[memorandum regarding national remedy ...apr 1 2 2016 memorandum subject: national remedy review...
TRANSCRIPT
-
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION6
1445 ROSS AVENUE, SUITE 1200 DALLAS TX 75202-2733
APR 1 2 2016
MEMORANDUM
SUBJECT: National Remedy Review Board Revie American Creosote Works Inc. SuR rfl
FROM:
TO:
Carl E. Edlund. P.E. , Directo Superfund Division (6SF)
James E. Woolford, Director
roposed Response Action
Office of Superfund Remediation and Technology Innovation (OSRTI)
Introduction and Purpose
This memorandum provides Region 6' s rationale that the proposed response action at the American Creosote Works Inc. (ACW) Superfund site in Winnfield, Louisiana, does not warrant a National Remedy Review Board (NRRB) review. The Office of Solid Waste and Emergency Response (OSWER) Directive 9285.6-21 (National Remedy Review Board Criteria Revision and Operational Changes, September 4, 2014), call for regions to implement a regional remedy review team (RRRT) to evaluate Superfund site response actions costing between $25 million and $50 million to determine if a full NRRB is warranted or not. The preferred proposed response action at the ACW site is estimated to cost $25 million. The Region 6 RRRT reviewed the ACW proposed remedy and recommended that a full NRRB review is not warranted.
The Site Remedial Project Manager has had several conversations over the last 2 years concerning development of the proposed response action with Office of Superfund Remediation and Technology Innovation (OSRTI) staff within the Assessment and Remediation Division and the Technology Innovation and Field Services Division.
Regional Remedy Review Team Process
The Region 6 RRRT was comprised of the Remedial Branch Chief (John Meyer), two Remedial Section Chiefs (Carlos Sanchez and Blake Atkins), the State of Louisiana ACW site project manager (John Halk), four senior Remedial Project Managers (RPMs) familiar with similar proposed remedy technologies (Vincent Malott, Camille Hueni, David Abshire, and Ursula Lennox), the site risk assessor (Kenneth Shewmake), a senior risk assessor who has previous experience with the site (Jon Rauscher) , the site attorney (Jacob Piehl), the site enforcement officer (Bob Werner), and a community involvement staff member (Adam Weece).
Internet Address (URL) • http://www.epa.gov/region6 Recycled/Recyclable • Printed with Vegetable Oil Based Inks on 100% Recycled Paper, Process Chlorine Free
022095
-
On February 25, 2016, the RPM presented the following information to the Region 6 ACW RRRT:
ACW site setting and background
Overview of current remedy
Rationale for initiation of a Revised FS and alternate remedy strategy
Summary of revised risk assessment results
Areas of the ACW site that have unacceptable risks
Proposed Remedial Action Objectives
Summary of Remedial Action Alternatives
Summary of Nine Criteria Evaluation
Detailed description of the preferred response action, including IC’s and cost
Key factors for proposing the preferred response action
Timing of activities concerning the preferred response action
Potential issues that could affect implementation of the preferred response action
Summary of OSWER Directive 9285.6-21 stakeholder/site circumstances issues
After the RPM’s presentation, Mr. John Halk, the State of Louisiana ACW site project manager presented
the State’s perspective concerning the ACW site. Mr. Halk has been the State’s project manager on the
site for over 20 years and has been intimately involved in the development of the Revised RI/FS. Mr.
Halk indicated that the State does not see the benefit from continuing operations of the current remedy
and therefore, is in agreement with and supports EPA’s preferred remedy. After Mr. Halk’s comments,
the ACW RRRT engaged in questions and deliberations with the Site RPM. Comments provided by the
RRRT during the February 25, 2016, meeting are attached along with responses from the Site RPM.
Site Information and Proposed Response Action
The ACW site is located (see Figure 1) in the City of Winnfield in Winn Parish, Louisiana. Decades of
wood treating activities and improper waste disposal contaminated soil, sediment, surface water and
groundwater with polycyclic aromatic hydrocarbons (PAHs), pentachlorophenol (PCP), benzene and
dioxin. The EPA placed the Site on the National Priorities List in October 1992. Removal actions in the
late 1980s addressed immediate threats to human health and the environment. EPA selected a long-term
remedy to address remaining contamination in a 1993 Record of Decision (ROD). Cleanup began in 1993
and included on-site incineration of highly contaminated tar and sludge; capping of contaminated surface
soil; in-place biological treatment of contaminated subsurface soil; and extraction, separation and
treatment of groundwater and non-aqueous phase liquids (NAPLs).
Due to several years of declining remedy performance and growing concerns of the long-term
effectiveness of the Site’s NAPL recovery and in-place biological treatment systems, EPA initiated an
evaluation in 2010 to develop a more sustainable remedy. Incremental funding resulting from budget and
resource constraints delayed the initiation and/or completion of various activities of this evaluation. EPA
completed a new remedial investigation in April 2014. The 2014 Remedial Investigation Report verified
that the Site’s treatment systems are not effectively addressing remaining site contamination, and also
discovered the presence of site related soil contamination outside of the Site’s previously-established
boundary.
The revised risk assessment evaluated seven different areas (Figure 2), called Decision Units (DU). The
Site was divided into these seven DU’s to facilitate risk management decisions that would be incorporated
into a revised remedy. The seven DU’s that were evaluated were:
022096
-
1. Southern DU (15.6 acres). This area, also known as the south parcel in the 1992 RI/FS and 1993
ROD, was reportedly used primarily to store untreated wood. Some non-recyclable scrap metal
and other non-hazardous debris generated during the 1987-1989 removal actions was reportedly
buried here. The area is now principally owned by the Winn Parish Police Jury. EPA released this
area for use in 1998. The Police Jury leases the property to a local earthwork contractor.
2. Process Area DU (14.2 acres). This area, which is part of the north parcel described in the 1992
RI/FS and 1993 ROD, is where historical wood-treatment operations were conducted. Four
impoundments, where liquid wood-treating wastes were managed, and a waste cell containing
stabilized material from the 1987 removal action and 7,000 CY of low-level contaminated soil
excavated from the Tar Mat Disposal Area are also present. This DU, and the adjacent Non-
Process Area and Tar Mat DUs, are principally owned by Winn Parish but under the control of
EPA through an access agreement and a perimeter fence. The ongoing NAPL recovery and in situ
bioremediation remedy in this DU is addressing the subsurface source of contamination in this
DU.
3. Non-Process Area DU (10.5 acres). This area lies to the east and southeast of the Process Area DU
and contains the fire water pond. This area also contained a portion of the tarry sludge-like
material, which was excavated and incinerated between 1996 and 1998.
4. Tar Mat DU (2.4 acres). This area contained a majority of the 25,000 CY of tarry sludge-like
material, which was excavated and incinerated between 1996 and 1998. The ash generated from
the incineration of this material was placed in the Tar Mat Ash disposal area, a geotextile-lined
and clay-covered disposal cell located in this DU.
5. Northern DU (9.9 acres). Treated wood was transported by rail from the former process area to
this area for drying and staging prior to customer shipment.
6. Creek DU (4.7 acres). This area includes the far western, western, and northern branches of
Creosote Branch Creek that flows through the ACW site. Site-related contaminants were detected
in sediment samples taken from the creek during the 1992 RI/FS and in samples collected in 2008
and 2013.
7. Western DU (4.3 acres). This area contained ACW’s former administration offices. A bridge
across the western branch of Creosote Branch Creek, which has since been removed, provided
access to the former process area where wood-treating operations were conducted.
The additional site information collected post-1993 ROD was utilized to develop an updated risk
assessment. This revised risk assessment identified the following major contaminants of concern (COC):
● Volatile organic compounds – benzene, toluene, ethylbenzene, and xylene (BTEX)
● Phenols – PCP, phenol, 2,3,4,6-tetrachlorophenol, 2,3,5,6-trichlorophenol, and cresols
● PAHs – naphthalene, phenanthrene, fluorine, anthracene, and benzo(a)pyrene
● Dioxins/furans
The post-1993 site remedy investigation activities performed in 2003, 2008, 2012, and 2013 confirmed
the presence of the above COCs in all the above 7 DU’s. Based upon the evaluation performed during the
revised risk assessment, there was unacceptable risk in three of the seven DU’s. These three DU’s and
their associated unacceptable risks (Tables 1, 2, and 3) are as follows:
022097
-
1. Northern DU – surface soil. Maximum‐based intake (doses) for the deer mouse yielded No Observed Adverse Effect Level based HQ’s ranging from 3.4 to 30.4, which exceeds the
CERCLA target ecological HQ of 1.0.
2. Non‐Process Area – surface soil. The industrial worker excess lifetime cancer risk (ELCR)
of 8.3 x 10‐4 exceeded the upper bound CERCLA target risk of 1 x 10‐4.
3a. Process Area – surface and subsurface soil. The industrial worker surface soil ELCR of 2.9 x 10‐4
exceeded the upper bound CERCLA target risk of 1 x 10‐4. The industrial worker subsurface soil
ELCR of 1.4 x 10‐3 also exceeded the upper bound CERCLA target risk of 1 x 10‐4.
3b. Process Area and Non‐Process Area shallow aquifer groundwater impacted by the source area. Groundwater was carried forward into the FS based on the following considerations:
- Shallow aquifer groundwater is not a current (Class IIA) drinking water source; however, based
on EPA groundwater classification guidance (EPA, 1986a) it is considered a potential future
(Class IIB) drinking water source. Per the NCP (40 CFR 300.430(a)(1)(iii)(F)), “EPA expects to
return usable ground waters to their beneficial uses wherever practicable, within a timeframe that
is reasonable given the particular circumstances of the site. When restoration of ground water to
beneficial uses is not practicable, EPA expects to prevent further migration of the plume, prevent
exposure to the contaminated ground water, and evaluate further risk reduction.”
- The concentration of several site‐related contaminants present in groundwater around the source area exceeds MCLs, which define chemical‐specific ARARs for groundwater that is a current or future drinking water source. For example, the BAP TEQ exposure point concentration of 351
μg/L exceeds the 0.2 μg/L MCL. Exceedance of one or more chemical-specific ARARs is the
primary basis for carrying shallow aquifer groundwater into the FS.
- Shallow aquifer groundwater is in hydraulic communication with Creosote Branch Creek. Under
the baseline (no action) condition, it is assumed that contaminated groundwater discharge to the
creek would result in surface water contaminant concentrations exceeding federal or state ambient
water quality criteria (AWQC).
Revised Remedial Action Objectives (RAO) were developed as part of the revised Remedial
Investigation/Feasibility Study (RI/FS).
The 1993 ROD listed the following RAO’s:
1. For shallow groundwater, prevent the exposure of potential receptors to on-site contaminated
groundwater in amounts above human health-based standards and to restore groundwater quality.
2. Remove the threat of potential exposure to future residents via direct contact with contaminated
surface soils, tar mat materials, and non-aqueous phase liquids (NAPL’s).
3. Reduce the potential for site contaminants to migrate into surface waters or groundwater.
Based on the findings of the human health and ecological revised risk assessment, remedial action at the
Site must address the following receptors and exposure pathways:
● Terrestrial ecological receptor direct-contact risk associated with PAH’s present in the Northern
DU surface soil.
● Industrial worker/Construction worker direct-contact risk associated with BAP TEQ, dioxin TEQ,
PCP, naphthalene, and other COC’s present in the Process Area DU surface/subsurface soil.
022098
-
● Industrial worker direct-contact risk associated with dioxin TEQ present in surface soil in the Non-
Process Area DU. Remedial actions that address dioxin TEQ are also expected to reduce BAP
TEQ direct-contact risk.
Under the current remedy, there is no unacceptable risk associated with human or ecological exposure to
COC's present in Creosote Branch Creek surface water or sediment. In the absence of remedial action,
shallow aquifer groundwater discharge to Creosote Branch Creek would likely result in surface water
COC concentrations exceeding ARAR’s or to-be-considered (TBC) guidelines. Therefore, remedial
action must also address:
● Ecological and secondary-contact recreational exposure to COC’s present in Creosote Branch
Creek surface water attributed to Process Area shallow aquifer groundwater discharge.
Based on the above human health and ecological risks that need to be addressed as determined by the
revised risk assessment (included in the Revised RI/FS), RAO’s (i.e., new, retained from 1993 ROD,
revised from the 1993 ROD, or eliminated from the 1993 ROD) for the Site are:
RAO #1 - Prevent industrial worker/construction worker exposure to surface/subsurface soil
contaminants of concern exceeding health based cleanup levels in the Process Area and
Non Process Area Decision Units. (New RAO based upon Revised RI/FS)
RAO #2 - Prevent terrestrial ecological receptor communities exposure to soil contaminants of
concern (Polycyclic Aromatic Hydrocarbons) above ecological risk based cleanup levels in
the Northern Decision Unit. (New RAO based upon Revised RI/FS)
RAO #3 - Minimize aquatic and secondary contact recreational receptors from exposure to the
contaminants of concern present in groundwater discharging to Creosote Branch at
concentrations exceeding health based and ecological based cleanup levels. (Revised 1993
ROD RAO based on Revised RI/FS)
RAO #4 - Minimize further migration of contaminants of concern from source materials to
groundwater. (Retained RAO from 1993 ROD)
RAO #5 - For shallow ground water, prevent the exposure of potential receptors to on-site
contaminated ground water in amounts above human health-based standards and to restore
ground water quality. (Retained from 1993 ROD)
With the anticipated future land use being commercial/industrial based on the Revised RI/FS, the RAO
from the 1993 ROD – Remove the threat of potential exposure to future residents via direct contact with
contaminated surface soils, tar mat materials, and non-aqueous phase liquids (NAPL’s) – is replaced with
the new RAO #1 above.
Based upon the above risks, the Revised RI/FS developed preliminary remediation goals (PRG’s)(see
Table 4). PRG’s define the allowable concentration of COC’s in environmental media that must be
achieved at the completion of the remedial action based on expectations for current and future land,
groundwater, and surface water beneficial use. PRG’s are also helpful in defining the area and volume of
environmental media to be addressed by a remedial action and to assist in the screening of various
technologies. Because there are no Federal or State cleanup standards for soil contamination, the PRG’s
for soil are based upon the revised risk assessment. PRG’s for surface water are a combination of federal
022099
-
and state ambient water quality criteria (AWQC) and other to-be-considered guidelines for the protection
of aquatic receptors and secondary-contact recreation human exposure.
EPA Region 6 evaluated seven detailed alternatives (see Table 5) in the Revised FS, which include (1) No
Action, (2) Institutional Controls with Long-Term Monitoring and Targeted Hot-Spot Excavation, (3)
Upgrade NAPL Recovery and Treatment System and Targeted Hot-Spot Excavation, (4) Slurry Wall and
Multi-Layer Cap and Targeted Hot-Spot Excavation, (5a) Partial-Depth Excavation with Thermal
Desorption and Thermal-Enhanced NAPL Recovery, (5b) Full-Depth Excavation with Thermal
Desorption, and (6) In Situ Solidification/Stabilization and Targeted Hot-Spot Excavation. While
presented for transparency, Alternative 2 was eliminated since it does not meet Threshold Criteria and
Alternative 5b was eliminated in the FS screening process due to implementability and cost. The above
alternatives are described below.
Common Elements
Common elements for the alternatives except for Alternative 1 – No Further Action are described below.
Preconstruction Activities – These activities associated with most of the alternatives include subcontractor
submittals, preparation of community involvement plan and periodic meetings to inform the community,
subcontractor mobilization and demobilization, installation of temporary facilities, underground utility
location survey, and construction surveying.
Institutional Controls – Per NCP requirements [40 CFR 300.430 (e)(3)(ii)], it is expected that IC’s, either
as a standalone alternative or as a component of alternatives employing more aggressive technologies,
would be included as appropriate to prevent or limit exposure to hazardous substances. The individual
IC’s include restrictions that limit land use to industrial/commercial, prevent deep excavation to protect
construction workers, and groundwater use restrictions in the Process Area, Non-Process Area, and Tar
Mat DU’s. Land use IC’s will be implemented through restrictive covenants written into property deeds
and would vary based on the alternative.
Northern DU Soil Excavation and Offsite Disposal – The revised risk assessment identified ecological
risk to invertebrates and terrestrial receptors through direct and indirect exposure to PAH’s in surface soil.
To achieve an acceptable level of risk, a remediation strategy will be used that is the least invasive to the
existing and functioning habitat while still facilitating DU-wide risk reduction. Sampling will be
performed to provide data in order to minimize that volume of surface soil that needs to be addressed.
These volumes of contaminated surface soil will be excavated, transported, and disposed of off-site.
Clean fill will be imported and hydroseeded to re-establish vegetation.
Creosote Branch Creek Bank and Western Fence Soil Excavation – Contaminated areas along the
northern and western fence line near Creosote Branch Creek lie outside the portion of the source area that
can be addressed by the primary technologies included in each alternative. If not addressed, these areas
will act as continuing sources of contamination. Of the technologies evaluated to address soils,
excavation is the only one capable of effectively removing soil contamination is these areas. As in the
Northern DU Soil Excavation common element above, sampling will be performed in these areas near the
creek to minimize the volume of soil that needs to be addressed. Once excavated, the contaminated soils
will be disposed of off-site. The creek excavation areas will replaced with clean fill and constructed to
maintain creek bank integrity.
Five Year Reviews - The NCP, under 40 CFR 300.430(f)(4)(ii), requires that periodic reviews be
conducted if a remedial action is selected that results in hazardous substances, pollutants, or contaminants
022100
-
remaining at the site above levels that allow for unlimited use and unrestricted exposure. These reviews
are conducted no less often than every 5 years after the selected remedial action is initiated. Four five‐year reviews (5YR) have been performed to date, with the last 5YR conducted in 2015. The 5YR would
continue in perpetuity until such a time that the industrial land use IC can be lifted (e.g., DUs released for
unrestricted use/unrestricted exposure).
Current Remedy - The on-site incineration of highly contaminated tars and sludges has been completed.
The pumping, separation, and treatment of liquid contaminants and the in-situ bioremediation components
of the 1993 ROD which were designed to address the subsurface source of shallow ground water
contamination are being replaced by the proposed remedy. A new soil cover to protect the in-situ
solidification/stabilization area will replace the capped surface soils completed under the current remedy.
The goal of restoring ground water to its potential beneficial use is retained from the 1993 ROD and
applies to the shallow ground water impacted by the source area.
The capital cost for the Common Elements is $1.6 million.
Alternative 1 – No Further Action
Estimated Capital Cost: $540,000
Estimated Annual O&M Cost: $0
Estimated Periodic Cost: $100,000
Estimated Present Worth Cost: $640,000
Estimated Construction Timeframe: 1 year
Estimated Time to Achieve RAOs: N/A
Section 300.430 (e)(6) of the NCP requires the inclusion of a no action alternative in the RI/FS, or a no
further action alternative if an interim or final action is already underway, for use as a baseline to compare
against other alternatives. Under this alternative, no further action would be taken in Northern and Non-
Process Area DUs, while in the Process Area DU all recovery wells, injection wells, monitor wells,
piezometers, and horizontal recovery trenches (extraction, injection, and infiltration) would be plugged
and abandoned, operation of the PLTS would cease with all process equipment being decontaminated and
decommissioned, and all underground and aboveground conveyance piping removed, decontaminated,
and decommissioned.
Alternative 1 requires the abandonment of all groundwater monitor wells, extraction wells, and injection
wells as well as the decontamination and decommissioning of the PLTS and associated equipment. The
general duration of Alternative 1 is estimated at 9 months. The present worth cost for this alternative is
estimated at $640,000 with a ‐30/+50 percent cost range of $448,000 to $960,000. Per the NCP (40 CFR 300.430), the no action alternative was carried through the detailed evaluation but was not retained since
it would not provide any protection to human health and the environment.
Alternative 2 – Institutional Controls with Long-Term Monitoring and Targeted Hot Spot Excavation
Estimated Capital Cost: $7.6 million
Estimated Annual O&M Cost: $73,000
Estimated Periodic Cost (every 5 years): $295,000
Estimated Present Worth Cost: $8.5 million
Estimated Construction Timeframe: 1 year
Estimated Time to Achieve RAOs: Greater than 100 years
022101
-
Alternative 2 utilizes an array of overlapping access controls to prevent exposure to contaminated soil and
groundwater. This alternative satisfies the NCP requirement to develop an alternative that involves little
or no treatment and protects human health and the environment by preventing or controlling exposure to
contaminants through engineering controls and, as necessary, ICs. This alternative includes the common
elements listed above, extension of perimeter fencing, the abandonment of all groundwater monitor wells,
extraction wells, and injection wells as well as the decontamination and decommissioning of the PLTS
and associated equipment, installation of a multi-layer soil cover (approximately 11 acres) in the Process
Area DU to provide a direct-contact barrier and prevent rainfall-induced leaching of contaminants present
in soil, long-term monitoring of groundwater and surface water to assess potential impacts to Creosote
Branch Creek, and long-term maintenance of the multi-layer cap.
Key components of Alternative 2 include the following:
The common elements listed above.
Extension of the perimeter fencing to the east to enclose the Non-Process Area DU, requiring an
additional 1,000 ft of 6-foot cyclone fencing to be installed.
Plugging and abandonment of all recovery wells, trenches, monitor wells, and piezometers, and
decontamination and decommissioning of the PLTS and conveyance piping as described for
Alternative 1.
Installation of a multi-layer soil cap (11 acres) in the Process Area DU to provide a direct-contact barrier
and to prevent rainfall-induced leaching of contaminants present in soil and their transport to the
shallow aquifer.
Long-term monitoring (LTM) of groundwater and surface water on a semi-annual basis with progress
reports prepared annually to assess potential impacts to Creosote Branch Creek. The scope of LTM
would be similar to that conducted currently.
LTM and O&M of the Process Area DU multi-layer cap would be conducted for at least 100 years.
Documentation of remedy performance and protectiveness in annual operation summary reports and
5YRs.
The total present worth for Alternative 2 is $8.5 million with a -30/+50 percent cost range of $6.0 million
to $12.8 million. Alternative 2 was carried through the detailed evaluation but was not retained since it
would not provide any protection to human health and the environment.
Alternative 3 – Upgrade NAPL Recovery and Treatment System, and Targeted Hot-Spot Soil Excavation
Estimated Capital Cost: $18.8 million
Estimated Annual O&M Cost: $644,000
Estimated Periodic Cost (every 5 years): $126,000, Additional periodic cost of $3.68 million for PLTS
replacement (year 30 & 60) and extraction well and trench replacement (year 50)
Estimated Present Worth Cost: $28.5 million
Estimated Construction Timeframe: 2 years
Estimated Time to Achieve RAOs: Greater than 100 years
Alternative 3 is a continuation of the current fluids recovery and in situ bioremediation remedy
component implemented under the 1993 ROD. In addition to the common elements, this alternative
022102
-
would include excavation and off-site disposal of dioxin contaminated soil in the Non-Process DU,
replacement and expansion of the soil cover in the Process Area DU, and upgrade/replacement of the
PLTS and the extraction/injection wellfield components to increase NAPL recovery and provide for
improved groundwater treatment.
Key components of Alternative 3 include the following:
The common elements listed above.
A remedial design investigation in the Non-Process Area DU to refine the surface soil excavation
footprint with excavation and offsite disposal of dioxin TEQ-contaminated soil at a RCRA treatment,
storage, and disposal facility (TSD).
Replacement of the north recovery trench and deep injection trench using one-pass technology.
Rehabilitation of all existing extraction wells through chemical addition and mechanical swabbing.
Conversion to a two-pump extraction system for groundwater and NAPL recovery.
Decontamination and decommissioning of the current system.
Upgrade of the PLTS building and treatment train.
Upgrade of the PLTS electrical and instrumentation and control (I&C) systems to provide greater
remote/offsite operations and improved reliability.
Replacement and expansion of the soil cover in the Process Area DU using a multi-layer cap to prevent
rainfall infiltration and limit vertical migration of COCs and NAPL in the vadose zone.
100 years of O&M. It is assumed the recovery wells and PLTS mechanical equipment will require
replacement approximately every 30 years.
Periodic sampling, analysis, and reporting to: 1) confirm PLTS treatment effectiveness, 2) assess the need
for treatment media change-out, and compliance with potential discharge criteria, 3) assess COC
concentration changes, and 4) verify hydraulic containment of the dissolved-phase plume.
Documentation of remedy performance and protectiveness in annual operation summary reports and
5YRs.
The total present worth cost for Alternative 3 is $28.5 million with a -30/+50 percent cost range of $19.9
million to $42.3 million.
Alternative 4 – Containment with Slurry Wall and Surface Multi-Layer Cap, and Targeted Hot-Spot Soil
Excavation
Estimated Capital Cost: $17.6 million
Estimated Annual O&M Cost: $117,000
Estimated Periodic Cost (every 5 years): $295,000
Estimated Present Worth Cost: $18.5 million
Estimated Construction Timeframe: 2 years
Estimated Time to Achieve RAOs: N/A
Alternative 4 satisfies the NCP requirement to develop an alternative that involves little or no treatment
and protects human health and the environment by preventing or controlling exposure to contaminants
through engineering controls and, as necessary, ICs. In addition to the common elements, this alternative
022103
-
would include excavation and off-site disposal of dioxin contaminated soil in the Non-Process DU, an
approximate 2,600 foot long subsurface containment slurry wall would be installed with a multi-layer
impermeable surface cap constructed to prevent infiltration into the area enclosed by the slurry wall, and a
deep aquifer dewatering system which would prevent upward groundwater migration which could result
in contaminants being pushed out of the containment area or failure of the slurry wall.
Key components of Alternative 4 include the following:
The applicable common elements listed above.
Remedial design investigation and excavation of surface soil in the Non-Process DU as described under
Alternative 3.
Remedial design investigation to determine the extent of NAPL underlying the Tar Mat Ash DU, a deep
aquifer pump test to determine the appropriate pumping rate needed to maintain a neutral vertical
gradient between the shallow and deep aquifers to prevent flooding inside the containment area, and
testing pits in the northwest corner of the Process Area DU (as necessary) to confirm that there is no
subsurface debris present that would interfere with construction of the slurry wall.
Abandonment and decommissioning of the existing groundwater extraction and injection wellfield as
described under Alternative 1.
Abandonment of 30 shallow/deep monitor wells in the Process Area DU. Ten wells located within the
slurry wall footprint and four outside the footprint would be retained as long-term monitoring
locations.
Installation of a 2,600-ft-long slurry wall encompassing the soil, NAPL, and dissolved-phase COC plume
where concentrations exceed PRGs within the Process Area DU.
Install deep aquifer dewatering wells, number of wells determined based on the results from the pump
test, it is assumed that pumping would be required for 100 years.
Installation of a GAC treatment system to treat deep aquifer groundwater if necessary.
Installation of a multi-layer cap over the area enclosed by the slurry wall.
LTM to verify remedy effectiveness.
The total present worth cost for Alternative 4 is $18.5 million with a -30/+50 percent cost range of $12.9
million to $27.7 million.
Alternative 5a – Partial-Depth Excavation with Thermal Desorption, and Thermal-Enhanced NAPL
Recovery
Estimated Capital Cost: $47.2 million
Estimated Annual O&M Cost (years 4-14): $1.3 million
Estimated Annual O&M Cost (years 15-100): $73,000
Estimated Periodic Cost (every 5 years): $295,000
Estimated Present Worth Cost: $45.7 million
Estimated Construction Timeframe: 5 years
Estimated Time to Achieve RAOs: 100 years
Alternative 5a addresses the NCP requirement to develop an alternative which at a minimum treats the
principal threats posed by the site but varies in the degree of treatment employed and quantities and
characteristics of the treatment residuals. In addition to common elements, this alternative would include
022104
-
excavation and treatment of soils down to 5 feet below ground surface, installation and operation of an
enhanced NAPL recovery system that would utilize heated water to enhance NAPL recovery, and an in-
situ barrier that would treat remaining ground water contamination as it discharges to Creosote Branch
creek.
Key elements of Alternative 5a include the following:
The applicable common elements listed above.
Remedial design investigation to determine the extent of NAPL underlying the Tar Mat Ash DU.
Excavation of surface soil in the Non-Process Area DU as described in Alternative 3.
Abandonment and decommissioning of the existing groundwater extraction and injection wellfield (as
described under Alternative 1) with the exception of the north recovery trench and extraction wells R-
19, -20, and -21. These would be operated to maintain hydraulic capture until the enhanced NAPL
recovery system is operational.
Excavation of soil from 0 to 5 ft bgs in the Process Area DU with COC concentrations greater than PRGs.
Treatment of excavated soil onsite using medium-temperature thermal desorption (MTTD).
Enhanced NAPL recovery using an array of alternating horizontal extraction and injection wells, installed
east-west perpendicular to the groundwater flow direction, using one-pass technology. A total of 12
wells is assumed.
Inject hot water (125 degrees Fahrenheit [°F]) to induce hydraulic, thermal, and viscosity gradients to
increase NAPL recovery. The effectiveness of this element and the design temperature are based on
bench-scale pilot tests conducted in 2003.
Upgrade of the PLTS (as described under Alternative 3). A heat exchanger would be installed at the head
of the PLTS to recover heat from extracted groundwater.
Installation of a multi-layer soil cap over the Process Area DU at the completion of enhanced NAPL
recovery efforts.
Installation of a funnel and gate permeable reactive barrier (PRB) as a polishing step for dissolved-phase
groundwater treatment at the completion of enhanced NAPL recovery efforts, which are presumed to
conclude after 10 years of operation.
The total present worth cost for Alternative 5a is $45.7 million with a -30/+50 percent cost range of $32.0
million to $68.6 million.
Alternative 5b – Full-Depth Excavation with Thermal Desorption
Estimated Capital Cost (nondiscounted): $101,000,000
Estimated Annual O&M Cost (nondiscounted): $73,000
Estimated 5 Year Periodic Cost (nondiscounted): $36,000
Estimated Present Worth Cost: $91,000,000
Estimated Construction Timeframe: 3 years
Estimated Time to Achieve RAOs: 5 years
Alternative 5b addresses the NCP requirement to develop an alternative that removes contaminants to the
maximum extent practicable minimizing the need for long-term management. Alternative 5b is similar to
022105
-
Alternative 5a but extends the excavation depth to the base of the contamination, removing all COCs
exceeding the PRG.
Key components of Alternative 5b include the following:
The applicable common elements listed above.
Remedial design investigation and excavation of surface soil in the Non-Process Area DU (detailed in
Alternative 3)
Abandonment and decommissioning of the existing groundwater extraction wellfield (detailed in
Alternative 1).
Excavation of soil from 0 to 30 ft bgs with contaminant concentrations greater than the PRGs. Excavation
would be completed in 75-ft by 75-ft cells. To reach the excavation depth and minimize dewatering,
the cells would have temporary sheet piling installed around the perimeter.
Large-scale dewatering would be required for each of the excavation cells.
Excavated soil would be treated onsite using MTTD. Treated soil would be used as backfill.
Even though this alternative was eliminated in the screening step, a detailed cost estimate was prepared,
and the total present worth cost for Alternative 5a is $88.4 million with -30/+50 percent cost range of
$62.1 million to $133.2 million.
Alternative 6 – In-Situ Solidification/Stabilization, and Targeted Hot-Spot Soil Excavation
Estimated Capital Cost: $26.1 million
Estimated Annual O&M Cost: $73,000
Estimated Periodic Cost (every 5 years): $295,000
Estimated Present Worth Cost: $25.0 million
Estimated Construction Timeframe: 6 years
Estimated Time to Achieve RAOs: 6 years
Alternative 6 addresses the NCP requirement to develop an alternative that treats the principal threats but
varies in the degree of treatment employed and the quantities and characteristics of the treatment
residuals. Although contaminants are not removed using in situ solidification/stabilization (ISS), they are
immobilized. Under Alternative 6, all mobile and immobile NAPL present within the Process Area and
Tar Mat DUs would be stabilized in situ using a mix of 1.5 percent Portland cement amended with 3.5
percent cement slag, 1 percent organo-clay, 1 percent bentonite, 2 percent tar mat ash. The mix design is
based on the results of the ISS Treatability Study presented in the Revised RI/FS. In addition, the mix
design concentrations will be doubled for the perimeter of the treatment area than used to treat the interior
portion to create a hardened shell that would have lower leachability and higher durability.
Key components of Alternative 6 include the following:
Each of the common elements listed above.
Remedial design investigation and excavation of surface soil in the Non-Process Area DU (detailed in
Alternative 3).
Remedial design investigation on the western side of the Tar Mat area to determine how much of the Tar
Mat area needs to be included in the ISS treatment area.
022106
-
Abandonment and decommissioning of the existing groundwater extraction and injection wellfield
(detailed in Alternative 1) with the exception of the north recovery trench and extraction wells R-19,
R-20, and R-21. These would be operated to maintain hydraulic capture until the ISS installation
reaches the downgradient portion of the Site.
ISS of mobile and immobile NAPL source materials using backhoe mixing or auger mixing.
Perimeter ISS columns extending to the bottom of the source area which would have lower leachability
and higher durability than the interior ISS columns in order to prevent any unidentified source
materials not treated by interior columns from migrating from the source area.
Air monitoring during ISS to ensure workers and residents are not exposed to site contaminants.
An approximately 3-ft-thick soil cover to protect the ISS treatment area and to prevent direct contact with
treatment residuals.
The total present worth cost for Alternative 6 is $25 million with a -30/+50 percent cost range of $17.5
million to $37.4 million.
The ACW team proposed that: (6) In Situ Solidification/Stabilization and Targeted Hot-Spot Excavation
be implemented to meet the anticipated future land use of commercial/industrial (see Figure 3 and
attached Final Draft Proposed Plan). Under Alternative 6, EPA would excavate and dispose of PAH
contaminated surface soils in the Northern Decision Unit to address unacceptable ecological risks;
investigate, excavate, and dispose of dioxin/PAH contaminated surface soils in the Non-Process Area
Decision Unit to address unacceptable human health and ecological risks; excavate a small portion and
primarily perform in situ solidification/stabilization within the source area located in the Process Area
Decision Unit to address unacceptable human health and ecological risks; and execute institutional
controls to limit land use to commercial/industrial, prevent deep excavation to protect the
solidified/stabilized source materials, and restrict the use of groundwater.
The proposed response action has an estimated capital cost of $26.1M, an annual O&M cost of $73,000,
and a periodic cost of $295,000, for a total present worth cost of $25M. EPA Region 6 estimates that the
remedy can be completed within 6 years at which time Remedial Action Objectives would be met except
for groundwater. As prescribed in the original 1993 ROD which would be amended by the proposed
response action, after the source control technologies are implemented, monitoring would be performed to
evaluate performance of the source control measures and their effect on the groundwater at the site.
The preferred alternative is protective of human health and the environment because PAH and dioxin
contaminated soil is removed and disposed off-site and source materials (principal threat wastes) are
solidified/stabilized to prevent migration of Contaminants of Concern to Creosote Branch Creek and to
surrounding groundwater. As indicated in the 1993 ROD which is being amended by the proposed
response action, groundwater at the site is expected to restore to its potential future beneficial use shortly
after completion of the solidification/stabilization of the source materials.
The proposed response action would comply with all federal and State ARARs.
The proposed response action was the highest rated alternative for the combination of Long-Term
Effectiveness, Reduction of Toxicity, Mobility, and Volume, Short-Term Effectiveness, and
Implementability compared to all the other potential alternatives. The proposed response action would
eliminate the migration of contaminants from the source materials to Creosote Branch Creek and the
022107
-
surrounding groundwater, would eliminate long term operation of a recovery system as being currently
implemented in the original remedy, and will make the site ready for commercial/industrial use.
All actions in the proposed response action are readily implementable and the Louisiana Department of
Environmental Quality has indicated that it supports the proposed response action.
NRRB Review Not Warranted
The ACW RRRT concluded that a review of the proposed response action by the NRRB would not be
necessary because excavation and in situ solidification/stabilization has routinely been used at other
creosote contaminated sites.
In addition, the proposed response action is less expensive than the alternative which upgrades the current
remedy at site and provides significantly more certainty concerning potential migration of contaminants
from the source area. It will also enable the site to be available for commercial/industrial use whereas the
alternative which upgrades the current remedy at the site would not.
Lastly, in consideration of pertinent stakeholder concerns and other site circumstances – (1) the Louisiana
Department of Environmental Quality supports the proposed response action at the ACW site and
understands that it would be responsible for a 10 percent cost match at the site, (2) there has been no
Congressional or community interest in the site since the implementation of the original remedy in the
mid-1990’s, specifically, no citizens attended the last public meeting held in December 2015. The City of
Winnfield is only interested in the site being addressed so that the site can be developed for
commercial/industrial purposes, (3) there are no tribal interests associated with the site, and (4)
technologies in the proposed response action are common to other sites and therefore, are consistent with
previous EPA response actions.
Please signify your concurrence below:
__________________ I concur that review of the proposed response action by the NRRB is not
warranted.
__________________ I do not concur.
Attachments (9)
022108
-
Regional Remedy Review Team
American Creosote Superfund Site
February 25, 2016
INTRODUCTION
The use of In-Situ Stabilization/Solidification (ISS) for treatment of shallow source material at former
wood treater and oily waste sites is considered to be a regional presumptive remedy approach in Region 6.
This technical recommendation is based on the experience of the Remedial Project Managers participating
in the RRRT and their experience and expertise gained from implementing remedial actions at a number
of sites over the last 20 years. The successful implementation of ISS has been completed at similar wood
treater and oily waste sites including North Cavalcade Street, Texarkana Wood Preserving, Mountain Pine
Pressure Treatment, and South 8th Street Landfill. At sites that did not include ISS as part of the remedy
implementation, there are long-term operational and maintenance issues with potentially significant costs.
RECOMMENDATIONS:
RPM 1 Comments
At the RRRT review, Solidification/stabilization (S/S) was presented as the preferred alternative. The
RRRT recommends that the following items be considered during the design and implementation of the
remedy:
S/S is expensive per cubic yard – by excavating soil above the S/S area, we can decrease the cubic yard stabilized. Solidification (cement) is not the major cost, stabilization (Powered Activated
Carbon - PAC) is the major cost.
1) We can expect up-to 30% swell of the solidified material, which will require offsite disposal or onsite consolidation in a cell (type cell depends on excavated soil risk). Based on soil volumes
discussed; the onsite cell appears to be more cost effective than offsite disposal.
RPM Response – The issue of how to manage swell will be evaluated in the RD.
2) For reuse – we may want to consider excavation of sufficient soil at the S/S site to allow for sufficient clean fill/soil thickness to promote tree growth, slabs, posts/pilings, etc.
RPM Response – Methods to reduce cost, such as excavation of clean soil to minimize the
amount of material that is addressed with in-situ solidification/stabilization will be evaluated
in the RD.
3) If we excavate for S/S, we should excavate a small area (e.g., 1-acre), S/S that area, and then backfill as soon as practicable, in this way we minimize contaminated stormwater
management.
RPM Response – Methods to minimize storm water management will be evaluated in the
RD.
4) A bench scale test usually tests to a UCS of 50 psi and a percent by weight carbon for concentrations below the MCL (usually 4%). I agree with the Pilot Test mentioned; we can
decrease costs by reducing the UCS based on the potential reuse (e.g., storage – 15-20
UCS). We can also reduce the cost for PAC through the Pilot.
RPM Response – The most predominant factor in the treatability study performed during
the FS was the leaching potential of contaminants. Various mixes that achieved acceptable
leaching results over achieved the requirements of unconfined compressive strength and
022109
-
hydraulic conductivity. The treatability study results will be re-evaluated in the RD to
determine if any changes to the treatability study mix designs.
Section Chief Comments
At the RRRT presentation, the RPM provided information to amend the soil remedy for the site. However, not enough information was provided regarding the groundwater component of the
existing remedy.
The RRRT recommends that the RPM fully discuss what is planned for the groundwater
component in the decision document.
RPM Response – The groundwater component of the existing/proposed remedy will be more
thoroughly discussed in the Proposed Plan.
At the RRRT presentation, the RPM discussed alternative 5b which was full removal of the contaminated soils. However, this alternative was not fully discussed under the nine criteria. The
RRRT recommends that alternative 5b be presented through the nine criteria and evaluation in the
decision document.
RPM Response – Alternative 5b will be incorporated into the Proposed Plan.
RPM 2 Comments
As explained at the RRRT review presentation, Solidification/Stabilization (SS), will both contain the larger NAPL source area and provide additional source “treatment” through immobilization of
mass within the SS ring itself. The SS approach is consistent with source remedies implemented at
Region 6 creosote sites over the last ~5 years, after original pump and treat remedies were shown
to be problematic. The combination of a SS ring, anchored in the Cockfield confining zone, with
a constructed cover over the interior of the ring will effectively encapsulate the primary source
area. During discussions, it was noted that the bottom confining layer is a Cockfield transitional
facies overlying the Sparta, the drinking water supply aquifer. There may be concerns that the
Cockfield may be a “leaky” confining layer, so the argument that the Cockfield has not been
impacted becomes most important. The RRRT recommends that the RPM clarify in the ground
water/site characteristics discussion that the monitoring coverage on the Cockfield is adequate to
make this argument. And you may want to consider that monitoring will continue into the future
and the network will be further evaluated during design or the Five-Year Review. You would want
to prepare a case for not needing to monitor the Sparta, if that is the case.
EPA Response – Several well pairs completed in the shallow/deep aquifers have been monitored
since before and after the remedy startup in the mid-1990’s. Historical observations from these
well pairs, including observations during non-pumping conditions, have always indicated an
upward gradient from the deep aquifer (Cockfield) to the shallow aquifer. In addition, the
Cockfield is approximately 150 feet thick and is comprised of interbedded clays, silts, and sands.
Based upon the historical upward gradient and the thickness of the Cockfield, it does not
appear that monitoring the Sparta is necessary.
RPM 3 Comments At the RRRT review, Alternative 6 was presented as the preferred alternative. The RRRT recommends
that the following items be considered during for the preferred alternative that could result in cost saving
during design and implementation of the remedy
For Alternative 6, consider dewatering of the former fire water pond and utilize the storage
capacity for excess ISS treated material within the Site boundary. The combination of the pond,
022110
-
and a potential excavation area within the incinerator ash waste cell, will provide capacity to
reduce the amount of mounding anticipated after ISS treatment of the contaminated soil area.
RPM Response – The use of the fire water pond for ISS swell management will be evaluated in
the RD.
For Alternative 6, consider removal and storage of the clean soil cap material for later use as the
soil cover on the ISS treated material. This material will reduce the total volume of soil requiring
ISS treatment.
RPM Response – Methods to reduce cost, such as excavation of clean soil to minimize the
amount of material that is addressed with in-situ solidification/stabilization will be evaluated in
the RD
For Alternative 6, consider adding a statement in the Proposed Plan on the need for air monitoring
during the ISS treatment to address potential exposure pathways to the community downwind of
the Site.
RPM Response – A statement concerning planned air monitoring during the ISS activities will
be inserted into the Proposed Plan.
For Alternative 6, consider incorporating the contaminated soil from the hot spots into the ISS
mixing process to eliminate the need for off-site transport and disposal. If the potential funding
plan does not allow this action, then consider adding an explanation in the Proposed Plan or other
record on why the action is a priority for risk reduction.
RPM Response – Methods to reduce costs such as combining hot spot contaminated soils into
the ISS mixing process will be evaluated in the RD.
For Alternative 6, the ISS treatment process that provides a continuous treatment perimeter as well
as treatment of the source material waste is not expected to require further treatment or monitoring
of the ground water remaining below the treated waste. Following completion of the source area
ISS treatment, the remaining ground water is considered to be within the waste management area,
and the ground water restoration objective in the ROD is not considered relevant for future action.
RPM Response – Agreed and the goal of restoration for the groundwater surrounding the
source area will be described in the Proposed Plan.
At the RRRT review, Alternative 2 was presented as one of the alternative considered. The RRRT
recommends that the RPM consider the following:
For Alternative 2, consider removing this alternative and include the remedy components as
common elements for Alternatives 3 – 6. While Alternative 2 does address RAOs 1 – 3, the
Alternative does not provide an action that will address the proposed RAO #4 for minimizing
further migration of contaminants of concern from source materials.
RPM Response – Agreed that Alternative 2 does not meet all the RAO’s, however, it will still be
presented in the Proposed Plan in order to be transparent to the public concerning all the
alternatives that EPA considered. However, the Proposed Plan will be clear that Alternative 2
cannot be considered for remedy selection since it does not meet the Threshold Criteria.
At the RRRT review, the RPM presented the RAOs for the Proposed Plan. The RRRT recommends that
the RPM consider including an explanation in the Proposed Plan that the objective to restore groundwater
quality has not been changed in the planned ROD Amendment.
022111
-
RPM Response – The Proposed Plan will be revised to make it clear RAO’s are either new, modified
from the original ROD, eliminated from the original ROD, or not eliminated from the original ROD
and thus still apply.
The RRRT notes that implementation of Alternative 6, or any of the other alternatives, does not trigger a
site-wide construction completion until the ground water issues are addressed in a subsequent ROD
Amendment.
RPM Response – It is acknowledged that the site-wide construction completion target is not achieved
until ground water issues are ultimately addressed.
022112
-
Figure 1 - American Creosote Works Inc. - Site Location Map
Disclaimer: This map and any boundary lines within the map are approximate and subject to change. The
map is not a survey. The map is for informational purposes only regarding EPA’s response actions at the
Site.
• Winnfield,
American Creosote Works, Inc. • (Winnfield Plant)
Louisiana "----~ Superfund Site
0 250 500 1,000 ••c:::=•••-Feet
0 NORTH
X -X Site Fence
American Creosote Works, Inc. (Winnfield Plant) Superfund Site Winnfield , Winn Parish, Louisiana
022113
-
_̂
Site Location
LEGEND
Former FireWater Pond
BoilerBuilding TankFarmRetort
Retort
Far West (FW) Branch
North (N) Branch
West (W) Branch
WasteCell 1 2
2 4
Southern Decision Unit/South Parcel(15.6 acres)
Process Area Decision Unit/North Parcel(14.2 acres)
Northern Decision Unit(9.9 acres)
Non-Process Area Decision Unit/North Parcel(10.5 acres)
Western Decision Unit(4.3 acres)
Tar Mat Decision Unit(2.4 acres)
FIGURE 2
American Creosote WorksWinnfield, Louisiana
0 225 450Feet
FenceCreek (Creosote Branch)
Pond/CreekHistorical Process Area Surface Water Drainage
! !
K
Approximate Locationof Historical Tar Mat Area
Historical ImpoundmentsHistorical Treated WoodStorage Areas
HOU \\Hollister\Groups\IS\Proj\American_Creosote\apr-mxd\2015\Figure 1-02 ACW Historic Facilities and Decision Units.mxd cg021858 4/21/2015 5:00:22 PM
Historic Facilities andDecision Unit Map
Source: ESRI World Imagery online mapping service
Decision UnitsCreek Decision UnitNon-Process Area Decision Unit/North ParcelNorthern Decision UnitProcess Area Decision Unit/North ParcelSouthern Decision Unit/South ParcelTar Mat Decision UnitWestern Decision Unit
Waste Cell
022114
-
TABLE 1 Process Area Decision Unit Quantitative Human Health Risk Summary American Creosote Works, Winnfield, Louisiana
Receptor Exposure
Area Medium Exposure
Route
Excess Lifetime Cancer
Risk Hazard Index Chemicals of Potential Concern
Industrial/
Commercial
Worker
Soil
(Process Area
DU)
Surface Soil
(0-1 foot bgs)
Total 2E-03 3.5 Total dioxin TEQ, 1,1-biphenyl, PCP, total BAP
TEQa
Subsurface Soil
(0-10 feet bgs)
Total 2E-03 4 2-methylnaphthalene, PCP, total BAP TEQ,
1,1-biphenyl, naphthalene
Groundwater
(Process Area
and Non-
Process DUs)
Groundwater Total 2E-01 262 Noncarcinogenic PAHsb, methylphenols, 1,1-
biphenyl, 1,1,2,2-tetrachloroethane, 1,1,2-
trichloroethane, 1,2-dibromoethane, 1,2-
dichloropropane, bromodichloromethane,
PCP, total BAP TEQ, benzene, and
ethylbenzene
Construction
Worker
Soil
(Process Area
DU)
Surface Soil
(0-1 foot bgs) Total 2E-04 6 Total dioxin TEQ, naphthalene, PCP, total BaP
TEQ
Subsurface Soil
(0-10 feet bgs) Total 2E-04 7 2-methylnaphthalene, PCP, total BAP TEQ,
naphthalene
Shallow
Aquifer
Groundwater
(Process Area
and Non-
Process DUs)
Groundwater Total 4E-03 11 Fluoranthene, PCP, naphthalene, total BAP
TEQ
Notes: a BAP TEQ includes: benzo(a)anthacene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(k)fluoranthene, chrysene,
dibenz0(a,h)anthacene, and indeno(1,2,3-cd)pyrene b noncarcinogenic PAHS include: acenaphthene, acenaphthylene, anthacene, fluoranthene, fluoranthene, phenanthrene, and pyrene
% = percent BAP TEQ = benzo(a)pyrene toxicity equivalent
bgs = below ground surface
COC = chemical of concern
DNAPL = dense non-aqueous phase liquid Dioxin TEQ = 2,3,7,8 tetrachlorodibenzo-p-dioxin toxicity equivalent
DU = decision unit
NAPL = non-aqueous phase liquid
PCP = pentachlorophenol
022115
-
TABLE 2 Preliminary Risk Screening All Decision Units American Creosote Works, Winnfield, Louisiana
Decision Unit Medium
Dioxins (ng/kg) PAHs (mg/kg) Quantitative RA
Dioxin TEQ Exposure
Point Conc. PRE (ELCR)*
BAP TEQ Exposure
Point Conc. PRE (ECLR)*
Total PRE (ECLR)
Exceeds Upper Bound (1.0E-04) of CERCLA Risk Range
Risk-based Screening Level (Industrial)** 18 1E-06 0.21 1E-06
Northern
Surface Soil (0 to 1 feet bgs)
175.1 1.E-05 17.7 8.E-05 9.E-05 No
Subsurface Soil (1 to 10 feet bgs)
NA NA 1.96 9.E-06 9.E-06 No
Non-Process Area
Surface Soil (0 to 1 feet bgs)
14,634.00 8.E-04 4.54 2.E-05 8.E-04 Yes
Subsurface Soil (1 to 10 feet bgs)
NA NA 2.83 1.E-05 1.E-05 No
Process Area
Surface Soil (0 to 1 feet bgs)
237.4 1.E-05 59.1 3.E-04 3.E-04 Yes
Subsurface Soil (1 to 10 feet bgs)
NA NA 296 1.E-03 1.E-03 Yes
Southern
Surface Soil (0 to 1 feet bgs)
288 2.E-05 4.87 2.E-05 4.E-05 No
Subsurface Soil (1 to 10 feet bgs)
NA NA 1.12 5.E-06 5.E-06 No
Western Surface Soil (0 to 1 feet bgs)
199.8 1.E-05 3.85 2.E-05 3.E-05 No
Tar Mat Subsurface Soil (1 to 10 feet bgs)
285.4 2.E-05 0.23 1.E-06 2.E-05 No
RSLs Sediment (Industrial)** 18 0.21
Fire Water Pond Sediment 79.96 4.E-06 0.44 2.E-06 7.E-06 No
022116
-
TABLE 2 Preliminary Risk Screening All Decision Units American Creosote Works, Winnfield, Louisiana
Decision Unit Medium
Dioxins (ng/kg) PAHs (mg/kg) Quantitative RA
Dioxin TEQ Exposure
Point Conc. PRE (ELCR)*
BAP TEQ Exposure
Point Conc. PRE (ECLR)*
Total PRE (ECLR)
Exceeds Upper Bound (1.0E-04) of CERCLA Risk Range
North Creosote Branch Sediment
60.55 3.E-06 3.33 2.E-05 2.E-05 No
West Creosote Branch Sediment
7.66 4.E-07 0.40 1.9E-06 2.E-06 No
Background Values
Background
Surface Soil 31.81 NA 0.432 NA NA
Subsurface Soil NA NA 0.425 NA NA
Surface Water NA NA 21.134 NA NA
Sediment 10.77 NA 0.876 NA NA
Notes: Identifies Decision Units and media carried forward to feasibility study based on exceedance of upper bound CERCLA risk range. *PRE = Preliminary Risk Evaluation = (Dioxin TEQ or BAP TEQ/ Industrial RSL)*10^-6 for carcinogens ** = PRE was calculated for sediment using the soil Industrial RSL value of 18 ng/kg for dioxins and 0.21 mg/kg for PAHs. Surface water criteria were not available for industrial workers for a PRE calculation. BAP-TEQ = benzo(a)pyrene toxicity equivalent concentration bgs = below ground surface CERCLA = Comprehensive Environmental Response, Compensation, and Liability Act of 1980 Dioxin TEQ = 2,3,7,8-TCDD toxicity equivalent concentration DU = Decision Unit ECLR = Estimated Lifetime Cancer Risk kg = kilogram mg = milligram NA = not applicable ng = nanogram
022117
-
TABLE 3
Summary of Risks ‐‐ Terrestrial Habitats
American Creosote Works, Winnfield, Louisiana
Constituents
Decision Unit
Direct Exposure
Indirect (Food Web) Exposure
Birds Mammals
NBQ AW AK DM NBA M RF
PAHs
Northern x
(HPAH)
x (6 HPAH)
Non‐Process x
(HPAH)
x (1 HPAH)
Process x
(LPAH & HPAH)
x
(2 HPAH)
x (8 HPAH)
Southern Western
Dioxins/Furans
(TEQs)
Northern
Not Evaluated
x Non‐Process x x x x x
Process x Southern Western
Notes:
An "x" indicates risk; blank cells indicate no risk. HPAH = high molecular weight PAHs AK =
American Kestrel LPAH = low molecular weight PAHs AW =
American Woodcock PAH = polycyclic aromatic hydrocarbon DM =
Deer Mouse TEQ = toxic equivalents
M = Mink NBA = Nine‐banded
Armadillo NBQ = Northern Bobwhite
Quail RF = Red Fox
022118
-
TABLE 4 Preliminary Remediation Goals for Soil and Groundwater American Creosote Works - Winnfield, Louisiana Preliminary Remediation Goal
Contaminant of Concern Units Northern DU Non-
process Area DU
Process Area DU
PRG Basis
Soil
High Molecular Weight PAHsa mg/kg 18 NA NA Ecological Receptor at HQ=1
1,1-Biphenyl mg/kg NA NA 200 Human Health at HQ = 1
2-Methylnaphthalene mg/kg NA NA 3,000 Human Health at HQ = 1
BAP TEQ mg/kg NA 3.0 3.0 Human Health at ELCR = 1 x 10-4
Dioxin TEQ mg/kg NA 0.00073 0.00073 Human Health at HQ = 1
Naphthalene mg/kg NA NA 290 Human Health at HQ = 1
Pentachlorophenol mg/kg NA NA 400 Human Health at ELCR = 1 x 10-4
Shallow Aquifer Groundwaterf
1,1-biphenyl µg/L NA 14 Ecological Screening Valuee
1-Methylnaphthalene µg/L NA 2.1 Ecological Screening Valuee
2-Methylnaphthalene µg/L NA 63 Ecological Screening Valuee
3&4-Methylphenol (m&p-Cresol) µg/L NA 272 Ecological Screening Valuee
Acenaphthene µg/L NA 23 Ecological Screening Valuee
Acenaphthylene µg/L NA 7,731 Site-specific Secondary Contact Recreationd
Anthracene µg/L NA 0.30 Ecological Screening Valuee
BAP TEQ µg/L NA 0.25 Site-specific Secondary Contact Recreationd
Benzene µg/L NA 1,125 Louisiana AWQC - Aquatic Organism Protectionb
Benzo(a)anthracene µg/L NA 35 Ecological Screening Valuee
Benzo(a)pyrene µg/L NA 0.014 Ecological Screening Valuee
Chrysene µg/L NA 7.0 Ecological Screening Valuee
Dibenz(a,h)anthracene µg/L NA 5.0 Ecological Screening Valuee
Dibenzofuran µg/L NA 94 Ecological Screening Valuee
Ethylbenzene µg/L NA 1,600 Louisiana AWQC - Aquatic Organism Protectionb
Fluoranthene µg/L NA 6.2 Ecological Screening Valuee
Naphthalene µg/L NA 250 Ecological Screening Valuee
Pentachlorophenol µg/L NA 15 Federal AWQC - Aquatic Organism Protectionc
Phenanthrene µg/L NA 30 Ecological Screening Valuee
Pyrene µg/L NA 7.0 Ecological Screening Valuee
Xylenes µg/L NA 1,340 Ecological Screening Valuee
Notes: a Ecological PRGs were not developed for individual high molecular weight PAH compounds, but they are included in the total high molecular weight PRG calculation. The individual high molecular weight PAHS include: benzo(a)anthracene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene, dibenz(a,h)anthracene, fluoranthene, indeno(1,2,3-c,d)pyrene, and pyrene. b Reference: Table 1, Freshwater Chronic Numerical Criteria for Specific Toxic Substances Louisiana Administrative Code Title 33, Part IX, Subpart 1 (2014b) c Reference: Environmental Protection Agency (EPA) National Recommended Water Quality Criteria (EPA, 2014) d Reference: Site-specific calculated value based on lowest value of excess lifetime cancer risk of 1 x 10-4 or hazard quotient of 1.0 e Reference: Texas Commission on Environmental Quality, http://www.tceq.state.tx.us/assets/public/remediation/eco/0106eragupdate.pdf f Non-Process Area and Process Area Decision Units lie in the same geographic portion of the shallow aquifer; therefore, the PRGs are the same. µg/L = microgram per liter AWQC = ambient water quality criteria BAP = benzo(a)pyrene DU = Decision Unit ELCR = excess lifetime cancer risk HQ = hazard quotient mg/kg = milligram per kilogram NA = not applicable PAH = polycyclic aromatic hydrocarbon PRG = preliminary remediation goal TEQ = toxicity equivalent
022119
-
Table 5- Comparative Evaluation of Alternatives American Creosote Works, Winnfield, Louisiana
Alternative 1: Criterion No Further
Action
Key Treatment Technologies
Northern DU Soil
Non-process Area DU (Soil) Not
Process Area DU (Soil < 5 feet) Applicable Process /\rea DU (Soil > 5 feet)
Threshold Criteria
Process Area, Non-process
Area, and Northern DUs
Protects H HE No
Complies with ARARs No
Balancing Criteria
Long-term Effectiveness and Not evaluated
Permanence
Reduction of TM V through Treatment Not evaluated
Short-term Effectiveness Not evaluated
lmplementability Not evaluated
Cost
Total Present Worth Cost $640,000
Present Worth Cost Range
-30 Percent $448,000
+50 Percent $960,000
Annual O&M Cost $0
Periodic Cost $0
Total Non-discounted Cost $640,000
Modifying Crit eria
Stat e Acceptance
Community Acceptance
Alternative 2: ICs with Alternative 3- Upgrade NAPL
LTM and Targeted Hot-Recovery and Treatment System,
spot Soil Excavation and Targeted Hot-Spot Soil
Excavation
Excavation and Disposal Excavation and Disposal
ICs and Fence
ICs and Multi-layer Cap Multi-layer Cap
Upgrade N/\PL Recovery and Treatment
Non-Process process, Process Non-process, Area DU Northern Area DU Northern DUs
DUs
No No Yes Yes
Yes' Yes Yes' Yes
Not evaluated * **** Not evaluated
·~ **** Not evaluated ** **** Not evaluated ***· ***Cl
$8,500,000 $28,500,000
$5,97,000 $19,920,000
$12,780,000 $42,690,000
$73,000 $664,000
$295,000 $4,930,000
$17,370,000 $92,450,000
****= The alternative performs superior against the CERCLA balancing criterion with no disadvantages or uncertainties
Alternative 4- Containment Alternative Sa- Partial Depth with Slurry Wall and Multi-layer Excavation- Thermal Cap with Targeted Hot-spot Soil Desorption, and Thermal
Excavation Enhanced Extraction
Excavation and Disposal Excavation and Disposal
Slurry Wall and Cap Excavation and MTID
Thermal Enhanced N/\P L Recovery
Process Non-process, Process Non-process, Area DU Northern DUs Area DU Northern DUs
Yes Yes Yes Yes
Yes' Yes Yes' Yes
** **** *** **** **ti1 **** *** **** *** **** ** **** rt-::n *** *-- ***Cl
$18,500,000 $45,700,000
$12,920,000 $32,010,000
$27,690,000 $68,605,000
$117,000 $1,300,000
$295,000 $295,000
$31,680,000 $69,040,000
Not evaluated in this FS
*** ** *
= The alternative performs well against the CERCLA balancing criterion with minimal disadvantages or uncertainties
=The alternative performs fair against the CERCLA balancing criterion but with some disadvantages or uncertainties
=The alternative performs poorly against the CE RCLA balancing criterion with more disadvantages or uncertainty
'This assessment does not include groundwater. The groundwater decision is postponed to a future decision document.
>=less than < = greaterthan ARARs =applicable or relevant and appropriate requirements CERCLA =Comprehensive Environment31 Response, Compensation, and Uability Act of 1980 (commonly known as Superfund)
DU =decision unit FS =feasibility study H HE = Human Health and the Environment I C = institutional control ISS= in situ solidification/stabilization
LTM =long-term monitoring MTID =medium temperature thermal desorption NAPL =nonaqueous phase liquid O&M =operation; and maintenance TMV =toxicity, mobility, and volume
Alternative Sb- Full Depth Excavation with Thermal Alternative 6 -ISS
Desorption
Excavation and Disposal Excavation and Disposal
Excavation and MTID ISS
Process Non-process, Process Non-process, Area DU Northern DUs Area DU Northern DUs
Yes Yes Yes Yes
Yes' Yes Yes' Yes
**** **** **** **** **** **** **** **** * " **** ** : **** _..1 ***~ ...-:~ '**'*"
$91,000,000 $25,000,000
$64,000,000 $17,4 70,000
$137,000,000 $37,430,000
$73,000 $73,000
$36,000 $295,000
$104,000,000 $31,190,000
022120
-
_̂
Site Location
LEGEND
PLTS SupportBldg.
PLTSBldg.Bioreactor
Pond
0 15075Feet K
T:\IS\Proj\American_Creosote\apr-mxd\Alt6_remediation_footprints.mxd 4/8/2016 gtwigg
FenceCreek (Creosote Branch)
! !
Site Utility RoadsTar Mat Ash Disposal Cell
Figure 3Alternative 6 Remediation FootprintsIn-Situ Solidification/StabilizationAmerican Creosote WorksWinnfield, Louisiana
NPDU – Non-Process Decision UnitDioxin Soil Excavation Footp rint(This Area will be Refined duringRemedial Desig n)NDU – Northern Decision Unit SoilExcavation Footp rintPDU – In Situ Solidification/Stabilization Footp rint
022121
-
PROPOSED PLAN Amendment to April 1993 Record of Decision
American Creosote Works Inc. Superfund Site
Winnfield, Louisiana
Xx/xx, 2016
The purpose of this Proposed Plan is to:
● Identify the proposed alternate remedy that will amend the April 1993 remedy;
● Summarize the information that prompted and supports fundamentally changing
the April 1993 remedy;
● Solicit public review and comment on the alternate cleanup strategy as well as
information contained in the Administrative Record file; and,
● Provide information on how the public can be involved in the remedy selection
process for the American Creosote Works Inc. Site.
Dates to Remember:
● Public Comment Period:
Xx/xx/xxx to xx/xx/xxxx
The EPA and LDEQ will accept written comments on the Proposed Plan during the public
comment period.
● Public Meeting: xx/xx/xxxx
The EPA will hold a public meeting to explain the Proposed Plan and all of the alternatives
presented in the Feasibility Study. Oral and written comments will also be accepted at the
meeting. The meeting will be held at the Winn Parish Library, 200 N. St. John Street,
Winnfield, LA, 71843, at x:xx pm.
● Administrative Record is available for viewing at:
EPA Region 6 LDEQ Headquarters
7th Floor Reception Area Public Records Center
1445 Ross Avenue, Suite 12D13 Galvez Building, 1st Floor – Room 127
Dallas, TX 75202-2733 602 N. Fifth Street
Toll Free (800) 533-3508 or (214) 665-6597 Baton Rouge, LA 70802
Monday – Friday 7:30 – 11:00 am/1:00 – 4:00 pm (225) 219-3181
Winn Parish Library
200 N. St. John Street
Winnfield, LA 71843
(318) 628-4478
Hours – 8:30 am-5:30 pm Monday - Friday, 10 am-2pm Saturday
022122
-
Introduction
In this Proposed Plan, the U.S. Environmental Protection Agency (EPA) presents summary
information for an alternate remedy for the American Creosote Works Inc. Superfund Site (Site)
located in the City of Winnfield, Winn Parish, Louisiana (Figure 1). The remedy implemented
pursuant to the April 1993 Record of Decision has been successful in reducing the amount of
contamination at the Site. However, due to several years of declining remedy performance and
growing concerns of the long-term effectiveness of the Site’s Non-Aqueous Phase Liquid
(NAPL) recovery and in-place biological treatment systems, EPA has concluded that the
previously selected remedy will not achieve existing cleanup objectives in a reasonable amount
of time.
This Proposed Plan highlights key information about the progress of the current remedy, the
current extent of the remaining contamination at the site, and the revised cleanup objectives. The
EPA is issuing this Proposed Plan to recommend the following alternate remedy for the Site:
● Alternative 6 – In-Situ Solidification/Stabilization, and Targeted Hot-Spot Soil Excavation
Alternative 6 would solidify/stabilize in situ the subsurface source of ground water
contamination (i.e., mobile and immobile NAPL) present within the Process Area and Tar Mat
Decision Units.
● Current Remedy – The on-site incineration of highly contaminated tars and sludges has been
completed. The pumping, separation, and treatment of liquid contaminants and the in-situ
bioremediation components of the 1993 ROD which were designed to address the subsurface
source of shallow ground water contamination are being replaced by the proposed remedy. A
new soil cover to protect the in-situ solidification/stabilization area will replace the capped
surface soils completed under the current remedy. The goal of restoring ground water to its
potential beneficial use is retained from the 1993 ROD and applies to the shallow ground water
impacted by the source area.
The EPA has conducted its activities in connection with the Site in accordance with the
Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or
Superfund), 42 U.S.C. §§ 9601 et seq., and the National Oil and Hazardous Substance
Contingency Plan (NCP), 40 C.F.R. Part 300. The EPA is issuing this Proposed Plan in
accordance with and as part of its public participation responsibilities under CERCLA § 117(a),
42 U.S.C. § 9617(a) and 40 C.F.R. § 300.430(f)(2). The summary information and
recommendations set forth in this Proposed Plan are based on information and documents
contained in the Administrative Record file for the Site.
The EPA Region 6 office is the lead agency for this Site and has conducted remedial activities at
the site since the 1990’s. The Louisiana Department of Environmental Quality (LDEQ) is the
support agency and provided technical review of the remedy performance through a cooperative
agreement with EPA.
022123
-
Community Participation
This Proposed Plan highlights information contained in the Administrative Record for the Site
which includes annual operation and maintenance reports, historical and revised investigation
reports, revised feasibility study reports, and other documents and reports used in preparing this
Proposed Plan. The EPA encourages the public to review those documents to obtain more
information about the Superfund activities that have been conducted at the Site. The EPA also
encourages the public to participate in the decision-making process for the Site. The
Administrative Record file is available at the following information repositories:
EPA Region 6 LDEQ Headquarters
7th Floor Reception Area Public Records Center
1445 Ross Avenue, Suite 12D13 Galvez Building, 1st Floor – Room 127
Dallas, TX 75202-2733 602 N. Fifth Street
Toll Free (800)533-3508 or (214)665-6597 Baton Rouge, LA 70802
Monday-Friday 7:30-11:00 am/1:00-4:00 pm (225)219-3181
Winn Parish Library
200 N. St. John Street
Winnfield, LA 71843
Monday-Friday 8:30 am-5:30 pm, Saturday 10:00 am-2:00 pm
The EPA will hold a public meeting to inform residents of the proposed alternate remedy for the
cleanup of the Site and obtain comments on the Proposed Plan for the American Creosote Works
Inc. Site in the City of Winnfield, Winn Parish, Louisiana.
The public meeting will be held on XXXXXX, MONTH DAY, YEAR, at TIME at the
Winn Parish Library, 200 N. St. John Street, Winnfield, Louisiana, 71843. The public meeting is
being held in a fully accessible facility. Should you have specific needs or questions about the
facility, please contact Michael A. Hebert, Remedial Project Manager, at (214) 665-8315 or toll-
free (800) 533-3508 or Jason McKinney, Community Involvement Coordinator, (214) 665-8132
or toll-free (800) 533-3508.
Public comments can be presented at the public meeting or can be submitted during the public
comment period from DATE, through DATE. All written comments should be addressed to:
Michael A. Hebert, Remedial Project Manager
U.S. EPA Region 6 (6SF-RL)
1445 Ross Avenue
Dallas, Texas 75202-2733
214-665-8315
For specific information about the LDEQ’s participation in the Superfund process, please
contact:
022124
-
John Halk, Project Manager
Louisiana Department of Environmental Quality
Remediation Services Division
Group 3
P.O. Box 4314
Baton Rouge, LA 70821-4314
225-219-3717
Site Background and Characteristics
The ACW site is a former wood-treating facility, spanning about 62 acres, located at 1006 Front
Street in Winnfield, Louisiana. According to the U.S. Census Bureau, about 4,600 people lived
in Winnfield in 2013. Land uses nearby include agricultural, residential, commercial, and
recreational uses. Residences near the Site are connected to the City of Winnfield’s public water
system. Wood treatment operations at the Site began around 1901 and continued under various
ownerships until 1985, when the Louisiana Department of Environmental Quality (LDEQ)
discovered that the Site had been abandoned.
Unplanned releases of creosote and pentachlorophenol (PCP) based wood-treating oil, and waste
handling practices resulted in extensive soil, groundwater, and sediment contamination.
Contaminant sources present at the time of abandonment included two storage tanks, visibly
contaminated soil present in the former process area, waste material present in a surface
impoundment located just north of the fire water pond, and tarry-sludge material present in an
area later identified as the Tar Mat sludge disposal area. In response to these conditions, EPA
completed two removal actions to stabilize contaminant sources and reduce the potential for
further contaminant releases. The removal actions were performed between 1987 and 1989.
A Remedial Investigation/Feasibility Study (RI/FS) was performed in 1992/1993 and focused
primarily on the areas where wood treating operations were conducted. From information
reviewed during the RI, the wood treating operations were determined to have occurred in the
north-central portion of the Site. A tank farm, with no visible secondary containment, was also
located in this north-central part of the site. The earliest aerial photographs (1940 and 1947) of
the Site showed evidence (soil staining and stressed vegetation) that wood-treating oil flowed
unimpeded from the former process area towards Creosote Branch Creek. An onsite drainage
pathway that discharged to Creosote Branch Creek is also visible on a 1940 aerial photograph as
is a natural drainage that flows eastward from the former process area.
Between April 1950 and May 1952, two impoundments were constructed in the process area
which received liquid wastes from the wood-treating process. Several shallow drainage ditches
were also constructed to convey runoff from the process area. A 1959 aerial photograph shows a
pool of standing liquid northeast of the tank farm in the process area. Evidence of standing
liquid and dark-stained soil at this location appears in subsequent aerial photographs through
1973.
022125
-
Sometime prior to 1966, additional wood treatment facilities were built in the southern portion of
the process area and a third impoundment was constructed east of the process area.
Interpretation of aerial photographs indicates heavy wood treating activity at the Site during the
mid- to late-1960s. According to facility records, during a 7-month period in 1966, 750,000
gallons of petroleum distillate, 40,000 gallons of creosote, and 54,000 pounds (3,200 gallons) of
PCP were used to treat 7.5 million board-ft of lumber. Between 1973 and 1976, extensive
earthwork that was performed north and east of the Process Area covered up the majority of
stained soil and removed all evidence of Impoundment 1. A fourth impoundment was built
northeast of Impoundment 2. This impoundment may have received drainage or overflow from
Impoundment 2. A water storage pond was also constructed south of Impoundment 2 to collect
and store rainwater for emergency fire-fighting. Evident in a 1973 photograph is the formation
of the “Tar Mat” area, located approximately 500 feet east of the Process Area. The Tar Mat was
a large, flat, asphalt-like waste material that extended over a marshy portion of the Site. The
source of the Tar Mat material is unknown, but the 1992/1993 RI/FS Report indicates that it
might have resulted from a large, single spill event. The Tar Mat area also may have resulted
from removal and disposal of impoundment sludge. By 1983, Impoundments 2 and 4 had been
backfilled, presumably with wood chips, and the impoundment dikes had been leveled.
However, Impoundment 3 remained active.
In June 1985, the Louisiana Department of Environmental Quality (LDEQ) found the site
abandoned and referred it to EPA, which placed the site on the National Priorities List (NPL) on
October 14, 1992, based on a hazard ranking score of 50.7.
The 1992/1993 RI/FS determined that the primary threats that the Site posed to public health
were direct contact or ingestion of contaminated site soils and ingestion of contaminated site
groundwater by potential future residents. The RI determined that site soil was contaminated
with polycyclic aromatic hydrocarbons (PAHs), volatile organic compounds (VOCs), dioxins
and PCP. The most heavily contaminated surface soils were located in the former process and
impoundment areas, the tar mat area, and its related drainage area in the northeast portion of the
Site. Contaminated subsurface soil is present throughout the former process area, the
impoundment area and the tar mat area. Contaminants in shallow aquifer groundwater include
PAHs, phenols and benzene. The RI determined that groundwater contamination was present
primarily in the former process and impoundment areas and areas hydraulically downgradient of
those locations. Surface water and sediment in Creosote Branch Creek were also impacted by
site activities.
EPA concluded that a future residential use scenario was most appropriate for estimated risks
posed by the Site. Exposure to contaminated soils at the Site under a residential exposu