MDOT ProjectWise Improvements and External Access 2015 MDOT – ACEC Partnering Workshop Richard Chelotti | Bergmann Associates Rachelle VanDeventer | Engineering Support Greg Vanis | Engineering Support Heather VerHage | Design Support

Upload: truongdiep

Post on 05-May-2018

229 views

Category:

Documents


6 download

TRANSCRIPT

MDOT ProjectWise Improvements and

External Access2015 MDOT – ACEC Partnering Workshop

Richard Chelotti | Bergmann AssociatesRachelle VanDeventer | Engineering Support

Greg Vanis | Engineering SupportHeather VerHage | Design Support

Overview

External ProjectWiseProcess Improvements (Included)CSD Consultant InvoicingBoilerplate Update

ProjectWise Solution

Electronic DocumentSubmission

Single Source of Truth

Secure Storage

Transparent

Accessible

Workflows

Digitally EncryptedElectronic Signatures

ProjectWise & PI: External Access• Three Design Pilots (Bay Region)

• Approximately 650 External Users

• 176 Companies to Date

MDOT Employee Consultant FHWA Contractor

• Security checks Run Daily

• Folder Permissions Set per Business Participation:

ProjectWise & PI

• Folders• Security & Sharing

• Business Processes

• Document Retention

• Workflows• Updated Existing & Added New

• Auto-generated & Fillable e-Mails

• Documentation• Naming Conventions

• Folder Template Map

• Workflow Instructions

• Web Page

Folder Template Map• Folder Structure Breakdown

• Descriptions

• File Examples

ProjectWise & PI: Supporting Documents

• Files to Highlight:

• Form 0303

• Turn-in Milestone Checklist

• Plan Review Contact List

• Design Exception Workflow

• CA Form Workflow – UNDER DEVELOPMENT

ProjectWise & PI:New & Combined Forms

• Updated and/or Improved Forms

• New Milestone Submission Form 0303 (Combined 6 Forms into 1)

• Milestone Checklist (Combined 3 Checklist into 1)

• Design Exceptions Form – Updated

• Still Under Review for Improvements

• Certification & Acceptance Forms

• Scoping Forms 1960 & 1961

RID Review Folders• RID Reviews

• Due With Applicable Milestones

• Reviewed During Review Time

• Comments Supplied by Due Date

• Email:

[email protected]

• MDOT Design Wiki:

http://mdotwiki.state.mi.us/design/index.php/Main_Page

ProjectWise & PI: Plan Set

• ‘PlanSet’ Files

• Folders by Discipline

• Security at Folder Level

• DGN Plan Files & Power GEOPAK Files

• Ability to Add Sub-Folders

ProjectWise & PI: Pre-Construction

• Organized by Document Categories

• Business Area Permissions

• Folders to Highlight:

• Record Plan Set Review Comments

• Stakeholder Engagement

• Working Design

Naming Convention

Folder Permissions

ProjectWise & PI: Construction

• October 2014 all Trunkline Projects

• Shop Drawings Folder

• Every Day Counts 3 Initiative

http://www.fhwa.dot.gov/everydaycounts/edc-3/econstruction.cfm

ProjectWise & PI: Milestone Review Workflows

Base Plan and OEC Workflows

•Pending Submittal•ReviewMilestone

Folder

•Pending•Ready for Review•Review Complete•PM Review Complete•Design Team Response•Review Completed

SubmittalForm

Sub-Folder

(Package Submittal)

(Review)

ProjectWise & PI:Plan Review Process w/Digital Comments

• Comments: Digital Pen (Internal) or Adobe Markup Tools

• 15 Work Days for Review

• Due Date for Electronic Comments

• 5 Work Days PM Review/Compile

• Comments Sent to All 5 Work Days (minimum) Prior to Meeting

• Meeting Held

ProjectWise & PI:Combined Construction & ROW Plans

• One Set, One Review

• DGN Reference Files• Parcel File – Real Estate • ROW File – Design Project Team

• Base and Preliminary Plan reviews will include ROW reviews

• Construction plans will be used to supplement the ROW sketches and other legal instruments during legal negotiations.

Implementation• Scope of Services

• E-sign Validation Form

• Access and Install

• No Cost

• MDOT Datasource

• Need Admin Rights to Install

• Sub-vendors

• Access Request

• March 2015 Implementation

Training• Website: www.Michigan.gov/MDOT/Doing Business/Vender Consultant

Services/Design Services/MDOT ProjectWise Training

• Face-to-Face Training - dates and request form on website

• Training Webinars - dates posted on website

• Tips/Tricks Webinars

ProjectWise:CSD ProjectWise Consultant Invoice Workflow

Pending

ConsultantSubmit

ToMDOT CSD

ProjectManagerReview

CSD Final Review

Submit to ASD for

processing

Payment Processed

Boilerplate

• Saves Space and Paper (if printed)

• All Versions Stored in ProjectWise

• All SPs, Unique SPs, and Special Details in One Spot in Proposal

• Pilot Letting(s) – May/June

• FY 2016 ImplementationExisting Proposal Boilerplate Proposal

STATUS UPDATE

Boilerplate:Checklist with Links

STATUS UPDATE

• SS/SP Checklist System

• Includes All Standard Plans & Special Details

• Generate Checklist for Final Turn-In

• Checklist Contains Links

Boilerplate:Proposal Table of Contents

STATUS UPDATE

Upcoming Initiatives• ProjectWise Tips & Tricks Webinars

• External Access to Local Agencies

• PM Workshop – Coming Soon!

• ProjectWise & Process Improvements

• Reference Information Documents (RID) & 3D Model Requirements

• Others…

• Electronic Sealing of Title Sheet

Summary• External ProjectWise Submittals

• RID Reviews

• One Plan Set

• March Implementation

• Training

Questions?