mba constructive accn
TRANSCRIPT
-
8/2/2019 MBA Constructive Accn
1/2
HOME
ABOUT THE ASSOCIATION
ADVERTISING
MEMBER SERVICES
EXCELLENCE AWARDS
GREEN BUILDING
PUBLIC SERVICES
MEMBER LOGIN
CONTACT US
BLOG
NETWORKING
NEWS & INFORMATION
HOME > NEWS > WHAT IS CONSTRUCTIVE ACCELERATION?
NEWS
General
Health & Safety
Contractual & Legal
Financial
Press Release
Financial Services
Industry Affairs
Training
Government
Stakeholder Relations
Labour Relations
Finance and Economics
Consumer Protection
Green Building
Newsletters
Member News
LOGIN
Username
Password
forgot your password?
Remember Me
LOGIN
REGISTER
SUBSCRIBE
Get the most from yourassociation with Newsand Announcementsdirect to your email.
Your Email Address
SUBSCRIBE
WHAT IS CONSTRUCTIVE ACCELERATION?
Contractors and subcontractors often argue
that they have been forced to accelerate the
works to overcome delays caused by the
architect, engineer o r principal agent.
Normally, in the absence of an agreement
to accelerate, the contractor is not entitled
to decide unilaterally to accelerate and
expect the employer to pay the costs.
The contractor or subcontractor may,
however, argue that he chose to accelerate
faced with the agents refusal or neglect to
grant a proper extension of time. This issometimes referred to as a constructive
acceleration order.
Constructive acceleration is defined by the US Corps of Engineers as;
An act or failure to act by the Employer which does not recognize that the contractor has encountered
excusable delay for which he is entitled to a time extension and which required the contractor to accelerate
his programme in order to complete the contract requirements by the existing contract completion date.
This situation may be brought about by the Employers denial of a valid request for a contract time
extension or by the Employers untimely granting of a time extension.
In the Australian case of Perini Pacific v Commonwealth of Australia (1969) Mr Justice Macfarlane in the
Commercial Court of New South Wales indicated clearly that this type of claim could only be on the basis
of some proven breach of contract by the owner coupled, of course, with proof of damages in the form of
completion to time by expenditure greater than would otherwise have been incurred. In that case, the
breach consisted of a refusal or failure by the certifier to give any consideration at all to the contractors
applications.
In the case in British Columbia of Morrison-Knudsen v BC Hydro & Power the owner, unknown to the
contractor, had secretly agreed with a government representative that no extension of time would be
granted in view of the pressing need for electricity by the contract completion date. All requests for an
extension of time w ere refused and the contractor carried on and m anaged to finish the project with only
slight delay. The Court of Appeal of British Columbia held that the contractor could have rescinded on the
basis of a fundamental breach of contract had he known the real reason for the refusals and, in that event,
would have been entitled, on the basis of established case law, to put his claim alternatively on a quantum
meruit basis and so to escape from the original contract prices. The fact that the contractor had not
rescinded but had completed the project limited his remedy to the usual one of damages, measured in this
case in terms of the additional expense incurred in completing to time, i.e. in accelerating progress.
Similarly in W Stephenson (Western) Ltd v Metro Canada Ltd (1987) the Canadian Court held that, by
stating in no circumstances would the contractor receive an extension of time for completion, the employer
had deliberately breached the contract and it awarded damages calculated by reference to the contractors
consequential acceleration.
The English courts have been a little slow at recognising a situation where a claim for constructive
acceleration would be r elevant. However, the situation has been changed by the decision in Motherwell
Bridge Construction Ltd v Micafil (2002). In this case Motherwell Bridge was a subcontractor to Micafil in
connection with the construction of an autoclave for BICC in Kent. Additional welding was required by
Micafil which involved a substantial amount of additional man hours. Micafil failed to grant an appropriate
extension of time. In an effort to complete by the original completion date, Motherwell Bridge incurred
substantial additional costs which formed the subject of a claim.
The matter was referred to court which found in favour of Motherwell Bridge. Judge Toulman considered
that Motherwell Bridge was entitled to an extension of time based upo n the period of delay which would
have been incurred using the original labour force, and as Micafil failed to grant an extension of time,
Motherwell Bridge was entitled to be paid the acceleration costs.
It would seem that to recover payment in respect of constructive acceleration a contractor or subcontractor
must be able to demonstrate the following:
1. An entitlement to an extension of time
2. Proper notice as required by the contract has been served
3. The employer or his agent has failed to grant an appropriate extension of time
4. The employer has requested completion by the original completion date
5. The contractor has incurred additional costs due to taking acceleration measures
6. The cost to the contractor in taking acceleration measures when estimated in advance of the
SHARE / PRINT THIS PAGE
2009
May
June
July
August
September
October
November
Mediation: The Civilized Wayto Resolve Disputes
Troubles with Tenders?
Tender Notice and Invitation to
Association MembersThe CIDB and You
National Healthcare Reform
Not The Gravy Train
Media Statement, MinisterBlade Nzimande
Competition Crackdown
Chief Inspector AddressesSafety Practitioners
Reasonable Steps To Avoid OrReduce Delay
Gamalakhe Community projectConcluded
Sexwale and Shoddy Houses -Paddy Hartdegen
Master Builders Newsletter -Edition 16
KwaZulu-Natal Leads the Wayin Safety Standards
JBCC True DemandGuarantee
Always Use a RecognisedForm of Contract Agreement
Obscuring Someone ElsesView
Solar Soulmates
MBSA Payment Quality SurveyFindings
Recovery of Loss Arising FromContract Instructions
Builders Newsletter - Edition17
Costs Incurred In Preparing aloss and Expense Claim
ARCHIVE
Page 1 of 2Master Builders KwaZulu-Natal - What is Constructive Acceleration?
2009/11/28http://www.masterbuilders.co.za/news/2009/August/what_is_constructive_acceleratio ...
-
8/2/2019 MBA Constructive Accn
2/2
decision being made to accelerate, is less than the cost resulting from an overrun to the completion
date.
BRUCE LYLE | MEMBERSHIP SERVICES MANAGER
(Original article by R D Pickles - former Membership Services Manager)
SHARE / PRINT THIS PAGE
Ma st e r B ui ld er s Kw aZu lu -N at al 20 09 Si te ma p | Di sc la im er | Pr iv ac y Po li cy | Si te by Bl ac k Sq uar e
Page 2 of 2Master Builders KwaZulu-Natal - What is Constructive Acceleration?
2009/11/28http://www.masterbuilders.co.za/news/2009/August/what_is_constructive_acceleratio ...