method statement kota kasablanka 3
TRANSCRIPT
CONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATIONCONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATION
22 EXISTING CONDITIONEXISTING CONDITION
33 CONSTRUCTION EXECUTION PLANCONSTRUCTION EXECUTION PLAN
44 SAFETY PROTECTIONSAFETY PROTECTION
55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN
PROJECT LOCATIONCONSTRUCTION EXECUTION PLAN
Legend :1. Puri Casablanca2. Park Lane Hotel3. Wisma Staco
Jl. Dr. SaharjoKOTA
KASABLANKA 3
651
3
42
3. Wisma Staco4. Kota Kasablanka 1 & 25. Apartment Casablanca6. Casablanca Mansion
Jl. KH. Abdullah Syafei
Jl. Casablanca Raya
Jl. Prof. Dr. Soepomo
32
MEGA KUNINGAN
DETAIL PROJECT LOCATIONCONSTRUCTION EXECUTION PLAN
42B
C
PROJECT NAME:KOTA KASABLANKA 3
CLIENT : PT ELITE PRIMA HUTAMA
PROJECT LOCATION:
PROJECT LOCATION
13
2
A
BC
PROJECT LOCATION:JL. KASABLANKA KAV. 88 MENTENG DALAM, TEBET, JAKARTA SELATAN
STORIES :5 BASEMENT2 PODIUM3 TOWER ( 2 TOWER APARTMENT, 42 FLOORS
1 TOWER OFFICE, 41 FLOORS)
SITE AREA : ± 27.011 m²GROSS FLOOR AREA : ± 336,596 m²
Legend : A. TOWER 1 (APARTMENT)B. TOWER 3 (APARTMENT)B. TOWER 3 (APARTMENT)C. TOWER 2 (OFFICE)
1. SITE OFFICE MAINCONT & SUBCONT2. STOCK YARD3. BATCHING PLAN4. LABOUR BARRACK
EXISTING CONDITIONCONSTRUCTION EXECUTION PLAN
27 MARCH 2015
AB C
D D
A B C
D
A B C
EXISTING CONDITIONCONSTRUCTION EXECUTION PLAN
27 MARCH 2015
A DDA
A B
B
C
D
C
D
A B C
EXISTING CONDITIONCONSTRUCTION EXECUTION PLAN
27 MARCH 2015
AB
C
D
D
A B C
D
A B C
EXISTING CONDITIONCONSTRUCTION EXECUTION PLAN
27 MARCH 2015
A
B
D
DA
A B
C
C
D
A B C
03 CONSTRUCTION EXECUTION PLAN
I Site Organization ChartII Site PlanIII Heavy Equipment PlanIII Heavy Equipment Plan
Construction Method1. Milestone Schedule
2. Zoning Plan
3. Structural Work Method
4. QA / QC Plan
SITE ORGANIZATION
I
Project Manager
LOTTE
Administration Mgr
LOTTE LOTTE
MEP Senior ManagerKOR
Construct. CoordinatorLOTTE
Engineering Manager
Senior. Const. Manager1
Chief SupervisorKOR
Quantity Surveyor Scheduler Drafer
Cost Controller
1
5
2
BBS
Typist / Secretary
Supervisor (Con'c)
4 4
Tower 3 Manager
1
Tower 1 Manager Tower 2 Manager
Typist / Secretary
Chief Drafter
8
Senior OS
1 1 1
5 1 4 2
Basement Manager
1
Supervisor (Rebar)
2
Safety Officer QA/QC Manager
1 1
Supervisor
2 2 1 1
Supervisor (Con'c) Supervisor (Con'c) Supervisor (Con'c)
Typist / Secretary
1
Material Asist.Supervisor (Form)Supervisor (Form)
2
Supervisor (Form)
2
Supervisor (Form)
1
22
1
Mech Supervisor Elect Supervisor General Affairs
1
2 2 1
Mech Engineer Elect Engineer Accountant
Typist / Secretary
Elect Manager Security Manager
1 LOTTE KOR 1 1 1
QS Manager Contract Manager Design Manager Mech Manager
2
Supervisor
Supervisor (Rebar) Supervisor (Rebar) Supervisor (Rebar)
1 1 1
2
Surveyor
4
1 1 11
Arch. Chief Supervisor
Arch. Chief Supervisor
Arch. Chief Supervisor
Arch. Chief Supervisor
Supervisor (Arch.)
12
Typist / Secretary1
4 4
Supervisor (Arch.)
3
Supervisor (Arch.) Supervisor (Arch.)
sub-total 5 3 112 120
Total 8 112 120
품질 QA/QC 7 7
안전 Safety 9 9
기전 MEP 1 15 16
관리 ADM. 1 5 6
공무 ENG. 2 1 17 20
공사 CON. 1 1 59 61
DescriptionKorean Local
합계LOTTE JO Totalindo & JO
소장 PM 1 1
SITE PLANCONSTRUCTION EXECUTION PLAN
Access road
REBAR FABRICATIONAND
REBAR STOCK PROTECTION ROAD WAY
Conc’ pump
SUBCONT SITE OFFICE(300m2
EXISTINGBUILDING
BATCHINGPLANT
CONTRACTOR SITE OFFICE
STOCKAREA
CANTEEN600 m2
LABOUR CAMP 11500 m2
BT.SLAB B5Elv.-3.3m
BOTTOM RAFTElv.-5.9
Elv.-5.9
Elv.-5.9
REBAR FABRICATIONAND
REBAR STOCK
Elv.-3.3
Elv.-3.3
Conc’ pump
Conc’ pump
Conc’ pump
Existing
(300m2)
BUILDINGSITE OFFICE
TEMPORARY FENCE
BASEMENT LINE
TEMPORARY ACCESS ROAD
LABOUR CAMP
CONTRACTOR SITE OFFICE
STOCK AREA
CONCRETE BATCHING PLANT
CANTEEN
SITE PLANCONSTRUCTION EXECUTION PLAN
Access roadF/W FABRICATION
REBAR FABRICATIONPROTECTION ROAD WAY
Conc’ pump
SUBCONT SITE OFFICE(300m2EXISTING
BATCHINGPLANT
CONTRACTOR SITE OFFICE
STOCKAREA
CANTEEN600 m2
LABOUR CAMP 11500 m2
GF
GF
TYP. FLOOR
TYP. FLOOR
TYP. FLOOR
B4
B4
GF
Conc’ pump
Conc’ pump
Existing
(300m2)
EXISTINGBUILDING
SITE OFFICE
TEMPORARY FENCE
BASEMENT LINE
TEMPORARY ACCESS ROAD
LABOUR CAMP
CONTRACTOR SITE OFFICE
STOCK AREA
CONCRETE BATCHING PLANT
CANTEEN
REBAR FABRICATION
REBARFABRICATION
ANDREBAR STOCK
CONSTRUCTION EXECUTION PLAN
III
TC #3R =50M
TC #5R =50M
Expected Max. Lifting Weight
DESCRIPTION Lifting Item Weight
FORM-WORKWall 2.0 Ton
Column 1.5 Ton
TC #1R =45M
TC #2R =50M
TC #4R =50M
R =50M
TC #6R =50M
TOWER CRANE SPECIFICATION
TC NAME T/C #1 T/C #2~6
TYPE HAMMER HEAD, STATIC HAMMER HEAD, STATIC
(TIP LOAD) 45M – 3.5 Ton 50M – 3.15 Ton
PERIODE 25 MONTH 26 MONTH
Column 1.5 Ton
REBARBundle Rebar 2.0 Ton
Prefab Rebar 2.5 Ton
FACAD
Panel 1 1.8 Ton
Panel 2 1.5 Ton
PC Panel 2 Ton
CONC’ CPB 5.0 Ton
ELECTRICAL & MACHINERY
Elec. Panel 2.0 Ton
ELEV 2.5 Ton
CONSTRUCTION EXECUTION PLAN
III
30m
30m
30m
30m
160m
200m
30m
30m
30m
IIICONSTRUCTION EXECUTION PLAN
MH#3
MH#4 MH#5
MH#6TOWER 3
TC3
TC5
MH#1
Note :MH = Material Hoist
TOWER 1
MH#2
MH#3MH#7
TOWER 2
TC1
TC2 TC4
TC6
MH#1
Description Specification Remark
Equipment Type Twin Medium Type
Equipment Name ALIMAK SC 65/32
Cage Size 1.5W*3.2L*2.5H
Load Capacity 2 TON
Speed 60 M/MIN
IIICONSTRUCTION EXECUTION PLAN
8M
CPB#3
CPB maximum distance from unapplied area: Approximately 8M
CPB#2
CPB#3
CPB#4
Concrete Placing Boom Specification
CPB Name CPB #1~4
Type Potential HG 28 H
Radius ± 28 Meter
High ± 22.9 Meter
CPB#1
Note :CPB = Concrete Placing Boom
CONSTRUCTION METHOD
1
CONSTRUCTION METHOD
2
Footprint tower is the priority area
Basement Line
Note:
ZONNING SUBSTRUCTUREZONNING SUBSTRUCTURE
Zone 18,115m2
Zone 35,742m2
Tower 1
Tower 3
Tower 2Zone 2
3,758m2
Footprint tower is the priority area
Note: ♦ Zoning area of sub-structure
work is divided into 3 zones:
Zone 1 : Area Tower 1, 8115 m²Zone 2 : Area Tower 3, 3758 m²Zone 3 : Area Tower 2, 5742 m²
Footprint tower is the priority area
the priority area
2CONSTRUCTION METHOD
Note: ♦ Zoning area of super-
structure work is divided into several zones
Area Tower 1 : 2100 m²Zone 1, 325 m²Zone 1, 325 m²Zone 2, 256 m²Zone 3, 469 m²Zone 1’, 325 m²Zone 2’, 256 m²Zone 3’, 469 m²
Area Tower 2 : 2294 m²Zone 1, 453 m²Zone 2, 465 m²Zone 3, 448 m²Zone 4, 421 m²
3’3’ 2’2’ 1’1’
11 22 443311 22
44 33
55
ZONNING SUPER STRUCTUREZONNING SUPER STRUCTURE
TOWER 3TOWER 3TOWER 3TOWER 3
TOWER 2TOWER 2TOWER 2TOWER 2
Zone 4, 421 m²Zone 5, 505 m²
Area Tower 3 : 1337 m²Zone 1, 322 m²Zone 2, 353 m²Zone 3, 340 m²Zone 4, 322 m²
33 22 11
TOWER 1TOWER 1TOWER 1TOWER 1
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- Detail Excavation for raft, cutting bore pile, Conc’ Foundation TC1
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
Conc’ Foundation TC1
TOWER 3 - Bulk Excavation (by Owner)
TOWER 2 - Bulk Excavation (by Owner)TC1
Tower 1 Tower 3 Tower 2
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- Excavation for raft, cutting bore pile, Install TC1 & TC2, Conc’ Lift Pit, Install rebar for raft foundation
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
rebar for raft foundation
TOWER 3 - Bulk Excavation (by Owner)
TOWER 2 - Bulk Excavation (by Owner)TC1
TC2
LIFT PIT
LIFT PIT
Tower 1 Tower 3 Tower 2
LIFT PIT
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- Excavation for raft foundation completed, Install rebar for raft foundation continued
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
foundation continued
TOWER 3 - Excavation (by Owner)
TOWER 2 - BExcavation (by Owner)TC1
TC2
TC1
Tower 1 Tower 3 Tower 2
RAFT FOUNDATION
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- Raft Foundation completed, B5 columns in progress, GWT in progress
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
Podium Outer Tower 1
- Excavation and cutting bored pile,B5 slab in progress
Podium Tower 1 –2
- Excavation and cutting bored pile,B5 slab in progress
TOWER 3 - Start Excavation for raft foundation
TOWER 2 - Bulk Excavation (by Owner)
TC1
TC2
B5
Tower 1 Tower 3 Tower 2
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- B4 slab in progress, GWT in B5 completed, B4 column in progressB5
TC3
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
Podium Outer Tower 1
- B5 slab completed
Podium Tower 1 –2
- B5 slab completed
TOWER 3
- Excavation for raft and cutting bored pile, install TC 3 & TC 4,Install rebar for lift pit and raft foundation
TOWER 2 - Bulk Excavation (by Owner)
B5 TC1
TC2
B5B4
TC4
Tower 1 Tower 3 Tower 2
B4 RAFT FOUNDATION
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- B4 slab completed, B3 slab & column in progress,B5
TC3
TC5
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
TOWER 3- Lift pit completed,Install rebar for raft foundation
TOWER 2- Excavation for raft & cutting boredpile, install TC 5 and TC 6B5 TC1
TC2
B5B3
TC4
B4 TC6
Tower 1 Tower 3 Tower 2
RAFT FOUNDATION
B3
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- B3 slab completed, B2 slab & column in progress,B5
TC3
B5 STP TC5
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
TOWER 3- Raft foundation completed,STP in progress, B5 column in progress,
Podium Outer Tower 3
- Excavation for pile cap & cutting boredpile, B5 Slab in progress
TOWER 2- Conc’ lift pit, install rebar for raft foundation in progress.
B5 TC1
TC2
B5B2
TC4
B3 TC6
B2
B5
Tower 1 Tower 3 Tower 2
B2RAFT
FOUNDATION
B5B5
3CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1- B1 slab completed, GF slab in progress,B5
TC5B5
B4
TC3 B5
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
Podium Outer Tower 1
- B4 and B3 slab in progress
TOWER 3 - B4 slab completed,
Podium Outer Tower 3
- B5 slab completed
TOWER 2 - Raft foundation completed
B4 TC1
TC2
B3B2
B1 TC6
GF
B5
B4
RAFT FOUNDATION
TC4B5
Tower 1 Tower 3 Tower 2
GF
B4
B1
B4B5
RAFT FOUNDATION
3CONSTRUCTION METHOD
Access road
B5
TC3 B5
B5
B4L2 GF
TC5
B4B5
ZONE ACTIVITIES
TOWER 1- Level 9 slab completed, Level 10 & 11 slab in progress,
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
GF TC1
GF
GF
TC2B5
L11
L9
L10
L2
B4
GF
TC6
B4
TC4
B3
B5 B5
B5
Podium Outer Tower 1
- GF slab completed
Podium Tower 1 -3
- B4 slab in progress,
TOWER 3- GF slab completed, Level 2 slab in progress
Podium Outer Tower 3
- B4 slab in progress
TOWER 2- B4 slab completed, B3 slab in progress
Podium
Tower 1Tower 3 Tower 2
GFLevel 2
Podium Outer Tower 3
- B5 slab complete
B3
Level 11
Level 10
B5 B5
3CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1- Roof slab completed, Lift Motor Room Completed,
TC3
TC2L2
TC5
TC4
GF GFGFL26
Access road
L25
L39
L38L37
TOWER 3- Level 37 slab completed, Level 38 & 39 slab in progress
TOWER 2- Level 25 slab completed, Level 26 & 27 slab in progress
Podium All - GF slab complete
Tower 1Tower 3 Tower 2
ROOF
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
GF TC1
GF
TC6
TC4
L27
LMRLMR
Level 39Level 38
ROOF
ROOF
GF
Level 37
Level 38
Level 27Level 26
GF GF
3CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1 - Finishing work in progress
TC3
TC2L2
TC5GF
GFL37
Access road
L36ROOF
TC4
L2
L2
TOWER 3- Roof slab completed, Lift Motor Room Completed
TOWER 2- Level 36 slab completed, Level 37& 38 slab in progress
Podium - L2 slab completed
Tower 1 Tower 3 Tower 2
ROOF
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
GF
GF
TC6L38
LMRLMRLevel 38Level 37
ROOF
ROOF
TC1
TC4L2
L2
ROOFLMRLMR
L2 L2GF
FINISHING WORK
3CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1 - Finishing work in progress
TC3
L2
TC6
TC5GF
GF
Access road
ROOF
ROOF
TC4
L3
L3 ROOF
TOWER 3 - Finishing work in progress
TOWER 2- Roof slab completed, Lift Motor Room Completed
Podium - L3 slab completed
Tower 1 Tower 3
ROOFLMRLMR
ROOF
ROOFLMRLMR
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
GF
GF
TC6
ROOF
ROOF
L3
LMR LMR
Tower 2
L3 L3
GF
FINISHING WORK
FINISHING WORK
CONSTRUCTION METHOD
3
Thermocoupleposisition
Thermocouple Plan
Existing
SUBCONT SITE OFFICE(300m2)
EXISTINGBUILDING
Bottom Slab B5Elv.-3.3m
Detail of thermocouple installation
Note: • Concrete volume±7500m³• Supportive equipments :
• Conc. Pump : 7unit (1 stand-by)• Vibrator : 25 unit (5 stand-by)• Tent for protecting area that should be poured concrete• Thermocouple for thermal monitoring
• After all preparation completed, pouring concrete use concrete pump ± 25m³/hr capacity.Casting raft foundation can be completed within ± 60 hours
Thermal monitoring
3
Excavation for raft foundation Cuti bored pile Spray anti termite (optional if necessary)
CONSTRUCTION METHOD
Lean concreteFormworkRebar work
Bottom layer Support rebar
Upper layerStarter rebar
3
ME installation Thermocouple installation Starter bar inspection
CONSTRUCTION METHOD
Cold-joint installationProtective Tent installation
3
Concrete finishingConcrete acceptance scheme
Casting Process
CONSTRUCTION METHOD
Concrete truck access
Area for concrete truck
Concrete curing
Always provide 1 unit Concrete pump stand-by
Concrete sample
Styrofoam installation
3CONSTRUCTION METHOD
1 2 3
4 5
3CONSTRUCTION METHOD
6 87
9 10
3CONSTRUCTION METHOD
ZONE 1’9 TABLES
ZONE 19 TABLES
Slab conc’: Zone 1 = ± 110.5 m³Zone 2 = ± 84.5 m³Zone 3 = ± 155 m³
ZONE 2’7 TABLES
ZONE 27 TABLES
Zone 3 = ± 155 m³Zone 1’ = ± 110.5 m³Zone 2’= ± 84.5 m³Zone 3’= ± 155 m³
ZONE 3’12 TABLES
ZONE 312 TABLES
CONVENSIONAL CONVENSIONAL
3CONSTRUCTION METHOD
Typical Elevation Table Tower 1
Typical Section Table Tower 1
3CONSTRUCTION METHOD
ZONE 19 TABLES
ZONE 27 TABLES
ZONE 49 TABLES
ZONE 37 TABLES
Slab conc’: Zone 1 = ± 106 m³Zone 2 = ± 117 m³Zone 3 = ± 112 m³Zone 4 = ± 106 m³
3CONSTRUCTION METHOD
Typical Elevation Table Tower 3
Typical Section Table Tower 3
3CONSTRUCTION METHOD
Slab conc’: Zone 1 = ± 150 m³Zone 2 = ± 153.5 m³Zone 3 = ± 147.8 m³Zone 4 = ± 138.93 m³Zone 4 = ± 138.93 m³
ZONE 27 TABLES
ZONE 17 TABLES
CONVENSIONAL
ZONE 37 TABLES
ZONE 48 TABLES
3CONSTRUCTION METHOD
Typical Elevation Table Tower 2
Typical Section Table Tower 2
3CONSTRUCTION METHOD
1st Set 2nd Set 3rd Set 1st Set
3
Note:Concrete mold for column and shearwall are usingAluma Beam, Steel waler and plywood 18mm double film
CONSTRUCTION METHOD
Typical Shear wallShear wall type
SW40A & SW35A
03
Note:
CONSTRUCTION METHOD
Note:This the illustrations when the TableForm Flying next to the upper floors,very easy and fast
03CONSTRUCTION METHOD
Note:Aluma Table Form is often calledAluma Table Form is often calledFlying Table because when the tablestripped out to next floor is lifted bytower crane, making it very fastfor the cycle time floor to the next floor
QA / QC PLAN
4
Shop Drawing &Shop Drawing &Material Submission Material Submission
Method of Construction (Trade)Method of Construction (Trade)
Method Briefing & Method Briefing & Training to WorkersTraining to WorkersMethod Briefing & Method Briefing & Training to WorkersTraining to Workers
Trade Demonstration Trade Demonstration (Mock Up)(Mock Up)
Trade Demonstration Trade Demonstration (Mock Up)(Mock Up) DefineDefine Holding PointHolding Point
Inspection & Test PlanInspection & Test Plan
Step by Step InspectionStep by Step Inspection
Execution of WorkExecution of Work
Quality WorkQuality Work
SetSet--upup Quality StandardQuality Standard
Consultant + Main-con + Subcon
04 SAFETY PROTECTION
01 Building Protection
Building Protection
01SAFETY DECK
SAFETY DECK
SAFETY DECK
SAFETY VOID
SAFETY DECKPERMANENT
Building Protection
01
SAFETY NET
SAFETY NET
SAFETY NET
Building Protection
01
Safety Rail
Building Protection
01
COUPLER
TIANG RAILINGHANDRAIL
INSTALLATION
MID HANDRAIL
BESI BEHEL D12
BASEPLATE
POLYNET
TIANG RAILING
POLYNET
safety wing net/Safety deck
safety wing net/Safety deck
CORNER
BESI BEHEL D12
Perimeter Safety Net / Safety Railing
Building Protection
01
Building Protection
01
HANDRAIL
MID HANDRAIL
OPENING 100 ~ 600 mm
OPENING > 2 M / VOID AREA
KAWAT AYAM + SAFETY NET
BESI BEHEL D12
OPENING 650~ 2000 mm
Building Protection
01
SAFETY NET DI LIFT SAFETY VOID
05 HSE MANAGEMENT PLAN
01 Certificate
02 Safety Plan
EHS MANAGEMENT PLAN
01
EHS MANAGEMENT PLAN
02
EHS MANAGEMENT PLAN
02
EHS MANAGEMENT PLAN
02
Thank youThank you