metered demand and distributed energy resources customer … · 2019-09-30 · make sure you attach...
TRANSCRIPT
MAKE SURE YOU ATTACH THE SURVEY FORM
Subject: - Ask the Expert Surgery Feedback
Metered Demand andDistributed Energy Resources
Customer Forum26th September 2019
Antony White & Steve Halsey
2016. UK Power Networks. All rights reserved
Housekeeping
Please take time to give feedback (SLIDO)
Toilets Fire exitsPlease put phones on
silent
2
2016. UK Power Networks. All rights reserved
Who is here today?
Guest Speakers
Lewis Hubbard Greater London Authority
Tom O’Connor Greater London Authority
Mark Adolphus Director of Connections
Neil Madgwick Head of Service Delivery
Steve Bradley Head of Major Connections
Richard Pepper Head of Connections Projects (London)
Andy Braund Head of Connections Projects (Eastern)
James Cooper Connections Manager Projects (South East)
Steve Foster Major Connections Manager
Steve May Senior Programme Manager
Steve Carlow Major Connections Manager
Jim Vasey Major Connections Manager
Mark Edwards Technical Services Manager
Neil Clarke Head of Highway Services & Disconnections
Holly Woolliscroft Communications Engagement & Event Lead
Judith Edgerton Customer Relationship Manager
Michael Howe Customer Relationship Manager
Francis Harris Customer Relationship Manager
Nigel Turner DER Business Analyst
Catherine Granick Project Manager
Adriana Laguna Senior Innovation Strategy Manager
Matt White Lead Power System Development Engineer
Harriet Walsh Power System Development Engineer
Rona Mitchell Innovation Engineer
Noel Jemma Property & Consents Connections Manager
3
2016. UK Power Networks. All rights reserved27/09/2019 4427/09/2019 4
Mark AdolphusDirector of Connections
4
2016. UK Power Networks. All rights reserved
Agenda 09:30 Housekeeping, Slido ‘test’ question – Antony White
09:40 Welcome & Intro - Mark Adolphus
09:50 Service Development Plan (ICE) - Initiatives completed and underway – Antony White & Steve Halsey
10:20 DNO to DSO (Update) & Active Network Management – Matt White
10:55 After coffee breakout sessions explained
11:00 – 11:15 Coffee and comfort break followed by breakout sessions
11:15
DER focus - SWRR (system wide resource register) | Outage planning tool | ALoMCP(accelerated loss of mains change programme) + 10 minute breakout for ideas for ICE 2020/21
Metered Demand focus – Legal, process overview | Heat, Planning for the future | GLA, Utilities / Developers Process | UK Power Networks Connections in the Competitive Marketplace + 10 minute breakout for ideas for ICE 2020/21
12:15 – 13:15 Lunch and networking
13:15 EVs – Current developments / standards – Neil Madgwick
14:00 Questions for Mark & the SMT, Event Feedback (Slido) & Close
5
2016. UK Power Networks. All rights reserved
Antony WhiteStakeholder Engagement & Account Manager
Service Development Plan 2018 / 19
6
2016. UK Power Networks. All rights reserved
Looking Back / Looking forward report 2018/19• The Looking Back/Forward report was submitted to Ofgem at the end of May
and is available on our website to view here• In it, we detail how we developed and delivered our plans for 2018/19
(‘Looking Back’) and how we developed our plan for 2019/20 (‘Looking Forward’).
7
2016. UK Power Networks. All rights reserved
Ofgem Consultation 2018/19• Ofgem issued a consultation seeking stakeholder feedback in late June
• At the end of July - Ofgem shared non-confidential responses with network companies
• In August, DNOs submitted their responses to Ofgem
• Ofgem now have to decide if we have involved you enough in our planning and delivered on our commitments and then decide if a financial penalty will be applied to DNOs
• We received 10 responses to the consultation - 1 Nil score, 1 not satisfied, 2 satisfied, 6 very satisfied. – See next slide
8
2016. UK Power Networks. All rights reserved
Ofgem Consultation responses - 2018/19
9
2016. UK Power Networks. All rights reserved
Antony WhiteStakeholder Engagement & Account Manager Steve HalseyDER Development Manager
Service Development Plan 2019 / 20
10
2016. UK Power Networks. All rights reserved
Service Development Workplan 2019/20• Through 6 months of collaboration with stakeholders, we published our 2019/20
Service Development Workplan at the end of April. The plan can be viewed here
11
2016. UK Power Networks. All rights reserved
Service Development Workplan 2019/20 – Quarter 1– Quarter 1 Update April – June 2019 was published at the end of July and can
be viewed here
– See the following slides which give more details
12
2016. UK Power Networks. All rights reserved13
2019/20 Initiatives Apr-Jun Jul - Aug Sept - Dec Jan - Mar
2019 2020
09.19 - Deliver Targeted EV Workshops
11.19 - Develop and publish an LV heat map for EV’s10.19 - Introduce an ‘Ask the expert’ service for EV customers
13.19 - Hold subject specific workshops14.19 - Review the process for extending quote validity15.19 - Develop and monitor a set of KPI’s for the quotation and delivery of
diversionary works
17.19 - Develop a guide of how to enhance security of supply18.19 - Develop a process for the refund/reuse of plant used for Temporary Builders
Supplies 19.19 - Provide a ‘Quote by’ date to the applicant [customer] when a project is
allocated to a designer (and minimum information has been received)
31.19 - Review our acceptance and milestone payment process
IN PROGRESS
IN PROGRESS
IN PROGRESS
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
IN PROGRESS
IN PROGRESS
IN PROGRESS
16.19 - Develop a guide on the process for undertaking EHV cable diversions
IN PROGRESS
2016. UK Power Networks. All rights reserved
Develop and publish an LV heat map for Ev’s – June 2019
To find further information on the visibility of available electricity network capacity for the connection of Electric Vehicle charge points, please click on the following link, which will open the LV electric vehicle heat map Here
11.19Introduce an ‘Ask the expert’ service for EV customers – April 2019
Did you know that UK Power Networks offer an EV Ask the Expert Service for all pre-application enquiries. If you would like to ask us a question;
Email us,Book a face-to-face meeting,
10.19Metered Demand - Initiatives Complete
Complete
14
2016. UK Power Networks. All rights reserved15
Metered Demand - Initiatives Complete 17.19Develop a guide of how to enhance security of supply – July 2019
9.19
Deliver targeted EV workshops -From September 2019
• 5 July – Delivered jointly with SSE
• 23 July – Delivered to Local Authorities
• Further workshops TBC
Complete
2016. UK Power Networks. All rights reserved
16.19Develop a guide on the process for undertaking EHV cable diversions- July 2019
Metered Demand - Initiatives Complete
Complete
16
2016. UK Power Networks. All rights reserved
Metered Demand - Initiatives Underway
Complete
Complete
Review the process for extending quote validity – September 2019
So far:
Following discussions with stakeholders, and internally with the Connections Design teams within UK Power Networks a process has been drafted
Next Steps:
• Finalise & publishoutcome
14.19 18.19Develop a process for the refund/reuse of plant used for temporary builders supplies – December 2019
So far we have: Identified circumstances wherethe refund/reuse of plant used for temporary builders supplies may be applicable (incl review of feedbackreceived in 2018)
Next Steps: Discuss potential solutions with UKPower Networks’ representatives(Operations, Supply Chain, Standards,Connections & Regulation)Draft proposal/ process
17
2016. UK Power Networks. All rights reserved
DER Initiatives 2019/201.19 Introduce SLAs for response to enquiries from flexibility service providers Sep-19 Green
2.19 Assess feasibility of introducing a curtailment index to reduce curtailment uncertainty for new flexible customers Dec-19 Green
3.19 Promote flexibility revenues opportunities to existing customers within flexibility zones Mar-20 Green
4.19 Develop and co-design with customers an innovative market-based approach to managing generation constraints on the network Mar-20 Green
5.19Deliver DSO KPIs that measure and track customer satisfaction, system performance, and reliability of flexible customers and providers and benefits of flexible connections
Sep-19 Green
6.19 Develop a combined connection and flexibility offer Sep-19 Green
7.19 Undertake a feasibility study to develop a system wide resource register as part of the Open Networks programme Ongoing project Green
8.19 Deliver DER outage planning tool Mar-20 Green
12.19 Run workshop with customers and agree a programme of work to make enhancecements to the DG Mapping tool Feb-20 Green
28.19 Develop Factsheets to support new customers looking to use the UKPN heat maps, DG Mapping Tool and Piclo Flex platform From Sep 19 Green
29.19 Introduce "optioneering" product Feb-20 Green
30.19 Review surgery trial (Initiative 33.18 in the 2018/19 Workplan) and implement a new process as BAU Jul-19 Complete
32.19 Deliver revised process for customer adding to/altering an existing connection Jul-19 Complete
18
2016. UK Power Networks. All rights reserved
Introduce SLAs for response to enquiries from flexibility service providers– September 2019
1.19Deliver DSO KPIs that measure and track customer satisfaction, system performance, and reliability of flexible customers and providers and benefits of flexible connections – September 2019
5.19
Service Response TimeGeneral enquiry 3-5 working days for basic
enquiries
Enquiry on an ongoingFlexibility Tender
3-5 working days for basicenquiries
Incident relating to theRegistration,Prequalification,Competition of an ongoingFlexibility Tender
2-3 working days
Enquiry on a futureFlexibility Tender
1-2 weeks
Advanced/Technicalenquiry
2-3 weeks
19
2016. UK Power Networks. All rights reserved
Run workshop with customers and agree a programme of work to make enhancements to the DG Mapping tool– February 2020
• Workshop held with customers to gather improvements / ideas
• 21 Improvement actions identified• Some functional, some new• Currently working with UKPN IS
and developer to scope• Phased delivery likely between
now and end of March 2020
12.19Develop Factsheets to support new customers looking to use the UKPN heat maps, DG Mapping Tool and Piclo Flex platform – From September 2019
28.19
20
2016. UK Power Networks. All rights reserved
Review surgery trial (Initiative 33.18 in the 2018/19 Workplan) and implement a new process as BAU - July 2019
Following customer feedback we trialled the booking of ad-hoc surgeries (rather than fixed day/week). Trial ran for 3 months and we have now implemented as BaU
• Surgery booking with 7 working days of initial contact
• Submit plans/details in advance• Trialling written response
30.19Deliver revised process for customer adding to/altering an existing connection –July 2019
32.19
G99 SAF
21
2016. UK Power Networks. All rights reserved2227/09/2019 22
A Smarter Energy Future“DNO to DSO”
22
2016. UK Power Networks. All rights reserved
May 2019 - 1 week without coal generation
The UK Energy mix is changing and the impacts are being felt now
Carbon emissions in electricity down
50% on 2012
The Capacity of Renewable Energy (41.9GW) overtakes that of fossil fuels (41.2GW) for the first time
Twilight for coal: Rugeley power station in Staffordshire, which is now being demolished. Photograph: Northern Nights Photography / Alamy Stock Photo
Britain has gone a week without using coal to generate electricity for the first time since Queen Victoria was on the throne, in a landmark moment in the transition away from the heavily polluting fuel
The Guardian 8 May 2019
UK sets new wind power record as turbines deliver 14 gigawatts for first time – 37 per cent of nation's electricity
23
2016. UK Power Networks. All rights reserved
What is driving the change?
Transition to a low carbon economy
• Mandated carbon budgets
• Air quality regulations• Vehicle emission
standards
Technology revolution
• Rapid cost reduction in renewable tech
• Digitisation • Connected homes• Electric Vehicles• Block chain technology• Machine learning
• Population growth/urbanisation
• ‘Local is best’ • Affordability• Increasing expectations -
choice, transparency, value
Societal changesChanging regulatory environment
• Outputs focused• Promoting innovation and
competition • Reducing Energy costs
24
2016. UK Power Networks. All rights reserved
Centralised- few large GeneratorsPredominantly fossil fuel based
One way power flowsPredictable - Planned
Customers consume onlyFlexibility from large generators
Decentralised (Thousands of distributed generators)Hybrid – Vast volumes of renewables
Bi-directional power and information flowsIntermittent – Actively Managed
Customers self-produce, consume and tradeFlexibility from Demand, Storage and generation
The evolving energy landscape“Traditional” “Emerging”
25
2016. UK Power Networks. All rights reserved
What could this look like in the next 10-15 years?
The UKPN world in 2030: Up to 4m EVs, 4GW of battery storage and 13GW of DG26
2016. UK Power Networks. All rights reserved
The future is now!
Electric Transport
Distributed Renewables
LocalStorage
Electric Transport Heat
Over 160,000distribution connected
generators
200,000EVs sold in the UK
18.5 million carbon emission-free passenger journeys
30% on our
networks
28GW enquiries
2.1GW
200MW+connected storage
accepted offers
300 non-domesticinstallations under the RHI
~6000 domestic installs under the RHI domestic
6GW+renewable DG connected
27
2016. UK Power Networks. All rights reserved
Keeping the lights
on
Providing great
customer service
Lowering our costs
Support whole
system optimisation
Enabling markets
Secure and reliable supplies taking into account two way flows and greater intermittency
Facilitating cheaper and quicker connections using proven innovation
Optimising network investment decisions using alternative flexible solutions
Collaborating with the GB SO to deliver ‘whole system’ outcomes that are best for customers
Enabling market solutions for DER to provide flexibility to local and wider system
Emergent DSO Full DSO
The changing role of distribution networks
28
2016. UK Power Networks. All rights reserved
Customers are shaping our DSO transition
Customers said
Visit: FutureSmart.ukpowernetworks.co.uk
29
2016. UK Power Networks. All rights reserved 30
Our DSO Strategy – 5 key areas 2017-2019
2016. UK Power Networks. All rights reserved
Distributed energy resources (DSR, generation, storage) that can increase generation or reduce consumption in return for payment to support the local electricity network
New network capacityInvestment trigger
WHAT: Strategy to Action: ‘Flexibility’
31
2016. UK Power Networks. All rights reserved
Our Key Flexibility Roadmap Principles
Creating new transparent, competitive markets in collaboration with the distributed energy community
32
2016. UK Power Networks. All rights reserved 33
Winter 18/19 Flexibility tender
94.76MWCapacity requirement
18.1MWFlexibility Contracts
4 met operational needs
Smaller volumes in 3 zones
28 zones tendered19 prequalified
15 bid
£450kNew revenue streams for
flexibility providers
£12mFunding pot for Flexibility
2016. UK Power Networks. All rights reserved
Flexibility – a network service
Brandon2MW
Lewes Newhaven
7MWRomney Warren
1.5MW
Leighton Buzzard5MW
34
2016. UK Power Networks. All rights reserved
Online dating…
“…Overworked substation seeking supportive battery…”
Visit: PicloFlex.com or email [email protected] 35
2016. UK Power Networks. All rights reserved
Timeline – the next few months
Completion of tender
Apr 2019
Flexibility Forum
May 2019
Flexibility contracts awarded
8 July 2019
Late July 2019
Publish new Flexibility zones
for Q1 2020
Sept2019
Oct2019
Publish Flexibility zones to be re-tendered Q4 2019
Close of registration and
bidding for flexibility tender
Nov – Dec 2019
8th OctPre-qualification
submission deadline
36
2016. UK Power Networks. All rights reserved
WHAT: Strategy to Action: ‘Rollout ANM’
“Using flexible network customers autonomously and in real-time to increase the utilisation of network assets without breaching operational limits, thereby reducing the need for reinforcement, speeding up connections and reducing costs”
ENA’s definition from ANM Good Practice Guide
Active Network Management
Software
Network Distributed Generation
Power
An intelligent centralised software platform that will support those services and products that require real-time monitoring and control of DER.
37
2016. UK Power Networks. All rights reserved
Roadmap of ANM Products
Flexible Connections
Flexible Services TSO-DSO Network
Optimisation
Cover all voltage levels Cover all three UKPN licenced regions Integrating innovative technologies
and commercial arrangements
Distributed Energy Resource Management
Constraint Management Network asset monitoring and network
optimisation Operational forecasting and offline
simulation Commercial and market capabilities
38
2016. UK Power Networks. All rights reserved
Active Network Management (ANM) – the rollout
Flexible connections offered in all 3 licenced areas using ANM
Wind(8)Solar
(13)
CHP(2)
Rollout of Active Network Management from 2020Rollout of Active Network Management
Live flexible connection DGs managed by ANM
117MW managed by ANMAcross 2 of our 6 live ANM zones23 flexible connection customers
2019
2020 Dispatching Flexibility resources to defer reinforcement using ANM
39
2016. UK Power Networks. All rights reserved
Flexible Connections across all parts of UKPN
A New Flexible DG Connections Process
xNo need to wait for specific ANM zones to open, you can apply for an FDG connection anywhere across our networks
Go live 30 September for new applications
from 1 October40
2016. UK Power Networks. All rights reserved
Check out our DG Mapping Tool and Heat Maps to see if there are active constraints in
your area
Apply for a Budget Estimate to compare (where applicable)
high-level costs of unconstrained and flexible
connection options (including estimated curtailment range)
You can use this information to decide whether you want to apply for an unconstrained or flexible connection for your
Formal Quote
If you apply for a Flexible Connection Quote, you will
receive a Curtailment Assessment report with your Flexible Connection Quote
The Process
41
2016. UK Power Networks. All rights reserved
Improved DG Mapping Tool – rollout 2019/20
New Curtailment Layer
42
2016. UK Power Networks. All rights reserved
In Summary – New Connections Process
Both unconstrained and constrained connection options will be made available across the three license areas:1. based on the technical parameters of the network;2. technologies looking to connect; and 3. the cost of connection.
What we’re improving to facilitate this
• Simple application process using existing forms (FDG feasibility is not needed)• Applicable to both budget and formals• Clarity on dates from application to energisation• Clear visibility of the criteria used by UK Power Networks in assessing constrained connections• Using DG Mapping as a first guide on curtailment or new areas of interest to FDG type
43
2016. UK Power Networks. All rights reserved
Flexible Connections - qualifiers Release 1
Thermal constraints on circuits and transformersVoltage constraintsHV and EHV Connections New Generation customers & storage customers with generation constraints
Future ReleasesExisting generation customersDemand customers & storage customers with demand constraintsLV connections
44
2016. UK Power Networks. All rights reserved27/09/2019 454527/09/2019 45
Q&A
45
2016. UK Power Networks. All rights reserved 46
2016. UK Power Networks. All rights reserved
Break Out Session• DER focus
– Room 2 – Steve Halsey » SWRR (system wide resource
register)» Outage planning tool » ALoMCP (accelerated loss of
mains change programme) » Ideas for improvements
2020/21
• Metered Demand focus – Room 1 - Antony White
» Legal, process overview » Utility Infrastructure - GLA» Heat - Planning for the future» UK Power Networks
Connections in the Competitive Marketplace
» Ideas for improvements 2020/21
47
2016. UK Power Networks. All rights reserved
DER Breakout slides• Delivered comprehensive range of initiatives since
2015 - update on some current activities• SWRR• Outage planning tool• ALoMCP
• What would you like us to focus on – initial thoughts for next years Service Delivery (ICE) plan?
48
2016. UK Power Networks. All rights reserved
System Wide Resource Register (SWRR)
• An Open Networks piece of work
• Started life in 2018 as feasibility study
• Developed further this year WS2 P1
• Interim webpage hosted on ENA website
49
2016. UK Power Networks. All rights reserved
System Wide Resource Register (SWRR)
50
2016. UK Power Networks. All rights reserved
Data structure
51
2016. UK Power Networks. All rights reserved
System Wide Resource Register (SWRR)
• Developing work done last year
• Defining data fields/descriptors
52
2016. UK Power Networks. All rights reserved
Next steps
53
2016. UK Power Networks. All rights reserved
Outage Planning Tool – Network Vision Listening to our customers
• Improving customer satisfaction is one of our key priorities and placing stakeholders at the heart of what we do has been a feature of our organisation since 2010
• This project has been created based on feedback from customer requirements
54
2016. UK Power Networks. All rights reserved
Interdependencies
Outage plan Capital
Programme
Asset Managem
ent
Projects/ Major
Connections
Interconnected DNOs Faults & defects
National Grid
Maintenance
Large Power Users
You/DERs
Maintenance Plan
Capital Plan 120 mths
Enquiries
P6 Plan
ED1 Plan96 mths
Local
National
Asset Portfolio Plan
Network Operations/Control
Customers
DAILY/WEEKLY/MONTHLY/YEARLY
WORK PIPELINE VISIBILITY
55
2016. UK Power Networks. All rights reserved
The challenge – striking a balance
RISK CONFIDENCE
96
mon
ths
ED
1 P
lan
12 M
onth
s
8 W
eek
ahea
d
3 M
onth
s
Projects/ Major
Connections
Asset Management
Capital Programme
18 M
onth
s
Network Operations/Control
Wee
k ah
ead
56
2016. UK Power Networks. All rights reserved
Outage Planning & Tracking Tool
57
2016. UK Power Networks. All rights reserved
Engaging with Customers
58
2016. UK Power Networks. All rights reserved
Developing DER User Stories
• When I need to request an outage–I would like to fill out a simple form–Allow Outage Planners to view and process request
• When an outage is planned that affects a DER site–I would like an automatic notification–Allows DER to take appropriate action
59
2016. UK Power Networks. All rights reserved
DER Requirements
60
2016. UK Power Networks. All rights reserved
Outages within the tool
61
2016. UK Power Networks. All rights reserved
Detailed Outage View
62
2016. UK Power Networks. All rights reserved
Companies will be added for web access
63
2016. UK Power Networks. All rights reserved
Manage your contact details
• Companies with individual logins will be added– Super user will be created per company with rights to alter companies
details and add/remove users– Customers will have the ability to change details in real time
removing delays in processing changes 64
2016. UK Power Networks. All rights reserved
Individual Site Information
• Sites will have companies associated to them
• Customers can chose who from their company list is associated on a person by person basis
• Sites will have address and MPAN data to ensure no misunderstanding on site being referred to
65
2016. UK Power Networks. All rights reserved
Notifications - Email
Notifications - Within the tool
66
2016. UK Power Networks. All rights reserved
Customer Reports
• What do you want to see?• Routine reports or just communication of changes?
67
2016. UK Power Networks. All rights reserved
Request Outage on your Sites
69
2016. UK Power Networks. All rights reserved
Dashboard• Is this of use?• What would be
useful to see here?– Changes– Number of
outages– Sites at Risk– Shutdowns– MW
constrained?
70
2016. UK Power Networks. All rights reserved
Progress
• Project due to trial in SPN October 2019• Moving system to UKPN IT environment (Sept/Oct 2019)
–Allows internal login classes for all users–Allows external logins and third party information to be
added–Allows customers to test interface
71
2016. UK Power Networks. All rights reserved
Feedback on Tool
• Does this have the information you want?• How do you want information presented?• How do you want the reports?
–Email–Notifications in tool–What level of detail in each?–What type of change is significant enough to instigate a
report?
72
2016. UK Power Networks. All rights reserved
Do you want to participate in Trial
• The trial and the feedback we receive will shape what is produced for you
• If you wish to get involved contact us:–DG-Q&[email protected]–[email protected]–[email protected]
73
7427/09/2019 7474
Accelerated Loss of Mains Change Programme
DER Forum Update - 23 Sept 2019
75
Accelerated Loss of Mains Change Programme
76
Accelerated Loss of Mains Change Programme
77
• Apply for payment on ENA website: http://www.ena-eng.org/gensite2/index?action=login
• Fixed Payment is according to the works required on site, as follows:
Accelerated Loss of Mains Change Programme
Payment Programme Details
• To apply you need to have identified the LoM protection settings at all devices that provide LoM protection at your site and state in application what works will be required at each device, i.e. settings change on existing device, device replacement, LoM function deactivation.
78
12WGenerators apply via online portal
Generators enters site, LoM protectiondetails and lead times - -
2W -DNO checks generator details against own records and pre-qualification criteria. Forwards to NGESO if criteria is met.
-
2W - -NGESO checks generators against prioritisation criteria, acceptsgenerators to scheme.
2W -Automatic email sent to generator from DNO to notify of acceptance and to complete works no later than specified date
-
Payment Scheme Design
6WGenerator submits evidence to DNO that work has been completed
DNO reviews evidence, carries out site sample checks (if required)If satisfied works are complete, DNO pays generator
-
New
Win
dow
Ope
ns
TBC Generator enters in portal date works will be completed and carries out the work.
DNO contacts generator to schedule and attends witnessing appointment (if required)
-
Generator actions DNO Actions NGESO Actions
Accelerated Loss of Mains Change Programme
Application
Verify
Assess
Accept
Implement
Payment
79
Delivery Assurance
Scope of Works Baseline Approach Recognised Contractor
Replace existing protection device with new device
DNO witness test required Self-certification (a % of which will be subject to post-event sample checks)
Disable LoM function in existing protection device
DNO witness test required As above
Change settings on existing protection device
Self-certification (a % of which will be subject to post-event sample checks)
As above
DNO’s and NGESO need to ensure that the correct changes have been made as part of this programme
This will be done through a combination of self-certification, on-site witnessing and post-event sample site checks
DNO’s may waive the requirement to witness test a site if the person/contractor carrying out the work is recognised as competent. Each DNO will have their own criteria regarding recognised contractors. UKPN to publish this information shortly.
No DNO charge for a successful first witness test.
Accelerated Loss of Mains Change Programme
80
Self-Certification
Generators not requiring witnessing will need to submit evidence of the changes made to the DNO before payment can be received
Generators must submit a Pro-Forma to their DNO with details of the LoM protection changes made to their site as well supporting evidence of the changes made
The accepted forms of supporting evidence are: Original site commissioning form Similar approved test document e.g. from periodic testing of G59 interface protection Time-stamped photographs of the LoM protection before and after the changes have bene
made
The Pro-Forma document will be sent with the notification that the generator has been accepted into the programme
Accelerated Loss of Mains Change Programme
81
For More Information
Dedicated UKPN mailbox for customer queries: [email protected]
Visit ENA website for more information on Framework Documents, FAQ’s and more information:
http://www.energynetworks.org/electricity/engineering/accelerated-loss-of-mains-change-programme.html
Accelerated Loss of Mains Change Programme
2016. UK Power Networks. All rights reserved 82
What about next year?
Is there anything you’d like us to do better?Is there anything you’d like us to do differently?Is there anything we’re not doing that you’d like us to start doing?Is there anything other DNOs do better/differently?
2016. UK Power Networks. All rights reserved
Break Out Session• Metered Demand focus
– Room 1 - Antony White » Legal, process overview » Utility Infrastructure - GLA» Heat - Planning for the future» UK Power Networks
Connections in the Competitive Marketplace
» Ideas for improvements 2020/21
83
2016. UK Power Networks. All rights reserved
Legal, process overview • Noel Jemma, Property & Consents Connections Manager
84
2016. UK Power Networks. All rights reserved85
Consents Update – YTD 2019
0
10
20
30
40
50
60
70
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
s.16 Avg. Working Day Tracker 2019
s.16 Actual s.16 2018 s.16 Average Target 60 w/days Stretch 55 w/days
2016. UK Power Networks. All rights reserved86
Consents Update – The Journey so far
164
10391
82
53 5744
s.16 Tracker Avg. W/Days2013 2014 2015 2016 2017 2018 2019
2016. UK Power Networks. All rights reserved87
Consents Update – What have we done
• Departmental Restructures to create a Team with a focus on Connections consents only
• Introduced new processes to continually drive down turnaround times
• Applied a new approach to risk
2016. UK Power Networks. All rights reserved88
Consents Update – Next Steps
• Introducing new processes to put the customer “front and centre”
• Increase visibility as the transaction progresses
• Roll-out of template letters, Heads of Terms etc
2016. UK Power Networks. All rights reserved89
Consents Update – How can you help?
• Respond promptly to UKPN correspondence
• Early contact with third party landowners, or landlords
• Promptly instruct Solicitors to progress legal formalities, and maintain focus on the transaction
• Ensure Solicitors seek Mortgagee and Restriction consents at an early stage
2016. UK Power Networks. All rights reserved
Greater London Authority consultation - Can we improve the process of connecting to utility networks?• Lewis Hubbard
90
UTIL ITY INFRASTRUCTURECAN WE IMPROVE THE PROCESS OF CONNECTING TO UTILITIES NETWORKS?
• Utility Streetworks Collaboration• Planning for Growth• Utility Works for Development• London Underground Asset Register• Infrastructure Mapping Application and
London Development Database• Framework Alliance Contract
I N F R A S T R U C T U R E A N D D E V E L O P M E N T C O O R D I N AT I O N T E A M
Through planning, design and construction of utility works for development, more could be done to:
1. Minimise the disruption to Londoners2. Enable better planning for growth3. Relieve pressure on development viability.
U T I L I T Y W O R K S F O R D E V E L O P M E N T –O U R P R E M I S E
Considering proposals for improvement in the planning, design and construction of utility works for development.
Engaging with local authorities, utility companies, developers, consultants and contractors to formulate the best proposals.
U T I L I T Y W O R K S F O R D E V E L O P M E N T –C U R R E N T A C T I V I T Y
Some have been working to relieve these challenges for many years, achieving success.
This is an opportunity to:• Share experiences• Align our ideas• Coordinate work
Most successful change will require mutual support
T H E S E A R E N O T A N E W P U R S U I T S
D E F I N I T I O N O F D E V E L O P M E N T F O R T H I S P U R P O S EAnything that, at some point, will require an excavator to dig into the ground…
Public Realm – Street Trees – Cycle Ways –SuDS – Residential – Offices – Industrial –Meanwhile Uses – Retail – Education – Arts –Health – Leisure – Food and Beverage –Community – Sports – Parks – Playgrounds –Wetlands – Transport Infrastructure – Utility Infrastructure – Flood Risk Management –Environmental Betterment – Waste & Recycling
• Location of utility infrastructure• Asset protection• Buildover agreements, wayleave agreements• Disconnections• Diversions• New supplies
D E F I N I T I O N O F U T I L I T I E S W O R KF O R T H I S P U R P O S E
• Investigated the nature of persistent procedural problems
• Assessed whether there is a real detrimental impact
• Gauged whether GLA involvement would be beneficial
• Begun to consider potential interventions• Assessed outcomes of Epsom Road
coordinated streetworks trial• Researched work by others
W H AT H AV E W E A N D O U R PA R T N E R S D O N E S O F A R ?
W H AT H AV E W E D O N E S O FA R ?
TYPI CAL PROBLEMS
TYPI CAL PROBLEMS
WHAT IF…
-1-
Local plans were supported by coordinated infrastructure strategies, identifying trigger points for upgrades and cost estimates for
interventions?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-2-
Developers were compelled to contact utilities at the pre-application stage?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-3-
Utility companies were able to assign project managers to development projects from pre-app
to delivery?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-4-
There was a utility capacity / development heatmap for use in pre-app planning, design and
engagement?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-5-
There was simple utility loading calculator, published and usable by any developer through
the pre-app process?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-6-
Asset location plans were able to advise stand-off distances to existing utilities?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-7-
Pre-commencement conditions required demonstration of attempted collaboration with neighbouring developers for planned works?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-8-
The GLA or Local Authorities convened local developer and utility forums, based on local
traffic zones to support collaboration?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-9-
There was a unique interoperable development ID that is usable through pre-planning, planning
and utility works?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-10-
What if there was standardised terminology, consistent between development phases and
utility company processes?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-11-
The GLA employed area specific utilities coordinators who could assist with arrangement
and coordination of utilities work?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-12-
The local highways authority could be engaged to undertake offsite utility works on the developer’s behalf, utilising their term
contractors?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-13-
The local highways authority established moratoriums on non-emergency works in the
public highway, except in defined works windows?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-14-
Survey, trial hole and as-built data could be fed back into utility company’s asset registers
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
WHAT IF…
-15-
We improved the notification of completions between all parties, so utility companies are prepared for resident’s supply applications?
P O T E N T I A L I N T E R V E N T I O N ST H AT W E H AV E H E A R D S O F A R
• Prioritise and develop proposals for meaningful interventions
• Establish working groups to develop ideas and launch pilot projects, with support from IDCT allocated budget.
• Monitor and share outcomes• Propagate successes• Nurture long term systemic change
W H AT A R E W E G O I N G TO D O ?
• Interventions could be for incremental change or total systemic overhaul
• Looking to launch first pilot projects this year
W H AT A R E W E G O I N G TO D O ?
We are currently working up detailed proposals for their role. Provisionally we are thinking…
• They would be based within a local authority.• They would be equipped with dedicated
contacts in each of the utility companies in their area.
• Developers would be referred to the utilities coordinator at pre-app engagement.
UT I L I T I ES COORDI NATOR S
• They would charge fees for their services.• They would provide design advice to developers, based
on local knowledge of infrastructure.• Given proposal information from developers at pre-app,
they would process utility pre-development enquires and return the budget estimates to the developer.
• Given detailed information from developers, they would process applications for detailed utility works quotes and return to the developer.
UT I L I T I ES COORDI NATOR S
• They would have access to the London Underground Asset Register and Infrastructure Mapping Applications to help them plan the utilities work.
• They would assist in early scheduling of utilities works and arrangement of highways licenses.
• They would seek to coordinate the developer’s utilities work with other works happening in the vicinity to minimise disruption and reduce costs.
UT I L I T I ES COORDI NATOR S
• And we will be available to discuss through the remainder of today’s session as well.
ANY QUESTI ONS?
Electrification of Heat
UK Power Networks
Driving Change
Electrifcationof heatWhat is our role?Adriana Laguna
124
2016. UK Power Networks. All rights reserved
Setting the context
Current Trends
125
Heat ElectrificationEV GrowthGrowth in DG
• 9.4GW of DG connected, doubled since 2011
• Over 170,000distribution connected generators
• 77.5GW formal enquiries
• 2.6GW accepted offers
• 217MW connected storage
• 226,000+ Plug-in vehicles sold in the UK, 30% on our networks
• 30,000+ charge points across UKPN
• One to watch -slower than expected
• Large flexible load
• A mix of solutions will be key
Energy Storage
2016. UK Power Networks. All rights reserved
Facilitating Electric Vehicles
UK Power Networks
Driving Change
Government’s Approach
126
Dec 2018: BEIS’s Clean Growth – Transforming Heating Report
• Heat is the single biggest source of UK greenhouse gas emissions• Decarbonising heat will bring extensive change for consumers• Electrification of heat could deliver emission reductions beyond the
levels required by 2050
Mar 2019: Government announced ban on fossil fuel heating new homes from 2025
2016. UK Power Networks. All rights reserved
Slido Q’s
127
2016. UK Power Networks. All rights reserved
Facilitating Electric Vehicles
UK Power Networks
Driving Change
1. What do you think are the biggest challenges to electrifying heat?
2. is there a role for networks to support that proposition?
3. What do you think is the commercial proposition for electrifying heat?
Roundtable Questions
128
2016. UK Power Networks. All rights reserved
UK Power Networks Connections in the Competitive Marketplace• Antony White, Stakeholder Engagement & Account
Manager
129
2016. UK Power Networks. All rights reserved
Internal Meter
Positions
Quote Follow up calls
Promotion&
Advertising
New Quote Letter
Review / Amend
Payment Terms
Substation Design Standards –
Confined Spaces
Review pricing model / methodology
130
2016. UK Power Networks. All rights reserved
Ideas for improvements 2020/21 • 10 Minutes (template)
131
2016. UK Power Networks. All rights reserved 132
What about next year?
Is there anything you’d like us to do better?Is there anything you’d like us to do differently?Is there anything we’re not doing that you’d like us to start doing?Is there anything other DNOs do better/differently?
Thank you…
133
2016. UK Power Networks. All rights reserved 134
DrivingChangeFacilitating EVs
Agenda
• New developments in the EV market
• Insights from our analysis of the market
• Domestic customers
• Local Authorities and on-street charging
• Fleets and depot optimisation
136
Industry consultations – New developments
Stage TimeConsultation Period Until 7 October 2019
Consultation Analysis and Policy Development Autumn 2019
Building Regulations laid in Parliament Winter 2019
Transposition By March 2020
Every new dwelling or building undergoing material change of use to create a new dwelling to have a chargepoint.Minimum rated output of 7kW powerUniversal socket (Untethered)Mode 3 or equivalent Compliance with forthcoming smart
functionality regulations
137
Industry consultations – Smart charging
Government's overall aim for smart charging is to maximise the use of smart charging technologies to benefit both consumers and the electricity system, whilst supporting the transition to EVs.
Aim:• encourage consumer uptake and innovation• Use coordination and regulation to ensure market
does not evolve to have negative consequences for grid protection and consumer protection
The consultation: 15 July 2019 until 7 October 2019https://www.gov.uk/dft#consultations
138
Electric vehicle uptake
18,000+
62,000 Plug-in cars
Charge points
1000+ EV street lights
500+ domestic installations upgraded
139
Insights from our analysis of the market
Once every 3 weeks
Users with access to home charging use rapid public charge points
2030
140
Who is charging where?
62%19%
6%
8%
4%
At Work
At HomeOff-street
DestinationEn-Route
Today
At HomeOn-street
72k38%
22%
22%
8%
9%
At Work
At HomeOff-street
Destination
En-Route
At HomeOn-street
2028
3.6m
141
Informing UKPN strategy – charging hotspots
London EV energy demand in 2025 in the BAU scenario
Secondary substation transformer reinforcement projections by 2025
142
Percentage of participants willing to change their charging behaviour for £3 a month
Peace of mind and control is key to customer buying behaviour
Understanding domestic customers charging behaviour
143
How to achieve the shift in charging behaviour
Industry-wide solutions (2023+)Interim solutions (2021-23)Market trials (2019-20)
24h
Cust
omer
de
man
d (k
W)
24h
Cust
omer
ac
cess
(kW
)
Core capacity
Optional capacity purchase
Peak pricing
24h
Cust
omer
DU
oS P
rice
“High”
“Low” “Low”
FlexibilityProcurement
Capacity based pricing
Time of UseDUoS
144
Understanding domestic V2G Powerloop
70 customer installations to begin in October
• What type of DSO service interfaces do we need?
• What commercial contracts between UKPN and third parties work?
• What are the opportunities to resolve local network constraints?
145
Informing Local Authority EV Planning Strategy
0
100,000
200,000
300,000
400,000
2020 2025 2030 2035 2040 2045 2050
Plug-in Hybrids
East Sussex EV Scenarios
0
100,000
200,000
300,000
400,000
2020 2025 2030 2035 2040 2045 2050
Low
East Sussex EV Uptake
146
Informing Local Authority EV Planning StrategyPublic charger penetration
< 1,0001,000 – 2,0002,000 – 3,000
> 4,0003,000 – 4,000
Number of EVs
East Sussex EV Uptake in 2030
147
Availability of electrical infrastructureSubstation EV heat map Capacity in the capital
Industrial Park, Lewes, East Sussex Signposting positions for rapids serving 200 town centres
https://dgmap.ukpowernetworks.co.uk/site/?q=ev_ext148
Fleets and depots
• How can fleet owners charge and be billed seamlessly at home?
• How can fleet owners use smart charging at home to participate in the flexibility market ?
149
Fleets and depots
• What tools can be developed and standardised to allow customers to optimise their behind-the-meter charging requirements (using smart charging and low carbon technologies)?
• How could a depot solution be optimised further with a profiled connection?
Seven Royal Mail depots identified for initial trial
A Depot Planning Model has been developed to optimise
energy requirements150
27/09/2019 15115127/09/2019 151
Closing Summary, Questions & feedback
151
Thank you…
152