© The McGraw-Hill Companies, Inc., 2008 7.1 McGraw-Hill/Irwin Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing (Section 7.1) 7.2–7.11 Using BIP for Project Selection: Tazer Corp. (Section 7.2)7.12–7.15 Using BIP for the Selection of Sites: Caliente City (Section 7.3) 7.16–7.19 Using BIP for Crew Scheduling: Southwestern Airways (Section 7.4) 7.20–7.24 Using Mixed BIP to Deal with Setup Costs: Revised Wyndor (Section 7.5) 7.25–7.30 Introduction to Integer Programming (UW Lecture) 7.31–7.46 These slides are based upon a lecture from the MBA core-course in Management Science at the University of Washington (as taught by one of the authors). Applications of Integer Programming (UW Lecture) 7.47–7.59 These slides are based upon a lecture from the MBA elective “Modeling with Spreadsheets” at the University of Washington (as taught by one of the authors).

Upload: rosamond-carr

Post on 13-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.1McGraw-Hill/Irwin

Table of ContentsChapter 7 (Using Binary Integer Programming)

A Case Study: California Manufacturing (Section 7.1) 7.2–7.11Using BIP for Project Selection: Tazer Corp. (Section 7.2) 7.12–7.15Using BIP for the Selection of Sites: Caliente City (Section 7.3) 7.16–7.19Using BIP for Crew Scheduling: Southwestern Airways (Section 7.4) 7.20–7.24Using Mixed BIP to Deal with Setup Costs: Revised Wyndor (Section 7.5) 7.25–7.30

Introduction to Integer Programming (UW Lecture) 7.31–7.46These slides are based upon a lecture from the MBA core-course in Management Science at the University of Washington (as taught by one of the authors).

Applications of Integer Programming (UW Lecture) 7.47–7.59These slides are based upon a lecture from the MBA elective “Modeling with Spreadsheets” at the University of Washington (as taught by one of the authors).

Page 2: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.2McGraw-Hill/Irwin

Applications of Binary Variables

• Since binary variables only provide two choices, they are ideally suited to be the decision variables when dealing with yes-or-no decisions.

• Examples:– Should we undertake a particular fixed project?

– Should we make a particular fixed investment?

– Should we locate a facility in a particular site?

Page 3: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.3McGraw-Hill/Irwin

California Manufacturing Company

• The California Manufacturing Company is a diversified company with several factories and warehouses throughout California, but none yet in Los Angeles or San Francisco.

• A basic issue is whether to build a new factory in Los Angeles or San Francisco, or perhaps even both.

• Management is also considering building at most one new warehouse, but will restrict the choice to a city where a new factory is being built.

Question: Should the California Manufacturing Company expand with factories and/or warehouses in Los Angeles and/or San Francisco?

Page 4: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.4McGraw-Hill/Irwin

Data for California Manufacturing

DecisionNumber

Yes-or-NoQuestion

DecisionVariable

Net PresentValue

(Millions)

CapitalRequired(Millions)

1 Build a factory in Los Angeles? x1 $8 $6

2 Build a factory in San Francisco? x2 5 3

3 Build a warehouse in Los Angeles? x3 6 5

4 Build a warehouse in San Francisco? x4 4 2

Capital Available: $10 million

Page 5: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.5McGraw-Hill/Irwin

Binary Decision Variables

DecisionNumber

DecisionVariable

PossibleValue

Interpretationof a Value of 1

Interpretationof a Value of 0

1 x1 0 or 1Build a factory inLos Angeles

Do not buildthis factory

2 x2 0 or 1Build a factory inSan Francisco

Do not buildthis factory

3 x3 0 or 1Build a warehouse inLos Angeles

Do not buildthis warehouse

4 x4 0 or 1Build a warehouse inSan Francisco

Do not buildthis warehouse

Page 6: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.6McGraw-Hill/Irwin

Algebraic Formulation

Let x1 = 1 if build a factory in L.A.; 0 otherwisex2 = 1 if build a factory in S.F.; 0 otherwisex3 = 1 if build a warehouse in Los Angeles; 0 otherwisex4 = 1 if build a warehouse in San Francisco; 0 otherwise

Maximize NPV = 8x1 + 5x2 + 6x3 + 4x4 ($millions)subject to

Capital Spent: 6x1 + 3x2 + 5x3 + 2x4 ≤ 10 ($millions)Max 1 Warehouse: x3 + x4 ≤ 1Warehouse only if Factory: x3 ≤ x1

x4 ≤ x2

andx1, x2, x3, x4 are binary variables.

Page 7: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.7McGraw-Hill/Irwin

Spreadsheet Model

3456789

1011121314151617181920

B C D E F GNPV ($millions) LA SF

Warehouse 6 4

Factory 8 5

Capital Required($millions) LA SFWarehouse 5 2 Capital Capital

Spent AvailableFactory 6 3 9 <= 10

Total MaximumBuild? LA SF Warehouses Warehouses

Warehouse 0 0 0 <= 1<= <=

Factory 1 1

Total NPV ($millions) 13

Page 8: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.8McGraw-Hill/Irwin

Sensitivity Analysis with Solver Table

2324252627282930313233343536

B C D E F GCapital Available Warehouse Warehouse Factory Factory Total NPV

($millions) in LA? in SF? in LA? in SF? ($millions)0 0 1 1 13

5 0 1 0 1 96 0 1 0 1 97 0 1 0 1 98 0 1 0 1 99 0 0 1 1 1310 0 0 1 1 1311 0 1 1 1 1712 0 1 1 1 1713 0 1 1 1 1714 1 0 1 1 1915 1 0 1 1 19

Page 9: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.9McGraw-Hill/Irwin

Management’s Conclusion

• Management’s initial tentative decision had been to make $10 million of capital available.

• With this much capital, the best plan would be to build a factory in both Los Angeles and San Francisco, but no warehouses.

• An advantage of this plan is that it only uses $9 million of this capital, which frees up $1 million for other projects.

• A heavy penalty (a reduction of $4 million in total net present value) would be paid if the capital made available were to be reduced below $9 million.

• Increasing the capital made available by $1 million (to $11 million) would enable a substantial ($4 million) increase in the total net present value. Management decides to do this.

• With this much capital available, the best plan is to build a factory in both cities and a warehouse in San Francisco.

Page 10: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.10McGraw-Hill/Irwin

Some Other Applications

• Investment Analysis– Should we make a certain fixed investment?

– Examples: Turkish Petroleum Refineries (1990), South African National Defense Force (1997), Grantham, Mayo, Van Otterloo and Company (1999)

• Site Selection– Should a certain site be selected for the location of a new facility?

– Example: AT&T (1990)

• Designing a Production and Distribution Network– Should a certain plant remain open? Should a certain site be selected for a new

plant? Should a distribution center remain open? Should a certain site be selected for a new distribution center? Should a certain distribution center be assigned to serve a certain market area?

– Examples: Ault Foods (1994), Digital Equipment Corporation (1995)

Page 11: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.11McGraw-Hill/Irwin

Some Other Applications

• Dispatching Shipments– Should a certain route be selected for a truck? Should a certain size truck be used?

Should a certain time period for departure be used?

– Examples: Quality Stores (1987), Air Products and Chemicals, Inc. (1983), Reynolds Metals Co. (1991), Sears, Roebuck and Company (1999)

• Scheduling Interrelated Activities– Should a certain activity begin in a certain time period?

– Examples: Texas Stadium (1983), China (1995)

• Scheduling Asset Divestitures– Should a certain asset be sold in a certain time period?

– Example: Homart Development (1987)

• Airline Applications:– Should a certain type of airplane be assigned to a certain flight leg? Should a certain

sequence of flight legs be assigned to a crew?

– Examples: American Airlines (1989, 1991), Air New Zealand (2001)

Page 12: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.12McGraw-Hill/Irwin

Project Selection at Tazer Corp.

• Tazer Corporation is searching for a new breakthrough drug.

• Five potential research and development projects:– Project Up: Develop a more effect antidepressant that doesn’t cause mood swings

– Project Stable: Develop a drug that addresses manic depression

– Project Choice: Develop a less intrusive birth control method for women

– Project Hope: Develop a vaccine to prevent HIV infection

– Project Release: Develop a more effective drug to lower blood pressure

• $1.2 billion available for investment (enough for 2 or 3 projects)

Question: Which projects should be selected to research and develop?

Page 13: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.13McGraw-Hill/Irwin

Data for the Tazer Project Selection Problem

1Up

2Stable

3Choice

4Hope

5Release

R&D ($million)

400 300 600 500 200

Success Rate 50% 35% 35% 20% 45%

Revenue if Successful ($million)

1,400 1,200 2,200 3,000 600

Expected Profit ($million)

300 120 170 100 70

Page 14: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.14McGraw-Hill/Irwin

Algebraic Formulation of Tazer Project Selection

Let xi = 1 if approve project i; 0 otherwise (for i = 1, 2, 3, 4, and 5)

Maximize P = 300x1 + 120x2 + 170x3 + 100x4 + 70x5 ($million)

subject to

R&D Budget: 400x1 + 300x2 + 600x3 + 500x4 + 200x5 ≤ 1,200 ($million)

and xi are binary (for i = 1, 2, 3, 4, and 5).

Page 15: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.15McGraw-Hill/Irwin

Spreadsheet for Tazer Project Selection Problem

123456789

10

A B C D E F G H I J

Tazer Corp. Project Selection Problem

Up Stable Choice Hope Release Total BudgetR&D Investment ($million) 400 300 600 500 200 1200 <= 1200

Success Rate 50% 35% 35% 20% 45%Revenue if Successful ($million) 1400 1200 2200 3000 600

Expected Profit ($million) 300 120 170 100 70 540

Do Project? 1 0 1 0 1

Page 16: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.16McGraw-Hill/Irwin

Selection of Sites for Emergency Services:The Caliente City Problem

• Caliente City is growing rapidly and spreading well beyond its original borders

• They still have only one fire station, located in the congested center of town

• The result has been long delays in fire trucks reaching the outer part of the city

Goal: Develop a plan for locating multiple fire stations throughout the city

New Policy: Response Time ≤ 10 minutes

Page 17: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.17McGraw-Hill/Irwin

Response Time and Cost Data for Caliente City

Fire Station in Tract

1 2 3 4 5 6 7 8

Response times

(minutes) for a fire in

tract

1 2 8 18 9 23 22 16 28

2 9 3 10 12 16 14 21 25

3 17 8 4 20 21 8 22 17

4 10 13 19 2 18 21 6 12

5 21 12 16 13 5 11 9 12

6 25 15 7 21 15 3 14 8

7 14 22 18 7 13 15 2 9

8 30 24 15 14 17 9 8 3

Cost of Station($thousands)

350 250 450 300 50 400 300 200

Page 18: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.18McGraw-Hill/Irwin

Algebraic Formulation of Caliente City Problem

Let xj = 1 if tract j is selected to receive a fire station; 0 otherwise (j = 1, 2, … , 8)

Minimize C = 350x1 + 250x2 + 450x3 + 300x4 + 50x5 + 400x6 + 300x7 + 200x8

subject to

Tract 1: x1 + x2 + x4 ≥ 1Tract 2: x1 + x2 + x3 ≥ 1Tract 3: x2 + x3 + x6 ≥ 1Tract 4: x1 + x4 + x7 ≥ 1Tract 5: x5 + x7 ≥ 1Tract 6: x3 + x6 + x8 ≥ 1Tract 7: x4 + x7 + x8 ≥ 1Tract 8: x6 + x7 + x8 ≥ 1

and xj are binary (for j = 1, 2, … , 8).

Page 19: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.19McGraw-Hill/Irwin

Spreadsheet Model for Caliente City Problem

123456789

1011121314151617181920212223242526272829

A B C D E F G H I J K L M N

Caliente City Fire Station Location Problem

Fire Station in Tract1 2 3 4 5 6 7 8

1 2 8 18 9 23 22 16 28Response 2 9 3 10 12 16 14 21 25

Times 3 17 8 4 20 21 8 22 17(Minutes) 4 10 13 19 2 18 21 6 12for a Fire 5 21 12 16 13 5 11 9 12in Tract 6 25 15 7 21 15 3 14 8

7 14 22 18 7 13 15 2 98 30 24 15 14 17 9 8 3

Cost of Station 350 250 450 300 50 400 300 200($thousands) Number

Covering1 1 1 0 1 0 0 0 0 1 >= 1

Response 2 1 1 1 0 0 0 0 0 1 >= 1Time 3 0 1 1 0 0 1 0 0 1 >= 1<= 4 1 0 0 1 0 0 1 0 1 >= 110 5 0 0 0 0 1 0 1 0 1 >= 1

Minutes? 6 0 0 1 0 0 1 0 1 1 >= 17 0 0 0 1 0 0 1 1 2 >= 18 0 0 0 0 0 1 1 1 2 >= 1

TotalFire Station in Tract Cost

1 2 3 4 5 6 7 8 ($thousands)Station in Tract? 0 1 0 0 0 0 1 1 750

Page 20: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.20McGraw-Hill/Irwin

Southwestern Airways Crew Scheduling

• Southwestern Airways needs to assign crews to cover all its upcoming flights.

• We will focus on assigning 3 crews based in San Francisco (SFO) to 11 flights.

Question: How should the 3 crews be assigned 3 sequences of flights so that every one of the 11 flights is covered?

Page 21: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.21McGraw-Hill/Irwin

Southwestern Airways Flights

Seat tl e (SEA)

San Francisco (SFO)

Los Angel es (LAX)

Denver (DEN)

Chicago ORD)

Page 22: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.22McGraw-Hill/Irwin

Data for the Southwestern Airways Problem

Feasible Sequence of Flights

Flights 1 2 3 4 5 6 7 8 9 10 11 12

1. SFO–LAX 1 1 1 1

2. SFO–DEN 1 1 1 1

3. SFO–SEA 1 1 1 1

4. LAX–ORD 2 2 3 2 3

5. LAX–SFO 2 3 5 5

6. ORD–DEN 3 3 4

7. ORD–SEA 3 3 3 3 4

8. DEN–SFO 2 4 4 5

9. DEN–ORD 2 2 2

10. SEA–SFO 2 4 4 5

11. SEA–LAX 2 2 4 4 2

Cost, $1,000s 2 3 4 6 7 5 7 8 9 9 8 9

Page 23: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.23McGraw-Hill/Irwin

Algebraic Formulation

Let xj = 1 if flight sequence j is assigned to a crew; 0 otherwise. (j = 1, 2, … , 12).

Minimize Cost = 2x1 + 3x2 + 4x3 + 6x4 + 7x5 + 5x6 + 7x7 + 8x8 + 9x9 + 9x10 + 8x11 + 9x12

(in $thousands)

subject to

Flight 1 covered: x1 + x4 + x7 + x10 ≥ 1

Flight 2 covered: x2 + x5 + x8 + x11 ≥ 1

: :

Flight 11 covered: x6 + x9 + x10 + x11 + x12 ≥ 1

Three Crews: x1 + x2 + x3 + x4 + x5 + x6 + x7 + x8 + x9 + x10 + x11 + x12 ≤ 3

and

xj are binary (j = 1, 2, … , 12).

Page 24: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.24McGraw-Hill/Irwin

Spreadsheet Model

3456789

101112131415161718192021222324

B C D E F G H I J K L M N O P QFlight Sequence

1 2 3 4 5 6 7 8 9 10 11 12Cost ($thousands) 2 3 4 6 7 5 7 8 9 9 8 9 At

LeastIncludes Segment? Total One

SFO-LAX 1 0 0 1 0 0 1 0 0 1 0 0 1 >= 1SFO-DEN 0 1 0 0 1 0 0 1 0 0 1 0 1 >= 1SFO-SEA 0 0 1 0 0 1 0 0 1 0 0 1 1 >= 1LAX-ORD 0 0 0 1 0 0 1 0 1 1 0 1 1 >= 1LAX-SFO 1 0 0 0 0 1 0 0 0 1 1 0 1 >= 1ORD-DEN 0 0 0 1 1 0 0 0 1 0 0 0 1 >= 1ORD-SEA 0 0 0 0 0 0 1 1 0 1 1 1 1 >= 1DEN-SFO 0 1 0 1 1 0 0 0 1 0 0 0 1 >= 1DEN-ORD 0 0 0 0 1 0 0 1 0 0 1 0 1 >= 1SEA-SFO 0 0 1 0 0 0 1 1 0 0 0 1 1 >= 1SEA-LAX 0 0 0 0 0 1 0 0 1 1 1 1 1 >= 1

Total Number1 2 3 4 5 6 7 8 9 10 11 12 Sequences of Crews

Fly Sequence? 0 0 1 1 0 0 0 0 0 0 1 0 3 <= 3

Total Cost ($thousands) 18

Page 25: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.25McGraw-Hill/Irwin

Wyndor with Setup Costs

Suppose that two changes are made to the original Wyndor problem:

1. For each product, producing any units requires a substantial one-time setup cost for setting up the production facilities.

2. The production runs for these products will be ended after one week, so D and W in the original model now represent the total number of doors and windows produced, respectively, rather than production rates. Therefore, these two variables need to be restricted to integer values.

Page 26: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.26McGraw-Hill/Irwin

Graphical Solution to Original Wyndor Problem

0 2 4 6 8

8

6

4

2

Production ratefor windows

Production rate for doors

FeasibleRegion

(2, 6)

Optimal solution

10

P = 3,600 = 300 D + 500 W

W

D

Page 27: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.27McGraw-Hill/Irwin

Net Profit for Wyndor Problem with Setup Costs

Net Profit ($)

Number ofUnits Produced Doors Windows

0 0(300) – 0 = 0 0 (500) – 0 = 0

1 1(300) – 700 = –400 1(500) – 1,300 = –800

2 2(300) – 700 = –100 2(500) – 1,300 = –300

3 3(300) – 700 = 200 3(500) – 1,300 = 200

4 4(300) – 700 = 500 4(500) – 1,300 = 700

5 Not feasible 5(500) – 1,300 = 1,200

6 Not feasible 6(500) – 1,300 = 1,700

Page 28: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.28McGraw-Hill/Irwin

Feasible Solutions for Wyndor with Setup Costs

0 2 4 6

2

4

6

8Production quantity for windows

(0, 0)gives P = 0

(4, 0) gives P = 500

(4, 3) gives P = 500 + 200

Production quantity for doors

(2, 6) gives P = -100 + 1700

(0, 6) gives P = 1700

8

= 1600

= 700

W

D

Page 29: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.29McGraw-Hill/Irwin

Algebraic Formulation

Let D = Number of doors to produce,W = Number of windows to produce,y1 = 1 if perform setup to produce doors; 0 otherwise,y2 = 1 if perform setup to produce windows; 0 otherwise .

Maximize P = 300D + 500W – 700y1 – 1,300y2

subject toOriginal Constraints:

Plant 1: D ≤ 4Plant 2: 2W ≤ 12Plant 3: 3D + 2W ≤ 18

Produce only if Setup:Doors: D ≤ 99y1

Windows: W ≤ 99y2

andD ≥ 0, W ≥ 0, y1 and y2 are binary.

Page 30: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.30McGraw-Hill/Irwin

Spreadsheet Model

3456789

1011121314151617

B C D E F G HDoors Windows

Unit Profit $300 $500Setup Cost $700 $1,300

Hours HoursUsed Available

Plant 1 1 0 0 <= 4Plant 2 0 2 12 <= 12Plant 3 3 2 12 <= 18

Doors WindowsUnits Produced 0 6

<= <= Production Profit $3,000Only If Setup 0 99 - Total Setup Cost $1,300

Setup? 0 1 Total Profit $1,700

Hours Used Per Unit Produced

Page 31: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.31McGraw-Hill/Irwin

Integer Programming

• When are “non-integer” solutions okay?– Solution is naturally divisible

• e.g., $, pounds, hours

– Solution represents a rate

• e.g., units per week

– Solution only for planning purposes

• When is rounding okay?– When numbers are large

• e.g., rounding 114.286 to 114 is probably okay.

• When is rounding not okay?– When numbers are small

• e.g., rounding 2.6 to 2 or 3 may be a problem.

– Binary variables

• yes-or-no decisions

Page 32: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.32McGraw-Hill/Irwin

The Challenges of Rounding

• Rounded Solution may not be feasible.

• Rounded solution may not be close to optimal.

• There can be many rounded solutions.

– Example: Consider a problem with 30 variables that are non-integer in the LP-solution. How many possible rounded solutions are there?

1 2 3 4 5

1

2

3

4

5

x1

x2

Page 33: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.33McGraw-Hill/Irwin

How Integer Programs are Solved

1 2 3 4 5

1

2

3

4

5

x1

x2

Page 34: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.34McGraw-Hill/Irwin

How Integer Programs are Solved

1 2 3 4 5

1

2

3

4

5

x1

x2

Page 35: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.35McGraw-Hill/Irwin

Applications of Binary Variables

• Making “yes-or-no” type decisions– Build a factory?

– Manufacture a product?

– Do a project?

– Assign a person to a task?

• Set-covering problems– Make a set of assignments that “cover” a set of requirements.

• Fixed costs– If a product is produced, must incur a fixed setup cost.

– If a warehouse is operated, must incur a fixed cost.

Page 36: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.36McGraw-Hill/Irwin

Example #1 (Capital Budgeting)

• Norwood Development is considering the potential of four different development projects.

• Each project would be completed in at most three years.

• The required cash outflow for each project is given in the table below, along with the net present value of each project to Norwood, and the cash that is available each year.

Cash Outflow Required ($million)

CashAvailable($million)Project 1 Project 2 Project 3 Project 4

Year 1 9 7 6 11 28

Year 2 6 4 3 0 13

Year 3 6 0 4 0 10

NPV 30 16 22 14

Question: Which projects should be undertaken?

Page 37: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.37McGraw-Hill/Irwin

Algebraic Formulation

Let yi = 1 if project i is undertaken; 0 otherwise (i = 1, 2, 3, 4).

Maximize NPV = 30y1 + 16y2 + 22y3 + 14y4

subject to

Year 1: 9y1 + 7y2 + 6y3 + 11y4 ≤ 28 ($million)

Year 2 (cumulative): 15y1 + 11y2 + 9y3 + 11y4 ≤ 41 ($million)

Year 3 (cumulative): 21y1 + 11y2 + 13y3 + 11y4 ≤ 51 ($million)

and

yi are binary (i = 1, 2, 3, 4).

Page 38: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.38McGraw-Hill/Irwin

Spreadsheet Solution

12345678910111213

A B C D E F G H I

Norwood Development Capital Budgeting

Project 1 Project 2 Project 3 Project 4NPV ($million) 30 16 22 14

Cumulative CumulativeOutflow Available

Year 1 9 7 6 11 22 <= 28Year 2 15 11 9 11 35 <= 41Year 3 21 11 13 11 45 <= 51

Total NPVProject 1 Project 2 Project 3 Project 4 ($million)

Undertake? 1 1 1 0 68

Cumulative Outflow Required ($million)

Page 39: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.39McGraw-Hill/Irwin

Additional Considerations(Logic and Dependency Constraints)

• At least one of projects 1, 2, or 3

• Project 2 can’t be done unless project 3 is done

• Either project 3 or project 4, but not both

• No more than two projects total

Question: What constraints would need to be added for each of these additional considerations?

Page 40: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.40McGraw-Hill/Irwin

Example #2 (Set Covering Problem)

• The Washington State legislature is trying to decide on locations at which to base search-and-rescue teams.

• The teams are expensive, so they would like as few as possible.

• Response time is critical, so they would like every county to either have a team located in that county or in an adjacent county.

Question: Where should search-and-rescue teams be located?

Page 41: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.41McGraw-Hill/Irwin

The Counties of Washington State

1

2

3

4

7

6

9

10

11

12

8

5

13

14

15

16

17

18

19

20

2122

2325

24

26 27 28

29 30

31 32

33

3435

36

37

1. Clallum2. J efferson3. Grays Harbor4. Pacific5. Wahkiakum6. Kitsap7. Mason8. Thurston9. Whatcom10. Skagit11. Snohomish12. King13. Pierce14. Lewis15. Cowlitz16. Clark17. Skamania18. Okanogan

19. Chelan20. Douglas21. Kittitas22. Grant23. Yakima24. Klickitat25. Benton26. Ferry27. Stevens28. Pend Oreille29. Lincoln30. Spokane31. Adams32. Whitman33. Franklin34. Walla Walla35. Columbia36. Garfield37. Asotin

Counties

Page 42: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.42McGraw-Hill/Irwin

Algebraic Formulation

Let yi = 1 if a team is located in county i; 0 otherwise (i = 1, 2, … , 37).

Minimize Number of Teams = y1 + y2 + … + y37

subject to

County 1 covered: y1 + y2 ≥ 1

County 2 covered: y1 + y2 + y3 + y6 + y7 ≥ 1

County 3 covered: y2 + y3 + y4 + y7 + y8 + y14 ≥ 1

:

County 37 covered: y32 + y36 + y37 ≥ 1

and

yi are binary (i = 1, 2, … , 37).

Page 43: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.43McGraw-Hill/Irwin

Spreadsheet Solution

123456789101112131415161718192021222324

A B C D E F G H I J K L M N

Search & Rescue Location

# Teams # TeamsCounty Team? Nearby County Team? Nearby

1 Clallam 0 1 >= 1 19 Chelan 0 2 >= 12 Jefferson 1 1 >= 1 20 Douglas 0 1 >= 13 Grays Harbor 0 2 >= 1 21 Kittitas 1 1 >= 14 Pacific 0 1 >= 1 22 Grant 0 1 >= 15 Wahkiakum 0 1 >= 1 23 Yakima 0 3 >= 16 Kitsap 0 1 >= 1 24 Klickitat 0 1 >= 17 Mason 0 1 >= 1 25 Benton 0 1 >= 18 Thurston 0 1 >= 1 26 Ferry 0 1 >= 19 Whatcom 0 1 >= 1 27 Stevens 1 1 >= 110 Skagit 1 1 >= 1 28 Pend Oreille 0 1 >= 111 Snohomish 0 1 >= 1 29 Lincoln 0 1 >= 112 King 0 1 >= 1 30 Spokane 0 1 >= 113 Pierce 0 2 >= 1 31 Adams 0 1 >= 114 Lewis 1 2 >= 1 32 Whitman 0 2 >= 115 Cowlitz 0 2 >= 1 33 Franklin 1 1 >= 116 Clark 0 1 >= 1 34 Walla Walla 0 1 >= 117 Skamania 1 2 >= 1 35 Columbia 0 1 >= 118 Okanogan 0 1 >= 1 36 Garfield 1 1 >= 1

37 Asotin 0 1 >= 1Total Teams: 8

Page 44: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.44McGraw-Hill/Irwin

Example #3 (Fixed Costs)

• Woodridge Pewter Company is a manufacturer of three pewter products: platters, bowls, and pitchers.

• The manufacture of each product requires Woodridge to have the appropriate machinery and molds available. The machinery and molds for each product can be rented at the following rates: for the platters, $400/week; for the bowls, $250/week; for the pitcher, $300/week.

• Each product requires the amounts of labor and pewter given in the table below. The sales price and variable cost are also given in the table.

LaborHours

Pewter(pounds)

SalesPrice

VariableCost

Platter 3 5 $100 $60

Bowl 1 4 85 50

Pitcher 4 3 75 40

Available 130 240

Question: Which products should be produced, and in what quantity?

Page 45: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.45McGraw-Hill/Irwin

Algebraic Formulation

Let x1 = Number of platters produced,x2 = Number of bowls produced,x3 = Number of pitchers produced,yi = 1 if lease machine and mold for product i; 0 otherwise (i = 1, 2, 3).

Maximize Profit = ($100–$60)x1 + ($85–$50)x2 + ($75–$40)x3 – $400y1 – $250y2 – $300y3

subject toLabor: 3x1 + x2 + 4x3 ≤ 130 hoursPewter: 5x1 + 4x2 + 3x3 ≤ 240 poundsAllow production only if machines and molds are purchased:

x1 ≤ 99y1

x2 ≤ 99y2

x3 ≤ 99y3

andxi ≥ 0, and yi are binary (i = 1, 2, 3).

Page 46: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.46McGraw-Hill/Irwin

Spreadsheet Solution

12345678910111213141516

A B C D E F G H

Woodridge Pewter Company

Platters Bowls PitchersSales Price $100 $85 $75

Variable Cost $60 $50 $40Fixed Cost $400 $250 $300

Constraint Usage (per unit produced) Total AvailableLabor (hrs.) 3 1 4 60 <= 130

Pewter (lbs.) 5 4 3 240 <= 240

Lease Equipment? 0 1 0Revenue $5,100

Production Quantity 0 60 0 Variable Cost $3,000<= <= <= Fixed Cost $250

Produce only if Lease 0 99 0 Profit $1,850

Page 47: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.47McGraw-Hill/Irwin

Applications of Binary Variables

• Making “yes-or-no” type decisions– Build a factory?

– Manufacture a product?

– Do a project?

– Assign a person to a task?

• Fixed costs– If a product is produced, must incur a fixed setup cost.

– If a warehouse is operated, must incur a fixed cost.

• Either-or constraints– Production must either be 0 or ≥ 100.

• Subset of constraints– meet 3 out of 4 constraints.

Page 48: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.48McGraw-Hill/Irwin

Capital Budgeting with Contingency Constraints(Yes-or-No Decisions)

• A company is planning their capital budget over the next several years.

• There are 10 potential projects they are considering pursuing.

• They have calculated the expected net present value of each project, along with the cash outflow that would be required over the next five years.

• Also, suppose there are the following contingency constraints:– at least one of project 1, 2 or 3 must be done,

– project 4 and project 5 cannot both be done,

– project 7 can only be done if project 6 is done.

Question: Which projects should they pursue?

Page 49: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.49McGraw-Hill/Irwin

Data for Capital Budgeting Problem

Cash Outflow Required ($million)

CashAvailable($million)

Project

1 2 3 4 5 6 7 8 9 10

Year 1 1 4 0 4 4 3 2 8 2 6 25

Year 2 2 2 2 2 2 4 2 3 3 6 25

Year 3 3 2 5 2 4 2 3 4 8 2 25

Year 4 4 4 5 4 5 3 1 2 1 1 25

Year 5 1 1 0 6 5 5 5 1 1 2 25

NPV 20 25 22 30 42 25 18 35 28 33 ($million)

Page 50: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.50McGraw-Hill/Irwin

Spreadsheet Solution

123456789101112131415161718192021

A B C D E F G H I J K L M N O

Capital Budgeting with Contingency Constraints

Project Project Project Project Project Project Project Project Project Project1 2 3 4 5 6 7 8 9 10

NPV ($million) 20 25 22 30 42 25 18 35 28 33Cumulative Cumulative

Cumulative Cash Outflow Required ($million) Total Outflow AvailableYear 1 1 4 0 4 4 3 2 8 2 6 22 <= 25Year 2 3 6 2 6 6 6 4 11 5 12 44 <= 50Year 3 6 8 7 8 10 8 7 15 13 14 73 <= 75Year 4 10 12 12 12 15 11 8 17 14 15 97 <= 100Year 5 11 13 12 18 20 16 13 18 15 17 117 <= 125

Project Project Project Project Project Project Project Project Project Project Total NPV1 2 3 4 5 6 7 8 9 10 ($million)

Undertake? 1 1 1 0 1 1 1 0 1 1 213

Contingency ConstraintsProject 1,2,3 3 >= 1Project 4,5 1 <= 1Project 7 1 <= 1 Project 6

Page 51: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.51McGraw-Hill/Irwin

Electrical Generator Startup Planning (Fixed Costs)

• An electrical utility company owns five generators.

• To generate electricity, a generator must be started up, and associated with this is a fixed startup cost.

• All of the generators are shut off at the end of each day.

Generator

A B C D E

Fixed Startup Cost $2,450 $1,600 $1,000 $1,250 $2,200

Variable Cost (per MW) $3 $4 $6 $5 $4

Capacity (MW) 2,000 2,800 4,300 2,100 2,000

Question: Which generators should be started up to meet the total capacity needed for the day (6000 MW)?

Page 52: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.52McGraw-Hill/Irwin

Spreadsheet Solution

123456789

10111213141516

A B C D E F G H I J

Electrical Utility Generator Startup Planning

Generator A Generator B Generator C Generator D Generator EFixed Startup Cost $2,450 $1,600 $1,000 $1,250 $2,200Cost per Megawatt $3 $4 $6 $5 $4Max Capacity (MW) 2,000 2,800 4,300 2,100 2,000

Startup? 1 1 0 1 0Total MW MW Needed

MW Generated 2,100 3,000 0 900 0 6000 >= 6,000<= <= <= <= <=

Capacity 2,000 2,800 0 2,100 0

Fixed Cost $5,300Variable Cost $22,800

Total Cost $28,100

Page 53: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.53McGraw-Hill/Irwin

Quality Furniture (Either-Or Constraints)

• Reconsider the Quality Furniture Problem:– The Quality Furniture Corporation produces benches and picnic tables. The firm

has a limited supply of two resources: labor and wood. 1,600 labor hours are available during the next production period. The firm also has a stock of 9,000 pounds of wood available. Each bench requires 3 labor hours and 12 pounds of wood. Each table requires 6 labor hours and 38 pounds of wood. The profit margin on each bench is $8 and on each table is $18.

• Now suppose that they would not produce any fewer than 200 units of either product (i.e., either produce 0 or at least 200).

Question: What product mix will maximize their total profit?

Page 54: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.54McGraw-Hill/Irwin

Spreadsheet Solution

12345678910111213141516171819

A B C D E F G

Quality Furniture (with either-or constraints)

Benches TablesProfit $8.00 $18.00

Min Production (if any) 200 200

Resources ResourcesUsed Available

Labor 3 6 1600 <= 1,600Wood 12 38 6400 <= 9,000

Produce? 1 0

Min Production 200 0<= <= Total Profit

Production Quantities 533.33 0 $4,266.67<= <=

Max Production 533 0Max Possible 533 237

Use of Resources

Page 55: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.55McGraw-Hill/Irwin

Meeting a Subset of Constraints

• Consider a linear programming model with the following constraints, and suppose that meeting 3 out of 4 of these is good enough

– 12x1 + 24x2 + 18x3 ≥ 2,400

– 15x1 + 32x2 + 12x3 ≥ 1,800

– 20x1 + 15x2 + 20x3 ≤ 2,000

– 18x1 + 21x2 + 15x3 ≤ 1,600

Page 56: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.56McGraw-Hill/Irwin

Meeting a Subset of Constraints

Let yi = 1 if constraint i is enforced; 0 otherwise.

Constraints:

y1 + y2 + y3 + y4 ≥ 3

12x1 + 24x2 + 18x3 ≥ 2,400y1

15x1 + 32x2 + 12x3 ≥ 1,800y2

20x1 + 15x2 + 20x3 ≤ 2,000 + M (1 – y3)

18x1 + 21x2 + 15x3 ≤ 1,600 + M (1 – y4)

where M is a large number.

Page 57: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.57McGraw-Hill/Irwin

Facility Location

• Consider a company that operates 5 plants and 3 warehouses that serve customers in 4 different regions.

• To lower costs, they are considering streamlining by closing one or more plants and warehouses.

• Associated with each plant are fixed costs, shipping costs, and production costs. Each plant has a limited capacity.

• Associated with each warehouse are fixed costs and shipping costs. Each warehouse has a limited capacity.

Questions:Which plants should they keep open?

Which warehouses should they keep open?

How should they divide production among the open plants?

How much should be shipped from each plant to each warehouse, and from each warehouse to each customer?

Page 58: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.58McGraw-Hill/Irwin

Data for Facility Location Problem

FixedCost

(per month)

(Shipping + Production) Cost(per unit)

Capacity(units per

month)WH #1 WH #2 WH #3

Plant 1 $42,000 $650 $750 $850 400

Plant 2 50,000 500 350 550 300

Plant 3 45,000 450 450 350 300

Plant 4 50,000 400 500 600 350

Plant 5 47,000 550 450 350 375

Fixed Cost(per month)

Shipping Cost (per unit)

Capacity(per month)Cust. 1 Cust. 2 Cust. 3 Cust. 4

WH #1 $45,000 $25 $65 $70 $35 600

WH #2 25,000 50 25 40 60 400

WH #3 65,000 60 20 40 45 900

Demand: 250 225 200 275

Page 59: McGraw-Hill/Irwin © The McGraw-Hill Companies, Inc., 2008 7.1 Table of Contents Chapter 7 (Using Binary Integer Programming) A Case Study: California Manufacturing

© The McGraw-Hill Companies, Inc., 2008

7.59McGraw-Hill/Irwin

Spreadsheet Solution

123456789

101112131415161718

192021222324252627282930313233

A B C D E F G H I J K L M

Plant to WarehouseShipping + Production FixedCost Warehouse 1 Warehouse 2 Warehouse 3 Cost Capacity

Plant 1 $650 $750 $850 $42,000 400Plant 2 $500 $350 $550 $50,000 300Plant 3 $450 $450 $350 $45,000 300Plant 4 $400 $500 $600 $50,000 350Plant 5 $550 $450 $350 $47,000 375

Shipment Total ActualQuantities Warehouse 1 Warehouse 2 Warehouse 3 Shipped Capacity Open? Total Costs

Plant 1 0 0 0 0 <= 0 0 Shipping Cost (P-->W) $332,500Plant 2 0 300 0 300 <= 300 1 Shipping Cost (W-->C) $37,375Plant 3 0 0 275 275 <= 300 1 Fixed Cost (P) $142,000Plant 4 0 0 0 0 <= 0 0 Fixed Cost (W) $90,000Plant 5 0 0 375 375 <= 375 1 Total Cost $601,875

Total Shipped 0 300 650

Warehouse to CustomerShipping FixedCost Customer 1 Customer 2 Customer 3 Customer 4 Cost Capacity

Warehouse 1 $25 $65 $70 $35 $45,000 600Warehouse 2 $50 $25 $40 $60 $25,000 400Warehouse 3 $60 $20 $40 $45 $65,000 900

Shipment Shipped Shipped ActualQuantities Customer 1 Customer 2 Customer 3 Customer 4 Out In Capacity Open?

Warehouse 1 0 0 0 0 0 <= 0 <= 0 0Warehouse 2 250 0 50 0 300 <= 300 <= 400 1Warehouse 3 0 225 150 275 650 <= 650 <= 900 1Total Shipped 250 225 200 275

>= >= >= >=Needed 250 225 200 275