mba constructive accn

Upload: dennis-hill

Post on 05-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 MBA Constructive Accn

    1/2

    HOME

    ABOUT THE ASSOCIATION

    ADVERTISING

    MEMBER SERVICES

    EXCELLENCE AWARDS

    GREEN BUILDING

    PUBLIC SERVICES

    MEMBER LOGIN

    CONTACT US

    BLOG

    NETWORKING

    NEWS & INFORMATION

    HOME > NEWS > WHAT IS CONSTRUCTIVE ACCELERATION?

    NEWS

    General

    Health & Safety

    Contractual & Legal

    Financial

    Press Release

    Financial Services

    Industry Affairs

    Training

    Government

    Stakeholder Relations

    Labour Relations

    Finance and Economics

    Consumer Protection

    Green Building

    Newsletters

    Member News

    LOGIN

    Username

    Password

    forgot your password?

    Remember Me

    LOGIN

    REGISTER

    SUBSCRIBE

    Get the most from yourassociation with Newsand Announcementsdirect to your email.

    Your Email Address

    SUBSCRIBE

    WHAT IS CONSTRUCTIVE ACCELERATION?

    Contractors and subcontractors often argue

    that they have been forced to accelerate the

    works to overcome delays caused by the

    architect, engineer o r principal agent.

    Normally, in the absence of an agreement

    to accelerate, the contractor is not entitled

    to decide unilaterally to accelerate and

    expect the employer to pay the costs.

    The contractor or subcontractor may,

    however, argue that he chose to accelerate

    faced with the agents refusal or neglect to

    grant a proper extension of time. This issometimes referred to as a constructive

    acceleration order.

    Constructive acceleration is defined by the US Corps of Engineers as;

    An act or failure to act by the Employer which does not recognize that the contractor has encountered

    excusable delay for which he is entitled to a time extension and which required the contractor to accelerate

    his programme in order to complete the contract requirements by the existing contract completion date.

    This situation may be brought about by the Employers denial of a valid request for a contract time

    extension or by the Employers untimely granting of a time extension.

    In the Australian case of Perini Pacific v Commonwealth of Australia (1969) Mr Justice Macfarlane in the

    Commercial Court of New South Wales indicated clearly that this type of claim could only be on the basis

    of some proven breach of contract by the owner coupled, of course, with proof of damages in the form of

    completion to time by expenditure greater than would otherwise have been incurred. In that case, the

    breach consisted of a refusal or failure by the certifier to give any consideration at all to the contractors

    applications.

    In the case in British Columbia of Morrison-Knudsen v BC Hydro & Power the owner, unknown to the

    contractor, had secretly agreed with a government representative that no extension of time would be

    granted in view of the pressing need for electricity by the contract completion date. All requests for an

    extension of time w ere refused and the contractor carried on and m anaged to finish the project with only

    slight delay. The Court of Appeal of British Columbia held that the contractor could have rescinded on the

    basis of a fundamental breach of contract had he known the real reason for the refusals and, in that event,

    would have been entitled, on the basis of established case law, to put his claim alternatively on a quantum

    meruit basis and so to escape from the original contract prices. The fact that the contractor had not

    rescinded but had completed the project limited his remedy to the usual one of damages, measured in this

    case in terms of the additional expense incurred in completing to time, i.e. in accelerating progress.

    Similarly in W Stephenson (Western) Ltd v Metro Canada Ltd (1987) the Canadian Court held that, by

    stating in no circumstances would the contractor receive an extension of time for completion, the employer

    had deliberately breached the contract and it awarded damages calculated by reference to the contractors

    consequential acceleration.

    The English courts have been a little slow at recognising a situation where a claim for constructive

    acceleration would be r elevant. However, the situation has been changed by the decision in Motherwell

    Bridge Construction Ltd v Micafil (2002). In this case Motherwell Bridge was a subcontractor to Micafil in

    connection with the construction of an autoclave for BICC in Kent. Additional welding was required by

    Micafil which involved a substantial amount of additional man hours. Micafil failed to grant an appropriate

    extension of time. In an effort to complete by the original completion date, Motherwell Bridge incurred

    substantial additional costs which formed the subject of a claim.

    The matter was referred to court which found in favour of Motherwell Bridge. Judge Toulman considered

    that Motherwell Bridge was entitled to an extension of time based upo n the period of delay which would

    have been incurred using the original labour force, and as Micafil failed to grant an extension of time,

    Motherwell Bridge was entitled to be paid the acceleration costs.

    It would seem that to recover payment in respect of constructive acceleration a contractor or subcontractor

    must be able to demonstrate the following:

    1. An entitlement to an extension of time

    2. Proper notice as required by the contract has been served

    3. The employer or his agent has failed to grant an appropriate extension of time

    4. The employer has requested completion by the original completion date

    5. The contractor has incurred additional costs due to taking acceleration measures

    6. The cost to the contractor in taking acceleration measures when estimated in advance of the

    SHARE / PRINT THIS PAGE

    2009

    May

    June

    July

    August

    September

    October

    November

    Mediation: The Civilized Wayto Resolve Disputes

    Troubles with Tenders?

    Tender Notice and Invitation to

    Association MembersThe CIDB and You

    National Healthcare Reform

    Not The Gravy Train

    Media Statement, MinisterBlade Nzimande

    Competition Crackdown

    Chief Inspector AddressesSafety Practitioners

    Reasonable Steps To Avoid OrReduce Delay

    Gamalakhe Community projectConcluded

    Sexwale and Shoddy Houses -Paddy Hartdegen

    Master Builders Newsletter -Edition 16

    KwaZulu-Natal Leads the Wayin Safety Standards

    JBCC True DemandGuarantee

    Always Use a RecognisedForm of Contract Agreement

    Obscuring Someone ElsesView

    Solar Soulmates

    MBSA Payment Quality SurveyFindings

    Recovery of Loss Arising FromContract Instructions

    Builders Newsletter - Edition17

    Costs Incurred In Preparing aloss and Expense Claim

    ARCHIVE

    Page 1 of 2Master Builders KwaZulu-Natal - What is Constructive Acceleration?

    2009/11/28http://www.masterbuilders.co.za/news/2009/August/what_is_constructive_acceleratio ...

  • 8/2/2019 MBA Constructive Accn

    2/2

    decision being made to accelerate, is less than the cost resulting from an overrun to the completion

    date.

    BRUCE LYLE | MEMBERSHIP SERVICES MANAGER

    (Original article by R D Pickles - former Membership Services Manager)

    SHARE / PRINT THIS PAGE

    Ma st e r B ui ld er s Kw aZu lu -N at al 20 09 Si te ma p | Di sc la im er | Pr iv ac y Po li cy | Si te by Bl ac k Sq uar e

    Page 2 of 2Master Builders KwaZulu-Natal - What is Constructive Acceleration?

    2009/11/28http://www.masterbuilders.co.za/news/2009/August/what_is_constructive_acceleratio ...