus, BLM’s EIS made clear that, pending further eagle use data and
consultation with the relevant resource agencies with respect to golden eagles (FWS
and CDFG), “all, none or part of the second portion of the project would be
authorized.” Id. (emphasis added).
Notwithstanding these commitments, in approving the Tule Phase II lease,
BIA not only disregarded the expert opinions and recommendations of FWS and
CDFG concerning bird mortality risks and reasonable alternatives for reducing such
risk, but BIA also made clear that it never intended even to consider any project
configurations consisting of less than the full build-out of 20 turbines, despite an
express mitigation measure predicated on the possibility that “none or part of the
second portion of the project will be authorized.” Id. Under pertinent precedent,
BIA’s failure to prepare any independent NEPA review for an action that deviates
so drastically from that contemplated in BLM’s EIS cannot withstand scrutiny.
It is well-established that agencies are either bound by any mitigation
measures adopted in a formal NEPA process, or, alternatively, that agencies
declining to adhere to mitigation measures previously adopted must, at minimum,
prepare new NEPA review disclosing and analyzing the impacts of the action in the
absence of those measures. For example, the CEQ regulations mandate that
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.792 Page 25 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-20-
“[m]itigation and other conditions established in the environmental impact statement
or during its review and committed as part of the decision shall be implemented by
the lead agency or other appropriate consenting agency.” 40 C.F.R. § 1505.3
(emphasis added). Analyzing this regulation, courts in this and other Circuits have
repeatedly held that an agency is bound to the commitments it makes in its EIS or
other environmental decisionmaking documents. See, e.g., Tyler v. Cisneros, 136
F.3d 603, 308 (9th Cir. 1998) (finding that an agency must comply with mitigation
measures agreed to by agency in NEPA review process); Lee v. U.S. Air Force, 220
F. Supp. 2d 1229, 1236 (D.N.M. 2002), aff’d, 354 F.3d 1229 (10th Cir. 2004)
(explaining that agencies are “legally bound” by the environmental reviews and are
“obligated” to act as promised under 40 C.F.R. § 1505.3); Friends of Animals v.
BLM, CV-15-59, 2016 WL 4082631, at *6-9 (D. Mont. July 29, 2016) (“find[ing]
that BLM made a binding commitment in the 2009 ROD” and that “BLM's failure
to adhere to this commitment is a violation of process prohibited by NEPA”); Sierra
Club v. Jacobs, No. 04-cv-374, 2005 WL 6247793, at *7 (S.D. Tex. Sept. 30, 2005)
(holding that mitigation measures set out in an environmental impact statement are
“directly binding”).
Here, BIA seeks coverage from BLM’s October 2011 EIS—in lieu of
preparing its own EIS or EA—but in the process BIA has failed to comply with a
critically important mitigation measure to which BIA committed in both BLM’s EIS
(as a cooperating agency) and in BIA’s December 2013 ROD adopting the prior
EIS. BIA cannot have it both ways.
As a threshold matter, BIA has eviscerated the purpose behind this vital
mitigation measure by disregarding, and failing even to address in a NEPA
document, highly relevant expert comments and recommendations from the
“required resource agencies,” TULE624-25—i.e., FWS and CDFG—that have
repeatedly raised grave concerns about the extremely high mortality risks this
project poses to golden eagles individually and the regional eagle population as a
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.793 Page 26 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-21-
whole, and urging BIA to consider macrositing and micrositing changes to the
project layout to address these major bird fatality concerns. See, e.g., TULE107160;
TULE106445-50; TULE106452-53; TULE11547-54. Perhaps most importantly
with respect to this mitigation measure, in approving a lease for 20 turbines on the
tribal ridgeline, BIA refused to accept the formal determinations by these expert
agencies that the project as a whole—and especially certain turbines located closest
to active golden eagle nests—pose an extremely high risk to golden eagles and thus,
under any yardstick, at least some “[t]urbine locations exceed[] the acceptable risk
levels to golden eagles” and therefore should not have been “authorized for
construction” in their current proposed configuration. TULE624-25.
In short, BIA has run roughshod over this binding mitigation measure by
rendering its consultation provision pointless, authorizing turbine construction and
operation in locations that plainly exceed acceptable risk levels according to the
agencies with scientific expertise on that matter, and refusing even to consider the
expert agencies’ recommendations as to how BIA might reduce the level of eagle
mortality risk to an acceptable threshold consistent with that contemplated in BLM’s
EIS. Accordingly, because BIA’s action in authorizing 20 turbines in high-risk
locations is not at all consistent with the terms of BLM’s October 2011 EIS and the
mitigation measures incorporated therein, BIA flouted NEPA by relying on BLM’s
EIS for its own NEPA compliance while failing even to prepare any NEPA review
to disclose to the public, and to analyze the reasons for, its abandonment of this vital
measure.
Moreover, even aside from BIA’s refusal to consider and address the expert
recommendations of FWS and CDFG as required by BLM’s EIS for any subsequent
authorization of Tule Wind Phase II, BIA’s post-EIS statements made before BIA
issued its ROD make clear that BIA never intended to consider any project
modifications based on input from the relevant wildlife agencies, which further
renders BIA’s reliance on BLM’s EIS (and the mitigation measures therein) legally
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.794 Page 27 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-22-
improper. For example, in response to FWS’s serious eagle mortality concerns and
recommendations to consider alternative layouts through macrositing changes (i.e.,
moving the entire ridgeline turbine project to a new location) or micrositing changes
(i.e., eliminating or moving the location of specific high-risk turbines within the
ridgeline project footprint) so as to at least reduce the grave risk to eagles and other
birds, BIA responded in September 2012, without even considering the issue in a
NEPA document, that it “has rejected the alternative of developing no turbines on
tribal land” because it would be “economically infeasible” and would “not meet the
BIA’s trust obligation to the [Tribe].” TULE107519.
Although this statement—issued more than a year before BIA signed the
ROD—fails to even consider recommended micrositing modifications such as
removing the most problematic and highest-risk turbines from the project design, in
any event it makes clear BIA’s stance that it never seriously contemplated, as
required by the mitigation measure adopted by BLM, that “none” or only “part of
the second portion of the project” might be authorized on the basis of consultation
with FWS and CDFG determining that certain turbines pose an unacceptable level
of risk. TULE624-25. NEPA, as well as the most basic strictures of reasoned
decisonmaking under the APA, dictate that BIA cannot on the one hand publicly
commit to following a specific process and making a decision at the culmination of
that process in consultation with the relevant expert agencies, while at the same time
BIA is refusing to adhere to that process or the determinations and recommendations
provided by the expert agencies. See New England Coal. on Nuclear Pollution v.
NRC, 727 F.2d 1127, 1130 (D.C. Cir. 1984) (Scalia, J.) (explaining that for an
agency to say one thing and do another is the “essence of arbitrary and capricious
action”) (quotation marks and citation omitted). By the same token, BIA acted
arbitrarily and capriciously by failing to prepare any NEPA review in connection
with its December 2013 decision, by instead relying on BLM’s EIS that did not
contemplate—much less analyze—a scenario in which BIA would authorize
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.795 Page 28 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-23-
construction of 20 extremely high-risk turbines on the tribal ridgeline against the
advice of the expert wildlife agencies, and by flatly admitting that it never intended
to even consider less harmful alternatives.6
Even more fundamentally, under both NEPA and the APA, a cooperating
agency must at least explain any significant discrepancies between the NEPA
document it is relying on and the final action. See Forty Questions, 46 Fed. Reg. at
18035 (“A cooperating agency with jurisdiction by law will have to prepare its own
[ROD] for its action, in which it must explain how it reached its conclusions. Each
agency should explain how and why its conclusions differ, if that is the case, from
those of other agencies which issued their Records of Decision earlier.”); State
Farm, 463 U.S. at 48 (an “agency must cogently explain why it has exercised its
discretion in a given manner”). Here, despite the fact that BIA’s action stands in
stark contrast to the process committed to in BLM’s EIS, nowhere in BIA’s ROD
does the agency mention—much less explain—the views of these expert agencies,
why BIA has refused to address these agencies’ concerns and recommendations, or
why BIA has chosen not to follow the process outlined in BLM’s EIS. Thus, on that
basis alone, BIA has violated NEPA and the APA by failing to “explain how it
reached its conclusions” and “how and why its conclusions differ” from BLM’s EIS
in significant respects, Forty Questions, 46 Fed. Reg. at 18035, thereby further
undermining BIA’s reliance on BLM’s EIS as the sole NEPA document for BIA’s
6 BIA’s result-oriented outcome—in which it reached a decision early in its decisionmaking process that it would authorize all 20 turbines regardless of risk and thereby refuse to accept the expert determinations made by FWS and CDFG—violates NEPA for another, related reason. As the CEQ regulations direct, the NEPA process “shall serve as the means of assessing the environmental impact of proposed agency actions, rather than justifying decisions already made.” 40 C.F.R. § 1502.2(g) (emphasis added); id. § 1502.5 (NEPA review “will not be used to rationalize or justify decisions already made”). Here, plainly, BIA’s ROD and the process leading to that decision merely justified an approach that BIA was intent on achieving regardless of the wildlife risks involved. See, e.g., Metcalf v. Daley, 214 F.3d 1135, 1142-45 (9th Cir. 2000) (NEPA review “must be taken objectively and in good faith, not as an exercise in form over substance, and not as a subterfuge designed to rationalize a decision already made”).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.796 Page 29 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-24-
decision that departs in drastic fashion from the action contemplated and the
mitigation measure incorporated in BLM’s EIS.
For all of these reasons, BIA’s reliance on BLM’S EIS in connection with its
lease approval for Tule Wind Phase II—and its failure to prepare its own NEPA
documentation for that decision—cannot pass muster under NEPA or the APA.
B. Because BLM’s October 2011 EIS Does Not Consider A
Reasonable Range Of Alternatives With Respect To Tule
Wind Phase II, BIA Was Obligated To Prepare NEPA
Review In Connection With Its Lease Approval.
Even if there were no binding mitigation measure from which BIA departed,
BIA’s reliance on BLM’s October 2011 EIS is nevertheless improper under NEPA
for an independent reason. In its EIS, BLM recognized that the second portion of
the project—i.e., the tribal ridgeline turbines—presented the highest risk to golden
eagle populations, and as a result the EIS expressly left open the possibility that BIA
may authorize all, some, or none of the Phase II turbines upon further study,
analysis, and consultation with FWS and CDFG. See TULE624-25. In turn,
because BLM’s analysis in its EIS of Tule Wind Phase II was necessarily a
preliminary assessment, BLM only considered two options with respect to Tule
Wind Phase II—i.e., BLM’s preferred alternative authorizing zero turbines on the
tribal ridgeline (and instead deferring that decision to BIA after further study and
consultation with FWS and CDFG) and several alternatives authorizing the full
build-out of 18 turbines on the tribal ridgeline in essentially the same configuration.
See TULE74-76. In other words, BLM’s initial assessment in its EIS only
considered the maximum number (18) and the minimum number (zero) of possible
turbines on the tribal ridgeline, and did not consider any reduced-turbine micrositing
alternatives that would eliminate what FWS and CDFG regarded as the highest-risk
Phase II turbines to reduce risks to golden eagles and other birds, presumably
because BLM assumed that BIA would conduct its own NEPA review analyzing
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.797 Page 30 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-25-
updated alternatives of this kind if and when it contemplated authorizing Tule Wind
Phase II. Accordingly, as explained below, BIA’s reliance on BLM’s EIS cannot
withstand scrutiny because that EIS did not even purport to analyze a reasonable
range of alternatives sufficient to discharge BIA’s NEPA responsibilities in
approving the Tule Wind Phase II lease.
As explained, an agency’s alternatives analysis “is the heart” of its NEPA
review because it must “present the environmental impacts of the proposal and the
alternatives in comparative form, thus sharply defining the issues and providing a
clear basis for choice among options by the decisionmaker and the public.” 40
C.F.R. § 1502.14. Thus, the Ninth Circuit has repeatedly confirmed that “a ‘viable
but unexamined alternative renders [the] environmental impact statement
inadequate.’” Muckleshoot Indian Tribe v. U.S. Forest Serv., 177 F.3d 800, 814
(9th Cir. 1999) (citing Citizens for a Better Henderson v. Hodel, 768 F.2d 1051,
1057 (9th Cir. 1985)). A NEPA violation of this kind is especially egregious where
an agency only considers action alternatives where there exists no meaningful
difference between those alternatives. See, e.g., id. at 812-13 (rejecting EIS where
“[t]he EIS considered only a no action alternative along with two virtually identical
alternatives”); W. Watersheds Project v. Abbey, 719 F.3d 1035, 1051 (9th Cir. 2013)
(finding that BLM failed to consider a reasonable range of alternatives when it
considered a no-action alternative and four action alternatives that all “reauthorized
grazing at the exact same level” but failed to meaningfully consider a reduced-
grazing alternative, and noting that “we do question how an agency can make an
informed decision on a project’s environmental impacts when each alternative
considered would authorize the same underlying action”); Friends of Yosemite
Valley v. Kempthorne, 520 F.3d 1024, 1038 (9th Cir. 2008) (finding that an SEIS
“lacked a reasonable range of action alternatives” where all of the action alternatives
“are virtually indistinguishable from each other”).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.798 Page 31 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-26-
The facts of this case make clear that BLM never intended for its preliminary
assessment of alternatives with respect to Tule Wind Phase II to serve as the
required “hard look” at a reasonable range of alternatives concerning a final decision
by BIA as to whether “all, none or part of the second portion of the project” should
be authorized. TULE624-25 (emphasis added). In fact, although BLM’s EIS
included consideration of five alternatives with respect to Tule Wind Phase II, one
alternative (Alternative 5) analyzed the effects of zero turbines and the four other
alternatives (Alternatives 1-4) considered the construction and operation of all 18
turbines on the tribal ridgeline. See TULE74-76. Indeed, BLM even explained in
the EIS that Alternatives 1-4, with respect to Tule Wind Phase II, “would essentially
be the same.” Id. Therefore, given the lack of any analysis whatsoever in BLM’s
EIS concerning reduced-turbine alternatives containing some number of turbines
between the maximum and minimum number, and the concession that all of the
action alternatives in the EIS were “essentially . . . the same,” id., BIA ran afoul of
NEPA by relying only on BLM’s preliminary assessment of alternatives in the
October 2011 EIS and failing to prepare its own NEPA review when subsequently
authorizing Tule Wind Phase II. See Muckleshoot Indian Tribe, 177 F.3d at 812-13;
Abbey, 719 F.3d at 1051; Friends of Yosemite Valley 520 F.3d at 1038.7
Moreover, BIA’s attempt to rely entirely on BLM’s preliminary alternatives
analysis is especially untenable under the circumstances in light of repeated
recommendations by the expert wildlife agencies and members of the public
7 Although failing to consider reduced-turbine options, BIA and Tule Wind LLC did consider curtailment of a few turbines in the Final Phase II ABPP. However, even aside from the fact that the ABPP is not a NEPA document and hence cannot satisfy the agency’s NEPA obligations, see e.g., Idaho Sporting Cong. Inc. v. Alexander, 222 F.3d 562, 566-67 (9th Cir. 2000) (holding that non-NEPA documents “cannot serve as a substitute” for NEPA review) (emphasis added), FWS made clear that this consideration was not sufficient to address the impact on golden eagles. Rather, as FWS explained in reviewing a nearly identical curtailment approach in the draft ABPP, “[t]he options proposed in the draft ABPP to curtail up to 4 turbines near this nest site, would not alleviate the potential loss of this territory” because the “curtailment options presented do not span enough of the golden eagle breeding season and fledgling period to avoid loss of the Cane Brake nest territory.” TULE106447 (emphasis added).
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.799 Page 32 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-27-
specifically requesting that BIA consider reduced-turbine alternatives. See, e.g.,
TULE106446 (FWS “recommend[ing] the Bureau of Indian Affairs and the project
proponent consider a different turbine siting design . . . to minimize and avoid eagle
take”) (emphasis added); TULE106453 (FWS urging “BIA, the Ewiiaapaayp Band
of Kumeyaay Indians, and the project proponent [to] consider a different turbine
siting design . . . to minimize and avoid eagle take”); TULE111549 (“Due to their
proximity to the nest site, the relative nest density, overall productivity of the Cane
Brake nests, and the overlap of the estimated home range with the Reduced
Ridgeline Project, [CDFG] recommends the BIA remove turbines H-1 and H-2 as
part of the Reduced Ridgeline Project.”) (emphasis added); TULE107615 (public
comment requesting a “micrositing study” so that “impacts to birds and bats can be
minimized”). Not only was BIA urged by many stakeholders, including the expert
wildlife agencies, to consider reduced-turbine alternatives, but even Tule Wind LLC
admits in the Phase II ABPP that “the risk of mortality varies more among turbine
location than among wind farms (Ferrer et al. 2011), and therefore micrositing
decisions based on eagle behavior . . . are probably the best means of avoiding and
minimizing take.” TULE110336 (emphasis added).
Notwithstanding the importance of turbine micrositing in eliminating or
relocating high-risk turbines to reduce the risk of eagle mortality—as FWS and
others repeatedly made known to BIA during its decisionmaking process—BIA
never analyzed in any formal NEPA process viable Phase II alternatives, such as the
specific options urged by FWS and CDFG, containing less than the full project
build-out of 18 turbines in order to eliminate the highest-risk turbines to eagles. In
light of these highly probative comments—from the expert federal and state wildlife
agencies no less—that result cannot be sustained under NEPA. See Envtl. Prot.
Info. Ctr. v. U.S. Forest Serv., 234 Fed. Appx. 440, 442–43 (9th Cir. 2007) (holding
that an agency’s “analysis of only a no action alternative and [the agency’s]
preferred alternative (the proposed project) was insufficient” where public
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.800 Page 33 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-28-
comments had identified a seemingly viable alternative and the agency had offered
only “[a] cursory dismissal of a proposed alternative unsupported by agency
analysis”).8
The D.C. Circuit recently addressed an analogous situation in which it found
that another commercial wind project authorized by the federal government—the
Buckeye Wind Project in Ohio—did not comport with NEPA because it, too, failed
to analyze a reasonable range of alternatives for addressing impacts on a protected
bat species. See Union Neighbors United, Inc. v. Jewell, No. 15-5147, __ F.3d ___,
2016 WL 4151237 (D.C. Cir. Aug. 5, 2016). In that case, FWS served as the lead
agency in authorizing the project under the Endangered Species Act. In preparing
its EIS for the project, FWS only considered two action alternatives to the proposed
action—“a minimally restricted operations alternative” and a “maximally restricted
operations alternative” that the Service conceded “is not an economically feasible
alternative”—despite public comments specifically requesting that FWS consider
mid-range alternatives between the maximum and the minimum operational
restrictions. Id. at *5, *8. On those facts, the court concluded that “the Service
failed to consider a reasonable range of alternatives because it did not consider any
reasonable alternative that would be economically feasible while taking fewer bats
than Buckeye’s proposal,” and the court therefore remanded the decision to FWS for
“[a]n analysis of a realistic mid-range alternative with a cut-in speed that would take
materially fewer bats than Buckeye’s proposal while allowing the project to go
forward.” Id. at *8.
8 Here, BIA did not even provide a cursory dismissal of any reduced-turbine alternatives. As explained, although BIA summarily asserted that “the alternative of developing no turbines on tribal land” would be “economically infeasible” and would “not meet the BIA’s trust obligation to the [Tribe],” TULE107519 (emphasis added), without any explanation as to why BIA deemed that to be the case, BIA never explained why it refused even to consider the reduced-turbine options repeatedly urged by FWS, CDFG, and others. Thus, there is no basis upon which the Court may defer to BIA’s decision—or lack thereof—to not consider reduced-turbine alternatives in a formal NEPA document.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.801 Page 34 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-29-
The same reasoning applies here. Because BLM’s EIS only considered
alternatives with respect to Tule Wind Phase II that would have authorized all or
none of the turbines contemplated on the tribal ridgeline—i.e., the maximum and
minimum number of possible turbines located there—BIA acted arbitrarily and
capriciously, and failed to consider a reasonable range of alternatives under the
circumstances in connection with its decision to authorize Tule Wind Phase II, by
relying only on the preliminary alternatives set forth in BLM’s EIS and failing,
instead, to independently analyze viable mid-range alternatives long urged by FWS,
CDFG, and members of the public that would have allowed the project to operate in
a manner posing a significantly reduced risk to golden eagles and other birds. For
this reason, BIA’s decision must be set aside and remanded for additional NEPA
analysis.9
II. EVEN IF IT WERE APPROPRIATE UNDER THE CIRCUMSTANCES
FOR BIA TO RELY ON BLM’S OCTOBER 2011 EIS, BIA WAS
NEVERTHELESS OBLIGATED TO PREPARE SUPPLEMENTAL
NEPA REVIEW TO ANALYZE SIGNIFICANT POST-2011 DATA
AND INFORMATION, AS WELL AS SUBSTANTIAL CHANGES IN
THE PROJECT DESIGN, BEFORE APPROVING THE LEASE.
Even if the Court finds that it could have been appropriate in theory for BIA
to rely on BLM’s October 2011 EIS to discharge its own NEPA obligations in
9 BIA’s reliance on BLM’s preliminary Tule Wind Phase II assessment in its EIS—in which BLM expressly raised questions concerning the adverse environmental consequences to eagles and birds that would likely result from authorization of Tule Wind Phase II—violated NEPA for an additional related reason. An agency may only “tier” to a prior NEPA document that raised concerns as to the impacts of a possible future action if, before authorizing the new action, the agency fully analyzes the impacts of, and reasonable alternatives to, that action. See Muckleshoot Indian Tribe, 177 F.3d at 811 (rejecting Forest Service’s attempt to tier to a prior EIS and report because the new NEPA document failed to analyze impacts previously identified). As the Ninth Circuit has noted, because of the preliminary nature of any pre-existing EIS, that earlier NEPA document “is only the starting point for the required analysis. It does not fill the gaps in the [] EIS.”). Id. The same is true here—although BLM’s EIS may have served as “the starting point,” it “does not fill the gaps” with respect to BIA’s obligations under NEPA to analyze relevant impacts and reasonable alternatives to reduce those impacts.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.802 Page 35 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-30-
connection with its December 2013 decision to authorize construction and operation
of Tule Wind Phase II, BIA nevertheless violated NEPA by failing to supplement
BLM’s EIS in order to analyze significant new information bearing on the
environmental impacts of, and reasonable alternatives to, Tule Wind Phase II that
emerged only after BLM issued its EIS, as well as substantial changes in the project
design on the tribal ridgeline occurring after BLM issued its EIS.10
A. Critical New Information Relevant To Environmental Concerns
And Bearing On BIA’s Action And Its Impacts Triggered BIA’s
Duty To Prepare Supplemental NEPA Review To Update The
October 2011 EIS.
NEPA’s implementing regulations require that, where there exists a prior EIS
analyzing a particular action, an agency nonetheless “[s]hall prepare supplements to
. . . final environmental impact statements if . . . [t]here are significant new
circumstances or information relevant to environmental concerns and bearing on the
proposed action or its impacts.” 40 C.F.R. § 1502.9(c)(1)(ii). As the Supreme
Court has explained:
Whether to prepare a supplemental EIS is similar to the decision whether to prepare an EIS in the first instance: If there remains ‘major Federal action’ to occur, and if the new information is sufficient to show that the remaining action will ‘affect the quality of the human environment’ in a significant manner or to a significant extent not already considered, a supplemental EIS must be prepared.
Marsh v. Or. Natural Res. Council, 490 U.S. 360, 374 (1989). CEQ’s NEPA
guidance notes that, in the context of a cooperating agency relying on a lead
agency’s EIS, “if the cooperating agency determines that the [lead agency’s] EIS is
. . . inadequate, it must prepare a supplement to the EIS, replacing or adding any
needed information, and must circulate the supplement as a draft for public and
agency review and comment.” Forty Questions, 46 Fed. Reg. at 18035. Thus, “[a]
10 As explained, see supra at 17, Plaintiffs’ supplemental NEPA claims on summary judgment relate only to materials contained in the administrative record that BIA received before issuing its final decision on December 16, 2013, at which time major Federal action still remained for purposes of NEPA.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.803 Page 36 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-31-
final supplemental EIS would be required before the agency could take action.” Id.
Moreover, supplemental NEPA review is not required if a new alternative proposed
by a commenter “is a minor variation of one of the alternatives” previously analyzed
or “is qualitatively within the spectrum of alternatives” already discussed. Id.
It is well-established in Ninth Circuit case law that “an agency that has
prepared an EIS cannot simply rest on the original document”; to the contrary, “[t]he
agency must be alert to new information that may alter the results of its original
environmental analysis, and continue to take a ‘hard look at the environmental
effects of [its] planned action, even after a proposal has received initial approval.’”
Friends of the Clearwater v. Dombeck, 222 F.3d 552, 557 (9th Cir. 2000) (quoting
Marsh, 490 U.S. at 374). In Dombeck, for example, the Court explained that
“‘[w]hen new information comes to light the agency must consider it, evaluate it,
and make a reasoned determination whether it is of such significance as to require
[an SEIS].’” Id. at 558 (quoting Warm Springs Dam Task Force v. Gribble, 621
F.2d 1017, 1024 (9th Cir. 1980)). Thus, in reviewing the facts of that case, the
Court of Appeals found that the Forest Service violated NEPA because “[t]here is
no evidence in the record that . . . the Forest Service ever considered whether the
seven new sensitive species designations or the inadequacy of the snag and old
growth standards upon which the original EIS relied were sufficiently significant to
require preparation of an SEIS.” Id. Thus, the Court held that “[w]hen confronted
with this important new information, it was incumbent on the Forest Service to
evaluate the existing EIS to determine whether it required supplementation.” Id.
Even where an agency has made a formal determination that NEPA
supplementation is not required, “courts should not automatically defer to the
agency[] . . . without carefully reviewing the record and satisfying themselves that
the agency has made a reasoned decision based on its evaluation of the
significance—or lack of significance—of the new information.” Marsh, 490 U.S. at
378. In Marsh, the Supreme Court reviewed the U.S. Army Corps of Engineers’
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.804 Page 37 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-32-
formal decision—as documented in a Supplemental Information Report—not to
prepare supplemental NEPA review upon the emergence of an interoffice
memorandum and a soil survey. Id. at 378-80. Although the Court ultimately
deferred to the Corps’ decision not to prepare a supplemental EIS because “[t]he
significance of the [new information] is subject to some doubt,” id. at 379, it
clarified that “if all of the information contained in the Cramer Memorandum and
SCS survey was both new and accurate, the Corps would have been required to
prepare a second supplemental EIS.” Id. at 385 (emphasis added). Thus, while
noting that “[i]t is also clear that, regardless of its eventual assessment of the
significance of this information, the Corps had a duty to take a hard look at the
proffered evidence,” the Court upheld the Corps’ decision because the agency
“determined based on careful scientific analysis that the new information was of
exaggerated importance.” Id.
Here, BIA bulldozed over NEPA in several distinct ways by failing to prepare
any supplemental NEPA review in connection with its December 2013 decision—
whether a supplemental EIS or at least an EA—analyzing the critically significant
information that had come to light in the more than two years since BLM issued its
October 2011 EIS that only preliminarily considered Tule Wind Phase II
alternatives and ultimately deferred authorizing that portion of the project precisely
so that BIA could gather new eagle mortality data, evaluate that new information,
and make an informed decision in consultation with FWS and CDFG as to whether
to authorize “all, none or part of” Tule Wind Phase II. TULE624-25 (emphasis
added).
At the outset, it is beyond legitimate dispute that, between BLM’s October
2011 EIS and BIA’s December 2013 ROD, BIA received copious amounts of
“significant new . . . information relevant to environmental concerns and bearing on
the proposed action or its impacts,” thereby triggering BIA’s duty to supplement
BLM’s pre-existing EIS. 40 C.F.R. § 1502.9(c)(1)(ii). For example, although none
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.805 Page 38 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-33-
of these materials was ever disclosed to the public through a formal NEPA
process—much less given the “hard look” that NEPA dictates—the record
demonstrates that, at minimum, BIA received the following highly pertinent
documents, which did not exist at the time of BLM’s EIS, before making its
decision: (1) FWS, in its role as the expert federal wildlife agency with jurisdiction over federally protected golden eagles and migratory birds, sent BIA at least two formal interagency memoranda raising grave concerns about eagle mortality risks and the loss of an eagle breeding territory, criticizing the methodologies employed by BIA and Tule Wind LLC in estimating eagle fatalities, formally determining that this is a high-risk project for eagles and other birds, and urging BIA to consider various macrositing and micrositing alternatives to reduce the risk to eagles and other birds, see TULE106445-50; TULE106452-53; (2) CDFG, in its role as the expert state wildlife agency, submitted formal interagency comments to BIA raising serious concerns about risks to eagles and other migratory birds and recommending that, at minimum, BIA “remove turbines H-1 and H-2” from the turbine configuration to lessen the risks to eagles and other birds, TULE111549; and (3) BIA received newly collected telemetry data documenting significant eagle use of the tribal ridgeline, and provided at least some of that data to FWS and CDFG for review, see TULE107818 (2012 Third Quarter Eagle Telemetry Report); TULE108837 (2012 Fourth Quarter Eagle Telemetry Report); TULE107160 (discussing new telemetry data); TULE105829 (referring to 2012 telemetry data); TULE106447 (explaining the importance of “telemetry data to assess risk”); TULE107792 (CDFG evaluating the eagle use telemetry data in assessing the project’s risk to eagles).
Although such highly relevant new information received by BIA after issuance of
the 2011 EIS is more than sufficient to trigger the need for supplemental NEPA
review, BIA’s own ROD further highlights the agency’s error in this respect by
admitting that, in addition to BLM’s “FEIR/EIS,” “BIA’s decision . . . is based on
. . . supplemental documents such as the Fire Plan, the revised [Tule Wind Phase II]
ABPP, and related responses to public comments.” TULE110202 (emphasis
added). Accordingly, under these facts in which BIA’s own decision document
concedes that BIA relied on key “supplemental documents” never before analyzed
in any formal NEPA process, id., there is no legal or logical basis for the Court to
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.806 Page 39 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-34-
condone BIA’s failure to prepare a supplemental EIS or at least a supplemental EA
under the circumstances.
Moreover, it is important to stress that BIA’s September 2012 Notice of
Availability and accompanying Draft Phase II ABPP and Fire Plan, see
TULE107639-41, cannot substitute for supplemental NEPA review. Not only did
the notice fail to incorporate the most important materials available to BIA from the
expert wildlife agencies, but the process did not even purport to incorporate the
formality required by NEPA mandating detailed analysis in a formal EIS or EA for
which notice must be provided in the Federal Register. To the contrary, BIA’s
notice solicited public comment only from an arbitrary selection of interested parties
as to a random subset of documents in BIA’s possession. Thus, as the Ninth Circuit
has held, an informal process that does not achieve NEPA’s underlying goals cannot
substitute for the formal procedures mandated by NEPA. See, e.g., Idaho Sporting
Cong., 222 F.3d at 566-67 (finding that “once an agency determines that new
information is significant, it must prepare a supplemental EA or EIS; [other
documents] cannot serve as a substitute” because “[i]t is inconsistent with NEPA
for an agency to use an[other document], rather than a supplemental EA or EIS, to
correct this type of lapse”) (emphasis added).
Indeed, it is not clear from the record that BIA ever even considered the
significance of these new and critically significant materials bearing directly on the
proposed action and its adverse impacts and then made any formal determination not
to prepare a supplemental EIS or EA. As was the case in Dombeck, “[t]here is no
evidence in the record that . . . the [agency] ever considered whether the” new
information concerning eagle and bird mortality, reasonable turbine configuration
alternatives, and other relevant materials “were sufficiently significant to require
preparation of an SEIS.” Dombeck, 222 F.3d at 558. Thus, as in Dombeck, given
the lack of any detailed consideration of these materials or any formal determination
that these materials are not “significant,” BIA flouted NEPA because “[w]hen
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.807 Page 40 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-35-
confronted with this important new information, it was incumbent on the [agency] to
evaluate the existing EIS to determine whether it required supplementation.” Id.
That alone renders BIA’s decision arbitrary and capricious.
Furthermore, even had BIA properly analyzed these materials and formally
determined that they did not warrant supplemental NEPA review—which is
nowhere documented in the record—that decision would also be arbitrary and
capricious and in violation of NEPA under the circumstances. As explained, there
can be no legitimate dispute that the new materials received by BIA after BLM
issued its EIS—especially the formal interagency materials submitted to BIA by the
expert federal and state wildlife agencies with jurisdiction over golden eagles
determining that this project poses an extremely high risk to birds (including eagles)
and recommending that BIA consider and analyze specific risk-reducing alternatives
that had never before been subject to any NEPA review—individually and
collectively constituted “significant new . . . information relevant to environmental
concerns and bearing on the proposed action or its impacts.” 40 C.F.R. §
1502.9(c)(1)(ii). In turn, BIA had no choice under NEPA and its regulations but to
prepare supplemental NEPA review considering these new materials, analyzing the
new alternatives urged therein, and assessing the impacts of reduced-turbine and
other reasonable alternatives urged by the expert wildlife agencies and the public.
This is precisely the result contemplated by the Supreme Court in Marsh.
Although the Court ultimately deferred to the Corps’ decision not to supplement a
prior EIS because the purportedly new materials reached questionable conclusions,
the Court unequivocally stated that “[t]here is little doubt that if all of the
information contained in the Cramer Memorandum and SCS survey was both new
and accurate, the Corps would have been required to prepare a second supplemental
EIS.” Marsh, 490 U.S. at 385 (emphasis added). This proposition applies with
particular force in this case because the materials at issue are not informal
interoffice memoranda (as was the case with one of the documents in Marsh), but
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.808 Page 41 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-36-
instead constitute the formal interagency determinations and recommendations of
the federal and state agencies designated by Congress and the California State
Legislature to administer laws protecting and conserving golden eagles and
migratory birds. On those facts, the Ninth Circuit has long recognized that an
agency violates NEPA by failing to heed—much less analyze in a supplemental
EIS—the expert agency’s advice, warnings, and recommendations based on that
agency’s scientific and technical expertise. See, e.g., Warm Springs Dam Task
Force, 621 F.2d at 1021 (noting “that the USGS is an agency having special
expertise in geology and seismic activity within the meaning of the statute” and
finding that “[t]he Corps’ response to the new information contained in the [USGS]
report did not satisfy NEPA” because “[o]n the basis of the information then
available, the Corps’ decision not to file a further supplement to the SEIS was not
reasonable”); Portland Audubon Soc’y v. Babbitt, 998 F.2d 705, 708-09 (9th Cir.
1993) (holding that “BLM's decision not to supplement the [timber management]
EISs was arbitrary and capricious” because “the body of scientific evidence
available by 1987 concerning the effect of continued logging on the ability of the
owl to survive as a species”—much of which had been studied by the Department of
the Interior (through FWS)—“raised serious doubts about the BLM’s ability to
preserve viability options for the owl if logging continued at the rates and in the
areas authorized”).11
Accordingly, in light of myriad documents constituting critically significant
new information bearing on BIA’s action, whether the Court determines that BIA
failed even to consider the “significance” of this new information before issuing its
lease approval decision, or that BIA somehow did in fact consider this information
and determined that no supplemental NEPA review was warranted, binding
11 In fact, the CEQ regulations deem agencies to have “special expertise” for purposes of NEPA where an agency has “statutory responsibility, agency mission, or related program experience” in the matter at hand. 40 C.F.R. § 1508.26.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.809 Page 42 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-37-
precedent compels the conclusion that BIA acted arbitrarily and capriciously, and at
odds with NEPA, by failing to prepare any supplemental NEPA review in
connection with its December 2013 ROD.12
B. Substantial Changes In The Project Configuration Also
Triggered BIA’s Duty To Prepare Supplemental NEPA
Review.
NEPA’s implementing regulations also require that, where there exists a prior
EIS for a particular action, an agency nonetheless “[s]hall prepare supplements to
. . . final environmental impact statements if [t]he agency makes substantial changes
in the proposed action that are relevant to environmental concerns.” 40 C.F.R. §
1502.9(c)(1)(i). In its December 2011 ROD, BLM emphasized this point by
explaining that “[a] proposed project change that has the potential for creating
significant environmental effects or represents a substantial change to the location or
use of the Selected Alternative will be evaluated to determine whether an amended
application and/or supplemental NEPA analysis is required.” TULE9766.
Here, BIA ultimately authorized the construction and operation of 20
commercial wind turbines on the tribal ridgeline that will have significant impacts to
golden eagles and other migratory birds, see TULE110202 (defining the action as
12 In stark contrast to how BLM addressed pertinent information from FWS raising serious concerns about eagle and bird mortality on the ridgeline—i.e., by adopting in its EIS “a comprehensive set of mitigation measures” to reduce risks to birds and by specifically “reposition[ing] turbines in valleys rather than on top of ridgelines, which would lessen any risk to” birds and especially golden eagles, see Protect Our Communities, 825 F.3d at 582-83 (emphasis added)—BIA never even looked at the expert federal agency’s scientific determinations and recommendations as part of any formal NEPA process, nor solicited public comment on the alternatives urged by those experts. Given that this Court “is deeply troubled by the Project’s potential to injure golden eagles and other rare and special-status birds,” 2014 WL 1364453, at *21, and the fact that both this Court and the Ninth Circuit relied heavily on BLM’s “removal” of all ridgeline turbines in finding that BLM had taken the requisite “hard look” in its detailed EIS, see id. at *6-7, it was especially incongruous for BIA to not prepare any NEPA review whatsoever when subsequently authorizing the turbines that BLM deliberately removed from its decisionmaking process on the advice of FWS, particularly in light of FWS’s repeated instructions to BIA to analyze specific alternatives to reduce the risk to eagles.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.810 Page 43 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-38-
“construction, maintenance, operation, and decommissioning of up to 20 turbines”),
despite the fact that BLM’s EIS—on which BIA relies—only considered a
maximum of 18 turbines on the tribal ridgeline, see TULE74-76 (Alternatives 1-4 in
BLM’s EIS would authorize construction and operation of up to 18 turbines on the
tribal ridgeline). Not only does the addition of two turbines on the tribal ridgeline
substantially increase the footprint of Tule Wind Phase II—as authorized by BIA—
by 11% in raw numbers, but given the expert predictions by FWS and CDFG of
high mortality of eagles and other birds on the tribal ridgeline, the expansion of this
project to include two more massive commercial wind turbines with large rotor-
swept areas likely to increase bird and eagle fatalities cries out for additional review
through a formal NEPA process to analyze the impacts of these new turbines and
reasonable alternatives to including them on BIA’s trust land. See, e.g., Envtl. Def.
Fund v. Marsh, 651 F.2d 983, 993 (5th Cir. 1981) (finding that a 50% increase in
land use was a substantial change requiring supplemental NEPA review);
Massachusetts v. Watt, 716 F.2d 946, 948-51 (1st Cir. 1983) (Breyer, J.) (finding
that a supplemental EIS was required even where the agency reduced by 97% the
amount of oil expected to be discovered in an offshore lease sale because “it is
important to know the probable magnitude of this change”); cf. Klamath Siskiyou
Wildlands Ctr. v. Boody, 468 F.3d 549 (9th Cir. 2006) (finding that an amendment
to a forest management plan was a substantial change under NEPA).
BIA’s only explanation for this substantial change in the project configuration
and the consequent effects that will result from Phase II turbines to eagles and other
birds is the agency’s assertion in the December 2013 ROD that:
While the Final EIR/EIS (FEIR/EIS) identified only 18 turbines as being located on the trust land, the FEIR/EIS analyzed the impact of siting 2 additional turbines in areas straddling BLM and trust lands, and therefore, this ROD anticipates that the final placement of those two turbines, which the EIS/EIR depicted as being located on BLM land directly adjacent to the trust land, may actually be on trust land within the area analyzed in the EIR/EIS after final engineering of the project is completed. Therefore, this ROD approves up to 20 wind turbines which may be sited on trust land, and which are consistent with the
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.811 Page 44 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-39-
environmental evaluation completed as part of the NEPA process for the Project.
TULE110192.
BIA’s cursory rationale for substantially expanding the footprint of Tule
Wind Phase II on BIA-administered trust land—by incorporating and adding two
large turbines never before contemplated on BIA trust land—cannot withstand
scrutiny for several reasons. First, because it is evident from the record that “BLM’s
ROD made no decision to move forward with the wind turbines on the ridgeline
portion of project that were located on BLM land,” TULE107639-40, BLM could
still, in the future, decide to authorize the maximum number of turbines it previously
contemplated on BLM-administered ridgeline lands. This means that the collective
number of turbines on BIA and BLM ridgeline lands could ultimately be higher than
previously contemplated in BLM’s EIS due to BIA’s expansion to authorize 20,
instead of 18, commercial wind turbines on its trust lands. BIA’s ROD ignores that
concern entirely.
Second, alternatively, assuming that BLM’s EIS and ROD indicate that
agency’s intention not to authorize any ridgeline construction on BLM lands in the
future, as would be consistent with the mitigation measure BLM incorporated in its
EIS, see TULE624-25 (indicating that “none or part of the second portion of the
project” may be authorized by BLM and other agencies), then BIA’s subsequent
commandeering of two BLM-rejected turbines for its own purposes undermines
BLM’s EIS and mitigation measure, which were expressly crafted in an effort to
avoid the risks associated with ridgeline construction, and in the process
unavoidably triggers the need for supplemental NEPA review to consider the
impacts of BIA building two turbines that BLM itself chose not to construct in order
to reduce eagle mortality risks.
Finally, even aside from the number of turbines authorized on the ridgeline,
the BIA ROD undoubtedly approved the two turbines in a different location than
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.812 Page 45 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-40-
were addressed in the BLM’s EIS. Given the significant consequences, this alone
has potential environmental implications that need to be analyzed in a supplemental
NEPA document.
For all of these reasons, BIA’s failure to prepare supplemental NEPA review
to analyze its new turbine configuration that substantially increases the project
footprint of Tule Wind Phase II and expands the magnitude of effects to eagles and
other migratory birds in a manner never contemplated by BLM’s EIS or the
mitigation measures found therein, is arbitrary and capricious and must be set aside
and remanded for fuller consideration by the agency. See, e.g., Dubois v. U.S. Dep’t
of Agric., 102 F.3d 1273, 1292 (1st Cir. 1996) (concluding “that a supplemental EIS
was required” because the selected action “entails a different configuration of
activities and locations, not merely a reduced version of a previously-considered
alternative.”); New Mexico ex rel. Richardson v. Bureau of Land Mgmt., 565 F.3d
683, 708 (10th Cir. 2009) (rejecting “BLM’s unanalyzed, conclusory assertion that
its modified plan would have the same type of effects as previously analyzed
alternatives . . . . [b]ecause location, not merely total surface disturbance, affects
habitat fragmentation” and holding that “Alternative A-modified was qualitatively
different and well outside the spectrum of anything BLM [previously] considered
. . . and BLM was required to issue a supplement analyzing the impacts of that
alternative under 40 C.F.R. § 1502.9(c)(1)(i)”). III. BY RELYING ON BLM’S EIS AND PREPARING NO INDEPENDENT
NEPA REVIEW IN CONNECTION WITH ITS DECEMBER 2013
ROD, BIA VIOLATED NEPA’S PUBLIC DISCLOSURE AND PUBLIC
PARTICIPATION REQUIREMENTS.
For many of the reasons described above, BIA also violated NEPA and its
implementing regulations by withholding from the public highly germane materials
bearing on the environmental impacts of, and reasonable alternatives to, BIA’s
action in approving Tule Wind Phase II.
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.813 Page 46 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-41-
Public disclosure of important information concerning an agency’s proposed
action, its impacts, and reasonable alternatives to the action is central to NEPA’s
statutory and regulatory scheme. For example, the CEQ regulations require that
federal agencies “shall to the fullest extent possible . . . encourage and facilitate
public involvement in decisions which affect the quality of the human environment.”
40 C.F.R. § 1500.2 (emphasis added). Thus, “NEPA procedures must insure that
environmental information is available to public officials and citizens before
decisions are made and before actions are taken.” Id. § 1500.1(b) (emphasis
added). Accordingly, NEPA’s implementing regulations explain that “[a]ccurate
scientific analysis, expert agency comments, and public scrutiny are essential to
implementing NEPA.” Id. (emphasis added). To accomplish these objectives,
agencies conducting NEPA review “shall provide full and fair discussion of
significant environmental impacts and shall inform decisionmakers and the public of
the reasonable alternatives which would avoid or minimize adverse impacts or
enhance the quality of the human environment.” Id. § 1502.1 (emphasis added).
In reviewing these public disclosure and public involvement obligations, the
Supreme Court has explained that the NEPA process ensures that “the agency, in
reaching its decision, will have available, and will carefully consider, detailed
information concerning significant environmental impacts; [and] it also guarantees
that the relevant information will be made available to the larger audience that may
also play a role in both the decisionmaking process and the implementation of that
decision.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989)
(emphasis added). This is crucial because “[s]imply by focusing the agency’s
attention on the environmental consequences of a proposed project, NEPA ensures
that important effects will not be overlooked or underestimated only to be
discovered after resources have been committed or the die otherwise cast.” Id.
Thus, as this Court noted in its Order dismissing some of Plaintiffs’ claims, “[t]he
key question is whether the EIS’s form, content, and preparation foster both
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.814 Page 47 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-42-
informed decisionmaking and informed public participation.” ECF No. 50 at 18
(quoting City of Sausalito v. O’Neill, 386 F.3d 1186, 1207 (9th Cir. 2004)). In this
case, BIA has failed on both counts—i.e., BIA’s failure to prepare any independent
NEPA review in connection with its December 2013 lease approval decision did not
promote informed public participation in the process nor did it facilitate informed
decisionmaking by BIA.
Not only did BIA disregard highly pertinent expert determinations and
recommendations from FWS and CDFG and fail to analyze them in any formal
NEPA document, but BIA failed even to disclose to the public in its Notice of
Availability that FWS and CDFG had raised these concerns and urged specific
project design alternatives to reduce the risks to golden eagles. See TULE107639.
Hence, by soliciting public comment only on self-serving materials hand-picked by
BIA, and failing to make available to the public (or even mention the existence of)
highly pertinent materials by the expert agencies opposing the proposed action, BIA
thwarted NEPA’s public disclosure and public involvement mandates and in the
process undermined the integrity of the process by stripping the public of its ability
to ultimately inform the agency’s decision in a manner that would minimize and
mitigate the project’s impacts. See, e.g., New Mexico ex rel. Richardson, 565 F.3d
at 708 (“A public comment period is beneficial only to the extent the public has
meaningful information on which to comment, and the public did not have
meaningful information on the fragmentation impacts of [the proposed action].
Informed public input can hardly be said to occur when major impacts of the
adopted alternative were never disclosed.”).13
13 To obtain this crucial information that should have been made available to the public as part of a formal NEPA process by BIA, members of the public—such as Plaintiff POC—had to resort to seeking these and other project-related materials through the Freedom of Information Act. By the time that BIA finally released these materials to POC and others subject to that statute, the 30-day comment period on BIA’s Notice of Availability had long expired and the materials were no longer of use in informing BIA’s decision through public comment. This is not how NEPA is intended to work. See Dombeck, 222 F.3d at 559 (“‘Compliance with NEPA is a primary duty of every federal agency; fulfillment of this vital responsibility should
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.815 Page 48 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-43-
At minimum, in light of BIA’s apparent disagreement with the expert
agencies’ scientific assessment of the project’s bird (and especially golden eagle)
mortality risk and necessary alternatives to be considered in order to reduce that
risk, BIA had a duty under NEPA to publicly acknowledge that disagreement, solicit
public comment on it, and provide a detailed and reasoned response to those
materials. See, e.g., 40 C.F.R. § 1502.9(b) (requiring that NEPA document “discuss
. . . any responsible opposing view . . . and indicate the agency’s response to the
issues raised”). BIA’s action here is functionally indistinguishable from the
situation in Center for Biological Diversity v. U.S. Forest Service, 349 F.3d 1157,
1167 (9th Cir. 2003), in which the Ninth Circuit found that “the concerns raised by
the FWS” and other experts “represent responsible opposing scientific viewpoints”
and that “those concerns identify scientific evidence and opinions contradicting the
[Forest] Service’s conclusion[s].” On that basis, the Court held that “[t]he Service’s
failure to disclose and analyze these opposing viewpoints violates NEPA”
“[b]ecause the commenters’ evidence and opinions directly challenge the scientific
basis upon which the Final EIS rests and which is central to it”; hence, the agency
was “required to disclose and respond to such viewpoints in the final impact
statement itself.” Id.; see also Friends of the Earth v. Hall, 693 F. Supp. 904, 934
(W.D. Wash. 1988) (holding that a NEPA document that “fails to disclose and
respond to the opinions held by well-respected scientists concerning the hazards of
the proposed action is fatally deficient”).
By failing to make available to the public all relevant materials bearing on the
proposed action, its impacts, and reasonable alternatives to it—and, instead, failing
even to reference those materials and to publicly respond in any meaningful fashion
not depend on the vigilance and limited resources of environmental plaintiffs.’”) (quoting Davis v. Coleman, 521 F.2d 661, 667 (9th Cir. 1975)); League of Wilderness Defenders / Blue Mountains Biodiversity Project v. Connaughton, No. 3:12-cv-2271, 2014 WL 6977611, at *14-19 (D. Or. Dec. 9, 2014) (finding that the Forest Service should have included an expert report in an EIS where the agency disclosed the report “in response to a second FOIA request, after the final EIS and the ROD were completed”)
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.816 Page 49 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-44-
to the expert scientific determinations and recommendations contained therein—
BIA flouted NEPA, its implementing regulations, and the public disclosure and
public participation purposes that undergird the statute.
CONCLUSION
For the foregoing reasons, Plaintiffs respectfully request that the Court
declare that BIA’s December 2013 ROD and lease approval violated NEPA and its
implementing regulations—and was arbitrary, capricious, and issued without
observance of procedure required by law—and therefore set aside and remand
BIA’s decision for further consideration consistent with NEPA and the APA.
DATED: September 9, 2016
Respectfully submitted,
By: /s/ William S. Eubanks II
William S. Eubanks II (pro hac vice)
MEYER GLITZENSTEIN & EUBANKS LLP
William S. Eubanks II, DC Bar No. 987036
245 Cajetan Street
Fort Collins, CO 80524
(970) 703-6060
Eric Glitzenstein, DC Bar No. 358287
4115 Wisconsin Ave., N.W., Suite 210
Washington, DC 20016
(202) 588-5206 / Fax: (202) 588-5049
Attorneys for Plaintiffs
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.817 Page 50 of 51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-45-
CERTIFICATE OF SERVICE
I hereby state and certify that today I filed the foregoing document using the
ECF system, and that such document will be served electronically on all parties of
record.
Respectfully submitted,
/s/ William S. Eubanks II
Case 3:14-cv-02261-JLS-JMA Document 59-1 Filed 09/09/16 PageID.818 Page 51 of 51