Matt Lennon
WCX1B Construction
Overview
2
3
Project Overview
Project overviewKey information
4
Value approx: $2.7 billion
Contract start date: 3 June 2015
Planning approval: 11 February 2016
Completion: Early 2019
Project overviewConstruction snapshot
5
Project length: 6.5 km
Expected vehicles upon opening: more than 100,000 per day
Tunnel speed limit: 80km/hr
Ramp speed limit: 60km/hr
Tunnel height: 5.3 metres
Lanes: 3 lanes in each direction
Ramp grades: The entry ramps into the tunnel are designed to a
maximum grade of 8% and the exit ramps out of the tunnels are a
maximum grade of 6%
Peak employment: Greater than 1400 people at project peak
6
Western connection to the widened M4 Homebush
7
Western connection to the widened M4 Homebush - artist’s impression, eastbound view
8
Western entry/exit point to M4 East tunnels Homebush
9
Western entry/exit point to M4 East tunnels Homebush - artist’s impression eastbound view
10
Concord Interchange
11
Concord InterchangeArtist’s impression - eastbound view
12
City West Link Interchange Haberfield
13
City West Link Interchange Haberfield - artist’s
impression, looking north east along Wattle Street
14
Parramatta Road Interchange Ashfield
15
Parramatta Road Interchange Ashfield
Parramatta Vent Facility
16
3 x 30m diameter
interconnected shafts
1 x Inlet shaft (shared with
future Stage 3)
2 x Exhaust shafts.
Average 43m depth
7 x connecting ventilation
tunnels (totalling 750m), cross-
section up to 150m2
Tunnel
19
SitesOverview
4 tunnelling sites
Decline access primarily with shaft access from the western portal
20
UNDERWOOD
CONCORD
CINTRA
NORTHCOTE
Underwood Site
21
• Up to 3 roadheaders• Tunnelling only• 12 month operation• M&E access
Concord Site
22
• Up to 4 roadheaders• Tunnelling & Civil fitout• 18 month operation
Concord Site
23
Cintra Site
24
• Up to 4 roadheaders• Tunnelling & Civil fitout• 24 month operation• M&E Access
Northcote Site
25
• Up to 10 roadheaders• Tunnelling & Civil fitout• 24 month operation• M&E Access
Northcote Site
26
Excavation General Arrangement
27
14.4m
29m
8m
9m
Fit for purpose water resisting treatment
Entire tunnel space proofed for secondary lining with
membrane
Installation of appropriate linings where needed to meet
project specified inflows and waterproofing requirements
All critical M&E spaces treated with a membrane
Waterproofing strategy
28
Main PlantRoadheaders
29
5 x Sandvik (3 x MT520, 2 x MT720)8 x Mitsui SLB3005 x Refurbished Mitsui SLB3001 x Mitsui S200VMT Guidance Systems
Main PlantBolters / Jumbo
30
11 x Robodrill1 x Tamrock QuasarVMT Guidance Systems
Main PlantShotcrete
31
8 x Meyco Potenza1 x Jacon Maxijet
Construction Innovations
32
Pendular Bolter
Mechanical installation of cable bolts up to 9m long.
Dual Cab Roadheader
Enables on the job roadheader operator training.