method statement[2]

Upload: ab5918590

Post on 03-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Method Statement[2]

    1/11

    PLANNING AND PREPARATION

    1.0 PURPOSE: This method statement provides guidance to prevent injury to persons engagedin excavation works on the site.

    2.0 SCOPE: Planning, preparation conduct and Method of excavation work.

    3.1 CONSULTATIONThe principal contractor, the contractor doing the work, employers, employees and theirrepresentatives will consult with each and determine the provision of all safeguards. The consultationprocess will be used during the planning and preparation stages to determine safe systems of workbased on the assessment of the risks. Structural or geotechnical engineers will be involved in theconsultation process when appropriate. The consultation process will at least cover the following!a" #ature and condition of the ground or working environment.!b" #ature of the work and other activities that may a$ect safety!c" Static and dynamic loads near excavation!d" %nteraction with other trades!e" &orkplace access!f" Management of surrounding vehicular tra'c and ground vibration!g" &ork force safety

    !h" Type of e(uipment used for excavation!i" The provision of appropriate amenities, which will depend on the type of work space.!j" )ompliance with all *S+ regulations

    3.2 PLANNINGPlanning and preparation will be the rst essential step in ensuring that work is done safely. Planningand preparation will involve consultation with all relevant persons engaged in the work and willinclude ha-ard identication, risk assessment and risk control processes. &here appropriate, theadvice of a geotechnical engineer will be sought before starting excavation work. The principalcontractor and the contractor in their capacity as employers will. Provide such information, instruction, training and supervision as maybe necessary to ensure thehealth and safety of his employees/ and0.Provide or maintain means of access to and egress from the work place safe and without risks.

    3.3 PLANNING BY PRINCIPAL CONTRACTORThe principal contractor will plan for the work to be done safely. The principal contractor will ensurethat a site specic occupational health and safety management plan is prepared and documented foreach place of work where excavation is to be carried out, before the excavation work commences.This plan will be developed in consultations undertaken with the contractor1s and their employees orrepresentatives. The plan will include a documented work method statement, provided by thecontractor, describing how the work is to be done safely. The health and safety management plan willbe monitored to ensure that work is carried out according to that plan and that the plan is e$ective.The plan will be maintained and up to date during the course of the excavation works. 2eforeexcavation work starts, the principal contractor in consultation with the contractor doing the work willat least consider!a" 3n assessment of the risks involved in carrying out the work.!b" the most appropriate method to prevent any risk of injury.!c" 3n assessment of the ground conditions and working environment!d" Providing suitable and safe access to and from the work place including the work area.!e" The area of the excavation work will be clearly dened by barricades and warning signs.!f" &here necessary the exact location of the work will be clearly marked.!g" The identication and marking of the location of any above ground, underground or overheadservices!h" That the work does not a$ect the structural integrity of adjoining buildings or structures, roads,footpaths.!i" +lectrical safety, including the location of underground and aboveground service cables and nearbyoverhead power lines and providing systems of work which comply with *S+ regulations.!j" That all persons carrying out the work will receive appropriate supervision, training and instruction.

    !k" Security of excavation during work and when left unattended.!l" +stablishment of emergency and rescue procedures in the event of an emergency.

    3.4 PLANNING BY THE CONTRACTOR

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    2/11

    The contractor doing the work has an obligation under *S+ regulations to provide and maintain aworkplace that is safe and without risks to health for their employees in relation to those matters overwhich he has control. %n addition to consultation with the principal contractor in the overall jobplanning, the contractor will at least consider!a" 3n assessment of the risks in carrying out the work.!b" The most appropriate methods of preventing the risk of injury.!c" Providing a documented safe work method statement describing how the work will be done safely.This safe work method statement will take into account an assessment of the risk involved in carrying

    out the work.!d" Providing suitable and safe access to and from the work area at all times.!e" Preventing persons entering a work area where there is a risk of injury.!f" 3n assessment of manual handling tasks which could cause back strains another injuries andproviding systems of work which comply with the provisions of *S+ regulations.!g" That the location of overhead and underground services, i.e. electricity and telecommunicationcables, are identied and clearly marked.!h" +lectrical safety, including the location of underground electrical service cables and nearbyoverhead power lines and providing systems of work which comply with *S+ regulations!i" The use of personal protective e(uipment !PP+" e.g Safety footwear, eye, coveralls, high visibilityjackets, hearing protection, safety helmets, gum boots, gloves, disposable clothing etc.!j" That all persons carrying out the work are provided with appropriate training and instruction.!k" That supervision is provided by a competent person.

    !l" +stablishment of emergency and rescue procedures in the event of an emergency.

    3.5 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL3 ha-ard identication risk assessment and control process will be carried out by the contractor inconsultation with the principal contractor to determine if persons are at risk. Safe systems of work willthen be put into place to control the risk. The identication of the ha-ards associated with excavationwork, the risk assessment and the risk control measures will be documented. The process of ha-ardidentication, risk assessment and control is made up of the following steps. %dentify the ha-ards0. 3ssess the risk!s" arising from the ha-ards.:. ;se appropriate control measures to eliminate or reduce the risk!s".6. Monitor and review the control measures to ensure continual safety. 3fter identifying the ha-ardsinvolved in carrying out the work the principal contractor in consultation with the contractor willassess the health and safety risks and determine what type of safeguards or systems of work will beimplemented to ensure the health and safety of all persons on site. This will always includeeliminating exposure of persons to the ha-ard.

    3. HIERARCHY OF CONTROL MEASURESThe following hierarchy of control measures is listed in terms of levels. Selecting the highest levelpossible to develop each control measure.5evel +liminate the ha-ard

    < =or example, choose di$erent +xcavation method.5evel 0 Minimi-e the risk by

    < substituting the system of work or plant !with something safer".< modifying the system of work or plant !to make it safer".

    < isolating the ha-ard !e.g. introduce a restrictive work area".< introducing engineering control !e.g. dust control".5evel : >ther controls

    < adopting administrative controls such as ha-ard warning signs and specic training and workinstructions.< using personal protective e(uipment !e.g. eye, respiratory and hearing protection". The controlmeasures at 5evel !eliminate the ha-ard" give the best results and will be adopted. The measuresat 5evels 0 !minimi-e the risk" and : !other controls" are less e$ective and they re(uire morefre(uent reviews of the ha-ards and systems of work. %n some situations a combination of controlmeasures may need to be used. The control measures recommended by the contractor will beconsidered by the principal contractor as part of the health and safety management plan. 3ny newcontrol measures will be evaluated to ensure that they are e$ective and safe and that new ha-ardsare not created !directly or indirectly" by them.

    3.! PREPARATION&hen preparing for the commencement of work the principal contractor and the contractor doing thework will ensure that the workplace is safe based on the health and safety management plan. They

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    3/11

    will also check to ensure that all controls identied by the risk assessment have been put in place andthat none ha-ards exist. Preparation will also at least include

    !a" an assessment of climatic1environmental conditions.!b" access to and from the workplace.!c" specic instructions for employees.!d" that plant and e(uipment is suitable for the intended use and inspected bay third party beforeuse and is properly maintained.!f" personal protective e(uipment.

    !g" that the location of underground, above ground and overhead services are identied and clearlymarked.!h" emergency and rescue procedures in the event of an accident, injury or other emergency,including the means of protect any other persons in the vicinity.

    3." EMERGENCY AND RESCUE PROCEDURESThe contractor will ensure that, in the event of an emergency, ade(uate arrangements have beenmade to ensure the safety of workers and other persons on site. The emergency may result from anaccident or injury, landslip or other potentially dangerous occurrence. #atural disaster includingelectrical storms, ?oods, plant or machinery re etc may also present ha-ards to the workingoperations. The contractor will plan for such matters and ensure that appropriate control measuresare in place. The risk assessment will take into account the following factors

    !a" nature of ha-ard and possible emergencies/

    !b" si-e and location of place of work/!c" number and mobility of persons at the workplace/ and!d" location of nearest emergency services.

    )ontrol measures may include!a" development and communication of a warning system.!b" development and communication of

    safe and rapid evacuation procedures, including injured persons.!c" having trained personnel to oversee evacuation and rescue procedures until emergency

    authorities arrive.!d" appropriate medical treatment and evacuation of injured persons.!e" shutting down of work, including plant and electrical e(uipment.!f" provision of reghting e(uipment at appropriate locations.!g" display of evacuation procedures in appropriate location!s"

    4. #ORK SYSTEMS AND CONTROL MEASURESThe principal contractor and contractor have an obligation under *S+ regulations to provide andmaintain a workplace that is safe and without risks to health for their employees in relation to thosematters over which they have control. )ontrol measures to prevent persons being injured duringexcavation work will be provided and maintained as part of a safe system of work. The system of workand control measures selected will be determined by individual job factors identied in theconsultation and risk assessment process. The following ha-ards are commonly associated withexcavation work and will be considered by the risk assessment process

    !a" the fall or dislodgement of earth and rock!b" the instability of the excavation or any adjoining structure!c" the inrush or seepage of water!d" unplanned contact with utility services eg, electricity

    !e" the placement of excavated material!f" falls into excavations!g" the movement and positioning of heavy plant and e(uipment a$ecting the excavation!h" ground vibration a$ecting the stability of the excavation!i" vehicle movement!j" excessive noise from the operation of machinery and plant!k" manual handling injuries!l" changes to excavation conditions.

    4.1 PRE$ENTION OF COLLAPSE OR FAILURE OF TRENCHES AND OPEN E%CA$ATIONS3 risk assessment will be conducted to determine which controls will be implemented to preventpersons being injured by collapse or failure of all or part of a trench or open excavation. %t willconsider at least the following

    !a" the depth of the excavation/!b" the nature of the strata 8 sand, clay, shale, ?oaters, etc. including their likely behavior upon

    exposure to the elements/!c" fractures or faults in rock.!d" the presence of moisture or water/

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    4/11

    !e" the possibility of exposure to wet weather and water from other sources/!f" any load close to the edge or in the -one of in?uence of the excavation/!g" vibration/!h" the exposure time/!i" any previous disturbance of the ground, eg previous excavations/ and!j" adjoining buildings or structures @emoval of soil from an excavation causes unbalanced soil

    stresses which reduce the capacity of the excavation to support itself.

    There may be additional geotechnical engineering issues that will be considered. 3ccordingly wherethe risk assessment identies the risk of an unstable condition, the following measures will beconsidered before starting excavation work

    !a" seeking advice from appropriately (ualied engineers,!b" carrying out a geotechnical analysis,!c" engaging a competent person to supervise the progress

    of the excavation work. Shoring systems, benching and battering are engineering issues thatinvolve both structural design and soil mechanics. The use of ade(uate shoring, benching andbattering is essential to control the risk of a collapse or failure of a trench or open excavation.

    4.2 DESIGN OF ENGINEERING CONTROLS7esign specications for engineering controls such as shoring support structures, benching orbattering will be prepared by an appropriately (ualied person in accordance with relevant standardsand codes. %n developing specications, at least the following factors will be considered

    !a" the si-e and strength of the component members of the shoring!b" existing and changing ground conditions!c" the loads and types of ground or soil conditions to be shored!d" static loads near excavation, eg. spoil pile, buildings and structures!e" dynamic loads near excavation, eg. tra'c and excavation e(uipment!f" ground vibration, eg. heavy tra'c, mobile plant, and pile driving.!g" di'culties or risks that other services may pose ie overhead power lines, existing or proposedunderground services!h" working environment such as exposure to dust, noise, water,!i" that systems of work are in accordance with any re(uirements of the *S+ regulations!j" location of utility services!k" safety during installation and removal.

    4.3 SHORING&here necessary, all trenches and excavations will be ade(uately shored or supported to prevent afall or dislodgement of earth, rock or other material forming the side of or adjacent to, any excavationwork from burying, trapping or striking a person that is in the excavation. &here such a risk alsoexists for those installing supports, other appropriate control measures will be in place to ensure thesafety of persons entering the excavation. 3 shoring system will not be re(uired if, having regard tothe nature and slope of the side of the excavation and other relevant circumstances there is noreasonable likelihood that earth, rocks other material will fall or dislodge from a height ofmorethan.9m and bury, trap or strike a person that is in the excavation. The risk assessment processwill be used to identify unstable conditions and the risks involved. Shoring the face of an excavationwill proceed as the work of excavation progresses. &here a mechanical digger is used, the riskassessment will be used to determine whether any part of the trench may be left unsupported.Shoring may include any suitable system of temporary support sand sheeting material used to

    maintain the stability of the sides of an excavation. The installation and removal of shoring will takeplace from outside an excavation.

    4 .3.1 REMO$AL OF SHORING SUPPORTS&hen removing shoring, the support system will be extracted 1 dismantled inthe reverse order of itsinstallation. Persons performing the work in the excavation will not work outside the protection of theground support system.

    4 .4 BENCHING AND BATTERING E%CA$ATION #ALLS2oth benching and battering of excavation walls are methods of work which may be used to minimi-ethe risk of the soil or rock slipping onto the excavation. %f battering is implemented, it will commencefrom the bottom of the excavation. &hen benching or battering the walls of an excavation, an angleof repose of 69 degrees will not be exceeded unless certied in writing by a geotechnical engineer.

    4.5 INSPECTION OF SUPPORT SYSTEMS&here risks or ha-ards that create a risk to health and safety of those carrying out the work areidentied, they will be controlled prior to any further work being carried out. This may re(uire furtheradvice from geotechnical and design engineers to review the ade(uacy of the control measures in

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    5/11

    place. The risk assessment will be reviewed at all terms during the excavation works. The followingconditions will be considered or monitored!a" shoring becoming unstable!b" shoring components not secure or failing!c" angle of batter remains su'cient to prevent collapse!d" premature removal of shoring!e" workers in excavations venturing outside the connes of shoring, benching or battering!f" cracks appearing near the edge of an excavation

    !g" excavated and other material being placed within the -one of in?uence of the excavation!h" machinery operating within the -one of in?uence of excavations causing weight and vibrationin?uences!i" surface soil falling into the excavation!j" water seeping into excavations from its side walls or base!k" changes to soil and1or weather conditions!l" extra loading!m"surface water or run8o$ entering the excavations or accumulating on surface near the excavation!n" inclined bedding planes AdippingB into the excavation!o" heaving or swelling of the ground at the bottom of the trench!p" subsidence alongside the excavations!(" unsafe access or egress!r" exposure of contaminated ground

    !s" undercutting of the excavation

    4 . SECURITY OF E%CA$ATIONS3 risk assessment will be conducted in order to determine which controls will be implemented toensure the security of excavation both during work and when left unattended. The control measuresimplemented will be appropriate and e$ective for the ha-ards and risks of the situation. )onsiderationwill be given to factors such as how long the excavation will be open, and who may gain access to theexcavation. The following control measures will be considered!a" isolating the ha-ardous area, such as by the use of perimeter fencing, barricades, screens,barriers, handrails and1or covers, which are capable of preventing access or preventing the fall of aperson!b" removal or lowering ladders on work site!c" immobili-ation of plant to prevent unauthori-ed use!d" compliance with relevant *S+ re(uirements.!e" ha-ard warning lights, signs, markers or ?ags!f" site security measures, including fencing or use of safety observer!s"!g" night lighting.Signs will be erected around the site showing the name and contact telephone number !includingafterhours emergency number" of the principal contractor1contractor emergency numbers.

    4 ..1 FALL PRE$ENTION3 safe system of work and appropriate control measures will be provided wherever persons areexposed to a risk of falling during excavation work. %t is a *S+ re(uirement to e$ectively fence allexcavations and holes more than.0m deep. %t will also be noted that all platforms, open sides ofstairways and stairway landings will be fenced. %n addition to the security measures listed above, the

    following measures to prevent falls will be considered!a" use of intermediate platforms for deep excavation!b" provision of a safe means of movement between di$erent levels of the excavation!c" provision of an ade(uate fall arrest system!d" backlling as work progresses )ontrol measures will be properly installed and maintained until thework is completed or until there is no longer any risk of persons falling into the excavation.

    4 ..2 PRE$ENTION OF DRO#NING&here, during excavation work, and excavation is likely to collect or retain water so as to create aha-ard to persons in the vicinity, the excavation will be covered or fenced o$. )ontrol measures willbe provided where there is a risk of a person drowning as a result of a fall into water or other li(uid,e.g. slurry. The following measures will be considered!a" provision of positive means of fall protection such as fencing, handrails and safety harness

    !b" provision of an observer.

    4 .! UNDERGROUND SER$ICES2efore starting the work, the location of any underground services !e.g. electricity, telecommunicationcables, etc." will be identied. &herever service plans are available they will be obtained by the

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    6/11

    principal contractor and also provided to the contractor and operator carrying out the excavationwork. The contractor will allow for inaccuracies and the possibility of other unknown or hiddenservices. =urther, the principal contractor will arrange for these services to be clearly markedaccording to the available plans and on site checks prior to commencement of work. Services will beexposed at su'cient intervals to positively identify their location and1or lie. The following are ways ofchecking for underground services!a" using remote location devices!b" hand digging, using hand tools with non8conductive handles. 3ll persons whose work may be

    a$ected by an underground service will be advised of the location of every underground service.3ppropriate control measures will be implemented after consultation with relevant service providers.These measures may include the protection, support or removal of services to ensure safety ofworkers.

    4 ." E%CA$ATIONS AD&ACENT TO BUILDINGS OR STRUCTURESThe contractor will ensure that excavation work which is likely to reduce the security or stability ofany part of any building or structure will not be commenced or continued unless ade(uate steps aretaken before and during the progress of the work to prevent danger to any person from collapse ofthe building or structure or a part of a building or structure. %n assessing the risk, measures such asthe following will be considered before starting excavation work!a" seeking advice from appropriately (ualied engineers!b" undertaking a geotechnical analysis

    !c" engaging a competent person to supervise the progress of the excavation work!d" underpinning of structures!e" construction of e$ective retaining walls!f" minimi-ing ground disturbance and vibration by taking into account the location of machinery, these(uence of work, the impact, severity and scale of excavation!g" backlling as work progresses!h" evacuation of a$ected areas. The contractor will also ensure the stability of vehicular access whichmight be a$ected by the work.4.' PROTECTION AGAINST RISING, IRRUPTIONOR INRUSH OF #ATEROR MATERIALThe contractor will ensure that where there is risk from rising water or from an eruption of water ormaterial, the means to enable every person to reach a position of safety will be provided. %f a riskassessment reveals a risk of rising, irruption or inrush of water or material, appropriate controlmeasures will be provided. These may include the following!a" provision of exploratory or warningholes where water ?ows at a reduced rate to warn of danger!b" provision of sumps!c" lowering thewater table !eg use of spear pumps"!d" increasing exit points e.g. increasing the number of exitladders!e" provision of pumps

    4.10 MATERIALS AND LOADS ABO$E AND NEAR E%CA$ATIONSTo reduce the risk of excavation collapse, excavated or other loose material will be e$ectively storedor retained away from the excavation. +xcavated material will be placed outside the -one ofin?uence. 3lternatively the support system will be designed to accommodate such additional loadincluding ground water pressures, saturated soil conditions and saturated materials. Mechanical plant,vehicles, storage of materials or any heavy loads will be prevented from approaching within orencroaching on the -one of in?uence of the excavation unless the support system has been

    specically designed for such loads. &here the risk assessment has identied a risk of collapse as aresult of loads or materials above or near the excavation, shoring will be in place before any personenters the excavated area. The following measures will also be considered before starting excavationwork!a" controlling access to exclude persons from ha-ardous areas, e.g. relocating means ofaccess!b" moving and storing loads outside the -one of in?uence of the excavation!c" provision ofwheel stoppers to limit movement of mobile e(uipment adjacent to the excavation!d" reducing thenumber of trench shields stored near excavation by pulling along trench shields and backlling as theexcavation progresses !e" securing all loose materials in place. &hen working on a slope, a riskassessment will be conducted to determine the safest side of the excavation to dump soil andexcavated material. This will often be on the lower side of the slope to reduce the risk of wall collapseor material falling into the excavation. Site factors will be considered.

    4 .11 PROTECTION FROM FALLING OB&ECTS

    The risk assessment will be used to determine appropriate control measures toprotect persons fromaccidental falls of objects including tools, plant and other construction materials. 3s far as practicable,loads will not be suspended or travel over a person. The following control measures will beconsidered!a" fences

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    7/11

  • 8/11/2019 Method Statement[2]

    8/11

    !e" tra'c and plant controls!f" safety fences and warning signs.

    4 .14.1 LIGHTING3de(uate lighting !natural or articial" will be provided to ensure the work areas and access ways arewell lit. 3de(uate local lighting will be provided for detailed work, for dangerous processes and wheremachinery is being operated. &hen articial lighting is used, including lighting for night work, thecontractor will ensure it does not create excessive glare or shadows.

    4 .14.2 RAMPS&hen access ramps are provided they will not exceed 0.E !0F degrees" or as per design.@ampssteeper than G !E degrees" will be cleared, grated or have surfaces which allow ade(uate foot grip.&here such ramps form part of an excavation, a risk assessment will be conducted to determine themaximum safe soil height above the ramp before some sort of soil support !e.g. trench shield" isprovided. @amps will be designed and constructed to e$ectively withstand any anticipated load thatthey may be re(uired to support during use.

    4 .14.3 LADDERSwhen ladders are used for access the contractor will provide the following!a" the ladder will be secured at both top and bottom against displacement. 5adders will have non8slipfeet and whenever practicable will be set up at an angle of 6 !E9degrees".

    !b" a safe and ade(uately si-ed landing place when stepping o$ the ladder will be provided.!c" the stiles of the ladder will extend at least one meter above the landing place.!d" metal or wire reinforced ladders will not be used where there is a risk of contact with electricalconductor wires!power lines" or of electric shock. #on8conducting ladders will be used or a clearanceof at least 6metres from conductors will be maintained.

    4 .14.4 SCAFFOLDINGSca$olding will be used to provide workers with a safe temporary work platform. %t will be planned,erected, inspected and tagged by competent persons and will be regularly inspected to ensure thereare no risks to safety and will comply with the re(uirements of *S+ regulations..

    4 .14.5 FI%ED PLATFORMS, #ALK#AYS, STAIR#AYS AND LADDERS=ixed platforms, walkways, stairways and ladders will comply with the re(uirements of *S+regulations

    4 .15 #ORKS NEAR TRAFFIC OR MO$ING PLANTPlanning and preparation will also include the development of a vehicle movement procedure for eachworksite. Hehicle movement procedures will identify the preferred travel paths for vehicles associatedwith a work site entering, leaving or crossing the through tra'c stream. 3 vehicle movementprocedure will include persons, moving e(uipment, plant and vehicle tra'c in the work area and alsoidentify travel paths for trucks at key points on routes remote from the work site, such as places toturn around, accesses, ramps and side roads. 3 vehicle movement procedure will be a documented

    procedure, a diagram, combined with or superimposed on a Tra'c )ontrol Plan, or may be verbalinformation and instructions specic to the particular construction workplace or site. The riskmanagement process will be used to determine which is the most appropriate. 3 risk assessment willbe conducted to determine what type of safeguards or systems of work that be implemented on thesite and will include eliminating exposure of persons to moving plant. Hehicle movement procedureswill be developed based on the risk assessment and will be developed each time the conditions onthe site change in a way that may a$ect the health and safety of persons. The risk assessment willconsider at least the following!a" isolating vehicles and plant used in or around the site and work area from persons on the site or

    work area, e.g. vehicles or persons may be guided around or past the work area.!b" securing the area where moving plant is being used e.g. fencing, barriers, barricades, temporary

    warning or control signs or a combination.!c" planning the direction that the plant moves so that the visibility of operators is not restricted. This

    will also include an assessment of the visibility of plant and tra'c from all areas of the work site.!d" the use of spotters1safety observers to control tra'c movement!e" implementing safe working

    distances

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    9/11

    !f" the use of audible reversing alarms and1or other technologies or other safe work practices. #otereversing alarms may cause confusion where multiple plant is using the same area and othersystems of work may be re(uired.

    !g" minimi-ing the number of moving plant working at one time. &here multiple plant is beingoperated around the work site a competent person will be used to direct the plant< when operating in close proximity to each other/< when reversing/< where persons are on the ground/ and

    < in other situations as indicated by the risk assessment.!i" where construction vehicles or plant enter or leave the work area by public roads, systems of

    control and notices will be placed at all entrances and exits to the work area to protect and warn allpersons approaching or in the vicinity

    !j" where plant is being operated near persons, near underground or aboveground services !any otherworkers, soils technicians, surveyors, visitors etc.

    !k" designated delivery and turning areas. The movement of delivery vehicles on construction sitesfre(uently presents a ha-ard particularly when reversing, loading and unloading. Procedures will beimplemented to warn all persons a$ected by the potential ha-ard. These procedures will include< the re(uirement for truck drivers to report to a suitably signposted area on the site/< the re(uirement for a designated worker to act as an observer to ensure all persons are clear of

    the reversing vehicle/ and< a system of communication and warning to persons near delivery point. 3ll personnel on site will

    wear high visibility garments.

    4 .1 NOISE#oise management provisions will be carried out by the contractor doing the work and will ensurenoise levels from machinery or e(uipment being used do not become a risk to hearing or health. 3nappropriately (ualied person will conduct a noise assessment to determine the level of noise thatemployees are exposed to. &here the noise is in excess of the noise exposure limits, engineeringcontrols will be implemented. &here this cannot be achieved or work cannot be organi-ed tominimi-e exposure, appropriate hearing protection e(uipment, hearing protectors, will be provided toall persons in the vicinity of the noise. The contractor will also ensure compliance with @5)+nvironmental Protection re(uirements in relation to noise.The contractors will ensure that all necessary prevention or protection measures are taken to ensurethe health and safety of persons who may be exposed to excavated material. &here there is a risk ofinhalation of harmful airborne substances such as silica dust or contact with harmful soilcontaminants, the contractor will ensure a safe system of work. The risk assessment process will beused to determine the engineering controls, work practices and site, atmospheric monitoring re(uired.3ppropriate assessment of the exposure levels will be undertaken before selecting the controlmeasures. The assessments will consider!a" any persons on site, including other contractors or persons working on the site/!b" persons conducting the assessment and site remediation, including subcontract workers/!c" visitors to the site !for example, couriers"/ and!d" site neighbors !as appropriate". The contractor will also ensure that exposure to nonha-ardoussubstances such as nuisance dust is at a level not greater than that established by safe exposurestandards. %n dry conditions, fre(uent watering, where practicable, or other similar methods will beused to reduce nuisance dust that will not exceed0Fmg1m:.

    *ydrogen Sulde )arbon dioxide +mployers will implement a suitable system of work so as to ensurea safe repairable atmosphere and e$ective ventilation and will protect persons against the e$ects ofinsu'cient oxygen. These may be encountered when carrying out work such as excavations forfoundations, in addition to trenches. &here the risk assessment indicates the possibility of aircontamination, the work will be examined by competent persons using appropriate detectinge(uipment and will include air testing for!a" oxygen deciency!b" airborne contaminants

    5 . INSPECTION AND MAINTENANCE OF PLANT AND E(UIPMENT3 risk assessment will be conducted before operating plant to identify any ha-ards that may arise andthe control measures to be implemented. The risk assessment will consider at least the following

    !a" that appropriate guards, including roll8over protective devices !@>PS" are tted!b" that the safe working load is displayed!c" record of testing, maintenance, servicing and repair!d" the general mechanical1electrical condition of plant, especially any wear or damage that may

    a$ect safe operation

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    10/11

    !e" specic controls to prevent entanglement or workers being trapped between moving parts. 3llplant such as excavators, tractors, etc. used for lifting will have their safe working loads displayedand maintained. %f the function or condition of plant represents an immediate risk to health andsafety, operation will cease and the plant will be withdrawn from use until a risk assessment andappropriate control measures are implemented.

    5 .1 ROUTINE INSPECTION@egular planned inspection and ade(uate maintenance will be carried out to ensure safe operation of

    all plant used on excavation work, whether leased, hired or owned. 2oth mechanical and electricaltesting will be done. The following checks will also be carried out!a" 7aily checks general condition and maintenance of the plant will be checked daily by the persondoing the excavation work.!b" @egular checks the plant will be inspected by a competent person on a regular basis, or at leastevery two weeks.

    5 .2 REPAIRS AND MAINTENANCEThe contractor will ensure the plant repairs will be carried out by a competent person and inaccordance with the designerDs or manufacturerDs re(uirements.

    5 .3 REPORTING DEFECTS3ny defects to e(uipment will be reported immediately to the person responsible for maintaining such

    plant. &here a defect is likely to pose an immediate risk to health and safety the e(uipment or plantwill not be used until the defect is rectied.

    5 .4 LOG BOOKS AND INSPECTION CHECK SHEETSThe contractor will keep logbooks and inspection check sheets containing a full service and repairshistory of the e(uipment.

    . TRAINING AND INSTRUCTION;nder *S+ regulations employers will provide training, instruction, information and supervision, asmay be necessary, to ensure the health and safety at work of their employees. This will be providedby a competent person. 3ll persons involved in any excavation or associated work will< be trained to follow systems of work and work practices that enable them to perform their work in amanner that is safe and without risks to health, and/< hold appropriate certicates of competencies where re(uired, particularly in the operation and useof load shifting e(uipment.>nly persons who have received training and instruction will carry out the work. The training providedand the instruction given will at least include

    !a" induction training which complies with )onstruction Safety 4 *S+ regulation!b" the work method to be used for the excavation or associated work and the manual handlingprocedures for the work to be carried out, including control measures based on the risk assessment toprevent injury.!c" the correct use, care and storage in accordance with the manufacturerDs recommendations whereappropriate, of< personal protective e(uipment/ and

    < tools and e(uipment to be used.!d" the use of plant and associated e(uipment, including electrical safety and ha-ardous substances.!e" procedures to be adopted in the event of accident, injury or other emergency, includingevacuation.

    ! . PERSONAL PROTECTI$E E(UIPMENT )PPE*The use of PP+ to control ha-ards and risks is the least e$ective measure and is lowest on thehierarchy of control measures. )ontrol measures will be selected from the highest level possible andbe adopted where practicable. The measures at the lower levels are less e$ective and they re(uiremore fre(uent reviews of the ha-ards and systems of work. They will only be used when other controlmeasures are impracticable or when, after implementing other controls, a residual risk remains.

    ! .1 PRO$ISION OF PPE

    2efore commencing any work, the principal contractor and or contractors will identify any conditionslikely to a$ect the health and safety of persons. %f other means of control are not practical, theprovision and use of appropriate PP+ that complies with the relevant *S+ regulations will bearranged. +mployees will be trained till they are competent in the proper selection, use and

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9

  • 8/11/2019 Method Statement[2]

    11/11

    maintenance of the PP+. There will be su'cient supervision and monitoring conducted to ensurecompliance.

    ! .1.1 SAFETY HELMETSThe use of safety helmets may prevent or lessen a head injury from falling objects or a person hittingtheir head against something. &here there is a likely hood of persons being injured by falling objectsand overhead protection is not provided, persons will be provided with and will use an appropriatesafety helmet. 3ppropriate safety helmets will also be provided and used where a person may strike

    their hand against a xed or protruding object or where there is a risk of accidental head contact withelectrical ha-ards.3ll persons on excavation sites will wear head protection that conforms to occupational protectivehelmets.

    ! .1.2 EYE PROTECTION+ye protection complying with *S+ regulations will also be provided, where there is a risk of eyeinjury. Selection, use and management systems will comply with *S+ regulations

    ! .1.3 PERSONAL HEARING PROTECTION3 noise assessment will be conducted to determine the level of noise that employees are exposed to.&here the noise is in excess of the noise exposure limits, engineering controls will be implemented.

    ! .1.4 HIGH $ISIBILITY GARMENTS+SAFETY REFLECTI$E $ESTSPersons working near tra'c, mobile plant or e(uipment under operator control, will be provided withand use high visibility garments. >ther clothing not covered by the high visibility garment will be lightcolored and all garments will be selected for best contrast with the surrounding background.

    ! .1.5 SAFETY GLO$ES&here there is a risk of hand injury hand protection that complies with *S+ regulations will beprovided and used.

    ! .2 MAINTENANCE AND USE OF PPEThe contractor will provide such information, instruction, training and supervision as may benecessary to ensure that PP+ are used and maintained as intended. 3ll PP+ used by persons duringexcavation work will be regularly inspected and replaced as necessary.

    ". OCCUPATIONAL HEALTH AND SAFETY&hile the obligation for each person is di$erent, all persons will ensure that the way they carry outtheir work will not interfere with the health and safety of the other persons who are present at theworkplace. 3ll work practices must comply with *S+ regulations.

    CONTRACTORS RESPONSIBILITIESThe contractor has an obligation to take reasonable care for the health and safety of the otherpersons in the place of work and to cooperate with their employer in the interests of health, safetyand welfare. +mployees will use appropriate protective e(uipment for the work being performed

    Shapoorji Pallonji 4 )o. 5td.SP )enter, 6166 Minoo 7esai Marg, )olaba, Mumbai 8 9