merc, order in case no. 91 of 2013 page 1 before the
TRANSCRIPT
MERC, Order in Case No. 91 of 2013 Page 1
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai – 400 005
Email: [email protected]
Website: www.mercindia.org.in/www.merc.gov.in
Case No. 91 of 2013
IN THE MATTER OF
Petition filed by Vidarbha Industries Power Limited (VIPL) and Reliance
Infrastructure Limited for determination of provisional Tariff for VIPL’s
Butibori Power Plant of 600 MW for FY 2014-15 and FY 2015-16
Shri Vijay L. Sonavane, Member
Smt Chandra Iyengar, Member
ORDER
Date: 17 January, 2014
Vidarbha Industries Power Limited and Reliance Infrastructure Limited submitted a
Petition under Sections 86 (1)(a), 86(1)(b), 62 of the Electricity Act, 2003 and Part E,
Part F and Regulation 100 of MERC MYT Regulations, 2011 before the Maharashtra
Electricity Regulatory Commission (MERC or the Commission) on 24 July, 2013 for
determination of Provisional Tariff for Vidarbha Industries Power Limited’s Butibori
Power Plant for FY 2014-15 and FY 2015-16. The Commission, in exercise of the
powers vested in it under Section 61 and Section 62 of the Electricity Act, 2003 (EA
2003) and all other powers enabling it in this behalf, and after taking into
consideration all the submissions made by the Petitioners, issues raised during the
Public Hearing, and all other relevant material, determines the provisional Tariff of
VIPL’s Butibori Power Plant for FY 2014-15 and FY 2015-16 as under.
MERC Order in Case No 91 of 2013 Page 2
Table of Contents
1 BACKGROUND AND BRIEF HISTORY ........................................................... 5
1.1 Background ..................................................................................................... 5
1.2 Admission of the Petition and Public Process ................................................ 6
1.3 Organisation of the Order ............................................................................... 7
2 OBJECTIONS RECEIVED, VIPL’S RESPONSE AND COMMISSION’S
VIEWS ................................................................................................................... 8
2.1 Offer for supply of power from Wardha power company limited .................. 8
3 APPROACH OF THIS ORDER .......................................................................... 11
4 PROVISIONAL TARIFF OF VIPL’S BUTIBORI POWER PLANT ................ 13
4.1 Background to Project Commissioning ........................................................ 13
4.2 Capital Cost ................................................................................................... 14
4.3 Capital Cost for determination of Tariff ....................................................... 29
4.4 Commission's Views on Prudence Check of Capital Cost ........................... 30
4.5 Means of Finance .......................................................................................... 33
4.6 PROVISIONAL TARIFF ............................................................................. 34
MERC Order in Case No 91 of 2013 Page 3
List of Abbreviations
ACQ Annual Contracted Quantity
AFC Annual Fixed Charges
ARR Aggregate Revenue Requirement
BoP Balance of Plant
BFP Boiler Feed Pump
BTG Boiler Turbine Generator
CA Chartered Accountant
CAPEX/Capex Capital Expenditure
CCEA Cabinet Committee on Economic Affairs
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CIL Coal India Limited
CWIP Capital Work In Progress
EAC Expert Advisory Committee
ECB External Commercial Borrowing
EPC Engineering, Procurement and Construction
ERP Enterprise Resource Planning
FBSM Final Balancing and Settlement Mechanism
FERV Foreign Exchange Rate Variation
FO Furnace Oil
FSA Fuel Supply Agreement
GCPP Group Captive Power Project
GCV Gross Calorific Value
GFA Gross Fixed Assets
ICAI Institute of Chartered Accountants of India
IDC Interest During Construction
IPP Independent Power Project
LoA Letter of Assurance
LDO Light Diesel Oil
LIBOR London Interbank Offered Rate
MAHAGENCO Maharashtra State Power Generation Company Limited
MERC Maharashtra Electricity Regulatory Commission
MIDC Maharashtra Industrial Development Corporation
MLD Million Litres per Day
MERC Order in Case No 91 of 2013 Page 4
MMT Million Metric Tonnes
MMTPA Million Metric Tonnes per Annum
MoC Ministry of Coal
MoEF Ministry of Environment and Forests
MoP Ministry of Power
MoPNG Ministry of Petroleum and Natural Gas
MSPGCL Maharashtra State Power Generating Company Limited
MT Metric Tonnes
OEM Original Equipment Manufacturer
OSBL Outside Boundary Limits
O&M Operation & Maintenance
PLF Plant Load Factor
RBI Reserve Bank of India
RH Relative Humidity
RHT Re-Heat Temperature
RInfra-D Reliance Infrastructure Limited-Mumbai Distribution
RO Reverse Osmosis
RoE Return on Equity
RPL Reliance Power Limited
SFOC Secondary Fuel Oil Consumption
SHR Station Heat Rate
SHT Super Heat Temperature
SICOM State Industrial & Investment Corporation Of
Maharashtra
SPV Special Purpose Vehicle
STPS Super Thermal Power Station
TMCR Turbine Maximum Continuous Rating
TVS Technical Validation Session
USD United States Dollar
VAT Value Added Tax
VIPL Vidharbha Industries Power Limited
WCL Western Coalfields Limited
WPCL Wardha Power Company Limited
MERC Order in Case No 91 of 2013 Page 5
1 BACKGROUND AND BRIEF HISTORY
1.1 Background
1.1.1 This order relates to the Petition filed by Vidarbha Industries Power Limited
(VIPL) and Reliance Infrastructure Limited (RInfra) for the determination of
provisional Tariff of VIPL’s Butibori Power Plant. VIPL is a Generating
Company, which has developed a 600 MW (2 x 300 MW) Power Plant at
Butibori, Nagpur in the State of Maharashtra. Reliance Infrastructure Limited
– Mumbai Distribution (RInfra-D) is a distribution licensee having been
granted a licence under the provisions of Section 14 of the Electricity Act,
2003 for distribution of electricity in the area of supply specified therein
comprising primarily of the suburbs of Mumbai and certain areas falling in the
Mira Bhayander Municipal Corporation.
1.1.2 The Petitioners, in the Petition, has prayed as under:
“
(a) admit the present Petition;
(b) approve the provisional tariff for the 1st Petitioner’s Butibori project
for 600 MW;
(c) approve the request for relaxation of norms and/or removal of
difficulty in respect of (i) Station Heat Rate; (ii) Auxiliary Power
Consumption; and (iii) treatment of cost for hedging foreign currency
loans and/or treatment of foreign exchange rate variation on foreign
currency loans;
(d) dispose-off the present Petition expeditiously
(e) condone any inadvertent omissions/errors or shortcomings in the
Petition;
(f) allow additions/alterations/changes/ amendments to the Petition at a
future date;
(g) grant such order as deemed appropriate under the facts and
circumstances of the case.”
1.1.3 The Petitioners submitted that by the Order dated 20 February, 2013, the
Commission had accorded in-principle approval to the Power Purchase
MERC Order in Case No 91 of 2013 Page 6
Agreement (PPA) between RInfra-D and VIPL for procurement of 300 MW
power on long-term basis from Unit # 2 of VIPL’s Butibori Power Plant.
1.1.4 The Petitioners submitted that by the Order dated 19 July, 2013, the
Commission had accorded in-principle approval to the PPA between RInfra-D
and VIPL for the procurement of 300 MW power on long term basis from
Unit # 1 of VIPL’s Butibori Power Plant.
1.1.5 The Petitioners further submitted that the Commission vide its Order dated 19
July, 2013 had also approved the Consolidation Agreement dated 4 June, 2013
executed between RInfra-D and VIPL for supply under the two PPAs for Unit
# 1 and Unit # 2 to be treated as supply from the Power Plant as a whole for
Tariff and Regulatory purposes.
1.2 Admission of the Petition and Public Process
1.2.1 A set of datagaps were forwarded to VIPL on 8 August, 2013. Another set of
datagaps were forwarded to VIPL on 12 August, 2013. The replies to datagaps
were submitted by VIPL vide its letters dated 16 August, 2013, 17 August,
2013, 19 August, 2013, 27 August, 2013, 28 August, 2013 and 5 September,
2013.
1.2.2 The Technical Validation Session (TVS) was held on 20 August, 2013. During
the TVS, the Petitioner made a presentation focusing on salient features of the
Petition. The list of individuals, who participated in the TVS held on 20
August, 2013 is provided at Appendix-1.
1.2.3 Further, on the directives of the Commission, the Officers of the Commission
held meetings with VIPL and RInfra on 19 August, 2013 and 20 August, 2013
to ensure adequacy of information submitted.
1.2.4 VIPL submitted the revised Consolidated Petition on 5 September, 2013. The
Commission admitted the revised Consolidated Petition on 10 September,
2013. In accordance with Section 64 of the Electricity Act, 2003, the
Commission directed VIPL to publish its Petition in the abridged form to
ensure public participation. The public notice was published in the following
newspapers inviting suggestions/objections from the stakeholders.
MERC Order in Case No 91 of 2013 Page 7
Table 1.1: Newspaper Notice of Public Hearing
Name of the Newspaper Date of publication
Saamna 13 September, 2013
LokSatta 13 September, 2013
Indian Express 13 September, 2013
Hindustan Times 13 September, 2013
1.2.5 The copies of VIPL’s Petition and its Executive summary were made available
at VIPL’s office and on VIPL’s website (www.reliancepower.co.in). The copy
of the Public Notice and the Executive Summary of the Petition were also
made available on the website of the Commission (www.mercindia.org.in/
www.merc.gov.in) in a downloadable format. The Public Notice specified that
the suggestions and objections, either in English or Marathi, may be filed in
the form of an affidavit along with proof of service on VIPL.
1.2.6 The Commission received objections/suggestions/comments from one (1)
stakeholder in writing. The Public Hearing was held on 17 October, 2013 at
Centrum Hall, World Trade Centre-1, Cuffe Parade, Colaba, Mumbai-400005.
The list of individuals who participated in the Public Hearing is provided at
Appendix – 2. The Commission has ensured that the due process as
contemplated under the law to ensure transparency and public participation
was followed at every stage meticulously and adequate opportunity was given
to all persons concerned to file their say in the matter.
1.3 Organisation of the Order
This Order is organised in the following Sections:
Section 1 of the Order provides a brief history of the quasi-judicial regulatory
process undertaken by the Commission. For the sake of convenience, a list of
abbreviations with their expanded forms has been included.
Section 2 of the Order discusses the suggestion raised by the stakeholder in
writing as well as during the Public Hearing before the Commission.
Section 3 of the Order deals with the approach of this Order.
Section 4 of the Order deals with the approval of Provisional Tariff for
VIPL’s Butibori Power Plant for FY 2014-15 and FY 2015-16.
MERC Order in Case No 91 of 2013 Page 8
2 OBJECTIONS RECEIVED, VIPL’S RESPONSE AND COMMISSION’S
VIEWS
2.1 OFFER FOR SUPPLY OF POWER FROM WARDHA POWER
COMPANY LIMITED
2.1.1 Wardha Power Company Limited (WPCL) submitted that it is currently
operating a power plant of installed capacity 540 MW (4 x 135 MW) at
Warora, Maharashtra. WPCL submitted that the Fuel Supply Agreement had
been signed with Western Coal Fields Limited for approximately 70% of the
coal requirement and it is in discussion with Western Coal Fields Limited for
execution of Fuel Supply Agreement for the balance requirement also.
2.1.2 WPCL submitted that the first two Units (2 x 135 MW) are currently
supplying power to RInfra-D in accordance with Power Purchase Agreement
dated 4 June, 2010 executed in pursuance of medium term bidding conducted
by RInfra-D. WPCL submitted that the power from the third and fourth Units
(2 x 135 MW) is being supplied primarily to captive consumers.
2.1.3 WPCL submitted that RInfra-D, in 2009, had floated a long term bid for
procurement of power to the extent of 1500 MW ± 20% for 20 years. WPCL
submitted that it had offered 320 MW at a Levellised Tariff of Rs. 3.421 per
kWh and was the lowest bidder. WPCL submitted that the bid was not taken
up and subsequently lapsed in July, 2010.
2.1.4 WPCL submitted that RInfra-D had floated a medium term bid for supply of
power for 3 years. WPCL submitted that it had offered 270 MW and was the
lowest bidder. WPCL submitted that in spite of RInfra-D seeking to terminate
the PPA, it could commence supply on the intervention of the Commission.
WPCL submitted that this PPA expires on 31 March, 2014.
2.1.5 WPCL submitted that RInfra-D again floated a long term tender for
procurement of 1000 MW ± 20% for supply of power for 25 years. WPCL
submitted that it had offered 220 MW and KSK Mahanadi Power Limited, a
Group Company of WPCL, had offered another 400 MW. WPCL submitted
that the bid was ultimately scrapped by RInfra-D.
2.1.6 WPCL submitted that the Commission vide its Order dated 20 February, 2013
accorded in-principle approval for the PPA between RInfra-D and VIPL for
MERC Order in Case No 91 of 2013 Page 9
supply of 300 MW for 25 years. WPCL submitted that vide its letter dated 5
March, 2013 it had offered to supply to RInfra-D on the same terms and rate
as indicated by VIPL on a long term basis, commencing April 2014.
2.1.7 WPCL submitted that the Commission vide its Order dated 19 July, 2013
accorded in-principle approval for the PPA between RInfra-D and VIPL for
supply of additional 300 MW for 25 years, totalling to 600 MW.
2.1.8 WPCL submitted that its project cost is Rs. 2811 Crore i.e. Rs. 5.2 Crore/MW
as against VIPL’s project cost of Rs. 4063 Crore i.e. Rs. 6.77 Crore/MW.
WPCL submitted that in view of the lower project cost, it would be in a
position to offer supply at a fixed cost lower than Rs. 2.25/ kWh as submitted
by VIPL.
2.1.9 WPCL submitted that while VIPL has Letter of Assurance (LoA) for supply of
coal from WCL, it has a commitment from WCL for full supply of coal
requirement and had been procuring coal from WCL. WPCL submitted that
from fuel preparedness and supply perspective, availability of fuel is more
secure for WPCL. WPCL submitted that its power station is fully operative
and has a track record of continuous supply of 270 MW to RInfra-D and no
changes would be required for physical enabling of the connectivity and
supply.
2.1.10 WPCL submitted that its power station within Maharashtra has not only been
supplying power to RInfra-D under the medium term PPA but has also been
consistently offering the capacity to RInfra-D on long term basis since 2009.
WPCL submitted that procurement from two sources and more than one
generating station would be a good practice and would ensure stability to the
procurement system.
2.1.11 WPCL submitted that on approval for supply at least to the extent of 270 MW,
it would make a detailed presentation on various costs and the likely Tariff for
RInfra-D, to ensure that the Tariff to the end consumer becomes competitive.
WPCL submitted that its participation in the procurement by RInfra-D would
render the Tariff discovery transparent and market determined. WPCL
submitted that it offers to supply 270 MW of power to RInfra-D at the same
Tariff and on the same terms and conditions as is being presently offered by
VIPL. WPCL submitted that being a distribution licensee, RInfra-D is bound
to afford it an opportunity prior to any finalisation and seeking approval of
MERC Order in Case No 91 of 2013 Page 10
PPA by the Commission and prayed that RInfra-D as well as the Commission
would consider its offer.
VIPL’s Reply
2.1.12 VIPL submitted that the present proceedings are for Tariff determination
pursuant to PPA between RInfra-D and VIPL approved by the Commission
and objections raised by WPCL are not relevant in these proceedings.
Commission’s view
2.1.13 In exercise of powers conferred under the Electricity Act, 2003 under Section
86 among others, the Commission has notified MERC MYT Regulations,
2011 and has specified the provisions for approval of Power Purchase
Agreement for supply of power from a Generating Station to a Distribution
Licensee. The Commission in accordance with the provisions of MERC MYT
Regulations, 2011 shall determine the Tariff for supply of electricity from a
Generating Station to a Distribution Licensee pursuant to the approval of PPA
between the Generating Station and Distribution Licensee. The Commission
had approved the PPAs as well as the Consolidation Agreement entered into
between VIPL and RInfra-D for supply of power from VIPL’s Butibori Power
Plant to RInfra-D after due regulatory process in accordance with MERC
MYT Regulations, 2011.
The Commission is of the view that the purchase of power by RInfra-D from
WPCL is a decision to be taken by RInfra-D. Moreover, the issue raised by
WPCL is not relevant as far as determination of provisional Tariff for VIPL
for supply of power to RInfra-D is concerned.
MERC Order in Case No 91 of 2013 Page 11
3 APPROACH OF THIS ORDER
3.1.1 VIPL filed the present Petition for determination of Provisional Tariff for
supply of 600 MW from its Butibori Power Plant for FY 2014-15 and FY
2015-16 under Sections 86 (1)(a), 86(1)(b), 62 of the Electricity Act, 2003 and
Part E, Part F and Regulation 100 of MERC MYT Regulations, 2011.
3.1.2 Regulation 17.2.1 of MERC MYT Regulations, 2011 specifies as under:
“The tariff for the supply of electricity by a Generating Company to a
Distribution Licensee from a new generating Unit/Station shall be in
accordance with tariff as per power purchase agreement approved by the
Commission, except if such power purchase agreement has been exempted
from requiring such approval in accordance with Part D of these
Regulations.”
3.1.3 The Commission accorded in-principle approval to the PPA executed between
VIPL and RInfra-D for supply from Unit # 2 of VIPL’s Butibori Power Plant
vide its Order dated 20 February, 2013 and for supply from Unit # 1 of VIPL’s
Butibori Power Plant vide Order dated 19 July, 2013. Further, the Commission
also approved the Consolidation Agreement for supply of 600 MW from
VIPL’s Butibori Power Plant to RInfra-D.
3.1.4 Regulation 38.4 of MERC MYT Regulations, 2011 specify as under:
“A Generating Company may make a Petition for determination of
provisional tariff in advance of the anticipated Date of Commercial Operation
of Unit or Stage or Generating Station as a whole, as the case may be, based
on the capital expenditure actually incurred up to the date of making the
Petition or a date prior to making of the Petition, duly audited and certified by
the statutory auditors and the provisional tariff shall be charged from the date
of commercial operation of such Unit or Stage or Generating Station, as the
case may be.”
3.1.5 VIPL submitted that Unit # 1 has achieved COD on 4 April, 2013 and COD of
Unit # 2 has taken longer time than expected due to non availability of
SICOM/railway land that constitutes small portion of total land required for
MERC Order in Case No 91 of 2013 Page 12
completion of Railway Siding. VIPL submitted that all efforts are being made
to get the approval for transfer of SICOM/Railway land at the earliest. VIPL
in its petition submitted that majority of works on railway siding have already
been completed and the completion of works for railway siding and COD of
Unit # 2 is expected to be achieved by March, 2014.
3.1.6 The regulated supply of power from VIPL to RInfra-D shall commence from 1
April, 2014. The Commission in this Order has approved the Provisional
Tariff of Butibori Power Plant for FY 2014-15 and FY 2015-16 based on the
scrutiny of information furnished by VIPL in accordance with the provisions
of MERC MYT Regulations, 2011.
MERC Order in Case No 91 of 2013 Page 13
4 PROVISIONAL TARIFF OF VIPL’S BUTIBORI POWER PLANT
4.1 Background to Project Commissioning
4.1.1 VIPL is a Special Purpose Vehicle (SPV) established for implementation of a
Group Captive Power Project through Competitive Bidding Process conducted
by MIDC.
4.1.2 The Generating Station awarded to VIPL for implementation was initially of
130 MW capacity and later enhanced to 300 MW. Further, VIPL was
permitted to expand the capacity of the Station by adding Unit # 2 of 300 MW
capacity under IPP route.
4.1.3 As adequate industrial consumers have not shown interest in procuring power
from Unit # 1 of Generating Station under GCPP route, VIPL has offered the
entire 600 MW to RInfra-D and has executed PPAs for supply of 600 MW to
RInfra-D under the provisions of Electricity Act, 2003 and MERC MYT
Regulations, 2011.
4.1.4 The Commission vide its Order dated 20 February, 2013 in Case No. 2 of
2013 accorded in-principle approval to the PPA between VIPL and RInfra-D
for supply of 300 MW from Unit # 2 (IPP).
4.1.5 The Commission vide its Order dated 19 July, 2013 in Case No. 76 of 2013
accorded in-principle approval to the PPA between VIPL and RInfra-D for
supply of 300 MW from Unit # 1 (GCPP converted to IPP).
4.1.6 VIPL submitted that it had awarded 3 separate EPC Contracts to Reliance
Infrastructure Limited for Unit # 1, Unit # 2 and Railway siding works.
4.1.7 VIPL submitted that Unit # 1 has achieved Commercial Operation Date
(COD) on 4 April, 2013 and Unit # 2 is expected to get commissioned by
March, 2014. VIPL further submitted that COD of Unit # 2 has taken longer
than expected time due to non-availability of SICOM/ railway land which
constitutes a small portion (~12%) of the total land required for completion of
Railway siding. VIPL submitted that all efforts are being made to get the
approval for transfer of SICOM/ Railway land at the earliest. VIPL also
submitted that since majority of works on railway siding have already been
MERC Order in Case No 91 of 2013 Page 14
completed, assuming availability of SICOM/ Railway land by October 2013,
the completion of works for railway siding and COD of Unit # 2 is expected to
be achieved by March, 2014.
4.1.8 The key milestones submitted by VIPL are shown in the Table below:
Table 4.1: Key milestones
S. No. Event Unit # 1 Unit # 2
1 Investment approval by the
Board 17 October, 2009 13 September, 2010
2 Date of synchronisation 25 June, 2012 2 January, 2013
3 Date of taking full load 17 August, 2012 19 March, 2013
4 Performance Guarantee
Tests Not carried out Not carried out
5 COD 4 April, 2013 Expected by March
2014
4.1.9 VIPL submitted the Audited Accounts for FY 2012-13. VIPL also submitted
the CA certificate for capital expenditure incurred till 31 May, 2013.
4.2 Capital Cost
4.2.1 As regards Capital Cost, Regulation 27 of MERC MYT Regulations, 2011
specifies as under:
“27.1 Capital cost for a project shall include
(a) the expenditure incurred or projected to be incurred, including
interest during construction and financing charges, any gain or
loss on account of foreign exchange risk variation on the loan
during construction up to the date of commercial operation of the
project, as admitted by the Commission, after prudence check;
(b) capitalised initial spares subject to the ceiling rates specified in
this Regulation; and
(c) additional capital expenditure determined under Regulation 28:
.....”
4.2.2 VIPL submitted that Unit # 1 achieved COD on 4 April, 2013 and Unit # 2 is
expected to get commissioned by March, 2014. VIPL submitted that COD of
Unit # 2 has taken longer than expected time due to non-availability of
MERC Order in Case No 91 of 2013 Page 15
SICOM/ railway land which constitutes a small portion (~12%) of the total
land required for completion of Railway siding. VIPL further submitted that
all efforts are being made to get the approval for transfer of SICOM/ Railway
land at the earliest. VIPL submitted that since majority of works on railway
siding have already been completed, assuming availability of SICOM/
Railway land by October 2013, the completion of works for railway siding and
COD of Unit # 2 is expected to be achieved by March, 2014. VIPL submitted
that for the purpose of this Petition, the COD of the station as a whole implies
that the second Unit of 300 MW is also declared to be commercially
operational.
4.2.3 VIPL submitted that the capital cost and Tariff calculations submitted in the
Petition are in accordance with the format prescribed by the Commission.
VIPL submitted that considering the overall principles enshrined in the Tariff
Regulations, the envisaged capital cost of the Power Station is Rs. 4132.36
Crore. VIPL submitted the detailed break-up of the aforesaid Capital Cost as
shown in the Table below:
Table 4.2: Capital Cost submitted by VIPL (Rs. Crore)
Sr. No. Particulars Expected Cost as on COD ( Rs.
Crore)
1a Owned Land 62.16
1b Leased Land 31.51
2 BTG (Rs. Crore) 832.27
2a BTG (USD Million) 176.60
3 BOP 1808.11
3a Design and Engineering 40.94
3b BOP Mechanical 666.37
3c BOP Electrical 342.83
3d C&I Package 72.96
3e BTG Erection 135.02
3f Civil Works 549.99
4 Taxes and Duties 182.00
5 Overheads 305.76
6 OSBL 382.49
7 IDC & FC* 449.54
8 FERV on settlement of Buyer’s Credit* 78.52
9 Total Capital Cost 4132.36
MERC Order in Case No 91 of 2013 Page 16
* till 31 May, 2013
4.2.4 VIPL submitted that the Capital Cost submitted is the expected Capital Cost of
the power station as a whole and the same is based on the following
considerations:
i. VIPL submitted that the IDC and Financing Charges submitted in the
Petition are till 31 May, 2013. VIPL submitted that IDC for Unit # 1 is
considered till its COD on 4 April, 2013. VIPL submitted that post
April 2013, 40% of the overall interest liability for the Station is
allocated to Unit # 1 and the balance has been considered as IDC
against Unit # 2. VIPL submitted that the same is assumed on a
notional basis since the loans have been taken for both Units together
and there is no segregation of loans between the two Units. VIPL
submitted that it would furnish the actual IDC for the project at the
time of final determination of Tariff.
ii. VIPL submitted that the capital cost is inclusive of overheads, start-up
expenses and the realized foreign exchange differences on settlements
of Buyer’s Credit as on 31 May, 2013 as per CA certificate. VIPL
submitted that the capital cost does not include any unrealized
exchange rate differences on foreign currency loan and liability and the
same shall be submitted to the Commission post the COD of the
station along with audited accounts at the time of final determination
of Tariff. VIPL submitted that it would submit the final capital cost
including IDC and other breakup post COD of the station along with
audited accounts at the time of final determination of Tariff.
Land and Site development
4.2.5 VIPL submitted that the land acquired for the project is a mix of
MIDC/SICOM land and private land. VIPL submitted that as against the
original estimate of Rs. 80 Crore for land and site development, the expected
cost as on COD of the project is Rs. 93.67 Crore. VIPL submitted that the
increase in cost of land and site development is because of the increase in
price of MIDC land from Rs. 4 Lakh/acre to Rs. 19 Lakh/acre. VIPL
submitted that this increase also had an impact on private land acquisition.
4.2.6 The Commission directed VIPL to submit the summary statement of land
acquired from all the sources along with the acquisition rate. Further, the
MERC Order in Case No 91 of 2013 Page 17
Commission asked VIPL to submit the supporting documents for increase in
price of MIDC land from Rs. 4 Lakh/acre to Rs. 19 Lakh/acre.
4.2.7 VIPL submitted the summary statement of land acquired from all sources as
shown in the Table below:
Table 4.3: Summary statement of land acquired as submitted by VIPL
S. No. Source Area (in acres) Total cost
(Rs. Crore)
Average
acquisition rate
(Rs. Crore/acre)
1 MIDC Land 298 23 0.08
2 Private Land 257 61 0.24
4.2.8 VIPL submitted the details of land acquired from MIDC as shown in the Table
below:
Table 4.4: Details of MIDC land acquired submitted by VIPL
MIDC land Area Cost of land Rate
Sq. m Acre Rs. Crore Rs. Crore/acre
D-3 700000 173 7.00 0.04
D-3/Part 200000 49 3.45 0.07
D-3/Part 1 205099 51 8.20 0.16
RS-1 101175 25 4.05 0.16
P-81 1250 0.31 0.06 0.19
P-82 1440 0.36 0.07 0.19
4.2.9 VIPL submitted that the details regarding the SICOM and Railway land would
be provided after the completion of transfer process.
4.2.10 VIPL submitted the lease deed of MIDC land D-3 that was acquired at rate of
Rs. 4 Lakh/acre and lease deed of MIDC land P-81 acquired at rate of Rs. 19
Lakh/acre.
4.2.11 The Commission further directed VIPL to submit the comparison of cost of
land and site development between original estimates and expected cost as on
COD of the project in terms of quantum and price. VIPL submitted the details
of land for Butibori Power Plant as shown in the Table below:
MERC Order in Case No 91 of 2013 Page 18
Table 4.5: Details of Land for Butibori Power Plant submitted by VIPL
S.
No. Particulars
Quantum of land
acquired/leased
(Acres)
Cost per acre of
land (Rs. Crore)
Total Cost (Rs.
Crore)
Original
estimate Actual
Original
estimate Actual
Original
estimate Actual
1 MIDC 305 298 0.040 0.078 12.20 23.24
2 Private 263 270 0.235 0.239 61.81 65.61
3 SICOM 47 47 0.110 0.113 5.17 5.31
4 Railway 3 3 0.167 0.167 0.50 0.50
Total 618 618 - - 79.68 93.67
EPC Contracts for Unit # 1 and Unit # 2
4.2.12 VIPL submitted that it has awarded two separate EPC contracts for Unit # 1
and Unit # 2 to Reliance Infrastructure Limited.
4.2.13 The Commission directed VIPL to submit the copies of EPC Contracts for
Unit # 1 and Unit # 2. The Commission also asked VIPL to submit the basis of
allocation of EPC cost under various heads as in Form 3.1.
4.2.14 VIPL submitted the copies of EPC contracts and amendments thereto for Unit
# 1 and Unit # 2.
4.2.15 VIPL submitted that the EPC contracts were awarded by VIPL as turnkey
project execution where the EPC contractor is responsible for engineering to
commissioning of the plant. VIPL submitted that the EPC cost has been
finalised as lump sum turnkey contract for total scope and not based on
individual package basis. VIPL submitted that the break-up of prices for
mechanical, electrical, civil and other packages have been provided in Form
3.1 based on the agreed billing schedule between the parties for the purpose of
payment, out of the total lump sum turnkey contract which provides the values
for onshore equipment supply, construction and services (other than BTG).
VIPL submitted that these prices are inclusive of Taxes and Duties as per the
EPC contracts.
MERC Order in Case No 91 of 2013 Page 19
4.2.16 The Commission also directed VIPL to submit how the least cost principle
was ensured in the award of contracts.
4.2.17 VIPL submitted that it is a 100% owned subsidiary of Reliance Power Limited
(RPL). VIPL submitted that as a leading private sector power developer, RPL
has institutionalised rigorous procurement processes. VIPL submitted that the
same are backed by repository of data gathered from own project development
experiences, information available in public domain and market intelligence.
4.2.18 VIPL submitted that all the special purpose vehicles (SPVs) set up by RPL
adopt the rigorous procurement processes stipulated by the parent company.
VIPL submitted that while undertaking capital procurement, the relevant
project development teams undertake a detailed benchmarking exercise. VIPL
submitted that all underlying cost assessments involve; (a) Total capital cost
and (b) Life cycle cost considering both, capital cost and operating cost.
4.2.19 VIPL submitted that the cost benchmarking exercise for EPC cost entails a
bottom-up build up of costs of distinct system/packages, considering
(a) Least purchase price ever paid for a given system/package – adjusted for
inflation /applicable commodity prices changes
(b) Bill of Materials based estimates, where possible
(c) Market comparables
(d) Price which can be sustained by the project to remain competitive
4.2.20 VIPL submitted that the target benchmark cost is based on the lowest of the
cost benchmarks developed using above approaches. VIPL submitted that the
confidentiality of the same is strictly maintained to ensure sanctity of the
procurement process and effectiveness of its outcome. VIPL submitted that the
target benchmark cost forms the critical guiding input for the decision to
award EPC Contract. VIPL submitted that other factors which also form key
inputs to the procurement decision are (a) Schedule of Delivery (b) Quality (c)
Sustainability and (d) Environmental impact. VIPL submitted that the above
approach ensures that capital procurement decisions are based on a sound and
rigorous process aimed at optimizing life cycle cost of the project.
MERC Order in Case No 91 of 2013 Page 20
4.2.21 VIPL submitted that Butibori project was originally conceived as one Unit of
300 MW to be developed as GCPP. VIPL submitted that the same was
awarded through competitive bidding process by MIDC. VIPL submitted that
51% of power to be produced by the project was proposed to be sold to
industrial consumers with their equity participation, to qualify as GCPP. VIPL
submitted that in addition, an additional capacity of 300 MW was undertaken
at the same site. VIPL submitted that ensuring competitiveness of the project
has been at the core of development philosophy of this project.
4.2.22 VIPL submitted that the project was executed by awarding the EPC contract,
whereby the entire responsibility of construction of the project is with the EPC
contractor. VIPL submitted that the EPC contract price offered by Reliance
Infrastructure Limited was compared with EPC contract cost benchmarks for
similar projects at that point of time, with BTG supply awarded to Reliance
Infra Projects (UK) Limited. VIPL submitted that for competiveness of
procurement, it had also undertaken due-diligence on the market dynamics
prevalent at the time of award of the contract.
4.2.23 VIPL submitted that for the construction of a power plant, there exist two
kinds of packages namely mandatory packages (BTG, BOP, Civil etc) and
project specific additional packages (township, transmission line and railway
siding). VIPL submitted that the comparison was undertaken for mandatory
packages.
4.2.24 VIPL submitted that post award of contracts, it has undertaken an exercise to
compare the EPC costs of some other stations developed by Central Sector
entities and State Sector entities. VIPL submitted that appropriate correction
factors (escalation factors for year of award, Unit size correction factors,
taxes) have been applied to make the comparison on a like-to-like basis.
4.2.25 The Commission asked VIPL to submit the Detailed Project Report (DPR) for
the project. VIPL submitted the DPR for Unit # 1 and Unit # 2. In the said
DPRs, the estimated capital cost for Unit # 1 is Rs. 2070 Crore including IDC
and the estimated capital cost for Unit # 2 is Rs. 1563 Crore including IDC.
Hence, the estimated capital cost as per the DPRs for the project is Rs. 3633
Crore including IDC.
MERC Order in Case No 91 of 2013 Page 21
Railway siding
4.2.26 VIPL submitted that it has awarded EPC contract for Railway siding works to
Reliance Infrastructure Limited.
4.2.27 VIPL submitted that as against the original estimate of Rs. 273 Crore, the
expected cost of Railway siding works as on COD of the project is Rs. 347.03
Crore.
4.2.28 VIPL submitted that the scope of Railway siding work changed due to
relocation of marshalling yard and route alignment change as per the
requirement of Railways. VIPL submitted that the variation is primarily on
account of following:
a. VIPL submitted that scope addition of Minor Bridges contributed to
increase of Rs. 20 Crore.
b. VIPL submitted that the span of major bridges has changed due to change
in location of marshalling yard. VIPL submitted that the scope addition of
Major Bridges contributed to increase of Rs. 22 Crore.
c. VIPL submitted that the track length had increased due to change in
location of marshalling yard and this contributed to increase of Rs. 4
Crore.
4.2.29 VIPL submitted that in order to have operational flexibility for handling
loaded rakes additional locomotive has been envisaged and this scope addition
of Diesel locomotive contributed to Rs. 11 Crore.
4.2.30 VIPL submitted that the scope addition of Station yard/Railway Utility
building and other miscellaneous works as per Railways requirement
contributed to Rs.10 Crore.
4.2.31 The Commission asked VIPL to submit the copy of EPC contract for Railway
siding. VIPL submitted the copy of EPC contract and amendments thereto for
Railway siding.
4.2.32 The Commission observed that the contract price in the EPC contract
submitted is Rs. 342.54 Crore where VIPL submitted the cost of Rs. 347.03
MERC Order in Case No 91 of 2013 Page 22
Crore. The Commission asked VIPL to submit the reason for this variation.
VIPL submitted that the difference is due to price adjustment of Rs. 4.49
Crore due to delay in transfer of land from SICOM and Railways.
Overheads
4.2.33 VIPL submitted that against the original estimate of Rs. 155 Crore, the
expected cost of overheads as on COD of the project is Rs. 305.76 Crore.
4.2.34 VIPL submitted that the increase in cost of overheads is due to the following
reasons:
i. Royalty payments for Railway siding embankment - VIPL submitted that
due to change in the rates of royalty from Rs. 100 per brass to Rs. 200 per
brass the variation in royalty is approximately Rs. 9 Crore.
ii. Capital cost contribution paid to MIDC for water allocation – VIPL
submitted that against the total water requirement of 22 MLD for one Unit,
MIDC initially allotted 15 MLD without charging capital cost contribution
(Onetime payment to MIDC) and for balance 7 MLD, MIDC charged
Rs.12 Crore as capital cost contribution fees.
iii. Restoration charges paid to Irrigation Department for water allocation –
VIPL submitted that as per MIDC policy, for the industries located in
MIDC area water shall be provided by MIDC. VIPL submitted that due to
non availability of water allocation to MIDC from Irrigation Department,
MIDC had asked VIPL to arrange water from alternate source. VIPL
submitted that it had approached Irrigation Department and got water
allocation. VIPL submitted that Irrigation Department charged restoration
charges of Rs. 13 Crore.
iv. Railway deposit works and codal charges – VIPL submitted that in Sindhi
station yard many modification works are being carried out as per the
instructions of Railways and the amount of such expenses is estimated at
Rs. 35 Crore.
v. Transmission line outage charges paid to MSETCL – VIPL submitted that
in Railway alignment one EHV line is crossing. VIPL submitted that it
MERC Order in Case No 91 of 2013 Page 23
necessitated increasing the height of EHV tower. VIPL submitted that for
raising the tower MSETCL has charged an outage charge of Rs.4 Crore.
vi. VIPL submitted that start up expenses have gone up primarily on account
of higher than anticipated spend on account of the following factors:
a. VIPL submitted that purchase of market coal due to non availability of
linkage coal resulted in additional cost of Rs. 15 Crore.
b. VIPL submitted that as per MSEDCL's policy, payments were made
only for infirm power during peak hours resulting in non recovery of
Rs. 20 Crore towards expenses for infirm power.
c. VIPL submitted that purchase of oil contributed to increase on start up
expenses.
d. VIPL submitted that start up power from MSEDCL contributed to
increase in start up expenses.
vii. VIPL submitted that administrative expenses have also gone up.
viii. VIPL submitted that increase in insurance and other expenses led to
increase of Rs.10 Crore.
ix. VIPL submitted that due to change in COD of units there is an increase in
overheads to the extent of Rs.10 Crore.
4.2.35 The Commission asked VIPL to submit the break-up of overheads cost. The
Commission also asked VIPL to submit the month wise details of fuel
consumed, revenue billed and revenue recovered by sale of infirm power.
4.2.36 The break-up of overheads cost submitted by VIPL is shown in the Table
below:
MERC Order in Case No 91 of 2013 Page 24
Table 4.6: Overhead expenses submitted by VIPL (Rs. Crore)
Particulars
Expected cost as on
COD of the project
(Rs. Crore)
Pre-operative and preliminary
expenses 124
Government fees 88
Commissioning expenses 93
Total 306
4.2.37 The Commission observed that the overheads cost includes royalty payments,
railway deposit works and railway codal charges. The Commission asked
VIPL to submit the rationale for such charges additional to the cost of railway
siding. VIPL submitted that the approval of railway siding has been granted by
Railways to VIPL for coal transportation up to the Butibori Power Plant. VIPL
submitted that all the royalty payments, railway deposit works and codal
charges had to be paid directly by VIPL to the concerned authorities.
4.2.38 VIPL submitted the details of sale of infirm power as shown in the Table
below:
Table 4.7: Revenue earned from infirm supply as submitted by VIPL (Rs.
Crore)
Period
Quantum of
energy
generated
(kWh)
Infirm supply
approved for
billing (kWh)
Rate of sale
of infirm
supply
(Rs./kWh)
Revenue
earned
from infirm
supply (Rs.
Lakhs)
Actual fuel
cost
incurred
(Rs. Lakhs)
Fuel cost
unrecovered
(Rs. Lakhs)
Jun-12 20200 1648 2.97 0.05 639.20 639.15
Jul-12 430000 170000 2.97 5.05 233.20 228.15
Aug-12 3116610 798.40 798.40
Sep-12
Oct-12
Nov-12
Dec-12
Jan-13 147287 102344 2.97 3.04 438.31 435.27
Feb-13
MERC Order in Case No 91 of 2013 Page 25
Period
Quantum of
energy
generated
(kWh)
Infirm supply
approved for
billing (kWh)
Rate of sale
of infirm
supply
(Rs./kWh)
Revenue
earned
from infirm
supply (Rs.
Lakhs)
Actual fuel
cost
incurred
(Rs. Lakhs)
Fuel cost
unrecovered
(Rs. Lakhs)
1 March, 2013 to
19 March, 2013 1515509 243.71 243.71
31 March 2013 21 FBSM not yet
finalised
Rate of Net
Realisation
from FBSM
statement
55.00 55.00
Apr-13 1380602 FBSM not yet
finalised
Rate of Net
Realisation
from FBSM
statement
304.00 304.00
Total 6610228 273992 - 8.14 2711.82 2703.68
4.2.39 The Commission asked VIPL to submit the copies of agreements executed for
infirm power supply. VIPL submitted the copies of letters from MSEDCL and
RInfra-D regarding the approval of purchase of infirm power from Unit # 1 of
its Butibori Power Plant.
4.2.40 The Commission also asked VIPL to submit the increase in overheads cost
due to delay in COD of the Units.
4.2.41 VIPL submitted that to complete the Railway siding, few pockets of identified
land were required to be procured from SICOM and Central Railways. VIPL
submitted that railway siding is critical for securing sustained fuel supplies to
the power station. VIPL submitted that transportation of coal by road and
simultaneous sustained operation of both the Units based on coal transported
by road is not a feasible option from environmental and logistical point of
view.
4.2.42 VIPL submitted that majority of works on railway siding are completed except
the work on pockets of land mentioned above. VIPL submitted that without
completion of these works, the railway siding cannot be put to use. VIPL
submitted that non availability of pockets of land has delayed completion of
railway siding and has therefore delayed COD of the project.
MERC Order in Case No 91 of 2013 Page 26
4.2.43 VIPL submitted that an application for transfer of identified land from SICOM
was made in January, 2009. VIPL submitted that based on the demand note
given by SICOM, it had paid 50% advance amount for the land in May, 2011.
VIPL submitted that for the final transfer of land, SICOM is required to take
clearance from Industry, Revenue and Law and Judiciary departments of
Government of Maharashtra. VIPL submitted that it had made significant
efforts at almost every level in each government department to speed up the
clearance process for land acquisition with the relevant authorities. VIPL
submitted that despite relentless follow-up, the process of clearance from
various departments has taken time far beyond expectations. VIPL submitted
that recent discussions with authorities have confirmed that final go through
for land acquisition from SICOM would be given soon.
4.2.44 VIPL submitted that similar application for transfer of identified land pocket
had been made to Central Railways in August, 2010. VIPL submitted that the
Detailed Engineering Scale Plan was approved by the relevant authorities in
June, 2011 enabling Railway Land Licensing approval process. VIPL
submitted that the final go ahead of Central Railways has not yet been
received because of prolonged internal clearance process. VIPL submitted that
recent discussions with authorities has confirmed that final go ahead will be
released soon by the Head Office of Central Railways enabling land
possession process. VIPL submitted that completion of railway siding is a
must for procurement of coal for sustained operation of the plant and the
procurement is not possible through other transportation means such as road
transport as it would lead to huge traffic congestion due to continuous
movement of vehicles and restrictions on such movement of vehicles on
account of railway crossing that the vehicles have to traverse for such coal
transport. VIPL submitted that in spite of such coal procurement issues, it had
declared the commercial operation of Unit # 1 based on market coal procured
through road transport. VIPL submitted that the same is not possible for entire
plant as this will lead to movement of at least 430 trucks carrying aggregate
8600 MT of coal on a daily basis from Butibori Railway Station to the Plant
Coal Yard. VIPL submitted that it would cause huge traffic congestion and is
logistically infeasible due to existence of railway crossing as mentioned
above.
4.2.45 VIPL submitted that although Unit # 1 has achieved full load operation on 17
August, 2012 the COD of the Unit was delayed on account of non availability
of Carpet Coal required for commissioning purposes from WCL. VIPL
MERC Order in Case No 91 of 2013 Page 27
submitted that Carpet coal was recommended by CEA and WCL has not
supplied the same.
4.2.46 VIPL submitted that because of the reasons stated above, the COD of the
Project has been delayed and the same has led to increase in overhead cost and
increase in IDC. VIPL submitted that none of the reasons can be attributed to
VIPL and have been caused primarily by external agencies and thus are
uncontrollable in nature. VIPL requested the Commission to accord its
approval for the increase in overheads as the same have arisen due to reasons
beyond its control and could not be avoided despite its best efforts.
Initial spares
4.2.47 The Commission asked VIPL to submit the list of initial spares included in
Capital Cost. VIPL submitted that the procurement of initial spares was done
as recommended by OEMs to the EPC contractor. VIPL submitted that the
quantum of initial spares lie within the normative limits as per MERC MYT
Regulations, 2011 and submitted the list of initial spares.
4.2.48 The Commission also asked VIPL to submit the cost of equipment and cost of
spares under each package separately inclusive of taxes and duties. VIPL
submitted the details of cost of spares as shown in the Table below:
Table 4.8: Cost of spares submitted by VIPL
Package Package Cost
(Rs. Crore)
Equipment cost
(Rs. Crore)
Spares cost
(Rs. Crore)
BTG 176.60 169.00 7.60
BOP Mechanical 666.37 616.88 49.48
BOP Electrical 342.83 337.16 5.68
BOP C&I 72.96 70.10 2.86
Total 65.62
Interest During Construction (IDC)
4.2.49 VIPL submitted Rs. 449.54 Crore as IDC as on 31 May, 2013 as against the
original estimate of Rs. 398.00 Crore. VIPL submitted that post COD of Unit
# 1, 40% of IDC is allocated to Unit # 1 and the balance has been allocated to
Unit # 2. VIPL submitted that the increase in IDC is due to delay in COD of
MERC Order in Case No 91 of 2013 Page 28
Unit # 1 and non achievability of COD of Unit # 2 due to non availability of
SICOM and Railway land required for completion of railway siding.
4.2.50 The Commission asked VIPL to submit the computations of original estimates
of IDC of Rs. 398.00 Crore submitted in the Petition. VIPL submitted the
excel workings of original estimates of IDC.
4.2.51 The Commission also asked VIPL to submit the rationale of allocating IDC
post COD of Unit # 1. VIPL submitted that the financing of the project is
combined financing. VIPL submitted that as the loans were not allocated Unit
wise, the allocation of interest liability post COD of Unit # 1 has been
considered based on the ratio of capitalisation of assets at the time of COD of
Unit # 1 (Rs. 1364 Crore) and the total hard cost of the project (Rs. 3604
Crore), which is around 40%.
Financing Charges
4.2.52 The Commission asked VIPL to submit the basis and computations of
financing charges, commitment charges and other charges as submitted in
Form 3.7. VIPL submitted that the financing charges submitted are based on
the audited accounts. The break-up of financing charges submitted by VIPL is
shown in the Table below:
Table 4.9: Breakup of financing charges submitted by VIPL
Loan Particulars
Financing
charges
(Rs. Crore)
Rupee Term Loan
Upfront fee paid to Rupee lenders in the consortium
14.16 Bank Guarantees issued in favour of
coal/customs/statutory bodies for performance
purposes. Commission paid on quarterly/upfront basis
ECB Loan Upfront fee paid 10.17
Buyer’s Credit
Commission/Bank charges/LC fee paid to domestic
lenders issuing the letter of undertaking to the foreign
bank for Buyer’s credit. Fee on sharing basis with lead
bank and domestic bank in consortium involving
multiple entities.
24.91
Arranger fee/upfront fee paid to foreign bank 0.99
Total 50.22
MERC Order in Case No 91 of 2013 Page 29
4.3 Capital Cost for determination of Tariff
4.3.1 VIPL submitted that for the purpose of provisional Tariff, it has considered the
written down value of the project as on 1 April, 2014 as Rs. 4063.05 Crore.
4.3.2 VIPL submitted that the envisaged capital cost of the project is Rs. 4132.36
Crore. VIPL submitted that Unit # 1 has achieved COD on 4 April, 2013 and
COD of Unit # 2 is envisaged by March, 2014. VIPL submitted that it would
be prudent to consider the written down value of assets for the purpose of
determination of Tariff under the PPA from 1 April, 2014.
4.3.3 VIPL submitted that it had deducted the depreciation amount of Rs. 69.31
Crore pertaining to the period from April, 2013 to March, 2014. VIPL
submitted that it would submit the corresponding depreciation amount
pursuant to COD of the project for the purpose of estimation of written down
value of the generating station during the determination of final Tariff. VIPL
submitted that the overall written down value of the power station considered
for the purpose of Tariff determination is Rs. 4063.05 Crore after deducting
the depreciation of Rs. 69.31 Crore from expected capital cost of Rs. 4132.36
Crore as on COD of the project.
4.3.4 VIPL submitted that it has considered the Debt Equity ratio of 70:30 as
envisaged at the time of COD of the station. VIPL submitted the overall loan
and equity components as on 1 April, 2014 based on the written down value of
the capital cost of the Station as shown in the Table below:
Table 4.10: Project funding based on written down value of capital cost as on
1 April, 2014 as submitted by VIPL
Source Amount
(Rs. Crore)
Rupee Loan 2006.98
ECB 602.65 ($ 128.57 million)
Normative additional loan for meeting
the written down value of the Project
as on 1 April, 2014
234.51
Total Loan 2844.14
Equity 1218.92
Total Capital Cost 4063.05
MERC Order in Case No 91 of 2013 Page 30
4.4 Commission's Views on Prudence Check of Capital Cost
4.4.1 The Commission in order to undertake prudence check of capital cost of
Butibori Power Plant asked VIPL to submit the necessary information to
establish the reasonability of expected capital cost as on COD of the project.
While VIPL has submitted most of the information, some vital information
required for prudence check of capital cost could not be submitted by VIPL
as elaborated in the following paragraphs.
4.4.2 MERC MYT Regulations, 2011 specifies as under:
“38.4 A Generating Company may make a Petition for determination of
provisional tariff in advance of the anticipated Date of Commercial Operation
of Unit or Stage or Generating Station as a whole, as the case may be, based
on the capital expenditure actually incurred up to the date of making the
Petition or a date prior to making of the Petition, duly audited and certified by
the statutory auditors and the provisional tariff shall be charged from the date
of commercial operation of such Unit or Stage or Generating Station, as the
case may be.
38.5 A Generating Company shall make a fresh Petition in accordance with
these Regulations, for determination of final tariff based on actual capital
expenditure incurred up to the date of commercial operation of the Generating
Station duly certified by the statutory auditors based on Annual Audited
Accounts.
38.6 Any difference in provisional tariff and the final tariff determined by the
Commission and not attributable to the Generating Company may be adjusted
at the time of determination of final tariff for the following year as directed by
the Commission.”
4.4.3 VIPL in its Petition submitted that Unit # 1has achieved COD on 4 April,
2013 and Unit # 2 is envisaged to achieve COD by March, 2014. VIPL
submitted that land transfer process/possession of SICOM/railway land for
completion of railway siding expected in the month of November, 2013, the
expected schedule for completion of Railway siding is by February, 2014.
VIPL submitted the detailed activity schedule for railway siding.
MERC Order in Case No 91 of 2013 Page 31
4.4.4 As Unit # 1 has already achieved COD, it would be prudent to assess the
reasonability of expected capital cost based on the audited capital cost as on
COD of Unit # 1 and projected capital expenditure up to COD of Unit # 2.
4.4.5 VIPL submitted the audited accounts for FY 2012-13 and CA certificate for
capital expenditure till 31 May, 2013. As Unit # 1 has achieved COD on 4
April, 2013, the Commission observes that the audited accounts for FY 2012-
13 depict majority of the cost under CWIP. The CA certificate submitted
depicts only the capital expenditure incurred till 31 May, 2013.
4.4.6 The Commission asked VIPL to submit the revised Form 3.1 showing the
details of audited capital cost as on COD of Unit # 1 i.e., 4 April, 2013 and
projected capital cost up to COD of the project. VIPL replied that out of the
two Units of Butibori Power Plant, only one Unit has achieved COD. VIPL
submitted that the required information would be submitted after the COD of
the project. VIPL submitted that the capital expenditure is reflected in the
auditor certified statement that has already been submitted.
4.4.7 Further, IDC of Rs. 449.54 Crore submitted by VIPL is only up to 31 May,
2013. As Unit # 2 is yet to achieve COD, the IDC for the project is subject to
change. VIPL also submitted Rs. 78.52 Crore towards realised exchange rate
variation on settlement of Buyer’s Credit. VIPL submitted that this is subject
to change as the same does not include unrealised exchange rate differences
on foreign currency loan. The Commission also asked VIPL to submit the
details of cost towards foreign exchange rate variation separately for Unit # 1
and Unit # 2. VIPL submitted that it could not submit the required information
as the financing has been arranged for the entire project and the Unit wise
allocation could not be submitted.
4.4.8 VIPL submitted the written down value of capital cost as on 1 April, 2014.
The Commission asked VIPL to submit the computation of depreciation
considered for FY 2013-14 for arriving at the written down value of capital
cost as on 1 April, 2014. VIPL submitted the computations of depreciation for
FY 2013-14. The Commission observed that for computing the depreciation of
Unit # 1 for FY 2013-14, VIPL has considered only the Hard Cost without
allocating the pre-operative expenses and IDC expenses separately for Unit #
1 and Unit # 2.
MERC Order in Case No 91 of 2013 Page 32
4.4.9 VIPL in its Petition submitted that the capital cost does not include any
unrealized exchange rate differences on foreign currency loan and liability and
the same shall be submitted to the Commission post COD of the station along
with audited accounts at the time of final determination of Tariff. VIPL
submitted that it would submit the final capital cost including IDC and other
breakup post COD of the station along with audited accounts at the time of
final determination of Tariff.
4.4.10 The Commission has taken the submissions of VIPL on record. However, the
Commission is of the view that at this stage, any attempt to approve the
Capital Cost by carrying out the prudence check based on limited information
will not serve any purpose as the some components of cost are likely to
undergo change up to COD of the Project as submitted by VIPL in its Petition.
As regards the details of audited Capital Cost as on COD of Unit # 1 and
projected Capital cost in Form 3.1, VIPL submitted that the required
information would be submitted after the COD of the project.
4.4.11 The Commission in its previous Orders on approval of Capital Cost has
carried out the detailed prudence check by analysing the reasons for variation
in Actual Capital Cost as on COD with respect to original estimated cost.
VIPL in its Petition has included the IDC only up to May 2013 as part of
Capital Cost, though the project is yet to achieve COD. Therefore, the
variation in capital cost till COD of the Project will also undergo change and it
will be more appropriate to analyse the reasons for variation in actual Capital
Cost with respect to original estimated capital cost. Further, to arrive at
Written Down Value of the Project as on April 1, 2014, another crucial aspect
is the depreciation to be considered for FY 2013-14 from COD of Unit 1 for
Unit 1 and from COD of Unit 2 for Unit 2. As discussed earlier, the
Commission also observed that for computing the depreciation of Unit # 1 for
FY 2013-14, VIPL has considered only the Hard Cost without allocating the
pre-operative expenses and IDC expenses separately for Unit # 1 and Unit # 2.
4.4.12 Hence, the Commission is of the view any approval of capital cost at this
stage will be based on limited prudence and based on certain
assumptions, which will undergo change based on actual capital cost till
COD of the Project. Hence, the Commission is not approving the capital
cost of Butibori Power Plant in this Order. The Commission shall
approve the capital cost of the project after carrying out the prudence
check of the capital cost while determining the final Tariff in accordance
MERC Order in Case No 91 of 2013 Page 33
with Regulation 38.5 of MERC MYT Regulations, 2011 based on audited
capital cost as on COD.
4.5 MEANS OF FINANCE
4.5.1 VIPL submitted that the envisaged capital expenditure of Rs. 4132.36 Crore as
on COD of the project would be financed at debt equity ratio of 70:30. VIPL
submitted that the requisite debt is funded by a consortium of banks led by
Axis Bank. VIPL submitted that additionally, during the construction period, it
has taken Buyer’s Credit for part funding of foreign equipment supply, which
has an interest rate of 3.5%. VIPL submitted that Buyer’s Credit of US $97.63
million would be converted into domestic loan post COD of the Power Plant.
VIPL submitted that it would infuse Rs. 1239.71 Crore as equity contribution
towards completion of the Butibori project.
4.5.2 VIPL submitted the details of financing arrangement as shown in the Table
below:
Table 4.11: Debt and Equity as on COD of the project as submitted by VIPL
Means of finance Amount
( Rs. Crore) %
Domestic Loan 2193.16 53.07%
ECB ( USD 150 Million) 699.49 16.93%
Equity 1239.71 30.00%
Total 4132.36 100.00%
4.5.3 The Commission observed that VIPL submitted an additional loan of Rs.
145.21 Crore in the details of financial package. The Commission asked VIPL
to submit the details regarding this additional loan. VIPL submitted that there
had been certain repayments envisaged for the actual portfolio of loans and
hence normative loans have been considered to maintain debt equity ratio of
70:30. VIPL submitted that for financing the additional loan, it had already
approached Banks and Financial Institutions. VIPL submitted the expected
terms and conditions of additional loan as shown in the Table below:
MERC Order in Case No 91 of 2013 Page 34
Table 4.12: Terms and Conditions of additional loan as submitted by VIPL
Particulars Terms and Conditions of
additional loan
Loan amount Rs. 145.21 Crore
Nature Rupee Term Loan
Source Banks and Financial Institutions
Interest Rate 13.75%
Duration 15 years
Moratorium period 1 year
Repayment 56 equal quarterly instalments
4.5.4 VIPL submitted that the financing for the project has been arranged in the
form of Rupee Term loan, ECB loan and Buyer’s Credit. The Commission
asked VIPL to submit the statement of loan disbursement and corresponding
assets purchased. VIPL submitted the statement of loan disbursement of
Rupee Term loan, ECB loan and Buyer’s Credit. VIPL submitted that the
Buyer’s Credit has been arranged for financing of specific assets and
submitted the details of the same. VIPL submitted that the balance assets have
been financed by a mix of Rupee Term loan and ECB loan. VIPL submitted
that it would not be possible to provide a statement showing date wise
disbursement of Rupee Term loan and the corresponding assets purchased.
4.5.5 The Commission also asked VIPL to submit the basis of exchange rate
considered for converting the foreign currency loan amounts to Rupees. VIPL
submitted the exchange rates considered for conversion of foreign currency
loan amounts to Rupees. VIPL has not submitted the basis of exchange rates
considered for converting the foreign currency loan amounts to Rupees.
4.6 PROVISIONAL TARIFF
ANNUAL FIXED CHARGES
4.6.1 As discussed in Section 4.4, as the Commission has not approved the Capital
Cost of the Project in this Order, the Commission has not analysed the various
components of Annual Fixed Charges in this Order. The submissions of VIPL
towards provisional Annual Fixed Charges and the approach adopted by the
Commission for approving the provisional Annual Fixed Charges is discussed
in subsequent paragraphs.
MERC Order in Case No 91 of 2013 Page 35
4.6.2 Regulation 40.1 of MERC MYT Regulations, 2011 specifies as under:
“The Annual Fixed Charges shall comprise of the FOLLOWING elements:
(a) Return on Equity Capital;
(b) Interest on Loan Capital;
(c) Depreciation;
(d) Operation & Maintenance Expenses;
(e) Interest on Working Capital;
Less:
(a) Non Tariff Income
.....”
O&M expenses
4.6.3 VIPL submitted that for the purpose of O&M expenses, it has relied upon the
normative O&M expenses as specified under Regulation 46 (a) of MERC
MYT Regulations, 2011. VIPL submitted that as per the Regulations, O&M
expenses for newly commissioned station for FY 2014-15 and FY 2015-16 are
Rs. 17.50 Lakh/MW and Rs. 18.50 Lakh/MW respectively. VIPL submitted
the O&M expenses for FY 2014-15 and FY 2015-16 as shown in the table
below:
Table 4.13: O&M Expenses for FY 2014-15 and FY 2015-16 submitted by
VIPL (Rs. Crore)
Parameter FY 2014-15 FY 2015-16
Capacity 600 600
O&M expenses norm
(Rs. Lakh/MW) 17.50 18.50
O&M expenses
(Rs. Crore) 105.00 111.00
Depreciation
4.6.4 VIPL submitted that for the purpose of depreciation, it has considered the
opening GFA as the written down value of the envisaged capital cost as on 1
April, 2014. VIPL submitted that the depreciation has been computed based
MERC Order in Case No 91 of 2013 Page 36
on the rates prescribed in MERC MYT Regulations, 2011. VIPL submitted the
depreciation for FY 2014-15 and FY 2015-16 as shown in the table below:
Table 4.14: Depreciation for FY 2014-15 and FY 2015-16 submitted by VIPL
(Rs. Crore)
Asset
Classification
Capital
Cost as on
COD of the
project
Written down
value of the
capital cost as
on 1 April, 2014
Depreciation
Rate (%)
Depreciation
FY 2014-15 FY 2015-16
Land owned under
full title 73.29 73.29 0.00% - -
Land under lease 37.79 37.79 3.34% 1.26 1.26
Building 2.06 2.06 3.34% 0.07 0.07
Cooling Towers &
CWS 114.91 112.30 5.28% 6.07 6.07
Hydraulic works - - 5.28% - -
Plant & Machinery 3378.05 3312.59 5.28% 178.36 178.36
Batteries 16.50 16.23 5.28% 0.87 0.87
Air conditioning 19.81 19.76 5.28% 1.05 1.05
Overhead Lines,
cables & networks 75.57 74.66 5.28% 3.99 3.99
Vehicles 0.17 0.17 9.50% 0.02 0.02
Furniture & fixtures 1.16 1.16 6.33% 0.07 0.07
Office equipment 1.93 1.93 6.33% 0.12 0.12
Civil works (Roads
and Railway
sidings)
411.11 411.11 3.34% 13.73 13.73
Total 4132.36 4063.05 205.61 205.61
4.6.5 The Commission observed that VIPL has arrived at the written down value of
capital cost as on 1 April, 2014 by deducting the depreciation for FY 2013-14
computed at the depreciation rates specified in MERC MYT Regulations,
2011. The Commission further observed that the VIPL has computed
depreciation only under some of the asset classes. In this regard, the
Commission asked VIPL to submit the computations of depreciation for FY
2013-14 to arrive at the written down value at the beginning of FY 2014-15.
VIPL submitted the computations of depreciation for FY 2013-14. The
Commission observed that for computing the depreciation of Unit # 1 for FY
MERC Order in Case No 91 of 2013 Page 37
2013-14, VIPL has considered only the Hard Cost without allocating the pre-
operative expenses and IDC expenses separately for Unit # 1 and Unit # 2.
Interest on loans
4.6.6 VIPL submitted that the total debt amount is raised from consortium of banks
through a mix of domestic (Rupee) loan and ECB. VIPL submitted that the
applicable interest rate post COD on domestic loan is is linked with the Axis
Bank Base Rate/Other Rupee Lenders’ base rate plus reset interest spread rate,
as applicable as per the terms of the loan agreement. VIPL submitted that the
domestic loan has repayment period of 11 years with quarterly repayment
frequency. VIPL submitted that ECB of US $ 150 Million is availed at interest
rate of 3 month LIBOR plus margin of 4.60%.
4.6.7 VIPL submitted that the project funding as on 1 April, 2014 is considered on a
normative basis as loan equal to 70 % of the written down value of capital cost
as on 1 April, 2014 and balance 30% as equity contribution for the purpose of
determination of Tariff. VIPL submitted that the rationale for the same is
based on the fact that the accounting principles always adopt a matching
concept of assets and liabilities. VIPL submitted that by considering the
written down value of capital cost as on 1 April, 2014, there has to be a
matching liability for considering the funding of these assets. VIPL submitted
that, to the extent, the value of the assets has been brought down under the
regulatory purview, the same needs to be considered to be funded in a
normative manner. VIPL submitted that since deployment of 30% equity has
already been envisaged in the project, the balance quantum has to be
considered to be funded through loan component in line with Regulation 30.1
of MERC MYT Regulations, 2011.
4.6.8 VIPL submitted that even otherwise, repayments and interest expenses being
incurred by it prior to COD of Unit # 2 will have to be met by internal accruals
or drawal of additional loans. VIPL submitted that since 30% of ceiling on
equity has already been considered as per Tariff Regulations, such additional
amount of deployment of funds needs to be considered as normative loan only.
VIPL submitted that the loan portfolio has been considered for the project as a
whole and it is not possible to segregate the loan portfolio for the two Units.
4.6.9 VIPL submitted that the Tariff Regulations permits variation between actual
loan portfolios as per books of accounts vis-a-vis the loan amount as per
MERC Order in Case No 91 of 2013 Page 38
regulatory accounts. VIPL submitted that in consideration of the aforesaid
provision in the Regulations, it has considered the matching principle and has
considered normative loans for funding the written down value of the capital
cost.
4.6.10 VIPL submitted that interest claimed as part of ARR is calculated in line with
the MERC MYT Regulations, 2011. VIPL submitted that the repayment for
FY 2014-15 and FY 2015-16 is assumed to be equal to the depreciation for the
respective years. VIPL submitted that the interest rate applied on normative
loan amount is calculated as weighted average of interest on basis of actual
loan portfolio at the beginning of the year. VIPL submitted the actual loan
portfolio as shown in the Table below:
Table 4.15: Actual Loan portfolio submitted by VIPL
Particulars Units FY 2014-15 FY 2015-16
Actual Domestic Loan
Opening domestic loan Rs. Crore 2006.98 1807.60
Repayment Rs. Crore 199.38 199.38
Closing domestic loan Rs. Crore 1807.60 1608.22
Interest rate on domestic loan % 13.75% 13.75%
Actual ECB
Opening ECB outstanding Rs. Crore 602.65 502.21
Repayment Rs. Crore 100.44 100.44
Closing ECB outstanding Rs. Crore 502.21 401.77
Interest rate on ECB % 5% 5%
Weighted average Interest Rate % 11.73% 11.85%
4.6.11 VIPL submitted the interest expenses for FY 2014-15 and FY 2015-16 as
shown in the Table below:
Table 4.16: Interest expenses for FY 2014-15 and FY 2015-16 submitted by
VIPL (Rs. Crore)
Particulars FY 2014-15 FY 2015-16
Opening Loan 2844.14 2638.53
Repayment 205.61 205.61
Closing loan 2638.53 2432.92
Weighted average interest rate 11.73% 11.85%
Interest 321.54 300.42
MERC Order in Case No 91 of 2013 Page 39
Removal of difficulty in treatment of cost of hedging foreign loans and/or
allowing the foreign exchange rate variation
4.6.12 VIPL submitted that it has taken a USD denominated loan for the project to
save on the interest costs in the long-term. VIPL submitted that the same is
exposed to exchange rate fluctuations. VIPL submitted that the benefit of
lower interest rate is transparently passed on in interest calculations in Tariff.
VIPL submitted that the hedging costs can be prohibitively high in a volatile
exchange rate scenario and is expected to be about 8% p.a. VIPL submitted
that currently Indian Rupee is going through this phase. VIPL submitted that
with active efforts by the Government to regain the reform momentum, the
economy is expected to bounce back to high growth trajectory in the medium-
term. VIPL submitted that a stronger economy with healthy foreign exchange
reserves is expected to strengthen Indian Rupee vis-à-vis US Dollars and other
hard currencies in the medium term. VIPL submitted that appreciation of
Rupee vis-à-vis USD would reduce the debt servicing obligations on its
foreign currency loans.
4.6.13 VIPL submitted that MERC MYT Regulations, 2011 do not explicitly cover
the treatment of such foreign exchange rate variations post the commissioning
of the project. VIPL submitted that currently no hedging of these foreign loans
is considered. VIPL submitted that a directive in this regard regarding whether
the actual cost can be passed through Tariff or else if such transactions are to
be hedged in future then the actual cost of hedging shall be passed through
Tariff may be issued by the Commission. VIPL submitted that Regulation 40
of CERC Tariff Regulations, 2009 allow for recognition of hedging cost and
extra Rupee liability towards foreign currency loan.
4.6.14 The Commission asked VIPL to submit the details of proposed hedging
arrangements for foreign currency loans.
4.6.15 VIPL submitted that one option could be converting the ECB loan to
equivalent Rupee loan at the time of COD of the project based on the then
prevailing exchange rate. VIPL submitted that in case exchange rate continues
to be high, the Rupee liability would be high resulting in higher repayments
and higher interest expenses in Tariff. VIPL submitted that at reasonable
exchange rate, this could be an option to evaluate.
MERC Order in Case No 91 of 2013 Page 40
4.6.16 VIPL submitted that another option could be maintaining ECB as foreign
currency loan with or without hedging. VIPL submitted that in case of no
hedging, the interest cost is low, but there could be exposure to movement in
exchange rate. VIPL submitted that if the variation in exchange rate during the
period 2002 to 2013 is considered, the impact in interest rate would be to the
extent of 3% resulting in the effective interest rate of 8% p.a. VIPL submitted
that this interest rate is lower than the interest rate of 13.75% for the Rupee
term loan. VIPL submitted the movement of exchange rate from 2002 to 2013
as shown in the Table below:
Table 4.17: Exchange rate variation submitted by VIPL
Year
Exchange rate
as on 31
March
Yearly
movement
Average exchange
rate variation
from 2002 to 2013
(Long Term)
Average
exchange rate
variation from
2008 to 2013
(Medium Term)
Average
exchange rate
variation from
2009 to 2013
(Medium Term)
2002 48.80 5%
3% 10% 6%
2003 47.51 -3%
2004 43.45 -9%
2005 43.75 1%
2006 44.61 2%
2007 43.59 -2%
2008 39.97 -8%
2009 50.95 27%
2010 45.14 -11%
2011 44.65 -1%
2012 51.16 15%
2013 65.00* 27%
*Exchange rate as on 23 August, 2013
4.6.17 VIPL submitted the indicative interest rate including hedging cost would be
12.98% for Development Bank of Singapore, 12.90% for Standard Chartered
Bank and 12.85% for Axis Bank.
4.6.18 VIPL submitted that considering the volatility in Indian currency and
considerably high cost of hedging, it would be prudent to assume continuation
of loan in USD. VIPL submitted that based on the inputs from financial
MERC Order in Case No 91 of 2013 Page 41
institutions and banks, appropriate view would be taken for converting to a
Rupee loan or to undertake hedging.
Commission’s Views on Removal of difficulty in treatment of cost of hedging
foreign loans and/or allowing the foreign exchange rate variation
4.6.19 In this regard, Regulation 27.1(a) of MERC MYT Regulations, 2011 specifies
as under:
“the expenditure incurred or projected to be incurred, including interest
during construction and financing charges, any gain or loss on account of
foreign exchange risk variation on the loan during construction up to the date
of commercial operation of the project, as admitted by the Commission, after
prudence check;”
4.6.20 As evident from the above, any gain or loss on account of foreign exchange
risk variation on the loan during construction up to COD of the project shall
be pass through in the capital cost subject to prudence check by the
Commission. In this regard, the Petitioner has considered the realised foreign
exchange rate variation of Rs. 78.52 Crore on the settlement of Buyer’s Credit
up to 31 May, 2013, based on the certified statement from the Statutory
Auditor.
4.6.21 The Petitioner had included the above FERV cost under the capital cost of the
project. In this regard, the Commission directed VIPL to segregate the FERV
cost for Unit # 1 and Unit # 2 separately. However, VIPL could not provide
the required details. VIPL, in its reply dated 4 September 2013, submitted that
the financing has been a combined financing for both the Units, and it would
not be possible to provide Unit wise break up of means of finance for the
project.
4.6.22 With regards to the status of COD of the project, VIPL in replies to datagaps
submitted that Unit # 1 has achieved COD on 4 April, 2013 and Unit # 2 is
expected to achieve COD by March 2014.
4.6.23 It may be noted here that the concerned loan agreement stipulates hedging to
cover the risk arising from foreign exchange rate variation. Clause 18.7 of the
foreign currency loan agreement expressly states as under:
MERC Order in Case No 91 of 2013 Page 42
“the borrower shall make suitable hedging arrangements through any
of the authorised entities, in accordance with the guidelines issued by
RBI from time to time, to protect the (i) rights and interest of the ECB
lender and (ii) the ECB facility for the purpose of covering the risks
associated with foreign exchange currency and LIBOR fluctuations
during the term of the ECB facility, to the satisfaction of the ECB
lender /Lenders Agent”
4.6.24 It may be noted here that there is vital difference in risk that future currency
recipient carries vis a vis risk carried by future currency payer. The future
currency receiver’s risk is limited to full value of currency at the extreme.
However the risk of future currency payer is unlimited.
In the given Case, VIPL is in position of future currency payers being
borrowers who have to repay dollars in future over fairly long period of time.
4.6.25 The petitioner had availed foreign currency loans and thus there arises the risk
of foreign exchange rate variation for repayment of loan as well as interest.
The Commission noted the submission made by the petitioner regarding the
risk arising from availing the foreign currency loans vis a vis the recent dollar
movements.
4.6.26 The risk arising from foreign exchange rate variation needs to be studied in
more detailed manner. The provisions of existing MERC MYT Regulations,
2011 do not deal with the issue. The Commission directs VIPL to study the
various options to protect the risk arising from Foreign exchange rate variation
in future period after COD and the cost of doing so along with the possible
impact of this cost on tariff and submit the same to the Commission. The
Commission shall take appropriate view on the same.
Return on Equity
4.6.27 VIPL submitted that as per Regulation 32.1.1 of MERC MYT Regulations
2011, RoE has to be computed on the equity capital determined in accordance
with Regulation 30 at the rate of 15.50% per annum in Indian Rupee terms.
VIPL submitted that additional 0.5% return may be allowed if such projects
are completed within the timelines specified in the Regulations.
MERC Order in Case No 91 of 2013 Page 43
4.6.28 VIPL submitted that as per Annexure III of MERC MYT Regulations, 2011,
timeline for first Unit of 300 MW project is 33 months with subsequent Units
at 4 months interval. VIPL submitted that this Regulation implies that the first
Unit of the green field project must be completed in 33 months and second
Unit must be completed within 37 months from the date when financial
commitments for the project are made. VIPL submitted that final Notice to
Proceed to EPC contractor for Unit # 1 was issued on 27 February, 2010.
VIPL submitted that this date signifies financial commitment. VIPL submitted
that Full Load Operation for Unit # 1 was achieved on 17 August, 2012. VIPL
submitted that Full Load Operation for Unit # 2 was achieved on 19 March,
2013. VIPL submitted that from the above dates, it is clear that the project is
within the timelines prescribed for additional 0.5% RoE on the Project and
therefore it has considered 16% return on equity.
Table 4.18 Return on Equity submitted by VIPL (Rs. Crore)
Parameter FY 2014-15 FY 2015-16
Equity as on 1 April, 2014 as per
written down value of capital cost 1218.92 1218.92
Rate of return (%) 16% 16%
Return on Equity 195.03 195.03
Income Tax
4.6.29 VIPL submitted that income tax has been computed by applying MAT rate of
20.96% on RoE for FY 2014-15 and FY 2015-16. VIPL submitted that the
total income tax payable works out to be Rs. 40.88 Crore for FY 2014-15 and
FY 2015-16. VIPL submitted that income tax has been worked out on a
notional basis since the Tariff is being worked out for the future years. VIPL
submitted that the actual income tax will be dealt as per the provisions of
MERC MYT Regulations, 2011. VIPL submitted that it would submit the
actual income tax for such years based on the audited accounts and would
subsequently seek a true-up on the same as per the current prevailing
regulatory practices.
Interest on Working Capital
4.6.30 VIPL submitted that the working capital has been calculated in line with
Regulation 35.1 of MERC MYT Regulations, 2011. VIPL submitted that the
MERC Order in Case No 91 of 2013 Page 44
short-term Prime Lending Rate of State Bank of India as on the date of filing
of the Petition has been considered for calculation of interest on working
capital. VIPL submitted the Interest on Working capital as shown in the Table
below:
Table 4.19 Interest on Working Capital submitted by VIPL (Rs. Crore)
Particulars FY 2014-15 FY 2015-16
Cost of Coal/Lignite 77.12 81.55
Cost of Secondary Fuel Oil 4.35 4.54
O&M expenses 8.75 9.25
Maintenance spares 41.32 41.32
Receivables 237.03 239.42
Less: Payable for fuel 40.74 43.04
Working Capital Requirement 327.84 333.04
Interest rate 14.45% 14.45%
Interest on Working Capital 47.37 48.12
Non Tariff Income
4.6.31 VIPL has not projected non Tariff income for FY 2014-15 and FY 2015-16.
4.6.32 The Commission asked VIPL to submit the reasons for not projecting non-
Tariff income for FY 2014-15 and FY 2015-16.
4.6.33 VIPL submitted that it has not considered any streams of non-Tariff income
post COD of the project. VIPL submitted that any such non-Tariff income
shall be submitted to the Commission in accordance with MERC MYT
Regulations, 2011.
Commission’s ruling on provisional fixed charges
4.6.34 As discussed in Section 4.4, the Commission is of the view that in the present
Case, the prudence check of the Capital Cost proposed by the Petitioner
cannot be carried out in the absence of audited Capital Cost as on CoD.
4.6.35 In similar cases for approval of provisional Fixed Charges , the Commission in
its Order dated 8 February, 2013 in Case No. 77 of 2012 has approved the
MERC Order in Case No 91 of 2013 Page 45
provisional Fixed Charges for Khaperkheda Unit # 5, Bhusawal Unit # 4 and
Bhusawal Unit # 5 for FY 2012-13, as 80% of the petitioned fixed charges by
analysing the annual fixed charges for Paras Unit 3 and Parli Unit 6 stations as
originally petitioned by MSPGCL vis a vis the annual fixed charges approved
by the Commission after prudence check of the Capital Cost.
4.6.36 In the present case, the Commission observed that Unit # 1 has already
achieved COD and Unit # 2 is likely to achieve COD by March 2014. As per
Regulation 38.4 of MERC MYT Regulations, 2011, the Generating Company
may make a Petition for determination of provisional tariff in advance of the
anticipated Date of Commercial Operation based on capital expenditure
actually incurred duly audited and certified by the statutory auditors.
4.6.37 The Commission is of the view that as the Generating Companies may submit
the Petition for determination of provisional tariff based on capital expenditure
actually incurred duly audited and certified by the statutory auditors, which
may vary from project to project, it is necessary to have a framework in place
for approving the provisional AFC in the present Case and for similar Cases in
the future. The amount of audited capital expenditure incurred and the
expected capital expenditure for the balance work to be completed to achieve
CoD of the power plant as submitted by the Petitioner will be analysed for
approval of provisional tariff. The Commission proposes the following slabs
for approving provisional Fixed Charges based on audited capital expenditure
incurred, as submitted by the Petitioner:
Table 4.20: Slabs for approving provisional Fixed Charges based on audited
capital expenditure
S.
No.
Audited Capital Expenditure as a
% (percentage) of total estimated
Project Cost till COD of the Plant
Allowable provisional Annual Fixed
Charges as % of AFC claimed by the
Petitioner
1 Upto 75% No approval of Provisional AFC
2 Above 75% and upto 80% 75% of AFC claimed by the Petitioner
3 Above 80% and upto 85% 80% of AFC claimed by the Petitioner
4 Above 85% and upto 90% 85% of AFC claimed by the Petitioner
5 Above 90% 90% of AFC claimed by the Petitioner
MERC Order in Case No 91 of 2013 Page 46
4.6.38 The Commission has analysed the amount of expenditure incurred by the
Petitioner and balance expenditure to be carried out to achieve CoD of the
Plant. The details of Capital Cost submitted by VIPL in its Petition and in
replies to datagaps are shown in the Table below:
Table 4.21: Details of Capital Cost submitted by VIPL
Particulars Capital Cost
(Rs. Crore)
% of expected Capital
Cost as on COD of the
Station
Expected Capital Cost as on COD of the
Station submitted in the Petition 4132.36 100.00%
Audited Capital Expenditure as on 31
May, 2013, excluding transmission line 3837.54 92.87%
4.6.39 Hence, in accordance with this analysis and the above framework, the
Commission approves the provisional Annual Fixed Charges for FY 2014-15
and FY 2015-16 as 90% of Annual Fixed Charges claimed by the Petitioner.
The Commission will approve the Annual Fixed Charges while determining
the final Tariff for FY 2014-15 and FY 2015-16 based on approved capital
cost as on COD based on audited accounts. Any variation between final
Annual Fixed Charges and provisional Annual Fixed Charges shall be
considered with carrying cost while approving the final Tariff for FY 2014-15
and FY 2015-16.
4.6.40 The provisional Annual Fixed Charges approved by the Commission for FY
2014-15 and FY 2015-16 is shown in the Table below:
Table 4.22: Provisional Annual Fixed Charges approved by the Commission
Particulars FY 2014-15 FY 2015-16
VIPL Approved VIPL Approved
Annual Fixed Charges (Rs.
Crore) 915.43 823.89 901.06 810.95
4.6.41 The Commission thus approves the provisional fixed charges of Rs.
823.89 Crore for FY 2014-15 and Rs. 810.95 Crore for FY 2015-16.
Provisional Energy Charges
MERC Order in Case No 91 of 2013 Page 47
Fuel Supply Agreement
VIPL’s submission
4.6.42 VIPL submitted that it envisages use of domestic coal as the primary fuel for
power generation. VIPL submitted that it has signed LoAs with WCL for
supply of 2.34 MMTPA of coal with GCV band of G9 for Butibori Power
Plant. VIPL submitted that quantum of coal required for achieving normative
PLF is around 2.29 MMTPA. VIPL submitted that it is taking all necessary
steps for expediting signing of FSAs. VIPL submitted that PPA for Unit # 2 as
approved by the Commission was submitted to WCL on 1 April, 2013. VIPL
submitted that MoP has included Unit # 2 in the list of projects for signing of
FSA. VIPL submitted that FSA for Unit # 2 is expected shortly.
4.6.43 VIPL submitted that based on the Commission’s order dated 19 July, 2013 in
Case No. 76 of 2013 for approval of PPA for Unit # 1, it has submitted letter
to MoP on 23 July, 2013 with request for recommending VIPL’s case to
Ministry of Coal (MoC) for conversion to IPP category and expeditious
signing of FSA thereafter. VIPL submitted that CEA has also been requested
to provide necessary inputs to MoP to enable it to make necessary
recommendations to MoC. VIPL submitted that WCL would sign FSA for
Unit # 1 once directions from MoC are received.
Commission's Analysis
4.6.44 The Commission observes that FSAs for the project have not been
executed. The Commission directs VIPL to expedite the process of
executing the FSAs so as to ensure the availability of linkage coal by the
date of commencement of supply under the regulated business from 1
April, 2014.
Operational parameters
VIPL’s submission
4.6.45 The operational parameters submitted by VIPL for FY 2014-15 and FY 2015-
16 are shown in the Table below:
Table 4.23: Operational parameters submitted by VIPL
MERC Order in Case No 91 of 2013 Page 48
Particulars Units FY 2014-15 FY 2015-16
No. of Days Days 365 366
Installed Capacity MW 600 600
Availability % 85% 85%
PLF % 85% 85%
Gross Generation MU 4468 4480
Auxiliary
Consumption % 9.13% 9.13%
Net Generation MU 4060 4071
Station Heat Rate kcal/kWh 2450 2450
Secondary Oil
Consumption ml/kWh 1.00 1.00
Auxiliary Consumption
4.6.46 VIPL submitted that MERC MYT Regulations, 2011 prescribes the normative
auxiliary consumption of 8.5% for conventional thermal power plant. VIPL
submitted that further to this, the MERC MYT Regulations, 2011 adequately
captures the additional auxiliary consumption of 0.5% over and above 8.5% in
case the generating stations employ induced draft cooling towers. VIPL
submitted that the MERC MYT Regulations, 2011 do not recognise the
requirement of Reverse Osmosis Plant and additional auxiliary requirement on
account of water pumping from distant location.
4.6.47 VIPL submitted that MoEF has directed all upcoming thermal power stations
to equip with zero effluent discharge system in order to optimize the water
usage. VIPL submitted that it had to install the Reverse Osmosis (RO) Plant in
compliance to this directive. VIPL submitted that the equipments of the RO
plant have its own electricity consumption with rated electricity consumption
of 440 kW. VIPL submitted that, the water source made available to it is
approximately at a distance of 20 km from the plant premises and therefore, it
is required to install additional pumping arrangement for pumping the water,
which has its own intrinsic electricity consumption with rated electricity
consumption as 326 kW. VIPL submitted that on account of the above stated
reasons, the normative auxiliary consumption will not be adequate to cater the
requirement of equipment. VIPL requested the Commission to allow
relaxation to include the additional auxiliary consumption of 0.13% over the
MERC Order in Case No 91 of 2013 Page 49
norm of 9%. VIPL submitted the auxiliary consumption details as shown in
the Table below:
Table 4.24: Auxiliary Consumption submitted by VIPL
Particulars Auxiliary
Consumption
Auxiliary Consumption for conventional
200 MW set series 8.50%
Add: Additional Auxiliary Consumption
for Induced Draft Cooling Towers 0.50%
Add: Auxiliary Consumption for Reverse
Osmosis Plant 0.073%
Add: Additional Auxiliary consumption
for additional water pumping system 0.054%
Total Auxiliary Consumption 9.13%
Station Heat Rate
4.6.48 VIPL submitted that as per Regulation 44.3 of MERC MYT Regulations,
2011, normative SHR is calculated by multiplying 1.065 with design heat rate
of the Units. VIPL submitted the guaranteed performance parameters for
Butibori Power Plant as shown in the Table below:
Table 4.25: Guaranteed Performance Parameters submitted by VIPL
Parameter Value
Turbine Heat Rate 1919.2 kcal/kWh (at 100% TMCR, Zero percent
make up, and 33 0C cooling water temperature)
Steam Generator
Efficiency
Not less than 86.2% (at 100% TMCR while firing
design coal)
4.6.49 VIPL submitted that considering the above guaranteed performance
parameters and the Regulations governing the determination of SHR in MERC
MYT Regulations, 2011, the allowable heat rate works out to 2456.67
kcal/kWh. VIPL submitted the computations of allowable SHR as shown in
the Table below:
MERC Order in Case No 91 of 2013 Page 50
Table 4.26: Allowable SHR submitted by VIPL
Parameter Value
Guaranteed Turbine Heat Rate (100%
TMCR) 1919.2 kcal/kWh
Turbine Cycle Heat Rate (including
piping losses and auxiliary steam) 1988.4 kcal/kWh
Boiler Efficiency 86.2%
Design Unit Heat Rate 2306.73 kcal/kWh
Allowable Heat rate (As per Clause 44.3
of MERC MYT Regulations, 2011)
1.065 x 2306.73 = 2456.67
kcal/kWh
4.6.50 VIPL submitted that any deviations in design parameters in actual running
conditions result in consequent increase/decrease of heat rate. VIPL submitted
that this aspect may not be adequately captured by factor of 1.065 in
calculating the allowable SHR. VIPL submitted that the following factors may
affect the performance of the Unit and increase heat rate:
i. Change in Ambient conditions (Temperature and Relative Humidity) -
VIPL submitted that though it is assumed that the design conditions would
be 33 0C and 60% RH, in practice the temperature variations are very high
especially in places like Nagpur, where the power plant is situated, where
temperatures would go up to an average of 48 0C in peak summer and is
above 35 0C for long periods of time. VIPL submitted that typically each 2
degree temperature increase in cooling water temperature leads to
deterioration in condenser back pressure by 0.01 bar resulting in heat rate
increase of 13.5-14.5 kcal/kWh.
ii. Change in Loading Factor - VIPL submitted that the design conditions
assume generation at 100% loading. VIPL submitted that due to various
factors during operation of the plant like load restrictions due to low
demand during nights, maintenance of various equipments during rainy
season and quality problems in coal, it may not be practically possible to
keep the loading factor at 100%. VIPL submitted that power plants usually
operate at a loading factor in the range of 95% after accounting for
scheduled and un-scheduled outages. VIPL submitted that with such
loading factors, the PLF would be in the range of 85-90%. VIPL submitted
that for 300 MW, for each 1% reduction of load, heat rate increases by 3.5-
MERC Order in Case No 91 of 2013 Page 51
4 kcal/kWh. VIPL submitted that for 5% of loading factor reduction, the
corresponding loss in heat rate would be 15-20 kcal/kWh.
iii. Continuous blow down - VIPL submitted that continuous blow down is
provided for achieving desired steam quality at turbine inlet. VIPL
submitted that this is generally one of the most effective operational
controls for limiting concentration of silica in main steam in the absence of
condensate Polishing Unit. VIPL submitted that operation of continuous
blow down is station specific and its quantum at any time may vary from
1-3% of main steam flow. VIPL submitted that it is generally estimated
that impact of 1% blow down on unit heat rate is around 9-10 kcal/kWh.
iv. Coal quality - VIPL submitted that the boiler is designed for particular
coal quality and the boiler efficiency is guaranteed by the supplier
accordingly. VIPL submitted that in practice, the coal quality received at
the station varies considerably. VIPL submitted that this is a widely
acknowledged fact by all coal based thermal plant operators in the country.
VIPL submitted that Competition Commission of India has looked into
this aspect based on information filed by MAHAGENCO. VIPL submitted
that to ensure proper combustion and emissions within the design limits,
the quality of coal is to be corrected by blending. VIPL submitted that in
the process, the boiler efficiency varies and affects the heat rate.
4.6.51 VIPL submitted that in view of the ground realities as highlighted above, SHR
is bound to show variation from the design SHR. VIPL submitted that in view
of the factors highlighted in the foregoing a heat rate of 2500 kcal/kWh would
be reasonable. VIPL submitted that however, to ensure a level playing field
among the sub-critical plants commissioned in the recent past, it has proposed
a relatively stringent heat rate of 2450 kcal/kWh. VIPL submitted that based
on the actual performance of the plant, SHR may be reviewed in the
subsequent Control Period beginning April, 2016.
Commission’s Analysis
4.6.52 The Commission has gone through the submissions of VIPL. The Commission
asked VIPL to submit performance guarantee test reports. VIPL submitted that
performance guarantee tests have not yet been carried out and the details of
the PG test would be submitted as soon as the test is completed.
MERC Order in Case No 91 of 2013 Page 52
4.6.53 The Commission further asked VIPL to submit the energy consumption of RO
plant and water pumping system outside the boundary limits of the Power
Plant separately. The Commission asked VIPL to submit the design
parameters for the generating Units as per the specifications in MERC MYT
Regulations, 2011. The Commission also asked VIPL to submit the supporting
documents for the guaranteed performance parameters.
4.6.54 VIPL submitted the assessed auxiliary consumption for each equipment. VIPL
submitted the design parameters of the generating Units as shown in the Table
below:
Table 4.27: Design Parameters submitted by VIPL
Parameter Value
Pressure rating at Turbine inlet 170 kg/cm2
Super Heat Temperature/Re-Heat
Temperature at Turbine inlet 538
0C/538
0C
Maximum Turbine Heat Rate as
guaranteed by the supplier 1988.4 kcal/kWh
Type of Boiler Feed Pump Motor Driven
4.6.55 VIPL submitted the relevant extract of EPC Contract depicting the guaranteed
performance parameters.
4.6.56 Regulation 44.3 of MERC MYT Regulations, 2011 specifies the methodology
of determination of Gross Station Heat Rate for new Generating Stations as
reproduced below:
“Gross Station Heat Rate – For new Generating Stations achieving COD after
the effectiveness of these Regulations
a) Coal and Lignite based thermal power Generating Stations
= 1.065 x Design Heat Rate (kcal/kWh)
Where the Design Heat Rate of a Unit means the Unit heat rate guaranteed by
the supplier at conditions of 100% MCR, zero percent make up, design coal
and design cooling water temperature/back pressure:
MERC Order in Case No 91 of 2013 Page 53
Provided that the design heat rate shall not exceed the following maximum
design Unit heat rates depending upon the pressure and temperature ratings
of the Units:
Pressure Rating
(kg/cm2) 150 170 170 247 247
SHT/RHT (0C) 535/535 537/537 537/565 537/565 565/593
Type of BFP
(Boiler Feed Pump)
Electrical
Driven
Turbine
Driven
Turbine
Driven
Turbine
Driven
Turbine
Driven
Max Turbine Cycle
Heat Rate (kcal/kWh) 1955 1950 1935 1900 1850
Min. Boiler Efficiency
Sub-Bituminous Indian
Coal 0.85 0.85 0.85 0.85 0.85
Bituminous Imported
Coal 0.89 0.89 0.89 0.89 0.89
Max Design Unit Heat
Rate (kcal/kWh)
Sub-Bituminous Indian
Coal 2300 2294 2276 2235 2176
Bituminous Imported
Coal 2197 2191 2174 2135 2079
Provided further that in case pressure and temperature parameters of a Unit
are different from above ratings, the maximum design Unit heat rate of the
nearest class shall be taken:
Provided also that where Unit heat rate has not been guaranteed but turbine
cycle heat rate and boiler efficiency are guaranteed separately by the same
supplier or different suppliers, the Unit design heat rate shall be arrived at by
using guaranteed turbine cycle heat rate and boiler efficiency:
Provided also that if one or more Units are declared under commercial
operation prior to the date of effectiveness of these Regulations, the heat rate
norms for those Units as well as Units declared under commercial operation
on or after the effectiveness of these Regulations shall be lower of the heat
rate norms arrived at by above methodology and the norms in accordance
with the Regulation 44.2 (a).
MERC Order in Case No 91 of 2013 Page 54
Provided also that in case of Lignite-fired Generating Stations (including
stations based on Circulating Fluidised Bed Combustion [CFBC] technology),
maximum design heat rates shall be increased using factor for moisture
content given in Regulation 44.2 (e) of this Regulation.
Note: In respect of Units where the boiler feed pumps are electrically
operated, the maximum design Unit heat rate shall be 40 kcal/kWh lower than
the maximum design Unit heat rate specified above with turbine driven boiler
feed pumps.
...............”
4.6.57 The Commission has computed the allowable SHR in accordance with
Regulation 44.3 of MERC MYT Regulations, 2011 as shown in the Table
below:
Table 4.28: SHR allowed by the Commission
S. No. Particulars Value
1 Pressure rating (As submitted by the
Petitioner) 170 kg/cm
2
2 SHT/RHT (As submitted by the
Petitioner) 538
0C /538
0C
3 Type of Boiler Feed Pump (As
submitted by the Petitioner) Motor driven
4 Guaranteed Turbine Cycle Heat Rate
(As submitted by the Petitioner) 1988.4 kcal/kWh
5 Guaranteed Boiler Efficiency (As
submitted by the Petitioner) 86.2%
6
Design Unit Heat Rate = Guaranteed
Turbine Cycle Heat Rate/Guaranteed
Boiler Efficiency (As submitted by the
Petitioner)
2306.73 kcal/kWh
7
Maximum Design Unit Heat Rate as per
MERC MYT Regulations, 2011( for
Motor Driven BFP)
2254 kcal/kWh*
8 Allowable Design Unit Heat Rate
(minimum of 6 and 7) 2254 kcal/kWh
9 Allowable SHR=1.065 x Design Unit
Heat Rate 2401 kcal/kWh
* Note: As per Regulation 44.3 MERC MYT Regulations 2011, in respect of
Units where the boiler feed pumps are electrically operated, the maximum
MERC Order in Case No 91 of 2013 Page 55
design Unit heat rate shall be 40 kcal/kWh lower than the maximum design
Unit heat rate of 2294 kcal/kWh specified for turbine driven boiler feed pump.
4.6.58 As regards the coal quality problem, the Commission had adequately dealt
with this issue in the Tariff Orders of other Generating Companies. The
Commission reiterates that in light of the Judgment of Hon’ble ATE dated 19
April, 2012 in Review Petition No. 9 of 2011 in Appeal No. 199 of 2010,
quality of coal is not totally beyond the control of the Generating Company
and does not qualify for relaxation of operational parameters from the norms,
in general. Further, the norms of operational parameters specified by the
Commission adequately address the effect of monsoon. The relevant extract of
the aforesaid ATE Judgement is reproduced below:
“We do not accept that the quality of coal is totally beyond the control of the
appellant. If the quality of raw coal supplied by the coal companies is poor,
the appellant has to make arrangements for washing of coal and blending with
superior quality of coal.”
4.6.59 The Commission has gone through the submissions of VIPL regarding the
variation in SHR from the design SHR. The Commission has specified the
norms of operation after giving due consideration to the design parameters of
the equipment being manufactured and the prevailing operating conditions.
Further, as submitted by the Petitioner, the performance guarantee tests are yet
to be carried out. The Commission, at this stage, in the absence of
performance guarantee tests has considered the Design SHR as per the
provisions of MERC MYT Regulations, 2011. The Commission will
further take a view in the matter based on the performance guarantee test
reports. The Commission directs VIPL to submit the performance
guarantee test reports after completion of the same.
4.6.60 The Commission observed that in the environmental clearance submitted for
Unit # 2 of Butibori Power Plant, MoEF specified natural draft cooling tower.
The Commission observed that VIPL submitted in its Petition that the power
plant is provided with induced draft cooling tower. The Commission asked
VIPL to submit if necessary approvals have been taken from MoEF for the
change in configuration of cooling tower along with documentary evidence for
the same.
MERC Order in Case No 91 of 2013 Page 56
4.6.61 VIPL submitted that from the conceptualisation of the project, it had proposed
induced draft cooling tower as the cooling technology. VIPL submitted that
the same was presented and the clearance was accorded by MoEF for Unit # 1.
VIPL submitted that on similar lines, induced draft cooling tower was
proposed for Unit # 2 and presented to Expert Advisory Committee (EAC) of
MoEF on 13 February, 2010 for obtaining environment clearance for Unit # 2.
VIPL submitted that during the meeting for the environment clearance, there
was no objection for use of induced draft cooling tower and no suggestions /
requirement were indicated by EAC for natural draft cooling tower. VIPL
submitted that in the environment clearance received from MoEF, natural draft
cooling tower was mentioned as the cooling technology. VIPL submitted that
on the receipt of the environmental clearance, it had represented to MoEF in
June, 2010 and subsequently in September, 2010 for necessary corrections in
the environmental clearance. VIPL submitted that in view of above and having
received approval of induced draft cooling tower for Unit # 1, it had
implemented induced draft cooling tower technology for Unit # 2 also. VIPL
submitted that in the regular compliance report submitted, the cooling tower
technology was also confirmed as induced draft cooling tower to MoEF. The
Commission has gone through the submissions of VIPL. The Commission
also observed that the cooling technology was specified as induced draft
cooling tower in the DPRs and the EPC Contracts submitted by VIPL.
4.6.62 The Commission has taken note of VIPL’s submission regarding the
relaxation in auxiliary consumption mainly because of RO plant which is a
new system to be installed to comply with the MoEF directions of achieving
zero effluent discharge system and additional water pumping system. The
Commission at this stage has considered the additional 0.13% auxiliary
consumption as requested by VIPL in its Petition while approving the
provisional tariff. The Commission directs VIPL to maintain monthly
auxiliary power consumption for the plant with details of auxiliary power
consumption for RO plant and additional water pumping system
separately and submit the same to the Commission. The Commission will
take a view in the matter based on analysis of actual auxiliary
consumption, so as to arrive at actual auxiliary power consumption for
RO plant and additional water pumping system, over and above the
normative auxiliary consumption.
4.6.63 The Commission has approved the operational parameters as per MERC MYT
Regulations, 2011 as shown in the Table below:
MERC Order in Case No 91 of 2013 Page 57
Table 4.29: Operational parameters approved by the Commission
Particulars Units FY 2014-15 FY 2015-16
VIPL Approved VIPL Approved
No. of days Days 365 365 366 366
Unit size MW 300 300 300 300
Installed Capacity MW 600 600 600 600
Availability % 85% 85% 85% 85%
PLF % 85% 85% 85% 85%
Gross Generation MU 4468 4468 4480 4480
Auxiliary
Consumption % 9.13% 9.13% 9.13% 9.13%
Net Generation MU 4060 4060 4071 4071
Station Heat Rate kcal/kWh 2450 2401 2450 2401
SFOC ml/kWh 1.00 1.00 1.00 1.00
Transit Loss % 0.80% 0.80% 0.80% 0.80%
Energy Charge
4.6.64 VIPL submitted the computations of Energy Charge considering 100%
domestic coal. VIPL submitted the energy charge of Rs. 1.25/kWh for FY
2014-15 and Rs. 1.32/kWh for FY 2015-16.
4.6.65 VIPL submitted that considering the inability of Coal India Ltd. to meet all the
domestic coal requirements, CCEA had taken up the proposal of finding a
solution for all linkage coal based power plants to meet their coal
requirements. VIPL submitted that in the meeting held in June, 2013, CCEA
approved the mechanism of signing FSAs for domestic coal quantity of 65%,
65%, 67% and 75% of Annual Contracted Quantity for the remaining four
years of the 12th
Five Year Plan. VIPL submitted that CCEA also approved the
import of coal to meet the balance FSA obligations to supply to the willing
thermal power plants on cost plus basis and that thermal power plants may
also import coal themselves.
4.6.66 VIPL submitted that considering the above developments, Tariff calculations
have been done under the blended coal scenario comprising linkage coal,
imported coal and e-auction coal. VIPL submitted that the following
MERC Order in Case No 91 of 2013 Page 58
assumptions have been made for working out the Energy Charge in the above
said condition:
i. VIPL submitted that out of the Annual Contracted Quantity of 2.34
MMTPA of E grade coal, it assumed that 65% would be delivered by
Coal India Ltd for FY 2014-15 and FY 2015-16.
ii. VIPL submitted that the balance requirement of coal would be met
through imports and e-auction coal in the ratio of 50:50.
iii. VIPL submitted that it has considered landed price of imported coal as
US $ 62.31/MT for Indonesian coal with GCV of 5000 kcal/kg.
iv. VIPL submitted that it had considered landed price of e-auction coal as
Rs. 3753/MT with average GCV of 4750 kcal/kg.
v. VIPL submitted that fuel price escalation factors have been considered as
per the latest annual escalation rates notified by CERC on 1 April, 2013
for bid evaluation purpose.
4.6.67 VIPL submitted the details of blending of coal as shown in the Table below:
Table 4.30: Details of blending of coal as submitted by VIPL
Fuel source Quantity (MMT) GCV (kcal/kg) Landed price (Rs./MT)
FY 2014-15 FY 2015-16 FY 2014-15 FY 2015-16 FY 2014-15 FY 2015-16
Linkage
coal 1.52 1.57 4750 4750 2017 2127
e-auction
coal 0.37 0.35 4750 4750 3997 4262
Imported
coal 0.38 0.36 5000 5000 6707 7434
4.6.68 VIPL submitted the likely Energy Charge considering the above blending of
coal as shown in the Table below:
MERC Order in Case No 91 of 2013 Page 59
Table 4.31: Likely Energy Charge with blending of coal as submitted by
VIPL
Particulars FY 2014-15 FY 2015-16
Energy Charge (Rs./kWh) 1.85 1.95
Commission’s Analysis
4.6.69 The Commission asked VIPL to submit the rationale for the prices of fuels
considered by VIPL.
4.6.70 VIPL submitted that the basic price of raw coal has been considered based on
the notified price of CIL for WCL coal of Grade G9. VIPL submitted that in
addition, freight charges have been considered from Railway Freight Rate
Circular for Class 150 material and for a distance of 151-175 km. VIPL
submitted that processing charges and S.T.C. have been considered based on
CIL price notification dated 26 February, 2011. VIPL submitted that as per the
notification dated 10 May, 2012 issued by Ministry of Coal royalty on coal is
14%. VIPL submitted that the price of Indonesian coal with GCV of 5000
kcal/kg on 2 July, 2013 was US $ 62.31. VIPL submitted that sea freight from
Indonesia is assumed to be US $ 14 on notional basis based on past trends.
VIPL submitted that exchange rate of Rs. 55.11/US $ has been considered
based on the average RBI quoted rates from 1 January, 2013 to 30 June, 2013.
VIPL submitted that the price of LDO and FO were proposed in the wake of
deregulation of oil prices by MoPNG and the notional escalation of 4%. VIPL
submitted the computations of landed prices of fuels. VIPL submitted that the
actual cost would be submitted at the time of true-up. VIPL submitted that
CERC escalation rates for bid evaluation have been considered for price
escalation of raw coal, imported coal, and transportation charges.
4.6.71 VIPL submitted that other variable charges are incidental to the continuous
operation of plant and procurement of coal through rail transport. VIPL
submitted that as the sustained coal transportation through rail has not yet
started, the incidental expenses pertaining to fuel have not been submitted at
this stage. VIPL submitted that the actual details along with documentary
evidence shall be submitted at the time of true-up.
4.6.72 The Commission observed that VIPL has considered the cost of water in FY
2014-15 and FY 2015-16. In this regard, the Commission asked VIPL to
submit the basis for the same.
MERC Order in Case No 91 of 2013 Page 60
4.6.73 VIPL submitted that it requires 44 MLD of water for the installed capacity of
600 MW. VIPL submitted that it has signed agreement for water supply with
MIDC and Irrigation Department, Government of Maharashtra. VIPL
submitted that 22 MLD of water would be supplied by Irrigation Department
at the rate of Rs. 51 per 10000 litres as per Clause 11 of Water Supply
Agreement signed with Irrigation Department. VIPL submitted that remaining
22 MLD of water would be supplied by MIDC. VIPL submitted that out of
this 22 MLD of water supplied by MIDC, 15 MLD of water would be supplied
at the rate of Rs. 125 per 10000 litres and 7 MLD of water would be supplied
at the rate of Rs. 185 per 10000 litres as per Clause 8 of MIDC letter dated 4
May, 2012. VIPL submitted the copies of Water Supply Agreements with
MIDC and Irrigation Department, Government of Maharashtra. VIPL
submitted that as per the provisions of the Agreements, the water charges are
subject to escalation. VIPL submitted that the escalation rates have not been
specified in the Water Supply Agreements. VIPL submitted that for projection
of water charges, it has considered the escalation rate of 5.85% applicable for
escalation of capacity charges as notified by CERC.
4.6.74 The Commission observes that the LoAs issued to VIPL assure supply of 2.34
MMT of coal per annum against requirement of approximately 2.30 MMT of
coal per annum at PLF of 85%. The Cabinet Committee on Economic Affairs
(CCEA) vide its notification dated 21 June, 2013 approved the mechanism of
supply of coal to power producers. In the said mechanism, CCEA formulated
that FSAs to be signed for domestic coal quantity of 65%, 65%, 67%, and
75% of Annual Contracted Quantity for the remaining four years of 12th
five
year plan.
4.6.75 The Commission has taken note of VIPL’s submission. The Commission
observes that the FSAs for the project are yet to be executed. The
Commission, at this stage, has computed the Energy Charge for VIPL
considering 100% domestic coal for FY 2014-15 and FY 2015-16 as
submitted by the Petitioner in its Petition. The Commission directs VIPL
to submit the FSAs executed for the project along with its Petition for
determination of final Tariff.
4.6.76 The Commission has considered the calorific value of fuels as submitted
by VIPL. The Commission has considered the landed fuel prices of fuels
as submitted by VIPL for FY 2014-15. The Commission has not
MERC Order in Case No 91 of 2013 Page 61
considered the escalation on fuel prices for projecting the fuel prices for
FY 2015-16 as any variation in actual fuel prices shall get adjusted in the
Fuel Cost Adjustment mechanism. Further, the Commission has
provisionally considered the other variable charges as submitted by
VIPL.
4.6.77 The Energy Charge approved by the Commission is shown in the Table
below:
Table 4.32: Energy Charges computed by the Commission
Particulars
FY 2014-15 FY 2015-16
VIPL Approved VIPL Approved
Calorific Value
Raw coal (kcal/kg) 4750 4750 4750 4750
FO (kcal/L) 10400 10400 10400 10400
LDO (kcal/L) 10700 10700 10700 10700
Landed Fuel Price
Raw coal (Rs./MT) 2017 2017 2127 2017
FO (Rs./kL) 52994 52994 55114 52994
LDO (Rs./kL) 71058 71058 73900 71058
Energy Charge considering
100% domestic coal
(Rs./kWh)
1.25 1.23 1.32 1.23
4.6.78 The Commission thus, approves the provisional Energy Charge of Rs.
1.23/kWh for FY 2014-15 and FY 2015-16 based on 100% domestic coal.
4.6.79 Any variation in Price and Gross Calorific Value of coal vis-a-vis
approved values for computing the provisional Energy Charge shall be
recoverable through Adjustment of rate of energy charge (REC) (Fuel
Surcharge Adjustment) in accordance with the provisions of Regulation
49.6 of MERC MYT Regulations, 2011.
Summary of the findings
MERC Order in Case No 91 of 2013 Page 62
i) As regards the approval of capital cost the Commission is of the view
that any approval of capital cost at this stage will be based on limited
prudence and based on certain assumptions, which will undergo change
based on actual capital cost till COD of the Project. Hence, the
Commission is not approving the capital cost of Butibori Power Plant in
this Order. The Commission shall approve the capital cost of the project
after carrying out the prudence check of the capital cost while
determining the final Tariff in accordance with Regulation 38.5 of MERC
MYT Regulations, 2011 based on audited capital cost as on COD.
ii) As regards the prayer of the petitioner for the request for relaxation of
norms and/or remove of difficulty in respect of treatment of cost for
hedging foreign currency loans and/or treatment of foreign exchange rate
variation on foreign currency loans, the Commission directs VIPL to
study the various options to protect the risk arising from Foreign
exchange rate variation in future period after COD and the cost of doing
so along with the possible impact of this cost on tariff and submit the
same to the Commission. The Commission shall take appropriate view on
the same..
iii) In accordance with the analysis and the framework specified, the
Commission approves the provisional Annual Fixed Charges for FY 2014-
15 and FY 2015-16 as 90% of Annual Fixed Charges claimed by the
Petitioner. The Commission will approve the Annual Fixed Charges while
determining the final Tariff for FY 2014-15 and FY 2015-16 based on
approved capital cost as on COD based on audited accounts. Any
variation between final Annual Fixed Charges and provisional Annual
Fixed Charges shall be considered with carrying cost while approving the
final Tariff for FY 2014-15 and FY 2015-16.
iv) The Commission thus approves the provisional fixed charges of Rs. 823.89
Crore for FY 2014-15 and Rs. 810.95 Crore for FY 2015-16.
v) The Commission observes that FSAs for the project have not been
executed. The Commission directs VIPL to expedite the process of
executing the FSAs so as to ensure the availability of linkage coal by the
MERC Order in Case No 91 of 2013 Page 63
date of commencement of supply under the regulated business from 1
April, 2014.
vi) The Commission, at this stage, in the absence of performance guarantee
tests has considered the Design SHR as per the provisions of MERC MYT
Regulations, 2011. The Commission will further take a view in the matter
based on the performance guarantee test reports. The Commission directs
VIPL to submit the performance guarantee test reports after completion
of the same.
vii) The Commission has taken note of VIPL’s submission regarding the
relaxation in auxiliary consumption mainly because of RO plant which is
a new system to be installed to comply with the MoEF directions of
achieving zero effluent discharge system and additional water pumping
system. The Commission at this stage has considered the additional
0.13% auxiliary consumption as requested by VIPL in its Petition while
approving the provisional tariff. The Commission directs VIPL to
maintain monthly auxiliary power consumption for the plant with details
of auxiliary power consumption for RO plant and additional water
pumping system separately and submit the same to the Commission. The
Commission will take a view in the matter based on analysis of actual
auxiliary consumption, so as to arrive at actual auxiliary consumption for
RO plant and additional water pumping system, over and above the
normative auxiliary consumption.
viii) The Commission observes that the FSAs for the project are yet to be
executed. The Commission, at this stage, has computed the Energy
Charge for VIPL considering 100% domestic coal for FY 2014-15 and
FY 2015-16 as submitted by the Petitioner in its Petition. The
Commission directs VIPL to submit the FSAs executed for the project
along with its Petition for determination of final Tariff.
ix) The Commission has considered the calorific value of fuels as submitted
by VIPL. The Commission has considered the landed fuel prices of fuels
as submitted by VIPL for FY 2014-15. The Commission has not
considered the escalation in fuel prices for projecting the fuel prices for
FY 2015-16, as any variation in actual fuel prices shall get adjusted in
the fuel cost adjustment mechanism.
MERC Order in Case No 91 of 2013 Page 64
x) The Commission thus, approves the provisional Energy Charge of Rs.
1.23/kWh for FY 2014-15 and FY 2015-16 based on 100% domestic coal.
xi) Any variation in Price and Gross Calorific Value of coal vis-a-vis
approved values for computing the provisional Energy Charge shall be
recoverable through Adjustment of rate of energy charge (REC) (Fuel
Surcharge Adjustment) in accordance with the provisions of Regulation
49.6 of MERC MYT Regulations, 2011.
With this Order, the Commission disposes off VIPL’s Petition in Case No. 91 of
2013.
Sd/- Sd/-
(Chandra Iyengar)
Member
(Vijay L. Sonavane)
Member
MERC Order in Case No 91 of 2013 Page 65
Appendix-1
List of Persons who attended the Technical Validation Session in Case No. 91 of
2013 held on 20 August, 2013
S. No. Name of the participant Organization
1 Shri. Mahesh Ghagan VIPL
2 Shri. L.C. Bhat RInfra
3 Shri. Vikas Nikumbh MAY & Co.
4 Shri. Shrikant Nene RPower
5 Shri. G. Ramchandra VIPL
6 Shri. Shrikant D. Kulkarni RPower
7 Shri. R. R. Mehta RInfra
8 Shri. K. R. Patil RInfra
9 Shri. Parag Deshmukh VIPL
10 Shri. Prashant RPower
11 Shri. Kapil Sharma R Infra
12 Shri. Shreyas M Deloitte
13 Shri. Rohit Khowale RPower
14 Shri. Madhav Tekawade VIPL
15 Shri. Vinay Patel Deloitte
16 Shri. Suresh Gehani ABPS Infra
17 Shri. Sanjiv Kumar Singh ABPS Infra
18 Shri. Namala K. M. Choudhary ABPS Infra
19 Shri. Krishna Chaitanye S RPower
20 Shri. Upkar Chaurasia VIPL
MERC Order in Case No 91 of 2013 Page 66
Appendix-2
List of Persons who attended the Public Hearing in Case No. 91 of 2013 held on
17 October, 2013
S. No. Name of the participant Organization
1 Shri. Ramandeep Singh Consultant VIPL
2 Shri. Shrikant Kulkarni VIPL
3 Shri. S. M. Nene VIPL
4 Shri. S. P. Jathar VIPL
5 Shri. Himanshu Mishra R Infra
6 Shri. Mahesh Ghagon VIPL
7 Shri. G. Ramchandran VIPL
8 Shri. Anupam Patra R Infra
9 Shri. Upkar Chaurasia VIPL
10 Shri. Madhav Tekawade VIPL
11 Shri. Vijay Chaudhary VIPL
12 Shri. Nihal Mehendale Reliance Power
13 Shri. Paresh Rathod Reliance Power
14 Shri. N. Ramakrishnan Wardha Power
15 Shri. Vinay Patel Consultant VIPL
16 Shri. P. S. Pandy RInfra
17 Shri. Vikas Nikumbh MAY & Co.
18 Shri. Kishor Patil R Infra
19 Shri. Vivek Mishra R Infra
20 Shri. R. R. Mehta R Infra
21 Shri. Kapil Sharma R Infra
22 Shri. Suresh Gehani ABPS Infra
23 Shri. Parag Deshmukh VIPL
24 Ms. Shital Khiraiya Tata Power
25 Shri. Karthik Tata Power
26 Shri. Rohit khowale VIPL