merc generation tariff order analysis

Upload: anandh-sundar

Post on 06-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 MERC Generation Tariff Order Analysis

    1/24

    Group Project

    Salient features of selected MERC tariff ordersand disposal of petitions of the MSPGCL (Genco)

    Faculty GuideProf. Sebastian Morris

    In partial fulfillment of the courseInfrastructure Development and Financing

    Submitted by Section B, Group 3

    Group members:

    Anandh Sundar TripuriAniket KhasgiwaleBadrinath Srinivasan

    Manish KumarMiheer Desai

    Rahul Venkatraj

  • 8/3/2019 MERC Generation Tariff Order Analysis

    2/24

    Table of Contents

    Introduction .................................................................................................................................................. 3

    Objectives and methodology used ............................................................................................................... 4

    Overview of Applicable Policies/Laws/Regulations ...................................................................................... 5

    About MSPGCL .............................................................................................................................................. 7

    Summary of Tariff Orders ............................................................................................................................. 8

    Non Routine Orders ...................................................................................................................................... 9

    Individual Tariff Order Highlights ................................................................................................................ 10

    AREAS OF DISPUTE ...................................................................................................................................... 13

    Window dressing / Behavioral orders ........................................................................................................ 15

    Performance Parameters ............................................................................................................................ 17

    Unique Hydel Power Policy ......................................................................................................................... 18

    General MERC Order Analysis- Quality and Consistency ............................................................................ 19

    Is MERC playing the game well? ................................................................................................................. 21

    Overall Observations ................................................................................................................................... 22

  • 8/3/2019 MERC Generation Tariff Order Analysis

    3/24

    Introduction

    The objective of the assignment is to bring out the salient features of the tariff orders /disposal of petitions

    of the MSPGCL (Genco). Power sector tariff regulations are manifold. The Central laws/regulations viz.Electricity Act 2003, Electricity Policy, Tariff Policy; are applied for interstate projects, and are used as

    guiding principles for designing state policies. The Forum of Regulators ensures some uniformity at the

    state level in terms of tariff setting etc.

    This project analyzes the key issues as:

    (1) Variations over various tariff orders implicit change in principle or in key assumptions in theorder of the MERC.

    (2) Variations between ARR and orders/directions resulting in petitions and the variations in the waythe petitions were dealt with.

    (3) How far were the directions adhered to and what measures were used to improve adherence?(4) The quality of the response of the MERC to the ARR/ Petitions.

    The project aims at seeing only the MSPGCL tariff orders over a defined time period.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    4/24

    Objectives and methodology used

    After the exploratory analysis about MERC tariff philosophy and approach to petition handling, this

    studys objectives was to diagnose whether:

    (1) The process could have been faster.(2) Are they true to the spirit of the provisions of the EA 2003?(3) What was the nature of the due diligence with regard to the ARRs /disposal of petitions and were

    they adequate given the law?

    (4) What are the regulatory risks imposed by the MERC? Could these have been avoided by upfrontlaying down the principles etc? (look at the general regulations, the format for submitting the

    ARR, the explanations etc)

    (5) Could the disputes and petitions have been avoided /reduced?(6) What improvements are therefore possible?

    For this, the methodology used was

    1. The tariff orders were downloaded from the MERC site.2. A checklist of points to be analyzed was prepared. This included points like prudence check on

    costs, timelines, appeals, dispute resolution techniques, regulatory risks, crosscheck of regulatory

    accounts with statutory accounts etc.

    3. The tariff orders were then evaluated using this checklist.4. Brainstorm about improving the process, and learn from the central best practices/best practices

    of other states.

    5. The checklist and draft report was then discussed with Prof Morris.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    5/24

    Overview of Applicable Policies/Laws/Regulations

    TitleDeals with Scope/Applies to

    Section 61 & 62 of the Electricity

    Act, 2003

    General unbundling of the

    electricity principles

    Central projects/interstate lines

    but is a model for state laws

    Maharashtra Electricity

    Regulatory Commission (Terms

    & Conditions of Tariff)

    Regulations, 2005

    Determining tariffs for the period

    2006-2011(originally 2009 but

    was extended due to data issues

    etc)

    Maharashtra power utilities.

    Principles follow the CERC

    norms/EA Act 2003 except for

    cross subsidy etc

    National Tariff Policy/CERC

    Tariff Regulations

    Principles and Guidelines for

    setting tariffs centrally

    Central projects/interstate lines

    but is a model for state laws, and

    forum of regulations adopt this.

    Section 7 of the Electricity Act 2003 permits any generating company to feely establish, operate and

    maintain a generating station without obtaining a license under that Act, if it otherwise complies with the

    technical standards relating to connectivity with the electricity grid. For hydel projects, certain

    additional approvals exist to ensure optimum riverine utilization and non conflict with other public

    purposes like irrigation, flood control, navigation etc. Section 61 of the Electricity Act 2003 lays down

    tariff setting principles, which are adhered to as follows.

    Principle Meaning/ Example as applied to generation units

    the principles and methodologies

    specified by the Central Commission for

    determination of the tariff applicable to

    generating companies and transmission

    licensees

    The cost accounting norms, efficiency principles and

    tariff philosophies of CERC should be adhered to at

    State level where possible. It will promote

    transparency, consistency and predictability in

    regulatory approaches across jurisdictions and

    minimize perceptions of regulatory risks

    the generation, transmission, distribution

    and supply of electricity are conducted on

    commercial principles

    This would mean arms length transactions between

    the unbundled arms of erstwhile integrated utilities

    the factors which would encourage

    competition, efficiency, economical use

    of the resources, good performance and

    optimum investments

    Open access, increasing normative standards yearly,

    permitting efficient standard costs (normative costs)

    only, setting quality of service linked bonus, and

    approving capex.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    6/24

    Principle Meaning/ Example as applied to generation units

    safeguarding of consumers' interest and at

    the same time, recovery of the cost of

    electricity in a reasonable manner

    Allowing cross subsidy for limited purpose of

    universal service obligation, till the time the

    appropriate state directly pays subsidy. Also,

    uncontrollable costs should be recovered speedily to

    ensure that future consumers are not burdened with

    past costs. Address the risk sharing mechanism

    between Utilities and consumers based on

    controllable and uncontrollable factors.

    the principles rewarding efficiency in

    performance

    Enhanced ROE for better PLF, sharing of efficiency

    gains. Operating parameters in tariffs should

    be at normative levels only and not at lower of

    normative and actuals

    multiyear tariff principles Approve business plans for 5years at a go, with

    minor annual revisions reflecting changed

    costs/projections, but rarely changed capex. Control

    period length however, depends on data uncertainties

    and other practical considerations

    that the tariff progressively reflects the

    cost of supply of electricity and also,

    reduces cross-subsidies in the manner

    specified by the Appropriate Commission

    Reducing customer categories(since this leads to

    cross subsidy), among other things

    the promotion of co-generation and

    generation of electricity from renewable

    sources of energy

    Mandating higher generation feed in tariffs, and

    compulsory off take contracts with distribution

    licensee, for renewable energy

    The National Electricity Policy and

    tariff policy

    National Tariff Policy should be used as the base,

    with appropriate state level modifications

  • 8/3/2019 MERC Generation Tariff Order Analysis

    7/24

    About MSPGCL

    The Maharashtra State Power Generation Company Limited (MSPGCL or MahaGENCO) is a Company

    is a company incorporated under the Companies Act, 1956 on 6th June, 2005, formed under the

    Government of Maharashtra General Resolution No. ELA-1003/P.K.8588/Bhag-2/Urja-5 Dated January

    24, 2005. This resolution gave effect to the reorganization of Maharashtra State Electricity Board in terms

    of the Maharashtra Electricity Reforms Transfer Scheme 2004. As per this Order, the Maharashtra State

    Electricity Board (MSEB) has been restructured into four entities MSPGCL, MSETCL, MSEDCL and

    MSEB Holding Company. The State Government as a part of this transfer scheme had allocated the

    generating stations of MSEB to MSPGCL. MSPGCL also maintains & operates the hydro plants owned

    by the Irrigation Department, Government of Maharashtra as a lessee. The State Government had

    allocated the generating stations of MSEB to MSPGCL. MSPGCL supplies electricity in bulk to

    MSEDCL, hence the role of the MERC to determine tariffs for MERC generating stations.

    It is said that the sins of the parent are borne by the children. In the case of MSPGCL, it was saddled with

    legacy old plants, under spending on O&M/capex in previous years and consequential inability to meet

    the normative standards. When MERC prodded MSPGCL to become more efficient by setting policy

    parameters close to normative levels, MSPGCL approached the Appellate Tribunal for Electricity to

    appeal against MERCs order, and was partly successful, including on substantive issues like fixing the

    levels(realistic versus normative). This had lead to some tension between MERC and MSPGCL as borne

    out by its critique of MSPGCL accounting, capex gold plating and faulty planning, but overall there is

    now a healthier relationship.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    8/24

    Summary of Tariff Orders

    Case

    Number

    ARR

    Period

    Tariff

    Period

    Subject Matter/Highlights Principle(s)/Remarks

    Case No.

    48 of

    2005

    FY 2005-

    06

    FY 2006-

    07

    FY 2006-

    07

    First ever tariff order for

    unbundled entity. Hence

    focus more on

    accounting/segregation

    issues

    Efficient and reasonable estimates

    for technical parameters and costs

    to arrive at tariff. Peaking power

    pricing for hydel power adopted.

    Appeal to MERC disposed of in

    Case 34 of 2006.

    Case No.

    68 of2006

    FY 2007-

    08FY 2008-

    09

    FY 2009-

    10

    FY 2007-

    08-extended

    till May

    31,2008

    first Control Period for MYT

    framework shall bethe three financial years from

    April 1, 2007 to March 31,

    2010

    Mahagenco C won an appeal at the

    ATE, and MERC had to revise thetariff in Order 71 of 2007

    Case No

    71 of

    2007

    second

    year of

    the first

    ControlPeriod

    June

    1,2008 till

    mar 31

    2009

    Mostly giving effect to the

    ATE order for setting tariffs

    N/A

    Case 16

    of 2008

    Truing up

    FY 2005-

    06, FY

    2006-07

    and FY

    2007-08

    ATE/CPR

    N/A MSPGCL to recover the

    approved amount of Rs.

    762.77 Crore in 12 equal

    monthly installments from

    MSEDCL, in order to avoid

    any tariff shock to the

    consumers.

    This order was to give effect to the

    ATE judgments and the CPRI

    norms. The only new principles

    introduced there were the

    identification of non tariff income

    to reduce ARR requirements.

    Case 115

    of 2008

    Last year

    of control

    period

    FY 2009-

    10

    Much lesser areas of disputes

    here, as ATE rulings/CPRI

    norms had resolved many

    issues

    N/A

  • 8/3/2019 MERC Generation Tariff Order Analysis

    9/24

    26/ 95 of

    2008

    First 2

    years of

    new Paras

    Thermal

    station

    FY 2008-

    09

    Unit No. 3 of Paras Thermal

    Power Station

    Appealed to ATE, and revised in

    2011. MERC revised its orders

    vide Orders 74/75 of 2011.

    102 of

    2009

    Truing up

    for FY

    2008-09,

    Annual

    Performa

    nce

    Review

    for FY

    2009-10

    FY 2010-

    11

    Much lesser areas of disputes

    here, as ATE rulings/CPRI

    norms had resolved many

    issues

    N/A

    Non Routine Orders

    FIRST TIME PLANT TARIFF

    The Tariff orders for the Parli Unit were for new plants, which had the special characteristics of

    unstable control period, need for incremental capex principle and fresh start. Both the projects

    experienced cost overruns, which the MERC disallowed blaming them on the Mahagenco induced delays.

    This, naturally, is now under appeal to the ATE.

    HYDEL LEASE RENTAL ORDER

    Order from first principles-ROE based Pass through for MSPGCL so very little opposition from the

    utility per se. Only others opposed it/submitted pleas. Another interesting order is on hydel lease rent

    needs some background to appreciate. As per Maharashtra law, the dams and hydel power plants are

    constructed by (and belong to) the Irrigation Dept. Many of these projects are ECB funded by World

    Bank and others. The Govt. (not unreasonably) wanted to charge the unbundled Mahagenco a fair lease

    rent to recover the interest & ROE on its dams. Now, the tariff fixation powers for this are not on any

    electricity regulator as this subject is missing in the Electricity Act 2003. But if the Govt. had arbitrarily

    fixed a higher amount (100% pass through to customers), this may have been challenged. Hence, Govt.

    requested MERC to calculate the amount on its behalf, in its administrative capacity. So MERC

    considered various methods like DCF but finally decided on a ROE model. This order is an excellent

    example of practicalities in financial management of power sector.

    http://www.mercindia.org.in/pdf/Ord_2008_10_27_CNo_17_of_2007.pdfhttp://www.mercindia.org.in/pdf/Ord_2008_10_27_CNo_17_of_2007.pdf
  • 8/3/2019 MERC Generation Tariff Order Analysis

    10/24

    Individual Tariff Orders Highlights

    1. Case No. 48 of 2005a. As envisaged in the tariff policies, two part station-wise generation tariffs.b.

    Unique hydel tariff policy envisaged, to ensure economic signals without burdeningconsumers unduly. This was done through differential energy tariff for peak and non-

    peak hours, and is elaborated later on. Has been specified, where peak is 20% higher

    than non peak.

    c. One-time R&M expenses permitted during future truing up(over and above the approvedamount) to compensate inadequate spending in the past

    d. While income tax expense in petition was sought at 33% on ROE(assuming that it wouldpay maximum marginal rate on its ROE), the allowed expense was capped at the MAT

    amount of 10%(prevailing then)

    e. Norms for new stations as per MERC Tariff Regulations have been applied for existingstations as well. This was the most controversial part of ruling, and successfully appealed

    by MSPGCL before the ATE.

    f. While O&M costs taken on normative basis, interest allowed only on actual, that too onlyon the approved borrowings.

    g. While rejecting MSPGCLs plea for lower normative PLFs, the MERC said that ageingof units and non-availability of time for Planned Outages cannot be considered as

    reasonable causes for high SHR or low PLF, and MSPGCL should explore all avenues

    for improvement in its plant operations, routine maintenance, and capital maintenance to

    enhance reliability and efficiency of their thermal generating units. Again, the ATE partly

    reversed this logic.

    h. The Commission has calculated the variable cost of fuel for FY 2006-07 based on theactual cost of fuel in the month of March 2006, agreeing to adjust changes via vetting of

    FAC claims. This is analogous to LIFO system of accounting!

    i. MSPGCL had been importing coal without a proper cost benefit analysis, and so MERCdirected MSPGCL to install and maintain the required meters with in next three months

    for measurement of Coal GCV and then carry out the cost benefit analysis of the usage of

    imported coal at its generating stations

    j. Most of the generating units had no weightometers and hence an accurate measurementof coal is not being done. The Commission has therefore not accepted the MSPGCLs

    projections and approved transit loss as per MERC Tariff Regulations only

  • 8/3/2019 MERC Generation Tariff Order Analysis

    11/24

    k. A systematic measurement of Gross calorific value of coal by taking periodic samples ofcoal being fired shall be institutionalized at all the stations

    l. MSPGCL has not provided any supporting information regarding the details of R&Mexpenses actually incurred during FY 2005-06 and resultant technical efficiency

    improvements, hence was told to get its R&M plans approved at the earliest.

    m. In absence of historical actuals for MSPGCL, Commission is not projecting non-tariffincome. This was however determined in later orders.

    n. R&M expenses are to be determined at an average of actuals as a percentage of GFA forthe preceding five (5) years. This is a standard practice by MERC

    2. Case 68 of 2006a. Much more systematic order, largely following the earlier ordersb. Conscious of the fact that the unbundling of the erstwhile MSEB should result in overall

    increase in expenditure on O&M.

    c. Despite not meeting the desired PLF norms for FY 2006-07-which could have led tolesser recovery for future years- MERC approved the full recovery of fixed charges

    during FY 2007-08 for all thermal stations. However, in the event ofactual availability

    for the year, computed in accordance with the Commissions Tariff Regulations

    (after accounting for the unavailability of fuel), being less than 80%, the fixed

    charges would be proportionately adjusted as per MERC Tariff Regulations, while truing

    up the revenue requirement in the next year.

    d. The funding of the schemes has been considered at debt: equity of 80:20 as proposed byMSPGCL in view of shortage of equity capital despite Tariff Regulations providing for

    normative debt: equity of 70:30.

    e. For approving the O&M expenses for the Control Period, the Commission hasconsidered the O&M expenses approved in FY 2006-07 as the base expenses. As MSEB

    under spent due to earlier cash crunch, the method of extrapolation could not have been

    used to calculate O&M costs.

    3. Case 71 of 2007a. Commission rejects MSPGCLs request for providing incentive for Uran gas thermal

    station on the basis of reduced availability and PLF, due to shortage of gas. The

    Commission is of the view that though full fixed cost recovery has been permitted to

    Uran gas station, despite non achievement of normative availability of 80%, it would not

    be fair to the consumers to provide incentive at such low PLF levels

  • 8/3/2019 MERC Generation Tariff Order Analysis

    12/24

    b. Though MSPGCL has been putting its efforts and expertise to optimize the performanceof scarce hydro resources, MSPGCL is not earning any commensurate returns/incentives

    over and above the actual cost incurred for such operations. MSPGCL, in its Petition,

    therefore, proposed a recovery of supervision charges to the extent of 15% of the

    Operations and Maintenance expenses incurred during the year for such hydro power

    plants. This was shot down because lease rent payable to GoM already had RoE

    component, also no provision in the MERC Tariff Regulations under which such

    expenses may be allowed.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    13/24

    AREAS OF DISPUTE

    Cost Item MSGPCL Stand MERC Stand Present Status

    Advance Against

    Depreciation

    in respect of some

    generating stations.

    intended to meet shortfall

    in meeting loan repayment

    obligations of the

    Generating

    Company. Hence to be

    calculated station wise.

    While tariff is

    determined on a station-

    wise basis, AAD is a

    special provision, which

    enables the Utility

    to meet its loan

    repayment obligations as

    a whole rather than for

    each Station(Order 115

    of 2008)

    ATE decides to have

    this done station wise.

    Judgment dated

    27.4.2011 in

    appeal no. 191 of 2009

    Disallowance in

    Project Cost

    Delay in commissioning of

    Unit No. 3 of Paras

    Thermal Power Station

    was not considered, and

    cost was disallowed.

    The delay was due to

    Mahagenco so

    additional cost due to

    delay is to be disallowed

    ATE partly agreed

    with MERC

    Operation &

    Maintenance cost

    that such an increase in R

    & M expenses may not fit

    into the ideology of

    setting normative O&M

    expenses since the hydel

    assets are old and may

    require more

    repairs and maintenance in

    future.

    norms for new stations

    as per MERC Tariff

    Regulations have been

    considered for existing

    stations also

    Agreed with MERC

    Appeal No. 86 & 87 of

    2007 .given that

    =expenditure for OLD

    HYDEL stations not

    covered under policy

    Remaining pending

    Fuel Costs provisions in the National

    Tariff Policy (NTP), which

    states that in case the

    actual performance is

    much less than the

    norms, then ARR should

    Not till actual

    parameters determined.

    truing up of actual fuel

    expenses

    till such time the re-

    assessed improvement

    trajectory of

    parameters is

  • 8/3/2019 MERC Generation Tariff Order Analysis

    14/24

    be determined based on

    relaxed levels.

    available

    Tariff for Small Hydel

    Stations

    entitlement of higher tariff

    for small hydro projects as

    the Commissions

    Order

    only in the case of new

    projects

    Agreed with MERC

    Appeal No. 86 & 87 of

    2007

    determination of hydel

    peak and off peak

    generation and tariff

    taking into consideration

    the operational

    capacity of MSPGCL and

    system pattern

    economic signal about

    pricing of hydel

    generation

    Endorsed MERC

    approach BUT tailored

    it to Mahagencos

    needs

    Appeal No. 86 & 87 of

    2007

    Transit Loss/Auxiliary

    parameters

    reset the operating

    parameters

    Normative align its Regulations

    by prescribing

    achievable norms and

    not merely ideal

    norms. engage an

    appropriate

    agency(ies) assess and

    suggest improvements

    non-tariff income should not be considered

    as part of the revenue

    Include for determining

    the revenue gap/surplus

    ATE partly agreed

    with MERC Appeal

    Nos. 86 & 87 of 2007

    Capex approvals Accept non DPR schemes

    after prudence check

    Mahagenco to bundle

    non DPR into DPR else

    suffer 50% cut till the

    prudence check done

    ATE agreed with

    Mahagenco. Order 199

    of 2010 dated 4 Aug

    2011.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    15/24

    Window dressing / Behavioral orders

    Regulated utilities will try to game the system/cook the books, while the regulator would want to structure

    the incentives to avoid gaming of the system. Some Examples of MERC efforts in this line are

    Order Example(s/Observation Action

    68 of 2006 The increase in quantum of Non-

    DPR schemes is a worrying trend,

    as the Commission observes a

    tendency to split capex schemes so

    that capital outlay of the scheme is

    below Rs. 10 Crore, to escape

    regulatory scrutiny.

    The Commission will take a review of the

    schemes being classified under Non-DPR

    category, and in case it is found that these

    schemes should have ideally been classified

    under DPR category, then that capex and the

    related capital charges will be disallowed till

    the DPR is submitted and the scheme is

    approved by the Commission. In Case 115

    of 2008, For Non-DPR schemes, the

    Commission has considered 50% of the

    proposed stabilization15 by MSPGCL on ad

    hoc basis, as the Commission is of the view

    that until it is ascertained that the projected

    benefits have actually accrued for the benefit

    of the consumers, it would not be appropriate

    to allow the entire expenses.

    68 of 2006 Seeing lackadaisical approach in

    fixed asset accounting/submitting

    capex schemes, MERC had to

    caution Mahagenco

    The Commission would like to reiterate that

    in-principle approval of the scheme does not

    absolve the senior management of MSPGCL

    of their responsibility to prioritize various

    schemes and undertake cost benefit analysis

    and financial analysis to validate the

    commercial prudence of each scheme.

    MSPGCL should ensure that the projected

    benefits actually accrue for the benefit of the

    stakeholders. It would be essential to monitor

    progress of each scheme as well as track

  • 8/3/2019 MERC Generation Tariff Order Analysis

    16/24

    expenditure and benefits accrued as per the

    scheme.

    68 of 2006 practice of treating Renovation and

    Modernization as revenue

    expenditure is not

    limited to any one department or

    any one generating station of

    MSPGCL, but is spread

    across all departments and all

    stations

    The Commission has not considered the

    truing up of R&M expenses for FY 2006-07

    at this stage. In order to have a clear picture

    regarding Repairs and maintenance

    expenditure, MSPGCL should maintain a

    clear demarcation of capital expenditure and

    revenue expenditure heads

    115 of 2008 Gold plating of capex

    The steep increase in the asset base

    every year has been suggested by

    the consumers to be an attempt by

    the Utilities to increase the returns

    from the regulated business. The

    addition to the asset base is clearly

    not commensurate either with the

    increase in sales or increase in

    demand in MW served. Utilities

    were able to serve the existing

    consumer base well enough with

    the existing assets

    The favourite argument of the Utilities that in

    the past, there was a backlog on this account

    and that they want to rake it up is also

    unconvincing to justify the 100% increase in

    the asset base in such a short period. As a

    general rule, the Commission has decided

    that the total capital expenditure and

    stabilization16 on non-DPR schemes in any

    year should not exceed 20% of that for DPR

    schemes during that year

    115 of 2008 Any fallout of poor governance

    and consequential financial

    implication/burden should not be

    passed on to consumers.

    In this context, the Commission observes

    that interest paid by MSPGCL on account of

    delayed payment of income tax, is not an

    expense properly incurred. The Utility is

    supposed to pay income tax on time as good

    governance. For example, any penalty paid

    by the Utility will not be passed on to the

    consumers. Accordingly, the Commission

    has considered the actual income tax, but has

    disallowed the interest paid by MSPGCL on

    account of delayed payment of income tax

  • 8/3/2019 MERC Generation Tariff Order Analysis

    17/24

    26 of 2008 and

    95/2008

    duty of the owner of the plant to

    ensure

    thorough inspection and testing that

    the equipment being procured are of

    good quality,

    these are stored at site as required

    and imparting training to its

    operating personnel

    well in advance, and any losses

    incurred through not performing

    these elementary

    duties properly cannot be passed on

    to the consumers

    stabilization period of coal based and lignite

    fired stations shall be reckoned as 180

    days from the date of commissioning. As

    against this, MSPGCL has requested for

    consideration of a higher period of

    stabilization of 427 days. Applied for Parli

    Unit No. 6/Unit No 3

    Performance Parameters

    In order 69 of 2006- The Commission has decided that the MYT framework for MSPGCL would

    incorporate the trajectory of following performance parameters:

    The various performance parameters are decided after taking into consideration the performance of units

    with similar vintage in India.

    However, Mahagenco went on appeal to the ATE, which ordered MERC to appoint an expert to suggest

    realistic performance norms. The ATE expert (CPRI) suggested the norms, which were first amended

    during the truing up of the tariffs till FY 2007-08.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    18/24

    Unique Hydel Power Policy

    MERC is quite proud (rightly so) of its hydel power pricing policy. The main features of this are

    a. Hydel power has low O&M costs. The effective energy charge in the case of MSPGCLs hydrogenerating stations work out to be very minimal as the Annual Fixed Charge is far lesser than the

    other-wise applicable energy charges (variable cost of the least-cost, available alternative source

    of power). Therefore, economic value of power is not priced in.

    b. As the pricing of hydro generation fails to send any economic signal and, guided by Section 61 ofthe Electricity Act, 2003, which calls for economic use of resources, the Commission has decided

    to adopt a one part (energy based) differential peaking tariff (for peak and non peak hours) for

    hydel generation). The tariff for non-peak hours is based on the highest variable cost of the

    thermal generating stations, as Ideally, the peaking tariff should be the least cost available

    alternative source of power if such hydel generation is not available in those hours.

    c. The rationale for having differential peak and non-peak tariff is that hydro power should be usedonly during peak hours, and during non-peak hours it has to be used only in case of exigencies

    like grid stability requirements, etc.

    d. 5% of excess recovery of peak generation to be shared between Genco & Distribution company,rest to passed on to users as rebate. But if peak generation < target (except for uncontrollable

    factors), then the revenue loss would not be trued up, but borne by Genco & Distribution

    company in ratio of 50:50. Hence, economic price signals are sent but users do not suffer.

    e. The rationale for having differential peak and non-peak tariff is that hydro power should be usedonly during peak hours, and during non-peak hours it has to be used only in case of exigencies

    like grid stability requirements, etc.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    19/24

    General MERC Order Analysis- Quality and Consistency

    We notice that MERC does issue speaking orders discussing the utility stand, opposite views and its own

    analysis. While the reasons/rationale for the order is quite clear, at times it is perverse to the regulated

    entity due to interpretation adopted. For example, AAD station wise, coal costs, O&M expenses were all

    calculated adversely to Mahagenco, without considering the plain text of regulations as applied to

    Mahagenco. That led to an appeal.

    There are very few errors of fact or law in the order. In the ATE orders we examined, there were no

    strictures passed against MERC/loss on this ground. Instead, the main disagreements happened in policy

    issues-essentially whether the norms of MERC were too strict. When ATE sided with Mahagenco

    (largely), this induced cascading effect on ROE, working capital, interest etc.

    Some ATE order extracts are below, with our comments in italics.

    1. The MERC Regulations did not specify any norms relating to admissibility of A&G expenses andhad approved the expenses based on the principle of reasonable year-on-year increase. The ATE

    critiqued the MERC order stating that it did not explain the reasonableness of selecting escalation

    rate of which is not even sufficient to mitigate the inflation rate. Essentially, it was not a speaking

    order. Also, the escalation factor had not been determined in advance by the regulations but was

    arbitrary

    2. Again for A&G norms, there being no laid down norms, any expenditure incurred on generationand purchase of energy was to be permitted for pass-through in tariff as per Sixth Schedule of

    Electricity Supply Act, 1948. This finding by ATE indicates that where there are no norms, any

    determination of norms post facto is likely to be struck down as arbitrary OR determined in

    favour of the utility

    3. For A&G expenses, Mahagenco came up with an interesting ratio of gross A&G expenses perMW generated. Its argument was that the gross A&G expenses averaged over the capacity in

    MW gives A&G expenses per MW to be 0.347 which is still less than what is allowed in the case

    of TPC and REL. Given the technical complexity, geographic dispersion, employee strength etc

    for Mahagenco compared to other utilities, ATE found a strong basis in that argument, and

    directed MERC to recomputed expenses.

    4. The SHR(Station Heat Ratio) targets set by MERC was not being achieved, therefore leading tolower tariffs due to under absorption of fixed costs/no efficiency gains. Observing that this

    practice did not benefit either the utility or the consumer (since wrong price signals), MERC

    mandates a scientifically determined ratio.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    20/24

    5. The MERC regulations did not stipulate anything about recovery of incentive. While MERC haddirected quarterly basis in the order, the utility wanted it monthly, and put forth the logical

    argument of synchrony with billing cycle. Hence, that argument was upheld by ATE.

    6. MERC disallowed the normative fuel cost as per the recommendations of CPRI for the years2005-06 to 2007-08 and restricted the fuel cost to the actuals, from the year 2008-09 onwards the

    norms as recommended by the CPRI have been followed. For 2008-09 to 2010-11 also the actual

    fuel cost should have been allowed or else the norms as recommended by the CPRI should have

    been used. Any other approach seems cherry picking of approaches in our view

    7. Coal costs is a major cost component but MERC had not provided detailed cost sheet workings toMahagenco, due to which inconsistent figures were there and appeals were preferred. Hence ATE

    ordered MERC to provide detailed workings of coal cost to Mahagenco. This is another example

    of needing transparency and two way information sharing between regulator and regulated

    enterprise.

    After studying the ATE orders in respect of Mahagenco/MERC, we infer that the main reasons for appeal

    were transparency (coal costs, reasons for exclusions, post facto regulations) and extraneous policy issues

    by MERC (disallowing AAD station wise, SHR factors).

    Barring the issue of coal costs,MERC has largely issued speaking orders, which have either been

    upheld/overruledby ATE without the need/request to adduce additional evidence. This speaks volumes

    for the quality of the regulatory orders. Maybe this is because MERC inducts retired utility officers to act

    as its Regulatory Experts. These people having decades of experience on the other side, can help the

    commission detect issues in implementation/genuine problems, and thereof build processes to ensure fair

    and speaking orders.

    There appears scope for improvement procedurally.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    21/24

    Is MERC playing the game well?

    Earlier, we modeled the tariff fixation process as a game where barring the regulator, every other player

    looks to its own parochial interests. This is not a stinging indictment of the process, but a mere

    recognition that in any political scenario (this IS one given the somewhat vague performance accounting

    norms & policy issues at stake), there are bound to be winners and losers. We note that Mahagenco being

    a state owned utility is constrained from subverting regulatory officials with corrupt practices. Therefore,

    one would expect a more stringent approach with Mahagenco than other utilities, which was partly borne

    out in the lower (per MW generated) O&M expenses allowed by MERC, which was afterwards felt as

    unfair by the ATE.

    One needs to know the game well to play it. MERC was fully acquainted with the situation of

    Mahagenco, having advised the Maharashtra Govt. on unbundling. Yet, it did not factor in those relaxed

    standards, leading to sustained under recovery of costs which was not trued up later. On the halter of

    efficiency, Mahagencos path dependency (reliance on poorly maintained systems, utility of last resort,

    state owned incumbent) was ignored. This is possible in a price cap situation but not for a normative cost

    plus situation where path dependency counts.

    MERC also, in our opinion, gets too hyper technical at times, forgetting the wider policy issues at play.

    For example, stricter unachievable norms imposed without a technical study violates principles of

    natural justice. Still, all is not lost. It has hopefully learnt from its earlier mistakes.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    22/24

    Overall Observations

    1. Path Dependency:- Following the hallowed legal doctrine of res juditica, the MERC prefers tofollow the reasoning laid down in its earlier orders. While this ensures regulatory consistency, it

    also results in a tariff shock if the earlier orders are revised with retrospective effect because of an

    ATE verdict favouring the utility.

    2. Maharashtra Govt. /erstwhile MSEB cash crunch:- This lead to deferring O&M/Capexexpenses and thus giving the impression of MSEB being the lowest cost power producer, while

    this was because of deferring of vital expenses. The MERC recognized this, and allowed one-time

    additional O&M (to make up for earlier year deficits) and relaxed norms. Mahagenco was entitled

    to 70:30 debt equity ratio for incremental capex, but has applied for 80:20 or even 100% debt-

    stating that GoM (Government of Maharashtra) would not infuse additional equity funds for new

    projects. This is astounding to say the least.

    3. Game Theory:-While reading the petitions/submissions/MERC reasoning, we got the feelingthat this situation is amenable to a game theory analysis, because this is a recurring situation

    where all participants play well defined roles.

    a. The regulated utility wants to overstate its estimated costs, so that it can get moreefficiency gains when it achieves lower actual. Also, even if tariff is adjusted

    downwards, it still gets interest free use of the surplus till the adjustment order which

    takes atleast a year. This incentive applies for overstating capex by capitalizing O&M

    expenses, and also gold plating to ensure higher rate of return.

    b. End Customers seek the lowest estimated costs so that they can pay lower tariffs. Whilethis will not help as the deficits are recoverable with interest in future truing up periods,

    they can still manage their cash flows better. That is why both individual consumer

    associations and industrial consumers like Tata Motors vehemently challenge each cost

    items rationale, amount and spending efficiency.

    c. Distribution companies see the generation cost as a 100% pass through to theircustomers, and so have rarely contested/attended the tariff hearings/technical validation

    sessions. This is although they are the direct generation customers, and in a sense most

    affected by the generation companys actions.

    d. Other generation companies oppose capex/plant location decisions at times forcompetitive reasons, because though generation capacity addition is de-licensed, the

    MERC still has the tariff setting authority and therefore carries out prudence checks.

  • 8/3/2019 MERC Generation Tariff Order Analysis

    23/24

    e. The State Government desires to cross subsidize its vote bank (farmers/individuals) atthe cost of industrial users. Therefore, the direction to the MERC includes the aspect of

    perpetuating cross subsidy.

    f. The regulator(MERC) itself must play a fine balancing act between ensuring theeconomic health of the generation company, and ensuring that the company has every

    incentive to maximize its efficiency and operate at minimal costs. While mechanisms like

    efficiency sharing gains (hydel, PLF>80% etc) do it, the main approach adopted is to

    estimate normative costs.

    4. Cost Accounting matters:- Instead of merely extrapolating incurred costs and calculating ROE,the MERC checks the prudence of those costs (aka performance audit), and then checks

    whether cost changes were controllable or uncontrollable. Controllable cost changes are mainly

    (2/3rd

    ) kept with the utility but uncontrollable cost changes are passed on to customers.

    5. Regulations fill data void:-The MERC regulations contain certain default technical parametersdepending on equipment used in plant. If the utility does not maintain reliable records, then these

    parameters are used. This was done for O&M costs, auxiliary factors etc for the period where

    Mahagenco did not maintain adequate records. This is akin to composition scheme/best

    judgement assessment under the IT Act 1961!.

    6. Developmental role-MERC had passed strictures on Mahagenco(detailed below) asking it tosegregate plant wise accounts, improve coal handling/purchase systems, streamline O&M

    management, instill proper capex planning scheme etc. These internal functions of Mahagenco

    had to be pushed for by the regulator.

    7. Petition Scrutiny does benefit MSPGCL at times-MSPGCL had at times sought lower interestrate than the prevailing market rates, and MERC suo moto granted the higher rates. Similarly for

    D/E ratio, MSPGCL even petitioned for 100% D/E ratio due to cash crunch from Govt. equity,

    but MERC allowed at 80%, thus ensuring in higher tariffs. D/E ratio, interest rate where MERC

    had adversely

    8. Gentle balancing act:- While the over arching objective of MERC seems to protect the interestof consumers in the State of Maharashtra(its reasons for prohibiting Load Management charge,

    high hydel lease fees, restricting interstate sales etc), it also keeps the interest of the generator in

    mind while deciding ROE, efficiency sharing gains etc.

    9. Use of incentives:- MSPGCL can keep 2/3rd of its efficiency gains/losses, while passing on 1/3rdto the distribution entity. Interesting, fuel costs being seen as a mix of controllable (consumption)

    and non controllable (procurement price), its pass through is allowed via Fuel Adjustment

  • 8/3/2019 MERC Generation Tariff Order Analysis

    24/24

    Charge mechanism, which encourages prudent short term power purchase practices. Other

    uncontrollable costs are passed through in full.

    10.Hydel Power incentive structure:- Unlike thermal plants where the utility owns the plant, hydelprojects are built by the State irrigation department, and then handed over to Mahagenco, in

    return for lease rent which encompasses ROE to GoM. Mahagenco is allowed by MERC merely

    to recover actual O&M expenses, on no profit no loss basis. Since it does not own the plant, there

    is no ROE/return given. Mahagencos request for an operating fee was shot down as no place in

    MERC regulations for this. The request does seem fair though, considering that virtually no

    efficiency gains/incentives exist for Mahagenco under the present tariff regulations.

    11. Truing Up:- Actual expenses and the actual revenue will be trued up at the end of the year basedon audited financial results and subject to a prudence check. Provisional truing up of certain

    elements of ARR is considered in cases where the impact is very high, or there is a change in the

    principles/methodology, or due to revision in capital expenditure/capitalization figures