merc generation tariff order analysis
TRANSCRIPT
-
8/3/2019 MERC Generation Tariff Order Analysis
1/24
Group Project
Salient features of selected MERC tariff ordersand disposal of petitions of the MSPGCL (Genco)
Faculty GuideProf. Sebastian Morris
In partial fulfillment of the courseInfrastructure Development and Financing
Submitted by Section B, Group 3
Group members:
Anandh Sundar TripuriAniket KhasgiwaleBadrinath Srinivasan
Manish KumarMiheer Desai
Rahul Venkatraj
-
8/3/2019 MERC Generation Tariff Order Analysis
2/24
Table of Contents
Introduction .................................................................................................................................................. 3
Objectives and methodology used ............................................................................................................... 4
Overview of Applicable Policies/Laws/Regulations ...................................................................................... 5
About MSPGCL .............................................................................................................................................. 7
Summary of Tariff Orders ............................................................................................................................. 8
Non Routine Orders ...................................................................................................................................... 9
Individual Tariff Order Highlights ................................................................................................................ 10
AREAS OF DISPUTE ...................................................................................................................................... 13
Window dressing / Behavioral orders ........................................................................................................ 15
Performance Parameters ............................................................................................................................ 17
Unique Hydel Power Policy ......................................................................................................................... 18
General MERC Order Analysis- Quality and Consistency ............................................................................ 19
Is MERC playing the game well? ................................................................................................................. 21
Overall Observations ................................................................................................................................... 22
-
8/3/2019 MERC Generation Tariff Order Analysis
3/24
Introduction
The objective of the assignment is to bring out the salient features of the tariff orders /disposal of petitions
of the MSPGCL (Genco). Power sector tariff regulations are manifold. The Central laws/regulations viz.Electricity Act 2003, Electricity Policy, Tariff Policy; are applied for interstate projects, and are used as
guiding principles for designing state policies. The Forum of Regulators ensures some uniformity at the
state level in terms of tariff setting etc.
This project analyzes the key issues as:
(1) Variations over various tariff orders implicit change in principle or in key assumptions in theorder of the MERC.
(2) Variations between ARR and orders/directions resulting in petitions and the variations in the waythe petitions were dealt with.
(3) How far were the directions adhered to and what measures were used to improve adherence?(4) The quality of the response of the MERC to the ARR/ Petitions.
The project aims at seeing only the MSPGCL tariff orders over a defined time period.
-
8/3/2019 MERC Generation Tariff Order Analysis
4/24
Objectives and methodology used
After the exploratory analysis about MERC tariff philosophy and approach to petition handling, this
studys objectives was to diagnose whether:
(1) The process could have been faster.(2) Are they true to the spirit of the provisions of the EA 2003?(3) What was the nature of the due diligence with regard to the ARRs /disposal of petitions and were
they adequate given the law?
(4) What are the regulatory risks imposed by the MERC? Could these have been avoided by upfrontlaying down the principles etc? (look at the general regulations, the format for submitting the
ARR, the explanations etc)
(5) Could the disputes and petitions have been avoided /reduced?(6) What improvements are therefore possible?
For this, the methodology used was
1. The tariff orders were downloaded from the MERC site.2. A checklist of points to be analyzed was prepared. This included points like prudence check on
costs, timelines, appeals, dispute resolution techniques, regulatory risks, crosscheck of regulatory
accounts with statutory accounts etc.
3. The tariff orders were then evaluated using this checklist.4. Brainstorm about improving the process, and learn from the central best practices/best practices
of other states.
5. The checklist and draft report was then discussed with Prof Morris.
-
8/3/2019 MERC Generation Tariff Order Analysis
5/24
Overview of Applicable Policies/Laws/Regulations
TitleDeals with Scope/Applies to
Section 61 & 62 of the Electricity
Act, 2003
General unbundling of the
electricity principles
Central projects/interstate lines
but is a model for state laws
Maharashtra Electricity
Regulatory Commission (Terms
& Conditions of Tariff)
Regulations, 2005
Determining tariffs for the period
2006-2011(originally 2009 but
was extended due to data issues
etc)
Maharashtra power utilities.
Principles follow the CERC
norms/EA Act 2003 except for
cross subsidy etc
National Tariff Policy/CERC
Tariff Regulations
Principles and Guidelines for
setting tariffs centrally
Central projects/interstate lines
but is a model for state laws, and
forum of regulations adopt this.
Section 7 of the Electricity Act 2003 permits any generating company to feely establish, operate and
maintain a generating station without obtaining a license under that Act, if it otherwise complies with the
technical standards relating to connectivity with the electricity grid. For hydel projects, certain
additional approvals exist to ensure optimum riverine utilization and non conflict with other public
purposes like irrigation, flood control, navigation etc. Section 61 of the Electricity Act 2003 lays down
tariff setting principles, which are adhered to as follows.
Principle Meaning/ Example as applied to generation units
the principles and methodologies
specified by the Central Commission for
determination of the tariff applicable to
generating companies and transmission
licensees
The cost accounting norms, efficiency principles and
tariff philosophies of CERC should be adhered to at
State level where possible. It will promote
transparency, consistency and predictability in
regulatory approaches across jurisdictions and
minimize perceptions of regulatory risks
the generation, transmission, distribution
and supply of electricity are conducted on
commercial principles
This would mean arms length transactions between
the unbundled arms of erstwhile integrated utilities
the factors which would encourage
competition, efficiency, economical use
of the resources, good performance and
optimum investments
Open access, increasing normative standards yearly,
permitting efficient standard costs (normative costs)
only, setting quality of service linked bonus, and
approving capex.
-
8/3/2019 MERC Generation Tariff Order Analysis
6/24
Principle Meaning/ Example as applied to generation units
safeguarding of consumers' interest and at
the same time, recovery of the cost of
electricity in a reasonable manner
Allowing cross subsidy for limited purpose of
universal service obligation, till the time the
appropriate state directly pays subsidy. Also,
uncontrollable costs should be recovered speedily to
ensure that future consumers are not burdened with
past costs. Address the risk sharing mechanism
between Utilities and consumers based on
controllable and uncontrollable factors.
the principles rewarding efficiency in
performance
Enhanced ROE for better PLF, sharing of efficiency
gains. Operating parameters in tariffs should
be at normative levels only and not at lower of
normative and actuals
multiyear tariff principles Approve business plans for 5years at a go, with
minor annual revisions reflecting changed
costs/projections, but rarely changed capex. Control
period length however, depends on data uncertainties
and other practical considerations
that the tariff progressively reflects the
cost of supply of electricity and also,
reduces cross-subsidies in the manner
specified by the Appropriate Commission
Reducing customer categories(since this leads to
cross subsidy), among other things
the promotion of co-generation and
generation of electricity from renewable
sources of energy
Mandating higher generation feed in tariffs, and
compulsory off take contracts with distribution
licensee, for renewable energy
The National Electricity Policy and
tariff policy
National Tariff Policy should be used as the base,
with appropriate state level modifications
-
8/3/2019 MERC Generation Tariff Order Analysis
7/24
About MSPGCL
The Maharashtra State Power Generation Company Limited (MSPGCL or MahaGENCO) is a Company
is a company incorporated under the Companies Act, 1956 on 6th June, 2005, formed under the
Government of Maharashtra General Resolution No. ELA-1003/P.K.8588/Bhag-2/Urja-5 Dated January
24, 2005. This resolution gave effect to the reorganization of Maharashtra State Electricity Board in terms
of the Maharashtra Electricity Reforms Transfer Scheme 2004. As per this Order, the Maharashtra State
Electricity Board (MSEB) has been restructured into four entities MSPGCL, MSETCL, MSEDCL and
MSEB Holding Company. The State Government as a part of this transfer scheme had allocated the
generating stations of MSEB to MSPGCL. MSPGCL also maintains & operates the hydro plants owned
by the Irrigation Department, Government of Maharashtra as a lessee. The State Government had
allocated the generating stations of MSEB to MSPGCL. MSPGCL supplies electricity in bulk to
MSEDCL, hence the role of the MERC to determine tariffs for MERC generating stations.
It is said that the sins of the parent are borne by the children. In the case of MSPGCL, it was saddled with
legacy old plants, under spending on O&M/capex in previous years and consequential inability to meet
the normative standards. When MERC prodded MSPGCL to become more efficient by setting policy
parameters close to normative levels, MSPGCL approached the Appellate Tribunal for Electricity to
appeal against MERCs order, and was partly successful, including on substantive issues like fixing the
levels(realistic versus normative). This had lead to some tension between MERC and MSPGCL as borne
out by its critique of MSPGCL accounting, capex gold plating and faulty planning, but overall there is
now a healthier relationship.
-
8/3/2019 MERC Generation Tariff Order Analysis
8/24
Summary of Tariff Orders
Case
Number
ARR
Period
Tariff
Period
Subject Matter/Highlights Principle(s)/Remarks
Case No.
48 of
2005
FY 2005-
06
FY 2006-
07
FY 2006-
07
First ever tariff order for
unbundled entity. Hence
focus more on
accounting/segregation
issues
Efficient and reasonable estimates
for technical parameters and costs
to arrive at tariff. Peaking power
pricing for hydel power adopted.
Appeal to MERC disposed of in
Case 34 of 2006.
Case No.
68 of2006
FY 2007-
08FY 2008-
09
FY 2009-
10
FY 2007-
08-extended
till May
31,2008
first Control Period for MYT
framework shall bethe three financial years from
April 1, 2007 to March 31,
2010
Mahagenco C won an appeal at the
ATE, and MERC had to revise thetariff in Order 71 of 2007
Case No
71 of
2007
second
year of
the first
ControlPeriod
June
1,2008 till
mar 31
2009
Mostly giving effect to the
ATE order for setting tariffs
N/A
Case 16
of 2008
Truing up
FY 2005-
06, FY
2006-07
and FY
2007-08
ATE/CPR
N/A MSPGCL to recover the
approved amount of Rs.
762.77 Crore in 12 equal
monthly installments from
MSEDCL, in order to avoid
any tariff shock to the
consumers.
This order was to give effect to the
ATE judgments and the CPRI
norms. The only new principles
introduced there were the
identification of non tariff income
to reduce ARR requirements.
Case 115
of 2008
Last year
of control
period
FY 2009-
10
Much lesser areas of disputes
here, as ATE rulings/CPRI
norms had resolved many
issues
N/A
-
8/3/2019 MERC Generation Tariff Order Analysis
9/24
26/ 95 of
2008
First 2
years of
new Paras
Thermal
station
FY 2008-
09
Unit No. 3 of Paras Thermal
Power Station
Appealed to ATE, and revised in
2011. MERC revised its orders
vide Orders 74/75 of 2011.
102 of
2009
Truing up
for FY
2008-09,
Annual
Performa
nce
Review
for FY
2009-10
FY 2010-
11
Much lesser areas of disputes
here, as ATE rulings/CPRI
norms had resolved many
issues
N/A
Non Routine Orders
FIRST TIME PLANT TARIFF
The Tariff orders for the Parli Unit were for new plants, which had the special characteristics of
unstable control period, need for incremental capex principle and fresh start. Both the projects
experienced cost overruns, which the MERC disallowed blaming them on the Mahagenco induced delays.
This, naturally, is now under appeal to the ATE.
HYDEL LEASE RENTAL ORDER
Order from first principles-ROE based Pass through for MSPGCL so very little opposition from the
utility per se. Only others opposed it/submitted pleas. Another interesting order is on hydel lease rent
needs some background to appreciate. As per Maharashtra law, the dams and hydel power plants are
constructed by (and belong to) the Irrigation Dept. Many of these projects are ECB funded by World
Bank and others. The Govt. (not unreasonably) wanted to charge the unbundled Mahagenco a fair lease
rent to recover the interest & ROE on its dams. Now, the tariff fixation powers for this are not on any
electricity regulator as this subject is missing in the Electricity Act 2003. But if the Govt. had arbitrarily
fixed a higher amount (100% pass through to customers), this may have been challenged. Hence, Govt.
requested MERC to calculate the amount on its behalf, in its administrative capacity. So MERC
considered various methods like DCF but finally decided on a ROE model. This order is an excellent
example of practicalities in financial management of power sector.
http://www.mercindia.org.in/pdf/Ord_2008_10_27_CNo_17_of_2007.pdfhttp://www.mercindia.org.in/pdf/Ord_2008_10_27_CNo_17_of_2007.pdf -
8/3/2019 MERC Generation Tariff Order Analysis
10/24
Individual Tariff Orders Highlights
1. Case No. 48 of 2005a. As envisaged in the tariff policies, two part station-wise generation tariffs.b.
Unique hydel tariff policy envisaged, to ensure economic signals without burdeningconsumers unduly. This was done through differential energy tariff for peak and non-
peak hours, and is elaborated later on. Has been specified, where peak is 20% higher
than non peak.
c. One-time R&M expenses permitted during future truing up(over and above the approvedamount) to compensate inadequate spending in the past
d. While income tax expense in petition was sought at 33% on ROE(assuming that it wouldpay maximum marginal rate on its ROE), the allowed expense was capped at the MAT
amount of 10%(prevailing then)
e. Norms for new stations as per MERC Tariff Regulations have been applied for existingstations as well. This was the most controversial part of ruling, and successfully appealed
by MSPGCL before the ATE.
f. While O&M costs taken on normative basis, interest allowed only on actual, that too onlyon the approved borrowings.
g. While rejecting MSPGCLs plea for lower normative PLFs, the MERC said that ageingof units and non-availability of time for Planned Outages cannot be considered as
reasonable causes for high SHR or low PLF, and MSPGCL should explore all avenues
for improvement in its plant operations, routine maintenance, and capital maintenance to
enhance reliability and efficiency of their thermal generating units. Again, the ATE partly
reversed this logic.
h. The Commission has calculated the variable cost of fuel for FY 2006-07 based on theactual cost of fuel in the month of March 2006, agreeing to adjust changes via vetting of
FAC claims. This is analogous to LIFO system of accounting!
i. MSPGCL had been importing coal without a proper cost benefit analysis, and so MERCdirected MSPGCL to install and maintain the required meters with in next three months
for measurement of Coal GCV and then carry out the cost benefit analysis of the usage of
imported coal at its generating stations
j. Most of the generating units had no weightometers and hence an accurate measurementof coal is not being done. The Commission has therefore not accepted the MSPGCLs
projections and approved transit loss as per MERC Tariff Regulations only
-
8/3/2019 MERC Generation Tariff Order Analysis
11/24
k. A systematic measurement of Gross calorific value of coal by taking periodic samples ofcoal being fired shall be institutionalized at all the stations
l. MSPGCL has not provided any supporting information regarding the details of R&Mexpenses actually incurred during FY 2005-06 and resultant technical efficiency
improvements, hence was told to get its R&M plans approved at the earliest.
m. In absence of historical actuals for MSPGCL, Commission is not projecting non-tariffincome. This was however determined in later orders.
n. R&M expenses are to be determined at an average of actuals as a percentage of GFA forthe preceding five (5) years. This is a standard practice by MERC
2. Case 68 of 2006a. Much more systematic order, largely following the earlier ordersb. Conscious of the fact that the unbundling of the erstwhile MSEB should result in overall
increase in expenditure on O&M.
c. Despite not meeting the desired PLF norms for FY 2006-07-which could have led tolesser recovery for future years- MERC approved the full recovery of fixed charges
during FY 2007-08 for all thermal stations. However, in the event ofactual availability
for the year, computed in accordance with the Commissions Tariff Regulations
(after accounting for the unavailability of fuel), being less than 80%, the fixed
charges would be proportionately adjusted as per MERC Tariff Regulations, while truing
up the revenue requirement in the next year.
d. The funding of the schemes has been considered at debt: equity of 80:20 as proposed byMSPGCL in view of shortage of equity capital despite Tariff Regulations providing for
normative debt: equity of 70:30.
e. For approving the O&M expenses for the Control Period, the Commission hasconsidered the O&M expenses approved in FY 2006-07 as the base expenses. As MSEB
under spent due to earlier cash crunch, the method of extrapolation could not have been
used to calculate O&M costs.
3. Case 71 of 2007a. Commission rejects MSPGCLs request for providing incentive for Uran gas thermal
station on the basis of reduced availability and PLF, due to shortage of gas. The
Commission is of the view that though full fixed cost recovery has been permitted to
Uran gas station, despite non achievement of normative availability of 80%, it would not
be fair to the consumers to provide incentive at such low PLF levels
-
8/3/2019 MERC Generation Tariff Order Analysis
12/24
b. Though MSPGCL has been putting its efforts and expertise to optimize the performanceof scarce hydro resources, MSPGCL is not earning any commensurate returns/incentives
over and above the actual cost incurred for such operations. MSPGCL, in its Petition,
therefore, proposed a recovery of supervision charges to the extent of 15% of the
Operations and Maintenance expenses incurred during the year for such hydro power
plants. This was shot down because lease rent payable to GoM already had RoE
component, also no provision in the MERC Tariff Regulations under which such
expenses may be allowed.
-
8/3/2019 MERC Generation Tariff Order Analysis
13/24
AREAS OF DISPUTE
Cost Item MSGPCL Stand MERC Stand Present Status
Advance Against
Depreciation
in respect of some
generating stations.
intended to meet shortfall
in meeting loan repayment
obligations of the
Generating
Company. Hence to be
calculated station wise.
While tariff is
determined on a station-
wise basis, AAD is a
special provision, which
enables the Utility
to meet its loan
repayment obligations as
a whole rather than for
each Station(Order 115
of 2008)
ATE decides to have
this done station wise.
Judgment dated
27.4.2011 in
appeal no. 191 of 2009
Disallowance in
Project Cost
Delay in commissioning of
Unit No. 3 of Paras
Thermal Power Station
was not considered, and
cost was disallowed.
The delay was due to
Mahagenco so
additional cost due to
delay is to be disallowed
ATE partly agreed
with MERC
Operation &
Maintenance cost
that such an increase in R
& M expenses may not fit
into the ideology of
setting normative O&M
expenses since the hydel
assets are old and may
require more
repairs and maintenance in
future.
norms for new stations
as per MERC Tariff
Regulations have been
considered for existing
stations also
Agreed with MERC
Appeal No. 86 & 87 of
2007 .given that
=expenditure for OLD
HYDEL stations not
covered under policy
Remaining pending
Fuel Costs provisions in the National
Tariff Policy (NTP), which
states that in case the
actual performance is
much less than the
norms, then ARR should
Not till actual
parameters determined.
truing up of actual fuel
expenses
till such time the re-
assessed improvement
trajectory of
parameters is
-
8/3/2019 MERC Generation Tariff Order Analysis
14/24
be determined based on
relaxed levels.
available
Tariff for Small Hydel
Stations
entitlement of higher tariff
for small hydro projects as
the Commissions
Order
only in the case of new
projects
Agreed with MERC
Appeal No. 86 & 87 of
2007
determination of hydel
peak and off peak
generation and tariff
taking into consideration
the operational
capacity of MSPGCL and
system pattern
economic signal about
pricing of hydel
generation
Endorsed MERC
approach BUT tailored
it to Mahagencos
needs
Appeal No. 86 & 87 of
2007
Transit Loss/Auxiliary
parameters
reset the operating
parameters
Normative align its Regulations
by prescribing
achievable norms and
not merely ideal
norms. engage an
appropriate
agency(ies) assess and
suggest improvements
non-tariff income should not be considered
as part of the revenue
Include for determining
the revenue gap/surplus
ATE partly agreed
with MERC Appeal
Nos. 86 & 87 of 2007
Capex approvals Accept non DPR schemes
after prudence check
Mahagenco to bundle
non DPR into DPR else
suffer 50% cut till the
prudence check done
ATE agreed with
Mahagenco. Order 199
of 2010 dated 4 Aug
2011.
-
8/3/2019 MERC Generation Tariff Order Analysis
15/24
Window dressing / Behavioral orders
Regulated utilities will try to game the system/cook the books, while the regulator would want to structure
the incentives to avoid gaming of the system. Some Examples of MERC efforts in this line are
Order Example(s/Observation Action
68 of 2006 The increase in quantum of Non-
DPR schemes is a worrying trend,
as the Commission observes a
tendency to split capex schemes so
that capital outlay of the scheme is
below Rs. 10 Crore, to escape
regulatory scrutiny.
The Commission will take a review of the
schemes being classified under Non-DPR
category, and in case it is found that these
schemes should have ideally been classified
under DPR category, then that capex and the
related capital charges will be disallowed till
the DPR is submitted and the scheme is
approved by the Commission. In Case 115
of 2008, For Non-DPR schemes, the
Commission has considered 50% of the
proposed stabilization15 by MSPGCL on ad
hoc basis, as the Commission is of the view
that until it is ascertained that the projected
benefits have actually accrued for the benefit
of the consumers, it would not be appropriate
to allow the entire expenses.
68 of 2006 Seeing lackadaisical approach in
fixed asset accounting/submitting
capex schemes, MERC had to
caution Mahagenco
The Commission would like to reiterate that
in-principle approval of the scheme does not
absolve the senior management of MSPGCL
of their responsibility to prioritize various
schemes and undertake cost benefit analysis
and financial analysis to validate the
commercial prudence of each scheme.
MSPGCL should ensure that the projected
benefits actually accrue for the benefit of the
stakeholders. It would be essential to monitor
progress of each scheme as well as track
-
8/3/2019 MERC Generation Tariff Order Analysis
16/24
expenditure and benefits accrued as per the
scheme.
68 of 2006 practice of treating Renovation and
Modernization as revenue
expenditure is not
limited to any one department or
any one generating station of
MSPGCL, but is spread
across all departments and all
stations
The Commission has not considered the
truing up of R&M expenses for FY 2006-07
at this stage. In order to have a clear picture
regarding Repairs and maintenance
expenditure, MSPGCL should maintain a
clear demarcation of capital expenditure and
revenue expenditure heads
115 of 2008 Gold plating of capex
The steep increase in the asset base
every year has been suggested by
the consumers to be an attempt by
the Utilities to increase the returns
from the regulated business. The
addition to the asset base is clearly
not commensurate either with the
increase in sales or increase in
demand in MW served. Utilities
were able to serve the existing
consumer base well enough with
the existing assets
The favourite argument of the Utilities that in
the past, there was a backlog on this account
and that they want to rake it up is also
unconvincing to justify the 100% increase in
the asset base in such a short period. As a
general rule, the Commission has decided
that the total capital expenditure and
stabilization16 on non-DPR schemes in any
year should not exceed 20% of that for DPR
schemes during that year
115 of 2008 Any fallout of poor governance
and consequential financial
implication/burden should not be
passed on to consumers.
In this context, the Commission observes
that interest paid by MSPGCL on account of
delayed payment of income tax, is not an
expense properly incurred. The Utility is
supposed to pay income tax on time as good
governance. For example, any penalty paid
by the Utility will not be passed on to the
consumers. Accordingly, the Commission
has considered the actual income tax, but has
disallowed the interest paid by MSPGCL on
account of delayed payment of income tax
-
8/3/2019 MERC Generation Tariff Order Analysis
17/24
26 of 2008 and
95/2008
duty of the owner of the plant to
ensure
thorough inspection and testing that
the equipment being procured are of
good quality,
these are stored at site as required
and imparting training to its
operating personnel
well in advance, and any losses
incurred through not performing
these elementary
duties properly cannot be passed on
to the consumers
stabilization period of coal based and lignite
fired stations shall be reckoned as 180
days from the date of commissioning. As
against this, MSPGCL has requested for
consideration of a higher period of
stabilization of 427 days. Applied for Parli
Unit No. 6/Unit No 3
Performance Parameters
In order 69 of 2006- The Commission has decided that the MYT framework for MSPGCL would
incorporate the trajectory of following performance parameters:
The various performance parameters are decided after taking into consideration the performance of units
with similar vintage in India.
However, Mahagenco went on appeal to the ATE, which ordered MERC to appoint an expert to suggest
realistic performance norms. The ATE expert (CPRI) suggested the norms, which were first amended
during the truing up of the tariffs till FY 2007-08.
-
8/3/2019 MERC Generation Tariff Order Analysis
18/24
Unique Hydel Power Policy
MERC is quite proud (rightly so) of its hydel power pricing policy. The main features of this are
a. Hydel power has low O&M costs. The effective energy charge in the case of MSPGCLs hydrogenerating stations work out to be very minimal as the Annual Fixed Charge is far lesser than the
other-wise applicable energy charges (variable cost of the least-cost, available alternative source
of power). Therefore, economic value of power is not priced in.
b. As the pricing of hydro generation fails to send any economic signal and, guided by Section 61 ofthe Electricity Act, 2003, which calls for economic use of resources, the Commission has decided
to adopt a one part (energy based) differential peaking tariff (for peak and non peak hours) for
hydel generation). The tariff for non-peak hours is based on the highest variable cost of the
thermal generating stations, as Ideally, the peaking tariff should be the least cost available
alternative source of power if such hydel generation is not available in those hours.
c. The rationale for having differential peak and non-peak tariff is that hydro power should be usedonly during peak hours, and during non-peak hours it has to be used only in case of exigencies
like grid stability requirements, etc.
d. 5% of excess recovery of peak generation to be shared between Genco & Distribution company,rest to passed on to users as rebate. But if peak generation < target (except for uncontrollable
factors), then the revenue loss would not be trued up, but borne by Genco & Distribution
company in ratio of 50:50. Hence, economic price signals are sent but users do not suffer.
e. The rationale for having differential peak and non-peak tariff is that hydro power should be usedonly during peak hours, and during non-peak hours it has to be used only in case of exigencies
like grid stability requirements, etc.
-
8/3/2019 MERC Generation Tariff Order Analysis
19/24
General MERC Order Analysis- Quality and Consistency
We notice that MERC does issue speaking orders discussing the utility stand, opposite views and its own
analysis. While the reasons/rationale for the order is quite clear, at times it is perverse to the regulated
entity due to interpretation adopted. For example, AAD station wise, coal costs, O&M expenses were all
calculated adversely to Mahagenco, without considering the plain text of regulations as applied to
Mahagenco. That led to an appeal.
There are very few errors of fact or law in the order. In the ATE orders we examined, there were no
strictures passed against MERC/loss on this ground. Instead, the main disagreements happened in policy
issues-essentially whether the norms of MERC were too strict. When ATE sided with Mahagenco
(largely), this induced cascading effect on ROE, working capital, interest etc.
Some ATE order extracts are below, with our comments in italics.
1. The MERC Regulations did not specify any norms relating to admissibility of A&G expenses andhad approved the expenses based on the principle of reasonable year-on-year increase. The ATE
critiqued the MERC order stating that it did not explain the reasonableness of selecting escalation
rate of which is not even sufficient to mitigate the inflation rate. Essentially, it was not a speaking
order. Also, the escalation factor had not been determined in advance by the regulations but was
arbitrary
2. Again for A&G norms, there being no laid down norms, any expenditure incurred on generationand purchase of energy was to be permitted for pass-through in tariff as per Sixth Schedule of
Electricity Supply Act, 1948. This finding by ATE indicates that where there are no norms, any
determination of norms post facto is likely to be struck down as arbitrary OR determined in
favour of the utility
3. For A&G expenses, Mahagenco came up with an interesting ratio of gross A&G expenses perMW generated. Its argument was that the gross A&G expenses averaged over the capacity in
MW gives A&G expenses per MW to be 0.347 which is still less than what is allowed in the case
of TPC and REL. Given the technical complexity, geographic dispersion, employee strength etc
for Mahagenco compared to other utilities, ATE found a strong basis in that argument, and
directed MERC to recomputed expenses.
4. The SHR(Station Heat Ratio) targets set by MERC was not being achieved, therefore leading tolower tariffs due to under absorption of fixed costs/no efficiency gains. Observing that this
practice did not benefit either the utility or the consumer (since wrong price signals), MERC
mandates a scientifically determined ratio.
-
8/3/2019 MERC Generation Tariff Order Analysis
20/24
5. The MERC regulations did not stipulate anything about recovery of incentive. While MERC haddirected quarterly basis in the order, the utility wanted it monthly, and put forth the logical
argument of synchrony with billing cycle. Hence, that argument was upheld by ATE.
6. MERC disallowed the normative fuel cost as per the recommendations of CPRI for the years2005-06 to 2007-08 and restricted the fuel cost to the actuals, from the year 2008-09 onwards the
norms as recommended by the CPRI have been followed. For 2008-09 to 2010-11 also the actual
fuel cost should have been allowed or else the norms as recommended by the CPRI should have
been used. Any other approach seems cherry picking of approaches in our view
7. Coal costs is a major cost component but MERC had not provided detailed cost sheet workings toMahagenco, due to which inconsistent figures were there and appeals were preferred. Hence ATE
ordered MERC to provide detailed workings of coal cost to Mahagenco. This is another example
of needing transparency and two way information sharing between regulator and regulated
enterprise.
After studying the ATE orders in respect of Mahagenco/MERC, we infer that the main reasons for appeal
were transparency (coal costs, reasons for exclusions, post facto regulations) and extraneous policy issues
by MERC (disallowing AAD station wise, SHR factors).
Barring the issue of coal costs,MERC has largely issued speaking orders, which have either been
upheld/overruledby ATE without the need/request to adduce additional evidence. This speaks volumes
for the quality of the regulatory orders. Maybe this is because MERC inducts retired utility officers to act
as its Regulatory Experts. These people having decades of experience on the other side, can help the
commission detect issues in implementation/genuine problems, and thereof build processes to ensure fair
and speaking orders.
There appears scope for improvement procedurally.
-
8/3/2019 MERC Generation Tariff Order Analysis
21/24
Is MERC playing the game well?
Earlier, we modeled the tariff fixation process as a game where barring the regulator, every other player
looks to its own parochial interests. This is not a stinging indictment of the process, but a mere
recognition that in any political scenario (this IS one given the somewhat vague performance accounting
norms & policy issues at stake), there are bound to be winners and losers. We note that Mahagenco being
a state owned utility is constrained from subverting regulatory officials with corrupt practices. Therefore,
one would expect a more stringent approach with Mahagenco than other utilities, which was partly borne
out in the lower (per MW generated) O&M expenses allowed by MERC, which was afterwards felt as
unfair by the ATE.
One needs to know the game well to play it. MERC was fully acquainted with the situation of
Mahagenco, having advised the Maharashtra Govt. on unbundling. Yet, it did not factor in those relaxed
standards, leading to sustained under recovery of costs which was not trued up later. On the halter of
efficiency, Mahagencos path dependency (reliance on poorly maintained systems, utility of last resort,
state owned incumbent) was ignored. This is possible in a price cap situation but not for a normative cost
plus situation where path dependency counts.
MERC also, in our opinion, gets too hyper technical at times, forgetting the wider policy issues at play.
For example, stricter unachievable norms imposed without a technical study violates principles of
natural justice. Still, all is not lost. It has hopefully learnt from its earlier mistakes.
-
8/3/2019 MERC Generation Tariff Order Analysis
22/24
Overall Observations
1. Path Dependency:- Following the hallowed legal doctrine of res juditica, the MERC prefers tofollow the reasoning laid down in its earlier orders. While this ensures regulatory consistency, it
also results in a tariff shock if the earlier orders are revised with retrospective effect because of an
ATE verdict favouring the utility.
2. Maharashtra Govt. /erstwhile MSEB cash crunch:- This lead to deferring O&M/Capexexpenses and thus giving the impression of MSEB being the lowest cost power producer, while
this was because of deferring of vital expenses. The MERC recognized this, and allowed one-time
additional O&M (to make up for earlier year deficits) and relaxed norms. Mahagenco was entitled
to 70:30 debt equity ratio for incremental capex, but has applied for 80:20 or even 100% debt-
stating that GoM (Government of Maharashtra) would not infuse additional equity funds for new
projects. This is astounding to say the least.
3. Game Theory:-While reading the petitions/submissions/MERC reasoning, we got the feelingthat this situation is amenable to a game theory analysis, because this is a recurring situation
where all participants play well defined roles.
a. The regulated utility wants to overstate its estimated costs, so that it can get moreefficiency gains when it achieves lower actual. Also, even if tariff is adjusted
downwards, it still gets interest free use of the surplus till the adjustment order which
takes atleast a year. This incentive applies for overstating capex by capitalizing O&M
expenses, and also gold plating to ensure higher rate of return.
b. End Customers seek the lowest estimated costs so that they can pay lower tariffs. Whilethis will not help as the deficits are recoverable with interest in future truing up periods,
they can still manage their cash flows better. That is why both individual consumer
associations and industrial consumers like Tata Motors vehemently challenge each cost
items rationale, amount and spending efficiency.
c. Distribution companies see the generation cost as a 100% pass through to theircustomers, and so have rarely contested/attended the tariff hearings/technical validation
sessions. This is although they are the direct generation customers, and in a sense most
affected by the generation companys actions.
d. Other generation companies oppose capex/plant location decisions at times forcompetitive reasons, because though generation capacity addition is de-licensed, the
MERC still has the tariff setting authority and therefore carries out prudence checks.
-
8/3/2019 MERC Generation Tariff Order Analysis
23/24
e. The State Government desires to cross subsidize its vote bank (farmers/individuals) atthe cost of industrial users. Therefore, the direction to the MERC includes the aspect of
perpetuating cross subsidy.
f. The regulator(MERC) itself must play a fine balancing act between ensuring theeconomic health of the generation company, and ensuring that the company has every
incentive to maximize its efficiency and operate at minimal costs. While mechanisms like
efficiency sharing gains (hydel, PLF>80% etc) do it, the main approach adopted is to
estimate normative costs.
4. Cost Accounting matters:- Instead of merely extrapolating incurred costs and calculating ROE,the MERC checks the prudence of those costs (aka performance audit), and then checks
whether cost changes were controllable or uncontrollable. Controllable cost changes are mainly
(2/3rd
) kept with the utility but uncontrollable cost changes are passed on to customers.
5. Regulations fill data void:-The MERC regulations contain certain default technical parametersdepending on equipment used in plant. If the utility does not maintain reliable records, then these
parameters are used. This was done for O&M costs, auxiliary factors etc for the period where
Mahagenco did not maintain adequate records. This is akin to composition scheme/best
judgement assessment under the IT Act 1961!.
6. Developmental role-MERC had passed strictures on Mahagenco(detailed below) asking it tosegregate plant wise accounts, improve coal handling/purchase systems, streamline O&M
management, instill proper capex planning scheme etc. These internal functions of Mahagenco
had to be pushed for by the regulator.
7. Petition Scrutiny does benefit MSPGCL at times-MSPGCL had at times sought lower interestrate than the prevailing market rates, and MERC suo moto granted the higher rates. Similarly for
D/E ratio, MSPGCL even petitioned for 100% D/E ratio due to cash crunch from Govt. equity,
but MERC allowed at 80%, thus ensuring in higher tariffs. D/E ratio, interest rate where MERC
had adversely
8. Gentle balancing act:- While the over arching objective of MERC seems to protect the interestof consumers in the State of Maharashtra(its reasons for prohibiting Load Management charge,
high hydel lease fees, restricting interstate sales etc), it also keeps the interest of the generator in
mind while deciding ROE, efficiency sharing gains etc.
9. Use of incentives:- MSPGCL can keep 2/3rd of its efficiency gains/losses, while passing on 1/3rdto the distribution entity. Interesting, fuel costs being seen as a mix of controllable (consumption)
and non controllable (procurement price), its pass through is allowed via Fuel Adjustment
-
8/3/2019 MERC Generation Tariff Order Analysis
24/24
Charge mechanism, which encourages prudent short term power purchase practices. Other
uncontrollable costs are passed through in full.
10.Hydel Power incentive structure:- Unlike thermal plants where the utility owns the plant, hydelprojects are built by the State irrigation department, and then handed over to Mahagenco, in
return for lease rent which encompasses ROE to GoM. Mahagenco is allowed by MERC merely
to recover actual O&M expenses, on no profit no loss basis. Since it does not own the plant, there
is no ROE/return given. Mahagencos request for an operating fee was shot down as no place in
MERC regulations for this. The request does seem fair though, considering that virtually no
efficiency gains/incentives exist for Mahagenco under the present tariff regulations.
11. Truing Up:- Actual expenses and the actual revenue will be trued up at the end of the year basedon audited financial results and subject to a prudence check. Provisional truing up of certain
elements of ARR is considered in cases where the impact is very high, or there is a change in the
principles/methodology, or due to revision in capital expenditure/capitalization figures