method statement
TRANSCRIPT
METHOD STATEMENT1.INTRODUCTIONThis Method Statement describes the specific safe working methods which will be
used by ------------------ to carry out the construction new storage facilities.2.SCOPEThis document covers the scope of work required for the
execution of the tank construction. The method statement is in the following sequence as the work will becarried out.
Tank specific design and drawings
Construction of new tank foundation
Plate, structural steel and tank component procurement
Floor, shell and roof plate fabrication
Installation of new floor plate and double deck roof
Fire protection system
Instrumentation and electrical works
Demolition of tank foundation, floor and roof
Tank decommissioning
Tank isolation
Tank cleaning
Tank conditional inspection survey
Blasting and painting works
Hydro-testing
Calibration
Hook up to existing process
line, commissioning and demobilisation
3.REFERENCES
API 650: Welded steel storage tanks for Oil Storage
API MPMS 3.1B: Manual of Petroleum Measurement Standards Chapter 3 – Tank Gauging (Section 1B: Standard Practice for
Level measurement of LiquidHydrocarbons in Stationery Tanks by Automatic Tank Gauging)Method Statement1 of 17
Recommended Practice 14FZ: Recommended practice for Design and Installation of Electrical Systems for Fixed and Floating
Offshore Petroleum Facilities for Unclassified and Class1, Zone 0, Zone 1 and Zone 2 Locations
NFPA 30: Flammable and Combustible
Liquid Code-2000 Edition
BS 8110: Structural use of Concrete in Building4.LIST OF EQUIPMENT
30 ton mobile crane
Flat deck/low bed trailer
Semi automatic welding machine
DC welding machines (400A)
Air compressor
Sand blasting set
Spray painting set
Wheel loader
Tipper truck
Mini dumper truck
Fuel tanker
Power generating set (30kVA,
50kVA, 60kVA, 100kVA)
NDT Equipment
Man Lifting Equipment (25m Boom height)
Dewatering pumps
Pneumatic power winch
Pneumatic air winch5.SITE PERSONNELC o n s t r u c t i on M a n a g e r1 S i t e
E n g i n e er 2 H S E O f f i c e r1 Q A / Q C O f f i c e r1 Q A E n g i n ee r 2 Q C I n s p e c to r 2 S i t e
S u p e r v i so r 1 P i p e / P la t e W e l d e r s 6Method Statement2 of 17
G r i t B l a s t e rs 4 O p e ra t o r s8
6.WORK SEQUENCE AND METHOD6.1.Tank Specific Design And DrawingsThe following elements design shall be considered for adequacy in
accordance with therelevant codes and standards as may be applicable and any findings communicated to theCOMPANY for review and approval before
changes will be effected.
The tank foundation shall be verified in accordance with appendix B of API650:2005 and BS 8110
The floor and annular plates shall be verified in accordance with the requirements of clauses 4.4 and 4.5 of API 650:2005
The shell plates shall be verified in accordance with the requirements of clauses 4.6of API 650:2005
Roof and other roof accessories shall be verified
to meet the requirement of Clause4.10 of API 650:2005
Nozzles shall be verified to meet the requirement of clauses 4.7.6 for shell and
4.8.5for roof of API 650:2005
The piping system shall be verified to meet the requirement of ASME B31.36.2.Plates, Structural Steel And Diesel
Storage Tank Components Procurement
Steel plate and sections procured shall be accompanied with their mill certificates
Samples shall be taken from the procured materials to confirm that the chemical andmechanical materials conform with the requirement of
clause 4 of API 650: 20056.3.Cutting, Forming and FabricationPlate material shall be straight and/or flattened by pressing or rolling audtties
shall bedone before the material is processed in any way.
MarkingTo enable the various
fabricated components to be assembled together correctly on site, each part shall be marked with unique numbering system asshowed
on the “Approved for Construction” drawings.Method Statement3 of 17