metrolink second city crossing consultation summary 18 ... · 2.9 the 2cc consultation brochure was...
TRANSCRIPT
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 1 of 23
Metrolink Second City Crossing Consultation Summary
18 October 2011
1. Background
1.1 Transport for Greater Manchester (TfGM) is currently delivering a £1.4 billion
investment programme that will see the Metrolink network triple in size by 2016
making it the largest tram system in the UK. The Second City Crossing (2CC)
has been identified as a key part of this programme.
Purpose of the Scheme
1.2 The key objectives of the Second City Crossing are:
• to increase the operational capacity through the city centre to enable
the full benefits of the extensions currently under construction to be
realised and to allow for the future growth of the network; and
• to increase the operational flexibility through the City Centre to improve
service reliability.
1.3 Funded by the Greater Manchester Transport Fund, this additional city centre
route will also bring a wide range of benefits to Metrolink users across the
network including:
• helping passengers access a wider range of city centre trams;
• providing more reliable services on the existing network and improved
flexibility for future services; and
• improving accessibility to businesses, retail and leisure facilities across a
wider area of the city centre.
Route selection
1.4 In September 2009, the Greater Manchester Integrated Transport Authority
GMITA (now TfGMC) approved the preferred route along Cross Street for the
2CC alignment. This route was chosen because it:
• offers significantly better value for money;
• has shorter journey times than other alternatives considered;
• can be designed to suit the local heritage;
• removes the need for significant new structures (such as bridges);
• incorporates two new stops, helping more passengers get to the city
centre without having to change trams;
• provides better links to the existing network and improved flexibility for
future services; and
• is relatively short and therefore reduces construction time and cost.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 2 of 23
1.5 Working closely with Manchester City Council (MCC), work was carried out to
develop and refine the detail of the Cross Street route to run through St Peter’s
Square. This allows for the integration of the plans for the second tram route
through the city centre and MCC’s proposals to redevelop St Peter’s Square.
This includes the proposals to relocate the Cenotaph to an improved location
within St Peter’s Square.
1.6 The route is shown in the plan below:
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 3 of 23
1.7 A Transport and Works Act Order (TWAO) is required to permit the construction
and operation of the 2CC route through the city centre. A pre-application
requirement for the TWAO is that a public consultation is undertaken in
accordance with the Transport and Works (Applications and Objections
Procedure) (England and Wales) Rules 2006. The public consultation for the
Metrolink Second City Crossing was undertaken for a period of 14 weeks from
3rd June to 9th September 2011.
2. Stakeholder Engagement, Communications and Consultation Approach
Key Stakeholders
2.1 As the new Metrolink route passes through Manchester city centre, TfGM
recognised the importance of ensuring that all relevant stakeholders were
consulted, including council members, residents, community groups and
businesses. A list of stakeholders was identified, including:
• Manchester City Council (MCC);
• local business and commercial property owners;
• residents and residential property owners;
• English Heritage, civic societies veteran groups;
• business groups such as CityCo, Marketing Manchester, Chamber of
Commerce;
• road users, including bus operators and taxi companies;
• Metrolink passengers;
• city centre shoppers, visitors, workers;
• disability groups; and
• press / media.
2.2 In addition, TfGM has worked closely with Manchester City Council to ensure
the route fits the Council’s regeneration aspirations for St Peter’s Square.
Respondents to the public consultation were asked to provide their views on
the proposed new Metrolink route across the City Centre and the relocation of
the Cenotaph.
Pre Consultation Engagement
2.3 2CC Stakeholder engagement activities started in advance of the launch of
the formal consultation period. The pre consultation engagement was aimed
at collecting data to inform the development of the scheme proposals in order
to prepare the requisite documents for the formal consultation.
2.4 The objectives of the pre-consultation activity were:
• liaising with policy makers, such as Manchester City Council, to obtain
their support for the scheme and the consultation;
• meeting and liaising with owners and tenants of properties with
frontages along the proposed route to obtain information such as
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 4 of 23
building details, current access, and servicing and delivery
arrangements and ensure a constant flow of information at key stages
of the scheme’s development; and
• engaging with regulatory and statutory bodies including MCC’s
conservation and planning officers and the Environment Agency to
obtain baseline data and, identify key issues which will inform the design
of the scheme.
2.5 Over 100 individual meetings were held with businesses close to the route
during 2010 and 2011 in advance of the Public Consultation. The purpose of
these meetings was to discuss the proposals and gain an understanding of the
operational requirements, particularly in terms of servicing and access for
businesses along the route.
2.6 A helpline number was established to open 9.00 am - 5.00 pm, Monday - Friday
manned by the 2CC team. An answer phone service was provided for out of
hours calls. The number was provided on all subsequent consultation material -
leaflet, information pack, exhibition, and advertising.
2.7 A specific email address was set up to act as an additional means for
members of the public and stakeholders to contact the team, raise questions
about the scheme and subsequently to send in their consultation responses.
Consultation Documentation
2.8 The public consultation invited the views of local residents, community
organisations, businesses and anyone who visits the city centre for work or
leisure. A copy of the consultation brochure can be found in Appendix 1.
2.9 The 2CC consultation brochure was produced in a wide-range of alternative
formats to ensure the consultation information was accessible to various
disabled groups including the visually impaired/blind, hard of hearing/deaf
and the learning disabled. The brochure is appended to this report and was
available in the following formats:
• British Sign Language Translation;
• audio CD;
• braille;
• large print;
• easy read; and
• screen reader compatible version.
2.10 The Second City Crossing consultation brochure was distributed to more than
7,000 residents, businesses and organisations within the city centre during the
week prior to the launch of the public consultation. A further 465 brochures
were sent out to businesses, tenants and property owners along the proposed
route. The brochure was distributed to statutory consultees and key
stakeholders including Ward Councillors, MPs and MEPs, organisations such as
CityCo, community organisations and other stakeholder groups.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 5 of 23
2.11 The consultation brochure was also sent to TfGM’s consultation panel. The
consultation panel is a database of 800 individuals who signed up to be
consulted on transport proposals or policies put forward by TfGM.
2.12 There were a number of ways people could formally respond to the
consultation:
• complete and return the response form in the consultation brochure;
• submit an electronic response via the TfGM 2CC website and submit an
electronic response;
• by email; and
• by post.
2.13 A prospectus style document was produced to support discussions with
businesses and property owners with frontage along the route. These were
issued during the consultation and will be used for ongoing stakeholder
engagement as the scheme progresses.
2.14 A dedicated consultation website was developed and included information
on the scheme, an electronic copy of the consultation brochure, event dates
and other supporting maps and documentation. There was also an online
facility to submit questions and to formally respond to the consultation using
the online brochure form. This site could be accessed from TfGM’s main home
page and from the Metrolink website. The website had 28,848 hits during the
consultation period.
2.15 Awareness of the 2CC route was raised through local media with regular press
releases and advertisements. The purpose of the media campaign was to let
Manchester residents and businesses have their say on the scheme. Seven
press releases were issued and four adverts were placed in each of the Metro
and Manchester Evening News. A full schedule of media activity and copies of
the advert can be found in Appendix 2.
2.16 Six large triangular hoardings providing information about 2CC were displayed
at various locations in the city centre. An example photograph of the
hoardings is shownbelow:
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 6 of 23
Example of a triangular hoarding in Piccadilly Gardens
2.17 A variety of 2CC posters of different designs were produced. One of these
posters appeared at every stop on every platform across the network during
the consultation.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 7 of 23
Example of posters across the Metrolink network.
2.18 Flyers were distributed by the 2CC Team at the start of the consultation period
in the city centre, at tram stops and along the tram network to promote the
proposals and the consultation exhibitions. A copy of the flyer can be found in
Appendix 3. Consultation brochures were also handed out at Metrolink stops.
2.19 A stakeholder email distribution list was collated to ensure that key groups were
updated with 2CC activities. The list included Local Councillors, MPs, the
emergency services, utility companies, bus operators and a range of specialist
interest groups. The group contains over 600 stakeholders.
2.20 290 stakeholders, including businesses and members of the public requested to
receive updates on the 2CC scheme. Updates included new information on
the website, key dates and activities.
2.21 Mail drops were used throughout the consultation to different drop areas with
some mail drop sizes ranged from 400 to 8,000. Businesses received a number
of mailings regarding the 2CC covering:
• introductory letter;
• notification of servicing and access surveys;
• notification of the land referencing process;
• consultation brochure;
• an invitation to the business events; and
• a reminder letter that the consultation was about to close.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 8 of 23
2.22 Thirteen exhibitions were held at locations along the 2CC route. The exhibitions
allowed people to find out more about the proposals, ask questions and
receive a response tailored to their area of interest, as well as submit their
written response to the consultation. A photo of one of the events is below:
Example of the Consultation exhibitions at the Manchester Arndale.
2.23 The exhibitions were held at various locations along the proposed route
including Victoria Station, Manchester Arndale Centre, the Triangle Shopping
Centre, the Town Hall and Bridgewater Hall.
2.24 The exhibitions were held on weekdays and at weekends. The exhibitions took
place all day with start times ranging from 7am to 10am and finish times from
5pm to 8pm. Dates and locations of the events were identified in the Brochure,
which is included in Appendix 1.
2.25 During the consultation period, the 2CC team continued to meet with
businesses, occupiers, residents and landlords to discuss the scheme, in
particular the proposed traffic arrangement and serving and access proposals.
A further 87 individual meetings took place during the consultation period.
2.26 The 2CC team also gave a presentation to businesses within the Arndale
shopping centre, which is located on the proposed Metrolink route.
2.27 The 2CC team also gave a presentation to the tenants in the Royal Exchange
Building which is located on the proposed Metrolink route.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 9 of 23
2.28 In addition to individual meetings, the 2CC team held meetings and gave
presentations to the major business and transport forums in and around
Manchester including Chamber of Commerce, Marketing Manchester, CityCo,
Passenger Focus and Travelwatch Northwest. In addition, the wider business
community in the Manchester area was invited to attend one of five
presentations on the 2CC scheme followed by a question and answer session.
2.29 Meetings including MCC and Heritage and Veteran groups including the British
Legion were held and discussions are on-going.
2.30 Two tailored workshops were held by TfGM with disability groups including the
Deaf and Learning Disabled groups. Sign language interpreters and a learning
disabled support worker attended the events to ensure that communications
were managed effectively.
2.31 A session was also held with the Disability Design Reference Group (DDRG) to
present the proposals and gain feedback on the scheme. The DDRG is made
up of people representing a range of disabilities to provide collective
feedback on designs with a focus on accessibility. TfGM have appointed
BreakthroughUK to manage this group.
2.32 Manchester Disabled People's Access Group (MDPAG) also facilitated a
session for TfGM to present the proposals to a number of groups including
representatives from MDPAG, Manchester Environmental Group of Blind &
Partially-sighted People (MEGOBAPP) and Greater Manchester Coalition of
Disabled People (GMCDP).
3. Consultation Results overview
3.1 The consultation brochure response form stated ‘We would like your views on
the Metrolink Second City Crossing and the relocation of the Cenotaph’ and
asked a single open question ‘What are your views on the proposals?’
Responses were analysed on the basis of positive or negative comments
specifically relating to the proposals, or those that were generally positive but
stated conditions or indicated neutral views. Common themes or topics were
picked out of the responses and analysed, as noted below.
3.2 A wide range of stakeholders have provided responses to the consultation.
Some are individual views, while some represent much larger organisations
such as businesses and local environmental groups.
3.3 1,205 consultation responses were received by TfGM during the 14 week
consultation period via a number of routes, 43% of which were by email /
brochure form filled in online.
Response type Numbers % of total
responses
Email / online form 520 43%
Letter / brochure form 484 40%
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 10 of 23
Event brochure form 201 17%
Total 1,205 100%
3.4 Further analysis showed that 93% of responses were from members of the
public and 7% from stakeholders such as businesses, organisations and
community groups.
3.5 The overall feedback on the proposals has been assessed as follows:
Positive 54%
Positive with a condition (s) 17%
Overall Positive 71%
Negative 19%
Neutral 10%
Total 100%
3.6 The responses received have been assessed in line with the fundamental
elements of the proposals:
• route
• stops; and
• the relocation of the Cenotaph.
3.7 In addition, further recurring themes in the consultation responses are also
reported in this consultation summary. These are:
• redevelopment of St Peter’s Square and the Peace Gardens
• funding and use of public money;
• traffic, congestion and impact on car users;
• bus provision and bus routing;
• cycling provision;
• pedestrian and disabled access;
• servicing and access;
• public realm and heritage;
• environment; and
• impact on local residents and businesses.
3.8 In the analysis below, all percentage figures are presented as a percentage of
the total number of responses not a percentage of a subset of the responses.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 11 of 23
Responses to the proposed route
3.9 Having considered the overall feedback to the proposals, the responses were
assessed in more detail against the proposed Cross Street route.
3.10 71% of the responses were positive about the proposals overall but 17% of
these were conditional. 5% within the 17% of conditional responses were
negative about the route. Overall therefore, 66% of responses were positive
about the proposals and the Cross Street route. In addition, 11% of responses
were negative about the proposals overall and specifically negative about the
route. Therefore in total 16% of responses were either negative about the
route. The remaining responses were either negative but did not raise any
specific issues with the route or were neutral.
3.11 Of the 16% who were negative about the route, a number of the responses
highlighted one or more specific issues including:
• 8% of the responses indicated a preference for the route to run along
Deansgate and a quarter of these indicated support for a proposal
made by Trams4Deansgate (T4D), a campaign group that was
established during the consultation;
• 2% of the responses indicated a preference for the route to go down
Mount Street and through Albert Square rather than through St Peter’s
Square and Princess Street;
• 4% of the responses felt that the line was too close to the existing
Metrolink lines; and
• 2% suggested other alternative routes including; further variants of a
Deansgate route, Whitworth Street and Oxford Street , suggestions for
serving Salford and moving either part or all of the scheme
underground.
Deansgate and the T4D proposals
3.12 In developing the 2CC proposals, a number of options were considered. Two
routes were reviewed in further detail:
• alternative 1: Connecting to the existing track in the vicinity of
Manchester Central complex and running to Victoria Station via Mount
Street, Albert Square, Cross Street and Corporation Street; and
• alternative 2: Connecting to the existing track north of the Trafford Bar
stop and running to Victoria Station via the A56 Bridgewater Boulevard /
Chester Road, Deansgate, Cateaton Street, Hanging Ditch and
Corporation Street.
3.13 At the time of the report to GMITA in September 2009, a shorter Deansgate
route was also considered, where the connection to the existing track would
be made at Castlefield / Deansgate, although this was discounted for a
number of reasons including the impact on surrounding properties, impact on
traffic and road users.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 12 of 23
3.14 During the consultation a campaign group, Trams4Deansgate (T4D) suggested
variants on a shorter Deansgate alignment. These proposed that the route
descends from the Castlefield Viaduct (which would need to be refurbished)
to reach Deansgate at the end of Bridgewater Street or alternatively for the
route to descend to street level at Watson Street and access Deansgate from
Peter Street in the vicinity of the Great Northern Warehouse. The proposals also
suggested two options for accessing Victoria Station, one via Cathedral
Gardens and one via Cathedral Approach. The T4D proposals are similar to
the TfGM alternative along Deansgate, except that the T4D route suggests re-
use of the old Castlefield viaduct from Cornbrook rather than routing along
Chester Road.
3.15 The Trams4Deansgate (T4D) proposals were reviewed in detail by TfGM. The
following points summarise the conclusion of this review:
• as well as the requirement for new/refurbished structures, the Deansgate
route option would involve a significant amount of land acquisition and
demolition of properties, such as those at no.1 & no.3 Bridgwater Street
and no.346 Deansgate. There would also be a major impact on
Manchester Central car parking and servicing in the area of the existing
Deansgate-Castlefield tramstop and much of this land would be lost to
future development for the proposed Castlefield Strategy. In
comparison the current Cross Street proposals involve little direct land-
take along the alignment;
• the T4D proposals would also impact heavily on the current tramstop at
Deansgate-Castlefield , with one proposed option preventing 2CC
trams stopping at Deansgate-Castlefield and another proposed option
potentially removing the existing inbound tramstop altogether. This
would place a major restriction on the accessibility of the Castlefield
area and the ability to interchange between rail and Metrolink services,
which is not considered an acceptable situation for the operation of the
Metrolink network, particularly given the anticipated future
developments in this area;
• running a tram along Deansgate itself would necessitate the removal of
traffic along significant stretches of the road as there is insufficient width
to accommodate the platforms and separate traffic requirements, such
as buses, loading bays, taxis etc. The increase in shared running areas
would lead to longer journey times for Metrolink passengers as well as
disruption to the bus services and other traffic currently using
Deansgate; and
• value for money is measured in terms of benefits and costs. In this
context the suggested Deansgate route is significantly more expensive
to construct and operate due to the requirement for new/refurbished
structures and a greater length of shared on-street running involving
greater utility diversions. In terms of benefits, while the suggested
Deansgate route has a slightly wider catchment area west of
Deansgate, this is at the expense of journey time for all passengers
crossing the city centre by this route, and creates an interchange
penalty for passengers trying to access Castlefield and the First Street
area.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 13 of 23
3.16 The costs of the Deansgate proposal are significantly higher and the level of
benefits reduced when compared to the Cross Street route, therefore an
investment case for a Deansgate route could not be sustained.
Mount Street and Albert Square alternatives
3.17 Manchester City Council (MCC) launched an international design competition
in 2010 for the redevelopment of St Peter’s Square and held a public
consultation in July 2010 where five proposals were displayed. One of the
tenders proposed changes to the location of the tram stop in St Peter’s Square.
3.18 Following the results from the July 2010 consultation, TfGM worked closely with
MCC to develop and refine the 2CC Cross Street route to run through St Peter’s
Square. This allows the integration of plans for the second tram route through
the City Centre and MCC’s proposals to redevelop St Peter’s Square.
3.19 Following a feasibility study to review the route proposals through St Peter’s
Square, the two localised route options (Mount Street/Albert Square option
and St Peter’s Square/Princess Street option) were assessed. This concluded
that:
• while St Peter’s Square and Albert Square are both sensitive from a
heritage perspective, trams already run through St Peter’s Square and
MCC’s redevelopment proposals offered an opportunity to better
integrate the tram into the square. The redevelopment of St Peter’s
Square also presented the opportunity to sensitively relocate the
Cenotaph to an improved setting;
• the St Peter’s Square and Princess Street alignment has fewer property
impacts than the Mount Street / Albert Square option alignment,
particularly for Manchester Central, the Midland Hotel, the Lexicon
Building and Friends Meeting House;
• the St Peter’s Square and Princess Street alignment avoids the need for
the ramp structure alongside Manchester Central to be extended;
• the route through St Peter’s Square and Princess Street would suffer less
operational disruption than the Mount Street route during high security
conferences when a secure zone is erected around the Manchester
Central Convention Complex and the Midland Hotel area. There would
be severe operational restrictions on the Mount Street route during such
an event;
• the St Peter’s Square and Princess Street route is consistent with the
Transport Strategy for Manchester City Centre and furthermore offers the
opportunity for improved interchange between Metrolink and the Cross
City Bus proposals; and
• the proposed platform arrangement for St Peter’s Square provides large
northbound and southbound island platforms for the 2CC route and the
existing city centre route which makes it easier for passengers to
interchange between services.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 14 of 23
3.20 Based on these conclusions this adjustment to the 2CC alignment at the
southern end of the route was proposed, and approved by MCC’s Executive
Committee and GMITA in March 2011.
Proximity to the existing lines
3.21 Two of the key purposes for the Metrolink 2CC are to:
• increase the capacity through the city centre in order to realise the full
potential of the Metrolink extensions under construction and enable
future expansion of the network; and
• improve operational flexibility and service reliability of Metrolink services
across the City Centre.
3.22 The Cross Street route has been identified as the optimum route to meet these
objectives. The route has been assessed against property impacts, new
structures, stops, impact on journey time, and value for money.
3.23 The Cross Street route, co-ordinated with the redevelopment of St Peter’s
Square provides a large catchment in the city centre and areas to the south
east of the Town Hall, Oxford Street and Princess Street. The proposed stop in
Exchange Square provides passengers with access by tram to a key retail and
leisure area not currently directly served by the existing Metrolink Line.
3.24 The Cross Street route also maximises interchange opportunities between
Metrolink services particularly at St Peter’s Square and Deansgate-Castlefield.
Other alternative routes
3.25 In addition to the alternative routes described above, a number of other
Deansgate variants and other route options were put forward during the public
consultation period. These have initially been reviewed by TfGM. For the
reasons stated above, TfGM believes that the proposed Cross Street route
provides the optimum solution for the Second City Crossing.
Proposed Stops – St Peter’s Square and Exchange Square
3.26 69% of responses were supportive of the St Peter’s Square and Exchange
Square stop proposals. 4% of responses were negative about the St Peter’s
Square stop and 5% were negative about the Exchange Square stop
proposals. The remaining responses did not raise any specific issues with the
stop proposals or were neutral.
3.27 3% of the consultation responses felt that the proposed stop in Exchange
Square is too close to Victoria Station.
3.28 1% of responses felt that the stop should be on Cross Street as opposed to
Exchange Square.
3.29 Some responses raised concerns about the impact on Exchange Square,
particularly for events and screenings.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 15 of 23
3.30 6% of the responses suggested that an additional stop should be
accommodated along the route, with 3% proposing that there should be an
additional stop on Cross Street in the vicinity of King Street and John Dalton
Street.
3.31 TfGM worked closely with MCC to develop the 2CC proposals. This included
reviewing a number of stop options along the route. Exchange Square was
selected as the optimum location for a stop as it can be technically integrated
into the surrounding environment, minimises the impact on servicing and
access for retailers and businesses as well as providing good accessibility to this
area of the city.
3.32 The tram route through Exchange Square will run along the current roadway
(Corporation Street) in order to minimise the impact on the Square itself. This,
along with the levels through this area of the route, also gives the opportunity
to maximise the integration of the platforms with the existing footways.
3.33 Options for a stop between Boots and the Royal Exchange were also
considered. This represented challenges in terms of availability of the space to
accommodate a full platform length including accessible ramps and
maintaining general traffic access to Newmarket Street (a key servicing route).
It would also involve the closure of this section of Cross Street which would
have a major impact on coach and servicing access for the Royal Exchange
Building and Theatre.
3.34 Options for a stop in the area of Corporation Street between Manchester
Arndale and M&S/Selfridges were also considered. However this location also
represented challenges in terms of availability of space to accommodate a
platform, pedestrian footways as well as technical difficulties integrating the
levels with the proximity of the building frontages in this area.
3.35 Other options for stops along Cross Street were considered. These were
discounted due to restrictions in terms of space and the significant implications
in terms of traffic, particularly for accessing and servicing the area including
King Street and the Central Business District.
3.36 A stop along Princess Street was discounted due to the difficulty of integrating
a platform in the highway with the Cross City Bus proposals, other traffic
requirements and pedestrian footway widths. In addition the proximity of a
2CC tramstop in Princess Street would not provide the benefit of a suitable
interchange with St Peter’s Square.
3.37 The stops proposed on the 2CC route through St Peter’s Square, Princess Street,
Cross Street and Corporation Street provide a sufficiently large catchment in
the city centre and areas to the south east of the Town Hall, Oxford Street and
Princess Street as well as providing passengers with access by tram to a key
retail and leisure area not currently directly served by the existing Metrolink line.
Relocation of the Cenotaph
3.38 67% of the responses received by TfGM were positive about the proposals
including the relocation of the Cenotaph. 9% of the responses received were
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 16 of 23
not supportive of the relocation. The remaining responses did not raise any
specific issues with the relocation of the Cenotaph or were neutral.
3.39 In developing the Second City Crossing proposals, meetings have been held
with Veteran groups to gauge views on the possibility of moving the Cenotaph.
Initial views on moving the Cenotaph were favourable subject to on-going
involvement as proposals progressed. A key requirement was to identify a
location that gives the Cenotaph a focus of its own and provides a place for
quiet contemplation and reflection. Three potential locations within the Square
were considered close to the Town Hall, the Library and Elisabeth House. The
first was identified as the preferred option as this provided an appropriate
setting in front of the Town Hall, a strong civic focus and improved views from
around the Square.
3.40 Liaison is on-going with the Veteran and Heritage groups (including the British
Legion, MADLEA (Manchester and District Liaison Ex-forces Association), SSAFA
(Soldiers, Sailors, Airmen and Families Association), 103 Regiment, Lutyens Trust,
War Memorials Trust, and Church representatives (of both the Dean and Bishop
of Manchester and Faith Communities). Led by MCC, liaison will continue
through the design process as a planning application and LBC is prepared for
relocating the Cenotaph.
3.41 MCC will lead the development of the Cenotaph proposals as part of the
wider plans for development of St Peter’s Square. MCC have appointed a
Heritage Architect to develop more detailed proposals to relocate the
Cenotaph.
3.42 TfGM will continue to work closely with MCC and the appointed Heritage
Architect to develop the Metrolink 2CC proposals in St Peter’s Square and
support the ongoing consultation with the Veteran and Heritage groups and
Church representatives.
4. Further Themes
4.1 A number of other issues and themes were raised in relation to the proposals
and the detail of the proposals.
St Peter’s Square redevelopment and the Peace Gardens
4.2 9% of the responses mentioned the wider redevelopment of St Peter’s Square.
6% of responses were positive about the proposals including St Peter’s Square.
1% of responses were negative about the wider development of the Square
and 2% were neutral.
4.3 A number of responses commented positively that the proposals for the Square
would improve the civic space and overall impression of the Square. Some
responses raised concerns that the Square would be dominated by the trams.
4.4 3% of responses were negative about the removal of the Peace Gardens. A
number of other responses queried what would happen to the Peace Gardens
but didn’t express an opinion.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 17 of 23
4.5 The proposals for the wider development of St Peter’s Square will be
developed through an international design competition managed by MCC.
Consultation will be undertaken by MCC on the proposals for the wider
development of the Square as they evolve. The Peace Gardens requirements
will be considered as part of this process.
4.6 TfGM will continue to work closely with MCC to develop the detail of the
Metrolink proposals in St Peter’s Square to ensure that it integrates
appropriately with the wider Square redevelopment.
Funding and use of public money
4.7 Whilst 71% of responses were supportive of the scheme, 8% of responses were
negative about the use of public money. Issues raised included:
• general comments that respondents felt the scheme was unnecessary
use of money or the money should be used on alternative schemes not
related to Metrolink, for example housing schemes;
• the money should be used to further extend Metrolink to other areas as
opposed to a second line across the city centre;
• the money should be spent on improving the current Metrolink network;
• the investment did not seem worthwhile for the number of new stops
that would be provided;
• the money would be better spent on alternative / Deansgate route
options; and
• money had only recently been spent on remodelling the St Peter’s
Square stop.
4.8 2CC is part of a wider investment programme that will see the Metrolink
network treble in size by 2016 and deliver a range of improvements to the
existing network including improved passenger facilities and information and
service reliability.
4.9 2CC is an integral part of the wider Transport Strategy for Manchester City
Centre and is funded by the Greater Manchester Transport Fund. The scheme
will be subject to the appropriate funding gateway approvals processes by the
Greater Manchester Combined Authority and Transport for Greater
Manchester Committee.
4.10 The St Peter’s Sq stop was remodelled during the programme of works to
replace the track in the city centre. This included making the platforms full
height along the length of the platform to improve accessibility and to make
provision for the new M5000 trams to be operated as doubles. This work was
completed in 2009 and therefore passengers will benefit from these
improvements for a number of years before work commences on the 2CC
proposals.
Traffic and Congestion
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 18 of 23
4.11 13% of responses made mention of perceived traffic impact due to the 2CC
proposals presented in the consultation material. 8% were positive about the
impact on traffic and congestion, 2% were neutral and 3% were negative.
4.12 Many responses were supportive of any measures which will “ease car
congestion” or “reduce traffic in the city centre through the Transport Strategy
for Manchester City Centre”.
4.13 3% of responses were concerned about the traffic implications on Princess
Street. Some responses had concerns specifically about the closure of St
Peter’s Square to traffic and the impact on traffic on Cross Street.
4.14 The 2CC route has been designed in conjunction with MCC to meet the
appropriate transport objectives of the TSfMCC to reduce traffic congestion in
the city centre by redirecting vehicles that do not need to travel through the
city centre. It also interfaces with the Cross City Bus scheme which is proposed
to run from Oxford Road, through the city centre, along Princess Street and
provides links with Middleton and the Leigh –Salford Guided Busway to the
north and west of Manchester. The 2CC scheme, in conjunction with the Cross
City Bus scheme and the TSfMCC, will require changes to the current traffic
arrangements along Princess Street which includes making Princess Street two
way for bus traffic and implementing a bus only restriction across the junction
with Mosley Street. The 2CC scheme also provides the opportunity for
improved passenger interchange between bus and tram at Princess Street / St
Peter’s Square.
4.15 TfGM has undertaken traffic modelling work during the initial design process,
using an accepted strategic model (which provides the anticipated overall
traffic flows on the highway network) aligned with the output from individual
junction modelling (which provides an understanding of how well the junctions
will work in terms of capacity). The strategic model accounts for a number of
other developments that are either underway or planned within the next few
years and combine the overall impacts on traffic in the city centre. The traffic
modelling indicates that Metrolink 2CC is compatible with the anticipated
traffic levels, subject to a number of changes to the highways as proposed
within the scheme, and meets the aspirations of the Transport Strategy for
Manchester City Centre.
4.16 TfGM has commenced engagement with taxi groups to discuss proposed
amendments to taxi ranks and potential routes through the city centre after
implementation of the 2CC and Cross City Bus schemes. This liaison will
continue as the design develops to ensure that all road users are considered in
the design proposals.
Buses and bus routing
4.17 2% of the responses were negative about the impact on buses in relation to the
scheme. The issues raised included:
• concern about the impact on the Metroshuttle services;
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 19 of 23
• re-routing of existing services and ability of passengers to access services
within the city centre in particular at St Peter’s Square, Albert Square,
Cross Street / King Street, Princess Street and Corporation Street; and
• the impact on the Cross City Bus proposals
4.18 Responses were received from bus operating companies / groups such as
Stagecoach, First Manchester, Bluebird and Greater Manchester Bus Operator
Association.
4.19 The 2CC proposals are part of the wider Transport Strategy for Manchester City
Centre.
4.20 A number of meetings have been held with representatives from various bus
operators. As the detail of the scheme develops, any concerns they have will
continue to be reviewed and addressed. TfGM will continue to work with
MCC and the bus operators to ensure that they are fully informed of the
scheme proposals and its integration with buses and bus routing.
4.21 The 2CC proposals will integrate with the Cross City Bus proposals including the
introduction of two way tram and bus traffic along the section of Princess
Street between St Peter’s Square and Cross Street.
4.22 Two of the current Metroshuttle routes will be slightly amended by the 2CC
proposals. However, new routes will be discussed and agreed with the
operator during construction and after implementation of the 2CC scheme.
Metroshuttle will continue to serve city centre areas.
Pedestrian and Disabled Access
4.23 4% of the total responses to the consultation commented on pedestrian access
and impact on pedestrians. 2% raised concerns about the impact of the
proposals on pedestrian access.
4.24 A number were positive about the pedestrianisation of St Peter’s Square, while
others indicated a preference for further pedestrianisation or pedestrian zones
and reducing city centre traffic.
4.25 There were some concerns raised about the ability of pedestrians to cross the
tramlines in St Peter’s Square and along Cross Street/Corporation Street. This
issue was also raised by a number of disabled people or groups representing
disabled people.
4.26 2% of the total responses to the consultation commented on disabled access
and the impact on disabled access. 1% raised concerns about impact of the
proposals on disabled access.
4.27 A number of responses raised concerns that the accessible parking for Blue
Badge holders along the route would be lost, particularly the spaces in front of
the library.
4.28 The 2CC proposals are consistent with the access objectives of the Transport
Strategy for Manchester City Centre (TSFMCC) and ensure servicing and
access is maintained for properties in the immediate vicinity of the route. At
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 20 of 23
this stage, it is not proposed to pedestrianise Cross Street. If at a later date,
MCC develops proposals to pedestrianise areas of the city which are shared
between tram and traffic, TfGM will work with MCC to consider and develop
these proposals.
4.29 Corporation Street between Market Street and Withy Grove will be restricted to
tram and cycle access only, with the exception of emergency vehicles and
hence will become pedestrianised.
4.30 With regard to concerns relating to pedestrians crossing the tram lines, these
issues can be addressed as the scheme progresses with careful design of urban
realm. Design guides and standards will be used to ensure that the scheme
incorporates appropriate solutions for pedestrians, particularly for those with
disabilities. This will also be a consideration during construction with alternative
walkways and signage to assist pedestrians. Trams currently operate
successfully elsewhere in Manchester city centre and it is anticipated that
these concerns can be adequately addressed as the design detail develops.
4.31 With regard to accessible parking for Blue Badge holders in the vicinity of the
Library, details are still being developed for the 2CC route and the
redevelopment of St Peter’s Square, however it is anticipated that an
equivalent number of accessible parking spaces will be provided in areas
close to their current location. It is understood that MCC intend to re-locate
the current accessible parking options from in front of the Library to nearby
areas such as Mount Street and Peter Street.
4.32 With regard to accessible parking for Blue Badge holders along the 2CC route,
TfGM will continue to work with MCC to agree suitable locations for other
accessible parking spaces in the vicinity of the 2CC route and it is anticipated
that the number of accessible parking spaces lost due to the 2CC proposals
will be replaced elsewhere in appropriate locations.
Cycling and cycling provision
4.33 4% of responses raised issues or queries regarding the provision or retention of
cycle routes across the city centre. Some responses indicated that a reduction
in traffic in the city centre would be better for cyclists (as well as pedestrians).
4.34 2% raised concerns that there did not appear to be any provision for cyclists
shown within the consultation material, or requested that particular routes be
maintained for cyclists.
4.35 The Metrolink proposals have been planned to accommodate the needs of
cyclists. In particular the section of Corporation Street between Market Street
and Withy Grove will be closed to general traffic while being designed to
accommodate cyclists, pedestrians and trams only.
4.36 With regard to cycle provision, TfGM is aware that Cross Street/Corporation
Street forms a major cross-town route for cyclists and will incorporate
appropriate provisions. The implementation of the TSfMCC will ensure that
much of this route is either traffic free or carries significantly lower volumes of
road traffic than at present. The design of the 2CC scheme will be progressed
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 21 of 23
to incorporate suitable traffic management proposals and allocation of road
space for the proposed users.
Servicing and Access
4.37 1% commented on servicing and access in relation to the scheme. A number
of these responses are from Stakeholders fronting onto the scheme such as
tenants, property owners and property managers. Predominantly issues raised
were in relation to vehicles’ access for servicing and access to specific
properties, or businesses in general, along the route.
4.38 TfGM has been engaging with businesses and properties along the route to
understand their servicing and access requirements as outlined above. This
has provided input to the development of the design and the draft servicing
and access plans produced during the consultation period.
4.39 TfGM is continuing to discuss these plans with stakeholders along the route in
order to ensure appropriate servicing and access is retained for all those
affected along the route.
4.40 As part of the wider stakeholder engagement and communications, TfGM will
continue to engage with stakeholders along the route through the TWAO
process and the ongoing development of the scheme.
Public Realm and Heritage
4.41 2% were negative about the design of the scheme with respect to the urban
environment and impact on public space in general along the route.
4.42 2% commented on the impact on heritage and / or listed buildings. Less than
1% were positive, less than 1% were neutral and 1% were negative about the
impact on local heritage.
4.43 In order to minimise street clutter and the impact on the urban environment
along the route, TfGM is proposing to use building fixings for the Overhead Line
Equipment (OLE) wherever possible.
4.44 Buildings will be assessed in terms of their suitability for building fixings and TfGM
will apply for Listed Building Consents where required. Historically many
buildings within the city centre held fixings for the trams that operated until the
late 1940’s and precedents have been set in terms of fixing to listed buildings
on both the current Metrolink network and other networks in the UK.
4.45 TfGM recognises that the scheme runs through important and sensitive areas of
the city centre. As part of this stage of the design process an Environmental
Impact Assessment (EIA) is being carried out. The EIA process is a formalised
procedure for the identification of significant environmental effects (both
beneficial and adverse) of a proposed scheme during both its construction
and operation. The assessment focuses on specific environmental topics
including land use, cultural heritage, townscape and visual impact, noise and
vibration, air quality etc. The process reviews the scheme, its potential impacts
and effects both during construction and in operation, and proposes possible
or anticipated mitigation measures that could be undertaken to avoid or
reduce some of the effects which are identified as significant. The findings of
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 22 of 23
the EIA are reported in an Environmental Statement (ES) which will accompany
the application for a TWAO and will be available to the public on submission of
the TWAO application.
4.46 TfGM will continue to work with MCC and the appropriate heritage bodies
throughout the development of the scheme to ensure that 2CC integrates into
the surrounding urban realm as fully as possible.
Environment
4.47 2% of responses commented positively about the environmental impact /
elements of the proposals and 2% made negative comments or raised
concerns.
4.48 A number of responses referred to the positive aspects of Metrolink being an
environmentally friendly form of transport and the 2CC scheme contributing to
removing traffic, and hence pollution, from the city centre.
4.49 2% raised comments or concerns about the likely loss of trees and the need to
retain some green spaces in the city centre. A number of responses raised
concerns about the perceived noise of the trams, particularly in the vicinity of
the Royal Exchange Theatre.
4.50 As part of this stage of the design process an Environmental Impact Assessment
is being carried out which assesses the scheme in relation to a number of
specific environmental topics and proposed possible or anticipated mitigation
measures that could be undertaken to avoid / reduce some of the impacts
which are identified as significant. The findings of the EIA will be reported in an
ES, which will be available to the public on submission of the TWAO
application.
4.51 There are a number of trees which will need to be removed along the 2CC
alignment, however TfGM will work with MCC to agree suitable locations for
replacing trees within the city centre area.
4.52 In particularly sensitive areas, such as the Royal Exchange Theatre, TfGM will
continue to work with specific stakeholders to assess their concerns and any
particular mitigation measures that may be required.
Impact on local residents and businesses during construction
4.53 1% of responses felt there would be a negative impact on local residents and
businesses and 2% of the responses were negative about the construction.
4.54 A number of responses commented positively about the impact on businesses
in terms of improved access and benefits in terms of supporting tourism as well
as access to employment.
4.55 Of the negative responses, issues raised included impact on local businesses in
terms of construction and the duration of the construction. Impact on local
residents and businesses as a result of changes to the traffic arrangements
along the route during both construction and operation was also raised.
Manchester City Council Appendix - Item 21 Executive 26 October 2011
Page 23 of 23
4.56 The detailed construction programme and methodology will be developed
once a main contractor for the scheme is appointed. TfGM will work closely
with MCC and the contractor to minimise the impact of construction where
possible.
4.57 In advance of appointing the contractor, a Code of Construction Practice will
be developed with MCC. This will provide guidelines to minimise the impact of
construction on local residents and businesses and will consider issues such as
working hours, noise, dust and vibration. The Code of Construction Practice will
be submitted as part of the application for an Order under the Transport and
Works Act.
5. Future Communications Strategy
5.1 Communications and stakeholder engagement will be an on-going
requirement throughout the TWA Order application processes and into the
construction phase.
5.2 TfGM will continue to undertake on-going engagement with specific
stakeholders, including property owners and businesses fronting onto the
proposed route, in order to continue to develop the scheme and to reach third
party agreements where appropriate.
5.3 In addition, the team will continue to communicate with residents, the general
public, and stakeholders such as Councillors, CityCo and Marketing
Manchester. This will be done through a variety of methods including briefings,
media releases and attendance at relevant meetings / events.
5.4 Those responding to the consultation that have requested to be registered for
updates will be included in any notifications issued to the existing stakeholder
list.
Appendices
Appendix 1 – Consultation Brochure
Appendix 2 – Media Schedule
Appendix 3 - Second City Crossing Flyer
Appendix 1 – Consultation Brochure
Public Consultation 2011
www.tfgm.com/haveyoursay
Artist’s impression
Please tell us what you think by
9 September 2011
Metrolink Second City Crossing
2
3
We would like to hear your views on the proposed new Metrolink route across the city centre and the relocation of the Cenotaph.
Why do we need a Second City Crossing?
The Metrolink Second City Crossing (2CC) proposal is a part of the Transport Strategy for Manchester City Centre and is crucial to delivering the Metrolink extensions currently under construction. The strategy seeks to develop a strong and prosperous economy with a range of proposals to make Greater Manchester a cleaner, safer and more attractive place to visit, live and work.
A new line to MediaCityUK has recently opened and Metrolink extensions to Chorlton, Droylsden, Oldham and Rochdale will open during 2011 and 2012. In addition, Metrolink extensions are under way from Chorlton to East Didsbury, from Droylsden to Ashton-under-Lyne town centre, through Oldham and Rochdale town centres and to Manchester Airport.
The impact of all the funded Metrolink extensions and service enhancements will be to treble, by 2021, the number of passengers accessing the city centre by tram. The additional !"#$%&'(&)%*"&"'+$"$ ),&-.//&0/*1$&,.2 .31* )&4$"* 4,&on the existing system, giving rise to the need for additional capacity in the city centre.
Transport for Greater Manchester (TfGM) is promoting a Second City Crossing which will increase operational capacity for all the Metrolink extensions, including services beyond those currently committed. It will also improve reliability for all Metrolink services including the new routes, will provide 5$6.#./.)7&)'&,$%+$&,0$1.*/&$+$ ),&* 4&%$4!1$&4.,%!0).' &caused by future maintenance and renewals in the city centre.
4
!"#$%&$&'"(#)"*&+(#,-./#,%&''-+0#%1+'#2%&3#4"5+'05."6,5'.7"8"7(#'.&$9#
through St Peter’s Square, along Princess Street, Cross Street and Corporation
Street, re-joining the existing Metrolink line just outside Victoria Station.
In developing the 2CC scheme, a number of route options were explored.
The potential solutions for a second Metrolink line through the city centre were
assessed against various criteria and reduced to two main route options. These
were the Cross Street/Corporation Street route and the Chester Road/Deansgate
route. Cross Street was selected as the preferred Metrolink Second City Crossing
route because it:
:# has short journey times;
:# can be designed to suit the local heritage;
:# %"3&;"'#.!"#+""(#2&%#'-0+-8*5+.#+"<#'.%1*.1%"'#='1*!#5'#>%-(0"'?@#
:# incorporates two new stops, helping more passengers get to the city centre
without having to change trams;
:# $%&;-("'#>".."%#7-+A'#.&#.!"#"B-'.-+0#+".<&%A#5+(#-3$%&;"(#C"B->-7-./#2&%#
future services;
:# is relatively short and therefore reduces construction time and cost; and
:# &D"%'#'-0+-8*5+.7/#>".."%#;571"#2&%#3&+"/#.!5+#.!"#,!"'."%#E&5(F4"5+'05."#%&1."G
Working closely with Manchester City Council (MCC), work has been carried out
.&#(";"7&$#5+(#%"8+"#.!"#(".5-7#&2#.!"#,%&''#).%"".#%&1."#.&#%1+#.!%&10!#).#H"."%I'#
Square. This allows the integration of plans for the second tram route through the
city centre and MCC’s proposals to redevelop St Peter’s Square.
Stops
Following a detailed assessment of options the proposed tram stops are located
in St Peter’s Square and in Exchange Square. Both stops will be accessible by ramps
and steps. Metrolink’s expansion plans include changes to the existing Metrolink
facilities at Victoria Station, which will increase platform capacity in order to
operate additional services and will be carried out with the Second City Crossing
scheme in close cooperation with Network Rail. There is also a proposal to
1$0%5("#4"5+'05."6,5'.7"8"7(#'.&$#.&#'1$$&%.#21.1%"#(";"7&$3"+.'#-+#.!-'#5%"5G
Second City Crossing – the new route
Proposed Metrolink Second City Crossing
MO
UN
T S
T
St Peter’sSquare
ExchangeSquare
Deansgate
ManchesterOxford Road
ManchesterVictoria
VIAD
UCT
ManchesterCentral
MidlandHotel
CentralLibrary
TownHall
St Ann’sChurch
Manchester Arndale
TheTriangle
ThePrintworks
ShudehillInterchange
MENArena
Chetham’sSchool of
Music
Urbis
ManchesterCathedral
RoyalExchange
M&S
Selfridges
sta
tues
Friends’ Meeting House
BeethamTower
GreatNorthern
Opera House
BridgewaterHall
Shudehill
Victoria
MarketStreet
MosleyStreet
Deansgate-Castlefield
PiccadillyGardens
SackvilleGardens
ParsonageGardens
PiccadillyGardens
River Irwell
Rochdale
Canal
River
Medlock
SOUTH KING ST
CH
EETHA
M H
ILL
RD
MILLER STREET
NEW BRIDGE STBRID
GEW
ATER
DEA
NS
GA
TE
DEA
NSG
ATE
DEA
NSG
ATE
DEA
NSG
ATE
V
ICTO
RIA
S
TREE
T
GR
EAT D
UC
IE ST
CHURCH STREET
HIG
H
S
TR
EE
T
SHUDEHILL
SWAN STREET
VICTORIA
BRIDGE ST
CR
OSS
ST
REE
T
CO
RP
OR
ATI
ON
ST
REE
T
PRINC
ESS STREET
PRINCESS STREET
BRIDGE STREET
JOHN DALTON ST PICC
AD
PORTLAN
D S
TREET
PORTLAN
D
S
TREET
NEW
TON
QUAY STREET
PETER STREET PETER ST
OX
FOR
D STR
EET
OX
FOR
D R
OA
D
WHITWORTH STREET WEST WHITWORTH STREET WEST
WHITWORTH
ST
AY
TO
UN
ST
RE
ET
ALB
ION
S
TR
EET
LOW
ER
MO
SLEY
ST
LIVERPOOL RD
BLACKFRIARS STREET
PICCADILLY
OLD
HA
M
S
T
Spinningfields
NorthernQuarter
Chinatown
GREAT BRIDGEWATER ST
WINDM
ILL
ST
MU
SE
UM
ST
BOOTLE ST
CENTRAL ST
LLOYD ST
LLOYD ST
ALBERTSQUARE
ST ANN’SSQUARE
EXCHANGESQUARE
BARBIROLLISQUARE
BRAZENNOSE ST
SOU
THM
ILL
ST
LIBRARY WA
LK
TASLE ALLEY
CH
EP
STOW ST
GREAT BRIDGEWATER ST
KING ST
KING ST
MARKET ST
BOW LA
BOO
TH
ST
TIB LA
FOU
R
MARSDEN ST
CH
EA
PS
IDE
ES
SE
X S
T
ST ANN ST
YAR
DS
NEWMARKET
CHAPELWALKS
BANK ST
OLD
MO
ON
HA
LF
ST
ST MARY’SGATE MARKET ST
NE
W C
ATH
EDRA
L ST
FENNEL ST
LON
G M
ILLGATE T
OD
D ST
VICTO
RIA STATIO
N
HUNT’S BANK
APPRO
AC
H
WITHY GROVE
BALLOON ST
MIL
LGAT
E
LON
G
HANOVER STREET
FIRST
STREET
CHAPEL STREET
Second City Crossing
Second City Crossing
Existing Metrolink & stop
Proposed new stop
© Crown copyright and database rights 2011 Ordnance Survey 0100022610. Use of this data is subject to terms and conditions. You are granted a non-exclusive, royalty free, revocable licencesolely to view the Licensed Data for non-commercial purposes for the period during which Transport for Greater Manchester makes it available; you are not permitted to copy, sub-license,distribute, sell or otherwise make available the Licensed Data to third parties in any form; and third party rights to enforce the terms of this licence shall be reserved to Ordnance Survey
© Transport for Greater Manchester 2011 11-0331-111434
Second City Crossing indicative only, not to scale
5
6
St Peter’s Square is anticipated to contain the busiest tram stop on the Metrolink network and is currently subject to a major international design competition.
The existing stop in St Peter’s Square will be relocated to the northern end of the Square, near the Mosley Street/Princess Street junction and the existing tracks will be realigned between Elisabeth House and the Central Library. This will provide the opportunity to create a major civic space.
Following initial discussions with key stakeholders, it was agreed that the Cenotaph required a new setting which would provide better opportunity for contemplation. The area of the square by the Cooper Street entrance to the Town Hall provides an appropriate setting for this hugely important memorial, with a strong civic focus and much improved views from around the square.
As the detailed proposals for the relocation of the Cenotaph develop, ongoing consultation involving all key stakeholders will ensure continued involvement in advance of any planning application. The cross will remain in the southern end of the square and will continue to mark the location of St Peter’s Church.
The new St Peter’s Square stop will provide passengers with the ability to easily interchange between tram services from all parts of Manchester. !"#$%&'"%(')"(**%''"!#"+,'-.%''%'/"
leisure and retail facilities in the St Peter’s Square area, including the Central Library and Manchester Town Hall. It will also provide a close link to the many events held in Albert Square, such as the Christmas Markets, and connections with taxi and bus facilities in the area.
St Peter’s Square stop and relocation of the Cenotaph
Town Hall
AlbertSquare
Town Hall Extension
Met
rolin
k st
op
Central PublicLibrary &
Library Theatre
MidlandHotel
Meeting House
Princess Street
Mos
ley
St
Dickinson
Street
Lloyd St
Coop
er S
t
Geor
ge
Stre
etPeter St
Oxford St
St Peter’sSquare
© Crown copyright and database rights 2011 Ordnance Survey 0100022610.Use of this data is subject to terms and conditions. You are granted anon-exclusive, royalty free, revocable licence solely to view the Licensed Datafor non-commercial purposes for the period during which Transport for GreaterManchester makes it available; you are not permitted to copy, sub-license,distribute, sell or otherwise make available the Licensed Data to third partiesin any form; and third party rights to enforce the terms of this licence shall bereserved to Ordnance Survey
© Transport for Greater Manchester 2011 11-0331-111403
Second City Crossing indicative only, not to scale
7
!"#$%&'(#)!*(#!+#,$),#!-$%./,&),#!01213!455!67&8$5&!$#,!7%97.$)76,!(%5:!$%9!&8;<,.)!)(!=(97>.$)7(%3!?()!)(!&.$5,3
Artist’s impression of St Peter’s Square, currently subject to international design competition
"/,!'#('(&$5&!7%!@)!A,),#B&!@C8$#,!(D,#!)/,!(''(#)8%7):!)(!(')7=7&,!)/,!.767.!
space in the square, enhance the setting for the Cenotaph and provide a new
stop for Metrolink users.
8
Exchange Square stop
This stop is located in the heart of the city’s
main shopping area and attractions including the
Royal Exchange Theatre and Shopping Arcade,
Manchester Arndale, Marks and Spencer, Selfridges,
Manchester Cathedral, the Triangle, the Printworks,
the Medieval Quarter, the new National Football
Museum at Urbis and other major retailers.
This location for the tram stop minimises the impact
on servicing and access for retailers and businesses
and can be technically integrated into the surrounding
!"#$%!& !'()*#!+((,-.#!+(/0-',%$&*1(-*(2 00(-*(%3 $#!+(
good accessibility to this area of the city centre. The
stop will be easily accessible by ramps and steps.
© Crown copyright and database rights 2011 Ordnance Survey 0100022610.Use of this data is subject to terms and conditions. You are granted anon-exclusive, royalty free, revocable licence solely to view the Licensed Datafor non-commercial purposes for the period during which Transport for GreaterManchester makes it available; you are not permitted to copy, sub-license,distribute, sell or otherwise make available the Licensed Data to third partiesin any form; and third party rights to enforce the terms of this licence shall bereserved to Ordnance Survey
© Transport For Greater Manchester 2011 11-0331-111404 Second City Crossing indicative only, not to scale
New
Cat
hedr
al S
t
The Triangle
Urbis
Marks &Spencer
Selfridges
Manchester Arndale
ManchesterCathedral
ThePrintworks
ExchangeSquare
Corp
orat
ion
Stre
etM
etro
link
stop
9
Artist’s impression of how the Exchange Square area stop could look
!"#$%&'(#)!*(#!+#,$),#!-$%./,&),#!!01213!455!67&8$5&!$#,!7%97.$)76,!(%5:!$%9!&8;<,.)!)(!=(97>.$)7(%3!?()!)(!&.$5,3
10
The proposed Second City Crossing route passes through a number of
conservation areas and adjacent to many listed buildings. We are working
closely with MCC and amenity bodies to develop these proposals in a sensitive
manner that integrates with the urban realm and ensures that appropriate
consideration is given to the city’s rich heritage. The design detail will include
!"#$%& "'("#$%)*"#$!%"#!+,-(%./%.0,12,-(%'"#,%3.',!%42,1,%-331.31"-+,%+.%5,,3%
the street furniture to a minimum.
The Transport Strategy for Manchester City Centre (TSfMCC) aims to provide a
6.1,%,78",#+%2"$24-9%#,+4.15:%1,;("1,8+"#$%0,2"8',!%+2-+%(.%#.+%#,,(%+.%+1-0,'%
+21. $2%+2,%8"+9%8,#+1,%"#%.1(,1%+.%"631.0,%-88,!!%-#(%,-!,%+2,%<.4%./%+1-78=%
To operate the Metrolink Second City Crossing route successfully, the design
will be consistent with the access objectives of the Strategy.
>,8+".#!%./%2"$24-9%31.3.!,(%/.1%6.(")8-+".#%
include:
?% >+%@,+,1A!%>B -1,%C%8'.!,(%+.%-''%+1-78%-!%3-1+%
of MCC’s St Peter’s Square redevelopment;
?% Windmill Street – possible restrictions to
+1-78%-!%3-1+%./%+2,%DEE%!82,6,F
?% @1"#8,!!%>+1,,+%C%1,!+1"8+".#!%+.%+21. $2%+1-78F%
+4.%4-9%+1-78%31.0"(,(%/.1%& !,!%-#(%& !%$-+,%
imposed between George Street and Cooper
Street as part of the Cross City Bus Package
proposed in the TSfMCC;
?% @1"#8,!!%>+1,,+%C%+4.%4-9%+1-78%31.0"(,(%/.1%
trams as part of the 2CC scheme;
?% Cross Street between Newmarket Street and
G-15,+%>+1,,+%C%%8'.!,(%+.%+21. $2%+1-78:%
changes to servicing access and bus routes as
part of the 2CC scheme; and
Design, access and construction
11Artist’s impression of Cenotaph in St Peters Square currently subject to international design competition
! Corporation Street between Market Street and Withy Grove - closed
"#!!"$%&'!%(!)%$"!#*!"+,!-..!('+,/,0
In developing the scheme, we are carefully considering the needs of
pedestrians, cyclists and access and servicing requirements for businesses.
A key consideration in the delivery of the Second City Crossing is the
1,,2!"#!,3,'"45,67!/%1%8,!'#1("$9'"4#1!41!"+,!'4"7!',1"$,!,154$#1/,1"!"#!
minimise disruption to businesses. This will be managed by working closely
with MCC and other stakeholders to plan an appropriate construction
programme and working to an agreed Code of Construction Practice.
12
How you can take part
We would like to hear the views of local residents, community organisations,
businesses and anyone who visits the city centre for work or leisure.
There are three ways to let us know what you think about our proposals:
! Complete and detach the enclosed response form and return it to us at:
TfGM Metrolink Second City Crossing,
FREEPOST RRHE-RKUU-KSJY, Manchester, M1 3BG
! Visit www.tfgm.com/haveyoursay to complete the response form online
! Email [email protected] to register your comments
Please let us know your comments by 9 September 2011.
You can visit an exhibition in the city centre where more details on the
proposed scheme will be available. The team will be on hand to answer your
questions and provide more information.
Exhibition dates
Monday 27 June Manchester Town Hall 0900 - 1700
Wednesday 29 June Exchange Court Manchester Arndale 0900 - 2000
Thursday 30 June Victoria Station 0700 - 1900
Saturday 2 July Exchange Court Manchester Arndale 0900 - 2000
Tuesday 5 July Victoria Station 0700 - 1900
Thursday 7 July Manchester Town Hall 0900 - 1700
Sunday 10 July Exchange Court Manchester Arndale 1000 - 1800
Monday 11 July Bridgewater Hall 0800 - 1730
Thursday 14 July Manchester Town Hall 0900 - 1700
Saturday 16 July Triangle 0900 - 1800
Tuesday 19 July Manchester Town Hall 0900 - 1700
Saturday 23 July Triangle 0900 - 1800
Tuesday 2 August Bridgewater Hall 0800 - 1730
13
What are your views on the proposals?
We would like your views on the Metrolink Second City Crossing and the relocation of the Cenotaph.
Please enclose additional sheets if you wish to.
Q1. Are you? Male Female
About you
Your answers to the following questions will help us monitor who has taken
part in our consultation. The information you provide will only be used for
the purposes of this consultation.
Q2. Which age group are you in?
Under 16 16–24 25–39 40–60 Over 60
Q3. Do you have any long-term illness, health problems or disability which
limits your daily activities or the work you can do?
Yes No
If yes, what type of disability or impairment do you consider
yourself to have? Please tick all that apply.
Visual Hearing Speech Wheelchair user
!"#$%&' ()*+$,- .$/0&*12 Learning
Other
14
Q4. Which ethnic group do you consider that you belong to?
Q5. Which is your main means of travel around Greater Manchester (please
tick one):
Bus Metrolink Rail Taxi Car Cycle On foot
Other (please state)
Q6. Which of the following statements applies to how close you are
to the proposed line (please tick one):
My workplace is close
Where I live is close
Both my work and where I live are close
Neither my workplace nor where I live are close
I would like to be kept informed of 2CC project developments (please tick).
Name:
Organisation (if any):
Email:
Address:
Postcode:
The information you provide will only be used by TfGM for the purposes of development of 2CC. The information will be stored securely but may be passed to a third party engaged by TfGM for analysis.
15
Next steps
Your comments will be considered as the proposals for the Metrolink Second City Crossing and relocation of the Cenotaph within St Peter’s Square are developed.
!"#$%&#$'!()$*+,*,-()-$.,+$/00$(+#$*+#*(+#12$3.45$67))$report the results of the consultation to Transport for Greater Manchester Committee (TfGMC) and Greater Manchester Combined Authority (GMCA) and will seek formal approval to make an application for a Transport and Works Act Order. The Order will provide the powers needed to build and operate the Second City Crossing.
The results of the consultation will also be reported back to MCC Executive. At the same time, work will proceed to develop a detailed design for re-locating the Cenotaph to ensure that this is addressed as part of developing designs for St Peter’s Square. It is intended that comprehensive proposals will be produced for consideration by MCC Executive in the summer.
Following a period of tendering, construction of the 2CC scheme is likely to commence in 2013 and the new Metrolink Second City Crossing extension is planned to be in service late in 2016.
We will keep you up to date with information on this project via our website www.tfgm.com/haveyoursay
16
Calls to 0871 200 22 33 cost 10p a minute from BT landlines. Mobile and other
!"# $"%&"%'()*+,&-!.&/0!*1%&!"&!##$'$)"! &'!*$23&4$"%,&!*%&)5%"&6*)-&7!-&')&85-&
Monday to Friday, 8am to 8pm Saturdays, Sundays and public holidays.
If you would like this information in other formats
such as Braille, in large print, on audio CD or in
other languages, please phone Traveline on
0871 200 22 33
!"#$!#%&'#!($#)!*+#
Come to an exhibition (details inside this
%!9%':;&)*&.)<&/!"&1%'&-)*%&$"6)*-!'$)"&6*)-=&
>& (((3'61-3/)-?0!@%.)<*,!.
>& 50)"%&<,&)"&ABCB&DEE&BEEE
>& %-!$ &D//3-%'*) $"+F'61-3/)-
>& (*$'%&')&<,&!'&
Transport for Greater Manchester
Metrolink Second City Crossing
FREEPOST RRHE-RKUU-KSJY
Manchester
M1 3BG
©T
ran
spo
rt for G
rea
ter M
an
che
ster 0
8-0
512
/27
94
–L–
35
k–
0110
Appendix 2 – Media Schedule
Adverts
Advertisements were placed In the Manchester Evening News (MEN) 23rd June and 18th
August 2011 and METRO on 27th June and 22nd August.
Press Releases
05/09/2011 Last chance to have your say on second city tram line
19/08/2011 Last chance to have your say on second city tram line
12/08/2011 TfGM launch business engagement events on new Metrolink line
17/07/2011 (reissued to MEN only) Have your say on plans for a second city tram
line
08/07/2011 Have your say on plans for a second city tram line
09/06/2011 Consultation on second city tram line launched
Co
nta
ins
Ord
nan
ce S
urv
ey d
ata
© C
row
n c
op
yrig
ht
and
dat
abas
e ri
ght
20
10.
© 0
100
02
26
10 T
ran
spo
rt f
or
Gre
ater
Man
ches
ter
20
11 1
1-0
33
1-11
104
3-A
Sec
on
d c
ity
cro
ssin
g ro
ute
an
d p
rop
ose
d n
ew s
top
loca
tio
n
Exi
stin
g M
etro
link
line
and
sto
p
PETER
STREET
OXFO
RD S
TREET
D
EA
NS
GA
TE
D
EA
NS
GA
TE
D
EA
NS
GA
TE
V
ICT
OR
IA S
TR
EE
T
GREAT
BRIDGEWATE R S
T
CH
EP
ST
OW
S
T
P
OR
TL
AN
D S
TR
EE
T
PICCADILLY
O
LD
HA
M S
TR
EE
T
JOHN DALTON ST
P
RINCESS
STREET
MARKET STREET
WHIT
WORTH STREET
WEST
WITHY G
R
OV
E
S
HU
DE
HIL
L
SWAN STREET
MILLER STREET
CO
RP
OR
AT
ION
S
TR
EE
T
C
RO
SS
S
TR
EE
T
Pic
cad
illy
Gar
den
s
Dea
nsg
ate
- !"#$%&%$'
BALLOON ST
H
IGH
S
TR
EE
T
M
OS
LE
Y S
TR
EE
T
L
OW
ER
M
OS
LE
Y S
TR
EE
T
PRINCESS STREET
Man
ches
ter
Tow
n H
all
Bri
dge
wat
er
Hal
l
Man
ches
ter
Arn
dal
eTria
ngl
eS
ho
pp
ing
Cen
tre
Vic
tori
aS
tati
on
to A
ltri
nch
am
and
Ecc
les
to P
icca
dill
y
to B
ury
E
xch
ange
Sq
uar
e st
op
St
Pet
er’s
Sq
uar
e st
op
(rel
oca
ted
)
Mo
sley
Str
eet
Vic
tori
a
Sh
ud
ehill
Inte
rch
ange
Met
rolin
k S
eco
nd
Cit
y C
ross
ing
Pu
bli
c co
nsu
lta
tio
n
Tran
spo
rt f
or
Gre
ater
Man
ches
ter
is p
rop
osi
ng
a se
con
d M
etro
link
rou
te
thro
ugh
th
e ci
ty c
entr
e. W
e w
ou
ld li
ke t
o h
ear
you
r vi
ews
on
th
e p
rop
ose
d
new
ro
ute
an
d t
he
relo
cati
on
of
the
Cen
ota
ph
wit
hin
St
Pet
er’s
Sq
uar
e.
Co
me
and
tal
k to
us
at o
ne
of
ou
r ev
ents
wh
ere
ou
r te
am w
ill b
e o
n h
and
to a
nsw
er y
ou
r q
ues
tio
ns
at:
!
Ma
nch
est
er
Tow
n H
all
9am
to
5p
m: 2
7 Ju
ne,
7 J
uly
, 14
Ju
ly a
nd
19
Ju
ly
!
Bri
dg
ew
ate
r H
all
8am
to
5.3
0p
m: 1
1 Ju
ly a
nd
2 A
ugu
st
!
Ma
nch
est
er
Arn
da
le, E
xch
an
ge
Co
urt
10am
to
6p
m: 2
9 J
un
e, 2
Ju
ly a
nd
10
Ju
ly
!
Tria
ng
le S
ho
pp
ing
Ce
ntr
e
9am
to
6p
m: 1
6 J
uly
an
d 2
3 J
uly
!
Vic
tori
a S
tati
on
7am
to
7p
m: 3
0 J
un
e an
d 5
Ju
ly
Ple
ase
tell
us
wh
at y
ou
th
ink
by
9 S
ep
tem
be
r 2
011
!C
om
ple
te a
nd
ret
urn
th
e re
spo
nse
fo
rm in
th
e b
roch
ure
ava
ilab
le f
rom
Trav
elsh
op
s in
Pic
cad
illy
Gar
den
s an
d S
hu
deh
ill In
terc
han
ge o
r at
on
e
of
ou
r p
ub
lic e
xhib
itio
ns
!V
isit
ww
w.t
fgm
.co
m/h
ave
yo
urs
ay
to
co
mp
lete
th
e re
spo
nse
fo
rm
! E
mai
l yo
ur
com
men
ts t
o 2
cc.m
etr
oli
nk
@tf
gm
.co
m
Appendix 3 Second City Crossing Flyer
Metrolink
Second City CrossingTransport for Greater Manchester is promoting a
second Metrolink route across the city centre with a
new stop at Exchange Square and a new larger stop
at the north end of St Peter’s Square.
It is also proposed to relocate the Cenotaph to a
new setting within St Peter’s Square.
www.tfgm.com
Artist’s impression of how the Exchange Square area stop could look
The proposed Metrolink Second City Crossing is part of the major Metrolink
expansion programme that will see the network triple in size by 2016 and will:
! enable more tram services to run across the city centre
! improve the reliability of all Metrolink services
! provide easy access to more parts of the city by tram
Public exhibitionsVisit one of our public exhibitions where our team will be on hand to answer
questions on the details of the scheme at:
! Manchester Town Hall
9am to 5pm: 27 June, 7 July, 14 July, 19 July
! Bridgewater Hall
8am to 5.30pm: 11 July and 2 August
! Manchester Arndale
9am to 8pm: 29 June, 2 July and 10am to 6pm: 10 July
! Triangle Shopping Centre
9am to 6pm: 16 July and 23 July
! Victoria Station
7am to 7pm: 30 June and 5 July
To find out more and to tell us what you think visit
www.tfgm.com/haveyoursay or phone 0161 244 1444
Artist’s impression of St Peter’s Square, currently subject to international
design competition
Artist’s impression of a new tram on Cross Street