[memorandum regarding national remedy ...apr 1 2 2016 memorandum subject: national remedy review...

65
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION6 1445 ROSS AVENUE, SUITE 1200 DALLAS TX 75202-2733 APR 12 2016 MEMORANDUM SUBJECT: National Remedy Review Board Revie American Creosote Works Inc. SuR rfl FROM: TO: Carl E. Edlund. P. E. , Directo Superfund Division (6SF) James E. Woolford, Director roposed Response Action Office of Superfund Remediation and Technology Innovation (OSRTI) Introduction and Purpose This memorandum provides Region 6's rationale that the proposed response action at the American Creosote Works Inc. (ACW) Superfund site in Winnfield, Louisiana, does not warrant a National Remedy Review Board (NRRB) review. The Office of Solid Waste and Emergency Response (OSWER) Directive 9285.6-21 (National Remedy Review Board Criteria Revision and Operational Changes, September 4, 2014), call for regions to implement a regional remedy review team (RRRT) to evaluate Superfund site response actions costing between $25 million and $50 million to determine if a full NRRB is warranted or not. The preferred proposed response action at the ACW site is estimated to cost $25 million. The Region 6 RRRT reviewed the ACW proposed remedy and recommended that a full NRRB review is not warranted. The Site Remedial Project Manager has had several conversations over the last 2 years concerning development of the proposed response action with Office of Superfund Remediation and Technology Innovation (OSRTI) staff within the Assessment and Remediation Division and the Technology Innovation and Field Services Division. Regional Remedy Review Team Process The Region 6 RRRT was comprised of the Remedial Branch Chief (John Meyer), two Remedial Section Chiefs (Carlos Sanchez and Blake Atkins), the State of Louisiana ACW site project manager (John Halk), four senior Remedial Project Managers (RPMs) familiar with similar proposed remedy technologies (Vincent Malott, Camille Hueni, David Abshire, and Ursula Lennox), the site risk assessor (Kenneth Shewmake), a senior risk assessor who has previous experience with the site (Jon Rauscher), the site attorney (Jacob Piehl), the site enforcement officer (Bob Werner), and a community involvement staff member (Adam Weece). Internet Address (URL) • http://www.epa.gov/region6 Recycled/Recyclable • Printed with Vegetable Oi l Based Inks on 100% Recycled Paper, Process Chl orine Free 022095

Upload: others

Post on 03-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION6

    1445 ROSS AVENUE, SUITE 1200 DALLAS TX 75202-2733

    APR 1 2 2016

    MEMORANDUM

    SUBJECT: National Remedy Review Board Revie American Creosote Works Inc. SuR rfl

    FROM:

    TO:

    Carl E. Edlund. P.E. , Directo Superfund Division (6SF)

    James E. Woolford, Director

    roposed Response Action

    Office of Superfund Remediation and Technology Innovation (OSRTI)

    Introduction and Purpose

    This memorandum provides Region 6' s rationale that the proposed response action at the American Creosote Works Inc. (ACW) Superfund site in Winnfield, Louisiana, does not warrant a National Remedy Review Board (NRRB) review. The Office of Solid Waste and Emergency Response (OSWER) Directive 9285.6-21 (National Remedy Review Board Criteria Revision and Operational Changes, September 4, 2014), call for regions to implement a regional remedy review team (RRRT) to evaluate Superfund site response actions costing between $25 million and $50 million to determine if a full NRRB is warranted or not. The preferred proposed response action at the ACW site is estimated to cost $25 million. The Region 6 RRRT reviewed the ACW proposed remedy and recommended that a full NRRB review is not warranted.

    The Site Remedial Project Manager has had several conversations over the last 2 years concerning development of the proposed response action with Office of Superfund Remediation and Technology Innovation (OSRTI) staff within the Assessment and Remediation Division and the Technology Innovation and Field Services Division.

    Regional Remedy Review Team Process

    The Region 6 RRRT was comprised of the Remedial Branch Chief (John Meyer), two Remedial Section Chiefs (Carlos Sanchez and Blake Atkins), the State of Louisiana ACW site project manager (John Halk), four senior Remedial Project Managers (RPMs) familiar with similar proposed remedy technologies (Vincent Malott, Camille Hueni, David Abshire, and Ursula Lennox), the site risk assessor (Kenneth Shewmake), a senior risk assessor who has previous experience with the site (Jon Rauscher) , the site attorney (Jacob Piehl), the site enforcement officer (Bob Werner), and a community involvement staff member (Adam Weece).

    Internet Address (URL) • http://www.epa.gov/region6 Recycled/Recyclable • Printed with Vegetable Oil Based Inks on 100% Recycled Paper, Process Chlorine Free

    022095

  • On February 25, 2016, the RPM presented the following information to the Region 6 ACW RRRT:

    ACW site setting and background

    Overview of current remedy

    Rationale for initiation of a Revised FS and alternate remedy strategy

    Summary of revised risk assessment results

    Areas of the ACW site that have unacceptable risks

    Proposed Remedial Action Objectives

    Summary of Remedial Action Alternatives

    Summary of Nine Criteria Evaluation

    Detailed description of the preferred response action, including IC’s and cost

    Key factors for proposing the preferred response action

    Timing of activities concerning the preferred response action

    Potential issues that could affect implementation of the preferred response action

    Summary of OSWER Directive 9285.6-21 stakeholder/site circumstances issues

    After the RPM’s presentation, Mr. John Halk, the State of Louisiana ACW site project manager presented

    the State’s perspective concerning the ACW site. Mr. Halk has been the State’s project manager on the

    site for over 20 years and has been intimately involved in the development of the Revised RI/FS. Mr.

    Halk indicated that the State does not see the benefit from continuing operations of the current remedy

    and therefore, is in agreement with and supports EPA’s preferred remedy. After Mr. Halk’s comments,

    the ACW RRRT engaged in questions and deliberations with the Site RPM. Comments provided by the

    RRRT during the February 25, 2016, meeting are attached along with responses from the Site RPM.

    Site Information and Proposed Response Action

    The ACW site is located (see Figure 1) in the City of Winnfield in Winn Parish, Louisiana. Decades of

    wood treating activities and improper waste disposal contaminated soil, sediment, surface water and

    groundwater with polycyclic aromatic hydrocarbons (PAHs), pentachlorophenol (PCP), benzene and

    dioxin. The EPA placed the Site on the National Priorities List in October 1992. Removal actions in the

    late 1980s addressed immediate threats to human health and the environment. EPA selected a long-term

    remedy to address remaining contamination in a 1993 Record of Decision (ROD). Cleanup began in 1993

    and included on-site incineration of highly contaminated tar and sludge; capping of contaminated surface

    soil; in-place biological treatment of contaminated subsurface soil; and extraction, separation and

    treatment of groundwater and non-aqueous phase liquids (NAPLs).

    Due to several years of declining remedy performance and growing concerns of the long-term

    effectiveness of the Site’s NAPL recovery and in-place biological treatment systems, EPA initiated an

    evaluation in 2010 to develop a more sustainable remedy. Incremental funding resulting from budget and

    resource constraints delayed the initiation and/or completion of various activities of this evaluation. EPA

    completed a new remedial investigation in April 2014. The 2014 Remedial Investigation Report verified

    that the Site’s treatment systems are not effectively addressing remaining site contamination, and also

    discovered the presence of site related soil contamination outside of the Site’s previously-established

    boundary.

    The revised risk assessment evaluated seven different areas (Figure 2), called Decision Units (DU). The

    Site was divided into these seven DU’s to facilitate risk management decisions that would be incorporated

    into a revised remedy. The seven DU’s that were evaluated were:

    022096

  • 1. Southern DU (15.6 acres). This area, also known as the south parcel in the 1992 RI/FS and 1993

    ROD, was reportedly used primarily to store untreated wood. Some non-recyclable scrap metal

    and other non-hazardous debris generated during the 1987-1989 removal actions was reportedly

    buried here. The area is now principally owned by the Winn Parish Police Jury. EPA released this

    area for use in 1998. The Police Jury leases the property to a local earthwork contractor.

    2. Process Area DU (14.2 acres). This area, which is part of the north parcel described in the 1992

    RI/FS and 1993 ROD, is where historical wood-treatment operations were conducted. Four

    impoundments, where liquid wood-treating wastes were managed, and a waste cell containing

    stabilized material from the 1987 removal action and 7,000 CY of low-level contaminated soil

    excavated from the Tar Mat Disposal Area are also present. This DU, and the adjacent Non-

    Process Area and Tar Mat DUs, are principally owned by Winn Parish but under the control of

    EPA through an access agreement and a perimeter fence. The ongoing NAPL recovery and in situ

    bioremediation remedy in this DU is addressing the subsurface source of contamination in this

    DU.

    3. Non-Process Area DU (10.5 acres). This area lies to the east and southeast of the Process Area DU

    and contains the fire water pond. This area also contained a portion of the tarry sludge-like

    material, which was excavated and incinerated between 1996 and 1998.

    4. Tar Mat DU (2.4 acres). This area contained a majority of the 25,000 CY of tarry sludge-like

    material, which was excavated and incinerated between 1996 and 1998. The ash generated from

    the incineration of this material was placed in the Tar Mat Ash disposal area, a geotextile-lined

    and clay-covered disposal cell located in this DU.

    5. Northern DU (9.9 acres). Treated wood was transported by rail from the former process area to

    this area for drying and staging prior to customer shipment.

    6. Creek DU (4.7 acres). This area includes the far western, western, and northern branches of

    Creosote Branch Creek that flows through the ACW site. Site-related contaminants were detected

    in sediment samples taken from the creek during the 1992 RI/FS and in samples collected in 2008

    and 2013.

    7. Western DU (4.3 acres). This area contained ACW’s former administration offices. A bridge

    across the western branch of Creosote Branch Creek, which has since been removed, provided

    access to the former process area where wood-treating operations were conducted.

    The additional site information collected post-1993 ROD was utilized to develop an updated risk

    assessment. This revised risk assessment identified the following major contaminants of concern (COC):

    ● Volatile organic compounds – benzene, toluene, ethylbenzene, and xylene (BTEX)

    ● Phenols – PCP, phenol, 2,3,4,6-tetrachlorophenol, 2,3,5,6-trichlorophenol, and cresols

    ● PAHs – naphthalene, phenanthrene, fluorine, anthracene, and benzo(a)pyrene

    ● Dioxins/furans

    The post-1993 site remedy investigation activities performed in 2003, 2008, 2012, and 2013 confirmed

    the presence of the above COCs in all the above 7 DU’s. Based upon the evaluation performed during the

    revised risk assessment, there was unacceptable risk in three of the seven DU’s. These three DU’s and

    their associated unacceptable risks (Tables 1, 2, and 3) are as follows:

    022097

  • 1. Northern DU – surface soil. Maximum‐based intake (doses) for the deer mouse yielded No Observed Adverse Effect Level based HQ’s ranging from 3.4 to 30.4, which exceeds the

    CERCLA target ecological HQ of 1.0.

    2. Non‐Process Area – surface soil. The industrial worker excess lifetime cancer risk (ELCR)

    of 8.3 x 10‐4 exceeded the upper bound CERCLA target risk of 1 x 10‐4.

    3a. Process Area – surface and subsurface soil. The industrial worker surface soil ELCR of 2.9 x 10‐4

    exceeded the upper bound CERCLA target risk of 1 x 10‐4. The industrial worker subsurface soil

    ELCR of 1.4 x 10‐3 also exceeded the upper bound CERCLA target risk of 1 x 10‐4.

    3b. Process Area and Non‐Process Area shallow aquifer groundwater impacted by the source area. Groundwater was carried forward into the FS based on the following considerations:

    - Shallow aquifer groundwater is not a current (Class IIA) drinking water source; however, based

    on EPA groundwater classification guidance (EPA, 1986a) it is considered a potential future

    (Class IIB) drinking water source. Per the NCP (40 CFR 300.430(a)(1)(iii)(F)), “EPA expects to

    return usable ground waters to their beneficial uses wherever practicable, within a timeframe that

    is reasonable given the particular circumstances of the site. When restoration of ground water to

    beneficial uses is not practicable, EPA expects to prevent further migration of the plume, prevent

    exposure to the contaminated ground water, and evaluate further risk reduction.”

    - The concentration of several site‐related contaminants present in groundwater around the source area exceeds MCLs, which define chemical‐specific ARARs for groundwater that is a current or future drinking water source. For example, the BAP TEQ exposure point concentration of 351

    μg/L exceeds the 0.2 μg/L MCL. Exceedance of one or more chemical-specific ARARs is the

    primary basis for carrying shallow aquifer groundwater into the FS.

    - Shallow aquifer groundwater is in hydraulic communication with Creosote Branch Creek. Under

    the baseline (no action) condition, it is assumed that contaminated groundwater discharge to the

    creek would result in surface water contaminant concentrations exceeding federal or state ambient

    water quality criteria (AWQC).

    Revised Remedial Action Objectives (RAO) were developed as part of the revised Remedial

    Investigation/Feasibility Study (RI/FS).

    The 1993 ROD listed the following RAO’s:

    1. For shallow groundwater, prevent the exposure of potential receptors to on-site contaminated

    groundwater in amounts above human health-based standards and to restore groundwater quality.

    2. Remove the threat of potential exposure to future residents via direct contact with contaminated

    surface soils, tar mat materials, and non-aqueous phase liquids (NAPL’s).

    3. Reduce the potential for site contaminants to migrate into surface waters or groundwater.

    Based on the findings of the human health and ecological revised risk assessment, remedial action at the

    Site must address the following receptors and exposure pathways:

    ● Terrestrial ecological receptor direct-contact risk associated with PAH’s present in the Northern

    DU surface soil.

    ● Industrial worker/Construction worker direct-contact risk associated with BAP TEQ, dioxin TEQ,

    PCP, naphthalene, and other COC’s present in the Process Area DU surface/subsurface soil.

    022098

  • ● Industrial worker direct-contact risk associated with dioxin TEQ present in surface soil in the Non-

    Process Area DU. Remedial actions that address dioxin TEQ are also expected to reduce BAP

    TEQ direct-contact risk.

    Under the current remedy, there is no unacceptable risk associated with human or ecological exposure to

    COC's present in Creosote Branch Creek surface water or sediment. In the absence of remedial action,

    shallow aquifer groundwater discharge to Creosote Branch Creek would likely result in surface water

    COC concentrations exceeding ARAR’s or to-be-considered (TBC) guidelines. Therefore, remedial

    action must also address:

    ● Ecological and secondary-contact recreational exposure to COC’s present in Creosote Branch

    Creek surface water attributed to Process Area shallow aquifer groundwater discharge.

    Based on the above human health and ecological risks that need to be addressed as determined by the

    revised risk assessment (included in the Revised RI/FS), RAO’s (i.e., new, retained from 1993 ROD,

    revised from the 1993 ROD, or eliminated from the 1993 ROD) for the Site are:

    RAO #1 - Prevent industrial worker/construction worker exposure to surface/subsurface soil

    contaminants of concern exceeding health based cleanup levels in the Process Area and

    Non Process Area Decision Units. (New RAO based upon Revised RI/FS)

    RAO #2 - Prevent terrestrial ecological receptor communities exposure to soil contaminants of

    concern (Polycyclic Aromatic Hydrocarbons) above ecological risk based cleanup levels in

    the Northern Decision Unit. (New RAO based upon Revised RI/FS)

    RAO #3 - Minimize aquatic and secondary contact recreational receptors from exposure to the

    contaminants of concern present in groundwater discharging to Creosote Branch at

    concentrations exceeding health based and ecological based cleanup levels. (Revised 1993

    ROD RAO based on Revised RI/FS)

    RAO #4 - Minimize further migration of contaminants of concern from source materials to

    groundwater. (Retained RAO from 1993 ROD)

    RAO #5 - For shallow ground water, prevent the exposure of potential receptors to on-site

    contaminated ground water in amounts above human health-based standards and to restore

    ground water quality. (Retained from 1993 ROD)

    With the anticipated future land use being commercial/industrial based on the Revised RI/FS, the RAO

    from the 1993 ROD – Remove the threat of potential exposure to future residents via direct contact with

    contaminated surface soils, tar mat materials, and non-aqueous phase liquids (NAPL’s) – is replaced with

    the new RAO #1 above.

    Based upon the above risks, the Revised RI/FS developed preliminary remediation goals (PRG’s)(see

    Table 4). PRG’s define the allowable concentration of COC’s in environmental media that must be

    achieved at the completion of the remedial action based on expectations for current and future land,

    groundwater, and surface water beneficial use. PRG’s are also helpful in defining the area and volume of

    environmental media to be addressed by a remedial action and to assist in the screening of various

    technologies. Because there are no Federal or State cleanup standards for soil contamination, the PRG’s

    for soil are based upon the revised risk assessment. PRG’s for surface water are a combination of federal

    022099

  • and state ambient water quality criteria (AWQC) and other to-be-considered guidelines for the protection

    of aquatic receptors and secondary-contact recreation human exposure.

    EPA Region 6 evaluated seven detailed alternatives (see Table 5) in the Revised FS, which include (1) No

    Action, (2) Institutional Controls with Long-Term Monitoring and Targeted Hot-Spot Excavation, (3)

    Upgrade NAPL Recovery and Treatment System and Targeted Hot-Spot Excavation, (4) Slurry Wall and

    Multi-Layer Cap and Targeted Hot-Spot Excavation, (5a) Partial-Depth Excavation with Thermal

    Desorption and Thermal-Enhanced NAPL Recovery, (5b) Full-Depth Excavation with Thermal

    Desorption, and (6) In Situ Solidification/Stabilization and Targeted Hot-Spot Excavation. While

    presented for transparency, Alternative 2 was eliminated since it does not meet Threshold Criteria and

    Alternative 5b was eliminated in the FS screening process due to implementability and cost. The above

    alternatives are described below.

    Common Elements

    Common elements for the alternatives except for Alternative 1 – No Further Action are described below.

    Preconstruction Activities – These activities associated with most of the alternatives include subcontractor

    submittals, preparation of community involvement plan and periodic meetings to inform the community,

    subcontractor mobilization and demobilization, installation of temporary facilities, underground utility

    location survey, and construction surveying.

    Institutional Controls – Per NCP requirements [40 CFR 300.430 (e)(3)(ii)], it is expected that IC’s, either

    as a standalone alternative or as a component of alternatives employing more aggressive technologies,

    would be included as appropriate to prevent or limit exposure to hazardous substances. The individual

    IC’s include restrictions that limit land use to industrial/commercial, prevent deep excavation to protect

    construction workers, and groundwater use restrictions in the Process Area, Non-Process Area, and Tar

    Mat DU’s. Land use IC’s will be implemented through restrictive covenants written into property deeds

    and would vary based on the alternative.

    Northern DU Soil Excavation and Offsite Disposal – The revised risk assessment identified ecological

    risk to invertebrates and terrestrial receptors through direct and indirect exposure to PAH’s in surface soil.

    To achieve an acceptable level of risk, a remediation strategy will be used that is the least invasive to the

    existing and functioning habitat while still facilitating DU-wide risk reduction. Sampling will be

    performed to provide data in order to minimize that volume of surface soil that needs to be addressed.

    These volumes of contaminated surface soil will be excavated, transported, and disposed of off-site.

    Clean fill will be imported and hydroseeded to re-establish vegetation.

    Creosote Branch Creek Bank and Western Fence Soil Excavation – Contaminated areas along the

    northern and western fence line near Creosote Branch Creek lie outside the portion of the source area that

    can be addressed by the primary technologies included in each alternative. If not addressed, these areas

    will act as continuing sources of contamination. Of the technologies evaluated to address soils,

    excavation is the only one capable of effectively removing soil contamination is these areas. As in the

    Northern DU Soil Excavation common element above, sampling will be performed in these areas near the

    creek to minimize the volume of soil that needs to be addressed. Once excavated, the contaminated soils

    will be disposed of off-site. The creek excavation areas will replaced with clean fill and constructed to

    maintain creek bank integrity.

    Five Year Reviews - The NCP, under 40 CFR 300.430(f)(4)(ii), requires that periodic reviews be

    conducted if a remedial action is selected that results in hazardous substances, pollutants, or contaminants

    022100

  • remaining at the site above levels that allow for unlimited use and unrestricted exposure. These reviews

    are conducted no less often than every 5 years after the selected remedial action is initiated. Four five‐year reviews (5YR) have been performed to date, with the last 5YR conducted in 2015. The 5YR would

    continue in perpetuity until such a time that the industrial land use IC can be lifted (e.g., DUs released for

    unrestricted use/unrestricted exposure).

    Current Remedy - The on-site incineration of highly contaminated tars and sludges has been completed.

    The pumping, separation, and treatment of liquid contaminants and the in-situ bioremediation components

    of the 1993 ROD which were designed to address the subsurface source of shallow ground water

    contamination are being replaced by the proposed remedy. A new soil cover to protect the in-situ

    solidification/stabilization area will replace the capped surface soils completed under the current remedy.

    The goal of restoring ground water to its potential beneficial use is retained from the 1993 ROD and

    applies to the shallow ground water impacted by the source area.

    The capital cost for the Common Elements is $1.6 million.

    Alternative 1 – No Further Action

    Estimated Capital Cost: $540,000

    Estimated Annual O&M Cost: $0

    Estimated Periodic Cost: $100,000

    Estimated Present Worth Cost: $640,000

    Estimated Construction Timeframe: 1 year

    Estimated Time to Achieve RAOs: N/A

    Section 300.430 (e)(6) of the NCP requires the inclusion of a no action alternative in the RI/FS, or a no

    further action alternative if an interim or final action is already underway, for use as a baseline to compare

    against other alternatives. Under this alternative, no further action would be taken in Northern and Non-

    Process Area DUs, while in the Process Area DU all recovery wells, injection wells, monitor wells,

    piezometers, and horizontal recovery trenches (extraction, injection, and infiltration) would be plugged

    and abandoned, operation of the PLTS would cease with all process equipment being decontaminated and

    decommissioned, and all underground and aboveground conveyance piping removed, decontaminated,

    and decommissioned.

    Alternative 1 requires the abandonment of all groundwater monitor wells, extraction wells, and injection

    wells as well as the decontamination and decommissioning of the PLTS and associated equipment. The

    general duration of Alternative 1 is estimated at 9 months. The present worth cost for this alternative is

    estimated at $640,000 with a ‐30/+50 percent cost range of $448,000 to $960,000. Per the NCP (40 CFR 300.430), the no action alternative was carried through the detailed evaluation but was not retained since

    it would not provide any protection to human health and the environment.

    Alternative 2 – Institutional Controls with Long-Term Monitoring and Targeted Hot Spot Excavation

    Estimated Capital Cost: $7.6 million

    Estimated Annual O&M Cost: $73,000

    Estimated Periodic Cost (every 5 years): $295,000

    Estimated Present Worth Cost: $8.5 million

    Estimated Construction Timeframe: 1 year

    Estimated Time to Achieve RAOs: Greater than 100 years

    022101

  • Alternative 2 utilizes an array of overlapping access controls to prevent exposure to contaminated soil and

    groundwater. This alternative satisfies the NCP requirement to develop an alternative that involves little

    or no treatment and protects human health and the environment by preventing or controlling exposure to

    contaminants through engineering controls and, as necessary, ICs. This alternative includes the common

    elements listed above, extension of perimeter fencing, the abandonment of all groundwater monitor wells,

    extraction wells, and injection wells as well as the decontamination and decommissioning of the PLTS

    and associated equipment, installation of a multi-layer soil cover (approximately 11 acres) in the Process

    Area DU to provide a direct-contact barrier and prevent rainfall-induced leaching of contaminants present

    in soil, long-term monitoring of groundwater and surface water to assess potential impacts to Creosote

    Branch Creek, and long-term maintenance of the multi-layer cap.

    Key components of Alternative 2 include the following:

    The common elements listed above.

    Extension of the perimeter fencing to the east to enclose the Non-Process Area DU, requiring an

    additional 1,000 ft of 6-foot cyclone fencing to be installed.

    Plugging and abandonment of all recovery wells, trenches, monitor wells, and piezometers, and

    decontamination and decommissioning of the PLTS and conveyance piping as described for

    Alternative 1.

    Installation of a multi-layer soil cap (11 acres) in the Process Area DU to provide a direct-contact barrier

    and to prevent rainfall-induced leaching of contaminants present in soil and their transport to the

    shallow aquifer.

    Long-term monitoring (LTM) of groundwater and surface water on a semi-annual basis with progress

    reports prepared annually to assess potential impacts to Creosote Branch Creek. The scope of LTM

    would be similar to that conducted currently.

    LTM and O&M of the Process Area DU multi-layer cap would be conducted for at least 100 years.

    Documentation of remedy performance and protectiveness in annual operation summary reports and

    5YRs.

    The total present worth for Alternative 2 is $8.5 million with a -30/+50 percent cost range of $6.0 million

    to $12.8 million. Alternative 2 was carried through the detailed evaluation but was not retained since it

    would not provide any protection to human health and the environment.

    Alternative 3 – Upgrade NAPL Recovery and Treatment System, and Targeted Hot-Spot Soil Excavation

    Estimated Capital Cost: $18.8 million

    Estimated Annual O&M Cost: $644,000

    Estimated Periodic Cost (every 5 years): $126,000, Additional periodic cost of $3.68 million for PLTS

    replacement (year 30 & 60) and extraction well and trench replacement (year 50)

    Estimated Present Worth Cost: $28.5 million

    Estimated Construction Timeframe: 2 years

    Estimated Time to Achieve RAOs: Greater than 100 years

    Alternative 3 is a continuation of the current fluids recovery and in situ bioremediation remedy

    component implemented under the 1993 ROD. In addition to the common elements, this alternative

    022102

  • would include excavation and off-site disposal of dioxin contaminated soil in the Non-Process DU,

    replacement and expansion of the soil cover in the Process Area DU, and upgrade/replacement of the

    PLTS and the extraction/injection wellfield components to increase NAPL recovery and provide for

    improved groundwater treatment.

    Key components of Alternative 3 include the following:

    The common elements listed above.

    A remedial design investigation in the Non-Process Area DU to refine the surface soil excavation

    footprint with excavation and offsite disposal of dioxin TEQ-contaminated soil at a RCRA treatment,

    storage, and disposal facility (TSD).

    Replacement of the north recovery trench and deep injection trench using one-pass technology.

    Rehabilitation of all existing extraction wells through chemical addition and mechanical swabbing.

    Conversion to a two-pump extraction system for groundwater and NAPL recovery.

    Decontamination and decommissioning of the current system.

    Upgrade of the PLTS building and treatment train.

    Upgrade of the PLTS electrical and instrumentation and control (I&C) systems to provide greater

    remote/offsite operations and improved reliability.

    Replacement and expansion of the soil cover in the Process Area DU using a multi-layer cap to prevent

    rainfall infiltration and limit vertical migration of COCs and NAPL in the vadose zone.

    100 years of O&M. It is assumed the recovery wells and PLTS mechanical equipment will require

    replacement approximately every 30 years.

    Periodic sampling, analysis, and reporting to: 1) confirm PLTS treatment effectiveness, 2) assess the need

    for treatment media change-out, and compliance with potential discharge criteria, 3) assess COC

    concentration changes, and 4) verify hydraulic containment of the dissolved-phase plume.

    Documentation of remedy performance and protectiveness in annual operation summary reports and

    5YRs.

    The total present worth cost for Alternative 3 is $28.5 million with a -30/+50 percent cost range of $19.9

    million to $42.3 million.

    Alternative 4 – Containment with Slurry Wall and Surface Multi-Layer Cap, and Targeted Hot-Spot Soil

    Excavation

    Estimated Capital Cost: $17.6 million

    Estimated Annual O&M Cost: $117,000

    Estimated Periodic Cost (every 5 years): $295,000

    Estimated Present Worth Cost: $18.5 million

    Estimated Construction Timeframe: 2 years

    Estimated Time to Achieve RAOs: N/A

    Alternative 4 satisfies the NCP requirement to develop an alternative that involves little or no treatment

    and protects human health and the environment by preventing or controlling exposure to contaminants

    through engineering controls and, as necessary, ICs. In addition to the common elements, this alternative

    022103

  • would include excavation and off-site disposal of dioxin contaminated soil in the Non-Process DU, an

    approximate 2,600 foot long subsurface containment slurry wall would be installed with a multi-layer

    impermeable surface cap constructed to prevent infiltration into the area enclosed by the slurry wall, and a

    deep aquifer dewatering system which would prevent upward groundwater migration which could result

    in contaminants being pushed out of the containment area or failure of the slurry wall.

    Key components of Alternative 4 include the following:

    The applicable common elements listed above.

    Remedial design investigation and excavation of surface soil in the Non-Process DU as described under

    Alternative 3.

    Remedial design investigation to determine the extent of NAPL underlying the Tar Mat Ash DU, a deep

    aquifer pump test to determine the appropriate pumping rate needed to maintain a neutral vertical

    gradient between the shallow and deep aquifers to prevent flooding inside the containment area, and

    testing pits in the northwest corner of the Process Area DU (as necessary) to confirm that there is no

    subsurface debris present that would interfere with construction of the slurry wall.

    Abandonment and decommissioning of the existing groundwater extraction and injection wellfield as

    described under Alternative 1.

    Abandonment of 30 shallow/deep monitor wells in the Process Area DU. Ten wells located within the

    slurry wall footprint and four outside the footprint would be retained as long-term monitoring

    locations.

    Installation of a 2,600-ft-long slurry wall encompassing the soil, NAPL, and dissolved-phase COC plume

    where concentrations exceed PRGs within the Process Area DU.

    Install deep aquifer dewatering wells, number of wells determined based on the results from the pump

    test, it is assumed that pumping would be required for 100 years.

    Installation of a GAC treatment system to treat deep aquifer groundwater if necessary.

    Installation of a multi-layer cap over the area enclosed by the slurry wall.

    LTM to verify remedy effectiveness.

    The total present worth cost for Alternative 4 is $18.5 million with a -30/+50 percent cost range of $12.9

    million to $27.7 million.

    Alternative 5a – Partial-Depth Excavation with Thermal Desorption, and Thermal-Enhanced NAPL

    Recovery

    Estimated Capital Cost: $47.2 million

    Estimated Annual O&M Cost (years 4-14): $1.3 million

    Estimated Annual O&M Cost (years 15-100): $73,000

    Estimated Periodic Cost (every 5 years): $295,000

    Estimated Present Worth Cost: $45.7 million

    Estimated Construction Timeframe: 5 years

    Estimated Time to Achieve RAOs: 100 years

    Alternative 5a addresses the NCP requirement to develop an alternative which at a minimum treats the

    principal threats posed by the site but varies in the degree of treatment employed and quantities and

    characteristics of the treatment residuals. In addition to common elements, this alternative would include

    022104

  • excavation and treatment of soils down to 5 feet below ground surface, installation and operation of an

    enhanced NAPL recovery system that would utilize heated water to enhance NAPL recovery, and an in-

    situ barrier that would treat remaining ground water contamination as it discharges to Creosote Branch

    creek.

    Key elements of Alternative 5a include the following:

    The applicable common elements listed above.

    Remedial design investigation to determine the extent of NAPL underlying the Tar Mat Ash DU.

    Excavation of surface soil in the Non-Process Area DU as described in Alternative 3.

    Abandonment and decommissioning of the existing groundwater extraction and injection wellfield (as

    described under Alternative 1) with the exception of the north recovery trench and extraction wells R-

    19, -20, and -21. These would be operated to maintain hydraulic capture until the enhanced NAPL

    recovery system is operational.

    Excavation of soil from 0 to 5 ft bgs in the Process Area DU with COC concentrations greater than PRGs.

    Treatment of excavated soil onsite using medium-temperature thermal desorption (MTTD).

    Enhanced NAPL recovery using an array of alternating horizontal extraction and injection wells, installed

    east-west perpendicular to the groundwater flow direction, using one-pass technology. A total of 12

    wells is assumed.

    Inject hot water (125 degrees Fahrenheit [°F]) to induce hydraulic, thermal, and viscosity gradients to

    increase NAPL recovery. The effectiveness of this element and the design temperature are based on

    bench-scale pilot tests conducted in 2003.

    Upgrade of the PLTS (as described under Alternative 3). A heat exchanger would be installed at the head

    of the PLTS to recover heat from extracted groundwater.

    Installation of a multi-layer soil cap over the Process Area DU at the completion of enhanced NAPL

    recovery efforts.

    Installation of a funnel and gate permeable reactive barrier (PRB) as a polishing step for dissolved-phase

    groundwater treatment at the completion of enhanced NAPL recovery efforts, which are presumed to

    conclude after 10 years of operation.

    The total present worth cost for Alternative 5a is $45.7 million with a -30/+50 percent cost range of $32.0

    million to $68.6 million.

    Alternative 5b – Full-Depth Excavation with Thermal Desorption

    Estimated Capital Cost (nondiscounted): $101,000,000

    Estimated Annual O&M Cost (nondiscounted): $73,000

    Estimated 5 Year Periodic Cost (nondiscounted): $36,000

    Estimated Present Worth Cost: $91,000,000

    Estimated Construction Timeframe: 3 years

    Estimated Time to Achieve RAOs: 5 years

    Alternative 5b addresses the NCP requirement to develop an alternative that removes contaminants to the

    maximum extent practicable minimizing the need for long-term management. Alternative 5b is similar to

    022105

  • Alternative 5a but extends the excavation depth to the base of the contamination, removing all COCs

    exceeding the PRG.

    Key components of Alternative 5b include the following:

    The applicable common elements listed above.

    Remedial design investigation and excavation of surface soil in the Non-Process Area DU (detailed in

    Alternative 3)

    Abandonment and decommissioning of the existing groundwater extraction wellfield (detailed in

    Alternative 1).

    Excavation of soil from 0 to 30 ft bgs with contaminant concentrations greater than the PRGs. Excavation

    would be completed in 75-ft by 75-ft cells. To reach the excavation depth and minimize dewatering,

    the cells would have temporary sheet piling installed around the perimeter.

    Large-scale dewatering would be required for each of the excavation cells.

    Excavated soil would be treated onsite using MTTD. Treated soil would be used as backfill.

    Even though this alternative was eliminated in the screening step, a detailed cost estimate was prepared,

    and the total present worth cost for Alternative 5a is $88.4 million with -30/+50 percent cost range of

    $62.1 million to $133.2 million.

    Alternative 6 – In-Situ Solidification/Stabilization, and Targeted Hot-Spot Soil Excavation

    Estimated Capital Cost: $26.1 million

    Estimated Annual O&M Cost: $73,000

    Estimated Periodic Cost (every 5 years): $295,000

    Estimated Present Worth Cost: $25.0 million

    Estimated Construction Timeframe: 6 years

    Estimated Time to Achieve RAOs: 6 years

    Alternative 6 addresses the NCP requirement to develop an alternative that treats the principal threats but

    varies in the degree of treatment employed and the quantities and characteristics of the treatment

    residuals. Although contaminants are not removed using in situ solidification/stabilization (ISS), they are

    immobilized. Under Alternative 6, all mobile and immobile NAPL present within the Process Area and

    Tar Mat DUs would be stabilized in situ using a mix of 1.5 percent Portland cement amended with 3.5

    percent cement slag, 1 percent organo-clay, 1 percent bentonite, 2 percent tar mat ash. The mix design is

    based on the results of the ISS Treatability Study presented in the Revised RI/FS. In addition, the mix

    design concentrations will be doubled for the perimeter of the treatment area than used to treat the interior

    portion to create a hardened shell that would have lower leachability and higher durability.

    Key components of Alternative 6 include the following:

    Each of the common elements listed above.

    Remedial design investigation and excavation of surface soil in the Non-Process Area DU (detailed in

    Alternative 3).

    Remedial design investigation on the western side of the Tar Mat area to determine how much of the Tar

    Mat area needs to be included in the ISS treatment area.

    022106

  • Abandonment and decommissioning of the existing groundwater extraction and injection wellfield

    (detailed in Alternative 1) with the exception of the north recovery trench and extraction wells R-19,

    R-20, and R-21. These would be operated to maintain hydraulic capture until the ISS installation

    reaches the downgradient portion of the Site.

    ISS of mobile and immobile NAPL source materials using backhoe mixing or auger mixing.

    Perimeter ISS columns extending to the bottom of the source area which would have lower leachability

    and higher durability than the interior ISS columns in order to prevent any unidentified source

    materials not treated by interior columns from migrating from the source area.

    Air monitoring during ISS to ensure workers and residents are not exposed to site contaminants.

    An approximately 3-ft-thick soil cover to protect the ISS treatment area and to prevent direct contact with

    treatment residuals.

    The total present worth cost for Alternative 6 is $25 million with a -30/+50 percent cost range of $17.5

    million to $37.4 million.

    The ACW team proposed that: (6) In Situ Solidification/Stabilization and Targeted Hot-Spot Excavation

    be implemented to meet the anticipated future land use of commercial/industrial (see Figure 3 and

    attached Final Draft Proposed Plan). Under Alternative 6, EPA would excavate and dispose of PAH

    contaminated surface soils in the Northern Decision Unit to address unacceptable ecological risks;

    investigate, excavate, and dispose of dioxin/PAH contaminated surface soils in the Non-Process Area

    Decision Unit to address unacceptable human health and ecological risks; excavate a small portion and

    primarily perform in situ solidification/stabilization within the source area located in the Process Area

    Decision Unit to address unacceptable human health and ecological risks; and execute institutional

    controls to limit land use to commercial/industrial, prevent deep excavation to protect the

    solidified/stabilized source materials, and restrict the use of groundwater.

    The proposed response action has an estimated capital cost of $26.1M, an annual O&M cost of $73,000,

    and a periodic cost of $295,000, for a total present worth cost of $25M. EPA Region 6 estimates that the

    remedy can be completed within 6 years at which time Remedial Action Objectives would be met except

    for groundwater. As prescribed in the original 1993 ROD which would be amended by the proposed

    response action, after the source control technologies are implemented, monitoring would be performed to

    evaluate performance of the source control measures and their effect on the groundwater at the site.

    The preferred alternative is protective of human health and the environment because PAH and dioxin

    contaminated soil is removed and disposed off-site and source materials (principal threat wastes) are

    solidified/stabilized to prevent migration of Contaminants of Concern to Creosote Branch Creek and to

    surrounding groundwater. As indicated in the 1993 ROD which is being amended by the proposed

    response action, groundwater at the site is expected to restore to its potential future beneficial use shortly

    after completion of the solidification/stabilization of the source materials.

    The proposed response action would comply with all federal and State ARARs.

    The proposed response action was the highest rated alternative for the combination of Long-Term

    Effectiveness, Reduction of Toxicity, Mobility, and Volume, Short-Term Effectiveness, and

    Implementability compared to all the other potential alternatives. The proposed response action would

    eliminate the migration of contaminants from the source materials to Creosote Branch Creek and the

    022107

  • surrounding groundwater, would eliminate long term operation of a recovery system as being currently

    implemented in the original remedy, and will make the site ready for commercial/industrial use.

    All actions in the proposed response action are readily implementable and the Louisiana Department of

    Environmental Quality has indicated that it supports the proposed response action.

    NRRB Review Not Warranted

    The ACW RRRT concluded that a review of the proposed response action by the NRRB would not be

    necessary because excavation and in situ solidification/stabilization has routinely been used at other

    creosote contaminated sites.

    In addition, the proposed response action is less expensive than the alternative which upgrades the current

    remedy at site and provides significantly more certainty concerning potential migration of contaminants

    from the source area. It will also enable the site to be available for commercial/industrial use whereas the

    alternative which upgrades the current remedy at the site would not.

    Lastly, in consideration of pertinent stakeholder concerns and other site circumstances – (1) the Louisiana

    Department of Environmental Quality supports the proposed response action at the ACW site and

    understands that it would be responsible for a 10 percent cost match at the site, (2) there has been no

    Congressional or community interest in the site since the implementation of the original remedy in the

    mid-1990’s, specifically, no citizens attended the last public meeting held in December 2015. The City of

    Winnfield is only interested in the site being addressed so that the site can be developed for

    commercial/industrial purposes, (3) there are no tribal interests associated with the site, and (4)

    technologies in the proposed response action are common to other sites and therefore, are consistent with

    previous EPA response actions.

    Please signify your concurrence below:

    __________________ I concur that review of the proposed response action by the NRRB is not

    warranted.

    __________________ I do not concur.

    Attachments (9)

    022108

  • Regional Remedy Review Team

    American Creosote Superfund Site

    February 25, 2016

    INTRODUCTION

    The use of In-Situ Stabilization/Solidification (ISS) for treatment of shallow source material at former

    wood treater and oily waste sites is considered to be a regional presumptive remedy approach in Region 6.

    This technical recommendation is based on the experience of the Remedial Project Managers participating

    in the RRRT and their experience and expertise gained from implementing remedial actions at a number

    of sites over the last 20 years. The successful implementation of ISS has been completed at similar wood

    treater and oily waste sites including North Cavalcade Street, Texarkana Wood Preserving, Mountain Pine

    Pressure Treatment, and South 8th Street Landfill. At sites that did not include ISS as part of the remedy

    implementation, there are long-term operational and maintenance issues with potentially significant costs.

    RECOMMENDATIONS:

    RPM 1 Comments

    At the RRRT review, Solidification/stabilization (S/S) was presented as the preferred alternative. The

    RRRT recommends that the following items be considered during the design and implementation of the

    remedy:

    S/S is expensive per cubic yard – by excavating soil above the S/S area, we can decrease the cubic yard stabilized. Solidification (cement) is not the major cost, stabilization (Powered Activated

    Carbon - PAC) is the major cost.

    1) We can expect up-to 30% swell of the solidified material, which will require offsite disposal or onsite consolidation in a cell (type cell depends on excavated soil risk). Based on soil volumes

    discussed; the onsite cell appears to be more cost effective than offsite disposal.

    RPM Response – The issue of how to manage swell will be evaluated in the RD.

    2) For reuse – we may want to consider excavation of sufficient soil at the S/S site to allow for sufficient clean fill/soil thickness to promote tree growth, slabs, posts/pilings, etc.

    RPM Response – Methods to reduce cost, such as excavation of clean soil to minimize the

    amount of material that is addressed with in-situ solidification/stabilization will be evaluated

    in the RD.

    3) If we excavate for S/S, we should excavate a small area (e.g., 1-acre), S/S that area, and then backfill as soon as practicable, in this way we minimize contaminated stormwater

    management.

    RPM Response – Methods to minimize storm water management will be evaluated in the

    RD.

    4) A bench scale test usually tests to a UCS of 50 psi and a percent by weight carbon for concentrations below the MCL (usually 4%). I agree with the Pilot Test mentioned; we can

    decrease costs by reducing the UCS based on the potential reuse (e.g., storage – 15-20

    UCS). We can also reduce the cost for PAC through the Pilot.

    RPM Response – The most predominant factor in the treatability study performed during

    the FS was the leaching potential of contaminants. Various mixes that achieved acceptable

    leaching results over achieved the requirements of unconfined compressive strength and

    022109

  • hydraulic conductivity. The treatability study results will be re-evaluated in the RD to

    determine if any changes to the treatability study mix designs.

    Section Chief Comments

    At the RRRT presentation, the RPM provided information to amend the soil remedy for the site. However, not enough information was provided regarding the groundwater component of the

    existing remedy.

    The RRRT recommends that the RPM fully discuss what is planned for the groundwater

    component in the decision document.

    RPM Response – The groundwater component of the existing/proposed remedy will be more

    thoroughly discussed in the Proposed Plan.

    At the RRRT presentation, the RPM discussed alternative 5b which was full removal of the contaminated soils. However, this alternative was not fully discussed under the nine criteria. The

    RRRT recommends that alternative 5b be presented through the nine criteria and evaluation in the

    decision document.

    RPM Response – Alternative 5b will be incorporated into the Proposed Plan.

    RPM 2 Comments

    As explained at the RRRT review presentation, Solidification/Stabilization (SS), will both contain the larger NAPL source area and provide additional source “treatment” through immobilization of

    mass within the SS ring itself. The SS approach is consistent with source remedies implemented at

    Region 6 creosote sites over the last ~5 years, after original pump and treat remedies were shown

    to be problematic. The combination of a SS ring, anchored in the Cockfield confining zone, with

    a constructed cover over the interior of the ring will effectively encapsulate the primary source

    area. During discussions, it was noted that the bottom confining layer is a Cockfield transitional

    facies overlying the Sparta, the drinking water supply aquifer. There may be concerns that the

    Cockfield may be a “leaky” confining layer, so the argument that the Cockfield has not been

    impacted becomes most important. The RRRT recommends that the RPM clarify in the ground

    water/site characteristics discussion that the monitoring coverage on the Cockfield is adequate to

    make this argument. And you may want to consider that monitoring will continue into the future

    and the network will be further evaluated during design or the Five-Year Review. You would want

    to prepare a case for not needing to monitor the Sparta, if that is the case.

    EPA Response – Several well pairs completed in the shallow/deep aquifers have been monitored

    since before and after the remedy startup in the mid-1990’s. Historical observations from these

    well pairs, including observations during non-pumping conditions, have always indicated an

    upward gradient from the deep aquifer (Cockfield) to the shallow aquifer. In addition, the

    Cockfield is approximately 150 feet thick and is comprised of interbedded clays, silts, and sands.

    Based upon the historical upward gradient and the thickness of the Cockfield, it does not

    appear that monitoring the Sparta is necessary.

    RPM 3 Comments At the RRRT review, Alternative 6 was presented as the preferred alternative. The RRRT recommends

    that the following items be considered during for the preferred alternative that could result in cost saving

    during design and implementation of the remedy

    For Alternative 6, consider dewatering of the former fire water pond and utilize the storage

    capacity for excess ISS treated material within the Site boundary. The combination of the pond,

    022110

  • and a potential excavation area within the incinerator ash waste cell, will provide capacity to

    reduce the amount of mounding anticipated after ISS treatment of the contaminated soil area.

    RPM Response – The use of the fire water pond for ISS swell management will be evaluated in

    the RD.

    For Alternative 6, consider removal and storage of the clean soil cap material for later use as the

    soil cover on the ISS treated material. This material will reduce the total volume of soil requiring

    ISS treatment.

    RPM Response – Methods to reduce cost, such as excavation of clean soil to minimize the

    amount of material that is addressed with in-situ solidification/stabilization will be evaluated in

    the RD

    For Alternative 6, consider adding a statement in the Proposed Plan on the need for air monitoring

    during the ISS treatment to address potential exposure pathways to the community downwind of

    the Site.

    RPM Response – A statement concerning planned air monitoring during the ISS activities will

    be inserted into the Proposed Plan.

    For Alternative 6, consider incorporating the contaminated soil from the hot spots into the ISS

    mixing process to eliminate the need for off-site transport and disposal. If the potential funding

    plan does not allow this action, then consider adding an explanation in the Proposed Plan or other

    record on why the action is a priority for risk reduction.

    RPM Response – Methods to reduce costs such as combining hot spot contaminated soils into

    the ISS mixing process will be evaluated in the RD.

    For Alternative 6, the ISS treatment process that provides a continuous treatment perimeter as well

    as treatment of the source material waste is not expected to require further treatment or monitoring

    of the ground water remaining below the treated waste. Following completion of the source area

    ISS treatment, the remaining ground water is considered to be within the waste management area,

    and the ground water restoration objective in the ROD is not considered relevant for future action.

    RPM Response – Agreed and the goal of restoration for the groundwater surrounding the

    source area will be described in the Proposed Plan.

    At the RRRT review, Alternative 2 was presented as one of the alternative considered. The RRRT

    recommends that the RPM consider the following:

    For Alternative 2, consider removing this alternative and include the remedy components as

    common elements for Alternatives 3 – 6. While Alternative 2 does address RAOs 1 – 3, the

    Alternative does not provide an action that will address the proposed RAO #4 for minimizing

    further migration of contaminants of concern from source materials.

    RPM Response – Agreed that Alternative 2 does not meet all the RAO’s, however, it will still be

    presented in the Proposed Plan in order to be transparent to the public concerning all the

    alternatives that EPA considered. However, the Proposed Plan will be clear that Alternative 2

    cannot be considered for remedy selection since it does not meet the Threshold Criteria.

    At the RRRT review, the RPM presented the RAOs for the Proposed Plan. The RRRT recommends that

    the RPM consider including an explanation in the Proposed Plan that the objective to restore groundwater

    quality has not been changed in the planned ROD Amendment.

    022111

  • RPM Response – The Proposed Plan will be revised to make it clear RAO’s are either new, modified

    from the original ROD, eliminated from the original ROD, or not eliminated from the original ROD

    and thus still apply.

    The RRRT notes that implementation of Alternative 6, or any of the other alternatives, does not trigger a

    site-wide construction completion until the ground water issues are addressed in a subsequent ROD

    Amendment.

    RPM Response – It is acknowledged that the site-wide construction completion target is not achieved

    until ground water issues are ultimately addressed.

    022112

  • Figure 1 - American Creosote Works Inc. - Site Location Map

    Disclaimer: This map and any boundary lines within the map are approximate and subject to change. The

    map is not a survey. The map is for informational purposes only regarding EPA’s response actions at the

    Site.

    • Winnfield,

    American Creosote Works, Inc. • (Winnfield Plant)

    Louisiana "----~ Superfund Site

    0 250 500 1,000 ••c:::=•••-Feet

    0 NORTH

    X -X Site Fence

    American Creosote Works, Inc. (Winnfield Plant) Superfund Site Winnfield , Winn Parish, Louisiana

    022113

  • Site Location

    LEGEND

    Former FireWater Pond

    BoilerBuilding TankFarmRetort

    Retort

    Far West (FW) Branch

    North (N) Branch

    West (W) Branch

    WasteCell 1 2

    2 4

    Southern Decision Unit/South Parcel(15.6 acres)

    Process Area Decision Unit/North Parcel(14.2 acres)

    Northern Decision Unit(9.9 acres)

    Non-Process Area Decision Unit/North Parcel(10.5 acres)

    Western Decision Unit(4.3 acres)

    Tar Mat Decision Unit(2.4 acres)

    FIGURE 2

    American Creosote WorksWinnfield, Louisiana

    0 225 450Feet

    FenceCreek (Creosote Branch)

    Pond/CreekHistorical Process Area Surface Water Drainage

    ! !

    K

    Approximate Locationof Historical Tar Mat Area

    Historical ImpoundmentsHistorical Treated WoodStorage Areas

    HOU \\Hollister\Groups\IS\Proj\American_Creosote\apr-mxd\2015\Figure 1-02 ACW Historic Facilities and Decision Units.mxd cg021858 4/21/2015 5:00:22 PM

    Historic Facilities andDecision Unit Map

    Source: ESRI World Imagery online mapping service

    Decision UnitsCreek Decision UnitNon-Process Area Decision Unit/North ParcelNorthern Decision UnitProcess Area Decision Unit/North ParcelSouthern Decision Unit/South ParcelTar Mat Decision UnitWestern Decision Unit

    Waste Cell

    022114

  • TABLE 1 Process Area Decision Unit Quantitative Human Health Risk Summary American Creosote Works, Winnfield, Louisiana

    Receptor Exposure

    Area Medium Exposure

    Route

    Excess Lifetime Cancer

    Risk Hazard Index Chemicals of Potential Concern

    Industrial/

    Commercial

    Worker

    Soil

    (Process Area

    DU)

    Surface Soil

    (0-1 foot bgs)

    Total 2E-03 3.5 Total dioxin TEQ, 1,1-biphenyl, PCP, total BAP

    TEQa

    Subsurface Soil

    (0-10 feet bgs)

    Total 2E-03 4 2-methylnaphthalene, PCP, total BAP TEQ,

    1,1-biphenyl, naphthalene

    Groundwater

    (Process Area

    and Non-

    Process DUs)

    Groundwater Total 2E-01 262 Noncarcinogenic PAHsb, methylphenols, 1,1-

    biphenyl, 1,1,2,2-tetrachloroethane, 1,1,2-

    trichloroethane, 1,2-dibromoethane, 1,2-

    dichloropropane, bromodichloromethane,

    PCP, total BAP TEQ, benzene, and

    ethylbenzene

    Construction

    Worker

    Soil

    (Process Area

    DU)

    Surface Soil

    (0-1 foot bgs) Total 2E-04 6 Total dioxin TEQ, naphthalene, PCP, total BaP

    TEQ

    Subsurface Soil

    (0-10 feet bgs) Total 2E-04 7 2-methylnaphthalene, PCP, total BAP TEQ,

    naphthalene

    Shallow

    Aquifer

    Groundwater

    (Process Area

    and Non-

    Process DUs)

    Groundwater Total 4E-03 11 Fluoranthene, PCP, naphthalene, total BAP

    TEQ

    Notes: a BAP TEQ includes: benzo(a)anthacene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(k)fluoranthene, chrysene,

    dibenz0(a,h)anthacene, and indeno(1,2,3-cd)pyrene b noncarcinogenic PAHS include: acenaphthene, acenaphthylene, anthacene, fluoranthene, fluoranthene, phenanthrene, and pyrene

    % = percent BAP TEQ = benzo(a)pyrene toxicity equivalent

    bgs = below ground surface

    COC = chemical of concern

    DNAPL = dense non-aqueous phase liquid Dioxin TEQ = 2,3,7,8 tetrachlorodibenzo-p-dioxin toxicity equivalent

    DU = decision unit

    NAPL = non-aqueous phase liquid

    PCP = pentachlorophenol

    022115

  • TABLE 2 Preliminary Risk Screening All Decision Units American Creosote Works, Winnfield, Louisiana

    Decision Unit Medium

    Dioxins (ng/kg) PAHs (mg/kg) Quantitative RA

    Dioxin TEQ Exposure

    Point Conc. PRE (ELCR)*

    BAP TEQ Exposure

    Point Conc. PRE (ECLR)*

    Total PRE (ECLR)

    Exceeds Upper Bound (1.0E-04) of CERCLA Risk Range

    Risk-based Screening Level (Industrial)** 18 1E-06 0.21 1E-06

    Northern

    Surface Soil (0 to 1 feet bgs)

    175.1 1.E-05 17.7 8.E-05 9.E-05 No

    Subsurface Soil (1 to 10 feet bgs)

    NA NA 1.96 9.E-06 9.E-06 No

    Non-Process Area

    Surface Soil (0 to 1 feet bgs)

    14,634.00 8.E-04 4.54 2.E-05 8.E-04 Yes

    Subsurface Soil (1 to 10 feet bgs)

    NA NA 2.83 1.E-05 1.E-05 No

    Process Area

    Surface Soil (0 to 1 feet bgs)

    237.4 1.E-05 59.1 3.E-04 3.E-04 Yes

    Subsurface Soil (1 to 10 feet bgs)

    NA NA 296 1.E-03 1.E-03 Yes

    Southern

    Surface Soil (0 to 1 feet bgs)

    288 2.E-05 4.87 2.E-05 4.E-05 No

    Subsurface Soil (1 to 10 feet bgs)

    NA NA 1.12 5.E-06 5.E-06 No

    Western Surface Soil (0 to 1 feet bgs)

    199.8 1.E-05 3.85 2.E-05 3.E-05 No

    Tar Mat Subsurface Soil (1 to 10 feet bgs)

    285.4 2.E-05 0.23 1.E-06 2.E-05 No

    RSLs Sediment (Industrial)** 18 0.21

    Fire Water Pond Sediment 79.96 4.E-06 0.44 2.E-06 7.E-06 No

    022116

  • TABLE 2 Preliminary Risk Screening All Decision Units American Creosote Works, Winnfield, Louisiana

    Decision Unit Medium

    Dioxins (ng/kg) PAHs (mg/kg) Quantitative RA

    Dioxin TEQ Exposure

    Point Conc. PRE (ELCR)*

    BAP TEQ Exposure

    Point Conc. PRE (ECLR)*

    Total PRE (ECLR)

    Exceeds Upper Bound (1.0E-04) of CERCLA Risk Range

    North Creosote Branch Sediment

    60.55 3.E-06 3.33 2.E-05 2.E-05 No

    West Creosote Branch Sediment

    7.66 4.E-07 0.40 1.9E-06 2.E-06 No

    Background Values

    Background

    Surface Soil 31.81 NA 0.432 NA NA

    Subsurface Soil NA NA 0.425 NA NA

    Surface Water NA NA 21.134 NA NA

    Sediment 10.77 NA 0.876 NA NA

    Notes: Identifies Decision Units and media carried forward to feasibility study based on exceedance of upper bound CERCLA risk range. *PRE = Preliminary Risk Evaluation = (Dioxin TEQ or BAP TEQ/ Industrial RSL)*10^-6 for carcinogens ** = PRE was calculated for sediment using the soil Industrial RSL value of 18 ng/kg for dioxins and 0.21 mg/kg for PAHs. Surface water criteria were not available for industrial workers for a PRE calculation. BAP-TEQ = benzo(a)pyrene toxicity equivalent concentration bgs = below ground surface CERCLA = Comprehensive Environmental Response, Compensation, and Liability Act of 1980 Dioxin TEQ = 2,3,7,8-TCDD toxicity equivalent concentration DU = Decision Unit ECLR = Estimated Lifetime Cancer Risk kg = kilogram mg = milligram NA = not applicable ng = nanogram

    022117

  • TABLE 3

    Summary of Risks ‐‐ Terrestrial Habitats

    American Creosote Works, Winnfield, Louisiana

    Constituents

    Decision Unit

    Direct Exposure

    Indirect (Food Web) Exposure

    Birds Mammals

    NBQ AW AK DM NBA M RF

    PAHs

    Northern x

    (HPAH)

    x (6 HPAH)

    Non‐Process x

    (HPAH)

    x (1 HPAH)

    Process x

    (LPAH & HPAH)

    x

    (2 HPAH)

    x (8 HPAH)

    Southern Western

    Dioxins/Furans

    (TEQs)

    Northern

    Not Evaluated

    x Non‐Process x x x x x

    Process x Southern Western

    Notes:

    An "x" indicates risk; blank cells indicate no risk. HPAH = high molecular weight PAHs AK =

    American Kestrel LPAH = low molecular weight PAHs AW =

    American Woodcock PAH = polycyclic aromatic hydrocarbon DM =

    Deer Mouse TEQ = toxic equivalents

    M = Mink NBA = Nine‐banded

    Armadillo NBQ = Northern Bobwhite

    Quail RF = Red Fox

    022118

  • TABLE 4 Preliminary Remediation Goals for Soil and Groundwater American Creosote Works - Winnfield, Louisiana Preliminary Remediation Goal

    Contaminant of Concern Units Northern DU Non-

    process Area DU

    Process Area DU

    PRG Basis

    Soil

    High Molecular Weight PAHsa mg/kg 18 NA NA Ecological Receptor at HQ=1

    1,1-Biphenyl mg/kg NA NA 200 Human Health at HQ = 1

    2-Methylnaphthalene mg/kg NA NA 3,000 Human Health at HQ = 1

    BAP TEQ mg/kg NA 3.0 3.0 Human Health at ELCR = 1 x 10-4

    Dioxin TEQ mg/kg NA 0.00073 0.00073 Human Health at HQ = 1

    Naphthalene mg/kg NA NA 290 Human Health at HQ = 1

    Pentachlorophenol mg/kg NA NA 400 Human Health at ELCR = 1 x 10-4

    Shallow Aquifer Groundwaterf

    1,1-biphenyl µg/L NA 14 Ecological Screening Valuee

    1-Methylnaphthalene µg/L NA 2.1 Ecological Screening Valuee

    2-Methylnaphthalene µg/L NA 63 Ecological Screening Valuee

    3&4-Methylphenol (m&p-Cresol) µg/L NA 272 Ecological Screening Valuee

    Acenaphthene µg/L NA 23 Ecological Screening Valuee

    Acenaphthylene µg/L NA 7,731 Site-specific Secondary Contact Recreationd

    Anthracene µg/L NA 0.30 Ecological Screening Valuee

    BAP TEQ µg/L NA 0.25 Site-specific Secondary Contact Recreationd

    Benzene µg/L NA 1,125 Louisiana AWQC - Aquatic Organism Protectionb

    Benzo(a)anthracene µg/L NA 35 Ecological Screening Valuee

    Benzo(a)pyrene µg/L NA 0.014 Ecological Screening Valuee

    Chrysene µg/L NA 7.0 Ecological Screening Valuee

    Dibenz(a,h)anthracene µg/L NA 5.0 Ecological Screening Valuee

    Dibenzofuran µg/L NA 94 Ecological Screening Valuee

    Ethylbenzene µg/L NA 1,600 Louisiana AWQC - Aquatic Organism Protectionb

    Fluoranthene µg/L NA 6.2 Ecological Screening Valuee

    Naphthalene µg/L NA 250 Ecological Screening Valuee

    Pentachlorophenol µg/L NA 15 Federal AWQC - Aquatic Organism Protectionc

    Phenanthrene µg/L NA 30 Ecological Screening Valuee

    Pyrene µg/L NA 7.0 Ecological Screening Valuee

    Xylenes µg/L NA 1,340 Ecological Screening Valuee

    Notes: a Ecological PRGs were not developed for individual high molecular weight PAH compounds, but they are included in the total high molecular weight PRG calculation. The individual high molecular weight PAHS include: benzo(a)anthracene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene, dibenz(a,h)anthracene, fluoranthene, indeno(1,2,3-c,d)pyrene, and pyrene. b Reference: Table 1, Freshwater Chronic Numerical Criteria for Specific Toxic Substances Louisiana Administrative Code Title 33, Part IX, Subpart 1 (2014b) c Reference: Environmental Protection Agency (EPA) National Recommended Water Quality Criteria (EPA, 2014) d Reference: Site-specific calculated value based on lowest value of excess lifetime cancer risk of 1 x 10-4 or hazard quotient of 1.0 e Reference: Texas Commission on Environmental Quality, http://www.tceq.state.tx.us/assets/public/remediation/eco/0106eragupdate.pdf f Non-Process Area and Process Area Decision Units lie in the same geographic portion of the shallow aquifer; therefore, the PRGs are the same. µg/L = microgram per liter AWQC = ambient water quality criteria BAP = benzo(a)pyrene DU = Decision Unit ELCR = excess lifetime cancer risk HQ = hazard quotient mg/kg = milligram per kilogram NA = not applicable PAH = polycyclic aromatic hydrocarbon PRG = preliminary remediation goal TEQ = toxicity equivalent

    022119

  • Table 5- Comparative Evaluation of Alternatives American Creosote Works, Winnfield, Louisiana

    Alternative 1: Criterion No Further

    Action

    Key Treatment Technologies

    Northern DU Soil

    Non-process Area DU (Soil) Not

    Process Area DU (Soil < 5 feet) Applicable Process /\rea DU (Soil > 5 feet)

    Threshold Criteria

    Process Area, Non-process

    Area, and Northern DUs

    Protects H HE No

    Complies with ARARs No

    Balancing Criteria

    Long-term Effectiveness and Not evaluated

    Permanence

    Reduction of TM V through Treatment Not evaluated

    Short-term Effectiveness Not evaluated

    lmplementability Not evaluated

    Cost

    Total Present Worth Cost $640,000

    Present Worth Cost Range

    -30 Percent $448,000

    +50 Percent $960,000

    Annual O&M Cost $0

    Periodic Cost $0

    Total Non-discounted Cost $640,000

    Modifying Crit eria

    Stat e Acceptance

    Community Acceptance

    Alternative 2: ICs with Alternative 3- Upgrade NAPL

    LTM and Targeted Hot-Recovery and Treatment System,

    spot Soil Excavation and Targeted Hot-Spot Soil

    Excavation

    Excavation and Disposal Excavation and Disposal

    ICs and Fence

    ICs and Multi-layer Cap Multi-layer Cap

    Upgrade N/\PL Recovery and Treatment

    Non-Process process, Process Non-process, Area DU Northern Area DU Northern DUs

    DUs

    No No Yes Yes

    Yes' Yes Yes' Yes

    Not evaluated * **** Not evaluated

    ·~ **** Not evaluated ** **** Not evaluated ***· ***Cl

    $8,500,000 $28,500,000

    $5,97,000 $19,920,000

    $12,780,000 $42,690,000

    $73,000 $664,000

    $295,000 $4,930,000

    $17,370,000 $92,450,000

    ****= The alternative performs superior against the CERCLA balancing criterion with no disadvantages or uncertainties

    Alternative 4- Containment Alternative Sa- Partial Depth with Slurry Wall and Multi-layer Excavation- Thermal Cap with Targeted Hot-spot Soil Desorption, and Thermal

    Excavation Enhanced Extraction

    Excavation and Disposal Excavation and Disposal

    Slurry Wall and Cap Excavation and MTID

    Thermal Enhanced N/\P L Recovery

    Process Non-process, Process Non-process, Area DU Northern DUs Area DU Northern DUs

    Yes Yes Yes Yes

    Yes' Yes Yes' Yes

    ** **** *** **** **ti1 **** *** **** *** **** ** **** rt-::n *** *-- ***Cl

    $18,500,000 $45,700,000

    $12,920,000 $32,010,000

    $27,690,000 $68,605,000

    $117,000 $1,300,000

    $295,000 $295,000

    $31,680,000 $69,040,000

    Not evaluated in this FS

    *** ** *

    = The alternative performs well against the CERCLA balancing criterion with minimal disadvantages or uncertainties

    =The alternative performs fair against the CERCLA balancing criterion but with some disadvantages or uncertainties

    =The alternative performs poorly against the CE RCLA balancing criterion with more disadvantages or uncertainty

    'This assessment does not include groundwater. The groundwater decision is postponed to a future decision document.

    >=less than < = greaterthan ARARs =applicable or relevant and appropriate requirements CERCLA =Comprehensive Environment31 Response, Compensation, and Uability Act of 1980 (commonly known as Superfund)

    DU =decision unit FS =feasibility study H HE = Human Health and the Environment I C = institutional control ISS= in situ solidification/stabilization

    LTM =long-term monitoring MTID =medium temperature thermal desorption NAPL =nonaqueous phase liquid O&M =operation; and maintenance TMV =toxicity, mobility, and volume

    Alternative Sb- Full Depth Excavation with Thermal Alternative 6 -ISS

    Desorption

    Excavation and Disposal Excavation and Disposal

    Excavation and MTID ISS

    Process Non-process, Process Non-process, Area DU Northern DUs Area DU Northern DUs

    Yes Yes Yes Yes

    Yes' Yes Yes' Yes

    **** **** **** **** **** **** **** **** * " **** ** : **** _..1 ***~ ...-:~ '**'*"

    $91,000,000 $25,000,000

    $64,000,000 $17,4 70,000

    $137,000,000 $37,430,000

    $73,000 $73,000

    $36,000 $295,000

    $104,000,000 $31,190,000

    022120

  • Site Location

    LEGEND

    PLTS SupportBldg.

    PLTSBldg.Bioreactor

    Pond

    0 15075Feet K

    T:\IS\Proj\American_Creosote\apr-mxd\Alt6_remediation_footprints.mxd 4/8/2016 gtwigg

    FenceCreek (Creosote Branch)

    ! !

    Site Utility RoadsTar Mat Ash Disposal Cell

    Figure 3Alternative 6 Remediation FootprintsIn-Situ Solidification/StabilizationAmerican Creosote WorksWinnfield, Louisiana

    NPDU – Non-Process Decision UnitDioxin Soil Excavation Footp rint(This Area will be Refined duringRemedial Desig n)NDU – Northern Decision Unit SoilExcavation Footp rintPDU – In Situ Solidification/Stabilization Footp rint

    022121

  • PROPOSED PLAN Amendment to April 1993 Record of Decision

    American Creosote Works Inc. Superfund Site

    Winnfield, Louisiana

    Xx/xx, 2016

    The purpose of this Proposed Plan is to:

    ● Identify the proposed alternate remedy that will amend the April 1993 remedy;

    ● Summarize the information that prompted and supports fundamentally changing

    the April 1993 remedy;

    ● Solicit public review and comment on the alternate cleanup strategy as well as

    information contained in the Administrative Record file; and,

    ● Provide information on how the public can be involved in the remedy selection

    process for the American Creosote Works Inc. Site.

    Dates to Remember:

    ● Public Comment Period:

    Xx/xx/xxx to xx/xx/xxxx

    The EPA and LDEQ will accept written comments on the Proposed Plan during the public

    comment period.

    ● Public Meeting: xx/xx/xxxx

    The EPA will hold a public meeting to explain the Proposed Plan and all of the alternatives

    presented in the Feasibility Study. Oral and written comments will also be accepted at the

    meeting. The meeting will be held at the Winn Parish Library, 200 N. St. John Street,

    Winnfield, LA, 71843, at x:xx pm.

    ● Administrative Record is available for viewing at:

    EPA Region 6 LDEQ Headquarters

    7th Floor Reception Area Public Records Center

    1445 Ross Avenue, Suite 12D13 Galvez Building, 1st Floor – Room 127

    Dallas, TX 75202-2733 602 N. Fifth Street

    Toll Free (800) 533-3508 or (214) 665-6597 Baton Rouge, LA 70802

    Monday – Friday 7:30 – 11:00 am/1:00 – 4:00 pm (225) 219-3181

    Winn Parish Library

    200 N. St. John Street

    Winnfield, LA 71843

    (318) 628-4478

    Hours – 8:30 am-5:30 pm Monday - Friday, 10 am-2pm Saturday

    022122

  • Introduction

    In this Proposed Plan, the U.S. Environmental Protection Agency (EPA) presents summary

    information for an alternate remedy for the American Creosote Works Inc. Superfund Site (Site)

    located in the City of Winnfield, Winn Parish, Louisiana (Figure 1). The remedy implemented

    pursuant to the April 1993 Record of Decision has been successful in reducing the amount of

    contamination at the Site. However, due to several years of declining remedy performance and

    growing concerns of the long-term effectiveness of the Site’s Non-Aqueous Phase Liquid

    (NAPL) recovery and in-place biological treatment systems, EPA has concluded that the

    previously selected remedy will not achieve existing cleanup objectives in a reasonable amount

    of time.

    This Proposed Plan highlights key information about the progress of the current remedy, the

    current extent of the remaining contamination at the site, and the revised cleanup objectives. The

    EPA is issuing this Proposed Plan to recommend the following alternate remedy for the Site:

    ● Alternative 6 – In-Situ Solidification/Stabilization, and Targeted Hot-Spot Soil Excavation

    Alternative 6 would solidify/stabilize in situ the subsurface source of ground water

    contamination (i.e., mobile and immobile NAPL) present within the Process Area and Tar Mat

    Decision Units.

    ● Current Remedy – The on-site incineration of highly contaminated tars and sludges has been

    completed. The pumping, separation, and treatment of liquid contaminants and the in-situ

    bioremediation components of the 1993 ROD which were designed to address the subsurface

    source of shallow ground water contamination are being replaced by the proposed remedy. A

    new soil cover to protect the in-situ solidification/stabilization area will replace the capped

    surface soils completed under the current remedy. The goal of restoring ground water to its

    potential beneficial use is retained from the 1993 ROD and applies to the shallow ground water

    impacted by the source area.

    The EPA has conducted its activities in connection with the Site in accordance with the

    Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or

    Superfund), 42 U.S.C. §§ 9601 et seq., and the National Oil and Hazardous Substance

    Contingency Plan (NCP), 40 C.F.R. Part 300. The EPA is issuing this Proposed Plan in

    accordance with and as part of its public participation responsibilities under CERCLA § 117(a),

    42 U.S.C. § 9617(a) and 40 C.F.R. § 300.430(f)(2). The summary information and

    recommendations set forth in this Proposed Plan are based on information and documents

    contained in the Administrative Record file for the Site.

    The EPA Region 6 office is the lead agency for this Site and has conducted remedial activities at

    the site since the 1990’s. The Louisiana Department of Environmental Quality (LDEQ) is the

    support agency and provided technical review of the remedy performance through a cooperative

    agreement with EPA.

    022123

  • Community Participation

    This Proposed Plan highlights information contained in the Administrative Record for the Site

    which includes annual operation and maintenance reports, historical and revised investigation

    reports, revised feasibility study reports, and other documents and reports used in preparing this

    Proposed Plan. The EPA encourages the public to review those documents to obtain more

    information about the Superfund activities that have been conducted at the Site. The EPA also

    encourages the public to participate in the decision-making process for the Site. The

    Administrative Record file is available at the following information repositories:

    EPA Region 6 LDEQ Headquarters

    7th Floor Reception Area Public Records Center

    1445 Ross Avenue, Suite 12D13 Galvez Building, 1st Floor – Room 127

    Dallas, TX 75202-2733 602 N. Fifth Street

    Toll Free (800)533-3508 or (214)665-6597 Baton Rouge, LA 70802

    Monday-Friday 7:30-11:00 am/1:00-4:00 pm (225)219-3181

    Winn Parish Library

    200 N. St. John Street

    Winnfield, LA 71843

    Monday-Friday 8:30 am-5:30 pm, Saturday 10:00 am-2:00 pm

    The EPA will hold a public meeting to inform residents of the proposed alternate remedy for the

    cleanup of the Site and obtain comments on the Proposed Plan for the American Creosote Works

    Inc. Site in the City of Winnfield, Winn Parish, Louisiana.

    The public meeting will be held on XXXXXX, MONTH DAY, YEAR, at TIME at the

    Winn Parish Library, 200 N. St. John Street, Winnfield, Louisiana, 71843. The public meeting is

    being held in a fully accessible facility. Should you have specific needs or questions about the

    facility, please contact Michael A. Hebert, Remedial Project Manager, at (214) 665-8315 or toll-

    free (800) 533-3508 or Jason McKinney, Community Involvement Coordinator, (214) 665-8132

    or toll-free (800) 533-3508.

    Public comments can be presented at the public meeting or can be submitted during the public

    comment period from DATE, through DATE. All written comments should be addressed to:

    Michael A. Hebert, Remedial Project Manager

    U.S. EPA Region 6 (6SF-RL)

    1445 Ross Avenue

    Dallas, Texas 75202-2733

    214-665-8315

    [email protected]

    For specific information about the LDEQ’s participation in the Superfund process, please

    contact:

    022124

  • John Halk, Project Manager

    Louisiana Department of Environmental Quality

    Remediation Services Division

    Group 3

    P.O. Box 4314

    Baton Rouge, LA 70821-4314

    225-219-3717

    [email protected]

    Site Background and Characteristics

    The ACW site is a former wood-treating facility, spanning about 62 acres, located at 1006 Front

    Street in Winnfield, Louisiana. According to the U.S. Census Bureau, about 4,600 people lived

    in Winnfield in 2013. Land uses nearby include agricultural, residential, commercial, and

    recreational uses. Residences near the Site are connected to the City of Winnfield’s public water

    system. Wood treatment operations at the Site began around 1901 and continued under various

    ownerships until 1985, when the Louisiana Department of Environmental Quality (LDEQ)

    discovered that the Site had been abandoned.

    Unplanned releases of creosote and pentachlorophenol (PCP) based wood-treating oil, and waste

    handling practices resulted in extensive soil, groundwater, and sediment contamination.

    Contaminant sources present at the time of abandonment included two storage tanks, visibly

    contaminated soil present in the former process area, waste material present in a surface

    impoundment located just north of the fire water pond, and tarry-sludge material present in an

    area later identified as the Tar Mat sludge disposal area. In response to these conditions, EPA

    completed two removal actions to stabilize contaminant sources and reduce the potential for

    further contaminant releases. The removal actions were performed between 1987 and 1989.

    A Remedial Investigation/Feasibility Study (RI/FS) was performed in 1992/1993 and focused

    primarily on the areas where wood treating operations were conducted. From information

    reviewed during the RI, the wood treating operations were determined to have occurred in the

    north-central portion of the Site. A tank farm, with no visible secondary containment, was also

    located in this north-central part of the site. The earliest aerial photographs (1940 and 1947) of

    the Site showed evidence (soil staining and stressed vegetation) that wood-treating oil flowed

    unimpeded from the former process area towards Creosote Branch Creek. An onsite drainage

    pathway that discharged to Creosote Branch Creek is also visible on a 1940 aerial photograph as

    is a natural drainage that flows eastward from the former process area.

    Between April 1950 and May 1952, two impoundments were constructed in the process area

    which received liquid wastes from the wood-treating process. Several shallow drainage ditches

    were also constructed to convey runoff from the process area. A 1959 aerial photograph shows a

    pool of standing liquid northeast of the tank farm in the process area. Evidence of standing

    liquid and dark-stained soil at this location appears in subsequent aerial photographs through

    1973.

    022125

  • Sometime prior to 1966, additional wood treatment facilities were built in the southern portion of

    the process area and a third impoundment was constructed east of the process area.

    Interpretation of aerial photographs indicates heavy wood treating activity at the Site during the

    mid- to late-1960s. According to facility records, during a 7-month period in 1966, 750,000

    gallons of petroleum distillate, 40,000 gallons of creosote, and 54,000 pounds (3,200 gallons) of

    PCP were used to treat 7.5 million board-ft of lumber. Between 1973 and 1976, extensive

    earthwork that was performed north and east of the Process Area covered up the majority of

    stained soil and removed all evidence of Impoundment 1. A fourth impoundment was built

    northeast of Impoundment 2. This impoundment may have received drainage or overflow from

    Impoundment 2. A water storage pond was also constructed south of Impoundment 2 to collect

    and store rainwater for emergency fire-fighting. Evident in a 1973 photograph is the formation

    of the “Tar Mat” area, located approximately 500 feet east of the Process Area. The Tar Mat was

    a large, flat, asphalt-like waste material that extended over a marshy portion of the Site. The

    source of the Tar Mat material is unknown, but the 1992/1993 RI/FS Report indicates that it

    might have resulted from a large, single spill event. The Tar Mat area also may have resulted

    from removal and disposal of impoundment sludge. By 1983, Impoundments 2 and 4 had been

    backfilled, presumably with wood chips, and the impoundment dikes had been leveled.

    However, Impoundment 3 remained active.

    In June 1985, the Louisiana Department of Environmental Quality (LDEQ) found the site

    abandoned and referred it to EPA, which placed the site on the National Priorities List (NPL) on

    October 14, 1992, based on a hazard ranking score of 50.7.

    The 1992/1993 RI/FS determined that the primary threats that the Site posed to public health

    were direct contact or ingestion of contaminated site soils and ingestion of contaminated site

    groundwater by potential future residents. The RI determined that site soil was contaminated

    with polycyclic aromatic hydrocarbons (PAHs), volatile organic compounds (VOCs), dioxins

    and PCP. The most heavily contaminated surface soils were located in the former process and

    impoundment areas, the tar mat area, and its related drainage area in the northeast portion of the

    Site. Contaminated subsurface soil is present throughout the former process area, the

    impoundment area and the tar mat area. Contaminants in shallow aquifer groundwater include

    PAHs, phenols and benzene. The RI determined that groundwater contamination was present

    primarily in the former process and impoundment areas and areas hydraulically downgradient of

    those locations. Surface water and sediment in Creosote Branch Creek were also impacted by

    site activities.

    EPA concluded that a future residential use scenario was most appropriate for estimated risks

    posed by the Site. Exposure to contaminated soils at the Site under a residential exposu