-Maximo Monday-Topic: Maximo for Utilities 6.3- Compatible Units Demonstration
Date: April 21, 2008
2Copyright © 2008 Accenture All Rights Reserved.
Today's Objectives
Overview of:• Settings to enable use of CU records and actions• CU Library (T&D)
– Create Linear CU – cables, wires or pipes– Create Point CU – a single pole– Create Labor only CU – create a labor only CU– Create Material only CU – create a Materials only CU
• Building a CUs in Maximo for Utilities 6.3 Demo• CU Estimating (T&D)
3Copyright © 2008 Accenture All Rights Reserved.
Compatible UnitsBuilding Blocks (Review)
&
Maximo Building BlocksFor Compatible Units
Labor in the form of Crafts/ CrewTypes.
Determines Internal and external effort for Install, Remove, Transfer and
abandon WorkFunctions
Item MasterMaterial IDs
Determines Bill of Material (BOM)
ToolsDetermines any
equipment or special tool to
perform the job
FERCs
Accounting Strings
Asset Codes
Continuous Property Record
Overhead Factors
Contractor’s Cost definition
CU Special Conditions, Utilization,
Structure, etc.
CU
Labor Adders
StoreroomsWork Groups
CrewType Assignment
BidUnit?
CU Classifications and Attributes.
Link to GIS
Integration Enabler
Elements
CU Foundations
4Copyright © 2008 Accenture All Rights Reserved.
Enabling for CU
• Organizations (T&D) Application – Includes settings for actions and records used for Compatible Units.– Configure Work Groups– Configure Classifications– Configure Crafts– Configure Items– Configure Tools
5Copyright © 2008 Accenture All Rights Reserved.
Setting The CU Options
• Organizations (T&D) continued:– Account Code Options– Account Override Options – CU Library Options– CU Estimating Options– CU Acceptance Options– Labor Adder Options– Loading Type Options– Work Type Options– Work Zone Options
6Copyright © 2008 Accenture All Rights Reserved.
CU Applications
• CU Library (T&D) – Located in the Planning module; used to create compatible unit records, build hierarchies, specify the items, labor, and tools to use in specific work site conditions.
• CU Estimating (T&D) – Located in the Work Order module used to create design and construction scenarios; perform and accept estimates.
7Copyright © 2008 Accenture All Rights Reserved.
Compatible Units Structure
Frame
+
Transformer + Arrester
Level 1Level 2
Pole
Level 3
Compatible Unit selected by designer
Framed Pole
8Copyright © 2008 Accenture All Rights Reserved.
Contact Information
• Sandy Jones – Senior Executive– [email protected]
• Jeff Daniel – Manager– [email protected]
• Felix J Torres – Manager– [email protected]